PART 1 - GENERAL

1.1 REQUIREMENTS
A. This section describes the requirements for temporary bypass pumping of sewage flows.

When sewage bypass and pumping is required, or the Contractor elects to perform, the Contractor shall submit a Temporary Bypass Plan conforming with the requirements of this Section.

B. Contractor shall provide labor, materials, equipment, and supervision to temporarily provide bypass pumping around the Work. No interruption of sewage flow shall be permitted throughout the duration of the project.

C. Bypass Operation: 24 hours per day during the period of Work. Operation of the bypass system shall be continuously monitored by the Contractor’s personnel.

D. The Contractor shall observe and comply with all Federal, State, and local laws, ordinances, codes, orders, and regulations which in any manner affect the conduct of the work, specifically as they relate to wastewater discharges, spills, or overflows to the environment. The Contractor shall be fully responsible for preventing wastewater discharges, spills or overflows ; containing the wastewater ; and recovery and legal disposal of wastewater. The Contractor shall be responsible for payment of any fines or penalties assessed against the Agency and for claims and liability arising from negligent or willful discharge of wastewater including attorney fees and costs associated with defending any action against the Agency resulting from such discharges, spills or overflows.

E. The Contractor shall not interrupt existing services and/or facility operations which may cause a wastewater discharge, spill or overflow. The Contractor will be charged for all costs associated with the Agency’s efforts if they are dispatched to the discharge, spill or overflow.

F. The Contractor is prohibited from discharging any groundwater, stormwater or hazardous waste encountered during construction project without prior written approval by the San Diego Regional Water Quality Control Board and the Encina Wastewater Authority. Refer to the General Provisions Section 7-8.6.

G. The Contractor is responsible for noise attenuation equipment and odor control measures if determined necessary by the Agency or County based on site conditions and impact to adjacent property owners.

H. The Contractor is responsible for contacting property owners and business that are affected by the construction activities to inform them of the W ork and the estimated schedule. Written notice shall be delivered to each home or business in accordance with the Gener al Provisions . A doorhanger notice to residential properties template is available from Agency.

I. Two (2) working days prior to any work affecting a sewer lateral, a follow-up notice shall be delivered to each home or business. The notice shall instruct occupants to minimize SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 2 of 7 ends

water usage on the day of the work and to fill floor drain traps with water to prevent potential odors.

1.2 SUBMITTALS
A. The Contractor shall submit a Temporary Bypass Pumping Plan (Plan) to the Agency at least fourteen (14) days prior to the implementation of flow diversion/bypass.

1. The Plan shall indicate the sequence of construction and the diversion operations and all other operations the Contractor will establish to maintain wastewater service during the diversion/bypass period.

2. The Plan shall be reviewed and approved by the Agency before flow can be diverted/bypassed. No deviation from the approved diversion/bypass plan will be allowed without prior approval from the Agency.

3. The Plan shall include a n Overflow Emergency Response Plan (OERP) indicating the procedures, personnel, equipment, and activities that will be implemented in the event of a wastewater discharge, spill or overflow to the environment, or diversion system failure. The Contractor shall be responsible for implementation of the OERP in accordance with this Section.

B. Bypass Pumping Plan.

1. Provide for each bypass pumping scenario for the project. Bypass pumping plan shall include at least the following:
a. A plan view drawing to graphically show the location of the bypass pumping equipment and appurtenances.
b. Staging areas for pumps.
c. Sewer plugging method and types of plugs.
d. Size and location of manholes or access points for suction and discharge piping. e. Size of pipeline or conveyance system to be bypassed. f. Number, size, material, location and method of installation and protection of suction and discharge piping.
g. Bypass pump sizes, capacities, and number of each size to be provided on-site including all primary, secondary, and spare pumping units. h. Calculations of static lift, friction losses, and flow velocity for selection of pumps and piping and pump head-capacity curves and operating ranges. i. System pressure for calculation of hydrostatic testing requirements. j. Downstream discharge plan.
k. Method of protecting discharge manholes or structures from erosion and damage.
l. Temporary pipe supports and anchoring requirements.
m. Thrust and restraint block sizes and locations. Provide the details necessary to demonstrate the integrity of all suction and discharge piping. n. Sections showing suction and discharge pipe depth, embedment, select fill and special backfill.
o. When required, s ound attenuation features for each pump and any additional equipment that is included in the Bypass Pumping Plan.
p. Access plans to all bypass pumping locations indicated on the drawings. q. Schedule for installation, testing and maintenance of bypass pumping system. r. Emergency plan for adverse weather and flooding.

SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 3 of 7 ends

s. Contractor’s plan for providing continuous monitoring of the bypass pumping operation as well as the monitoring persons’ qualifications. t. Flow-thru plugs: If flow-thru plugs are utilized for bypass, provide detailed design including, but not limited to, the flow-thru pipe size(s), configuration and location, and a capacity analysis to verify plug capacity vs design flow. The flow-thru plug shall be tethered or adequately braced during all diversion activities.

2. Subject to the approval of the Agency, if bypass pumping is not required for a location, the Contractor may elect to plug and vactor sewage flows for the duration of the Work . The Contractor shall submit a plug and vactor plan for each location which shall include at least the following:
a. Sewer plugging method and types of plugs.
b. Size of pipeline or conveyance system to be bypassed. c. Duration of plugging and calculated volume of sewage, including elevation of sewage head.
d. Emergency plan for adverse weather and flooding for various phases of the Work.
e. Contractors plan for providing continuous monitoring of the sewage flows as well as the monitoring persons’ qualifications.

3. Emergency Contact List: Provide three emergency contacts who are able to respond and be on site within two hours of contact. Provide name, cell phone, and email addresses. List shall be posted in a conspicuous location at the bypass pump location.

C. Overflow Emergency Response Plan (OERP)

1. The OERP shal l be developed to respond to any construction related wastewater discharge, spill or overflow to the environment. The Contractor’s OERP shall not rely on Agency personnel for emergency response, but they may be dispatched, at the Agency’s discretion and/or availability, to assist the Contractor . If the Agency’s personnel respond, the Contractor shall be responsible for all associated costs.

