Payment for claims shall be processed within 30 calendar days of their resolution for those claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Section 3-5, Disputed Work, for those claims remaining in dispute.
9-3.3 Delivered Materials. When provided for in the Specifications, and subject to the limitation and conditions therein, the cost of materials and equipment delivered but not incorporated into the Work will be included in the progress estimate.
9-3.3.1 Delivered Materials. The cost of materials and equipment delivered but not incorporated into the work will not be included in the progress estimate.
9-3.4 Mobilization. When a bid item is included in the Proposal form for mobilization and subject to the conditions and limitations in the Specifications, the costs of work in advance of construction operations and not directly attributable to any specific bid item will be included in the progress estimate. When no such bid item is provided, payment for such costs will be considered to be included in the other items of work.
9-3.4.1 Mobilization and Preparatory Work. Payment for mobilization, which includes all preparatory Work will be made at the stipulated lump-sum price bid therefore in the bid schedule, and shall not exceed 5% of the sum total of the other items of work, and includes full compensation for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment and incidentals, and for doing all the work involved in mobilization and preparatory work and operations, including, but not limit ed to, those necessary for the movement of personnel, equipment, supplies, and incidental to preparing to conduct work on and off the project site and other offsite facilities necessary for work on the project; for all other facilities, sureties, work and operations which must be performed or costs incurred prior to beginning work on various contract items on or off the project site, excepting those specifically paid for under separate sections of these specifications. The Contractor hereby agrees that the stipulated lump sum amount is
Revised 6/15/17 Project No. 6096/6104 Page 107 of 129
sufficient for Mobilization, as described in this section, and that the Contractor shall have no right to additional compensation for Mobilization.
Progress payments for Mobilization will be made as follows:
For the first progress payment (after the issuance of the Notice to Proceed), forty percent (40%) of the amount bid for Mobilization will be allowed. For the second progress payment, an additional sixty percent (60%) of the amount bid for mobilization will be allowed therefor.
9-4 BID ITEMS. Payment for each Bid Item shall be made at the quantity and type as listed in the Contractor's Proposal. All work shown or mentioned on the plans, in the Contract Documents, General Provisions, or Supplemental Provisions/Specifications shall be considered as included in the Bid Items. Contractor must protect existing utilities, improvements, landscaping, irrigation systems, and vegetation in place. If damaged during the work, Contractor is responsible to repair or replace any utilities, improvements, landscaping, irrigation systems, and vegetation at his expense.
Bid Item No. 1 - Payment for Mobilization (Project No. 6096) shall be at the contract unit price per Lump Sum and shall include full compensation for conforming to the requirements of Section 9-3.4.1, “Mobilization and Preparatory Work,” in these Supplemental Provisions, as specified in the Standard Specifications, and as directed by the Engineer. No additional c ompensation shall be allowed.
Bid Item No. 2 - Payment for Mobilization (Project No. 6104) shall be at the contract unit price per Lump Sum and shall include full compensation for conforming to the requirements of Section 9-3.4.1, “Mobilization and Preparatory Work,” in these Supplemental Provisions, as specified in the Standard Specifications, and as directed by the Engineer. No additional compensation shall be allowed.
Bid Item No. 3 - Payment for Traffic Control (Project No. 6096) shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Part 6, “Temporary Traffic Control,” including development of the project traffic control plan, flagmen, warning signs, changeable message signs, temporary items, maintenance, repair, replacement, removals, all other appurtenances, as shown on the Plans, as specified in the Standard Specifications, these Supplemental Provisions, and as directed by the Engineer. No additional compensation shall be allowed.
Bid Item No. 4 - Payment for Traffic Control (Project No. 6104) shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Part 6, “Temporary Traffic Control,” including development of the project traffic control plan, flagmen, warning signs, changeable message signs, temporary items, maintenance, repair, replacement, removals, all other appurtenances, as shown on the Plans, as specified in the Standard Specifications, these Supplemental Provisions, and as directed by the Eng ineer. No additional compensation shall be allowed.
Bid Item No. 5 - Payment for Type II Slurry Seal (Project No. 6096) shall be at the contract unit price per Square Foot and shall be considered full compensation for furnishing all labor, tools, equipment, and shall include water, asphalt emulsion, aggregate, sweeping and vacuuming, cleaning, crack sealing, hauling, and incidentals to accomplish the work as specified herein and as indicated on the Plans and no additional compensation shall be allowed.
Revised 6/15/17 Project No. 6096/6104 Page 108 of 129
Bid Item No. 6 - Payment for Signing and Striping (Project No. 6096) shall be at the contract price per Lump Sum and shall include full compensation for installing of Traffic Striping, Legends, Markings, and Raised Pavement Markers shall be made at the contract lump sum price and shall include full compensation fo r all paint and thermoplastic pavement markings, green bike traffic paint and raised pavement markers, removals and furnishing all labor, materials, tools, equipment and incidentals to accomplish all the work as specified herein and no additional compensation will be allowed therefor.
Bid Item No. 7 - Payment for Signing and Striping (Project No. 6104) shall be at the contract price per Lump Sum and shall include full compensation for installing of Traffic Striping, Legends, Markings, and Raised Pavement Markers shall be made at the contract lump sum price and shall include full compensation for all paint and thermoplastic pavement markings, green bike traffic paint and raised pavement markers, removals and furnishing all labor, materials, tools, equipment and incidentals to accomplish all the work as specified herein and no additional compensation will be allowed therefor.
Revised 6/15/17 Project No. 6096/6104 Page 109 of 129
SUPPLEMENTAL PROVISIONS
All the Work to be done under this contract shall be in accordance with these Supplemental Provisions and the 2018 Edition of the “GREENBOOK” Standard Specifications for Public Works Construction, including all supplements, as written and promulgated by Pu blic Works Standards, Inc., unless otherwise noted.
Copies of the Standard Specifications are available from the publisher:
BNi Building News
Division of BNi Publications, Inc.
990 Park Center Drive, Suite E
Vista, California 92081
(760) 734-1113 or (888) BNI-BOOK (264-2665)
The Standard Specifications set forth above, referred hereinafter as Standard Specifications, will control the supplemental provisions, construction materials, and construction methods for this contract except as amended by the Plans, Supplemental Provisions, or other contract documents provided herein.
The section numbers of these Supplemental Provisions coincide with those of the said Standard Specifications. Only those sections requiring amendment, elaboration, or specifying options, are called out. In the event of a conflict between the section number and the section title, the section title shall govern.
Revised 6/15/17 Project No. 6096/6104 Page 110 of 129
SUPPLEMENTAL PROVISIONS
TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 2 - CONSTRUCTION MATERIALS
SECTION 203 – BITUMINOUS MATERIALS
203-3 EMULSIFIED ASPHALT.
203-3.1 General.
Add the following section:
Tack Coat shall be SS-1h type.
203-5 SLURRY SEAL.
203-5.1 General.
Add the following section:
When slurry seal is specified or indicated on the plans without further qualification, the Contractor shall supply Type 2 quick set emulsion (Type II-CQS-1h-EAS) with 2.5% latex added.
