2022-07-19; City Council; ; Approval of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the Street Lighting Replacement Program Phase II Project

Carlsbad City Council
July 19, 2022

Document
2022-07-19; City Council; ; Approval of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the Street Lighting Replacement Program Phase II Project
Meeting
July 19, 2022
Body
Carlsbad City Council
Pages
9
Original file
697 KB
Text extracted from the city's file for reading and search. Open the original on records.carlsbadca.gov. That file is the official record.

For door hangers, the notification shall be pre -cut in a manner that enables it to be affixed to a doorknob without adhesives. It shall be a minimum size of 3-1/2 inches by 8-1/2 inches and shall be brightly colored with contrasting printing. The material shall be equivalent in strength and du- rability to 65 lb. card stock. The printing on the notice shall be no smaller than 12 point. The precut notices shall be as shown on the example provided in Appendix “A”, with the day of the week circled and appropriate information specific to the work inserted at the locations indicated in the italicized font.

The preparation, materials, printing and distribution of the notifications shall be included in the contract price bid for Traffic Control and the Contractor will not be entitled to any additional com- pensation for printing and distributing these notices.

302-5 ASPHALT CONCRETE PAVEMENT

Add the following:
302-5.2 Pavement Transitions. The Contractor shall ramp the approaches and termini to all structures and vertical joints in the cold- milled area which are transverse to through traffic with temporary asphalt concrete pavement as specified in section 306- 1.5.1. Ramps shall be con- structed the same day as cold milling and removed the same day as permanent paving. Ramp dimensions and compaction shall be as approved by the Engineer.

302-5.5 Distribution and Spreading. Modify as follows: After second sentence of sixth para- graph, add: The Contractor shall provide the spreading and finishing machine used to construct the asphalt concrete surface course with an automatic screed control for surface course paving.

The automatic screed control shall be 9 m (30’) minimum length. The paving machine shall be operated by an operator and two full -time screed men during all paving. The Contractor shall provide an on-site backup paving during all paving operations.

Revised 6/15/17 Contract No. 6062 Page 175 of 210
Delete the second sentence of paragraph 7 and the subsequent subsections A. thru E. which reference windrow operations. Add the following sentence in place of the deleted sentence and subsequent subsections: The use of windrow operations shall not be allowed.

302-5.6.1 General. Modify as follows: Second paragraph, Part (2), add: Pinched joint rolling pro- cedures shall be required, and vibratory rollers shall be limited to breakdown, unless otherwise directed by the Engineer.

Modify as follows: After last paragraph, add: Unless directed otherwise by the Engineer, the initial breakdown rolling shall be followed by a pneumatic-tired roller as described in this section.

302-5.8 Manholes (and other structures). Delete the first paragraph and replace with the fol- lowing:

When placing the overlay the Contractor shall pave over appurtenances in the roadway which includes sanitary and storm access covers, water valve boxes, air vents, sewer dead end boxes and survey monument boxes. Each appurtenance shall be treated or covered to prevent adhesion of the overlay. Each appurtenance shall be located immediately after the overlay is placed and shall be thoroughly cleaned of any and all construction debris which may have entered due to the Contractor’s operation. The contractor shall adjust all CMWD water valve boxes per CMWD Standard Drawing No. W11 or CMWD Standard Drawing No. W13. All City of Carlsbad sanitary sewer access covers shall be adjusted per CMWD Drawing No. S1. All storm sewer access co- vers shall be adjusted per SDRSD D -10. Riser rings or extensions shall not be used for the ad- justment of these appurtenances.

Raising and adjusting to grade all appurtenances in the roadway shall be paid for at the contract unit price per each as shown in the Bid. Such price shall constitute full compensation for all labor, materials, and equipment necessary for completing the work as described in these specifications and plans.

302-5.9 Measurement and Payment. Add the following: Payment for asphalt concrete shall be at the unit price bid per ton. No additional payment shall be made for any tack coat or sand blotter.

Add the following section:
302-11 ASPHALT PAVEMENT REPAIRS AND REMEDIATION

Add the following section.
302-11.1 General. Asphalt pavement Repairs and Remediation shall consist of the repair and restoration of existing asphalt pavement. Repair of asphalt pavement shall consist of the saw cutting, removal and disposal of existing asphalt pavement in conformance with section 300-1.3, compaction of existing subgrade in conformance with section 301- 1, grading and compaction of base material in conformance with section 301- 2, application of grade SS-1h emulsified asphalt and the placement of asphalt concrete base and wearing courses as specified herein.

Add the following section.
302-11.2 Full Depth Asphalt Concrete Patch. Full depth asphalt concrete patch shall consist of removing asphalt concrete and/or aggregate base/subgrade to 300 mm (1’) below existing asphalt surface and placing replacing the material so removed with asphalt concrete. The area shown on the plans or set forth in the bid item are for estimating purposes only, final quantity will be as measured in the field. The Engineer will designate and mark the final limits of the asphalt patch area by outlining the area to be patched. The Contractor shall cut such areas to straight lines in square or rectangular areas as marked. The area so cut shall have two of the sides at right angles

Revised 6/15/17 Contract No. 6062 Page 176 of 210
to the direction of traffic. The excavated faces of the base/subgrade shall be straight and vertical.

The Contractor shall compact the upper 300mm (1’) of subgrade to 95% relative compaction. A tack coat of SS-1h emulsified asphalt shall be applied uniformly to all asphalt to asphalt contact surfaces at a rate of 0.25 L/m2 to 0.45 L/m2 (0.05 to 0.10gallons per square yard) in accordance with subsection 302-5.4, SSPWC. The Contractor shall fill and compact areas designated to be removed with 300 mm ( 1.0’) full depth asphalt concrete. Asphalt concrete for full depth asphalt concrete patch shall be B-AR-4000. The asphalt concrete so constructed shall have a finish sur- face and density conforming to subsection 302-5.6.2 SSPWC.

Add the following section.
302-11.3 Crack Sealing The Contractor shall wash, blow out and thoroughly dry all cracks des- ignated to be sealed before installing hot poured rubber-asphalt joint sealant material. The sealant shall conform to the requirements of ASTM D1190. The Contractor shall dispose debris from crack cleaning outside the public way in accordance with Section 7 -8.1, “Cleanup and Dust Control .” The hot-melt rubberized asphalt shall be melted in a jack eted, double boiler type melting unit.

Temperature of the heat transfer medium shall not exceed 245°C (475°F). Application of the hot- melt sealant shall be made with a pressure feed applicator or pour pot. Sealant shall be applied when the pavement surface temperature is greater than 4°C (40°F). Containers of hot-melt seal- ant shall be delivered to the job -site in unopened containers that are clearly marked with data showing the manufacturer’s name, the product designation and the manufacturer’s batch number and lot numbers. The level of the sealant shall be flush with the surface of the existing pavement.

All excess sealant shall be removed from the crack with a minimum overlap onto adjacent pave- ment.

Add the following section:
302-11.4. Measurement and Payment. Quantities of full depth asphalt concrete patch and crack sealing set forth in the bid item are for estimating purposes only, final quantity will be as desig- nated and measured in the field. The Engineer will designate and mark the limits of the Full depth asphalt concrete patch and crack sealant application areas. Payment for resurfacing shall include post emergent herbicide treatment. Full compensation for conforming to the requirements of con- structing full depth asphalt concrete patch shall include but not be limited to: furnishing all labor, tools, equipment, and materials necessary for doing the work including, saw cutting and removing and disposing 300 mm (1’) thick section of existing asphalt concrete, aggregate base/subbase and basement soil as designated by the engineer, placement of asphalt concrete, compaction of subbase and asphalt concrete, placement of SS-1h asphalt emulsion and all other work incidental to full depth asphalt concrete patch shall be considered as included in the contract unit price bid for full depth asphalt concrete patch and no additional compensation will be allowed therefore.

Full compensation for conforming to the requirements of crack sealing shall include but not be limited to, furnishing all labor, materials, tools, equipment, and incidentals necessary to do the work. Crack cleaning, roadway clean up, application of sealant, removal of excess sealant and all other work incidental to crack sealing shall be considered as included in the contract unit price bid and no additional compensation will be allowed therefor.

SECTION 303 CONCRETE AND MASONRY CONSTRUCTION

303-1 CONCRETE STRUCTURES

303-1.6.2 Falsework Design. Add the following: The Contractor shall provide all temporary brac- ing necessary to withstand all imposed loads during erection, construction, and removal of any

Revised 6/15/17 Contract No. 6062 Page 177 of 210
falsework. The Contractor shall provide falsework drawings and calculations prepared by a reg- istered professional engineer, civil or structural, that show provisions for resolution of all loads that may be imposed upon the falsework. Such plans and calculations shall include:

1. Resolution of all live, dead, wind, construction and impact loads that may be imposed on the falsework.

2. Temporary bracing or methods to be used during each phase of erection and removal of the falsework.

3. Concrete placement sequence.

4. Erection and removal sequence.

5. Deflection values for the falsework that include recommended methods to compensate for falsework deflections, vertical alignment, and anticipated falsework deflection.

Add the following section:
303-1.9.5 Surface Finish for Concrete Spillway. The Contractor shall provide a surface finish for concrete spillway to prevent the use of rollerblades, skateboards, and other rolling devices.

Surface finish shall be a rough rake finish approved by the Engineer.

303-2 AIR-PLACED CONCRETE

303-2.1.1 General. add the following: Modify Regional Standard Drawing D-75 as follows: replace stucco netting with 150mm x 150mm (6” x 6”) by No. 10 by No. 10 welded wire mesh.

Add the following section:

303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY

INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS

303-5.5.2 Curb. Add the following: The Contractor shall stamp the curb face with 75 mm (3”) high block letters directly above the point that it is crossed by underground facilities with the marking specified in Table 303-5.5.2(A).

TABLE 303-5.5.2(A)
Curb Face Markings
Type of underground facilities Marking
Water Service Lateral W
Sewer Service Lateral S
Irrigation Water Lateral or Sleeve RW

303-5.9 Measurement and Payment. Add the following: Curb and gutter, and curb, shall be con- sidered as continuing across driveways and access ramps when constructed adjacent thereto.

Neither curb and gutter nor curb will be paid for across the length of local depressions, except that which occurs in gutter transitions at each side of an inlet.

303-6 STAMPED CONCRETE

303-6.1 General. Add the following: Concrete shall be 560- C-3250 with 6”x6” – 10 guage wire mesh throughout.

Revised 6/15/17 Contract No. 6062 Page 178 of 210
Add the following:
303-6.5 XXXX Medians- Use color application method “B” (integral color). Color shall be per Section 201-1.2.4(a). The pattern shall be xxx pattern or approved equal. The pattern shall match the existing median condition adjacent to the prposed construction along xxxx Street.

Add the following:
303-6.6 Measurement and Payment. Payment for colored, stamped concrete paving shall be paid under the contract unit price bid per square foot for median concrete paving. Said payment shall include compensation for all excavation, grading, backfill, permeable material, f orming, mesh, reinforcing steel, concrete, integral color, texture sealers, and other material necessary to construct the specific paving.

SECTION 304 - METAL FABRICATION AND CONSTRUCTION

304-3 CHAIN LINK FENCE

304-3.2 Fence Construction.

304-3.3 Installation of Gates.

SECTION 306 - UNDERGROUND CONDUIT CONSTRUCTION

306-1 OPEN TRENCH OPERATIONS

Add the following section:
306-1.1.7 Steel Plate Bridging - With a Non-Skid Surface. This section covers the use of steel plate bridging. The Contractor shall not employ the use or use steel plate bridging or trench plate that does not meet the requirements of this section both in application and circumstance of use.

Add the following section:
306-1.1.7.1 Requirements for Use. Alternate construction methods that avoid the use of steel plate bridging shall be used by the Contractor unless otherwise approved by the Engineer.