2. The Contractor is prohibited from unauthorized discharge of any wastewater, groundwater, storm water, or hazardous waste encountered during the construction project.

3. The Contractor shall immediately contact the Agency upon discovery or knowledge of an unauthorized discharge and proceed to control, contain or capture such discharge to the maximum extent possible. The Contractor shall cooperate with the Agency for the Agency’s reporting requirements for the unauthorized discharge.

4. The OERP shall include at a minimum:
a. Identification of environmentally sensitive areas that could be affected by a wastewater discharge, spill or overflow, including but not limited to, waterways, channels, catch basins and entrances to existing underground storm drains. b. An emergency notification procedure the complies with the state and federal requirements including but not limited to, California Health and Safety Code Section 5411.5. The Contractor shall designate primary and secondary representatives, their respective home and mobile phone numbers. Agency contacts for City Contractors shall also be listed.
c. Identification of personnel and equipment/tools that will be utilized in the event of a wastewater discharge, spill or overflow to the environment. Include an SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 4 of 7 ends

emergency team with arrangements for backup personnel and equipment. The emergency response team shall be able to dispatch to the site 24 hours a day, 7 days a week including weekends and holidays to respond immediately to any wastewater discharge, spill or overflow to the environment related to the Project work.
d. Identification of downstream public water systems.
e. Identification of owners of storm water inlets in the immediate vicinity. f. Step-by-step procedures to contain, control, and minimize wastewater discharges, spills or overflows to the environment.

5. At the pre-construction meeting, the Contractor will be provided with a list of Agency representatives to contact in case of a wastewater discharge, spill, or overflow to the environment. These contacts shall be added to the OERP.

6. The Contractor cannot begin work until the Agency has approved the OERP in writing. An approved copy of the OERP shall be available on the job site at all times.

7. It is the Contractor’s responsibility to assure that all employees, including subcontractors, know and obey all emergency procedures included in the OERP.

PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION

3.1 GENERAL
A. The Contractor shall notify the Engineer 48 hours prior to bypassing or diverting flow in any of the pipelines or laterals. Notification shall include location of bypass, when bypass will be activated, and length of time bypass will be in place.

B. Contractor shall maintain sufficient equipment and materials on site to ensure continuous and successful operation of the bypass systems. The Contractor shall maintain spare valves, pumps, tees, elbows, connections, tools, sewer plugs, piping, fuel and/or back - up generator, and other parts or system hardware to ensure immediate repair or modification of any part of the system as necessary.

C. Bypass piping cannot be placed within private property without the written approval of the Agency.

3.2 BYPASS PUMPING EQUIPMENT
A. All equipment, including but not limited to vactors and pumps shall be fully installed, operational, and ready for immediate use.

B. Noise Restrictions

1. Pumps and generators shall keep the noise level below 70 dBA at 30 feet.

2. Equipment used in residential areas or night time operation shall have sound attenuation enclosures.

C. Capacity
SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 5 of 7 ends

1. Pumps and bypass lines shall be of adequate capacity and size to handle all sewer flow. The bypass pumping equipment shall be sized to handle 100% of the required flows:

Average dry weather flow: As shown on the Plans
Peak wet weather flow: As shown on the Plans

2. Bypass lines, fittings and all accessories shall withstand twice the maximum pressure required for bypassing and shall be in good working condition.

3. The Contractor is responsible for verifying the actual peak flow rate and designing the flow diversion/bypass pumping system.

4. Spare pumps and generators, with a total capacity equal to 100% of the peak flows, must also be supplied to provide 100% redundancy.

D. The Contractor shall perform the necessary maintenance and repairs on the flow bypass system, and exercise and ensure the operation of the backup pumps . The Contractor shall operate backup pumps for a minimum of 25% of the total bypass time on a daily basis
E. The Contractor shall provide one dedicated fuel tank for each pump/generator if fuel/generator driven pumps are used. Each fuel tank shall have a fuel level indicator.

The Contractor shall continuously monitor the fuel level in the tanks and ensure that the fuel level does not drop below a level equivalent of two hours of continuous flow diversion system operation. The Contractor shall protect the fuel supply from contamination. This could include but is not limited to fuel line water traps, fuel line filters, and protecting fuel stores from precipitation. The Contractor shall also monitor all hoses and repair leaks immediately.

F. The bypass pumping system shall be manned at all times, including any bypass pumping performed after normal work hours, weekends and holidays.

3.3 PROTECTION
A. Contractor shall mark and protect suction and discharge pipes.

B. The Contractor shall inspect the entire bypass pumping and piping system for leaks or spills on a continuous basis.

C. No bypassing to the ground surface, receiving waters, storm drains, or bypassing which results in soil or groundwater contamination or any potential health hazards shall be permitted.

D. In the event of any sewage spill the Contractor shall follow the approved OERP and the steps outlined in Paragraph 3.4.

3.4 WASTERWATER DISCHARGE EVENT
A. In event of wastewater discharge, spill, or overflow to the environment, the Contractor shall:

SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 6 of 7 ends

1. Immediately implement the OERP without direction from the Agency , to control and contain the discharge, spill, or overflow.

2. Contact Agency personnel immediately. Information to provide shall include at minimum, the following:
a. Location of discharge, spill, or overflow
b. Start time of discharge, spill, or overflow
c. Duration if already terminated, or expected duration if in progress d. Estimated wastewater volume spilled
e. Cause (if known)
f. Control measures implemented
g. Type of remedial and/or clean up measures taken
h. Description of affected or potentially affected sensitive areas such as waterways, channels, catch basins and entrances to existing underground storm drains

3. Based on the above information, the Agency will determine if the discharge, spill or overflow is contained, and whether Agency personnel should be dispatched to the site. If dispatched, the Contractor shall be responsible for all costs incurred by the Agency as associated with the discharge, spill, or overflow.

4. Contact owner of stormwater inlets if discharge, spill or overflow enters stormwater system.

5. Report the spill to the applicable jurisdictional agency following the procedures in the OERP.

B. The Contractor shall, within 24 hours of the wastewater discharge, spill or overflow, submit to the Agency a written Wastewater Discharge Incident Report.

