CITY OF CAMARILLO

PUBLIC WORKS DEPARTMENT

CAPITAL PROJECTS

NOTICE TO BIDDERS, PROPOSAL, CONTRACT

AND SPECIFICATIONS

FOR THE CONSTRUCTION OF

STANDBY POWER AT CITY HALL AND

CORPORATION YARD
PROJECT NO. CH-5067-2

BIDS TO BE OPENED ON
August 1, 2024 AT 3:00 P.M.

JAMES CAMPERO ANDREW GRUBB, PE

ASSISTANT DIRECTOR OF PUBLIC WORKS - PRINCIPAL CIVIL ENGINEER

CITY ENGINEER
R. C. E. 76459, Exp. 12/31/2024

STANDBY POWER AT CITY HALL AND

CORPORATION YARD
PROJECT NO. CH-5067-2

PROJECT ADMINISTRATION
All inquiries relative to this project shall be directed to Andrew Grubb, Principal Civil Engineer of the City of Camarillo Public Works Department, prior to opening of bids. All questions relating to interpretation of the Contract Documents or prod ucts must be submitted in writing five (5) days prior to the opening of bids , and responses will be in the form of written addenda, if required as further described in the bid documents . Questions submitted after this time period will not be answered.

Andrew Grubb, PE
Principal Civil Engineer
Public Works Department
601 Carmen Drive
Camarillo, CA 93010
Telephone: (805) 388-5344
Fax: (805) 388-5387
Email: [email protected]
(8-2023)

CITY OF CAMARILLO

1. NOTICE INVITING BIDS

2. INSTRUCTIONS TO BIDDERS

3. BID PROPOSAL

4. PUBLIC WORKS CONTRACT

5. GENERAL CONDITIONS/SPECIFICATIONS

6. SPECIAL PROVISIONS

STANDYBY POWER AT CITY HALL AND CORPORATION YARD
PROJECT NO. CH-5067-2

Project Number: CH-5067-2

Date: June 25, 2024

Assistant Director of Public Works - City Engineer

BIDS WILL BE RECEIVED UNTIL

August 1, 2024 AT 3:00 P.M.

Via electronic transmission on the City of Camarillo
PlanetBids portal site

(8-2023)

NOTICE INVITING BIDS
- 1 -

CITY OF CAMARILLO

NOTICE INVITING BIDS
NOTICE IS HEREBY GIVEN that the City of Camarillo (“CITY”), will receive bids for the below stated Project ONLY via electronic transmission on the CITY’S online PlanetBids portal site until 3:00 p.m., August 1, 2024, and will be opened and posted online via PlanetBids portal site immediately thereafter.

STANDBY POWER AT CITY HALL AND CORPORATION YARD
PROJECT NO. CH-5067-2

The project to be constructed at City Hall consists of construction of a concrete foundation, soundwall, switchgear, conduit, electrical, and related work to install a City -furnished 200kW diesel powered generator. At the Corporation Yard, the project consists of construction of a concrete foundation, soundwall, switchgear, conduit, electrical, and related work to install a City- furnished 300kW diesel powered generator and related work.

Obtaining Bid Documents: The Bid Documents for this project are on file in the office of the undersigned. In addition, p rospective bidders may obtain free copies of these documents, including Proposal, Bid forms, Specifications, and Plans by registering online as a prospective bidder on the City of C amarillo PlanetBids portal site:
https://pbsystem.planetbids.com/portal/56271/portal-home. Hard copies are also available from the City of Camarillo, at 601 Carmen Drive, Camarillo, California 93010. THERE IS A $40 SERVICE CHARGE (ADD $15 POSTAGE IF PLANS ARE TO BE MAILED). These amounts are not refundable. Checks should be made payable to the City of Camarillo. Bidders may also obtain Bid Documents from the CITY website at https://www.cityofcamarillo.org/cip with no fee.

Plans, general and special provisions, and proposal forms for the project are also filed with the following: Dodge Data & Analytics, www.construction.com; Ventura County Contractors’ Association, 1830 Lockwood Street, Suite 110, Oxnard, California 93030; BidAmerica, 41085 Elm Street, Murrieta, California 92562 (www.bidamerica.com); Plan Room, Construction Bidboard, Inc., 11622 El Camino Real, 1 st Floor, San Diego, California 92130; Builders Notebook, 133 E.

De La Guerra Street, Suite 62, Santa Barbara, Ca lifornia, 93101; and are by reference made a part of this Notice.

Bidders must be registered on the City of Camarillo’s PlanetBids portal in order to receive addendum notifications and to submit a bid. Go to PlanetBids for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.

Plans and special provisions are based on the use of the Standard Specifications for Public Works Construction, 202 1 edition, written and promulgated by Public Works Standards, Inc. and all supplements thereto.
(8-2023)

NOTICE INVITING BIDS
- 2 -
Bid Bond: The bid must be accompanied with an uploaded scanned copy to PlanetBids of the bid security in the form of a money order, a certified cashier’s check, or bidder’s bond executed by an admitted surety, made payable to CITY. The bid security shall be an amo unt equal to ten percent (10%) of the total annual bid amount included with their proposals as required by California law.

Note: The original security of the three (3) lowest bidders must be submitted to the Public Works Department at 601 Carmen Drive, Camarillo, California 93010, in a sealed envelope and be received or postmarked within three (3) City business days after the bid due date and time for the bid to be considered. The sealed envelope should list the Bidder’s Name and be plainly marked on the outside: “SEALED BID SECURITY FOR STANDBY POWER AT CITY HALL AND CORPORATION YARD – PROJECT NO. CH-5067-2.”
Pre-Bid Meeting: A non-mandatory pre-bid meeting is scheduled for 2:30 p.m. on July 9, 2024, in the Central Conference Room at Camarillo City Hall, 601 Carmen Drive, Camarillo, California 93010.

Required Contractor’s License(s): Under Business & Professions Code section 7028.15 (e), a bid submitted to the City must be by a licensed contractor in accordance with Division 3, Chapter 9 of the Business & Professions Code unless one of the exceptions in Section 7028.15 applies.

Under Public Contract Code section 3300, the bidder must possess at the time a contract is awarded all classifications of contractor’s licenses required by the City. For this project, the City requires that the bidder possess a valid Class A or B contractor’s license. The subcontractor performing electrical work must possess a valid C-10 contractor’s license.

Under Public Contract Code section 20103.5, failure of a bidder to be properly licensed at the time of the award of the contract will constitute a failure to execute the contract and will result in a forfeiture of the security of the bidder.

Required Contractor and Subcontractor DIR Registration: The City will accept bids only from bidders that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code § 7029.1) or if federal funds are involved in the project, then City may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded . Information on registration with the DIR is available at: https://www.dir.ca.gov/Public-Works/Contractor-Registration.html. This is a separate requirement from the Contractors State License Board licensing requirement.

Substitution of Securities: In accordance with Public Contract Code section 22300, substitution of eligible and equivalent securities for any moneys withheld to ensure performance under the contract for the work to be performed will be permitted at the request and expense of the successful bidder. Such equivalent securities must be deposited with City or with a state or federally chartered bank as the escrow agent who will then pay such moneys to the contractor.

Upon satisfactory completion of the contra ct, the securities will be returned to the contractor.

Securities eligible for investment include those listed in Government Code section 16430, bank or savings and loan certificates of deposit, interest bearing demand deposit accounts, standby letters of credit, or any other security mutually agreed to by the contractor and City. The contractor will be the beneficial owner of any securities used to secure its performance. Any escrow agreement will be substantially similar to the form set forth in Public Contract Code section 22300. (8-2023)

NOTICE INVITING BIDS
- 3 -
Federal Certificate: If this Notice indicates that this project is a federally-funded project and the Bid Proposal is for more than $100,000, the bidder and each of its subcontractors must submit signed copies of the Federal Certificate for Contracts, Grants, Loans and Coop erative Agreements.

Labor Code Compliance: Any contract entered into pursuant to this Notice will incorporate the applicable provisions of the California Labor Code.

Prevailing Wage Laws : The successful bidder must comply with all prevailing wage laws applicable to the project, and related requirements contained in the contract documents. Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the contract, as determined by Director of the State of California Department of Industrial Relations, are on file at the City, and may be obtained from the DIR website:
https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm. Upon request, City will make available copies to any interested party. Also, the successful bidder must post the applicable prevailing wage rates at the work site.

Payroll Records and Prevailing Wage Monitoring: This project is subject to prevailing wage compliance monitoring and enforcement by the Department of Industrial Relations. (Labor Code § 1771.4.). Each contractor and subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the contrac tor or subcontractor in connection with the public work. These records must be certified and made available by the contractor as required by Labor Code section 1776. In the case of state -funded public works projects, certified payroll reports must be provided to City on a weekly basis.

Reservation of Rights: The City Council reserves the right to reject any or all bids , waive any irregularities in the bids, and to make an award or any rejection in what it alone considers to be in the best interest of the City.

Dated this 25th day of June, 2024.

CITY OF CAMARILLO
By:

James Campero
Assistant Director of Public Works –
City Engineer

(8-2023)

INSTRUCTIONS TO BIDDERS
- 1 -

CITY OF CAMARILLO

INSTRUCTIONS TO BIDDERS

WORK IDENTIFICATION: STANDBY POWER AT CITY HALL AND

CORPORATION YARD
PROJECT NO. CH-5067-2

1. Terms Defined

1.1 Terms used in these Instructions to Bidders which are defined in the General Conditions/Specifications have the meaning assigned to them in the General Conditions/Specifications.

1.2 The term “successful bidder” means the lowest, responsible bidder to whom City makes an award of contract on the basis of City’s evaluation as provided in these Instructions.

1.3 The term “Standard Specifications” or “S.S.P.W.C.” means Standard Specifications for Public Works Construction written and promulgated by Public Works Standards, Inc., 2021 edition and all supplements thereto, available from BNi Publications, Inc., 990 Park Center Drive, Suite E Vista, CA 92081.

2. Copies of Contract Documents

2.1 Bidders may obtain complete sets of the Contract Documents from PlanetBids, the City of Camarillo website, or the City’s Public Works Department for the sum stated in the notice inviting bids.

2.2 Bidders will use a complete set of Contract Documents in preparing bids.

2.3 The City makes copies of the Contract Documents available, on the above terms, for the sole purpose of obtaining bids for the Work and does not confer a license or g rant permission for any other use of the Contract Documents.

2.4 Complete sets of Contract Documents must be used in preparing bids. It is the bidder’s obligation to ensure that the bidder has received a complete set of Contract Documents. Neither City nor its agents, officers or employees assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Contract Documents.

The City does not assume any liability or responsibility based on any defective or incomplete copying, excerpting, scanning, faxing, downloading, or printing of the Bidding Documents.

3. Qualifications of Bidder

3.1 The City will accept bids only from bidders that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to (8-2023)

INSTRUCTIONS TO BIDDERS
- 2 -
Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code §7029.1) or if federal funds are involved in the project, then City may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded. This is a separate requirement from the Contractors State License Board licensing requirement below.

3.2 The bidder must be licensed to perform as prime contractor in accordance with the provisions of the Contractor’s State License Law (Bus. & Prof. Code § 7000 and following). Prior to awarding a bid, unless an exemption set forth in Business and Professions Code section 7028.15 applies, City will verify that the bidder was properly licensed when the bid was submitted. If a bidder was not so licensed, the bid will be considered non-responsive and will be rejected by City.

Under Public Contract Code section 3300, the bidder must possess at the time a contract is awarded all classifications of contractor’s licenses required by the City. For this project, the City requires that the bidder possess a valid Class A or B contractor’s license. The subcontractor performing electrical work must possess a valid C-10 contractor’s license.

3.3 In addition to a state license, the contractor must also obtain a City of Camarillo business tax certificate before commencing work. The business tax certificate may be secured after the bids are opened, but prior to executing the contract. The business tax certificate must be kept current throughout the project until the recording of the Notice of Completion.

3.4 In order for City to determine the successful bidder, the bidder must be prepared to submit in writing, within five days after being requested to do so by City, such information and data as City may request, including without limitation, financial data, and previous experience. City reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy City that the bidder is the lowest responsible bidder properly qualified to carry out the contract.

3.5 The bidder may be required to establish to the satisfaction of City the reliability and responsibility of the persons or entities proposed to furnish and perform the work described in the Contract Documents.

3.6 Experience: The bidder must have a minimum of 3- years of experience in constructing work similar in character and magnitude to the work included in the bid. The work must be prosecuted with employees meeting the experience requirements along with appropriate apprentices. Employees used for satisfying this experience requirement or alternate staff with equal or better experience must be used continuously for the duration of the project.

Changes in staffing must be submitted for approval by the Engineer.

4. Examination of Contract Documents and Site

4.1 Before submitting a bid, the bidder must: (i) examine the Contract Documents thoroughly, including without limitation the Contract wherein each of the other Contract Documents is identified; (ii) visit the site and the locality where the work is to be performed to become familiar with local conditions that may in any manner affect the cost, progress or performance of the work in strict accordance with the Contract Documents; (iii) become familiar with all federal, state and local laws, ordinances, rules and regulations that may (8-2023)

INSTRUCTIONS TO BIDDERS
- 3 -
in any manner affect the cost, progress or performance of the work in strict accordance with the Contact Documents; and (iv) study and carefully correlate bidder’s observations with the Contract Documents.

4.2 Under Public Contract Code section 3400 and the Contract Documents, all specifications are deemed to include the words “or equal,” provided, however, permissible exceptions may be noted in the General Conditions/Specifications.

4.3 Reports, if any, of investigations and test of subsurface and latent physical conditions at the work site or otherwise affecting cost, progress or performance of the work which have been relied upon by the City Engineer in preparing the drawings and specifications are identified in the Special Provisions. City will make copies of such reports available to any bidder upon request. These reports are not guaranteed as to accuracy or completeness, nor are they part of the Contract Documents. Before submitting the bid, the bidder must, at bidder’s expense, make such additional investigations and tests as the bidder may deem necessary to determine its bid for performance of the work in strict accordance with the Contract Documents.

4.4 Upon request to the office of the City Engineer at 601 Carmen Drive, Camarillo, 805- 388-5340, City will provide each bidder reasonable access to the job site to conduct such investigations and tests as the bidder may deem necessary for submission of its bid. Bidders performing investigative testing must obtain permit and restore areas affected by such activities. Investigations and tests that cause unreasonable disruptions may not be permitted.

4.5 The lands upon which the work is to be performed, rights -of-way for access thereto and other lands designated for use by contractor in performing the work are identified in the Drawings and/or Specifications.

4.6 By submitting a bid, the bidder warrants that it has complied with every requirement of this Section 4 and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance of the work.

5. Interpretation

5.1 In the event of conflict between requirements as shown on the drawings and the specifications, the following order of precedence will govern: permits from other agencies; change orders; supplemental agreements and approved revisions to plans and specifications; Special Provisions; General Conditions/Specifications; plan details ; Plans; Standard Plans; Standard Specifications; Reference Specifications. In the event of any discrepancy between any drawings and the figures written thereon, the figures will govern.

5.2 All questions about the meaning or intent of the Contract Documents must be submitted to the Engineer in writing not less than five days prior to the date for the opening of bids.

5.3 All interpretations will be issued by written Addenda, which will be on file in the office of the City Engineer at 601 Carmen Drive, Camarillo, and posted to the City’s website, PlanetBids, and distributed to the planrooms listed in the Notice Inviting Bids It is the bidder’s responsibility to determine if any Addenda have been issued. Failure of the bidder to receive any such Addenda will not relieve the bidder from any obligation under its submitted bid. (8-2023)

INSTRUCTIONS TO BIDDERS
- 4 -

5.4 Only interpretations issued by written Addenda will be binding. All such Addenda will become part of the Contract Documents. Interpretations issued orally or by any means other than as specified in this Section 5 will have no legal effect.

6. Bid Proposal

6.1 Bids MUST be submitted on the City of Camarillo PlanetBids Portal. Hard copy bids submitted or any other method of bid submission to the City of Camarillo will not be accepted. Each bid must be on a Bid Proposal furnished by City as part of the Contract Documents. Any change in, or addition to, the Bid Proposal or any other modification of the Bid Proposal which is not specifically called for in the Contract Documents or the omission from the Bid Proposal of any information or response which is specifically called for in the Contract Documents may result in City’s rejection of the bid as not being responsive to the Notice Inviting Bids.

6.2 All blanks in the Bid Proposal must be appropriately responded to. If an answer or other response to a blank is not applicable, the bidder should respond with “N.A.”

6.3 Bid on all items listed in the Bid Schedule including all Prices (Unit and Total).

6.4 State in figures the unit prices, lump sum prices and extensions as indicated, which will be the prices for which you propose to supply all services and materials and to perform all work required by the plans and specifications. All items described are to be construed as complete and in place.

6.5 Include in the items for which bids are entered, all work shown on the plans or required by the specifications for which a specific bid item is not provided.

6.6 The Bid Proposal may not contain any erasures, interlineations or other corrections, unless each such correction is suitably authenticated by affixing in the margin immediately opposite the correction the initials of the person(s) signing the bid.

6.7 The Bid Proposal and each Attachment must be executed in the manner required by Section 14 below.

6.8 No person, including without limitation, any individual, partnership or corporation, may make, file or be interested in more than one bid for the work unless alternate bids are specifically called for in the Specifications. A person that has submitted a sub- bid to a bidder or that has quoted prices of materials to a bidder is not disqualified from submitting a sub-bid or quoting prices to other bidders or making a prime bid.

6.9 When the Notice Inviting Bids indicates that this project is a federally-funded project and the Bid Proposal is for more than $100,000, the bidder and each of its subcontractors must submit signed copies of the Federal Certificate for Contracts, Grants, Loans and Cooperative Agreements.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 5 -

7. Submission of Bid

7.1 The bid must be submitted within the time prescribed, at the place and in the manner indicated in the Notice Inviting Bids.

7.2 The bid must be accompanied by bidder’s security in an amount equal to at least ten percent (10%) of the bid amount, which security must be lawful money of the United States of America and in one of the following forms: (i) cash; (ii) cashier’s check made payable to City; (iii) certified check made payable to City; or (iv) bid bond executed by a surety insurer authorized to do business in the State of California and made payable to City. If the security is a bid bond, it must be submitted on the form which is part of the Bid Proposal or on a form substantially similar thereto. (Public Contract Code § 20170.)

7.3 All bids must be accompanied with an uploaded scanned copy of the bid security uploaded to PlanetBids. The original security of the three (3) lowest bidders must be submitted to the Public Works Department at 601 Carmen Drive, Camarillo, California 93010, in a sealed envelope and be received or postmarked within three (3) City business days after the bid due date and time for the bid to be considered. The sealed envelope should list the Bidder’s Name and be plainly marked on the outside: “SEALED BID SECURITY FOR STANDBY POWER AT CITY HALL AND CORPORATION YARD – PROJECT NO. CH-5067-2.”

7.4 The bid form, bid security, and all other documents required to be submitted with the bid must be submitted via electronic transmission on the City of Camarillo PlanetBids portal site as further described in the Notice to Bidders.

7.5 Bidders must be registered on the City of Camarillo’s PlanetBids portal in order to submit a bid. Go to the PlanetBids portal site for bid results and awards. It is the responsibility of the bidder to submit the bid with sufficient time to be received by PlanetBids prior to the bid opening date and time. Allow time for technical difficulties, uploading, and unexpected delays. Late or incomplete bids will not be accepted.

7.6 Submission of a bid on PlanetBids portal shall constitute acknowledgement and acceptance of all terms and conditions set forth herein.

8. Withdrawal or Modification of Bid

The bidder may withdraw or modify its bid in the PlanetBids Portal system at any time prior to the opening of bids.

9. Bids to Remain Open

All bids will remain open for 60 days after the date of the opening of bids. Prior to that date, City may, at its sole discretion, (i) release any bid and return the bidder’s security, or (ii) release all bids and return all bidder’s security, upon the successful bidder’s furnishing of the required bonds and certificate and any other required documents and return to City the required number of executed copies of the Contract.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 6 -

10. Errors In Bid

10.1 If a discrepancy between the unit price and the item total of a bid exists, the unit price will control unless the unit price is illegible, omitted, or the same as the item total, in which case the bid will be deemed nonresponsive. If applicable, the total bid amount will be adjusted according to any revised item totals.

10.2 If a discrepancy between the item totals and the total bid amount exists, the item totals will control unless the total bid is illegible or omitted, in which case the bid will be deemed nonresponsive.

10.3 Except as provided in Sections 10.4 and 10.5 below, bidders will not be released from their bids on account of error.

10.4 Where the prime contractor asserts a claim of inadvertent clerical error in the listing of a subcontractor, City will allow the substitution of the intended subcontractor under the procedures set forth in Public Contract Code section 4107.5.

10.5 Where the bidder gives City notice addressed to the City contact listed in the Project Administration page within five days of the opening of the bid and can establish to the satisfaction of City that a mistake was made which makes the bid materially different than intended, that the mistake was made in filling out the bid and not due to error in judgment or carelessness in inspecting the site or in reading the plans or specifications and specifies how the mistake occurred, City will relieve the bidder without forfeiture of security in accordance with Public Contract Code section 5100 and following.

11. Bid Analysis and Determination of Responsive Bid

11.1 After the bids have been opened and uploaded to Plane tBids, the Bid Schedule will be checked and compared; and after the withdrawal of any bids as provided in Section 8 above; and after errors in bids are adjusted as provided in Section 10 above, the results will be made public.

11.2 F ailure of a bidder to attend a mandatory pre -bid meeting will result in its Bid not being accepted and/or being rejected.

11.3 A b id from any individual, firm, partnership, corporation, or association which prepared, in part or in whole, the Plans, Specifications, or estimates for the Contract will be rejected.

11.4 More than one bid for the same Contract from any individual, firm, partnership, corporation, or association under the same or different names may be rejected.

Reasonable grounds for believing that any bidder has an interest in more than one b id for the Work may be cause for rejecting all bids in which such bidder is interested. However, this requirement does not prevent a bidder who submits a bid from being listed as a subcontractor by another bidder. Apparent collusion among bidders may be sufficient cause for rejecting any or all bids, and the participants in such collusion may be barred from future bidding.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 7 -

11.5 A bid in which a bid item is left totally blank will be considered nonresponsive and will be rejected.

11.6 A bid in which the Contract Unit Prices are unbalanced may be considered nonresponsive and may be rejected.

11.7 A b id in which the signature of the bidder has been omitted may be considered nonresponsive and may be rejected.

11.8 A bid in which each section of the Bid Proposal has not been completely filled out, or which shows any alteration of form or irregularities of any kind, or which contains any additions or conditional or al ternate b ids that are not called for, may be considered nonresponsive and may be rejected.

11.9 A b id in which the Acknowledgement of Addenda Received form is missing, or in which the receipt of each Addendum issued has not been acknowledged, may be considered nonresponsive and may be rejected.

11.10 A bid in which the Noncollusion Declaration form is missing, or in which the form has not been executed and signed, may be considered nonresponsive and may be rejected.

11.11 A b id in which the Request for Local D BE Program Preference Consideration and DBE Firm/Organization Information Form is missing, or in which the form has not been completely filed out, may be considered nonresponsive and may be rejected.

11.12 A bid in which the Bidder DBE Information form is required to be submitted with the b id and is missing, or in which the Bidder DBE Information is not submitted within the time specified in the Special Provisions, may be considered nonresponsive and may be rejected.

11.13 A bid in which the List of Subcontractors form is missing will be considered nonresponsive and will be rejected.

11.14 A b id in which the List of Subcontractors form or the Bidder DBE Information form is incomplete, or the data included therein is inaccurate, inconsistent, of a misrepresentation of the work to be subcontracted or materials to be procured, may be considered nonresponsive and may be rejected.

11.15 The bidder must perform, with its own organization, Contract work amounting to at least 50 percent of the Contract Price. A bid which fails to meet this requirement will be considered nonresponsive and will be rejected.

11.16 A bid in which the Bid Guaranty is missing, or in which the Bid Guaranty surety bond is not signed by the Surety, or in which the Surety has not had the Bid Guaranty surety bond notarized, or is not provided to the City, if one of the three lowest bidders, 3 business days after opening as further detailed in the NIB, will be considered nonresponsive and will be rejected.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 8 -

12. Award of Contract

12.1 City reserves the right to reject any and all bids. City also reserves the right to reject any bid that is not in strict accordance with the Contract Documents or, in the alternative, to waive any irregularity or informality in any bid or in the bidding.

12.2 If alternate bids are called for in the Specifications, the contract may be awarded at the election of City to the successful bidder on the base bid or on the base bid and any alternate or combination of alternates specifically identified in the Specifications as being used for the purpose of determining the lowest bid price.

12.3 If the contract is to be awarded, it will be awarded to the lowest responsible bidder. City may conduct such investigations as it deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of the bidders. The award, if made, will be within 60 days after the opening of bids.

12.4 If the lowest responsible bidder refuses or fails to execute the contract, City may consider the next lowest bidder to be the lowest responsible bidder.

12.5 The periods of time specified in this Section within which the award of contract may be made, are subject to extension for such further period as may be agreed upon in writing between City and the bidder concerned.

13. Delivery of Contract

13.1 An official “Notice of Award of Contract” will be emailed or mailed to the successful bidder, enclosing the contract and bond forms for signature.

13.2 Within 10 days after the Notice of Award of Contract, the successful bidder must sign and deliver at least three counterparts of the Contract to the City of Camarillo together with security in a form acceptable to City’s Attorney’s office guaranteeing both one hundred percent (100%) of payment (labor and materials) and one hundred percent (100%) of performance, certificates and endorsements to satisfy the insurance requirements of the Contract, proof of a valid City of Camarillo business tax certificate and any other documents required by the Contract Documents. Bonds must be submitted on the forms which are part of the Contract Documents; no substitutions will be accepted. Within 10 days of receipt of the Contract and related documents, City will deliver one fully signed counterpart of the Contract to the successful bidder.

13.3 The Contract and each attachment must be executed in the manner required by Section 14 below.

13.4 If the successful bidder fails to execute and deliver the Contract and furnish the required bonds, certificates and other documents within 10 days after the Notice of Award of Contract, City may annul the award of the contract and the bidder’s security will be forfeited, except as provided by Public Contract Code section 20174.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 9 -

14. Signatures

14.1 The Contract Documents and all attachments must be executed in the following manner: If the bidder is:

(a) An individual, in the name of the individual and if doing business by a fictitious name, the fictitious name and, if the document is the Bid Proposal or Contract, the business address and telephone number of the individual must be shown below the signature.

(b) A partnership, in the partnership name and signed by a general partner, whose title must appear under the signature and, if the document is the Bid Proposal or Contract, the business address and telephone number of the partnership must be shown below the signature.

(c) A corporation, in the corporate name by a duly authorized officer or agent accompanied by evidence of authority to sign and the corporate seal must be affixed and attested by the secretary or an assistant secretary. If the document is the Bid Proposal or Contract, the state of incorporation must be shown below the corporation name, and the corporate address and telephone number must be shown below the signatures.

14.2 Attorneys-in-fact who sign any Contract Document or any attachment thereto must file with the document a certified copy of their power of attorney to sign such document.

14.3 Electronic Signatures; Documents will be considered executed when the signature page of a party is delivered by electronic transmission. Such electronic signatures will have the same effect as an original signature.

14.4 Signatures on all bonds must be acknowledged before a notary public and a notary’s certificate of each acknowledgment must be scanned and uploaded to Planet Bids with the document.

15. Time for Commencement and Completion

15.1 Unless otherwise specified in the Special Provisions, the contractor must:

(a) commence the work within 30 days after the award of the contract by the City Council, but not before fully complying with Sections 13 and 14 above; and

(b) diligently prosecute the work to completion within the allowed number of working days specified on Page 1 of the Bid Proposal, counting from the start date given in the Notice to Proceed.

15.2 Upon written request of the Contractor and if approved in writing by the City Engineer, the time for commencement, completion or both may be extended.

(8-2023)

INSTRUCTIONS TO BIDDERS
- 10 -

16. Bid Protest

16.1 Any protest of any bid must be submitted in writing to the Office of the City Clerk by email to [email protected] or by facsimile transmission to 805 -388-5318 no later than 5:00 PM on the seventh calendar day following the date of the bid opening.

16.2 The protest must contain a complete statement of the factual basis for the protest and copies of pertinent documents.

16.3 The protest must identify the specific portion of the document and the specific statute, if any, that forms the basis for the protest. The protest must include the name, mailing address, email address and telephone number of the person representing the protesting party.

16.4 The party filing the protest must have actually submitted a bid for the Project. A subcontractor of a party filing a bid for the Project may not submit a bid protest. A party may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest.

16.5 The procedure and time limits set forth in these Instructions to Bidders are mandatory and are the bidders’ sole and exclusive remedy in the event of a bid protest. Any bidder’s failure to fully comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including filing of a challenge of the award pursuant to the Public Contract Code, filing of a claim pursuant to the Government Code, or filing of any other legal proceedings.

16.6 The City Director of Public Works , or designee, will review all timely protests prior to award of the Project and will recommend that the City Council either reject the protest and award to the lowest responsible and responsive bidder or accept the protest and award the bid to the next lowest responsible and responsive bidder.

17. Liquidated Damages

The amount of liquidated damages for each calendar day , is set forth on page 1 of the Bid Proposal, in accordance with Section 6.5 of the General Conditions/Specifications.

18. Survey Data

18.1 Electronic survey data will not be made available to the bidder as part of the bid process and no such data should be relied upon for the purposes of preparing the bid.

Survey data desired by bidders should be obtained in the field by the bidder. Permits for survey work may be necessary.

(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 1 -

CITY OF CAMARILLO

DEPARTMENT OF PUBLIC WORKS

BID PROPOSAL

FOR

STANDBY POWER AT CITY HALL AND CORPORATION YARD
PROJECT NO. CH-5067-2

In and for the

CITY OF CAMARILLO, CALIFORNIA

Project Number CH-5067-2, including thirty (30) sheets of plans. Drawings Numbers C18622 through C18651.

Completion Time: Sev enty-five (75) Working Days

Bids To Be Received: 3: 00 p.m. on August 1, 2024

Liquidated Damages: Pr oject Milestone Dates as follows:

Electrical Delays: $2,500 Per Calendar Day
Stormwater: $250 Per Calendar Day
Project Complete: $1,500 Per Calendar Day

Name of Contractor

Address

Telephone

State Contractor’s License Number

Department of Industrial Relations Registration Number
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 2 -

BID PROPOSAL

WORK IDENTIFICATION: STANDBY POWER AT CITY HALL AND CORPORATION YARD PROJECT NO. CH-5067-2

NAME AND ADDRESS OF BIDDER:

Before awarding a bid, City will verify that bidder was properly licensed in accordance with Business and Professions Code sections 7000 and following. City will also verify that bidder that (along with all subcontractors listed) are currently registered and qualified to perform public work pursuant to Labor Code section 1725.5; provided, however, that if a bidder is a joint venture (Business & Professions Code §7029.1) or if federal funds are involved in the project, then City may accept a non-complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded. Bidder acknowledges that if the bidder is not properly licensed or registered at the time the bid is awarded or as otherwise required by law, the bid will be considered non-responsive and will be rejected.

1. Proposal

(a) Bidder has examined copies of all of the Contract Documents, including without limitation the document wherein each of the other Contract Documents is identified, and accepts all of the terms and conditions of the Contract Documents.

(b) Bidder proposes and agrees, if this bid is accepted, to enter into an agreement with City in the form included in the Contract Documents to complete all work as specified in the Contract for the contract price and within the contract time indicated in this bid and in accordance with the Contract Documents.

(c) This bid will remain open and not be withdrawn for the period specified in the Instructions to Bidders. If awarded the bid, bidder will sign the Contract and submit the bonds, certificates and other documents required by the Contract Documents within 10 days after the date of the Notice of Award of Contract.

(d) Bidder has examined the site and locality where the work is to be performed and the legal requirements and conditions affecting the cost, progress and performance of the work in strict accordance with the Contract Documents.

2. Payroll and Compliance Reports

Each contractor and subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by the contractor or subcontractor in connection with the public work. Such records must be certified and made available for (5-2023) Project No. CH-5067-2

BID PROPOSAL
- 3 -

inspection at all reasonable hours at the principal place of the contractor as required by Labor Code section 1776. In the case of state funded public works projects, certified payroll reports must be provided to City on a weekly basis. In the case of federally-funded public works project and in accordance with 29 C.F.R. § 5.5(a)(3), bidder agrees to furnish to City weekly payroll reports and weekly compliance statements for all labor used on this project.

3. Bid

If the Contract Documents include a Unit Price List, bidder acknowledges that the total bid sum shown on the Bid Schedule(s) and the estimated quantities and amounts shown on the Unit Price List are for purposes of comparison of bids only. Bidder also acknowledges that City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work as may be deemed necessary or expedient by the City and that final payment will be made at the unit prices bid, upon the basis of actual measured quantities as determined by the City Engineer or his/her designee.

Bidder acknowledges that the total Bid Schedule(s) and all sums shown on any Unit Price List attached thereto, includes (i) all labor, materials, tools, equipment and services and all taxes, insurance, other general expenses, overhead and profit and (ii) all trenching, backfilling, grading, excavation and fill, resurfacing of every character, grubbing and clearing and removal of all obstructions necessary for the doing of the work, the preservation of existing structures, shrubs, and trees, where required, and the shoring, bridging and bracing required and incident to the doing of the work, together with all fittings and joints, of every character, connected in place, area clean- up, traffic protection, and the reconstruction and severances required in the doing of the work.

Items for which quantities are indicated as “Lump Sum,” “L.S.,” “job” or words of like import will be paid for at the price named. Such payment will be full compensation for the work named and all work appurtenant thereto required by the contract that is not specifically provided for by other pay items.

4. Schedule

Bidder understands that tim ely completion is important to City. Therefore, time being of the essence, bidder proposes that the work will be commenced and will be completed as specified herein and in Section 15 of the Instructions to Bidders.

5. Addenda

Bidder acknowledges receipt of Addenda identified as:

(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 4 -

6. Bidder Information

(a) Bidder has ________ years of experience as a contractor in construction work.

(b) Bidder has recently completed the three following construction works similar in character and magnitude to the work included in the bid in accordance with Section 3.6 of the Instructions to Bidders:

Class
Amount
Class
of Work
Date
Completed

Name/Address/Telephone # of Owner

7. Designation of Subcontractors

In compliance with the Subletting and Subcontracting Fair Practices Act, Public Contracts Code section 4100 and following, listed on page 5 is each subcontractor who will perform work or labor or render service to the bidder in or about the construction of the work or will specifically fabricate and install a portion of the work in an amount in excess of one half of one percent (0.5%) of the total bid sum or in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one- half of one percent (0.5%) of the total bid or $10,000, whichever is greater. (List only one subcontractor for each portion of the work as is defined by the bidder in this bid.) No other subcontractors may be used other than those specified without written approval of the City Engineer ; such approval will be made upon showing by the contractor of good and sufficient cause.

Failure to specify a subcontractor or specifying more than one subcontractor for the same portion of work to be performed under the contract in excess of one- half of one percent (0.5%) of the total bid constitutes an agreement that the contractor is fully qualified and will perform that portion of the work. Any contractor who subcontracts for any portion of work not set forth herein, except as otherwise provided by Public Contract Code sections 4107 or 4109, will be subject to the penalties set forth in Public Contract Code sections 4110 and 4111.

(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 5 -

PROPOSAL

LIST OF SUBCONTRACTORS
WORK IDENTIFICATION: STANDBY POWER AT CITY HALL AND CORPORATION YARD PROJECT NO. CH-5067-2

NAME AND ADDRESS OF BIDDER:

Completion of this form must comply with Section 7 of the Bid Proposal.

Name/Address/State License
Number of Subcontractor
Department of Industrial
Relations Registration
Number*

Items of Work
Portion of Work
(% of Contract Price)

% of Total Contract
Price by Subcontract

% of Total Contract
Price by Contractor

*Pursuant to Division 2, Part 7, Chapter 1 (commencing with section 1720 including section 1725.5) of the Labor Code
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 6 -

8. Attachments

The following documents, signed in accordance with Section 13 of the Instructions to Bidders, are attached to, and made a part of, this Bid Proposal:

(a) N
oncollusion Declaration, as required by Public Contract Code section 7106 and made a part of this Bid Proposal.

(b) Required Bidder’s Security in the form of

(c) Unit Price List, if required

(d) Federal Certificate, if required

(e) Other pertinent Documents (list here and attach to this bid)

Dated this __________ day of ____________________, 20____. (5-2023) Project No. CH-5067-2

BID PROPOSAL
- 7 -

If BIDDER is:

An Individual
By:
(Print Individual’s Name)
doing business as
Business Address:

Telephone Number:

Signature
A Partnership

(Firm Name)
By:
(Print General Partner’s Name)

(Title)
Business Address:

Telephone Number:

Signature
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 8 -

A Corporation

(Corporation Name)

(State of Incorporation)
By:
(Print Name and Title of Person Authorized to Sign)
(Corporate Seal)
Signature
Attest:
(Secretary)
Business Address:

Telephone Number:

Signature
A Joint Venture
By:
(Print Name)

(Address and Telephone Number)
By:
(Print Name)

(Address and Telephone Number)

Signature

Signature
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 9 -

NONCOLLUSION DECLARATION

TO BE EXECUTED BY BIDDER

AND SUBMITTED WITH BID
The undersigned declares:

I am the _________________ of ______________, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.

Executed this ________ day of ___________________, 20___, at _____________________, California.

Firm (print or type) Signature

(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 10 -

BID SCHEDULE

UNIT PRICE LIST -- FIGURES

WORK IDENTIFICATION STANDBY POWER AT CITY HALL AND CORPORATION YARD PROJECT NO. CH-5067-2

NAME OF BIDDER:

Item
No. Item Description Quantity Unit
Unit Price
in Figures
*Item Total
Price in
Figures
1 Mobilization, Bonds, and Insurance 1 LS

2 Clearing and Grubbing 1 LS

3 Stormwater Pollution Control Plan 1 LS

4 Construct CMU Enclosures and Concrete
Pads 1 LS

5 Trench and Install Utility Runs 1 LS

6 Furnish and Install Switchgears 1 LS

7 Install City-Furnished Generators 1 LS

8 Electrical 1 LS

9 Functional Testing 1 LS

TOTA L BID $

*NOTE: In case of error in extension of price into the total price column, the unit price will govern.
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 11 -

BIDDER’S INFORMATION CERTIFICATION
Bidder certifies that the following information is true and correct:

Bidder’s Name
Business Address

Telephone
State Contractor’s License No. and Class
Original Date Issued Expiration Date
The following are the names, titles, addresses, and phone numbers of all individuals, firm members, partners, joint venturers, or corporate officers having a principal interest in this bid:

The dates of any voluntary or involuntary bankruptcy judgments against any principal having an interest in this bid are as follows:

All current and prior DBAs, alias, and/or fictitious business names for any principal having an interest in this bid are as follows:

I declare under penalty of perjury under the laws of the State of California that the above representations are true and correct.

Executed this ________ day of ___________________, 20___, at _____________________, California.

Signature and Title of Authorized Official
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 12 -

DECLARATION OF ELIGIBILITY TO CONTRACT
The undersigned, a duly authorized representative of the bidder, certifies and declares that:

1. The bidder is aware of Labor Code sections 1771.1 and 1777.7, which prohibit a contractor or subcontractor who has been found by the Labor Commissioner or the Director of Industrial Relations to be in violation of certain provisions of the Labor Code from bidding on, being awarded, or performing work as a subcontractor on a public works project for specified periods of time.

2. T he bidder is currently registered and qualified to perform public work pursuant to Labor Code section 1725.5 and is not prohibited from bidding on, being awarded, or performing work as a contractor or subcontractor on a public works project under Labor Code sections 1771.1 and 1777.7, or any other provision of law; provided, however, that if a bidder is a joint venture (Business & Professions Code § 7029.1) or if federal funds are involved in the project, then City may accept a non- complying bid provided that the bidder and all listed subcontractors are registered at the time the contract is awarded.

3. The bidder is aware of Public Contract Code section 6109, which states:
(a) A public entity, as defined in Section 1100 [of the Public Contract Code], may not permit a contractor or subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to Section 1771.1 or 1777.7 of the Labor Code to bid on, be awarded, or perform work as a subcontractor on, a public works project. Every public works project shall contain a provision prohibiting a contractor from performing work on a public works project with a subcontractor who is ineligible to perform work on the public works project pursuant to Section 1777.1 or 1777.7 of the Labor Code. (b) Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract, and any public money that may have been paid to a debarred subcontractor by a contractor on the project will be returned to the awarding body. The contractor is responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project.

4. The bidder has investigated the eligibility of each and every subcontractor that bidder intends to use on this public works project, and determined that none of them is ineligible to perform work as a subcontractor on a public works project by virtue of Public Contract Code section 6109, Labor Code sections 1725.5, 1771.1 and 1777.7, or any other provision of law.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.

Executed this ________ day of ___________________, 20___, at ______________________, California.

Signature and Title of Authorized Official
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 13 -

BID BOND
(not necessary when certified check or cash accompanies bid)

PROJECT TITLE: ___________________

WHEREAS,
(“Contractor”) intends to submit a bid to the City of Camarillo, California, a municipal corporation (“City”), for the work identified as follows:

NOW, THEREFORE, we, the Contractor, as Principal, and
,
a corporation organized and existing under the laws of the State of and duly authorized to transact business under the laws of the State of California, as Surety, are held and firmly bond unto City in the sum of
dollars ($ )
lawful money of the United States of America, such sum being not less than ten percent (10%) of the bid amount for the payment of which sum to be made, the Principal and Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if City accepts the bid of the Principal and enters into a contract in accordance with the terms of the bid, the Principal must give the bonds, certificates and other documents as required by the Notice Inviting Bids or the other contract documents. In the event Principal fails to enter into such contract or provide the bonds, certificates or other documents, City may apply this security to the difference between the low bid and the next lowest bidder with whom City contracts to perform the work covered by the bid; the surplus, if any, will be returned to Surety. In case suit is brought upon this bond, the court will fix and award and the Surety must pay, in addition to the face amount hereof, all costs and reasonable attorney’s fees incurred by City in successfully enforcing the obligations of this bond.
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 14 -

IN WITNESS THEREOF, we have hereunto set our hands and seals this day of , 20 .

(affix seal below) [PRINCIPAL]

By

Title

(affix seal below) [SURETY]

By

Title

Address

[P.C.C. §§ 20170, 20171]

* ALL SIGNATURES ON THIS BID BOND MUST BE NOTARIZED USING APPROPRIATE 8 ½” x 11” NOTARY ACKNOWLEDGEMENT FORM.

** Corporations must affix corporate seal.
(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 15 -

CERTIFICATION FOR CONTRACTS,

GRANTS, AND COOPERATIVE AGREEMENTS

(Federal Fiscal Year October 1, 20____, to September 30, 20____)

I, ,
(Name and Title of Grantee Official)

hereby certify on behalf of th
at
(Name of Grantee)

(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.

(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an office or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned must complete and submit Standard Form -LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U. S. Code. Any person who fails to file the required certification will be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

Executed this __________ day of __________________, 20____.

By:
(Signature of Authorized Official)

(Title of Authorized Official)

(5-2023) Project No. CH-5067-2

BID PROPOSAL
- 16 -

CERTIFICATION REGARDING DEPARTMENT OF INDUSTRIAL

RELATIONS CONTRACTOR / SUBCONTRACTOR REGISTRATION

By my signature hereunder, as the Contractor, I certify that Contractor, and all Subcontractors listed on the “List of Subcontractors” are registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.

Contractor’s Department of Industrial Relations registration number is _____________.

Subcontractors’ Department of Industrial Relations registration numbers are as indicated in the Subcontractors List.

Executed this __________ day of __________________, 20____.

By:
(Signature of Authorized Official)

(Title of Authorized Official)

Project No. CH-5067-2

STATE OF CALIFORNIA – DEPARTMENT OF INDUSTRIAL RELATIONS

FORMS MUST BE COMPLETED AND SUBMITTED FOR BID PROPOSAL
WITHIN NO LATER THAN 4:00 P.M. (LOCAL TIME) ON FOURTH BUSINESS

DAY AFTER BID OPENING

• Submit State of California DIR-PWC 100 form

STATE OF CALIFORNIA – DEPARTMENT OF INDUSTRIAL RELATIONS TO: California Department of Industrial Relations
Division of Apprenticeship Standards
P.O. Box 420603
San Francisco, CA 94142
FROM:

AWARDING AGENCY ID NUMBER:

If you do not have an ID number please contact DAS

EXTRACT OF

PUBLIC WORKS CONTRACT AWARD
A CONTRACT TO PERFORM PUBLIC WORKS UNDER LABOR CODE SECTION 1777.5 HAS BEEN AWARDED TO:

1. NAME OF GENERAL CONTRACTOR 2. CONTRACTOR’S LICENSE NO

3. MAILING ADDRESS (STREET NUMBER OR P.O. BOX) 4. CITY

5. ZIP CODE 6. TELEPHONE NUMBER

7. GENERAL CONTRACTOR’S CONTACT EMAIL ADDRESS 8.ADDRESS/LOCATION OF PUBLIC WORKS SITE (INCLUDE CITY AND COUNTY):
8a. County

9. NAME OF PROJECT

10. CONTRACT NUMBER 11. PROJECT NUMBER 12. DOLLAR AMOUNT OF CONTRACT AWARD

13. FIRST ADVERTISED BID DATE

MONTH DAY YEAR
14 CONTRACT AWARD DATE

MONTH DAY YEAR
12a ESTIMATED TOTAL PROJECT COSTS, IF DIFFERENT FROM
ITEM 12 (see instructions).

15. WHICH STATUTE, IF ANY, APPLIES TO THIS PROJECT?

16. STATE CONSTRUCTION BONDS YES NO
If YES, List the Sources and Dollar Amount of Bond Proceeds:

SOURCES DOLLAR AMOUNT

17. WILL YOU OPERATE A DIR-APPROVED LABOR COMPLIANCE
PROGRAM (LCP) FOR THIS PROJECT?
YES NO

18. IS THERE A PROJECT LABOR AGREEMENT (PLA) ASSOCIATED WITH THIS PROJECT? If yes, please email a copy to [email protected] YES NO

19. STARTING DATE (ESTIMATED OR ACTUAL)
(MM/DD/YYYY)

20. COMPLETION DATE (ESTIMATED OR ACTUAL)
(MM/DD/YYYY)

21. BRIEF DESCRIPTION OF WORK TO BE PERFORMED 22.

NEW CONSTRUCTION REMODELING

ALTERATION, DEMOLITION, REPAIR OR MAINTENANCE

23. CLASSIFICATION OR TYPE OF WORKER (CARPENTER, PLUMBER, ETC.) THAT WILL BE EMPLOYED BY THE CONTRACTOR(S) Please list Sub-contractors and their worker classifications on page 2

24. Is language included in the Contract Award to effectuate the requirements of sections 1771, 1774, 1775, 1776, 1777.5, 1813, and 1815 of the Labor Code? YES NO

25. SIGNATURE 26.TITLE 27.DATE

28. PRINTED OR TYPED NAME 29.E-MAIL ADDRESS 30.TELEPHONE NUMBERS If different from above, name, title, and contact information of person responsible for carrying out Awarding Body’s LCP or CMU responsibilities.

31. NAME 32.TITLE 33. E-MAIL ADDRESS 34. TELEPHONE NUMBER

Duplication of this form is permissible
DIR-PWC 100 (rev. 10/11) successor to the DAS 13 form
EXTRACT OF PUBLIC WORKS CONTRACT AWARD (Continued)
Listing of Sub Contractors
Con. Lic. # Contractor Classification of workers

DIR-PWC 100 (rev. 10/11) successor to the DAS 13 form
(12-2023) Project No. CH-5067-2

CONTRACT

Page 1 ends

CITY OF CAMARILLO

PUBLIC WORKS CONTRACT
This contract (“Contract”) is effective as of __________________________, and is between the C ITY OF C AMARILLO, a California general law city and municipal corporation (“City”), a nd ____________________________________, a corporation/partnership/limited liability company (“Contractor”), collectively referred to as the “Parties.” Section 1. Reci tals. This Contract is entered into with respect to the following facts:

1.1 City noticed and received bids for the work involved in Standby Power at City Hall and Corporation Yard - Project No. CH-5067-2 (“Project”), which is more fully described in the Contract Documents.

1.2 The City Council o f City determined that Contractor was the lowest responsive bidder and awarded to Contractor the bid.

1.3 Contractor has represented it is qualified to perform all of the work required to complete the Project.

1.4 Contractor has agreed to perform all such work in the time and manner set forth in the Contract Documents.

1.5 The City Council of City has determined that the public interest, convenience and necessity require the execution of this Contract and its implementation.

Section 2. Cont
ract Documents . This Contract consists of the following documents (“Contract Documents”), all of which are made a part of this Contract:

2.1 Notice Inviting Bids

2. 2 Instructions to Bidders

2.3 Bid Proposal, as accepted, including the Certificate of Bidders’ Experience and Qualifications and the List of Subcontractors

2.4 Notice of Award

2.5 Notice to Proceed

2.6 This Contract

2.7 Verification of California Contractor’s License

2.8 Contractor’s Certificate Regarding Workers’ Compensation

2.9 Security for payment (labor and materials)

2.10 Security for performance
(12-2023) Project No. CH-5067-2

CONTRACT

Page 2 ends

2.11 Certificate(s) of Insurance

2.12 General Conditions/Specifications

2.13 Special Provisions

2.14 Plans and Standard Drawings

2.15 Prevailing Wage Scales

2.16 S. S. P. W. C.

2.17 Addenda Nos.

2.18 Other documents (list here)
Exhibit A – Co mpensation
Exhibit B – Insurance

Section 3. The Work.

3.1 The work (“Work”) to be performed by Contractor is described in the Contract Documents.

3.2 In completing the Work, Contractor must employ, at a minimum, the applicable generally accepted professional standards of its industry in existence at the time of performance as utilized by persons engaging in similar work.

3.3 Except as specifically provided in the Contract Documents, Contractor must furnish, at its sole expense, all of the labor, materials, tools, equipment, services and transportation necessary to perform all of the Work.

3.4 Contractor must perform all of the Work in strict accordance with the Contract Documents.

Section 4. Ti
me to Perform the Work.

4.1 Time is of the essence with respect to Contractor’s Work. Contractor agrees to diligently pursue performance of the Work within the time specified by the Contract Documents.

4.2 Contractor will be excused from any delay in performance or failure to perform due to causes beyond the control of Contractor. Such causes include, but are not limited to, acts of God, acts of terrorism, acts of federal, state or local governments, acts of City, court orders, fires, floods, epidemics, strikes, embargoes, and unusually severe weather.
(12-2023) Project No. CH-5067-2

CONTRACT

Page 3 ends

4.3 If Contractor is delayed by any cause beyond Contractor’s control, City may, but is not required to, grant a time extension for the completion of the Work. If delay occurs, Contractor must notify City in writing within 48 hours of the cause and the extent of the delay and how such delay interferes with Contractor’s performance of the Work.

Section 5. Com
pensation and Payment.

5.1 Subject to any limitations provided in the Contract Documents, City agrees to pay Contractor as full consideration for the faithful performance of all of the Work the compensation set forth in Exhibit A (“Compensation”), which is made a part of this Contract.

5.2 Contractor must furnish Cit y with a Pay Estimate for the Work performed in accordance with the Contract Documents. Contractor may not submit a Pay Estimate more often than once every 30 days.

5.3 City will review each Pay Estimate and determine whether the Work performed is in accordance with the Contract Documents. The Director of Public Works (“Director”) m ay require Contractor to provide a release of all undisputed Contract amounts contained in the Pay Estimate.

5.4 If City disputes any item on a Pay Estimate , City will give Contractor notice stating the reasons for the dispute. The Parties will meet and confer in good faith to attempt to resolve the dispute.

5.5 Except as to any charges for the Work performed that City disputes and the City’s standard five-percent retention of the approved progress payment, City will cause Contractor to be paid within 30 days of the date of the invoice or the date that Contractor furnishes City with a release of all undisputed Contract amounts, whichever occurs later. Federally funded projects will not have a five -percent retention.

5.6 In the event there is any claim specifically excluded by Contractor from the operation of any release, City may retain an amount not to exceed the amount of the excluded claim.

Section 6. Labor
Code and Prevailing Wage Requirements.

6.1 Contractor agrees to comply with the requirements of California Labor Code sections 1810 through 1815. Eight hours of labor constitutes a legal day’s work per Labor Code s ection 1810. Contractor will forfeit the statutory penalty to City for each worker employed in the execution of this Contract by Contractor or any subcontractor for each calendar day during which such worker is required or permitted to work more than eight hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Labor Code sections 1810 through 1815.

6.2 Copies of the determination of the Director of the Department of Industrial Relations of the prevailing rate of per diem wages for each craft, classification or (12-2023) Project No. CH-5067-2

CONTRACT

Page 4 ends

type of worker needed to execute this Contract are available for download from the State website: https://www.dir.ca.gov/OPRL/dprewagedetermination.htm.

6.3 Contractor must post at the work site, or if there is no regular work site then at its principal office, for the duration of the Contract, a copy of the determination by the Director of the Department of Industrial Relations of the specified prevailing rate of per diem wages. (Labor Code § 1773.2.) When applicable, copies of the prevailing rate of per diem wages will be on file at City’s Department of Public Works and available to Contractor and any other interested party upon request.