It is recognized that to accommodate excavation work, steel plate bridging may be necessary. All conditions for use of steel plate bridging set forth in the following requirements must be fulfilled as conditions of approval of the use of steel plate bridging. Consideration of steel plate bridging in the review process will take into account the following factors:

1. Traffic volume and composition.

2. Duration of use of the steel plate bridging.

3. Size of the proposed excavation.

4. Weather conditions.

The following formula shall be used to score the permitted use of steel plate bridging:

PS = [ ADT + EWL + DAYS + 10 X WEEKEND + 5 X NIGHTS + 20 X WEATHER + SPEED (kmh) + SLOPE X 100] X LANES 1000 8

PS = [ ADT + EWL + DAYS + 10 X WEEKEND + 5 X NIGHTS + 20 X WEATHER + SPEED (mph) + SLOPE X 100] X LANES 1000 5

Revised 6/15/17 Contract No. 6062 Page 179 of 210
where:

PS = plate score.

ADT = average daily traffic as defined in the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement.

EWL = equivalent wheel loads as defined in the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement.

DAYS = total number of 24 hour periods during which the plates will be utilized at the site being considered.

WEEKEND = total number of Saturdays, Sundays and holidays that the plates will be utilized at the site being considered.

NIGHTS = total number of overnight periods that the plates will be in place, exclusive of Saturday, Sunday and holiday nights.

WEATHER = total number of 24-hour periods that the plates will be utilized at the site being considered when the possibility of rain exceeds 40 percent.

SPEED = the design speed in kilometers per hour or miles per hour, as applicable in the formulae above, of the street where the plates are to be installed. This number shall not be reduced for construction zone speed reductions.

SLOPE = the quotient of the vertical differential divided by the horizontal distance. The vertical and horizontal dimensions shall be measured at the locations spanning a distance of 15 m (50’) up and downstream of the position of the proposed steel plate bridging.

LANES = the number of lanes where plates will be used.

When the computed value of the plate score exceeds 50, steel plate b ridging shall not be used unless, and at the sole discretion of the Engineer, the Engineer determines that no alternative method of construction is possible in lieu of using steel plate bridging or that other overriding considerations make the use of steel plate bridging acceptable. Alternatives considered to bridg- ing shall include, but not be limited to, detouring traffic, construction detour routes, tunneling, boring and other methods of trenchless construction. Unless specifically noted in the provisions of the Engineer's approval, the use of steel plate bridging at each location so approved shall not exceed four (4) consecutive working days in any given week.

Add the following section:
306-1.1.7.2 Additional Requirements. In all cases when the depth of the trench exceeds the width of the steel plate bridging resting on each side of the pavement adjacent to the trench, safety regulations require or the Engineer determines that shoring is necessary to protect the health or safety of workers or the public the Contractor shall install shoring conforming to Section 7-10.4.1 of the Standard Specifications. The trench shoring shall be designed and installed to support the steel plate bridging and traffic loads. All approvals for design, substitution of materials or methods shall be submitted by the Contractor in accordance with all provisions of section 2 -

5.3 Shop Drawings and Submittals. The Contractor shall backfill and resurface excavations in accordance with section 306-1.5.

Add the following section:
306-1.1.7.3 Installation. When backfilling operations of an excavation in the traveled way, whether transverse or longitudinal cannot be properly completed within a workday, steel plate bridging with a non- skid surface and shoring may be required to preserve unobstructed traffic flow. In such cases, the following conditions shall apply:

Revised 6/15/17 Contract No. 6062 Page 180 of 210

1. Steel plate bridging when the plate score exceeds 50 is not allowed except when, at the sole discretion of the Engineer, it is approved as specified hereinbefore.

2. Steel plates used for bridging must extend a minimum of 610 mm (2’) beyond the edges of the trench.

3. Steel plate bridging shall be installed to operate with minimum noise.

When the use of steel plate bridging and shoring is approved by the Engineer, the Contractor shall install using either Method (1) or (2) depending on the design speed of the portion of street where the steel plate bridging is proposed for use.

Method 1 [For speeds more than 70 Km/hr (45 MPH)]: The pavement shall be cold planed to a depth equal to the thickness of the plate and to a width and length equal to the dimensions of the plate. The cold milling shall produce a flat surface that the plate shall rest on with no horizontal or vertical movement. Horizontal gaps between the unmilled pavement and the plate shall not ex- ceed 25 mm (1”) and shall be filled with elastomeric sealant material which may, at the contrac- tor’s option, be mixed with no more that 50%, by volume, of Type I aggre gate conforming to the requirements of tables 203-5.2(B) and 203-5.3(A).

Method 2 [For speeds 70 Km/hr (45 MPH) or less]: Approach plate(s) and ending plate (if longi- tudinal placement) shall be attached to the roadway and shall be secured against displacement by using two adjustable cleats that are no less than 50 mm (2”) shorter than the width of the trench bolted to the underside of each plate and located within 150 mm (6”) of the beginning and end of the trench for plates at the beginning and end of the trench, a minimum of two 300 mm long by 19 mm diameter (12” x ¾”) steel bolts placed through the plate and driven into holes drilled 300 mm (12”) into the pavement section, or other devices approved by the Engineer. Subsequent plates shall be butted to each other. Fine graded asphalt concrete shall be compacted to form ramps, maximum slope 8.5% with a minimum 300 mm (12”) taper to cover all edges of the steel plates. When steel plates are removed, the dowel holes in the pavement section shall be com- pletely filled with elastomeric sealant material. At the Contractor’s option, the methods required for Method 1 may be used. If the Contractor so elects, all requirements of Method 1 shall be used.

The Contractor shall maintain the steel plates, shoring, and asphalt concrete ramps and maintain and restore the street surface during and after their use.

Add the following section:
306-1.1.7.4 Materials. The minimal thickness of steel plate bridging shall be as shown in Table 306-1.1.7.4(A).

TABLE 306-1.1.7.4(A)

REQUIRED PLATE THICKNESS FOR A GIVEN TRENCH WIDTH
Maximum Trench Width (1) Minimum Plate Thickness

0.3 m (10”) 13 mm (1/2”)

0.6 m (23”) 19 mm (3/4”)

0.8 m (31”) 22 mm (7/8”)

1.0 m (41”) 25 mm (1”)

1.6 m (63”) 32 mm (1 ¼”)
(1) For spans greater than 1.6 m (5’), a structural design shall be prepared by a registered civil engineer and submit- ted to the Engineer for review and approval in accordance with section 2-5.3.

Steel plate bridging shall be steel plate designed to suppo rt the HS20 -44 truck loading per CALTRANS Bridge Design Specifications Manual. The Contractor shall maintain a non-skid sur- face on the steel plate with no less than a coefficient of friction of 0.35 as determined by California

Revised 6/15/17 Contract No. 6062 Page 181 of 210
Test Method 342. If a different test method is used, the Contractor may utilize standard test plates with known coefficients of friction available from the CALTRANS District 11 Materials Engineer to correlate skid resistance results to California Test Method 342. In addition to all ot her required construction signing, the Contractor shall install Rough Road (W33) sign with black lettering on an orange background in advance of steel plate bridging.

Add the following section:
306-1.1.7.5 Measurement and Payment. Steel plate bridge materials including, but not limited to: steel plates, anchoring devices, cold milling, elastomeric sealant material, asphalt ramping and padding, signage, placing, installation, removal, relocation, preparation and processing of shop drawings and submittals to support the use of steel plate bridging and all other materials, labor, supervision, overhead of any type or description will be paid for as an incidental to the work that the bridging is instal led to facilitate. No separate payment for steel plate bridging will be made.

No extension to contract time will be allowed for, or because of, the use of steel plate bridging.

306-1.2.1 Bedding. All installation of, and bedding for recycled water, or pot able water mains shall conform to Carlsbad Municipal Water District Rules and Regulations for the Construction of (Potable or Reclaimed) Water Mains, latest edition.

306.1.2.2 Pipe Laying. add the following: The Contractor shall place electrical conduit per SDG&E plans, Construction Order No. xxx, Project No. xxx.

306-1.2.4 Field Jointing of Reinforced Concrete Pipe. add the following: The Contractor shall provide Gasket -type joints for reinforced concrete pipe (watertight joints) where indicated on plans.

306-1.3.1 General. Add the following: The Contractor shall install detectable underground utility marking tape 230 mm x75 mm (9” x 3”) above each or, in the case of bundled underground conduit of the same type, the upper underground conduit being installed by the open trench method. The type and color of detectable underground utility marking tape shall conform to the requirements of section 207-25 et seq.

306-1.3.4 Compaction Requirements. delete Section 306-1.3.4 and replace with the following:

The Contractor shall densify trench backfill to a minimum of 90 percent relative compaction except that in the top 300 mm (12”) of the street right-of-way, compaction shall be 95 percent.

306-1.5 Trench Resurfacing.

306-1.5.1 Temporary Resurfacing. Delete the fourth and fifth paragraphs and substitute the fol- lowing: Temporary bituminous resurfacing materials which are placed by the Contractor are for its convenience and shall be at no cost to the Agency. Temporary bituminous resurfacing materi- als shall be used in lieu of permanent resurfacing only when approved by the Engineer. When temporary bituminous resurfacing materials are used in lieu of permanent resurfacing it shall be removed and replaced with permanent resurfacing within 7 days of placement. No additional pay- ment will be made for temporary bituminous resurfacing materials. The price bid for the associated conduit or structure shall include full compensation for furnishing, placing, maintaining, removing, and disposing of such temporary resurfacing materials.

306-1.5.2 Permanent Resurfacing. Add the following: Except as provided in section 306-1.5.1, “Temporary Resurfacing,” the Contractor shall perform permanent trench resurfacing within 24 hours after the completion of backfill and densification of backfill and aggregate base materials.

Revised 6/15/17 Contract No. 6062 Page 182 of 210

306-1.6 Basis of Payment for Open Trench Installation. add the following: Payment for utilities undergrounding which includes the utility trench for CATV and SDG&E and con duit for SDG&E’s electric conversion shall be made on the basis of contract lump sum price for utilities undergrounding and no other payments will be made. Cox Cable will supply and deliver conduits and fittings to be installed by the Contractor. Cox Cable will install enclosures. The Contractor will furnish and install 6.4 mm (¼”) nylon pull ropes in all conduit.

306-5 ABANDONMENT OF CONDUITS AND STRUCTURES. Add the following: Unless other- wise noted on plans, the Contractor shall remove all existing abandoned pipelines and conduits of any type, or use, and pipelines and conduits of any type, or use, that are abandoned during the course of the work and shall r eplace said pipelines and conduits with properly compacted soils.

Payment for removal and disposal of abandoned utilities shall be included in the lump-sum bid for Clearing and Grubbing, and no additional payment will be made.

SECTION 307 - STREET LIGHTING AND TRAFFIC SIGNALS

307 STREET LIGHTING AND TRAFFIC SIGNALS. Modify as follows: Section 86, “Signals, Lighting and Electrical Systems”, of the Caltrans Standard Specifications replaces Section 209, “Electrical Components”, and Section 307, “Street Lighting and Traffic Signals”, of the SSPWC, in all matters pertaining to the specifications for measurement, payment, warranty, materials and methods of construction of street lighting and traffic signals.