SECTION 206 - MISCELLANEOUS METAL ITEMS
Add the following section:
206-7 TRAFFIC SIGNS.
206-7.1 Roadside Signs. This work shall consist of furnishing and installing roadside signs in accordance with details shown on the plans, the California Sign Specifications and these special provisions. Permanent and temp orary signs shall be free from blemishes that may affect the serviceability and detract from the general sign color and appearance when viewing during daytime and nighttime from a distance of 25 feet. The face of each finished sign shall be uniform, flat, smooth, and free of defects, scratches, wrinkles, gel, hard spots, streaks, extrusion marks, and air bubbles. The front, back and edges of the sign panels shall be free of router chatter marks, burns, sharp edges, loose rivets, delaminated skins, excessi ve adhesive overspray, and aluminum marks.
206-7.1.2 Sign Identification. The following notation shall be placed on the lower right side of the back of each sign where the notation shall not be blocked by the sign post or frame:
A. PROPERTY OF THE CITY OF CARLSBAD,
B. Name of the sign manufacturer,
C. Month and year of fabrication,
D. Type of retroreflective sheeting, and
Revised 6/15/17 Project No. 6096/6104 Page 111 of 129
E. Manufacturer’s identification and lot number of retroreflective sheeting.
The above notation shall be applied directly to the aluminum sign pane ls in 1/4-inch upper case letters and numerals by die -stamp and applied by similar method to the fiberglass reinforced plastic signs. Painting, screening, or engraving of the notation will not be allowed. The notation shall be applied without damaging the finish of the sign.
206-7.1.3 Drawings. Standard signs shall be as per the most recently approved California Sign Specifications. The date of approval shall be the date most closely preceding the date of manufacture of the sign(s) or the date of the “Notice to Proceed” of this contract, whichever is most recent.
206-7.1.4 Reflective Sheeting. All advisory signs, warning signs and all regulatory signs shall be fabricated with Type IV prismatic sheeting (High Intensity Prismatic or equivalent) or Type IX prismatic cube lens sheeting (Diamond Grade VIP or equivalent) in accordance to ASTM Designation D4956 and conforming to the requirements of these special provisions.
206-7.1.5 Sign Panel. Sign panels shall be fabricated from sheet aluminum in accorda nce with ASTM Designation B209. Sheet aluminum shall be pretreated in accordance to ASTM Designation B449. The surface of sheet aluminum shall be cleaned, deoxidized, and coated with a light and tightly adherent chromate conversion coating free of powdery residue. The conversion coating shall be Class 2 with a mass between 10 milligrams per square foot. Following the cleaning and coating process, the sheet aluminum shall be protected from exposure to grease, oils, dust, and contaminants. Sheet aluminum shall be free of buckles, warps, dents, cockles, burrs, and defects resulting from fabrication.
206-7.1.6 Mounting Traffic Signs. Traffic signs shall be mounted using a standard City of Carlsbad approved mounting bracket with straps and per manufacturer recommendation.
For traffic signs mounted on non -Type 15-FBS poles, traffic signs shall be installed on 10 -gage or 12-gage cold-rolled steel perforated tubing posts as shown on San Diego Regional Standard Drawing M-45 or, when the sign area exceeds the maximum area allowed for on that drawing, on multiple 10-gage or 12-gage cold-rolled steel perforated tubing posts. The number of posts shall be determined by the parameters in SDRS drawing M-45 or as approved by the Engineer. Traffic signs will be provided with back braces and mounting blocks as approved by the Engineer consisting of 10-gage or 12-gage cold-rolled steel perforated tubing when multiple posts are used.
206-7.1.6 Traffic Sign Posts. San Diego Regional Standard Drawing M -45 posts shall be constructed of 10 -gage or 12 -gage cold-rolled steel perforated tubing posts as shown on San Diego Regional Standard drawing M-45.
206-7.2 Temporary Traffic Signs. Temporary traffic signs shall consist of all signs used for the direction, warning, and regulation of vehicle (including bicycle) and pedestrian traffic during the Contractor’s performance of the Work. Temporary traffi c signs include both stationary and portable signs.
206-7.2.1 General. This work shall consist of furnishing and installing temporary signs in accordance with details shown on the plans, the California Sign Specifications and these special provisions. Permanent and temporary signs shall be free from blemishes that may affect the serviceability and detract from the general sign color and appearance when viewing during daytime and nighttime from a distance of 25 feet. The face of each finished sign shall be uniform,
Revised 6/15/17 Project No. 6096/6104 Page 112 of 129
flat, smooth, and free of defects, scratches, wrinkles, gel, hard spots, streaks, extrusion marks, and air bubbles. The front, back and edges of the sign panels shall be free of router chatter marks, burns, sharp edges, loose rivets, delaminate d skins, excessive adhesive overspray, and aluminum marks.
206-7.2.2 Drawings. Standard signs shall be as per the most recently approved California Sign Specifications. The date of approval shall be the date most closely preceding the date of manufacture of the sign(s) or the date of the “Notice to Proceed” of this contract, whichever is most recent.
206-7.2.3 Reflective Sheeting. All advisory signs, warning signs and all regulatory signs shall be fabricated with Type IV prismatic sheeting (High Intensity Prismatic or equivalent) or Type IX prismatic cube lens sheeting (Diamond Grade VIP or equivalent) in accordance to ASTM Designation D4956 and conforming to the requirements of these special provisions.
206-7.2.4 Sign Panel. Sign panels shall be fabricated from sheet aluminum in accordance with ASTM Designation B209. Sheet aluminum shall be pretreated in accordance to ASTM Designation B449. The surface of sheet aluminum shall be cleaned, deoxidized, and coated with a light and tightly adherent chromate conversion coating free of powdery residue. The conversion coating shall be Class 2 with a mass between 10 milligrams per square foot. Following the cleaning and coating process, the sheet aluminum shall be protected from exposure to grease, oils, dust, and contaminants. Sheet aluminum shall be free of buckles, warps, dents, cockles, burrs, and defects resulting from fabrication.
206-7.2.5 Stationary Mounted Temporary Traffic Signs. Stationary mounted temporary traffic signs shall be installed on 10 -gage and 12-gage cold-rolled steel perforated tubing posts in the same manner shown on the State of California, Department of Transportation Sta ndard Plans RS1, RS2, RS3 and RS4 for installation of roadside signs, except as follows:
1. Wood posts shall not be used.
2. Back braces and blocks for sign panels will not be required.
3. The height to the bottom of the sign panel above the edge of traveled way shall be at least
2.1 m (7’).
4. Unless otherwise shown on the plans traffic sign posts shall conform in materials and installation to SDRS drawing M -45 and shall have one post provided for each 0.48 m 2 (5 ft2) of sign area, or the signs may be installed on ex isting lighting standards when approved by the Engineer.
5. Sign panels mounted on temporary traffic sign posts shall conform to the requirements of these special provisions.
206-7.2.6 Temporary Traffic Sign Posts. Posts shall be 10 -gage or 12 -gage cold-rolled steel perforated tubing used for the support and stabilization of stationary mounted temporary signs.
