Lewis Road Water Main
Relocation
November 12, 2025
2 CALTRANS SR-34 PROJECT
Somis
Rice
Ave
Water Main
Relocation
Caltrans Relocation
of City Water Main
• Various locations along Lewis Road
from Barry Street to past Temple Ave
• Designed by Caltrans with concept
developed by City staff
• Work performed by Caltrans
contractors
• Inspection by City staff
• Design cost $59,772, paid in FY26
• Construction estimate of
$670,770 paid after physical work
completed
Lewis Road Water Main Relocation –
Caltrans Utility Agreement No. 2025-186
4 Recommendation:
1. Authorize the City Manager to execute a Utility Agreement No. 2025-186 and any necessary documents and agreement
amendments with Caltrans for the relocation of the City’s water main in the Lewis Road project area.