SECTION 308 LANDSCAPE AND IRRIGATION INSTALLATION

308-2 EARTHWORK AND TOPSOIL PLACEMENT

308-2.3.2 Fertilization and Conditioning Procedures. Add the following: The Contractor shall cultivate the surface of all areas to be planted or hydroseeded by discing, ripping or scarifying the finish grade. After cultivation the Contractor shall clear the planting areas of stones to the depth of cultivation and shall be rake the planting areas to a smooth friable and plantable surface. The Contractor shall cultivate all planting areas, except slopes steeper than 3-1/2:1 (horizontal to ver- tical), to a depth of 300 mm (12”). The planting areas that are slopes steeper than 3- 1/2:1, shall be cultivated to a depth of 150 mm (6”). After cultivation, the soil amendments shown in table 308-2.3.2(A) shall be thoroughly blended 150 mm (6”) deep in all planting areas. Except for plant- ing pits the cultivation depths are designated as the root area. Backfill for planting pits shall con- form to the requirements of section 308-4.5. After surface preparation and application of the soil amendments shown in Table 308-2.3.2(A) the Contractor shall obtain a minimum of one test for each soil property listed in Tables 308- 2.3.2(B) and 308-2.3.2(C) from each median planter, at least one test per 150 m (500’) from each parkway and for each hectare (2.5 acres) of hy- droseeded area and shall submit the results of said tests to the Engineer. The Contractor shall then adjust the soil properties to the acceptable ranges of soil properties shown in Tables 308-

2.3.2(B) and 308-2.3.2(C) using such materials and methods as may be necessary. Organic soil amendment materials shall not be included in the samples used to determine compliance to the soil particle gradation requirements of Table 308-2.3.2(C). If adjustments are necessary the soil shall be tested by the Contractor after such adjustments for each soil property listed in Table 308-

2.3.2(B) and 308-2.3.2(C) to determine that the adjustments to the soil made by the Contractor result in soil properties within the acceptable range. The Contractor shall adjust the soil properties

Revised 6/15/17 Contract No. 6062 Page 183 of 210
and show acceptable ranges prior to any planting or application of hydroseed slurry. Prior to the start of any planting or application of hydroseed slurry the surface and root area shall be evenly and thoroughly moistened to no less than 75 percent of field capacity. The Contractor shall certify, in writing, that the ground surface has been prepared in accordance with this section and shall request inspection by the Engineer prior to any planting or seeding. The Contractor shall obtain the Engineer’s approval before any planting or hydroseeding.

TABLE 308-2.3.2(A)

SOIL AMENDMENTS
Soil Amendment Metric Application Rate Approx. U.S. Application Rate Agricultural Gypsum 500 g per square meter 100 lbs. per 1,000 square feet Iron Sulfate 50 g per square meter 10 lbs. per 1,000 square feet Calcium Carbonate
Lime
500 g per square meter 100 lbs. per 1,000 square feet
Organic Soil Amend-
ment

0.04115 cubic meters per square
meter (average depth 41 mm)
5 cubic yards per 1,000 square
feet (average depth 1 5/8”)

TABLE 308-2.3.2(B)

SOIL PROPERTIES
Soil Property Acceptable Range Test Method Repeatability Range of Test
pH 6.5 to 7.3 Saturation Paste pH ± 0.1 pH
Dissolved Salts
(Ece)
< 4.0 dS m-1 Saturation Paste Sol-
uble Salts
± 7%
Liquid Limit N/A to 30 ASTM D 423 ± 2
Plasticity Index NP to 10 ASTM D 424 ± 2

TABLE 308-2.3.2(C)

SOIL PARTICLE GRADATION
Sieve Size Percent Passing
19 mm (3/4”) 100

9.5 mm (3/8”) 95 - 100

4.75 mm (No. 4) 60 - 85

1.89 mm (No. 10) 40 - 75
475 µm (No. 40) 35 - 70
75 µm (No. 200) 30 - 70

For areas to receive planting of all types, excluding only hydroseeding, the Contractor shall amend the prepared soil by blending 200 g of 7-7-7 fertilizer per square meter (40 lbs. per 1,000 square feet) into the top 150 mm (6”) of soil after the completion of adjustment of soil properties and acceptance of the planting area by the Engineer. The Contractor shall apply post -plant 12-4-6 fertilizer at the rate of 20 pounds per 1,000 square feet, 30 days after planting and every 30 days through the end of the maintenance period.

308-2.4 Finish Grading . Add following: The Contractor shall prepare the finish grade in hy- droseed slope areas with a moderately rough texture to provide a suitable surface for adherence of the hydroseed mix.

Revised 6/15/17 Contract No. 6062 Page 184 of 210
308-4 PLANTING

308-4.1 General. Add the following: The Contractor shall perform actual planting during those periods when weather and soil conditions are suitable and in accordance wit h locally accepted horticultural practice and as approved by the Engineer. No planting shall be done in any area until it has been satisfactorily prepared in accordance with these specifications. Soil moisture level prior to planting shall be no less than 75 percent of field capacity. The Contractor shall obtain the Engineer’s approval of planting pits before planting operations begin. For pit planted vegetation when the soil moisture level is found to be insufficient for planting, the Contractor shall fill the planting pits with water and allow them to drain before starting planting operations. No more plants shall be distributed in the planting area on any day than can be planted and watered on that day.

The Contractor shall plant and water all plants as herein specified immediately after removal from their containers. Containers shall not be cut prior to placing the plants in the planting area. It shall be the responsibility of the Contractor to provide continuous horticultural services and temporary and/or permanent irrigation to all planted and hydroseeded areas so that the planted and hy- droseeded vegetation is 100 percent healthy and thriving prior to, and throughout the, landscape maintenance period.

308-4.2 Protection and Storage. Add the following: The Contractor shall submit a sheltered and secure location for on-site plant storage area for the Engineer’s approval prior to the delivery of any plant materials. Any plant determined by the Engineer to be wilted, broken, or otherwise damaged shall be rejected at any time during the project, whether in the ground or not. All plants shall be handled by their containers. Any plant that has been handled by its trunk or stem shall be rejected. All rejected plants shall be removed from the site immediately.

308-4.3 Layout and Plant Location . Modify as follows: Planting areas shall be staked by the Contractor and the Contractor shall obtain the Engineer’s approval of the planting layout before planting operations begin.

308-4.5 Tree and Shrub Planting. Add the following: The Contractor shall amend the backfill for planting holes to a thoroughly blended mixture of clean loamy soil meeting the requirements of Tables 308-2.3.2(B) and 308-2.3.2(C) and then blend the amendments listed in Table 308-4.5(A) into the backfill for planting holes.

TABLE 308-4.5(A)

BACKFILL AND AMENDMENTS FOR TREE AND SHRUB PLANTING
Soil Amendment Metric Application Rate Approx. U.S. Application Rate
Agricultural Gypsum 18 kg per cubic meter 30 lbs. per cubic yard Iron Sulfate 600 g per cubic meter 1 lb. per cubic yard Calcium Carbonate Lime 6 kg per cubic meter 10 lbs. per cubic yard Organic Soil Amendment 0.67 cubic meters per cubic meter 2/3 cubic yards per cubic yard Planting Tablets 1 1 per 100 mm dia. pot container 1 per 4” dia. pot container Planting Tablets 1 2 per 19 liter container 2 per 5 gal. container Planting Tablets 1 1 per each 50 mm width of each
box-size container
1 per each 2” width of each
box-size container

1. Planting tablet requirements are not cumulative and apply to the size container indicated

Pruning shall be limited to the minimum necessary to remove injured twigs and branches, and to compensate for loss of roots during transplanting, but never to exceed one- tenth the branching

Revised 6/15/17 Contract No. 6062 Page 185 of 210
structure. Pruning may be done only with the approval of, and in the presence of, the Engineer.

Cuts over 19 mm (¾“) shall be painted with an approved tree wound paint.

Add the following section:
308-4.5.1 Root Barriers. Root barriers shall conform to section 212-1.8, Root Barriers. The Con- tractor shall install root barriers continuously at the edges of all median planter areas. The top of the root barrier shall be 25 mm (1”) below the finish grade of the planted area. The bottom of the root barrier shall be installed 520 mm (20
1/2“) below the finish grade of the planted area. Install as indicated on the plans, eliminating any breaks in the barrier by providing at least 150 mm (6”) of overlap at splices or damaged areas. Splices and repair patches shall be stitched to the root barrier material by a running stitch of no less than 6 6 1 stitches per 25 mm (1”).

308-4.6 Plant Staking and Guying. Add the following: The Contractor shall install all boxed trees per drawings L-1 and L-2 of the San Diego Regional Standard Drawings unless details shown on the project plans differ therefrom.

308-4.8.2(b) Method B. Add the following: The Contractor shall prepare hydroseeding slurry on the job site. Slurry additives shall arr ive at the site in bags sealed and properly identified by the manufacturer. All specified additives and water shall be added on the job site at the rates specified and shall be thoroughly mixed at the job site. The Contractor shall add seed to the slurry after the fiber mulch has been thoroughly incorporated. The Contractor shall spray all areas with a uniform, visible coat using the green color of the mulch as a guide. The Contractor shall apply the slurry in a sweeping motion, in an arched stream so as to fall like rain allowing the mulch fibers to built on each other until a good coat is achieved and the material is spread, evenly, at the required rate per area. The Contractor shall use care not to drag spray hoses over container planted material and shall attempt to spray from the edges of the planting areas wherever possible. Any slurry mixture which has not been applied to the planting areas within four (4) hours after mixing is be rejected and removed from the project at the Contractor's expense. Any s lurry spilled into areas outside the limits of work shall be cleaned up at the Contractor's expense to the satisfaction of the Engineer. The Contractor shall assure that the site is properly prepared. The Contractor shall repair all tire ruts created by the equipment. Areas needing grading repair prior to hydroseeding shall be blended and floated to match surrounding grades. Areas having less than 80% plant coverage within thirty (30) days after the initial application shall be reseeded every twenty (20) days until 80% of the ground surface is evenly covered by hydroseeded or subsequently reseeded growth.

Add the following section:
308-4.8.3.1 Weed Eradication. The Contractor shall water all irrigated areas to be hydroseeded for three (3) weeks prior to hydroseeding to allow for germination of the weed seeds. The Con- tractor shall spray all weeds with a post emergent herbicide immediately after the completion of the three week irrigation period. After two (2) weeks, the Contractor shall again eradicate the weeds and complete the preparation of the soil prior to the application of the hydroseed mixes.

Add the following section:
308-4.10 Erosion Control Matting Installation

Add the following section,
308-4.10.1 General. Before installation of erosion control matting the Contractor shall complete all soil preparation, fine grading, and hydroseeding of the areas to receive erosion control matting.

Revised 6/15/17 Contract No. 6062 Page 186 of 210
Add the following section:
308-4.10.2 Coordination with Hydroseeding. Erosion control matting shall be installed by the Contractor immediately after the first application of hydroseed materials. In all cases the Contrac- tor shall place the erosion control matting within three days after the first hydroseed material ap- plication. Should any seed in the hydroseed materials begin to germinate within the three -day period after application or before the installation of the erosion control matting, the installation of the erosion control matting shall be considered as late and the Contractor shall disc the hydroseed materials into the top 100m (4”) of the underlying soil, condition the soil for hydroseeding, apply hydroseeding materials at the rates and of the type specified and then install the erosion control matting. No additional payment will be made for second or subsequent hydroseed applications resulting from late installation of erosion control matting.

Add the following section:
308-4.10.3 Installation. The Contractor shall install erosion control matting using the following techniques:

1. Begin at the top of the slope by placing the erosion control matting into a 150 mm (6“) wide by 150 mm (6“) deep trench with the end of the matting laid flat in the bottom of the trench

2. Anchor the end of the erosion control matting with erosion control mat staples spaced no more than 300 mm (12”) on centers placed at the intersection of the bottom and the down- hill vertical face of the trench.

3. Roll the erosion control matting down the slope.

4. Staple the erosion control matting on an alternating grid consisti ng of three across and two across lines of staples in horizontal lines spaced 900mm (3’) on centers.

5. Erosion control mat so stapled shall be spaced such that no less than 1 ¾ staples per square meter (1½ staples per square yard) are provided to anchor the erosion control matting.

6. Start the adjacent erosion control mat as in Item 1. of this section, overlapping the previ- ously placed mat by no less than 50 mm (2”).

7. Staple placement may be such as to use the staples used to secure the adjacent mat to secure both mats along their edges.

308-5 IRRIGATION SYSTEM INSTALLATION.

308-5.1 General. Add the following: The Contractor shall apply irrigation water as often and in sufficient amounts, as conditions may require, to germinate and establish the seed and keep the container plants healthy and growing. The Contractor shall lay out lines, valves, and other under- ground utilities and receive the approval of the Engineer before digging trenches. The Contractor shall be responsible for damages caused by its operations. Connections shall be made at approx- imately the locations shown on the drawings. The Contractor shall be responsible for unapproved changes. Permission to shut off any existing in- use water lines must be obtained 48 hours in advance, as to the date, time and exact length of time of each shut -off. The Contractor shall demonstrate that the entire irrigation system is under full automatic operation for a period of seven days prior to any planting.

