AGREEMENT NO. 2022-186B

SECOND AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
This Second Amendment to Professional Services Agreement No. 202 2-186 (Amendment) effective date of October 23, 202 4, is entered into between the City of Camarillo, a general law city (City) and Kimley -Horn and Associates, Inc., a North Carolina corporation (Consultant), collectively referred to as the Parties.

Recitals.

A. The Parties have entered into a written agreement entitled “ Professional Services Agreement Number 2022-186” having an effective date of September 28, 2022 (Agreement) to provide for certain professional services in the amount of $473,243.80 as outlined in Exhibit A of Agreement from Consultant.

B. The Parties have entered into a written agreement entitled “First Amendment to Professional Services Agreement” having an effective date of August 22, 2023 (Agreement No. 202 2-186A) to provide additional design support services to support the plan, specification, and estimate package, which includes traffic signal design and Caltrans encroachment permit processing in the amount of $35,500.

C. All capitalized terms not defined in this Amendment have the meaning set forth in the Agreement.

D. The parties desire to modify the scope of work in accordance with Section

3.3 of the Agreement.

Section 1. Amendment. The Agreement is amended to add the following:

1. Additional “Scope of Services” of the Agreement is
amended to add the following:

Provide additional professional services in the amount of $79,740 as included in the proposal dated July 19, 2024, to provide additional design support services to complete the floodplain analyses required to complete design of the
Central Avenue Bike Land project.

Section 2. Compensation and Payment. Second Amendment to Professional Services Agreement is for a not-to-exceed amount of $79,740 for services provided in the proposal dated July 19, 2024, for a total agreement amount of $588,483.80.

Section 3. Continuation of Terms of Agreement. Except as expressly modified by the terms and provisions of this document, the remaining terms and provisions of the Agreement remain in full force and effect.

Page 2 of 2 ends

THE AUTHORIZED REPRESENTATIVES of the Parties have caused this Second Amendment to Agreement No. 2022-186 to be executed as of the Effective Date.

CITY OF CAMARILLO

Greg Ramirez, City Manager
ATTEST:

Kristy Buxkemper, City Clerk

KIMLEY-HORN AND ASSOCIATES, INC., a North Caroliina corporation

Sri Chakravarthy, P.E., Senior Vice President

Nicole Dias, P.E., Assistant Secretary

_ _034018_____ ____________________ _ 12/31/2024_____ Camarillo Business Tax Certificate Number Expiration Date

Attachments: Exhibit A, Scope of Services

kimley-horn.com 660 South Figueroa Street, Suite 2050, Los Angeles, CA 90017 213 261 4040 July 19, 2024
Alyssa Yim
Public Works Department
City of Camarillo
601 Carmen Drive
Camarillo, CA 93010
RE: ST-5102 Central Avenue Bike Lane Project
FEMA Analysis - Amendment Request #2
Kimley-Horn is presenting this letter proposal to request an amendment to the current contract to allow Kimley-Horn to complete the floodplain analyses required to support the Central Avenue Bike Lanes Project (“Project”).

Background
While advancing the drainage analysis, it was identified that there is a Federal Emergency Management Agency (FEMA) Zone AE floodplain and regulatory floodway area within the project limits, which is subject to 1% annual chance flood, also known as the base flood. Encroachments into the floodway require certification and analysis demonstrating that the improvements do not increase flood levels during base flood events.

After review of the FEMA designations, the City and Kimley-Horn met on 7/2/24 to discuss the scope of work required to complete the floodplain analysis and channel modeling to confirm whether the proposed project improvements increase the FEMA base flood model.

Understanding
Kimley Horn understands that the proposed project improvements along the north side of Central Avenue occur within the FEMA Zone AE floodplain and regulatory floodway, according to Flood Insurance Rate Map (FIRM) Panel 06111C0926E, effective January 20, 2010. FEMA Flood Zone AE and Floodway Areas are designations of a Special Flood Hazard Area (SFHA), subject to inundation by the 1% annual chance flood, also known as the base flood. Zone AE specifically refers to a SFHA where Base Flood Elevations (BFEs) have been determined. The Floodway is the channel of a stream plus adjacent floodplain areas that must be kept free of encroachment so that the 1% annual chance flood can be carried without increases in flood heights. Approximately 690 linear feet of the corridor are within Zone AE, followed by approximately 97 linear feet within the Floodway Area.

Per section 16.34.450 Floodways of the City of Camarillo Municipal Code, encroachments into the floodway are prohibited, unless certification by a registered PE is provided demonstrating that the encroachment does not result in any increase in flood levels during the base flood discharge. FEMA’s CC Agreement 2022-186B

EXHIBIT A

Page 2 ends

kimley-horn.com 660 South Figueroa Street, Suite 2050, Los Angeles, CA 90017 213 261 4040 National Flood Insurance Program (NFIP) Regulations indicate that this is demonstrated through hydrologic and hydraulic analyses of the proposed encroachment.

Scope of Services
The following Tasks will be performed to support the Project.

Task 3: Floodplain Analysis and Floodplain Evaluation Memo Task 3.1 City Coordination
Kimley-Horn will attend up to two (2) virtual meetings with the City to coordinate this scope of work.

Kimley-Horn will provide the City with updates regarding the status of the effort, and schedule.

Kimley-Horn will prepare up to four (4) additional invoices for the delay in the project schedule due to this effort.

