Arneill Road Housing Project No. CUP-400 – Award
Construction Contract
June 10, 2026
Budget Analysis
Construction Funding Amount
ERF Grant Funding $5,350,088.32
ERF Grant Interest through 3/31/2026 $267,932.91
Projected ERF Grant Interest through 6/30/2026 $75,000.00 Available Grant Funding Subtotal $5,693,021.23
Continuum of Care Reserve Funds for Base Construction Contract $248,766.44 Continuum of Care Reserve Funds for 15% Construction Contingency $891,268.15 Reserve Fund Subtotal $1,140,034.59
General Contractor Funding Total $6,833,055.82
S.L. Leonard Contract (grant funds already committed) $1,093,559.70 Total $7,926,615.52
Recommended Action
3 1. Find that Negative Declaration 2023-1 for CUP-
400 was previously approved by the City Council
and no further CEQA review is required pursuant
to CEQA Guideline 15162.
2. Reject the bid protest from Riviera Construction
Group LLC and find SBS as the lowest responsive
bidder;
3. Authorize other actions as stated in the Agenda
Report.