Nothing in this section shall be construed as relieving the Contractor from full responsibility for correcting defective work or materials.
Revised 6/15/2017 Contract No. 6001-22E Page 97 of 148
In the event the Agency exercises its right to place into service and utilize all or part of any completed facility or appurtenance, the Agency will assume the responsibility and liability for injury to persons or property resulting from the utilization of the facility or appurtenance so placed into service, except for any such injury to persons or property caused by any willful or negligent act or omission by the Contractor, Subcontractor, their officers, employees, or agents.
Revised 6/15/2017 Contract No. 6001-22E Page 98 of 148
SECTION 7 – RESPONSIBILITIES OF THE CONTRACTOR
7-1 CONTRACTOR’S EQUIPMENT AND FACILITIES . The Contractor shall furnish and maintain in good condition all equ ipment and facilities as required for the proper execution and inspection of the Work. Such equipment and facilities shall meet all requirements of applicable ordinances and laws.
7-2 LABOR.
7-2.1 General. Only competent workers shall be employed on the Work. Any person employed who is found to be incompetent, intemperate, troublesome, disorderly, or otherwise objectionable, or who fails or refuses to perform work properly and acceptably, shall be immediately removed from the Work by the Contractor and not be reemployed on the Work.
7-2.2 Laws. The Contractor, its agents, and employees shall be bound by and comply with applicable provisions of the Labor Code and Federal, State, and local laws related to labor.
The Contractor shall strictly adhere to the provisions of the Labor Code regarding minimum wages; the 8 -hour day and 40 -hour week; overtime; Saturday, Sunday, and holiday work; and nondiscrimination because of race, color, national origin, sex, or religion. The Contractor shall forfeit to the Agency the penalties prescribed in the Labor Code for violations.
In accordance with the Labor Code, the Board has on file and will publish a schedule of prevailing wage rates for the types of work to be done under the Contract. The Contractor shall not pay less than these rates.
Each worker shall be paid subsistence and travel as required by the collective bargaining agreement on file with the State of California Department of Industrial Relations.
The Contractor’s attention is directed to Section 1776 of the Labor Code which imposes responsibility upon the Contractor for the maintenance, certification, and availability for inspection of such records for all persons employed by the Contractor or Subcontractor in connection with the project. The Contractor shall agree through the Contract to comply with this Section and the remaining provisions of the Labor Code.
7-3 LIABILITY INSURANCE. Insurance shall be required as specified in section 10 of the Public Works Contract.
The cost of this insurance shall be included in the Contractor’s Bid.
7-4 WORKERS’ COMPENSATION INSURANCE. Before execution of the Contract by the Board, the Contractor shall file with the Engineer the following signed certification:
“I am aware of the provisions of Section 3700 of the Lab or Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the wo rk of this contract.”
Revised 6/15/2017 Contract No. 6001-22E Page 99 of 148
The Contractor shall also comply with Section 3800 of the Labor Code by securing, paying for, and maintaining in full force and effect for the duration of the contract, complete Workers’ Compensation Insurance, and shall furnish a Ce rtificate of Insurance to the Engineer before execution of the Contract. The Agency, its officers, or employees, will not be responsible for any claims in law or equity occasioned by failure of the Contractor to comply with this paragraph.
All compensation insurance policies shall bear an endorsement or shall have attached a rider whereby it is provided that, in the event of expiration or proposed cancellation of such policies for any reason whatsoever, the Agency shall be notified by registered mail not l ess than 30 days before expiration or cancellation is effective.
All insurance is to be placed with insurers that are admitted and authorized to conduct business in the state of California and are listed in the official publication of the Department of Insurance of the State of California. Policies issued by the State Compensation Fund meet the requirement for workers' compensation insurance.
7-5 PERMITS. Except as specified herein , the Contractor will obtain, at no cost to the Contractor all City of Carlsbad encroachment, right -of-way, grading and building permits necessary to perform work for this contract on Agency property, streets, or other rights -of-way.
For work within the City of Encinitas (e.g., along La Costa Ave.), the Contractor will be required to pay for and obtain all necessary permits from the City of Encinitas for construction improvements in their jurisdiction at no cost to the City of Carlsbad (see Appendix A). For work within Caltrans Right -of-Way, Contractor will be required to obtain all necessary permits for construction improvements identified in Schedule B. Contractor shall not begin work until all permits incidental to the work are obtained. The Contractor shall obtain and pay for all permits for the disposal of all materials removed from the project. The cost of said permit(s) shall be included in the price bid for the appropriate bid item and no additional compensation will be allowed therefor. The Contractor shall obtain and pay for all costs incurred for permits necessitated by its operations such as, but not limited to, those permits required for night work, overload, blasting, and demolition. For private contracts, the Contractor shall obtain all permits incidental to the Work or made necessary by its operations, and pay all costs incurred by the permit requirements.
The Contractor shall pay all business taxes or license fees that are required for the work.
7-5.1 Resource Agency Permits. No Resource agency permits are required for the work.
7-6 THE CONTRACTOR’S REPRESENTATIVE. Before starting work, the Contractor shall designate in writing a representative who shall have complete authority to act for it. An alternative representative may be designated as well. The representative or alternate shall be present at the Work site whenever work is in progress or whenever actions of the elements necessitate its presence to take measures necessary to protect the Work, persons, or property. Any order or communication given to this representative shall be deemed delivered to the Contractor. A joint venture shall designate only one representative and alternate. In the absence of the Contractor or its representative, instructions or directions may be given by the Engineer to the superintendent or person in charge of the specific work to which the order applies. Such order shall be complied with promptly and referred to the Contractor or its representative.
In order to communicate with the Agency, the Contractor’s representative, superintendent, or person in charge of specific work shall be able to speak, read, and write the English language.
Revised 6/15/2017 Contract No. 6001-22E Page 100 of 148 7-7 COOPERATION AND COLLATERAL WORK. The Contractor shall be responsible for ascertaining the nature and extent of any simultaneous, collateral, and essential work by others.
The Agency, its workers and contractors and others, shall have the right to operate within or adjacent to the Work site during the performance of such work.
The Agency, the Contractor, and each of such workers, contractors and others, shall coordinate their operations and cooperate to minimize interference.
The Contractor shall include in its Bid all costs involved as a result of coordinating its work with others. The Contractor will not be entitled to additional compensation from the Agency for damages resulting from such simultaneous, collateral, and essential work. If necessary to avoid or minimize such damage or delay, the Contractor shall redeploy its work force to other parts of the Work.
Should the Contractor be delayed by the Agency, and such delay could not have been reasonably foreseen or prevented by the Contractor, the Engineer will determine the extent of the delay, the effect on the project, and any extension of time.
7-7.1 Coordination. The Contractor shall coordinate and cooperate with all the utility companies during the relocation or construction of their lines. The Contractor may be granted a time extension if, in the opinion of the Engineer, a delay is caused by the utility company. No additional compensation will be made to the Contractor for any such delay.
7-8 PROJECT SITE MAINTENANCE.
7-8.1 Cleanup and Dust Control. Throughout all phases of construction, including suspension of work, an d until the final acceptance, the Contractor shall keep the site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by cleaning, sweeping and sprinkling with water, or other means as necessary. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods.
Starting the day after the application of the slurry seal, the contractor shall sweep the slurry-sealed streets for three (3) consecutive days using a self-loading motor sweeper with spray nozzles. One week later, contractor shall sweep the slurry -sealed streets once per week for two weeks. The Engineer has the authority to require more sweeping than specified herein. All sweeping costs shall be included in the Contractor’s Bid.
Materials and equipment shall be removed from the site as soon as they are no longer necessary.
Before the final inspection, the site shall be cleared of equipment, unused materials, and rubbish so as to present a satisfactory clean and neat appearance. All cleanup costs shall be included in the Contractor’s Bid.
Care shall be taken to prevent spillage on haul routes. Any such spillage shall be removed immediately and the area cleaned.
Excess excavation material from catch basins or similar structures shall be removed from the site immediately. Sufficient material may remain for use as backfill if permitted by the Specifications.
Forms and form lumber shall be removed from the site as soon as practicable after stripping.
Failure of the Contractor to comply with the Engineer’s cleanup orders may result in an order to suspend work until the condition is corrected. No additional compensation will be allowed as a result of such suspension.
============--
Revised 6/15/2017 Contract No. 6001-22E Page 101 of 148
Cleanup and dust control required herein shall also be executed on weekends and other non-working days when needed to preserve the health safety or welfare of the public. The Contractor shall conduct effective cleanup and dust control throughout the duration of the Contract. The Engineer may require increased levels of cleanup and dust control that, in his/her sole discretion, are necessary to preserve the health, safety and welfare of the public. Cleanup and dust control shall be considered incidental to the items of work that they are associated with and no additional payment will be made therefor.
7-8.2 Air Pollution Control. The Contractor shall not discharge smoke, dust, or any other air contaminants into the atmosphere in such quantity as will violate the regulations of any legally constituted authority.
7-8.3 Vermin Control. At the time of acceptance, structures entirely constructed under the Contract shall be free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contract time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors resulting from extermination operations.
7-8.4 Sanitation. The Contractor shall provide and maintain enclosed toilets for the use of employees engaged in the Work. These accommodations shall be maintained in a neat and sanitary condition. They shall also comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps.
Wastewater shall not be interrupted. Should the Contractor disrupt existing sewer facilities, sewage shall be conveyed in closed conduits and disposed of in a sanitary sewer system. Sewage shall not be permitted to flow in trenches or be covered by backfill.
7-8.5 Temporary Light, Power, and Water. The Contractor shall furnish, install, maintain, and remove all temporary light, power, and water at its own expense. These include piping, wiring, lamps, and other equipment necessary for the Work. The Contractor shall not draw water from any fire hydrant (except to extinguish a fire), without obtaining permission from the water agency concerned. The Contractor shall obtain a construction meter for water used for the construction, plant establishment, maintenance, cleanup, testing and all other work requiring water related to this contract. The Contractor shall contact the appropriate water a gency for requirements. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter and any, and all, other charges, deposits and/or fees therefor. Said costs shall be considered incidental to the items of work t hat they are associated with and no additional payment will be made therefor.
7-8.6 Water Pollution Control. The Contractor shall exercise every reasonable precaution to protect channels, storm drains, and bodies of water from pollution. It shall conduct and schedule operations so as to minimize or avoid muddying and silting of said channels, drains, and waters.
Water pollution control work shall consist of constructing those facilities which may be required to provide prevention, control, and abatement of water pollution.
The Contractor shall comply with the California State Water Resources Control Board (SWRCB) Order Number 99-08-DWQ, National Pollutant Discharge Elimination System (NPDES) General Permit Number CAS000002, Waste Discharge Requirements (WD R’s) for Discharges of Stormwater Runoff associated with Construction Activity (General Permit) and subsequent
Revised 6/15/2017 Contract No. 6001-22E Page 102 of 148 adopted modifications and with all requirements of the Storm Water Pollution Prevention and Monitoring Plans for this project in accordance with these regulations.
7-8.7 Drainage Control. The Contractor shall maintain drainage within and through the work areas. Earth dams will not be permitted in paved areas. Temporary dams of sandbags, asphaltic concrete, or other acceptable material will be perm itted when necessary. Such dams shall be removed from the site as soon as their use is no longer necessary.
Temporary Drainage Inlet Protection:
Temporary drainage inlet protection shall be constructed, maintained, and removed at drainage inlets as required downstream of the project boundaries and within the project limits. Temporary drainage inlet protection shall be one of the water pollution control practices for sediment control.
Under no circumstances shall construction runoff enter the storm drain system without adequate controls in place to capture and trap sediment. Throughout the duration of the project the Contractor shall provide protection to meet the changing conditions around each drainage inlet.
Temporary drainage inlet protection shall be installed such that ponded runoff does not encroach on the traveled way or overtop the curb. Gravel-filled bags shall be placed to control ponding and prevent runoff from overtopping the curb. Temporary drainage inlet protection shall be maintained to provide sediment holding capacity. Temporary drainage inlet protection shall be repaired or replaced as needed. Sediment deposits, trash, and debris shall be removed and hauled away as needed or when directed by the project inspector. Removed sediment shall be deposited within the project limits so that the sediment is not subject to erosion by wind or by water. Trash and debris shall be removed and hauled offsite. Gravel -filled bags shall be replaced when the bag material ruptures or when the binding fails. Geotextile fabric shall be removed and replaced when torn. The fabric shall also be replaced with clean fabric when odors from stagnant, ponded water are present.
7-8.8 Noise Control. All internal combustion engines used in the construction shall be equipped with mufflers in good repair when in use on the project with special attention to the City Noise Control Ordinance, Carlsbad Municipal Code Chapter 8.48.
7-9 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS. The Contractor shall be responsible for the protection of public and private property adjacent to the Work and shall exercise due caution to avoid damage to such property.
The Contractor shall repair or replace all existing improvements within the right-of-way which are not designated for removal (e.g., curbs, sidewalks, driveways, fences, walls, signs, utility installations, pavement, structures, etc.) which are damaged or removed as a result of its operations. When a portion of a sprinkler system within the right-of-way must be removed, the remaining lines shall be capped. Repairs and replacements shall be at least equal to existing improvements and shall match them in finish and dimension.
Maintenance of street and traffic signal systems that are damaged, temporarily removed or relocated shall be done in conformance with 307-1.5.
Trees, lawns, and shrubbery that are not to be removed shall be protected from damage or injury.
If damaged or removed due to Contractor’s operations, they shall be resto red or replaced in as nearly the original condition and location as is reasonably possible. Lawns shall be reseeded and covered with suitable mulch.
Revised 6/15/2017 Contract No. 6001-22E Page 103 of 148 The Contractor shall give reasonable notice to occupants or owners of adjacent property to permit them to salvage or relocate plants, trees, fences, sprinklers, and other improvements, within the right-of-way which are designated for removal and would be destroyed because of the Work.
All costs to the Contractor for protecting, removing, and restoring existing improvements shall be included in the Bid.
7-10 PUBLIC CONVENIENCE AND SAFETY.
7-10.1 Traffic and Access. The Contractor’s operations shall cause no unnecessary inconvenience. The access rights of the public shall be considered at all times. Unless otherwise authorized, traffic shall be permitted to pass through the Work as per an approved Traffic Control Plan.
Safe and adequate pedestrian and vehicular access shall be provided and maintained to: fire hydrants; commercial and industrial establishments; churches, schools and parking lots; service stations and motels; hospitals; police and fire stations; and establishments of similar nature.
Access to these facilities shall be continuous and unobstructed unless otherwise approved by the Engineer.
Safe an d adequate pedestrian zones and public transportation stops, as well as pedestrian crossings of the Work at intervals not exceeding 90 m (300 feet), shall be maintained unless otherwise approved by the Engineer.
Vehicular access to residential driveways sh all be maintained to the property line except when necessary construction precludes such access for reasonable periods of time. If backfill has been completed to the extent that safe access may be provided, and the street is opened to local traffic, the Contractor shall immediately clear the street and driveways and provide and maintain access.
The work shall be conducted by the Contractor in a manner to provide a satisfactory surface for traffic.
The Contractor shall cooperate with the various parties in volved in the delivery of mail and the collection and removal of trash and garbage to maintain existing schedules for these services.
The Contractor shall schedule the work so as to prevent damage by all traffic, including but not limited to mail delivery. The Contractor shall not schedule work so as to conflict with trash pickup.
The trash hauling schedule can be obtained by calling the City’s contracted waste disposal company, Coast Waste Management at 760-929-9417.
During overlay operations, the Contr actors schedule for overlay application shall be designated to provide residents and business owners whose streets are to be overlaid sufficient paved parking within an 800 feet distance from their homes or businesses.
Public Notification of Work:
See Section 302-4.4 “Public Convenience and Traffic Control” for details about the notification letter to residences and businesses which is required to be mailed at least 2 weeks prior to the work. In addition to the two-week notification letter, a 72-hr notification door hangar shall be given to all residences and businesses on the affected streets at least 72 hours prior to resurfacing.
Seventy-two (72) hours prior to the start of any construction in the public right-of-way that affects vehicular traffic and/or parking or pedestrian routes, the Contractor shall give written notification
Revised 6/15/2017 Contract No. 6001-22E Page 104 of 148 of the impending disruption. For a full street closure, all residences and/or businesses on the affected street or alley shall be notified. For partial street closures, or curb, sidewalk and driveway repairs, the residences and/or businesses directly affected by the work shall be notified.
The notification shall be hand delivered and shall state the date and time the work will begin and its anticipated duration. The notification shall list two telephone numbers that may be called to obtain additional information. One number shall be the Contractor’s permanent office or field office and the other number shall be a 24 -hour number answered by someone who is knowledgeable about the project. At least one of the phone numbers shall be in the (760) area code. An answering machine shall not be connected to either number. The notification shall also give a brief description of the work and simple instructions to the home or business owner on what they need to do to facilitate the construction. The Contractor shall submit the contents of the notification to the Engineer for approval. Notices shall not be distributed until approved by the Engineer.
For residences, the notificatio n shall be pre -cut in a manner that enables it to be affixed to a doorknob without adhesives. It shall be a minimum size of 3-1/2 inches by 8-1/2 inches and shall be brightly colored with contrasting printing. The material shall be equivalent in strength a nd durability to 65 lb. card stock. The printing on the notice shall be no smaller than 12 point s. An example of such notice is provided in these Special Provisions.
In addition to the notifications, the contractor shall post no parking signs 72 hours in advance of the work being performed. The no parking signs shall state the date and time of parking restriction for a duration not to exceed the time necessary to complete the work at that location. Failure of the contractor to meet the posted date require s re -posting the no parking signs 72 hours in advance of the rescheduled work. If the work is delayed or rescheduled the no parking signs shall be removed and re-posted 72 hours in advance of the rescheduled work.
