Appendix A
2016 Final SEIR MMRP
Mitigation Monitoring and Reporting Program

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
Traffic and Circulation
TC-1 The project developer shall install a traffic signal at the intersection of West Ventura Boulevard (east-west segment) and “A” Street when traffic conditions warrant a signal.

City Public Works staff shall
monitor the operational
status of the West Ventura
Boulevard (east-west
segment) and “A” Street
and the vehicle trips
generation for each new
building planned for
development at the project
site.

Prior to issuance of
occupancy permits for
each building at the
project site.

Public Works Department
The project developer shall
install a traffic signal at the
intersection of West Ventura
Boulevard (east-west
segment) and “A” Street
when traffic conditions
warrant a signal.

Prior to issuance of
occupancy permits for
the buildings at the
project site that cause
operational conditions
that warrant a traffic
signal.

Public Works Department
Air Quality
AQ-1 All developers of new buildings at the project site shall implement fugitive dust control measures throughout all phases of construction. The project developers shall include in construction contracts the control measures required and recommended by the VCAPCD at the time of development.

Examples of the types of measures currently required and recommended include the following:
•Minimize the area disturbed on a daily basis by clearing, grading, earthmoving, and/or excavation operations.

Measures shall be included
in construction documents
and implemented during
grading and construction.

Prior to issuance of
grading permits and
during grading and
construction.

Public Works Department
Final Subsequent Environmental Impact Report H- !3
Mitigation Monitoring and Reporting Program
•Pre-grading/excavation activities shall include watering the area to be graded or excavated before the commencement of grading or excavation operations. Application of water should penetrate sufficiently to minimize fugitive dust during these activities.
•All trucks shall be required to cover their loads as required by California Vehicle Code §23114.
•All graded and excavated material, exposed soil areas, and active portions of the construction site, including unpaved on- site roadways, shall be treated to prevent fugitive dust.

Treatment shall include, but not necessarily be limited to, periodic watering, application of environmentally-safe soil stabilization materials, and/or roll-compaction as appropriate.

Watering shall be done as often as necessary.
•Material stockpiles shall be enclosed, covered, stabilized, or otherwise treated, to prevent blowing fugitive dust offsite. •Graded and/or excavated inactive areas of the construction site shall be monitored by a City-designated monitor at least weekly for dust stabilization. Soil stabilization methods, such as water and roll-compaction, and environmentally-safe
control materials, shall be periodically applied to portions of the construction site that are inactive for over four days. If no further grading or excavation operations are planned for the area, the area should be seeded and watered until grass growth is evident, or periodically treated with
environmentally-safe dust suppressants, to prevent excessive fugitive dust.
•Signs shall be posted on-site limiting on-site traffic to 15 miles per hour or less.

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
H-! Springville Commercial4
Mitigation Monitoring and Reporting Program
•During periods of high winds (i.e., wind speed sufficient to cause fugitive dust to impact adjacent properties), all clearing, grading, earth moving, and excavation operations shall be curtailed to the degree necessary to prevent fugitive dust created by on-site activities and operations from being a nuisance or hazard, either off-site or on-site. The site superintendent/supervisor shall use his/her discretion in conjunction with the VCAPCD is determining when winds are excessive.
•Adjacent streets and roads shall be swept at least once per day, preferably at the end of the day, if visible soil material is carried over to adjacent streets and roads.
•Personnel involved in grading operations, including
contractors and subcontractors should be advised to wear respiratory protection in accordance with California Division of Occupational Safety and Health regulations.

AQ-2 All developers of new buildings at the project site shall implement measures to reduce the emissions of pollutants generated by heavy-duty diesel-powered equipment operating at the Project site throughout the project construction phases. The project developer shall include in construction contracts the control measures required and recommended by the VCAPCD at the time of development. Examples of the types of measures currently required and recommended include the following:
•Maintain all construction equipment in good condition and in proper tune in accordance with manufacturer’s specifications. •Limit truck and equipment idling time to five minutes or less. •Minimize the number of vehicles and equipment operating at the same time during the smog season (May through October). •Use alternatively fueled construction equipment, such as compressed natural gas (CNG), liquefied natural gas (LNG), or electric, to the extent feasible.