C. The Agency will evaluate the need for procedural changes to avoid further discharges, spills or overflows and the Contractor shall implement such changes immediately at no additional cost to the Agency . The Agency may institute further corrective actions, as deemed necessary.

D. The Contractor shall not damage existing public and private improvements, interrupt existing services and/or facility operations which may cause a wastewater discharge, spill or overflow to the environment. Any utility and/or improvement which is damaged by the Contractor shall immediately be repaired at the expense of the Contractor.

E. Once the discharge, spill or overflow has been contained and the situation causing the event has been stabilized, the Contractor shall restore the affected areas to original condition.

3.5 FIELD QUALITY CONTROL
A. Hydrostatic Pressure Test:

1. Notify the Engineer 24 hours prior to testing. The test shall be observed by an Agency Representative.

2. Attach bulkheads, isolation valves and pressure gauges to the piping to be tested.

3. Fill the discharge piping with potable water and seal the piping on both ends. The Contractor shall be responsible for securing potable water supply.

SECTION 02960 – TEMPORARY SEWER BYPASS PUMPING
CONTRACT NO. 5548-A TEMPORARY SEWER BYPASS PUMPING

Page 7 of 7 ends

4. Test the discharge piping with maximum pressure equal to 2.0 times the maximum operating pressure or 50 psi, whichever is greater for a period of 30 minutes.

5. If no leaks are observed after the test period, the line may be placed in service.

B. Inspection:

1. Operator shall inspect temporary bypass pumping and piping system at a minimum of every hour.

2. Operator shall continuously monitor the flow levels downstream and upstream of the flow diversion to detect any possible failure that may cause a wastewater discharge.

3. Keep written inspection log at each pumping location. Provide weekly copies to the Agency in a manner acceptable to the Agency.

C. Maintenance:

1. The Contractor shall inspect and maintain the bypass system daily, including the backup system.

2. The Contractor shall submit maintenance procedures and frequency to the Agency prior to any flow bypass.

3. The Contractor shall maintain a log of system operation and inspection, maintenance and repair records, and provide copies to the Agency upon request in a manner acceptable to the Agency.

3.6 CLEAN-UP
A. The bypass pumping system shall be flushed with potable water and drained prior to being dismantled and moved to the next location. Drain residual wastewater from the piping system into the Agency sewer main prior to disassembly, taking care to avoid wastewater spills.

B. Upon completion of bypass pumping operation, clean disturbed areas, restoring to original condition, including pavement restoration, at least equal to that which existing prior to start of Work.

3.7 SCHEDULING
A. The bypassing system shall not be shut down between shifts, on holidays or weekends, or during work stoppages.

B. The bypass system shall have a trained and qualified attendant on site 24 hours per day, 7 days per week to maintain the bypass pumping system from the start of bypass until the bypassing of the specific pipeline is no longer required.

END OF SECTION

APPENDIX A

DOOR HANGER TEMPLATE
AP PENDIX “A”

CITY OF CARLSBAD

UTILITY WORK

ABC CONTRACTORS
OFFICE # (760) XXX-XXXX
FIELD # (760) XXX-XXXX
Dear resident:

As a part of the City of Carlsbad’s ongoing
program to maintain its utilities , existing utility
infrastructure will be replaced and the street
resurfaced in your neighborhood. This
construction will require the closing of your street,
from ______ St. to ______ Ave. to through traffic
on:

MON. TUE. WED. THU. FRI.

DATES: XX / XX / XX to XX / XX / XX
T IME: _ AM to PM__
If you don’t plan to leave your home by 7:00 A.M.
on the above date(s), please park your car on an
adjacent street that will not be affected by
construction. Please do not drive, walk on, walk
pets, play, or skate in the areas of construction
work.

U.S. m ail delivery and trash pickup will not be
impacted.

If you have a moving company or other services
requiring vehicle access scheduled for these
date(s), please call and inform the Contractor of
the date and time.

Please contac t ABC Contractors at the above
phone number if you have questions regarding
the work.

If you have any concerns which cannot be
addressed by the Contractor, you may call the
City’s Project Inspector @ (xxx) xxx-xxxx.

Thank you for your cooperation as we work to
make a better City of Carlsbad.

APPENDIX B

SWPPP TEMPLATE

VALLEY STREET
SEESHEET3FORDETAILS
PLANT
BUILDING3000

CHILLER

STORM WATER POLLUTION PREVENTION NOTES
APN :

TIER 2 CITY STORM WATER POLLUTION PREVENTION PLAN (TIER 2 SWPPP) AREA OF DISTURBANCECONSTRUCTION THREAT: OWNER/APPLICANT:SITE ADDRESS:EMERGENCY CONTACT :2 1PROJECT NAME:SHEET INDEX:

TIER 2
OWNER'S CERTIFICATION:

STAMPIFAPPLICABLE

WEATHER TRIGGERED ACTION PLAN

VICINITY MAP
LEGEND
CASQA DesignationConstruction Activity(BMP) DescriptionBest Management Practice* Erosion Control
Sediment Control BMPs
BMPs
TrackingControl BMPs
Non-Storm WaterManagement BMPs
Waste Management and MaterialsPollution Control BMPs

BEST MANAGEMENT PRACTICES (BMP) SELECTION TABLE

PIO PICO DRIVE (PUBLIC)
2 2PROJECT NAME:TIER 2
TIER 2 STORM WATER POLLUTION PREVENTION PLAN (SWPPP)
SAMPLE

EROSION CONTROL PLAN

APPENDIX C

SPECIAL USE DISCHARGE PERMIT TEMPLATE
(ENCINA WASTEWATER AUTHORITY)

ENCINA WASTEWATER AUTHORITY . .

A Public Agency

SERVING THE CITY OF VISTA, CITY OF CARLSBAD, BUENA SANITATION DISTRICT, VALLECITOS WATER DISTRICT,

LEUCADIA WASTEWATER DISTRICT AND CITY OF ENCINITAS
6200 Avenida Encinas
Carlsbad, CA 92011-1095
Telephone (760) 438-3941
FAX (760) 438-3861 (Plant)
(760) 431-7493 (Admin)

Thank you for contacting Encina Wastewater Authority to obtain information about the permitting process.