The preparation, materials, printing and distribution of the notifications shall be included in the contract price bid for traffic control and the Contractor will not be entitled to any additional compensation for printing and distributing these notices.
The contractor shall replace all street markings and striping damaged by construction activities.
The Contractor shall include in its Bid all costs for the above requirements.
7-10.2 Storage of Equipment and Materials in Public Streets. Construction materials shall not be stored in streets, roads, or highways for more than 5 days after unloading. All materials or equipment not installed or used in construction within 5 days after unloading shall be stored elsewhere by the Contractor at its expense unless authorized additional storage time.
Construction equipment shall not be stored at the Work site before its actual use on the Work nor for more than 5 days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer.
Excavated material, except that which is to be used as backfill in the adjacent trench, shall not be stored in public streets unless otherwise permitted. After placing backfill, all excess material shall be removed immediately from the site.
The Contractor shall secure approval, in advance, from authorities concerned for the use of any bridges proposed by it for public use. Temporary bridges shall be clearly posted as to load limit, with signs and posting conforming to cu rrent requirements covering “signs” as set forth in the
Revised 6/15/2017 Contract No. 6001-22E Page 105 of 148 Traffic Manual published by the California Department of Transportation. This manual shall also apply to the street closures, barricades, detours, lights, and other safety devices required.
All costs involved shall be included in the Bid.
Traffic controls shall be in accordance with the plans, The California Manual on Uniform Traffic Control Devices latest edition (FHWA MUTCD as amended for use in California , latest version) and these provisions. If any component in the traffic control system is damaged, displaced, or ceases to operate or function as specified, from any cause , during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace s aid component and shall restore the component to its original location. In the event that the Contractor fails to install and/or maintain barricades or such other traffic signs, markings, delineation or devices as may be required herein, the Engineer may, at his/her sole option, install the traffic signs, markings, delineation or devices and charge the Contractor twenty -five dollars ($25.00) per day per traffic sign or device, or the actual cost of providing such traffic control facility, whichever is the greater.
7-10.3 Street Closures, Detours, Barricades. The Contractor shall comply with all applicable State, County, and City requirements for closure of streets. The Contractor shall provide barriers, guards, lights, signs, temporary bridges, flagpersons, and watchpersons. The Contractor shall be responsible for compliance with additional public safety requirements which may arise. The Contractor shall furnish and install signs and warning devices and promptly remove them upon completion of the Work.
The Contractor shall secure approval, in advance, from authorities concerned for the use of any bridges proposed by it for public use. Temporary bridges shall be clearly posted as to load limit, with signs and posting conforming to current requirements covering “signs” as set forth in the Traffic Manual published by the California Department of Transportation. This manual shall also apply to the street closures, barricades, detours, lights, and other safety devices required.
All costs involved shall be included in the Bid.
Traffic controls shall be in accordanc e with the plans, The California Manual on Uniform Traffic Control Devices latest edition (FHWA MUTCD as amended for use in California, latest version) and these provisions. If any component in the traffic control system is damaged, displaced, or ceases to operate or function as specified, from any cause, during the progress of the work, the Contractor shall immediately repair said component to its original condition or replace said component and shall restore the component to its original location. In the event that the Contractor fails to install and/or maintain barricades or such other traffic signs, markings, delineation or devices as may be required herein, the Engineer may, at his/her sole option, install the traffic signs, markings, delineation or devices and charge the Contractor twenty dollars ($25.00) per day per traffic sign or device, or the actual cost of providing such traffic control facility, whichever is the greater.
7-10.3.1 Construction Area Signs and Control Devices. All construction traffic signs and control devices shall be maintained throughout the duration of work in good order and according to the approved traffic control plan. All construction area signs shall conform to the provisions of Section 206-7.2 et seq. All temporary reflective pavement markers shall conform to the provisions of Section 214-5.1.et seq. All temporary reflective channelizers shall conform to the provisions of Section 214-5.2 et seq. All paint for temporary traffic striping, pavement marking, and curb marking shall conform to the provisions of Section 210-1.6 et seq. except that all temporary paint
Revised 6/15/2017 Contract No. 6001-22E Page 106 of 148 shall be rapid dry water borne conforming to Section 210 -1.6 for materials and Section 310-5 et seq. For workmanship. Warning and advisory signs, lights and devices installed or placed to provide traffic control, direction and/or warning shall be furnished, installed and maintained by the Contractor. Warning and advisory signs, lights and devices shall be promptly removed by the Contractor when no longer required. Warning and advisory signs that remain in place overnight shall be stationary mounted signs. Stationary signs that warn of non -existent conditions shall be removed from the traveled way and from the view of motorists in the traveled way or shielded from the view of the traveling public during such periods that their message does not pertain to existing conditions. Care shall be used in performing excavation for signs in order to protect underground facilities. All excavation required to install stationary construction area signs shall be performed by hand methods without the use of power equipment. Warning and advisory signs that are used only during working hours may be portable signs. Portable signs shall be removed from the traveled way and shielded from the view of the traveling public during non-working hours.
During the hours of darkness, as defined in Division 1, Section 280, of the California Vehicle Code, portable signs shall be illuminated or, at the option of the Contractor, shall be in conformance with the provisions in Section 206 -7.2 et seq. If illuminated traffic cones rather than post -type delineators are used during the hours of darkness, they shall be affixed or covered with reflective cone sleeves as specified in CALTRANS “Standard Specifications”, except the sleeves shall be 7” long. Personal vehicles of the Contractor's employees shall not be parked within the traveled way, including any Section closed to public traffic. Whenever the Contractor’s vehicles or equipment are parked on the shoulder within 6’ of a traffic lane, the shoulder area shall be closed with fluorescent traffic cones or portable delineators placed on a taper in advance of the parked vehicles or equipment and along the edge of the pavement at not less than 25’ intervals to a point not less than 25’ past the last vehicle or piece of equipment. A minimum of nine (9) cones or portable delineators shall be used for the taper. A W20 -1 (Road Work Ahead) or C24 (Shoulder Work Ahead) sign shall be mounted, as required herein, on a signpost or telescoping flag tree with flags. The signpost or flag tree shall be placed where directed by the Engineer.
7-10.3.2 Maintaining Traffic. The Contractor’s personnel shall ma intain a safe buffer distance from any traffic lane occupied by traffic. The Contractor’s equipment shall maintain a safe distance from any traffic or pedestrians.
A minimum of one (1) paved traffic lane , not less than 12’ wide, shall remain open and unobstructed for use by public traffic in each direction of travel at all times. If this is not possible due to road width constraints in certain areas, the Contractor shall submit a separate, additional traffic control plan to the Engineer for review and approval prior to implementation.
For the cold-mill and overlay project limits, the contractor shall pave all cold -milled areas within the same workday. The contractor shall not allow public traffic to drive on the cold-milled surface.
See Section 6-7 for details on working hours and traffic control.
7-10.3.3 Traffic Control System for Lane Closure. A traffic control system consists of closing traffic lanes or pedestrian walkways in accordance with the details shown on the plans, California Manual on Uniform Traffic Control Devices latest edition (FHWA MUTCD as amended for use in California, latest version) and provisions under "Maintaining Traffic" elsewhere in these Provisions. The provisions in this section will not relieve the Contractor from its responsibility to provide such additional devices or take such measures as may be necessary to maintain public safety.
When lanes are closed for only the duration of work periods, all components of the traffic control system, except portable delineators p laced along open trenches or excavation adjacent to the =========~-=-=-=-==
Revised 6/15/2017 Contract No. 6001-22E Page 107 of 148 traveled way, shall be removed from the traveled way and shoulder at the end work period. If the Contractor so elects, said components may be stored at selected central locations, approved by the Engineer, within the limits of the right-of-way.
7-10.3.4 Traffic Control for Permanent and Temporary Traffic Striping. During traffic stripe operations, traffic shall be controlled with lane closures, as provided for under "Traffic Control System for Lane Cl osure" of these Supplemental Provisions or by use of an alternative traffic control plan proposed by the Contractor and approved by the Engineer. The Contractor shall not start traffic striping operations using an alternative plan until the Contractor has submitted its plan to the Engineer and has received the Engineer's written approval of said plan.
7-10.3.5 Temporary Pavement Delineation. Temporary pavement delineation shall be furnished, placed, maintained and removed in accordance with the minimum sta ndards specified in the California Manual on Uniform Traffic Control Devices latest edition published by CALTRANS.
Whenever the work causes obliteration of pavement delineation, temporary or permanent pavement delineation shall be in place prior to opening the traveled way to public traffic. Lane line or centerline pavement delineation shall be provided at all times for traveled ways open to public traffic. All work necessary, including any required lines or marks, to establish the alignment of temporary pa vement delineation shall be performed by the Contractor. When temporary pavement delineation is removed, all lines and marks used to establish the alignment of the temporary pavement delineation shall be removed by grinding.
Surfaces to receive temporary pavement delineation shall be dry and free of dirt and loose material. Temporary pavement delineation shall not be applied over existing pavement delineation or other temporary pavement delineation. Temporary pavement delineation shall be maintained until superseded or replaced with permanent pavement delineation.
Temporary pavement delineation shall be removed when, as determined by the Engineer, the temporary pavement delineation conflicts with the permanent pavement delineation or with a new traffic pattern for the area and is no longer required for the direction of public traffic. When temporary pavement delineation is required to be removed, all lines and marks used to establish the alignment of the temporary pavement delineation shall be removed.
7-10.3.6 Preparation of New, or Modifications and Additions to Existing, Traffic Control Plan Sheets. If no traffic control plans (TCP) or Traffic Control Staging plans (TCP) are included in the project plans, or if the Contractor elects to modify TCP included in the project plans, the Contractor shall have such new or modified TCP prepared and submitted as a part of the Work for any and all construction activities that are located within the traveled way. The Contractor shall have TCP prepared and submitted as a part of the Work for any construction activities that are a part of this project that are not included in the project plans. The Contractor must submit the TCP for the Engineer’s review in conformance with the requirements of Section 2 -5.3, et seq. and obtain the Engineer’s approval of the TCP prior to implementing them. The minimum 20 -day review period specified in Section 2-5.3.1 for shop drawings and submittals shall pertain to each submittal of TCP , new, modified or added to, for the Engi neer’s review. New or revised TCP submittals shall include all TCP needed for the entire duration of the Work. Each phase of the TCP shall be shown in sufficient scale and detail to show the lane widths, transition lengths, curve radii, stationing of featu res affecting the traffic control plan and the methodology proposed to transition to the subsequent TCP phase. When the vertical alignment of the traveled surface differs from the finished pavement elevation vertical curves must also be shown. Such modifications, supplements and/or new design of TCP shall meet the requirements of the Engineer and the California Manual on Uniform Traffic Control Devices latest edition as published
Revised 6/15/2017 Contract No. 6001-22E Page 108 of 148 by CALTRANS. Such modification, addition, supplement, and/or new design of TCP shall be prepared by a registered professional engineer appropriately registered in the State of California.
The Engineer shall be the sole judge of the suitability and quality of any such modifications, supplements, and/or new designs to TCP . The Engineer may approve any such modifications, supplements, and/or new designs to the TCP when, in the Engineer’s sole opinion, such modifications, supplements, and/or new designs to the TCP prepared by the registered professional engineer retained by the Contracto r will be beneficial to the best interests of the Agency. Such modification, addition, supplement, and/or new design shall not be implemented and no work shall be commenced that is contingent on such approval until the changed TCP are approved by the Engin eer. The preparation of such modification, addition, supplement, and/or new designs of TCP shall not presuppose their approval or obligate the Agency in any fashion.
Submittal and review requirements for such modifications, supplements, and/or new designs to TCP shall conform to the requirements of Section 2-5.3 Shop Drawings and Submittals.
7-10.3.7 Payment. The Contractor shall prepare “Traffic Control and Detour Plans” at the contract lump sum price bid and shall include any revisions necessary. The contract lump sum price paid for "Traffic Control Plan Implementation" shall include full compensation for furnishing all labor (including flagging costs), materials (including signs), tools, equipment and incidentals, and for doing all the work involved in p reparation, reproduction and changing of traffic control plans, placing, applying traffic stripes and pavement markers with bituminous adhesive, removing, storing, maintaining, moving to new locations, replacing, and disposing of the components of the traffic control system as shown on the plans and approved additions and modifications, as specified in these supplemental provisions, and as directed by the Engineer. All expenses and time to prepare and review modifications, additions, supplements and/or new TCP designs shall be included in the lump sum bid for traffic control and no additional payment will be made thereof.
Flagging costs will be paid for as a part of the Lump Sum Amount for "Traffic Control Plan Implementation." The cost of labor and material for portable concrete barriers will be paid for at the unit price bid. When there is no bid item the cost of labor and material for portable concrete barriers they will be paid as an incidental to the work being performed and no additional payment will be made thereof. Progress payments for "Traffic Control Plan Implementation" will be based on the percentage of the improvement work completed.
7-10.4 Safety.
7-10.4.1 Safety Orders. The Contractor shall have at the Work site, copies or suitable extracts of: Construction Safety Orders, Tunnel Safety Orders and General Industry Safety Orders issued by the State Division of Industrial Safety. The Contractor shall comply with provisions of these and all other applicable laws, ordinances, and regulations.
Before excavating any trench 5 feet or more in depth, the Contractor shall submit a detailed plan to the Agency showing the design of shoring, bracing, sloping, or other provisions to be made for the workers’ protection from the hazard of caving ground during the excavation of such trench. If the plan varies from the shoring system standards, the plan shall be prepared by a registered Civil Engineer. No excavation shall start until the Engineer has accepted the plan and the Contractor has obtained a permit from the State Division of Industrial Safety. A copy of the permit shall be submitted to the Engineer.
Payment for performing all work necessary to provide safety measures shall be included in the prices bid for other items of work except where separate bid i tems for excavation safety are provided or required by law.
Revised 6/15/2017 Contract No. 6001-22E Page 109 of 148 7-10.4.2 Use of Explosives. Explosives may be used only when authorized in writing by the Engineer, or as otherwise stated in the Specifications. Explosives shall be handled, used, and stored in accordance with all applicable regulations.
The Engineer’s approval of the use of explosives shall not relieve the Contractor from liability for claims caused by blasting operations.
7-10.4.3 Special Hazardous Substances and Processes. Materials that contain hazardous substances or mixtures may be required on the Work. A Material Safety Data Sheet as described in Section 5194 of the California Code of Regulations shall be requested by the Contractor from the manufacturer of any hazardous products used.
Material usage shall be accomplished with strict adherence to California Division of Industrial Safety requirements and all manufacturer warnings and application instructions listed on the Material Safety Data Sheet and on the product container label.
The Contractor shall notify the Engineer if a specified product cannot be used under safe conditions.
7-10.4.4 Confined Spaces.
(a) Confined Space Entry Program. The Contractor shall be responsible for implementing, administering and mainta ining a confined space entry program (CSEP) in accordance with Sections 5156, 5157 and 5158, Title 8, CCR.
Prior to starting the Work, the Contractor shall prepare and submit its comprehensive CSEP to the Engineer. The CSEP shall address all potential physical and environmental hazards and contain procedures for safe entry into confined spaces, including, but not limited to the following:
1. Training of personnel
2. Purging and cleaning the space of materials and residue
3. Potential isolation and control of energy and material inflow
4. Controlled access to the space
5. Atmospheric testing of the space
6. Ventilation of the space
7. Special hazards consideration
8. Personal protective equipment
9. Rescue plan provisions
The Contractor’s submittal shall include the nam es of its personnel, including subcontractor personnel, assigned to the project who will have CSEP responsibilities, their CSEP training, and their specific assignment and responsibility in carrying out the CSEP.
(b) Permit-Required Confined Spaces. Entry into permit-required confined spaces as defined in Section 5157, Title 8, CCR may be required as a part of the Work. All manholes, tanks, vaults, pipelines, excavations, or other enclosed or partially enclosed spaces shall be considered permit- required confined spaces until the pre-entry procedures demonstrate otherwise. The Contractor shall implement a permit space program prior to performing any work in a permit -required confined space. A copy of the permit shall be available at all times for review by Contractor and Agency personnel at the Work site.
Revised 6/15/2017 Contract No. 6001-22E Page 110 of 148 (c) Payment. Payment for implementing, administering, and providing all equipment and personnel to perform the CSEP shall be included in the bid items for which the CSEP is required.
7-10.4.5 Safety and Protection of Workers and Public. The Contractor shall take all necessary precautions for the safety of employees on the work and shall comply with all applicable provisions of Federal, State and Municipal safety laws and building codes to prevent accident s or injury to persons on, about, or adjacent to the premises where the work is being performed. The Contractor shall erect and properly maintain at all times, as required by the conditions and progress of the work, all necessary safeguards for the protection of workers and public and shall use danger signs warning against hazards created by such features of construction as protruding nails, hoists, well holes, and falling materials.
7-11 PATENT FEES OR ROYALTIES. The Contractor shall absorb in its Bid the patent fees or royalties on any patented article or process furnished or used in the Work. The Contractor shall indemnify and hold the Agency harmless from any legal action that may be brought for infringement of patents.
7-12 ADVERTISING. The names, add resses and specialties of Contractors, Subcontractors, architects, or engineers may be displayed on removable signs. The size and location shall be subject to the Engineer’s approval.
Commercial advertising matter shall not be attached to or painted on the surfaces of buildings, fences, canopies, or barricades.
