CA Review GH
Meeting Date: Nov. 14, 2023
To: Mayor and City Council
From: Scott Chadwick, City Manager
Staff Contact: Brian Bacardi, Public Works Superintendent [email protected], 442-339-2944
Subject: Approval of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the Las Palmas Roof Replacement Project
District: 2
Reco
mmended Action
Adopt a resolution approving the plans, specifications and contract documents and authorizing the City Clerk to advertise for bids for the Las Palmas Roof Replacement Project.
Executive Summary
The Las Palmas facility, located at 2075 Las Palmas Drive, as shown in Exhibit 2, is a city-owned property leased to Mira Costa College for its Technology Career Institute programs. The five- year lease agreement was entered into on Sept. 22, 2021.
The Las Palmas facility was built in 1986, and the roof is now leaking and needs replacement.
Under the terms of Article 10.3 of the lease agreement provided as Exhibit 3, the city is responsible for keeping the roof in good order. Staff request the City Council’s approval of the plans, project specifications and contract documents for the Las Palmas Roof Replacement Project to be used to solicit construction bids to complete this work.
City Council approval of these plans and specifications is required under Carlsbad Municipal Code Section 3.28.080(E) because the expected cost of this work is greater than $200,000.
Explanation & Analysis
The Facilities Maintenance Division coordinates routine preventive maintenance inspections on all city facility roofs twice a year. In early 2020, the Las Palmas facility roof was identified with chronic issues and needed replacement. The Las Palmas Roof Replacement Project, Capital Improvement Program Project No. 4752, was then approved as part of the fiscal year 2021-22 budget process.
The plans, specifications and contract documents, as shown in Exhibit 4, have been submitted for the required building permit. A building permit will be on file with the Building Division of the Community Development Department, ready to be used by the successful bidder.
Nov. 14, 2023
Item #2 Page 1 of 8
The scope of the project includes the complete removal and replacement of the existing modified bitumen roofing, insulation and flashings, a traditional roofing method. The underlying layer will be inspected and areas with identified defects will be replaced. New insulation will be installed, as well as a new ketone ethylene ester roof system, the preferred and more modern roofing system for this type of building.
As an added value for the project, staff intend to purchase the materials for this project t
hrough a cooperative purchasing agreement and provide them to the awarded contractor for installation. Staff intend to return to the City Council with a request to authorize purchase of the materials at the same time the City Council is asked to accept a construction contract to the lowest responsive and responsible bidder. This will result in an estimated 25% savings for the city on the materials portion of the project.
Staff request City Council approval of the completed and permitted project plans, specifications and contract documents, and authorization for the City Clerk to advertise the project for construction bids.
Fiscal An
alysis
Sufficient funding is available in the Capital Improvement Program Project No. 4752 budget to complete the project. The funding source for the project is the Infrastructure Replacement Fund.
La Palmas Roof Replacement Project
Capital Improvement Program Project No. 4752
Total appropriation to date $500,000
Total expenditures/encumbrances to date $0
Total available balance $500,000
Project Costs
Construction contract (engineer’s estimate) -$223,700
Construction materials via cooperative purchasing (estimated) -$201,300 Construction management (estimated) -$75,000
Total estimated construction costs -$500,000
Estimated additional appropriation needed $0
Next Steps
With the City Council’s approval, the City Clerk will advertise a request for bids for the project.
Staff will then evaluate the bids received and identify the lowest responsive and responsible bidder.
Staff will then return to the City Council in fall 2023 with a recommendation to award a construction contract to the identified lowest responsible and responsive bidder.
Construction is expected to begin in early 2024 with an anticipated project duration of four to six weeks.
Nov. 14, 2023
Item #2 Page 2 of 8
Environmental Evaluation
The City Planner, through the process outlined in Carlsbad Municipal Code Section 19.04.060, has determined that the project belongs to a class of projects that the state Secretary for Natural Resources has found do not have a significant impact on the environment, and it is therefore categorically exempt from the requirement for the preparation of environmental documents in accordance with Section 15301 (d) of California Environmental Quality Act guidelines.
In making this de termination, the City Planner has found that the exceptions listed in Section 15300.2 of the CEQA guidelines do not apply to this project. The project is consistent with the Class 1 exemption in Section 15301(d) because it consists of maintenance of public facilities, such as the restoration or rehabilitation of deteriorated or damaged structures, facilities, or mechanical equipment to meet current standards of public health and safety.
Exhibits
1. City Council resolution
2. Location map
3. Lease Agreement with Mira Costa College ( on file in the Office of the City Clerk)
4. Plans, specifications and contract documents ( on file in the Office of the City Clerk) Nov. 14, 2023
Item #2 Page 3 of 8
RESOLUTION NO. 2023-270
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE PLANS, SPECIFICATIONS AND CONTRACT
DOCUMENTS AND AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS
FOR THE LAS PALMAS ROOF REPLACEMENT PROJECT
WHEREAS, the City Council of the City of Carlsbad, California has determined that the plans, specifications and contract documents for the Las Palmas Roof Replacement Project, Capital Improvement Program Project No. 4752, have been completed to the satisfaction of staff; and WHEREAS, the City Council has determined it necessary, desirable and in the public interest to construct the project; and
WHEREAS, the plans, specifications and contract documents for the project have been prepared, are on file in the City Clerk's office and are incorporated by reference; and WHEREAS, the City Council approval of the plans and specifications is required under Carlsbad Municipal Code Section 3.28.080(E) because the expected value to construct the project exceeds the $200,000 limit established by the Public Contract Code, including the alternative provisions of the Uniform Public Construction Cost Accounting Act; and
WHEREAS, the City Planner has determined that the project is exempt from the California Environmental Quality Act, or CEQA, Guidelines Section 15301(d), which applies to the restoration or rehabilitation of deteriorated or damaged structures, facilities, or mechanical equipment to meet current standards of public health and safety, and that no exception to the exemption as set forth in CEQA Guidelines Section 15300.2 applies.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the plans, specifications and contract documents for the Las Palmas Roof Replacement Project, Capital Improvement Program Project No. 4752, are approved and are on file in the City Clerk's Office.
3. That the City Clerk is hereby authorized and directed to publish, in accordance with state law and Carlsbad Municipal Code Section 3.28.080((), a notice to contractors inviting bids for construction of the project in accordance with plans, specifications and contract documents referred to herein.
Exhibit 1
Nov. 14, 2023 Item #2 Page 4 of 8
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 14th day of November, 2023, by the following vote, to wit:
AYES:
NAYS:
ABSTAIN:
ABSENT:
Blackburn, Bhat-Patel, Acosta, Burkholder, Luna.
None.
None.
None.
�
SHERRY FREISINGER, City Clerk r
(SEAL}
Nov. 14, 2023 Item #2 Page 5 of 8
AMBROSIA
LN
CORTE DE LA PINA
CORTEDELABETO
CASSIA RD
CORTE
DELNOGAL
OWENS AV
LAS PALMAS DR
CAMINO VIDA ROBLE
PALOMAR AIRPORT RD YARROW DR
Copyright nearmap
LOC ATI ON MA P
PROJECT NAME EXHIBIT
2 LAS PALMAS ROOF REPLACEMENT
$
!Å
**#5$
**#
5$ ·|}þ78
VISTA
ENCINITAS
SAN MARCOS
S.D. COUNTY
OCEANSIDE
PACIFIC
OCEAN
TAMARACK AV
LA C OSTA AV
P OINSETTIA LN
CARLSBAD
BL
EL CAMINOREALAVI
AR
A
PY
A LGARD
CA NNONRD
Created By: Sara Jadhav 8/7/2023 J:\SaraJadhav_Customers\BrianBacardi\LasPalmasRoofReplacement\LocationMap-4752.mxd
SITE LOCATION
2075 Las Palmas Dr
$
!Å
PROJECT
NUMBER
4752
2075
Las Palmas
Drive
Exhibit 2
Nov. 14, 2023
Item #2 Page 6 of 8
Exhibit 3
Lease Agreement with Mira Costa College
(on file in the Office of the City Clerk)
Nov. 14, 2023
Item #2 Page 7 of 8
Exhibit 4
Plans, specifications and contract documents
(on file in the Office of the City Clerk)
Nov. 14, 2023
Item #2 Page 8 of 8
00 01 01 TITLE PAGE Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
CITY OF CARLSBAD
CONTRACT DOCUMENTS, SUPPLEMENTAL PROVISIONS
AND TECHNICAL SPECIFICATIONS
FOR:
LAS PALMAS ROOF REPLACEMENT
Project No. 4752
PWS24-2330FAC
1635 Faraday Ave, Carlsbad, CA 92008
Email: [email protected]
Exhibit 4
TABLE OF CONTENTS Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
Table of Contents
SECTION 1 ......................................................................................... Error! Bookmark not defined. 00 11 10 NOTICE INVITING BIDS ................................................... Error! Bookmark not defined.
1. RECEIPT OF BIDS. .............................................................. Error! Bookmark not defined.
2. DESCRIPTION OF WORK. ................................................... Error! Bookmark not defined.
3. COMPLETION OF WORK. ................................................... Error! Bookmark not defined.
4. OPENING AND AWARD OF BIDS. ...................................... Error! Bookmark not defined.
5. PERIOD FOR AWARD. ........................................................ Error! Bookmark not defined.
6. BIDDER QUALIFICATIONS. ................................................. Error! Bookmark not defined.
7. PRE-BID CONFERENCE. ...................................................... Error! Bookmark not defined.
8. OBTAINING CONTRACT DOCUMENTS. ............................. Error! Bookmark not defined.
9. BID GUARANTEE AND BONDS. .......................................... Error! Bookmark not defined.
10. PREVAILING WAGE RATES AND LABOR COMPLIANCE. ..... Error! Bookmark not defined.
11. PROJECT ADMINISTRATION/QUESTIONS.......................... Error! Bookmark not defined. 00 21 10 INSTRUCTIONS TO BIDDERS ........................................... Error! Bookmark not defined.
1. SECURING CONTRACT DOCUMENTS. ............................... Error! Bookmark not defined.
2. EXAMINATION OF SITE AND CONTRACT DOCUMENTS. ... Error! Bookmark not defined.
3. INTERPRETATION OF DRAWINGS AND DOCUMENTS. ...... Error! Bookmark not defined.
4. QUESTIONS. ...................................................................... Error! Bookmark not defined.
5. PRE-BID CONFERENCE. ...................................................... Error! Bookmark not defined.
6. ADDENDA. ......................................................................... Error! Bookmark not defined.
7. ALTERNATE BIDS. .............................................................. Error! Bookmark not defined.
TABLE OF CONTENTS Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
8. COMPLETION OF BID FORMS. ........................................... Error! Bookmark not defined.
9. GOVERNING GENERAL PROVISIONS ................................. Error! Bookmark not defined.
10. MODIFICATIONS OF BIDS. ................................................. Error! Bookmark not defined.
11. BID GUARANTEE. ............................................................... Error! Bookmark not defined.
12. LABOR & MATERIAL BOND AND PERFORMANCE & WARRANTY BOND REQUIREMENTS. ........................................................................ Error! Bookmark not defined.
13. SUBSTITUTION OF SECURITY. ............................................ Error! Bookmark not defined.
14. OPTIONAL ESCROW FOR SECURITY DEPOSIT. ................... Error! Bookmark not defined.
15. INSURANCE REQUIREMENTS ............................................ Error! Bookmark not defined.
16. LICENSING REQUIREMENTS. ............................................. Error! Bookmark not defined.
17. SUBCONTRACTORS. .......................................................... Error! Bookmark not defined.
18. BIDDER INFORMATION AND EXPERIENCE FORM. ............ Error! Bookmark not defined.
19. NON-COLLUSION AFFIDAVIT. ............................................ Error! Bookmark not defined.
20. IRAN CONTRACTING ACT OF 2010. ................................... Error! Bookmark not defined.
21. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION. .... Error! Bookmark not defined.
22. PREVAILING WAGES. ......................................................... Error! Bookmark not defined.
23. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS. ........... Error! Bookmark not defined.
24. SIGNING OF BIDS. .............................................................. Error! Bookmark not defined.
25. SUBMISSION OF SEALED BIDS. .......................................... Error! Bookmark not defined.
26. OPENING OF BIDS. ............................................................ Error! Bookmark not defined.
27. WITHDRAWAL OF BID. ...................................................... Error! Bookmark not defined.
28. BIDDERS INTERESTED IN MORE THAN ONE BID. .............. Error! Bookmark not defined.
TABLE OF CONTENTS Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
29. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES, AND FEES. ................ Error! Bookmark not defined.
30. PERMIT AND INSPECTION FEE ALLOWANCE. .................... Error! Bookmark not defined.
31. BASIS OF AWARD; BALANCED BID. ................................... Error! Bookmark not defined.
32. AWARD PROCESS. ............................................................. Error! Bookmark not defined.
33. EXECUTION OF CONTRACT. .............................................. Error! Bookmark not defined.
34. BUSINESS LICENSE ............................................................. Error! Bookmark not defined.
35. PARTICIPATION OF MINORITY AND WOMEN-OWNED BUSINESSES. .... Error! Bookmark not defined.
36. USE OF RECYCLED MATERIALS .......................................... Error! Bookmark not defined.
37. STATUTORY REFERENCES .................................................. Error! Bookmark not defined. 00 41 00 BID FORM ....................................................................... Error! Bookmark not defined.
1. BID SCHEDULE ................................................................... Error! Bookmark not defined.
2. TOTAL BID PRICE ............................................................... Error! Bookmark not defined.
3. RECITALS ........................................................................... Error! Bookmark not defined. 00 43 10 BID BOND FORM ............................................................. Error! Bookmark not defined. 00 43 20 BID SECURITY .................................................................. Error! Bookmark not defined. 00 43 30 PROPOSED SUBCONTRACTORS FORM ........................... Error! Bookmark not defined. 00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM ........... Error! Bookmark not defined.
1. INFORMATION ABOUT BIDDER ......................................... Error! Bookmark not defined.
2. LIST OF CURRENT PROJECTS (BACKLOG) .......................... Error! Bookmark not defined.
3. VERIFICATION AND EXECUTION ........................................ Error! Bookmark not defined. 00 45 10 NON-COLLUSION AFFIDAVIT .......................................... Error! Bookmark not defined.
TABLE OF CONTENTS Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
00 45 15 IRAN CONTRACTING ACT CERTIFICATION ...................... Error! Bookmark not defined. 00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION ... Error! Bookmark not defined.
00 45 25 CERTIFICATE OF INSURANCE .......................................... Error! Bookmark not defined. 00 45 25 STATEMENT REGARDING DEBARMENT .......................... Error! Bookmark not defined. 00 45 35 DISCLOSURE OF DISCIPLINE RECORD ............................. Error! Bookmark not defined. 00 52 00 CONTRACT ...................................................................... Error! Bookmark not defined. 00 61 10 LABOR AND MATERIALS BOND ...................................... Error! Bookmark not defined. 00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND ....... Error! Bookmark not defined. 00 61 30 OPTIONAL ESCROW AGREEMENT .................................. Error! Bookmark not defined. 00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS .......... Error! Bookmark not defined.
INTRODUCTION ......................................................................... Error! Bookmark not defined. 00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS ..................................................... 1 INTRODUCTION ......................................................................... Error! Bookmark not defined.
PART 2 CONSTRUCTION MATERIALS ......................................... Error! Bookmark not defined.
SECTION 2 ......................................................................................... Error! Bookmark not defined. 01 11 00 SUMMARY OF WORK ...................................................... Error! Bookmark not defined.
PART 1 GENERAL ........................................................................ Error! Bookmark not defined.
PART 2 PRODUCTS (NOT USED) ................................................. Error! Bookmark not defined.
PART 1 EXECUTION (NOT USED) ................................................ Error! Bookmark not defined. 01 11 20 MEASUREMENT AND PAYMENT .................................... Error! Bookmark not defined.
PART 1GENERAL ......................................................................... Error! Bookmark not defined.
PART 2 PRODUCTS (NOT USED) ................................................. Error! Bookmark not defined.
TABLE OF CONTENTS Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
PART 3 EXECUTION (NOT USED) ................................................ Error! Bookmark not defined. 01 32 00 SUBMITTALS ................................................................... Error! Bookmark not defined.
PART 1 GENERAL ........................................................................ Error! Bookmark not defined.
PART 2 PRODUCTS (NOT USED) ................................................. Error! Bookmark not defined.
PART 3 EXECUTION (NOT USED) ................................................ Error! Bookmark not defined. 01 33 00 CONSTRUCTION PROGRESS SCHEDULE .......................... Error! Bookmark not defined.
PART 1 GENERAL ........................................................................ Error! Bookmark not defined.
PART 2 EXECUTION .................................................................... Error! Bookmark not defined. 01 41 26 PERMIT REQUIREMENTS ................................................ Error! Bookmark not defined.
PART 1 GENERAL ........................................................................ Error! Bookmark not defined.
PART 2 PRODUCTS (NOT USED) ................................................. Error! Bookmark not defined.
PART 3 EXECUTION (NOT USED) ................................................ Error! Bookmark not defined. 01 50 00 TEMPORARY FACILITIES AND CONTROLS ....................... Error! Bookmark not defined.
PART 1 GENERAL ........................................................................ Error! Bookmark not defined.
PART 2 PRODUCTS (NOT USED) ................................................. Error! Bookmark not defined.
PART 3 EXECUTION (NOT USED) ................................................ Error! Bookmark not defined.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
SECTION 1
00 11 10 NOTICE INVITING BIDS
1. RECEIPT OF BIDS.
The City of Carlsbad / Carlsbad Municipal Water District (“Agency”) will accept Bids via electronic format via the City of Carlsbad Electronic Bidding Site up to and no later than Tuesday, February 6, 2024 at 11 a .m. through the online bidding portal (Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov)) for the construction of the Work entitled:
LAS PALMAS ROOF REPLACEMENT
PWS24-2330FAC
Project No. 4752
2. DESCRIPTION OF WORK.
The Work includes the provision of all equipment, labor, materials, tools, services, transportation, permits, utilities, and all other items necessary to complete the construction of the following, as specified and shown in the Construction Documents: The Las Palmas Building is located at 2075 Las Palmas Drive in Carlsbad, CA 920 11.The City desires to replace the existing 23,400 sf low slope roofing with single ply membrane.
3. COMPLETION OF WORK.
The Contract Time is established as ninety (90) working days. The Contract Time shall begin as specified in the Notice to Proceed. The Engineers’ estimate for this Project is $450,000.00.
4. OPENING AND AWARD OF BIDS.
Agency shall consider awarding the Contract for the Project to the lowest, responsive, responsible Bidder as determined by the Agency from the base Bid alone. The Agency has the right to reject any or all Bids or to waive any irregularities or informalities in any Bids or in the Bidding process.
