Cities Index.
Attachment 1 - Calleguas CIP Response 2025

Camarillo City Council
June 25, 2025

Document
Attachment 1 - Calleguas CIP Response 2025
Meeting
June 25, 2025
Body
Camarillo City Council
Original file
242 KB
Text extracted from the city's file for reading and search. Open the original on camarillo.primegov.com. That file is the official record.

RAUL AVILA, PRESIDENT
DIVISION 1

THIBAULT ROBERT, SECRETARY
DIVISION 4

REDDY PAKALA, DIRECTOR
DIVISION 3
SCOTT H. QUADY, VICE PRESIDENT
DIVISION 2

JACQUELYN MCMILLAN, TREASURER
DIVISION 5

KRISTINE MCCAFFREY

GENERAL MANAGER
web site: www.calleguas.com

2100 OLSEN ROAD • THOUSAND OAKS, CALIFORNIA 91360-6800 805/526-9323 • FAX: 805/522-5730

March 31, 2025

David Sanchez, Director
Department of Community Development
City of Camarillo
601 Carmen Drive
Camarillo, CA 93010

Subject: Five Year Capital Improvement Projects

Dear Mr. Sanchez:

The following is provided in response to your letter dated March 10, 2025 requesting information on capital projects. Calleguas has the following projects planned in Camarillo in the next five years.

Project Location and Description Estimated
Cost
Project
Status
Somis Farmworker
Housing SMP
Discharge Station
Metering station for discharge of brine and recycled water from the farmworker housing development adjacent to the North Pleasant Valley Desalter into the Salinity Management Pipeline.
~$300K Design in
progress
City of Camarillo
SMP Discharge
Station
Metering station for discharge of recycled water from the City of Camarillo WWTP into the Calleguas Salinity Management Pipeline. ~$300K Design in
progress
OSR Feeder and
Santa Rosa Hydro
Improvements
Improvements to address surge c oncerns, improve operability and reliability, and avoid failure of aging components. (One project element is located in Camarillo.)
~$5M Design in
progress
Salinity Management
Pipeline, Phase 3
Approximately 5 miles of 24” PVC pipe from the intersection of Upland and Lewis Rds. to Santa Rosa and Hill Canyon Rds.
~$22M Design in
progress
Calleguas-Ventura
Interconnection
Approximately 7 miles of 30” diameter pipeline connecting the City of Ventura and Calleguas water syst ems, connecting to Calleguas’ system near the intersection of Camino Tierra Santa and Via Zamora. ~$21.5M Design in
progress

Please contact me at (805) 579-7156 or [email protected] if you have any questions or need additional information.

Sincerely,

Fernando Baez, P.E.

Manager of Engineering