7-13 LAWS TO BE OBSERVED. The Contractor shall keep fully informed of State and National laws and County and Municipal ordinances and regulations which in any manner affect those employed in the Work or the materials used in the Work or in any way affect the conduct of the Work. The Contractor shall at all times observe and comply with such laws, ordinances, and regulations. Municipal ordinances that affect this work include Chapter 11.06. Excavation and Grading. If this notice specifies locations or possible materials, such as borrow pits or gravel beds, for use in the proposed construction project which would be subject to Section 1601 or Section 1603 of the Fish and Game Code, the conditions established pursuant to Section 1601 et seq. of the Fish and Game Code shall become conditions of the contract.
7-14 ANTITRUST CLAIMS. Section 7103.5 of the Public Contract Code provides:
“In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C.
Sec 15) or Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or subcontract.
The assignment shall be made and become effective at the time the awarding body tenders final payment to the contractor, without further acknowledgment of the parties.”
Revised 6/15/2017 Contract No. 6001-22E Page 111 of 148 SECTION 8 – FACILITIES FOR AGENCY PERSONNEL
8-1 GENERAL. Facilities are not required for agency personnel.
Revised 6/15/2017 Contract No. 6001-22E Page 112 of 148 SECTION 9 – MEASUREMENT AND PAYMENT
9-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK.
9-1.1 General. Unless otherwise specified, quantities of work shall be determined from measurements or dimensions in horizontal planes. However, linear quantities of pipe, piling, fencing and timber shall be considered as being the true length measured along longitudinal axis.
Unless otherwise provided in Specifications, volumetric quantities shall be the product of the mean area of vertical or horizontal sections and the intervening horizontal or vertical dimension.
The planimeter shall be considered an instrument of p recision adapted to measurement of all areas.
9-1.2 Methods of Measurement. Materials and items of work which are to be paid for on basis of measurement shall be measured in accordance with methods stipulated in the particular sections involved.
9-1.3 Certified Weights. When payment is to be made on the basis of weight, the weighing shall be done on certified platform scales or, when approved by the Engineer, on a completely automated weighing and recording system. The Contractor shall furnish the Enginee r with duplicate licensed weighmaster’s certificates showing actual net weights. The Agency will accept the certificates as evidence of weights delivered.
9-1.4 Units of Measurement. The system of measure for this contract shall be the U.S.
Standard Measures.
9-2 LUMP SUM WORK. Items for which quantities are indicated “Lump Sum”, “L.S.”, or “Job”, shall be paid for at the price indicated in the Bid. Such payment shall be full compensation for the items of work and all work appurtenant thereto.
When required by the Specifications or requested by the Engineer, the Contractor shall submit to the Engineer within 15 days after award of Contract, a detailed schedule in triplicate, to be used only as a basis for determining progress payments on a lump sum contract or designated lump sum bid item. This schedule shall equal the lump sum bid and shall be in such form and sufficiently detailed as to satisfy the Engineer that it correctly represents a reasonable apportionment of the lump sum.
9-3 PAYMENT.
9-3.1 General. The quantities listed in the Bid schedule will not govern final payment. Payment to the Contractor will be made only for actual quantities of Contract items constructed in accordance with the Plans and Specifications. Upon completion of construction, if the actual quantities show either an increase or decrease from the quantities given in the Bid schedule, the Contract Unit Prices will prevail subject to the provisions of Section 3-2.2.1.
The unit and lump sum prices to be paid shall be full compensation for the items of wor k and all appurtenant work, including furnishing all materials, labor, equipment, tools, and incidentals.
Payment will not be made for materials wasted or disposed of in a manner not called for under the Contract. This includes rejected material not unloaded from vehicles, material rejected after it
Revised 6/15/2017 Contract No. 6001-22E Page 113 of 148 has been placed, and material placed outside of the Plan lines. No compensation will be allowed for disposing of rejected or excess material.
Payment for work performed or materials furnished under an Assessme nt Act Contract will be made as provided in particular proceedings or legislative act under which such contract was awarded.
Whenever any portion of the Work is performed by the Agency at the Contractor’s request, the cost thereof shall be charged against the Contractor, and may be deducted from any amount due or becoming due from the Agency.
Whenever immediate action is required to prevent injury, death, or property damage, and precautions which are the Contractor’s responsibility have not been taken and are not reasonably expected to be taken, the Agency may, after reasonable attempt to notify the Contractor, cause such precautions to be taken and shall charge the cost thereof against the Contractor, or may deduct such cost from any amount due or becomin g due from the Agency. Agency action or inaction under such circumstances shall not be construed as relieving the Contractor or its Surety from liability.
Payment shall not relieve the Contractor from its obligations under the Contract; nor shall such payment be construed to be acceptance of any of the Work. Payment shall not be construed as the transfer of ownership of any equipment or materials to the Agency. Responsibility of ownership shall remain with the Contractor who shall be obligated to store any fully or partially completed work or structure for which payment has been made; or replace any materials or equipment required to be provided under the Contract which may be damaged, lost, stolen or otherwise degraded in any way prior to acceptance of the Work, except as provided in Section 6-10.
Guarantee periods shall not be affected by any payment but shall commence on the date of recordation of the “Notice of Completion.”
If, within the time fixed by law, a properly executed notice to stop payment is filed with the Agency, due to the Contractor’s failure to pay for labor or materials used in the Work, all money due for such labor or materials will be withheld from payment to the Contractor in accordance with applicable laws.
At the expiration of 35 days from the date of acceptance of the Work by the Board, or as prescribed by law, the amount deducted from the final estimate and retained by the Agency will be paid to the Contractor except such amounts as are required by law to be withheld by properly e xecuted and filed notices to stop payment, or as may be authorized by the Contract to be further retained.
9-3.2 Partial and Final Payment. The Engineer will, after award of Contract, establish a closure date for the purpose of making monthly progress payments. The Contractor may request in writing that such monthly closure date be changed. The Engineer may approve such request when it is compatible with the Agency’s payment procedure.
Each month, the Engineer will make an approximate measurement of the work performed to the closure date as basis for making monthly progress payments. The estimated value will be based on contract unit prices, completed change order work and as provided for in Section 9-2 of these General Provisions. Progress payments shall be made no later than thirty (30) calendar days after the closure date. Five (5) working days following the closure date, the Engineer shall complete
Revised 6/15/2017 Contract No. 6001-22E Page 114 of 148 the detailed progress pay estimate and submit it to the Contractor for the Contractor’s information.
Should the Contractor assert that additional payment is due, the Contractor shall within ten (10) days of receipt of the progress estimate, submit a supplemental payment request to the Engineer with adequate justification supporting the amount of supplemental payment request. Upon receipt of the supplemental payment request, the Engineer shall, as soon as practicable after receipt, determine whether the supplemental payment request is a proper payment request. If the Engineer determines that the supplemental payment request is not proper, then the request shall be returned to the Contractor as soon as practicable, but not later than seven (7) days after receipt. The returned request shall be ac companied by a document setting forth in writing the reasons why the supplemental payment request was not proper. In conformance with Public Contract Code Section 20104.50, the City shall make payments within thirty (30) days after receipt of an undisputed and properly submitted supplemental payment request from the Contractor. If payment of the undisputed supplemental payment request is not made within thirty (30) days after receipt by the Engineer, then the City shall pay interest to the Contractor equiva lent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
From each progress estimate, 5 percent will be deducted and retained by the Agency, and the remainder less the amount of all previous payments will be paid. After 50 percent of the Work has been completed and if progress on the Work is satisfactory, the deduction to be made from remaining progress estimates and from the final estimate may be limited to $500 or 5 percent of the first half of total Contract amount, whichever is greater.
No progress payment made to the Contractor or its sureties will constitute a waiver of the liquidated damages under 6-9.
As provided in Section 22300 of the California Public Contract Code, the Contractor may substitute securities for any monies withheld by the Agency to ensure performance under the Contract.
After final inspection, the Engineer will make a Final Payment Estimate and process a corresponding payment. This estimate will be in writing and shall be for the total amount owed the Contractor as determined by the Engineer and shall be itemized by the contract bid item and change order item with quantities and payment amounts and shall show all deductions made or to be made for prior payments and amounts to be deduct ed under provisions of the contract. All prior estimates and progress payments shall be subject to correction in the Final Payment Estimate.
The Contractor shall have 30 calendar days from receipt of the Final Payment Estimate to make written statement disputing any bid item or change order item quantity or payment amount. The Contractor shall provide all documentation at the time of submitting the statement supporting its position. Should the Contractor fail to submit the statement and supporting documentation within the time specified, the Contractor acknowledges that full and final payment has been made for all contract bid items and change order items.
If the Contractor submits a written statement with documentation in the aforementioned time, the Engineer will review the disputed item within 30 calendar days and make any appropriate adjustments on the Final Payment. Remaining disputed quantities or amou nts not approved by the Engineer will be subject to resolution as specified in Section 3-5, Disputed Work.
The written statement filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said dispute d items. The Engineer will consider the merits of
Revised 6/15/2017 Contract No. 6001-22E Page 115 of 148 the Contractor’s claims. It will be the responsibility of the Contractor to furnish within a reasonable time such further information and details as may be required by the Engineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying payment for the disputed items.
9-3.2.1 Payment for Claims. Except for those final payment items disputed in the written statement required in Section 9-3.2 all claims of any dollar amount shall be submitted in a written statement by the Contractor no later than the date of receipt of the final payment estimate. Those final payment items disputed in the written statement required in Section 9-3.2 shall be submitted no later than 30 days after receipt of the Final Payment estimate. No claim will be considered that was not included in this written statement, nor will any claim be allowed for which written notice or protest is required unde r any provision of this contract including Sections 3 -4 Changed Conditions, 3-5 Disputed Work, 6-6.3 Payment for Delays to Contractor, 6-6.4 Written Notice and Report, or 6 -7.3 Contract Time Accounting, unless the Contractor has complied with notice or protest requirements.
The claims filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said claims. The Engineer will consider and determine the Contractor’s claims and it will be the responsibility of the Contractor to furnish within a reasonable time such further information and details as may be required by the Engineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying the claims.
Payment for claims shall be processed within 30 calendar days of their resolution for those claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Section 3-5, Disputed Work, for those claims remaining in dispute.
9-3.3 Delivered Materials. When provided for in the Specifications, and subject to the limitation and conditions therein, the cost of materials and equipment delivered but not incorporated into the Work will be included in the progress estimate.
9-3.3.1 Delivered Materials. The cost of materials and equipment delivered but not incorporated into the work will not be included in the progress estimate.
9-3.4.1 Mobilization and Preparatory Work. Payment for Mobilization and preparatory work will be made at the stipulated lump-sum price of $50,000 and includes full compensation for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment and incidentals, and for doing all the work involved in mobilization and preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidental to preparing to conduct work on and off the project site and other offsite facilities necessar y for work on the project; for all other facilities, sureties, work and operations which must be performed or costs incurred prior to beginning work on various contract items on or off the project site, excepting those specifically paid for under separate sections of these specifications. The Contractor hereby agrees that the stipulated lump sum amount is sufficient for Mobilization and Preparatory Work, as described in this section, and that the Contractor shall have no right to additional compensation for Mobilization and Preparatory Work.
Progress payments for Mobilization and Preparatory Work will be made as follows:
For the first progress payment (after the issuance of the Notice to Proceed), forty percent (40%) of the amount bid for Mobilization and Preparatory Work will be allowed. For the second progress
Revised 6/15/2017 Contract No. 6001-22E Page 116 of 148 payment, an additional sixty percent (60%) of the amount bid for mobilization and preparatory work will be allowed therefor.
9-4 BID ITEMS. Payment for each Bid Item shall be made at the quantity and type as listed in the Contractor's Proposal. All work shown or mentioned on the plans, in the Contract Documents, General Provisions, or Technical Provisions/Specifications shall be considered as included in the Bid Items. Contractor must protect existing utilities, improvements, landscaping, irrigation systems, and vegetation in place. If damaged during the work, Contractor is responsible to repair or replace any utilities, improvements, landscaping, irrigation systems, and vegetation at his expense.
Mobilization (Stipulated Lump Sum)
Mobilization shall be at the stipulated contract unit price per Lump Sum and shall include full compensation for conforming to the requirements of Section 9 -3.4.1, “Mobilization and Preparatory Work,” in these Supplemental Provisions, as specified in the Standard Specifications, and as directed by the Engineer. No additional compensation shall be allowed.
Public Notification of Work (Lump Sum)
Public notification of the work shall be at the contract unit price Lump Sum and shall include full compensation for conforming to the requirements of Section 7-10.1 and Section 302 -4.7. No additional compensation shall be allowed.
Prepare Water Pollution Control Program (Lump Sum)
Preparation of the Water Pollution Control Program documents shall be at the contract unit price Lump Sum and shall include full compensation for conforming to the requirements of Section 7-
8.6. No additional compensation shall be allowed.
Prepare Water Pollution Control Program (Lump Sum)
Preparation of the Water Pollution Control Program documents shall be at the contract unit price Lump Sum and shall include full compensation for conforming to the requirements of Section 7-
8.6. No additional compensation shall be allowed.
Temporary Drainage Inlet Protection (Lump Sum)
Temporary Drainage Inlet Protection shall be at the contract unit price Lump Sum and shall include full compensation for conforming to the requirements of Section 7-8.6 and Section 7-8.7.
This includes, but i s not limited to, to the construction, maintenance, and removal of temporary drainage inlet protection at drainage inlets as required downstream of the project boundaries and within the project limits. No additional compensation shall be allowed.
Prepare Traffic Control and Detour Plans (Lump Sum)
Preparation of Traffic Control and Detour Plans shall be at the contract price Lump Sum and shall include full compensation for conforming to the requirements of Section 7 -10.3, including development of the proje ct traffic control plans and detour plans as well as any revisions as required by the agency. No additional compensation shall be allowed.
Traffic Control Plan Implementation (Lump Sum)
Traffic Control Plan Implementation shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Section 7 -10, including development of the project traffic control plan, flagmen, warning signs, changeable message signs, temporary items, maintenance, repair, re placement, removals, all other appurtenances, as shown on the
Revised 6/15/2017 Contract No. 6001-22E Page 117 of 148 Plans, as specified in the Standard Specifications, these Supplemental Provisions, and as directed by the Engineer. No additional compensation shall be allowed.
Street Sweeping and Dust Control (Lump Sum)
Street Sweeping and Dust Control shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Section 7-8 and Section 302-4.8.2.2. This includes, but is not limited to, scheduling street sweeping to occur following slurry sealing on each individual street. No additional compensation shall be allowed.
Clearing and Grubbing, Weed Killing, and Tree Trimming (Lump Sum) Clearing and Grubbing, Weed Killing, and Tree Trimming shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Section 300-1 and these Special Provisions. No additional compensation shall be allowed.
Survey Monument Field Survey, Set Reference Ties, Pre -Construction Corner Record (Lump Sum)
A Survey Monument Field Survey, Setting Reference Ties, and filing a Pre-Construction Corner Record with the County for portions of the work requiring overlay shall be at the contract price per Lump Sum and shall include full compensation for conforming to the requirements of Section 2-
9. No additional compensation shall be allowed.
Tie Out and Re-establish Survey Monuments, Pre-Construction Corner Record (Each) Tying Out and Re-establishing Survey Monuments and filing a Pre -Construction Corner Record with the County for portions of the work requiring overlay shall be at the contract price Each for each monument requiring re-establishment and shall include full compensation for conforming to the requirements of Section 2-9. No additional compensation shall be allowed.
Remove Existing Thermoplastic (Lump Sum)
The contract unit price paid for this bid item shall constitute full compensation for the removal of thermoplastic striping conforming to the requirements in Section 314-3. This shall include, but is not limited to, furnishing all labor, materials, equipment, tools and incidentals and for performing all the work complete and accepted in place. No additional compensation shall be allowed.
Cold Mill 2" AC Cold Milling and Disposal of Grindings - For Patching Only (Square Feet) The contract unit price paid for this bid item shall constitute full compensation for two (2) inches deep asphalt concrete cold milling and disposal of grindings in areas where patching is necessary before slurry sealing; all of which conforming to the requirements in Section 302-15. The area set forth in the bid item is for estimating purposes only and the final quantities will be as measured in the field by the City Inspector.
Cold Mill 3" AC Cold Milling and Disposal of Grindings (Square Feet) The contract unit price paid for this bid item shall constitute full compensation for three (3) inches deep asphalt concrete cold milling and disposal of grindings in areas where overlay of new, polymer modified asphalt concrete is shown on the project Plans; all of which conforming to th e requirements in Section 302-15. No additional compensation shall be allowed.
Construct 2" Type III-C3-PG-64-10-R0 (WMA Additive Optional) - For Patching Only (at 2” cold mill and removal locations) (Tons)
The contract unit price paid for this bid item shall constitute full compensation for two (2) inches deep of asphalt concrete (AC) where patching is necessary before slurry sealing; all of which conforming to the requirements in Section 203-5. Warm mix asphalt (WMA) additive may be used
Revised 6/15/2017 Contract No. 6001-22E Page 118 of 148 as an option to help facilitate proper compaction requirements. The amount of AC set forth in the bid item is for estimating purposes only and the final quantities will be as measured and calculated in the field by the City Inspector.
Construct 3" Type III-C2-PG 64-28PM-R15 AC (WMA Additive Optional) (at 3” cold mill and removal locations) (Tons)
The contract unit price paid for this bid item shall constitute full compensation for three (3) inches deep of asphalt concrete (AC) in areas where overlay is shown on the project Plans; all of which conforming to the requirements in Section 203-5. Warm mix asphalt (WMA) additive may be used as an option to help facilitate proper compaction requirements. No additional compensation shall be allowed.