Measures shall be included
in construction documents
and implemented during
grading and construction.

Prior to issuance of
grading permits and
during grading and
construction.

Public Works Department

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
Final Subsequent Environmental Impact Report H- !5
Mitigation Monitoring and Reporting Program
AQ-3 All developers of new buildings at the project site shall include in construction and building management contracts the
following requirements or measures shown to be equally
effective:
•Use solar or low-emission water heaters in new buildings. •Require that commercial landscapers providing services at the common areas of project site use electric or battery-powered equipment, or other internal combustion equipment that is either certified by the California Air Resources Board or is three years old or less at the time of use, to the extent that such equipment is reasonably available and competitively priced in Ventura County (meaning that the equipment can be easily purchased at stores in Ventura County and the cost of the equipment is not more than 20 percent greater than the cost of standard equipment).

Measures shall be included
in construction and building
management contracts and
implemented during
construction and operation.

Prior to issuance of
building and
occupancy permits.

Department of
Community Development
AQ-4 A site-wide Transportation Demand Management (TDM) program shall be implemented and managed to reduce the
number of vehicle trips generated by the uses at the project site.

The TDM program shall be
prepared and implemented
during project operation to
accommodate the actual
occupants of the overall site.

On an annual basis
during project
operation.

Department of
Community Development
AQ-5 All developers of new buildings at the project site shall have the City of Camarillo Department of Public Works calculate the number of motor vehicle trips that would be generated by the new building and shall pay to the City TDM fund $30.79 for each vehicle trip generated by the new building constructed no later than 2020. The developers of buildings constructed after 2020 may request that the City of Camarillo Department of
Community Development recalculate the applicable mitigation fee and pay the appropriate amount for each vehicle trip generated by the new building.

City Public Works staff shall
calculate the vehicle trips
generation for each new
building planned for
development at the project
site.

Prior to issuance of
occupancy permits for
each building at the
project site.

Public Works Department
The project developer shall
pay the calculated TDM
fund to the City.

Prior to issuance of
occupancy permits for
each building at the
project site.

Department of
Community Development

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
H-! Springville Commercial6
Mitigation Monitoring and Reporting Program
Water Supply
WS-1No new potable water service connections will be provided, no new temporary meters or permanent meters will be provided, and no statements of immediate ability to serve or provide potable water service (such as will-serve letters or letters of water verification) will be issued, unless the project developer provides, to the satisfaction of the city in accordance with Camarillo Municipal Code Chapter 14.12, substantial evidence of an enforceable commitment that water demands for the project will be offset prior to the provision of a water will-serve letter.

The project developer may satisfy this requirement through any one or a combination of the following methods: (i) modifications to the project to provide non-required water savings features, (ii) agreements with existing city water users to retrofit existing improvements and facilities with water savings features, (iii) by making a payment to the city's water conservation credit fund in an amount necessary to offset the project's water demand as established under the city's water conservation credit program, or (iv) by transferring groundwater pumping rights or allocations that comply with GSP strategies adopted by the FCGMA and are immediately available for use by the city.

Review of project water
supply plan for the project
or/and confirmation of
payment to the city’s water
conservation credit
program.

Prior to issuance of
building permits.

Department of Public
Works

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
Final Subsequent Environmental Impact Report H- !7
Mitigation Monitoring and Reporting Program
Impacts Found to be Less Than Significant
BIO-1 A pre-construction survey for resident burrowing owls shall be conducted by a qualified biologist within 30 days prior to commencement of grading and construction activities within the project site. If ground disturbing activities in the surveyed areas are delayed or suspended for more than 30 days after the pre- construction survey, the area shall be resurveyed for owls. The pre-construction survey and any relocation activity would be conducted in accordance with the current Staff Report for Burrowing Owl Mitigation published by the California
Department of Fish and Wildlife (CDFW).

If active nests are identified at the project site during the pre- construction survey, the nests shall be avoided or the owls actively or passively relocated. To adequately avoid active nests, no grading or heavy equipment activity shall take place within at least 250 feet of an active nest during the breeding season (February 1 through August 31), and 160 feet during the non- breeding season.