5. PERIOD FOR AWARD.
A period of ninety (90) Calendar Days from the time of Bid opening may be required to award the Contract. No Bidder may withdraw its Bid or Bid Guarantee during this period. Bidders shall assume full responsibility for their Bid Price during this period and shall make certain that such delay does not restrict the Bid Guarantee.
6. BIDDER QUALIFICATIONS.
Bidders shall be licensed contractors pursuant to Business and Professions Code Sections 7000 et seq. under the classification of C-39, Roofing, or Class B, General Building Contractor, as of the date of submittal of the Bid Documents and shall maintain such license until final acceptance of the Work. Additional qualifications are included in the Contract Documents.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
7. PRE-BID CONFERENCE.
The Agency will conduct a Mandatory Pre-Bid Conference at the Agency’s office (address listed below) on Tuesday, January 16, 2024 at 10 a.m.. Bidders will have the opportunity to walk the roof.
Address: 2075 Las Palmas Dr., Carlsbad, CA 92011
Representatives of the Agency , consulting engineers and architects, if any, will be present.
Questions asked by Bidders at the Pre -Bid Conference not specifically addressed within the Contract Documents shall be submitted in writing through the bidding portal, and be answered in writing, and shall be sent to all Bidders present at the Pre -Bid Conference and be posted on the online bidding portal. Bids will not be accepted from any bidder who did not attend the Mandatory Pre-Bid Conference.
8. OBTAINING CONTRACT DOCUMENTS.
Bidders may obtain a copy of the Contract Documents from Agency’s website (Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) ). To the extent required by Public Contract Code Section 20103.7, upon request from a contractor plan room service, the Agency shall provide an electronic copy of the Contract Documents at no charge to the contractor plan room. It is the responsibility of each prospective Bidder to download and print all Bid Documents for review and to verify the completeness of Bid Documents before submitting a Bid. All Addenda will be posted on the online bidding portal. It is the responsibility of each prospective Bidder to check the online bidding portal on a daily basis through the close of the bidding period for any applicable Addenda.
The Agency does not assume any liability or responsibility for any defective or incomplete copying, excerpting, scanning, faxing, downloading or printing of the Bid Documents. Information on the online bidding portal may change without notice to prospective Bidders. The Contract Documents shall supersede any information posted or transmitted by the online bidding portal.
No time extensions or other consideration will be given for non -receipt or other circumstance associated with the review or acquisition of Contract Documents. Bids must be submitted on the Agency’s Bid Forms in the Contract Documents.
9. BID GUARANTEE AND BONDS.
Each Bid shall be accompanied by cash, a certified or cashier’s check or Bid Bond secured from a surety company satisfactory to the Agency, the amount of which shall not be less than 10% of the submitted Total Bid Price, made payable to the Agency as bid security. The bid security shall be provided as a guarantee that within 10 Working Days after the Agency provides the successful bidder the Notice of Award, the successful Bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful Bidder fails to comply within these 10 Working Days. No interest will be paid on funds deposited with the Agency.
All Bidders must upload Bidder’s Bond to the online bidding portal. The original Bid Bond for the 3 apparent low Bidders must be submitted to the city within 2 Business Days of Bid opening.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
The successful Bidder will be required to furnish a Faithful Performance Bond and a Labor and Material Bond each in an amount equal to 100% of the Contract Price. Each bond shall be in the forms set forth in the Contract Documents, shall be secured from a surety company that meets all State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer. Pursuant to Public Contract Code Section 22300 , the successful Bidder may subst itute certain securities for funds withheld by Agency to ensure its performance under the Contract.
10. PREVAILING WAGE RATES AND LABOR COMPLIANCE.
This Project is subject to prevailing wages and labor compliance per the Labor Code. To this end, Bidder shall sign and submit with its Bid the California Department of Industrial Relations (DIR) Public Works Contractor Registration Certification on the form 00 45 00 provided. Failure to submit this form may render the bid non -responsive. In addition, each Bidder shall provide the registration number for each listed Subcontractor in the space provided in the Proposed Subcontractors form. In bidding this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this Contract and applicable law in its Bid. A copy of the prevailing wage rates may be obtained via the internet at: www.dir.ca.gov/dlsr/.
11. PROJECT ADMINISTRATION/QUESTIONS.
Requests for Information (RFI) or interpretations of Bid Documents during the bid period shall be submitted via Online Q&A in the online bidding portal.
The cutoff date and time to submit questions or substitution request regarding this Project via Online Q&A in the online bidding portal is Thursday, January 18, 2024 at 5 p.m. . No questions will be entertained after that date.
For further information, see the online bidding portal.
END OF SECTION
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 21 10 INSTRUCTIONS TO BIDDERS
1. SECURING CONTRACT DOCUMENTS.
Bids must be submitted to the Agency on the Bid Forms which are a part of the Contract Documents for the Project. The Contract Documents may be obtained from the Agency’s online bidding portal (Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) ). Prospective bidders are encouraged to communicate with the Agency well in advance of the date and time bids are due to the Agency (“Bid Submission Deadline”) to determine the availability of Contract Documents.
The Agency may also make the Contract Documents available for review at one or more plan rooms. Prospective Bidders who choose to review the Contract Documents at a plan room must contact the Agency to obtain the required Contract Documents if they decide to submit a Bid for the Project.
Addenda will be posted on the online bidding portal . Failure to acknowledge all Addenda may make a Bid nonresponsive and ineligible for award of the Contract. Bidders are advised to verify the issuance of all Addenda and receipt of them 1 Working D ay prior to bidding. Failure to acknowledge all Addenda may make a Bid nonresponsive and ineligible for award of the Contract.
2. EXAMINATION OF SITE AND CONTRACT DOCUMENTS.
At its own expense and before submitting its Bid, each Bidder shall attend the Mandatory Pre - Bid meeting and fully acquaint itself with the conditions relating to the construction and labor required so that the Bidder may fully understand the Work, including but not limited to, difficulties and restrictions attending the execution of the Work under the Contract. Each Bidder shall carefully examine the Drawings, and shall read the Specifications, Contract Documents, and all other referenced documents. Each Bidder shall also determine the local conditions which may in any way affect the performance of the Work, including local tax structure, contractors’ licensing requirements, availability of required insurance, the prevailing wages and other relevant cost factors. Each Bidder shall also familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the Work, including the cost of permits and licenses required for the Work, and shall make such s urveys and investigations, including investigations of subsurface or latent physical conditions at the Site or where Work is to be performed as may be required. Bidders are responsible for consulting the standards referenced in the Contract. The failure or omission of any Bidder to receive or examine any contract documents, forms, instruments, addenda, or other documents, or to visit the Site and acquaint itself with conditions there existing shall in no way relieve any Bidder from any obligation with respe ct to its Bid or to the Contract and no relief for error or omission will be given except as required under California law. The submission of a Bid shall be taken as conclusive evidence of compliance with this Section.
3. INTERPRETATION OF DRAWINGS AND DOCUMENTS.
During the bidding period, prospective Bidders unclear as to the true meaning of any part of the Drawings, Specifications or other parts of the Contract Documents, or discrepancies in or
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
omissions from the Drawings and Specifications, may promptly submit a written request for information, interpretation, clarification, or correction (“RFI”) to the Bid Administrator (defined below). The Agency may not respond to RFIs submitted past the Q&A Submission Deadline. The Bidder submitting the RFI is responsible for prompt delivery to the Bid Administrator.
Responses to RFIs will be made only by duly issued written Addenda. The Agency shall not provide verbal responses to RFIs. Copies of written Addenda will be posted on the online bidding portal for each prospective Bidder who has downloaded a set of Contract Documents. The Agency will not be responsible for any other explanation or interpretations of the Drawings, Specifications or other parts of the Contract Documents. If any Prospective Bidder becomes aware of any errors or omissions in any part of the Contract Documents, the Prospective Bidder must promptly notify the Agency of such error or omission.
Before award of the Contract, no addition to, modification of, or interpretation of any provision in the Contract Documents will be given by any agent, employee or contractor of the Agency except as otherwise specified in these Instructions to Bidders. No bidder may rely on verbal directions given by any agent, employee or contractor of the Agency except as specified in these Instructions to Bidders.
4. QUESTIONS.
Questions regarding this Project must be submitted through the online bidding portal. Questions shall be definite and certain, and shall reference applicable drawing sheets, notes, details or specification sections. The deadline to submit questions is iden tified in the Notice Inviting Bids.
Questions received after the deadline may not be answered. Responses to questions submitted during the bidding period will be published in an Addendum and provided to those bidding on the Project no later than the date specified in the Notice Inviting Bids.
Except for the Agency’s Bid Administrator, no other members of the Agency’s staff or Board should be contacted about this procurement during the bidding process. All inquiries and comments from Prospective Bidders regarding a proposed Bid must be communicated in writing, unless otherwise instructed by the Agency. The Agency may, in its sole discretion, disqualify any Prospective Bidder who engages in any prohibited communications.
5. PRE-BID CONFERENCE.
Bids will not be accepted from any bidder who did not attend a Mandatory Pre -Bid Conference.
The Conference will commence at the specified start time and the Site visit will begin at the conclusion of the Conference. Prospective Bidders who arrive late (t en or more minutes after the Conference has started) or who do not sign the “Sign-In” sheet, may be disqualified from the bidding process.
Representatives of the Agency and its consultants, if any, will be present to the extent possible.
Questions asked by Bidders at the Pre -Bid Conference not specifically addressed within the Contract Documents shall be answered in writing and shall be sent to all Bidders present at the Pre-Bid Conference.
I ■
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
A Pre -Bid Conference may include a Project Site visit. Personal Protective Equipment (PPE) is required of all Job Walk attendees. Attendees are required to wear closed toe shoes and long pants. Sleeved shirts, safety glasses (may be prescription with side shields if in process areas), safety vests and hard hats are recommended. Only those possessing required attire will be allowed on the Job Site. The Agency will not provide personal protective equipment to Job Walk attendees.
6. ADDENDA.
The Agency may revise the Contract Documents before the Bid Submission Deadline. Revisions, if any, shall be made by written Addenda. All Addenda will be posted on the online bidding portal.
All Addenda issued by the Agency shall be acknowledged by the Bidder on the online bidding portal and made part of the Contract Documents. The Bidder shall acknowledge the Addenda before submitting its Bid. Bidders are responsible for the receipt of all Addenda. The Agency may reject a Bid if the Bidder fails to acknowledge all Addenda.
Pursuant to Public Contract Code Section 4104.5, if the Agency issues an Addendum which includes material changes to the Project less than 72 hours before the Bid Submission Deadline, the Agency will extend the Bid Submission Deadline by no less than 72 ho urs. The Agency may determine, in its sole discretion, whether an Addendum warrants postponement of the Bid Submission Deadline.
7. ALTERNATE BIDS.
If alternate Bid items are called for in the Notice Inviting Bids and the Contract Documents, the time required for completion of the Work for the alternate Bid items is factored into the Contract duration and no additional Contract time will be awarded. The Agency may elect to include one or more of the alternate Bid items, or to otherwise remove certain work from the Project scope of work. Accordingly, each Bidder must ensure that each Bid item contains a proportionate share of profit, overhead, and other costs or expenses which will be incurred by the Bidder.
If the Agency utilizes alternate Bid items as described above, the Notice Inviting Bids will prescribe predetermined criteria for the Bid package selection or a selection process in which price information and Bidder identities are not revealed to the Agency before the Bid Submission Deadline.
8. COMPLETION OF BID FORMS.
Bids shall only be prepared using the Bid Forms which are included in the Contract Documents.
The use of substitute Bid Forms other than legible and correct photocopies of those provided by the Agency are prohibited. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable), and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither de lete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. Use of black or blue ink, indelible pencil, or a typewriter is required.
Deviations from these instructions may result in the Bid being deemed non-responsive.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
The following documents must be completed and properly executed including notarization, where indicated, and submitted as a part of the complete Bid Package:
1. Bid Form (00 41 00)
2. Bid Bond (00 43 10) or Bid Security (00 43 20) with check/cash
3. Proposed Subcontractors Form (00 43 30)
4. Bidder Information and Experience Form (00 43 40)
5. Non-Collusion Affidavit (00 45 10)
6. Iran Contracting Act Certification (00 45 15)
7. Public Works Contractor Registration Certification (00 45 20)
8. Certificate of Insurance (00 45 25)
9. Statement Regarding Debarment (00 45 30)
10. Disclosure of Discipline Record (00 45 35)
11. Acknowledgement of ALL Addenda on the online bidding portal.
12. Optional Escrow Agreement, as applicable (00 61 30)
When paper copies are submitted, all prices must be written in ink or typewritten. Changes or corrections may be crossed out and typed or written in with ink and must be initialed in ink by a person authorized to sign for the Contractor.
9. GOVERNING GENERAL PROVISIONS.
The Specifications contained in the Agency Supplemental General Provisions (00 73 00) take precedence over the specification language contained in the Standard Specifications for Public Works Construction, “the Greenbook” latest edition and all errata. The Supplemental General Provisions address th e unique conditions in the City of Carlsbad that are not addressed in the Greenbook. Therefore, if there is a conflict between the two, the Supplemental Provisions shall control over the Greenbook.
The Greenbook may be purchased at Bidder’s/Contractor’s local technical bookstore, online or directly from the publisher. The Supplemental Provisions are available only for download from the online bidding portal with Contract Documents. The Agency does not provide hard copies.
10. MODIFICATIONS OF BIDS.
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions, or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall not delete, modify, or supplement the printed matter on the Bid Forms, or make substitutions thereon. Oral, telephonic, and electronic modifications will not be considered.
11. BID GUARANTEE.
Each Bid shall be accompanied by: (a) a cashier’s check; or, (b) a certified check made payable to Agency; or, (c) a Bid Bond secured from a surety company satisfactory to the Board, the amount of which shall not be less than 10% of the total bid price, made payable to Agency as bid security.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be a California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120.
The bid security shall be provided as a guarantee that within 10 Working Days after the Agency provides the successful Bidder the Notice of Award, the successful Bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security may be declared forfeited if the successful Bidder fails to enter into a contract and provide the necessary bonds and certificates of insurance. Any Bid received that does not comply with these Bid Guarantee instructions may be rejected as non-responsive, and Agency may enter into a contract with the next lowest, responsive, responsible Bidder, or may call for new Bids. No interest shall be paid on funds deposited with the Agency. Copies of Bid Bonds submitted to the Agency shall have the same force and effect as the original.
The Bidder’s security of the second and third next lowest responsive Bidders may be withheld until the Contract has been fully executed. The security submitted by all other unsuccessful Bidders shall be returned to them, or deemed void, within 10 Working Days after the Contract is awarded
The proceeds of the Bidder’s security may also become property of the Agency if the Bidder withdraws its Bid within 15 Calendar Days after the Bid opening date, unless otherwise required by law, including Public Contract Code Section 5100 et. seq., and notwithstanding the award of the Contract to another Bidder.
The Bidder shall submit Bid Bond (00 43 10) or Bid Security (00 43 20) with properly certified check with the Bid Package.
12. LABOR & MATERIAL BOND AND PERFORMANCE & WARRANTY BOND REQUIREMENTS.
The successful Bidder shall furnish Agency with a Labor and Material Payment Bond and a Performance and Warranty Bond, each in an amount equal to 100% of the Contract price. Each bond shall be secured from a surety company that meets all State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120 and is admitted by the State of California, and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The Agency shall not accept pe rsonal sureties and unregistered surety companies. Each bond shall be accompanied, upon the request of Agency, with all documents required by Code of Civil Procedure Section 995.660 to the extent required by law. All bonding and insurance requirements shall be completed and submitted to Agency within 10 Working Days from the date the Agency provides the successful Bidder with the Notice of Award.
These bonds shall be kept in full force and effect during the course of this Project, and shall extend in full force and effect and be retained by the Agency until they are released as stated in the Contract. The Bonds are to be accompanied by an original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
I ■
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
13. SUBSTITUTION OF SECURITY.
The Contract Documents call for monthly progress payments based upon the percentage of the Work completed. The Agency will retain a percentage of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidd er, the Agency will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.
14. OPTIONAL ESCROW FOR SECURITY DEPOSIT.
Pursuant to applicable provisions of law (i.e. , Public Contract Code Section 10263), appropriate securities may be substituted for any obligation required by these instructions or for any monies withheld by the Agency to ensure performance under the Contract. Public Contract Code Section 10263 requires monies or securities to be deposited with the Agency or a state or federally chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions o f the agent in connection with the handling of retentions under this section in an amount not less than $100,000 per contract.
15. INSURANCE REQUIREMENTS.
Before commencing the Work, the successful Bidder shall purchase and maintain insurance as set forth in the Agency General Conditions. If the Bid is accepted, and if requested by the Agency, Contractor shall provide Agency or preferred vendor copies of the insurer’s most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Insurance Code Section 900 et seq. within 10 Calendar Days of the insurer’s receipt of a request to submit the statements.
In accordance with the provisions of Labor Code Section 3700, Contractor shall secure the payment of compensation to its employees. Contractor shall sign and file with the Agency the following certificate before performing the Work under the Contract:
I am aware of the provisions of Labor Code Section 3700 , which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of the Contract.
The form of such, Certificate of Insurance (00 45 25), shall be submitted as a part of the Bid Package.
Insurance must be placed with insurers that:
1) Have a rating in the most recent Best’s Key Rating Guide of at least A-:VII, or 2) Appear on the List of Approved Surplus Line Insurers, (“LASLI”) with a Best’s Key Rating Guide of at least A: X.
3) Are admitted to conduct the business of insurance in the State of California by the Insurance Commissioner.
4) Otherwise comply with all other aspects of City Council Policy No. 70.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Auto policies offered to meet the specification of this Contract must:
1) Meet the conditions stated above for all insurance companies. 2) Cover any vehicle used in the performance of the Contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.
Workers’ compensation insurance required under this Contract must be offered by a company meeting the above standards with the exception that the Best’s rating condition may be waived.
The Agency does accept policies issued by the State Compensation Fund m eeting the requirement for workers’ compensation insurance.
The Contractor shall be required to maintain insurance as specified in the Contract. Any additional cost of the insurance shall be included in the Bid price.
The award of the Contract by the Board is contingent upon the Contractor submitting the required bonds and insurance, as described in the Contract Documents, within 10 Working Days of bid opening. If the Contractor fails to comply with these requirements, the Agency may award the Contract to the second or third lowest Bidder and the bid security of the lowest Bidder may be forfeited.
16. LICENSING REQUIREMENTS.
Pursuant to Business and Professions Code Section 7028.15 and Public Contract Code Section 3300, all Bidders must possess proper licenses for performance of the Contract. Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Business and Professions Code Section 7028.5, the Agency shall consider any Bid submitted by a contractor not currently licensed in accordance with California law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the Agency shall reject the Bid. The Agency shall have the right to request, and Bidders sh all provide within 10 Calendar Days, evidence satisfactory to the Agency of all valid license(s) currently held by that Bidder and each of the Bidder’s Subcontractors, before awarding the Contract.