308-5.2 Irrigation Pipeline Installation. Add the following: The Contractor shall install all pres- sure main line piping from the irrigation system so as to maintain 3.1 m (10’) minimum horizontal separation from all potable water piping. Where reclaimed and potable water pressure mainline piping cross, the reclaimed water piping shall be installed below the potable water piping, sleeved in a pressure rating of 200 PSI SDR 21 “Alertline” PVC sleeve which extends a minimum of 3.1 m (10’) on either side of the potable water piping and be located to provide a minimum vertical clearance of 300 mm (12”) between the reclaimed and potable water lines. Conventional (white)

Revised 6/15/17 Contract No. 6062 Page 187 of 210
PVC pipe Schedule 40 may be used for sleeving material if it is taped along its entire length with 75 mm (3“) wide purple warning tape which reads “Caution Reclaimed Water”.

For trenching through areas where topsoil has been spread, the Contractor shall deposit topsoil on one side of trench and subsoil on opposite side. Subsoil shall be free of all rocks 13 mm (½“) in diameter or larger, debris, and litter, prior to use as backfill. The Contractor shall repair any leaks and replace all defective pipe or fittings until lines meet test requirements. The Contractor shall not cover any lines until they have been inspected and approved by the Engineer for tight- ness, quality of workmanship, and materials. The Contractor shall not be backfill trenches until all required tests and observations are performed. Observations include sprinkler heads, all fittings, lateral and mainline pipe, valves, and direct burial wire.

308-5.2.3 Plastic Pipeline. Add the following: The Contractor shall store all pipe and fittings under cover until used, and all pipe and fittings shall transported in a vehicle with a bed long enough to allow the length of pipe to lay flat so as not to be subjected to undue bending or concentrated external load at any point. Pipe ends and fittings shall be wiped with MEK, or equal, before welding solvent is applied. Welded joints shall be given a minimum of 15 minutes to set before moving or handling.

All field cuts shall be beveled to remove burrs and excess before fitting and gluing together. The Contractor shall center load pipe with small amount of backfill to prevent arching and slipping under pressure. Joints shall be exposed for inspection during testing. Plastic-to-plastic joints shall be solvent-welded, using only solvent recommended by pipe manufacturer.

Add the following section:
308-5.2.6 Installation of Brass Pipe. The Contractor shall cut brass piping by power hacksaw, circular cutting machine using an abrasive wheel, or hand hacksaw. No piping shall be cut with metallic wheel cutter of any description. The Contractor shall ream and remove rough edges or burrs on all pipe so that smooth and unobstructed flow is obtained, place Teflon tape, Teflon dope, or approved equal on male threads only, and tighten to prevent any leakage. The Contractor shall tighten screwed joints with tongs or wrenches. Caulking is not permitted.

Add the following section:
308-5.3.1 Valves. Add the following:

The Contractor shall install each control valve in a separate valve box with a minimum of 300 mm (12”) separation between valves and 150 mm (6”) from any fixed object or structure.

Add the following section
308-5.3.2 Valve Boxes. The Contractor shall install no more than one valve per box. All boxes are to be marked as to the type of valve. Remote control valve boxes shall also indicate control station number.

Add the following section:
308-5.3.3 Backflow Preventer. The Contractor shall install backflow preventer assembly in ac- cordance with manufacturer's specifications and as directed on drawings. Exact location and po- sitioning shall be verified on the site by the Engineer.

308-5.4.4 Sprinkler Head Adjustment. Add the following: The Contractor shall flush and adjust all irrigation heads and valves for optimum performance and to prevent overspray onto walks, roadways buildings, walls, and other structures.

Revised 6/15/17 Contract No. 6062 Page 188 of 210
Add the following section:
308-5.4.5 Drip Assembly. The Contractor shall install drip emitter filter on the supply side of all electric pressure regulating control valve for all emitter systems. The Contractor shall install a flush valve on the discharge side of all drip laterals.

308-5.5 Automatic Control System Installation. Add the following: The Contractor shall install all portions of the electrical installation with materials and methods conforming to the requirements of the 1996 National Electrical Code. The Contractor shall provide no less than one control wire and one common ground wire to service each valve in system.

308-5.6.3 Sprinkler Coverage Test. Add the following: This test shall be accomplished before any ground cover is planted.

308-6 MAINTENANCE AND PLANT ESTABL ISHMENT. Add the following: For hydroseeded areas, median planting and mitigation area, The Contractor shall maintain said areas for period of no less than 120 days or until final acceptance of the project, whichever is the greater. Mowing is not required for hydroseeded areas. The Contractor shall provide complete landscape maintenance of all planted areas. The work shall include, but not be limited to, watering, litter control, weed control, stake repair, cultivating, supplementary fertilization, repair of irrigation systems, and control of dis- eases and pests. The Contractor shall submit a written plan to control weeds, disease, and pest infestations in the planting areas. The submittal shall conform to the requirements for shop drawings as specified in section 2-5.3 et seq. of the specifications. The Engineer shall approve all methods and materials for such control. Upon approval, the Contractor shall implement the control measures, exercising extreme caution in using pesticides and taking all steps to ensure the safety of the public.

Only licensed personnel will be permitted to perform toxic spraying work. During the plant establish- ment period, the Contractor shall furnish sufficient workers and equipment on a daily basis to perform the work required by this section. Any day when the Contractor fails to adequately carry out specified maintenance work, as determined necessary by the Engineer, will not be credited as one of the plant establishment days. All planting areas which are damaged by construction shall be repaired by the Contractor within twenty (20) days following completion of construction in such. The Contractor shall repair such damaged areas. The repair shall consist of bringing the damaged area back to final grade, preparing the soil, replanting the area with the same vegetation as originally specified, and maintaining the area to achieve acceptable plant establishment.

The Contractor shall provide temporary irrigation for hydroseeded areas for a minimum of 120 days to ensure adequate plant establishment. Towards the end of the maintenance period, the Contrac- tor shall gradually reduce the amount of irrigation to allow plant adaptation to non-irrigated condi- tions. Upon the approval of the engineer, the temporary irrigation system shall be shut off at the end of the maintenance period. The hydroseeded areas must have their growth of 80% established and the coverage must be evenly successful over the entire hydroseeded area and adequate to prevent erosion no less than 30 days before the end of the maintenance period. Should the coverage not be achieved the maintenance period shall be extended until the required coverage is achieved plus an additional 30 day period. The Contractor shall call for a final inspection 30 days before the end of the maintenance period and at the end of the maintenance period. Failure to pass inspection will result in an extension of the maintenance period. The Contractor shall continue to provide mainte- nance for such time necessary to obtain conformance to the specifications.

308-7 GUARANTEE. Add following: The Contractor shall guarantee all 600 mm (24”) box trees installed under the contract to live and grow for one year from the day of final acceptance of the contract work. The Contractor shall guarantee all other plant material, including ground covers to live and grow for a period of 30 days from the last day of the maintenance period or final acceptance

Revised 6/15/17 Contract No. 6062 Page 189 of 210
of the contract work, whichever is the later. The Contractor shall replace, at its expense, all plant material found to be dead, missing, or in poor condition during the maintenance period within 5 days of discovery of such plant material. The Engineer shall be the sole judge as to the condition of the plant material. Plant material found to be dead or in poor condition within the guarantee period shall be replaced by the Contractor, at its expense, within 15 days of written notification. Replacements shall be made to the same specifications required for the original plantings.

The Contractor shall submit written vegetation, planting and irrigation guarantee in approved form that all work showing defects in materials or workmanship will be repaired or replaced at no cost to the Engineer for a period of one year from the date of acceptance by the Engineer. The Guar- antee form shall be retyped on the Contractor's letterhead and contain the following verbiage:

“Guarantee For Vegetation, Planting and Irrigation System For (Project Name) We hereby guarantee that the vegetation, planting and irrigation system we have furnished and installed for (project name) is free from defects in materials and workmanship, and the work has been completed in accordance with the drawings and specifications. We agree to repair or replace any defect in vegetation, material or workmanship, including that due to ordinary wear and tear, which may develop during the periods specified in section 308- 7 of the Standard Specifications and the Special Provisions of said project from date of completion of the Work or termination of any maintenance period, whichever is the later, and also to repair or replace any damage resulting from the repairing or replacing of such defects at no additional cost to the Agency.

This guarantee does not extend to unusual abuse or neglect that may occur subsequent to the date of completion of the Work or termination of any maintenance period, whichever is the later.

We shall make such repairs or replacements within a reasonable time, as determined by the Engineer, after receipt of written notice. In the event of failure to make such repairs or replace- ments within a reasonable time after receipt of written notice from the Engineer, we authorize the Engineer to proceed to have said repairs or replacements made at our expense, and we will pay the costs and charges therefore upon demand.

Project: (Project Name)
Location: (Legal Description of Project Property)
Name of Contractor:

Address: (of Contractor)
Telephone: (of Contractor)
By: (Typed or printed names of signing Officer(s) of the Contractor authorized to bind the Con- tractor in legal matters)
Title: (of said officer(s))
Signature(s)
Date of Execution:”

Add the following section:
308-7.1 Record Drawings. In addition to the requirements of section 2-5.4, herein, the Contractor shall prepare r ecord drawings that show all changes in the work constituting departures from the original contract drawings , including those involving both constant -pressure and intermittent-pressure lines and appurtenances. The Contractor shall accurately record, on a daily basis, on one set of bl ue lin e prints of the irrigation drawings, all changes in work constituting departures from the original contract drawings, including changes in both pressure and nonpressure line. The Contractor shall post information on record drawings no later than the next working day after the work is installed. The Contractor s hall record changes and dimensions in a legible and professional manner. When the drawings are approved by the Engineer the Contractor shall transfer

Revised 6/15/17 Contract No. 6062 Page 190 of 210
all information to a set of reproducible photo mylar drawings. Items required to be shown shall be dimensioned by the Contractor from two permanent points of reference (buildings, monuments, sidewalks, curbs, pavement). The accuracy of location of all items to be shown on the drawings shall be 150 mm (6”) in both the vertical and horizontal planes. All text and numerals placed on drawings shall be 0.30 mm (
1/8”) in size. Facilities and items to be located in their horizontal and vertical positions and shown on the record drawings include all:

1. Point(s) of connection, for water and electrical services

2. Routing of irrigation pressure mainlines

3. Backflow preventors

4. Ball, gate and check valves

5. Irrigation control valves.

6. Quick coupler valves

7. Routing of service wires

8. Routing of control wires

9. Electrical service equipment

10. Electrical junction boxes

11. Irrigation controllers

12. Sleeves for future connections

13. Other equipment of a similar nature (as directed by the Engineer).

The Contractor shall keep the blue print drawings available for the Engineer’s inspection at any time.

The Contractor shall make all changes to reproducible drawings in waterproof black ink (no ball point pen). Changes in dimensions shall be recorded in a legible and professional manner. Record construction drawings shall be maintained at the job site during construction. The Contractor shall provide one set of mylar "record" drawings to the Engineer after submitting blueline prints of the proposed "record" drawings for, and obtaining their approval by, the Engineer.

Add the following section:
308-7.2 Controller Chart. The Contractor shall prepare record drawings which shall be submitted to the Engineer for approval by the Engineer before charts are prepared. The Contractor shall provide one controller chart of the maximum size the controller doorwill allow, for each controller supplied, showing the area covered by that automatic controller. The chart shall be a reduction of the actual record system drawing with a legend to explain all symbols. If the controller sequence is not legible when the drawing is reduced, The Contractor shall enlarge it to a size that will be readable when reduced. The Contractor shall photocopy the chart, with a pastel transparent color used to show area of coverage for each station. When completed and approved, the Contractor shall hermetically seal the chart between two pieces of plastic, each piece being a minimum 20 mils thick. The Contractor shall complete the charts and obtain the Engineers approval prior to final inspection of the irrigation system.