Crack Seal streets with hot applied crack sealant, crack sealant shall be Elastoflex 670 (Polyskin). DETACK detackifer shall be used on all crack seal immediately following application (Boxes)
The contract unit price paid for this bid item shall constitute full compensation for each box of Elastoflex 670 (Polyskin) crack sealant conforming to the requirements of Section 203-10 and Section 302 -15 shall include but not be limited to: furnishing all labor, tools, equipment, and materials necessary for doing the work as outlined in these Special Provisions. This bid item shall also include costs for furnishing all labor, tools, equipment, and materials necessary for applying DETACK detackifer on all crack seal immediately following application. The number of boxes of crack seal set forth in the bid item is for estimating purposes only and the final quantities will be accounted for in the field by the City Inspector.
Rout cracks (using Crafco Model 30 or approved equal) as directed by City inspector (Linear Feet)
The contract unit price paid for this bid item shall constitute full compensation for routing by linear foot and conforming to the requirements of Section 203-10 and Section 302-15. This bid item shall include, but not be limited to: furnishing all labor, tools, equipment, and materials necessary for doing the work as outlined in these Special Provisions. The amount of routing linear feet set forth in the bid item is for estimating purposes only and the final quantities will be measured in the field by the City Inspector.
Protect Utility Covers, MH, and vaults in place (Lump Sum) The contract unit price paid for this bid item shall constitute full compensation for locating, surveying, and record ing locations of all appurtenances in th e roadway conforming to the requirements of Section 302-5.8. No additional compensation shall be allowed.
Slurry Seal, Type I-PMCQS-1h-EAS w/2.5% Polymer by Weight of Residual Asphalt (in bike lanes and buffers) (ELT)
The contract unit price of extra-long ton (ELT) paid for this bid item shall constitute full compensation for polymer modified, type 1 slurry seal conforming to the requirements of Sections 203-3 and 302-4 of the Standard Specifications, and 203 -4 of these Special Provisions. Type I slurry seal will be placed in bike lanes and buffers as illustrated on the project Plans and as described in these Special Provisions, Section 302-4.8.2.4. No additional compensation shall be allowed.
Slurry Seal, Type II-PMCQS-1h-EAS w/2.5% Polymer by Weight of Residual Asphalt (in travel lanes and turn pockets) (ELT)
The contract unit price of extra -long ton (ELT) paid for this bid item shall constitute full compensation for polymer modified, type 2 slurry seal conforming to the requirements of Sections
Revised 6/15/2017 Contract No. 6001-22E Page 119 of 148 203-3 and 302-4 of the Standard Specifications, and 203-4 of these Special Provisions, Section 302-4.8.2.4. Type II slurry seal will be placed in vehicular travel lanes as illustrated on the project Plans and as described in these Special Provisions. No additional compensation shall be allowed.
Install Dual Curb Ramps; Caltrans Std. Plan A88A, Detail A (Each) The contract unit price paid for this bid item shall constitute full compensation to furnish and install a dual curb ramp per Caltrans Standard Plan A88A, Detail A and in accordance with the plans , contract documents, and in conformance with Section 303-5. This includes, but is not limited to, surveying, transitions, excavation, forming, base material, compaction, sawcutting, and removing and replacing pavement adjacent to the curb ramp. No additional compensation shall be allowed.
Install Curb Ramp; Caltrans Std. Plan A88A, Detail B (Each) The contract unit price paid for this bid item shall constitute full compensation to furnish and install a curb ramp per Caltrans Standard Plan A88A, Detail B and in accordance with the plans, contract documents, and in conformance with Section 303-5. This includes, but is not limited to, surveying, transitions, excavation, forming, base material, compaction, sawcutting, and removing and replacing pavement adjacent to the curb ramp. No additional compensation shall be allowed.
Install Curb Ramp; Caltrans Std. Plan A88A, Case C (Each) The contract unit price paid for this bid item shall constitute full compensation to furnish and install a curb ramp per Caltrans Standard Plan A88A, Case C and in accordance with the plans, contract documents, and in conformance with Section 303-5. This includes, but is not limited to, surveying, transitions, excavation, forming, base material, compaction, sawcutting, and removing and replacing pavement adjacent to the curb ramp. No additional compensation shall be allowed.
Temporary pavement markers (Lump Sum)
The contract unit price paid for this bid item shall constitute full compensation to furnish and install temporary pavement markers and in accordance with the plans , contract documents , and in conformance with Sections 214-6 and 315-4. No additional compensation shall be allowed.
Striping, Thermo, and RPMs per Plans and Caltrans Details (Lump Sum) The contract unit price paid for this bid item shall constitute full compensation to furnish and install Striping, Thermo, and RPMs per Plans and Caltrans Details and in accordance with the plans , contract documents , and in conformance with Section 214 -4 as well as Section 314 -3. This includes, but it not limited to green traffic paint as specified in Section 214-4.3. No additional compensation shall be allowed.
Install Blue fire hydrant reflective pavement markers (Each) The contract unit price paid for this bid item shall constitute full compensation to c furnish and install Blue fire hydrant reflective pavement markers in accordance with the plans , contract documents, and in conformance with Section 214 -6. The number of blue fire hydrant reflective pavement markers set forth in the bid item is for estimating purposes only and the final quantities will be accounted for in the field by the City Inspector.
Replace water valve and survey monument boxes and adjust to grade (Each) The contract unit price paid for this bid item shall constitute full compensation to replace water valves and survey monument boxes and adjust them to grade in accordance with the plans , contract documents, and in conformance with Section 302-5.8. The number of water valves and survey monument boxes set forth in the bid item is for estimating purposes only and the final quantities will be accounted for in the field by the City Inspector.
Revised 6/15/2017 Contract No. 6001-22E Page 120 of 148 Adjust manholes to grade (Each)
The contract unit price paid for this bid item shall constitute full compensation to adjust manholes to grade in accordance with the plans, contract documents, and in conformance with Section 302-
5.8. The number of manhole boxes set forth in the bid item is for estimating purposes only a nd the final quantities will be accounted for in the field by the City Inspector.
Replace Traffic Signal Detector Loop, Type D (Each)
The contract unit price paid for this bid item shall constitute full compensation to replace traffic signal detector loops, type D, in accordance with the plans, contract documents, and as described in conformance with Section 302 -15.2. This includes, but is not limited to, installing a new, dedicated DLC with home run back to the cabinet for every existing loop that is currently sliced with other loops connecting to one DLC back to a cabinet. The number of detector loops set forth in the bid item is for estimating purposes only and the final quantities will be accounted for in the field by the City Inspector.
Replace Traffic Signal Detector Loop, Type E (Each)
The contract unit price paid for this bid item shall constitute full compensation to replace traffic signal detector loops, type E, in accordance with the plans, contract documents, and as described in conformance with Section 302 -15.2. This includes, but is not limited to, installing a new, dedicated DLC with home run back to the cabinet for every existing loop that is currently sliced with other loops connecting to one DLC back to a cabinet. The number of detector loops set forth in the bid item is for estimating purposes only and the final quantities will be accounted for in the field by the City Inspector.
Replace Induction Loop System and Install Video/ Radar Detection System (La Costa Ave./ Saxony Dr. Intersection) (Lump Sum)
The contract unit price paid for this bid item shall constitute full compensation to replace the induction loop system with a Iteris Vantage Next Vector video/ radar detection system for intersection of La Costa Ave./ Saxony Dr. Intersection , in accordance with the plans , contract documents, and as described in conformance with Sections 700 and 701 and the City of Carlsbad Traffic Signal and Electrical Specifications. No additional compensation shall be allowed.
Revised 6/15/2017 Contract No. 6001-22E Page 121 of 148
SUPPLEMENTAL PROVISIONS TO
“GREENBOOK”
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 2, CONSTRUCTION MATERIALS
SECTION 200 - ROCK MATERIALS
200-2 UNTREATED BASE MATERIALS
200-2.1 General. Add the following: Aggregate base shall be Crushed Aggregate Base per Greenbook Section 200-2 and as specified herein.
200-2.2 Crushed Aggregate Base. Add the following: Crushed Aggregate Base shall be free from organic matter and other deleterious substances and shall be of such nature that it can be compacted readily under watering and rolling to form a firm, stable base.
The aggregate shall not be treated with lime, cement or other chemical material before tests are performed.
Samples for testing shall represent every 500 cubic yards or one day's production, whichever is smaller. If the results of the aggregate grading tests do not meet the requirements for Percentage Passing Sieve as specified in Table 200-2.2.2 but meet the Quality Requirements as specified in Table 200-2.2.3, placement of the aggregate base may be continued for the remainder of that day. However, another day's work may not be started until test results indicate to the satisfaction of the Engineer that the next material to be used in the work will comply with the requirements specified for Percentage Passing Sieve.
If the results of both the aggregate grading and Sand Equivalent tests do not meet the requirements of Section 200-2.2, the aggregate base which is represented by these tests shall be removed. However, if requested by the Contractor, and approved at the sole discretion of the Engineer, the aggregate base may remain in place and the Contractor shall pay to the City $50 per cubic yard for such aggregate base left in place. The City may deduct this amount from any moneys due, or that may be come due, to the Contractor under the contract.
SECTION 203 - BITUMINOUS MATERIALS
203-3 EMULSIFIED ASPHALT.
203-3.1 General. Replace the entire subsection with the following:
For slurry seal, emulsified asphalt shall be polymer modified emulsion. It shall contain polymer mixed with a paving asphalt uniformly emulsified with water and an emulsifying or stabilizing agent. The polymer shall be neoprene, or butadiene and styrene copolymer. The polymer must be homogenous and milled into the emulsified asphalt at the colloid mill. Polymer modified emulsion shall content a minimum of 2.5% polymer by weight of residual asphalt, as determined
Revised 6/15/2017 Contract No. 6001-22E Page 122 of 148 by Caltrans Test 401. A Certificate of Compliance conforming to 4 -1 of the Greenbook shall be submitted to the Engineer prior to application.
203-3.4 Physical Properties.
203-3.4.5 Polymer modified Emulsion (PME). Add the following:
For slurry seal, p olymer modified emulsion must be grade PMCQS -1h (cationic) and have the values of the properties shown in the following table:
Polymer Modified Emulsion
Property
Test method
Value
Min Max
Tests on emulsion:
Saybolt Furol Viscosity @ 25 °C,
SFSa
AASHTO T 59 15 90
Sieve test, % AASHTO T 59 -- 0.30
Storage stability, 1 day, % AASHTO T 59 -- 1
Residue by evaporation, % California Test 331 57 --
Particle charge AASHTO T 59 Positive
Tests on residue by evaporation test
Penetration, 25 °C AASHTO T 49 40 90
Ductility, 25 °C, mm AASHTO T 51 400 --
Torsional recovery, % California Test 332 18 --
Polymer content, % by wt. of
residual asphalt
California Test 401 2.5 --
Note:
aSFS means Saybolt Furol seconds
Sampling must comply with Caltrans Standard Specifications Section 94-1.03.
203-4 NOT USED
Add the following:
203-4 EMULSION-AGGREGATE SLURRY
203-4.1 General. Add the following:
Emulsion-Aggregate Slurry shall be polymer -modified (min 2.5% polymer by weight of residual asphalt), cationic quick -set (PMCQS-1h) and shall conform to the requirements of 203 -3, and 302-4 of the Greenbook.
A Certificate of Compliance conforming to 4 -1.5 of the Greenbook shall be submitted to the Engineer prior to application.
203-6 ASPHALT CONCRETE.
203-6.1 General. Add the following:
Asphalt Concrete (AC) for patches shall be Type III -C3-PG 64 -10-R0. No recycled asphalt pavement (RAP) shall be used in the AC mix used for patching.
Revised 6/15/2017 Contract No. 6001-22E Page 123 of 148
Asphalt Concrete for full width overlay shall be Type III-C2-PG 64-28PM-R15. Asphalt Concrete in base course, if necessary or required by the City Inspector, shall be Type III-B2-PG 64-10-R15.
No more than 15% RAP shall be used in the full width overlay and base course AC mixes.
203-6.3 Job Mix Formula (JMF) and Mix Designs. Add the following:
Asphalt Concrete (AC) shall be Type III-C3-PG 64-10-R0 for patches and shall be Type III-C2- PG 64-28PM-R15 for full width overlay; both of which with Warm Mix Asphalt (WMA) additive technology optional.
No reclaimed asphalt pavement (RAP) is allowed in the AC mix used for patching. No more than 15% RAP is allowed in any AC mixes used for base course or full width overlay. If more RAP than allowed amount is used in any portion of asphalt concrete for any part of the project, that part will be rejected, and the contractor will be required to remove and replace that section at its own cost.
If the use of WMA additive is desired, the WMA additive used must be on the Caltrans Authorized Material List for WMA authorized technologies in effect as of the date of advertisement of the contract, https://mets.dot.ca.gov/aml/WarmMixAsphaltTechnologiesList2.php?print=yes. Only additive technologies are acceptable. No foaming or water injection technology shall be used.
A technical representative for the WMA additive technology must attend the Preconstruction Meeting should WMA be used by the Contractor.
203-6.4.4 Composition and Grading. Add the following:
Evaluation of asphalt concrete shall be determined from samples of final asphalt concrete material. In addition to evaluation of the final asphalt material, samples of aggregate, RAP, and asphalt binder will be taken for testing. In case of dispute between the contractor and the Agency, the Engineer has the authority to request core samples for analysis from the placed asphalt concrete for any of the acceptance criteria, at the locations determined by the Engineer. All samples shall be taken in accordance with California Test 125, and the following table:
Sampling Location
Asphalt Concrete • Trucks, or
• Mat behind the paver
Aggregate • Cold feed belts, or
• Hot bins prior to addition of asphalt binder
RAP • RAP system, or
• RAP feed belts
Asphalt Binder • Asphalt binder supplier, or
• Storage tanks at the plant during production
When behind the paver or core samples of asphalt concrete are to be used for evaluation, sufficient size samples shall be taken to ensure representative and adequate quantity of material for the required testing.
When using core samples, the samples must be properly prepared to safeguard against influx of outside contaminates and so that the cut surfaces do not influence the test results. ~~ \..
Revised 6/15/2017 Contract No. 6001-22E Page 124 of 148
Materials sampling and testing of the asphalt concrete shall be on a lot basis. A Lot shall be defined as the amount of pavement placed in 1 day. A Sub -Lot shall be defined as 500 tons.
Should the amount of pavement placed in 1 day be less than 500 tons, the Sub-Lot and Lot shall be one and the same. Each Lot shall be from a single source unless otherwise approved by the Engineer. The samples and testing results shall be representative of their entire sample sub-lot.
203-6.8 Storage. Replace existing section with the following: Storage of asphalt concrete shall not be allowed.
203-10 NOT USED
Add the following:
203-10 ASPHALT PAVEMENT CRACK SEALANTS.
203-10.1 Hot Pour Crack Sealant and Routing. Crack sealant shall be Elastoflex 670 (Polyskin) at 70 boxes per pallet. DETACK detackifer shall be used on all crack seal immediately following application – Unit: Box
The Contractor will rout cracks as directed by the City Inspector. All cracks will be crack sealed, whether routed or not. The Contractor shall thoroughly clean and seal all cracks and joints in the pavement and apply hot applied crack sealant. The Contractor shall provide hot applied Elastoflex 670 (Polyskin) crack sealant at 70 boxes per pallet. DETACK detackifer shall be used on all crack seal immediately following application.
The Contractor shall use “V” squeegees to strike off excess material from the street surface and shall use DETACK detackifier to spray all crack sealant immediately after the material is squeegeed.
The Contractor will be required to maintain all traffic, through and local, as required. Accordingly, the Contractor will not be allowed to seal more than one-half the roadway width at any given time.
The Contractor shall post “No Parking” signs on each st reet 48 hrs. prior to routing and/or crack sealing.
It shall be the responsibility of the Contractor to provide, install and maintain signs, lights, flagmen, barricades, arrow boards and other devices as may be necessary to properly protect the work and to provide for safe and convenient travel by the public through the construction area. Flagmen shall use “STOP” and “SLOW” paddles and shall be properly attired and equipped with safety devices.
The Contractor shall use a mobile street sweeper to clean the street after the routing is completed per street and before the street is crack sealed. The Contractor shall blow out all cracks and joints with an air compressor with wand attachment with a nozzle pressure of at least 125 psi. On cracks that have e xisting weeds growing within, if the weeds are not removed during routing, the Contractor shall use a “Billy goat” or similar machine equipped with a wire brush wheel to remove the weeds or shall use a heat lance capable of providing air temperatures of 2500 degrees F and will be required to remove all forms of vegetation and moisture ahead of the sealing operation. All joints and cracks must be dry and free of moisture before installation of the crack sealant. The crack sealing material shall not be applied when the weather is foggy or when rain threatens.
Revised 6/15/2017 Contract No. 6001-22E Page 125 of 148 The sealant shall be supplied in solid form which, when melted and properly applied with a squeegee, forms a resilient and adhesive compound that will effectively seal cracks and joints in asphalt concrete pavement. The sealant shall have a minimum pot application life of twelve hours and have re-heat capability at least one time after initial heat-up.
Router(s) shall be Crafco Model 30 or approved equal. The router shall provide a 1/2” wide cut and be set to cut 3/4” depth. The City Inspector will direct the Contractor on which cracks to rout on each street and will measure the length of each routed crack for payment purposes. Payment for routing will be per linear foot of routed crack.
Payment of cra ck sealant shall be per box of crack sealant used. The Contractor and the City Inspector will count the number of boxes of crack sealant used on the project streets. The Contractor will be paid for the actual amount of crack sealant material used, based on the number of boxes used on the project.
