AGREEMENT NO. 2020-1A

FIRST AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
This First Amendment to Professional Services Agreement No. 2020-1 (Amendment) effective date of November 8, 2023, is entered into between the City of Camarillo, a general law city (City) and Ravatt, Albrecht & Associates, Inc., a California corporation (Consultant), collectively referred to as the Parties.

Recitals.

A. The parties have entered into a written agreement entitled “Professional Services Agreement Number 2020-1” having an effective date of January 8, 2020 (Agreement) to provide for certain professional services in the amount of $267,559 as outlined in Exhibit A of Agreement from Consultant.

B. All capitalized terms not defined in this Amendment have the meaning set forth in the Agreement.

C. The parties desire to modify the scope of work in accordance with Section

3.3 of the Agreement.

Section 1. Amendment. The Agreement is amended to add the following:

1. Additional “Scope of Services” of the Agreement is
amended to add the following:

Provide additional professional services in the amount of $88,893.55 as included in the proposal dated October 9, 2023, to provide additional design support services during construction. See attached Exhibit A, Scope of Services.

2. The “Fee Schedule” of the Agreement is amended to
include the attached Exhibit B, Fee Schedule.

Section 2. Compensation and Payment. First Amendment to Professional Services Agreement is for a not-to-exceed amount of $88,893.55 for services provided in proposal dated October 9, 2023, for a total agreement amount of $356,452.55.

Section 3. Continuation of Terms of Agreement. Except as expressly modified by the terms and provisions of this document, the remaining terms and provisions of the Agreement remain in full force and effect.

Page 2 of 2 ends

THE AUTHORIZED REPRESENTATIVES of the Parties have caused this First Amendment to Agreement No. 2020-1 to be executed as of the Effective Date.

CITY OF CAMARILLO
Greg Ramirez, City Manager
ATTEST:

Kristy Buxkemper, City Clerk
RAVATT, ALBRECHT & ASSOCIATES, INC., a California corporation

Gregory A. Ravatt, President

James P. Albrecht, Vice President/Secretary
_ _042531_____ ____________________ _ 08/31/2024_____ Camarillo Business Tax Certificate Number Expiration Date Attachments: Exhibit A, Scope of Services
Exhibit B, Fee Schedule

October 9, 2023
Mr. Eric Maple
City of Camarillo
601 Carmen Drive
Camarillo, CA 93010
City of Camarillo
City Hall Council Chambers Remodel, proposal for Design Services during Construction Dear Mr. Maple;
As the project is now proceeding into construction, RA proposes to provide design support for construction and project closeout. The following services are proposed; Pre-construction Services including Prints on Mylar for Bidding Construction Kick-off Meeting
Travel to Site (Mileage - SLO to Camarillo)
RFI Review and Response
Submittal Review and Response
Weekly Meetings (Quantity of 20 Virtual and 6 Physical) Travel to Weekly Meeting (Quantity of 6 Physical)
Record Drawing Preparation
Prints on Mylar for Record Drawings
A/V Consultant Services During Construction
AV Rough-In Site Inspection
On site Commissioning
As Built Review
Structural Construction Administration
Response to contractor generated field questions
Review of contractor submittals
As-built drawings upon project completion.

Two site visits during the Construction Phase
Fees for Extra Services at current Billing Rates Total: $ 88,893.55 Reimbursable Expenses
As per the original contract, Reimbursable Expenses are included in the Fees for Extra Services and include project related expenses incurred by the project team and consultants in the direct interest of the Project.

CC Agreement 2020-1A

EXHIBIT A

| page 2
Please don’t hesitate to call our office with any questions you may have with regard to this additional fee.

Greg Ravatt, AIA
Principal Architect
Ravatt, Albrecht & Associates
125 Union Ave. Suite 201
PO Box 2267
Orcutt, CA, 93457-2267
(805) 928-5002
CC Agreement 2020-1A

Camarillo Council Chambers Remodel Audiovisual Improvements 601 Carmen Drive
Camarillo, CA 93010
Date: 10/9/2023
Description
Principal
Architect/
Architect
Mechanical
Engineer
Electrical
Engineer Designer
Structural
Engineering &
Drafting
AV
Consultant
fee
Prints
Mylar Mileage Subtotal
Rates (per schedule) $180 $170 $170 $105 Subconsultant + 15% mk up $25.75/sht $0.655 Phase 4 Construction Administration
Pre Construction Services 40 4 8 $483.00 61 300 $11,490.25 Kick‐off Meeting 8 $1,440.00
Travel to Site (Mileage ‐ SLO to CAM) 300 $196.50
RFI Review and Response 48 6 16 $2,435.70 $14,815.70
Submittal Review and Response 60 12 30 $2,435.70 $20,375.70 Weekly Meetings (QTY, 20 virtual, 6 physical) 88 12 12 $2,732.40 $22,652.40 Travel to Weekly Meeting (QTY, 6 physical) 1800 $1,179.00 A/V Consultant services during construction $8,734.25 $8,734.25 Record Drawing Preparation 8 2 24 $2,139.00 $6,439.00
Prints on Mylar for Record Drawings 61 $1,570.75
$88,893.55
Total Hours 252 34 68 24
Subtotal by Staff Category $45,360.00 $5,780.00 $11,560.00 $2,520.00 $10,225.80 $8,734.25 $3,141.50 $1,572.00 $88,893.55Total Fee:

Page 3 ends

CC Agreement 2020-1A

$180.00
170.00
180.00
180.00
170.00
170.00
170.00
140.00
105.00

95.00 85.00

HOURLY RATE SCHEDULE
RAVATT, ALBRECHT & ASSOCIATES, INC.

EMPLOYEE RATES
Principal Architect
Licensed Project Architect
Principal Engineer
Projects Director
Project Manager
Licensed Mechanical Engineer
Licensed Electrical Engineer
Staff Engineer
Designer
Senior CAD
CAD/Clerical

MILEAGE RATE (REIMBURSABLE)
Per mile .655

REPRODUCTION COSTS (REIMBURSABLE)
Graphics, Printing Invoice plus 15%

CONSULTANT FEES (REIMBURSABLE)
The fees charged by all consultants RA uses will be charged at the actual cost plus 15% to cover overhead and administrative expenses.

BILLING AND PAYMENTS
Billing will be made on a monthly basis unless arranged otherwise.

Payments are due and payable on presentation.

CC Agreement 2020-1A

EXHIBIT B

← All documents from this meeting