Camarillo City Council
AGENDA REPORT
Date: May 13, 2026
To: Honorable Mayor and City Councilmembers
From: Greg Ramirez, City Manager
Submitted by: Dave Klotzle, Director of Public Works
Subject: Stormwater Trash Compliance (Project No. SD-5032-1) – Adopt a Resolution Exonerating Warranty Securities
BACKGROUND
On April 9, 2025, the City Council accepted the public improvements and warranty securities for Stormwater Trash Compliance - Project No. SD-5032-1 (Project). Work performed by the contractor, Downstream Services, Inc., consisted of the manufacturing and installation of 267 full capture trash devices within existing storm drain catch basins and standpipes throughout the City of Camarillo. The devices are certified by the State Water Board and accepted as part of the City of Camarillo’s Full Capture Systems (FCS).
The full capture trash devices were needed to meet municipal and statewide stormwater permit requirements.
On June 12, 2024, the City Council adopted a resolution finding the Project exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guideline Section 15303 Class 3.
DISCUSSION
Western Surety Company Performance/Payment Bonds No. 30221672 in the amount of $838,897 have been held for the required maintenance period and may be exonerated.
FISCAL IMPACT
There is no budget impact as a result of this action.
RECOMMENDATION
Adopt a Resolution exonerating warranty securities for Stormwater Trash Compliance - Project No. SD-5032-1 with Downstream Services, Inc.