SECTION 206 - MISCELLANEOUS METAL ITEMS
Add the following section:
206-7 PORTABLE CHANGEABLE MESSAGE SIGN (PCMS)
Add the following section:
206-7.1 General. Each portable changeable message sign (PCMS) unit sha ll consist of a controller unit, a power supply, and a structural support system all mounted on a trailer. The PCMS unit shall be assembled to form a complete self-contained portable changeable message sign, which can be delivered to the site of the work a nd placed in immediate operation. The complete PCMS unit shall be capable of operating in an ambient air temperature range of -20ºC (-4ºF) to +70ºC (158ºF) and shall not be affected by unauthorized mobile radio transmissions.
The trailer shall be equipped so that it can be leveled and plumbed. Full operation height shall be with the bottom of the sign at least 2.1 m (7') above the ground and the top no more than 4.4 m (14.5') above the ground. After initial placement, PCMS shall be moved from location to location as directed by the Engineer
As part of the bid item “Traffic Control Plan Implementation,” at least one PCMS will be required in each direction of travel affected by the work on the major streets and intersection work. The traffic control plans shall clearly show the PCMS’ locations. The PCMS shall warn motorists of the work one (1) week prior to start of the work and for the entire duration of the work.
Add the following section:
206-7.2 Message Board. The message displayed on the PCMS shall be visible from a distance of 460 m (1500') and shall be legible from a distance of 230 m (750'), at noon on a cloudless day, by persons with vision corrected to 20/20. The sign panel shall be 3-line matrix and shall display not less than 7 characters per line. Sign messages to be displayed shall be as approved by the Engineer. The sign face shall be flat black and shall be protected from glare of the sun by a method which does not interfere with the clarity of the sign message. The sign shall be raised and lowered by means of a power driven lifting mechanism. The matrix sign shall be capable of complete alphanumeric selection.
Revised 6/15/2017 Contract No. 6001-22E Page 126 of 148 Lamp matrix type signs shall be equipped with an automatic dimming operational mode that automatically compensates for the influence of a temporary light source or other abnormal lighting conditions. The sign shall have manual dimming operation modes of 3 or more different lamp intensities.
Matrix signs not utilizing lamps shall be either internally or externally illuminated at night.
The controller shall be an all solid-state unit containing all the necessary circuitry for the storage of at least 5 pre -programmed messages. The controller shall be installed in a location allowing the operator to perform all functions from one position. A keyboard entry system shall be provided to allow an operator to generate an infinite number of additional messages over the pre - programmed stored messages. The keyboard shall be equipped with a security lockout feature to prevent unauthorized use of the controller. The controller shall contain a nonvolatile memory to hold the keyboard created messages in memory during periods when the power is not activated.
The controller shall provide for a variable message display rate which allows the operator to match the information display to the speed of the approaching traffic. The flashing off time shall be operator adjustable within the control cabinet.
Add the following section:
206-7.3 Operation and Maintenance. PCMS shall be furnished, placed, operated, and maintained at locations shown on the plans, specified herein, or designated by the Engineer. The PCMS will be diligently maintained and repaired by the Contractor throughout the project in accordance with the manufacturer's recommendations. When ownership is transferred to the City (at the end of the job), it must be demonstrated to be in good working condition, and meet the provisions of these specifications, including current registration.
Add the following section:
206-7.4 Measurement and Payment. The cost for PCMS shall be included in the bid item Traffic Control Plan Implementation and include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the wo rk involved in furnishing , placing, operating, maintaining, repairing, replacing, transporting from location to location, and delivery of the signs to the City at the completion of the construction, in good working order, and as directed by the Engineer, and no other compensation will be made.
SECTION 214 – TRAFFIC STRIPING, CURB AND PAVEMENT
MARKINGS, AND PAVEMENT MARKERS
214-4 PAINT FOR STRIPING AND MARKINGS.
Add the following section:
214-4.3 Paint for Traffic Striping, Pavement Marking, and Curb Mar king. Modify as follows:
Paint for traffic lane lines, turn pocket lines, edge lines, channelizing lines, bike lane lines, chevrons, and curbs shall be rapid dry water borne conforming to CALTRANS Specification No.
PTWB-01R2. Paint for pavement legends, pa vement symbols, pavement arrows, cross walks, parking stall markings and stop bars shall be alkyd thermoplastic conforming to CALTRANS Specification No. PTH-02ALKYD. Glass beads shall be applied to the surface of the rapid dry water borne paint and the molten thermoplastic material and shall conform to the requirements of CALTRANS Specification No. 8010 -004 (Type II). CALTRANS Specifications for water borne paint, thermoplastic material and glass beads may be obtained from the CALTRANS
Revised 6/15/2017 Contract No. 6001-22E Page 127 of 148 Transportation Laboratory, P.O. Box 19128, Sacramento, CA 95819, telephone number (916) 227-7000.
Green traffic paint shall be Ennis -Flint 985216 Green Standard Fast Dry Waterborne 1952F ½ Traffic Paint, Product Color Green (34115) or approved equal. Paint shall meet federal spec TT- P-1952F Type I & II.
214-6.4 RETROREFLECTIVE PAVEMENT MARKERS
Add the following section:
214-6.5 Temporary Reflective Pavement Markers. Temporary pavement markers shown on the plans and required in the specifications shall be one of the types shown in Table 214 -6.4.2, or equal thereto.
TABLE214-6.4.2
TEMPORARY REFLECTIVE PAVEMENT MARKERS
Type Manufacturer of Distributor
TOM- Temporary Overlay
Markers
Davidson Traffic Control Products, 3110 70 th Avenue East, Tacoma, WA 98424,
(877) 335-4638
Revised 6/15/2017 Contract No. 6001-22E Page 128 of 148
SUPPLEMENTAL PROVISIONS TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 3, CONSTRUCTION METHODS
SECTION 302 - ROADWAY SURFACING
302-4.3 Emulsion-Aggregate Slurry (EAS).
Add the following section:
302-4.3.4 Submittal.
At least 15 days before starting placement of a slurry seal, the following shall be submitted to the Engineer:
1. Samples for:
1.1. Emulsified asphalt slurry seal, two 1 -quart wide mouth plastic containers with screw top lid of emulsified asphalt
1.2 Polymer modified emulsified asphalt slurry seal, two 1 -quart wide mouth plastic containers with screw top lid of polymer modified emulsified asphalt
2. Emulsified asphalt, polymer modified emulsified asphalt data as follows:
2.1. Supplier and Type/Grade of emulsified asphalt
2.2. Type of modifier polymer for polymer modified emulsified asphalt
2.3. Copy of the specified test results for emulsified asphalt, polymer modified emulsified asphalt
3. 50 lb of aggregate
4. Aggregate test results for the followings:
4.1. Gradation
4.2. Los Angeles Rattler
4.3. Percent of crushed particles
4.4 Sand equivalent
4.5 Durability
At least 10 days before starting placement of a slurry seal, a laboratory report of test results and the proposed mix design shall be submitted to the Engineer from an authorized laboratory. The authorized laboratory must sign the laboratory report and mix design.
The report must include:
1. Test results used in the mix design compared with specification requirements
2. Proportions based on the dry weight of aggregate, including ranges, for:
2.1. Aggregate
2.2. Water
2.3. Additives
2.4. Mineral filler
2.5. Slurry seal emulsion residual asphalt content
3. Quantitative moisture effects on the aggregate's unit weight determined under ASTM C29M
If any of the materials in the mix design is changed, a new mix design and laboratory report shall be submitted to the Engineer at least 10 days before starting slurry seal work.
Revised 6/15/2017 Contract No. 6001-22E Page 129 of 148 A certificate of compliance as specified for emulsified asphalt in section 203-3.1with each shipment of emulsified asphalt or polymer modified emulsified asphalt shall be submitted to the Engineer.
Add the following section:
302-4.3.5 Quality Control. Add the following:
An effective quality control system shall be established, maintained and followed in accordance with 2022 Caltrans Standard Specification procedures . The quality control system must detail plans, procedures, and organization necessary to furnish and apply a slurry seal that complies with the contract. The quality control system shall be followed until work is accepted.
A Contractor Quality Control (CQC) plan shall be established, maintained and followed sufficient to ensure that the warranty related treatm ent complies with the contract. The CQC plan must cover all slurry seal operations. A copy of the plan shall be submitted to the Engineer, at the preconstruction meeting, for approval. The approved plan shall be followed throughout the project.
An authorized laboratory must perform sampling and testing.
The following information, at a minimum, shall be included in the CQC plan:
1. Materials to be used on the project
2. Sampling and testing methods used to determine compliance with material specifications
3. Equipment to be used on the project
4. Calibration method used to determine compliance with the application rates
5. Procedures for pavement preparation
6. Controls implemented by the Contractor to ensure that the slurry seal materials are cured or set up satisfactorily before opening to traffic
7. Procedures implemented by the Contractor for monitoring initial acceptance requirements
The Engineer shall be allowed to have access to all work in progress for the purpose of qualit y assurance review and testing.
Immediately after sampling, two 1 -quart wide mouth plastic containers of emulsified asphalt or polymer modified emulsified asphalt taken in the presence of the Engineer shall be submitted to the Engineer. Samples must be submitted in insulated shipping containers
Add the following section:
302-4.3.6 Documentation.
The Engineer shall be provided with a daily report including the following information:
1. Project number, route/road, Engineer
2. Date, air temperature, pavement temperature, humidity
3. Asphalt emulsion temperature
4. Beginning and ending stations
5. Job Mix Formula (JMF): application and dilution rates (emulsified asphalt)
6. Length, width, total square yards
7. Contractor's signature
The contractor shall provide proof of calibration of the slurry seal distributor. Calibration shall be conducted no earlier than five days prior to operations. The contractor shall submit the results of the calibration procedure to the Engineer.
Revised 6/15/2017 Contract No. 6001-22E Page 130 of 148 302-4.7 Scheduling, Public Convenience and Traffic Control. Add the following:
The Contractor shall schedule the work so as to prevent damage by all traffic. The Contractor shall not schedule work so as to conflict with trash pickup. The trash hauling schedule can be obtained by calling Republic Services at (760) 332-6464. The Contractor shall accommodate mail delivery to residences and businesses during the work.
At least two weeks prior to work, Contractor shall send, by first class mail, notification letters to all property addresses on which resurfacing shall occur. Obtaining the appropriate addresses shall be the contractor’s responsibility. A sample letter shall be provided by the city and the Contractor shall use the city’s sample letter with appropriate street names, dates, times, and phone numbers specific to the work inserted in the letter.
During resurfacing operations, the Contractor’s schedule shall be designed to provide residents and business owners sufficient paved parking within a 900 feet distance from their homes or businesses.
Seventy-two hours prior to the start of any constructi on in the public right -of-way that affects vehicular traffic and/or parking or pedestrian routes, the Contract shall give written notification of the impending disruption. For a full street closure, all residences and/or businesses on the affected street or alley shall be notified. For partial street closures, or curb, sidewalk and driveway repairs, the residences and/or businesses directly affected by the work shall be notified.
The Contractor shall deliver the 72 -hour advance notification door hangar whi ch shall state the date and time the work will begin and its anticipated duration. The notification shall list two telephone numbers that may be called to obtain additional information. One number shall be the Contractor’s permanent office or field office and the other number shall be a 24 hours number answered by a representative of the Contractor who is knowledgeable about the project. At least one of the phone numbers shall be in the 760 area code. An answering machine shall not be connected to either nu mber. The notification shall also give a brief description of the work and simple instructions to the home or business owner on what they need to do to facilitate the construction. The Contractor shall use the sample door hangar provided by the city and su bmit door hangars to the Inspector for approval. Notices shall not be distributed until approved by the Inspector.
The notification shall be pre -cut in a manner that enables it to be affixed to a doorknob without adhesives. It shall be a minimum size of 3 ½ inches by 8 ½ inches and shall be brightly colored with contrasting printing. The material shall be equivalent in strength and durability to 65lb card stock. The printing on the notice shall be no smaller than 12 points. The door hangars shall show the street name, date, time, phone numbers, and appropriate information specific to the work inserted.
The preparation, materials, printing and distribution of the notifications shall be included in the contract price bid for “Public Notification of Work” and the Contractor will not be entitled to any additional compensation for work outlined in this section.
Revised 6/15/2017 Contract No. 6001-22E Page 131 of 148 (Name of Contractor)
(Address of Contractor)
(Contractor’s License Number)
(Date)
As part of the City of Carlsbad’s ongoing program to maintain our roadways, streets in your neighborhood are scheduled for resurfacing in the coming weeks. The resurfacing work will require traffic control to be put in place in those areas. The work will take place between the hours of 8:30 a.m. and approximately 3:30 p.m., or until the traffic control devices are removed.
Residents located on the streets scheduled for resurfacing will be notified 72 hours in advance of the work. Look for a brightly colored 3 ½” x 8 ½” card attached to your doorknob. You will also notice temporary “no parking” signs on your street with a specific “no parking” date written on it.
PLEASE NOTE: weather conditions and other factors outside our control can sometimes cause work to be rescheduled at the last minute. If this happens, we will notify you as soon as possible of the new date.
To prepare for this road work, we are asking neighbors to help. Here’s how:
• Park your car outside the area of work unless you plan to leave before 8 a.m. the morning the work starts. Watch for “no parking” signs.
• Park your car in your driveway or garage (off the street) if you aren’t going to need it between 8:30 a.m. and 3:30 p.m.
• Avoid walking, bik ing and skate boarding on new roads until construction signs are removed.
• Please keep kids and pets off the new roadway on the day of the resurfacing. • Do not walk on the newly resurfaced street or you may get black residue on the bottom of your shoes. The residue may damage or mark surfaces and be very difficult to remove. • Please try to keep the work area and new road dry until construction signs are removed.
Monitor sprinklers, hoses and other water sources around your home. • Please note that mail could be delayed on the day of the resurfacing if your postal carrier cannot reach your mailbox.
• Work will be coordinated with trash pick-up.
• If you have a special concern or need reasonable accommodations, please call the City of Carlsbad at 760-602-2780.
(Contractor Name) will be performing the resurfacing work for the city. You may call a contractor representative at (XXX) XXX -XXXX for more information about the project and to answer questions. For a map of all streets scheduled for resurfacing throughout the city, please visit the city website at www.carlsbadca.gov, click on City Services> Streets and Traffic> Maintenance> Street Resurfacing.
The City of Carlsbad has some of the most well -maintained streets in the region thanks to the cooperation of community members like you. We appreciate your patience and understanding, and we will do everything we can to get this work done quickly and efficiently.
~~ \..
Revised 6/15/2017 Contract No. 6001-22E Page 132 of 148 302-4.8.2 Emulsion-Aggregate Slurry (EAS)
302-4.8.2.1 Application Temperature. Add the following:
Seal coat, tack coat, or slurry seal activities shall not be started when precipitation is forecasted during the application and curing period.
Slurry seal shall not be placed if rain is imminent or the air temperature is expected to be below 36°F within 24 hours after placement.
Before applying and during the application of slurry seals, drainage inlets, manholes, valve and monument covers, grates, and other exposed facilities located within the area of application shall be covered using plas tic or oil resistant construction paper secured by tape or adhesive to the facility being covered. The covered facilities shall be referenced with enough control points to relocate the facilities after application of the slurry seals.
Immediately before a pplying slurry seal, the surface to receive slurry seal shall be cleaned by removing any extraneous material affecting adhesion of the slurry seal with the existing surface.
Self-propelled power brooms shall be used to clean the existing pavement.
Add the following section:
302-4.8.2.3 Maintenance.
The slurry seal ed streets shall be swept 24 hours after placement without damaging the slurry seal. For 3 consecutive days afterwards, the streets received slurry seal shall be swept daily using a self-loading motor sweeper with spray nozzles unless determined otherwise by the Engineer.
One week later, the Contractor shall sweep the slurry sealed streets once per week for two weeks.
The Engineer has the authority to require more sweeping than specified herein. All sweeping costs shall be included in the Contractor’s bid.
The slurry seal must not show bleeding, raveling, separation, or other distresses for 15 days after placing. If bleeding, raveling, delaminating, rutting, or wash-boarding occurs after placing the slurry seal, make repairs using an authorized method.
Slurry sealed streets shall be protected from damage until it has set and will not adhere or be picked up by vehicle tires. Slurry se al must not exhibit distress from traffic such as bleeding, raveling, separation or other distresses.
Add the following section:
302-4.8.2.4 Construction Method.
Construction of Type I & II slurry seal shall comply with the requirements set forth in 302-4 of the Standard Specifications, except as modified herein.
The slurry seal mixture ( PMCQS-1h w/ 2.5% polymer by weight of residual asphalt ) shall be of proper consistency at all times so as to provide the application rate required by the surface condition. The average application rate shall be in accordance with the following Slurry Seal Application Rates:
Type I to be used in the bike lanes and buffered areas as illustrated in the pr oject Plans and described in Table 302-4.8.2.4:
1,750 SF/ELT (square feet/extra-long ton).
Revised 6/15/2017 Contract No. 6001-22E Page 133 of 148 Type 2 to be used in the vehicular lanes as illustrated in the project Plans and the areas beyond what is described in Table 302-4.8.2.4:
1,250 SF/ELT (square feet/extra-long ton).