6.4 Contractor, and any subcontractor engaged by Contractor, may pay not less than the specified prevailing rate of per diem wages to all workers employed in the execution of the contract. (Labor Code § 1774.) Contractor is responsible for compliance with Labor Code section 1776 relative to the retention and inspection of payroll records.

6.5 Contractor must comply with all provisions of Labor Code section 1775. Under Section 1775, Contractor will forfeit the statutory penalty to City for each worker employed in the execution of the Contract by Contractor or any subcontractor for each calendar day, or portion thereof, in which the worker is paid less than the prevailing rates. Contractor may also be liable to pay the difference between the prevailing wage rates and the amount paid to each worker for each calendar day, or portion thereof, for which each worker was paid less than the prevailing wage rate.

6.6 Nothing in this Contract prevents Contractor or any subcontractor from employing properly registered apprentices in the execution of the Contract. Contractor is responsible for compliance with Labor Code section 1777.5 for all apprenticeable occupations. This statute requires that contractors and subcontractors must submit contract award information to the applicable joint apprenticeship committee, must employ apprentices in apprenticeable occupations in a ratio of not less than one hour of apprentice’s work for every five hours of labor performed by a journeyman (unless an exception is granted under § 1777.5), must contribute to the fund or funds in each craft or trade or a like amount to the California Apprenticeship Council, and that contractors and subcontractors must not discriminate among otherwise qualified employees as apprentices solely on the ground of sex, race, religion, creed, national origin, ancestry or color. Only apprentices defined in Labor Code section 3077, who are in training under apprenticeship standards and who have written apprentice contracts, may be employed on public works in apprenticeable occupations.

6.7 Contractor has reviewed and agrees to comply with any applicable provisions for any public work subject to Department of Industrial Relations (DIR) Monitoring and Enforcement of prevailing wages, including the registration requirements of Labor Code Section 1771.1(a). City hereby notifies Contractor that Contractor is responsible for submitting certified payroll records directly to the State Compliance Monitoring Unit (CMU). For further information concerning compliance monitoring please visit the website location at:
https://www.dir.ca.gov/dlse/cmu/cmu.html.
(12-2023) Project No. CH-5067-2

CONTRACT

Page 5 ends

6.8 Contractor must comply with Labor Code section 1771.1(a), which provides that Contractor may award any contracts and subcontracts for work that qualifies as a “public work” only to subcontractors which are at that time registered and qualified to perform public work pursuant to Labor Code S ection 1725.5.

Contractor must obtain proof of such registration from all such subcontractors.”

6.9 If federal funds are used to pay for the Work, Contractor and any subcontractor agree to comply, as applicable, with the labor and reporting requirements of the Davis-Bacon Act (40 USC § 276a-7), the Copeland Act (40 USC § 276c and 18 USC §874), and the Contract Work Hours and Safety Standards Act (40 USC § 327 and following).

Section 7. Non-D
iscrimination. Contractor, its officers, agents, employees, and subcontractors may not discriminate in the employment of persons to perform the Work in violation of any federal or state law prohibiting discrimination in employment, including based on the race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation, of any person, except as provided under California Government Code section 12940. Contractor is responsible for compliance with this section.

Section 8. Genera
l Legal Compliance.

8.1 In performing the Work, Contractor must comply with all applicable statutes, laws and regulations, including, but not limited to, OSHA requirements and the Camarillo Municipal Code.

8.2 Contractor must, at Contractor’s sole expense, obtain all necessary permits and licenses required for the Work, and give all necessary notices and pay all fees and taxes required by law, including, without limitation, any business license tax imposed by City. Contractor is exempt from any City encroachment permit fee pursuant to Camarillo Municipal Code Section 13.04.020.

8.3 Contractor must maintain a valid California Contractor’s License throughout the term of this Contract.

Section 9. Cl
ayton and Cartwright Act Assignments. In entering into this Contract or a contract with a subcontractor to supply goods, services, or materials pursuant to this Contract for the Project, Contractor and any subcontractor will be deemed to have offered and agreed to assign to City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700 of Part 2 of Division 7 of the California Business and Professions Code), arising from purchases of goods, services, or materials for the Project. This assignment will be deemed made and will become effective at the time City tenders final payment to Contractor, without further acknowledgement by the Parties.

Section 10. Independent
Contractor. Contractor is and will at all times remain as to City a wholly independent contractor. Neither City nor any of its officers, employees, or (12-2023) Project No. CH-5067-2

CONTRACT

Page 6 ends

agents will have control over the conduct of Contractor or any of Contractor’s officers, employees, agents or subcontractors, except as expressly set forth in the Contract Documents. Contractor may not at any time or in any manner represent that it or any of its officers, employees, agents, or subcontractors are in any manner officers, employees, agents or subcontractors of City.

Section 11. Indem nification.

11.1 Contractor agrees to the fullest extent permitted by law to (1) immediately defend and (2) indemnify City from and against, any and all claims and liabilities, regardless of the nature or type, that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of Contractor, or its officers, employees, agents, or subcontractors committed in performing any Work under this Contract or the failure to comply with any of the obligations of this Contract (collectively, “Claims”). The Claims subject to Contractor’s duties to defend and indemnify include, without limitation, all claims, actions, causes of action, proceedings, suits, losses, damages, penalties, fines, judgments, liens, levies, and associated investigation and administrative expenses. Such Claims also include defense costs, including reasonable attorneys’ fees and disbursements, expert fees, court costs, and costs of alternative dispute resolution.

11.2 Contractor’s duty to defend is a separate and distinct obligation from Contractor’s duty to indemnify. Contractor is obligated to defend City in all legal, equitable, administrative, or special proceedings, with counsel approved by City, immediately upon tender to Contractor of the Claim in any form or at any stage of an action or proceeding, whether or not liability is established. An allegation or determination that persons other than Contractor are responsible for the Claim does not relieve Contractor from its separate and distinct obligation to defend under this section. The obligation to defend extends through final judgment, including exhaustion of any appeals. The defense obligation includes an obligation to provide independent defense counsel if Contractor asserts that liability is caused in whole or in part by the negligence or willful misconduct of any City indemnified party. If it is finally adjudicated that liability was caused by the comparative active negligence or willful misconduct of any City indemnified party, then Contractor may submit a claim to City for reimbursement of reasonable attorneys’ fees and defense costs in proportion to the established comparative liability of the City indemnified party.

11.3 Contractor agrees that its defense and indemnification obligation under this section, includes the reasonable costs of attorneys’ fees incurred by the City Attorney’s office to monitor and consult with Contractor regarding the defense of any Claims, including providing direction with regard to strategy, preparation of pleadings, settlement discussions, and attendance at court hearings, mediations, or other litigation related appearances. City will use its best efforts to avoid duplicative attorney work or appearances in order to keep defense costs to a reasonable minimum.

11.4 Contractor agrees that settlement of any Claim will require the consent of City.

City agrees that its consent will not be unreasonably withheld provided that Contractor is financially able (based on demonstrated assets) to fulfill its (12-2023) Project No. CH-5067-2

CONTRACT

Page 7 ends

obligation to indemnify City for the costs of any such settlement as required under this Contract.

11.5 Contractor’s obligation to indemnify City applies unless it is finally adjudicated that the liability was caused by the sole active negligence or sole willful misconduct of a City indemnified party. If a Claim is finally adjudicated and a determination made that liability was caused by the sole active negligence or sole willful misconduct of a City indemnified party, then Contractor’s indemnification obligation will be reduced in proportion to the established comparative liability.

11.6 For the purposes of this section, “ City” includes City’s officers, officials, employees and agents.

11.7 The provisions of this section will survive the expiration or earlier termination of this Contract.

Section 12. Insur
ance. Contractor agrees to have and maintain in full force and effect during the term of this Contract the insurance coverages listed in Exhibit B (“Insurance”), which is made a part of this Contract.

Section 13. Noti ce.

13.1 All written notices required or permitted to be given under this Contract will be deemed made when received by the other Party at its respective address as follows:

To City: C ity of Camarillo
601 Carmen Drive
Camarillo, California 93010
Attention: James Campero
(Tel.) 805-388-5340
(Fax) 805-388-5387
E-Mail [email protected]

To Contractor:

Attention:
(Tel.)
(Fax)
E-Mail

13.2 Notice will be deemed effective on the date personally delivered or transmitted by facsimile or email. If the notice is mailed, notice will be deemed given three days after deposit of the same in the custody of the United States Postal Service, postage prepaid, for first class delivery, or upon delivery if using a major courier service with tracking capabilities.
(12-2023) Project No. CH-5067-2

CONTRACT

Page 8 ends

13.3 Any Party may change its notice information by giving notice to the other Party in compliance with this section.

Section 14. Cit y Rights of Termination and to Complete the Work.

14.1 The occurrence of any of the following is a default by Contractor under this Contract:

14.1.1 Contractor refuses or fails to prosecute the Work or any part thereof with such diligence as will insure its completion within the time specified or any permitted extension.

14.1.2 Contractor fails to complete the Work on time.

14.1.3 Contractor is adjudged bankrupt, or makes a general assignment for the benefit of creditors, or a receiver is appointed on account of Contractor’s insolvency.

14.1.4 Contractor fails to supply enough properly skilled workers or proper materials to complete the Work in the time specified.

14.1.5 Contractor fails to make prompt payment to any subcontractor or for material or labor.

14.1.6 Contractor fails to abide by any applicable laws, ordinances or instructions of City in performing the Work.

14.1.7 Contractor breaches or fails to perform any obligation or duty under the Contract.

14.2 Upon the occurrence of a default by Contractor, City will serve a written notice of default on Contractor specifying the nature of the default and the steps needed to correct the default. Unless Contractor cures the default within 10 days after the service of such notice, or satisfactory arrangements acceptable to City for the correction or elimination of such default are made, as determined by City, City may thereafter terminate this Contract by serving written notice on Contractor. In such case, Contractor will not be entitled to receive any further payment, except for Work actually completed prior to such termination in accordance with the provisions of the Contract Documents.

14.3 If the Engineer determines that the default should be cured in less than 10 days, then the written notice of default served on the Contractor will specify the shorter deadline for the Contractor to cure the default.

14.4 In event of a termination of this Contract, the City will also immediately serve written notice of the termination upon Contractor’s surety. The surety will have the right to take over and perform pursuant to this Contract; provided, however, that if the surety does not give City written notice of its intention to take over and perform this Contract within five days after service of the notice of termination or does not commence performance within 10 days from the date of such notice, (12-2023) Project No. CH-5067-2

CONTRACT

Page 9 ends

City may take over the Work and prosecute the same to completion by contract or by any other method it may deem advisable for the account and at the expense of Contractor. Contractor and the surety will be liable to City for any and all excess costs or other damages incurred by City in completing the Work.

14.5 If City takes over the Work as provided in this Section, City may, without liability for so doing, take possession of, and utilize in completing the Work, such materials, appliances, plant, and other property belonging to Contractor as may be on the site of the Work and necessary for the completion of the Work.

14.6 If City takes over the Work, City may also take possession of outstanding materials on order for the completion of the project, upon payment to the vendor.

All excess costs incurred by City in obtaining such materials, will be the responsibility of the Contractor.

14.7 If the Contractor does not cure a default within the time period required, then in lieu of terminating of the Contract, the City, in its sole discretion, may take action to cure the default and all costs incurred by City to cure the default will be deducted from any amount otherwise due to the Contractor.

Section 15. Pr
oject Documents . All data, drawings, maps, models, notes, photographs, reports, studies and other documents (collectively, “Project Documents”) prepared, developed or discovered by Contractor in the course of performing any of the Work under this Contract will become the sole property of City. Upon the expiration or termination of this Contract, Contractor must turn over all original Project Documents to City in its possession, but may retain copies of any of the Project Documents it may desire.

Section 16. Genera
l Provisions.

16.1 Authority to Execute. Each Party represents and warrants that all necessary action has been taken by such Party to authorize the undersigned to execute this Contract and to bind it to the performance of its obligations.

16.2 Assignment. Contractor may not assign this Contract without the prior written consent of City, which consent may be withheld in City’s sole discretion since the experience and qualifications of Contractor were material considerations for this Contract.

16.3 Binding Effect. This Contract is binding upon the heirs, executors, administrators, successors and permitted assigns of the Parties.

16.4 Integrated Contract. This Contract, including the Contract Documents, is the entire, complete, final and exclusive expression of the Parties with respect to the Work to be performed under this Contract and supersedes all other agreements or understandings, whether oral or written, between Contractor and City prior to the execution of this Contract.

16.5 Modification of Contract. No amendment to or modification of this Contract will be valid unless made in writing and approved by Contractor and by the City (12-2023) Project No. CH-5067-2

CONTRACT

Page 10 ends

Council or City Manager, as applicable. The Parties agree that this requirement for written modifications cannot be waived and that any attempted waiver will be void.

16.6 Electronic Signatures; Counterparts. This Contract and any amendment will be considered executed when the signature page of a party is delivered by electronic transmission. Such electronic signatures will have the same effect as an original signature. The Contract may be executed in multiple counterparts.

16.7 Waiver. Waiver by any Party of any term, condition, or covenant of this Contract will not constitute a waiver of any other term, condition, or covenant. Waiver by any Party of any breach of the provisions of this Contract will not constitute a waiver of any other provision, or a waiver of any subsequent breach or violation of any provision of this Contract. Acceptance by City of any Work performed by Contractor will not constitute a waiver of any of the provisions of this Contract.

16.8 Interpretation. This Contract will be interpreted, construed and governed according to the laws of the State of California. Each party has had the opportunity to review this Contract with legal counsel. The Contract will be construed simply, as a whole, and in accordance with its fair meaning. It will not be interpreted strictly for or against either party.

16.9 Severability. If any term, condition or covenant of this Contract is declared or determined by any court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions of this Contract will not be affected and the Contract will be read and construed without the invalid, void or unenforceable provision.

16.10 Venue. In the event of litigation between the parties, venue in state trial courts will be in the County of Ventura. In the event of litigation in a U.S. District Court, venue will be in the Central District of California, in Los Angeles. [Signatures on the following page.]

(12-2023) Project No. CH-5067-2

CONTRACT

Page 11 ends

The Parties have caused this Contract to be executed by their undersigned authorized agents as follows:

CITY OF CAMARILLO

Greg Ramirez, City Manager
ATTEST:

Kristy Buxkemper, City Clerk

CONTRACTOR
(If not an individual, two signatures are required)

Name and Title

Name and Title

Camarillo Business Tax Certificate Number Expiration Date

(12-2023) Project No. CH-5067-2

CONTRACT
A-1

EXHIBIT A

COMPENSATION
The total compensation under this Contract will not exceed:

ALTERNATE 1
If a Lump Sum Bid: “The sum of $ .”
ALTERNATE 2
If a Unit Price Bid: “The total unit prices set forth in the bid and the actual measured quantities utilized for the Project as determined by the Director.” ALTERNATE 3
If both Lump Sum and Unit Price Bid: “The sum of $ , and the amount due based upon the unit prices set forth in the bid and the actual measured quantities utilized for the Project as determined by the Director.”

(12-2023) Project No. CH-5067-2

CONTRACT
B-1

EXHIBIT B

INSURANCE

1. General Requirements. Contractor must procure and maintain in full force and effect during the term of this Contract the following types of insurance with coverage limits complying, at a minimum, with the limits set forth below:

Type of Insurance Lim its (combined single)
Commercial General Liability $2 ,000,000 / $4,000,000 Aggregate Business Automobile Liability $1,000,000
Workers’ Compensation Statutory Requirements

2. Commercial General Liability Insurance. This policy must meet or exceed the requirements of Insurance Services Office (ISO) CGL Form No. CG 00 01. The amount of insurance set forth above will be a combined single limit per occurrence for bodily injury, personal injury, and property damage for the policy coverage . The insurance must be on an “occurrence” not a “claims -made” basis. Defense costs must be paid in addition to limits. There must be no cross -liability exclusion for claims or suits by one insured against another.

Liability policies must be endorsed to name City,
its officials, employees and agents
as “additional insureds” under the insurance coverage.

The policy must state that such insurance will be deemed “primary” such that any other ins
urance that may be carried by City will be deemed “excess” to that of Contractor.

This endorsement must be reflected on ISO Form No. CG 20 01, or equivalent form as determined by City.

Coverage must be applicable to City for injury to employees of Contractor, subcontractors, agents or others performing any part of the Work required under this Contract. Each policy must be endorsed to provide a separate limit applicable to this Project.

The Commercial General Liability policy must not contain any endorsements limiting coverage beyond the basic policy coverage for any of the following:

1. Explosion, collapse or underground hazard (XCU);

2. Products and completed operation;

3. Pollution liability; or

4. Contractual liability.

3. Business Auto Coverage. This policy must be on ISO Business Auto Coverage Form CA 00 01 including symbol 1 (Any Auto) and Endorsement CA 0025, or equivalent forms approved in writing by City. If Contractor neither leases nor owns vehicles, this requirement may be satisfied by a non- owned auto endorsement to the general liability policy described above. If Contractor or Contractor’s employees will use personal autos (12-2023) Project No. CH-5067-2

CONTRACT
B-2
in any way on this Project, Contractor must provide evidence of personal auto liability coverage for each such person.

4. Workers Compensation. Contractor must have a State of California approved policy form providing the statutory benefits required by law with employer’s liability, or Contractor must provide evidence of an approved self-insurance program.

5. Other Insurance; Revisions to Insurance. Contractor may be required to obtain such other insurance coverage as may be required by applicable law or by City. City reserves the right at any time during the term of the Contract to change the amounts and types of insurance required by giving Contractor 60 days advance written notice of such change.

If such change results in substantial additional cost to Contractor, City and Contractor may renegotiate Contractor’s compensation.

6. Acceptable Insurers. All required insurance policies must be issued by an insurance company currently authorized by the California Insurance Commissioner to transact the business of insurance in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by the City’s Risk Manager.

7. Excess or Umbrella Liability Insurance (Over Primary). If an excess or umbrella liability policy is used to meet limit requirements, the insurance must provide coverage at least as broad as specified for the underlying coverages. Any such coverage provided under an excess or umbrella liability policy must include a “drop- down provision” providing primary coverage above a maximum $25,000 self -insured retention for liability not covered by primary but covered by the umbrella. Coverage must be provided on a “pay-on-behalf” basis, with defense costs payable in addition to policy limits. There may be no cross -liability exclusion precluding coverage for claims or suits by one insured against another. Coverage must be applicable to City for injury to employees of Contractor, its subcontractors or others performing work to satisfy Contractor’s obligations under this Contract. The scope of coverage provided is subject to approval of City following receipt of proof of insurance as required herein.

8. Certificates of Insurance and Endorsements. Prior to commencing any Work under this Contract, Contractor must file with the City Certificates of Insurance and Endorsements evidencing the existence of all insurance required by this Contract, along with such other evidence of insurance or copies of policies as may reasonably be required by City. Such Certificates of Insurance and Endorsements must be in a form approved by City’s Attorney. Contractor must maintain current certificates and endorsements on file with City during the term of this Contract reflecting the existence of all required insurance. Each of the certificates must expressly provide that no material change in the policy, or termination thereof, will be effective except upon 30 days’ prior written notice to City.

9. Failure to Maintain Required Insurance. If Contractor, for any reason, fails to have in place at all times during the term of this Contract all of the required insurance coverage, City may, in addition to any other available remedies, (a) obtain such coverage at Contractor’s expense and deduct the cost from the sums due Contractor , (b) make a claim against the Contractor’s surety, or (c) terminate the Contract. (12-2023) Project No. CH-5067-2

CONTRACT
B-3

10. Effect of Coverage. The existence of the required insurance coverage under this Contract will not be deemed to satisfy or limit Contractor’s indemnity obligations under this Contract.

11. Higher Limits of Insurance. If Contractor m aintains higher limits of insurance than the required amounts shown in Section 1 above, then such amounts will be the minimum required under this Contract.

.
(12-2023) Project No. CH-5067-2

CONTRACT

VERIFICATION OF CALIFORNIA

CONTRACTOR’S LICENSE

I certify, under penalty of perjury, that I have a valid California Contractor’s license issued pursuant to Business and Professions Code section 7000 and following, and was so licensed at the time that the bid was awarded:

California Contractor’s License:

License Number Class Expiration Date

CONTRACTOR (PRINT OR TYPE)

Date Signature

(Public Contract Code § 6100)
(12-2023) Project No. CH-5067-2

CONTRACT

CERTIFICATE REGARDING

WORKERS’ COMPENSATION

I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self - insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

Name (print or type)

Date Signature
(12-2023) Project No. CH-5067-2

BOND

Page 1 of 6 ends

BOND NO.

PERFORMANCE BOND
On _____________________________, the City Council of the City of Camarillo, California, a municipal corporation (“CITY”), awarded a contract (“Contract”) to ____________________________________________________________________________ (“CONTRACTOR” or “PRINCIPAL”), for the work (“Work”) identified as ____________________________________________________________________________ The Contract and related documents (“Contract Documents”) are incorporated and made a part of this performance bond.

Under the Contract, CONTRACTOR is required to furnish this bond providing for the faithful performance of the Work
NOW, THEREFORE, we, CONTRACTOR, as PRINCIPAL, and
____________________________________________________________________________, a corporation organized and existing under the laws of the State of ________________________ and duly authorized to transact business under the laws of the State of California, as SURETY, are held and firmly bound unto CITY, in the sum of _______________________________________________________________________dollars ($_________________________), lawful money of the United States of America, this sum being not less than one hundred percent (100%) of the estimated amount payable by CITY under the terms of the Contract , PRINCIPAL and SURETY, bind ourselves and our heirs, executors, administrators, successors and assigns, jointly and severally, by this instrument.

BOND CONDITIONS

1. PRINCIPAL will perform the Work the identified in the Contract. CITY has estimated the required amount of the bond as shown above.

2. PRINCIPAL’s performance of the Work will be done in accordance with the Contract Documents. Should PRINCIPAL fail to satisfactorily complete all required Work within the time allowed, CITY may, at its sole discretion, either (1) cause all required Work to be done and the parties executing this bond will be firmly bound for the payment of all necessary costs for the performance of this Work or (2) make demand upon the SURETY to complete the required Work in which event the SURETY will commence completion of the Work within 30 days of the CITY’S demand unless otherwise agreed in a writing signed by the parties.

3. PRINCIPAL will guarantee the Work against any defective work, labor or materials for a period of one year following the completion and acceptance of the Work by CITY. (12-2023) Project No. CH-5067-2

BOND

Page 2 of 6 ends

4. This bond is conditioned upon and guarantees due compliance with all applicable law including, without limitation, the Camarillo Municipal Code.

5. SURETY agrees that no changes, extensions of time, alteration or modification of the Contract or of the obligations to be performed thereunder will in any way affect its obligation on this bond, and waives notice of any such change, extension of time, alteration or modification of the Contract or of the obligations to be performed.

Furthermore, SURETY expressly waives the provisions of California Civil Code sections 2845 and 2849.

6. This bond consists of this instrument, the Contract and Contract Documents referenced above, and the following two attached exhibits, all of which are incorporated herein by reference:

A. A certified copy of the appointment, power of attorney, bylaws or other instrument entitling or authorizing the persons executing this bond to do so; and B. A certificate issued by the county clerk for the county in which SURETY’s representative is located conforming with California Code of Civil Procedure § 995.640 and stating that SURETY’s certificate of authority has not been surrendered, revoked, cancelled, annulled, or suspended, or in the event that it has, that renewed authority has been granted.

7. In case suit is brought upon this bond, the court will award and SURETY must pay, in addition to the face amount of this bond, all costs and reasonable attorney’s fees incurred by CITY in successfully enforcing any obligation under this bond.

IN WITNESS THEREOF, we have hereunto set our hands and seals this _______ day of ____________________, 20____.

PRINCIPAL
By
Title
Address

Telephone Number

Signature
(12-2023) Project No. CH-5067-2

BOND

Page 3 of 6 ends

SURETY
By
Title
Address

Telephone Number

Signature

* ALL SIGNATURES ON THIS PERFORMANCE BOND MUST BE NOTARIZED USING APPROPRIATE 8½” x 11” NOTARY ACKNOWLEDGEMENT FORM.

** Appropriate modifications will be made to this form if the bond is being furnished for the performance of an act not provided for by agreement.

*** Corporations must affix corporate seal.

(12-2023) Project No. CH-5067-2

BOND

Page 4 of 6 ends

BOND NO.

PAYMENT BOND
On __________________________, the City Council of the City of Camarillo, California, a municipal corporation (“CITY”), awarded a contract (“Contract”) to ____________________________________________________________________________ (“CONTRACTOR” or “PRINCIPAL”), for the work (“Work”) identified as ____________________________________________________________________________.

PRINCIPAL is required to furnish a bond under the Contract to secure the payment of claims of laborers, mechanics, material persons, and other persons as provided by law.

PRINCIPAL and __________________________________________________ ___________________________________, a corporation incorporated under the laws of the State of _______________________________ and licensed by the State of California to execute bonds and undertakings as sole surety (“SURETY”), are held and firmly bound unto CITY in the sum of ___________________________________________________ ______________________________________ dollars ($_________________________), lawful money of the United States, which may be increased or decreased by a rider hereto executed in the same manner as this bond, for the payment of which sum PRINCIPAL and SURETY bind themselves, their successors, and assigns, jointly and severally, by this instrument.

BOND CONDITIONS

1. PRINCIPAL will construct the Work identified in the Contract. Such performance will be in accordance with the Contract Documents identified in the Contract, which are hereby incorporated and made a part of this bond. CITY has estimated the required amount of the bond as shown above.

2. If PRINCIPAL, its heirs, executors, administrators, successors, assigns or subcontractors fail to pay any of the persons named in California Civil Code section 3181, or any amounts due under the California Unemployment Insurance Code with respect to work or labor performed under the Contract, or any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of the Contractor and its subcontractors under Unemployment Insurance Code section 13020, with respect to work or labor performed under the Contract, SURETY will pay for the same in an amount not exceeding the penal sum specified in this bond.

3. This bond inures to the benefit of any of the persons named in Civil Code section 3181 so as to give a right of action to such persons or their assigns in any suit brought upon this bond. In case suit is successfully brought upon this bond, SURETY further agrees to pay all reasonable attorneys’ fees and costs in an amount fixed by the court. (12-2023) Project No. CH-5067-2

BOND

Page 5 of 6 ends

4. This bond is conditioned upon and guarantees due compliance with all applicable law including, without limitation, the Camarillo Municipal Code.

5. SURETY agrees that no changes, extensions of time, alteration or modification of the Contract or of the obligations to be performed thereunder will in any way affect its obligation on this bond, and waives notice of any such change, extension of time, alteration or modification of the Contract or of the obligations to be performed.

Furthermore, SURETY expressly waives the provisions of California Civil Code sections 2845 and 2849.

6. This bond consists of this instrument, the Contract and Contract Documents referenced above, and the following two attached exhibits, all of which are incorporated herein by reference:

A. A certified copy of the appointment, power of attorney, bylaws or other instrument entitling or authorizing the persons executing this bond to do so; and B. A certificate issued by the county clerk for the county in which SURETY’s representative is located conforming with California Code of Civil Procedure § 995.640 and stating that SURETY’s certificate of authority has not been surrendered, revoked, cancelled, annulled, or suspended, or in the event that it has, that renewed authority has been granted.

IN WITNESS THEREOF, we have hereunto set our hands and seals this _______ day of ____________________, 20____.

PRINCIPAL
By
Title
Address

Telephone Number

Signature
(12-2023) Project No. CH-5067-2

BOND

Page 6 of 6 ends

SURETY
By
Title
Address

Telephone Number

Signature

* ALL SIGNATURES ON THIS PAYMENT BOND MUST BE NOTARIZED USING APPROPRIATE 8½” x 11” NOTARY ACKNOWLEDGEMENT FORM.

** Appropriate modifications will be made to this form if the bond is being furnished for the performance of an act not provided for by agreement.

*** Corporations must affix corporate seal.

(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 1 -

CAM #4816-7464-0911 v5

CITY OF CAMARILLO

GENERAL CONDITIONS/SPECIFICATIONS

WORK IDENTIFICATION: STANDBY POWER AT CITY HALL AND CORPORATION YARD PROJECT NO. CH-5067-2

SECTION
NO.

PAGE
NO.

1. Definitions ................................ ................................ ....................... 4

1.1 General Construction ................................ .......................... 4

1.2 Terms Defined ................................ ................................ .... 4

1.3 General Conditions/Specifications ................................ ....... 5

1.4 Abbreviations ................................ ................................ ...... 5

2. Work and Material Requirements ................................ ................... 6

2.1 Use of Premises ................................ ................................ .. 6

2.2 Materials Furnished By City ................................ ................ 6

2.3 Or Equal ................................ ................................ .............. 6

2.4 Samples ................................ ................................ .............. 6

2.5 Warranty ................................ ................................ ............. 6

2.6 Liens ................................ ................................ ................... 7

2.7 Manufacturer’s Recommendations ................................ ...... 8

2.8 Certificates of Compliance ................................ .................. 8

3. Grading Ordinance ................................ ................................ ......... 8

4. Progress Payments to Contractor ................................ ................... 8

4.1 Progress Payments to Subcontractors ................................ 8

4.2 Substitution of Securities ................................ ..................... 8

5. Time for Completion ................................ ................................ ....... 9

5.1 Payment for Delays to Contractor ................................ ....... 9

5.2 Rights of City to Increase Working Days ............................. 9

6. Construction Schedule and Commencement of Work ..................... 9

6.1 Proposed Construction Schedule ................................ ........ 9

6.2 Beginning of Work ................................ ............................... 11

6.3 Temporary Suspension of Work ................................ .......... 12

6.4 Starting of Contract Time ................................ .................... 12

6.5 Liquidated Damages ................................ ........................... 12

(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 2 -
CAM #4816-7464-0911 v5

7. Subcontracting ................................ ................................ ................ 12

7.1 Subcontractors Bound By Contract ................................ ..... 12

7.2 City Consent to Subcontractors ................................ ........... 13

8. Work By Others ................................ ................................ .............. 13

8.1 City’s Right to Award Other Contracts ................................ . 13

8.2 Contractor’s Responsibilities ................................ ............... 13

9. Authority of the City Engineer ................................ ......................... 13

9.1 General Authority ................................ ................................ .. 13

9.2 Interpretation of Drawings and Specifications ....................... 14

9.3 Inspection ................................ ................................ ........... 14

9.4 Disputes Pertaining to Payment for Work ............................ 14

10. General Provisions ................................ ................................ ......... 14

10.1 Utilities ................................ ................................ ................ 14

10.2 Water Supply ................................ ................................ ...... 15

10.3 Dust Control ................................ ................................ ........ 15

10.4 Removal and Disposal of Structures and
Obstructions ................................ ................................ ........

15 10.5 Surveys ................................ ................................ ............... 15

10.6 Layout and Field Engineering ................................ .............. 15

10.7 Traffic Requirements ................................ ........................... 16

10.8 Tests and Inspections ................................ ......................... 17

10.9 Soils Investigation Report ................................ .................... 17

10.10 Compaction Tests ................................ ............................... 17

10.11 Cutting and Patching ................................ ........................... 18

10.12 Earthquake and Tidal Wave Damage ................................ .... 18

10.13 Highway and Railroad Permits ................................ .............. 18

10.14 Noise Control ................................ ................................ ....... 18

11. Acceptance of Work ................................ ................................ ....... 18

11.1 No Waiver of Legal Rights ................................ ................... 18

11.2 Non-Complying Work ................................ .......................... 19

11.3 Fulfillment of Contract ................................ ......................... 19

11.4 Correction of Work Before Acceptance ............................... 19

11.5 Deductions for Uncorrected Work ................................ ....... 19

11.6 Final Clean Up ................................ ................................ .... 19

11.7 Certificate as to Compliance With
Certain Regulations ................................ .............................

19 12. Claims between City and Contractor ................................ ............... 20

12.1 Definition of Claim ................................ ............................... 20

12.2 Notice of Potential Claim Procedure ................................ .... 20

12.3 Claim Processing Procedure ................................ ............... 21 (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 3 -
CAM #4816-7464-0911 v5

13. Assignment of Rights ................................ ................................ ...... 22

14. Prohibited Interests ................................ ................................ ......... 22

15. Labor Code Requirements ................................ .............................. 22

15.1 State Wage Determination ................................ .................. 22

15.2 Compliance Monitoring ................................ ....................... 23

15.3 Payroll Records ................................ ................................ ... 23

15.4 Apprentices ................................ ................................ ......... 24

15.5 Working Hours ................................ ................................ .... 25

15.6 Workers Compensation ................................ ....................... 25

15.7 Protection of Workers in Trench
Excavations ................................ ................................ ........

25 16. Sales and Use Tax Cooperation ................................ ..................... 26

17. Documentation of Status of Surety ................................ ................. 26

18. Construction and Demolition Waste ................................ ................ 26

19. Use of Premises ................................ ................................ ............. 27

(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 4 -
CAM #4816-7464-0911 v5

GENERAL CONDITIONS/SPECIFICATIONS

1. Definitions

1.1 General Construction
Terms used in these General Conditions/Specifications and in other Contract Documents will have the definition provided in this Section 1, unless the context requires a different meaning.

The word “person” includes a corporation, association, partnership and any other form of legal entity.

Unless otherwise specifically defined herein, or unless the context requires a different meaning, all words, terms and phrases having a well -known or technical meaning will be so construed.

In the event of conflict, the order of precedence of governing documents will be as set forth in Section 5.1 of the Instructions to Bidders.

1.2 Terms Defined
Acceptance: The formal written acceptance by City of a project that has been completed in all respects in accordance with the plans and specifications and any modifications.

Addendum: The modi f ication of the plans and/or specifications issued to all prospective bidders during the period when necessary to change, correct, clarify, or further define any phase of the work.

Bidder: Any person submitting a proposal for the work contemplated, acting directly or through a duly authorized representative.

City: The City o f Camarillo, County of Ventura, State of California City Clerk: The City Clerk of City.

City Council: The City Council of City.

City Engineer/Engineer of Work/Engineer: The City Engineer of City or his/her duly authorized deputies, agents, representatives or inspectors.

Contractor: The succ essful bidder who is awarded the Contract.

Days: Calendar days, unless business days or work days, are expressly specified.

Materials: Any material, equipment, appliance, process, item or article of any nature whatsoever installed or incorporated into the work or provided to City under the Contract.

Project: The pro j ect is the total improvement, of which the work performed under the Contract may be the whole or a part.
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 5 -
CAM #4816-7464-0911 v5
Punch List: Lis t of corrective items, determined by the Engineer, which must be completed by the Contractor.

Special Provisions: A ny provision in the Contract Documents that supplements, modifies and, when in conflict, supersedes these General Conditions/Specifications.

Standard Specifications/Green Book/SSPWC: Standar d Specifications for Public Works Construction, 2021 edition, written and promulgated by Public Works Standards, Inc. and all supplements thereto.

State Standard Plan: Standar d Plans prepared by the State of California, Business & Transportation Agency, Department of Transportation, latest edition.

Subcontractor: Any subcontractor under Contractor.

Work: That which is proposed to be constructed or done under the Contract, in strict accordance with the Contract Documents, including the furnishing of all necessary or convenient tools, equipment, material, labor and transportation.

Working Days: A wor king day is defined as any day, except Saturdays, Sundays, legal holidays and except days when Work is suspended by the Engineer, and any other day determined to be non-working in accordance with the Contract Documents.

1.3 General Conditions/Specifications
The provisions of these General Conditions/Specifications and any other Contract Document supersede the SSPWC to the extent that the provisions supplement, modify or conflict with the SSPWC in accordance with Section 5.1 of the Instructions to Bidders.

1.4 Abbreviations
AAN American Association of Nurserymen
AGC Associated General Contractors of America
AISC American Institute of Steel Construction
APWA American Public Works Association
ASME American Society of Mechanical Engineers
AWS American Welding Society
AWWA American Water Works Association
EIA Electronic Industries Association
IEEE Institute of Electric and Electronic Engineers
NEC National Electric Code
NEMA National Electrical Manufactures Association
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 6 -
CAM #4816-7464-0911 v5
SSS State of California Standard Specifications, Latest edition, Department of Public Works, Department of Transportation VCSS Ventura County Standard Specifications

2. Work and Material Requirements

2.1 Use of Premises
(a) Contractor must confine all tools and equipment, the storage of materials, and the operation of workers to areas designated by the Engineer. (b) With respect to any premises, tools or equipment of City made use of in the performance of the Contract, Contractor will be deemed to have inspected the same prior to use, have accepted them in good and safe condition and have agreed to maintain them in a safe condition for the protection of workmen while using them during the performance of the Work.

2.2 Materials Furnished By Cit y
Materials furnished by City will be available at locations designated in the Special Provisions, or if not designated in the Special Provisions, will be delivered to a single location of City’s choice within the project area. The materials will be hauled to the site of installation by Contractor at its expense, including any necessary loading and unloading that may be involved.

The cost of handling and placing materials furnished by City will be considered as included in the price paid for the item involving such furnished material.

2.3 Or Equal
In the event that an item is called for by a specific product or trade name, Contractor will have 35 days after the award of the Contract for submission of data substantiating a request for a substitution of “an equal” item. In the event Contractor furnishes any “or equal” material more expensive than that specified in the bid form, the difference in cost of such material so furnished will be borne by Contractor under Public Contract Code section 3400.

2.4 Samples
Contractor must furnish for approval, within 35 days following notice of award of Contract, all samples as required in specifications together with catalogs and supporting data required by the Engineer. This provision does not authorize any extension of time for performance of the Contract. The Engineer will review such samples only for conformance with design and concept of Work and for compliance with information given in the Contract Documents. Work must be in accordance with approved samples under Public Contract Code section 3400.

2.5 Warranty
(a) The labor and materials bond must remain in effect until expiration of six months after the period in which verified claims may be filed as provided in Civil Code section 9356, and the performance bond must be paid up and in effect for one year after the acceptance of the job by City in accordance with the guarantee required by Subsection 2.5(b), below. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 7 -
CAM #4816-7464-0911 v5
(b) Besides warranties and guaranties otherwise required by the Contract Documents, Contractor warrants and guarantees all Work for a period of one year after date of acceptance of the Work by City, unless a longer period is specified, and must repair or replace any or all such Work, together with any other Work, which may be displaced in so doing, that may prove defective in workmanship, materials or both within one year from date of acceptance without expense whatsoever to City, ordinary wear and tear, unusual abuse or neglect excepted. The Engineer will give notice of observed defects with reasonable promptness.

Contractor must notify the Engineer upon completion of repairs. (c) In the event Contractor fails to commence the corrective work within 10 days after being notified in writing to do so by the Engineer and prosecute the corrective work to timely completion, City may proceed to have defects corrected and made good at the expense of Contractor who must pay the costs and charges of such corrective work immediately on demand.
(d) If, in the opinion of the Engineer, defective work creates a condition that requires immediate corrective work, the Engineer will attempt to give the notice required by this Section.

If Contractor cannot be contacted or does not comply with City’s request for correction within a reasonable time as determined by the Engineer, City may, notwithstanding the provisions of this Section, proceed to make such corrective work, and Contractor will be liable for costs of such corrective work. Such action by City will not relieve Contractor of the warranties and guaranties provided in this Section or elsewhere in the Contract.
(e) This Section does not in any way limit the warranty or guaranty on any material for which a longer warranty or guaranty is specified in the Contract Documents or on any items for which a manufacturer gives a warranty or guaranty for a longer period. Contractor must furnish the Engineer with all appropriate warranty and guaranty certificates upon completion of the Work.
(f) For federally funded transportation projects, City does not require a warranty and the applicable bonds may be exonerated administratively.

2.6 Liens
No materials, supplies, tools or equipment for Work under this Contract may be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest herein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all materials installed or incorporated in the Work by Contractor or any subcontractor and agrees upon completion of all Work to deliver premises, together with all improvements and appurtenances constructed or placed thereon by Contractor, to City free from any claim, liens, or charges. Contractor further agrees that neither Contractor nor any person furnishing any materials, supplies, tools, equipment or labor for any Work covered by this Contract will have any right to lien upon the premises or any improvement or appurtenance thereon, except that Contractor may install metering devices or other equipment of utility companies or of political subdivisions title to which is commonly retained by utility companies or political subdivisions. In event of the installation of any such metering device or equipment, Contractor will so advise City. Nothing contained in this article, however, will defeat or impair the rights of persons furnishing material or labor under any bond given by Contractor for their protection or any rights under any law permitting such persons to look to funds due Contractor in the hands of City, and this provision will be inserted in all subcontracts and material contracts and notice of its provisions will be given to all persons furnishing material for Work when no formal contract is entered into for such material.
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 8 -
CAM #4816-7464-0911 v5

2.7 Manufacturer’s Recommendations
Where the manufacturer of any material or equipment provides written recommendations or instructions for its use or method of installation (including labels, tags, manuals or trade literature), such recommendations or instructions must be complied with, except where the Contract Documents specifically require deviations.

2.8 Certificates of Compliance
The City Engineer may require certificates of compliance with the specifications for materials or manufactured items produced outside of the job site. Such certificates will not relieve Contractor from the requirements of providing materials and manufactured items complying with the specifications even though they have been incorporated into the job.

3. Grading Ordinance
(a) All excavation, filling and grading operations in Camarillo are governed by City’s Grading Ordinance. No grading permit is required of Contractor for Work performed within the limits of the project right-of-way shown on the plans.
(b) Materials, exported or wasted outside of the project right -of-way shown on the plans, are subject to all requirements of the Grading Ordinance. The requirements may include, but are not limited to, submitting a grading plan prepared by a civil engineer, obtaining a grading permit, paying the permit fee, posting a grading bond, hiring professionals for engineering and testing services, compacting fills, constructing drainage facilities, and providing erosion protection. These requirements are the responsibility of the owner of the land on which the material is placed. To ensure that neither City nor Contractor are a party to aiding or abetting any property owner to violate the Grading Ordinance, no material may be exported or wasted outside the limits of the project right- of-way until Contractor has furnished the Engineer a copy of the grading permit or certificate of exemption covering such operation on land where the material is to be deposited.

4. Progress Payments to Contractor

4.1 Progress Payments to Subcontractors
Contractor must pay to any subcontractor, no later than seven days after receipt of each City progress payment, unless otherwise agreed to in writing, the respective amounts allowed Contractor on account of the work performed by the subcontractors, to the extent of each subcontractor’s interest in the progress payment. In the event that there is a good faith dispute over all or any portion of the amount due on a progress payment from the Contractor to a subcontractor, the Contractor may withhold no more than 150% of the amount disputed.

In all contracts between Contractor and its subcontractors , the percentage of the retention of proceeds withheld may not exceed the percentage specified in the Contract Documents between the City and the Contractor.

4.2 Substitution of Securities
Pursuant to Public Contract Code section 22300 and upon Contractor’s request, City will make payment of funds retained from progress payments for performance security, if Contractor deposits in escrow with City’s Finance Director or with a state or federal chartered (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 9 -
CAM #4816-7464-0911 v5
bank acceptable to City as escrow agent, securities eligible for the investment of City funds under Government Code section 16430 or bank or savings and loan certificates of deposit.

Securities may be substituted upon the following terms and conditions:
(a) Contractor will bear all expenses in connection with the escrow deposit made. (b) Securities or certificates of deposit must be of a value equal to 100% of the amounts of retention to be paid to Contractor.
(c) Contractor must enter into an escrow agreement that is substantially the same as set forth in Public Contract Code section 22300.
(d) Contractor must obtain the written consent of the surety to the escrow agreement.

5. Time for Completion

5.1 Payment for Delays to Contractor
Contractor will be compensated when any extension of time is granted for delays caused solely by action or inaction of City, which the Engineer determines materially increases or decreases the costs of any portion of the Work. If the Engineer determines that compensation is not justified, Contractor will be so advised in writing. Contractor may then submit a notice of potential claim to the Engineer, as provided in the Standard Specifications relative to disputed Work.

5.2 Rights of Cit
y to Increase Working Days
If such Work is not completed within the time for completion, the City Council has the right to increase the number of working days in the amount it may determine will best serve the interests of City, and, if it desires to increase the number of working days, it has the further right to charge Contractor and deduct from the final payment for the Work, the actual cost of engineering, inspection, superintendence, and other overhead expenses that are directly chargeable to Contractor, and that accrue during the period of such extension, except that the cost of the final service and preparation of the final estimates may not be included in such charges.

6. Construction Schedule and Commencement of Work

6.1 Proposed Construction Schedule
(a) After notification of award and prior to the start of any Work, Contractor must submit to the City Engineer for approval the proposed construction schedule. The construction schedule must be in the form of a Critical Path Method (CPM) in sufficient logic and detail to show the chronological relationship of all activities of the project, including, but not limited to, estimated starting and completion dates of various activities, procurement of materials and scheduling of equipment, work of subcontractors, interface with work by others, and other tasks required to complete the project. The level of detail must be consistent with the complexity of the project as determined by the City Engineer. The construction schedule must reflect completion of all Work included in the Contract within the Completion Time in accordance with these specifications. A construction schedule showing the project complete in less than the Completion Time will not be accepted. The construction schedule must be cost loaded on a monthly basis. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 10 -
CAM #4816-7464-0911 v5
(b) If Contractor desires to make a major change in its method of operation after commencing construction, or if its schedules fail to reflect the actual progress, it must submit to City a revised construction schedule in advance of beginning any revised operations. (c) The baseline construction schedule must utilize the Completion Time included in the Contract and must not extend beyond the number of working days. The baseline schedule must have a date of the first working day of the Contract and not include any completed work to date. The baseline construction schedule must not attribute negative float or negative lag to any activity. If the Contractor intends to complete the Work prior to the time of completion, the intended date of completion must be set forth in the construction schedule and the Contractor must execute a zero -cost Contract Change Order that reduces the number of working days allowed for completion to conform to the intended completion date. (d) Float, slack time, or contingency within the schedule and the total float within the overall construction schedule, is not for the exclusive use of the Contractor or the City, but is jointly owned and is a resource to meet Contract milestones and the Contract Completion Time.

The Contractor must not sequester shared float through such strategies as extending activity duration estimates, using preferential logic, or using extensive crew/resource sequencing. Since float time within the construction schedule is jointly owned, no time extensions will be granted nor delay damages paid unless a delay occurs that extends the Work beyond the Contract Completion Time. Since float time within the construction schedule is jointly owned, it is acknowledged that City caused delays can be offset by City caused time savings. Therefore, the Contractor will not be entitled to receive a time extension or delay damages until all City caused time savings are exceeded and the Contract Completion Time is also exceeded. (e) If the Contractor has fallen behind the accepted Construction Schedule by more than 15 percentage points based on earned progress payments, the Contractor must take steps, including, but not limited to, increasing the number of personnel, shifts, and/or overtime operations, days of work, and/or amount of construction equipment until such time as the Work is back on schedule. Contractor must also submit for review no later than the next request for partial payment, such supplementary schedule or schedules as may be deemed necessary to demonstrate the manner in which the rate of progress will be regained. All cost required to bring the Project back on schedule will be borne by the Contractor without additional cost to the City.

(f) If the Contractor falls behind the accepted construction schedule, as modified by such time extensions as may have been granted by the City for unavoidable delays, by more than 35 percentage points based on earned progress payments, the Contractor will be deemed in material breach of Contract and the Work turned over to the surety for completion within the scheduled time.

(g) Contractor must include in the schedule, detailed information for each operation.

When the project schedule includes multiple streets or sites, Contractor must include detailed information for each street or site. When notifications or parking restrictions are required such dates must be included in the schedule.

(h) Contractor must provide critical path schedules in legible hardcopy format and must also submit schedules with each update in an editable electronic format compatible with MS Project or Primavera as directed by Engineer.

(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 11 -
CAM #4816-7464-0911 v5

6.2 Beginning of Work
(a) The delivery to City, for execution and approval of the Contract Documents properly executed on behalf of Contractor and surety, constitutes Contractor’s authority to enter upon the site of the Work and to begin operations, subject to its assumption of the risk of the disapproval of the Contract, as herein provided, and subject also to the following:
(1) Contractor’s receipt from City for the properly executed Contract Documents, including bonds and certificates of insurance. (2) City may, for any reason, order Contractor not to enter upon the site of the Work, which order will nullify the authority of Contractor to enter upon the site prior to receipt of the Notice to Proceed.
(3) Notice in writing of Contractor’s intention to start Work prior to approval, specifying the date on which Contractor intends to start, must be given to the Engineer at least 48 hours in advance.
(4) Contractor must, on commencing operations, take all precautions required for public safety and observe all the provisions in these General Conditions/Specifications and any Special Provisions.
(5) In the event of disapproval of the Contract, Contractor must, at its expense, do such Work as is necessary to leave the site in a neat condition to the satisfaction of the Engineer. If the Work done affects any existing road or highway, Contractor must, at its expense, restore it to its former condition or the equivalent thereof to the satisfaction of the Engineer.
(6) All Work done according to the Contract prior to its approval will, when the Contract is approved, be considered authorized Work and will be paid for as provided in the Contract.
(b) Entry upon the site without authority will be treated as trespassing. (c) Should Contractor begin the Work in advance of receiving notice that the Contract has been approved as provided above, any Work performed by Contractor in advance of the date of approval will be considered as having been done by Contractor at Contractor’s own risk and as a volunteer unless the Contract is so approved. (d) Contractor may start the Work at any time after the Notice to Proceed is issued, but Work must begin within the number of days indicated on the Bid Proposal after the starting date for the Contract, or at such other times as may be indicated in the Special Provisions. The actual date on which Contractor starts the Work will not affect the required item for completion as provided for in the Contract.
(e) If required by the Special Provisions, Contractor must start construction operations on that part of the project designated by the Engineer. (f) Contractor must perform all the Work in such a manner and with sufficient materials, equipment, and labor to ensure its completion in accordance with the plans and specifications within the time set forth in the Contract. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 12 -
CAM #4816-7464-0911 v5

6.3 Tempor ary Suspension of Work
(a) Should suspension of the Work be ordered by reason of the failure of Contractor to carry out orders or to perform any provisions of the Contract; or by reason of weather conditions being unsuitable for performing any item or items of the Work; Contractor, at its expense, must take all steps necessary to provide and maintain a safe, smooth, and unobstructed passageway through construction for use by public traffic during the period of such suspension. In the event that Contractor fails to take such steps, City may perform such tasks and the cost thereof will be deducted from monies due Contractor. (b) If the Engineer orders a suspension of all of the Work or a portion of the Work which is the current controlling operation or operations, due to unsuitable weather or to such other conditions as are considered unfavorable to the suitable prosecution of the Work, the days on which the suspension is in effect will not be considered working days for the purpose of calculating Contractor’s time of performance.
(c) If a portion of the Work at the time of such suspension is not a current controlling operation or operations, but subsequently does become the current controlling operation or operations, the determination of working days will be made on the basis of the then current controlling operation or operations.
(d) If suspension of the Work is ordered by the Engineer, due to the failure on the part of Contractor to carry out orders given or to perform any provision of the Contract, no time extension for such suspension will be granted.

6.4 Starting of Contract Time
As soon as practicable after the Contract has been executed by both parties, a Notice to Proceed will be issued by City stating the starting date of the Contract time, which will be as stated in the Notice to Proceed, unless otherwise provided in the Special Provisions.

6.5 Liquidated Damages
The parties agree that time is of the essence in the completion of the Work, and that in case all the Work called for under the Contract is not completed before or upon the expiration of the time limit as set forth in the Contract Documents, as modified by extensions of time granted by City, damage will be sustained by City. As it is impracticable to determine the actual delay damage, the parties agree that Contractor must pay liquidated damages to City in the amount set forth on page 1 of the Bid Proposal, per calendar day for each and every calendar day’s delay beyond the time prescribed to complete the Work. If Contractor fails to pay the liquidated damages, City may deduct the amount from any monies due or that may become due Contractor under the Contract.

7. Subcontracting

7.1 Subcontractors Bound By Contract
Contractor agrees to bind every subcontractor by the terms of the Contract as far as such terms are applicable to the subcontractor’s work. If Contractor subcontracts any part of this Contract, Contractor will be fully responsible to City for the acts and omissions of every subcontractor and of persons either directly or indirectly employed by every such subcontractor. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 13 -
CAM #4816-7464-0911 v5
Nothing contained in the Contract Documents, however, creates any contractual relation between any subcontractor and City.

7.2 City C onsent to Subcontractors
City’s consent to, or approval of, any subcontractor under the Contract does not in any way relieve Contractor of its obligations under the Contract nor will such subcontract or approval be deemed to waive any provision of the Contract between City and Contractor.

8. Work By Others

8.1 City’s Right to Award Other Contracts
(a) City reserves the right to award other contracts in connection with the project.

Nothing in these General Conditions/Specifications may be interpreted as granting to Contractor exclusive occupancy at the site of the project.
(b) If simultaneous execution of any contract is likely to cause interference with performance of some other contract or contracts, City will decide which contractor must cease Work temporarily and which contractor must continue or whether Work can be coordinated so that contractors may proceed simultaneously. Notwithstanding any other provision of these General Conditions/Specifications, City is not responsible for any damages suffered or extra costs incurred by Contractor resulting directly or indirectly from the award or performance or attempted performance of any other contract or contracts on the project, or caused by any decision or omission of City respecting the order of precedence in performance of contracts.

