Camarillo City Council
AGENDA REPORT
Date: February 11, 2026
To: Honorable Mayor and City Councilmembers
From: Greg Ramirez, City Manager
Submitted by: Dave Klotzle, Director of Public Works
Subject: Annual Resurfacing (Project No. ST-5088) – Award Construction Contract
BACKGROUND
The Annual Resurfacing – Project No. ST-5088 (Project) will provide needed street rehabilitation consisting of resurfacing of various streets as shown in the attached Project Location Map (Attachment 1). The Project plans and specifications included a base bid as well as alternate bids to provide additional flexibility at time of award.
DISCUSSION
Construction Bids
Staff prepared the bid documents, including plans and specifications, for the Project (Attachment 2).
Staff issued a Notice Inviting Bids on October 11, 2025, for the Project. On November 20, 2025, the City received three (3) bids for construction as shown in the following table:
Name of Bidder $ Amount of Bid
American Asphalt South,
Inc. Fontana, CA
Base Bid ..................................$ 3,227,726.00 Alternate Bid 1.........................$ 1,801,368.00
Alternate Bid 2............................$ 233,728.00 Alternate Bid 3............................$ 143,275.00 Alternate Bid 4.............................$ 86,675.00 TOTAL.....................................$ 5,492,772.00
Project No. ST-5088 - Award Construction Contract
February 11, 2026
3 0
8 1
Pavement Coatings Co.
Jurupa Valley, CA
Base Bid ..................................$ 4,205,069.50 Alternate Bid 1.........................$ 2,129,141.00
Alternate Bid 2 .............................$303,195.00 Alternate Bid 3............................$ 141,127.50 Alternate Bid 4..............................$ 83,225.00 TOTAL......................................$ 6,861,758.00 VSS International,
Inc. West
Sacramento, CA
Base Bid ..................................$ 5,103,120.00 Alternate Bid 1.........................$ 2,200,000.00
Alternate Bid 2 .............................$270,000.00 Alternate Bid 3............................$ 162,000.00 Alternate Bid 4............................$ 155,000.00 TOTAL ....................................$ 7,890,120.00 The Base Bid and Alternate Bid 1 consists of concrete repairs, pavement repairs, crack seal, slurry seal, Asphalt Rubber Aggregate Membrane (ARAM) cape seal and striping on various streets as identified in the Pavement Management Program (PMP) adopted in 2024. Alternate Bid 2 includes pavement repairs, crack seal, slurry seal resurfacing and pavement markings on Calleguas Creek Bike Path. Alternate Bid 3 includes pavement repairs, slurry seal resurfacing and striping at the City Hall parking lot. Alternate Bid 4 consists of base, asphalt concrete pavement and striping at the Pleasant Valley Historical Society Museum parking lot in coordination with the Museum renovation project and the City’s upcoming water pump station project WT-5081 which will be located adjacent to the parking lot. The City received favorable unit bid prices, therefore staff recommends award of the Base Bid and all four Alternate Bids in accordance with the adopted PMP.
Staff reviewed the low bid submitted by American Asphalt South, Inc. (American Asphalt South) and all associated forms, investigated the contractor, and determined American Asphalt South to be responsive to the bid solicitation. Therefore, staff recommends awarding a construction contract (Attachment 3) to American Asphalt South for the Base Bid in the amount of $3,227,726; Alternate Bid 1 in the amount of $1,801,368; Alternate Bid 2 in the amount of $233,728; Alternate Bid 3 in the amount of $143,275; and Alternate Bid 4 in the amount of $86,675 for a total amount of $5,492,772 and authorizing a construction contingency in the amount of $825,000 (Approximately 15%) for unforeseen additional work if required, for a total contract authorization of $6,317,772. Staff also recommends City Council adopt a resolution approving the plans and specifications for the Project (Attachment 4).
Construction Management, Inspection, and Materials Testing Services Consultant construction management, inspection, and materials testing services are required for the Project. On October 25, 2025, staff advertised a Request for Proposals (RFP) to provide construction management, inspection, and materials testing services for the City’s Annual Pavement Resurfacing and Overlay Projects. Proposals were received from nine (9) firms. A consultant selection team composed of City staff reviewed and Project No. ST-5088 - Award Construction Contract
February 11, 2026
3 0
8 1
ranked all proposals received then interviewed the top three (3) most qualified, highest- ranking consultant firms. Flowers & Associates, Inc. (Flowers) was selected as the most qualified firm to provide the necessary construction management, inspection, and materials testing services for this Project No. ST-5088. Flowers has successfully performed work for the City in the past and has significant construction management, inspection, and materials testing experience working on similar types of capital projects.