This letter will help to facilitate the permit process on behalf of Encina Wastewater Authority . Once the documentation has been received, reviewed, and approved by EWA, a site inspection will be scheduled.

Please note, prior to EWA’s issuance of the permit, the system mu st be demonstrated in the field and functional as per the specifications provided to EWA in the permit application. The standard turn-around time to issue a permit is approximately 4-6 weeks.

1. Provide a completed discharge permit application including all the supporting documentation listed below.

2. Liability Insurance.
a. "Encina Wastewater Authority and Membership Agencies" named as Additionally Insured in the Certificate of Liability Insurance.
b. Min $5,000,000 general liability AND $5,000,000 for all environme ntal impairment damages resulting from discharge; valid for the entire duration of the Permit.

3. Provide a sewer map that identifies all test pits, excavation pit locations, and names of each discharge point (Manhole) on the map.

4. Provide representative analytical sample results.

5. Provide a signed Indemnity Agreement from the participating agency Valid Entire Duration of the Permit.

6. Provide written plan approval from the participating agency for the proposed discharge flow rate, flow volume, discharge points, including any special condition requirements (wet weather discharge, Storm Water BMPs, manhole protection, etc.).

7. Provide a printout of Geotracker results with 1000’ search radius (map).

8. Provide details regarding the pretreatment system including the proposed maximum discharge flow rate and max hours pumped per day, the size of the hoses used, (model number of the pump and the max pumping rate, calculations for the retention time in the sedimentation tank, (baffles or no baffles in the tank), the model number and optimum flow ranges for the flow meter, documentation defining the length of straight pipe required before and after the meter for accurate measurements, flow restrictor information (if needed) and sample point details (Spigot).

9. Provide a Ground Water Discharge Sketch to include the details of excavation pump, high level shut off, sediment tank (baffles or not), discharge pump, high/low level shut off, treatment train, inverted U, straight pipe, flow meter, straight pipe, governor, sample point, etc.

Please contact me directly with questions or concerns.

Thank you,

Robert Grigg
Encina Wastewater Authority
Environmental Compliance
Source Control Manager
[email protected]

Office: 760-438-3941 ext: 3603
1 INDEMNITY AGREEMENT

THIS AGREEMENT is made on , by and between the MEMBER AGENCY DISTRICT OR CITY AND THE ENCINA WASTEWATER AUTHORITY (hereinafter "Licensors"), and _________________________________(hereinafter "Licensee"); Licensors and Licensee shall sometimes hereinafter be referred to as the "Parties".

R E C I T A L S

A. Licensors are the owner/operator of the sewer treatment plant located at 6200 Avenida Encinas in Carlsbad, California (the "Property") and the associated collection system;

B. Licensee now desires to discharge to the sanitary sewer syste m as described in the Special Use Discharge Application attached hereto and made a part hereof.

NOW THEREFORE, in consideration of the granting of the foregoing, the mutual premises, covenants, conditions and agreements hereinafter set forth, and other go od and valuable consideration, the receipt and adequacy of which are acknowledged, the Parties agree as follows:

1. Grant of License - Licensors hereby grant to Licensee, and its employees, representatives and contractors a non -exclusive license (h ereinafter the "License") to discharge to the sanitary sewer system as described in Recitals Paragraph B above. This License shall commence on ______________, and shall end on , unless the parties agree in writing to extend the term of the License. Prior to the expiration of the License, Licensee shall, at its sole cost and expense, (a) permanently close the connection to the sanitary sewer system and (b) remove all debris resulting from operations.

2. Compliance with Laws - Licensee shall conduct all operations, which are the subject of this License in compliance with all federal, state, and municipal statutes and ordinances, and with all regulations, orders, and directives of appropriate governmental agencies, as such statutes, ordinances, regulations, orders and directives now exist or provide.

3. Permits - Licensee, at no cost or expense to Licensors, shall be responsible for obtaining any and all governmental permits and approvals, which may be necessary for it to conduct any work or activities under this License Agreement.

4. Liens and Claims - Licensee will not permit any mechanics', vendor’s, or similar liens or claims to stand against the Licensors for labor or material furnished in connection with any work performed by Licensee under this License Agreement. Upon reasonable and timely notice o f any such lien or claim delivered to Licensee, Licensee may bond and contest the validity and the amount of such lien, but Licensee will immediately pay any judgment rendered, will pay all proper costs and charges, and will have the lien or claim released at its sole expense.

5. Cooperation - Licensee agrees to coordinate its activities with Licensors to minimize any impairment of access by customers or business invitees of Licensors to the Property.

6. Indemnification - Licensee agrees that it wil l indemnify and hold Licensors, their officers, directors, agents and employees, harmless from and against any claims, demands, liens,

2 actions, suits, ju dgments, losses, damages, attorney's fees, costs or expenses, and civil criminal or administrative penalties based upon or arising out of or claimed to have arisen out of alleged acts, errors or omissions of Licensee or its authorized contractors, employee s and agents in conducting the activities under this License Agreement, including the activities authorized under the Wastewater Discharge Permit issued by the Encina Wastewater Authority (EWA). This indemnification is expressly conditioned on the following:

(a) In the event Licensors identify any matter to which this indemnification may apply or receive a notice or claim from any third party of such matter, it shall immediately, and in every case within ninety (90) days of said notice or claim, notify Lic ensee in writing of such matter.

(b) Licensors shall cooperate with Licensee by allowing Licensee, its agents, representatives, contractors and consultants, prompt and ready access to the sanitary sewer system for the purpose of investigating any matter to which this indemnity may apply. Licensors shall provide Licensee with copies of all investigative reports, data or other information in any form which Licensors, its consultants, agents or attorneys may have pertaining to any such matter, on request of Licensee.

(c) Notwithstanding anything in this agreement to the contrary, in no event shall Licensee be liable for any special, indirect or consequential damages, including but not limited to claims for loss of use, rents, anticipated profit or business opportunity, or business interruption or mental or emotional distress or fear of injury or disease.