8.2 Contractor’s Responsibilities
Contractor must ascertain to its own satisfaction the scope of the project and nature of any other contracts that have been or may be awarded by City in prosecution of the project to the end that Contractor may perform the Contract in consideration of such other contracts, if any.

Contractor must afford other contractors and utilities reasonable opportunity for introduction and storage of their materials and execution of their tasks and must properly connect and coordinate its efforts with theirs. Contractor may not cause any unnecessary hindrance or delay to any other contractor working on the project.

If any part of Contractor’s Work depends for proper execution or results upon Work of any other contractor, Contractor must inspect and promptly report to the City Engineer any defects in such Work that render it unsuitable for such proper execution and results. Its failure so to do constitutes a waiver by Contractor of any claim of delay caused by events beyond Contractor’s control.

9. Authority of the Engineer

9.1 General Authority
The Engineer will decide any and all questions which may arise as to the quality or acceptability of materials furnished and Work performed, and as to the manner of performance and rate of progress of the Work, and must decide all questions that may arise as to the interpretation of the drawings and specifications, and all questions as to the acceptable (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 14 -
CAM #4816-7464-0911 v5
fulfillment of the Contract on the part of Contractor, and as to compensation. The Engineer’s decisions are final and the Engineer has authority to enforce and make effective such decisions and orders.

9.2 Interpretation of Drawings and Specifications
The Engineer will interpret the meaning of any part of the drawings and specifications about which any misunderstanding may arise and the Engineer’s decision will be final. Should there appear to be any error or discrepancy in or between the drawings and specifications, Contractor must refer the matter to the Engineer for adjustment before proceeding with the Work. Should Contractor proceed with the Work without so referring the matter, it does so at its own risk.

9.3 Inspection
(a) The Engineer must be provided full access to all operations involving the Work under the Contract and be provided reasonable advance notice of the time and place of operations which the Engineer desires to observe. The Engineer must be provided with all requested samples of materials and Work for testing purposes. (b) Contractor must furnish the Engineer reasonable facilities for obtaining such information as may be necessary to keep the Engineer fully informed respecting the progress and the manner of the Work. The Engineer’s inspection of the Work will not relieve Contractor from any obligation under the Contract. The Engineer has authority to stop any Work whenever provisions of Contract Documents are not being complied with and Contractor must instruct its employees and any subcontractors accordingly.

9.4 Disputes Pertaining to Payment for Work
Should any dispute arise respecting the true value of any of the Work done, of any of the Work omitted, or any extra Work which Contractor may be required to do, or respecting the size of any payment to Contractor during the performance of the Contract, such dispute will be decided by the Engineer.

10. General Provisions

10.1 Utilities
(a) All utilities, including but not limited to, electricity, water, gas, telephone used on the Work will be furnished at Contractor’s sole expense. Contractor must furnish and install necessary, temporary distribution systems, including meters, from distribution points to points on site where utility is necessary to carry on the Work. Upon completion of the Work, Contractor must remove all temporary distribution systems. Unless otherwise indicated, the Contractor must also arrange for permanent utilities as necessary for completion and operation of the work. Contractor must pay for utilities until the “Project Acceptance and Final Payment” form is executed and the Work is accepted by the Engineer. (b) If the Contract is for an addition to an existing structure, Contractor may, with written permission of the Engineer, use City’s existing utilities to carry on the Work by making prearranged payments to City.
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 15 -
CAM #4816-7464-0911 v5

10.2 Water Supply
Water may only be used in the service area of the applicable water purveyor.

Water may not be imported or exported from one water purveyor’s service area to another water purveyor’s service area. If the work area crosses multiple water purveyor’s service areas, one fire hydrant meter from each water purveyor must be obtained, and water from each fire hydrant meter may only be used in the applicable water service area for each water purveyor.

All water used other than through a service connection and meter must be through a fire hydrant meter. Hydrant meters will be installed by the City of Camarillo Water Division or applicable water purveyor and moved from one location to another only upon approval of the City of Camarillo Water Division or other applicable water purveyor. The Contractor must pay all applicable fees and charges related to the construction water account, including but not limited to deposits, installation, inspection and related costs.

Water used will be charged at the unit rate per 100 cubic feet as currently established by City Council resolution or by the applicable water purveyor.

10.3 Dust Control
Contractor must provide such dust control equipment and methods as may be required to protect adjacent property from annoyance or damage from dust caused by its operations, and failure to control such dust will be cause for the Engineer to stop the Work until the dust is controlled. Contractor will have no recourse to collect from City for any loss of time or expense sustained by Contractor due to such suspension of the Work.

10.4 Removal and Disposal of Structures and Obstructions All fences, trees, and obstructions of any nature to the execution of the Work removed by Contractor must be disposed of, reused or delivered to City’s Corporation Yard as required. These tasks are to be included in the cost of other items bid on, if there is no item covering the same. Any obstruction that is privately owned that is removed by Contractor must be replaced or compensated at Contractor’s sole expense to the satisfaction of the Engineer.

10.5 Surveys
Surveys to determine location of property lines and corners, locations of construction, grading and site Work must be supplied by Contractor.

No survey information beyond the information on the plans will be provided by the Engineer. Contractor must preserve all stakes set for the lines, grades or measurements of the Work until authorized to remove them by the Engineer. Any expense incurred in replacing such stakes which Contractor may have failed to preserve will be borne by Contractor.

10.6 Layout and Field Engineering
All field engineering required for laying out the Work and establishing grades for earthwork operations will be furnished by Contractor at its sole expense. Such engineering will be done by a qualified Civil Engineer approved by the Engineer. Any required “as built” drawings of site development must be prepared by the approved Civil Engineer at Contractor’s sole expense.
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 16 -
CAM #4816-7464-0911 v5

10.7 Traffic Requirements
(a) Street Closures, Detours, and Barricades.
(1) Street closures require discretionary City Council authorization and are not allowed unless no safe and effective alternative exists. Contractor must prepare a comprehensive justification for the proposed alternative.

Contractor must consider contract time in the justification, and allow at least 45 calendar days for City review and processing. Meetings, including those outside normal working hours may be necessary. (2) All costs involved in complying with the following requirements for street closures, detours and barricades will be borne by Contractor. (3) Contractor must notify the Engineer at least 5 working days before closing or partially closing any street. The Contractor must arrange detour routes and issue signing instructions, if required. All detour routes must be submitted for approval by the Engineer at least 10 working days before the detour.
(4) Contractor must notify the following agencies, at least 48 hours in advance of the closing, partial closing, or opening of any street or alley:

Camarillo Police Department 805-388-5100
Ventura County Fire Department 805-389-9710
Camarillo Public Works Department 805-388-5340
Camarillo Streets Division 805-388-5338
E.J. Harrison 805-207-0159
Camarillo Post Office 805-383-9804
Camarillo Area Transit 805-388-5346

(5) Contractor must install, maintain, and remove all temporary barricades, lights, warning signs, and other facilities necessary to control traffic as specified in the California Manual on Uniform Traffic Control Devices (CMUTCD). Materials for a temporary facility may be provided from new or used materials. If used materials are provided, they must be sound, in good condition, and otherwise meet the requirements of new materials. (6) If at any time any portion of the street is obstructed to traffic, Contractor must post “No Parking Anytime” signs on both sides of the street for a distance of 300 feet beyond the obstructed portion of the street. (7) In addition to the lane width specified in subsection (b) below, Contractor must maintain a minimum clearance of three feet to excavations and a minimum of two feet to curbs and other obstructions. When traffic patterns required by the Work are such that opposing lanes of traffic must cross the existing centerline, Contractor must separate the opposing lanes at intervals, not to exceed 25 feet, or as directed by the Engineer. (b) Minimum Requirements for Maintaining Traffic Flow: Traffic in each direction must be maintained on all streets at all times. Traffic lanes of at least 10 feet must be used. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 17 -
CAM #4816-7464-0911 v5

10.8 Tests and Inspections
(a) If the Contract, or any laws, ordinances, regulators or any public authority requires any of the Work to be specially inspected, tested or approved, Contractor must give notice in accordance with such authority of its readiness for such inspection or test at least two working days prior to such inspection. If inspection or testing is by an authority other than City, Contractor must arrange for such inspection or testing, and Contractor must also give at least two working days prior written notice to the authority and the Engineer of the date fixed for such inspection. Required certificates of inspection or approval must be secured by Contractor. The Engineer will promptly make observations, where practicable, and do so at the source of supply.

If any of the Work is covered up without approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for inspection or testing and satisfactorily reconstructed at Contractor’s sole expense in strict accordance with the Contract Documents. Costs of tests and inspections of any materials found to be not in compliance with the Contract must be paid for by Contractor at its sole expense. Other costs for tests and inspection of materials will be paid by City.
(b) Where such inspection and testing are to be conducted by an independent laboratory agency, such materials or samples of materials to be tested will be selected by such laboratory or agency, or the Engineer, and not by Contractor. (c) Contractor must notify the Engineer in writing a sufficient time in advance of manufacture of materials to be supplied under contract, which must by terms of the contract be tested, in order that the Engineer may arrange for testing of same at the source of supply. Any materials shipped by Contractor from the source of supply prior to having satisfactorily passed such testing and inspection, or prior to receipt of notice from the Engineer that such testing and inspection will not be required, may not be incorporated in the Work without prior approval of the Engineer and subsequent testing and inspections.
(d) Re-examination of questioned Work may be ordered by the Engineer and, if so ordered, the Work must be uncovered by Contractor. If such Work is found to be in accordance with the Contract Documents, City will pay the costs of re-examination and replacement. If such Work is found not to be in accordance with the Contract Documents, Contractor must pay the costs at its sole expense.

10.9 Soils Investigation Report
When a soils investigation report is available from City, such report will not be a part of the Contract. Any information obtained from such report or any information given on drawings as to subsurface soil condition or to elevations of existing grades or elevations of underlying rock is approximate only, is not guaranteed, and does not form a part of the Contract.

Contractor is required to make a visual examination of site and must make whatever tests it deems appropriate to determine underground condition of soil.

10.10 Compaction Tests
(a) Contractor must perform compaction tests as required by the City Engineer, in accordance with ASTM D-1557 or California Test Method No. 216. (b) Contractor must bear the total expense of all failing tests. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 18 -
CAM #4816-7464-0911 v5

10.11 Cutting and Patching
(a) Contractor must do all cutting, fitting, or patching of the Work as required to make its several parts come together properly and fit to receive or be received by other contractors showing upon, or reasonably implied by, the drawings and specifications for the completed project, as the Engineer may direct. All costs caused by defective or ill-timed Work will be borne by the Contractor.
(b) Contractor may not endanger any of the Work by cutting, excavating, or otherwise altering the Work and may not cut or alter any Work of any other contractor, except with the written consent of the Engineer.

10.12 Earthquake and Tidal Wave Damage
Notwithstanding the provisions of Subsection 4 -1.2 of the SSPWC, when the Governor of California or the President of the United States declares that the area where the Work is being constructed is a disaster area due to earthquakes or tidal waves, Contractor will be relieved of the responsibility for repairing damage to the Work caused by earthquake or tidal wave, unless such damage results from negligent acts or omissions of Contractor.

10.13 Highway and Railroad Permits
The Engineer will obtain the basic state highway and railroad encroachment permits, which will include checking of plans. Contractor must also obtain its own permits from these agencies. Inspection and permit fees charged by these agencies must be paid by Contractor. Any other permits must be obtained by Contractor at no additional cost to City.

10.14 Noise Control
Construction Noise Level Limits: Construction operations must comply with City of Camarillo Municipal Code, specifically Chapter 10.34, Noise Regulations.

11. Acceptance of Work

11.1 No Waiver of Legal Rights
(a) City will not be precluded or estopped by any measurement, estimate, or certificate made either before or after the completion and acceptance of the Work and payment therefor from showing the true amount and character of the Work performed and materials furnished by Contractor, nor from showing that any such measurement, estimate, or certificate is untrue or is incorrectly made, nor that the Work or materials do not in fact conform to the Contract.
(b) City will not be precluded or estopped, notwithstanding any such measurement, estimate, or certificate and payment in accordance therewith, from recovering from Contractor or its surety, or both, such damages as it may sustain by reason of Contractor’s failure to comply with the terms of the Contract.
(c) Neither the acceptance by the Engineer nor by the Engineer’s representative nor any payment for or acceptance of the whole or any part of the Work, nor any extension of time, nor any possession taken by the Engineer will operate as a waiver of any portion of the Contract or of any power herein reserved, or of any right to damages. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 19 -
CAM #4816-7464-0911 v5
(d) A waiver of any breach of the Contract will not be held to be a waiver of any other or subsequent breach.

11.2 Non-C omplying Work
Neither the final certificate of payment nor any provision in the Contract Documents, nor partial or entire occupancy of the premises by the City, will constitute an acceptance of any of the Work not done in accordance with the Contract Documents or relieve Contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship.

11.3 Fulfillment of Contract
Contractor must, at its sole expense, protect and care for all the Work it performs until the Contract has been fulfilled to the satisfaction of, and the Work has been accepted in writing by, the Engineer. The date upon which the Engineer accepts the Work as complete will be the date that Contractor is relieved from responsibility to protect the Work.

11.4 Correction of Work Before Acceptance
(a) Contractor must promptly remove from the site or premises all Work determined by the Engineer as failing to conform to Contract, whether or not installed or incorporated.

Contractor must promptly replace and re- execute the Work to comply with the Contract Documents without additional expense to City and will bear the expense of making good all Work of other contractors destroyed or damaged by such removal or replacement. (b) If Contractor does not remove such nonconforming Work within a reasonable time, City may remove it and may store the material at Contractor’s expense. If Contractor does not pay expenses of such removal within 10 days’ time thereafter, City may, upon 10 days’ written notice, discard such materials or sell such materials at auction or at private sale and will provide an accounting to Contractor for net proceeds of such sale, after deducting all costs and expenses that should have been borne by Contractor.

11.5 Deductions for Uncorrected Work
If City deems it inexpedient to correct any Work injured or not done in accordance with the Contract, City will make an equitable deduction from the Contract price.

11.6 Final Clean Up
Upon completion of the Work and before acceptance and final payment will be made, Contractor, as its sole expense, must clean the Work area and all premises occupied by it in connection with the Work. All rubbish, weeds, graffiti, one- call USA markings, excess materials, falsework, temporary structures, tools and equipment must be removed and all parts of the Work must be left in a neat and presentable condition. All excavations left by removal of structures must be filled and compacted with clean suitable soil acceptable to the Engineer.

11.7 Certificate as to Compliance With Certain Regulations Contractor must file with Engineer, prior to the acceptance of the Work, a certificate in form substantially as follows:
(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 20 -
CAM #4816-7464-0911 v5
I (We) hereby certify that all of the Work has been performed and materials supplied in accordance with the specifications, drawings, and Contract Documents for the Work and that:
(a) no less than the prevailing rates of per diem wages as ascertained by the Director of Industrial Relations has been paid to workers employed on this Work and a copy of these rates has been posted and maintained at the Work site at all times during the course of the Work;
(b) there have been no unauthorized substitutions of subcontractors; nor have any unauthorized subcontracts been entered into;
(c) no subcontract was assigned or transferred or performed by anyone other than the original subcontractor, except as provided in the Subletting and Subcontracting Fair Practices Act, Public Contract Code section 4100 and following; and
(d) all claims for materials and labor and other services performed in connection with the Contract Documents have been paid.

12. Claims between Cit
y and Contractor

12.1 Definition of Claim
As used in this section, “claim” means a separate demand by Contractor, sent by registered mail or certified mail with return receipt requested, for (1) a time extension ( including, without limitation, for relief from damages or penalties for delay assessed by the City), (2) payment of money or damages arising from Work done by or on behalf of Contractor pursuant to the Contract and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (3) an amount the payment of which is disputed by City.

12.2 Notice of Potential Claim Procedure
(a) Contractor agrees that it may not be entitled to the payment of any additional compensation for any claim that may be based on any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, RFI response, or for the happening of any event or occurrence, unless the Contractor has given the Engineer written notice of a potential claim as provided in this subsection.
(b) The written notice of a potential claim must be submitted on the City’s claim form and certified with reference to the California False Claims Act, Government Code sections 12650-12655. The written notice of potential claim must include the following information:
(1) The complete nature and circumstances of the dispute which caused the potential claim.
(2) The Contract provisions that provide the basis of the claim. (3) The estimated cost of the potential claim, including an itemized breakdown of individual costs and how the estimate was determined. (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 21 -
CAM #4816-7464-0911 v5
(4) A time impact analysis of the project schedule that illustrates the effect on the scheduled completion date due to schedule changes or disruptions where a request for adjustment of contract.
(c) The written notice of potential claim must be submitted to the Engineer prior to the time that the Contractor performs any additional work giving rise to the potential claim for additional compensation, if based on an act or failure to act by the Engineer and for which is not expressly provided for under this Contract. The Contractor must provide the Engineer the opportunity to examine the site or Work and respond within five business days from the date the notice of potential claim was submitted to the Engineer. The Contractor must then proceed with the performance of the additional work unless otherwise specified or directed by the Engineer.

When the affected work is completed, the Contractor must submit substantiation of the Contractor’s actual costs and total amount of the claim within 10 days of completing the work.

Failure to do so will be sufficient cause for denial of any claim subsequently filed on the basis of the notice of potential claim.
(d) In all other cases, the written notice of potential claim must be submitted to the Engineer within 15 days after the happening of the event, occurrence or other cause, giving rise to the potential claim.

12.3 Claim Processing Procedure
All claims for which a written notice of potential claim was filed and which claim is not resolved promptly resolved under subsection 12.2 will be processed and resolved in accordance with Public Contract Code section 9204, which is hereby incorporated by this reference, and the provisions of section 9204 are generally set forth in this subsection. This subsection and the requirements of Public Contract Code will not preclude the claimant and City from entering into a written waiver of the claim processing procedures outlined in this subsection and electing to resolve the dispute by arbitration pursuant to Public Contract Code section 10240 and following.
(a) The claimant must submit a written claim that includes reasonable documentation necessary to substantiate the claim.
(b) Upon receipt of the claim, the City and the claimant may, by mutual written agreement, extend the time period for the City to respond to the Contractor’s claim. (c) City will respond in writing to any written claim within: (i) 45 days of receipt of the claim; (ii) the extended time period according to Section 12.3(b); or (iii) where the City Council does not meet within 45 days or the extended time period, three days after the next duly publicly noticed meeting on calendar.
(d) The City’s written response will identify the disputed and undisputed portions of the claim, and the City will process payment for any undisputed claims within 60 days after the written statement referenced in Section 12.3(c). If the claimant disputes City’s written response, or City fails to respond within the time prescribed in Section 12.3(c), the claimant may so notify City, in writing, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, City will schedule a meet and confer conference within 30 days for settlement of the dispute.
(e) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City will provide the (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 22 -
CAM #4816-7464-0911 v5
Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the City issues its written statement. (f) Any disputed portion of the claim, as identified by the claimant in writing, must be submitted to nonbinding mediation, with the City and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators may select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party bear s the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute may be resolved through other means, including civil action or arbitration in accordance with Public Contract Code sections 20104.4 and 20104.6.

13. Assignment of Rights
In entering into this Contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700 of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment will be made and become effective at the time City tenders final payment to Contractor, without further acknowledgement by the parties. (Pub. Con. Code § 7103.5.)

14. Prohibited Interests
No official, employee, or agent of City, nor any member of their immediate family, may have any direct or indirect interest in this Contract.

15. Labor Code Requirements

15.1 State Wage Determination
(a) Under California Labor Code section 1770 and following, Contractor must pay not less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations. Copies of such prevailing rate of per diem wages are on file at the office of the Owner, which copies must be made available to any interested party on request, and are also available on the Internet at the website of the Department of Industrial Relations: http://www.dir.ca.gov/dlsr/PWD/index.htm. Contractor must post a copy of such determination at each job site.
(b) Under Labor Code section 1775, Contractor will, as a penalty to Cit y, forfeit the statutory penalty each calendar day, or portion thereof, for each worker paid less than the prevailing rates as determined by the Director for such work or craft in which such worker is employed for any public work done under the Contract by it or by any subcontractor under it. (c) Contractor must comply with all provisions of Labor Code section 1775.

(5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 23 -
CAM #4816-7464-0911 v5

15.2 Compliance Monitoring
(a) The Work is subject to prevailing wage compliance monitoring and enforcement by the Department of Industrial Relations (Labor Code § 1771.4). (b) Pursuant to Labor Code section 1771.4, Contractor and its subcontractor(s) must furnish the payroll records specified in Labor Code section 1776 directly to the Labor Commissioner and to the City, in the following manner:
(1) At least monthly or more frequently if specified in the contract with the awarding body.
(2) In a format prescribed by the Labor Commissioner.
(c) Contractor must post job site notices, as prescribed by regulation (Labor Code § 1771.4).
(d) If the City determines based on its review of the Contractor ’s or any of its subcontractor’s certified payroll records that the Contractor or any subcontractor has underpaid its employees, then upon the second occurrence of such underpayment, the City reserves the right to obtain a certified payroll compliance monitoring consultant to assist the City in the additional work required to ensure Contractor or any subcontractor compliance and the associated costs will be the responsibility of the Contractor and will be deducted from Pay Estimates due to the Contractor.

15.3 Payroll Records
(a) Under Labor Code section 1776, Contractor and each subcontractor must keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by it in connection with the public work.
(b) The payroll records enumerated in subsection (a) above, must be certified and made available for inspection at all reasonable hours at the principal office of Contractor on the following basis:
(1) A certified copy of an employee’s payroll record must be made available for inspection or furnished to the employee or his or her authorized representative on request.
(2) A certified copy of all payroll records enumerated in subsection (a) must be made available for inspection or furnished upon request to a representative of the body awarding the Contract, the Division of Labor Standards Enforcement, and the Division of Apprenticeship Standards of the Department of Industrial Relations.
(3) A certified copy of all payroll records enumerated in subsection (a) must be made available upon request by the public for inspection or copies thereof made. However, a request by the public must be made through either the body awarding the Contract, the Division of Apprenticeship Standards, or the Division of Labor Standards Enforcement. If the (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 24 -
CAM #4816-7464-0911 v5
requested payroll records have not been provided pursuant to subparagraph (2) above, the requesting party must, prior to being provided the records, reimburse the costs of preparation by Contractor, subcontractors, and the entity through which the request was made. The public may not be given access to the records at the principal offices of Contractor.
(c) Contractor or any subcontractor must file a certified copy of the records enumerated in subsection (a) with the entity that requested the records within 10 days after receipt of a written request.
(d) Any copy of records made available for inspection and copies furnished upon request to the public or any public agency by City, the Division of Apprenticeship Standards, or the Division of Labor Standards Enforcement must be marked or obliterated in such a manner as to prevent disclosure of an individual’s name, address, and social security number. The name and address of Contractor or any subcontractor performing the contract may not be marked or obliterated.
(e) Contractor must inform City of the location of the records enumerated under subsection (a), including the street address, city and county, and must, within five working days, provide a notice of change of location and address.
(f) Contractor or any subcontractor has 10 days in which to comply subsequent to r
eceipt of written notice requesting the records enumerated under subsection (a). In the event of noncompliance with the requirements of this Section, Contractor must, as a penalty to the state or City, forfeit the statutory penalty for each calendar day, or portion thereof, for each worker, until strict compliance is effectuated. These penalties will be withheld from progress payments then due. Responsibility for compliance with Section 15. 3 (a) through (f) lies with Contractor.
(g) For all projects, the payroll records enumerated in subsection 15.3 ( a) above, must be delivered to the Labor Commissioner (no event less frequently than monthly) directly to the Labor Commissioner in the format prescribed by the Labor Commissioner. (h) For federally f unded projects, Contractor must submit certified payroll records weekly to the Engineer.
(i) Upon request, Contractor must submit backup documentation for certified payroll records including cancelled checks, proof of payment of fringe benefits, time cards, apprenticeship documentation, and other backup records.

15.4 Apprentices
(a) Contractor must comply with Labor Code section 1777.5 and following, and Title 8, California Administrative Code section 200 and following, with respect to apprentices . To ensure compliance and complete understanding of the law regarding apprentices, and specifically the required ratio thereunder, Contractor and subcontractors should, where some question exists, contact the Division of Apprenticeship Standards prior to commencement of the Work. Responsibility for compliance with this Section lies with Contractor. City policy is to encourage the employment and training of apprentices on its construction contracts as may be permitted under local apprenticeship standards. These provisions require that contractors and subcontractors submit contract award information to the applicable joint apprenticeship (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 25 -
CAM #4816-7464-0911 v5
committee, employ apprentices in apprenticeable occupations in a ratio of not less than one hour or apprentice’s work for every five hours of labor performed by a journeyman (unless an exception is granted in accordance with Section 1777.5), contribute to the fund or funds in each craft or trade or a like amount to the California Apprenticeship Council, and that contractors and subcontractors may not discriminate among otherwise qualified employees as apprentices solely on the ground of sex, race, religion, creed, national origin, ancestry or color. Only apprentices as defined in Labor Code section 3077, who are in training under apprenticeship standards and who have written apprentice agreements may be employed on public works in apprenticeable occupations. The responsibility for compliance with these provisions is fixed with the prime contractor for all apprenticeable occupations. Contractor agrees to provide Division of Apprenticeship Standards (DAS) Form 13 or any successor apprenticeship reporting form to City no later than the time of Contractor’s execution of the Contract Documents. (b) Contractor must comply with the requirements of Form FHWA 1273 (for federally funded projects), and Labor Code sections 1777.5 and 1776. In the event of conflict between the provisions, Contractor must comply with the most stringent provision that requires the largest number of apprentices.

15.5 Working Hours
(a) Contractor must comply with all applicable provisions of Labor Code section 1810 and following relating to working hours. Contractor will forfeit the statutory penalty to City for each worker employed in the execution of the Contract by Contractor or by any subcontractor for each calendar day during which such worker is required or permitted to work more than eight hours in any one calendar day and 40 hours in any one calendar week, unless such worker receives compensation for all hours worked in excess of eight hours at not less than one and a half (1 -1/2) times the basic rate of pay. Contractor must comply with all requirements for payment of overtime and holiday rates of pay. (b) City may withhold from any monies payable on account of Work performed by Contractor or any subcontractor, such sums as may administratively be determined to be necessary to satisfy any liabilities of such Contractor or subcontractor, for unpaid wages and liquidated damages as provided for in subsection (a), above.

15.6 Workers Compensation
(a) Under Labor Code sections 1860 and 3700, Contractor is required to secure the payment of compensation of its employees.
(b) Under Labor Code section 1861, Contractor must sign and file with City the following certification prior to performing the Work of the Contract: “I am aware of the provisions of section 3700 of the Labor Code which require every employer to be insured against liability for worker’s compensation or to undertake self -insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the Work of this Contract.”

15.7 Protection of Workers in Trench Excavations
As required by Labor Code section 6705, whenever Work under the Contract involves the excavation of any trench or trenches five feet or more in depth, Contractor must submit for acceptance by City or by a registered civil or structural engineer, employed by City, to whom authority to accept has been delegated, in advance of excavation, a detailed plan (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 26 -
CAM #4816-7464-0911 v5
showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation, of such trench or trenches.

If such plan varies from the shoring system standards established by the Construction Safety Orders of the Division of Industrial Safety, the plan must be prepared by a registered civil or structural engineer employed by Contractor, and all costs therefor will be included in the price named in the Contract for completion of the Work as set forth in the Contract Documents.

Nothing in this Section may be deemed to allow the use of a shoring, sloping, or other protective system less effective than that required by the Construction Safety Orders. Nothing in this Section may be construed to impose tort liability on City, the City Engineer, nor any City officers, agents, representatives, or employees. Unless a specific bid item is included in the Bid Proposal, payment for protection of workers in excavations requiring adequate sheeting, shoring, bracing and other safety provisions must be included in the bid item for mobilization. A separate item must be shown in the schedule of values for protection of workers in trench excavations. Contractor must obtain all necessary permits for excavation work from Cal/OSHA at Contractor’s expense.

16. Sales and Use Tax Cooperation
Contractor must take all steps reasonably necessary, as instructed by the Director of Finance, with respect to collection and reporting California Sales and Use Tax, to ensure that, to the extent legally possible, sales and use taxes collected for personal property purchased pursuant to this Contract, are reported with a point of sale within City.

17. Documentation of Status of Surety
Contemporaneously with the filing of a bid bond, labor and materials bonds, and faithful performance bond (or others), Contractor must obtain and file with City from the following documents:
(a) a certified copy of the unrevoked appointment Power of Attorney, By Laws or other instrument entitling or authorizing the person who executed the bond to do so; and (b) a certified copy of the Certificate of Authority of the issuer issued by the Insurance Commissioner of the State of California; and
(c) a certificate from the Clerk of the County where the principal office of the issuer is located that the Certificate of Authority of the issuer has not been surrendered, revoked, cancelled, annulled or suspended, or, in the event that it has been surrendered, revoked, cancelled, annulled or suspended, that renewed authority has been granted; and (d) copies of the insurers’ most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Article 10 of Chapter 1 of Part 2 of Division 1 of the Insurance Code (section 900 and following).

18. Construction and Demolition Waste

Contractor must provide an accurate estimate of the amount of construction debris recycled as a result of the project. Any materials that could have been disposed of in a landfill, but were instead processed and reused on the project or elsewhere will be considered recycled.

Amounts must be itemized with description of the items recycled and must be reported in either cubic yards or tons (see Appendix). Examples of recycled construction debris are: asphalt concrete grindings, chunks of broken asphalt concrete, PCC chunks, base, soil, metals, and (5-2023)

GENERAL CONDITIONS/SPECIFICATIONS
- 27 -
CAM #4816-7464-0911 v5
other similar materials. Contractor must sign the estimate of recycled construction debris and must certify that the estimate is accurate to the best of contractor’s knowledge. Contractor must provide this estimate prior to submittal of the final pay estimate and at such other reasonable intervals during the course of the project as requested by the Engineer.

19. Use of Premises

(a) The Work must be confined to City owned or controlled land or right -of-way as shown on the plans, unless otherwise expressly provided in the Contract Documents. If the right- of-way is not shown on the plans, the Contractor must field verify the right-of-way at no additional cost to the City. Contractor must provide at Contractor’s own expense and without liability to the City any additional land and access thereto that Contractor may desire for temporary construction facilities, or for storage and staging of materials.
(b) Contractor may not trespass upon or in any way disturb property adjacent to City owned or controlled land or right -of-way or outside any permanent or temporary project construction easements without first obtaining written permission from the applicable property owner. A copy of such written permission must be furnished to the Engineer. (c) If Contractor finds it necessary to obtain additional working area, it is the responsibility of Contractor to negotiate permissions, obtain applicable permits and pay all costs pertaining to the additional work area.
(d) If additional work area is required and obtained, the following requirements will apply:
(1) Contractor must restore such property to the full satisfaction of the property owner at no additional cost to the City, and must obtain from the property owner a written release stating that restoration has been satisfactorily made. Contractor must provide the Engineer a copy of the written release from the property owner.
(2) Contractor may not place or dispose any excess earth, stone, or other excavated material on any property without first obtaining necessary permits and written permission of the owner of the property and securing the approval of the City Engineer. Contractor must provide the Engineer with one copy of the property owner's written permission and one copy of a written release from the property owner stating that the work has been completed to the satisfaction of the property owner.
(3) All items within any City owned or controlled land or right-of-way or within any permanent or temporary construction easements must be removed, or removed and replaced, or restored as required by the Plans and Specifications, as directed by the Engineer.

CITY OF CAMARILLO

DEPARTMENT OF PUBLIC WORKS

STANDBY POWER AT CITY HALL AND

CORPORATION YARD
PROJECT NO. CH-5067-2
These Special Provisions have been prepared under the direction of the following professional Architect, licensed by the State of California
NV5 W
EST, INC.
1868 Palma Drive, Suite A
Ventura, CA 93003

1 CITY OF CAMARILLO

DEPARTMENT OF PUBLIC WORKS

STANDBY POWER AT CITY HALL AND

CORPORATION YARD
PROJECT NO. CH-5067-2

TECHNICAL SPECIFICATIONS
David C. Kesterson, AIA Date
Registered Architect #C-21175
Exp. 02/28/2025
Division 01, 02, 03, 04, 05, 07, 08, 09, 31, 32

Date
6/26/2024
exp 9/30/2025
SIGNED 06/26/2024
Charles Joy, PE
Registered Electrical Engineer #20461
Exp. 9/30/2025
Division 26
2 CITY OF CAMARILLO

STANDBY POWER AT CITY HALL AND CORPORATION YARD
PROJECT NO. CH-5067-2

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 – GE NERAL REQUIREMENTS

011000 SCOPE OF WORK
012000 GENERAL
012001 MOBILIZATION
012003 MEASUREMENT AND PAYMENT
012005 COMPENSATION
013301 PROCESS AND SUBMITTALS
013516 ALTERATION PROJECT PROCEDURES
015723 STORMWATER POLLUTION CONTROL PLAN
017300 EXECUTION
017700 CLOSEOUT PROCEDURES

DIVISION 02 – SIT E CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

031000 CONCRETE FORMWORK AND ACCESSORIES
032000 CONCRETE REINFORCEMENT
033000 CAST-IN-PLACE CONCRETE
037000 DRYPACK AND MECHANICAL ANCHORS

DIVISION 04 – MA
SONRY

042200 CONCRETE UNIT MASONRY

DIVISION 05 – STEEL

055000 METAL FABRICATIONS

DIVISION 07 – THE RMAL AND MOISTURE PROTECTION

076220 SHEET METAL FLASHING AND TRIM
3 DIVISION 08 – DOOR AND WINDOWS

081110 HOLLOW METAL DOORS AND FRAMES

DIVISION 09 – FIN ISHES

092400 PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS 093113 TILING
099113 EXTERIOR PAINTING

DIVISION 26 – EL ECTRICAL

260000 GENERAL ELECTRICAL
260523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES
262300 LOW-VOLTAGE SWITCHGEAR
263213 GENERATOR - DIESEL
263713 MICROGRID CONTROLLER
265619 LED EXTERIOR LIGHTING

DIVISION 31 – EA

RTHWORK

311100 SITE CLEARING
312000 EARTH MOVING

DIVISION 32 – EXTERIOR IMPROVEMENTS

321216 ASPHALT PAVING
321313 CONCRETE PAVING
321313A ACCESS RAMPS
329500 TREE PROTECTION

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-1

SECTION 011000 – SCOPE OF WORK
PART 1 - GENERAL

1.01 SUMMARY
A. Project locations:

1. City Hall; 601 Carmen Dr, Camarillo, CA 93010

2. Corporation Yard; 283 S Glenn Dr, Camarillo, CA 93010 B. This section describes the Scope of Work for the Project. Requirements provided in this section may be addressed in further detail elsewhere in the Contract or Specification Documents.

C. This specification applies to a design- bid-build project and includes the scope for Owner approved alternate design process, construction, commissioning, and operation of a complete energy system as described here and elsewhere in the Contract and Specification Documents.

D. In this document, "Owner" shall refer to the City where project will be located, regardless of system ownership, and include any representative of the City, such as independent engineers, consultants , or inspectors. "Contract" refers to the construction contract and any associated "Contractor" refers to the entity performing the work.

E. Contractor shall perform all work and provide submittals consistent with this specification, other technical specifications, and the Contract and Specification Documents for all stages of work.

F. Design Documents may be amended or supplemented to include elements or ideas from Contractor’s Proposal or other proposals, but only to the extent Owner expressly agrees in writing. Contractor is solely responsible for confirming the extent of any changes to the Contract and Specification Documents.

PART 2 - SCOPE OF WORK

2.01 REQUIREMENTS OF WORK
A. DUE DILIGENCE. Contractor shall identify and perform all necessary due diligence to implement the Project. Due diligence shall include, but not be limited to:
geotechnical investigations, structural investigations, surveying, underground utility location (including Ground Penetrating Radar (GPR)), p otholing/hand-digging to verify critical UG constraints, utility coordination, title reports, geohazard review, electrical equipment inspection and testing, identification of Authorities Having Jurisdiction (AHJs), etc.

B. PERMITS

1. Contractor shall identify and obtain all required permits. Permitting shall include all required coordination and submittals with the AHJ(s), including the utility the project is interconnected with. Contractor shall take all steps to secure AHJ approvals and all other required reviews and approvals of the Construction Documents.

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-2

2. Where a permit process was begun prior to the Contract (e.g. Interconnect Applications with the utility), Contractor shall take over the permitting process from the Owner upon Contract execution.

3. Contractor shall pay all permitting fees required for the project, inclusive of utility interconnect costs, except where expressly identified as an Owner - cost in the Contract.

4. For California Environmental Quality Act (CEQA) permitting, Contractor shall assume that the Owner will conduct the initial required CEQA permitting and documentation. Contractor shall support the Owner in preparing any required CEQA documentation (including any exemption materials).

5. The Contractor shall be responsible for adhering to all permit requirements, including all costs associated with adherence. This shall include all CEQA requirements, including mitigation requirements.

2.02 ACCESS AND SITE COORDINATION
A. Contractor is responsible for on- site installation supervision throughout the duration of the project.

B. The Contractor is responsible for maintaining fire lane access and clearances at all easements at all times.

C. The Contractor shall coordinate closely with the Owner to ensure all construction activities minimize impact on Owner operations at the sites.

D. The Contractor and Owner will mutually agree in writing on site access policies prior to the beginning of work. Policies will cover allowable times or schedules for entry, support for testing and inspections, access to utility meters and lockable disconnect, vehicle entry and access, use of site utilities or amenities, fencing requirements, and access points.

E. The Contractor shall schedule its operations on the job site to provide for:

1. Pedestrian/vehicle ingress and egress from site at all times, except if otherwise approved in writing by the Owner.

2. Driveways, Walkways and Entrances: Keep driveways, parking lots, loading areas, and entrances serving premises clear and available to Owner, Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize use of driveways and entrances by construction operations.

4. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

5. The construction schedule shall show the start and end of any partial closures to any site access points. Contractor shall notify the Owner seventy-two (72) hours in advance of any closures.

6. Contractor shall notify Owner immediately upon any change in project schedule or operation that may affect access. Owner will be responsible for notification to affected parties.

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-3

F. Contractor, Contractor’s employees, and all subcontractors shall adhere to applicable Owner requirements as well as all Federal, State, and County Public Health.

G. All active work areas must be fenced off from start of work at that area until completion or until area is safe for entry, whichever is longer. Temporary fencing and access control layouts shall be submitted to the Owner and approved for each site prior to commencing construction. Temporary fencing shall also be installed to protect trees and vegetation adjacent to work areas from construction damage.

For roof installation, fall protection shall be provided and utilized by the Contractor.

H. Contractor acknowledges that adjacent facilities may remain in operation during all or a portion of the Work, and it shall take all reasonable precautions to minimize noise as required by applicable laws and the Contract Documents. Notice of proposed noisy operations, including without limitation, operation of pneumatic demolition tools, concrete saws, and other equipment, shall be submitted to Owner a minimum of forty -eight (48) hours in advance of their performance. Contractor shall further prevent any of its employees or its subcontractor employees from playing any recorded music devices or radios or wearing any radio headphone devices for entertainment while working on the project.

I. Driving on the Site(s) shall be limited to periods when the public is not present. If driving or deliveries must be made when people are present on site, two (2) or more ground guides shall lead the vehicle across the area of travel. The speed limit on -the Premises shall be five (5) miles per hour (maximum) or less if conditions require. Owner shall designate a construction entry point to each site.

J. During the operational phase, all staff or subcontractors must provide twenty-four (24) hours advanced notice to Owner and check in with the Owner upon arrival at the site.

2.03 CONSTRUCTION PHASE
A. Contractor shall provide complete Construction Phase oversight, inclusive of onsite construction management and management of all sub-contractors.

B. Dies
el-Genset

1. Section includes packaged engine-generator sets for standby power supply with the following features:
a. Fuel system base tank.
b. Concrete Pad.
c. Outdoor Enclosure.
d. Acceptance Testing.

2. A Caterpillar manufactured engine driven electrical generating system is the basis of design for this project.
a. Equivalent alternatives must be approved in writing by Owner.

3. Obtain packaged generator sets and all associated auxiliary components through one source from a single manufacturer. Walk -in enclosures may deviate from this requirement.

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-4

C. Spare Conduits. Contractor shall install spare conduits with appropriate rated pull tape/strings and terminations at each site as follows (See technical specifications for further detail):

1. Data. ( 1) x 1.5 -in conduits from nearest existing Site data connection to Generator.

2. Conduit shall terminate in an 8" x 8" x 3" NEMA 4X junction box.

D. Any changes to Owner property required for the Project, including, but not limited to: grading, tree or vegetation removal, repair of damage caused by Contractor, light standard removal, new lighting, parking islands, ADA improvements, re - striping of parking areas, etc. are the sole responsibility of the Contractor.

E. Where a project is installed in a parking lot, Contractor shall ensure that parking lot striping designs meet current AHJ, City and/or County standards. Where designs are out of compliance and corrective work has not been included in the Contract, Contractor shall identify corrective measures and provide a Request for Information (RFI) to Owner whether to include re-design in Project scope.

F. Contractor shall coordinate with, and provide support to, the Owner, all Inspectors, and Owner’s Representatives during all phases of work.

G. SCHEDULE & MEETINGS

1. Contractor shall coordinate and schedule weekly project meetings from Notice to Proceed (NTP) through project closeout with all stakeholders.

2. Contractor shall maintain formal meeting minutes and agendas, submitted to the Owner prior to the next meeting for review.

3. Contractor shall maintain a detailed master project schedule and three-week look ahead. Master schedules and three-week look ahead schedules shall be distributed to all attendees the day prior to the next scheduled project meeting. Master project schedules shall be promptly provided to Owner upon request throughout the project life cycle.

4. Frequency of meetings are allowed to change upon the stakeholder availability and approval from the Owner.

H. UTILITY COORDINATION & INTERCONNECTION

1. Contractor shall manage and be responsible for all work and costs for the Project to be interconnected with the utility.

2. Contractor shall manage the interconnection process after contract turnover, including tariff change requests, processing costs , coordination with the local utility(ies), shutdowns, inspections, testing, etc. necessary to achieve interconnection and permission to operate for all energy systems.

3. Should an issue arise that may jeopardize the project completion target date, some other utility milestone, substantially increase interconnection costs or the ability to interconnect the project, the Contractor shall promptly notify the Owner and seek approval from Owner before making any changes to the interconnect application.

I. AMERICANS WITH DISABILITIES ACT (ADA).

1. Contractor shall be responsible for the identification all ADA deficiencies at the Project site that will require upgrades as a result of the Project.

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-5

2. Contractor shall design all required improvements during detailed design in order to secure permits from the AHJ(s).

3. Contractor shall be responsible for implementation of all ADA work detailed on the drawings and required by the permit, including, but not limited to:
parking lot restriping, covered parking space ratios, signage, path of travel, etc.

J. MISCELLANEOUS. Contractor shall provide:

1. S ecure storage facility at job site for all equipment and supplies, including any required security.

2. Legal toilet and hand wash sink facilities at job Sites.

3. Daily cleanup to “broom clean” conditions.

4. Implementation and management of all Stormwater Pollution Control Plan (SWPCP) and other permit required measures for construction.

5. Return of disturbed areas to pre-construction conditions including repair of all pavement and concrete, street sweeping & cleaning, restriping, and removal of survey marks, equipment track marks & scuffs on finished concrete surfaces.

6. Remediation of all fields , turf, landscaping and irrigation to restore to pre- construction conditions.

7. Installation of Owner approved project information signage and removal at completion of project if needed.

2.04 COMMISSIONING & CLOSEOUT
A. See Specification 013301, Process and Submittals for further details regarding commissioning and closeout.

B. Commissioning and closeout shall follow industry best practices and applicable codes and standards identified in the Contract and Specification Documents.

C. Startup, Testing and Commissioning.

1. Contractor shall provide complete startup, testing, commissioning, and documentation of these activities for all energy systems installed or modified as part of the Project.

2. Commissioning shall include all associated tasks and documentation required to successfully commission the system per Contract/Specification Document requirements and industry best practice.

3. Contractor shall assist Owner and any third- party commissioning agents/inspectors, including provision of licensed electricians to interact with energy systems and provision of documentations.

4. Contractor shall perform performance testing to confirm that all energy systems are performing per the design and operational/functional requirements of the Contract and Specification Documents.

D. Contractor shall ensure successful interconnection with the Utility and achieve permission to operate (PTO) from the Utility. Contractor shall coordinate with the

City of Camarillo SCOPE OF WORK
CH-5067-2 011000-6

Owner to ensure the interconnected service has been placed on the intended and appropriate Utility tariff.

E. Undertake punchlist walks with Owner , ensure completion of punchlist work and provide comprehensive labeled, time stamped photo library of complete items.

F. Record Documents. Contractor shall provide final, “as-built” Construction Documents clearly conformed with all changes made during construction, at a minimum in CAD and PDF formats, including all underground trenching/boring routes and depths.

G. Closeout Documents. Contractor shall provide a comprehensive set of closeout documents per Specification 01 33 00, including an Operations & Maintenance Manual for each site that includes all energy systems.

H. Training. Conduct a training for Owner staff, with orientation to the energy systems, monitoring platforms, safety procedures, and Operations & Maintenance Manuals.

I. Permit Closeout

1. Contractor shall ensure that all permit requirements have been met and ensure closeout of all permits required for the Project.

2.05 OPERATIONAL PHASE
A. Contractor shall provide:

1. One-year extended commissioning with full wrap troubleshooting and repair of all work and equipment installed as part of the Project to meet functional, operational and performance requirements. All work in the one- year extended commissioning period shall be at no cost to the Owner, except for damage or misuse by Owner or others not under the control of the Contractor.

2. All work required by the Warranty detailed in the Contract.

3. All work required by any Operations and Maintenance Agreement.

4. All warranty and work required of the installation Contractor by utility interconnection rules.

END OF SECTION 011000 - SCOPE OF WORK

City of Camarillo GENERAL
CH-5067-2 012000-1

SECTION 012000 - GENERAL

GENERAL

1.01 GENERAL DESCRIPTION OF THE WORK
A. Project locations:

1. City Hall; 601 Carmen Dr, Camarillo, CA 93010

2. Corporation Yard; 283 S Glenn Dr, Camarillo, CA 93010 B. The General Contractor shall furnish all labor, materials, tools, and equipment as necessary to complete project; all in accordance with the Standard Specifications, general conditions/specifications, plans, and these Special Provisions. The work to be performed by Contractor includes but is not limited to the following.

1. Where indicated on the construction drawings, demolish, remove, and properly dispose of all existing utilities, structures, planters, trees, and all other site features, unless otherwise noted on the plan to be protected, relocated, and/or salvaged.

2. Where indicated on the construction drawings, and as designated by the project QSP and/or City, implement the Storm Water Pollution Control Plan during demolition and construction, employing noted Best Management Practices, (BMPs).

3. Where indicated on the construction drawings, construct the enclosures, equipment pads, and curb and sidewalk.

4. Where indicated on the construction drawings, install the City purchased generators and provide the required electrical equipment and infrastructure.

5. Where indicated on the construction drawings, replace or re -feed the Main Switchgear at each fac.

1.02 STANDARD SPECIFICATIONS AND DETAILS
A. The work provided herein must conform to and be in accordance with the Contract Plans, General Conditions/Specifications and Special Provisions, as well as the 2021 edition Standard Specifications for Public Works Construction ("SSPWC"), written and promulgated by the Public Works Standards, Inc.; herein referred to as the "Standard Specifications", the 2021·edition Standard Plans for Public Works Construction ("SPPWC"), written and promulgated by the Public Works Standards, Inc.; herein referred to as the "Standard Plans", Califor nia Manual on Uniform Traffic Control Devices (CMUTCD), City of Camarillo (City) Standards, City of Camarillo Water Division Standards, and Camarillo Sanitary District (District) Standards.

B. Whenever in the Contract Documents references are made to published specifications, codes, standards, or other requirements, it is understood that if a

City of Camarillo GENERAL
CH-5067-2 012000-2

date is not specified, only the latest specifications, standards, or requirements of the respective issuing agency which have been published as of the date that the Work is advertised for bids will apply; except to the extent that such standards or requirements may be in conflict with applicable laws, ordinances, or governing codes. No requirements set forth herein or shown on the drawings will be waived because of any provision of, or omission from, the standards or requirements.

1.03 REQUIREMENTS OF THE WORK
A. The phasing of work, including means and methods, of how to meet the requirements of the Contract Documents shall be proposed by the Contractor for City review and approval. Contractor shall secure all permits prior to commencing and proceeding with the work.

B. All work shall be coordinated with the Engineer, Project Plans, Traffic Control Plan, Project Schedule, Contract Period, Submittals, and other requirements of these Contract Documents.

C. All necessary submittals shall be reviewed and accepted by the Engineer prior to the scheduling of any phase of work and start of construction.

D. Any modification to the traffic control plan shall be approved in advance by the Traffic Engineer.

E. Required notifications shall be delivered prior to each applicable phase of the work.

F. The City reserves the right to direct the order of work in the interest of safety and convenience. The Engineer will endeavor to give the Contractor 72 hours of notice of any such directed order of work.

G. Access to businesses, schools and residences shall be maintained at all times except during approved street closures.

H. Contractor shall allow utility owners access to the work and shall schedule around interference by utility owners performing concurrent work.

I. Closed lanes shall be opened to traffic and traffic controls removed as soon as the work is complete and all temporary striping at required locations is placed.

J. Tree removal shall be the first item of work to be performed.

K. Contractor shall work closely with the City and adjacent school, church, residents and businesses to ensure disturbances are minimal and corrective actions addressed immediately or in less than 24 hours as deemed necessary by the Engineer.

L. Contractor shall allow access of emergency vehicles at all times.

M. All turning movements are to be maintained during the work unless approved in advance by the Engineer.

City of Camarillo GENERAL
CH-5067-2 012000-3

N. If a traffic loop is damaged the Contractor shall notify the Engineer immediately.

Damaged traffic loops shall be replaced within 48 hours of being damaged at the Contractor's expense.

O. No street lanes may be closed prior to 8:30 a.m. and all lanes must be opened by 4:00 p.m.

P. The Contractor shall diligently execute the contract work within the allowed number of working days specified in Page 1 of the Bid Proposal, counting from the date stated in the Notice to Proceed for construction. The days to finish the punch list, provided by the City, are included in the working days.

1.04 CONTRACTOR’S USE OF PREMISES
A. Contractor shall always maintain construction site security and adhere to City’s site security measures.

B. The Contractor shall maintain a minimum access lane of not less than fourteen (14) feet wide, or the full width of the existing access roadway, on all roadways at all times as directed by the City. Where these requirements cannot be met, Contractor shall submit traffic control plan to traffic engineer for approval prior to proceeding with work. Contractor shall provide traffic control per Specification Section 012002. Restricted or impacted roadway access shall be minimized to the extent possible.

The Contractor shall provide fixed and/or portable chemical toilets and washing facilities for the use of the Contractor’s employees, subcontractors, and visitors to the work site. Contractor employees and subcontractors shall not use City facilities without prior written permission.

1. These accommodations shall be in sufficient quantity and have regular service to maintain them in a neat and sanitary condition. Toilets and washing facilities shall conform to the requirements of Title 8, California Code of Regulations and be in accordance with the Portable Toilet BMP WM-9 identified in the Storm Water Pollution Control Plan and shall be placed in near proximity to the worksite. The portable toilet should be located away from drainage facilities, watercourses, and from traffic circulation. If site conditions allow place portable facilities a minimum of 50 feet from drainage conveyances and traffic work areas. When subjected to high winds, temporary sanitation facilities should be secured to prevent overturning.

2. Present location of accommodations to City for approval via formal submittal.

3. All temporary toilets and washing facilities shall be furnished and placed during mobilization to the work site and shall be removed upon demobilization. Facilities are to be cleaned at minimum once a week or as directed by the Engineer.

City of Camarillo GENERAL
CH-5067-2 012000-4

C. SECURITY FENCING

1. Contractor shall furnish and install security fencing around the entire perimeter of the work area. Contractor shall maintain the fencing in upright condition at all times and ensure all requests by City are addressed on the same day the written or verbal notice is received.

2. Contractor to fence off the construction area during the entire duration of construction and should be installed prior to commencing other construction work. Privacy screen should be installed throughout the perimeter and replaced as needed throughout the contract duration as requested by the City.

3. Temporary fence shall be installed per ASTMF3342-19 Standard Guide for Temporary Fence Applications for Construction Sites.
a. Posts to be 10’ o.c. and driven to a minimum footing depth of 24 in.

Gate posts to be set in concrete footing.
b. Fabric to be installed in accordance with ASTM F 567, stretched taut and attached to each post.
c. If required, top rail to be installed in accordance with ASTM F 567 in lengths not less than 21’.
d. Swing Gates: Installation of swing gates and gateposts in compliance with ASTM F 567. Electrically operated gates must be manufactured and installed in compliance with ASTM F2200 and UL 325.
e. Horizontal Slide Gates: Installation varies by design and manufacturer, install according to manufacturer’s instructions and in accordance with ASTM F567. Electrically operated gate installation must conform to ASTM F2200 and UL 325.

D. SUBMITTALS

1. Shop drawings: Site plan showing layout of fence location with dimensions, location of gates and opening size, cleared area, elevation of fence, gates, footings and details of attachments.