The project developer shall
contract with a qualified
biologist to conduct a
survey for resident
burrowing owls. The survey
shall be conducted within
30 days of grading and
construction activities
within the project site. If
active nests are identified at
the project site during the
pre-construction survey, the
nests shall be avoided or the
owls actively or passively
relocated. A report
describing the results of the
survey shall be provided to
the Department of
Community Development.

Within 30 days of
grading and
construction activities
within the project site.

Department of
Community Development

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
H-! Springville Commercial8
Mitigation Monitoring and Reporting Program
If burrowing owls occupy the project site and cannot be avoided, active or passive relocation shall be used to exclude owls from their burrows, as agreed to by the City of Camarillo Community Development Department and the CDFW. Relocation shall be conducted outside the breeding season or once the young are able to leave the nest and fly. Passive relocation is the exclusion of owls from their burrows (outside the breeding season or once the young are able to leave the nest and fly) by installing one- way doors in burrow entrances. These one-way doors allow the owl to exit the burrow, but not enter it. These doors shall be left in place 48 hours to ensure owls have left the burrow. Artificial burrows shall be provided nearby. The project area shall be monitored daily for one week to confirm owl use of burrows before excavating burrows in the impact area. Burrows shall be excavated using hand tools and refilled to prevent reoccupation.

Sections of flexible pipe shall be inserted into the tunnels during excavation to maintain an escape route for any animals inside the burrow. The CDFW shall be consulted prior to any active relocation to determine acceptable receiving sites available where this species has a greater chance of successful long-term relocation.

BIO-2 A qualified biologist shall be on site during initial ground disturbance activities of a construction area at the project site in order to identify and move out of harms way any wildlife of low mobility. The services of the biologist will no longer be needed once the ground surface is cleared and the potential habitat of wildlife is removed from the development area.

The project developer shall
contract with a qualified
biologist to monitor the site
during initial ground
disturbance activities of a
construction area. The
biologist shall be on site in
order to identify and move
out of harms way any
wildlife of low mobility.

During initial ground
disturbance activities of
a construction area at
the project site.

Department of
Community Development

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
Final Subsequent Environmental Impact Report H- !9
Mitigation Monitoring and Reporting Program
ILS-1 The project developer shall include in construction contracts the requirement that the project be halted if any archaeological materials are encountered during the course of project
development. The services of an archaeologist shall be secured by contacting the Center for Public Archaeology – California State University Fullerton, or a member of the Society of Professional Archaeologists (SOPA) or a SOPA-qualified
archaeologist to assess the resources and evaluate the impact.

Copies of the archaeological survey, study, or report shall be submitted to the UCLA Archaeological Information Center.

This requirement shall be
included in construction
documents and
implemented during
grading and construction.

Prior to issuance of
grading permits and
during grading and
construction.

Department of
Community Development
ILS-2 The project developer shall include in construction contracts the requirement that the project be halted if any paleontological materials are encountered during the course of project
development. The services of a paleontologist shall be secured by contacting the Center for Public Paleontology, which can be found at the following universities; USC, UCLA, California State University at Los Angeles, California State University at Long Beach or the County Museum, to assess the resources and evaluate the impact.

This requirement shall be
included in construction
documents and
implemented during
grading and construction.

Prior to issuance of
grading permits and
during grading and
construction.

Department of
Community Development
ILS-3 The project developer shall include in construction contracts the requirement that the project be halted if any human remains are encountered during the course of project development and the City of Camarillo Public Works Department and County Coroner shall be immediately notified. If the remains are determined by the County Coroner to be Native American, the Native American Heritage Commission (NAHC) shall be notified within 24 hours, and the guidelines of the NAHC shall be adhered to in the treatment and disposition of the remains.

This requirement shall be
included in construction
documents and
implemented during
grading and construction.

Prior to issuance of
grading permits and
during grading and
construction.

Department of
Community Development

MITIGATION MEASURES ADOPTED FOR THE SPRINGVILLE COMMERCIAL PROJECT Mitigation Measure Action Required Mitigation Timing Monitoring Responsibility
H-! Springville Commercial10