Payment reduction for noncompliance shall conform to 302 – 4.11.1
TABLE 302-4.8.2.4 – TYPE 1 AVERAGE WIDTH
(EASTBOUND AND WESTBOUND DIRECTIONS)
Street Name From Street To Street
Width of Type I (FT) - EB
Width of Type I (FT) - WB
CARLSBAD VILLAGE DR I-5 CVD SB OFF RAMP RA I-5 8 8
CARLSBAD VILLAGE DR I-5 I-5 8 8
CARLSBAD VILLAGE DR I-5
I-5 CVD NB ON RAMP
RA 8 8
CARLSBAD VILLAGE DR I-5 CVD NB ON RAMP RA PIO PICO DR 6 6 CARLSBAD VILLAGE DR PIO PICO DR HIGHLAND DR 8 8
CARLSBAD VILLAGE DR HIGHLAND DR VALLEY ST 8 8
CARLSBAD VILLAGE DR VALLEY ST MONROE ST 8 8
CARLSBAD VILLAGE DR MONROE ST DONNA DR 8 8
CARLSBAD VILLAGE DR DONNA DR CELINDA DR 8 8
CARLSBAD VILLAGE DR CELINDA DR EL CAMINO REAL 8 8
CARLSBAD VILLAGE DR EL CAMINO REAL AVENIDA DE ANITA 6 6 CARLSBAD VILLAGE DR AVENIDA DE ANITA APPIAN RD 8 8
CARLSBAD VILLAGE DR APPIAN RD SANTA CLARA WY 13 13
CARLSBAD VILLAGE DR SANTA CLARA WY CONCORD ST 13 13
CARLSBAD VILLAGE DR CONCORD ST PONTIAC DR 13 13
CARLSBAD VILLAGE DR PONTIAC DR VICTORIA AV 6 6
CARLSBAD VILLAGE DR VICTORIA AV CHATHAM RD 13 13
CARLSBAD VILLAGE DR CHATHAM RD TAMARACK AV 8 8
CARLSBAD VILLAGE DR TAMARACK AV GLASGOW DR 10 10
CARLSBAD VILLAGE DR GLASGOW DR COLLEGE BL 10 10
TAMARACK AV CARLSBAD BL GARFIELD ST 6 6
TAMARACK AV GARFIELD ST AT & SF RR 8 8
TAMARACK AV AT & SF RR HIBISCUS CR 8 8
TAMARACK AV HIBISCUS CR SHERIDAN PL 8 8
TAMARACK AV SHERIDAN PL LINMAR LN 8 8
TAMARACK AV LINMAR LN JEFFERSON ST 6 8
TAMARACK AV JEFFERSON ST
I-5 TAMARACK SB ON R
RA 6 10
Revised 6/15/2017 Contract No. 6001-22E Page 134 of 148 Street Name From Street To Street
Width of Type I (FT) - EB
Width of Type I (FT) - WB
TAMARACK AV
I-5 TAMARACK SB ON R
RA I-5 6 6
TAMARACK AV I-5
I-5 TAMARACK NB ON
RA 6 6
TAMARACK AV I-5 TAMARACK NB ON RA PIO PICO DR 6 6
TAMARACK AV PIO PICO DR ADAMS ST 8 8
TAMARACK AV ADAMS ST ADAIR WY 13 13
TAMARACK AV ADAIR WY MARGARET WY 13 13
TAMARACK AV MARGARET WY POLLY LN 13 13
TAMARACK AV POLLY LN HIGHLAND DR 13 13
TAMARACK AV HIGHLAND DR JAMES DR 13 13
TAMARACK AV JAMES DR VALLEY ST 13 13
TAMARACK AV VALLEY ST PARK DR 13 13
TAMARACK AV PARK DR SCOTT DR 13 13
TAMARACK AV SCOTT DR ALDER AV 13 13
TAMARACK AV ALDER AV CRESCENT POINT RD 13 13
TAMARACK AV CRESCENT POINT RD SUNNYHILL DR 13 13
TAMARACK AV SUNNYHILL DR SKYLINE RD 13 13
TAMARACK AV SKYLINE RD HIGH RIDGE AV 13 13
TAMARACK AV HIGH RIDGE AV EAST POINTE AV 13 13
TAMARACK AV EAST POINTE AV PALISADES DR 13 13
TAMARACK AV PALISADES DR AMBERWOOD CT 13 13
TAMARACK AV AMBERWOOD CT EL CAMINO REAL 13 13
TAMARACK AV EL CAMINO REAL LA PORTALADA DR 13 13
TAMARACK AV LA PORTALADA DR PONTIAC DR 13 13
TAMARACK AV PONTIAC DR PRIVATE ST 13 13
TAMARACK AV PRIVATE ST KIRKWALL AV 13 13
TAMARACK AV KIRKWALL AV EDINBURGH DR 13 13
TAMARACK AV EDINBURGH DR CARLSBAD VILLAGE DR 13 13
CANNON RD (EB) CARLSBAD BL LOS ROBLES DR 13
CANNON RD (WB) LOS ROBLES DR CARLSBAD BL 13
CANNON RD (EB) LOS ROBLES DR EL ARBOL DR 13
CANNON RD (WB) EL ARBOL DR LOS ROBLES DR 13
CANNON RD (EB) EL ARBOL DR AT & SF RR 13
CANNON RD (WB) AT & SF RR EL ARBOL DR 13
Revised 6/15/2017 Contract No. 6001-22E Page 135 of 148 Street Name From Street To Street
Width of Type I (FT) - EB
Width of Type I (FT) - WB
CANNON RD (EB) AT & SF RR AVENIDA ENCINAS 13
CANNON RD (WB) AVENIDA ENCINAS AT & SF RR 13
CANNON RD (EB) PASEO DEL NORTE CAR COUNTRY DR 10
CANNON RD (WB) CAR COUNTRY DR PASEO DEL NORTE 10
CANNON RD (EB) CAR COUNTRY DR LEGOLAND DR 10
CANNON RD (WB) LEGOLAND DR CAR COUNTRY DR 10
CANNON RD (EB) LEGOLAND DR GRAND PACIFIC DR 10
CANNON RD (WB) GRAND PACIFIC DR LEGOLAND DR 10
CANNON RD (EB) GRAND PACIFIC DR FARADAY AV 10
CANNON RD (WB) FARADAY AV GRAND PACIFIC DR 10
POINSETTIA (EB) CARLSBAD BL ISTHMUS DR 13
POINSETTIA (WB) ISTHMUS DR CARLSBAD BL 13
POINSETTIA (EB) ISTHMUS DR AT & SF RR 13
POINSETTIA (WB) AT & SF RR ISTHMUS DR 13
POINSETTIA (EB) AT & SF RR AVENIDA ENCINAS 13
POINSETTIA (WB) AVENIDA ENCINAS AT & SF RR 13
POINSETTIA (EB) AVENIDA ENCINAS
I-5 POINSETTIA SB OF
RA 10
POINSETTIA (WB) I-5 POINSETTIA SB OF RA AVENIDA ENCINAS 8 POINSETTIA (EB) I-5 POINSETTIA SB OF RA I-5 6
POINSETTIA (WB) I-5
I-5 POINSETTIA SB OF
RA 6
POINSETTIA (EB) I-5
I-5 POINSETTIA NB ON
RA 8
POINSETTIA (WB)
I-5 POINSETTIA NB ON
RA I-5 6
POINSETTIA (EB)
I-5 POINSETTIA NB ON
RA LOWDER LN 8
POINSETTIA (WB) PASEO DEL NORTE
I-5 POINSETTIA NB ON
RA 8
POINSETTIA (EB) LOWDER LN BATIQUITOS DR 10
POINSETTIA (WB) BATIQUITOS DR PASEO DEL NORTE 10
POINSETTIA (EB) BATIQUITOS DR SNAPDRAGON DR 10
POINSETTIA (WB) SNAPDRAGON DR BATIQUITOS DR 10
POINSETTIA (EB) SNAPDRAGON DR CRYSTALLINE DR 10
POINSETTIA (WB) CRYSTALLINE DR SNAPDRAGON DR 10
POINSETTIA (EB) CRYSTALLINE DR AVIARA PY 10
POINSETTIA (WB) AVIARA PY CRYSTALLINE DR 10
Revised 6/15/2017 Contract No. 6001-22E Page 136 of 148 Street Name From Street To Street
Width of Type I (FT) - EB
Width of Type I (FT) - WB
POINSETTIA (EB) AVIARA PY PRIVATE DWY 10
POINSETTIA (WB) PRIVATE DWY AVIARA PY 10
POINSETTIA (EB) PRIVATE RD BRIGANTINE DR 10
POINSETTIA (WB) BRIGANTINE DR PRIVATE RD 10
POINSETTIA (EB) BRIGANTINE DR BLACK RAIL RD 10
POINSETTIA (WB) BLACK RAIL RD BRIGANTINE DR 10
POINSETTIA (EB) BLACK RAIL RD FISHERMAN DR 10
POINSETTIA (WB) FISHERMAN DR BLACK RAIL RD 10
POINSETTIA (EB) FISHERMAN DR AMBROSIA LN 10
POINSETTIA (WB) AMBROSIA LN FISHERMAN DR 10
POINSETTIA (EB) AMBROSIA LN CASSIA RD 10
POINSETTIA (WB) CASSIA RD AMBROSIA LN 10
POINSETTIA (EB) CASSIA RD ENCELIA 10
POINSETTIA (WB) ENCELIA PL CASSIA RD 10
POINSETTIA (EB) ENCELIA PL SPARTINA CT 10
POINSETTIA (WB) SPARTINA CT ENCELIA PL 10
POINSETTIA (EB) SPARTINA CT ARTEMISIA 10
POINSETTIA (WB) ARTEMISIA CT SPARTINA CT 10
POINSETTIA (EB) ARTEMISIA CT BRIDGE 10
POINSETTIA (WB) BRIDGE ARTEMISIA CT 10
POINSETTIA (EB) BRIDGE SKIMMER CT 10
POINSETTIA (WB) SKIMMER CT BRIDGE 10
POINSETTIA (EB) EL CAMINO REAL ESTRELLA DE MAR RD 8
POINSETTIA (WB) ESTRELLA DE MAR RD EL CAMINO REAL 8
POINSETTIA (EB) ESTRELLA DE MAR RD ALICANTE RD 10
POINSETTIA (WB) ALICANTE RD ESTRELLA DE MAR RD 10
POINSETTIA (EB) ALICANTE RD QUARTZ WY 10
POINSETTIA (WB) QUARTZ WY ALICANTE RD 10
POINSETTIA (EB) QUARTZ WY MICA RD 10
POINSETTIA (WB) MICA RD QUARTZ WY 10
POINSETTIA (EB) MICA RD EL FUERTE ST 10
POINSETTIA (WB) EL FUERTE ST MICA RD 10
POINSETTIA (EB) EL FUERTE ST PASEO ESCUELA 10
Revised 6/15/2017 Contract No. 6001-22E Page 137 of 148 Street Name From Street To Street
Width of Type I (FT) - EB
Width of Type I (FT) - WB
POINSETTIA (WB) PASEO ESCUELA EL FUERTE ST 10
POINSETTIA (EB) PASEO ESCUELA MELROSE DR 10
POINSETTIA (WB) MELROSE DR PASEO ESCUELA 10
LA COSTA AV EL CAMINO REAL PRIVATE DWY 8 8
LA COSTA AV PRIVATE DWY FAIRWAY LN 10 10
All remaining widths of slurry seal not addressed in Table 302.4.8.2.4 shall be Type 2 and any changes will need to be authorized by the City Inspector and Engineer.
302-5 ASPHALT CONCRETE PAVEMENT.
302-5.1 General. Add the following:
The Contractor shall treat all vegetation within the limits of the paved area to receive asphalt concrete paving in accordance with the City’s Integrated Pest Management (IPM) plan. The document can be found on the City’s website. Allowance for the vegetation treatment period shall be shown in the schedule required per section 6-1.
302-5.2 Pavement Transitions. Add the following:
The Contractor shall ramp the approaches and termini to all structures and vertical joints in the cold-milled area which are transverse to through traffic with temporary asphalt concrete pavement as specified in section 306 -13.1. Ramps shall be constructed the same day as cold milling and removed the same day as permanent paving. Ramp dimensions and compaction shall be as approved by the Engineer.
302-5.4 Tack Coat. Add the following:
The Contractor shall place a tack coat between the successive interfaces of existing pavement and new asphalt concrete.
302-5.5 Distribution and Spreading. Modify as follows:
After second sentence of sixth paragraph, add: The Contractor shall provide the self -propelled spreading and finishing machine used to const ruct the asphalt concrete surface course with an automatic screed control. The automatic screed control shall be 5.5 m (18’) minimum length. The paving machine shall be operated by an operator and two full-time screed men during all paving.
The Contractor shall provide an on-site backup paving machine during all paving operations.
No conveyor belt systems will be allowed for moving the AC. No AC windrows will be allowed. Only a surge volume/remix material transfer vehicle (MTV) is allowed to receive the AC from the haul trucks and then place it in the self -propelled spreading and finishing machine. If the Engineer determines the use of the MTV is not practical for a portion of the project, the Engineer may waive its requirement for that portion.
=========---
Revised 6/15/2017 Contract No. 6001-22E Page 138 of 148 302-5.6.1 General. Modify as follows:
Second paragraph, Part (2), add: Pinched joint rolling procedures shall be required, and vibratory rollers shall be limited to breakdown, unless otherwise directed by the Engineer.
302-5.8 NOT USED
Add the following section:
302-5.8 Manholes and Valve Boxes (and other structures).
The Contractor must locate , survey, and record locations of all appurtenances in the roadway including, but not limited to, manholes, access holes, valve boxes, blow-offs, air releases, sewer cleanouts, and survey monument boxes (please refer to Section 2-9 for specific requirements to survey monuments). GIS based maps/ exhibits of water, sewer, and storm water manholes and covers can be seen in Appendix B -1 to B -3, Contractor to verify. Prior to grinding or paving adjacent to any structure, Contractor shall install plywood shelves or umbrella devices in order to prevent debris from falling into structures. Prior to placing the overlay, the Contractor shall install rubber nipples/risers on top of all appurtenances in the roadway and pave over the rubber nipples/risers. Each manhole cover shall be treated or covered to prevent adhesion of the overlay.
Each City-owned manhole and cleanout shall be located and raised to grade within 72 hours after the overlay is placed and shall be thoroughly cleaned of any construction debris which may have entered due to the Contractor’s operation. Each valve box shall be replaced per City Standard Drawings, Volume 3, Chapter 4 (refer to Current City Standards Plans https://www.carlsbadca.gov/home/showpublisheddocument/334/637980518271200000).
The contractor shall be responsible for matching the finish grades of the new pavement to match the existing manholes, as to create a smooth finish surface, and not have any abrupt changes in or around the manholes.
In the event of any damage to existing manholes during construction activities, the contractor shall replace them at the contractor’s expense, and no extra payment shall be made to the contractor.
All City of Carlsbad sanitary sewer access covers shall be adjusted per City Standard Drawing No. S1. All storm sewer access covers shall be adjusted per SDRSD D-10.
For all non-City owned appurtenances, manholes, valve boxes, or other structures in the roadway or in conflict with the propo sed improvements, the contractor shall coordinate with the proper agency contact. For Leucadia Wastewater District, contact Ian Riffel at (760) 753-0155 ext.3002.
For Olivenhain Municipal Water District, contact Dan Bean at (760) 415-8548.
For all non-City owned appurtenances, manholes, valve boxes, or other structures in the roadway or within the project limits, if the contractor and the owner of the non-City owned utilities mutually agree to contract with one another to adjust or replace the appurtenance s, the contractor shall extend them the same bid prices as offered in this contract, with up to 10% markup only.
Survey monument boxes shall be replaced and adjusted to grade per SDRSD M-10.
Riser rings or extensions shall not be used for the adjustment of City-owned appurtenances.
Replacing and adjusting to grade all City-owned appurtenances in the roadway shall be paid for at the contract unit price per each as shown in the Bid. Such price shall constitute full compensation for all labor, materials, and equipment necessary for completing the work as described in these specifications, including traffic control and prevention from debris falling into structures. Other Agencies may adjust their own appurtenances or other Agencies may contract with a third party to raise their appurtenances.
~~ \..
Revised 6/15/2017 Contract No. 6001-22E Page 139 of 148
302-5.9 Measurement and Payment. Add the following: Payment for asphalt concrete placed and compacted shall be at the unit price bid per ton. No additional payment shall be made for any tack coat, material transfer vehicle, compaction, traffic control, or other incidentals.
302-14 POLYMER MODIFIED ASPHALT CONCRETE (PMAC).
Add the following section:
302-14.1 General. Add the following section:
Quality Control Program. The Contractor shall implement a Quali ty Control Program throughout the production and placement of PMAC. The Quality Control Program shall consist of the preparation and implementation of a Quality Control Plan (QCP).
At least 5 business days prior to the Preconstruction Meeting, the Contrac tor shall submit to the Engineer a QCP for PMAC production and placement for review and approval. The QCP shall include the name(s) of personnel responsible for quality control, their qualifications, and specific procedures to be followed during PMAC placement operations.
The Contractor shall maintain accurate records of all tests it performs as part of its Quality Control Program and shall make these records available to the Engineer upon request. The Contractor can also be required to submit its QC test results at the end of each day. The Contractor shall satisfy itself that its materials and workmanship, including those of its subcontractors and suppliers, are in conformance with the Contract Documents. The Contractor shall submit to the Engineer for review copies of the results of all Quality Control tests it has performed prior to requesting the Agency to perform Quality Assurance testing.
The QCP must describe the organization and procedures for:
1. Controlling PMAC quality characteristics
2. Taking samples, including sampling locations
3. Establishing, implementing, and maintaining QC
4. Determining when corrective actions are needed
5. Implementing corrective actions
6. Using methods and materials for backfilling core locations, if applicable
The QCP must address the elements affecting PMAC quality, including:
1. Aggregates
2. Asphalt binder
3. Additives (i.e. WMA additive)
4. Production
5. Paving
The Contractor shall allow 5 business days for review of the QCP by the Agency.
If the Contractor changes QC procedures, personnel, or sample testing locations, the Contractor shall submit a QCP supplement before implementing the proposed change. The Contractor shall allow 3 business days for review of the QCP supplement.