Add the following section:
308-7.3 Operation and Maintenance Manuals. The Contractor shall prepare and deliver to the Engineer, within 10 calendar days prior to completion of construction, all required and necessary descriptive material in complete detail and sufficient quantity, properly prepared in four individual bound copies. The descriptive material shall describe the material installed in sufficient detail to permit qualified operating personnel to understand, operate, and maintain all equipment. The Contractor shall include spare parts list and related manufacturer information for each equipment item installed. Each manual shall include the following:

1. Index sheet stating Contractor's address and telephone number.

Revised 6/15/17 Contract No. 6062 Page 191 of 210

2. Duration of Guarantee period.

3. List of equipment, with names and addresses of manufacturer's local representative.

4. Complete operating and maintenance instructions on all major equipment.

5. In addition to the maintenance manuals, the Contractor shall provide the agency mainte- nance personnel with instructions for major equi pment and show written evidence to the Engineer at the conclusion of the work that this service has been rendered.

Add the following section:
308-7.4 Check List. The Contractor shall complete and forward signed and dated checklist to the Engineer before final acceptance of project, using the format shown:

1. Plumbing permits (if none required, so note)

2. Materials approval

3. Pressure mainline test (by whom, and date)

4. Record drawings completed (received by, and date)

5. Controller chart completed (received by, and date)

6. Materials furnished (received by, and date)

7. Operation and maintenance manuals furnished (received by, and date)

8. System and equipment operation instructions (received by, and date)

9. Manufacturer warranties (received by, and date)

10. Written guarantee by Contractor (received by, and date)

308-8 MEASUREMENT AND PAYMENT. Add the following: The lump -sum or unit prices set forth in the contract documents shall include, but not be limited to, full compensation for furnishing all labor, materials, tools, and equipment and performing all work necessary to complete, main- tain, and guarantee the planting and irrigation work described or specified in the contract docu- ments, including soils testing and recommended soil amendments, seed and hydroseed slurr y, tree stakes, bark mulch, erosion control matting, plant materials, temporary irrigation and perma- nent irrigation, including reduced-pressure back-flow preventer, ball valves, drip valve assembly, electric control valves, quick couplers, control wires, pull boxes, valve boxes, all piping and sleeves, electrical conduits, irrigation heads, drip emitters, bubblers, drip irrigation equipment, connection from electrical service to irrigation electrical meter, connection from meter to irrigation controller(s), installation of controller enclosure, concrete pads, preparation, correction, reproduc- tion and lamination of “as-built” drawings, controller charts, assembly and submittal of the check list and operation and maintenance manuals and all appurtenances to the aforementioned items, as well as 120 days' maintenance and project guarantees. After completion of the project, the Engineer will retain $12,000 of the total contract amount and will subsequently disburse the $12,000 to the Contractor on a monthly basis of $3,000 per month. The Engineer reserves the right to stop payment until all punch list submitted to the Contractor every month are completed.

The wetland mitigation site revegetation work shown on Drawing 336- 5, Sheets L-1 through L-4 is included as landscape and irrigation installation and all labor and materials to install, maintain and guarantee pertain to it.

Add the following section:
308-9 WETLAND MITIGATION.

Add the following section:
308-9.1 General. All work shown on Sheets L-1 through L-4 of Drawing Number 336-5 including:

Revised 6/15/17 Contract No. 6062 Page 192 of 210

1. The marshes within the limits of work shall be protected by laying geotextile and adding a 300 mm (12”) layer of soil over the cloth. The limits of work are shown on Sheet 37 of Drawing 336-5 and consist of the limits of work on the west, north and east and the limits of grading on the southerly boundary.

2. The willow scrub within the limits of work shall be cut down to just above soil height.

3. The cut materials shall be mulched back onto the site and Geotextile shall then be placed over the wetland.

4. Prior to construction and placement of geotextile, the outer boundary of limits of work shall be staked and flagged with fluorescent tape at 7.6 m (25’) on center to avoid additional wetland impacts.

5. The Contractor shall take care that the soil remains within the limits of work to avoid sed- imentation of downstream areas. Should such sedimentation occur the Contractor shall remove all sediments so deposited and shall take all measures to restore the streambed to its preconstruction condition at the Contractor’s expense.

6. Immediately subsequent to the completion of construction activities in the vicinity of the wetlands the Contractor shall remove the soil and geotextile covers.

Add the following section:
308-9.2 Payment. Temporary marsh protection shown on Sheets L-1 through L-4 will be paid for at the contract lump sum price for temporary marsh protection and shall include full compensation for protection, furnishing, marking, installing and removing of geotextile and soil cover, planting, irrigation, and erosion control measures. No additional payment shall be made for sediment re- moval and/or streambed rehabilitation due to sedimentation caused by the Contractor’s failure to contain the soil cover.

SECTION 310 - PAINTING

310-5 PAINTING VARIOUS SURFACES

310-5.6 Painting Traffic Striping, Pavement Markings and Curb Markings. Modify the fifth paragraph as follows: The Contractor shall furnish all equipment, materials, labor, and supervision necessary for painting traffic l anes, directional arrows, guidelines, curbs, parking lines, cross- walks, and other designated markings in accordance with the Plans, or for approved temporary detours essential for safe control of traffic through and around the construction site. The Contrac- tor shall remove by wet grinding all existing or temporary traffic markings and lines that may con- fuse the public. When temporary detour striping or markings are no longer required, they shall be removed prior to painting the new traffic stripes or markings.

310-5.6.3 Equipment. Delete the ninth paragraph and substitute the following: The Contractor shall provide a wet grinding machine with sufficient capacity to completely remove all existing or temporary traffic striping or markings that conflict with the striping plan, or are contrary to the Traffic Manual, or that may be confusing to the public. The surface produced by grinding the existing or temporary traffic striping or markings on pavement shall not exceed variations from a uniform plane more than 3 mm (
1/8”) in 3 m (10’) when measured parallel to the centerline of the street or more than 6 mm (1/4”) in 3 m (10’) when measured perpendicular to the centerline of the street. The use of any equipment that leaves ridges, indentations or other objectionable marks in the pavement shall be discontinued, and equipment capable of providing acceptable surface shall be furnished by the Contractor. This equipment shall meet all requirements of the air pollution control district having jurisdiction.

Revised 6/15/17 Contract No. 6062 Page 193 of 210

310-5.6.6 Preparation of Existing Surfaces. Modify the first paragraph as follows: The Contrac- tor shall remove all existing markings and striping, either permanent or temporary, which are to be abandoned, obliterated or that conflict wi th the plans by wet grinding methods. Removal of striping by high velocity water jet may be permitted when there is neither potential of the water and detritus from the high velocity water jetting to damage vehicles or private property nor to flow from the street into any storm drain or water course and when approved by the Engineer. The Contractor shall vacuum all water and detritus resulting from high velocity water jet striping re- moval from the pavement immediately after the water jetting and shall not allow such materials to flow in the gutter, enter the storm drain system or to leave the pavement surface. Surface varia- tion limitations for high velocity water jet striping removal shall be the same as for grinding. The Contractor shall not use dry or wet sandblasting in any areas. Alternate methods of paint removal require prior approval of the Engineer. Obliteration of traffic striping with black paint, light emulsion oil or any other masking method other than a minimum 30mm (0.10’) thick asphalt concrete over- lay is not permitted.

310-5.6.7 Layout, Alignment, and Spotting. Modify the first paragraph as follows: The Contrac- tor shall establish the necessary control points for all required pavement striping and markings by surveying methods. No layout of tr affic striping shall be performed by the Contractor before es- tablishment of the necessary control points. The Contractor shall establish all traffic striping be- tween these points by string line or other method to provide striping that will vary less than 80mm per 100m (1/2 inch in 50 feet) from the specified alignment. The Contractor shall obliterate, straight stripes deviating more than 80mm per 100mm (1/ 2 inch in 50 feet) by wet grinding, and then correcting the markings. The Contractor shall lay out (cat track) immediately behind installa- tion of surface course asphalt and as the work progresses.

310-5.6.8 Application of Paint. Modify the second paragraph as follows: The Contractor shall apply the first coat of paint immediately upon approval of striping layout by the Engineer. The Contractor shall paint the ends of each median nose yellow.

Add the following to the eighth paragraph: The Contractor shall apply temporary traffic stripes in one coat. Temporary traffic stripes shall be maintained by the Cont ractor so that the stripes are clearly visible both day and night.

310-5.6.10 Measurement and Payment. Modify the first paragraph as follows: Final and tempo- rary traffic striping, curb markings and pavement markings as shown on the plans and required by the specifications shall be included in the lump- sum price bid for temporary and final traffic striping, and no additional compensation will be allowed therefore. Reapplication of temporary stripes and markings shall be repainted at the Contractor's expense, and no additional compen- sation will be allowed therefore. The lump sum prices bid and shall include all labor, tools, equip- ment, materials, and incidentals for doing all work in installing the final and temporary traffic strip- ing.

Add the following Section:
310-7 PERMANENT SIGNING

Add the following Section:
310-7.1 General. Add the following section: The Contractor shall provide and install all permanent traffic control signs at locations shown on plans and as specified herein.

Revised 6/15/17 Contract No. 6062 Page 194 of 210
Add the following section:
310-7.2 Measurement And Payment. Permanent signing and appurtenances thereto shown on the plans or required in the specifications are a part of the lump-sum item for permanent signing and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in supplying and installing perma- nent signing and appurtenances, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer.

SECTION 312 - PAVEMENT MARKER PLACEMENT AND REMOVAL

312-1 PLACEMENT. Add the following to the third paragraph:

4) When being installed on asphalt concrete pavement sooner than 14 days after place- ment of the asphalt concrete pavement course on which the pavement markers are to be placed.

Add the following section:
312-1.1 Reflective Channelizer Placement and Removal. The Contractor shall place and re- move reflective channelizers the same as for pavement marker placement and removal. The Con- tractor shall place the channelizers uniformly, straight on tangent alignment and on a true arc on curved alignment to the same tolerances of position as for application of paint in section 310 -

5.6.8. The Contractor shall perform all layout work necessary to place the channelizers to the proper alignment. If the channelizers are displaced or fail to remain in an upright position, from any cause, the channelizers shall immediately be replaced or restored to their original location, by the Contractor. When reflective channelizers are removed the pavement surface shall be re- stored to the same color and surface finish as the adjacent pavement.

SECTION 313 - TEMPORARY TRAFFIC CONTROL DEVICES

Add the following section:
313-1 TEMPORARY TRAFFIC PAVEMENT MARKERS.

Add the following section:
313-1.1 General. The Contractor shall supply and install temporary traffic pavement markers, channelizers, signing, railing (type K), crash cushions and appurtenances at the locations shown on the plans and as required in the specifications, complete in place prior to opening the traveled way served by said final and temporary traffic pavement markers, signing, railing (type K) and appurtenances to public traffic.

313-1.2 Temporary Pavement Markers. Temporary reflective raised pavement markers shall be placed in accordance with the manufacturer's instructions. Temporary reflective raised pavement markers shall be cemented to the surfacing with the adhesive recommended by the manufacturer, except epoxy adhesive shall not be used to place temporary reflective raised pavement markers in areas where removal of the markers will be required. Pavement striping, legends and markers which conflict with any traffic pattern shall be removed by grinding as determined by the Engineer.

The Contractor shall use temporary reflective raised pavement markers for temporary pavement marking, except when the temporary pavement markers are used to replace patterns of temporary traffic stripe that will be in place for less than 30 days. Reflective pavement markers used in place

Revised 6/15/17 Contract No. 6062 Page 195 of 210
of the removable- type pavement markers shall conform to the section 312 "Pavement Marker Placement and Removal", except the 14-day waiting period before placing the pavement markers on new asphalt concrete surfacing as specified in section 312-1 “Placement”, shall not apply; and epoxy adhesive shall not be used to place pavement markers in areas where removal of the markers will be required.

Add the following section:
313-1.3 Channelizers. Channelizers shall be new surface-mounted type and shall be furnished, placed, and maintained at the locations shown on the plans. Channelizer posts shall be orange in color. Channelizers shall have affixed white reflective sheeting as specified in the special pro- visions. The reflective sheeting shall be 75 mm x 300 mm (3” x 12”) in size. The reflective sheeting shall be visible at 300 m (1000’) at night under illumination of legal high beam headlights, by persons with vision of or corrected to 20/20. The channelizer bases shall be cemented to the pavement in the same manner as provided for cementing pavement markers to pavement in sec- tion 312-1, “Placement.” Channelizers shall be applied only on a clean, dry surface. Channelizers shall be placed on the alignment and location shown on the plans and as directed by the Engineer.