2. Material samples: When required, provide representative samples of chain link fabric, framework and fittings.

3. General contractor to furnish all labor and materials necessary and perform other related work as necessary to complete this scope of work; all in accordance with the Standard Specifications, general conditions, specifications, plans, and these special provisions.

1.05 COORDINATION WITH OWNER AND IMPACT OF WORK
A. During construction of improvements, the work shall be performed in such a manner to mitigate impacts to the City, businesses, schools, and residents. It is

City of Camarillo GENERAL
CH-5067-2 012000-5

the sole responsibility of the Contractor to ensure City sidewalks are usable and accessible to maximum extent feasible during construction.

B. Contractor shall coordinate with the City the timing for all work to ensure minimal disturbance in day -to-day business and obtain schedule approval from the City prior to commencement.

1.06 PUBLIC NOTIFICATION AND PROJECT SIGNS
A. The Contractor must furnish and install two (2) project signs. The signs must be installed at least 2 weeks prior to the start of work at specific locations to be determined by the Engineer. The signs must meet the requirements of City of Camarillo Standard Drawing No. TR-10, see Appendix I.

B. The Engineer shall stipulate the wording of the signs, but both will be the same.

The Contractor is responsible for changing the dates on the signs at the City’s direction within 24 hours of given notice.

C. The sign must contain an anti -graffiti coating. The anti -graffiti coating must be a protective film and must protect the sign from graffiti and must allow removal of graffiti without damage to the sign, including after removal of the graffiti with solvents. Such film shall not reduce retro reflectivity of the sign at any time.

Contractor shall submit anti -graffiti coating for review and approval by the Engineer. The Contractor must maintain the sign for graffiti and must provide a new sign if the graffiti or other event damages the sign. At the end of construction, or when directed to do so by the City, the Contractor is responsible for the removal and safe disposal of all signs and related materials. The Contractor must maintain the sign for the duration of construction, removing them only after the completion date. All costs incurred in furnishing, installing, maintaining, relocation and removing the sign must be included in other items of work and no separate payment will be made.

D. At least seven (7) calendar days prior to beginning work, the Contractor must distribute notices to all residences, owners, businesses, and schools adjacent to or affected by the proposed work. In addition, the Contractor must notify property owners and adjacent neighborhoods in writing as directed by the City, 72 hours in advance of area specific work. Such notices must at minimum give the start date of the work, daily schedule for the proposed work, typical parking restriction for the work, the times of any restricted driveway access, impacts to residences and businesses, the Contractor's representative name and phone number, the City representative name and phone number, along with any other information requested by the Engineer.

E. Such notices must be prepared and printed by the Contractor, reviewed & approved by the Engineer, and must be served by the Contractor's representative in person to each residence and business within two blocks of the work are in each direction or as directed by the Engineer. Failure of the Contractor to properly serve such notices will be cause for suspension of work until compliance with this requirement is achieved. No extension of time will be allowed to the Contractor for lost time due to his failure to distribute such notices in a timely manner or from suspension of

City of Camarillo GENERAL
CH-5067-2 012000-6

work due to non -compliance. Contractor must document delivery of notices by providing an e- mailed list of locations where notices were delivered including the date and time of completion, by the end of the day of delivery. Contractor must also e-mail a min imum of five clear photos (5- megapixel) showing completion of the delivery and parking restriction signs for each street notified. Contractor must send e-mail to an e-mail address as directed by Engineer.

F. The Contractor is responsible for and must deliver public notification for all phases of the work. The Contractor must submit for approval all notices for content and delivery schedule two weeks prior to actual delivery.

G. Contractor must photo document the following events as they occur to provide photographic evidence of the occurrence along with time and date from the photo and email:
• Completion of delivery of Public Notification
• Posting of Parking Restrictions (include list of locations and time and date of posting)
• Opening of street or lanes to traffic by the required time • CMS placement including massage displayed
• Traffic control checked

Contractor must email a minimum of five (5) clear (5- Megapixel) photos showing the completion of the required item by the required time. Photos must clearly depict completion of the item and must include close-up photos of signs and postings, or other items of work called for. Photos must also include larger scale photos of streets indicating that the entire street posting was completed. Photos of each end of a street must be provided. Contractor must send email to an email address as directed by the Engineer. Emails must include location depicted in the photos.

Photos must be submitted by the Time Limit of the end of each Workday unless an earlier Time Limit is specified.

H. Failure by the Contractor to provide timely and accurate photo documentation of Public Notifications and Posting of Parking Restrictions may result in suspension of the Contractors work by the City. The work will be suspended until the Contractor can demonstrate to the City’s satisfaction that the Public Notifications and Posting of Parking Restrictions can be properly documented. Suspension of the Contractors work by the City will not result in a time extension to the Contract in accordance with General Conditions Section 6.3(d).

I. Full compensation for conforming to the requirements of this section will be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed.

J. Full compensation for conforming to the requirements of this section will be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed.

City of Camarillo GENERAL
CH-5067-2 012000-7

1.07 WORKDAYS AND HOURS
A. No work may be performed on Saturday, Sunday, or holidays unless approved in advance by the Engineer. Holidays are anticipated as follows:

Holiday Hol iday Date:

New Years Day January 1
Martin Luther King Day 3rd Monday in January
Presidents Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 4th
Labor Day 1st Monday in September
Veterans Day November 11th
Thanksgiving Day 4th Thursday in November
Day after Thanksgiving 4th Friday in November
Christmas Eve December 24th
Christmas Day December 25th
Note: If a holiday falls on a weekend, a Saturday holiday will be observed on Friday and a Sunday holiday will be on a Monday. If part or all of a 2-day holiday falls on a weekend, the City will determine which 2 weekdays will be holidays.

No work may be performed in the downtown area or within 2,000- feet of the Camarillo Premium Outlet Center from November 1 to January 1.

No work will be allowed to be performed or be underway on the parade route or parade staging areas of the Camarillo Christmas Parade, on the day of the parade which occurs on a Saturday in December. Contractor shall clean- up work site, restore all surfaces and make full width of the roadway and right of way safe and available for traffic and pedestrians.

No work may be performed the day before or during any special event in the downtown area or that may impact traffic in the downtown area during these special events. Contractor must monitor the City of Camarillo website “Events Calendar” to verify actual dates for special events including the following:

Event E vent
Date:

Fiesta A weekend event in mid-July
Art & Jazz Festival A weekend in August or September
Classic Car Cruise 4 th Friday of each month from April thru September

The holiday and event dates listed above are approximate dates and will vary depending on the year construction occurs. The Contractor is required to obtain and account for the City’s observed holiday dates and special event dates that will impact the project during the course of the Contract.

B. Work shall occur during the following time period:

1. Normal daily work hours are from 8:00 a.m. to 5:00 p.m.

City of Camarillo GENERAL
CH-5067-2 012000-8

C. If the Contractor performs any work or has any site presence outside the hours listed in this section, or on weekends or holidays without prior City approval, the City reserves the right to hire a security service to ensure contractor compliance and associated costs will be the responsibility of the contractor and will be deducted from Pay Estimates due to the Contractor.

D. Contractor shall submit a written request to City for extended work hours for specific portions of work as required for safety and convenience or emergency.

City denial of the Contractor’s request for extended work hours does not warrant an extension of the Contract Time
E. Contractor must reimburse City for costs for overtime inspection associated with project work hours. Costs will include hours in excess of 8-hours per workday shift, hours in excess of 40-hours per work week, and weekend and holiday work when specifically authorized.

F. The Contractor must diligently prosecute the contract work within the allowed number of working days specified in Page 1 of the Bid Proposal, counting from the date stated in the Notice to Proceed. The days to finish the punch list, provided by the City, are included in the working days.

1.08 PERMITS
A. Before beginning work, Contractor must confirm with agencies having jurisdiction that Contractor has obtained all necessary permits and licenses and given all notices.

B. Contractor must apply for, procure, and pay all charges and fees for all other necessary permits and licenses required to perform the work. Contractor is responsible for obtaining all necessary permits (not provided by City), reviewing the conditions and r equirements contained therein, and including the cost of meeting these conditions and requirements in this bid. Contractor shall be responsible for obtaining permit extensions including extensions for 3 months beyond the baseline completion date. The original permits must be submitted to City and Contractor must maintain a copy of these permits at the job site at all times. All provisions of all project permits (including those provided by City and obtained by Contractor) will apply as stated in these Specifications. Contractor must follow the more restrictive of the conditions, as determined by the Engineer, if there is a conflict. Any costs incurred due to compliance with these permits must be included in the contract costs. No additi onal payment will be m ade for such permits.

C. The Contractor shall coordinate with the Engineer and obtain the necessary demolition permits and all other permits required by the City Building and Safety Department.

D. The Contractor shall coordinate with the Engineer after removal of trees and obtain all necessary permits as required by Ventura County Air Pollution Control District.

E. Any work in or affecting Caltrans right-of-way will require a Caltrans double permit, Contractor must apply for and pay for this double permit when necessary.

City of Camarillo GENERAL
CH-5067-2 012000-9

F. Full compensation for conforming to the requirements of this section will be considered as included in the prices paid for the various contract items of work and no additional compensation will be allowed.

1.09 FEES AND FINES
If the City receives a fine or penalty due to the Contractor’s actions or inactions, Contractor will be held responsible for paying such cost. City may deduct such amount from amounts due, or to become due the Contractor.

1.10 REVIEW OF CONTRACT DOCUMENTS AND JOB SITE
A. The Contractor must carefully study and compare each element of the Contract Documents with each other and with information available to the Contractor as furnished by the City. The Contractor will assume all responsibility for deductions and conclusions as to the difficulties in performing the work.

B. The Plans show conditions as they are supposed or believed by the City to exist.

The City does not warrant the completeness or accuracy of such information. It is the Contractor’s responsibility to ascertain the existence of all conditions affecting the cost of work. The Contractor must immediately notify the Engineer of errors, inconsistencies, or omissions discovered. If the Contractor performs any construction activity knowing it involves a recognized error, inconsistency, or omission in the Contract Documents without such notice to the Engineer, the Contractor will assume appropriate responsibility for such performance and will assume responsibility for the cost of correction.

1.11 R IGHT-OF-WAY
A. Coordinate with the City and confirm the Right of Entry/Temporary Construction Easement is in place with adjacent church/school.

B. Attention is directed to Section 2-8 “Right-of-Way” of the Standard Specifications, Section 2.1 and Section 19 “Use of Premises” of the General Conditions/Specifications and these Special Provisions.

C. The Contractor must verify that the acquisition(s) is completed prior to beginning any work outside the public right of way. All cost for remobilization, downtime, etc., due to delays in obtaining the required rights of way, easements, and rights of entry must be included in the lump sum price bid for the various items of work and no additional compensation will be allowed.

D. The Contractor will not be entitled to the exclusive use of any public street or rights- of-way during the performance of the work under the contract, and the Contractor must conduct operations so as not to interfere unnecessarily with business, traffic, pedestrians, and the authorized work of utility companies or other agencies in the street or rights-of-way. Neither the Specifications nor the Plans may be construed to entitle the Contractor to conduct operations within the rights-of-way which are in violation of any local, county, or state ordinance or regulation restricting interference with water courses and drainage channels. The Contractor must take adequate precaution against obstructing storm water flow within the project limits.

City of Camarillo GENERAL
CH-5067-2 012000-10

The Contractor may not deposit excavated materials, store equipment or construction materials within the street.

1.12 SURVEYING
A. Attention is directed to Section 3- 10, "Surveying" of the Standard Specifications, and these Special Provisions. Delete Section 3 -10.1, "General," of the Standard Specifications.

B. Contractor is responsible for all project construction surveying to determine locations of construction, grading and site work. Surveys to determine location of property lines and corners must be supplied by the Contractor. Surveying must be performed by a Land Surveyor or Civil Engineer registered in the State of California to perform these services. The Engineer reserves the right to check Contractor's work at any time during the project. Checks performed by the Engineer will not relieve Contractor of responsibility to properly locate and construct the work in accordance with the Contract Documents. If the Engineer's check of the surveying identifies errors in the survey work, the Contractor must correct such survey work and the cost of the survey check pe rformed by City will be charged to the Contractor and the cost may be deducted from monies due or to become due the Contractor.

C. No lines and/or grades will be set by City or the Engineer. Contractor will be responsible for establishing the lines and grades required for the completion of the work specified in the specifications, on the plans, and in the special provisions.

D. Survey Monument Inventory: Contractor must prepare survey monument inventory of the project site, including any area affected by the work. Such inventory must be prepared by a Land Surveyor or Civil Engineer qualified to perform Land Surveying, licensed in the State of California. Survey monument inventory must be submitted to the Engineer one week prior to beginning any work that may affect a survey monument. Inventory must indicate location, monument description, how the monument is protected, location ties, a statement indicating that the survey monument inventory is a complete listing of survey monuments affected by the work, and must be signed and sealed by the Land Surveyor or Civil Engineer.

E. Existing survey monuments located adjacent to and outside of construction areas must be adequately protected from any damage that may result from Contractor's operations. Contractor must provide location ties to survey monuments in the work zone. Contractor must immediately notify the Engineer if any survey monument in the work area is accidentally disturbed or damaged. All survey monuments and monument wells damaged or displaced by Contractor's operations must be reported to the County Surveyor. Contractor must replace disturbed or damaged survey monuments in accordance with the provisions of the Land Surveyor's Act, Code of the State of California, at Contractor's expense. Prior to relocation or removal of any survey monument, Contractor must contact City for direction, at least 5 working days prior to relocating a survey monument. Contractor must file required survey tie and monument records with the County Surveyor.

City of Camarillo GENERAL
CH-5067-2 012000-11

F. The cost of surveying, staking, and layout is to be included in the various items of work and no additional payment will be allowed.

1.13 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS

A. Attention is directed to Part 4 Existing Improvements, Section 400 “Protection and Restoration” of the Standard Specifications, these Special Provisions, and to Section 02 03 43 “Period Structure Relocating.”
B. Contractor agrees to assume sole and complete responsibility for protection of public and private property in the vicinity of the job site and further agrees to, at Contractor's expense, repair or replace to original condition all existing improvements within or in the vicinity of the job site which are not designated for removal and which are damaged or removed as a result of Contractor's operations.

C. Repair or replacement must be completed within three (3) working days from the date the damage occurred, unless immediate repair or replacement is determined to be necessary by the Engineer. If the Contractor fails to restore existing improvements in a timely manner, within the timeframe specified, the City may complete the work and costs will be deducted from payments due the Contractor.

D. Contractor must coordinate with operations such that damage to newly constructed improvements is avoided. In the event newly constructed improvements, shown on the Contract Documents, interfere with other project work or is necessary for safety or access and must be removed and replaced, the City will only pay for the improvements to be constructed one time. Multiple replacements or work necessary for the convenience of the Contractor will be considered performed at the Contractor’s expense.

E. Existing improvements, visible at the Work or which can be reasonably ascertained by available information to exist, and which interfere with the completion of the Work but which no specific disposition is made on the Plans or Specifications, shall be addressed by the Contractor as follows:

1. Existing improvements which interfere with the completion of the Work shall be removed and replaced, in kind. The exact location and alignment of the replacement shall be confirmed with the Engineer prior to removal and adjustments to the location to conform to the Work shall be made as necessary.

2. The Engineer may determine that the existing improvements are to be removed and not replaced. Removed improvements shall be properly disposed of by the Contractor.

3. The area where existing improvements were removed shall be restored to conform with the Work and match the surrounding area. Restoration shall conform to adjacent improvements.

4. All costs for addressing proposed improvements in conjunction with existing improvements shall be included in the bid.

City of Camarillo GENERAL
CH-5067-2 012000-12

1.14 UTILITY REQUIREMENTS AND POTHOLING
A. GENERAL:

1. Attention is directed to Section 402 “Utilities” of the Standard Specifications (SSPWC), the contract Plans, and these Special Provisions. The Contractor must verify the location, size, and type of all existing utilities prior to construction. Utilities include, but are not limited to; telephone, electricity, gas, fiber -optic cable, cable television lines, traffic signal systems, communication systems, petroleum lines, water, irrigation systems, storm drains and sanitary sewer.

2. When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such work must be included in the Bid for the items of work necessitating such work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience are the Contractor’s responsibility and the Contractor must make all arrangements and bear all costs.

3. The Contractor must obtain all necessary permits and notify the utility agencies at least 48 hours in advance of excavating around any of their facilities. It is the responsibility of the Contractor to coordinate all phases of construction with the various utility companies involved. See APPENDIX A for electrical utility requirements and application for service.

4. The Contractor must notify Underground Service Alert at 811 at least 48 hours prior to any excavation or construction work. Paint indications for underground utilities must be limited to only those areas to be affected. The Contractor must document USA mar kings with photographs or video and must provide a copy of the photographs and video to the Engineer. The Contractor must remove any painting marks that remain after the construction is complete as follows:

5. When placing markings on the pavement or other right- of-way areas to indicate the location of underground facilities, Contractors and/or utility companies are required to use a temporary water-based marking chalk with a visibility life not to exceed (15) working days. Contractor must arrange for markings to be removed as needed. In the event that a Contractor or utility company uses a non-approved marking material, it will be the responsibility of the Contractor to ensure the complete removal of all pavement markings remaining upon completion of the permitted work. If the Contractor fails to properly and completely remove all pavement markings, the City may affect the removal and deduct from payments due or become due the Contractor for both direct and indirect costs as determined by the Engineer.

B. UTILITY VERIFICATION:

1. The location and existence of utilities shown on the plans are approximate and taken from available records. Not all underground utilities are shown on the Plans. The Contractor must verify the location of existing utilities in coordination with District staff, by potholing or other suitable methods, and

City of Camarillo GENERAL
CH-5067-2 012000-13

must take all precautions to protect them whether shown or not. The exact location and identification of all existing utilities must be determined by the Contractor prior to the start of any work.

2. The Contractor must physically locate, verifying horizontal and vertical locations, and map existing underground facilities within the work area that are marked by Underground Service Alert (USA), shown on the drawings or visible in the field. Contractor must protect all such facilities from damage due to construction activities for the duration of the project. In the event any such unknown facilities or substructures should be disturbed or damaged due to the failure of the Contractor’s exercising reasonable care, the Contractor must at once make necessary emergency repair at no cost to and to the approval of the owner. In the event the utility owner requires its own forces or approved vendors to perform such repairs, Contractor must coordinate and cooperate with the utility to complete the repairs. All costs for repairs, staff time, direct and indirect costs, and any costs billed by the utility must be borne by the Contractor and costs may be deducted from payments due or to become due the Contractor. Contr actor is responsible for following all applicable rules and regulations concerning work in the vicinity of underground and/or overhead utilities.

3. All utilities designated on the Plans to be protected in place must be carefully uncovered if located within the lines of excavation and time must be allowed for the Engineer to field check the location of such utilities to make certain that they will not interfere with construction. In the event a utility conflict exists, the City will either arrange for utility owner to relocate the utility or adjust grade and/or alignment of the proposed improvement.

Contractor must allow sufficient time for this utility work and must adjust Contractor’s operation to move to other areas to allow the utility relocation work to occur.

4. In the event any such facility should be disturbed or damaged, the Contractor must at once make repairs to the satisfaction of the owner, or arrange with the owner to make repairs, at no cost to the City. Any delays or reconstruction of improvements resulting from the Contractor’s failure to verify utility locations and depths will be made at the Contractor’s expense.

C. UTILITY COMPANY WORK REQUIREMENTS:

1. Where facilities are shown on the Plans, “To be Relocated by Others,” the City will issue the owner a “Notice to Relocate” or by City agreement with owner, require owner to relocate. Contractor must coordinate and schedule work with the various utilities. Contractor must be familiar with the utility company requirements, scheduling the work with adequate time in advance of needing utilities relocated, protected, installed or removed. In the event difficulties delay relocation, which in the judgment of the Engineer cannot reasonably be foreseen, and require a delay in Contractor’s completion date after all reasonable remedies for keeping contract on schedule have been exhausted by Contractor including, but not limited to flow-charts and critical path scheduling, work simplification, and alternative construction

City of Camarillo GENERAL
CH-5067-2 012000-14

methods, Engineer may allow extra time to the Contractor, but no additional compensation will be allowed.

2. The Contractor must protect facilities shown on the Plans, “To Be Relocated By Others,” in both original and relocated positions and any damage to such facilities must be immediately repaired to the owner’s satisfaction at no cost to the City.

3. Payment: The cost for coordination with the utility companies, providing work areas for utilities, locating facilities including potholing, protecting utility facilities in place, and conforming to the requirements of this section will be considered as included in the prices paid for the various contract items of work involved and no additional compensation will be allowed.

1.15 SUBSURFACE CONDITIONS
A. Where investigations of subsurface conditions have been made by the City with respect to subsurface conditions, utilities, foundation, or other structural designs, and that information is shown in the Plans, it represents only a statement by the City as to the character of materials and general location which have actually been encountered by the City’s investigation. This information is only included for the convenience of Bidders.

B. Investigations of subsurface conditions are made for the purpose of design only.

The City assumes no responsibility with respect to the sufficiency or accuracy of borings or of the log of test borings or other preliminary investigations or of the interpretation thereof. There is no guaranty, either expressed or implied, that the conditions indicated are representative of those existing throughout the Work, or any part of it, or that unanticipated conditions may not occur. When a log of test borings is included in the Plans, it is expressly understood and agreed that such log of test borings does not constitute a part of the Contract. The log of test borings represents only an opinion of the City as to the character of the materials to be encountered, and is included in the Plans only for the convenience of the Bidders.

Making information available to Bidders is not to be construed in any way as a waiver of the provisions of the first paragraph of this Section, and Bidders must satisfy themselves through their own investigations as to conditions to be encountered.

1.16 PRE-CONSTRUCTION JOB SITE VIDEO
A. A minimum of (7) working days prior to start of construction, the Contractor shall video all areas where construction is to take place. Such videos (DVD or other approved media) must be provided to the Engineer before construction commences. These videos will serve as a record of the existing conditions for disputes arising from restoration and should therefore be taken along the line of construction and site access and staging areas at sufficient detail as necessary to clearly depict details of existing conditions.

1. Video must document existing conditions, park property, trees, fencing, equestrian statue, sidewalks, intersections, and all painted curb markings in the project area. The Contractor must also video any unusual conditions

City of Camarillo GENERAL
CH-5067-2 012000-15

encountered during construction that are not already a matter of photographic record.

2. The videos must be on standard flash drives viewable on a computer, taken in high quality color video 1080p HD (1920x1080p) minimum in MP4, AVCHD, MOV or h.264 format. All videos will become the property of the City.

3. All videos must be indexed and catalogued in such a manner that each photographed area is readily identifiable and must also indicate the date and time on which the video was made.

4. In the event damage to existing improvements occurs, the video will be available as a resource to determine existing conditions. In any areas where existing conditions cannot be determined by means of videos, the area must be restored as approved by the Engineer at Contractor’s expense.

1.17 PRE-CONSTRUCTION CONFERENCE
A. A pre -construction meeting will be conducted prior to commencement of construction at a time and place designated by the Engineer. Those attending the meeting must include, but not be limited to, the following:

1. The Contractor and superintendent who will be supervising the work for the duration of the project.

2. The City of Camarillo/Camarillo Sanitary District

3. The Architect

4. Electrical Engineer

5. The Construction Engineer

6. Representatives of affected Utility Companies (SoCal Gas, SCE)

7. Representatives of Permitting Agencies
B. Pre-construction conference will not be scheduled until the following have been submitted:

1. Key Personnel, Telephone Numbers, and Emergency Telephone Numbers

2. Project Schedule

3. Project Phasing Plan

4. Traffic Control Plans

5. Pre-Construction Job Site Video

City of Camarillo GENERAL
CH-5067-2 012000-16

6. SWPCP

7. Soil Management Plan

8. Material haul routes

9. Demolition Waste Recycle Plan/Statement

10. Construction Waste Management Plan

11. Long Lead Item Schedule with Documentation of Order and confirmation numbers
City receives any submittals related to first items of work, and major components required have been procured and are in possession of the WEEKLY SCHEDULE AND MEETINGS A. By Tuesday of each week, the Contractor must prepare and submit a detailed schedule of the work projected for the next three weeks on a daily basis. The Contractor must make revisions as required by the Engineer.

B. The Engineer will conduct a Weekly Project Status Meeting that must be attended by the Contractor, subcontractors, utility companies (as required), and the Engineer. The meeting will have duration of approximately one hour. The meeting will be held on the day, time, and location as determined by Engineer. The purpose of this meeting will be to discuss interfacing work, scheduling, problems, issues, and the like. If not previously submitted, the Contractor must submit the following to the Engineer at the beginning of the meeting:

1. Daily manpower and equipment utilization for the preceding week

2. Projected work for the next three weeks on a daily basis.

C. The Contractor must attend all miscellaneous meetings as requested by the Engineer.

D. Several projects may be ongoing within the limits of the work during the Contract period. The Contractor is required to coordinate the work with other contractors such that both projects can be diligently pursued to their timely completion.

Interfacing work must be shown on the project schedule, and the Contractor will be responsible for meeting that schedule. Contractor must include time for others to perform work within the Work Area and this must be reflected in the Project Schedule. Delays due to interfacing with concurrent projects are considered avoidable and no compensation will be made therefore such delays. Contractor must include in the bid all costs for coordination, scheduling, meetings, staging and the like that result from interfacing with concurrent work.

1. Contractor is responsible for obtaining contract documents including plans and specifications and thoroughly understanding the requirements of and Work called for in the contract documents for the concurrent project. The Contractor must include in the bid all costs for Work called for or indicated

City of Camarillo GENERAL
CH-5067-2 012000-17

in Contract Documents for this project even though shown in the contract documents prepared for concurrent projects.

1.18 CONSTRUCTION SCHEDULE
A. Attention is directed to Section 6 -1.1 “Construction Schedule” of the Standard Specifications, Section 6.1 “Proposed Construction Schedule” of the General Conditions/Specifications and these Special Provisions.

B. The Contractor must update the Construction Schedule as specified in the Standard Specifications, weekly, due on Thursday for the following three weeks, or when directed by the Engineer. Preparation and updating of the Construction Schedule must be performed at Contractor's sole expense.

C. Failure by the Contractor to submit updated or revised Construction Schedules when required may prevent acceptance of progress payment requests by the Engineer until such updated or revised Construction Schedules have been submitted for review and have been accepted by the Engineer.

D. The Construction Schedule must include obtaining all necessary materials and equipment and must reflect completing all work within the specified time in accordance with these Specifications. Contractor must show completion of the project completely filling the Contract time and may not show early completion. In the event the Contractor requests early completion, Contractor must execute a no- cost Contract Change Order that reduces the number of Working Days allowed for completion to conform with such intended completion date.

E. Contractor must include in the schedule detailed information for each operation.

When the project includes multiple areas or job sites, Contractor must include detailed information for each site. When notifications, parking restrictions, shutdowns, or District support are required, such dates must be included in the schedule.

F. Contractor must provide critical path schedules in legible hardcopy format and must also submit schedules with each update in electronic format compatible with MS Project or Primavera, as directed by the Engineer.

G. Full compensation for the required construction schedules and conforming to the requirements of this section will be considered as included in the contract prices paid for the various items of work involved and no additional compensation will be allowed.

1.19 SUBMITTALS
A. In addition to the required submittals and shop drawings of the Standard and Technical Specifications, the Contractor must submit the following shop drawings and/or submittals in adequate detail, including a list of all deviations from the Contract Documents for each item submitted. The following items marked (*) shall be submitted to the Engineer for review at least seven (7) working days prior to the Pre-construction Meeting. All other submittals must be submitted in accordance

City of Camarillo GENERAL
CH-5067-2 012000-18

with the submittal procedures listed below. The Engineer will determine if the specifications are being met for all work including but not limited to the following:

B. GENERAL REQUIREMENTS

1. Key Personnel, Telephone Numbers, and Emergency Telephone Numbers *

2. Project Schedule*

3. Project Phasing Plan*

4. Traffic Control Plans*

5. Pre-Construction Job Site Video*

6. SWPCP*

7. Soil Management Plan*

8. Material haul routes*

9. Demolition Waste Recycle Plan/Statement*

10. Construction Waste Management Plan*

11. Long Lead Item Schedule *

12. Submittals:
a. Switchgear shop drawings
b. Concrete design mixtures
c. Steel reinforcement shop drawings
d. Concrete unit masonry reinforcing steel shop drawings e. Tile
f. Steel gate shop drawings
g. Paint
i. Samples
ii. Paint system locations
iii. VOC content
h. Signage
i. Document style, lettering, dimensions, materials
ii. Sign material
iii. Sign samples
iv. Sign manufacturer's installation instructions
i. Electrical
i. C lose-out Facility EPM program binders
ii. Close-out operation and maintenance data
iii. Software and firmware operational documentation

City of Camarillo GENERAL
CH-5067-2 012000-19

iv. Software

j. Low Voltage sustainable design submittals

k. Grounding and Bonding for Electrical Systems
i. Product data
ii. Shop drawings
iii. Field quality control reports
iv. Sustainable design submittals
l. S leeves and Sleeve Seals for Electrical raceways product data

m. Identification for Electrical Systems
i. Product data
ii. Samples
iii. Identification schedule

n. Low Voltage Switchgear
i. Dedicated design submittal
ii. System power riser diagrams
iii. Maintenance material submittals – spare parts and tools

o. Panelboards
i. Product data
ii. Shop drawings
iii. Panelboard schedules
iv. Maintenance material submittals – spare parts and tools v. Warranty

p. Wiring Devices
i. Product data
ii. Shop drawings
iii. Samples
iv. Field quality-control reports
v. Manufacturer's instructions
vi. Sample warranties
vii. Record floor plan drawings
viii. M aintenance materials submittals – extra stock and special tools ix. Warranties

q. General Use Electrical Switches
i. Product data
ii. Samples
iii. Field quality-control reports
iv. Manufacturer's instructions
v. Record floor plan drawings
vi. Maintenance material submittals

r. General Grade Duplex Straight-Blade Receptacles
i. Product data

City of Camarillo GENERAL
CH-5067-2 012000-20

ii. Shop drawings/diagrams
iii. Samples
iv. Field quality-control reports
v. Manufacturer's instructions
vi. Sample warranties
vii. Close-out Warranty documentation
viii. Warranties
ix. Close-out record floor plans

s. L ocking Receptacles
i. Product data
ii. Samples
iii. Field quality-control reports
iv. Manufacturer's instructions
v. Sample warranties
viii. Warranties

t. Enclosed Switches, Circuit Breakers
i. Product data
ii. Shop drawings
iii. Maintenance material spare parts
iv. Warranties

u. Lighting
i. Product data
ii. Sustainable design product data
iii. Samples
iv. Shop drawings
v. Manufacturer's published instructions
viii. Field reports
ix. Warranty documentation
x. Maintenance material
xi. Warranties

v. Hot asphalt paving
i. Product data
ii. Job-mix designs
iii. Material certificates
iv. Log of placement

w. Concrete paving
i. Product data
ii. Design mixtures

x. Tree protection
i. Arborist protection certification
ii. Certified arborist
iii. I ndicate any damaged trees
C. EQUIPMENT

City of Camarillo GENERAL
CH-5067-2 012000-21

1. Construction Equipment

2. Manufacturer Certifications and Testing Reports

3. Product and Material Specifications
D. SITE WORK

1. Emergency Response and Access Plan *

2. Log of Work-Related Injuries and Illnesses *

3. Job Hazard Analysis *

1.20 SUBMITTAL PROCEDURES
A. Where possible, the Contractor shall submit electronically in PDF format compatible with Adobe Acrobat. Files less than 5 MB in size may be submitted to the Owner’s Representative via email. Files larger than 5 MB shall be submitted by means of an FTP server, USB flash drive, external hard drive, or other method approved by Owner’s Representative. Scans shall be at a resolution necessary for legibility and shall be in color when necessary for clarity. Wherever called for in the Contract Documents or where required by the Engineer, the Contractor must furnish to the Engineer for review four (4) physical copies of each submittal.

B. Make submittals promptly in such a sequence as to cause no delay in the work.

Schedule submissions a minimum of twenty (20) working days before reviewed and approved submittals will be needed.

C. Each submittal item must be individually numbered, logged, and must identify the specification section that relates to item being submitted so that approved and rejected submittals can be tracked.

D. Each submittal shall have a transmittal form including the date, project name, project number, submittal number, submittal revision, and submittal content.

1. Each submittal shall be assigned a unique number and numbered sequentially. Resubmittals shall bear an alphanumeric system denoting the subsequent resubmittal of the original.

2. Every page in a submittal shall be numbered in sequence and shall be collated.

3. Where product data from a manufacturer is submitted, clearly mark which model is proposed with all pertinent data, capacities, dimensions, clearances, diagrams, controls, connections, anchorage, and supports.

Present a sufficient level of details for assessment of compliance with the contract documents. Extraneous information should not be included in submittals.

City of Camarillo GENERAL
CH-5067-2 012000-22

4. Disorganized submittals that do not meet all requirements will be returned without review.

E. At the time of each submission, give Engineer specific written notice of each variation that the submittal may have from the requirements of the Contract Documents. If a variation is identified that was not brought to the attention of the Engineer, correction will be at the Contractor’s expense.

F. The Engineer will have a minimum of (10) working days to review each submittal, except were specified differently in these special provisions. It is the responsibility of the Contractor to organize submittals in order of importance and need.

Resubmittals of submittals will be reviewed and returned in the same review period as for the original submittal. It is considered reasonable that the Contractor shall make a complete and acceptable submittal by the second submission of a submittal item. The Owner’s Representative reserves the right to withhold monies due the Contractor to cover costs of any review beyond the second submittal.

G. Only one submittal will be reviewed for an item and Contractor may not submit multiple shop drawings from multiple vendors for the same item.

H. Engineer’s review will be only for conformance with the design concept of the project and for compliance with the information given in the Contract Documents, not extending to means, methods, techniques, sequences, or procedures of construction (except where indicated or required by the Contract Documents) nor to safety precautions or programs incident thereto. Submittals processed by Engineer do not become Contract Documents and are not Change Orders.

I. Delays caused by the need for re-submittal or replace unaccepted “or equal” items will not constitute a basis for claim.

J. No substitutions will be considered for products determined to be a sole source as noted in the Notice Inviting Bids. For all else, the following applies:

1. In the event that an item is called for by a specific product or trade name, Contractor will have five (5) working days after the bid opening for submission of data substantiating a request for a substitution of “an equal” item. In the event Contractor furnishes any “or equal” material more expensive than that specified in the bid form, the difference in cost of such material so furnished will be borne by Contractor under Public Contract Code section 3400.

2. “Or equal” products may be accepted by the Engineer upon submittal of the following information:
a. Product Date Design Criteria
b. Physical Properties Limitations of Process
c. Material Specifications List of Previous Projects
d. Installation Specifications Size of Completed Projects

City of Camarillo GENERAL
CH-5067-2 012000-23

e. Testing Methods List of Current Projects
f. Third Party Test Data
g. Size of Current Projects
h. References (All references must include current names and telephone numbers).
i. List of all deviations from the specifications or referenced product or materials.
j. Additional testing may be required, and all costs for testing will be borne by Contractor.

K. City reserves the right to modify the procedures and requirements for submittals, as necessary to accomplish the specific purpose of each submittal. Direct inquiries regarding the procedure, purpose, or extent of any submittal to the Engineer.

L. Repetitive Review

1. Shop drawings and other submittals will be reviewed no more than twice at the City’s expense. All subsequent reviews will be performed at times convenient to the Engineer and at the Contractor’s expense, including but not limited to consultant costs, staff charges, overhead, and other related expenses. Contractor shall reimburse the City for such costs, and City may deduct these costs from amounts due or to become due the Contractor.

Submittals are required until approved.

2. Any need for more than one resubmission, or any other delay in obtaining Engineer’s review of submittals, will not entitle Contractor to extension of the Contract Time.

1.21 OPERATION AND MAINTENANCE MANUALS
A. O&M Manual submittals shall be furnished for all equipment, individual subsystems of complete assemblies, and notable materials. Manuals shall be organized into separate electronic files, shall be formatted to allow word search, and shall include:

1. List of equipment furnished with name, address, and telephone number of each vendor.

2. Order number, model, and serial number.

3. Blue line prints or reviewed shop drawings and diagrams of all systems.

4. Certified equipment drawings or reviewed shop drawing data clearly marked for equipment furnished.

5. Complete operating and maintenance instructions for each and every item of equipment, setting forth detailed procedures for starting, stopping,

City of Camarillo GENERAL
CH-5067-2 012000-24

operating, and maintaining the entire system as installed. Include schedule of recommended maintenance intervals.

6. Complete parts list of replaceable parts, their part numbers, and the name and address of their nearest vendor.

7. Copy of manufacturer’s equipment guarantees and warranties.

8. Equipment data sheets summarizing the equipment furnished and the manufacturer’s maintenance instructions and recommendations and the frequency/interval.

1.22 LUMP SUM BID ITEMS
The Contractor must submit a detailed schedule of values breakdown for all lump sum bid items. The breakdown of items must be submitted to the Engineer for approval and the level of detail will be as determined appropriate by the Engineer. The schedule of values must be submitted to the Engineer prior to the first progress payment request and the progress payment will not be reviewed without approved schedule of values for all Lump Sum bid items. The schedule of values will be used as a basis for determining appropriate monthly progress payment amounts for lump sum bid items. The schedule of values must equal, in total, the lump sum bid item cost and be in such form and sufficiently detailed to satisfy the Engineer that it correctly represents a reasonable apportionment of the lump sum.

1.23 DAILY REPORT
A. The Contractor must complete a Daily Report indicating manpower, major equipment used and on standby (itemized separately), subcontractors, materials used, and similar items involved in the performance of the Work. The Daily Report must be completed on forms prepared by the Contractor and acceptable to the Engineer and must be submitted to the Engineer prior to construction on the subsequent workday.

B. Contractor must supply daily reports to the inspector at the start of work on a daily basis. If the Contractor fails to provide daily reports for 2 or more working days during the scheduled work week, then a Stop Work Notice will be issued, and progress payments will not be processed until all paperwork is current. Contract period will continue to be in force while the Stop Work Notice is in effect.

1.24 TESTING AND INSPECTION
A. Attention is directed to Section 3- 5 “Inspection” of the Standard Specifications, Section 9.3 “Inspection”, Section 10.8 “Tests and Inspections”, and Section 10.10 “Compaction Tests” of the General Conditions/ Specifications and these Special Provisions.

B. It is the responsibility of the Contractor to facilitate sampling to be used for testing purposes. Costs for failed tests and retesting necessary because of the Contractor’s failure to comply with specification requirements will be borne by the Contractor.

City of Camarillo GENERAL
CH-5067-2 012000-25

C. Contractor must notify the City Public Works Department 72 hours in advance of commencing construction at (805) 388-5380.

1.25 NON-WORKING FOREMAN
A. The Contractor must provide a non-working foreman on-site for all phases of work for the duration of the Project. The non-working foreman must be available to the Engineer at all times. Failure to supply a non- working foreman at any time during the Contract Period during work hours can result in an immediate Stop Work Notice until the Contractor provides or replaces the non -working foreman. The Contract Period will remain in force and continue.

B. All work completed during an absence of a non- working foreman will be Non- Complying Work per General Condition 11.2. Any costs incurred by the City in dealing with issues resulting from work performed by the Contractor when a non- working foreman was not available will be deducted from payments due to Contractor. The City reserves the right to have the Contractor remove and replace non-complying work in accordance with General Condition 11.4 at no additional cost to the City.

C. The non-working foreman must be in possession of a working cellular telephone and must be available to communicate with the Engineer 24-hours per day.

1.26 RESPONSIBILITY FOR JOB SITE CONDITIONS
A. Contractor agrees that, in accordance with generally accepted construction practices, Contractor will be required to assume sole and complete responsibility for job site conditions during the course of construction of this Project including safety of all persons and property, and that this requirement will apply continuously and will not be limited to normal working hours. Contractor further agrees to defend, indemnify and hold the City and the City’s design and construction observation professionals harmless from all liability and claims, real or alleged, in connection with the performance of work on this Project.

B. The Contractor must make field measurements and verify field conditions and must carefully compare such field measurements and conditions and other information known to the Contractor with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered must be reported to the Engineer immediately by telephone and in writing. When conditions are encountered which, in the opinion of the Engineer, require temporary suspension of work for design modifications or for other determinations to be made, the Contractor must move to other areas of work until such determinations are made at no cost to the Owner. No additional compensation will be allowed by reason of such temporary suspension of a portion of the Work, or modifications to work.

Appropriate extension of time for completion may be allowed where justified in the opinion of the Engineer. If articles having archeological significance are identified, the Contractor must suspend work to allow evaluation by the Engineer.

C. Provide and install non-skid steel plates at open trench excavations at the end of workday. Plates on arterial streets must be flush with adjacent pavement surface and secured as directed by Engineer in accordance with CALTRANS TR -0157

City of Camarillo GENERAL
CH-5067-2 012000-26

Method 1. Plates on other streets may be placed on pavement with temporary transitions as directed by Engineer in accordance with CALTRANS TR -0157 Method 2.

1.27 GENERAL SAFETY REQUIREMENTS
A. Contractor must do whatever work is necessary for safety and be solely and completely responsible for conditions of the job site, including safety of all persons (including employees) and property during the Contract period. Safety provisions must conform to Federal and State Departments of Labor Occupational Safety and Health Act (OSHA), and other applicable Federal, State, County and local laws, ordinances, codes, requirements set forth herein, and regulations that may be specified in other parts of these Contract Documents. Contractor must do all work necessary to protect the general public from hazards, including, but not limited to, surface irregularities or un- ramped grade changes in vehicular travel ways (including but not limited to streets, roads and driveways), pedestrian sidewalks or walkways. Barricades, lanterns, and proper signs must be furnished in sufficient amount to safeguard the public and the work. This requirement applies continuously and is not limited to normal working hours.

B. Contractor must develop and maintain for the duration of the Contract, a safety program that will effectively incorporate and implement required safety provisions.

The Contractor must appoint a qualified employee who is authorized to supervise and enforce compliance with the safety program.

1.28 CONSTRUCTION WASTE MANAGEMENT AND RECOVERABLE MATERIALS A. With the exception of those materials indicated in the plans and specifications, (the equestrian statue; and donor bricks and plaques, the District refuses right to recoverable materials from this Project. No recoverable materials will be collected or preserved from the demolition or construction activities. The Contractor must dispose of all recoverable materials in a proper and legal manner. The Contractor must include in the bid all costs for disposal. The District reserves the right to modify its decision regarding refusal up to the point in time the materials are removed from the site.

1.29 PROJECT APPEARANCE AND CLEANUP
A. The Contractor must keep the site clean, control dust from construction operations, provide sanitation for workers, and control air pollution from construction operations. Broken concrete and debris developed during demolition, clearing and grubbing must be disposed of concurrently with its removal. Broken concrete, debris, and construction materials that remain on the job site overnight will be subject to Liquidated Damages for Failure to Perform as specified in these Special Provisions.

B. Weeds, trash, and debris must be removed from the work site regularly and when directed by the Engineer. Graffiti must be removed within 24- hours of the graffiti appearing and when directed by the Engineer. All graffiti within the project limits must be removed. Contractor must submit method of removal to the Engineer for

City of Camarillo GENERAL
CH-5067-2 012000-27

approval prior to graffiti abatement. Stickers, paint, and other forms of graffiti must also be removed.

C. Upon completion of the Work and before the final inspection, the Contractor must at the Contractor’s own cost satisfactorily dispose of, or cause to be disposed of, all plant, buildings rubbish, waste products, debris, unused materials, concrete forms, and other equipment used during the construction of the improvements. In the event that the Contractor fails to perform this final cleanup, the City may remove and/or dispose of the articles or materials at the Contractor’s expense.

D. SWPCP, failure to perform and document the required daily inspections shall result in a daily liquidated damage of $250/calendar day.

1.30 DIFFERING CONDITIONS

A. Contractor may not willfully install work as shown on the drawings when it is obvious in the field that obstructions, grade differences or differences in the area dimensions exist that might not have been considered or observed during design.

Contractor must promptly notify the Engineer and the agency having jurisdiction by telephone and in writing upon discovery of, and before disturbing, any physical conditions differing from those represented by approved plans and specifications.

In the event this no tification is not performed, the Contractor must assume full responsibility for necessary revisions.

1.31 CHANGES IN WORK

A. Attention is directed to Section 3- 1 “Changes Requested by the Contractor,” Section 3-2 “Changes Initiated by the Agency,” and Section 3 -3 “Extra Work” of the Standard Specifications and these Special Provisions.

B. The City will issue a Contract Change Order (CCO) if a change to the Total Contract Price or Contract Time is necessary. The Contractor will not be entitled to any adjustments in either Contract Time or Total Contract Price for changes performed without written direction from the City. Adjustments in Contract Time or Total Contract Price for changes performed will not be made until a Contract Change Order is approved. The labor rates paid for time and material work will not be higher than the applicable prevailing wage rate for the worker classifications required for the work. The Contractor shall prepare a time impact justification for consideration for any adjustments in Contract Time. The time impact justification accepted by the City will be used to adjust the Contract Time in the CCO.

C. If the Contractor requests an extension of time as a part of a contract change order, Contractor must provide a revised construction schedule and written justification for the extension of time, at the time of Contractor’s request for the change order.

The justification must include an analysis for the time requested, showing how the change affects the critical path/controlling item of work and must be provided to the Engineer in editable electronic format compatible with MS Project, in addition to a legible hardcopy.

D. The sections that follow replace sections of like number in the Standard

City of Camarillo GENERAL
CH-5067-2 012000-28

Specifications for Public Works Construction (SSPWC).

3-2.2.2 Increases of More Than 25 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 25 percent, payment for the quantity in excess of 125 percent of the Bid quantity will be made on the basis of a decrease in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or in the event mutual agreement cannot be reached, on the basis of Extra Work per 3- 3 or at the Contract Unit Price at the Agency’s option.

The Extra Work per 3 -3, basis of payment, does not include fixed costs. Fixed costs will be deemed to have been recovered by the Contractor through payment for 125% of the Bid quantity at the Contract Unit Price.

3-2.2.3 Decreases of More Than 25 Percent. The District, at its sole discretion, may decrease the quantities of the items of work to be completed under this contract. In such an event, payment will be made based upon the decrease in quantity at the Contract Unit Price, except for Major Bid Items as described below.

A Major Bid Item is defined as a single Contract item constituting 10% or more of the original Contract Price. In the case of a decrease in a Major Bid Item, the following will apply:

Should the actual quantity of an item of work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less than 75 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per 3- 3; however in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 75 percent of the Bid quantity at the Contract Unit Price.

1.32 EXTRA WORK
A. Subsection 3 -3.2.2.1, Labor rates used for Extra Work shall be at applicable prevailing wage rates plus allowable markups per this section.

B. Subsection 3-3.2.3, “Markup” of the Standard Specifications (SSPWC) is deleted in its entirety and replaced by the following:

3-3.2.3 Markup.

1. Work by Contractor. When extra work is to be paid for on a force account basis, use the CALTRANS Equipment Rental Rate Book for equipment rental rates. The following percentages will be added to the Contractor’s costs and will constitute the markup for all overhead and profits:

a. Labor………………………………….35

City of Camarillo GENERAL
CH-5067-2 012000-29

b. Materials……………………………...15
c. Equipment Rentals…………………..15

The markup percentages above will reimburse the Contractor for all additional costs, and no other additional payment will be made by reason of performance of the extra work.

2. Work by Subcontractor. When extra work to be paid for on a force account or lump sum basis is performed by a subcontractor, the markup established above in 3-3.2.3(a)“Work by Contractor” will be applied to the subcontractor’s actual cost of such work. An additional markup of ten (10) percent of the subcontracted portion of the extra work may be added by the Contractor. The markup will constitute the markup for all overhead and profit for the Contractor on extra work done by the subcontractor, and no other additional payment will be made.

3. Equipment Rental rates will be determined using CALTRANS Labor Surcharge and Equipment Rental Rates in effect at the time the work is performed.

4. The labor rates paid by the City for (time and material) Force Account work will be at the applicable prevailing wage rate for the worker classifications required for the work plus applicable mark-ups described in this section.

1.33 FINAL INSPECTION AND PUNCHLIST
A. Attention is directed to Section 11 “Acceptance of Work” of the General Conditions/Specifications and these Special Provisions.

B. Substantial Completion is defined as completion of all items, as determined by the Engineer and for the full beneficial use and enjoyment of the Work as required in the Contract Documents. Project shall be deemed Substantially Complete after 355 working days. Each day after the 355 working days will be subject to Liquidated Damages as detailed on the bid proposal.

C. The Contractor shall notify the Engineer 10 working days prior to seeking Substantial Completion. The Engineer will create a punch list of deficient items that need to be corrected by the Contractor. The Engineer reserves the right to add items to the projects punch list as deemed necessary. All punch list items must be completed with sufficient time for Engineer inspection prior to Substantial Completion. Liquidated Damages as noted on Page 1 of the Bid Proposal for Substantial Completion will continue until all items affecting Substantial Completion as noted in 2000-33B are completed.

D. The Contractor will be assessed Liquidated Damages as noted on Page 1 of the Bid Proposal for any Work items remaining after Substantial Completion until all remaining Work in the Contractor Documents is completed.

City of Camarillo GENERAL
CH-5067-2 012000-30

1.34 CLAIMS BETWEEN CITY AND CONTRACTOR
A. Attention is directed to Section 12, “Claims between City and Contractor”, of the General Conditions/Specifications.

1.35 CONSTRUCTION AS BUILT DRAWINGS
A. The Contractor must maintain a complete and accurate record of all changes of construction from that shown in these plans and specifications for providing a basis for construction as built drawings. These drawings must be maintained on- site during the course of construction and updated monthly, at minimum.

B. The Contractor must use a job set of contract drawings, clearly labeled “Construction As Built Drawings,” to record all changes in construction.

Completely, accurately, and legibly mark the job set of as-built drawings in red ink to record actual construction. Use additional copies of prints, if necessary, to ensure legible recording of data and date all entries. Call attention to the entry by drawing a “cloud” around the area affected. In case of overlapping changes, use different colors for each change. Maintain consistent color coding throughout the drawings.

C. The Contractor must submit a copy (11x17 or full size) of the updated construction as built drawings in progress with each progress payment to document the status of the drawings. Progress payments may not be processed until acceptable drawings are submitted. The Contractor must submit a complete set of original construction as built drawings to the Engineer 10 days after final inspection along with a letter declaring that other than these noted changes on the as built drawings, “the Project was constructed in conformance with the Contract Documents.” Each plan sheet must be marked “As Built” and signed by the Contractor. The Contractor must provide this set of as built drawing and letter prior to processing of the final pay estimate.

D. Full compensation for recording construction changes and furnishing the Construction As-Built Drawings is considered included in the prices paid for the various bid items of work and no additional compensation will be allowed.

1.36 CLOSEOUT PROCEDURES
A. Attention is directed to Section 11 “Acceptance of Work” of the General Conditions/Specifications and these Special Provisions.

B. Contractor must submit closeout submittals upon completion of work, including completion of punch list items, and at least seven (7) days prior to application for final payment, including, but not limited to the following:

1. Evidence of compliance with requirements of governing authorities.

2. Project record documents.

3. Operations and maintenance manuals.

City of Camarillo GENERAL
CH-5067-2 012000-31

4. Keys, spare parts, remotes and other required devices.

5. Warranties and bonds including an Increase Rider in the amount of final contract.

6. Evidence of payment and release of liens as outlined in conditions of the contract.

7. Release of claims as outlined in conditions of contract.

8. Survey record documents.

9. Certification of final completion.

1.37 REGULATORY REQUIREMENTS
A. CEQA MONITORING AND MITIGATION REQUIREMENTS:

1. The City has conducted an environmental review. The Contractor shall comply with specific permit requirements including CEQA monitoring and mitigation requirements. The Contractor shall obtain and pay for all additional permits, licenses, and inspection fees necessary to complete installation in accordance with the requirements of the local, state, and federal governing jurisdictions and with the requirements of CEQA mitigation.

2. General provisions for the CEQA monitoring and mitigation requirements are included in APPENDIX C of these Contract Documents and are an integral part of the Contractor’s scope of work.

3. General contractor to furnish all labor and materials necessary and perform other related work as necessary to complete this scope of work; all in accordance with the Standard Specifications, general conditions, specifications, plans, and these special provisions.

4. ADDITIONAL CEQA AND AGENCY EVIRONMENTAL REQUIREMENTS

a. AESTHETICS

i. The Contractor shall incorporate light shields onto all lighting fixtures used during nighttime construction to minimize spillover lighting. Lighting shall be directed downward and away from adjacent properties and roadways.

b. MIGRATORY BIRD TREATY ACT AND CALIFORNIA DEPARTMENT
OF FISH AND WILDLIFE CODE 3503

i. No physical disturbance of vegetation, operational structures (e.g., inlet/outlet towers, overhangs, etc.), buildings, or other potential habitat (e.g., open ground, gravel, construction equipment or vehicles, etc.) that may support nesting birds protected by the Migratory Bird Treaty Act and California Fish and Game Code 3503

City of Camarillo GENERAL
CH-5067-2 012000-32

shall occur in the breeding season, except as necessary to respond to public health and safety concerns, or otherwise authorized by the Engineer. The breeding season extends from February 1 through August 30.