Post size and number of posts shall be as shown on the plans, ex cept that when stationary mounted signs are installed and the type of sign installation is not shown on the plans, post size and the number of posts will be determined by the Engineer. Sign panels for stationary mounted signs shall consist of reflective sheeting applied to a sign substrate.
206-7.2.7 Portable Temporary Traffic Signs. Each portable temporary traffic sign shall consist of a base, standard or framework and a sign panel. The units shall be capable of being delivered to the site of use and placed in immediate operation. Sign panels for portable signs shall conform to the requirements of these special provisions, or shall be cotton drill fabric, flexible industrial
Revised 6/15/17 Project No. 6096/6104 Page 113 of 129
nylon fabric, or other approved fabric. Fabric signs shall not be used during the hours of darkness.
Size, color, and legend requirements for p ortable signs shall be as described for station ary mounted sign panels in section 206 -7.2 of these special provisions. The height to the bottom of the sign panel above the edge of traveled way shall be at least 0.3 -m (12”). All parts of the sign standard or framework shall be finished with 2 applications of orange enamel which will match the color of the sign panel background. Testing of paint will not be required.
Add the following section:
206-8 LIGHT GAGE STEEL TUBING AND CONNECTORS.
Add the following section:
206-8.1 General. This Section pertains to 10-gage and 12-gage cold-rolled steel perforated tubing used for the support and stabilization of signs. All shapes shall have a galvanized finish and shall be cold -roll-formed steel conforming to ASTM Designation A -446, Grade A. Galvanizing shall conform to ASTM A-525, Designation G-90. Galvanizing shall be performed after all forming and punching operations have been completed. Cold-rolled steel perforated tubing shall be perforated on all four faces with 11mm (7/16”) holes on 25 mm (1”) centers.
Add the following section:
206-8.2 Tolerances. Wall thickness tolerance shall not exceed +0.28 mm, -0.13 mm (+0.011”, -0.005”). Convexity and concavity measured in the center of the flat side shall not exceed a tolerance of +0.25 mm (+0.010”) applied to the specific size determined at the corner.
Straightness tolerance variation shall not exceed 1.6 mm in 1 m (1/16” in 3’). Tolerance for corner radius is 4.0mm (5/32”), plus or minus 0.40 mm (1/64“). Weld flash on corner -welded square tubing shall permit 3.60 mm (9/64”) radius gage to be placed in the corner. Using 10 -gage or 12-gage square tube, consecutive size tubes shall telescope freely for 3.1m (10’). Tolerance on hole size is plus or minus 0.40 mm (1/64“) on a size. Tolerance on hole spacing is plus or minus
3.2 mm in 6.1 m (1/8” in 20’). In addition, for the following specific sizes of light gage steel tubing, dimensional tolerances shall not exceed those listed in tables 206-8.2 (A) and 206-8.2(B).
TABLE 206-8.2(A)
LIGHT GAGE STEEL TUBING SIZE TOLERANCE
Nominal Outside
mm
Dimensions
(inches)
Outside Tolerance for
mm
All Sides at Corners
(inches)
25 x 25 (1 x 1) 0.13 0.005
32 x 32 (11/4 x 11/4) 0.15 0.006
38 x 38 (11/2 x 11/2) 0.15 0.006
44 x 44 (13/4 x 13/4) 0.20 0.008
51 x 51 (2 x 2) 0.20 0.008
56 x 56 (23/16 x 23/16) 0.25 0.010
57 x 57 (21/4 x 21/4) 0.25 0.010
64 x 64 (21/2 x 21/2) 0.25 0.010
51 x 76 (2 x 3) 0.25 0.010
Revised 6/15/17 Project No. 6096/6104 Page 114 of 129
TABLE 206-8.2(B)
LIGHT GAGE STEEL TUBING SQUARENESS OF SIDES AND TWIST
Nominal Outside
mm
Dimension
(Inches)
Squar
mm
eness(1)
(Inches)
Twist Permissible
mm(2)
in 900 mm (3”)
(Inches)(2)
25 x 25 (1 x 1) 0.15 0.006 1.3 0.050
32 x 32 (1-1/4 x 1-1/4) 0.18 0.007 1.3 0.050
38 x 38 (1-1/2 x 1-1/2) 0.20 0.009 1.3 0.050
44 x 44 (1-3/4 x 1-3/4) 0.25 0.010 1.6 0.062
51 x 51 (2 x 2) 0.30 0.012 1.6 0.062
56 x 56 (2-3/16 x 2-3/16) 0.36 0.014 1.6 0.062
57 x 57 (2-1/4 x 2-1/4) 0.36 1.014 1.6 0.062
64 x 64 (2-1/2 x 2-1/2) 0.38 0.015 1.9 0.075
51 x 76 (2 x 3) 0.46 0.018 1.9 0.075
(1) Tubing may have its sides failing to be 90 degrees to each other by the tolerance listed. (2) Twist is measured by holding down the edge of one end of a square tube on a surface plate with the bottom side of the tube parallel to the surface plate and noting the height that either corner on the opposite end of the bottom side is above the surface plate.
Add the following section:
206-8.3 Fasteners. Fasteners used to assemble cold-rolled steel perforated tubing shall be steel “pull-through” electrogalvanized rivets with 9.5 mm (3/8”) diameter shank, 22 mm (7/8”) diameter head, and a grip range of from 5 mm (0.200”) to 0.90 mm (0.356”). The fasteners shall conform to ASTM B-633, Type III.
Add the following section:
206-9 PORTABLE CHANGEABLE MESSAGE SIGN.
206-9.1 General. Each portable changeable message sign (PCMS) unit shall consist of a controller unit, a power suppl y, and a structural support system all mounted on a trailer.
The PCMS unit shall be assembled to form a complete self -contained portable changeable message sign, which can be delivered to the site of the work and placed in immediate operation.
The complete PCMS unit shall be capable of operating in an ambient air temperature range of - 20ºC ( -4ºF) to +70ºC (158ºF) and shall not be affected by unauthorized mobile radio transmissions.
The trailer shall be equipped so that it can be leveled and plumbed. Full operation height shall be with the bottom of the sign at least 2.1 m (7') above the ground and the top no more than 4.4 m (14.5') above the ground. After initial placement, PCMS shall be moved from location to location as directed by the Engineer.
As part of the bid item "Traffic Control," at least one PCMS shall be required in each direction of travel affected by the work. Traffic control plans shall clearly show the PCMS' location. The PCMS shall warn motorists of the work one (1) week prior to start of work and for the entire duration of work.
Add the following section:
206-9.2 Message Board. The message displayed on the PCMS shall be visible from a distance of 460 m (1500') and shall be legible from a distance of 230 m (750'), at noon on a cloudless day, by persons with vision corrected to 20/20. The sign panel shall be 3-line matrix and shall display not less than 7 characters per line. Sign messages to be displayed shall be as approved by the
Revised 6/15/17 Project No. 6096/6104 Page 115 of 129
Engineer. The sign face shall be flat black and shall be protected from glare of the sun by a method which does not interfere with the clarity of the sign message. The sign shall be raised and lowered by means of a power driven lifting mechanism. The matrix sign shall be capable of complete alphanumeric selection.