Revised 6/15/2017 Contract No. 6001-22E Page 140 of 148 The Contractor shall collect and hold data for the duration of the contract and sh all make these records available to the Engineer upon request. The snapshot of production data must include the following:
1. Production date
2. Production location
3. Time of day the data is captured
4. AC mix type being produced and target binder content
5. AC additive type, brand, and target rate
6. Temperature of the binder and AC mixture
7. For a continuous mixing plant, the rate of flow of the dry aggregate
8. For a continuous mixing plant, the rate of flow of the asphalt meter
9. For a continuous mixing plant, the rate of flow of AC additive meter
10. For batch plant mixing, actual batch weights of all ingredients
11. Dry aggregate to binder ratio calculated from metered ingredient output
12. Dry aggregate to AC additive ratio calculated from metered output
AC with WMA additive technology must be produced between 260°F and 325°F.
Using WMA additive is optional for this project. If the Contractor desires to use WMA additive, then a technical representative for the WMA additive technology must attend the Preconstruction Meeting should WMA be used by the Contractor.
302-14.3 Distribution and Spreading. Replace with the following: Distribution and spreading shall conform to 302-5.5 of the SSPWC except as follows:
Replace the fourth paragraph with the following:
Polymer modified asphalt concrete with WMA additive technology shall not be placed until the atmospheric temperature is a minimum of 45 oF and rising, and the surface temperature of the underlying material is a minimum of 45ºF. Polymer modified asphalt concrete shall also not be placed during unsuitable weather.
For PMAC produced with WMA additive technology:
1. 1st coverage of breakdown compaction before the surface temperature drops below 230°F
2. Breakdown and intermediate compaction before the surface temperature drops below 170°F
3. Finish compaction before the surface temperature drops below 130°F
The Contractor may continue static rolling below 130°F to remove roller marks.
302-14.4 Rolling. Replace the third paragraph of 302-5.6.2 with the following:
The Contractor shall determine the in-place density and relative compaction of polymer modified asphalt concrete placed on this Project as part of its Quality Control Program. The Contractor shall follow the procedures and methods specified in California Test 375, February 2012 modified as follows:
PART 4. DETERMINATION OF IN -PLACE DENSITY WITH THE NUCLEAR DENSITY GAGE
Revised 6/15/2017 Contract No. 6001-22E Page 141 of 148 4A. APPARATUS/MATERIAL
1. Add the following:
The nuclear device shall be specifically designed for testing the density of asphalt concrete.
4B. DETERMINING IN-PLACE DENSITY
Add the following:
13. The Contractor shall furnish the Engineer with a copy of the test results for each Sub- Lot at the end of each Working Day. The test results shall identify the Lot and Sub - Lot in the following manner:
a. Each Lot shall be consecutively numbered (i.e., first day of paving, Lot “1"; second day of paving, Lot “2"; ...)
b. Each Lot shall be divided into Sub-Lots of 500 tons each and shall be consecutively lettered starting with Sub-Lot “A” (i.e., the first Sub-Lot of the first day of paving will be Lot “1-A”, the second Sub-Lot of the first day of paving will be Lot “1 -B” …the first Sub-Lot of the second day of paving will be Lot “2 -A”, …). A Sub -Lot may, when approved by the Engineer, be placed at 2 separate locations as long as placement is in conformance with the Specifications and the Contractor clearly identifies the location and limits of the placement.
c. The Contractor shall test a minimum of 10 sites for each 500 tons of polymer modified asphalt concrete placed. For areas containing less than 500 tons, the Contractor shall test at the rate of 1 test site for each 50 tons or portion thereof of polymer modified asphalt concrete placed.
PART 6. CALCULATION OF RELATIVE COMPACTION
3. Add the following:
The Agency will take a set of 3 cores per Sub -Lot for the purposes of determining in- place density. In-place density will be determined by the Agency in accordance with California Test 308, Method “A”, with the exception that the Agency will use zinc stearate. The average in-place density of the 3 cores will be used for the purpose of calculating relative compaction per Part 6. The Agency, at its option, may determine the average in-place density using a nuclear device in accordance with California Test 375. In the event of a dispute between the results obtained by the Contractor using the nuclear device, and the results obtained by the Agency using California Test 308, the latter results shall prevail.
302-14.4 Payment. Payment for PMAC pavement in which the relative compaction, by lot, is less than 95 percent, but greater than 91.9 percent, will be made at the Contract Unit Price minus (the Reduced Compensation Factor multiplied by the Contract Unit Price) as shown in Table 302-14.8.
Revised 6/15/2017 Contract No. 6001-22E Page 142 of 148 TABLE 302-14.8
Relative
Compaction
(Percent)
Reduced
Compensation
Factor
Relative
Compaction
(Percent)
Reduced
Compensation
Factor
95.0 0.000 93.4 0.062
94.9 0.002 93.3 0.068
94.8 0.004 93.2 0.075
94.7 0.006 93.1 0.082
94.6 0.009 93.0 0.090
94.5 0.012 92.9 0.098
94.4 0.015 92.8 0.108
94.3 0.018 92.7 0.118
94.2 0.022 92.6 0.129
94.1 0.026 92.5 0.142
94.0 0.030 92.4 0.157
93.9 0.034 92.3 0.175
93.8 0.039 92.2 0.196
93.7 0.044 92.1 0.225
93.6 0.050 92.0 0.300
93.5 0.056
Should the compaction of any lot be less than 91.9 percent, the lot shall be removed and replaced at the Contractor's expense.
Add the following section:
302-15 ASPHALT PAVEMENT REPAIRS AND REMEDIATION
Add the following section:
302-15.1 General. Damage to existing traffic loops caused by pavement repairs or cold milling will require immediate replacement of the traffic loops unless video detection has been set up and the loops are unnecessary. If pavement fabric or geo-textile is encountered during any pavement repairs or cold milling, the Contractor shall remove and dispose of it at the Contractor’s expense.
The cost of the work described in this section shall be included in the bid price for the repair itself or cold milling (grinding).
302-15.2 AC Cold Milling and Disposal of Grindings. Cold Milling or grinding shall be in accordance with the provisions of Section 404 of the Greenbook, latest edition. The Contractor shall cold mill or diamond grind the existing AC to the width and depth as shown on the plans and described in the Standard Specifications and these Special Provisions. In the field, the Engineer may change the width and depth of the cold milling at his discretion. If the Contractor’s cold milling severs any traffic detection loo ps, the Contractor shall replace them immediately at the Contractor’s expense. Existing advance traffic signal loop detectors shall be replaced by the Contractor and paid for per the bid item Replace Traffic Signal Detector Loop, Type E, even when video de tection has been installed at the intersection. Contractor shall install Type E Loop Detector per Caltrans Revised Standard Plan RSP ES -5B. For all traffic signal loops that are to be replaced, a new, dedicated DLC with home run back to the cabinet is required for every existing loop that is currently sliced with other loops connecting to one DLC back to a cabinet. Each advance loop should have its own homerun back to the signal cabinet as well. Contractor shall construct temporary AC ramps at the cold-milled edges parallel and perpendicular to the direction of travel. Payment for construction, removal, and disposal of temporary asphalt concrete ramps ~~ \..
Revised 6/15/2017 Contract No. 6001-22E Page 143 of 148 shall be included in the bid item for cold milling. As shown on the plans, some cold milling may require tapering of milled thickness.
If and when the Contractor encounters pavement fabric or petromat during cold milling, the Contractor shall remove and dispose of the pavement fabric or petromat. The cost of removing and disposing pavement fabric or petromat shall be included in the Contractor’s bid price for cold milling and no additional payment will be made therefor.
302-15.3 Two (2) Inch Depth AC Cold Mill and Replace. The area set forth in the bid items is for estimating purposes only and the final quantities will be as measured in the field by the City Inspector. The Inspector will designate and mark the final limits of the remove and replace areas in the field by outlining the area to be patched with paint. The Contractor shall remove the asphalt concrete in the designated area to the depth required per the requirements of Section 404 of the SSPWC. The Contractor shall sweep the street, keep dust to a minimum, and remove and dispose of the AC at the Contractor’s expense. A tack coat of SS -1h emulsified asphalt shall be applied uniformly to all asphalt-to-asphalt contact surfaces at a rate of 0.25 L/m2 to 0.45 L/m2 (0.05 to 0.10 gallons per square yard) in accordance with s ubsection 302-5.4, SSPWC. The Contractor shall fill the area with asphalt concrete and compact so that the finished surface of the new AC is flush with the surrounding pavement. The Contractor is required to use a self-propelled paving machine for areas 6 feet wide and wider. The asphalt concrete so constructed shall have a finish surface and density conforming to subsection 302-5.6.2 SSPWC.
302-15.4 Crack Sealing. All joints and cracks equal or >1/4” wide shall be cleaned to a minimum depth of 1” (25 mm) with high pressure air jet and/or routed as directed by the City inspector as specified in Section 203-10. No sealant material shall be placed until the joints and cracks have been cleaned of all loose dirt, old material, and are sufficiently dry. Both sid e walls of the cracks and joints must be free of dust and debris to assure optimum sealant adhesion. The joints and cracks shall be inspected and approved by the Inspector prior to placing the crack sealant material. Final joint and crack cleaning will be the same day of the sealing operation except as otherwise approved by the Inspector.
The Contractor shall dispose of debris from crack cleaning outside the public way in accordance with Section 7-8.1, “Cleanup and Dust Control.” The hot-melt rubberized asphalt shall be melted in a jacketed, double boiler type melting unit. Temperature of the heat transfer medium shall not exceed manufacturer’s recommendations. Application of the hot-melt sealant shall be made with a pressure feed applicator or pour pot. Se alant shall be applied when the pavement surface temperature is greater than 50°F. Containers of hot-melt rubberized sealant shall be delivered to the jobsite in unopened containers that are clearly marked with data showing the manufacturer’s name, the product designation and the manufacturer’s batch number and lot numbers. The level of the sealant shall be flush with the surface of the existing pavement. All excess sealant shall be removed from the crack with a minimum overlap onto adjacent pavement. Crack sealant shall be allowed to cure for 7 days prior to street resurfacing.
302-15.5 Measurement and Payment. Quantities of pavement repairs as set forth in the bid items are for estimating purposes only. Final quantities will be as designated and measured in the field. The Engineer will designate and mark the limits of the repairs. Full compensation for conforming to the requirements of constructing pavement repairs shall include but not be limited to: furnishing all labor, tools, equipment, and materials n ecessary for doing the work as outlined in the appropriate section, including saw cutting and removing and disposing of existing asphalt concrete, aggregate base/subbase and basement soil as designated by the engineer, placement of asphalt concrete, compac tion of subbase and asphalt concrete, placement of SS -1h asphalt
Revised 6/15/2017 Contract No. 6001-22E Page 144 of 148 emulsion and all other work incidental to the pavement repairs shall be considered as included in the contract unit price bid and no additional compensation will be allowed therefor.
The bid price for cold milling shall include removing and disposing of pavement fabric or geo - textile when encountered.
Full compensation for conforming to the requirements of crack sealing shall include but not be limited to, furnishing all labor, materials, tools, equipment, and incidentals necessary to do the work. Crack cleaning, roadway clean up, application of sealant, removal of excess sealant and all other work incidental to crack sealing shall be considered as included in the contract unit price bid and no additional compensation will be allowed therefor.
SECTION 303 CONCRETE AND MASONRY CONSTRUCTION.
303-1 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.
Add this section:
303-5.10 Curb Ramp Construction.
303-5.10 Installation. The curb ramp work will conform to the requirements of Section 303 ‐5 of the Standard Specifications as modified herein. The work will consist of the following:
a) The Contractor shall be solely responsible for means and methods for laying out and verifying all proposed curb ramps’ and appurtenances’ grades, including all associated sidewalks, curbs, and gutter plates, in accordance with the standard drawings and as indicated in the construction documents. The final g rades for all constructed curb ramps and appurtenances shall not exceed maximum grades indicated in the standard drawings and the construction documents. There shall be no construction tolerances allowed. Any curb ramps or appurtenances constructed in exce ss of maximum grades as indicated in the aforementioned documents shall be removed and replaced at the Contractor’s sole expense. Removal or AC pavement disposal of existing concrete including curb and gutter or portion of spandrel as occurs, and sidewalk necessary to construct the ramp shall be made as straight edges and by the full depth saw cutting only. Removal limits shall be agreed to in writing prior to the saw cutting operation for each ramp location. b) The pedestrian ramps locations and types are shown on the plans. Details for saw cutting existing cross gutter spandrels and replacement of existing AC pavement are shown on the plans.
303-5.10.2 Payment. Payment for construction of curb ramps will be made at the contract unit price per each, and shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals and for doing all work involved in providing and constructing the curb ramps including removal of and construction of curb, curb and gutter, cross gutter spandrel, alley apron, AC pavement and sidewalk, removal of existing ramps and sidewalk associated with ramp construction, and construction of curb, gutter and sidewalks in place, as necessary to achieve ADA compliant grades (regardless of replacement limits shown on plans), construction staking of curb ramps, removal and reconstruction of adjacent improvements including but not limited to private hardscape improvements and landscaping/irrigation improvements, repainting of new curb to match painting of existing curb, if any, prior to ramp
Revised 6/15/2017 Contract No. 6001-22E Page 145 of 148 construction, and joining work to tie proposed ramp into the adjacent existing PCC (doweling, epoxy, etc.) as shown on plans, complete in place as specified in the special provisions and as directed by the Engineer. The payment for curb ramps shall include the detectable warning strip. Payment for construction of curb ramps shall include full compensation for furnishing all labor, materials, tools, equipment, including but not limited to; saw cutting, removal & disposal of materials, compaction, adjacent asphalt paving and all related incidentals required to complete the work in place.
SECTION 314 - TRAFFIC STRIPING, CURB AND PAVEMENT
MARKINGS, AND PAVEMENT MARKERS
314-3 REMOVAL OF PAVEMENT MARKERS.
314-3 General. Add the following: The Contractor shall remove all existing thermoplastic and raised pavement markers. The Contractor shall collect all water and detritus resulting from removal from the pavement immediately and shall not allow such materials to flow in the gutter, enter the storm drain system or to leave the pavement surface. Surface variation limitations shall be the same as for grinding. The Contractor shall not use dry or wet sandblasting in any areas.
Alternate methods of thermoplastic removal require prior approval of the Engineer. Obliteration of traffic striping with black paint, light emulsion oil or any other masking method other than a minimum 30mm (0.10’) thick asphalt concrete overlay is not permitted.
The surface produced shall not exceed variations from a uniform plane more than 3 mm ( 1/8”) in 3 m (10’) when measured parallel to the centerline of the street or more than 6 mm ( 1/4”) in 3 m (10’) when measured perpendicular to the centerline of the street. The use of any equipment that leaves ridges, indentations or other objectionable marks in the pavement shall be discontinued, and equipment capable of providing acceptable surface shall be furnished by the Contractor. This equipment shall meet all requirements of the air pollution control district having jurisdiction.
For the three (3) bridge locations over the Interstate-5 on Tamarack Avenue, Poinsettia Lane, and La Costa Avenue, only water blasting shall be used to remove painted pavement markers on the concrete bridge deck (Refer to Schedule B of these Provisions). Equipment for water blasting within CALTRANS Right-of-Way shall be a Stripe Hog SH8000 or approved equal with a recovery system and capable of a blasting pressure up to 40,000 PSI with control interlocks to prevent high pressure discharge while blasting heads are in operation. Under no circumstances shall damage occur to the concrete pavement surface within CALTRANS Right-of-Way.
314-3.3 Payment. Modify section as follows: Payment for removal of pavement markers other than Thermoplastic shall be paid per lump sum in the bid item Striping, Thermo, and RPMs per Plans and Caltrans Details. Payment for removal of Thermoplastic markers shall be paid per lump sum in the bid item Removing Existing Thermoplastic.
314-4 APPLICATION OF TRAFFIC STRIPING AND CURB AND PAVEMENT MARKINGS.
314-4.3.5 Application . Add the following paragraph: The Contractor shall lay out (cat track) immediately after resurfacing and as the work progresses. The contractor shall apply the first coat of paint immediately upon approval of striping layout by the Engineer and within 72 hours of pavement resurfacing. After one week, a second coat of paint shall be applied to all final, approved striping. The Contractor shall paint the ends of each median nose yellow.
Revised 6/15/2017 Contract No. 6001-22E Page 146 of 148
314-4.3.7 Payment. Modify section as follows: Final and temporary traffic striping, curb markings and pavement markings shall be included in the prices bid for striping and markings, and no additional compensation will be allowed therefor. Reapplication of temporary stripes and markings shall be repainted at the Contractor's expense, and no additional compensation will be allowed therefor. The prices bid shall in clude all labor, tools, equipment, materials, and incidentals for doing all work in installing the final and temporary traffic striping.
314-5 PAVEMENT MARKERS.
314-5.2.2.1 General . Add the following sentence: Epoxy adhesives shall not be installed on asphalt concrete pavement sooner than 14 days after placement of the asphalt concrete pavement.
Add the following section:
314-6.1 Reflective Channelizer Placement and Removal. The Contractor shall place and remove reflective channelizers the same as for pavement marker placement and removal. The Contractor shall place the channelizers uniformly, straight on tangent alignment and on a true arc on curved alignment to the same tolerances of position as for application of paint in section 314-
4.3.5. The Contractor shall perform all layout work necessary to place the channelizers to the proper alignment. If the channelizers are displaced or fail to remain in an upright position, from any cause, the channelizers shall immediately be replaced or rest ored to their original location, by the Contractor. When reflective channelizers are removed , the pavement surface shall be restored to the same color and surface finish as the adjacent pavement.