The channelizers shall be placed uniformly, straight on tangent alignment and on a true arc on curved alignment. All layout work necessary to place the channelizers to the proper alignment shall be performed by the Contractor. If the channelizers are displaced or fail to remain in an upright position, from any cause, the channelizers shall immediately be replaced or restored to their original location, by the Contractor. The Contractor shall provide the Engineer with a Certifi- cate of Compliance in accordance with the provisions of section 4-1.5, "Certification”. Said certif- icate shall certify that the channelizers comply with the plans and specifications and conform to the prequalified design and material requirements approved by the Engineer and were manufac- tured in accordance with a quality control program approved by the Engineer.

Add the following section:
313-2 TEMPORARY TRAFFIC SIGNING

Add the following section:
313-2.1 General. The Contractor shall provide and install all temporary traffic control signs, mark- ers, markings, and delineators at locations shown on plans and specified herein.

Add the following section:
313-2.2 Maintenance of Temporary Traffic Signs. If temporary traffic signs are displaced or overturned, from any cause, dur ing the progress of the work, the Contractor shall immediately replace the signs in their original approved locations. The Contractor shall maintain all temporary traffic signs used in the Work in a clean, reflective and readable condition. The Contractor shall replace or restore graffiti marked temporary traffic signs and posts used in the Work within 18 hours of such marking being discovered during non- working hours or, when the marking is dis- covered during working hours, within 2 hours of such discovery of marking.

Add the following section:
313-3 TEMPORARY RAILING (TYPE K) AND CRASH CUSHIONS

Add the following section:
313-3.1 Temporary Railing and Crash Cushions. Temporary railing (Type K) shall consist of interconnected new or undamaged used precast concrete barrier units as shown on the plans.

Temporary sand-filled crash cushions shall consist of new or undamaged used temporary sand- filled crash cushions units as shown on the plans.

Revised 6/15/17 Contract No. 6062 Page 196 of 210
313-3.1.1 Appearance. Exposed surfaces of new and used units of Temporary railing (Type K) shall be freshly coated with a white color paint prior to their first use on the project. The paint shall conform to the provisions in sections 210-1.5 “Paint Systems” and 310 “Painting”. Contractor shall be responsible for the removal and cleanup or painting over the graffiti from the K-Rails within 48 hours. The Contractor Shall replace or repaint units of Temporary railing (Type K) or shall remove graffiti, tire or vehicle m arks, dirt or any and all materials such that said marks or discoloration mar the appearance of said units when ordered by the Engineer after the units are in place.

Add the following section.
313-3.1.2 Manufacture of Temporary Railing. In addition to the requirements herein the tempo- rary railing (Type K) shall be manufactured per CALTRANS Standard Drawing T3. Concrete used to manufacture Temporary railing (Type K) shall conform to the provisions in sections 201- 1, “Portland Cement Concrete” and 303 -1 “Concrete Structures.” Load tickets and a Certificate of Compliance will not be required. Reinforcing steel shall conform to the provisions sections 201-1, “Portland Cement Concrete” and 303-1 “Concrete Structures”. Steel bars to receive bolts at ends of concrete panels shall conform to ASTM Designation: A 36/A 36M. The bolts shall conform to ASTM Designation: A 307. A round bar of the same diameter may be substituted for the end- connecting bolt shown on the plans. The bar shall conform to ASTM Designation: A 36/A 36M, shall have a minimum length of 660 mm and shall have a 75 mm (3”) diameter by 9 mm (3/8”) thick plate welded on the upper end with a 5-mm (3/16”) fillet weld. The final surface finish of temporary railings (Type K) shall conform to the provisions in section 303 -1.9.2 “Ordinary Surface Finish.” Exposed surfaces of concrete elements shall be cured by the water method, the forms -in-place method, or the pigmented curing compound method. The pigmented curing compound shall be type 2 curing compound. Temporary railing (Type K) may have the Contractor’s name or logo on each panel. The name or logo shall not be more than 100 mm in height and shall be located not more than 300 mm above the bottom of the rail panel.

Add the following section.
313-3.1.3 Installation of Temporary Railing. In addition to the requirements herein the tempo- rary railing (Type K) shall be installed per CALTRANS Standard Drawing T3. Temporary railing (Type K) shall be set on firm, stable foundation. The foundation shall be graded t o provide a uniform bearing throughout the entire length of the railing. Abutting ends of precast concrete units shall be placed and maintained in alignment without substantial offset to each other. The precast concrete units shall be positioned straight on tangent alignment and on a true arc on curved align- ment Each rail unit placed within 3 m (10’) of a traffic lane shall have a reflector installed on top of the rail as directed by the Engineer. Reflectors and adhesive will be furnished by the Contrac- tor. A Type P marker panel conforming to the requirements of the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement shall also be installed at each end of rai ling installed adja- cent to a two-lane, two-way highway and at the end facing traffic of railing installed adjacent to a one-way roadbed. If the railing is placed on a skew, the marker shall be installed at the end of the skew nearest the traveled way. Type P marker panels shall conform to the provisions of sec- tion 206-7.2, “Temporary Traffic Signs”. Where shown on the plans, threaded rods or dowels shall be bonded in holes drilled in existing concrete. When temporary railings (Type K) are removed, any area where temporary excavation or embankment was used to accommodate the temporary railing shall be restored to its previous condition or constructed to its planned condition.

Add the following section:
313-3.2 Temporary Sand- Filled Crash Cushions. Temporary sand-filled crash cushion units shall be “Energite III” manufactured by Energy Absorption Systems, “Fitch Inertial Barrier System Modules” manufactured by Roadway Safety Service, or equal. Features required to determine

Revised 6/15/17 Contract No. 6062 Page 197 of 210
equivalence of any other temporary sand-filled crash cushion units shall be approval of the system by CALTRANS and that the temporary sand- filled crash cushion units meet NCHRP 350 stand- ards. Other features will be suitability to application, operational characteristics, durability and other such characteristics that the Engineer shall determine. Temporary sand- filled crash cush- ions (TSFCC) shall be of the type and array configurations shown on plans, and installed at every end of, or gap in, the temporary railing (Type K) whenever the closest point of approach of traffic, regardless of direction, is 4.6 m (15’) or less to the end of the temporary railing (Type K) being considered. The TSFCC shall be installed per CALTRANS Standard Drawings T1 and T2 for ap- proach speeds no less than the posted speed of the street prior to construction or 55 kilometers per hour (35 mph), whichever is the greater. The TSFCC array shall be appropriate to the appli- cation as shown on said standard drawings. A Type J and/or P marker panel conforming to the requirements of the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement shall also be installed at each TSFCC array as shown in CALTRANS Standard Drawings T1 and T2.

Particular care shall be taken to assure that crash cushions are installed with the soil supporting them and the adjacent soil leveled to match the elevation of the bottom of the temporary railing immediately adjacent to the crash cushion. All routes of approach to the TSCFF array shall be graded such that any vehicle diverging from the travelled way to strike the TSCFF will travel on a vertical alignment parallel to the segment of the travel lane that it departed from.

Add the following section:
313-4 MEASUREMENT AND PAYMENT. Temporary traffic pavement markers, temporary chan- nelizers, temporary signing, temporary railing (type K), temporary crash cushions and temporary appurtenances thereto shown on the plans or required in the specifications are a part of the lump- sum item for traffic control and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in apply- ing, installing, maintaining, and removing temporary traffic pavement markers, channelizers, sign- ing, railing (type K), crash cushions and appurtenances, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer. Payment for temporary crash cushions, concrete barriers and the signs and reflectors marking them shall include the installation, grading for installation, grading for the approach path, maintenance, painting and re-painting, replacement of damaged units and removal and shall also be included in the lump-sum price bid for traffic control. Payment for installation and/or relocation of K-rails and crash cushions when not shown on the plans and requested by the Engineer shall be made per section 3-3, Extra Work, SSPWC.

Revised 6/15/17 Contract No. 6062 Page 198 of 210

SUPPLEMENTAL PROVISIONS
TO

STANDARD SPECIFICATIONS FOR PUBLIC WORKS

CONSTRUCTION

PART 6, MODIFIED ASPHALTS, PAVEMENTS AND PROCESSES

600-3 RUBBERIZED EMULSION - AGGREGATE SLURRY

600-3.2 Materials. Add the following: Aggregate for Rubberized Emulsion - Aggregate Slurry shall be Type I Slurry Aggregate.

600-3.4 Application of REAS . Add to the first paragraphs: No slurry shall be applied until the provisions of subsection 212- 1.2.6, Herbicide Application, Section 302- 11 Asphalt Concr ete Pavement Crack Filling and Sealing, Section 312- 3 Pavement Marker Removal have all been satisfied.

The Contractor shall remove all existing markings, legends and striping, either permanent or tem- porary in those areas to be slurried. Removal of striping by high velocity water jet may be permit- ted when there is neither potential of the water and detritus from the high velocity water jetting to damage vehicles or private property nor to flow from the street into any storm drain or water course and when approved by the Engineer. The Contractor shall vacuum all water and detritus resulting from high velocity water jet striping removal from the pavement immediately after the water jetting and shall not allow such materials to flow in the gutter, enter the storm drain system or to leave the pavement surface. Surface variation limitations for high velocity water jet striping removal shall be the same as for grinding. The Contractor shall not use dry or wet sandblasting in any areas.

All cracks and areas between existing curb and gutter and edge of pavement that contain weeds or plant growth of any kind shall be treated with herbicides. Herbicides shall be applied at least 2(two) working days prior to sealing of street. Allowance for the two day period shall be shown in the schedule required per section 6- 1. Contractor shall remove any visible plant growth prior to placement of Herbicide.

Full compensation for removal of striping and herbicide application shall include but not be limited to: furnishing all labor, tools, equipment, and materials necessary for doing the work and shall be considered as included in the contract unit price bid for Rubberized Emulsion Aggregate Slurry and no additional compensation will be allowed therefore.

600-3.6 Public Convenience and Traffic Control. Modify the first line with the following: Public Convenience and traffic control shall conform to 302-4.4.4. There shall be no stockpiling of mate- rial allowed on City right-of-way.

Revised 6/15/17 Contract No. 6062 Page 199 of 210

SUPPLEMENTAL PROVISIONS
TO

STANDARD SPECIFICATIONS FOR PUBLIC WORKS

CONSTRUCTION

PART 7, STREET LIGHTING AND TRAFFIC SIGNAL SYSTEMS

SECTION 700 - Materials

700-4 STREET LIGHTING SYSTEM MATERIALS

700-4.7 Photoelectric Controls
700-4.7.2 Photoelectric Control Units

Replace the subsection with the following:

The photoelectric unit shall consist of a photoelectric cell in a weatherproof housing which plugs into an EEI-NEMA twist-lock receptacle integral with the luminaire and shall be installed with the clear UV -stabilized photocell window facing north. The control unit shall contain a uniformly coated cadmium-sulfide photoelectric cell suitable for operation with 120- or 240-volt line supply with surge protection to prevent damage and made to fail in the “ON” position. The unit shall have a HID load rating of 1,800 VA with a Tungsten load rating of 1,000 watts. The unit shall have time- delay capabilities. Photocell unit shall be hermetically sealed.

The response level of the unit to changing light levels shall remain stable t hroughout the life of the unit (5,000 operations). The “turn- on” level shall be nominal 1 foot -candle and the “turn -on:
turn-off” ratio shall be 1.5.

A Fisher-Pierce # TRS -2 105-305 VAC LED photo control or approved equal shall be installed with each light fixture. The photo control unit shall meet the following minimum electrical and mechanical criteria:

• Operating Voltage Range: 105-305 VAC, 50/60 Hz- Nominal Voltage 120/208/240/277 V • Load Rating: 1,000 W / 1,800 VA
• Operating Temperature: -40°F to 150°F
• Surge Protection: 40,000 Amps
• Power Consumption: <0.5 Watts @120 V
• Dielectric Strength: 5,000 V between current carrying parts • Circuit Board: Glass epoxy, ionic cleaning and decontamination, and conformal coated • Operating Light Levels: Turn-on 1.5FC, 1.5:1 Off/On Ratio

Add new subsections:

700-4.9 LED Streetlight Luminaires
700-4.9.1 General

Revised 6/15/17 Contract No. 6062 Page 200 of 210
Street lighting fixtures shall be GE Evolve LED Roadway Lighting ERLH-0-11-C3-30-D-GRAY-LY or approved equal.