(d) This indemnification shall survive termination of this Agreement and expiration of the Permit and shall be effective until the expiration of any applicable statutes of limitations.

7. Compliance with Wastewater Discharge Permit - Licensee agrees to comply with the EWA Pretreatment Ordinance and the terms of the Wastewater Discharge Permit issued by the EWA. Licensee shall not add to the sanitary sewer any material not authorized under the Permit.

In the event Licensee adds any material to the sewer that causes a violation of EWA's NPDES Permits, as defined in the EWA Pretreatment Ordinance, Licensee shall indemnify Licensors in accordance with paragraph 6 above.

8. Severability - In case any one or more of the provisions contained in this Agreement shall be invalid, illegal or unenforceable in any respect, the validity, legality, and enforceability of the remaining provisions contained herein shall not in any way be affected or impaired thereby.

9. Notices - Any notice provided for herein or otherwise required to be given hereunder shall be deemed received when personally served or three (3) days after mailing by certified or registered United States mail, return receipt requested, postage prepaid, or by facsimile machine, with transmission and receipt confirmed, or by nationally recognized overnight delivery service, addressed as follows:

To Licensors: Encina Wastewater Authority District or City 6200 Avenida Encinas Address
Carlsbad, California 92011
3 To Licensee:

With Copies to:

The person and place to which notices are to be mailed may be changed by either party by providing written notice of same to the other.

10. Assignment Successors and Assigns - This Agreement may be assigned by either party and in and in such event shall b e binding upon and inure to the benefit of the Parties' respective representatives, successors and assigns.

11. Entire Agreement - This License Agreement represents the full, complete and entire agreement between the parties with respect to the subject ma tter hereof, and the rights and remedies of the Parties shall be solely and exclusively those herein contained, and in lieu of any remedies otherwise available at law or in equity.

12. Governing Law - This Agreement shall be construed and interpreted and governed by and in accordance with the local law of the State of California without reference to any choice of law, rules or policies which may refer the resolution of any dispute arising hereunder to the laws of any other jurisdiction.

13. Counterparts - This Agreement may be executed in one or more counterparts, each of which shall be deemed an original, and all of which, taken together, shall constitute one and the same Agreement.

IN WITNESS WHEREOF, the Parties have executed this License Agreement by their duly authorized representative on the date first above written.

LICENSORS: LICENSEE:

DISTRICT OR CITY &

ENCINA WASTEWATER AUTHORITY

By: By:

Name: Name:

Title: Title:

Date: Date: _

-12-

Table 1

LOCAL DISCHARGE LIMITS
Daily Maximum Limits
Constituent Limits for Users in
MWRF Service Area
Limits for Users in
EWPCF Service Area
Arsenic, Total 1.5 mg/L 1.5 mg/L
Boron, Total 7.4 mg/L -
Cadmium, Total 0.77 mg/L 0.77 mg/L
Chromium, Total 3.5 mg/L 3.5 mg/L
Copper, Total 11 mg/L 11 mg/L
Iron, Total 67 mg/L -
Lead, Total 5.1 mg/L 5.1 mg/L
Manganese, Total 1.7 mg/ L -
Mercury, Total 0.27 mg/L 0.27 mg/L
Molybdenum, Total 4.1 mg/L 4.1 mg/L
Nickel, Total 15 mg/L 15 mg/L
Selenium, Total 2.5 mg/L 2.5 mg/L
Silver, Total 4.2 mg/L 4.2 mg/L
Zinc, Total 29 mg/L 29 mg/L
Oil and Grease 400 mg/L 400 mg/L
Total Toxic Organics (TTO) 2.00 mg/L 2.00 mg/L
Biochemical Oxygen Demand (BOD) 250 mg/L* 500 lbs/day
Total Suspended Solids (TSS) 250 mg/L 500 lbs/day
Instantaneous Limits
Constituent Limit Limit
pH 5.5 – 12.0 units 5.5 – 12.0 units
Temperature 140° Fahrenheit 140° Fahrenheit
*Permittees in the MWRF Service Area as of February 22, 2012 are grandfathered in at their existing pollutant loading for BOD.

2.13 BEST MANAGEMENT PRACTICES
EWA may develop BMPs by ordinance or in individual W astewater Discharge Permits to implement Local Limits and the requirements of Section 2.1.

EPA APPROVED SAMPLING AND ANALYTICAL METHODS
Parameter Analytical  Method1 Container2 Preservation Method3 Maximum Holding
Time4
BOD or CBOD SM5210B* P, G, FP COOL, 0‐6°C 48  HOURS
COD
HACH 8000*; EPA 410.3 &
410.4 REV 2.0; SM5220C &
5220D P, G, FP COOL,  0‐6°C, H2SO4 TO pH <2 28 DAYS
CN,
AMENABLE SM4500 ‐CN (G) P, G, FP
COOL, 0‐6°C, NaOH TO pH >
12, 0.6g ASCORBIC ACIDŦ 14 DAYS
CN, TOTAL
EPA 335.4 REV 1.0; SM4500‐
CN (F) & 4500‐CN(G) & 4500‐
CN (E) P, G, FP
COOL, 0‐6°C, NaOH TO pH >
12, 0.6g ASCORBIC ACIDŦ 14 DAYS
METALS:  Cd,
Cr, Cu, Pb, Ni,
Ag
SM3111B or C, 3113B,
3120B; EPA 200.9 Rev 2.2,
200.7 Rev 4.4*, 200.8 Rev

5.4 P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Sb
SM3111B, 3113B, 3120B;
EPA 200.9 Rev 2.2, 200.7 Rev

4.4*, 200.8 Rev 5.4 P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
SM3114B, 3113B, 3120B;
EPA 200.9 Rev 2.2, 200.7 Rev  HNO3 TO pH < 2 OR HNO3 TO METALS: As

4.4*, 200.8 Rev 5.4; SM3500‐
As (C or B) P, G, FP
3 p 3
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Be
SM3111D, 3113B, 3120B;
EPA 200.9 Rev 2.2, 200.7 Rev