SECTION 315 - TEMPORARY TRAFFIC CONTROL DEVICES
Add the following section:
315-1 TEMPORARY TRAFFIC PAVEMENT MARKERS.
Add the following section:
315-1.1 General. The Contractor shall supply and install temporary traffic pavement markers, channelizers, and signing at the locations shown on the plans and as required in the specifications, complete in place prior to opening the traveled way to public traffic.
315-1.2 Temporary Pavement Markers . Temporary reflective raised pavement markers shall be placed in accordance with the manufacturer's instructions. Temporary reflective raised pavement markers shall be cemented to the surfacing with the adhesive recommended by the manufacturer, except epox y adhesive shall not be used to place temporary reflective raised pavement markers in areas where removal of the markers will be required. Pavement striping, legends and markers which conflict with any traffic pattern shall be removed by grinding as determined by the Engineer. The Contractor shall use temporary reflective raised pavement markers for temporary pavement marking, except when the temporary pavement markers are used to replace patterns of temporary traffic stripe that will be in place for less t han 30 days.
Reflective pavement markers used in place of the removable -type pavement markers shall conform to the section 312 "Pavement Marker Placement and Removal", except the 14 -day waiting period before placing the pavement markers on new asphalt conc rete surfacing as specified in section 312-1 “Placement”, shall not apply; and epoxy adhesive shall not be used to place pavement markers in areas where removal of the markers will be required.
Revised 6/15/2017 Contract No. 6001-22E Page 147 of 148 Add the following section:
315-1.3 Channelizers. Channelizers shall be new surface -mounted type and shall be furnished, placed, and maintained at the locations shown on the plans. Channelizer posts shall be orange in color. Channelizers shall have affixed white reflective sheeting as specified in the special provisi ons. The reflective sheeting shall be 75 mm x 300 mm (3” x 12”) in size. The reflective sheeting shall be visible at 300 m (1000’) at night under illumination of legal high beam headlights, by persons with vision of or corrected to 20/20. The channelizer b ases shall be cemented to the pavement in the same manner as provided for cementing pavement markers to pavement in section 314. Channelizers shall be applied only on a clean, dry surface. Channelizers shall be placed on the alignment and location shown on the plans and as directed by the Engineer.
The channelizers shall be placed uniformly, straight on tangent alignment and on a true arc on curved alignment. All layout work necessary to place the channelizers to the proper alignment shall be performed by t he Contractor. If the channelizers are displaced or fail to remain in an upright position, from any cause, the channelizers shall immediately be replaced or restored to their original location, by the Contractor. The Contractor shall provide the Engineer w ith a Certificate of Compliance in accordance with the provisions of section 4-1.5, "Certification”. Said certificate shall certify that the channelizers comply with the plans and specifications and conform to the prequalified design and material requireme nts approved by the Engineer and were manufactured in accordance with a quality control program approved by the Engineer.
Add the following section:
315-2 TEMPORARY TRAFFIC SIGNING.
Add the following section:
315-2.1 General. The Contractor shall provide and install all temporary traffic control signs, markers, markings, and delineators at locations shown on approved Traffic Control plans and specified herein. As part of the Contractor’s Traffic Control Plan, at least one Portable Changeable Message Sign (PCMS) is required in each direction of travel impacted by the work on all roadways for the project. The PCMS shall warn motorists of the work 7 days prior to start of the work, and for the entire duration of the work.
Add the following section:
315-2.2 Maintenance of Temporary Traffic Signs . If temporary traffic signs are displaced or overturned, from any cause, during the progress of the work, the Contractor shall immediately replace the signs in their original approved locations. The Contractor shall maintain all temporary traffic signs used in the Work in a clean, reflective and readable condition. The Contractor shall replace or restore graffiti marked temporary traffic signs and posts used in the Work within 18 hours of such marking being discovered during non -working hours or, when the marking is discovered during working hours, within 2 hours of such discovery of marking.
Add the following section:
315-4 MEASUREMENT AND PAYMENT.
Temporary traffic pavement markers sha ll be paid for per the lump sum bid item ‘Temporary Pavement Markers.’ However, PCMS’s, temporary channelizers , temporary signing, temporary railing (type K), temporary crash cushions and temporary appurtenances thereto shown on the plans or traffic control plans, or required in the specifications are a part of the lump sum item for Traffic Control Plan Implementation and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in applying, installing, maintaining, and removing temporary traffic pavement markers, channelizers, signing, railing (type K), crash cushions and appurtenances, complete in place, as
Revised 6/15/2017 Contract No. 6001-22E Page 148 of 148 shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer. Payment for temporary crash cushions, concrete barriers and the signs and reflectors marking them shall include the installation, grading for installation, grading for the approach path, maintenance, painting and re-painting, replacement of damaged units and removal shall also be included in the lump-sum price bid for traffic control plan implementation.
PART 7
STREET LIGHTING AND
TRAFFIC SIGNAL SYSTEMS
SECTION 700 - MATERIALS
Add the following section:
700-5.10 Video/ Radar Detection System.
Video/ Radar detection system shall be a n Iteris Vantage Next Vector multi-camera video radar system for the intersection of La Costa Ave. and Saxony Dr. The Iteris detection system shall consist of vantage extension modules and a central control unit housed in a traffic signal cabinet.
The Iteris Vantage Next system shall have a 17-inch drop down monitor.
SECTION 701 - CONSTRUCTION
701-17.6.4 NOT USED
Add the following section:
701-17.6.4 Video/ Radar Detection System.
Contractor to furnish and install an Iteris Vantage Next Vector multi-camera video radar system at the intersection of La Costa Ave. and Saxony Dr. Detection units shall be bracket mounted on a signal mast arm. Contractors shall pull a shielded CAT 6 cable per Iteris specifications in a complete home run pull from each detection unit to cabinet with no splices. Contractor to program video camera and radar detection for advanced vehicles. Contractor to contact the City of Carlsbad Traffic Engineer for detection details at least two (2) weeks prior to field installation.
APPENDIX “A”
Project Limits within City of Encinitas
A
B
C
D
Copyright nearmap 2015
¯
Legend
Project Limits within City of Encinitas
Right of Way Line
Location Area SqFt
La Costa A 846
La Costa B 16385
La Costa C 13086
La Costa D 24099
Date: 1/30/2023 Document Path: Z:\Eric_Zielke\Pavement\Overlay\Encinitas_Portion\Encinitas_LaCosta.mxdAndy Chang Appendix A
-D
APPENDIX “B”
City of Carlsbad Water, Sewer, Stormwater Utilities
ÐÒ
ÐÒ
!
!("
" !(
"!(
!(
!(!
"
!?
!É!É
!É!É!?
!?
!?
!?
!?!?!? !?!?!? !?
!?
!?!?!?
!?!?
!?!?!? !?
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
$1
$1
$1
$1
$1
$1
$1
$1
$1
$1
$1
$1
!! !! !! !!
!!
!!
!!
!!
!!
21D3D20
27B1D54
27B1D64
27B1D30
27B1D29
27B1D61
27B1D59
27B1D42
27B1D51
27B1V115
27B1V117
27B1V126
CANNON RD
I-5 CANNON NB ON RAMP
I-5 CANNON SB ON RAMP
I-5
I-5 CANNON SB OFF RAM
P
I-5 CANNON NB OFF RAM
P
27B2V9
27B1V6827B1V69
21D4V17
21D4V18
21D3V19
27B1V53
21D3V22
27B1V2627B1V28
27B1V27
27B1V2 27B1V3
27B1V4
27B1V31
27B1V36
27B1V57
27B1V56
27B1V120
27B1V125
27B1V16627B1V168
27B1V167
27B1V165
27B-4
27B-22
21D-22
27B-2
21D-5
27B-54
21D-7
27B-23
27B-63
27B-3
27B-57
Copyright nearmap 2015
Legend
Sewer Access Hole
!( Standard
Storm Junction
!! Junction
Storm Cleanout
$1 Cleanout
Author: An dy Chang Date: 1/30/2023 Docu ment Path: Z:\Eric_Z ielke\Pavem ent\O verl ay\ForCon tractor\ForContractor_Append ix_B-1.mxd Appendix B-1
¯
* Utilities based on assets serviced by City of Carlsbad only. Some areas may be serviced by Leucadia Wastewater District (LWWD) and Vallecitos Water District (VWD) and are not shown on this map.
Contractor to verify utilities not serviced by City of Carlsbad. $1
$1
$1
$1
$1
$1
$1
$1
$1
$1$1
!!
!!
!!
!!
!!
!!
!!
!!
LA
NEVASCA
LN
CORTE CELESTE CAMINO GATO
VIA PEPITA
RANCHO
SANTA
FE
RD
OLIVENHAIN RD
Copyright nearmap 2015
Author: An dy Chang Date: 1/30/2023 Docu ment P ath: Z:\E ric_Z ielke\Pavem ent\O verl ay\ForCon tractor\ForContractor_A ppend ix_B-2.mxd Appendix B-2
¯
Legend
City Boundary
Sewer Access Hole
!( Standard
Storm Junction
!! Junction
Storm Cleanout
$1 Cleanout
* Utilities based on assets serviced by City of Carlsbad only. Some areas may be serviced by Leucadia Wastewater District (LWWD) and Vallecitos Water District (VWD) and are not shown on this map.
Contractor to verify utilities not serviced by City of Carlsbad.
D
ÐÒ
ÐÒ
ÐÒ
ÐÒÐÒ
ÐÒ!(
!("!
!("!(" !("!(!( "
"
!(" !
"!("!
!(!("!(
!
!("
""
!("
!
""
""!(
"!(
"
"
"
"
!(
"!
"
"
"
"
"
"!(
"
!
""
"
"
!(
""
!("
"
"!(
!(!(
!("!
"
!(
!(
"
!("!(
!("
!
"
"
"!(!(
!"
"
!( "
"
"
"
"
"
!("
!(
! !("!("!(
"!( "
!(
ÐÒ
ÐÒ
!?!?!?
!?!?!?
!?
!?
!?!?!?
!?!?!?!? !?!?!?!?!?!?
!?
!?
!?
!?!?!?!? !?
!?!?!?
!?!?!?!?!?
!?!?!?!?
!É!É
!?!?!?!?
!?!?!?
!?!?!? !?
!?!?!?!?
!?
!?!?
!?
!?!?!?
!?!?!?!?
!?
!?!?!? !?!?!?
!?
!?
!É
!?!?!É!É
!?!?
!É!É!?
!É
!É!?!É
!É!É!É!?
!?
!? !?
!É!É
!?!?!?
!?!?
!? !?
!?
!?
!?
!?
!?!?
!?!?!?!?!?!?
!?
!? !?!?
!?
!?!?!?
!?
!?
!?
!?
!?!?
!?
!?!?!?
!?!?!?!
!É!É!É
!?
!?!?!?
! !?
!?!?!?!?
!?
!?
!?
!?!?!?!?
!?
!?!?
!?
!?!É!?
!?!? !?!!?
!?!?!?! !?
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
$1
$1$1
$1
$1$1$1$1
$1
$1 $1 $1
$1$1
$1
$1
$1
$1
$1 $1$1
$1
$1
$1$1$1
$1$1
$1$1
$1
$1
$1 $1 $1
$1$1
$1
$1 $1$1 $1
$1
$1$1
$1$1
$1 $1
$1$1$1$1
$1
$1
$1
$1$1
$1
$1$1
$1
$1
$1$1$1$1$1 $1
$1
$1
$1
$1
$1
$1$1
$1$1
$1
$1
$1
$1
$1$1
$1
$1
$1
$1
$1
$1
$1
$1$1
$1$1
$1
!!
!!
!!
!!
!!
!! !!
!!
!!
!!
!!
!!
!!
!!
!!
!! !! !! !! !!
!! !!
!!
!!
!! !!
!!
!!
!!
!!
!!
!!
!!
!! !!
!!
!!
!! !!
!!
!!
!!
!!
!! !!
!!
!!
!! !! !!
!!
!!
!!
!!
!!
!!
ARYANA
DR
EOLUSAV RAVEAN CT
PLATO PL
BURGUNDY RD
I-5 NB
I-5 SB
I-5 RA
PIRAEUS ST
HAW
K
VIEW
DR
I-5
EL CAMINO REAL
SKY LOFT RD
GASCONY RD
TRAILEASEMENT
SAXONY RD
LA COSTAAV
Copyright nearmap 2015
Legend
City Boundary
Sewer Access Hole
!( Standard
Storm Junction
!! Junction
Storm Cleanout
$1 Cleanout
Author: An dy Chang Date: 1/30/2023 Docu ment P ath: Z:\E ric_Z ielke\Pavem ent\O verl ay\ForCon tractor\ForContractor_A ppend ix_B-3.mxd Appendix B-3
¯
* Utilities based on assets serviced by City of Carlsbad only. Some areas may be serviced by Leucadia Wastewater District (LWWD) and Vallecitos Water District (VWD) and are not shown on this map.
Contractor to verify utilities not serviced by City of Carlsbad.
D
APPENDIX “C”
CITY OF CARLSBAD
ROAD WORK
ABC CONTRACTORS
OFFICE # (760) XXX-XXXX
FIELD # (760) XXX-XXXX
Dear resident:
As a part of the City of Carlsbad’s ongoing program to
maintain its streets, your street will be resurfaced with asphalt concrete over the existing roadway surface. This construction will require the closing of your street to through traffic for one day. Your street, from XYZ St. to DEF Ave. will be closed to through traffic and resurfaced on:
MON. TUE. WED. THU. FRI.
DATE: / /
from 7:00A.M. to 5:00 P.M.
If you don’t plan to leave your home by 7:00 A.M. on the above date, please park your car on an adjacent street in your neighborhood that will not be resurfaced. Streets
scheduled for resurfacing can be determined by calling
either the Contractor or the City of Carlsbad’s Project Inspector. When walking to and from your car, remember
not to walk on the newly overlaid street or you will have black residue on the bottom of your shoes. Please do not drive, walk on, walk pets, play, or skate on the newly
overlaid asphalt. Also, please refrain from watering you r lawns, washing cars, etc., approximately 6 -8 hours after the asphalt is laid as running water will cause damage to the new surface.
You may call the Contractor that will be performing the resurfacing work for the city at the above phone number if you have any questions. Resurfacing of your street will not occur on the day your trash is collected. Mail delivery may be delayed if the postman cannot reach the mailbox
that day. If you have a moving company or other service scheduled for that day , please call and inform the
Contractor of the date. If you have any concerns which
cannot be addressed by the Contractor, you may call the City’s Project Inspector @ (xxx) xxx-xxxx.
Thank you for your cooperation as we work to make a
better City of Carlsbad.
Tammy Cloud-McMinn
Subject: RE: No Roundabout
From: Marcellina Kim <[email protected]>
Date: February 6, 2023 at 9:33:19 AM PST
All Receive - Agenda Item # ~
For the Information of the :
CITY COUNCIL
Datd MrZ!> CA ..rec _-::_'
CM -LACM .....I<!'.:. DCM (3) ./
To: Priya Bhat-Patel <[email protected]>, Keith Blackburn <[email protected]>, Melanie Burkholder <[email protected]>, Teresa Acosta <[email protected]>
Subject: No Roundabout
Please, no roundabout at Carlsbad Blvd. and Tamarack.
I don't live in proximity to this intersection, but enjoy heading to the coast as many residents.
Don't hinder our enjoyment and adopt a more reasonable solution.
Thank you,
Marcellina Friedrich
6629 Hollylyeaf Court 92011
CAUTION: Do not open attachments or click on links unless ou reco nize the sender an know the content is safe.
1 2022 East-West Corridors
Tom Frank, Transportation Director/City Engineer
Transportation Department
Feb. 7, 2023
RECOMMENDED ACTION
• Approve plans and contract, and authorize to
bid
• Approve roadway reconfiguration and
associated level of service for westbound
Carlsbad Village Drive to El Camino Real
ITEM 15: EAST WEST CORRIDORS
2 3
Safer Streets Together Plan
44 5
DESIGN FEATURES
6 6
Benefits for all users
• Reduces speeding
• More separation between cars and bikes
• Improves the line of sight and access for side
street users
• Identifies conflict areas
• Reduces the long-term maintenance costs
7 ITEM 15: EAST WEST CORRIDORS
Striping Approach
• 10 to 10.5-foot-wide vehicle lanes
• 8-foot bike lanes
• Buffers next to door-zones and vehicles
• Green paint reserved for conflict zones
• Reflectors added next to medians
• Transitions to interchanges
8 ITEM 15: EAST WEST CORRIDORS
Reconfigure Arterials Approach
• Typically, no change to number of
vehicle lanes approaching intersections
• Intersection Guidelines for
Transportation Impact Studies in the San
Diego Region
• Comply with Mobility Element
9 ITEM 15: EAST WEST CORRIDORS
10 10
11 11
Avenida Encinas- Palomar Airport Rd to Cannon Rd
12 ITEM 15: EAST WEST CORRIDORS
13 13
Carlsbad Village Drive
ITEM 15: EAST WEST CORRIDORS
• Road reconfiguration Appian Road to Chatham Road
• Changing travel lanes at two intersections
– Pontiac Drive and Concord Drive
• LOS C to LOS D - westbound
• No congestion at intersections
Public input
• Traffic & Mobility Commission
• Community input
14 ITEM 15: EAST WEST CORRIDORS
NEXT STEPS
15 ITEM 15: EAST WEST CORRIDORS
• City Council to award contract early spring
• Target construction late spring
• Complete this summer
RECOMMENDED ACTION
• Approve plans and contract, and authorize to
bid
• Approve roadway reconfiguration and
associated level of service for westbound
Carlsbad Village Drive to El Camino Real
ITEM 15: EAST WEST CORRIDORS
16