Cities Index.
Agenda Report Cover

Camarillo City Council
May 22, 2024

Document
Agenda Report Cover
Meeting
May 22, 2024
Body
Camarillo City Council
Pages
2
Original file
131 KB
Text extracted from the city's file for reading and search. Open the original on camarillo.primegov.com. That file is the official record.

Camarillo City Council

AGENDA REPORT
Date: May 22, 2024
To: Honorable Mayor and City Councilmembers
From: Greg Ramirez, City Manager
Submitted by: Dave Klotzle, Public Works Director
Subject: Treated Water Diversion – North Pleasant Valley Groundwater Desalter (Project No. MC-2023-5) – Adopt a Resolution Approving Final Pay Estimate and Accepting Improvements

BACKGROUND
The operational processes of the North Pleasant Valley Groundwater Desalter have determined the need to periodically divert treated water to the facility drainage system before delivering water to the distribution system. The need to divert treated water can arise when the facility resumes operation after being offline for maintenance. The Treated Water Diversion - Project No. MC-2023-5 (Project) modified existing piping, installed a new flow meter, and constructed sidewalk, driveway, and drainage improvements to provide for the ability to divert treated water when needed.

On November 8, 2023, the City Council adopted Resolution No. 2023-92, finding the Project exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Article 19 Categorical Exemptions Sections 15301 Class 1, approving the plans and specifications, and proceeding with construction of the project; and awarded a Public Works Contract to Travis Agricultural Construction, Inc. (Travis Ag) for the Project , in the amount of $81,650 with a contingency of $12,500 for a total contract authorization of $94,150.

DISCUSSION
The Project is complete and Contract Pay Estimate No. 2 (Final) (Attachment 1) to Travis Ag in the amount of $4,115.87 is recommended for this project. The total final cost of this contract is $86,492.36.

Staff recommends adopting a Resolution approving the Final Pay Estimate and accepting improvements. The Resolution (Attachment 2) authorizes the Mayor to sign the Notice of Completion (Attachment 3) and directs the City Clerk to record the Notice with the Ventura County Recorder.

Project No. MC-2023-5 - Acceptance and Final Pay Estimate May 22, 2024

Page 2 of 2 ends

1 8
5 6

FISCAL IMPACT
Funds for the Treated Water Diversion contract are included in the Water Capital Projects Fund, Account No. 863-8716-487.92-41 and Project WT-11-01.

RECOMMENDATION
Adopt a Resolution accepting improvements, approving Contract Pay Estimate No. 2 (Final) to Travis Agricultural Construction, Inc., and authorizing the Mayor to sign the Notice of Completion.

ATTACHMENTS

1. Contract Pay Estimate No. 2 (Final)

2. Resolution

3. Notice of Completion
REFERENCE MATERIALS – AVAILABLE FOR REVIEW AT CITY HALL None

← All documents from this meeting