Notwithstanding anything contained in this Contract , if the Work involves federal funds, the Contractor shall be properly licensed by the time the Contract is awarded, pursuant to the provisions of Public Contract Code Section 20103.5.
17. SUBCONTRACTORS.
Bidder shall set forth the name, address of the place of business, and contractor license number of each Subcontractor who will perform work, labor, furnish materials or render services to the bidder on the Contract. This requirement includes each Subcontractor licensed by the State of California who, under subcontract to Bidder, specially fabricates and installs a portion of the Work described in the Drawings and Specifications in an amount in excess of one -half of one percent (0.5%) of the total Bid price. Additionally, the Bidder shall indicate the portion of the Work to be done by each Subcontractor in accordance with Public Contract Code Section 4104.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Bidder shall submit Proposed Subcontractors Form (00 43 30) with the Bid Package.
This form will be used by the Agency to determine the percentage of work that the Bidder proposes to perform. Bidders are cautioned that failure to provide complete and correct information may result in rejection of the Bid as non -responsive. Any Bid that proposes performance of more than 50 percent of the Work by Subcontractors or performance by forces other than the Bidder’s own organization will be rejected as non -responsive. Specialty items of work that may be so designated on the Proposed Subcontractor s Form (00 43 30) “Contractor’s Bid” will not be included in computing the percentage of work proposed to be performed by the Bidder.
Suppliers of materials from sources outside the limits of Work are not Subcontractors. The value of materials and transport of materials from sources outside the limits of Work, as shown on the plans, shall be assigned to the Contractor or the Subcontractor, as the case may be, that the Bidder proposes as installer of the materials. The value of material incorporated in any Subcontractor-installed Bid item that is supplied by the Bidder shall be included as a part of the Work that the Bidder proposes to be performed by the Subcontractor installing the item.
When the Bidder proposes to use a Subcontractor to construct or install less than 100 percent of a Bid item, the Bidder shall attach an explanation sheet to the Proposed Subcontractor Form (00 43 30). The explanation sheet shall clearly apprise the Agency of the specific facts that show the Bidder proposes to perform no less than fifty percent (50%) of the Work with its own forces.
Determination of the subcontract amounts for purposes of award of the Contract shall be determined by the Board in conformance with the provisions of the Contract Documents. The decision of the Board shall be final.
Contractor is prohibited from performing any Work on this Project with a Subcontractor who is ineligible to perform work on a public works project pursuant to Labor Code Section 1771.1 or 1777.7.
Bidders shall make copies of the disclosure forms as may be necessary to provide the required information to Subcontractors. The page number and total number of additional form pages shall be entered in the location provided on each type of form so duplicated.
18. BIDDER INFORMATION AND EXPERIENCE FORM.
Each Bidder shall complete the provided questionnaire and shall submit the questionnaire along with its Bid. Failure to provide all information requested within the questionnaire along with the Bid may cause the Bid to be rejected as non -responsive. The Agency may reject any Bid if an investigation of the information submitted does not satisfy the Agency that the Bidder is qualified to properly carry out the terms of the Contract.
The Bidder shall submit Bidder Information and Experience Form (00 43 40) with the Bid Package.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
19. NON-COLLUSION AFFIDAVIT.
Bidders on all public works contracts are required to submit an affidavit of non -collusion with their Bid. This form (00 45 10 Non-Collusion Affidavit) is included with the Bid Package and must be signed and dated under penalty of perjury.
20. IRAN CONTRACTING ACT OF 2010.
In accordance with Public Contract Code Section 2200 et seq ., the Agency requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the Agency with respect to goods or services of $1,000,000 or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list created pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.
The form of such Iran Contracting Certificate is included with the Bid Package and must be signed and dated under penalty of perjury.
21. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION.
Pursuant to Labor Code Section 1773, the Agency has obtained the prevailing rate of per diem wages and the prevailing wage rate for holiday and overtime work applicable in San Diego County from the Director of the Department of Industrial Relations for eac h craft, classification, or type of worker needed to execute this Contract. A copy of these prevailing wage rates may be obtained via the internet at www.dir.ca.gov/dlsr/.
In addition, a copy of the prevailing rate of per diem wages is available at the Agency and shall be made available to interested parties upon request. The successful Bidder shall post a copy of the prevailing wage rates at each job site. It shall be manda tory upon the Bidder to whom the Contract is awarded, and upon any Subcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the specified prevailing wage rates to all workers employed by th em in the execution of the Contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors.
Pursuant to Labor Code Sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded the Contract, the Bidder and its Subcontractors, of any tier, sha ll maintain active registration with the Department of Industrial Relations for the duration of the Project.
This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. In bidding on this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance req uirements under the Contract and applicable law in its Bid.
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
To this end, Bidder shall sign and submit with its Bid the Public Works Contractor Registration Certification on the form provided, attesting to the facts contained in the registration certificate.
Failure to submit this certificate may render the Bid non-responsive. In addition, each Bidder shall provide the registration number for each listed Subcontractor in the space provided in the Proposed Subcontractors Form (00 43 30).
22. PREVAILING WAGES.
Pursuant to Labor Code Sections 1720, et. seq. and 1770, et. seq., Contractor shall pay prevailing wages for all Work performed under the Contract. The Agency has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which the Work will be performed for each craft or type of worker needed to execute the Contract. These rates are available at the Agency or may be obtained online at http://www.dir.ca.gov. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).
23. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS.
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code Section 1777.1 or 1777.7. An y contract on a public works project executed between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any pub lic money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the Agency. The Contractor shall be responsible for the payment of wages to workers of a debarred Subcontractor who has been allowed to work on the Project.
The Agency may disqualify a Contractor or Subcontractor from participating in bidding when a Contractor or Subcontractor has been debarred by the Agency or another jurisdiction in the State of California as an irresponsible bidder.
24. SIGNING OF BIDS.
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.
If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations that the Bidder assumes under the Bid and under any Contract
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.
25. SUBMISSION OF SEALED BIDS.
Once the Bid and supporting documents have been completed and signed as set forth in these Instructions to Bidders, they shall be uploaded, along with other required materials, to the online bidding portal before the deadline for submitting bids.
At the time of Bid submission, whether in the form of a cashier’s check, a properly certified check or an approved corporate surety bond payable to the Agency, Bidders must upload an electronic Portable Document Format (PDF) copy of the Bid Guarantee to the online bidding portal. The first 3 apparent low Bidders must provide the Agency with the original Bid Guarantee within 2 Business Days after the Bid opening date.
Failure to submit the electronic version of the Bid Guarantee at time of bid submission shall cause the bid to be rejected and deemed non-responsive. Failure to provide the original within 2 business days may deem the bidder non-responsive.
Original Bid Bond shall be submitted to:
Public Works Contract Administration
Attention: Janean Hawney, Contract Administrator
1635 Faraday Avenue
Carlsbad, California, 92008
No oral or telephonic Bids will be considered. Pursuant to Public Contract Code Sections 1600 and 1601, Bidders will submit their Bids via electronic transmission ( the online bidding portal ).
Bids received after the Bid Submission Deadline will not be accepted. Agency may reject any Bid not strictly complying with Agency’s designated methods for delivery.
26. OPENING OF BIDS.
Bids submitted on the online bidding portal will be reviewed by the Agency. Once the Bid Submission Deadline has passed, Bidders, proposers, the general public, and Agency staff are able to immediately see the results online. Agency shall consider award of the Contract to the lowest, responsive, responsible Bidder as determined by the Agency consistent with Section 32 below. In case of a discrepancy between the line item entries submitted in the online bidding portal and the Bid Form, the online bidding portal shall prevail. In the event of any discrepancies, written numbers (e.g., fifty, hundred) will govern over numerical numbers (e.g., 50, 100) on the Bid Form. Also, the sum of all lump sum line items will govern over the “Total Proposed Lump Sum Price” line item.
The Agency may reject any or all Bids or waive any irregularities or informalities in any Bids or in the Bidding process.
■■
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
The Bid and the terms of the Contract Documents constitute an irrevocable offer that shall remain valid and in full force for a period of 90 Calendar Days from the Bid Submission Deadline and such additional time as may be mutually agreed upon by the Agency and the Bidder.
27. WITHDRAWAL OF BID.
Any Bid may be withdrawn via written letter, incurring no penalty, at any time before the scheduled closing time for receipt of Bids. Requests to withdraw Bids shall be worded to not reveal the amount of the original Bid. Withdrawn Bids may be resubmitted until the Bid Submission Deadline, provided that resubmitted Bids are in conformance with these Instructions to Bidders.
Bids may be withdrawn after bid opening only by providing written notice to Agency within five (5) Working Days of the bid opening and in compliance with Public Contract Code Section 5100 et seq., or as otherwise may be allowed with the consent of the Agency.
28. BIDDERS INTERESTED IN MORE THAN ONE BID.
No Bidder shall be allowed to make, file or be interested in more than 1 Bid for the same work unless alternate Bids are specifically called for. If the Notice Inviting Bids provides for alternate Bids, a person, firm or corporation that has submitted a sub -proposal to a Bidder, or that has quoted prices of materials to a Bidder, is not disqualified from submitting a sub -proposal or quoting prices to other Bidders. No person, firm, corporation, or other entity may submit a sub - proposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.
29. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES, AND FEES.
Contractor and its Subcontractors performing work under the Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the Work will be located, unless otherwise expressly provided by the Contract Documents.
30. PERMIT AND INSPECTION FEE ALLOWANCE.
Section not used.
31. BASIS OF AWARD; BALANCED BID.
The Agency shall award the Contract to the lowest responsible Bidder submitting a responsive Bid. The lowest Bid will be determined on the basis of the total Bid price. In the event of any discrepancies, written numbers (e.g., fifty, hundred) will govern over numerical numbers (e.g., 50, 100) on the Price Proposal Form. Also, the sum of all lump sum line items will govern over the “Total Proposed Lump Sum Price” line item.
The Agency may reject any Bid which, in its opinion when compared to other Bids received or to the Agency’s internal estimates, does not accurately reflect the cost to perform the Work. The Agency may reject as non-responsive any Bid which unevenly weights or allocates costs, including ■■
00 11 10 NOTICE INVITING BIDS Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
but not limited to overhead and profit to 1 or more particular Bid items or otherwise violates Public Contract Code Section 9203.
32. AWARD PROCESS.
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the Board may award the Contract. Once notified by Agency staff, the apparent successful Bidder should begin to prepare the following documents: (1) the Labor and Materials Bond; (2) the Performance and Warranty Bond; and (3) the required insurance certificates and endorsements. Once the Agency notifies the Bidder of the award, the Bidder will have 10 Working Days from the date of this notification to execute the Contract and supply the Agency with all of the required documents and certifications or the Bidder may forfeit the Bid security and the Agency may pursue award of the Contract to the next lowest, responsive, responsible Bidder.
Once the Agency receives all properly drafted and executed documents and certifications from the Bidder, the Agency shall issue a Notice to Proceed to that Bidder.
33. EXECUTION OF CONTRACT.
As required in these Instructions to Bidders, the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The Agency may require appropriate evidence that the persons executing the Contract are duly empowered to do so. The Contract and bond forms to be executed by the successful Bidder are included within these Specifications and shall not be detached.
34. BUSINESS LICENSE
The prime Contractor and all Subcontractors are required to have and maintain a valid City of Carlsbad Business License for the duration of the Contract.
35. PARTICIPATION OF MINORITY AND WOMEN-OWNED BUSINESSES.
The Agency encourages the participation of minority and women-owned businesses.
36. USE OF RECYCLED MATERIALS
The Agency encourages Bidders, suppliers, manufacturers, fabricators and contractors to utilize recycled and recyclable materials when available, appropriate and approved by the Agency’s Engineer.
37. STATUTORY REFERENCES
All references in these Instructions to Bidders (00 21 10) to any statute, rule or regulation are to the statute, rule or regulation as amended, modified, supplemented or replaced from time to time by the corresponding legislative or regulatory body.
END OF SECTION
■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
00 41 00 BID FORM
NAME OF PROJECT: Las Palmas Roof Replacement
CONTRACT NO.: PWS24-2330FAC
NAME OF BIDDER:
AGENCY: City of Carlsbad
1635 Faraday Ave
Carlsbad, CA 92008
The undersigned declares that we have carefully examined the location of the proposed Work, and have read and examined the Contract Documents, including all Plans, Specifications, and Addenda, if any, for the above -mentioned Project. The undersigned has acknowledged receipt, understanding, and full consideration of ANY and ALL Addenda to the Contract Documents via the online bidding portal.
We propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project, as described and in strict conformity with the Drawings, and the se Specifications for TOTAL BID PRICE.
Attached is the required Bid Bond (00 43 10) or Bid Security (00 43 20) in the amount of not less than 10% of the Total Bid Price.
Attached is the completed Proposed Subcontractors form (00 43 30). Attached is the completed Bidder Information and Experience form (00 45 40) Attached is the fully executed Non-collusion Affidavit (00 45 10). Attached is the completed Iran Contracting Act Certification form (00 45 15). Attached is the completed Public Works Contractor Registration Certification form (00 45 20).
Attached is the completed Certificate of Insurance form (00 45 25). Attached is the Statement of Regarding Debarment form (00 45 30) Attached is the Disclosure of Discipline Record (00 45 35) Attached is the Optional Escrow Agreement (if applicable) (00 61 30)
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
1. BID SCHEDULE
Schedule “A” per GENERAL AND TECHNICAL SPECIFICATIONS, PROJECT MANUAL AND PLANS Item
No.
Item Desc. Unit Of
Measure
Quantity Unit
Price
1 Properly remove and dispose of existing roofing,
insulation and flashings to substrate. Inspect existing plywood decking and replace any defective plywood
with new 15/32" APA rated plywood sheeting.
Lump Sum 1
2 Cost per square foot to replace defective existing
plywood decking with 15/32" APA rated plywood
sheeting.
Sqft. 1170
2 Remove and replace primary roof drains on east side
of roof with new 1010 Smith Cast Iron roof drain
assemblies with cast iron drain domes. Drain shall
have a no hub connection and be properly secured
and sealed to existing drain line. Provide and install
cast iron covers for overflows on east side of roof.
Remove and replace drain domes on west side of roof
with new cast iron domes
Lump Sum 1
3 Remove and replace condensation clamping rings with
new cast iron rings.
Lump Sum 1
4 Lift AC #1 and condensing unit to allow for re-roofing underneath, fabricate and install wood curbs under
units with 8" clearance above roof line, install high
temp peel and stick membrane on top of new curbs,
24 gage sheet metal cap, and properly re-install and
secure units.
Lump Sum 1
5 Install 1 layer 1.8" Isocyanurate insulation over entire roof, mechanically fasten per detail drawings (Exhibit
C) with #14 fasteners and 3" plates, install tapered iso crickets behind curbs and at perimeter waterways to
provide positive slope to drain, set in low rise foam
adhesive, install 1/4" dens deck prime cover board set
in low rise foam adhesive.
Lump Sum 1
6 Install KEE Fleece back membrane system in low VOC
membrane adhesive applied at 1 gallon per square.
Mechanically secure membrane at perimeter edges
and flashing terminations with #15 fasteners and 2
3/8" membrane plates, 12" on center.
Lump Sum 1
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
7 Install KEE flashing membrane per warranty detail
requirements. Seal and secure with termination bar
of butyl tape at perimeter edge 6" on center and caulk
with polyurethane sealant. Install new 24 gage skirt
metal counterflashing at AC units and coping metal
detail, secure 12" on center. Clean and reseal coping joints with Tremseal Pro.
Lump Sum 1
8 Remove and replace designated skylight with new
curb mounted skylight to match existing and install
Cal-OSHA approved safety screen cover. Remove all
other skylights and install wood support framing 16"
on center and 15/32" plywood sheeting, completely
cover with new insulation and roof membrane.
Lump Sum 1
9 Install new KEE walkway surface leading from roof
access locations to and around all service locations on roof. Contractor shall include bid allowance of 360
linear feet in bid price.
Lft. 360
10 Replace service line supports with new Dura-Blok
recycled rubber supports set on KEE protection mat.
Lump Sum 1
11 Replace T-Top vents with new KEE Clad Cylindrical
vent covers.
Lump Sum 1
12 Saw cut reglet a minimum of 10" above finished roof
surface and install new 2-piece counterflashing at
perimeter parapet wall. Saw cut of reglet shall be
done during approved off hours to minimize
disruption to ongoing operations. Waterproof inside
of parapet wall above counterflashing with
elastomeric wall coating system.
Lump Sum 1
13 Provide the City of Carlsbad with a 30-year QA NDL
system Warranty. Lump Sum 1
The costs for any Work shown or required in the Contract Documents, but not specifically identified as a line item are to be included in the related line items and no additional compensation shall be due to Contractor for the performance of the Work.
The estimated quantities for Unit Price items are for purposes of comparing Bids only and the Agency makes no representation that the actual quantities of Work performed will not vary from
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
the estimates. Final payment shall be determined by the Engineer from measured quantities of Work performed based upon the Unit Price.
2. TOTAL BID PRICE
The undersigned agrees that this Bid Form constitutes a firm offer to the Agency which cannot be withdrawn for ninety (90) Calendar Days from and after the Bid opening, or until a Contract for the Work is fully executed by the Agency and the lowest responsible Bidder, whichever is later.
The Undersigned has carefully checked all the above figures and understands that the Agency will not be responsible for any error or omission on the part of the Undersigned in preparing this Bid.
3. RECITALS
The successful Bidder agrees to sign the Contract and furnish the necessary bonds and certificates of insurance within 10 Working Days after the Agency issues the Notice of Award to the successful Bidder.
The Undersigned agrees that in case of failure to execute the required Contract with necessary bonds and insurance policies within this time period, the Agency may pursue award ing the Contract to the next lowest responsible Bidder and the Bid Security of the lowest Bidder may be forfeited.
Upon receipt of the signed Contract and other required documents, the Agency will proceed to execute the Contract and issue a purchase order and the Notice to Proceed. The time of completion shall commence on the date of the Notice to Proceed, unless otherwise specified.
The undersigned agrees to begin the Work within 10 Working Days of the date of the Notice to Proceed, unless otherwise specified.
The Undersigned is aware of the provisions of Labor Code Section 3700, which requires every employer to be insured against liability for workers' compensation or to undertake self-insurance The TOTAL BID PRICE on Bid Schedule total of Unit Prices:
Total Bid Price in Numbers: __________________
Total Bid Price in Written Form:
In case of discrepancy between the written price, the numerical price, or the price as submitted via the online bidding portal, the online bidding portal price shall prevail.
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
in accordance with the provisions of that code, and agrees to comply with such provisions before commencing the performance of the Work of this Contract and continue to comply until the Contract is complete.
The Undersigned is aware of the provisions of Labor Code Section 1770 et seq. relative to the general prevailing rate of wages for each craft or type of worker needed to execute the Contract and agrees to comply with its provisions.