Lamp matrix type signs shall be equipped with an automatic dimming operational mode tha t automatically compensates for the influence of a temporary light source or other abnormal lighting conditions. The sign shall have manual dimming operation modes of 3 or more different lamp intensities.
Matrix signs not utilizing lamps shall be either internally or externally illuminated at night.
The controller shall be an all solid-state unit containing all the necessary circuitry for the storage of at least 5 pre -programmed messages. The controller shall be installed in a location allowing the operator to perform all functions from one position. A keyboard entry system shall be provided to allow an operator to generate an infinite number of additional messages over the pre - programmed stored messages. The keyboard shall be equipped with a security lockout feature to prevent unauthorized use of the controller. The controller shall contain a nonvolatile memory to hold the keyboard created messages in memory during periods when the power is not activated.
The controller shall provide for a variable message display rate which allows the operator to match the information display to the speed of the approaching traffic. The flashing off time shall be operator adjustable within the control cabinet.
Add the following section:
206-9.3 Operation and Maint enance. PCMS shall be furnished, placed, operated, and maintained at locations shown designated by the Engineer. The PCMS will be diligently maintained and repaired by the Contractor throughout the project in accordance with the manufacturer's recommendations.
Add the following section:
206-9.4 Measurement and Payment. PCMS are a part of the lump -sum item for traffic control and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved in furnishing, placing, operating, maintaining, repairing, replacing, transporting from location to location, and removing signs at the completion of the construction, and as directed by the Engineer, and no other compensation will be made.
SECTION 210 - PAINT AND PROTECTIVE COATINGS
210-1 PAINT.
210-1.6 Paint for Traffic Striping, Pavement Marking, and Curb Marking. Modify as follows:
Paint for traffic lane lines, turn pocket lines, edge lines, channelizing lines, bike lane lines, chevrons, and curbs shall be rapid dry water borne con forming to CALTRANS Specification No.
PTWB-01. Pavement legends, pavement symbols, pavement arrows, cross walks, parking stall markings and stop bars shall be alkyd thermoplastic conforming to CALTRANS Specification No. 8010-19A. Glass beads shall be applied to the surface of the rapid dry water borne paint and the molten thermoplastic material and shall conform to the requirements of CALTRANS Specification No. 8010-004 (Type II). CALTRANS Specifications for water borne paint, thermoplastic material
Revised 6/15/17 Project No. 6096/6104 Page 116 of 129
and glass beads may be obtained from the CALTRANS Transportation Laboratory, P.O. Box 19128, Sacramento, CA 95819, telephone number (916) 227-7000.
SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT
MARKINGS
214-1 GENERAL.
The following Sections of the Caltrans Standard Specifications, and California Manual on Uniform Traffic Control Devices latest editions, shall be used for all work specified in these sections:
Section 84: Existing Facilities: Traffic Striping Removals Section 84: Markings: Thermoplastic & Paint
Section 81: Miscellaneous Traffic Control Devices: Pavement Markers
All pavement striping and markings shall be reflective with glass beads and conform to requirements of the South Coast Air Quality Management District.
214-4 PAINT FOR TRAFFIC STRIPING AND MARKINGS.
214-4.1 General.
Add the following:
The installing of striping shall conform to the general provisions in Section 84, “Markings” of the Caltrans Standard Specifications and the Caltrans Standard Plans (Latest Edition), and the following Technical Provisions.
All linear striping, bike lane delineation, bike lane symbols and letters, and curb markings shall be waterborne paint conforming to Section 84 -2.02C, “Paint,” of the State of California Standard Specifications.
Green bike traffic paint to be EF Series WB GRN Fast Dry 1952F ½, Product Code 183, Product Color Green (34108) By Ennis-Flint or approved equal. Paint to meet Federal Spec TT-P-1952F Type I & II with retroreflective glass beads.
214-5 THERMOPLASTIC MATERIAL FOR TRAFFIC STRIPING AND MARKINGS.
214-5.1 General.
Delete entire section and replace with the following:
The installing of striping shall conform to the general provisions in Section 84, “Markings” of the Caltrans Standard Specifications an d the Caltrans Standard Plans (Latest Edition), and the following Technical Provisions.
All pavement symbols and legends, cross walks, and stop bars, with exception to the bike lane markings, shall be Thermoplastic conforming to Section 84-2.02B, “Thermoplastic,” of the State of California Standard Specifications.
Revised 6/15/17 Project No. 6096/6104 Page 117 of 129
214-6 PAVEMENT MARKERS.
Markers shall conform to Section 81 -3, “Pavement Markers,” of the Caltrans Standard Specifications, latest edition.
214-7 ADHESIVES FOR PAVEMENT MARKERS.
214-7.1 General.
Markers shall be applied using rapid-set epoxy conforming to Section 95-1.02E, “Rapid Set Epoxy Adhesive for Pavement Markers,” of the Caltrans Standard Specifications, latest edition.
Add the following section:
SECTION 215 – SIGNAGE
The following Sections of the Caltrans Standard Specifications, and California Manual on Uniform Traffic Control Devices latest editions, shall be used for all work specified in these sections:
Section 82: Signs and Markers
215-1 TRAFFIC SIGNS.
New traffic sign materials including color, size, reflectivity, symbols and lettering shall conform to the latest CAMUTCD and latest Caltrans Sign Specification Sheets.
The following Sections of the Caltrans Standard Specifications, and California Manual on Uniform Traffic Control Devices latest editions, shall be used for all work specified in these sections:
Section 82: Signs and Markers
215-2 TRAFFIC SIGN POST.
All signs shall be installed on metal sign posts, unless wood posts are specified.
Revised 6/15/17 Project No. 6096/6104 Page 118 of 129
SUPPLEMENTAL PROVISIONS
TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 3 - CONSTRUCTION METHODS
SECTION 300 - EARTHWORK
300-1 CLEARING AND GRUBBING.
300-1.1 General. Add the following to the third paragraph: During surface clearing operations, the Contractor shall not cover or bury any plant growth or other objectionable materials. If the Contractor cannot successfully separate the plant growth from the surface soil and advertently or inadvertently mixes organic or other objectionable materials with the soil, the soil so contaminated shall be removed from the site by the Contractor. All costs, if any, associated with removing the soil mixed with organic or other object ionable materials and importing soil to replace said contaminated soil shall be borne by the Contractor and no additional payment therefore shall be made to the Contractor.
Existing trash, construction debris, abandoned structures and other deleterious ma terial are included in this item.
Areas to be cleared shall be grubbed to a depth necessary to remove stumps, roots, buried logs and other objectionable material.
All areas used by the Contractor as temporary right -of-way and staging areas shall not be contaminated with fuels, chemicals, lime or other soil stabilization treatments.
The Contractor shall notify the Engineer, in accordance with Subsection 3 -4, “Changed Conditions,” of the Standard Specifications, of any changed conditions or material diff ering from that represented in the Contract which the Contractor believes to be hazardous waste.
All stockpiling of cleared and grubbed material designated by the Contractor for final removal shall be considered incidental to this paid item and no additio nal compensation shall be allowed therefor.
