CAMARILLO TRAIN STATION
UNDERCROSSING PROJECT
Project No. ST-14-05
July 9, 2025
The Camarillo Train Station Undercrossing Project proposes to construct a new pedestrian undercrossing beneath the railroad tracks for improved accessibility.
Ø Coordinated design effort with Ventura County Transportation Commission (VCTC) and Los Angeles - San Diego – San Luis Obispo Rail Corridor Agency (LOSSAN)
Ø Provides more direct route between east and west platforms Ø Improves access and connectivity to Old Town Camarillo Project Description
LOSSAN Grant Funding
Ø TIRCP: $ 3,445,000
Ø Proposition 1B: $ 3,445,000
Ø Additional Prop. 1B: $ 1,300,000
Senate Bill 1 Grant Funding
Ø SB1 SCCP: $ 7,920,000
City Contribution: $ 910,000
Total Funding = $ 17,020,000
Funding
Ø Design is underway and being presented to all stakeholders including Union Pacific Railroad (UPRR) for review
Ø A request for a 12-month funding extension was approved by CTC on May 15, 2025
Ø City staff has coordinated with Sheriff’s Department on security enhancements and their feedback will be incorporated into the final design
Ø The draft maintenance agreement has been received from VCTC and is currently under review
Project Update
N
14’
24’
23’
47’
6’6’
Next Steps
May 26, 2020 &
June 28, 2023
Grant Funding
Awarded
November 8, 2023
City Council Approved
CEQA Statutory Exemption
June 14, 2023 &
December 11, 2024
City Council Approved
Preliminary & Final Design
Agreements
July 9, 2025
City Council Meeting
Present Proposed Design
TODA
Y
June 30, 2026
Deadline to Obligate
Construction Funds
2027 – 2028
Construction
Summer 2026
City Council Meeting
Approve Plans and NIB
Provide input and direction on the proposed undercrossing design.
Recommendation