The Undersigned Bidder declares, under penalty of perjury, that the undersigned is licensed to do business or act in the capacity of a contractor within the State of California and that this statement is true and correct and has the legal effect of an affidavit. The following are the Bidder’s applicable license number(s), with their expiration date(s) and class of license(s):
______________________________________________________________________________ ______________________________________________________________________________ ______________________________________________________________________________
If the Bidder is a joint venture, each member of the joint venture must include the required licensing information.
A Bid submitted to the Agency by a Contractor who is not licensed as a Contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the Agency. In all contracts where federal funds are involved, no Bid submitted shall be invalidated by the failure of the Bidder to be licensed in accordance with California law. However, at the time the Contract is awarded, the Contractor shall be properly licensed.
The Undersigned Bidder represents as follows:
1. That no elected or appointed official , officer , agent, or employee of the Agency is personally interested, directly or indirectly, in this Contract, or the compensation to be paid under it; that no representation, oral or in writing, of the Agency, its officers, agents, or employees has induced Bidder to enter into this Contract, excepting only those contained in this form of Contract and the papers made a part of this Contract by its terms; and
2. That this Bid is made without connection with any person, firm, or corporation making a Bid for the same Work, and is in all respects fair and without collusion or fraud.
Accompanying this Bid is _________________________________ (Cash, Certified Check, Bidder’s Bond or Cashier's Check) for 10% of the amount Bid, payable to Agency as Bid Security and which is given as a guarantee that the undersigned will enter into a Contract and provide the necessary bonds and certificates of insurance if awarded the Contract.
Organized under the laws of the State of ________________________.
■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
an individual
a partnership
a corporation
{signatures on following page}
■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:
I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.
1 Name under which
business is
conducted
______________________________________________________
2 Signature (given and
surname) of
proprietor
Printed/Typed Name
______________________________________________________
______________________________________________________
3 Place of Business
(Full Address: street,
number, city, state,
zip)
______________________________________________________
______________________________________________________
______________________________________________________
4 Telephone Number ______________________________________________________
5 Email ______________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED
■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
IF A PARTNERSHIP, SIGN HERE:
I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.
1 Name under which
business is
conducted
______________________________________________________
2 Signature (given and
surname and role)
(Note: Signature
must be made by a
general partner)
Printed/Typed Name
______________________________________________________
______________________________________________________
3 Place of Business
(Full Address: street,
number, city, state,
zip)
______________________________________________________
______________________________________________________
______________________________________________________
4 Telephone Number ______________________________________________________
5 Email ______________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED ■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
IF A CORPORATION, SIGN HERE:
I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.
1 Name under which
business is
conducted
______________________________________________________
2 Signature (given and
surname and Title)
(Note: Signature
must be made by a
someone who can
bind the
corporation)
Printed/Typed Name
______________________________________________________
______________________________________________________
3 Place of Business
(Full Address: street,
number, city, state,
zip)
______________________________________________________
______________________________________________________
______________________________________________________
4 Telephone Number ______________________________________________________
5 Email ______________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED
■■
00 41 00 BID FORM Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
List below names of president, vice president, CFO, secretary and assistant secretary, if a corporation; if a partnership, list names of all general partners, and managing partners:
Approved as to form this ___________________day of _____________________ 20_______.
______________________________________________
Attorney for Contractor
END OF SECTION
00 43 10 BID BOND Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
00 43 10 BID BOND FORM
(Note: This form is not required when other form of Bidder’s Security, e.g. cash, certified check or cashier’s check, accompanies Bid. In that case, use form 00 43 20 Bid Security)
NAME OF PROJECT: Las Palmas Roof Replacement
CONTRACT NO.: PWS24-2330FAC
NAME OF BIDDER:
The makers of this bond are, as Principal,
and , as Surety and are held and
firmly bound unto the City of Carlsbad (“Agency”) in the penal sum of 10% OF THE TOTAL BID PRICE of the Principal submitted to the Agency for the Work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying Bid dated .
If the Principal does not withdraw its Bid within the time specified in the Contract Documents; and if the Principal provides all required documents to the Agency and is awarded the Contract; then this obligation shall be null and void. Otherwise, this bond will remain in full force and effect.
Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents shall affect its obligation under this bond, and Surety waives notice of any such changes.
In the event a lawsuit is brought upon this bond by the Agency and judgment is recovered, the Surety shall pay all litigation expenses incurred by the Agency in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and expenses.
///
///
///
///
///
00 43 10 BID BOND Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
IN WITNESS WHEREOF, the above -bound parties have executed this instrument under their several seals this_____________ day of _____________________________, 20______, the name and corporate seal of each corporation.
PRINCIPAL:
___________________________________
(Name of Principal)
By:
___________________________________
(sign here)
___________________________________
(Print name here)
___________________________________
(Title and Organization of Signatory)
Executed by SURETY
this ______day of ________________, 20____
SURETY:
_____________________________________
(name of Surety)
_____________________________________
(address of Surety)
_____________________________________
(telephone number of Surety)
By:
_____________________________________
(signature of Attorney-in-Fact)
_____________________________________
(printed name of Attorney-in-Fact)
Required Attachments:
Corporate resolution showing current power of attorney. Proper execution by PRINCIPAL.
Proper notarial acknowledgment of execution by SURETY. President or vice -president and CFO, secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.
END OF SECTION
■■
00 43 20 BID SECURITY Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
00 43 20 BID SECURITY
(Note: This form is required when cash, certified check or cashier’s check, accompanies Bid. If Bid Bond is being provided, use form 00 43 10 Bid Bond)
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
Accompanying this proposal is a Certified / Cashier’s check payable to the order of the City of Carlsbad (“Agency”), in the sum of
dollars ($___________________), this amount being 10% of the total amount of the Bid. The proceeds of this check shall become the property of the Agency, provided this proposal shall be accepted by the Agency through action of its legally constituted cont racting authorities and the Undersigned shall fail to execute a Contract and furnish the required Performance, Warranty and Payment Bonds and proof of insurance coverage within the stipulated time; otherwise, the check shall be returned to the Undersigned. The proceeds of this check shall also become the property of the Agency if the Undersigned shall withdraw his or he r Bid within the period of 15 Calendar Days after the date set for the opening of the Bid, unless otherwise required by law, and notwithstanding the award of the Contract to another Bidder.
_______________________________________
BIDDER
Required Attachments:
Certified Check or Cashier’s Check
END OF SECTION
00 40 30 PROPOSED SUBCONTRACTORS FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 43 30 PROPOSED SUBCONTRACTORS FORM
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
In compliance with the Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.), Bidder shall set forth below: (a) the name and the location of the place of business, (b) the California contractor license number, (c) the DIR public works contractor registration number, and (d) the portion of the Work which will be done by each Subco ntractor who will perform work or labor or render service to the Bidder in or about the construction of the Work or improvement to be perform ed under this Contract in an amount in excess of one - half of one percent (0.5%) of the Bidder’s Total Bid Price. Notwithstanding the foregoing, if the Work involves the construction of streets and highways, then the Bidder shall list each Subcontractor who will perform work or labor or render service to the Bidder in or about the Work in an amount in excess of one-half of one percent (0.5%) of the Bidder’s Total Bid Price or $10,000, whichever is greater. No additional time shall be granted to provide the b elow requested information.
If a Bidder fails to specify a Subcontractor or if a Contractor specifies more than one Subcontractor for the same portion of Work, then the Bidder shall be deemed to have agreed that it is fully qualified to perform that portion of Work and that it shall perform that portion itself. No changes in the Subcontractor’s listed Work will be made without the prior approval of the Agency.
Attach additional pages as required.
(Signature of Bidder)
00 40 30 PROPOSED SUBCONTRACTORS FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Name of
Subcontractor
Location of
Business
CSLB
Contractor
License
No./ Exp
Date
DIR
Registration
Number /
Exp. Date
Type of Work
to be done by
Subcontractor
% of
Work
Amount of
Work by
Subcontractor
in Dollars*
Pursuant to Public Contract Code Section 4104, subdivision (a)(3)(A), receipt of the information preceded by an asterisk (*) may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the “Notice Inviting Bids.”
END OF SECTION
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM
NAME OF PROJECT: Las Palmas Roof Replacement
CONTRACT NO.: <insert contract number>
NAME OF BIDDER:
1. INFORMATION ABOUT BIDDER
(Indicate not applicable (“N/A”) where appropriate.)
NOTE: Where Bidder is a joint venture, pages shall be duplicated, and information provided for all parties to the joint venture.
1. Type, if Entity:
2. Bidder Address:
a. Facsimile Number
b. Telephone Number
c. Email Address
3. How many years has Bidder’s organization been in business as a contractor?
4. How many years has Bidder’s organization been in business under its present name? a. Under what other or former names has Bidder’s organization operated?
5. If Bidder’s organization is a corporation, answer the following:
a. Date of Incorporation:
b. State of Incorporation:
c. President’s Name:
d. Vice-President’s Name(s):
e. Secretary’s Name:
f. Treasurer’s Name:
g. CFO’s Name:
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
6. If an individual or a partnership, answer the following:
a. Date of Organization:
b. Name and address of all partners (state whether general or limited partnership):
7. If other than a corporation or partnership, describe organization and name principals:
8. List other states in which Bidder’s organization is legally qualified to do business.
9. What type of work does the Bidder normally perform with its own forces?
10. Has Bidder ever failed to complete any work awarded to it? If so, note when, where, and why:
11. Within the last 5 years, has any officer or partner of Bidder’s organization ever been an officer or partner of another organization when it failed to complete a contract? If so, attach a separate sheet of explanation:
12. List Trade References:
13. List Bank References (Bank and Branch Address):
14. Name of Bonding Company and Name and Address of Agent:
[REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK]
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2. LIST OF CURRENT PROJECTS (BACKLOG)
[**Duplicate or attach additional pages if needed for listing current projects.**] Project Name
Sub or Prime?
Description of Bidder’s Work Client
Name
Completion
Date
Cost of
Bidder’s Work
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
LIST OF COMPLETED PROJECTS (LAST 3 YEARS)
[**Duplicate or attach additional pages if needed for listing completed projects. **]
Please include only those projects which are similar enough to demonstrate Bidder’s ability to perform the required Work.
Project Name
Sub or Prime?
Description of Bidder’s Work Client
Name
Completion
Date
Cost of
Bidder’s Work
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
EXPERIENCE AND TECHNICAL QUALIFICATIONS QUESTIONNAIRE
Personnel:
The Bidder shall identify the key personnel to be assigned to this Project in a management, construction supervision or engineering capacity. Add additional pages to identify ALL key personnel. Bidder may submit a 2-page resume of each key personnel mentioned above.
Bidder agrees that personnel named in this Bid will remain on this Project until completion of all relevant Work, unless substituted by personnel of equivalent experience and qualifications approved in advance by the Agency.
Job Title
Name
% time on this
Project
Specialized
Education
Years of
construction
experience
relevant to the
Project
Summarize the
experience
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Additional Bidder’s Statements:
If the Bidder feels that there is additional information which has not been included in the questionnaire above, and which would contribute to the qualification review, it may add that information in a statement here or on an attached sheet, appropriately marked:
00 43 30 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3. VERIFICATION AND EXECUTION
These Bid Forms shall be executed only by a duly authorized official of the Bidder:
I declare under penalty of perjury under the laws of the State of California that the foregoing information is true and correct:
Name of Bidder:
Signature ________________________________________________________________
Name ______________________________________________________________________
Title ______________________________________________________________________
Date ______________________________________________________________________
END OF SECTION
00 45 10 NON-COLLUSION AFFIDAVIT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 10 NON-COLLUSION AFFIDAVIT
NONCOLLUSION DECLARATION TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
Consistent with Public Contract Code Section 7106, t he undersigned declares:
I am the of , the
party making the foregoing Bid.
The Bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The Bid is genuine and not collusive or sham.
The Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham bid. The Bidder has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or anyone else to put in a sham bid, or to refrain from bidding. The Bidder has not in any manner, directly or indirectly, sought by agreement, communication, or co nference with anyone to fix the Bid Price of the Bidder or any other Bidder, or to fix any overhead, profit, or cost element of the Bid Price, or of that of any other Bidder. All statements contained in the Bid are true. The Bidder has not, directly or indirectly, submitted his or her Bid Price or any breakdown of it, or the contents of it, or divulged information or data relative to it, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent of these, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a Bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, represents that he or she has full power to execute, and does execute, this declaration on behalf of the Bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and c orrect a nd that this d eclaration is e xecuted ________________ 20 ____ at _______________ [city], _____ [state].
Signature
Name _________________________________
Title
END OF SECTION
00 45 15 IRAN CONTRACTING ACT CERTIFICATION Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 15 IRAN CONTRACTING ACT CERTIFICATION
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
As required by Public Contract Code Section 2204, the Contractor certifies subject to penalty of perjury that the option checked below relating to the Contractor’s status in regard to the Iran Contracting Act of 2010 (Public Contract Code Section 2200 et seq.) is true and correct:
The Contractor is not:
1) identified on the current list of persons and entities engaged in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or
2) a financial instruction that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.
The Agency has exempted the Contractor from the requirements of the Iran Contracting Act of 2010 after making a public finding that, absent the exemption, the Agency will be unable to obtain the goods and/or services to be provided pursuant to the Contract.
The amount of the Contract payable to the Contractor for the Project does not exceed $1,000,000.
Signature: Date:
Name: Title:
Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for 3 years.
END OF SECTION
00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
Pursuant to Labor Code Sections 1725.5 and 1771.1, all Contractors and Subcontractors that wish to Bid on, be listed in a Bid proposal, or enter into a Contract to perform public work must be registered with the Department of Industrial Relations. See Public Works (ca.gov) for additional information.
No Bid will be accepted, nor any Contract entered into without proof of the Contractor’s and Subcontractors’ current registration with the Department of Industrial Relations to perform public work.
Bidder certifies that it is aware of the registration requirements set forth in Labor Code Sections 1725.5 and 1771.1 and is currently registered as a Contractor with the Department of Industrial Relations.
Name of Bidder:
DIR Registration Number:
DIR Registration Expiration:
Bidder further certifies:
1. Bidder shall maintain a current DIR registration for the duration of the Project.
2. Bidder shall include the requirements of Labor Code Sections 1725.5 and 1771.1 in its Contract with Subcontractors and ensure that all Subcontractors are registered at the time of Bid opening and maintain registration status for the duration of the Project.
3. Failure to submit this form or comply with any of the above requirements may result in a finding that the Bid is non -responsive.
Signature: Date:
Name: Title:
END OF SECTION
00 45 25 CERTIFICATE OF INSURANCE Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 25 CERTIFICATE OF INSURANCE
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
Bidder must attach either of the following to this page.
Certificates of insurance showing conformance with the requirements for each of:
a. Comprehensive General Liability
b. Automobile Liability
c. Workers Compensation
d. Employer’s Liability
Statement with an insurance carrier’s notarized signature stating that the carrier can, and upon payment of fees and/or premiums by the Bidder, will issue to the Bidder the required policies of insurance for Comprehensive General Liability, Automobile Liability, Workers Compensation and Employer’s Liability in conformance and the required Certificates of insurance to the Agency.
END OF SECTION
00 45 30 STATEMENT REGARDING DEBARMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 25 STATEMENT REGARDING DEBARMENT
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
1. Have you or any of your Subcontractors ever been debarred as an irresponsible Bidder by another public agency in the State of California?
YES
NO
2. If yes, what was/were the name(s) of the public agency(ies) and what was/were the period(s) of debarment(s)? Attach additional copies of this page to accommodate more than 2 debarments.
__________________________________
party debarred
__________________________________
public agency
__________________________________
period of debarment
___________________________________
party debarred
___________________________________
public agency
___________________________________
period of debarment
BY CONTRACTOR:
By: __________________________________
(sign here)
___________________________________
(print name/title)
Page _____ of _____ pages of this Statement Regarding Debarment form
END OF SECTION
00 45 35 DISCLOSURE OF DISCIPLINE RECORD Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 45 35 DISCLOSURE OF DISCIPLINE RECORD
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a latent act or omission is filed within 4 years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation. Any questions concerning a Contractor may be referred to the Re gistrar, Contractor s’ State License Board, P.O. Box 26000, Sacramento, California 95826.
1. Have you ever had your contractor’s license suspended or revoked by the California Contractors’ State license Board 2 or more times within an 8-year period? YES
NO
2. Has the suspension or revocation of your contractor’s license ever been stayed? YES
NO
N/A
3. Have any Subcontractors that you propose to perform any portion of the Work ever had their contractor’s license suspended or revoked by the California Contractors’ State Llicense Board 2 or more times within an 8-year period?
YES
NO
4. Has the suspension or revocation of the license of any Subcontractors that you propose to perform any portion of the Work ever been stayed?
YES
NO
N/A
00 45 35 DISCLOSURE OF DISCIPLINE RECORD Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
5. If the answer to either of 1 or 3 above is “yes,” fully identify, in each and every case, the party disciplined, the date of and violation that the disciplinary action pertains to, the nature of the violation and disciplinary action taken.
(If needed attach additional sheets to provide full disclosure.)
6. If the answer to either of 2 or 4 above is “yes,” fully identify, in each and every case, the party whose discipline was stayed, the date of and the violation that the disciplinary action pertains to, the nature of the violation and the condition (if any) upon which the disciplinary action was stayed.
(If needed attach additional sheets to provide full disclosure.)
BY CONTRACTOR:
By: __________________________________
(sign here)
__________________________________
(print name and title)
END OF SECTION
00 52 00 CONTRACT Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
00 52 00 CONTRACT
This Project No. 4752 (“Contract”) is made and entered into this ____________ day of ________________________________, 20___, by and between the City of Carlsbad (“Agency”) and ____________________________________ (“Contractor”), whose principal place of business is _______________________________________________________.
The parties agree:
1. SCOPE OF WORK.
The Contractor shall perform all Work within the time stipulated in the Contract, and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all the Work required in strict compliance with the Contract Documents for the following Project:
NAME OF PROJECT: Las Palmas Roof Replacement
The Contractor and its surety shall be liable to the Agency for any damages arising as a result of the Contractor’s failure to comply with the obligation described in this Section 1.
2. TIME OF COMPLETION.
Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the Agency’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within ninety (90) working days from the commencement date stated in the Notice to Proceed. Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
3. CONTRACT PRICE.
The Agency shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions made in accordance with the Contract Documents, and including all applicable taxes and costs, the sum of _______________ ____________________ Dollars ($ _____________________________). Payment shall be made as set forth in the General Conditions.
The Engineer will close the estimate of work completed for progress payments on the last working day of each month. The Agency shall withhold retention as required by Public Contract Code Section 9203.