The Manufacturer shall have a minimum of a 15 -year history of designing and manufacturing outdoor luminaires and at least 10 years of LED design history in outdoor application which can include signage, traffic signals or roadway/parking fixtures.

LED streetlight luminaires shall meet the applicable requirements of the following industry stand- ards:

• ANSI/NEMA/ANSLG C78.377 -2011-Specifcations for the Chromaticity of Solid- State Lighting (SSL) Products
• IES LM-79-08 – Approved Method: Electrical and Photometric Measurements of Solid- State Lighting Products
• IESNA LM-80-08 – Approved Method measuring Lumen Maintenance of LED chips / Fix- ture Manufacturer must provide extrapolation explanation for Lumen Maintenance derived from In-Situ testing upon request
• IEEE C62.41.2-2002-IEEE Recommended Practice on Characterization of Surges in Low- Voltage (1000 V and less) AC Power Circuits
• IESNA TM-15-11 & Addendum A (replaces TM-15-07 and TM-15-07 Addendum A) – Lu- minaire Classification System for Outdoor Luminaires; Backlight, Uplight, and Glare (BUG) Ratings
• ANSI/UL 8750: Additional requirements for LED luminaires as well as drivers and LED arrays
• LM-79-08 Approved Method: Electrical and Photometric Measurements of Solid- State Lighting Products
• LM-80-08 Approved Method: Measuring Lumen Maintenance of LED Light Sources • TM21 tests and reports shall be available and performed in accordance with IESNA Stand- ards
• LM-79 tests and reports shall be available and performed in accordance with IESNA standards
• Shall be IP 65 rated optical enclosure per ANSI C136.25-2009 • Shall be RoHS compliant

Test data that establishes compliance with the requirements of ANSI/UL 1598 and the other in- dustry standards listed above shall be provided upon request.

700-4.9.2 Optical System Requirements

Optical configurations shall meet the following criteria:

• An embedded reflector system that is metallic coated with a high-quality reflectance finish material containing a long-life finish designed to last the life of the fixture without corroding, peeling or fading under normal operating conditions.
• A 16-gauge aluminum metal core printed circuit board assembly designed to operate as a class I circuit.
• LED’s shall be recessed into the reflective optical system and surface mounted to the aluminum core board using advanced SMT manufacturing processes. • The circuit board shall be attached to a machined surface on the casting using tri-lobular thread forming screws so as to maximize heat transfer over the life of the fixture.

Revised 6/15/17 Contract No. 6062 Page 201 of 210
• Lumen maintenance at 50,000 hours of life to be no less than 88% of initial lumen output. • Shall have 95% survival rate at 50,000 hours.
• Integral 10K surge suppressor for diode and entire system protection. • Street lighting fixture shall provide a minimum 11,000 Lumens and shall be IESNA Type III distribution.
• The LED pad temperature shall not exceed 75°C at 25°C ambient. • On units that contain more than one optical assembly, there shall be a provision to specify that at least one of the optical assemblies can offer photometry in the house side direction. • The optical assembly shall be from the same manufacturer as the luminaire housing. • Each fixture shall contain a single transparent flat tempered glass optical cover and optical cavity must be vented.

700-4.9.3 Photometric Requirements

Luminaires shall meet the following criteria:

• High efficacy LED’s rated at a minimum of 120 Lumens per Watt (LPW) • A typical Color Rendering Index (CRI) ≥ 70.
• An IESNA TM-15 UL/UH rating of 0.
• All fixtures shall have a field adjustable driver factory installed with present dimming marks for ease of adjustment.

700-4.9.4 Electrical System Requirements

The luminaires fixture assembly shall meet the following criteria:

• Off-state power draw of 0 watts (excluding PE or remote control devices). • 7-prong locking ANSI C136.41 photocell receptacle with tool-less orientation and the op- tion to have two additional wires for 0-10V.
• A minimum system power factor of .9 tested and specified at 120v input at full power. • Maximum THD < 20% tested and specified at 120v input at full power. • Operating temperature range of UL1598 Tested -40º C to 50º C. • UL Class 1 power supply units (i.e. drivers) operating in DC constant current mode. • EMI compliance with FCC 47 CFR Part 15 Class A.
• Electrical components have a Class A sound rating.
• The luminaire shall contain the factory-installed driver supplied with the optic assembly. • The optic assembly and housing shall be from the same manufacturer. • The drivers shall reliably start and operate the optic assembly at ambient te mperatures from -40°C to 50°C.
• The drivers and fixture shall be from the same manufacturer. • Drive current is not field switchable.
• Complete assembly weight shall not exceed 25 lbs.
• Fixture, including the LEDs, drivers and electrical components, shall carry a limited ten- year warranty and housing paint and finish shall carry a ten-year warranty. • Color temperature and CRI:
o 3000K color temperature for Street Lighting, minimum 70 CRI.

Fixture surge protection shall meet the following criteria:

Revised 6/15/17 Contract No. 6062 Page 202 of 210
• Per ANSI C136.2- 2015. 6KV / 3KA For the 120- 277 VAC single phase luminaire, the standard protection for the electrical system shall survive 120 repetitive surge events • Per ANSI C136.2-2015 Enhanced High Capacity 10KV/5KA Surge Protection for 120-277 VAC single phase luminaire The standard protection for the electrical system shall survive 40 repetitive surge events

Electrical Wiring and Connections shall meet the following criteria:

• The electrical cavity shall use only copper wire within the fixture but be able to accommo- date aluminum field wiring into the terminal board.
• Main voltage harness and wiring insulation shall be AWM rated for 125°C and 600 Volt. • Terminal block shall be oriented to be “lineman friendly” within the electrical cavity to al- low for easy wire connections.
• The terminal block shall accommodate AWG 8-16 gauge CU wire and up to AWG 6 gauge AL wire.
• UL Listed to UL1598 for Wet Locations.

LED drivers shall be component -type consisting of precision wound coils and welded magnetic steel laminations assembled together and impregnated with baked -on, insulating, weatherproof varnish; and metal-cased, hermetically-sealed capacitor, suitable for use on multiple distribution circuits with 60Hz, 120 - or 240-Volt rating. The operating sound press ure noise level shall not exceed the ambient noise level by more than five (5) decibels at 30 -feet when measured by a sound level meter conforming to the American Standards for Sound Level Meters. Where the ambient noise level is less, a minimum of 40 deci bels shall be assumed. The driver shall be the same manufacturer as the fixture.

Power supply / driver shall be field replaceable by means quick-disconnect connectors and easy access mounting hardware. Power supply / driver shall be wet-listed in the US and Canada, UL, ROHS compliant, meet Caltrans 611 vibration testing and GR-63-CORE section 4.4.1/5.4.2 earth- quake zone 4.

LED driver shall meet the following criteria:

• Electronic:
o voltage range = universal 120 – 277 v +/- 10%;
o frequency = 50/60 Hz;
o power factor > 90% @ full load;
o THD < 20% @ full load;
o output ripple < 10%;
o output shall be isolated;
o case temperature rated for -40°C to 60°C;
o fully encased and potted;
o overheat protection, self-limited short circuit protection, and overload protected – minimum integral 10k surge protection tested in accordance with IEEE C62.41 and ANSI standard 62.41.2;
o Driver Life Rating not less than 100,000 hours.

Revised 6/15/17 Contract No. 6062 Page 203 of 210
700-4.9.5 Luminaire Housing and Mechanical Construction

Luminaire housing shall be furnished with an optical assembly, be powder-coated silver, include a level bubble to facilitate installation, allow for tool-less entry, and shall include an integral twist- lock type receptacle for photoelectric cell control in accordance with the latest EEI-NEMA stand- ards which is adjustable with respect to north and prewired to the terminal board. Photocell control shall be for a 7-pin receptacle per ANSI C136.41.

The housing construction will incorporate heat sink fins that are integrally cast with the housing and door to maximize heat transfer and minimize thermal impacts of environmental conditions such as debris-clogged fins.

Housings shall meet 3G vibration per ANSI C136.31- 2010 and all mounting hardware/parts are corrosion resistant.

Finish shall be corrosion resistant Polyester powder paint capable of surviving the ASTM B117 salt fog environment for a minimum of 500 hours without blistering or peeling.

The coating must demonstrate the gloss retention of great than or equal to 90% for 500 hours QUV test per ASTM G154 UVB -313, 4 hour UV-B 60 degrees Celsius, 4 hour condensation 50 degrees (spec is not complete nor does it state evaluation criteria standard). Dry film thickness of the powder paint shall be a minimum of 2.0 mils thickness.

Slipfitter in the housing shall contain two- bolt single piece clamp fastening for the ERL fixtures which do not pass through the housing and tighten from the arm directly to mount on 1.66” to

2.375” O.D. horizontal tenons and provide +/ - 5 degrees of tilt adjustment. S lip fitter assembly includes wildlife intrusion protection guard.

Luminaire external housing shall have a minimum rating of IP66 as specified in IEC 60529, with the ability to shed water from inside the housing (i.e. weep holes).

Luminaire circuitry shall include quick connect / disconnects to allow easy separation and removal of driver and power door. Grounding requirements: ANSI/UL Standards and NFPA 70.

The luminaire power unit assembly shall consist of an integral driver, capacitor, 10K surge sup- pressor, and heavy-duty terminal block. The power unit assembly shall be mounted on a separate component of the luminaire to facilitate replacement.

The luminaire optical chamber shall have a minimum rating of IP66 as specified in IEC 60529.

The luminaire housing cooling system shall consist of a passive heat sink with no fans, pumps, or liquids and shall be designed and constructed to accept a standard plug type, locking, three- pole, three-wire, streetlight photocontrol. The fixture and finis h endurance tested to withstand 5,000 hours of elevated ambient salt fog conditions as defined in ASTM Standard B 117.

An easily-viewable nameplate shall be permanently affixed to the inside of each luminaire hous- ing. The nameplate shall contain the following information: manufacturer’s name, manufacturer’s catalog number, date of manufacture (month and year), plant location, input power consumption, driver output current, IEC IP Rating, correlated color temperature (CCT), IES light distribution type, IESNA TM-15 BUG ratings, and serial number. Utility approved luminescent name plate with

Revised 6/15/17 Contract No. 6062 Page 204 of 210
light source and wattage shall be permanently affixed on the exterior of the Luminaire to be visible from the ground.

The driver assembly shall be enclosed in a separate compartment from the optical assembly. The entire fixture shall be “wet listed” with the optical assembly compartment being rated at IP66. The LED Luminaire shall be constructed to provide the required light distribution with the lower edge of the Luminaire housing below the entire light source close contact refractors. The Luminaire must be Dark Sky Compliant with U0 bug rating . The light distribution pattern shall be per optical system requirements section above.

Luminaire head shall be equipped with a photoelectric control unit.

700-4.9.6 Performance Claims

Fixtures shall meet or exceed the following performance claims:

• LED performance claims shall be independently verified from the LED manufacturer. Ver- ification shall include lumen output, life and color properties and be measured in accord- ance with LM-80.
• CCT and CRI and shall be tested and measured in accordance with LM-79. • Lumen depreciation data shall be measured in accordance with LM-80 and TM-21. • TM21 performance data to be a minimum of L91 @50,0000 hours @25c. • Lumen Maintenance projections shall not exceed 6 times (6x) the available system -level lumen depreciation test data at an ambient temperature of 25º C or as specified by the end user.
• A normal UL1598 operation temperature from -40º C to 50º C.