All combustible waste materials resulting from clearing and grubbing from any construction operations of this Contract shall be removed from the site to an acceptable disposal area in accordance with Subsection 300-1.3, “Removal and Disposal of Materials,” of the Standard Specifications.
Clearing and Grubbing shall be limited to the areas within items to be constructed. All other vegetation outside clear and grub areas shall be protected in place from damage resulting from the Contractor’s operation. Any item outside the construction limits that is damaged or destroyed by the Contractor shall be replaced or restored to its original condition prior to acceptance of the improvements or the Contractor shall compensate the City for its replacement.
Revised 6/15/17 Project No. 6096/6104 Page 119 of 129
The Contractor shall protect all existing structures or facilities which are adjacent to or fall within the limits of the work to be done under this Contract in accordance with Subsection 7 -9, “Protection and R estoration of Existing Improvements,” of the Standard Specifications. Any structure or facility to be protected which is damaged as a result of the Contractor’s construction operation, shall be replaced by the Contractor, at their cost, to the satisfaction of the Engineer.
Removal/Adjustments/Relocations of items shall be in conformance with respective owner/agency (City/Utility Company) standards and specifications.
300-1.2 Preservation of Property.
Replace Subsection with the following:
Existing improvements, adjacent property, utility and other facilities, trees and plants that are not to be removed, and all items shown on the approved plans to be protected in place or stated in the City’s Supplemental Provisions or Conditions to be protected in place, shall be protected from injury or damage as provided in accordance with Section 7 -9, “Protection and Restoration of Existing Improvements,” regardless of whether or not these items are found within the construction limits. If an item to be protected in place is found within the construction limits, the Contractor shall grade around the item to be protected in place as required.
Any structure or facility to be protected which is damaged as a result of the Contractor’s construction operation, shall be replaced by the Contractor, at their cost, to the satisfaction of the Engineer.
300-1.3 Removal and Disposal of Materials.
300-1.3.1 General.
Replace the entire subsection with the following:
Unless otherwise stated on the Plans or Specifications, all material removed from the Work shall become the property of the Contractor and shall be disposed of in a lawful manner. Burning shall not be permitted on the site.
Add the following new subsections:
300-1.3.2 Requirements.
Add the following section to subparagraphs (a):
Existing concrete and miscellaneous removals shall be immediately removed from the project site and disposed of by the Contractor at his own expense at a legal dump and/or recycling site.
All materials removed shall be lawfully disposed of at a site secured by the Contractor. The Contractor shall make effort to recycle concrete, steel, and other excavated materials. The Contractor shall provide the Engineer with a letter indicating the final disposition of all excavated and demolition materials from the project within (5) working days after project completion. No excavated or demolition materials shall be left in the public right of way overnight.
Add the following subparagraphs after c):
d) Miscellaneous Removals and Relocations. The work under this item shall include all removals and relocations not specifically listed in the Plans or otherwise covered by these Specifications, including all necessary removals, rel ocations, and restorations of walls,
Revised 6/15/17 Project No. 6096/6104 Page 120 of 129
plants, hardscape, signs and other items, whether shown on the Plans or not, and as necessary to complete the improvements.
300-1.4 Payment
Replace the first paragraph with the following:
Full compensation for conforming to the requirements of Clearing and Grubbing , including all labor, tools, equipment, materials and incidentals necessary for accomplishing the work complete and in place, including haul permits, fees, removal, haul away, an d disposal of materials, including, but not limited to, trash vegetation and deleterious debris removal and disposal, and shall be considered as included in the various proposed improvements and no additional compensation shall be allowed therefore.
All stockpiling of cleared and grubbed material designated by the Contractor for final removal shall be considered incidental other items of work and no additional compensation shall be allowed.
Reinforcing or other steel may be encountered in portions of existing concrete items to be removed. No additional compensation shall be allowed for the removal of concrete containing reinforcing or other steel.
No additional payment for restoration of adjacent trees, roots, grass, and parkway, to remain -in- place, but damaged by the Contractor during construction, shall be made.
Replace the second paragraph with the following:
Clearing and Grubbing and Removals are included in other items of work:
1. Remove and Relocate Sign and Post - Payment for Relocate Existing Road Side Sign (One Post) shall be considered included in Signing and Striping and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in Remove Sign and P ost, Salvaging, and relocating to proposed location, complete in place, including, but not limited to, removal and disposal of concrete foundations, and salvaging post, mounting hardware, and all sign panels on post, exaction, pouring new concrete foundation, and relocating existing sign and post, as shown on the Plans, as specified in the Standard Specifications, these Technical Provisions, and as directed by the Engineer.
2. Miscellaneous Removals and Relocations - Payment for Miscellaneous Removals and Relocations shall be considered included in Mobilization, and shall include all labor, tools, equipment, materials and incidentals necessary for accomplishing the work complete and in place, including haul permits, fees, removal, haul away, and disposal of materials.
300-4 UNCLASSIFIED FILL
300-4.2 Preparation of Fill Areas. Add the following: Except as provided in section 300 -4.7, “Compaction”, areas proposed for improvements all fill (including backfill) shall be compacted by the Contractor to no less than 90 percent of maximum dry density as determined in accordance with ASTM Test Procedure D1557-91.
300-4.5 Placing Materials for Fills. Add the following: The Contractor shall perform backfill composed of properly compacted low expansive soils. Low expansive soils are defined as those soils that have an Expansion Index of 50 or less when tested in accordance with 1994 UBC
Revised 6/15/17 Project No. 6096/6104 Page 121 of 129
Standard 18 -2 as published by the International Conference of Building Officials. Should insufficient soils meeting t he requirement of an expansion index of 50 or less be present within the limits of work, soils of the least expansion index that are available within the limits of work.
The Contractor shall break rock encountered in the excavation into particles of less than 75 mm (3”). Particles with dimensions greater than 75 mm (3”) shall be uniformly distributed over the area to be filled so that construction equipment can be operated in such a manner that the larger pieces will be broken into smaller particles and become incorporated with the other materials in the layer.
This requirement for particle size reduction does not apply to cobbles, small boulders, and small hard rocks found within the surface soils and formational materials. Rocks having any dimension greater than 460mm (18”) shall not be incorporated into the fill. Rock exceeding 150 mm (6”) in diameter shall not be placed in any fill. Oversize material which cannot be utilized for landscaping onsite shall be broken to acceptable sizes or removed from the site by the Contractor. If disposed of within the City of Carlsbad, a separate grading permit will be required for disposal of rock.
300-4.6 Application of Water. Add the following: The Contractor shall place all fill soil at a moisture content no less than one (1) percent below optimum moisture as determined by ASTM test D-1557-91.
300-4.7 Compaction. Add the following: The Contractor shall compact all fill soils placed within the top 1 m (3’) of roadway subgrade to a minimum of 95 percent relative compaction. On all areas to receive planting, the top 150 mm (6”) shall be compacted to 85%, +2% -5%, to allow for plant growth.
300-4.9 Measurement and Payment. Delete and substitute the following: Unclassified fill, grading, shaping, compacting or consolidating, backfilling, construction of transitions and all work included in and incidental to Section 300-4, “Unclassified Fill” will be paid for in the other various items of work being removed or installed, and no additional payment will be made therefore.