Staff negotiated a scope of services and fee with Flowers for the Project and recommends approving a standard professional services agreement with Flowers in an amount not-to- exceed $678,551.15 for construction management, inspection, and materials testing services (Attachment 5) and authorizing a contingency in the amount of $102,000 (approximately 15%) for unforeseen additional services if required, for a total agreement authorization of $780,551.15. Additional services for future Annual Pavement Resurfacing and Overlay Projects will be added via a professional services agreement amendment or new professional services agreement with Flowers based on the future fee schedules provided and will be brought to City Council for approval when awarding construction contracts for future Annual Pavement and Overlay Projects.
Budget Analysis
The Project construction costs are summarized below:
Contractor Contract $ 5,492,772.00
Change Order/Contingency $ 825,000.00
Construction Management (CM) $ 678,551.15
CM Contingency $ 102,000.00
Staff Time $ 125,000.85
Total Construction Expenses $ 7,223,324.00
The Project’s construction expenses will be funded primarily through the Annual Overlay/Resurfacing Projects (Project Nos. ST-5088, ST-5089, ST-5099, and ST-5100), with additional minor funding from the Water Utility Fund, the CSD Utility Fund, and Project No. WT-5081 for their respective associated work. The list of streets proposed by the Project match the adopted PMP and associated funding, and includes funding and streets that were not completed and carried over from the prior year.
FISCAL IMPACT
Approximately $2,921,450 is expected to be spent in FY 2025/26 with the remaining $4,301,874 spent in FY 2026/27. FY 2025/26 funds for the construction contract, professional services agreement, contingencies, and staff time are included in the Project budget. The remaining $4,301,874 will be budgeted for the Project in FY 2026/27.
CITY COUNCIL STRATEGIC PLAN FY 2025/26
Project No. ST-5088 - Award Construction Contract
February 11, 2026
3 0
8 1
This item supports the City Council’s Strategic Plan Goal and Objective 6.3 - Natural Resource Infrastructure Management – Develop major project work plans to prioritize, plan, fund, and execute infrastructure projects
CEQA DETERMINATIONS
The Project is not subject to CEQA review pursuant to CEQA Guideline Section 15301 Class 1, which exempts from CEQA review projects that involve existing facilities. This agenda item meets the criteria for this exemption because the project involves repair of existing streets, and it does not expand the perimeter of the existing facility.
RECOMMENDATION
1. Find Project No. ST-5088 exempt from review under the California Environmental Quality Act (CEQA) pursuant to Article 19 Categorical Exemptions Section 15301 Class 1; and
2. Adopt a Resolution approving Annual Resurfacing – Project No. ST-5088; approving the Project plans and specifications; and proceeding with construction of the Project; and
3. Authorize the City Manager to execute Public Works Contract No. 2026-5 with American Asphalt South, Inc. in an amount not-to-exceed $5,492,772, and authorize a contingency in the amount of $825,000, for a total contract authorization of $6,317,772; and
4. Authorize the City Manager to execute future contract change orders to the contract for unforeseen additional work up to the authorized contingency amount; and
5. Authorize the City Manager to execute Professional Services Agreement No. 2026-6 with Flowers & Associates, Inc. in an amount not-to-exceed $678,551.15 for construction management, inspection, and materials testing services, and authorize a contingency in the amount of $102,000, for a total agreement authorization of $780,551.15; and
6. Authorize the City Manager to execute future amendments to the agreement with Flowers & Associates, Inc. for unforeseen additional services up to the authorized contingency amount.
ATTACHMENTS
1. Location Map
2. Project Plans and Specifications
3. CC Agreement No. 2026-5
4. Resolution
5. CC Agreement No. 2026-6
REFERENCE MATERIALS – AVAILABLE FOR REVIEW AT CITY HALL Project No. ST-5088 - Award Construction Contract