4.4*, 200.8 Rev 5.4; SM3500‐
Be (D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: B
SM4500‐B (B), 3120B; EPA
200.7 Rev 4.4* P, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Cd
(optional) SM3500  Cd (D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Cr
(optional) SM3500  Cr (B or D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Cu
(optional) SM3500  Cu (B, C, D, or E) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
L:\SOURCE\Industry Handouts\EPA Approved Sampling and Analytical Methods_010312.xlsx EPA APPROVED SAMPLING AND ANALYTICAL METHODS
Parameter Analytical  Method1 Container2 Preservation Method3 Maximum Holding
Time4
METALS:  Fe
SM3111B or C, 3113B,
3120B; EPA 200.9 Rev 2.2,
200.7 Rev 4.4*; SM3500‐Fe
(B or D)  P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Pb
(optional) SM3500  Pb (B or D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS:  Hg
SM3112B, EPA 245.1 Rev

3.0*, 245.2, 245.7 Rev 2.0,
1631E P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 28  DAYS
METALS:  Mn
SM3111B, 3113B, 3120B;
EPA 200.9 Rev 2.2, 200.7 Rev

4.4*, 200.8 Rev 5.4; SM3500‐
Mn (B or D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Mo
SM3111D, 3113B, 3120B;
EPA 200.7 Rev 4.4*, 200.8
Rev 54 P G FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6 MONTHSMETALS:  Mo Rev 5.4 P, G, FP PRIOR TO ANALYSIS 6 MONTHS METALS: Ni
(optional) SM3500  Ni (D) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS:  Se
SM3113B, 3120B, 3114B;
EPA 200.9 Rev 2.2, 200.7 Rev

4.4*, 200.8 Rev 5.4 P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS:  Tl
SM3111B, 3120B; EPA 279.2,
200.9 Rev 2.2, 200.7 Rev

4.4*, 200.8 Rev 5.4 P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
METALS: Zn
SM3111B or C, 3120B; EPA
289.2, 200.7 Rev 4.4*, 200.8
Rev 5.4; SM3500 Zn (B, E, or
F) P, G, FP
HNO3 TO pH < 2 OR HNO3 TO
pH < 2 AT LEAST 24 HOURS
PRIOR TO ANALYSIS 6  MONTHS
OIL & GREASE SM5520B;  EPA 1664A G
COOL, 0‐6°C, HCl OR H2SO4 TO
pH < 22 8  DAYS
pH SM4500‐H+B*; EPA 150.2 P, G, FP NONE
ANALYZE WITHIN 15
MIN
TDS SM2540C* P, G, FP COOL, 0‐6°C7  DAYS
TSS SM2540D* P, G, FP COOL, 0‐6°C7  DAYS
TTO
EPA 624 & 625; EPA 1624
&1625 G
COOL, 0‐6°C, 624/1624 = HCl
TO pH < 2
624/1624 = 14 DAYS;
625/1625 = 7 DAYS
L:\SOURCE\Industry Handouts\EPA Approved Sampling and Analytical Methods_010312.xlsx EPA APPROVED SAMPLING AND ANALYTICAL METHODS
Parameter Analytical  Method1 Container2 Preservation Method3 Maximum Holding
Time4
PHARM.

ORGANICS:

ACETONE
EPA 524.2; ASTM D3695,
D4763 G
COOL, 0‐6°C, 1666/524.2 =
HCl TO pH < 2
524.2 = 14 DAYS;
D3695 = 28 DAYS
PHARM.

ORGANICS:

METHYLENE
CHLORIDE EPA  502.2, 524.2 G
COOL, 0‐6°C, 1666/524.2 =
HCl TO pH < 2
502.2/524.2 = 14
DAYS
PHARM.

ORGANICS:

ETHYL
ACETATE EPA  1666; ASTM D3695 G
COOL, 0‐6°C, 1666/524.2 =
HCl TO pH < 2
1666 = 14 DAYS;
D3695 = 28 DAYS
PHARM.

ORGANICS:  N‐
AMYL
ACETATE EPA  1666; ASTM D3695 G
COOL, 0‐6°C, 1666/524.2 =
HCl TO pH < 2
1666 = 14 DAYS;
D3695 = 28 DAYS
PHARM.

ORGANICS:

ISOPROPYL
ACETATE EPA  1666; ASTM D3695 G
COOL, 0‐6°C, 1666/524.2 =
HCl TO pH < 2
1666 = 14 DAYS;
D3695 = 28 DAYS
1 Refer to 40 CFR Part 136 for complete list of approved test procedures Refer to 40 CFR Part 136 for complete list of approved test procedures. 2 "P" is Polyethylene; "G" is Glass; "FP" is Fluoropolymer, PTFE, or Teflon. 3 Confirm with EPA certified lab the preservation and holding times for each specific method. 4 Holding time starts at the end of the composite period. * Methods currently performed by the Encina Wastewater Authority (EWA).

Ŧ Only added if residual chlorine is present
L:\SOURCE\Industry Handouts\EPA Approved Sampling and Analytical Methods_010312.xlsx KELLY DRIVE SEWER REPLACEMENT PROJECTIMPROVEMENT PLAN FOR: 1/2" 01" 5548-A540-5BID SET - NOT FOR CONSTRUCTION
14TITLE SHEETNISDDP

PROJECT SITEVICINITY MAPAVECOSTALABLVDCARLSBAD
RDALGA

PALOMAR

AIRPORTRD

ELCAMINOREALRANCHOSANTA FERD
POINSETTIALANEALICANTERDELFUERTEOLIVENHAIN RD.MELROSEDR.