SECTION 302 – ROADWAY SURFACING
302-4 SLURRY SEAL SURFACING.
302-4.6 Emulsion-Aggregate Slurry (EAS).
302-4.6.1 General.
Add the following:
The Contractor shall be responsible for tree trimming along the curb line as noted in Section 300- 1 Clearing and Grubbing – so as to provide a clear travel way during the construction of the roadway resurfacing.
The Contractor shall treat all vegetation within the limits of the paved area to be surfaced with a post emergent herbicide. Herbicide shall be applied at least 2 (two) working days prior to surfacing the street. Allowance for the two day period shall be shown in the schedule required per Section 6-1.
The road to be slurry sealed shall be swept clean of debris and dust no more than 30 minutes prior to application of the slurry seal. However, this 30 -minute window may be extended if authorized by the Engineer in cases where extending the time does not jeopardize a clean surface
Revised 6/15/17 Project No. 6096/6104 Page 122 of 129
prior to slurry seal operations. The pavement shall be swept with a motorized broom to remove loose material. Depressions not reached by the motorized broom shall be cleaned with a hand broom. The outer edges of the pavement to be sealed including an adjacent paved shoulder shall be cleaned. No washing of any residue into gutters and/or drainage structure shall be allowed.
Before applying and during the application of slurry seals, drainage inlets, manholes, valve and monument covers, grates, and other exposed facilities located within the area of application shall be covered using plastic or oil resistant construction paper secured by tape or adhesive to the facility being covered. The covered facilities shall be referenced with enough control points to relocate the facilities after application of the slurry seals.
Cracks shall be cleaned of loose and extraneous materials, routed, blown with high-pressure air to remove loose materials, surface cleaned, sealed, and fully coated with tack prior to slurry seal. Crack sealing shall be in accordance with Section 37 -6, “Crack Treatment,” of the Caltrans Standard Specifications (2018).
302-4.6.3 Application and Site Condition.
Delete the first paragraph and replace with the following:
Slurry seal shall only be placed if existing pavement surface is dry and both the pavement and ambient temperatures are at least 50°F and rising within 24 hours after placement. Application of the slurry seal shall be only during daylight hours and be completed at least 2 hours before sunset unless otherwise approved by the Engineer.
When precipitation is forecasted during the application and curing period slurry seal activities shall not be started. Slurry seal shall not be placed within 24 hours of rain or within 24 hours of forecast rain or freezing temperatures.
If a condition is identified that causes an unsatisfactory slurry seal, all production and application work shall be stopped, and corrective action shall be immediately performed at no additional cost to the contract. If there are adverse environmental conditions, the Engineer shall be provided with an action plan that clea rly demonstrates how the slurry seal operation will be adjusted for the actual environmental conditions.
Slurry seal shall be allowed to cure undisturbed for at least 2 hours. Slurry sealed streets shall be protected from damage until it has set and will not adhere or be picked up by vehicle tires.
Add the following Section:
302-4.6.4 Maintenance.
The slurry sealed streets shall be swept 24 hours after placement without damaging the slurry seal. For 3 consecutive days afterwards, the streets received slurry seal shall be swept daily using a self-loading motor sweeper with spray nozzles unless determined otherwise by the Engineer.
One week later, the Contractor shall sweep the slurry sealed streets once per week for two weeks.
The Engineer has the authority to require more sweeping than specified herein. All sweeping costs shall be included in the Contractor’s bid.
The slurry seal must not show bleeding, raveling, separation, or other distresses for 15 days after placing. If bleeding, raveling, delaminating, rutting, or wash -boarding occurs after placing the slurry seal make repairs using an authorized method.
Revised 6/15/17 Project No. 6096/6104 Page 123 of 129
Add the following section:
302-4.6.5 Measurement and Payment.
Material which is delivered to the project site and not used or is rejected, and specifically material which is delivered to the site in excess of that actually needed, shall not be paid for. The Contractor shall provide weight tickets, which clearly indicate the quantity of material delivered.
Payment for Type II Slurry Seal shall be at the contract unit price per Square Foot and shall be considered full compensation for furnishing all labor, tools, equipment, and shall include water, asphalt emulsion, aggregate, sweeping and vacuuming, cleaning, crack sealing, hauling, and incidentals to accomplish the work as specified herein and as indicated on the Plan s and no additional compensation shall be allowed.
Add the following:
302-4.6.6 Public Convenience and Traffic Control.
The Contractor shall schedule the work so as to prevent damage by all traffic. The Contractor shall not schedule work so as to confl ict with trash pickup. The trash hauling schedule can be obtained by calling Coast Waste Management at (760) 929-9400. At least two weeks prior to work, Contractor shall send, by first class mail, notification letters to all property addresses within 500’ of the work. Obtaining the appropriate addresses shall be the contractor’s responsibility. Letters shall be as shown in bold type as follows, with the appropriate information specific to the work inserted at the locations indicated in the brackets and italicized.
SECTION 310 - PAINTING
310-5 PAINTING VARIOUS SURFACES.
310-5.6 Painting Traffic Striping, Pavement Markings and Curb Markings. Modify the fifth paragraph as follows: The Contractor shall furnish all equipment, materials, labor, and supervision necessary for painting traffic lanes, directional arrows, guidelin es, curbs, parking lines, crosswalks, and other designated markings in accordance with the Plans, or for approved temporary detours essential for safe control of traffic through and around the construction site.
The Contractor shall remove by wet grinding all existing or temporary traffic markings and lines that may confuse the public. When temporary detour striping or markings are no longer required, they shall be removed prior to painting the new traffic stripes or markings.
310-5.6.3 Equipment. Delete the ninth paragraph and substitute the following: The Contractor shall provide a wet grinding machine with sufficient capacity to completely remove all existing or temporary traffic striping or markings that conflict with the striping plan, or are contra ry to the Traffic Manual, or that may be confusing to the public. The surface produced by grinding the existing or temporary traffic striping or markings on pavement shall not exceed variations from a uniform plane more than 3 mm (1/8”) in 3 m (10’) when measured parallel to the centerline of the street or more than 6 mm (1/4”) in 3 m (10’) when measured perpendicular to the centerline of the street. The use of any equipment that leaves ridges, indentations or other objectionable marks in the pavement shall be discontinued, and equipment capable of providing acceptable surface shall be furnished by the Contractor. This equipment shall meet all requirements of the air pollution control district having jurisdiction.
Revised 6/15/17 Project No. 6096/6104 Page 124 of 129
310-5.6.6 Preparation of Existing S urfaces. Modify the first paragraph as follows: The Contractor shall remove all existing markings and striping, either permanent or temporary, which are to be abandoned, obliterated or that conflict with the plans by wet grinding methods. Removal of striping by high velocity water jet may be permitted when there is neither potential of the water and detritus from the high velocity water jetting to damage vehicles or private property nor to flow from the street into any storm drain or water course and when approved by the Engineer. The Contractor shall vacuum all water and detritus resulting from high velocity water jet striping removal from the pavement immediately after the water jetting and shall not allow such materials to flow in the gutter, enter the s torm drain system or to leave the pavement surface. Surface variation limitations for high velocity water jet striping removal shall be the same as for grinding.