4. LIQUIDATED DAMAGES.
In accordance with Government Code Section 53069.85, it is agreed that the Contractor will pay the Agency the sum set forth in Section 00 73 00 Supplemental General Provisions for each and every Calendar Day of delay beyond the time of completion prescribed in this Contract as Liquidated Damages and not as a penalty or forfeiture. If this sum is not paid, the Contractor agrees the Agency may deduct that amount from any money due or that may become due the ■■
00 52 00 CONTRACT Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
Contractor under the Contract. This Section does not exclude recovery of other damages specified in the Contract Documents.
5. CONTRACT DOCUMENTS.
The “Contract Documents” include the following:
● 00 11 10 Notice Inviting Bids
● 00 21 10 Instructions to Bidders
● 00 41 00 Bid Form
● 00 42 10 Bid Bond or 00 43 20 Bid Security
● 00 43 30 Proposed Subcontractors
● 00 43 40 Bidder Information and Experience
● 00 45 10 Non-Collusion Affidavit
● 00 45 15 Iran Contracting Act Certification
● 00 45 20 Public Works Contractor Registration Certification ● 00 45 30 Statement of Regarding Debarment
● 00 45 35 Disclosure of Discipline Record
● 00 52 10 Contract
● 00 61 10 Labor and Materials Bond
● 00 61 20 Faithful Performance and Warranty Bond
● 00 61 30 Optional Escrow Agreement (if applicable)
● 00 73 00 Supplemental General Provisions
● Technical Specifications for the Project
● All Addenda
● Plans and Drawings
● Permits
● 00 74 00 Supplemental Technical Provisions
● “Standard Specifications and Drawings,” as last revised ● Standard Specifications for Public Works Construction “Greenbook ,” latest edition and including all errata
o Part 1 General Provisions
o Part 2 to Part 8 (Construction Materials, Construction Methods, Existing Improvements, Pipeline System Rehabilitation, Temporary Traffic Control, Street Lighting and Traffic Signal Systems, Landscaping and Irrigation) ● Standard Plans for Public Works Construction, latest edition and including all errata ● Applicable Local Agency Standards and Specifications, as last revised ● Approved and fully executed change orders
■■
00 52 00 CONTRACT Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
● Any other documents contained in or incorporated by reference into the Contract Documents
The Contractor shall complete the Work in strict accordance with the Contract Documents. The requirements of the various sections or documents comprising the Contract Documents are intended to be complementary. Work required by 1 of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.
6. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE.
Every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the Labor Code and Public Contract Code which are applicable to the Work.
7. INDEMNIFICATION.
Contractor shall provide indemnification and defense as set forth in the 00 73 00 Agency Supplemental General Provisions.
8. PREVAILING WAGES.
Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates may be obtained online at http://www.dir.ca.gov and which must be posted at the job site.
{signatures on following page}
00 52 00 CONTRACT Date Printed: November 8, 2023
Document Version: 1.0 Current Update: October 2022
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED
(CORPORATE SEAL)
CONTRACTOR City of Carlsbad
By: By:
(sign here)
Keith Blackburn, Mayor
(print name/title)
ATTEST:
By:
(sign here) for Sherry Freisinger, City Clerk
(print name/title)
If required by the Agency, proper notarial acknowledgment of execution by contractor must be attached. If a corporation, the Contract must be signed by 1 corporate officer from each of the following 2 groups.
Group A Group B
Chairman, Secretary,
President, or Assistant Secretary,
Vice-President CFO or Assistant Treasurer
Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation.
APPROVED AS TO FORM:
CINDIE K. McMAHON, City Attorney
BY: _____________________________
City Attorney
END OF SECTION
00 61 10 LABOR AND MATERIALS BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 61 10 LABOR AND MATERIALS BOND
KNOW ALL PERSONS BY THESE PRESENTS THAT:
WHEREAS, the City of Carlsbad ( “Agency”) has awarded to (“Principal,”) a Contract for the Work described as follows: Contract No PWS24-2330FAC Project No. 4752, Palmas Roof Replacement (the “Project”) in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated by this reference; and
WHEREAS, Principal is required to furnish a bond in connection with the Contract providing that if Principal or any of its Subcontractors fail to pay (1) for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the Work contracted to be done, (2) for any Work or labor of any kind performed under the Contract, (3) for amounts due under the Unemployment Insurance Code for any Work or labor of any kind performed under the Contract, or (4) for any amo unts required to be deducted, withheld, and paid over to the Employment Development Department under Unemployment Insurance Code Section 13020 or to the Franchise Tax Board under Revenue and Taxation Code Section 18663 from the wages of employees of Principal and its Subcontractors with respect to the Work or labor, the Surety on this bond will pay for the same to the extent set forth below.
NOW THEREFORE, we, Principal and , as Surety, are held and firmly bound unto the Agency in the penal sum of
Dollars ($___________), for the payment of which sum being an amount equal to 100% of the total amount payable under the terms of the Contract by the Agency, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if Principal, or its Subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code Section 9100 ; fail to pay for any materials, provisions , provender, equipment, or other supplies, used in, upon, for or about the performance of the Work contracted to be done; fail to pay for any Work or labor of any kind performed under the Contract; fail to pay amounts due under the Unemployment Insurance Code for any Work or labor of any kind performed under the Contract; or fail to pay for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of Principal or its Subcontractors pursuant to Unemployment Insurance Code Section 13020 or Revenue and Taxation Code Section 18663, with respect to the Work or labor, then the Surety will pay for the same, in an amount not exceeding the penal sum specified above, and also, in case suit is brought upon this bond, all litigation expenses incurred by the Agency in the suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses to be fixed by the court consistent with Civil Code Section 9554.
00 61 10 LABOR AND MATERIALS BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond.
The Surety stipulates and agrees that this bond shall not be exonerated or released from the obligation of this bond by:
1. Any change, extension of time for performance, addition, alteration or modification in, to, or of any Contract, Plans, Specifications, or agreement pertaining or relating to any scheme or Work of improvement described above, or the furnishing of labor, materials, or equipment pertaining or relating to any scheme or Work of improvement described above.
2. Any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or Work of improvement described above.
3. Any rescission or attempted rescission or attempted rescission of the Contract, agreement or bond.
4. Any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such Contract or agreement or under the bond.
5. Any fraud practiced by any person other than the claimant seeking to recover on the bond.
The Surety also stipulates and agrees that this bond shall be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit this bond has been given by reason of any breach of contract between the Agency and Principal or on the part of any obligee named in this bond. Finally, the Surety waives notice of any such change, extension of time, addition, alteration or modification mentioned in this bond, including but not limited to the provisions of Civil Code Sections 2819 and 2845.
If Principal is an individual, it is agreed that the death of any such Principal shall not exonerate the Surety from its obligations under this bond.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
■■
00 61 10 LABOR AND MATERIALS BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Executed by PRINCIPAL this _________
day of _______________________, 20____.
PRINCIPAL:
____________________________________
(name of Contractor)
By:_________________________________
(sign here)
____________________________________
(print name here)
____________________________________
(title and organization of signatory)
Executed by SURETY this ____________ day
of _______________________, 20____.
SURETY:
____________________________________
(name of Surety)
____________________________________
(address of Surety)
____________________________________
(telephone number of Surety)
By:
____________________________________
(signature of Attorney-in-Fact)
____________________________________
(printed name of Attorney-in-Fact)
(attach corporate resolution showing current
power of attorney)
(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)
(President or vice -president and secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
CINDIE K. McMAHON, City Attorney
BY: _____________________________
Deputy City Attorney
END OF SECTION
■■
00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND
KNOW ALL PERSONS BY THESE PRESENTS THAT:
WHEREAS, the City of Carlsbad ( “Agency”) has awarded to ________________ (“Principal,”) a Contract for the Work described as follows: Contract No PWS24-2330FAC Project No. 4752, Las Palmas Roof Replacement (the “Project”) in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated by this reference; and
WHEREAS, the Work to be performed by the Principal is more particularly set forth in the Contract Documents for the Project dated ____________, (“Contract Documents”), the terms and conditions of which are incorporated by reference; and
WHEREAS, the Principal is required by the Contract Documents to perform the terms of them and to furnish a bond for the faithful performance and warranty of the Contract Documents.
NOW THEREFORE, we, Principal, and
,as Surety, are held and firmly bound unto the Agency in the penal sum of dollars ($ ____________),
which is equal to 100% of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if Principal, its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration of the Contract Documents made as provided in the Contract Documents, on its part, to be kept and performed at the time and in the manner specified in the Contract Documents , and in all respects according to their true inten t and meaning; and shall indemnify and save harmless the Agency, its Board, members of the Board, officers, directors, managers, employees, agents, and authorized volunteers, as stipulated in the Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.
As a part of the obligation secured by this bond and in addition to the face amount specified in this bond, there shall be included costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by Agency in enforcing such obligation, all to be taxed as costs and included in any judgment rendered.
As a condition precedent to the satisfactory completion of the Work unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of 1 year after the acceptance of the Work by the Agency. During this 1-year period, if Contractor fails to make full, complete, and satisfactory repair and replacements and totally protect the Agency from loss or damage resulting from or caused by defective materials or faulty workmanship in connection
00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
with Contractor’s Work on the Project, the obligations of Surety under this bond shall continue so long as any obligation of Principal remains to the Agency. Nothing in this bond shall limit the Agency’s rights or the Principal’s or Surety’s obligations un der the Contract, law or equity, including, but not limited to, Code of Civil Procedure Section 337.15.
Whenever Principal shall be, and is declared by the Agency to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the Agency’s option:
i. Take over and complete the Project in accordance with all terms and conditions in the Contract Documents;
ii. Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a contract between such bidder, the Surety and the Agency, and make available as Work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the Contract Price, including other costs and damages for which Surety may be liable. The term “balance of the Contract Price” as used in this paragraph shall mean the total amount payable to Principal by the Agency under the Contract and any modification to the Contract, less any amount previously paid by the Agency to the Principal and any other set offs pursuant to the Contract Documents.
Or
iii. Permit the Agency to complete the Project in any manner consistent with Applicable Law and make available as Work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the Contract Price, including other costs and damages for which Surety may be liable. The term “balance of the Contract Price” as used in this paragraph shall mean the total amount payable to Principal by the Agency under the Contract and any modification to the Contract, less any amount previously paid by the Agency to the Principal and any other set offs pursuant to the Contract Documents.
Surety expressly agrees that the Agency may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Principal.
Surety shall not utilize Principal in completing the Project, nor shall Surety accept a bid from Principal for completion of the Project, if the Agency, when declaring the Principal in default, notifies Surety of the Agency’s objection to Principal’s further participation in the completion of the Project.
The Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed under the Contract Documents shall in any way affect Surety’s obligations on this bond, and Surety waives notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project.
■■
00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
If Principal is an individual, it is agreed that the death of any such Principal shall not exonerate the Surety from its obligations under this bond.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
■■
00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Executed by PRINCIPAL this _________ day of
________________________, 20___.
PRINCIPAL:
____________________________________
(name of Contractor)
By:_________________________________
(sign here)
____________________________________
(print name here)
____________________________________
(title and organization of signatory)
Executed by SURETY this ____________ day
of ________________________, 20___.
SURETY:
____________________________________
(name of Surety)
____________________________________
(address of Surety)
____________________________________
(telephone number of Surety)
By: _________________________________
(signature of Attorney-in-Fact)
____________________________________
(printed name of Attorney-in-Fact)
(attach corporate resolution showing current
power of attorney)
(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)
(President or vice-president and secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.)
APPROVED AS TO FORM:
CINDIE K. McMAHON, City Attorney
BY: _____________________________
Deputy City Attorney
END OF SECTION
■■
00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 61 30 OPTIONAL ESCROW AGREEMENT
NAME OF PROJECT: Las Palmas Roof Replacement
NAME OF BIDDER:
This Escrow Agreement is made and entered into by and between the City of Carlsbad, Carlsbad, California, 92008 ("Agency"), whose address is
("Contractor") and
whose address is
("Escrow Agent").
Agency, Contractor and Escrow Agent agree as follows:
1. Pursuant Public Contract Code Section 22300, Contractor has the option to deposit securities with Escrow Agent as a substitute for retention earnings required to be withheld by Agency pursuant to the construction contract entered into between Agency and Contractor for the Las Palmas Roof Replacement in the amount of ___________ dated __________ ("Contract").
Alternatively, on written request of Contractor, Agency shall make payments of the retention earnings directly to Escrow Agent. When the Contractor deposits the securities as a substitute for Co ntract earnings, Escrow Agent shall notify Agency within 10 Calendar D ays of the deposit. The market value of the securities at the time of the substitution shall be at least equal to the cash amount then required to be withheld as retention under the terms of the Contract. Securities shall be held in Agency’s name and shall designate Contractor as the beneficial owner.
2. Agency shall make progress payments to Contractor for those funds which otherwise would be withheld from progress payments pursuant to the Contract provisions, provided that Escrow Agent holds securities in the form and amount specified above.
3. When Agency makes payment of retentions earned directly to Escrow Agent, Escrow Agent shall hold them for the benefit of Contractor until the time that the escrow created under this Escrow Agreement is terminated. The Contractor may direct the investment of the payments into securities. All terms and conditions of this Escrow Agreement and the rights and responsibilities of the parties shall be equally applicable and binding when Agency pays Escrow Agent directly.
4. Contractor shall be responsible for paying all fees for the expenses incurred by Escrow Agent in administering the Escrow Account and all expenses of Agency. These expenses and payment terms shall be determined by Agency, Contractor, and Escrow Agent.
5. The interest earned on the securities or the money market accounts held in escrow and all interest earned on that interest shall be for the sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to Agency.
6. Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow Agent accompanied by written authorization from Agency to Escrow Agent that Agency consents to the withdrawal of the amount sought to be withdrawn by Contractor.
00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
7. Agency shall have a right to draw upon the securities in the event of default by the Contractor.
Upon 7 Calendar Days' written notice to Escrow Agent from Agency of a default, Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as instructed by Agency.
8. Upon receipt of written notification from the Agency certifying that the Work required by the Contract is final and complete and that Contractor has complied with all requirements and procedures applicable to the Contract, Escrow Agent shall release to Contractor all securities and interest on deposit less escrow fees and charges of Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges.
9. Escrow Agent shall rely on the written notifications from Agency and Contractor pursuant to Sections (5) to (8), inclusive, of this Escrow Agreement and Agency and Contractor shall hold Escrow Agent harmless from Escrow Agent's release, conversion and disbursement of the securities and interest as set forth above.
10. The names of the persons who are authorized to give written notices or to receive written notice on behalf of Agency and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:
For Agency
(Finance
Director)
Title _________________________________________________________
Name
_____________________________________________________________
Signature
_____________________________________________________________
Address
_____________________________________________________________
For Contractor
Title
_____________________________________________________________
Name
_____________________________________________________________
Signature
_____________________________________________________________
■■
00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Address
_____________________________________________________________
For Escrow
Agent
Title
_____________________________________________________________
Name
_____________________________________________________________
Signature
_____________________________________________________________
Address
_____________________________________________________________
At the time the Escrow Account is opened, Agency and Contractor shall deliver to the Escrow Agent a fully executed counterpart of this Escrow Agreement.
IN WITNESS WHEREOF, the parties have executed this Escrow Agreement by their proper officers on the date first set forth above.
For Agency Title
______________________________________________________________
Name
______________________________________________________________
Signature
______________________________________________________________
Address
______________________________________________________________
For Contractor
Title
______________________________________________________________
■■
00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Name
______________________________________________________________
Signature
______________________________________________________________
Address
______________________________________________________________
For Escrow
Agent
Title
______________________________________________________________
Name
______________________________________________________________
Signature
______________________________________________________________
Address
______________________________________________________________
APPROVED AS TO FORM:
CINDIE K. McMAHON, City Attorney
BY: _____________________________
City Attorney
END OF SECTION
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS
INTRODUCTION
The specifications contained in this 00 73 00 Agency Supplemental General Provisions take precedence over the specification language contained in the Standard Specifications for Public Works Construction, “The Greenbook,” latest edition and all errata. This specification addresses the unique conditions in Carlsbad that are not addressed in The Greenbook. Therefore, if there is a conflict, these specifications shall control.
The Greenbook may be purchased at Bidder ’s/Contractor’s local technical bookstore or directly from the publisher. These Supplemental General Provisions are available only for download from the online bidding portal with Contract Documents. The Agency does not provide hard copies.
When used in the Contract Documents, statements, or command phrases (active voice and imperative mood) refer to and are directed at the “Bidder” or “Contractor” as applicable. The specifications are written to the “Bidder” before award and the “Contractor” after award. Before award, interpret sentences written in the imperative mood as starting with “The Bidder shall .” Interpret the term “you” as “the Bidder” and interpret the term “your” as “the Bidder’s .” After award, interpret sentences written in the imperative mood starting with “The Contractor shall. ” Interpret the term “you” as “the Contractor” and interpret the term “your” as “the Contractor’s.” PART 1 GENERAL PROVISIONS
SECTION 1 – GENERAL, TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND
SYMBOLS
1-1 GENERAL
ADD the following:
1. The word “provide” shall mean “furnish and install,” unless otherwise stated.
2. In reference to Drawings, where words “shown ,” “indicated,” “detailed ,” “noted ,” “scheduled,” or words of similar import are used, it shall be understood that reference is made to the Plans accompanying these provisions, unless stated otherwise.
3. Where the words “equal ,” “approved equal ,” “equivalent,” and words of similar import are used, it shall be understood such words are followed by the expression “in the opinion of the Engineer,” unless otherwise stated.
4. The word “perform” shall be understood to mean that the Contractor, at its expense, shall “perform all operations and furnish labor, tools and equipment,” and further, “furnish and install materials that are indicated, specified or required” shall be under stood to mean that the Contractor, at its expense, shall “furnish and install the Work, complete in place and ready to use, including furnishing of necessary labor, materials, tools, equipment, and transportation.”
5. Where words “directed,” “designated,” “selected,” or words of similar import are used, it shall be understood that the direction, designation, or selection of the Engineer is intended, unless stated otherwise. The word “required” and words of similar import shall be understood to mean “as required to p roperly complete the Work as required and as approved by the Engineer,” unless stated otherwise.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Where the words “approved,” “approval,” “acceptance,” or words of similar import are used, it shall be understood that the approval, acceptance, or similar import of the Engineer is intended.
1-2 TERMS AND DEFINITIONS
Where applicable ADD/REPLACE the following:
1. Agency - The City of Carlsbad, the owner of the Project.
2. Agency Approval - Except where stated in this Contract to the contrary, the phrases “Agency approval,” and “Agency’s written approval” or such similar phrases shall mean approval by the City Manager for the City of Carlsbad, which approval shall not be unreasonably withheld.
3. Agency Forces – City of Carlsbad employees who coordinate construction work.
4. Agency Supplement - 00 73 00 Agency Supplemental General Provisions; and 00 74 00 Agency Supplemental Technical Provisions.
5. Allowance (AL) - Payment under Allowance Bid items, denoted as “AL,” shall be based on the actual expenditures and for pre-authorized items of the Work in accordance with the Contract Documents. The unused portions of the Allowances shall revert to the Agency upon acceptance of the Project or Work.