FARADAYCOLLEGEBLVDPASEODELNORTE
AVE

AVENIDAENCINASCANNONRDMONROESTCARLSBADVILLAGEDRMARRONTAMARACKAVERDLAKECALAVERA

BUENAVISTALAGOONAGUAHEDIONDALAGOONBATIQUITOSLAGOONAVIARAPKWYPOINSETTIALANE

LOCATION MAPPROJECT SITE
KELLY DRIVE SEWER REPLACEMENTCIP 5548-ACONSTRUCTION PLANSFOR THE CARLSBAD, CALIFORNIACITY OF CARLSBAD, UTILITIES DEPARTMENTKEITH BLACKBURN - MAYORCITY COUNCIL MEMBERSSCOTT CHADWICKPAZ GOMEZDECEMBER 2022 CITY MANAGERDEPUTY CITY MANAGER, PUBLIC WORKSTERESA ACOSTA - DISTRICT 4VACANT - DISTRICT 2PRIYA BHAT-PATEL - DISTRICT 3MELANIE BURKHOLDER - DISTRICT 1 KELLY DRIVE SEWER REPLACEMENT PROJECTIMPROVEMENT PLAN FOR: 1/2" 01" 5548-A540-5BID SET - NOT FOR CONSTRUCTION

LEGENDDESCRIPTION
SYMBOL

ABBREVIATIONSDESCRIPTION

ABBREVIATION
24 NOTES, LEGEND AND ABBREVIATIONSNISDDP
12'' S12'' S12'' S12'' S12'' S12'' S12'' S
12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S (AB)12'' S (AB) SSS
S

SSSSSSSSSSSSSSSSSSSSSSSSS
12'' S12'' S12'' S8'' S8'' S8'' S8'' S
8'' S8'' S8'' S REPLACE 585 LF (E) 12" VCP SEWERW/ NEW 15" PVCSEE SHEET 4 (E) MH 17D-9(E) MH 17B-11(E) MH 17D-10PIP (E) 8"SEWER
PIP (E) 12"SEWERABANDONED 12" SEWER MAINCONTRACTOR TO VERIFY PIP (E) SEWER LATERALCONTRACTOR TO VERIFYPIP (E) 12"SEWERABOVE GROUNDSEWER BYPASSBYPASS AND STANDBY PUMPFOR REFERENCE ONLY(E) MH 17D-2STA: 0+00 33'32'84'
RR (E) CSD S-4CAST IRON MH FRAME AND COVERCITY TO SUPPLY FRAME AND COVER(E) PAVEMENTRR (E) CONCRETE COLLARPER CSD S-1 (E) CSD S-1CIP BASE
APPLY EPOXY COATINGTO (E) CHANNEL AND(P) 15" CHANNEL PERCSD S-1ACORE DRILL NEWINLET/OUTLETFOR (P) 15" PVC(P) WATER TIGHT MANHOLE ADAPTERWITH RUBBER GASKET.GROUT INTO PLACE (TYP)(P) 15" PVCMATCH EXISTINGCHANNEL IE (E) MANHOLESEE MH DIMENSION TABLESHEET 2(E) 12" VCP TO BE REMOVEDAPPLY EPOXYCOATING TOREBUILT BENCHAND MANHOLEINTERIOR PERCSD S-1AREFORM CHANNELTO MATCH 15"OUTLET PIP (E) 12" VCP SEWER
(E) MANHOLE BASEPIP (E) 8"ABS SEWER
(E) 12" ABANDONED SEWERCONTRACTOR TO VERIFYINSTALL SLURRY PLUGAT (E) ABANDONED12" INLET CONNECTION (P) 15" PVC SEWERSEE DETAIL 1 FORCONNECTIONDETAILREFORM CHANNEL ANDBENCH TO ELIMINATEABANDONED 12" SEWER INLET REBUILD (E) BENCHPER CSD S-1A(E) 12" CHANNEL INLET(E) 12" CHANNEL OUTLET(P) 15" CHANNEL INLETSEE DETAIL 1 FOR CONNECTIONDETAIL(E) MANHOLE BASE (P) 15" CHANNEL OUTLETSEE DETAIL 1 FOR CONNECTIONDETAILREFORM CHANNELTO MATCH 15"INLET/OUTLETREBUILD (E) BENCHPER CSD S-1A (E) 12" CHANNEL OUTLET(P) 15" CHANNEL INLETSEE DETAIL 1 FOR CONNECTIONDETAIL(E) MANHOLE BASE REFORM CHANNEL TOMATCH 15" INLET(E) 12" VCP SEWERREBUILD (E) BENCHPER CSD S-1A MANHOLE NEW CONNECTION DETAIL - PROFILE VIEWSTA: 2+84, 5+96, 8+69 SCALE: N.T.S.1 KELLY DRIVE SEWER REPLACEMENT PROJECTIMPROVEMENT PLAN FOR: 1/2" 01" 5548-A540-5BID SET - NOT FOR CONSTRUCTION

SITE PLAN AND BYPASS PLAN
MANHOLE DIMENSION TABLEMHSTA.RIM El.INV. EL.DIA.
17B-118+6949.9135.225'
17D-95+9644.0133.375'
17D-102+8438.8231.475'SEWER BYPASS NOTES·EXPECTED BYPASS FLOWS:PEAK WET WEATHER FLOW: 1.97 MGDAVERAGE DRY WEATHER FLOW: 0.79 MGD·CONTRACTOR RESPONSIBLE FOR DESIGN,FURNISHMENT AND INSTALLATION OF SEWERBYPASS PER CONTRACT SPECIFICATIONS·CONTRACTOR TO MAINTAIN ALL SEWER LATERALFLOWS AT ALL TIMES

TRAFFIC CONTROL NOTES
NOTES:1.SEE CSD S-1 FOR TYPICAL EXISTING MANHOLE DIMENSIONS.2.MANHOLE CONNECTION DETAIL SHOWN IS AT THE INLET. DETAIL APPLIES TO ALLEXISTING MANHOLE INLETS AND OUTLETS WHERE NEW CONNECTION IS PROPOSED TONEW PVC SEWER.34SITE PLANNISDDP ANTICIPATED LANE CLOSURES INCLUDE SOUTHBOUND LANEOF KELLY DRIVE.·SEE CONTRACT DOCUMENTS FOR TRAFFIC CONTROLSTANDARD DETAILS·CONTRACTOR TO MAINTAIN DRIVEWAY ACCESS TO ALLRESIDENTS AT ALL TIMESMANHOLE 17B-11 CONNECTION DETAIL - PLAN VIEWSTA: 8+69 SCALE: N.T.S.2MANHOLE 17B-11, 17D-9, 17D-10 NOTES:1.FOR JUNCTION MANHOLES AND CHANGE IN SEWER ALIGNMENT, FORM THE CHANNELS TOFACILITATE THE FLOW OF SEWAGE. INVERTS SHALL BE TRUE TO GRADE AND ALIGNMENT,FINISHED WITH SMOOTH SURFACE, AND MAINTAIN 0.2' DROP ACROSS THE MANHOLE.2.SEE DETAIL 1 FOR CONNECTION DETAIL AND REHABILITATION REQUIREMENTS.