The Contractor shall not use dry or wet sandblasting in any areas. Alternate methods of pain t removal require prior approval of the Engineer. Obliteration of traffic striping with black paint, light emulsion oil or any other masking method other than a minimum 30mm (0.10’) thick asphalt concrete overlay is not permitted.
310-5.6.7 Layout, Align ment, and Spotting. Modify the first paragraph as follows: The Contractor shall establish the necessary control points for all required pavement striping and markings by surveying methods. No layout of traffic striping shall be performed by the Contractor before establishment of the necessary control points. The Contractor shall establish all traffic striping between these points by string line or other method to provide striping that will vary less than 80mm per 100m (1/2 inch in 50 feet) from the specif ied alignment. The Contractor shall obliterate, straight stripes deviating more than 80mm per 100mm (1/ 2 inch in 50 feet) by wet grinding, and then correcting the markings. The Contractor shall lay out (cat track) immediately behind installation of surface course asphalt and as the work progresses.
310-5.6.8 Application of Paint. Modify the second paragraph as follows: The Contractor shall apply the first coat of paint immediately upon approval of striping layout by the Engineer. The Contractor shall paint the ends of each median nose yellow.
Add the following to the eighth paragraph: The Contractor shall apply temporary traffic stripes in one coat. Temporary traffic stripes shall be maintained by the Contractor so that the stripes are clearly visible both day and night.
310-5.6.10 Measurement and Payment. Modify the first paragraph as follows: Final and temporary traffic striping, curb markings and pavement markings as shown on the plans and required by the specifications shall be included in the Lump Sum price bid for Signing and Striping (per Project no. specified), and no additional compensation will be allowed therefor .
Reapplication of temporary stripes and markings shall be repainted at the Contractor's expense, and no additional compensation wi ll be allowed therefor . The lump sum prices bid and shall include all labor, tools, equipment, materials, and incidentals for doing all work in installing the final and temporary traffic striping.
Add the following Section:
310-7 PERMANENT SIGNING.
Add the following Section:
310-7.1 General. Add the following section: The Contractor shall provide and install all permanent traffic control signs at locations shown on plans and as specified herein.
Add the following section:
310-7.2 Measurement and Paymen t. Permanent signing, sign & post relocations, and
Revised 6/15/17 Project No. 6096/6104 Page 125 of 129
appurtenances thereto shown on the plans or required in the specifications are a part of the Lump Sum price bid for Signing and Striping (per Project no. specified), and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in supplying and installing permanent signing and appurtenances, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer.
SECTION 313 - TEMPORARY TRAFFIC CONTROL DEVICES
Add the following section:
313-1 TEMPORARY TRAFFIC PAVEMENT MARKERS.
Add the following section:
313-1.1 General. The Contractor shall supply and install temporary channelizers, signing, railing (type K), crash cushions and appurtenances at the locations shown on the plans and as required in the specifications, complete in place prior to opening the traveled way served by said final and temporary traffic pavement markers, signing, railing (type K) and appurtenances to public traffic.
Add the following section:
313-2 TEMPORARY TRAFFIC SIGNING.
Add the following section:
313-2.1 General . The Contractor shall provide and install all temporary traffic control signs, markers, markings, and delineators at locations shown on plans and specified herein.
Add the following section:
313-2.2 Maintenance of Temporary Traffic Signs. If temporary traffic signs are displa ced or overturned, from any cause, dur ing the progress of the work, the Contractor shall immediately replace the signs in their original approved locations. The Contractor shall maintain all temporary traffic signs used in the Work in a clean, reflective and readable condition. The Contractor shall replace or restore graffiti marked temporary traffic signs and posts used in the Work within 18 hours of such marking being discovered during non -working hours or, when the marking is discovered during working hours, within 2 hours of such discovery of marking.
Add the following section:
313-4 MEASUREMENT AND PAYMENT . Temporary channelizers, temporary signing, temporary railing (type K), temporary crash cushions and temporary appurtenances thereto shown on th e plans or required in the specifications are a part of the lump -sum item for traffic control and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved i n applying, installing, maintaining, and removing temporary channelizers, signing, railing (type K), crash cushions and appurtenances, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer. Payment for temporary crash cushions, concrete barriers and the signs and reflectors marking them shall include the installation, grading for installation, grading for the approach path, maintenance, painting and re-painting, replacement of damaged units and removal and shall also be included in the lump-sum price bid for traffic control. Payment for installation and/or relocation of K -rails and crash cushions when not shown on the plans and requested by the Engineer shall be made per section 3-3, Extra Work, SSPWC.
Revised 6/15/17 Project No. 6096/6104 Page 126 of 129
SECTION 315 –SIGNAGE
315-1 TRAFFIC SIGN INSTALLATION.
315-1.1 General.
This work consists of furnishing and installation of guide, regulatory, and warning signs at the locations shown on the Plans in accordance with the California Manual on Uniform Traffic Control Devices (CAMUTCD) (latest edition) , the provision in Section 82 -3, “Roadside Signs,” of the Caltrans Standard Specifications, the Specification in the Plans, and as directed by the Engineer.
All new and relocated signs shall be clearly visible, not blocked by any obstruction. The Contractor is responsible to trim or remove any vegetation blocking the new and relocated signs.
All existing roadside signs including street name signs (SNS) show n on plan, for the sole convenience and direction of public traffic, shall be protected in place and maintained by the Contractor. All signs damaged by construction activities whether or not shown on plan shall be repaired or replaced to the satisfaction of the Engineer.
Revised 6/15/17 Project No. 6096/6104 Page 127 of 129
SUPPLEMENTAL PROVISIONS
TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 6 – TEMPORARY TRAFFIC CONTROL
SECTION 600 – ACCESS
600-1 GENERAL.
Add the following section:
The Contractor shall be responsible for warning motorists, cyclists, and pedestrians entering areas where the Work is being performed of in hazardous or dangerous conditions resulting from work activities.
The Contractor shall not limit access unless approved by the Engineer or otherwise specified.
600-3.6 Public Convenience and Traffic Control modify the first line with the following: Public Convenience and traffic control shall conform to 302 -4.4.4. There shall be no stockpiling of material allowed on City right-of-way.
SECTION 601- WORK AREA TRAFFIC CONTROL
601-1 GENERAL.
Add the following section:
Temporary traffic control for construction and work zones shall conform to the Part 6 of the California MUTCD (latest edition), the Specifications, Plans, and any traffic control plans approved by the Engineer.
Traffic control shall only be performed during working hours as indicated in Section 6-15, unless otherwise approved on a traffic control plan or indicated by the Project Special Provisions.
If Work is to be done in phases, the Contractor shall complete all work associated with the current phase prior to moving on to the next. Phased Work shall be shown in a plan submitted to the Engineer within fifteen (15) working days after the Notice of Award has been issued to the Contractor. No work shall commence until this plan has been revie wed and approved by the Engineer.
Contractor shall remove or cover any conflicting signs.
Roadways adjacent to the Work site shall be kept clean and free of obstructions or other hazards.