6. Apparent Low Bidder - The Bidder whose Bid having been publicly opened, initially meets the material requirements of the Bid Documents and whose Bid price is the lowest received.
7. Applicable Laws - Laws, statutes, ordinances, rules, orders, and regulations of governmental authorities and courts having jurisdiction over the Project.
8. As-Builts - The CADD drawings prepared from the approved Red-lines for record keeping purposes.
9. Award of Contract (Award) - The date on which the Board or designee executes the Contract.
10. Bid - Any proposal submitted to the Agency in competitive bidding for the construction, alteration, repair, or improvement of any structure, building, road or other improvement of any kind.
11. Bid Administrator – The City’s designated representative for soliciting and conducting bids on the City’s online bidding portal.
12. Board – The officer or body constituting the awarding authority of the Agency, which is the City Council for the City of Carlsbad.
13. Board of Directors for the Carlsbad Municipal Water District – The legislative body that governs the Carlsbad Municipal Water District and has the authority to pass ordinances and appropriate funds.
14. Business Day - See Working Day.
15. Calendar Day – Every day on the calendar, including weekends and holidays.
16. City - The term “City” or “the City” means, City of Carlsbad. See also Agency.
17. City Council - The legislative body that governs the City of Carlsbad and has the authority to pass ordinances and appropriate funds.
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
18. City Engineer - The term “ City E ngineer” is defined as the Transportation Director, or designee, and is the person authorized to perform the functions of the City Engineer as defined in Government Code Section 66416.5. The City Engineer is the City's "duly authorized officer" for the purposes of Public Contract Code Sections 4107 and 4107.5.
19. City Manager – The appointed official who directs the administration of the City of Carlsbad.
20. Construction Documents - Plans and details, including Plans showing installation of major systems, equipment, fixed furnishings and graphics, the technical specifications and all other technical drawings, schedules, diagrams and specifications, accepted Shop Drawings, Working Drawings, and submittals that are necessary to set forth in detail the requirements for the Project.
21. Construction Manager – The City’s Consultant Project Inspector and the Engineer’s designated representative for the first level of appeal for informal dispute resolution .
Contractor to review all work progress, monthly payment applications, monthly schedule updates and project documentation (e.g., submittals, RFI’s, etc.) with Construction Manager.
22. Construction Work - The portion of the Work to construct the Project as set forth in the Contract Documents in conformance with 2-1, “WORK TO BE DONE.”
23. Contract – The written agreement between the Agency and the Contractor covering the Work.
24. Contract Documents - Contract Documents include the following: The signed Contract, Addenda, Notice Inviting Bids, funding agency provisions, Bid including documentation accompanying the Bid and any post -Bid documentation submitted prior to the Notice of Award when attached as an exhibit to the Contract, Bonds, Permits, CEQA documents, Standard Specifications (the “Greenbook”), Agency Supplement, Plans, Standard Plans, Construction Documents, Reference Specifications, and Change Orders. Contract Documents, when applicable, shall also include Site and Coastal development permits, NEPA documents, re -vegetation plans, biological letters or technical reports, habitat mitigation plans, storm water documents, and local, state, and federal resource agency permits.
25. Contract Time - The number of Working Days to complete the Work as specified in the Contract Documents.
26. Contractor – The individual, partnership, corporation, joint venture, or other legal entity having a Contract with the Agency to perform the Work. In the case of Work being done under permit issued by the Agency, the permittee shall be constructed to be the Contractor. The term “prime contractor” shall mean Contractor.
27. Critical Path – In the Construction Schedule, the sequence of activities that represents the longest path through the Project network of activities and the shortest possible Project duration.
28. Days – Days shall mean consecutive calendar days unless otherwise specified in this Contract.
29. Defective Work - Work that does not conform to the Contract Documents.
30. Delay Factor - The Delay Factor may be the basis for compensation for idle equipment time on an excusable delay. The factor has been calculated to include the ownership costs ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
without including operating costs. The Delay Factor recovers all the Contractor’s non - operating costs in an 8-hour day. If payment is made for equipment on an excusable delay, it is limited to 8 hours per day or 40 hours per week maximum.
31. Deputy City Engineer – The Engineering Manager of the Construction Management & Inspection Division and the Construction Manager’s immediate supervisor and the Engineer’s designated representative for the second level of appeal for informal dispute resolution.
32. Dispute Board – Persons designated by the City Manager of the City of Carlsbad, to hear and advise the City Manager on claims submitted by the Contractor. The City Manager for the City of Carlsbad is the last appeal level for informal dispute resolution.
33. Drawings - See Plans.
34. D-size Sheet - “D” size paper for engineering design applications refers to 22” x 34” paper.
35. Engineer - The Deputy City Manager , Public Works of the City of Carlsbad acting either directly or through designated representatives and the fourth level of appeal for informal dispute resolution.
36. Engineer of Record/Design Engineer – A registered Professional Engineer licensed in the State of California who is qualified to act as an agent of a Project Owner or to prepare Plans for facilities to be accepted by the City of Carlsbad . The term includes persons licensed in the State of California as Civil Engineers or Structural Engineers, as well as other licensed professionals like Architects and Landscape Architects.
37. Engineering Manager – For this project, this capacity will be served by the Public Works Manager.
38. Field Book - The Agency field maps showing sewer and water facilities.
39. Field Order - A Field Order is a written agreement by the Engineer to compensate the Contractor for work items in accordance with 2 -8, “EXTRA WORK” or 2 -9, “CHANGED CONDITIONS.” A Field Order does not change the Contract Price or Contract Time or the intent of the Contract. The unused portions of the Field Orders shall revert to the Agency upon acceptance of the Work.
40. Final Environmental Document - The CEQA and/or NEPA document issued for the Project, such as certified environmental impact reports, mitigated negative declarations (MNDs), negative declarations, or exemptions.
41. Final Payment - The last payment for the Contract made to the Contractor, excluding Retention.
42. Fleet & Facilities Project Manager – The Project Manager with the Fleet & Facilities Division and the Construction Manager’s immediate supervisor and designated representative for the second level of appeal for informal dispute resolution.
43. Float – The number of days by which an activity in the Construction Schedule may be delayed from either its earliest start date or earliest completion date without extending the Contract Time (total float). Total float belongs to the Project and to any Party to accommodate changes in the Work or to mitigate the effect of events which may delay completion.
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
44. Holiday - Holidays observed by the Agency are listed below:
Holiday Observed On
New Year’s Day January 1
Martin Luther King Day 3rd Monday in January
Presidents’ Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1st Monday in September
Indigenous Peoples’ Day 2nd Monday in October
Veteran’s Day November 11
Thanksgiving Day 4th Thursday/Friday in
November
Christmas Day December 25
If any Holiday listed falls on a Saturday, the Saturday and the preceding Friday are both legal Holidays. If the Holiday falls on a Sunday, both Sunday and the following Monday shall be legal Holidays. Unless specified otherwise in the Contract Documents or authorized by the Engineer, do not work on Holidays.
45. Limited Notice to Proceed (LNTP) - A written notice given from the Agency that authorizes the Contractor to start a limited amount of work that, as described in the notice, is not Construction Work.
46. Minor Bid Item – a single contract item constituting less than 10 percent (10%) of the original Contract Price bid.
47. Night Work - See Working Night.
48. Normal Working Hours - Unless specified otherwise, Normal Working Hours core periods shall be 7:00 AM to 5:00 PM, Monday through Friday, inclusive. Saturdays, Sundays, and Agency Holidays are excluded. For Traffic Control Permits, Normal Working Hours are defined as 8:30 AM to 3:30 PM, unless specified otherwise.
49. Notice of Completion (NOC) - A document recorded with the County of San Diego to signify that the Work has been completed to the satisfaction of the Construction Manager and accepted by the Agency.
50. Notice to Proceed (NTP) - A written notice to proceed with the work of the contract as mutually agreed in the Preconstruction Meeting.
51. Party or Parties - The Agency, the Contractor, or both, their respective permitted successors or assigns, and any other future signatories to the Contract.
52. Plans – The drawings, profiles, cross sections, Standard Plans, working drawings, and shop drawings, or reproductions thereof, approved by the City Engineer, which show the location, character, dimensions or details of the Work.
53. Prime Contractor - See Contractor.
54. Project Inspector – the Engineer’s designated representative for inspection, Contract administration and the first level for informal dispute resolution.
55. Project Site (Site) - Areas where the Work is performed pursuant to the Contract.
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
56. Punchlist - A list of items of Work or corrections generated after a Walk -through that is conducted when the Contractor considers that the Work and Services are complete.
57. Quality Control Standards and Procedures - The standards and procedures that are stated in a written manual that can be furnished to the Engineer upon request. The standards and procedures are followed by the Supplier in the production of materials supplied for the Work Site.
58. Red-lines - Plans with annotations of changes made during construction to reflect the actual improvements or facilities built during construction whether concealed or visible.
59. Retention - The amount withheld from the money due to the Contractor in accordance with 7-3.2, “PARTIAL AND FINAL PAYMENT.”
60. Samples - Physical examples of the materials, equipment, or workmanship specified or required and which conform with the standards and specifications in the Contract Documents and by which the Work shall be evaluated.
61. Schedule - A Critical Path Method (CPM) schedule of construction activities and their durations to be performed during the Contract Time and prepared by the Contractor in accordance with 6 -1, “CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK,” and accepted by the Engineer.
62. Scope of Work (SOW ) - Labor, materials, equipment, facilities, and services required to be performed or provided by the Contractor to complete the entire Project or the various separately identifiable parts of the Project pursuant to the provisions of the Contract Documents.
63. Services - Work performed in connection with the layout, construction, testing, inspection, and commissioning of the Work or administration of the Contract and which may include professional services such as engineering, surveying, construction management and lega l services that are required in accordance with the Contract Documents. Services are incidental to the Work.
64. Separate Contractors - Those individuals or entities that have entered into arrangements with the Agency for the provision of labor, materials, or other services in connection with the Project who are not under contract with the Contractor.
65. Signal Pre-Check - The procedure that the City uses to evaluate traffic signal systems prior to Signal Turn-On and generating a Punchlist.
66. Signal Turn-On - The day the City activates new traffic signals.
67. Supplemental Provisions – See Agency Supplement.
68. Tonne – Also referred to as “metric ton.” Represents a unit of measure in the International System of Units equal to 1,000 kilograms.
69. Walk-through - The procedure the Agency uses to evaluate the status of the Project and to generate a Punchlist prior to acceptance of the Work.
70. Work – All labor, materials, equipment, tools, and services and other requirements of the Contract Documents as modified by Change Order, whether completed or partially completed, provided or to be provided by Contractor to fulfill Contractor’s obligations.
The Work may constitute the whole or a part of the Project.
71. Working Day - Any day within the period between the start of the Contract time as defined in Section 6-1 and the date provided for completion, or upon field acceptance by the Engineer for all work provided for in the Contract, whichever occurs first, other than:
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
• Saturday;
• Sunday;
• any day designated as a holiday by the Agency;
• any other day designated as a holiday in a Master Labor Agreement entered into by the Contractor or on behalf of the Contractor as an eligible member of a contractor association;
• any day the Contractor is prevented from working at the beginning of the workday for cause as defined in Section 6-6.1; or
• any day the Contractor is prevented from working during the first 5 hours with at least 60 percent of the normal work force for cause as defined in Section 6-
6.1. 72. Working Night (Night Work) - A period of nighttime work, allowed only on Sunday through Thursday, excluding Holidays.
73. Work Site - See Project Site (Site).
1-3 ABBREVIATIONS
1-3.2 Common Usage.
ADD the following:
AML Approved Material List
CADD Computer Aided Design and Drafting
CA MUTCD California Manual on Uniform Traffic Control Devices CCT Correlated Color Temperature
CEQA California Environmental Quality Act.
CFR Code of Federal Regulations
CGP Construction General Permit
CL Centerline
CMS Content Management System Database
CNC Computer Numerical Control
CRI Color Rendering Index
DBE Disadvantaged Business Enterprise
DCE Data Computer Equipment
DG Decomposed Granite
DVBE Disabled Veteran Business Enterprise
DWT Detectable Warning Tiles
EOW Engineer of Work
FRP Fiberglass Reinforced Plastic
GFE Good Faith Effort
GMT Greenwich Mean Time
GPS Global Positioning System
LCD Liquid Crystal Display
M&M Maintenance and Monitoring
MMC Mitigation and Monitoring Coordination
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
NC Not Connected, Normally Closed
NEPA National Environmental Policy Act of 1969
NOC Notice of Completion
NPDES National Pollutant Discharge Elimination System
NTP Notice to Proceed
OC On Center
PB Pull Box
PL Property Line
RFP Request for Proposal
RFI Request for Information
SOW Statement of Work, Scope of Work
SOV Schedule of Values
SPDT Single Pole Double Throw
SSD Surge Suppression Devices
UF Underground Feeder
VAC Volts AC
VPC Vitrified Polymer Composite
WBE Women Business Enterprise
1-3.3 Institutions.
ADD the following:
AISC American Institute of Steel Construction
ANSI American National Standards Institute
ASTM American Society for Testing and Materials
AWPA American Wood Preservers Association
AWS American Welding Society
AWWA American Water Works Association
DSD Development Services Department
ISO International Organization for Standardization
MTS San Diego Metropolitan Transit System
NAFP National Association of Pipe Fabricators
NCTD North County Transit District
NEMA National Electrical Manufacturers Association
NOAA National Oceanic and Atmospheric Administration (Dept. of Commerce) NFPA National Fire Protection Association
PCI Prestressed Concrete Institute
SANDAG San Diego Association of Governments
UL Underwriters’ Laboratories Inc.
USGS United States Geological Survey
1-6 BIDDING AND SUBMISSION OF THE BID
1-6.2 Subcontractor Listing.
ADD the following:
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Each Bidder shall comply with the Chapter of the Public Contract Code including Sections 4100 through 4113. The use of Subcontractors in no way relieves the Contractor of any obligations or responsibilities under the Contract.
The following excerpts or summaries of some of the requirements of this Chapter are included below for information:
The Bidder shall set forth in the Bid, as provided in Section 4104:
“(a) The name and location of the place of business of each Subcontractor who will perform Work or Labor or render service to the prime Contractor in or about the construction of the Work or improvements, or a Subcontractor licensed by the State of California who, under Subcontract to the prime Contractor, specially fabricates and installs a portion of the Work or improvement according to detailed Drawings contained in the Plans and Specifications, in an amount in excess of one-half of 1 percent of the prime Contractor’s total Bid, or, in the case of Bids or offers for the construction of streets or highways, including bridges, in excess of one- half of 1 percent of the prime Contractor’s total Bid or ten thousand dollars ($10,000), whichever is greater.”
“(b) The portion of the Work which will be done by each such Subcontractor under this act. The prime Contractor shall list only one Subcontractor for each such portion as is defined by the prime Contractor in his Bid.”
If the Contractor fails to specify a Subcontractor or specifies more than one Subcontractor for the same portion of the Work to be performed under the Contract (in excess of one-half of 1 percent of the Contractor’s total Bid), the Contractor shall be qualified to perform that portion itself, and shall perform that portion itself, except as otherwise provided in the Code.
As provided in Section 4107, no Contractor whose Bid is accepted shall substitute any person as Subcontractor in place of the Subcontractor listed in the original Bid, except for causes and by procedures established in Section 4107.5. This section provides procedures to correct a clerical error in the listing of a Subcontractor.
Section 4110 provides that a Contractor violating any of the provisions of the Chapter violates the Contract and the Board may exercise the option either to cancel the Contract or assess the Contractor a penalty in an amount of not more than 10 percent of the Subcontract involved, after a public hearing.
1-7 AWARD AND EXECUTION OF THE CONTRACT
1-7.1 General.
DELETE in its entirety and SUBSTITUTE with the following:
1-7.1 Standard Contract Provisions.
1-7.1.1 Successor’s Obligations.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
All grants, covenants, provisions and claims, rights, powers, privileges and abilities contained in the Contract Documents shall be read and held as made by and with, and granted to and imposed upon, the Contractor, the Agency, and the Contractor’s and the Agency’s respective heirs, executors, administrators, successors, and assigns. 1-7.1.2 Waiver of Legal Rights.
1. The Agency’s failure to insist, in any 1 or more instances, upon the performance of any provision of the Contract, or to exercise any right therein, shall not be construed as a waiver or relinquishment of such provisions or rights.
2. Any waiver of any breach of the Contract shall not be held to be a waiver of any other or subsequent breach.
3. Any waiver the Agency issues to any provision of the Contract shall only be effective if it is agreed upon in writing by the Agency and if it is specific to the matter concerned. 1-7.1.3 Requests for Information (RFI).
1. Inquiries from the Contractor seeking clarification of the requirements of the Contract Documents shall be submitted in writing to the Agency as a Request for Information (RFI).
1-7.1.4 Assignment to Awarding Body.
1. In accordance with subdivision (b) of Public Contract Code Section 7103.5 , the Contractor and the Contractor’s Subcontractors shall conform to the following requirements:
a. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the Contractor or the Contractor’s Subcontractor offer and agree to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Business and Professions Code Section 16700 et seq.) arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract.
b. This assignment shall be made and become effective at the time the awarding body tenders to the Contractor, without further acknowledgment by the Parties.
1-7.2 Contract Bonds.
ADD the following:
1. Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below. Bonds issued by a Surety, who is authorized to issue bonds in California, and whose bonding li mitation shown in the circular is enough to provide bonds in the amount required by the Contract shall be deemed approved unless specifically rejected by the Agency. Bonds from all other sureties shall be accompanied by all documents enumerated in Code of Civil Procedure Section 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.
2. Each bond shall incorporate, by reference, the Contract and be signed by both the Bidder and Surety and the signature of the authorized agent of the Surety shall be notarized. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3. The faithful performance/warranty bond will be reduced to 25 percent of the original amount 30 Calendar Days after recordation of the Notice of Completion and will remain in full force and effect for the 1-year warranty period and until all warranty repairs are completed to the satisfaction of the Engineer. The bond to secure payment of laborers and materials suppliers shall be released 6 months plus 30 Calendar D ays after recordation of the Notice of Completion if all claims have been paid.
4. All bonds are to be placed with a Surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed its liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to contain the following documents:
a. An original, or a certified copy, of the unrevoked appointment, power of attorney, bylaws, or other instrument entitling or authorizing the person who executed the bond to do so.
b. A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.
5. If the Bid is accepted, the Agency may require a financial statement of the assets and liabilities of the Surety for the quarter calendar year preceding the date of the execution of the bond.
The financial statement shall be made by an officer’s certificate as defined in Corporations Code Section 173. In the case of a foreign Surety, the financial statement may be verified by the oath of the principal officer or manager residing within the United States.