1. If nesting habitat must be cleared or project activities must occur in the vicinity of nesting habitat within the breeding season as defined above, a qualified biologist will perform a nesting bird survey no more than five days prior to clearing or removal of nesting habitat or start of project activities.

2. If active nests for sensitive species, raptors and/or migratory birds are observed, an adequate buffer zone or other
avoidance and minimization measures, as appropriate, may be established, as identified by a qualified biologist and approved by the Engineer. The buffer will be clearly marked in the field by the Contractor, as directed by the Engineer, and construction or clearing will not be conducted within this zone, until the young have fledged and are no longer reliant on the nest.

3. A qualified biologist will monitor active nests or nesting bird habitat within or immediately adjacent to project
construction areas and the Engineer will provide necessary recommendations to the Contractor to minimize or avoid
impacts to protected nesting birds.

4. If implementation of avoidance and minimization measures is not feasible, the qualified biologist responsible for monitoring will be empowered to temporarily halt
construction activities, until the young have fledged and are no longer reliant on the nest or biological monitoring
indicates that construction can proceed with no impacts to the nest and/or young. Such a halt to activities will incur no additional cost to the City.

c. AIR QUALITY / CEQA

i. All construction equipment greater than 50 horsepower shall meet the emissions requirements for Tier 4 EPA-rated engines and/or be alternatively (non -diesel) fueled as feasible. Where Tier 4 and alternative fuel is not feasible, all construction equipment greater than 50 horsepower shall meet tier 3 EPA -rated engine
requirements and incorporate a level 3 particulate filter. All construction equipment less than 50 horsepower shall be alternatively (non- diesel) fueled. Copies of the anticipated construction fleet shall be provided to the City Project Engineer prior to the start of construction. During construction, copies of the equipment certifications shall be kept on the project site for inspection purposes.

d. AIR QUALITY/VENTURA COUNTY AIR POLLUTION CONTROL

DISTRICT

City of Camarillo GENERAL
CH-5067-2 012000-33

i. Construction Equipment

1. Purpose: In order to ensure that ozone precursor and particulate emissions from diesel- powered mobile
construction equipment are reduced to the greatest amount feasible.

2. Requirement: The Permittee shall comply with the
provisions of all applicable California State Laws and APCD Rules and Regulations regarding portable construction
equipment and construction vehicles.

3. Documentation: The project applicant shall ensure
compliance with the following State Laws and APCD
requirements:
a. Construction equipment shall not have visible emissions greater than 20% opacity, as required by APCD Rule 50,
Opacity.
b. All portable diesel- powered equipment over 50 BHP
shall be registered with the State’s Portable Equipment Registration Program (PERP) or an APCD Portable
Permit.
c. Off-Road Heavy -Duty trucks shall comply with the
California State Regulation for In- Use Off-Road Diesel Vehicles (Title 13, CCR §2449), the purpose of which is to reduce NOx and diesel particulate matter exhaust
emissions.
d. On-Road Heavy -Duty trucks shall comply with the
California State Regulation for In- Use On-Road Diesel
Vehicles (Title 13, CCR §2025), the purpose of which is to reduce NOx and diesel particulate matter exhaust
emissions.
e. All commercial on-road and off-road diesel vehicles are subject to the idling limits of Title 13, CCR §2485,
§2449(d)(3), respectively. Construction equipment shall not idle for more than five (5) consecutive minutes. The idling limit does not apply to:
i. idling when queuing;
ii. idling to verify that the vehicle is in safe operating condition;
iii. idling for testing, servicing, repairing or diagnostic purposes;
iv. idling necessary to accomplish work for which the
vehicle was designed (such as operating a crane);
v. idling required to bring the machine system to
operating temperature,
vi. idling necessary to ensure safe operation of the
vehicle.

City of Camarillo GENERAL
CH-5067-2 012000-34

It is the Permittee’s responsibility to have a written idling policy that is made available to operators of the vehicles and equipment and informs them that idling is limited to 5
consecutive minutes or less, except as exempted in
subsection e. above.

4. The following are recommended emission reduction
measures for construction equipment and vehicles:
a. Diesel powered equipment should be replaced by
electric equipment whenever feasible.
b. Maintain equipment engines in good condition and in
proper tune as per manufacturer’s specifications.
c. Lengthen the construction period during smog season
(May through October), to minimize the number of
vehicles and equipment operating at the same time.
d. Use alternatively fueled construction equipment, such as compressed natural gas (CNG), liquefied natural gas
(LNG), or electric, if feasible.
e. Use of Tier 3 and Tier 4 off-road construction equipment shall be used, if feasible.

END OF SECTION 012000 – GENERAL

City of Camarillo MOBILIZATION
CH-5067-2 012001-1

SECTION 012001 - MOBILIZATION

1.01 GENERAL REQUIREMENTS
A. Mobilization work will include all mobilization, demobilization, bonds, and insurance, utility locating, coordination with City staff, preparatory and operations work necessary to provide for bonds, insurance, required permits and fees, submittals, shop drawings, project phasing, multiple move- ins and move- outs required to prosecute the work, supervision, survey, coordination and concurrent work with other contractors, meetings, preparing “as -built” plans or record drawings, movement of personnel, equipment , supplies, and incidentals to and from the project site; the establishment of all other facilities necessary for work on the project; for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items of work at the project site; and work and improvements called for or implied by the Contract Documents, which are not included in the other bid items but are required to complete the Work and Special Provisions.

B. General contractor to furnish all labor and materials necessary and perform other related work as necessary to complete this scope of work; all in accordance with the Standard Specifications, general conditions, specifications, plans, and these special provisions.

END OF SECTION 012001 – MOBILIZATION

City of Camarillo MEASUREMENT AND PAYMENT
CH-5067-2 012003-1

SECTION 012003 - MEASUREMENT AND PAYMENT

1.01 MEASUREMENT
A. Measurement will be in accordance with Standard Specification unless otherwise specified.

Bid Item List Abbreviations
Abbreviation Meaning
CF cubic foot
CY cubic yard
EA each
(F) final pay item
GAL gallon
ELT extra long ton
HR hour
LB pound
LF linear foot
LS lump sum
MO month
SF square foot
SY square yard
TN 2,000 pounds

B. When an item of work is designated as (F) in the bid schedule, then the item shall be a final pay item for payment purposes only. For a final pay item, payment shall be based on the quantity shown in the bid schedule for that item, regardless of the actual quantity used, unless the item quantity is changed by the Engineer.

1.02 PAYMENT
A. Payment for the various items of the Bid Schedule, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles, and for all labor, operations, and incidentals appurtenant to the items of work being described, as necessary to complete the various items of work as specified and shown on the drawings, including all appurtenances thereto complete and in place, and including all costs of compliance with the regulations of public agencies having jurisdiction.

B. Please refer to Section 012005 Compensation.

END OF SECTION 012003 – MEASUREMENT AND PAYMENT

City of Camarillo COMPENSATION
CH-5067-2 012005-1

SECTION 012005 - COMPENSATION

BID ITEMS

The following Bid Schedule Items, designated as Base Bid Item Number 1 through Number 9, comprise the work described in the Contract Documents.

Bid Item No. 1 – MO BILIZATION, BONDS, AND INSURANCE

A. Specification References: 012001
B. Measurement and Payment: Payment for Mobilization, Bonds, and Insurance shall be made at the Contract Lump Sum price.

C. This price will be considered full compensation for the furnishing of all materials and f
or all labor, bonds, insurance, permit fees, equipment, tools, and incidentals necessary to complete the item. Bid item shall not exceed 10% of total bid amount.

A 25% payment of the lump sum total will be paid with the setting of the generator on the pad. The remaining 75% will be paid incrementally over the life of the Contract where these subsequent payments will be based on the percentage of the Contract Time completed to date.

Bid Item No. 2 – CLE ARING AND GRUBBING

A. Specification References: 311100, 312000 , 329500
B. Measurement and Payment: Payment for Clearing and Grubbing, including site clearing, tree removal, and tree protection shall be made at the Contract Lump Sum price listed in the Bid Schedule.

C. Compensation and progress payment shall be made as agreed to by the City on t
he basis of the percentage of completed Work on this bid item. This price shall include full compensation for furnishing all labor, tools, materials, hazard material removal and disposal, debris removal and disposal, transportation, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

City of Camarillo COMPENSATION
CH-5067-2 012005-2

Bid Item No. 3 – STORMWATER POLLUTION CONTROL PLAN

A. Specification References: 015723

B. Measurement and Payment: The Contractor shall be paid for the work of preparing, implementing, inspecting, maintaining, and removing the Stormwater Pollution Control Plan at the Contract Lump Sum price listed on the Bid Schedule. In addition, failure to perform and document the required daily inspections shall result in a daily liquidated damage of $250/calendar day. This liquidated damage shall be in addition to any other liquidated damage. The imposition of liquidated damages shall not relieve the Contractor of any obligations of these project requirements.

Pay
ment for the work involved under the bid item for the Stormwater Pollution Control Plan may be made on a partial payment system based on the completion of the following stages of work:

WORK DESCRIPTION PAYMENT
Develop Plan 10% of Bid Price
Initial Plan Implementation 10% of Bid Price
Removal of BMPs (at Completion) 10% of Bid Price
Inspection & Maintenance of SWPCP 70% of Bid Price

Payment for the SWPC P shall include all the labor, materials, equipment, and incidentals for preparing, maintaining, and updating a SWPCP and complying with all provisions including maintenance and updating of BMPs throughout construction, as specified herein.

Fines and penalties from regulatory agencies levied against the City as a result of the Contractor’s work, including actions or inactions shall be the responsibility of the Contractor and may be deducted from payments due or to become due the Contractor.

Bid Item No. 4 – CO

NSTRUCT CMU ENCLOSURES AND CONCRETE PADS

A. Specification References: 024119, 031000, 032000, 033000, 037000 , 042200, 076220, 055000, 081110, 092400, 093113, 099113, 265619, 311100, 312000, 321216, 321313, 321313A

B. Measurement and Payment: P ayment for Pad, Generator, Gates, Sidewalk , and Access Ramp shall be made at the Contract Lump Sum Price for constructing the 1) Pad: including saw cutting, demolition, earthwork, soil import, soil disposal, vaults, formwork, concrete, rebar, backfill, drainage adjustment, realignment of surface drainage, 2) Generator Surround: tie-in to foundation, steel, concrete block, mortar, gate, finish, bollards, wall drainage, import aggregate, and waterproofing, and 3) Sidewalk: including demolition, backfill, rebar, concrete, ADA striping and signage, and railing , as listed in the Bid Schedule.

City of Camarillo COMPENSATION
CH-5067-2 012005-3

C. Compensation and progress payment shall be made as agreed to by the City on the basis of the percentage of completed Work on this bid item. This price shall include full compensation for furnishing all labor, tools, materials, hazard material removal and disposal, debris removal and disposal, transportation, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

Bid Item No. 5 – TRE NCH AND UTILITY RUNS

A. Specification References: 312000, 321216

B. Measurement and Payment: P ayment for Utility Run, including sawcut, pavement demo, pavement removal, earthwork, shoring, import backfill, soil disposal, conduit, tracer tape, compaction, traffic control, AC pavement, and replacement of striping and shall be made at the Contract Lump Sum Price listed in the Bid Schedule.

C. Com
pensation and progress payment shall be made as agreed to by the City on the basis of the percentage of completed Work on this bid item. This price shall include full compensation for furnishing all labor, tools, materials, hazard material removal and disposal, debris removal and disposal, transportation, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

Bid Item No. 6 – FURNI

SH AND INSTALL SWITCHGEARS

A. Specification References: 260000, 262300

B. Measurement and Payment: P ayment for Switchgear, including tie -in to the main gear and appurtenances, shall be made at the Contract Unit Price Lump Sum as listed in the Bid Schedule. In addition, failure to perform shall result in a daily liquidated damage of $2,500/calendar day. The liquidated damages shall be in addition to any other liquidated damages. The imposition of liquidated damages shall not relieve the Contractor of any obligations of these project requirements.

Pay
ment for the work involved under this bid item for switchgear may be made on a partial payment system based on the completion of the following stages.

WORK DESCRIPTION PAYMENT
Order switchgear shop drawings 10% of bid Price
Approve shop drawings and order switchgear 60% of bid price Receive switchgear on-site 10% of bid price
Install switchgear 10% of bid price
Complete functional testing 10% of bid price

Payment shall include all labor, materials, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

City of Camarillo COMPENSATION
CH-5067-2 012005-4

Bid Item No. 7 – INSTALL CITY-FURNISHED GENERATORS

A. Specification References: 263213

B. Measurement and Payment: P ayment for Generator shall be made at the Contract Unit Lump Sum Price for obtaining the City purchased generator from the City, installing and anchoring the generator to the pad, and additional appurtenances indicated in the drawings, as listed in the Bid Schedule.

C. Com
pensation and progress payment shall be made as agreed to by the City on the basis of the percentage of completed Work on this bid item. This price shall include full compensation for furnishing all labor, tools, materials, hazard material removal and disposal, debris removal and disposal, transportation, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

Bid Item No. 8
– ELECTRICAL

A. Specification References: 260000, 260523, 262300, 263713, 265619

B. Measurement and Payment: P ayment for Electrical shall be made at the Contract Unit Lump Sum Price, including installation of conductor, wire termination in equipment, grounding, communication cable, termination of communication equipment, mounting of pull boxes, switches, disconnects, transfer switch, removal or adjustment of existing electrical gear, reconnecting of existing electrical load or onsite generation, shall be made at the Contract Lump Sum Price as listed in the Bid Schedule. In addition, failure to perform shall result in a daily liquidated damage of $2,500/calendar day. The liquidated damages shall be in addition to any other liquidated damages. The imposition of liquidated damages shall not relieve the Contractor of any obligations of these project requirements.

C. Compensation and progress payment shall be made as agreed to by the City on the basis of
the percentage of completed Work on this bid item. This price shall include full compensation for furnishing all labor, tools, materials, hazard material removal and disposal, debris removal and disposal, transportation, equipment and all incidentals to complete this bid item as specified in the Contract Documents for City Hall and Corporation Yard.

City of Camarillo COMPENSATION
CH-5067-2 012005-5

Bid Item No. 9 – FUNCTIONAL TESTING

A. Specification References: 263213

B. Measurement and Payment: P ayment for Functional Testing shall be made at the Contract Lump Sum Price for the verification of proper operation of existing loads, proper operation of existing on -site generation, and commissioning and performance testing of the generator proper operation in both simulated and actual test outages as listed in the Bid Schedule for City Hall and Corporation Yard .

C. Com
pensation and payment shall be made as agreed to by the City the work is fully completed for this bid item.

END OF SECTION 012005 - COMPENSATION

City of Camarillo PROCESS AND SUBMITTALS
CH-5067-2 013301-1

SECTION 013301 – PROCESS AND SUBMITTALS

PART 1 - GENERAL

1.01 CONSTRUCTION PHASE
A. Contractor shall obtain all required permits and approvals from the AHJ(s) and the Utility(ies) prior to starting Construction, in coordination with the Owner, and shall make copies available to the Owner of all permit applications and approvals.

B. Owner will provide formal NTP for construction upon receipt of acceptable Final Approved Permit Sets with all necessary AHJ approvals and all required proof of bonding. Contractor shall submit Building Permit to the Owner prior to commencing construction.

C. Prior to beginning construction, Contractor shall:

1. Provide a comprehensive onsite Construction Management and Safety Plan for the construction of the Project in accordance with all applicable laws, policies and OSHA compliant safety practices. Plan should include, at a minimum, address of local emergency medical facilities, project directory, information on Sub- Contractors, coordination with Owner staff during specific construction tasks, and communication protocols.

2. Provide an updated detailed Construction Schedule and a three-week look- ahead. Contractor shall keep the detailed construction schedule up to date.

Accurate and up to date three -week look-ahead schedules shall also be provided throughout construction on a weekly basis the day prior to the weekly meeting.

3. Conduct a kickoff meeting with the Owner to confirm all logistics for mobilization and start of construction.

D. The Contractor shall provide Manufacturers' Installation Manuals for major project components, including, but not limited to: racking or mounting structure, monitoring/control systems, diesel generator, and other major electrical equipment.

When approved by the Owner, recommended installation standards shall become the basis for commissioning, inspecting, and accepting or rejecting actual installation procedures used on the work.

E. Prior to ordering equipment and materials, the Contractor shall verify all measurements at each project site and notify the Owner in writing on any discrepancies between the drawings and site measurements.

F. Any proposed changes to design or scope of work shall be submitted in writing to the Owner for approval before any changes are made. Submittal for changes shall contain all necessary details of the proposed changes, detailed costs, and an updated energy system details, including size and production spreadsheet.

G. CONSTRUCTION SUBMITTALS: Shall be provided by the Contractor as detailed in Table 2:

City of Camarillo PROCESS AND SUBMITTALS
CH-5067-2 013301-2

Table 2 – Construction Submittals *
Construction Submittal Submittal Schedule

1. Construction Mgt &
Safety Plan
No later than 15 days prior to site mobilization.

2. Construction Schedule - Three-week look-ahead schedule updated and submitted weekly prior to the weekly meeting.
- Detailed schedule regularly maintained and provided every two weeks or as-requested.

3. Manufacturers' Installation
Manuals
No later than 5 days after construction kickoff meeting.

4. Weekly Meeting minutes No later than the day prior to the next scheduled project meeting.

5. Test Reports As available

6. Factory Tests As available

7. Field Tests As available

8. Design Deviations/
Requests for Information
As-needed. All deviations shall be accurately and legibly detailed by the Contractor and approved by Designer of Record, then presented to the Owner/Owner Reps in the form of an RFI. All changes shall be recorded on as-built drawings at the time of the change.

9. Proposed Change Orders Prior to commencing any changed work. Shall be formally submitted and approved by the Owner/Owner Rep in writing. * In addition to the Construction Submittals listed in Table 2, Contractor shall provide all submittals listed in Section 012000, General, Subsection 1.19 and as otherwise described in the Plans and Specifications herein.

1.02 COMMISSIONING PHASE
A. The Contractor shall provide complete commissioning of all energy systems installed as part of this project.

1. Assist any Owner staff, commissioning agents, or inspectors with their process and providing documentation as requested.

2. Verify that the installation is complete, and done according to the contract documents, manufacturer’s recommendations and industry accepted minimum standards

3. Verify that the installation is safe.

4. Verify that all components of the installation are robust and permanent.

5. Document as-built conditions.

6. Verify and document performance of equipment, installed as part of the Project.

7. Verify and document proper Diesel Generator operation and maintenance.

8. Establish and document performance benchmarks.

City of Camarillo PROCESS AND SUBMITTALS
CH-5067-2 013301-3

B. Commissioning protocols shall be provided in the form of a Method of Procedure (MOP) for review and approval by the Owner for all major energy systems.

Protocols shall adhere to all design document requirements and follow standard industry practices.

C. Prior to commencement of commissioning tasks, the Contractor shall notify the Owner and Owner representatives. The Contractor shall reference the previously approved procedures and provide a schedule of all commissioning, testing and safety activities.

D. Contractor shall provide electricians and support to Owner and Owner representative for verification of commissioning and workmanship, including providing reasonable notice prior to conducting commissioning activities so Owner representatives may observe.

E. A detailed and comprehensive commissioning report shall be submitted within 15 days after commissioning has been completed on a site-by-site basis.

1.03 CLOSEOUT PHASE / PROJECT ACCEPTANCE
A. Contractor shall deliver document submittals to the Owner per Table 3 in order to achieve each completion milestone and successfully closeout the project. A digital library will be created by the Owner, and the Contractor shall upload organized and collated digital versions of closeout documentation for each of the items listed below on a site-by-site basis. The Owner will review each submittal and formally approve each item upon review and confirmation of completeness. Incomplete submittals shall be corrected by the Contractor prior submittal acceptance. A formal notice by the Contractor shall be provided for each milestone acknowledging this checklist and successful submission of completed and approved checklist items. The Owner shall review and formally approve the notice for each site.

City of Camarillo PROCESS AND SUBMITTALS
CH-5067-2 013301-4

Table 3 – Closeout Document Submittals & Milestones

Substantial Completion
1 AHJ Substantial Completion Notice (As-needed for Utility Interconnect Request) 2 Schedule for Project Closeout
3 Sample Commissioning Protocol or Checklist for review 4 Utility Interconnection Request Submitted (emails and/or executed Interconnection Agreement)
5 Contractor Notice of Substantial Completion (if applicable) Commercial Operation Date - COD (All Substantial Completion items plus:) 6 Utility Permission-to-Operate (PTO) Notice
7 Permit to Operate from VCAPCD
8 AHJ(s) Acceptance/Completion Documentation (Closed permit) 9 Contractor Commissioning Documentation (completed commissioning and testing reports) 10 As-Built Plan Sets/Record Drawings
11 Major Equipment Cut Sheets/Warranty Documentation
12 DAS Login Access and Credentials & Verification of Function 13 Subcontractor Notices of Completion/Lien Waver/Unconditional Lien Release 14 Contractor Formal Commercial Operation Notice including Date (COD) Final Completion/Acceptance (All COD items plus:)
15 Punchlist – All Lists Signed Off
16 O&M Manual Final
17 Contractor to Coordinate Final Inspection
18 Operation and Safety Training
19 All Change Orders/Payments Finalized
20 Contractor Notice of Final Completion

B. Contractor shall submit complete digital “As-Built” Record Drawings for all sites for review and approval by the Owner. Final as-built plans shall be provided in portable document format (PDF). All deviations from the sizes, locations and other features shown in the Final plan sets must be captured in detail in the As -Built Record Drawings, including as -built sketches, details, and clarifications. Details shall include locations of work buried under or outside each building, including, without limitation, all utilities, plumbing and electrical lines and conduits. All directional boring logs, depths and routes and canopy or other foundation locations and depths shall be accurately shown on As-Built Record Drawings.

C. The Contractor shall submit documentation of Punch List Completion for items under control of the Contractor within 30 days of the Owner issuing the Final Punch List. The document must be signed and show proof of completion of each item.

D. The C ont
ractor shall submit to the Owner a comprehensive Operations and Maintenance (O&M) manual . O&M manuals shall be collated into a single, bookmarked portable document format (PDF) file. The document shall be a well - organized, comprehensive and custom document with details for each site. The O&M document should not duplicate closeout submittal items listed in Table 3 and should not be a collection of manufacturers cut -sheets. The intention of the

City of Camarillo PROCESS AND SUBMITTALS
CH-5067-2 013301-5

document is to provide an overview of the energy systems installed at each site for the Owner’s reference to safely interact with the systems, monitor performance, contact the owner during operation, respond during or after an emergency, and to understand the regular maintenance that will occur. The O&M manual shall include the following minimum items:

1. An overview and description of the energy systems installed, including system nameplates, system functions and key performance details.

Summary shall also include the date and reference number for: Permi t-to- Operate (PTO) from VCAPCD for generators, Commercial Operation Date, Final Completion, and AHJ Closeout.

2. A simple site plan for each site identifying the locations of major equipment, array/system naming conventions, monitoring system locations, and disconnects or other safety related equipment.

3. Safety details, including shut-down procedures.

4. Contact information for routine items and for emergencies.

5. Monitoring system details including information for accessing the platform and key performance metrics the Owner should review.

6. Maintenance information, including schedules, responsibilities for ongoing maintenance, and Standard Operating Procedures for both O&M personnel and the Owner. Detail shall include notification and site access protocols for O&M personnel.

7. Troubleshooting and repair, including responses to typical issues and responsible parties.

8. Any other information that may be required for the Owner to easily and safely interact with, confirm performance, troubleshoot, maintain and/or service the materials and equipment installed under this Contract.

E. Contractor shall provide any other Project documentation required by AHJs to successfully closeout permits or meet other project requirements.

END OF SECTION 013301 - PROCESS AND SUBMITTALS

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-1

SECTION 013516 – ALTERATION PROJECT PROCEDURES
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes special procedures for alteration work.

1.02 DEFINITIONS
A. Alteration Work: This term includes remodeling, renovation, repair, and maintenance work performed within existing spaces or on existing surfaces as part of the Project.

B. Consolidate: To strengthen loose or deteriorated materials in place.

C. Design Reference Sample: A sample that represents the Architect's Prebid selection of work to be matched; it may be existing work or work specially produced for the Project.

D. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

E. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, or finish; as approved by Architect.

F. Refinish: To remove existing finishes to base material and apply new finish to match original, or as otherwise indicated.

G. Repair: To correct damage and defects, retaining existing materials, features, and finishes. This includes patching, piecing- in, splicing, consolidating, or otherwise reinforcing or upgrading materials.

H. Replace: To remove, duplicate, and reinstall entire item with new material. The original item is the pattern for creating duplicates unless otherwise indicated.

I. Replicate: To reproduce in exact detail, materials, and finish unless otherwise indicated.

J. Reproduce: To fabricate a new item, accurate in detail to the original, and from either the same or a similar material as the original, unless otherwise indicated.

K. Retain: To keep existing items that are not to be removed or dismantled.

L. Strip: To remove existing finish down to base material unless otherwise indicated.

1.03 COORDINATION
A. Alteration Work Sub- schedule: A construction schedule coordinating the sequencing and scheduling of alteration work for entire Project, including each activity to be performed, and based on Contractor's Construction Schedule. Secure time commitments for pe rforming critical construction activities from separate entities responsible for alteration work.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-2

1. Schedule construction operations in sequence required to obtain best Work results.

2. Coordinate sequence of alteration work activities to accommodate the following:
a. Owner's continuing occupancy of portions of existing building. b. Owner's partial occupancy of completed Work.
c. Other known work in progress.
d. Tests and inspections.

3. Detail sequence of alteration work, with start and end dates. a. Any required shutdown of City Hall or Corporation Yard shall be coordinated a minimum of two (2) weeks in advance with Owner. b. Shutdowns may only occur between the hours of 6:00 a.m. Saturday through 6:00 a.m. the following Monday.
c. If power is not restored by 6:00 a.m. Monday Contractor shall be subject to Liquidated Damages in the amount of $2,500 per calendar day.

4. Utility Services: Indicate how long utility services will be interrupted.

Coordinate shutoff, capping, and continuation of utility services.

5. Use of elevator and stairs.

6. Equipment Data: List gross loaded weight, axle-load distribution, and wheel- base dimension data for mobile and heavy equipment proposed for use in existing structure. Do not use such equipment without certification from Contractor's professional engineer that the structure can support the imposed loadings without damage.

B. Pedestrian and Vehicular Circulation: Coordinate alteration work with circulation patterns within Project building(s) and site. Some work is near circulation patterns.

Circulation patterns cannot be closed off entirely and in places can be only temporarily redirected around small areas of work. Plan and execute the Work accordingly.

1.04 PROJECT MEETINGS FOR ALTERATION WORK
A. Preliminary Conference: Before starting alteration work, Construction Manager will conduct conference at City Hall; 601 Carmen Dr, Camarillo, CA 93010 and Corporation Yard; 283 S Glenn Dr, Camarillo, CA 93010.

1. Attendees: In addition to representatives of Owner, Construction Manager, Architect, and Contractor, and specialists shall be represented at the meeting.

2. Agenda: Discuss items of significance that could affect progress of alteration work, including review of the following:
a. Alteration Work Sub -schedule: Discuss and finalize; verify availability of materials, specialists' personnel, equipment, and facilities needed to make progress and avoid delays.
b. Fire-prevention plan.
c. Governing regulations.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-3

d. Areas where existing construction is to remain and the required protection.
e. Hauling routes.
f. Sequence of alteration work operations.
g. Storage, protection, and accounting for salvaged and specially fabricated items.
h. Existing conditions, staging, and structural loading limitations of areas where materials are stored.
i. Qualifications of personnel assigned to alteration work and assigned duties.
j. Requirements for extent and quality of work, tolerances, and required clearances.
k. Embedded work such as flashings and lintels, special details, collection of waste, protection of occupants and the public, and condition of other construction that affects the Work or will affect the work.

3. Reporting: Construction Manager will record conference results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from conference.

B. Coordination Meetings: Conduct coordination meetings specifically for alteration work at monthly intervals. Coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.

1. Attendees: In addition to representatives of Owner, Construction Manager, Architect, and Contractor, each specialist, supplier, installer, and other entity concerned with progress or involved in planning, coordination, or performance of alteration work act ivities shall be represented at these meetings. All participants at conference shall be familiar with Project and authorized to conclude matters relating to alteration work.

2. Agenda: Review and correct or approve minutes of previous coordination meeting. Review other items of significance that could affect progress of alteration work. Include topics for discussion as appropriate to status of Project.
a. Alteration Work Sub-schedule: Review progress since last coordination meeting. Determine whether each schedule item is on time, ahead of schedule, or behind schedule. Determine how construction behind schedule will be expedited with retention of quality; s ecure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities are completed within the Contract Time.
b. Schedule Updating: Revise Contractor's Alteration Work Sub-schedule after each coordination meeting where revisions to schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.
c. Review present and future needs of each entity present, including review items listed in the "Preliminary Conference for Alteration Work" Paragraph in this article and the following:
i. Interface requirements of alteration work with other Project Work.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-4

ii. Status of submittals for alteration work.
iii. Access to alteration work locations.
iv. Effectiveness of fire-prevention plan.
v. Quality and work standards of alteration work.
vi. Change Orders for alteration work.

3. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.

1.05 MATERIALS OWNERSHIP
A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may be encountered or uncovered during the Work, regardless of whether they were previously documented, remain Owner's property.

1.06 INFORMATIONAL SUBMITTALS
A. Alteration Work Sub-schedule:

1. Submit alteration work sub- schedule within 30 days of date established for commencement of alteration work.

B. Preconstruction Documentation: Show preexisting conditions of adjoining construction and site improvements that are to remain, including finish surfaces, that might be misconstrued as damage caused by Contractor's alteration work operations.

1.07 QUALITY ASSURANCE
A. Specialist Qualifications: An experienced firm regularly engaged in specialty work similar in nature, materials, design, and extent to alteration work as specified in each Section and that has completed a minimum of five recent projects with a record of successful in- service performance that demonstrates the firm's qualifications to perform this work.

1. Field Supervisor Qualifications: Full- time supervisors experienced in specialty work similar in nature, material, design, and extent to that indicated for this Project. Supervisors shall be on-site when specialty work begins and during its progress. Supervisors shall not be changed during Project except for causes beyond the control of the specialist firm.
a. Construct new mockups of required work whenever a supervisor is replaced.

B. Alteration Work Program: Prepare a written plan for alteration work for whole Project, including each phase or process and protection of surrounding materials during operations. Show compliance with indicated methods and procedures specified in this and other Sections. Coordinate this whole-Project alteration work program with specific requirements of programs required in other alteration work Sections.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-5

1. Dust and Noise Control: Include locations of proposed temporary dust - and noise-control partitions and means of egress from occupied areas coordinated with continuing on- site operations and other known work in progress.

2. Debris Hauling: Include plans clearly marked to show debris hauling routes, turning radii, and locations and details of temporary protective barriers.

C. Fire-Prevention Plan: Prepare a written plan for preventing fires during the Work, including placement of fire extinguishers, fire blankets, rag buckets, and other fire- control devices during each phase or process. Coordinate plan with Owner's fire- protection equipment and requirements. Include fire- watch personnel's training, duties, and authority to enforce fire safety.

D. Safety and Health Standard: Comply with ANSI/ASSE A10.6.

1.08 FIELD CONDITIONS
A. Survey of Existing Conditions: Record existing conditions that affect the Work by use of preconstruction photographs.

B. Discrepancies: Notify Architect of discrepancies between existing conditions and Drawings before proceeding with removal and dismantling work.

C. Owner's Removals: Before beginning alteration work, verify in correspondence with Owner that the following items have been removed:

D. Size Limitations in Existing Spaces: Materials, products, and equipment used for performing the Work and for transporting debris, materials, and products shall be of sizes that clear surfaces within existing spaces, areas, rooms, and openings, including temporary protection, by 12 inches (300 mm) or more.

PART 2 - EXECUTION

2.01 PROTECTION
A. Protect persons, motor vehicles, surrounding surfaces of building, building site, plants, and surrounding buildings from harm resulting from alteration work.

1. Use only proven protection methods, appropriate to each area and surface being protected.

2. Provide temporary barricades, barriers, and directional signage to exclude the public from areas where alteration work is being performed.

3. Erect temporary barriers to form and maintain fire-egress routes.

4. Erect temporary protective covers over walkways and at points of pedestrian and vehicular entrance and exit that must remain in service during alteration work.

5. Contain dust and debris generated by alteration work and prevent it from reaching the public or adjacent surfaces.

6. Provide shoring, bracing, and supports as necessary. Do not overload structural elements.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-6

7. Protect floors and other surfaces along hauling routes from damage, wear, and staining.

8. Retain subparagraph below if required for partially occupied buildings; revise to suit Project.

9. Provide supplemental sound- control treatment to isolate demolition work from other areas of the building.

B. Temporary Protection of Materials to Remain:

1. Protect existing materials with temporary protections and construction. Do not remove existing materials unless otherwise indicated.

2. Do not attach temporary protection to existing surfaces except as indicated as part of the alteration work program.

C. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, components, and vegetation.

D. Utility and Communications Services:

1. Notify Owner, Architect, authorities having jurisdiction, and entities owning or controlling wires, conduits, pipes, and other services affected by alteration work before commencing operations.

2. Disconnect and cap pipes and services as required by authorities having jurisdiction, as required for alteration work.

3. Maintain existing services unless otherwise indicated; keep in service and protect against damage during operations. Provide temporary services during interruptions to existing utilities.

E. Existing Drains: Prior to the start of work in an area, test drainage system to ensure that it is functioning properly. Notify Architect immediately of inadequate drainage or blockage. Do not begin work in an area until the drainage system is functioning properly.

1. Prevent solids such as adhesive or mortar residue or other debris from entering the drainage system. Clean out drains and drain lines that become sluggish or blocked by sand or other materials resulting from alteration work.

2. Protect drains from pollutants. Block drains or filter out sediments, allowing only clean water to pass.

2.02 PROTECTION FROM FIRE
A. General: Follow fire-prevention plan and the following:

1. Comply with NFPA 241 requirements unless otherwise indicated.

2. Remove and keep area free of combustibles, including rubbish, paper, waste, and chemicals, unless necessary for the immediate work.

3. If combustible material cannot be removed, provide fire blankets to cover such materials.

City of Camarillo ALTERATION PROJECT PROCEDURES CH-5067-2 013516-7

B. Heat-Generating Equipment and Combustible Materials: Comply with the following procedures while performing work with heat -generating equipment or combustible materials, including welding, torch-cutting, soldering, brazing, removing paint with heat, or other operations where open flames or implements using high heat or combustible solvents and chemicals are anticipated:

1. As far as practicable, restrict heat -generating equipment to shop areas or outside the building.

2. Do not perform work with heat -generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. Use a combustible gas indicator test to ensure that the area is safe.

3. Use fireproof baffles to prevent flames, sparks, hot gases, or other high- temperature material from reaching surrounding combustible material.

4. Prevent the spread of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings.

C. Fire-Control Devices: Provide and maintain fire extinguishers, fire blankets, and rag buckets for disposal of rags with combustible liquids. Maintain each as suitable for the type of fire risk in each work area. Ensure that nearby personnel and the fire- watch personnel are trained in fire-extinguisher and blanket use.

D. Sprinklers: Where sprinkler protection exists and is functional, maintain it without interruption while operations are being performed. If operations are performed close to sprinklers, shield them temporarily with guards.

1. Remove temporary guards at the end of work shifts, whenever operations are paused, and when nearby work is complete.

2.03 GENERAL ALTERATION WORK
A. Have specialty work performed only by qualified specialists.

B. Ensure that supervisory personnel are present when work begins and during its progress.

C. Record existing work before each procedure (preconstruction), and record progress during the work. Use digital preconstruction documentation photographs.

D. Perform surveys of Project site as the Work progresses to detect hazards resulting from alterations.

E. Notify Architect of visible changes in the integrity of material or components whether from environmental causes including biological attack, UV degradation, freezing, or thawing or from structural defects including cracks, movement, or distortion.

1. Do not proceed with the work in question until directed by Architect.

END OF SECTION 013516 - ALTERATION PROJECT PROCEDURES

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-1

SECTION 015723 – STORMWATER POLLUTION CONTROL PLAN

PART 1 - GENERAL
A. The Contractor shall prepare and maintain a Stormwater Pollution Control Plan (SWPCP) on the form provided by the City, included in this specification, which describes in specific detail the Contractor’s program to prevent contamination of the stormwater collection system. Contractor shall implement, maintain, inspect and remove all erosion and sediment controls identified in the SWPCP. The program shall address both common construction activities and extraordinary events.

B. Contractor shall include water pollution control drawings (WPCD) in the SWPCP to illustrate the locations, applications and deployment of best management practices (BMPs) identified in the SWPCP. The WPCDs shall be included as an attachment to the SWPC P. Sample WPCDs can be obtained from the California Stormwater Quality Association (CASQA) Construction BMP Handbook. The SWPCP shall also comply with the Regional Los Angeles and Ventura Counties Municipal Separate Storm Sewer System (MS4) Permit (Order N o. R4 -2021-0105, Permit No.

CAS004004). A copy of the permit is available for review from the City of Camarillo Stormwater Program Manager; phone 805-383-5659.

C. The Contractor shall comply with laws, rules, and regulations of the State of California and agencies of the United States Government prohibiting the pollution of lakes, wetlands, streams, or river waters from the dumping of contaminates, refuse, rubbish or debris.

D. The C ont
ractor shall submit three (3) copies of the SWPCP a minimum of 10 working days prior to beginning construction. Construction shall not begin until the SWPCP is approved. Contractor shall update the SWPCP as necessary during the work to prevent contamination of the stormwater collection system. At completion of construction, contractor shall provide City with site copy of the SWPCP, including all required inspection and training reports.

E. Before start of work, Contractor shall train all employees and subcontractors on the S
WPCP and related WPCD and provide City with written documentation of said training.

F. Suggested BMPs can be obtained from the following sources:

1. Ventura County Municipal Separate Storm Sewer System Permit/Order 2010-0108 and the Regional Los Angeles and Ventura Counties MS4 Permit/Order R4- 2021-0105 available at Los Angeles Regional Water Quality Control Board web site at
https://www.swrcb.ca.gov/rwqcb4/water_issues/programs/stormwater/muni cipal/index.shtml

2. California Stormwater BMP Handbooks for Construction or Municipal Activities www.cabmphandbooks.com

3. Ventura Countywide Stormwater Quality Management Program www.vcstormwater.org.

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-2

4. Caltrans’ Stormwater Quality Handbooks
https://www.dot.ca.gov/hq/construc/stormwater/stormwater1.htm PART 2 - CONSTRUCTION
A. The Contractor shall keep a copy of the SWPCP on the job site. The Contractor shall provide continuously at the jobsite all of the tools, equipment, and materials necessary to implement the SWPCP at all times from project initiation through completion, including any punchlist or warranty work on the project.

B. At a minimum the following requirements should be met as applicable, to the maximum extent practicable, at construction sites regardless of size:

1. Storm Drain System Protection – At the first order of work, the Contractor shall protect the existing storm drain system from entrance of construction debris and pollutants. Such protection shall include implementing the BMPs as outlined in the SWPCP. Protection shall prohibit the discharge of untreated runoff from temporary or permanent street maintenance/landscape maintenance material and waste storage areas from entering the storm drain system. Sediment that is generated on the project site shall be retained using structural drainage controls. In addition, the protection system shall have a minimum of three features: 1) a particulate filter of geosynthetic material securely fastened in place such that it cannot be bypassed without significant physical damage; 2) a prefilter for the particulate filter; and 3) on- hand materials to close off the inlet or opening in the case of a significant pollution spill. Contractor shall monitor and maintain all storm drain inlet protection devices during rain events to prevent flooding. All curb inlet BMP devices shall be fabricated “L” or “Z” shaped reusable type with high flow bypass and have gravel bags.

2. Material Management & Storage – No construction- related materials, wastes, spills or residues shall be discharged from the project site to streets, drainage facilities or adjacent properties by wind or runoff. All materials and/or equipment storage areas where liquid construction mat erials are placed shall be protected by a physical barrier capable of containing the entire volume of stored liquid materials. During active construction activities, portions of the barrier may be removed for access. However, the barrier materials must be readily accessible for replacement by onsite construction personnel. The barrier must be in place at all times during the absence of Contractor personnel at the storage site. Building materials should be placed on pallets and covered in event of rain. Do not store materials in the street or gutter area.

3. Equipment & Vehicle Maintenance – Non-stormwater runoff from equipment and vehicle washing and any other activity shall be contained at the project site and shall not be allowed to discharge from the project site to streets, drainage facilities or adjacent properties by wind or runoff. The Contractor shall inspect vehicles and equipment on each day of use. Leaks shall be repaired off-site if possible. If necessary to repair on site, the runoff must be contained or the problem vehicle or equipment shall be removed from the project site until repaired. If necessary, drip pans should be placed

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-3

under the vehicles or equipment while not in use to catch and/or contain drips and leaks.

4. Soil Erosion Control – Erosion from slopes and channels will be significantly reduced by implementing BMPs, including but not limited to, minimizing grading activities during the wet season, inspecting graded areas during rain events, planting and maintaining vegetation on slopes or other erosion controls such as hydraulic mulch, hydroseeding, soil binders, and straw mulch, or covering slopes susceptible to erosion with geotextiles and mats.

5. Spill Prevention & Cleanup Plan - C
ontractor shall have a spill prevention
plan and spill cleanup materials readily available and addressed in the SWPCP. Spills shall be cleaned up immediately using dry methods if possible. Spill cleanup material shall be properly disposed of. Refer to SC- 11 Spill Prevention BMP from the California Stormwater BMP Handbook for Municipal Activities . Contractor shall keep a record of any spills in the inspection log. In addition, at the end of the project, the Contractor must certify that all contaminated materials have been properly disposed in accordance with the SWPCP.

6. Asphalt, Concrete, Road Reconstruction, Roadbed or Street Paving, R
epaving, Patching, Digouts, or Resurfacing Roadbed Surfaces, & Related Activities – Contractor shall implement the following BMPs:
a. Restrict paving/repaving activity to exclude periods of rainfall or predicted rainfall unless required by emergency conditions. b. Install gravel bags and filter fabric at all susceptible storm drain inlets and at manholes to prevent spills of paving products and tack coat.

Filter fabric must be fabricated “L” or “Z” shaped reusable type with high flow bypass.
c. Prevent the discharge of release agents including soybean oil, other oils, or diesel to the storm drain system or receiving waters. d. Prevent non- stormwater runoff from water use for the roller and for evaporative cooling of the asphalt.
e. Clean equipment over absorbent pads, drip pans, plastic sheeting or other material to capture all spillage and dispose of properly. f. Collect liquid waste in a container, with a secure lid, for transport to a maintenance facility to be reused, recycled or disposed of properly. g. Collect solid waste by vacuuming or sweeping and securing in an appropriate container for transport to a maintenance facility to be reused, recycled, or disposed of properly.
h. Cover the cold mix, asphalt, materials (i.e., pre- mixed aggregate and asphalt binder) with protective sheeting during a rainstorm. i. Cover loads with tarp before haul -off to a storage site, and do not overload trucks.
j. Minimized airborne dust by using water spray during grinding.

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-4

k. Avoid stockpiling soil, sand, sediment, asphalt material and asphalt grinding material or rubble in or near storm water drainage systems or receiving waters.
l. Protect stockpiles with a cover or sediment barriers during a rain event.

7. Sidewalk Washing – The following methods should be utilized to prevent discharge of sidewalk cleaning wastewater into the storm drain system:
a. Sweep and remove trash, debris, and free standing oil/grease spills/leaks (use absorbent material if necessary) from all areas to be cleaned before using water.
b. Manually scrape gum from sidewalks and other surfaces. c. Must use high pressure, low volume spray using only potable water with no cleaning agents at an average usage of 0.006 gallons per square foot of surface area to be rinsed.
d. Use a wet/dry vacuum to collect wash water for disposal. Large volumes of wash water may require the use of a small sump pump to remove wash water from the job site.
e. One or more of the following methods are recommended to prevent pollutants from entering the storm drain system:
• Sandbags can be used to create a barrier around storm drains. * • Rubber mats or plugs can be used to seal drain openings. * • Temporary berms or containment pads help keep water on site. * • Use berms of sandbags to direct wash water to landscaping. * • Use large squeegees to accumulate sheet flow for collection. *Remember to remove plugs, berms, and sandbags or you may be liable for possible flooding.

8. Wash water that may contain hazardous waste such as oil -saturated absorbents, water with lead or other heavy metals from oxidized paint, and solvent cleaners requires special treatment and must be disposed of through a hazardous waste facility.

9. Employee BMP Training – Contractor shall train employees and subcontractors on BMP implementation, general good housekeeping, and proper spill containment and cleanup. Before start of work, Contractor shall provide City with written documentation of training and keep all documentation in the SWPCP.

10. Inspection – The Contractor shall inspect all pollution control BMPs per schedule below. Contractor shall forward electronic copies of inspection reports to City Stormwater Program Manager by the end of the week that inspection took place. The Contractor should also repair/replace any damaged BMP or clogged element on a daily basis. The Contractor shall keep a monitoring inspection log of each inspection in the SWPCP. Minimum inspection frequency:

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-5

1. Once per month during the non- rainy season (April 16 – September 30)

2. Once per week during the rainy season (Oct. 1 – April 15)

3. Before, during and after a major rain event, the area shall be inspected at a minimum twice per day, seven days per week, whether or not any work has been performed. The daily checks shall be between 6 and 9 am and 4 and 8 pm.

11. Dewatering – Avoid dewatering discharges where possible by using the water for dust control, infiltration, etc. If necessary to dewater, Contractor shall obtain a permit from the Los Angeles Regional Water Quality Control Board. Contractor shall be responsible for all costs related to implementing the dewatering permit. For further instruction refer to the California Construction Handbook – BMP NS-2.

12. Removal of Accumulated Rainwater – The Contractor shall follow the City Camarillo Guidelines for Removal of Rainwater that has accumulated on the job site. The preferred method is to filter the rainwater into a water truck for use in dust control or irrigation. If it is necessary to rem ove rainwater from the site to the street, gutter or storm drainage system, Contractor shall use BMPs to insure that the water does not exceed 100 mg/l of Total Suspended Solids and no other construction waste is present in the water to be discharged before discharging to drainage facilities.

13. High Risk Sites - Hillside or Construction Discharging Directly to Sediment Impaired Waterbody – Contractor shall implement enhanced BMPs on sites located on hillsides (slopes that are 20 percent or greater) or that discharge directly to Conejo Creek, Calleguas Creek, or Revolon Slough/Beardsley Wash. For a list of enhanced BMPs see Table 9 in Par t

4.F.4 in the Ventura County Municipal Stormwater Permit (Order No. 2010 - 0108) available at:
https://www.swrcb.ca.gov/rwqcb4/water_issues/programs/stormwater/muni cipal/index.shtml. In addition to enhanced BMPs, these type of “high risk” sites must be inspected by a qualified SWPPP Practitioner or Developer (QSP or QSD) at least weekly during the wet season and once each 24 hour period during a storm event that generates runoff from the site to identify BMPs that need maintenance to operate effectively, that have failed or could fail to operate as intended.

PART 3 - PAY
MENT
A. The Contractor shall be paid for work of preparing, implementing, inspecting, maintaining, and removing the SWPCP on a lump sum basis as enumerated in the Bid Schedule for the Stormwater Pollution Control Program. In addition, failure to perform and document the required daily inspections shall result in a daily liquidated damage of $250/calendar day. This liquidated damage shall be in addition to any other liquidated damage. The imposition of the penalty shall not relieve the Contractor of any obligations of these project requirements.

City of Camarillo STORMWATER POLLUTION CONTROL PLAN
CH-5067-2 015723-6

B. Payment for the work involved under the bid item for the Stormwater Pollution Control Program may be made on a partial payment system based on the completion of the following stages of work:

Work Description Payment
Develop Plan 10% of Bid Price
Initial Plan Implementation 10% of Bid Price
Inspection & Maintenance of SWPCP 70% of Bid Price (will be paid incrementally over the life of the project)
Removal of BMPs at Completion 10% of Bid Price
C. Payment for the SWPCP shall include all the labor, materials, equipment, and incidentals for preparing, maintaining, and updating a SWPCP and complying with all provisions including maintenance and updating of BMPs throughout construction, as specified herein.

D. Fines and penalties from regulatory agencies levied against the City as a result of the Contractor’s work, including actions or inactions shall be the responsibility of the Contractor and may be deducted from payments due or to become due the Contractor.

END OF SECTION 015723 – STORMWATER POLLUTION CONTROL PLAN

City of Camarillo EXECUTION
CH-5067-2 017300-1

SECTION 017300 – EXECUTION
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Field engineering and surveying.

3. Installation of the Work.

4. Cutting and patching.

5. Coordination of Owner-installed products.

6. Progress cleaning.

7. Starting and adjusting.

8. Protection of installed construction.

1.02 DEFINITIONS
A. Cutting: Removal of in -place construction necessary to permit installation or performance of subsequent work.

B. Patching: Fitting and repair work required to restore construction to original conditions after installation of subsequent work.

1.03 QUALITY ASSURANCE
B. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated.

C. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

1. Structural Elements: When cutting and patching structural elements, notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural elements during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.

2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operational elements include the following:
a. Primary operational systems and equipment.
b. Fire separation assemblies.
c. Air or smoke barriers.

City of Camarillo EXECUTION
CH-5067-2 017300-2

d. Fire-suppression systems.
e. Plumbing piping systems.
f. Mechanical systems piping and ducts.
g. Control systems.
h. Communication systems.
i. Fire-detection and -alarm systems.
j. Conveying systems.
k. Electrical wiring systems.
l. Operating systems of special construction.

3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load- carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.

Other construction elements include but are not limited to the following:
a. Water, moisture, or vapor barriers.
b. Membranes and flashings.
c. Exterior curtain-wall construction.
d. Sprayed fire-resistive material.
e. Equipment supports.
f. Piping, ductwork, vessels, and equipment.
g. Noise- and vibration-control elements and systems.

D. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities.

Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

E. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.

PART 2 - PRODUCTS

2.01 MATERIALS
A. General: Comply with requirements specified in other Sections.

1. For projects requiring compliance with sustainable design and construction practices and procedures, use products for patching that comply with sustainable design requirements.

B. In-Place Materials: Use materials for patching identical to in- place materials. For exposed surfaces, use materials that visually match in- place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials.

City of Camarillo EXECUTION
CH-5067-2 017300-3

PART 3 - EXECUTION

3.01 EXAMINATION
A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, mechanical and electrical systems , and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water -service piping; underground electrical services; and other utilities.

2. Furnish location data for work related to Project that must be performed by public utilities serving Project site.

B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

3.02 PREPARATION
A. Existing Utility Information: Furnish information to SCE and the City of Camarillo that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction.

Coordinate with authorities having jurisdiction.

B. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field m easurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

E. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Owner.

City of Camarillo EXECUTION
CH-5067-2 017300-4

3.03 CONSTRUCTION LAYOUT
A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect and Construction Manager promptly.

B. General: Engage a professional engineer to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.

2. Establish limits on use of Project site.

3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

4. Inform installers of lines and levels to which they must comply.

5. Check the location, level and plumb, of every major element as the Work progresses.

6. Notify Architect and Construction Manager when deviations from required lines and levels exceed allowable tolerances.

7. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and rim and invert elevations.

D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations.

E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect.

3.04 FIELD ENGINEERING
A. Identification: Owner will identify existing benchmarks, control points, and property corners.

B. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

1. Do not change or relocate existing benchmarks or control points without prior written approval of Architect or Construction Manager. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to Architect and Construction Manager before proceeding.

2. Replace lost or destroyed permanent benchmarks and control points promptly. Base replacements on the original survey control points.

City of Camarillo EXECUTION
CH-5067-2 017300-5

C. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

2. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work.

3. Remove temporary reference points when no longer needed. Restore marked construction to its original condition.

D. Certified Survey: On completion of foundation walls, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework.

E. Final Property Survey: Engage a professional engineer to prepare a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by professional engineer, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey.

1. Show boundary lines, monuments, streets, site improvements and utilities, existing improvements and significant vegetation, adjoining properties, acreage, grade contours, and the distance and bearing from a site corner to a legal point.

2. Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey."

3.05 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated.

4. Maintain minimum headroom clearance of 96 inches (2440 mm) in occupied spaces and 90 inches (2300 mm) in unoccupied spaces.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

City of Camarillo EXECUTION
CH-5067-2 017300-6

E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.

F. Tools and Equipment: Where possible, select tools or equipment that minimize production of excessive noise levels.

G. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other portions of the Work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

H. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.

2. Allow for building movement, including thermal expansion and contraction.

3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

I. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

J. Repair or remove and replace damaged, defective, or nonconforming Work.

3.06 CUTTING AND PATCHING
A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.

C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in- place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage

City of Camarillo EXECUTION
CH-5067-2 017300-7

elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

1. In general, use hand or small power tools designed for sawing and grinding, not hammering, and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

3. Concrete and Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

4. Excavating and Backfilling: Comply with requirements in applicable Sections where required by cutting and patching operations.

5. Proceed with patching after construction operations requiring cutting are complete.

H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.
a. Clean piping, conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. a. Where patching occurs in a painted surface, prepare substrate and apply primer and intermediate paint coats appropriate for substrate over the patch, and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces.

4. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.

I. Cleaning: Clean areas and spaces where cutting and patching are performed.

Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

City of Camarillo EXECUTION
CH-5067-2 017300-8

3.07 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold waste materials more than seven days during normal weather or three days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
a. Use containers intended for holding waste materials of type to be stored.

4. Retain subparagraph below for projects involving multiple contracts.

5. Coordinate progress cleaning for joint-use areas where Contractor and other contractors are working concurrently.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom -clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Do not bury or burn waste materials on- site. Do not wash waste materials down sewers or into waterways.

I. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

J. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

City of Camarillo EXECUTION
CH-5067-2 017300-9

L. Limiting Exposures: Supervise construction operations to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.08 STARTING AND ADJUSTING
A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

B. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

3.09 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Protection of Existing Items: Provide protection and ensure that existing items to remain undisturbed by construction are maintained in condition that existed at commencement of the Work.

C. Comply with manufacturer's written instructions for temperature and relative humidity.

END OF SECTION 017300 - EXECUTION

City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-1

SECTION 017700 – CLOSEOUT PROCEDURES
PART 1 - GENERAL

1.01 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures.

2. Final completion procedures.

3. Warranties.

4. Final cleaning.

5. Repair of the Work.

1.02 ACTION SUBMITTALS
A. Product Data: For each type of cleaning agent.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Certified List of Incomplete Items: Final submittal at final completion.

1.03 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.

B. Certificate of Insurance: For continuing coverage.

C. Field Report: For pest control inspection.

1.04 MAINTENANCE MATERIAL SUBMITTALS
A. Schedule of Maintenance Material Items: For maintenance material submittal items specified in other Sections.

1.05 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list), indicating the value of each item on the list and reasons why the Work is incomplete.

B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

1. Certificates of Release: Obtain and submit releases from authorities having jurisdiction permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-2

2. Submit closeout submittals specified in other Division 01 Sections, including project record documents, operation and maintenance manuals, damage or settlement surveys, property surveys, and similar final record information.

3. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

4. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Construction Manager. Label with manufacturer's name and model number.

5. Submit testing, adjusting, and balancing records.

6. Retain first subparagraph below when sustainable design submittals are required for Project.

7. Submit sustainable design submittals not previously submitted.

8. Submit changeover information related to Owner's occupancy, use, operation, and maintenance.

C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.

D. Advise Owner of pending insurance changeover requirements.

E. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions.

F. Complete startup and testing of systems and equipment.

1. Perform preventive maintenance on equipment used prior to Substantial Completion.

2. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems.

3. Advise Owner of changeover in utility services.

4. Participate with Owner in conducting inspection and walkthrough with local emergency responders.

5. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.

6. Complete final cleaning requirements.

7. Touch up paint and otherwise repair and restore marred exposed finishes to eliminate visual defects.

G. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 prior to date the Work will be completed and ready for final inspection and tests. On receipt of request, Architect and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-3

items identified by Architect, that must be completed or corrected before certificate will be issued.

1. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.06 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting final inspection for determining final completion, complete the following:

1. Certified List of Incomplete Items: Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Certificate of Insurance: Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Submit pest-control final inspection report.

4. Submit final completion photographic documentation.

5. Revise "Inspection" Paragraph below to comply with office policy and Project requirements.

6. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request, Architect and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued. a. Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.07 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

1. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

2. Include the following information at the top of each page:
a. Project name.
b. Date.
c. Name of Architect and Construction Manager.
d. Name of Contractor.

City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-4

e. Page number.

3. Submit list of incomplete items in the following format:
a. MS Excel electronic file. Architect, through Construction Manager, will return annotated file.
b. PDF electronic file. Architect, through Construction Manager, will return annotated file.
c. Web-based project software upload. Utilize software feature for creating and updating list of incomplete items (punch list).

1.08 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Architect for designated portions of the Work where warranties are indicated to commence on dates other than date of Substantial Completion, or when delay in submittal of warranties might limit Owner's rights under warranty.

B. Partial Occupancy: Submit properly executed warranties within 15 d ays of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual.

D. Warranty Electronic File: Provide warranties and bonds in PDF format. Assemble complete warranty and bond submittal package into a single electronic PDF file with bookmarks enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

E. Warranties in Paper Form:

1. Bind warranties and bonds in heavy -duty, three-ring, vinyl-covered, loose- leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch (215-by-280-mm) paper.

2. Provide heavy paper dividers with plastic -covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

F. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS

2.01 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-5

1. Use cleaning products that comply with Green Seal's GS -37, or if GS-37 is not applicable, use products that comply with the California Code of Regulations maximum allowable VOC levels.

PART 3 - EXECUTION

3.01 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste -removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning.

Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

3. Rake grounds that are not planted, mulched, or paved to a smooth, even- textured surface.

4. Remove tools, construction equipment, machinery, and surplus material from Project site.

5. Remove snow and ice to provide safe access to building.

6. Clean exposed exterior and interior hard- surfaced finishes to a dirt -free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

7. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

8. Sweep concrete floors broom clean in unoccupied spaces.

9. Remove labels that are not permanent.

10. Wipe surfaces of mechanical and electrical equipment, and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

11. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

City of Camarillo CLOSEOUT PROCEDURES
CH-5067-2 017700-6

12. Clean ducts, blowers, and coils if units were operated without filters during construction or that display contamination with particulate matter on inspection.

13. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency.

14. Leave Project clean and ready for occupancy.

3.02 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair, or remove and replace, defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that already show evidence of repair or restoration.
a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

END OF SECTION 017700 – CLOSEOUT PROCEDURES

City of Camarillo SELECTIVE DEMOLITION
CH-5067-2 024119-1

SECTION 024119 – SELECTIVE DEMOLITION
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

1.02 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off -site unless indicated to be salvaged or reinstalled.

B. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

C. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

D. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

1.04 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1.05 INFORMATIONAL SUBMITTALS
A. Engineering Survey: Submit engineering survey of condition of building.

B. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on -site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

4. Use of elevator and stairs.

5. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.

City of Camarillo SELECTIVE DEMOLITION
CH-5067-2 024119-2

C. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by demolition operations.

D. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.

1.06 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.

1.07 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. Storage or sale of removed items or materials on-site is not permitted.

D. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire- protection facilities in service during selective demolition operations.

1.08 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties. Notify warrantor before proceeding.

B. Notify warrantor on completion of selective demolition, and obtain documentation verifying that existing system has been inspected and warranty remains in effect.

Submit documentation at Project closeout.

1.09 COORDINATION
A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

PART 2 - PRODUCTS

2.01 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

City of Camarillo SELECTIVE DEMOLITION
CH-5067-2 024119-3

PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. Steel Tendons: Locate tensioned steel tendons and include recommendations for de-tensioning.

D. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

3.02 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.
a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.
b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place. c. Equipment to Be Removed: Disconnect and cap services and remove equipment.
d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.
e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

City of Camarillo SELECTIVE DEMOLITION
CH-5067-2 024119-4

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.
g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.03 PROTECTION
A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

4. Cover and protect furniture, furnishings, and equipment that have not been removed.

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

C. Remove temporary barricades and protections where hazards no longer exist.

3.04 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

B. Proceed with selective demolition systematically, from higher to lower level.

Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

C. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

1. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

2. Do not use cutting torches until work area is cleared of flammable materials.

At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame- cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

City of Camarillo SELECTIVE DEMOLITION
CH-5067-2 024119-5

3. Maintain fire watch during and for at least 2 hours after flame- cutting operations.

4. Maintain adequate ventilation when using cutting torches.

5. Remove decayed, vermin- infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

6. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

7. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

D. Site Access and Temporary Controls: Conduct selective demolition and debris - removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

E. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

F. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.

3.05 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS A. Concrete: Demolish in small sections. Using power -driven saw, cut concrete to a depth of at least 3/4 inch (19 mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power -driven saw, and then remove concrete between saw cuts.

C. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

D. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

END OF SECTION 024119 – SELECTIVE DEMOLITION

City of Camarillo CONCRETE FORMWORK AND ACCESSORIES
CH-5067-2 031000-1

SECTION 031000 – CONCRETE FORMWORK AND ACCESSORIES
PART 1 - GENERAL

1.01 SUMMARY
A. Provide concrete formwork and accessories as indicated on the drawings and specifications, including the following:

1. Design and construction of formwork for concrete.

2. Setting in forms, all anchor bolts, metal inserts, sleeves, etc., embedded in concrete.

3. Miscellaneous concrete work, including but not limited to areaways, cast -in-place valve boxes, pits, splash blocks, equipment bases, and other items as shown or required to complete all Work.

B. Design and carry out the engineering and construction of all formwork, shoring, and bracing, by and under the direction of the Contractor. The Contractor shall be responsible for the engineering, construction, maintenance, and safety of all formwork during the entire construction period. The formwork shall be designed for the loads and lateral pressures outlined ACI 347, and other forces as specified by the Building Code.

1.02 QUALITY ASSURANCE:

A. Construct forms according to ACI 347 "Recommended Practice for Concrete Formwork", and conforming to tolerances specified in ACI 301, "Specifications for Structural Concrete for Buildings", as applicable, unless exceeded by code requirements or other-wise indicated or specified.

B. Prior to construction of formwork for concrete beams and slabs above grade, Contractor shall conduct a meeting at the site to determine and define all cambers required for the project. The Architect, Structural Engineer of record, Contractor and Contractor's formwork installer shall attend this meeting.

1.03 DELIVERY, STORAGE, AND HANDLING:

A. Deliver materials for forms in timely manner to ensure uninterrupted progress.

B. Store materials by methods that prevent damage and permit ready access for inspection and identification.

PART 2 - PRODUCTS

2.01 CONCRETE FORMWORK AND ACCESSORIES:

A. Forms for Unexposed Concrete: Form concrete surfaces which will not be exposed in the finished structure with plywood, lumber, metal or other acceptable material.

1. Lumber: Standard or better grade Douglas fir, meeting the requirements of WCLIB "Standard No. 17, Grading Rules for West Coast Lumber" or WWPA City of Camarillo CONCRETE FORMWORK AND ACCESSORIES
CH-5067-2 031000-2

"Western Lumber Grading Rules 91". Use boards which are surfaced on at least 2 edges and one side for a tight fit.

2. Plywood: B B Plyform, Class I, Exterior grade meeting the requirements of PS 1 96 & PS 1-83, 5/8 inch minimum thickness for 12 inch stud spacing and 3/4 inch minimum thickness for 16 inch stud spacing.

B. Forms for Exposed Finish Concrete: Construct formwork for exposed concrete surfaces with plywood, metal, metal framed plywood faced or other acceptable panel type materials, to provide continuous, straight, smooth, exposed surfaces.

Furnish in largest practical sizes to minimize number of joints. Provide form material with sufficient thickness to withstand pressure of newly placed concrete without bow or deflection.

1. Provide High Density Overlay Plyform Class I Exterior plywood meeting the requirements of PS 1 83 for concealed surfaces.

2. Provide B B Plyform Class I Exterior plywood meeting the requirements of PS 1 83 for exposed surfaces.

C. Form Liners: Form architectural finish concrete surfaces with PVC or ABS plastic, fiber glass reinforced plastic or elastomeric urethane form liners of face design indicated.

D. Waterstops: Provide PVC water stops of the shape and size indicated and meeting the minimum requirements of Corps of Engineers Specification CRD C 572 89.

E. Framing, Studding and Bracing: "Standard" or "Construction" grade Douglas fir, rough or S4S, meeting the requirements of WCLIB "Standard No. 17, Grading Rules for West Coast Lumber" or WWPA "Western Lumber Grading Rules 91".

F. Form Ties and Spreaders: Standard metal form clamp assembly, of type acting as spreaders and leaving no metal within 1 inch of concrete face. Inner tie rod shall be left in concrete when forms are removed. Wire ties or wood spreaders will not be permitted.

G. Form Coating: Non-grain raising and non-staining type that will not leave residual matter on surface of concrete or adversely affect proper bonding of subsequent application of other material applied to concrete surface. Coatings containing mineral oils or other nondrying ingredients will not be permitted. Form coating for use with form liners shall be of type recommended by form liner manufacturer.

H. Nails: Common wire, steel.

PART 3 - EXECUTION

3.01 CONSTRUCTION
A. Conform to ACI 301 and ACI 347 except as exceeded by the requirements of Building Code, regulatory agencies, or herein.

B. Earth Forms: Earth forms may be used for footings only where the soil is firm and stable and the concrete will not be exposed to view. Where earth forms are to be used, excavations shall be cut neat and accurately to size for placing of concrete directly against the excavation. Except for bottom of footings, allow for two inches of additional concrete beyond the dimensions or profiles shown on the drawings.

City of Camarillo CONCRETE FORMWORK AND ACCESSORIES
CH-5067-2 031000-3

Construct wood edge strips at each side of trench at top to secure reinforcing and prevent trench from sloughing. Form sides of footings where earth sloughs more than six inches. Earth forms shall be tamped firm and cleaned of all debris and loose material before depositing concrete.

C. Wood Forms: Construct forms of sound material to the correct shape and dimensions, mortar tight, and of sufficient strength, and so braced and tied together that the movement of men, equipment, materials, or placing and vibrating the concrete will not throw them out of exact shape under imposed loads. They shall be so constructed that they may be easily removed without damage to the concrete.

Before concrete is placed in forms, carefully verify the horizontal and vertical position of the form and correct inaccuracies. Complete wedging and bracing in advance of placing of concrete.

D. Form Liners: Position liners on the forms so that grooves and joints are aligned with tie slots. Attach form liners to plywood forms with staples and to metal forms with sheet metal screws or pop rivets. Space fasteners not to exceed 4 inches on centers around the perimeter of each sheet. Place staples perpendicular to the edges. Install staples using a power staple with pressure regulated so that staple heads are driven flush with the surface. Seal joints between liners and joints at top and bottoms of liners with foam tape placed on the back side of liners.

E. Framing bracing, supporting members, and centering shall be of ample size and strength to safely carry, without deflection, dead and live loads to which forms may be subjected, and shall be spaced sufficiently close to prevent bulging or sagging of forms. Concrete out of line, level, or plumb will be cause for rejection of the whole construction affected.

F. Tolerances: Formwork shall be constructed so as to ensure that the concrete surfaces will conform to the tolerances of ACI 117. Camber formwork where necessary to compensate for anticipated deflections due to fresh concrete and construction loads.

G. Chamfered Corners: Chamfer exposed corners 3/4 inch, unless otherwise indicated. Provide molding in forms for all chamfering required.

H. Form Ties: Use ties of sufficient strength and in sufficient quantities to prevent spreading of the forms. Place ties at least 1 inch away from the finished surface of the concrete.

I. Arrangement: Arrange formwork to allow proper erection sequence and to permit form removal without damage to concrete.

J. Joints: Install construction joints, isolation joints, shrinkage control joints and expansion joints as approved. Coordinate location of construction joints, particularly those exposed to view at walls and columns, in advance of concrete placement.

K. Embedded Piping and Rough Hardware:

1. Coordinate with other trades who are required to fasten materials to formwork, or who are required to insert piping, boxes, bolts, anchors, inserts, or other rough hardware, within the forms.

2. Locate conduits or pipes sleeves so as not to reduce the strength of the construction. Do not bury conduit in a concrete slab unless prior approval is obtained from the engineer.

City of Camarillo CONCRETE FORMWORK AND ACCESSORIES
CH-5067-2 031000-4

L. Waterstops: Install PVC water stops to form a continuous diaphragm at each joint. Make provisions to support and protect exposed waterstops during progress of construction. Fabricate field joints in waterstops in accordance with manufacturer's printed instructions.

M. Coating of Forms: Thoroughly clean forms and coat with specified form coating before each use. Do not reuse forms for exposed construction which cannot be reconditioned to "like new" condition. Apply form coating to forms in accordance with the manufacturer's specifications. Apply form coating to forms before placing reinforcing steel.

N. Inspection: Before placing of concrete, and after placement of reinforcing steel in the forms, provide sufficient prior notification so that proper inspection can be made.

O. Rejection of Defective Work: Any movement or bellying of forms during construction or variations in excess of the tolerances specified will be considered just cause for the removal of such forms and, in addition, the concrete construction so affected. Reconstruct forms, place new concrete and required reinforcing steel at no additional cost to the Owner.

3.02 REMOVAL OF FORMS:

A. F orm Removal: Do not remove concrete forms until concrete attains sufficient strength to support its own weight and all superimposed loads as determine by testing field cured concrete cylinders, but not sooner than specified in ACI 347.

1. Reshore structural members as specified below because of design requirements or construction conditions to permit successive construction.

2. Remove formwork progressively so unbalanced loads are not imposed on the structure.

3. Avoid damage concrete surfaces during form removal.

4. Store reusable forms for exposed architectural concrete to prevent damage to contact surfaces.

5. Remove formwork in same sequence as concrete placement to achieve similar concrete surface coloration.

B. Formwork for walls, sides of beams, and other parts not supporting the weight of the concrete may be removed as soon as the concrete has hardened sufficiently to resist damage from removal operations, particularly when form ties will be bent by the removal operations, but not sooner than 24 hours after placing concrete.

C. Formwork for girder and beam soffits and above grade slabs and other parts that support the weight of concrete, shall remain in place until the concrete has reached its specified 28 day strength, unless otherwise specified or permitted. Load supporting forms may be removed when concrete has attained 75 percent of required 28 day compressive strength, provided construction is reshored.

D. When shores and other vertical supports are so arranged that the form facing material may be removed without loosening or disturbing the shores and supports, the facing material may be removed at an earlier age as specified or permitted. The shores and supports shall remain in place until the concrete has reached its specified 28 day strength, unless otherwise specified or permitted.

City of Camarillo CONCRETE FORMWORK AND ACCESSORIES
CH-5067-2 031000-5

E. Whenever the formwork is removed during the curing period, cure the exposed concrete by one of the methods specified in Section 033000.

F. Construction loads exceeding the design loads shall not be imposed on any member unless it is properly shored and braced.

G. Use softwood wedges to release form faces from concrete. Do not pry with metal tool.

3.03 RESHORING:

A. When reshoring is permitted or required the operations shall be planned in advance and shall be subject to review.

B. Perform reshoring for the purpose of early form removal so that at no time will large areas of new construction be required to support their own weight. While reshoring is under way, no live loads shall be permitted on the new construction. Tighten re- shores to carry their required loads but do not over tightened so that the new construction is overstressed. Re-shores shall remain in place until the concrete has reached its specified 28 day strength, unless otherwise specified or permitted.

3.04 FIELD QUALITY CONTROL
A. Inspection: Obtain inspection and approval of forms before placing structural concrete.

END OF SECTION 031000 – CONCRETE FORMWORK AND ACCESSORIES

City of Camarillo CONCRETE REINFORCEMENT
CH-5067-2 032000-1

SECTION 032000 – CONCRETE REINFORCEMENT
PART 1 - GENERAL

1.01 SUMMARY
A. GENERAL
B. Section Includes:

1. Reinforcing bars for cast-in-place concrete.

2. Reinforcing mesh for cast-in-place concrete.

3. Accessories, including but not limited to, chairs and tie wires.

4. Furnish and deliver to site steel bar reinforcing for masonry.

5. Reinforcing bars for site-cast precast concrete.

6. Miscellaneous concrete work, including but not limited to areaways, cast-in- place valve boxes, pits, splash blocks, equipment bases, and other items as shown or required to complete all Work.

1.02 SUBMITTALS:

A. Shop Drawings: Submit including complete layouts, sections, and details for congested conditions, typical bending diagrams and offsets, splice lengths and locations, proposed layout where vertical and horizontal bars intersect, and wherever welding is proposed, detailed to conform to AWS and code requirements.

After approval of initial submission, subsequent submittals may be waived.

B. Certification: Submit copies of welding operator's certificate.

C. Chemical Analysis: Provide for bars to be welded, in accordance with code.

1.03 QUALITY ASSURANCE:

A. Source Quality Control: Refer to Section Division 1 of the specifications for general requirements and to following paragraphs for specific procedures. Testing Laboratory shall perform following conformance testing, shall select test samples of bars, ties, and stirrups from the material at the site or from place of distribution, each sampling including at least two 18" long pieces, and perform the following tests according to ASTM A615.

1. Identified Bars: If samples are obtained from bundles as delivered from the mill, identified as to heat number, accompanied by mill analyses and mill test reports, and properly tagged with Identification Certificate so as to be readily identified, perform one tensile and one bend test for each 10 tons or fraction thereof of each size of bars. Submit mill reports when samples are selected.

2. Unidentified Bars: When positive identification of reinforcing bars cannot be made and when random samples are obtained, perform tests for each 2.5 tons or fraction thereof, one tensile and one bend test from each size of bars.

City of Camarillo CONCRETE REINFORCEMENT
CH-5067-2 032000-2

B. Certification of Welders: All welding both in shop and in field shall be performed by certified welding operators.

1.04 MARKING AND SHIPPING:

A. Bundle bars, tag with identification, and transport and store so as not to damage any material. Use metal tags indicating size, length and other marking shown on placement drawings. Maintain tags after bundles are broken.

1.05 EXTRA MATERIAL:

A. Contractor shall provide for material and installation of an additional 3% of reinforcing steel in addition to quantities shown on drawings. This additional steel shall be installed during construction, in sizes and locations as directed. Provide unit price for purpose of adjusting contract price to reflect quantity of extra material actually used.

PART 2 - PRODUCTS

2.01 MATERIALS:

A. Reinforcing bars: ASTM A615, Grade 60, unless otherwise indicated on drawings.

B. Reinforcing bars for welding: ASTM A706, Grade 60.

C. Reinforcing mesh: ASTM A185, mesh size and gauge as shown, 65 ksi minimum tensile strength. Provide mesh in flat sheets only.

D. Tie wire: ASTM A82, Annealed copper-bearing steel, 16 gauge minimum.

E. Chairs and similar support items:

1. Standard manufactured products conforming to CRSI Manual of Standard Practice.

2. Use dense precast concrete supports with embedded wire ties for reinforcement placed on grade. Elsewhere, use wire bar supports.

F. Welding electrodes: AWS D1.4. – Low Hydrogen.

2.02 FABRICATION OF REINFORCING BARS:

A. Comply with CRSI Manual of Standard Practice for Reinforced Concrete Construction for fabrication of reinforcing steel.

B. Bending and Forming: Fabricate bars of the indicated sizes and bend and form to required shapes and lengths by methods not injurious to materials. Do not heat reinforcement for bending. Bend bars No. 6 size and larger in the shop only. Bars with unscheduled kinks or bends are subject to rejection. Use only tested and approved bar materials.

C. Welding: Use only ASTM 706 steel where welding is proposed. Perform welding, where shown or approved in accordance with AWS D1.4 using specified low - hydrogen electrodes. Protect joints from drafts during the cooling process; accelerated cooling is prohibited. Do not tack weld bars. Clean metal surfaces to City of Camarillo CONCRETE REINFORCEMENT
CH-5067-2 032000-3

be welded of all loose scale and foreign material. Clean welds each time electrode is changed and chip burned edges before placing welds. When wire brushed, the completed welds must exhibit uniform section, smooth welded metal, feather edges without undercuts or overlays, freedom from porosity and clinkers, and good fusion and penetration into the base metal. Cut out welds or parts of welds found defective with chisel and replace with proper welding. Prequalification of welds shall be in accordance with Code.

D. Galvanizing: Hot -dip galvanize fully completed reinforcing assemblies in accordance with ASTM A123 where indicated.

PART 3 - EXECUTION

3.01 INSTALLATION OF REINFORCING
A. Provide additional reinforcing bars at wall and slab openings as required. Before placing bars, and again before concrete is placed, clean bars of loose mill scale, oil, or any other coating that might destroy or reduce bond.

B. Securing in Place: Accurately place bars and wire tie in precise position where bars cross. Bend ends of wire ties away from the forms. Wire tie bars to corners of ties and stirrups. Support bars according to the current edition of "Recommended Practice for Placing Bar Supports" of Concrete Reinforcing Steel Institute, using approved accessories and chairs. Place precast concrete cubes with embedded wire ties to support reinforcing steel bars in concrete placed on grade and in footings. Use care not to damage vapor barriers where they occur.

C. Exposed Concrete Surfaces: Provide stainless steel or exterior quality vinyl plastic tipped chairs, bolsters, and accessories where exposed on exterior or interior concrete surfaces not to be painted or permanently covered.

D. Clearances: Maintain minimum clear distances between reinforcing bars and face of concrete as indicated or directed.

E. Splices: Do not splice reinforcing bars at the points of maximum stress except where indicated. Lap splices as shown or required to develop the full strength or stress of bars.

F. Field Welding of Bars: As specified for fabrication.

G. Maintaining Bars In Position: Take adequate precautions to assure that reinforcing position and spacing is maintained during placement of concrete.

H. Reinforcing Mesh: Lap one full mesh plus 2", or 9" whichever is greater, at splices, wire tie, and support the same as specified for bars.

1. Splice Devices: Type and manufacture, noted on drawings. If substitution is requested Contractor to supply manufacturer calculations and supporting data showing proposed substitution conforms to requirements indicated and supplied.

2. Install in accordance with manufacturer's written instructions.

3. Splice in a manner developing at least 150% of the yielding strength of the bar.

City of Camarillo CONCRETE REINFORCEMENT
CH-5067-2 032000-4

3.02 FIELD QUALITY CONTROL
A. Inspection: Obtain inspection and approval of reinforcing before concrete is placed.

B. Welding Inspection. Whether welding is done in the shop or at the site, perform welding of reinforcing bars under inspection of the Testing Laboratory Welding Inspector.

END OF SECTION 032000 – CONCRETE REINFORCEMENT

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-1

SECTION 033000 – CAST-IN-PLACE CONCRETE
PART 1 - GENERAL

1.01 SUMMARY
A. Furnish and install cast in place concrete as indicated on the drawings and specified including, the following:

1. Placing, patching, and initial curing of cast- in-place concrete unless otherwise specified. Fly ash shall be used to replace minimum 20% of the portland cement in the mix.

2. Grout and drypack, except as otherwise specified.

3. Placing of embedded anchor bolts and inserts.

4. Miscellaneous concrete work, including but not limited to areaways, cast-in- place valve boxes, pits, splash blocks, equipment bases, and other items as shown or required to complete all Work.

5. Slurry concrete.

1.02 SUBMITTALS:

A. Shop Drawings: Not Required.

B. Product Data: Submit the coloring admix manufacturer's technical data for products, methods, and color control procedures.

C. Certificates: Certify that materials meet requirements of paragraph "Quality Assurance".

D. Delivery Tickets: With each transit truck, provide delivery ticket, signed by an authorized representative of the batch plant, containing all information required by ASTM C94, as well as time batched, type and brand of cement, cement content, maximum size of aggregate and total water content.

1.03 QUALITY ASSURANCE:

A. Compliance with Regulations: All materials shall comply with the current rules and regulations of the local air quality management district, with the rules regarding volatile organic compounds, and with FDA rules and regulations for dangerous substances in construction products.

B. Concrete Manufacturer: Furnish concrete from licensed commercial ready -mix concrete plants conforming to ASTM C94 and approved by Building Official.

Requirements herein govern when exceeding ASTM C94.

C. Allowable Tolerances: Construct concrete conforming to the tolerances specified in ACI 117 "Recommended Tolerances for Concrete Construction and Materials", as applicable, unless exceeded by requirements of regulatory agencies or otherwise indicated or specified.

D. Source Quality Control: Refer to the following paragraphs for specific procedures.

Concrete materials which, by previous tests or actual service, have shown City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-2

conformance may be used without testing when so approved by the Architect and Building Official. Testing Laboratory shall perform following conformance testing.

1. Portland Cement: Furnish Mill Certificates, acceptable to Architect and Building Official, showing conformance with requirements specified; otherwise, the Testing Laboratory shall test each 250 barrels of cement in accordance with ASTM C150.

2. Aggregate For Normal Weight Concrete: Test the aggregate before and after concrete mix is designed and whenever character of aggregate varies or source of material is changed. Include a sieve analysis. Obtain samples of aggregates at the dry batching or ready-mix concrete plant in accordance with ASTM D75 and perform tests for the following properties:

3. Lightweight Aggregates: Test the lightweight aggregates before mix is designed and whenever the character of aggregate varies or source is changed in accordance with ASTM C330. Include a sieve analysis and report on unit weights, deleterious substances, unburned or underburned lumps, loss on ignition, soundness, and staining materials.

4. Color Control for Integrally -Colored Concrete: Color admix manufacturer shall furnish the services of his technical representatives equipped with wet- batch color control test devices at ready -mix plant and site as required to assure concrete of uniform color matching approved Samples, at no extra cost.

5. Exposed Architectural Concrete: Where exposed architectural concrete is indicated by the architect, concrete shall be constructed in accordance with the recommendations of ACI 303 – “Guide to Cast -in-Place Architectural Concrete Practice.”

6. Admixtures: The admixturer manufacturer’s technical representative shall review and approve the final mix designs with proposed admixtures for applicability to the project requirements.

PHYSICAL PROPERTIES
Physical Properties, units Test Method Minimum values
Sieve analysis ASTM C136
Organic impurities ASTM C40 Fine aggregate not darker than reference standard color
Soundness ASTM C88 Loss after 5 cycles not more than 8
percent of coarse aggregate, nor
more than 10 percent of fine
aggregate
Abrasion ASTM C131 Weight loss not more than 10.5
percent after 100 revolutions, 42
percent after 500 revolutions
Deleterious materials ASTM C33
Materials finer than No. 200
sieve
ASTM C117 Not over 1 percent for gravel, 1.5
percent for crushed aggregate
Reactivity potential ASTM C227, C289,
C342
Ratio of silica released to reduction
in alkalinity not to exceed 1.0.

Sand equivalent ASTM D2419 California sand equivalent values operating range not below 71
percent

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-3

1.04 CONCRETE MIX DESIGNS
A. Testing Laboratory shall design concrete mixes for concrete requiring 28- day compressive strength exceeding 2,500 psi. Contractor shall bear all costs for concrete mix designs.

B. Strength Requirements: Design mixes for structural concrete for minimum 28-day compressive strengths required by Drawings and Specifications. All mix designs for structural concrete shall be proportioned in accordance with ACI 318 – Chapter 5 and ACI 301. If trial batches are used, the mix design shall be prepared by an independent testing laboratory and shall achieve an average compressive strength 1,200 psi higher than the specified strength. This over-design shall be increased to 1,400 psi when concrete strengths over 5,000 psi are used.

C. Basis of Mix Designs: Design all mixes for workability and durability of concrete.

Control mixes in accordance with ACI 318 – Chapter 4 and ACI 301. Make adjustments in water/cement ratios as necessary for required concrete strengths at the Contractor's expense. Calcium chloride, thiocyanates or admixtures containing more than 0.05 percent chloride ions are not permitted.

D. Maximum Aggregate Sizes: Not exceeding 3/4 of minimum clear space between bars and between bars and forms, nor larger than 1/5 of least dimensions between the forms. Design the mixes with 3/4" maximum size, except maximum 1 1/2" size for foundations and maximum 3/8" size at congested reinforcing or thin sections, when approved by the Architect.

E. Lightweight Structural Concrete: Design for air-dry density of 110 pounds per cubic foot maximum. With each mix design, include test reports showing that concrete covered by the mix design meets shrinkage test requirements specified under Article "Field Quality Control" herein, or include certified test reports showing conformance as furnished by ready-mix concrete manufacturer.

F. Air Content: All concrete shall contain an air-entraining agent producing air content of 3.5% to 6.5% by volume and adjusted for weather conditions, and other concrete requirements.

1.05 DELIVERY, STORAGE, AND HANDLING:

A. Deliver all materials in timely manner to ensure uninterrupted progress of the Work.

B. Store materials by methods that prevent damage and permit ready access for inspection and identification.

1.06 PROJECT SITE CONDITIONS:

A. Do not place concrete during rain or adverse weather conditions without means to prevent all damage. Conform to requirements specified hereinafter whenever concrete placement is required during cold or hot weather.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-4

PART 2 - PRODUCTS

2.01 MATERIALS:

A. Portland cement: ASTM C150, Type I, Type II, low alkali. Do not change brand or source without prior approval.

B. White Portland Cement: ASTM C150, Type I, from one approved source. Use for integrally-colored concrete.

C. Aggregates:

1. Normal weight aggregates: ASTM C33.

2. Lightweight aggregates: ASTM C330, expanded shale type coarse aggregate, dry loose weight maximum 38 pounds per cubic foot, maximum 9/16" size; all aggregate vacuum or thermally fully saturated for pumped concrete.

D. Admixtures:

1. Chemical (Water Reducing) Admixture: ASTM C494, Type A, D, or E. Only one brand. When used, are subject to approval of Architect.

2. Air-entraining admix: ASTM C260.

3. Pozzolan: ASTM C618, Class F or C Fly Ash, 100 pounds maximum per cubic yard, containing 1 percent or less carbon. Fly ash shall not be used in excess of 20 percent by weight of total cement quantity.

4. Super-Plasticizers (High Range Water Reducers): ASTM C494, Type F or G. Only one brand, when used, are subject to approval of architect.

5. Color Admixture: As indicated or approved by architect.

E. Water: From potable domestic source.

F. Curing Materials:

1. Liquid Curing compound: Comply with the requirements of ASTM C309 and as recommended in ACI 308 – “Standard Practice for Curing Concrete”.

2. Curing sheet: Comply with the requirements of ASTM C171, non- staining white types, and as recommended in ACI 308 – “Standard Practice for Curing Concrete.

G. Non-shrink grout: Conform to Corps of Engineers CRD-C 621, and as follows:

1. Metallic for concealed areas: Master Builders "Embeco 885," or equal, non- gas-forming and free of oxidizing catalysts and inorganic accelerators, used as dry or damp pack, or mixed to a 20 -second flow (CRC -C 621), without segregation or bleeding at any temperature between 45 degrees F and 100 degrees F. Working time 30 minutes or more.

2. Non-metallic for exposed areas: Master Builders "Masterflow 928," or Euclid "Euco Hi-Flow Grout,” with same characteristics as specified for concealed areas.

3. Epoxy grout where indicated: Multi -component, premeasured, fast -curing combination of thermosetting resins and inert fillers, Master Builders City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-5

"Ceilcote 648," Sikadur 42 Industrial Group- Pak by Sika Chemical Corporation, or Euclid "Euco High Strength Grout."
H. Drypack: Field mixture of 1 part Portland cement to 2 parts fine aggregate mixed to a damp consistency such that a ball molded in the hands will stick together and hold its shape. At Contractor's option, the specified admixture may be added for increased workability at lower water/cement ratio. In lieu of field mixing, Contractor may use factory mixed drypack material, such as Master Builders "SetGrout" or Euclid "Euco Dry Pack Grout."
I. Expansion Joint Filler: Asphalt impregnated fiber or non-extruding foam type, conforming to ASTM D994 and D1751, or D1752.

J. Construction Joint Materials: As approved by engineer, of profiles indicated.

K. Bonding Agent: "Weld- Crete," manufactured by Larsen Products Co., P.O. Box 2127, Rockville, MD 20852, Master Builders "Concresive," or equal.

2.02 CONCRETE MIXING
A. Furnish ready-mixed concrete from an approved concrete batch plant. Conform to ASTM C94, except materials, testing, and mix designs as specified herein. Use transit mixer trucks equipped with automatic devices for recording number of revolutions of drum.

B. Admixtures: All approved admixtures shall be introduced into the concrete at the batch plant. Field additions are not acceptable.

C. Slump: Adjust quantity of water so concrete at point and time of placing does not exceed the following slumps when tested according to ASTM C143. Use the minimum water necessary for workability required by part of structure being cast.

SLUMP AND WATER/CEMENT RATIOS
Part of Structure
Maximum
Slump Inches*
Maximum Water-
Cement Ratio
Footings, foundation walls, and mass concrete. 4 0.60 Slabs on grade, reinforced and non-reinforced 4 0.60 Reinforced concrete over 8" thick 4 0.60
Reinforced concrete 8" or less thick 4 0.60
All other concrete 4 0.60

1. *If super-plasticizers are used, slumps may be as indicated by admixture manufacturer, with water -cement ratio unchanged or lower than slumps without admixture.

2.03 REQUIREMENTS FOR COLORED CONCRETE
A. Cement for the entire project shall be same type and brand, and from the same mill.

Aggregate, both fine and coarse, shall be supplied from one source. Mix design shall remain constant for all colored concrete. Slump shall not exceed 4 inches.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-6

B. Mixers transporting concrete shall be thoroughly cleaned prior to loading colored concrete.

C. Pigments shall be added to mix at the plant, and shall be measured accurately. The mixer shall be operated at charging speed for 5 to 10 minutes while color is being added.

2.04 SLURRY CONCRETE
A. Slurry concrete shall conform to requirements of this section for regular concrete, except that testing will not be required. Slurring concrete shall contain not less than 2 sacks of cement per cubic yard. Aggregate may be material selected from excavation, free from organic matter, or imported fill, conforming to the following gradation:

Sieve Size Percent passing
1-1/2" 100
1" 80 - 100
3/4" 60 - 100
3/8" 50 - 100
No. 4 40 - 80
No. 100 10 - 40

B. Sufficient water shall be added to produce a fluid, workable mix that will flow and can be pumped without segregation of aggregate. Materials shall be mechanically mixed until the cement and water are thoroughly dispersed.

PART 3 - EXECUTION

3.01 PREPARATION FOR CONCRETE PLACING:

A. Remove all free water from forms before concrete is deposited. Remove hardened concrete, debris, and foreign materials from interior surfaces of forms, exposed reinforcing, and from surfaces of mixing and conveying equipment.

B. Wetting: Wet wood forms sufficiently to tighten up cracks. Wet other materials sufficiently to reduce adsorption and to help maintain concrete workability.

C. Earth Subgrade: Dampen 24 hours before placing concrete, but do not muddy. Re- roll where necessary for smoothness and remove loose material.

D. Gravel Fill: Recompact disturbed gravel and bring to correct elevation.

E. Sand Beds or Subslab Drainage Fill: Recompact disturbed material and bring to correct elevation.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-7

3.02 CONCRETE PLACING
A. Conveying and Placing: Do not place concrete until the reinforcing steel, forms, or metal decking have been approved. Do not use aluminum tubes or any aluminum equipment for pumping concrete, nor allow concrete to free fall from its point of release at m ixer, hoppers, tremies, or conveying equipment more than 6 feet for concealed concrete and 3 feet for exposed concrete. Deposit concrete so that the surface is kept level throughout, a minimum being permitted to flow from one portion to another. Place concrete in horizontal layers not more than 18" thick within 45 minutes after water is first added to the batch. Place concrete by methods that prevent segregation of materials.

1. Where new concrete is placed against or on old or existing concrete, clean and roughen existing surface to 1/4” amplitude and apply bonding agent to properly prepared surface of old concrete prior to placement of new concrete.

B. Joints In Concrete: Locate joints only where approved, and obtain prior approval for points of stoppage of any pour. Clean and roughen the surface of construction joints by removing the entire surface and exposing 1/4" amplitude of clean aggregate solidly embedded in mortar matrix by sandblasting, chipping, use of an approved surface retarder, or equal. Water and keep hardened concrete wet for not less than 24 hours and slush with portland cement slurry just before placing joining concrete. Cover horizontal surfaces of existing or previously placed and hardened concrete with a 2" thick layer of fresh concrete less 50% of coarse aggregate just before balance of concrete is placed.

C. Compacting: Compact each layer of the concrete as placed with mechanical vibrators or equivalent equipment. Transmit vibration directly to concrete and in no case through the forms unless approved. Accomplish thorough compaction.

Supplement by rodding or spading by hand adjacent to forms. Compact concrete into corners and angles of forms and around reinforcement and embedded fixtures.

Recompact deep sections with congestion due to reinforcing steel as required.

D. Operation of Vibrators: Do not horizontally transport concrete in forms with vibrators nor allow vibrators to contact forms or reinforcing. Push vibrators vertically into the preceding layers that are still plastic and slowly withdraw, producing maximum obtainable density in concrete without creating voids or segregation. In no case disturb concrete that has partially set. Vibrate at intervals not exceeding two-thirds the effective visible vibration diameter of the submerged vibrator. Avoid excessive vibration that causes segregation. Use and type of vibrators shall conform to ACI 309 "Recommended Practice for Consolidation of Concrete".

E. Correction of Segregation: Before placing next layer of concrete, and at the top of last placement for vertical elements, remove concrete containing excess water or fine aggregate or showing deficiency of coarse aggregate and fill the space with compacted concrete of correct proportions.

F. Waterproof Membranes: Perform work adjacent to waterproof membranes to prevent damage to membranes. Arrange work so that membrane is left unprotected for minimum period of time, as approved. Prior to placing concrete, inspect the membrane and arrange for repair to all damage which may have occurred.

G. Concrete Encased Columns: Clean columns as specified for cleaning other steel in contact with concrete. When concrete is not carried to structure above, stop City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-8

concrete perpendicular to column axis at the same elevation on all parts of all columns in the space. Float top neatly to column.

H. Slabs:

1. Float Finish: Place, consolidate, strike off and level concrete slab to proper elevation. Use highway straightedge, bull float or darby. Remove all bleed water. After the concrete has stiffened sufficiently to permit the operation, and water sheen has disappeared, the surface shall be floated, at least twice, to a uniform sandy texture.

2. On-Grade Slabs: Place with maximum 40 -foot edge dimension. Generally locate joints on column lines, exact locations as directed or approved.

3. On-Grade Slab Construction and Contraction Joints: Use types as indicated at column lines and intermediate locations.

4. Expansion Joints: Conform to details and approved submittal. Provide expansion joint filler finished flush with slab surface except for those joints shown to be sealed with sealant.

5. Control Joints: Provide for concrete slabs as indicated. At Contractor's option, "Soff-Cut" saw may be used to depth of 1 1/4" providing spalling or undercutting of the concrete does not occur, and in no case shall slab reinforcement be cut or damaged. Conventional saws shall be used as soon as possible without dislodging aggregate to 1/4 slab thickness. Complete sawing of joints within 12 hours after finishing is completed. If early sawing causes undercutting or washing of the concrete, delay the sawing operation and repair the damaged areas. The saw cut shall not vary more than 1/2 inch from the true joint alignment. Discontinue sawing if a crack develops ahead of a saw cut. Immediately after each joint is sawed, thoroughly clean the saw cut and adjacent concrete surface. Respray surfaces treated with curing compound which are damaged during the sawing operations as soon as the water disappears. Protect joints in a manner to prevent the curing compound from entering the joints.

3.03 COLD WEATHER PROVISIONS
A. Conform to the provisions of ACI 306, Recommended Practice for Cold Weather Concreting, except as modified herein.

B. Normal Concrete: When the temperature is below 40 degrees F. the temperature of the concrete placed in the forms shall be at least 60 degrees F. When the temperature is below 30 degrees F. the temperature of the concrete as mixed shall be 65 degrees F. In all cases, when the daily average temperature is below 40 degrees F. the concrete shall be kept at 55 degrees F. for the 72 hours and then allowed to drop uniformly to the air temperature over the next 24 hours.

1. Concrete temperature shall be measured by placing a thermometer 2" from the top of the concrete being placed.

C. Air-entrained concrete shall be kept at the above temperature for 27 hours and above freezing for an additional 72 hours.

D. No calcium chloride shall be used to accelerate hardening of concrete. Contractor to certify that any additive used does not contain calcium chloride.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-9

E. If low temperature accelerating admixture is proposed, adjust concrete mix as required and obtain approval of Architect.

F. All concrete materials, reinforcement, forming materials and ground with which concrete is to come in contact shall be free of frost.

G. The covering or other protection used in connection with the curing shall remain in place and intact for at least 24 hours.

H. The work shall be protected from the elements, flowing water, and defacements of any nature during the construction operations.

3.04 HOT WEATHER PROVISIONS
A. Conform to ACI 305R and the following requirements.

B. Take extra care to reduce the temperature of the concrete being placed, and to prevent rapid drying of newly placed concrete. When the outdoor ambient temperature is more than 90 degrees F., shade the fresh concrete as soon as possible after placing, and start curing as soon as the surface of the fresh concrete is sufficiently hard to permit it without damage.

C. Concrete placement temperatures shall be controlled by the Contractor and shall not be limited to:

1. Shading and cooling the aggregate;

2. Avoiding use of hot cement;

3. Cooling mixing water by additions of ice;

4. Insulating water supply lines and tanks; and

5. Insulating mixer drums or cooling them with sprays or wet burlap.

3.05 CONCRETE CURING
A. Comply with the recommendations of ACI 308 – “Standard Practice for Curing Concrete.”
B. Keep forms containing concrete in a wet condition until removed. Keep concrete continuously moist for not less than 7 days after placement. Keep concrete moist with a fine fog water spray until protected by curing media.

C. During times of dry or excessive winds, high ambient temperature, low humidity, or other ambient conditions causing rapid drying, use specified evaporation retardant and finishing aid material according to the manufacturer's instructions and cure concrete with a fine fog spray of water, or equal, applied both during and after finishing and continued until final curing operations are started.

D. Use the water curing method, curing sheet material, or a clear liquid membrane - forming curing compound except as otherwise specified.

E. Do not use any type of finishing or curing materials or methods that interfere with the correct application or bonding of subsequent materials; verify exact requirements as they apply to all applicable materials.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-10

3.06 PATCHING FORMED CONCRETE
A. Remove fins, projections, and offsets. Cut out rock pockets, honeycomb, and all other defects to sound concrete, with edges of cuts straight and back -beveled.

Dampen cut-outs and edges, and scrub with neat portland cement slurry just before patching, or an apply approved epoxy concrete adhesive.

B. Saturate form tie holes with water and fill voids and patches with flush smooth- finished mortar of same mix as concrete (less coarse aggregate), cure, and dry.

3.07 FINISHING
A. Match up finish work to adjacent or nearby surfaces at all joints, edges, and corners.

Coordinate sawn joints, to keep all joints straight and continuous. Keep joint lines uniform and free of damage.

B. Floating, troweling, and special finishes shall be as noted on the Drawings. Do not begin floting until bleed water is gone and avoid over-troweling. Do not dust cement to expedite troweling start time. Remove any marks left by finishing tools.

C. Complete finishes as shown on the Drawings including trowelded finish for walking surfaces or those receiving floor covering or membrane. Broom finish shall be light, medium or coarse, at the direction of the architect. Scratched finish for surfaces to receive Cementitious material. Non- slip finish for steps, landings, platforms, and ramps.

D. After first floating check plane of surface with 10’ steel straightedge. Finish work, measured with a 10’ straightedge, must be a tolerance of 1/8” in 10’ in any direction for slabs under flooring; a true plane of 1/4” in 10’ for intermediate grade work.

3.08 GROUTING AND DRYPACKING
A. Install as indicated or required. Where grouting and drypacking is part of the work of other sections, it shall conform to the following requirements, as applicable.

B. Drypacking: Mix materials thoroughly with minimum amount of water. Install drypack by forcing and rodding to fill voids and provide complete bearing under plates. Finish exposed surfaces smooth and cure with damp burlap or liquid curing compound.

C. Non-Shrink Grouting:

1. Mixing: Mix the approved non-shrink grout material with sufficient water per manufacturers recommendations.

2. Application: Surfaces to receive the non- shrink grout shall be clean, and shall be moistened thoroughly immediately before placing the mortar. Before grouting, surfaces to be in contact shall be roughened and cleaned thoroughly, all loose particles shall be removed and the surface flushed thoroughly with neat cement grout immediately before the grouting mortar is placed. Place fluid grout from one side only and puddle, chain, or pump for complete filling of voids; do not remove the dams or forms until grout attains initial set. Finish exposed surfaces smooth, and cure as recommended by grout manufacturer.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-11

3.09 OFF-SITE CONCRETE WORK
A. Provide new concrete items where indicated, and replace existing items damaged by Contractor's operations. Secure and pay for required permits, inspections, engineering, and surveying.

3.10 SLURRY CONCRETE
A. Slurry concrete may be used as fill or backfill where indicated or approved by the geotechnical engineer. Slurry concrete shall be placed within 1 hour after mixing, and shall be placed in manner that will prevent voids in, or segregation of, the concrete.

B. Backfilling over slurry concrete shall not be done less than 4 hours after placing.

3.11 FIELD QUALITY CONTROL
A. Level of Floors: Continuously monitor concrete placing to maintain level floor by use of an instrument level, transit, or laser.

B. Continuous Inspection: Construct structural concrete exceeding 2,500 psi compressive strength under continuous inspection of Inspector. Obtain inspection and approval of forms and reinforcing by Building Department as required and by the Inspector before placing structural concrete.

C. Testing of Concrete: Testing Laboratory shall perform following tests. Samples for testing shall be obtained in accordance with ASTM C172, and shall be taken from as close to point of placement as possible.

1. Compressive Strength Tests: Cast one set of four or more cylinders from each day's placing and each 150 cubic yards, or fraction thereof, or not less than once for each 2,000 square feet of surface area for slabs and walls, of each strength of structural concrete. Date cylinders, assign record number, and tag showing the location from which sample was taken. Also record slump test result of sample. Do not make more than two series of tests from any one location or batch of concrete.

2. Test Cylinders: Samples will be made in accordance with ASTM C172. Cast cylinders according to ASTM C31; 24 hours later, store cylinders under moist curing conditions at about 70 degrees F. Test according to ASTM C39 at 7 and 28 day ages. The remaining cylinder shall be kept in reserve in case tests are unsatisfactory.

3. Control Test Cylinders: Cast a set of two or more cylinders for each day's placing of concrete for slabs supported on shoring. Place test cylinders on slabs represented by cylinders and cure the same as slabs. Test cylinders to determine proper times for removal of shores and reshoring. A strength test shall be the average of the compressive strengths of 2 cylinders made from the same sample of concrete.

D. Tests for Lightweight Structural Concrete: Perform following test for each 150 cubic yards of lightweight structural concrete.

1. Along with slump test, ASTM C143, and from same sample, determine air content, unit weight and yield per ASTM C138.

City of Camarillo CAST-IN-PLACE CONCRETE
CH-5067-2 033000-12

2. Shrinkage Test: Cast 4" by 4" by 11" long bars with 10" effective gauge length, cured for 7 days in moist room and as specified in ASTM C157. Make measurements at 7-day intervals to 35 day age. Allowable shrinkage shall not exceed 0.05% after period of 35 days.

3. Previous Shrinkage Tests: Ready -mix concrete manufacturer may furnish certified test reports from an approved Testing Laboratory as proof of meeting shrinkage requirements provided aggregates used and concrete covered by such test reports conform to the mix design approved for use on the Work.

E. Core Tests: If tests show the compressive strength of any concrete falls below the required minimum, additional testing of concrete which unsatisfactory tests represent may be required. Make core samples according to ASTM C42. Fill core holes with drypack concrete of strength required for concrete. Contractor shall bear cost of tests for below -strength concrete even if such tests indicate concrete has attained required minimum compressive strength, and all costs for required corrections.

END OF SECTION 033000 – CAST-IN-PLACE CONCRETE

City of Camarillo DRYPACK AND MECHANICAL ANCHORS CH-5067-2 037000-1

SECTION 037000 – DRYPACK AND MECHANICAL ANCHORS
PART 1 - GENERAL

1.01 SUMMARY
A. Description of Work: Work included, but not necessarily limited to: Placement of mechanical anchors into concrete and drypacking of baseplates, as shown on the drawings and as specified herein.

1.02 References:

A. American Society of Testing Materials (ASTM):

1. C 150 Portland Cement.

B. International Code Council Research Report

1. Wedge Anchors
a. ESR-1917 Hilti Kwik Bolt TZ by Hilti Corporation
b. ESR-2251 ITW Ramset/Redhead Trubolt
c. ESR 1396 Simpson Wedge All

2. Screw Anchors
a. ESR-1423 HUS-H Concrete Screw Anchor by Hilti Corp. b. ESR-1059 Simpson Titen HD Screw Anchor
PART 2 - PRODUCTS

2.01 Materials:

A. Cement: Portland Cement Type II, low alkali, conforming to ASTM C 150. One brand of cement shall be used throughout the work for structural purposes.

B. Silica Sand: A factory processed oven -dried aggregate, conforming to ASTM C 144, gradation as indicated.

C. Water: Clean, fresh, free from acid, alkali, organic matter or other impurities liable to be detrimental to the concrete.

D. Mechanical Anchor:

1. Wedge Anchors
a. Hilti Kwik Bolt TZ by Hilti Corporation
b. ITW Ramset/Redhead Trubolt
c. Simpson Wedge All

2. Screw Anchors
a. HUS-H Concrete Screw Anchor by Hilti Corp.
b. Simpson Titen HD Screw Anchor
City of Camarillo DRYPACK AND MECHANICAL ANCHORS CH-5067-2 037000-2

2.02 Drypack Mix:

A. A sand-cement mixture at 3:1 ratio with enough water added to dampen the entire mixture.

PART 3 - EXECUTION

3.01 Drilling Concrete and Masonry :

A. Verification: Prior to drilling or coring, verify that all existing conditions are compatible with the proposed methods of construction as shown on the drawings and specified herein.

B. Drilling Existing Concrete: Drills used shall be a diamond core or carbide- tipped helical drill bits. Drill to required depth and diameter exercising caution so as not to spall or crack existing concrete. Use minimal water as necessary for drilling. No impact drilling allowed.