MANHOLE 17D-9 CONNECTION DETAIL - PLAN VIEWSTA: 5+96 SCALE: N.T.S.3MANHOLE 17D-10 CONNECTION DETAIL - PLAN VIEWSTA: 2+84 SCALE: N.T.S.4 WWWWW
WWWWWW

WWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW
WWWW
WWWW
WWWW
WWWW
WW
WWWWWW
WW
12'' WW 12'' W12'' W12'' W12'' W
WW
WW 12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S12'' S (AB)SSS SS SS
SS SS
SSSS
SS SS
SS SS
SSSS
SS
SS SS
12'' S8'' S8'' S8'' S

EEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEE EEEEEEEEEEEEEEE
EEE
EEEE
EEEE

EEEEEE EEE
EEEEE

EEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEE

EEEEEEEEEEEEEEEEEEEEEEEEEE
EEEE

EEEEEEEEEEE
EEEE
EEE
EEEEE

EEEEEEEEEEE
EEE

EEEEEEEEEEEEEE
EEEEE
EEEE
EEEE
EEE
EEEE

EEEEEEEEE
GGG
GG
GGG
GGG

GGGGGGGGGGGGG
GGG
GGGGG

GGGGG GGGGG
GGGGGG
4'' G4'' G4'' G4'' G4'' G TTTTTTTTTTTTTTTTTTTTTTTTTTTTTT

TTTTTTTTTTTTTTTTTTTTTTTTT

TTTTTTTTTTTTTTTTTTTTTTTTTT

CATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATV

CATVCATVCATVCATV

CATVCATVCATVCATVCATVCATV
CATV

CATVCATVCATVCATVCATV

CATVCATVCATVCATV

CATVCATVCATVCATVCATV

CATVCATVCATVCATVCATV

CATVCATVCATVCATV

CATVCATVCATVCATVCATVCATVCATV

CATVCATVCATVCATVCATVCATVCATV

CATVCATVCATVCATVCATV

CATVCATV
TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)TS (AB)4'' G4'' G4'' G EEEE

TTTTT TSTSTSTS

RWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRW RWRWRW
GGGGG
G
G
GG
EEE
MH 17B-11MH 17D-9 MH17D-10585 LF1
CAUTION, HIGH PRESSUREGAS PER DWG 477-6.CONTRACTOR TO VERIFYLOCATION. 4 (TYP)4
CONTRACTOR TO VERIFYSEWER LATERAL LOCATIONOF 4803 KELLY DR 222 (E) 4" VCP SEWERLATERAL (TYP) 10'
17'ABANDONED12" SEWER
SEWER LATERALTO APN 2072300900
3+004+005+006+007+008+00
STA:4+48.02ELEV:38.29
STA:3+00.80ELEV:32.33STA:3+03.48ELEV:32.33
STA:3+72.26ELEV:32.73STA:3+73.98ELEV:32.74
STA:4+38.68ELEV:33.22STA:4+44.66ELEV:33.26
STA:5+09.57ELEV:33.65STA:5+12.40ELEV:33.66
STA:5+81.42ELEV:34.13STA:5+85.23ELEV:34.14
STA:6+53.98ELEV:34.57STA:6+57.02ELEV:34.57STA:6+97.09ELEV:34.78STA:7+44.91ELEV:35.16STA:7+57.02ELEV:35.21 STA:8+69.24ELEV:35.74 444444444444444
STA:2+84.01ELEV:38.81
STA:5+96.30ELEV:44.00
STA:8+69.08ELEV:49.904 2 22
15" SDR35 PVC @ 0.62%
15" SDR35 PVC @ 0.62%585 LF1
(E) FINISH GRADE
X3 X3X3 (E) 12" VCP SEWEREEEEEEEEEEEEEE C CCCCC GGGG CATV(TYP)WWWW6" RWWWWWWW W E 25303540455055
0+0025303540455055
10+13
NOTES:1.UTILITY MAPPING IS FOR REFERENCE ONLY. CONTRACTOR TO VERIFY ALL UTILITY LOCATIONS AND PROTECT INPLACE UNLESS NOTED OTHERWISE. ALL SEWER LATERALS WITHIN THE LIMIT OF WORK SHALL BE RECONNECTEDPER CONSTRUCTION NOTE 4.

KELLY DRIVE SEWER REPLACEMENT PROJECTIMPROVEMENT PLAN FOR: 1/2" 01" 5548-A540-5BID SET - NOT FOR CONSTRUCTION
PROFILE STA: 2+84 TO 8+69PLAN STA: 2+84 TO 8+691.REPLACE-IN-PLACE EXISTING 12" VCP SEWER MAIN WITH NEW 15" SDR35 PVC PER CSD S-5. INSTALL FILTER FABRICPER CSD S-5. RESURFACE TRENCH PER CSD MODIFIED GS-26 AND GS-28, 4' MAX. TRENCH WIDTH.2.REHABILITATE EXISTING MANHOLE PER DETAIL 1, SHEET 2 AND CSD S-1A.3.CONNECT NEW 15" SEWER TO EXISTING MANHOLE. SEE SHEET 2 FOR CONNECTION DETAIL.4.RECONNECT EXISTING 4" VCP SEWER LATERAL WITH NEW WYE PER CSD S-7. INSTALL COUPLING AT NEW PVC TO (E)VCP LATERAL CONNECTION.123CONSTRUCTION NOTES444PLAN AND PROFILENISDDP