6. If the Surety on any bond furnished by the Contractor is declared bankrupt, becomes insolvent, or its right to do business is terminated in any state where any part of the Project is located, immediately notify the Engineer; and immediately substitute anot her bond and Surety acceptable to the Agency.
7. The Contractor shall require the Surety to mail its standard “Bond Status” form to the Agency.
SECTION 2 – SCOPE OF THE WORK
2-1 WORK TO BE DONE
ADD the following:
1. Where approval or acceptance by the Agency is required, only a general approval is required.
However, such approval does not relieve the Contractor from the Contractor’s responsibility for complying with all applicable laws, codes, and best industry practi ces. Contractor has its obligation to fulfill all conditions of the Contract.
2. In accordance with the provisions of California Law, the Contractor shall possess or require the Contractor’s Subcontractor(s) to possess valid appropriate license(s) for the Work being performed as conveyed in the Bidding Documents.
2-2 PERMITS
ADD the following:
2-2 PERMITS, FEES, AND NOTICES
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2-2.1 Building Permits.
1. The Contractor shall obtain the required building permits from Agency’s permitting departments. Any prior approval obtained for the Plans shall not in any way waive this requirement.
2. Request inspections in accordance with the building codes in effect on the permitted Plans and by City’s Development Services Department, Building Division. Any Work performed without the benefit of the required permit and subsequent inspection shall be re moved and replaced at the discretion of the City Building Inspector at no additional cost.
3. The payment for procuring Building Permits shall be included in the Allowance Bid item for “Building Permits.” If no such Bid item is included in the Bid Schedule, payment shall be included in the various Bid items and no additional payment shall be made. 2-3 RIGHT-OF-WAY
ADD the following:
1. The Contractor shall coordinate access to private property with the property owners and the timing of accessing private property when the Agency has already obtained rights of entry.
Unless otherwise provided, the Contractor shall coordinate, pay for, and assume all responsibility for acquiring using, and disposing of additional work areas and facilities temporarily required. The Contractor shall indemnify and hold the Agency harmless from all claims for damages caused by such actions. The Contractor shall protect any private and public improvements.
2-4 COOPERATION AND COLLATERAL WORK
ADD the following:
1. The Contractor shall coordinate and cooperate with all the utility companies during the relocation or construction of their lines. The Contractor may be granted a time extension if, in the opinion of the Engineer, a delay is caused by the utility company. No additional compensation will be made to the Contractor for any such delay.
2. If work to be performed by the Agency or its separate Contractors is not shown or specified in the Contract Documents, the Engineer shall notify the Contractor in writing 10 Working Days prior to the start of such work and make available Plans or Specifications for work to be performed by others that may be pertinent to Contractor’s Work. If Contractor determines that the work to be performed by the Agency or its separate Contractors may interfere with or cause damage or delays to Contractor’s Work, notify the Engineer in writing within 3 Working Days of the Engineer’s notice. The Contractor shall diligently pursue with the Engineer resolution of potential conflicts with the work of others.
3. The Contractor shall prepare and submit to the Engineer for approval a plan and schedule to integrate the work of Contractor or its Subcontractors, Agency or the work of others. The plan shall conform to the tasks identified in the Construction Schedule and identify additional tasks as necessary and the sequencing of interrelated activities. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2-5 THE CONTRACTOR’S EQUIPMENT AND FACILITIES
2-5.2 Temporary Utility Services.
ADD the following:
1. The Contractor shall furnish, install, maintain, and remove all temporary utility services, such as light, power, electrical, gas, and water, at its own expense for construction and maintenance activities until acceptance of Work. These include piping, wir ing, lamps, and other equipment necessary for the Work.
2. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter, and any, and all, other charges, deposits and/or fees. The costs shall be considered incidental to the items of Work that they are associated with and no additional payment will be made for them.
2-6 CHANGES REQUESTED BY THE CONTRACTOR
ADD the following:
1. Any plan or method of work suggested to the Contractor by the Agency, but not specified or required by the Contract or Change Order, which is adopted or followed by the Contractor in whole or in part shall be done at the Contractor’s sole risk and responsibility.
2. The Contract Price is not subject to adjustment for any type of tax increases after the Award.
ADD 2-6.1 Cost Reduction Proposal.
1. The Contractor may submit to the Engineer in writing, proposals for modifying the Plans, Specifications, or other requirements of the Contract for the sole purpose of reducing the total cost of construction.
2. The cost reduction proposal shall not impair, in any manner, the essential functions or characteristics of the Project such as service life, economy of operation, ease of maintenance, quality, desired appearance, or design and safety standards.
3. The following information must be included in the cost reduction proposal:
a. A description of both the existing Contract requirements for performing the Work and the proposed changes.
b. An itemization of the Contract requirements that shall be changed if the proposal is adopted.
c. A detailed estimate of the cost of performing the Work under the existing Contract and under the proposed change.
d. A statement of the time within which the Engineer shall act on the cost reduction proposal.
e. The Contract items of Work affected by the proposed changes, including any quantity variation attributable thereto.
4. This subsection does not require the Engineer to consider any cost reduction proposal. The Agency shall not be liable to the Contractor for not approving or acting upon any cost ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
reduction proposal the Contractor submitted nor for any delays to the Work attributable to the cost reduction proposal.
5. If a cost reduction proposal is similar to the information included in the Contract Documents or adopted by the Agency after the advertisement and prior to Award of the Contract, the Engineer will not accept such proposal and reserves the right to make suc h changes without compensation to the Contractor under the provisions of this subsection.
6. The Contractor shall continue to perform the Work in accordance with the requirements of the Contract until a Change Order incorporating the cost reduction proposal has been issued.
7. The Engineer is the sole judge of the acceptability of a cost reduction proposal and the estimated net savings. In determining the estimated net savings, the Agency has the right to disregard the Contract Bid prices if, in the judgment of the Engineer, suc h prices do not represent a fair measure of the value of the Work to be performed or to be deleted.
8. The Agency reserves the right to require the Contractor to share in the Agency’s costs of investigating the Contractor’s cost reduction proposal. When this is required, the Contractor shall indicate the Contractor’s acceptance in writing allowing the Agency to deduct amounts payable to the Contractor.
9. If the Engineer accepts the Contractor’s cost reduction proposal in whole or in part, the Engineer shall issue a Change Order to incorporate the changes in the Plans and Specifications which are necessary to permit the cost reduction proposal or such part of it as has been accepted to be put into effect. If the Engineer’s approval is conditional, the Change Order shall include any conditions upon which the Engineer’s approval is based.
10. The Change Order also includes the estimated net savings in the cost of performing the Work due to the accepted cost reduction proposal and provides that the Contract cost be adjusted by crediting the Agency with 50% of estimated net savings amount.
11. The Contract Time shall not be extended by the acceptance of the cost reduction proposal and the performance of the Work unless specified otherwise in the Change Order.
12. The amount specified as payable to the Contractor in the Change Order is full compensation for the cost reduction proposal and the performance of the Work.
13. The Agency expressly reserves the right to adopt a cost reduction proposal for general use on contracts administered by the Agency when it determines that the proposal is suitable for application to other contracts. When an accepted cost reduction proposal is adopted for general use, only the Contractor who first submitted such propo sal shall be eligible for compensation subject to this subsection, and in that case, only for contracts awarded prior to submission of the accepted cost reduction proposal.
14. The cost reduction proposals identical or similar to previously submitted proposals shall be eligible for consideration and compensation under the provisions of this subsection if the identical or similar previously submitted proposals were not adopted for general application to other contracts administered by the Agency.
15. Subject to the provisions contained in the Contract, the Agency or any other public agency shall have the right to use all or any part of any submitted cost reduction proposal without obligation or compensation of any kind to the Contractor.
16. The Contractor shall bear all costs to revise bonds for the Project to include the cost reduction incentive proposal work.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2-7 CHANGES INITIATED BY THE AGENCY
2-7.1 General.
ADD the following:
a. The Agency may change the Plans, Specifications, character of the Work, or quantity of Work provided the total arithmetic dollar value of all such changes, both additive and deductive, does not exceed 25 percent of the Contract Price. Should it become necessary to exceed this limitation, the change shall be by written supplemental agreement between the Contractor and Agency, unless both parties agree to proceed with the change by Change Order.
b. Change Orders shall be in writing and state the dollar value of the change or established method of payment, any adjustment in Contract Time of completion, and when negotiated prices are involved, and shall provide for the Contractor’s signature indicating acceptance.
c. Unless expressly set forth in writing in a Change Order signed by the Agency and the Contractor, changes initiated by the Agency shall not be construed as the Agency directing the Contractor’s mean-and-methods in the execution of the Work.
ADD:
2-7.2 Payment-Contract Unit Prices.
1. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the Work from that shown on the Plans or specified in the Specifications, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price.
2. If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications varies from the Bid quantity by 50 percent or less, payment will be made at the Contract Unit Price. If the actual q uantity of the item of work varies from the Bid quantity by more than 50 percent, payment will be made per Section 2-7.3 or 2-7.4 as appropriate.
3. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does involve a substantial change in the character of the Work from that shown on the Plans or specified in the Specifications, an adjustment in payment will be made per Section 2-7.6. 2-7.3 Payment – Increases of More than 50 Percent.
1. Should the actual quantity of an item of Work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 50 percent, payment for the quantity in excess of 150 percent of the Bid quantity will be made on the basis of an ad justment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 2 -8. The Extra Work per Section 2 -8, basis of paymen t, shall not include fixed ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
costs. Fixed costs shall be deemed to have been recovered by the Contractor through payment for 150 percent of the Bid quantity at the Contract Unit Price. 2-7.4 Payment – Decreases of More than 50 Percent
Should the actual quantity of an item of Work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less than 50 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 2-8; however, in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 50 percent of the Bid quantity at the Contract Unit Price. 2-7.5 Stipulated Unit Prices.
Stipulated Unit Prices are unit prices established by the Agency in the Contract Documents as distinguished from Contract Unit Prices submitted by the Contractor. Stipulated Unit Prices may be used for the adjustment of Contract changes when so specified in the Supplemental General Provisions.
2-7.6 Agreed Prices.
Agreed Prices are prices for new or unforeseen Work, or adjustments in Contract Unit Prices per Section 2 -7.2, established by mutual agreement between the Contractor and the Agency. If mutual agreement cannot be reached, the Engineer may direct the Contractor to proceed on the basis of Extra Work in accordance with Section 2 -8, except as otherwise specified in Sections 2 -
7.3 and 2-7.4.
2-7.7 Schedule of Values.
Before construction, Contractor shall provide a schedule of values for all lump-sum Bid items that shall be used for the purpose of progress payments. The prices shall be valid for the purpose of Change Orders to the Project.
2-7.8 Eliminated Items.
Should any Bid item be eliminated in its entirety, payment will be made to the Contractor for its actual costs incurred in connection with the eliminated item prior to notification in writing from the Engineer so stating its elimination. If material confor ming to the Plans and Specifications is ordered by the Contractor for use in the eliminated item prior to the date of notification of elimination by the Engineer, and if the order for that material cannot be canceled, payment will be made to the Contractor for the actual cost of the material. In this case, the material shall become the property of the Agency. Payment will be made to the Contractor for its actual costs for any further handling. If the material is returnable, the material shall be returned, and payment will be made to the Contractor for the actual cost of charges made by the supplier for returning the material and for handling by the Contractor. Actual costs, as used in this Agency Supplement, shall be computed on the basis of Extra Work per Section 2-8. 2-8 EXTRA WORK
ADD the following:
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
1. New or unforeseen Work will be classified as “Extra Work” when the Engineer determines that it is not covered by Contract Unit Prices or stipulated unit prices.
2. Any request by the Contractor for Extra Work shall be in writing to the Engineer and shall include itemized estimates and in accordance with Section 7 -4. The Contractor shall fully itemize the Extra Work cost estimates such as labor and payroll costs, quantities, crew composition, production rates, material costs, Subcontractor and Supplier costs, equipment costs, supplemental costs, and time impact.
2-9 CHANGED CONDITIONS
ADD the following:
The Contractor shall promptly notify the Engineer of the following Work Site conditions (“Changed Conditions”), in writing, upon their discovery and before they are disturbed:
1. Subsurface or latent physical conditions differing materially from those represented in the Contract;
2. Unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in work of the character being performed; and
3. Material differing from that represented in the Contract which the Contractor believes may be hazardous waste, as defined in Health and Safety Code Section 25117, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
The Engineer will promptly investigate conditions which appear to be Changed Conditions. If the Engineer determines that conditions are Changed Conditions and they will materially affect performance time, the Contractor, upon submitting a written request, will be granted an extension of time subject to Section 6-4.2.
If the Engineer determines that the conditions do not justify an adjustment in compensation, the Contractor will be notified in writing. This notice will also advise the Contractor of its obligation to notify the Engineer in writing if the Contractor disagrees.
The Contractor’s failure to give notice of Changed Conditions promptly upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection with them.
1. The Contractor shall not be entitled to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a Change Order, or for the occurrence of any event or other cause, unless the Contract or shall have first given the Engineer written notice of potential claim as specified in this Section 2-9. Compliance with this section shall not be required as a prerequisite to notice provisions in Section 6 -4.2(4) Extensions of Time, nor to any claim th at is based on differences in measurement or errors of computation as to Contract quantities.
2. The Contractor shall provide the Agency with a written document containing a description of the particular circumstances giving rise to the potential claim, the reasons for which the ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Contractor believes additional compensation may be due and the nature of any and all costs involved within 20 Working Days of the date of service of the written notice of potential claim for Changed Conditions. Verbal notifications will not be accepted.
3. The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-12656.
“The undersigned certifies that the above statements are made in full awareness of the California False Claims Act, Government Code Sections 12650 -12656. The undersigned further understands and agrees that this potential claim, unless resolved, must be restated as a claim in response to the Agency’s proposed final estimate for it to be further considered.”
By: Title:
Date:
Company Name:
4. The Contractor’s estimate of costs may be updated when actual costs are known. The Contractor shall submit proof of its actual costs to the Engineer within 20 Working Days after the affected Work is completed. Failure to do so shall be cause to deny any l ater-filed claim regarding a potential claim described in this Section 2-9.
5. The intent of this Section 2 -9 is to have differences between the parties arising under the Contract brought to the attention of the Engineer at the earliest possible time so that such matters can be settled, if possible, or other appropriate action promptly taken. 2-10 DISPUTED WORK
ADD 2-10.1 Claims.
1. A Claim is a written demand by the Contractor that seeks an adjustment in the Contract Price, Contract Time, or other relief associated with a dispute arising under or relating to the Contract, including a breach of any Contract provision. A voucher, invoice, or other routine request for payment is not a Claim.
2. A Claim shall conform to these specifications and may be considered after the Agency has previously denied a request by the Contractor for a Change Order seeking the demanded relief.
3. The Contractor shall submit a Claim to the Engineer if a dispute occurs that arises from or relates to the Contract. The Claim shall seek all relief to which the Contractor asserts the Contractor is entitled as a result of the event(s) giving rise to the d ispute. The Contractor’s failure to process a Claim in accordance with these specifications shall constitute a waiver of all relief associated with the dispute. Claims are subject to 6-10, “Right to Audit.”
4. The Contractor shall continue to perform the Services and Work and shall maintain the Schedule during any dispute proceedings. The Engineer will continue to make payments for undisputed Services and Work.
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
5. The Agency’s Claims process specified in the Agency Supplement shall not relieve the Contractor of the Contractor’s statutory obligations to present Claims prior to any action under the Government Code.
6. Except for those final payment items disputed in the written statement required in Section 7-3.2, all Claims of any dollar amount shall be submitted in a written statement by the Contractor no later than the date of receipt of the final payment estimate. Those final payment items disputed in the written statement required in Section 7-3.2 shall be submitted no later than 30 Calendar Days after receipt of the Final Payment estimate. No Claim will be considered that was not included in this written statement, nor will any Claim be allowed for which written notice or protest is required under any provision of this Contract , including Sections 2 -9 Changed Conditions, 2 -10 Disputed Work, 4 -1(22) Protection, 6 -4.4 Written Notice and Report, or 6 -4.2(4) Extensions of Time, unless the Contractor has complied with notice or protest requirements.
7. The Engineer will consider Contractor’s filed Claims, which must be detailed enough so the Engineer can determine the basis and amount of the Claims. Contractor shall provide the Engineer additional information to determine the facts or contentions involved in a Claim if requested by the Engineer. If additional information is needed, Contractor must provide Engineer with this information within a reasonable time of being asked for additional information. Failure to submit such information and details will b e sufficient cause for denying the Claims.
8. Payment for Claims shall be processed by the next payment application of their resolution for those Claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Section 2-10, Disputed Work, for those Claims remaining in dispute. 2-10.1.1 Initiation of Claim.
1. A Claim is a written demand by the Contractor that seeks an adjustment in the Contract Price, Contract Time, or other relief associated with a dispute arising under or relating to the Contract, including a breach of any provision of the Contract. A voucher, invoice, payment application or other routine request for payment is not a Claim. A Claim shall conform to these specifications and may be considered after the City has previously denied a request from the Contractor for a Change Order seeking the demanded relief. The Contractor shall, consistent with 2 -10.1.2, give the Agency written notice of Claim prior to commencing any Disputed Work. Failure to give the notice shall constitute a waiver of all Claims in connection with the Disputed Work. If the Contractor and the Agency are unable to reach agreement on Disputed Work, the Agency may direct the Contractor to proceed with the Work and such direction shall not be construed as the Agency directing the Contractor’s mean-and-methods in the execution of the Work. After the Agency has rejected a Change Order request and prior to proceeding with dispute resolution pursuant to the Public Contract Code, applicable provisions of which are specified below, the Contractor shall attempt to resolve all disputes informally through the following dispute resolution chain of command:
For claims with a monetary value of $50,000 or less:
i. Project Inspector
ii. Construction Manager
iii. Engineering Manager
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
For claims with a monetary value greater than $50,000:
iv. Project Inspector
v. Construction Manager
vi. Engineering Manager
vii. City Engineer
viii. City Manager or Executive Manager
2. Consistent with Section 2 -10.1.2, the Contractor shall submit a complete report within 20 Working Days after completion of the Disputed Work stating its position on the Claim, the contractual basis for the Claim, along with all documentation supporting the costs, Contract Time, and all other evidentiary materials. At each level of Claim or appeal of Claim the Agency will, within 10 Working Days of receipt of the Claim or appeal of Claim, review the Contractor’s report and respond with a position, request a dditional information or request that the Contractor meet and present its report. When additional information or a meeting is requested the Agency will provide its position within 10 Working Days of receipt of the additional information or Contractor’s presentation of its report. The Contractor may appeal each level’s position up to the Public Works Manager for claims less than $50,000 and/or up to the City Manager for the City of Carlsbad for claims greater than $50,000 after which the Contractor may proce ed under the provisions of the Public Contract Code. The Agency’s failure to state a position or otherwise respond to a Claim within the timeframes set forth above shall be deemed a rejection of the Claim by the Agency.