C. Hole size drilled shall be per manufacturer recommendations for the anchor utilized.

3.02 Mechanical Anchor Placement:

A. Cleaning: Clean holes with a jet of compressed air and nylon brush. Concrete holes that are fouled with oil or dust shall be cleaned with toluene and a bottle brush prior to placement of anchor.

B. Install anchor in compliance with manufacturer recommendations. Do not overtorque or damage anchor during installation.

3.03 Field Quality Control:

A. Anchor Placement: Mechanical Anchors do not need to be installed in the presence of a deputy inspector, unless specifically noted on the approved drawings.

B. Clean-up:

At completion of concrete work, remove all concrete debris, slurry, hardened concrete, and other waste products.

END OF SECTION 037000 – DRYPACK AND MECHANICAL ANCHORS

City of Camarillo CONCRETE UNIT MASONRY
CH-5067-2 042200-1

SECTION 042200 – CONCRETE UNIT MASONRY
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Concrete block masonry.

2. Grouting of masonry.

3. Installing reinforcing steel bars in masonry.

B. Related Work Specified Elsewhere:

1. Furnishing and delivery of steel bar reinforcing for masonry.

2. Water repellent sealer.

1.02 SUBMITTALS
A. Mix Designs: Submit for mortar and grout.

1.03 JOB CONDITIONS
A. Inspect and verify surfaces to receive Work of this Section. Report all conditions that prevent correct installation of masonry.

1.04 QUALITY ASSURANCE
A. Tolerances: Unit masonry shall be placed within 1/8" of dimensions noted.

Reinforcement shall be placed within tolerances recommended by ACI Detailing Manual, 1980 Edition, Special Publication, SP 66.

B. REFERENCES, CODES AND STANDARDS: The following latest edition of the references, codes and standards are hereby made a part of this Section and work shall conform to the applicable requirements therein except as otherwise specified herein or shown on the Drawings. Latest edition of references and codes adopted by the Governing Agency shall apply. Nothing contained herein shall be construed as permitting work that is contrary to code requirements.

1. California Building Code (CBC) latest edition.

2. ACI 530.1 – Latest Revision, “Specification for Masonry Structures”.

PART 2 - PRODUCTS

2.01 BASIC MATERIALS
A. Portland cement: UBC Std. 19-1/ASTM C150, Type I or II, low alkali; mortar cement or plastic cement not permitted. Use one brand.

B. Hydrated lime: UBC Std. 21-13/ASTM C207, Type S.

City of Camarillo CONCRETE UNIT MASONRY
CH-5067-2 042200-2

C. Mortar sand: UBC Std. 21- 14 and ASTM C144, minimum 4% passing No. 100 sieve, uniformly graded fine to coarse.

D. Grout aggregates: UBC Std. 21-19 and ASTM C404, natural, Size No. 1 or No. 2 for fine aggregate, Size No. 8 for coarse aggregate.

E. Mortar admix: None without prior approval of Architect and Structural Engineer.

F. Grout admix: Sika Chemical Corp. GA Grout Aid, type as required; or equal.

G. Color pigment: Pure ground mineral oxides, non- fading, alkali and lime proof, factory packaged, not more than 3 pounds per sack of cement.

H. Control joint filler: Dur-O-Wal "Rapid Control Joint" or approved equal, wide flange unless regular flange is shown, approved sizes.

2.02 CONCRETE BLOCK MATERIALS
A. General: Block shall be as indicated on the drawings and conform to ASTM C90, Grade N 1, steam -cured or yard air cured for 28 days, meeting Quality Control Standards of Concrete Masonry Association, natural cement color smooth faced units unless otherwise indicated or specified. Include matching jamb, lintel, control joint, bond beam, wall cap, and other special shape, type, or size units as required.

B. Colored Concrete Block: Same as above except integrally colored, color as selected from tan or buff range of colors.

C. Slump Stone or Split -Face Concrete Block: Integrally colored of the color as selected from tan or buff range of colors, with approved texture on all exposed faces and ends.

2.03 MORTAR AND GROUT PROPORTIONS AND MIXING
A. Strengths: Minimum compressive strengths, 1,800 psi for mortar and 2,000 psi for grout at 28 days unless noted otherwise.

B. Proportions: Accurately measure all mortar and grout by the volume method using calibrated containers. Shovel measurements are not acceptable.

1. Mortar: Per 2103.3, one part portland cement, 3 1/2 to 4 parts sand based on dry loose volume, and not less than 1/4-part nor over 1/2-part lime.

2. Grout: Per 2103.4, and as follows. Mix with enough water to produce consistency for pouring without segregation.

3. Colored Mortar: Same as for mortar plus add color pigment to produce cured dry color matching concrete unit color and the approved Sample.

C. Mixing: Place half of the required water and sand in an operating machine mixer; then add portland cement, remainder of sand and water, and then hydrated lime.

Machine mix not less than 5 minutes after all ingredients are charged.

D. Retempering: Retemper mortar within one hour after leaving the mixer and maintain high plasticity. Add water in a basin formed in the mortar and rework mortar into water. Discard all mortar that is not used within one hour or that has begun to initially set.

City of Camarillo CONCRETE UNIT MASONRY
CH-5067-2 042200-3

PART 3 - EXECUTION

3.01 INSTALLATION OF CONCRETE BLOCK MASONRY
A. General: Lay out unit masonry to minimize cutting of units and use of odd joint sizes or bond. Construct all masonry in accordance with Code and Concrete Masonry Association standards for reinforced masonry. Place and embed in masonry anchors, bolts, reglets, sleeves, conduits, and all other items furnished under other Sections, fully grouted in place. Work out details and be responsible for size, position, and arrangement of embedded items and necessary openings. Cut units by machine saw. Install only clean uncracked units.

B. Setting: Install masonry to preserve unobstructed vertical continuity of block cells.

Full bed face shells and cross webs in mortar. Fill header or end joints solid with mortar to a depth from face of wall or unit not less than the thickness of the longitudinal face shells. Provide corner bond by lapping units in successive vertical courses.

C. Cleanout Openings: Provide openings at the bottom of cells containing bar reinforcing, and at each lift or pour of grout exceeding 48" height. Remove all overhanging mortar and other obstructions or debris from the interior of block cells.

Seal cleanouts with matching whole units and mortar joints D. Reinforcing: Use deep- cut bond beam units at horizontal reinforcing bars. Install open end units for vertical bars unless otherwise shown. Hold vertical reinforcing bars in correct position at top, bottom, and intervals not over 160 bar diameters between, and secure in place with wood frames or similar devices as required for proper alignment. Install horizontal reinforcement as erection progresses, laps wire tied. Maintain a minimum 3/4" clear space between masonry and bars. Make laps and splices in bars not less than 40 bar diameters unless otherwise indicated.

E. Grouting: Fill all cells with grout except where noted otherwise in the drawings.

Pour in 4- foot lifts, waiting about 1 -hour between lifts. Pour full height in each section of the wall in one work shift. Consolidate grout by puddling or internal vibration, then reconsolidate about 10 minutes later before plasticity is lost. Form horizontal construction joints by stopping the grout pour 1 1/2" below the top of masonry units. High lift grout placement may be used at Contractor's option as approved by the Architect and Structural Engineer and according to Code.

F. Bond and Joints: Lay units with 1/2 -unit running bond, vertical joints in alternate courses aligned and plumb. Make joints uniformly 3/8" size, concealed joints struck flush. Compact and dense concave tool exposed joints with 1 1/2" diameter plastic or similar non-staining tool.

G. Weep Holes: Provide 1/4" diameter weep holes at bottom of ungrouted cells of exterior walls, or provide weep holes at maximum 32" centers with drain slots under webs of intervening units.

3.02 WALL CONTROL JOINTS
A. Provide for walls where shown, control joint filler placed for full height of each joint.

Caulk exterior face of joints with elastomeric sealant.

B. Unless lesser distance apart is indicated on the drawings, construct control joints at 40’ on centers.

City of Camarillo CONCRETE UNIT MASONRY
CH-5067-2 042200-4

3.03 PARGING
A. Parge walls wherever required to assure smooth surfaces to receive waterproofing.

B. Clean wall surfaces thoroughly. Apply Larson Products Co. Weldcrete bonding agent to surfaces of wall in accordance with manufacturer's instructions.

C. Apply parge coat of Type S mortar, conforming to Title 24, Table 21- A (1 part Portland cement, 1/4 to 1/2 part hydrated lime, 2-1/4 to 3 parts fine aggregate) with Laticrete latex admix added per admix manufacturer's directions. Apply in 2 uniform coats to a total thickness of 3/4 inch. Scarify first parging coat to ensure full bond to subsequent coat.

D. Use a steel trowel finish to produce a smooth, flat, dense surface with a maximum surface variation of 1/8 inch per foot. Form a wash at top of parging and a cove at bottom. Damp cure parging for at least 24 hours and protect until cured. Provide nailers if required for attachment of membrane.

3.04 CEMENT WASH ON WALL TOPS
A. Use mortar the matching masonry joints. Trowel dense and smooth with clean edges, sloped as shown or directed, and cross score using an approved tool at nominal 32" centers. As soon as hardened, cover with sealed plastic sheeting and keep moist for at least 10 days after placing.

3.05 CURING
A. Keep newly constructed masonry damp for 3 days with regulated fog spray of water sufficient only to moisten faces of masonry but not in an amount as to cause water to flow down over masonry. Do not saturate masonry with water for curing or any other purposes and protect from rain or flooding during curing period.

3.06 CLEANING
A. Clean mortar and grout off exposed surfaces immediately and as the Work progresses. Acceptably repair imperfect joints, holes, defaced units, chipped edges or corners, and all other defects, or replace the defective units as required for approval. Mortar or grout staining on exposed masonry surfaces is subject to sandblast cleaning of the entire surface involved to obtain clean uniform approved appearance, as directed and at no additional contract cost.

3.07 FIELD QUALITY CONTROL
A. Testing: Testing Laboratory shall test mortar and grout to extent shown, directed, or required by Code.

B. Continuous Inspection: Required if indicated, and for high lift grouting operations.

END OF SECTION 042200 – CONCRETE UNIT MASONRY

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-1

SECTION 055000 – METAL FABRICATIONS
PART 1 - GENERAL

1.01 SUMMARY
A. A. Section includes metal fabrications and includes, but is not limited to, the following types of fabrications:

1. Steel gates and hardware

1.02 COORDINATION
A. Coordinate installation of anchorages for metal fabrications. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

1.03 ACTION SUBMITTALS
A. Product Data: Submit product data for the following:

1. 1.Paint products.

2. Grout.

B. CALgreen Submittals:

1. Product Data for Section 5.504.4.1.1: Provide documentation for adhesives, adhesive bonding primers, adhesive primers, sealants, sealant primers and caulks, including printed statement of VOC content showing compliance with local or regional air pollution control or air quality management district rules where applicable, or SCAQMD 100 Rule 1168 VOC limits as shown in CALgreen Tables 5.504.4.1 and 5.504.4.2.

2. Product Data for Section 5.504.4.1.2: Provide documentation for aerosol adhesives, and smaller unit sizes of adhesives, sealant, and caulking compounds (in units of product, less packaging, which do not weigh more than one (1) pound and do not consist of more than sixteen (16) fluid ounces) comply with statewide VOC standards and prohibitions on use of certain toxic compounds, of CCR Title 17, commencing with Section 94507.

3. Product Data for Section 5.504.4.3: For architectural paints and coatings, provide documentation including printed statement of VOC content showing compliance with Table 1 of the ARB, Architectural Coatings Suggested Control Measure, unless more stringent local limits apply.

4. Product Data for Section 5.504.4.3.1: Aerosol paints and coatings, provide documentation that products meet the PWMIR Limits for ROC in Section 94522 (a)(3) and other requirements, including prohibitions on use of certain toxic compounds and ozone depleting substances, in Section 94522(c)(2 and (d)(2) of CCR Title 17.

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-2

C. Shop Drawings: Submit shop drawings detailing the fabrication and erection of each metal fabrication indicated. Include plans, elevations, sections, and details of metal fabrications and their connections. Show anchorage and accessory items.

1. For installed products indicated to comply with design loads, include structural analysis data, for information only, signed and sealed by the qualified professional engineer responsible for their preparation.

2. Include plans and elevations at not less than 1" to 1'-0" scale, and include details of sections and connections at not less than 3" to 1'-0" scale.

1.04 INFORMATIONAL SUBMITTALS
A. Welding Certificates: Copies of certificates for welding procedures and personnel.

B. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

1.05 QUALITY ASSURANCE
A. Fabricator/Installer Qualifications: A firm experienced in producing metal fabrications similar to those indicated for this Project for a minimum of 5 years, with a record of successful in-service performance, with sufficient production capacity to produce required units without causing delay in the work.

B. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of metal fabrications that are similar to those indicated for this Project in material, design, and extent.

C. Welding: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code--Steel."

2. AWS D1.2/D1.2M, "Structural Welding Code--Aluminum."

3. AWS D1.3/D1.3M, "Structural Welding Code--Sheet Steel."

4. Certify that each welder has satisfactorily passed AWS qualification tests for welding processes involved and, if pertinent, has undergone recertification.

D. Sample Installation:

1. Following review of samples, construct sample installation of the following:
a. Sample gate: 24” x 24”; hinges welded to gate post

2. The sample installation shall be complete with hinges, jointing, finished, as shown in accordance with the final shop drawings. Sample installations shall be reviewed by the Architect and/or Owner for acceptance of workmanship only. Replace unsatisfactory work as directed for final acceptance. Maintain sample installations during construction as a standard for judging acceptability of work. Properly finished and City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-3

maintained sample installation may be retained as a portion of the completed Work.

1.06 DELIVERY, STORAGE, AND HANDLING
A. Store metal fabrications in a dry, well -ventilated, weathertight place. Deliver and handle so as to prevent any type of damage to the fabricated work

1.07 FIELD CONDITIONS
A. Field Measurements: Where metal fabrications are indicated to fit walls and other construction, verify dimensions by field measurements before fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

B. Established Dimensions: Where field measurements cannot be made without delaying the Work, establish dimensions and proceed with fabricating metal fabrications without field measurements. Coordinate construction to ensure that actual dimensions correspond to established dimensions. Allow for trimming and fitting.

PART 2 - PRODUCTS

2.01 PERFORMANCE REQUIREMENTS
A. Structural Performance - Exterior Metal Fabrications: All exterior metal fabrications shall be fabricated and installed to prevent buckling, opening up of joints and overstressing of welds and fasteners under the following temperature conditions:

1. Base fabrication on a temperature of +70 deg F at time of installation with allowance made for an exposed metal surface temperature range of -5 deg F to +180 deg F. Make all necessary adjustments and provisions for concealed expansion.

2.02 METALS, GENERAL
A. Metal Surfaces, General: For metal fabrications exposed to view in the completed Work, provide materials with smooth, flat surfaces without blemishes. Do not use materials with exposed pitting, seam marks, roller marks, rolled trade names, or roughness.

2.03 FERROUS METALS
A. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.

B. Stainless-Steel Sheet, Strip, Plate, and Flat Bars: ASTM A 666, Type 304.

C. Stainless-Steel Bars and Shapes: ASTM A 276, Type 304.

D. Cold Finished Steel Bars: ASTM A 108, grade as selected by fabricator.

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-4

E. Rolled-Steel Floor Plate: ASTM A 786/A 786M, rolled from plate complying with ASTM A 36/A 36M or ASTM A 283/A 283M, Grade C or D.

F. Rolled-Stainless-Steel Floor Plate: ASTM A 793.

G. Steel Tubing: Cold- formed steel tubing complying with ASTM A 500/A 500M, or hot formed steel tubing complying with ASTM A 501/A 501M.

H. Steel Pipe: ASTM A 53/A 53M, standard weight (Schedule 40) minimum, unless otherwise indicated or required to satisfy the performance requirements; finish as follows:

1. Black finish, unless otherwise indicated.

2. Galvanized finish for exterior installations and where indicated.

I. Slotted Channel Framing (Unistrut): Cold-formed metal channels with continuous slot and with flanged edges returned toward web complying with MFMA -4 and fabricated from steel complying with ASTM A 1011/A 1011M. Width, depth, and metal thickness as required to suit performance requirements.

J. Malleable-Iron Castings: ASTM A 47, Grade 32510.

K. Gray-Iron Castings: ASTM A 48, Class 30, unless another class is indicated or required by structural loads.

L. Cast-in-Place Anchors in Concrete: Anchor channel type, with filler strips, manufactured from formed hot or cold rolled carbon steel channels with flange edges returned toward web, having a minimum of 2 stud, or I, anchors shop welded to the back of each channel, complying with ASTM A 1011. Provide channels, bolts, washers, and shims hot -dip galvanized per ASTM A 153/A 153M. Width, depth, and metal thickness as required to suit performance requirements.

M. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

N. Wire Rod for Grating Crossbars: ASTM A 510.

2.04 PAINT
A. Shop Primer for Ferrous Metal: Fast -curing, lead- and chromate-free, universal modified-alkyd primer; selected for good resistance to normal atmospheric corrosion, compatibility with finish paint systems indicated, and capability to provide a sound foundation for field-applied topcoats despite prolonged exposure.

1. 94-258 Series Multi -Prime Fast Dry 2.8 VOC Universal Metal Primer; Pittsburgh Paints.

2. B50AZ6 Kem Kromik Universal Metal Primer; Sherwin-Williams Co.

3. Series 37H Phenolic Alkyd Primer Chem-Prime; Tnemec.

B. Shop Primer for Ferrous Metal: Organic zinc -rich primer, complying with SSPC- Paint 20 and compatible with topcoat.

1. Products: Subject to compliance with requirements, provide one of the following:
a. Carboline 621; Carboline Company.
b. Aquapon Zinc-Rich Primer 97-670; PPG Paints.

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-5

c. Tneme-Zinc 90-97; Tnemec Company, Inc.

C. Galvanizing Repair Paint: High-zinc-dust-content paint for regalvanizing welds in steel, complying with SSPC-Paint 20.

D. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187.

2.05 FASTENERS
A. General: Provide Type 304 or 316 stainless -steel fasteners for exterior use and zinc-plated fasteners with coating complying with ASTM B 633, Class Fe/Zn 5, where built into exterior walls. Select fasteners for type, grade, and class required.

B. Bolts and Nuts: Regular hexagon- head bolts, ASTM A 307, Grade A; with hex nuts, ASTM A 563; and, where indicated, flat washers.

C. Anchor Bolts: ASTM F 1554, Grade 36.

D. Eyebolts: ASTM A 489.

E. Machine Screws: ASME B18.6.3.

F. Lag Bolts: ASME B18.2.1.

G. Wood Screws: Flat head, carbon steel, ASME B18.6.1.

H. Plain Washers: Round, carbon steel, ASME B18.22.1.

I. Lock Washers: Helical, spring type, carbon steel, ASME B18.21.1.

J. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below with capability to sustain, without failure, a load equal to six times the load imposed when installed in unit masonry and equal to four times the load imposed when installed in concrete, as determined by testing per ASTM E 488, conducted by a qualified independent testing agency.

1. Interior Expansion Anchor Material: Carbon-steel components zinc-plated to comply with ASTM B 633, Class Fe/Zn 5.

2. Expansion Anchor Material: Alloy Group 1 or 2 stainless- steel bolts complying with ASTM F 593 and nuts complying with ASTM F 594.

K. Toggle Bolts: FS FF-B-588, tumble-wing type, class and style as needed.

2.06 GROUT
A. Non-shrink, Non-metallic Grout: Factory -packaged, non-staining, non-corrosive, non-gaseous grout complying with ASTM C 1107/C 1107M. Provide grout specifically recommended by manufacturer for interior and exterior applications.

2.07 CONCRETE FILL
A. Concrete Materials and Properties: Composed of ASTM C 150 Type I Portland cement, ASTM C 33 sand and coarse aggregates and potable water to produce a low slump mix suitable for placement. Grade coarse aggregate from 1/8 inch with at least 95 percent passing a 3/8 inch sieve and not more than 10 percent passing City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-6

a No. 8 sieve. Fill shall be proportioned to provide a minimum 28-day compressive strength of 3000 psi.

2.08 FABRICATION, GENERAL
A. Shop Assembly: Preassemble items in shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation.

1. Welded connections may be used where bolted connections are shown.

B. Shear and punch metals cleanly and accurately. Remove burrs.

C. Ease exposed edges to a radius of approximately 1/32 inch, unless otherwise indicated. Form bent -metal corners to smallest radius possible without causing grain separation or otherwise impairing work.

D. Weld corners and seams continuously along entire line of contact to comply with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. At exposed connections, finish exposed welds and surfaces smooth and blended so no roughness shows after finishing and contour of welded surface matches that of adjacent surface.

E. Provide for anchorage of type indicated; coordinate with supporting structure.

Fabricate and space anchoring devices and fasteners to secure metal fabrications rigidly in place and to support indicated loads.

F. Cut, reinforce, drill, and tap metal fabrications as indicated to receive finish hardware, screws, and similar items.

G. Fabricate joints that will be exposed to weather in a manner to exclude water, or provide weep holes where water may accumulate.

H. Form exposed work true to line and level with accurate angles and surfaces and straight sharp edges.

I. Remove sharp or rough areas on exposed traffic surfaces.

J. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners where possible. Use exposed fasteners of type indicated or, if not indicated, Phillips flat -head (countersunk) screws or bolts. Locate joints where least conspicuous. Make up threaded connections tight so that threads are entirely concealed.

K. Hot-dip galvanize all exterior ferrous metal fabrications embedded in concrete.

Hot-dip galvanize all other items where specified or shown.

1. Exterior ferrous metal fabrications are defined as those items which are indicated to be installed in areas exposed to conditions which are not controlled by the building heating and cooling systems.

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-7

2. Interior ferrous metal fabrications are defined as those items which are indicated to be installed in areas exposed to conditions which are controlled by the building heating and cooling systems.

2.09 MISCELLANEOUS STEEL TRIM
A. Unless otherwise indicated, fabricate units from structural -steel shapes, plates, and bars of profiles shown with continuously welded joints, and smooth exposed edges. Miter corners and use concealed field splices where possible.

B. Provide cutouts, fittings, and anchorages as needed to coordinate assembly and installation with other work. Provide anchors, welded to trim, for embedding in concrete or masonry construction, spaced not more than 6 inches from each end, 6 inches from corners, and 24 inches o.c., unless otherwise indicated.

C. Surface Applied Corner Guards: Provide corner guards fabricated from angles of sizes shown, or if not shown, of minimum 4-1/2 inch by 4-1/2 inch by 1/4 inch thick equal leg angles. Drill and countersink legs of angles, for fastening to substrates indicated, with holes spaced 24 inches on center. Provide corner guard lengths of 42 inches, if not otherwise indicated.

D. Cast-In-Corner Guards: Provide corner guards fabricated from angles of size as shown, or if not shown, of minimum 4-1/2 inch by 4-1/2 inch by 1/4 inch thick equal leg angles. Fabricate each angle with welded-on stud anchors spaced 24 inches on center. Provide corner guard lengths of 42 inches, if not otherwise indicated.

E. Cast-in Pit Angles and Edge Angles: Provide edge angles, and pit angles, fabricated from angles of size as shown, or required, with welded-on stud anchors spaced 24 inches on center. Provide pit and edge angles in as long lengths as possible. Miter and weld corners and provide splice plates for alignment between sections.

2.10 STEEL AND IRON FINISHES
A. Galvanizing: Hot -dip galvanize items as indicated to comply with applicable standard listed below:

1. ASTM A 123/A 123M, for galvanizing steel and iron products.

2. ASTM A 153/A 153M, for galvanizing steel and iron hardware.

B. Preparation for Shop Priming: Prepare uncoated ferrous -metal surfaces by removing oil, grease, and similar contaminants in accordance with SSPC -SP 1 "Solvent Cleaning," followed with the SSPC surface- preparation specifications listed below and environmental exposure conditions of installed metal fabrications.

Surface preparation shall be done after fabrication and immediately prior to shop painting. Apply shop coat of paint within 4 hours after cleaning and before rust bloom occurs.

1. 1. Interiors (SSPC Zone 1A): SSPC-SP 3, "Power Tool Cleaning."

2. 2. Exteriors (SSPC Zone 1B): SSPC-SP 6, "Commercial Blast Cleaning." C. Apply a minimum of one coat of shop primer to uncoated surfaces of metal fabrications, except those with galvanized finishes and those to be field welded, and those to be embedded in concrete, sprayed- on fireproofing, or masonry, City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-8

unless otherwise indicated. Comply with SSPC -PA 1, "Paint Application Specification No. 1," for shop painting.

1. Stripe paint corners, crevices, bolts, welds, and sharp edges.

2. Dry Film Thickness of Primer: 2.5 to 3.0 mils, dry film thickness. Apply paint thoroughly and evenly to dry surfaces, free from holidays and pinholes, in accordance with manufacturer's directions.

PART 3 - EXECUTION

3.01 INSTALLATION, GENERAL
A. Fastening to In- Place Construction: Provide anchorage devices and fasteners where necessary for securing metal fabrications to in-place construction. Include threaded fasteners for concrete and masonry inserts, toggle bolts, through- bolts, lag bolts, wood screws, and other connectors. Drill holes for bolts to the exact diameter of the bolt. Provide screws threaded full length to the screw head.

B. Cutting , Fitting, and Placement: Perform cutting, drilling, and fitting required for installing metal fabrications. Set metal fabrications accurately in location, alignment, and elevation; with edges and surfaces level, plumb, true, and free of rack; and measured from established lines and levels.

C. Provide temporary bracing or anchors in formwork for items that are to be built into concrete, masonry, or similar construction.

D. Fit exposed connections accurately together to form hairline joints. Weld connections that are not to be left as exposed joints but cannot be shop welded because of shipping size limitations. Do not weld, cut, or abrade surfaces of exterior units that have been hot-dip galvanized after fabrication and are for bolted or screwed field connections.

E. Field Welding: Comply with the following requirements:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.\

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. Quality of Workmanship:
a. At concealed connections: No improvement from mill finish, except preparation necessary for priming is required. Welds are not required to be ground.
b. At exposed connections, finish exposed welds and surfaces smooth and blended so no roughness , pits, mill marks, nicks, or scratches shows after finishing and contour of welded surface matches that of adjacent surface. Defects and distortions shall not be visible to the eye nor show through painted or polished surfaces.

F. Corrosion Protection: Coat concealed surfaces of aluminum that will come into contact with grout, concrete, masonry, wood, or dissimilar metals with a heavy coat of bituminous paint.

City of Camarillo METAL FABRICATIONS
CH-5067-2 055000-9

3.02 ADJUSTING AND CLEANING
A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC -PA 1 for touching up shop-painted surfaces.

1. Apply by brush or spray to provide a minimum 2.0 mil dry film thickness.

B. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint are specified in Section 09 91 23 "Interior Painting" and Section 09 96 00 "High-Performance Coatings." C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780.

END OF SECTION 055000 – METAL FABRICATIONS

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-1

SECTION 076220 – SHEET METAL FLASHING AND TRIM
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Manufactured reglets.

2. Formed wall flashing and trim. This includes galvanized wall cap

3. Flashing related to equipment installation to be provided by manufacturer.

1.02 ACTION SUBMITTALS
A. Product Data: Submit product data for each type of product indicated. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes.

B. CALgreen Submittals:

1. Product Data for Section 5.504.4.1.1: For sealants, adhesives and caulks, provide documentation including printed statement of VOC content showing compliance with SCAQMD Rule 1168 VOC limits and CCR (California Code of Regulations) Title 17 for aerosols.

2. Product Data for Section 5.504.4.1.2: Provide documentation for aerosol adhesives, and smaller unit sizes of adhesives, sealant, and caulking compounds (in units of product, less packaging, which do not weigh more than one (1) pound and do not consist of more than sixteen (16) fluid ounces) comply with statewide VOC standards and prohibitions on use of certain toxic compounds, of CCR Title 17, commencing with Section 94507.

3. Product Data for Section 5.504.4.3: For architectural paints and coatings, provide documentation including printed statement of VOC content showing compliance with Table 1 of the ARB, Architectural Coatings Suggested Control Measure, unless more stringent local limits apply.

4. Product Data for Section 5.504.4.3.1: Aerosol paints and coatings, provide documentation that products meet the PWMIR Limits for ROC in Section 94522 (a)(3) and other requirements, including prohibitions on use of certain toxic compounds and ozone depleting substances, in Section 94522(c)(2 and (d)(2) of CCR Title 17.

C. Shop Drawings: Submit shop drawings showing layouts of sheet metal flashing and trim, including plans and elevations. Distinguish between shop - and field- assembled work. Include the following:

1. Identify material, thickness, weight, and finish for each item and location in Project.

2. Details for forming sheet metal flashing and trim, including profiles, shapes, seams, and dimensions.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-2

3. Details for fastening, joining, supporting, and anchoring sheet metal flashing and trim, including fasteners, clips, cleats, and attachments to adjoining work.

1.03 QUALITY ASSURANCE
A. Installer Qualifications: Subcontract the sheet metal flashing and trim work to a firm which is specialized in the fabrication and installation of sheet metal flashing and trim and who has successfully installed work similar in design and extent to that required for the project, in not less than three projects of similar scope to the satisfaction of the Architect, and whose work has resulted in construction with a record of successful in-service performance for a period of 5 years.

B. Sheet Metal Flashing and Trim Reference Standards: Comply with the industry standard sources below. Where sheet metal flashing and trim work details have not been specifically detailed on the drawings or specified the Contractor shall submit, for the Architect's approval, proposed sheet metal detailing. The primary source for proposed sheet metal detailing shall come from the industry standard sources below.

1. SMACNA's Architectural Sheet Metal Manual.

2. NRCA's Roofing and Waterproofing Manual.

3. ANSI/SPRI ES-1 Wind Design Standard for Edge Systems Used with Low Slope Roof Systems except where the Performance Requirements are more stringent.

C. Sealant Compatibility and Adhesion Testing: Use sealant manufacturer's standard test methods to determine whether priming and other specific joint preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint substrates.

D. Design Modifications: Submit design modifications necessary to meet the performance requirements and field coordination. Variations in details or materials which do not adversely affect the appearance, durability or strength of components shall be submitted to the Architect for review. Maintain the general design concept without altering size of members, profiles and alignment.

1.04 COORDINATION
A. Coordinate installation of sheet metal flashing and trim with interfacing and adjoining construction to provide a leakproof, secure, and noncorrosive installation.

1.05 WARRANTY
A. Furnish written warranty against water leakage resulting from defects of materials or workmanship. Upon notification of such defects, within the warranty period, make the necessary repairs and replacements at the convenience of, and no cost to, the Owner. This warranty shall be in addition to and not a limitation of other rights the Owner may have against the Contractor under the Contract Documents.

1. Warranty period shall be 5 years after the date of Substantial Completion.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-3

PART 2 - PRODUCTS

2.01 PERFORMANCE REQUIREMENTS
A. General: Install sheet metal flashing and trim to withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failing, rattling, leaking, and fastener disengagement.

B. Fabricate and install exterior wall and roofing sheet metal flashing and trim capable of resisting the wind forces greater than or equal to those shown on Structural Drawings for components and cladding.

C. SPRI Wind Design Standard: Manufacture and install roof edge flashings tested according to SPRI ES-1 and capable of resisting the following design pressure:

1. Design Pressure: As indicated on Drawings.

D. Thermal Movements: Provide sheet metal flashing and trim that allow for thermal movements resulting from surface temperatures ranging from +10 degrees F. to +180 degrees F., without buckling, opening of joints, hole elongation, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Provide clips that resist rotation and avoid shear stress as a result of sheet metal and trim thermal movements.

1. Dimensions shown on Drawings are based on an assumed design temperature of +70
° F. Fabrication and installation procedures shall take into account the ambient temperature range at the time of the respective operations.

E. Water Infiltration: Provide sheet metal flashing and trim that do not allow water infiltration.

2.02 SHEET METALS
A. Zinc-Coated (Galvanized) Steel Sheet: ASTM A 653/A 653M, G90 coating designation; structural quality, mill phosphatized for field painting.

B. Prepainted, Metallic-Coated Steel Sheet: Steel sheet metallic coated by the hot - dip process and prepainted by the coil -coating process to comply with ASTM A 755/A 755M.

1. Zinc-Coated (Galvanized) Steel Sheet: ASTM A 653/A 653M, G90 coating designation; structural quality.

2. Exposed Finishes: Apply the following coil coating:
a. Factory Prime Coating: Factory-applied, baked-on epoxy primer coat. b. High-Performance Organic Finish: Two -coat thermocured system containing not less than 70 percent polyvinylidene fluoride resin by weight; complying with physical properties and coating performance requirements of AAMA 2604, except as modified for below:
i. Color: Match Architect's samples.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-4

2.03 MISCELLANEOUS MATERIALS
A. General: Provide materials and types of fasteners, solder, separators, sealants, and other miscellaneous items as required for complete sheet metal flashing and trim installation.

B. Underlayment: Self -Adhering, High- Temperature Sheet: 0.76 mm thick, self adhering, self sealing, underlayment consisting of slip- resisting high density cross laminated polyethylene-film top surface laminated to layer of butyl rubber based adhesive, with release-paper backing; cold applied. Provide primer when recommended by underlayment manufacturer.

1. Thermal Stability: Stable after testing at 116 deg C ; ASTM D 1970.

2. Product Reference: Grace, W. R. & Co.; Ultra.

C. Fasteners: Wood screws, same metal as flashing/sheet metal, annular threaded nails, self -tapping screws, and other suitable fasteners designed to withstand design loads.

D. Sealing Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealing tape with release- paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape.

E. Elastomeric Sealant: ASTM C920 and Section 07 92 00 "Joint Sealants," elastomeric polyurethane polymer sealant; of type, grade, class, and use classifications required to seal joints in sheet metal flashing and trim and remain watertight.

F. Butyl Sealant: ASTM C1311, single- component, solvent -release butyl rubber sealant, polyisobutylene plasticized, heavy bodied for hooked- type expansion joints with limited movement.

G. Epoxy Seam Sealer: Two- part, noncorrosive, aluminum seam -cementing compound.

H. Bituminous Coating: Cold-applied bituminous paint complying with ASTM D1187, compounded for 15 mil dry film thickness per coat.

I. Wood Nailer Strips: Provide wood nailer strips, fabricated to sizes indicated, from lumber complying with the requirements of Section 06 10 53 "Miscellaneous Rough Carpentry" and fire retardant treated by pressure process using chemical solution which is non-hygroscopic and non-corrosive to sheet metal used.

J. Adhesives, adhesive bonding primers, adhesive primers, sealants, sealant primers and caulks shall comply with local or regional regulations as referenced in Section 01 81 23 "CALgreen Requirements."
K. Aerosol adhesives, and smaller unit sizes of adhesives, and sealant or caulking compounds shall comply with regulations as referenced in Section 01 81 23 "CALgreen Requirements."
L. Architectural paints and coatings shall comply with VOC limits as defined by local, regional, or state regulations as referenced in Section 01 81 23 "CALgreen Requirements."
M. Aerosol paints and coatings shall meet the Product-weighted MIR Limits for ROC as referenced in Section 01 81 23 "CALgreen Requirements." City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-5

2.04 REGLETS
A. Material: Galvanized steel, 0.0217 inch thick.

2.05 FABRICATION, GENERAL
A. General: Custom fabricate sheet metal flashing and trim to comply with the referenced standards that apply to design, dimensions, metal, and other characteristics of item indicated. Shop fabricate items where practicable. Obtain field measurements for accurate fit before shop fabrication.

B. Fabricate sheet metal flashing and trim in thickness needed to comply with performance requirements, but not less than that specified for each application and metal.

C. Fabricate sheet metal flashing and trim without excessive oil canning, buckling, and tool marks and true to line and levels indicated, with exposed edges folded back to form hems.

1. Seams for Aluminum: Fabricate nonmoving seams with flat -lock seams.

Form seams and seal with epoxy seam sealer. Rivet joints for additional strength.

2. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories with flat-lock seams. Tin edges to be seamed, form seams, and solder.

D. Sealed Joints: Form nonexpansion but movable joints in metal to accommodate elastomeric sealant to comply with SMACNA recommendations.

E. Expansion Provisions: Where lapped or bayonet-type expansion provisions in the Work cannot be used, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with butyl sealant concealed within joints.

F. Conceal fasteners and expansion provisions where possible on exposed- to-view sheet metal flashing and trim, unless otherwise indicated.

G. Fabricate cleats and attachment devices from same material as accessory being anchored. Cleats shall be 2 inches wide by nominal 3 inches long typically, minimum 0.0187 inch thick, punch for minimum 2 nail or screw holes. One end shall be locked into seams, or into folded edge of sheet metal sheets, the other end shall be secured with nails or screws and folded back over nail or screw heads.

2.06 ROOF DRAINAGE SHEET METAL FABRICATIONS
A. Conductor Heads: Fabricate conductor heads with flanged back and stiffened top edge and of dimensions and shape indicated complete with outlet tubes, andbuilt - in overflows.

2.07 MISCELLANEOUS SHEET METAL FABRICATIONS
A. Equipment Support Flashing: By Equipment Manufactuer:

1. Prepainted, Metallic-Coated Steel: 0.0276 inch thick.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-6

PART 3 - EXECUTION
A. Examine substrates, areas, and conditions, with Installer present, to verify actual locations, dimensions and other conditions affecting performance of work.

1. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely anchored.

2. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 INSTALLATION, GENERAL
A. General: Anchor sheet metal flashing and trim and other components of the Work securely in place, with provisions for thermal and structural movement. Use fasteners, solder, protective coatings, separators, sealants, and other miscellaneous items as required to complete sheet metal flashing and trim system.

1. Torch cutting of sheet metal flashing and trim is not permitted.

B. Nailer and Underlayment Installation for copings / wall caps:

1. Provide wood nailers shown to properly install the coping. Form to shapes indicated and cut as required for true line and level of attached work. Set to required levels and lines. Allow approximately 1/8" between nailer ends and offset joints a minimum of 12" in multiple layers. Locate nailers to comply with requirements for attaching other construction.

2. Utilize mechanical fasteners that will have no detrimental effect on the components of the coping. Recess fasteners flush with surfaces. Fasten in accordance with FM 1- 49 standards and the coping manufacturers recommendations.

3. Underlayment Installation: Install a course of self adhering high temperature sheet underlayment directly over nailers in accordance with the underlayment manufacturers instructions to the extent indicated on the drawings. Lap ends of underlayment lengths a minimum of 4 inches.

C. Metal Protection: Where dissimilar metals will contact each other or corrosive substrates, protect against galvanic action by painting contact surfaces with bituminous coating or by other permanent separation as recommended by fabricator or manufacturers of dissimilar metals.

1. Underlayment: Where installing metal flashing directly on cementitious or wood substrates, install a course of underlayment.

2. Bed flanges in thick coat of asphalt roofing cement where required for waterproof performance.

D. Install exposed sheet metal flashing and trim without excessive oil canning, buckling, and tool marks.

E. Install sheet metal flashing and trim true to line and levels indicated. Provide uniform, neat seams with minimum exposure of solder, and butyl sealant.

F. Install sheet metal flashing and trim to fit substrates and to result in watertight performance. Verify shapes and dimensions of surfaces to be covered before fabricating sheet metal.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-7

1. Space cleats not more than 12 inches apart. Anchor each cleat with two fasteners. Bend tabs over fasteners.

G. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim.

Space movement joints at a maximum of 10 feet with no joints allowed within 24 inches of corner or intersection. Where lapped or bayonet -type expansion provisions cannot be used or would not be sufficiently watertight, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with butyl sealant concealed within joints.

H. Fasteners: Use fasteners of sizes that will penetrate substrate not less than 1- 1/4 inches for nails and not less than 3/4 inch for wood screws.

1. Galvanized or Prepainted, Metallic -Coated Steel: Use stainless -steel fasteners.

2. Aluminum: Use aluminum or stainless-steel fasteners.

3. Stainless Steel: Use stainless-steel fasteners.

I. Seal joints with butyl sealant as required for watertight construction.

1. Where sealant-filled joints are used, embed hooked flanges of joint members not less than 1 inch into sealant. Form joints to completely conceal sealant.

J. Soldered Joints: Edges of sheets to be soldered shall be in close contact at every point along the joint before soldering. Edges of all sheets of sheet metal to be soldered shall be tinned with solder on both sides for a minimum width of 1 -1/2 inches. Where specified, all seams shall be thoroughly soldered to produce watertight joints. All soldering shall be done slowly with well heated metal - to heat sheet thoroughly and to sweat solder completely through full width of seam. Ample solder shall be used and seam shall show at least one full inch of evenly flowed solder. Wherever possible all soldering shall be done in flat position. Remove every trace of flux residue from metal promptly after tinning. Comply with manufacturer's recommended methods for cleaning and neutralization. Clean exposed surfaces of sheet metal flashing and trim of every substance which is visible or might cause corrosion of metal surfaces. Use soldering irons (3 lb. Minimum each). Do not use abrasives in preparing the sheet metal surfaces for soldering. All exposed parts of finished soldered joints shall be smooth and free of smeared solder.

K. Do not solder prepainted, metallic-coated steel sheet.

3.03 WALL FLASHING INSTALLATION
A. General: Install sheet metal wall flashing to intercept and exclude penetrating moisture according to SMACNA recommendations and as indicated. Coordinate installation of wall flashing with installation of wall -opening components such as windows, doors, and louvers.

B. Openings Flashing in Frame Construction: Install continuous through wall head, sill, jamb, and similar flashings to extend 4 inches beyond wall openings.

3.04 MISCELLANEOUS SHEET METAL FABRICATION INSTALLATION A. Overhead-Piping Safety Pans: Suspend pans from pipe and install drain line to plumbing waste or drain line.

City of Camarillo SHEET METAL FLASHIN AND TRIM
CH-5067-2 076220-8

B. Equipment Support Flashing: Coordinate installation of equipment support flashing with installation of roofing and equipment. Seal flashing with elastomeric sealant to equipment support member.

3.05 CLEANING AND PROTECTION
A. Clean exposed metal surfaces for uniform oxidation and weather exposure; neutralize flux materials; clean off excess solder and sealants; and remove strippable films, if any.

B. On completion of installation, clean finished surfaces, including removing unused fasteners, metal filings, and pieces of flashing. Maintain in a clean condition during construction.

C. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond successful repair by finish touchup or similar minor repair procedures.

END OF SECTION 076220 – SHEET METAL FLASHING AND TRIM

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-1

SECTION 081110 – HOLLOW METAL DOORS AND FRAMES
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes:

1. Standard and custom hollow metal doors and frames
B. Codes and References: Comply with the version year adopted by the Authority Having Jurisdiction.

1. ANSI/SDI A250.8 - Recommended Specifications for Standard Steel Doors and Frames.

2. ANSI/SDI A250.4 - Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors, Frames, Frames Anchors and Hardware Reinforcing.

3. ANSI/SDI A250.6 - Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames.

4. ANSI/SDI A250.10 - Test Procedure and Acceptance Criteria for Prime Painted Steel Surfaces for Steel Doors and Frames.

5. ANSI/SDI A250.11 - Recommended Erection Instructions for Steel Frames.

6. ASTM A1008 - Standard Specification for Steel Sheet, Cold-Rolled, Carbon, Structural, High- Strength Low -Alloy and High- Strength Low -Alloy with Improved Formability.

7. ASTM A653 - Standard Specification for Steel Sheet, Zinc -Coated (Galvanized) or Zinc -Iron Alloy -Coated (Galvannealed) by the Hot- Dip Process.

8. ASTM A924 - Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process.

9. ASTM C 1363 - Standard Test Method for Thermal Performance of Building Assemblies by Means of a Hot Box Apparatus.

10. ANSI/BHMA A156.115 - Hardware Preparation in Steel Doors and Frames.

11. ANSI/SDI 122 - Installation and Troubleshooting Guide for Standard Steel Doors and Frames.

12. ANSI/NFPA 80 - Standard for Fire Doors and Fire Windows; National Fire Protection Association.

13. ANSI/NFPA 105: Standard for the Installation of Smoke Door Assemblies.

14. NFPA 252 - Standard Methods of Fire Tests of Door Assemblies; National Fire Protection Association.

15. UL 10C - Positive Pressure Fire Tests of Door Assemblies.

16. UL 1784 - Standard for Air Leakage Tests of Door Assemblies.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-2

1.02 QUALITY ASSURANCE
A. Source Limitations: Obtain hollow metal doors and frames through one source from a single manufacturer wherever possible.

B. Quality Standard: In addition to requirements specified, furnish SDI -Certified manufacturer products that comply with ANSI/SDI A250.8, latest edition, "Recommended Specifications for Standard Steel Doors and Frames".

C. Pre-Submittal Conference: If required by Owner, conduct conference in compliance with requirements in Division 01 Section "Project Meetings" with attendance by representatives of Supplier, Installer, and Contractor to review proper methods and procedures for installing hollow metal doors and frames and to verify installation of electrical knockout boxes and conduit at frames with electrified or access control hardware.

1.03 DELIVERY, STORAGE, AND HANDLING
A. Deliver hollow metal work palletized, wrapped, or crated to provide protection during transit and Project site storage. Do not use non-vented plastic.

B. Deliver welded frames with two removable spreader bars across bottom of frames, tack welded to jambs and mullions.

C. Store hollow metal work under cover at Project site. Place in stacks of five units maximum in a vertical position with heads up, spaced by blocking, on minimum 4 - inch high wood blocking. Do not store in a manner that traps excess humidity.

1. Provide minimum 1/4 -inchspace between each stacked door to permit air circulation. Door and frames to be stacked in a vertical upright position.

1.04 PROJECT CONDITIONS
A. Field Measurements: Verify actual dimensions of openings by field measurements before fabrication.

1.05 COORDINATION
A. Coordinate installation of anchorages for hollow metal frames. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors. Deliver such items to Project site in time for installation.

B. Coordinate doors/frames with placement of concrete masonry units.

1.06 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace doors that fail in materials or workmanship within specified warranty period.

B. Warranty includes installation and finishing that may be required due to repair or replacement of defective doors.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-3

PART 2 - PRODUCTS

2.01 MANUFACTURERS
A. SDI Certified manufacturer:

1. CECO Door Products (C).

2. Curries Company (CU).

2.02 MATERIALS
A. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B; suitable for exposed applications.

B. Metallic-Coated Steel Sheet: ASTM A 653/A 653M, Commercial Steel (CS), Type B; with minimum G60 metallic coating.

C. Frame Anchors: ASTM A 653/A 653M, Commercial Steel (CS), Commercial Steel (CS), Type B; with minimum G60 metallic coating.

2.03 HOLLOW METAL DOORS
A. General: Provide 1- 3/4 inch doors of design indicated, not less than thickness indicated; fabricated with smooth surfaces, without visible joints or seams on exposed faces unless otherwise indicated. Comply with ANSI/SDI A250.8 and ANSI/NAAMM HMMA 867.

B. Exterior Doors: Face sheets fabricated of commercial quality hot-dipped zinc coated steel that complies with ASTM A 653/A 653M, Coating Designation A60. Provide doors complying with requirements indicated below by referencing ANSI/SDI A250.8 for level and model and ANSI/SDI A250.4 for physical performance level:

1. Design: Flush panel.

2. Core Construction: Manufacturer's standard polystyrene. Where indicated, provide doors fabricated as thermal -rated assemblies with a minimum R- value of 2.8 or better.

3. Level/Model: Level 3 and Physical Performance Level A (Extra Heavy Duty), Minimum 16 gauge (0.053-inch - 1.3-mm) thick steel, Model 2.

4. Top and Bottom Edges: Reinforce tops and bottoms of doors with a continuous steel channel not less than 16 gauge, extending the full width of the door and welded to the face sheet. Doors with an inverted top channel to include a steel closure channel, screw attached, with the web of the channel flush with the face sheets of the door. Plastic or composite channel fillers are not acceptable.

5. Hinge Reinforcement: Minimum 7 gauge (3/16") plate 1-1/4" x 9" or minimum 14 gauge continuous channel with pierced holes, drilled and tapped.

6. Hardware Reinforcements: Fabricate according to ANSI/SDI A250.6 with reinforcing plates from same material as door face sheets.

C. Manufacturers Basis of Design:

1. Curries Company (CU) - QMax Core - 707 Series.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-4

2.04 HOLLOW METAL FRAMES
A. General: Comply with ANSI/SDI A250.8 and with details indicated for type and profile.

B. Exterior Frames: Fabricated of hot -dipped zinc coated steel that complies with ASTM A 653/A 653M, Coating Designation A60.

1. Fabricate frames with mitered or coped corners. Profile as indicated on drawings.

2. Frames: Minimum 14 gauge (0.067-inch - thick steel sheet.

3. Manufacturers Basis of Design:
a. CECO Door Products (C) – SU SR Series.
b. Curries Company (CU) – M Series.

C. Hardware Reinforcement: Fabricate according to ANSI/SDI A250.6 Table 4 with reinforcement plates from same material as frames.

2.05 FRAME ANCHORS
A. Jamb Anchors:

1. Masonry Type: Adjustable strap -and-stirrup or T- shaped anchors to suit frame size, formed from metallic coated material, not less than 0.042 inchthick, with corrugated or perforated straps not less than 2 incheswide by 10 incheslong; or wire anchors not less than 0.177 inchthick.

2. Stud Wall Type: Designed to engage stud and not less than 0.042 inchthick.

3. Compression Type for Drywall Slip- on (Knock -Down) Frames: Adjustable compression anchors.

B. Floor Anchors: Floor anchors to be provided at each jamb, formed from metallic coated material, not less than 0.042 inchesthick.

C. Mortar Guards: Formed from same material as frames, not less than 0.016 inches thick.

2.06 ACCESSORIES
A. Mullions and Transom Bars: Join to adjacent members by welding or rigid mechanical anchors.

B. Grout Guards: Formed from same material as frames, not less than 0.016 inches thick.

2.07 FABRICATION
A. Fabricate hollow metal work to be rigid and free of defects, warp, or buckle.

Accurately form metal to required sizes and profiles, with minimum radius for thickness of metal. Where practical, fit and assemble units in manufacturer's plant.

When shipping limitations so dictate, frames for large openings are to be fabricated in sections for splicing or splining in the field by others.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-5

B. Tolerances: Fabricate hollow metal work to tolerances indicated in ANSI/SDI A250.8.

C. Hollow Metal Doors:

1. Exterior Doors: Provide optional weep- hole openings in bottom of exterior doors to permit moisture to escape where specified.

2. Louvers: Factory cut openings in door and install louvers into prepared openings where indicated.

3. Astragals: Provide overlapping astragals as noted in door hardware sets in Division 08 Section "Door Hardware" on one leaf of pairs of doors where required by NFPA 80 for fire-performance rating or where indicated. Extend minimum 3/4 inch beyond edge of door on which astragal is mounted.

D. Hollow Metal Frames:

1. Shipping Limitations: Where frames are fabricated in sections due to shipping or handling limitations, provide alignment plates or angles at each joint, fabricated of same thickness metal as frames.

2. Welded Frames: Weld flush face joints continuously; grind, fill, dress, and make smooth, flush, and invisible.
a. Welded frames are to be provided with two steel spreaders temporarily attached to the bottom of both jambs to serve as a brace during shipping and handling. Spreader bars are for bracing only and are not to be used to size the frame opening.

3. Sidelight and Transom Bar Frames: Provide closed tubular members with no visible face seams or joints, fabricated from same material as door frame.

Fasten members at crossings and to jambs by butt welding.

4. High Frequency Hinge Reinforcement: Provide high frequency hinge reinforcements at door openings 48-inches and wider with mortise butt type hinges at top hinge locations.

5. Provide countersunk, flat - or oval -head exposed screws and bolts for exposed fasteners unless otherwise indicated for removable stops, provide security screws at exterior locations.

6. Mortar Guards: Provide guard boxes at back of hardware mortises in frames at all hinges and strike preps regardless of grouting requirements.

7. Floor Anchors: Weld anchors to bottom of jambs and mullions with at least four spot welds per anchor.

8. Jamb Anchors: Provide number and spacing of anchors as follows:
a. Masonry Type: Locate anchors not more than 18 inchesfrom top and bottom of frame. Space anchors not more than 32 inches o.c. and as follows:
i. Two anchors per jamb up to 60 incheshigh.
ii. Three anchors per jamb from 60 to 90 incheshigh.
iii. Four anchors per jamb from 90 to 120 incheshigh.
iv. Four anchors per jamb plus 1 additional anchor per jamb for each 24 inchesor fraction thereof above 120 inches high.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-6

9. Door Silencers: Not Required

10. Bituminous Coating: Where frames are fully grouted with an approved Portland Cement based grout or mortar, coat inside of frame throat with a water based bituminous or asphaltic emulsion coating to a minimum thickness of 3 mils DFT, tested in accordance with UL 10C and applied to the frame under a 3rd party independent follow-up service procedure.

E. Hardware Preparation: Factory prepare hollow metal work to receive template mortised hardware; include cutouts, reinforcement, mortising, drilling, and tapping according to the Door Hardware Schedule and templates furnished as specified in Division 08 Section "Door Hardware."

1. Locate hardware as indicated, or if not indicated, according to ANSI/SDI A250.8.

2. Reinforce doors and frames to receive non- template, mortised and surface mounted door hardware.

3. Comply with applicable requirements in ANSI/SDI A250.6 and ANSI/DHI A115 Series specifications for preparation of hollow metal work for hardware.