Do not store or allow equipment, material, or debris to remain in public right-of-way without prior approval by the Engineer.
Revised 6/15/17 Project No. 6096/6104 Page 128 of 129
601-2 TRAFFIC CONTROL PLAN (TCP).
Delete section and replace with:
Traffic Control Plans will be submitted in accordance with Section 2-5.3 whenever the Contractor will suspend or alter the normal operations of a roadways, bicycle route, or pedestrian pathway in order to accomplish the Work. The Contractor shall provide a 20 -day review period for each submittal of TCPs.
The Contractor shall submit site specific traffic control plans. The traffic control plans shall be stamped by a registered Traffic Engineer or Civil Engineer.
Revised 6/15/17 Project No. 6096/6104 Page 129 of 129
APPENDIX “A”
CITY OF CARLSBAD
ROAD WORK
ABC CONTRACTORS
OFFICE # (760)XXX-XXXX
FIELD # (760)XXX-XXXX
Dear resident:
As a part of the City of Carlsbad’s ongoing
program to maintain its streets, your street will be
slurry sealed over the existing roadway surface.
This construction will require the closing of your
street to through traffic for one day. Your street,
from XYZ St. to DEF Ave. will be closed to
through traffic and resurfaced on:
MON. TUE. WED. THU. FRI.
DATE: _XX / XX / XX______________
from 7:00A.M. to 5:00 P.M.
If you don’t plan to leave your home by 7:00 A.M.
on the above date please park your car on an
adjacent street in your neighborhood that will not
be resurfaced. Streets scheduled for resurfacing
can be determined by calling either the
Contractor or the C ity of Carlsbad’s Project
Inspector. When walking to and from your car,
remember not to walk on the newly overlaid street
or you will have black residue on the bottom of
your shoes. Please do not drive, walk on, walk
pets, play, or skate on the newly overlaid asphalt.
Also, please refrain from watering your lawns,
washing cars, etc., approximately 6-8 hours after
the asphalt is laid as running water will cause
damage to the new surface.
ABC is the Contractor that will be performing the
resurfacing w ork for the city and you may call
them at the above phone number if you have any
questions regarding the project. Resurfacing of
your street will not occur on the day your trash is
collected. Mail delivery may be delayed if the
postman cannot reach the mailbox that day. If you
have a moving company scheduled for that day
please call and inform the Contractor of the date.
If you have any concerns which cannot be
addressed by the Contractor, you may call the
City’s Project Inspector @ (xxx) xxx-xxxx.
Thank you for your cooperation as we work to
make a better City of Carlsbad.
RECOMMENDED ACTION
Adopt one resolution:
• Approving the proposed lane reduction on southbound Carlsbad Blvd between Solamar Dr and Island Way
• Approving the plans and specifications and awarding a contract to VSS International, Inc., in the amount of $381,120 for construction of the Carlsbad Boulevard Restriping Project between Manzano Drive and Island Way; bike lane improvements at five locations on Carlsbad Boulevard; and three Sustainable Mobility Bike Enhancement Projects
ITEM 9
BACKGROUND
• Three Projects:
1. Carlsbad Blvd Restriping Project, CIP No. 6096
a) Restriping of Carlsbad Blvd from Manzano Dr and Island Way b) Bike lane improvements at five locations on Carlsbad Blvd south of Island Way
2. Green bike lane enhancements at five locations on Carlsbad Boulevard
3. Sustainable Mobility Plan projects in three locations, CIP No. 6104 • Projects combined into a single set of plans and specifications to maximize cost efficiency
ITEM 9
CARLSBAD BOULEVARD RESTRIPING PROJECT
ITEM 9
Manzano Dr
Legend
Project Limit
Proposed Lane Reduction
CARLSBAD BOULEVARD RESTRIPING PROJECT
ITEM 9
• Project will:
– Reduce number of travel lanes
from two to one lane
– Shift traffic to the east
– Add bike buffer to existing bike
lane for the entire segment
– Add shoulder between bike lane
and existing curb
– Add green bike lane
enhancements
Existing Conditions
• Carlsbad Blvd is classified as a Coastal Street in the General Plan Mobility Element therefore it is not subject to vehicular level of service standards
• Per General Plan Mobility Element Policy 3-P .15
“City Council shall have the sole discretion to approve any such road diet or vehicle traffic calming improvements that would reduce vehicle capacity to or below a LOS D…”
• Traffic operational analysis was performed to analyze roadway segment and traffic signal operations with the proposed lane reduction on southbound Carlsbad Blvd
ITEM 9
MOBILITY ELEMENT POLICIES
• Roadway Segment Analysis Results:
ITEM 9
LEVEL OF SERVICE ANALYSIS
Scenario Segment
Capacity*
Weekdays
AM Peak
Weekday
PM Peak
Weekend
Mid-day Peak
Existing two travel lanes 1,820 C C D
One travel lane with
2022 traffic level 910 D D E
One travel lane with
pre-pandemic traffic level 910 D F F
* Source: City of Carlsbad Segment Volume Table Report
• Traffic signal at Solamar Dr: LOS A under all scenarios • Traffic signal at Island Way: LOS B under all scenarios
LONG-TERM LANE CLOSURE ON SB CARLSBAD BLVD
ITEM 9
• No. 2 lane on southbound Carlsbad Blvd between
Solamar Dr and Island Way was closed for over a year
(Jan. 2016 through early 2017) to facilitate necessary
repairs needed after severe erosion near the Encinas
Creek Bridge
• Traffic impacts were observed to be minimal
• One southbound lane was found to provide adequate
capacity to carry the traffic volumes in 2016 which were higher
than current traffic volumes
BIKE LANE IMPROVEMENTS AT FIVE
INTERSECTIONS ON CARLSBAD BLVD
• Bike lane improvements at five intersections:
Lanikai Ln; Breakwater Rd; Poinsettia Ln; Ponto Rd; and Avenida Encinas
– Add green paint bike lane to highlight conflict areas – Add green bike lane adjacent to dedicated right turn lane ITEM 9
SUSTAINABLE MOBILITY PLAN PROJECTS
ITEM 9
• Three SMP bike enhancement CIP projects included as part of the design package
– La Costa Ave at intersections of Piraeus, Saxony and
El Camino Real
– Jefferson St between Las Flores Dr and I-5 Overpass
– Paseo Del Norte and Cannon Rd intersection
GREEN PAINT BIKE LANE ENHANCEMENTS
ITEM 9
TRAFFIC & MOBILITY COMMISSION
ITEM 9
• At its meeting on Sep. 6, the Traffic & Mobility Commission voted to support the design plans for the Carlsbad
Restriping Project.
AWARD OF CONTRACT
ITEM 9
• The projects were advertised on Sept. 13, 2022
• Staff received three quotes to construct the projects on Sept. 20, 2022
• Staff recommend the City Council award the construction contract to VSS International, Inc. in an amount not to exceed $318,120 for construction of the projects
• Sufficient funding is available for the contract
NEXT STEPS
• Once the City Council awards the construction
contract to VSS International, Inc., staff will
schedule a preconstruction meeting and issue a
notice to proceed for construction of the
projects
• Estimated projects completion date is Jan. 2023.