SECTION 701 - CONSTRUCTION

701-16 STREETLIGHT CONSTRUCTION
701-16.1 General

Add the following:

For streetlights with existing lighting shields, picture documentation shall be performed and re- ported back to City with associated Asset ID number. Existing shields shall be removed and rein- stalled with the replacement of the lighting fixture. Contractor shall attach shield with stainless steel screws and install in such a way to not affect the new lighting fixture.

Contractor shall cap and test all new fixtures to ensure operability. For inoperable fixtures, con- tractor shall troubleshoot by checking line side of the fuse in pole. Contractor shall replace fuse and test operability of light fixture. If replacing of the fuse does not correct the street light opera- bility issues, contractor shall document issue and report back to the City with associated street light Asset ID number.

Add new subsections:

701-16.8 LED Wireless Lighting Controls and Asset Management

Revised 6/15/17 Contract No. 6062 Page 205 of 210
All hardware, software and firmware necessary for installation, operation and management of all components shall be provided.

Contractor will be responsible for installation of all field device hardware associated with the pro- posed lighting control management system.

A separate software/licensing agreement contract will be established between the City and ven- dor of the lighting management system excluding the contractor.

Vendor of the wireless lighting control system shall provide the following services:
• Provide all pertinent installation and start up instructions and manuals. • Vendor or a manufacturer-qualified representative shall provide installation support in per- son, or via telephone and/or internet
• Vendor shall provide installation training
• Vendor and City shall jointly perform an installation audit

The system start-up shall be performed by the City or their 3 rd party representative and supported
by the following vendor requirements:

Wireless lighting control system start-up and responsibilities shall be as follows:
• The wireless communications shall be automatically established and optimized without the use of any form of “in field” programing. The use of field programing electronic tools/computes will not be required during the installation. The physical location of each controller shall be automatically transmitted to the CMS without any in field program re- quirements.
• The System shall be examined for any hardware, software, or firmware incompatibilities or errors that occurred during installation.
• The Configuration period shall begin immediately following the completion of installation, successful Start-Up, and successful demonstration of all System functions and capabili- ties.
• The Configuration period shall include a trial period comprised of 30 consecutive calendar days of System operation. The trial will not start until the system has reached "substantial completion", been signed off by the City or City’s representative, and has met the specifi- cation requirements.
• Over the course of the trial period, all System functions and capabilities described during Vendor training shall be successfully demonstrated.
• Over the course of the trial period, all System functions and capabilities shall operate nor- mally for at least ninety-eight percent (98%) of the time. • The Commissioning Period shall end following City acceptance of a successful trial period.

Vendor of the wireless lighting control system shall provide the following training:

• Comprehensive training at the City’s facility, covering at a minimum:
o Testing and programming
o Configuration
o Administration
o Operation
o Operation
o Troubleshooting
• Training shall be scheduled based on availability if City staff

Revised 6/15/17 Contract No. 6062 Page 206 of 210
• Provide training manuals and all other documentation (i.e. Operations and Maintenance manuals) in pdf form.
• Provide all necessary instructional equipment to be used during the training sessions for training purposes.
• Provide instruction using the installed system (not using a remote system or a simulated system) and geared towards new users.
• City may elect to record these training sessions for City’s sole use for future training pur- poses. The resulting recordings shall be the sole property of the City and for the sole use of the City.
• Shall specify the degree of coordination needed with the City’s IT staff in regards to com- munications with existing systems.

The system shall be maintained by the City or 3
rd party contractor. Vendor shall provide compre-
hensive maintenance training at the City’s facility, covering all aspects of the system.

Vendor shall provide hardware and software maintenance and support according to the warranty terms for the duration of the warranty period. Any maintenance term shall start following the ap- plicable warranty period.

The vendor shall specify any and all mandatory maintenance required to maintain the terms of the warranty.

Software and firmware upgrades, maintenance and support shall be provided for one year at no extra cost.

701-20 SALVAGE

Add the following:

Existing LED fixtures shall be salvaged and returned to Carlsbad Public Works building located at 405 Oak Ave, Carlsbad CA, 92008 by the Contractor. Existing induction fixtures shall be re- moved and recycled appropriately per State recycling guidelines by the Contractor.

Revised 6/15/17 Contract No. 6062 Page 207 of 210

SPECIAL PROVISIONS

Per Section 6-7.1, the contractor shall complete all contract work within 90 working days from the time the material is first received (unless otherwise approved by the Agency).

Failure of the Contractor to complete the Work within the time allowed will result in damages being sustained by the Agency. For each consecutive calendar day in excess of the time specified for completion of Work (90 days from Notice to Proceed), in accordance with Section 6 -9, the Con- tractor shall pay the Agency, or have withheld monies due it, the sum of seven hundred dollars ($700.00). Such sum is liquidated damages and shall not be construed as a penalty and may be deducted from payments due the Contractor if such delay occurs.

Products proposed to be submitted as an “or equal” substitute shall be submitted with a minimum of 7 days prior to bid closing. Requests received after this period may be accepted or rejected at the discretion of the City. If an “or equal” substitute product is submitted, the following additional information shall be provided to the City:

1. An explanation of the advantages to the City for accepting the substitution.

2. A comparison of significant qualities of the proposed substitution with those specified.

3. A list of changes or modifications needed to other parts of the work and to construction performed by the City and separate Contractors that will be necessary to accommodate the proposed substitution.

4. A statement indicating the substitution's effect on the Construction Schedule compared to the Construction Schedule without acceptance of the substitution. Indicate the effect of the proposed substitution on overall contract time.

5. Cost information, including a proposal of the net change, if any, in the Contract Sum.

6. Certification that the substitution is equal to or better i n every respect to that required by Contract Documents, and that it will perform adequately in application indicated. Include Contractor's waiver of rights to additional payment or time extensions that may be neces- sary because of the substitution's failure to perform adequately.

The substituted product will not be considered unless the submittal is accompanied by complete information and descriptive data necessary to determine equality of offered material(s), article(s), or equipment. Samples shall be provided when requested by the City. Burden of proof as to com- parative quality, suitability, and performance of offered material(s), article(s), or equipment shall be upon the Contractor. The City will be the sole judge as to such matters. In the event the Cit y rejects the use of such alternative(s) submitted, then one of the particular products originally spec- ified in the Contract Documents shall be furnished.

If mechanical, electrical, structural, or other changes are required for installation, fit of alternative materials, articles, or equipment, or because of deviations from Contract Drawings and Specifi- cations, such changes shall not be made without consent of the City, and shall be made without additional cost to the City.

Specifications shall provide a period of time prior to or after, or prior to and after, the award of the contract for submission of data substantiating a request for a substitution of "an equal" item. If no time period is specified, data may be submitted any time within 35 days af ter the award of the contract." It is not uncommon for the specifications to provide as few as seven days to submit the request for substitution.

Revised 6/15/17 Contract No. 6062 Page 208 of 210
The statute also requires the public entity, if aware of an equal product manufactured in this state, to name that product in the specification.

Typical "Or Equal" Requirements
A typical substitution clause will include the following: (1) a requirement that any proposed sub- stitution be submitted within a fixed period of time (as few as 7 days); (2) notification by the con- tractor as how the substituted product will impact the completion; (3) notification by the contractor as to the difference in cost between the substituted product and the listed product; (4) a require- ment that the contractor provide a detailed analysis of the difference between the listed product and the proposed product; (5) a requirement that the contractor provide (a) product identification, manufacturer literature, samples, names and addresses of similar projects where the substituted product has been used; (b) and the name and address of the manufacturer's representative; and (7) that the contractor pay the cost of the design team to review the proposed substitution.

Substitutions and Approved Equals: Alternative material(s), art icle(s), or equipment that are of equal quality and of required characteristics for the purpose intended may be proposed by the Contractor. The AOC or the AOC’s authorized Representative will examine any and all proposed alternatives for compliance with the Contract Documents. The proposed material(s), article(s) or equipment will be reviewed for comparative quality, suitability, and performance against the prod- uct(s) specified in the Contract Documents.

Substitutions and Approved Equals: Alternative material(s), article(s), or equipment that are of equal quality and of required characteristics for the purpose intended may be proposed by the Contractor for use in the Work, provided the Contractor complies with the attached Specifications and the following requirements:

1. The Contractor shall submit a proposal for the alternative material(s), article(s), or equip- ment, in writing, within 10 days after Contract start date stated in the Notice to Proceed.

In exceptional cases where the best interests of the AOC so require, the AOC may give written consent to a submittal or re- submittal received after expiration of the time limit designated.

2. The proposal will not be considered unless the submittal is accompanied by complete information and descriptive data necessary to determine equality of offered material(s), article(s), or equipment. Samples shall be provided when requested by the AOC. Burden of proof as to comparative quality, suitability, and performance of offered material(s), arti- cle(s), or equipment shall be upon the Contractor. The AOC will be the sole judge as to such matters. In the event the AOC rejects the use of such alternative(s) submitted, then one of the particular products originally specified in the Contract Documents shall be fur- nished.

3. If mechanical, electrical, structural, or other changes are required for installation, fit of alternative materials, articles, or equipment, or because of deviations from Contract Draw- ings and Specifications, such changes shall not be made without consent of the AOC, and shall be made without additional cost to the AOC.

SUBSTITUTION REQUESTS. Requests for substitution will be considered only if received within 10 calendar days from the date of award. Requests received after this period may be accepted or rejected at the discretion of the City. Prepare and submit each request for substitution to the City in accordance with the procedures for submittals on the request form provided by the City.

The following additional information shall be provided: 1. An explanation of the advantages to the

Revised 6/15/17 Contract No. 6062 Page 209 of 210
City for accepting the substitution. 2. A comparison of significant qualities of the proposed substi- tution with those specified. 3. A list of changes or modifications needed to other parts of the work and to construction performed by the City and separate Contractors that will be necessary to accommodate the proposed substitution. 4. A statement indicating the substitution's effect on the Construction Schedule compared to the Construction Schedule without acceptance of the substi- tution. Indicate the effect of the proposed substitution on overall contract time. 5. Cost information, including a proposal of the net change, if any, in the Contract Sum. 6. Certification that the sub- stitution is equal to or better in every respect to that required by Contract Documents, and that it will perform adequately in application indicated. Include Contractor's waiver of rights to additional payment or time extensions that may be necessary because of the substitution's failure to perform adequately.

AREA DEFINITIONS. Maps and spreadsheets listing assets to be replaced or repaired in ‘Phase II’ are enclosed as supporting documents.

Revised 6/15/17 Contract No. 6062 Page 210 of 210
APPENDIX “A”

CITY OF CARLSBAD

ROAD WORK

ABC CONTRACTORS
OFFICE # (760)XXX-XXXX
FIELD # (760)XXX-XXXX
Dear resident:

As a part of the City of Carlsbad’s ongoing
program to maintain its streets, your street will be
resurfaced with asphalt concrete over the existing
roadway surface. This construction will require
the closing of your street to through traffic for one
day. Your street, from XYZ St. to DEF Ave. will be
closed to through traffic and resurfaced on:

MON. TUE. WED. THU. FRI.

DATE: _XX / XX / XX______________
from 7:00A.M. to 5:00 P.M.

If you don’t plan to leave your home by 7:00 A.M.
on the above date please park your car on an
adjacent street in your neighborhood that will not
be resurfaced. Streets scheduled for resurfacing
can be determined by calling either the
Contractor or t he City of Carlsbad’s Project
Inspector. When walking to and from your car,
remember not to walk on the newly overlaid street
or you will have black residue on the bottom of
your shoes. Please do not drive, walk on, walk
pets, play, or skate on the newly overlaid asphalt.

Also, please refrain from watering your lawns,
washing cars, etc., approximately 6-8 hours after
the asphalt is laid as running water will cause
damage to the new surface.

ABC is the Contractor that will be performing the
resurfacing work for the city and you may call
them at the above phone number if you have any
questions regarding the project. Resurfacing of
your street will not occur on the day your trash is
collected. Mail delivery may be delayed if the
postman cannot reach the mailbox that day. If you
have a moving company scheduled for that day
please call and inform the Contractor of the date.

If you have any concerns which cannot be
addressed by the Contractor, you may call the
City’s Project Inspector @ (xxx) xxx-xxxx.

Thank you for your cooperation as we work to
make a better City of Carlsbad.