4. Coordinate locations of conduit and wiring boxes for electrical connections with Division 26 Sections.

2.08 STEEL FINISHES
A. Prime Finishes: Doors and frames to be cleaned, and chemically treated to insure maximum finish paint adhesion. Surfaces of the door and frame exposed to view to receive a factory applied coat of rust inhibiting shop primer.

1. Shop Primer: Manufacturer's standard, fast -curing, lead and chromate free primer complying with ANSI/SDI A250.10 acceptance criteria; recommended by primer manufacturer for substrate; and compatible with substrate and field-applied coatings.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

B. General Contractor to verify the accuracy of dimensions given to the steel door and frame manufacturer for existing openings or existing frames (strike height, hinge spacing, hinge back set, etc.).

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION
A. Remove welded in shipping spreaders installed at factory. Restore exposed finish by grinding, filling, and dressing, as required to make repaired area smooth, flush, and invisible on exposed faces.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-7

B. Prior to installation, adjust and securely brace welded hollow metal frames for square, level, twist, and plumb condition.

C. Tolerances shall comply with SDI -117 "Manufacturing Tolerances Standard Steel Doors and Frames."
D. Drill and tap doors and frames to receive non- template, mortised, and surface - mounted door hardware.

E. Verify tolerances against manufacturers installations instructions for tornado and hurricane storm shelter openings.

3.03 INSTALLATION
A. General: Install hollow metal work plumb, rigid, properly aligned, and securely fastened in place; comply with Drawings and manufacturer's written instructions.

B. Hollow Metal Frames: Install hollow metal frames of size and profile indicated.

Comply with ANSI/SDI A250.11 and NFPA 80 at fire rated openings.

1. Set frames accurately in position, plumbed, leveled, aligned, and braced securely until permanent anchors are set. After wall construction is complete and frames properly set and secured, remove temporary braces, leaving surfaces smooth and undamaged. Shim as necessary to comply with installation tolerances.

2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor, and secure with post-installed expansion anchors.

3. Masonry Walls: Coordinate installation of frames to allow for solidly filling space between frames and masonry with mortar.

4. Grout Requirements: Do not grout head of frames unless reinforcing has been installed in head of frame. Do not grout vertical or horizontal closed mullion members.

C. Hollow Metal Doors: Fit hollow metal doors accurately in frames, within clearances specified below. Shim as necessary.

1. Non-Fire-Rated Standard Steel Doors:
a. Jambs and Head: 1/8 inch plus or minus 1/16 inch.
b. Between Edges of Pairs of Doors: 1/8 inchplus or minus 1/16 inch. c. Between Bottom of Door and Top of Threshold: Maximum 3/8 inch. d. Between Bottom of Door and Top of Finish Floor (No Threshold):

Maximum 3/4 inch.

2. Fire-Rated Doors: Install doors with clearances according to NFPA 80.

3.04 ADJUSTING AND CLEANING
A. Final Adjustments: Check and readjust operating hardware items immediately before final inspection. Leave work in complete and proper operating condition.

Remove and replace defective work, including hollow metal work that is warped, bowed, or otherwise unacceptable.

B. Remove grout and other bonding material from hollow metal work immediately after installation.

City of Camarillo HOLLOW METAL DOORS AND FRAMES
CH-5067-2 081110-8

C. Prime-Coat and Painted Finish Touchup: Immediately after erection, sand smooth rusted or damaged areas of prime coat, or painted finishes, and apply touchup of compatible air drying, rust-inhibitive primer, zinc rich primer (exterior and galvanized openings) or finish paint.

3.05 FIELD QUALITY CONTROL
A. Field Inspection (Punch Report): Reference Division 01 Sections “Closeout Procedures”. Produce project punch report for each installed door opening indicating compliance with approved submittals and verification hardware is properly installed, operating and adjusted. Include list of items to be completed and corrected, indicating the reasons or deficiencies causing the Work to be incomplete or rejected.

1. Organization of List: Include separate Door Opening and Deficiencies and Corrective Action Lists organized by Mark, Opening Remarks and Comments, and related Opening Images and Video Recordings.

END OF SECTION 081110 – HOLLOW METAL DOORS AND FRAMES

City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-1

SECTION 092400 – PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS PART 1 - GENERAL

1.01 REFERENCES
A. ASTM C150 – Portland Cement
B. ASTM C144/C897 – Aggregate for Job-Mixed Portland Cement-Based Plaster C. ASTM C926 – Application of Portland Cement-Based Plaster D. PCA (Portland Cement Association) – Plaster (Stucco) Manual E. SMA Details and Technical Bulletins

1.02 ASSEMBLY DESCRIPTION
A. General: Portland cement plaster over masonry
B. Application Methods: The plaster may be applied by hand tools or machine pumps but must be applied with sufficient pressure to adhere to the substrate.

C. Masonry and concrete shall be sound, free of coatings, cured minimum 28 days.

D. Thickness of plaster are considered maximum nominal measurements.

E. Fire Rated assemblies shall be constructed per the test report or special instructions.

1.03 SUBMITTALS
A. Product Data: All product data sheets, evaluation reports, details, and warranty information that pertain to the project in accordance with Section 01 33 01 Submittal Procedures.

B. Samples: Submitted upon request.

Samples of the finish coat shall be of an adequate size as required to represent each color and texture to be utilized on the project and produced using the same techniques and tools required to complete the project. No sample shall be less than 12” by 12”.

Samples shall demonstrate that new finishes will match existing structures on site.

Retain approved samples at the construction site throughout the application process.

1.04 QUALITY ASSURANCE
A. Manufacturer: All component materials shall be SMA approved and shall be distributed by authorized dealers.

B. Plastering Contractor:

Shall specialize in lath and plaster contracting with documented experience of at least 5 years in business. Follow published SMA recommendations or provide certificates to demonstrate knowledge in stucco.

City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-2

Provide proof of current contractor’s license and bond where required.

C. On-Site Mock-Ups: Produce upon request.

D. Mock-up shall represent construction using the same quality/techniques to be utilized on the project.

E. Retain approved mock-up at job site throughout the application process.

1. Where acceptable to the Architect, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

Contractor shall provide a letter at completion, they have installed plaster per SMA recommendations.

1.05 DELIVERY, STORAGE, AND HANDLING
A. Delivery: Deliver all materials to the construction site in their original, unopened packaging with labels intact.

B. Inspection: Inspect the materials upon delivery to assure that specified products have been received. Report defects or discrepancies to the responsible party according to the construction documents; do not use reported material for application.

C. Storage: Store all products per manufacturer’s recommendations. Generally, store materials in a cool, dry location; away from direct contact with the ground and/or concrete; out of direct sunlight; and protect from weather and other damage.

1.06 PROJECT CONDITIONS
A. Environmental Requirements: Follow product manufacturer's recommendations for environmental conditions and surface preparation.

B. Temperatures: Before, during and following the application of the portland cement plaster, the ambient and surface temperatures must remain above 40 degrees F ( 4 C) for a minimum period of 24 hours. Protect stucco from uneven and excessive evaporation, especially during hot, dry and/or windy weather. Protect the portland cement plaster from freezing for a period of not less than 24- hours after set has occurred.

C. Substrates: Prior to installation, inspect the wall for surface contamination, bond breakers, or other defects that may adversely affect the performance of the materials, and shall be free of foreign matter. Do not apply the portland cement plaster to substrates with temperatures less than 40 degrees F ( 4 C) or that contain frost or ice.

D. Inclement Weather: Protect applied material from deleterious effects until cured or dry.

E. Existing Conditions:

1. Contractor shall walk the project prior to starting work and notify the architect or owner’s representative of any deficiencies that will negatively impact the plaster or parge coating. Do NOT proceed until remedied and contractor can provide warranty.

F. Contractor shall advise architect of any horizontal surfaces with inadequate slope.

City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-3

1. Jobsite Resources: Notify architect if General Contractor fails to provide access to electrical outlets, clean, potable water, and a suitable and safe work area at the construction site throughout the application of the lath and portland cement plaster.

1.07 SEQUENCING AND SCHEDULING
A. Sequencing: Coordinate the installation of the lath and portland cement plaster with all other construction trades. To reduce stucco cracking, insure the concrete/masonry substrate is cured a minimum of 28 days and not saturated prior to plastering.

B. Plastering contractor shall request and attend a pre- installation meeting with general contractor and architect to advise architect of any control/expansion joint layout concerns. There shall be no cost to the owner for moving one-piece control joints prior and up to this meeting date, additional lineal footage of control joints from plans shall warrant a change order.

C. Staffing: Provide sufficient manpower and proper supervision to ensure continuous operation, free of cold joints, scaffolding lines, curing, variations in texture, etc.

1.08 WARRANTY
A. Warranty: Submit documentation on all products. At completion of work, contractor shall provide a written warranty documentation for the assembly and products used.

B. Warranty Length: Shall start at the time of substantial completion.

1.09 MAINTENANCE
A. The following materials shall be presented to the owner following the application of the work: Supply a maintenance program for Owners O&M manual as required.

PART 2 - PRODUCTS

2.01 MANUFACTURERS
A. SMA Manufacturers: Must be from the current list on SMA website under appropriate category.

1. BMI

2. Dryvit

3. Parex

4. La Habra

5. California Stucco

6. Shamrock Stucco

7. Quikrete/Specmix
City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-4

8. Merlex

9. El Rey Stucco

10. Omega Products

11. CalPortland/Riverside Cement

12. Mission Stucco

13. Sacramento Stucco

14. Cemex

15. BMI/SIKA

16. Amermix/Old Castle
B. Lath and Trim Accesories

1. Stockton Products

2. Structa Wire

3. Tree Island/K-Lath

4. Fry reglet

5. Plastic Components

2.02 SCRATCH ( IF LATH IS APPLIED) AND BROWN COAT (BASECOAT) A. Cement: A portland cement complying with ASTM C150.

B. Sand:

1. Field mixes shall comply with ASTM C -926 and must have sand that is clean and free from deleterious amounts of loam, clay, silt, soluble salts and organic matter. Sampling and testing shall comply with ASTM C144 or C897.

2. An “engineered performance mix” by an SMA manufacturer is acceptable with appropriate approvals (ICC ES, IAPMO or Interek report) .

C. Water: Clean and potable without foreign matter.

2.03 WATER-RESISTIVE BARRIER
A. Water-Resistive Barrier is required, it shall be a fluid applied product compatible with cement plaster AND recommended for use by the manufacturer for this exact purpose.

1. Acceptable Manufacturers
a. Omega
b. Dryit
c. Parex
d. La Habra
e. California Stucco
f. Sacramento Stucco
g. Shamrock Stucco
City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-5

h. Merlex
i. BMI/Sika

2.04 ACCESSORIES
A. Sealants: Acrylic latex complying with ASTM C834, Polyurethane, polyurethane modified, polysulfide, or silyl-terminated polyether elastomeric sealant complying with ASTM C920 or 100% silicone.

B. Fasteners: Nails, staples, or screws used to rigidly secure lath and associated accessories shall be corrosion- resistant and meet the minimum requirements of ASTM C1063.

C. Zinc and Zinc -Coated (Galvanized) Accessories: Refer to Section 07 62 00 – Sheet metal flashing and trim
D. Plastic Trim: Fabricated from high-impact PVC.

E. Cornerbeads: With perforated flanges; Square-edge style; use unless otherwise indicated.

F. Casing Beads: With perforated flanges in depth required to suit plaster bases indicated and flange length required to suit applications indicated.

2.05 FINISHES
A. Color and Texture: Manufacturer, color and finish texture shall be as approved by the Architect (to match finishes at existing)

2.06 MIXES
A. Portland Cement Plaster Basecoats:

1. Prescriptive Method: Ratios and Mix Design shall be per ASTM C926.

Contractor shall select one of the following mixes (sand is per combined volume of cements), lime is cement:
a. MIX 1:
i. Portland Cement 1 part
ii. Masonry Cement 1 part
iii. Sand 3 ½ to 4 ½ parts per Cement
iv. Fibers Maximum 3 oz per batch
b. MIX 2:
i. Portland Cement 1 part
ii. Lime (type S) ¼ to ½ part
iii. Sand 3 to 4 parts per cement & Lime
iv. Fibers Maximum 3 oz per batch c. MIX 3:
d. Plastic Cement 1 part
e. Sand 3 ½ to 4 ½ parts per cement
f. Fibers Maximum 3 oz per bag plastic cement

2. Engineered Method: Pre-mix blends or silos per SMA manufacturer.

City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-6

B. Finish Coats: Mixing and tinting instructions are contained in the appropriate product data sheets by the SMA Manufacturer.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Prior to the application of the portland cement plaster basecoat the plastering contractor shall ensure that:

B. Surface and site conditions are ready to receive work.

C. Grounds and Blocking: Verify that the items within the walls for other sections of work have been installed.

D. Notify architect/owner of any defects that may impact the finished assembly.

Proceed as directed.

E. Substrates:

1. Acceptable substrates must be sound, secure and suitable for plaster.

2. Substrates and adjacent materials must be dry and clean. Substrate surface must be flat, free of protrusions or planar irregularities greater than ¼-nch in 10-feet (6mm in 3m).

F. Flashings/Sealant joints: All flashing or sealant joints around windows, at deck attachments, utility penetrations, roof lines, etc. and all kick -out flashing must be properly installed prior to application of portland cement plaster. Notify owner if flashings are missing, proceed as directed.

G. Casing bead shall be applied around all penetrations with a minimum ¼ inch to maximum ¾ inch gap to receive a backer rod and sealant. Gap width will depend on conditions.

H. Unsatisfactory conditions or concerns shall be reported to the general contractor and/or builder and/or architect and/or owner. Do not proceed until directed in writing by architect or general contractor.

3.02 PREPARATION
A. Substrate: inspect all work prior to starting lath and plastering. Notify architect of any issues impacting performance, proceed as directed.

B. Surrounding Areas: Protect surfaces near the work of this section from damage, disfiguration, and overspray. Mask off all dissimilar materials.

3.03 INSTALLATION, GENERAL
A. General Installation: Refer to ASTM C926, ASTM C1063, and/or the appropriate manufacturer’s product data sheet for additional installation requirements and recommendations of the SMA.

City of Camarillo PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS CH-5067-2 092400-7

3.04 INSTALLING WEATHER PROTECTION
A. Water-Resistive Barrier: Generally not required. Coating of concrete/masonry substrate may be called out. Use a fluid applied material approved by SMA manufacturer and compatible for stucco over masonry. Apply per manufacturers recommendations.

3.05 INSTALLING FINISH COAT
A. General: Mix and apply per manufacturer’s product data sheet.

B. Do not apply to soft, contaminated or frozen basecoat.

C. Avoid applying to excessively hot walls.

D. Verification: Verify the desired color, material and texture to match the approved sample and/or mock-up prior to installation.

E. Avoid scaffold lines and cold joints
F. Fog coat (cement finish only) as needed to blend color variations G. Finish coat shall be free of eye catching imperfections.

3.06 CLEANING/PATCHING/TOLERANCE
A. Cleaning: Remove any and all materials used, overspray from adjacent surfaces, and all protective masking.

B. Patch and repair as needed, including but not limited to fog coating, imperfections and blisters.

C. Cracks shall be repaired per the most current SMA Crack Policy (Technical Bulletin 4)
D. The basecoat of plaster shall be in tolerance:

1. Residential: Not to exceed ¼ inch in eight (8) feet

2. Commercial: Not to exceed ¼ inch in ten (10) feet
E. Eye catching variations in color or texture pattern will not be accepted.

3.07 PROTECTION
A. Protection: Protect applied material from inclement weather until dry and prevent it from freezing for a minimum of 24- hours after set and/or until dry. Refer to manufacturer’s product data sheet for additional requirements.

END OF SECTION 092400 – PORTLAND CEMENT PLASTER ON CONCRETE/MASONRY WALLS

City of Camarillo TILING
CH-5067-2 093113-1

SECTION 093113 – TILING
PART 1 - GENERAL

1.01 SECTION INCLUDES
A. Tile for floor applications.

B. Tile for wall applications.

C. Cementitious backer board as tile substrate.

D. Ceramic trim.

1.02 REFERENCE STANDARDS
A. ANSI A108 Series/A118 Series/A136.1 - American National Standard Specifications for the Installation of Ceramic Tile (Compendium) ; 2017.

1. ANSI A108.4 - American National Standard Specifications for Installation of Ceramic Tile with Organic Adhesives or Water Cleanable Tile- Setting Epoxy Adhesive;

2. ANSI A108.5 - American National Standard Specifications for Installation of Ceramic Tile with Dry -Set Portland Cement Mortar or Latex -Portland Cement Mortar;.

3. ANSI A108.6 - American National Standard Specifications for Installation of Ceramic Tile with Chemical Resistant, Water Cleanable Tile-Setting and -Grouting Epoxy;.

4. ANSI A108.8 - American National Standard Specifications for Installation of Ceramic Tile with Chemical Resistant Furan Resin Mortar and Grout;

5. ANSI A108.9 - American National Standard Specifications for Installation of Ceramic Tile with Modified Epoxy Emulsion Mortar/Grout ;

6. ANSI A108.10 - American National Standard Specifications for Installation of Grout in Tilework ;

7. ANSI A118.3 - American National Standard Specifications for Chemical Resistant, Water Cleanable Tile Setting and -Grouting Epoxy and Water Cleanable Tile-Setting Epoxy Adhesive ;

8. ANSI A118.6 - American National Standard Specifications for Standard Cement Grouts for Tile Installation ;

9. ANSI A118.7 - American National Standard Specifications for Polymer Modified Cement Grouts for Tile Installation;

10. ANSI A137.1 - American National Standard Specifications for Ceramic Tile ; 2008.

B. TCNA (HB) - Handbook for Ceramic, Glass, and Stone Tile Installation ; 2012.

City of Camarillo TILING
CH-5067-2 093113-2

1.03 SUBMITTALS
A. Samples: Mount tile and apply grout on two plywood panels, minimum 18 x 18 inches in size illustrating pattern, color variations, and grout joint size variations.

B. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

C. Maintenance Data: Include recommended cleaning methods, cleaning materials, stain removal methods, and polishes and waxes.

D. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.

1. Extra Tile: 6 square feet of each size, color, and surface finish combination.

1.04 QUALITY ASSURANCE
A. Maintain one copy of The Tile Council of North America Handbook and ANSI A108 Series/A118 Series on site.

B. Installer Qualifications: Company specializing in performing tile installation, with minimum of 5 years of documented experience.

PART 2 - PRODUCTS

2.01 TILE
A. Manufacturers: All products of each type by the same manufacturer.

1. American Olean: www.americanolean.com.

2. Dal-Tile Corporation: www.daltile.com.

3. Crossville Americana, Inc.: www.crossvilleinc.com base for design.

B. Quarry Tile Flooring: Standard Red

1. Moisture Absorption: 0 to 0.5 percent.

2. Size and Shape: as shown in the drawings.

3. Colors: Standard Red

4. Trim Units: Matching bead, cove, and surface bullnose shapes in sizes coordinated with field tile.

5. Sealant as required for Health Department Approval

2.02 SETTING MATERIALS
A. Epoxy Adhesive: ANSI A118.3, thinset bond type.

2.03 GROUT MATERIALS
A. Grout: Any type specified in ANSI A118.3.

B. Colors: To be selected by Architect from manufacturer's standard range.

City of Camarillo TILING
CH-5067-2 093113-3

C. Sealant as required for Health Department Approval
PART 3 - EXECUTION

3.01 EXAMINATION
A. Verify that sub-floor surfaces are smooth and flat within the tolerances specified for that type of work and are ready to receive tile.

B. Verify that wall surfaces are smooth and flat within the tolerances specified for that type of work, are dust-free, and are ready to receive tile.

C. Verify that required floor-mounted utilities are in correct location.

3.02 PREPARATION
A. Epoxy Grout: ANSI A118.3 chemical resistant and water-cleanable epoxy grout.

B. Protect surrounding work from damage.

C. Vacuum clean surfaces and damp clean.

D. Seal substrate surface cracks with filler. Level existing substrate surfaces to acceptable flatness tolerances.

E. Prepare substrate surfaces for adhesive installation in accordance with adhesive manufacturer's instructions.

3.03 INSTALLATION - GENERAL
A. Install tile and thresholds and grout in accordance with applicable requirements of ANSI A108.1 through A108.13, manufacturer's instructions, and The Tile Council of North America Handbook recommendations.

B. Lay tile to pattern indicated. Do not interrupt tile pattern through openings.

C. Place tile joints uniform in width, subject to variance in tolerance allowed in tile size. Make joints watertight, without voids, cracks, excess mortar, or excess grout.

D. Form internal angles square and external angles bullnosed.

E. Install thresholds where indicated.

F. Sound tile after setting. Replace hollow sounding units.

G. Allow tile to set for a minimum of 48 hours prior to grouting.

H. Grout tile joints. Use standard grout unless otherwise indicated.

I. Apply sealant to junction of tile and dissimilar materials and junction of dissimilar planes.

3.04 INSTALLATION - FLOORS - THIN-SET METHODS
A. Over interior concrete substrates, install in accordance with The Tile Council of North America Handbook Method F113, dry -set or latex -Portland cement bond coat, with standard grout, unless otherwise indicated.

City of Camarillo TILING
CH-5067-2 093113-4

3.05 CLEANING
A. Clean tile and grout surfaces.

3.06 PROTECTION
A. Do not permit traffic over finished floor surface for 4 days after installation.

END OF SECTION 093113 – TILING

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-1

SECTION 099113 – EXTERIOR PAINTING
PART 1 - GENERAL

1.01 SUMMARY
A. This Section includes surface preparation and the application of paint systems on the following exterior substrates:

1. Concrete.

2. Concrete masonry units (CMU).

3. Steel.

4. Galvanized metal.

5. Exterior Portland cement plaster (stucco).

1.02 SUBMITTALS
A. Product Data: For each type of product indicated.

B. Samples for Verification: For each type of paint system and each color and gloss of topcoat indicated.

1. Submit Samples on rigid backing, 8 inches square.

2. Step coats on Samples to show each coat required for system.

3. Label each coat of each Sample.

4. Label each Sample for location and application area.

C. Product List: For each product indicated, include the following:

1. Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules.

2. Printout of current "MPI Approved Products List" for each product category specified in Part 2, with the proposed product highlighted.

1.03 QUALITY ASSURANCE
A. MPI Standards:

1. Products: Complying with MPI standards indicated and listed in "MPI Approved Products List."

2. Preparation and Workmanship: Comply with requirements in "MPI Architectural Painting Specification Manual" for products and paint systems indicated.

B. Mockups: Apply benchmark samples of each paint system indicated and each color and finish selected to verify preliminary selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

1. Architect will select one surface to represent surfaces and conditions for application of each paint system specified in Part 3.

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-2

a. Vertical and Horizontal Surfaces: Provide samples of at least 100 sq. ft..
b. Other Items: Architect or owner will designate items or areas required.

2. Final approval of color selections will be based on benchmark samples. a. If preliminary color selections are not approved, apply additional benchmark samples of additional colors selected by Architect at no added cost to Owner.

1.04 DELIVERY, STORAGE, AND HANDLING
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F.

1. Maintain containers in clean condition, free of foreign materials and residue.

2. Remove rags and waste from storage areas daily.

1.05 PROJECT CONDITIONS
A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are between 50 and 95 deg F.

B. Do not apply paints in snow, rain, fog, or mist; when relative humidity exceeds 85 percent; at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.

1.06 EXTRA MATERIALS
A. Furnish extra materials described below that are from same production run (batch mix) as materials applied and that are packaged for storage and identified with labels describing contents.

1. Quantity: Furnish an additional 5 percent, but not less than 1 gal of each material and color applied.

PART 2 - PRODUCTS

2.01 MANUFACTURERS
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Dunn-Edwards Corporation.

2. Sherwin-Williams Company.

3. ICI Paints.

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-3

2.02 PAINT, GENERAL
A. Material Compatibility:

1. Provide materials for use within each paint system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

2. For each coat in a paint system, provide products recommended in writing by manufacturers of topcoat for use in paint system and on substrate indicated.

B. Colors: to match existing structures (City Hall Building or Corporation Yard, respectively); Owner to provide color name/manufacturer; As selected by Architect from manufacturer's full range and or as indicted on drawings.

2.03 BLOCK FILLERS
A. Interior/Exterior Latex Block Filler: MPI #4.

1. VOC Content: E Range of E2.

2.04 PRIMERS/SEALERS
A. Alkali-Resistant Primer: MPI #3.

1. VOC Content: E Range of E2.

B. Bonding Primer (Water Based): MPI #17.

1. VOC Content: E Range of E2.

C. Bonding Primer (Solvent Based): MPI #69.

1. VOC Content: E Range of E2.

D. Wood-Knot Sealer: Not used

2.05 METAL PRIMERS
A. Alkyd Anticorrosive Metal Primer: MPI #79.

1. VOC Content: E Range of E2.

B. Quick-Drying Alkyd Metal Primer: MPI #76.

1. VOC Content: E Range of E2.

C. Cementitious Galvanized-Metal Primer: MPI #26.

1. VOC Content: E Range of E1.

D. Waterborne Galvanized-Metal Primer: MPI #134.

1. VOC Content: E Range of E2.

2. Environmental Performance Rating: EPR 2.

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-4

2.06 EXTERIOR LATEX PAINTS
A. Exterior Latex (Flat): MPI #10 (Gloss Level 1).

1. VOC Content: E Range of E2.

B. Exterior Latex (Semigloss): MPI #11 (Gloss Level 5).

1. VOC Content: E Range of E2.

C. Exterior Latex (Gloss): MPI #119 (Gloss Level 6, except minimum gloss of 65 units at 60 deg).

1. VOC Content: E Range of E2.

2.07 QUICK-DRYING ENAMELS
A. Quick-Drying Enamel (Semigloss): MPI #81 (Gloss Level 5).

1. VOC Content: E Range of E2.

B. Quick-Drying Enamel (High Gloss): MPI #96 (Gloss Level 7).

1. VOC Content: E Range of E2.

2.08 TEXTURED AND HIGH-BUILD COATINGS
A. Latex Stucco and Masonry Textured Coating: MPI #42.

1. VOC Content: E Range of E2.

PART 3 - EXECUTION

3.01 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of work.

B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

1. Concrete: 12 percent.

2. Masonry (Clay and CMU): 12 percent.

3. Wood: not used

4. Plaster: 12 percent.

C. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers.

D. Begin coating application only after unsatisfactory conditions have been corrected and surfaces are dry.

1. Beginning coating application constitutes Contractor's acceptance of substrates and conditions.

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-5

3.02 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates and paint systems indicated.

B. Remove plates, machined surfaces, and similar items already in place that are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface -applied protection if any.

2. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

C. Clean substrates of substances that could impair bond of paints, including dirt, oil, grease, and incompatible paints and encapsulants.

1. Remove incompatible primers and re- prime substrate with compatible primers as required to produce paint systems indicated.

D. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that permitted in manufacturer's written instructions.

E. Concrete Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that permitted in manufacturer's written instructions.

F. Steel Substrates: Remove rust and loose mill scale. Clean using methods recommended in writing by paint manufacturer.

G. Galvanized-Metal Substrates: Remove grease and oil residue from galvanized sheet metal fabricated from coil stock by mechanical methods to produce clean, lightly etched surfaces that promote adhesion of subsequently applied paints.

H. Wood Substrates: NOT USED
I. Plastic Trim Fabrication Substrates: NOT USED
J. Plaster Substrates: Do not begin paint application until plaster is fully cured and dry.

3.03 APPLICATION
A. Apply paints according to manufacturer's written instructions.

1. Use applicators and techniques suited for paint and substrate indicated.

2. Paint surfaces behind movable items same as similar exposed surfaces.

Before final installation, paint surfaces behind permanently fixed items with prime coat only.

B. Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of same material are to be applied. Tint undercoats to match color of topcoat, but provide sufficient difference in shade of undercoats to distinguish each separate coat.

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-6

C. If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance.

D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections.

Cut in sharp lines and color breaks.

3.04 FIELD QUALITY CONTROL
A. Testing of Paint Materials: Owner reserves the right to invoke the following procedure at any time and as often as Owner deems necessary during the period when paints are being applied:

1. Owner will engage the services of a qualified testing agency to sample paint materials being used. Samples of material delivered to Project site will be taken, identified, sealed, and certified in presence of Contractor.

2. Testing agency will perform tests for compliance of paint materials with product requirements.

3. Owner may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying- paint materials from Project site, pay for testing, and repaint surfaces painted with rejected materials. Contractor will be required to remove rejected materials from previously painted surfaces if, on repainting with complying materials, the two paints are incompatible.

3.05 CLEANING AND PROTECTION
A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

B. After completing paint application, clean spattered surfaces. Remove spattered paints by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and leave in an undamaged condition.

D. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.

3.06 EXTERIOR PAINTING SCHEDULE
A. Concrete Substrates, Non-traffic Surfaces:

1. Latex System: MPI EXT 3.1A.
a. Prime Coat: Exterior latex matching topcoat.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

2. Latex Aggregate/Latex System: MPI EXT 3.1 B.
a. Prime Coat: Latex stucco and masonry textured coating. b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

City of Camarillo EXTERIOR PAINTING
CH-5067-2 099113-7

3. Latex Over Alkali-Resistant Primer System: MPI EXT 3.1K. a. Prime Coat: Alkali-resistant primer.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

B. Concrete Substrates, Traffic Surfaces:

1. NOT USED
C. CMU Substrates:

1. Latex System: MPI EXT 4.2A.
a. Prime Coat: Interior/exterior latex block filler.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

2. Latex Over Alkali-Resistant Primer System: MPI EXT 4.2L. a. Prime Coat: Alkali-resistant primer.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

D. Steel Substrates:

1. Quick-Drying Enamel System: MPI EXT 5.1A.
a. Prime Coat: Quick-drying alkyd metal primer.
b. Intermediate Coat: Quick-drying enamel matching topcoat. c. Topcoat: Quick-drying enamel (semigloss) (high gloss).

2. Alkyd System: MPI EXT 5.1D.
a. Prime Coat: Alkyd anticorrosive metal primer.
b. Intermediate Coat: Exterior alkyd enamel matching topcoat. c. Topcoat: Exterior alkyd enamel (flat) (semigloss) (gloss).

E. Galvanized-Metal Substrates:

1. Latex System: MPI EXT 5.3A.
a. Prime Coat: Cementitious galvanized-metal primer.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

2. Latex Over Water-Based Primer System: MPI EXT 5.3H. a. Prime Coat: Waterborne galvanized-metal primer.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

F. Exterior Cement Plaster Substrates:

1. Latex System: MPI EXT 9.1A.
a. Prime Coat: Exterior latex matching topcoat.
b. Intermediate Coat: Exterior latex matching topcoat. c. Topcoat: Exterior latex (flat) (semigloss) (gloss).

END OF SECTION 099113 – PAINTING
City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-1

SECTION 260000 – GENERAL ELECTRICAL
PART 1 - GENERAL

1.01 SUMMARY
A. This specification defines the general electrical work required for complete and fully functioning BESS ready standby power systems at each site, including any ancillary electrical work. The work shall include the design, procurement, construction, commissioning and startup of the electrical systems, materials, equipment, fabrication, installation, and tests in conformity with applicable codes, laws, regulations, and professionally recognized standards.

B. “Owner” shall refer to the City regardless of system ownership, and include any representative of the City, such as independent engineers, consultants or inspectors. “Contract” refers to the construction contract and any associated “Contractor” refers to the entity performing the work.

1.02 DEFINITIONS
A. AC: Alternating Current.

B. AWG: American Wire Gage
C. IEEE: Institute of Electrical and Electronics Engineers.

D. HDB: Horizontal Directional Bore.

E. NEC: National Electrical Code.

F. NEM: Net Energy Meter.

G. NEMA: National Electrical Manufacturers Association
H. NRTL: Nationally Recognized Testing Laboratory.

I. RFI: Request for Information
J. RFP: Request for Proposals
K. PTO: Permission to Operate (from the electrical utility) L. PVC: Polyvinyl Chloride
M. UBC: Uniform Building Code
N. UL: Underwriters Laboratories.

1.03 CODES & REFERENCES
A. The installation shall conform to all requirements as defined by the applicable codes, laws, rules, regulations and standards of applicable code enforcing authorities (Latest Edition unless otherwise noted). The following are key standards that shall be followed. The Architect/Engineer of Record and Contractor shall ensure all applicable codes are followed:

1. American National Standards Institute (ANSI)
City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-2

2. California Building Code (CBC), with State of California Amendments

3. California Department of Forestry and Fire Protection, Office of the State Fire Marshal

4. California Energy Commission (CEC) Title 24 Building Energy Efficiency Requirements

5. California Public Utilities Commission (CPUC), Including Title 21

6. Institute of Electrical and Electronics Engineers (IEEE)

7. International Electrical Testing Association (NETA)

8. Local Fire Permit Requirements

9. National Electrical Manufacturers Association (NEMA)

10. National Fire Protection Association (NFPA), National & California Electrical Code (NEC & CEC)

11. Underwriters Laboratory (UL), including:

12. UL 2200 – Standard for Safety Stationary Engine Generator Assemblies.

13. Utility company standards and requirements

14. Owner Specifications and Requirements

15. All other applicable Codes and Ordinances

1.04 WORK INCLUDED
A. The Contractor shall include all items and all work reasonably inferred by these specifications and the Contract, including any design- bid-build bridging documents. If the Contractor is in doubt as to the intent of any portion of these specifications or the Contract, or necessary information is omitted, the Contractor shall notify the Owner in writing for clarifications or corrections to be provided by addendum.

B. All required construction documents and compliance documentation.

C. All required as-built and close-out documents and compliance documentation.

D. Temporary power and lighting as required for construction and security during construction.

E. All required incidental work directly related to the construction of the System, including, but not limited to: excavating, directional boring, backfilling, roof flashing, fire stopping, waterproofing, pavement repair, striping, and testing.

F. Any other electrical work as might reasonably be implied as required to fulfill the contracted scope, even though not specifically mentioned herein or shown on the drawings.

G. Construction coordination with all other disciplines and trades.

H. All other utilities, labor, materials, apparatus, tools, equipment, transportation, and special or occasional services as required to fulfill the contracted scope.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-3

1.05 CONDITIONS AT SITE
A. Contractor is responsible for familiarizing themselves with all discernible site conditions. No extra payment will be allowed for work required because of these conditions, whether specifically mentioned or not.

B. Lines of other services that are damaged as a result of this work shall promptly be repaired at no expense to the Owner and to the complete satisfaction of the Owner.

1.06 QUALITY ASSURANCE
A. GENERAL

1. Construction Documents shall be designed and signed by a validated, registered professional engineer in the State of California.

2. No modifications shall be made to the approved Construction Documents without the Owner’s written consent.

B. CONFORMANCE

1. All equipment and accessories to be the product of a manufacturer regularly engaged in its manufacture.

2. Supply all new equipment and accessories free from defects and listed by Underwriter’s Laboratories, Inc., or bearing its label or label of a Nationally Recognized Testing Laboratory (NRTL).

3. All items of a given type shall be the products of the same manufacturer, or equal.

4. If after contract is awarded, minor changes and additions are required by aforementioned authorities, they shall be included at Contractor’s expense.

C. COORDINATION

1. Contractor shall become familiar with the conditions at each job site and plan the installation of the electrical work to conform with the existing conditions so as to provide the best assembly of the combined work of all trades.

D. COORDINATION DRAWINGS FOR ELECTRICAL INSTALLATION

1. Prepare Coordination Drawings, to scale. Detail major elements, components and systems of electrical equipment and materials in relation to each other and to other systems, installations, and building components.

Indicate locations and space requirements for installation, access and working clearances. Show where sequence and coordination of installations are important to the efficient flow of the Work. Indicate the following:
a. Provisions for scheduling, sequencing, moving, and positioning large equipment in or on the site or buildings during construction. b. Plans, elevations, and details including the following:
i. Clearances to meet safety requirements and for servicing and maintaining equipment, including space for equipment
disassembly required for periodic maintenance.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-4

ii. Equipment support details.
iii. Exterior wall, roof and foundation penetrations of cable and raceway; and their relation to other penetrations and
installations.
iv. Fire-rated wall and roof penetrations by electrical installations. v. Sizes and locations of required concrete pads and bases. vi. Grounding system details.

1.07 DELIVERY, STORAGE AND HANDLING
A. Protection: Use all means necessary to protect the materials of this Section before, during, and after installation and to protect the work and materials of all trades.

B. Delivery and Storage: Deliver all materials to the job site in their original containers with all labels intact and legible at time of use. Store in strict accordance with approved manufacturers' recommendations. All deliveries are to be made to the Contractor’s job trailer or approved storage location. Under no circumstances shall Owner be responsible for accepting deliveries.

C. Replacements: In the event of damage, immediately make all repairs and replacements necessary to the approval of the Owner and at no additional cost to the Owner.

D. Contractor shall personally, or through an authorized representative, check all materials upon receipt at jobsite for conformance with approved shop drawings and/or plans and specifications.

1.08 SCHEDULING/SEQUENCING
A. Contractor shall coordinate all schedules and sequencing of electrical work with Owner.

B. Place orders for all equipment in time to prevent any delay in construction schedule or completion of project. If any materials or equipment are not ordered in time, additional charges made by equipment manufacturers to complete their equipment in time to meet the construction schedule, together with any special handling charges, shall be borne by the Contractor.

C. Contractor shall coordinate production and delivery schedule for all Owner - supplied equipment with the equipment suppliers to ensure that all Owner-supplied equipment is delivered to site in coordination with the construction schedule and in such a manner as to cause no delays in completion of the Contract as scheduled.

1.09 WIND LOADING AND SEISMIC DESIGN
A. Comply with all applicable codes and standards and provide wind load restraints for all equipment installed under this contract that requires restraint. The electrical equipment wind loading restraint shall be designed as required by the Authorities Having Jurisdiction (AHJs).

B. The electrical system shall be designed for the appropriate seismic zone and to meet all seismic design requirements of the AHJs. Where applicable, the electrical equipment shall be designed to accommodate lateral displacement in the event of City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-5

an earthquake based on a nonlinear response- history seismic analysis for the appropriate seismic zone.

1.10 PERMITS AND INSPECTIONS
A. Contractor shall obtain all required permits and arrange for all required inspections, including utility company requirements, inspections, and sign-offs. Utility company coordination and permitting shall include the complete interconnect process and securing utility permission to operate (PTO).

B. Do not allow or cause any of the work to be covered or enclosed until it has been tested and/or inspected.

PART 2 - PRODUCTS

2.01 MATERIALS
A. Materials of the same type or classification, used for the same purpose, shall be the product of the same manufacturer, or equal.

2.02 CATALOGED PRODUCTS / SERVICE AVAILABILITY
A. Materials and equipment shall be current products by manufacturers regularly engaged in the production of such products. Specified product models shall have been in satisfactory commercial or industrial use for a minimum of 2 years prior to design. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The 2 -year period shall be satisfactorily completed by a product for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures. Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6,000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished. The equipment items shall be supported by service organizations which are reasonable convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

2.03 ACCEPTABLE MANUFACTURERS
A. Materials shall be of make mentioned elsewhere in this specification, or equal. All materials shall be new and approved by the Underwriters' Laboratories or an NRTL approved by Owner.

2.04 BASIC ELECTRICAL EQUIPMENT AND MATERIALS
A. AC Panelboards:

1. As manufactured by Eaton, Schneider Electric, General Electric, Siemens, IEM, or to match existing equipment at each Site, wherever possible.

Similar products may be submitted for considerations and formal approval.

Equipment shall at a minimum be NEMA 3R outdoors or NEMA 1 for surface mount in unfinished interior locations and flush mounted in finished City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-6

and occupied spaces. Provide housekeeping pads for all floor or slab mounted equipment.

2. Enclosures: code gauge galvanized sheet steel with welded full flange end pieces, stretcher-leveled steel trim, back pan and door or painted steel or powder-coated steel. All surface mounted panels to have enclosures painted in gray enamel. Phase and ground bussing of copper with silver - plated or tin-plated or nickel-plated contact surfaces.

3. Trims on surface-mounted cabinets secured with nickel-plated screws with cup washers, bottom of all trims to have lugs for resting on cabinet flange.

4. Panels shall be 20 inches minimum in width, provided with approved gutter space, barriers and adjustable supports. Doors mounted with concealed hinges provided with standard locking mechanism by panel manufacturers.

Doors and trims and surface mounted cabinets primed and finished with standard primer provided by manufacturer and factory.

5. Each panel shall be equipped with a copper ground bus.

6. All panels shall be fully bussed to accept future circuit breakers.

B. Distribution Low Voltage Dry-Type Transformers (120/208V and 277/480V):

1. Ventilated type, NEMA 3R where used outdoors.

2. Transformer shall be 3 -phase, 60 Hertz. Primary winding shall be Delta connected and secondary winding shall be Wye connected. The temperature rise at rated voltage and full load shall not exceed 150 degrees C with a 220 degrees C U.L. Component Recognized Insulation System.

The windings shall be Aluminum or Copper.

3. The higher voltage winding shall have quantity (6) 2.5% taps - (2) FCAN and (4) FCBN. Set secondary voltage for 120/208V.

4. Transformer terminals shall be front connected for ease of installation and maintenance.

5. Where the transformers are installed outdoors provide weatherproof drip cover, rodent screen and a NEMA 3R rating of the enclosure.

C. Circuit Breakers:

1. Circuit breakers shall be molded case rated 250 or 480 volt, multiple or single pole with amperage ratings as required for each circuit. All breakers to be bolt on, manually operated with "de-ion" arc chutes. Plug-in breakers are not acceptable.

2. Circuit breakers shall be suitable for reverse feed and rated to interrupt the available short circuit current at the point of application.

D. Raceways and Conduit Bodies: Only the raceways specified below shall be utilized on these projects. Substitutions shall be pre-approved in writing:

1. Rigid Type - hot dip galvanized, to be used at all exterior locations where exposed to physical damage, or in concrete slab, and to 18" on either side of structural expansion joints in floor slabs, with completely watertight, threaded fittings throughout.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-7

2. All rigid steel conduit couplings and elbows in soil or concrete or under membrane to be ½ lap wrapped with Scotch #50 tape and threaded ends coated with T&B #S.C.40 rust inhibitor prior to installation of couplings.

3. ½ lap wrap all rigid steel conduit stub -ups from slab or grade to 6" above finished grade level with Scotch #50 tape.

4. In lieu of rigid steel conduit for power and control raceways and branch circuit conduits in soil or concrete slabs, "Schedule 40" PVC with Schedule 80 PVC conduit elbows and stub -ups may be used with code size (minimum No. 12) ground wire. A “stub- up” is considered to terminate 6" above the finished surface.
a. Schedule 80 PVC conduit shall be used in all concrete footings or foundations and to 18" of either side of footings or foundation walls. b. Schedule 80 PVC conduit shall be used in all concrete masonry unit (CMU) walls or columns.

5. Provide a minimum cover of 30 inches for all conduits in ground outside of buildings, unless otherwise noted.

6. Horizontal Directional Boring:
a. Conduit installed using horizontal directional boring (HDB) shall include tracer tape or traceable conduit. Minimum depth of the conduit shall be per CEC 2022 Article 300.5 or per Owner Requirements, whichever is more stringent. The Contractor is responsible for demonstrating that all conduits installed utilizing horizontal boring meets the minimum depth requirement and is solely responsible for any remediation costs and schedule impacts if the specification is not met. Contractor shall provide documentation of final depth and routes of all conduit installed in horizontal bores.
b. Prior to construction, final boring and trenching plans shall be approved by signature by the engineer of record to confirm that depths and routing are compliant with all code requirements related to area of repose for adjacent buildings and other structures. Boring and trenching should stay out of this zone of structural influence wherever possible. In areas where the bore or trench must fall in this area, all measures necessary (such as addition of slurry encasement) will be taken to comply with code requirements and the requirements of the structural and geotechnical engineers.
c. Complete and accurate as-builts and reporting of bore path, diameter, depth, and conduit configuration shall be provided in hard copy and electronic format at completion of construction. As -built record set to be updated within 30 days of completion of this work. The boring data shall be recorded in minimum 10ft intervals during installation, and the full data set shall be provided.
d. Threshold on voltage: Allowable for electrical/wiring systems not exceeding 600V only. (Open trench installation with concrete encasement is required where voltage is greater than 600V.) Encasement will not be required in bore trenches in drive aisles where bentonite will be used to sufficiently fill the interstitial space / annulus. e. Bore trench will avoid the 2- 5 ft depth range where possible, as this area is commonly congested with existing underground utilities.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-8

f. Since conduits are pulled in bundles when installing in bore trenches, Contractor shall take measures necessary to allow for heat dissipation between conduits, by addition of empty conduit or other means as required by code. All conduit to be PVC Sch 40 or as approved by Owner.
g. Minimum separation between electrical conduit and conduit for communications cabling shall be maintained per code and for proper functioning of data conductors. Owner will consider deviations from requirements, such as use of a single bore path for both electrical and low voltage wiring with an RFI from Contractor that propose alternate solution.
h. Detectable locator tape is to be used along entire length of each bore route to indicate alignment of conduits and presence of shallow utilities.
i. Conduit buried underground shall be suitable for the application and compliant with all applicable codes. PVC shall be constructed of a virgin homopolymer PVC compound and be manufactured according to NEMA and UL specifications.

All PVC conduit feeders shall contain an appropriate copper grounding conductor sized per CEC requirements and
continuity shall be maintained throughout conduit runs and pull boxes. Minimum conduit size shall be ¾”. A metallic
tracing/caution tape shall be installed in the trench over all buried conduits.

7. All underground conduits placed in trenches, buried under roadways, or under swales shall be encased with red dyed concrete.

8. All conduit runs in concrete floor slabs (where allowed) shall be installed to comply with all applicable UBC and structural codes to maintain the structural integrity of the floor slab. Where conflicts occur, alternate routing shall be provided at no additional cost to the Owner.

9. Electrical Metallic Tubing (EMT) shall only be exposed in electrical and mechanical rooms and in unfinished spaces and in concealed and furred spaces, made up with steel watertight or steel set screw type fittings and couplings. Set screws shall have hardened points. Cast fittings are unacceptable. EMT may be used in exterior installations where allowed by CEC or AHJ requirements and any other applicable code. All exterior fittings shall be watertight. EMT may not be installed in areas subject to severe physical damage, including in any carport location with potential for vehicle strike. EMT may not be installed within 8’ of grade in exterior locations.

10. Fasten conduits securely to boxes with locknuts and bushings to provide good electrical continuity.

11. To facilitate pulling of conductors, install junction boxes as required.

12. If empty conduits are provided as part of the project, conduits shall be provided with a minimum of two sufficiently rated pull strings or wires inside conduit and properly capped for future wire pull.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-9

13. If conduits are to pass through structural expansion joints in floor slab, rigid galvanized conduit shall be used 18" on either side of joint, complete with Appleton expansion couplings and bonding jumpers, or equal. All above grade expansion joint crossings shall also utilize expansion joint couplings or flex conduit transitions as required for each particular installation. No solid conduits shall be allowed to cross expansion joints without proper provisions for building and seismic movement.

14. Provide thermal expansion fittings or provisions, per CEC 300.7(b), for all raceways subject to high temperatures in direct exposure to sunlight.

Provide expansion provisions where more than 0.25" of expansion is calculated.

15. Provide and install exterior wall conduit seals and cable seals in the locations listed below. Coordinate installation and scheduling with other trades:

16. Conduit seals through exterior wall or slab (below grade): O.Z. Gedney series “FSK" (or approved equivalent) in new cast in concrete locations, series "CSM" (or approved equivalent) in cored locations.

17. Conduit seals through exterior wall or slab (above grade): O.Z. Gedney series "CSMI" (or approved equivalent).

18. Cable seals at first interior conduit termination after entry through exterior wall or slab: O.Z. Gedney series "CSBI" (or approved equivalent).

Coordinate quantity of conductors at each location.

E. Junction Boxes / Pull Boxes:

1. One-piece steel knockout type drawn j -boxes, unless otherwise noted, sized as required for conditions at each location.

2. J- boxes for wet locations, cast aluminum FS or FD type with cast aluminum gasketed spring lid cover. Weatherproof “Bell” type boxes are not acceptable.

3. Pull boxes to be NEMA 1 (indoor) or NEMA 3R (outdoor), sized per code, with grey enamel finish, steel construction, and screw -on covers. All connectors from conduit to junction or outlet boxes shall have insulated throats. Connectors shall be manufactured with insulated throats as integral part. Insertable insulated throats are unacceptable.

4. Conduit Bodies: Malleable iron type, with lubricated spring steel clips over edge of conduit body, O-Z/Gedney type EW, or equal.

F. Site Pull boxes /Handholes: All site pull boxes shall be flush in- ground concrete, with engraved covers identifying service use (i.e. electrical, communications, etc.).

Boxes shall be NEMA 250, Type 6, outside flanged, with recessed cover for flush mounting, by Christy or equal, with required depth to provide box and conduit depths shown or required.

1. Provide concrete covers for all boxes in planted or paved areas (up to available concrete cover size).

2. Provide galvanized steel covers for all larger boxes (when concrete is not available), or in traffic areas. No cast iron covers.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-10

3. Provide bolted covers and slab bottoms (with grouted perimeter) or vault type boxes for all electrical distribution and signal system pull boxes used for site distribution, to prevent rodent entry. No collar type boxes with dirt or gravel bottoms.

4. Provide drain hole at bottom of all vault type boxes, with loose aggregate base below, for proper drainage.

5. All covers to be completely flush with finished adjacent surfaces.

6. Provide galvanized steel H20 rated covers and installation of box rated for H20 in all traffic areas.

G. Wire and Cable:

1. 600 or 1,000-volt or 1,500-volt class, as required for system design, with color coded insulation, minimum No. 12 AWG for DC string circuits or AC circuits.

2. All conductors shall be copper. Any substitution shall require written approval from Owner.

3. Insulation type:
a. Standard locations: All AC wire sizes used shall be based on a 75- degree insulation rating, unless specifically used with 90-degree rated devices. For wires/cables with 90 deg C insulation, the 90 deg C ampacity ratings shall be used for cable sizing before conditions of use de-rates are applied per CEC.
b. All conductors, excluding bare copper ground conductors, shall be stranded.
c. Install all wiring (low voltage and line voltage) in conduit. d. Do not pull conductors into conduit until raceways and boxes have been thoroughly cleaned and swabbed as necessary to remove water and debris.
e. Approximately balance all AC circuits about the neutral conductors in AC collector panels.
f. All wire and cable shall bear the Underwriters' Label or equivalent NRTL label, brought to the job in unbroken packages.
g. The equipment grounding conductor shall be insulated. Insulation color shall be green.
h. Install all circuits in one continuous section unless splices are approved by Owner. Contractor shall exercise care in pulling to avoid damage or disarrangement of conductors, using approved grips. No cable shall be bent to a smaller radius than the spool on which it was delivered from the manufacturer or as required by CEC code, whichever is greater. Color code feeder cables at terminals. Provide identifying linen tags in each pull box.

H. Fire stopping: as manufactured by 3M Fire Protection Products or equal.

1. Fire-rated and smoke barrier construction: Maintain barrier and structural ceiling fire and smoke resistance ratings including resistance to cold smoke at all penetrations, connections with other surfaces or types of construction, at separations required to permit building movement and sound vibration absorption, and at other construction gaps.

City of Camarillo GENERAL ELECTRICAL
CH-5067-2 260000-11

2. Systems or devices listed in the UL Fire Resistance Directory under categories XHCR and XHEZ may be used, providing that it conforms to the construction type, penetration type, annular space requirements and fire rating involved in each separate instance, and that the system be symmetrical for wall penetrations. Systems or devices must be asbestos free.

PART 3 - EXECUTION

3.01 INSPECTION
A. Examine the areas and conditions under which the work of this Section will be installed. Correct conditions detrimental to the proper and timely completion of the Work. Do not proceed until unsatisfactory conditions have been corrected.

3.02 FIELD QUALITY CONTROL
A. All workmanship shall be first class and carried out in a manner satisfactory to and approved by the Owner.

B. This Contractor shall personally, or through an authorized and competent representative, constantly supervise the work and, as much as possible, keep the same foreman and workmen on the job throughout.

3.03 INSTALLATION/APPLICATION/ERECTION
A. All cutting, repairing and structural reinforcing for the installation of this work shall be done by the General Contractor in conformance with the Owner's requirements.

B. Excavate and trench or directional bore as necessary for the electrical installation, and when the work has been installed, inspected and approved, backfill all excavations with clean earth from excavation, or imported sandy soil in maximum 8" (eight-inch) layers, moisten and machine tamp to 95% compaction, and restore the ground and/or paving or floor surfaces to their original condition.

C. Floor Mounted Equipment Installation: Provide mounting channels for grouting into floor or slab. Channels shall be properly drilled to receive the equipment placed flush in floor, leveled and secured in place prior to pouring of floor, of length as required for switchboard. Bolt or weld switchboard to channels.

D. Furnish and install all disconnect switches as required by code.

3.04 EARTHQUAKE RESISTANT INSTALLATION & FASTENING:

A. All electrical equipment and raceways shall be designed to withstand forces generated by earthquake motions. As a minimum, equipment and equipment frames shall be designed to withstand a force of 25% of the weight of the equipment and frame acting at its center of gravity. Anchorage of the equipment and/or frame to the structure shall be for a force of 50% gravity also acting at the center of gravity.