Task 3.2 FEMA Coordination
Kimley-Horn will coordinate with FEMA to obtain FEMA’s effective Hydraulic Engineering Center River Analysis System (HEC-RAS) hydraulic models.

Task 3.3 Existing Conditions Analysis
Kimley-Horn will perform a hydrologic modeling analysis using federal standards and compare the results against peak flow rates in FEMA’s effective HEC-RAS hydraulic models. This hydrologic modeling would use the US Army Corps of Engineer’s Hydraulic Engineering Center Hydrologic Modeling System (HEC-HMS) software to develop hydrographs and peak flow rates for the base flood, 100-year (1% annual) storm event.

Task 3.4 Post-Project Conditions Analysis
Kimley-Horn will Evaluate the existing Base Flood Elevations (BFEs) and spatial floodplain extents using the HEC-RAS software to develop a two-dimensional hydraulic model of the river and calculate BFEs in the study area. This model will be based on the more conservative of modeled peak flow rates, either those from the newly developed HEC-HMS modeling or from FEMA’s effective HEC-RAS models.

1. If the FEMA effective model is a recent 2D HEC-RAS model, then modeling BFEs and the floodplain will only require checking the effective model inputs and duplicating results.

2. If the FEMA effective model is a one-dimensional (1D) model, then a full 2D model may need to be developed to evaluate existing BFEs.

Task 3.5 Floodway Impacts Analysis and Design Modification Kimley-Horn will utilize the Post-Project Conditions Analysis completed under Task 3.4, to analyze the Floodway Encroachment impacts for the post-project conditions to determine the limits of the regulatory floodway and base flood impacts.

Kimley-Horn will evaluate if and to what extent project grading impacts the updated 100-year floodplain and floodway.

1. For the segment of the proposed project within the floodway, this impact must be zero feet of increase to the base flood water surface. Kimley-Horn will assess minor cross-sectional design modifications to the channel and project improvements to obtain an impact of zero CC Agreement 2022-186B

Page 3 ends

kimley-horn.com 660 South Figueroa Street, Suite 2050, Los Angeles, CA 90017 213 261 4040 feet increase. If larger design modifications are required, an additional scope of work will be discussed with the City at that time.

2. For the segment of the proposed project within Zone AE, the design must not result in an increase in water surface of the base flood by more than one foot.

A summary of these findings will be compiled in a memo for the City to review. One round of consolidated comments is anticipated on the Draft Floodplain Memo for inclusion in the Final Memo.

A CLOMR MT-2 application is not included as part of this amendment. If a CLOMAR MT-2 application is determined to be required, a separate scope and fee will be discussed with the City at that time.

Deliverables: Draft and Final Floodplain Analysis memo.

Schedule
The anticipated effort to complete the work is as follows:

LABOR TASKS
Task 3.2 – FEMA Coordination
Task 3.3 – Existing Conditions Analysis
Task 3.4 – Post-Project Conditions Analysis
Task 3.5 – Floodway Impacts Analysis and
Design Modification

SCHEDULE
One (1) Month from Notice to Proceed
One (1) Month from the completion of Task 3.2
One (1) Month from the completion of Task 3.3
Two (2) Months from the completion of Task 3.4
Fee
These services will be provided on a time and materials basis for a not to exceed total amount of $79,740. Any required permitting, application, or other project fees will be paid directly by the City.

A breakdown of costs by task is provided below:

LABOR TASKS
Task 3.1 – City Coordination
Task 3.2 – FEMA Coordination
Task 4.1 – Existing Conditions Analysis
Task 4.2 – Post-Project Conditions Analysis
Task 4.3 – Floodway Impacts Analysis and Design Modification Amendment Total:

FEE
$6,220
$6,460
$11,330
$13,430
$42,300
$79,740
CC Agreement 2022-186B

Page 4 ends

kimley-horn.com 660 South Figueroa Street, Suite 2050, Los Angeles, CA 90017 213 261 4040 We appreciate the opportunity to provide these services to you. Please contact me if you have any questions.

Sincerely,
KIMLEY-HORN AND ASSOCIATES, INC.

Yiota Georgalis, P.E.

Project Manager
CC Agreement 2022-186B

Name
Category/Title
Billing Rate $360 $235 $175 $175 $150
Task 3 Floodplain Analysis and Floodplain Evaluation Memo 36 28 56 156 154 430 $ 79,740

3.1 City Coordination 2 10 10 8 30 $ 6,220

3.2 FEMA Coordination 2 4 6 18 4 34 $ 6,460

3.3 Existing Conditions Analysis 6 2 4 20 30 62 $ 11,330

3.4 Post-Project Conditions Analysis 6 2 6 30 30 74 $ 13,430

3.5 Floodway Impacts Analysis and Design Modification 20 10 30 80 90 230 $ 42,300 TOTAL HOURS 36 28 56 156 154 430
Subtotal Labor: $12,960 $6,580 $9,800 $27,300 $23,100 $ 79,740 Other Direct Costs $ -
TOTAL COST: $ 79,740
ST-5102 Central Avenue Bike Lane Project
Sr.

Professional II
Drainage
Professional Analyst II

TOTAL HOURS TOTAL COST
ProfessionalSr.

Professional I
FEMA Analysis - Amendment Request #2
CC Agreement 2022-186B