3. The authority within the dispute resolution chain of command is limited to recommending a resolution to a Claim to the City Manager for the City of Carlsbad. Actual approval of the Claim is subject to the Change Order provisions in the Contract.
4. Any remaining Claims not resolved by the informal dispute resolution process described above shall be resolved in accordance with Public Contract Code Section 9204, the relevant portion of which is included below:
(d)(1)(A) Upon receipt of a Claim pursuant to this section, the public entity to which the Claim applies shall conduct a reasonable review of the Claim and, within a period not to exceed 45 days, shall provide the Claimant a written statement identifying w hat portion of the Claim is disputed and what portion is undisputed. Upon receipt of a Claim, a public entity and a Contractor may, by mutual agreement, extend the time period provided in this subdivision.
(B) The Claimant shall furnish reasonable documentation to support the Claim.
(C) If the public entity needs approval from its governing body to provide the Claimant a written statement identifying the disputed portion and the undisputed portion of the Claim, and the governing body does not meet within the 45 days or within the mutu ally agreed to extension of time following receipt of a Claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
the governing body after the 45 -day period, or extension, expires to provide the Claimant a written statement identifying the disputed portion and the undisputed portion.
(D) Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2)(A) If the Claimant disputes the public entity's written response, or if the public entity fails to respond to a Claim issued pursuant to this section within the time prescribed, the Claimant may demand in writing an informal conference to meet and conf er for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B) Within 10 business days following the conclusion of the meet and confer conference, if the Claim or any portion of the Claim remains in dispute, the public entity shall provide the Claimant a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the Claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the Claimant sharing the associated costs equally. The public entity and Claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this section.
(C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotia tion or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
(D) Unless otherwise agreed to by the public entity and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program if mediation under this section does not resolve the parties' dispute.
(3) Failure by the public entity to respond to a Claim from a Contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the Claim being deemed rejected in its entirety. A Claim that is denied by reason of the public entity's failure to have responded to a Claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the Claim or the responsibility or qualifications of the Claimant.
(4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
(5) If a Subcontractor or a lower tier Subcontractor lacks legal standing to assert a Claim against a public entity because privity of Contract does not exist, the Contractor may present to the public entity a Claim on behalf of a Subcontractor or lower ti er Subcontractor. A Subcontractor may request in writing, either on their own behalf or on behalf of a lower tier Subcontractor, that the Contractor present a Claim for work which was performed by the Subcontractor or by a lower tier Subcontractor on behal f of the Subcontractor. The Subcontractor requesting that the Claim be presented to the public entity shall furnish reasonable documentation to support the Claim.
Within 45 days of receipt of this written request, the Contractor shall notify the Subcontrac tor in writing as to whether the Contractor presented the Claim to the public entity and, if the original Contractor did not present the Claim, provide the Subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the Plans or Specifications for any Public Works Project that may give rise to a Claim under this section.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
(f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a Claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civi l action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable Change Order, Claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g) This section applies to contracts entered into on or after January 1, 2017.
(h) Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i) This section shall remain in effect only until January 1, 2027, and as of that date is repealed, unless a later enacted statute that is enacted before January 1, 2027, deletes, or extends that date.
In addition, all Claims by Contractor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code Section 20104 et seq., applicable provisions of which are included below:
20104.2 For any Claim subject to this article, the following requirements apply:
(a) The Claim shall be in writing and include the documents necessary to substantiate the Claim. Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to extend the time limit or supersede notice requirements othe rwise provided by contract for the filing of Claims.
(b)(1) For Claims of less than fifty thousand dollars ($50,000), the local agency shall respond in writing to any written Claim within 45 days of receipt of the Claim, or may request, in writing, within 30 days of receipt of the Claim, any additional docum entation supporting the Claim or relating to defenses to the Claim the local agency may have against the Claimant.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the Claimant.
(3) The local agency's written response to the Claim, as further documented, shall be submitted to the Claimant within 15 days after receipt of the further documentation or within a period of time no greater than that taken by the Claimant in producing the additional information, whichever is greater.
(c)(1) For Claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy -five thousand dollars ($375,000), the local agency shall respond in writing to all written Claims within 60 days of receipt of the Claim, or may request, in writing, within 30 days of receipt of the Claim, any additional documentation supporting the Claim or relating to defenses to the Claim the local agency may have against the Claimant.
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the Claimant.
(3) The local agency's written response to the Claim, as further documented, shall be submitted to the Claimant within 30 days after receipt of the further documentation, or within a period of time no greater than that taken by the Claimant in producing th e additional information or requested documentation, whichever is greater.
(d) If the Claimant disputes the local agency's written response, or the local agency fails to respond within the time prescribed, the Claimant may so notify the local agency, in writing, either within 15 days of receipt of the local agency's response or w ithin 15 days of the local agency's failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, the local agency shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(e) Following the meet and confer conference, if the Claim or any portion remains in dispute, the Claimant may file a Claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a Claim must be filed shall be tolled from ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
the time the Claimant submits his or her written Claim pursuant to subdivision (a) until the time that Claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process.
(f) This article does not apply to tort Claims and nothing in this article is intended nor shall be construed to change the time periods for filing tort Claims or actions specified by Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division
3.6 of Title 1 of the Government Code.
20104.4 The following procedures are established for all civil actions filed to resolve Claims subject to this article:
(a) Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to nonbinding mediation unless waived by mutual stipulation of both parties. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to select a mediator within the 15-day period, any party may petition the court to appoint the mediator.
(b)(1) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code. The Ci vil Discovery Act (Title 4 (commencing with Section 2016.010) of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration.
(2) Notwithstanding any other provision of law, upon stipulation of the parties, arbitrators appointed for purposes of this article shall be experienced in construction law, and, upon stipulation of the parties, mediators and arbitrators shall be paid nece ssary and reasonable hourly rates of pay not to exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no eve nt shall these fees or expenses be paid by state or county funds.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
(3) In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, any party who after receiving an arbitration award requests a trial de novo but does not obtain a more favorable judgment shall, in additi on to payment of costs and fees under that chapter, pay the attorney's fees of the other party arising out of the trial de novo.
(b) The court may, upon request by any party, order any witnesses to participate in the mediation or arbitration process.
20104.6 Payment on undisputed portion of Claim; interest on arbitration awards or judgments:
(a) No local agency shall fail to pay money as to any portion of a Claim which is undisputed except as otherwise provided in the Contract.
(b) In any suit filed under Section 20104.4, the local agency shall pay interest at the legal rate on any arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court of law.
5. Although not to be construed as proceeding under Extra Work provisions, the Contractor shall keep and furnish records of disputed Work in accordance with Section 2-10. 2-10.1.2 Claim Certification Submittal.
1. If the Contractor’s Claim seeks an increase in the Contract Price, the Contract Time, or both, submit with the Claim an affidavit certifying the following:
a. The Claim is made in good faith and covers all costs and delays to which the Contractor is entitled as a result of the event(s) giving rise to the Claim. b. The amount Claimed accurately reflects the adjustments in the Contract Price, the Contract Time, or both to which the Contractor believes the Contractor is entitled. c. All supporting costs and pricing data are current, accurate, and complete to the best of the Contractor’s knowledge. The Contractor shall supply a cost breakdown per item of Work.
d. The Contractor shall ensure that the affidavit is executed by an official who has the authority to legally bind the Contractor.
2-10.1.3 Agency’s Final Determination.
1. If the Contractor disagrees with the City Manager or Executive Manager’s final determination, as described in 2 -10.1.1(1-2), Contractor must notify the Engineer in writing of the Contractor’s objection within 15 Working Days after receipt of the written determination and file a “Request for Mediation” in accordance with 2-10.2, “Dispute Resolution Process.”
2. Failure to give notice of objection within the 15 Working Days period shall waive the Contractor’s right to pursue the Claim.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2-10.1.6 Mandatory Assistance.
1. If a third-party dispute, litigation, or both, arises out of or relates in any way to the Services provided under the Contract, upon the Agency’s request, the Contractor shall assist in resolving the dispute or litigation. The Contractor’s assistance includes, but is not limited to the following:
a. Providing requested documents in a timely manner.
b. Providing professional consultations.
c. Attending mediations, arbitrations, depositions, trials, or any event related to the dispute resolution and litigation.
2-10.1.6.1 Compensation for Mandatory Assistance.
1. The Agency will reimburse the Contractor for reasonable fees and expenses incurred by the Contractor for any required assistance rendered in accordance with 2 -10.1.6, “Mandatory Assistance” as Extra Work.
2. The Engineer will determine whether these fees and expenses were necessary due to the Contractor’s conduct or failure to act.
3. If the Engineer determines that the basis of the dispute or litigation in which these fees and expenses were incurred were the result of the Contractor’s conduct or the Contractor’s failure to act in part or in whole, the Contractor shall reimburse the Agency for any payments made for these fees and expenses.
Reimbursement may be through any legal means necessary, including the Agency’s withholding of the Contractor’s payment.
ADD 2-10.2 Dispute Resolution Process
2-10.2.1 Mandatory Non-binding Mediation.
1. If a dispute arises out of or relates to the Contract, or the breach of it, and if the dispute cannot be settled through those procedures described in Section 2 -10.1.1, the parties must attempt to settle the dispute in an amicable manner, using mandatory mediation under the Construction Industry Mediation Rules of the American Arbitration Association before having recourse in a court of law.
2. To initiate mediation, the initiating party shall serve a Request for Mediation at the American Arbitration Association (AAA).
2-10.2.2 Mandatory Mediation Costs.
1. The expenses of witnesses for either side shall be paid by the party producing such witnesses. All other expenses of the mediation, including required traveling and other expenses of the mediator and the cost of any proofs or expert advice produced at the direct request of the mediator, shall be borne equally by the parties, unless they agree otherwise.
2-10.2.3 Selection of Mediator.
1. A single mediator, knowledgeable in construction aspects and acceptable to both parties, shall be used to mediate the dispute.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2. If AAA is used, the initiating party shall concurrently file with AAA a “Request for Mediation” along with the appropriate fees, a copy of requested mediators marked in preference order, and a preference for available dates.
3. If AAA is selected to coordinate the mediation (Administrator), within 10 Working Days from the receipt of the initiating party’s Request for Mediation, the opposing party shall file the following:
a. A copy of the list of the preferred mediators listed in preference order after striking any mediators to which they have any objection. b. A preference for available dates.
c. Appropriate fees.
4. If the parties cannot agree on a mediator, then each party shall select a mediator and those mediators shall select the neutral third party to mediate the matter. 2-10.2.4 Conduct of Mediation Sessions.
1. Mediation hearings shall be conducted in an informal manner and discovery shall not be allowed.
2. Discussions, statements, or admissions shall be confidential to the proceedings and shall not be used for any other purpose regarding the party’s legal position. The parties may agree to exchange any information they deem necessary.
3. Both parties shall have an authorized representative attend the mediation. Each representative shall have the authority to recommend entering into a settlement. Either party may have attorney(s), witnesses, or expert(s) present. Either party may request a list of witnesses and notifications of whether attorney(s) shall be present.
4. Any resulting agreements from mediation shall be documented in writing. Mediation results and documents, by themselves, shall be “non -binding” and inadmissible for any purpose in any legal proceeding, unless such admission is otherwise agreed upon in writing by both parties. Mediators shall not be subject to any subpoena or liability and their actions shall not be subject to discovery.
ADD 2-10.3 Governing Law & Forum for Litigation.
1. This Contract shall be governed by and construed in accordance with the laws of the State of California. Any lawsuits, at law or in equity, between the parties arising out of this Contract shall be filed in a court of competent jurisdiction in the County of San Diego. With respect to venue, the parties agree that this Contract is made in and will be performed in the County of San Diego. The parties waive all provisions of law providing for a change of venue in these proceedings to any other county.
ADD 2-10.4 Pre-judgment Interest.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
1. The parties stipulate that if a judgment is entered against a party for breaching this Contract, the pre-judgment interest shall be 2% per annum.
SECTION 3 – CONTROL OF THE WORK
3-2 SELF-PERFORMANCE
ADD the following:
1. If Contractor fails to satisfy the provisions requiring the Contractor to complete Work amounting to at least 50 percent of the Contract price with its own organization unless stipulated otherwise in the Contract Documents, the Agency may at its sole discr etion elect to cancel the Contract or deduct an amount equal to 10 percent of the value of the Work performed in excess of 50 percent of the Contract Price by other than the Contractor’s own organization. The Board shall be the sole body for determination of a violation of these provisions. In any proceedings under this section, the Contractor, or prime Contractor, shall be entitled to a public hearing before the Board and shall be notified 10 Calendar Days in advance of the time and location of the hearing. The determination of the Board shall be final. 3-3 SUBCONTRACTORS
ADD the following:
1. The Contractor shall incorporate these Specifications in the Contractor’s subcontracts for the work being performed by the Contractor’s Subcontractor.
2. The Contractor shall obtain or require that each Subcontractor obtains insurance policies in accordance with 5-4, “INSURANCE” which shall be kept in full force and effect for the duration of the Contract and in any attached supplemental agreements.
3. In any dispute between the Contractor and the Contractor’s Subcontractors, the Agency shall not be made a party to any judicial or administrative proceeding to resolve the dispute.
4. The Contractor shall ensure that the Contractor’s Subcontractors are appropriately licensed for the duration of the work that is performed under the Subcontracts in accordance with 2- 1, “WORK TO BE DONE.” If a Subcontractor is not properly licensed, the Contractor shall cease payment to the Subcontractor for all work performed when the Subcontractor was not properly licensed. The Contractor shall return to the Agency any payment the Contractor made to a Subcontractor for work performed when the Subcontractor was not licensed.
5. Subcontractors shall be considered employees of the Contractor, and the Contractor shall be responsible for their work.
6. Where the Contract Documents require that a particular product be installed or applied by an applicator approved by the manufacturer, ensure the Subcontractor or Supplier employed for such work is approved by the manufacturer.
7. Before the work of any Subcontractor is started, the Contractor shall submit to the Engineer for approval a written statement showing the Work to be subcontracted giving the name and business of each Subcontractor and description and value of each portion of the Work to be so subcontracted. This submittal will confirm the Subcontractor’s commitments in the Bid. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3-4 AUTHORITY OF THE ENGINEER
ADD the following:
1. The Engineer shall be the single point of contact and shall be included in all communications between Contractor and any Agency representative.
3-5 INSPECTION
ADD the following:
1. Contractor shall make available to the Engineer accurate books and accounting records regarding all its activities. Contractor shall contractually require all Subcontractors to this Contract to do the same. The Engineer shall have access to the Contractor’ s, and any Subcontractors documents described in this Section 3 -5(1) within San Diego County. The Engineer shall have the right to monitor, assess, and evaluate Contractor’s and its Subcontractor’s performance pursuant to this Contract. The Engineer’s moni toring, assessments, and evaluations will include, but shall not be limited to, audits, inspection of premises, reports, contracts, subcontracts and interviews of Contractor’s staff and the staff of all Subcontractors to this Contract. Upon reasonable advance notice, Contractor shall make available to the Engineer for examination, all of its, and all Subcontractors to this Contract, records with respect to all matters covered by this Contract. Contractor shall also permit the Engineer to audit, examine, cop y and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, payrolls, records of personnel, and other data relating to all matters covered by this Contract. Any inspection described in this Section 3 -5(1) s hall occur as often as the Engineer deems necessary and during normal business hours. However, any such inspection shall not unreasonably interfere with Contractor’s ongoing business operations. Contractor and all Subcontractors to this Contract shall maintain such data and records for as long as may be required by applicable laws and regulations.
2. The Agency may utilize consultants to assist the Engineer during construction in observing the Contractor’s performance. The consultant shall be the Agency’s Representative on the Site assisting the Engineer and must not be confused with a building inspect or with the Agency or with a Special Inspector.
3. The Agency may utilize a Special Inspector for inspection of specialty work and materials, whose costs the Agency will pay for unless the Contractor fails inspection. If inspections or tests reveal non -compliance with the requirements of the Contract Docum ents, the Contractor shall pay for all corrective measures deemed necessary by the Engineer and also pay the cost of the Agency’s subsequent re-inspection and re-testing.
4. Inspections required by codes or ordinances are the Contractor’s responsibility.
5. The Contractor’s quality control testing and inspections are the Contractor’s responsibility.
Contractor shall coordinate and schedule all inspections and tests. The Contractor shall give the Engineer notice of tests and inspections made by others. At least 5 Working Days of notice shall be given for offsite inspec tions. The Contractor shall wait until the Engineer has responded and agreed to Contractor’s schedule before scheduling test or inspections. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
6. The Agency shall schedule any inspections and tests as the Agency deems necessary to ensure the Work is accomplished in accordance with the requirements of the Contract Documents (other than inspections for work performed in accordance with a permit). The Contractor is responsible for the inspection of all Work performed in accordance with the Contract Documents.
7. Contractor shall provide access in accordance with Cal-OSHA Standards as necessary.
8. Contractor shall remove and replace any items of Work performed without the required permit or inspection. For required subsequent inspection, the Contractor shall remove and replace Work at the discretion of Engineer at no additional cost to the Agency. I nspection of the Work does not relieve the Contractor of full compliance with the Contract Documents.
9. Contractor shall not conceal the Work prior to inspection, testing, or approval required by the Contract Documents, the Engineer’s prior written request, or by other agencies. If any item of Work is done prior to obtaining the required approvals when reque sted by the Engineer, Contractor shall expose the Work for inspection, testing, and/or approval. Upon successful completion of the inspection, testing, or approval, the Contractor shall proceed with the Work. The Contractor shall bear all direct and indire ct costs and damages of such uncovering and re-covering and shall not be entitled to an increase in the Contract Price or the Contract Time, unless the Contractor has given the Engineer and any other affected agencies written notice of the Contractor’s intention to cover the Work and the Engineer has not acted in response to such notice.
10. When specified, Contractor shall make arrangements for tests, inspections, and approvals with an independent testing laboratory or entity acceptable to the Engineer, or with the appropriate public authority. The payment for such tests, inspections, and approvals are included in the Contract Price.
11. Unless specified otherwise, the Contractor shall pay the cost of inspections and tests. If inspections or tests reveal non -compliance with the requirements of the Contract Documents, the Contractor shall bear the cost of corrective measures deemed necessar y by the Engineer and the cost of the Agency’s subsequent re-inspection and re-testing.
12. The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor’s or Subcontractor’s possession pertaining to the Work that the Engineer may request.
13. Contractor agrees to maintain and/or make available, to the Engineer, within San Diego County, accurate books, and accounting records relative to all its activities and to contractually require all Subcontractors to this Contract to do the same. The Engine er shall have the right to monitor, assess, and evaluate Contractor’s and its Subcontractors performance pursuant to this Contract, the monitoring, assessments, and evaluations to include, but not be limited to, audits, inspection of premises, reports, contracts, subcontracts and interviews of Contractor’s staff and the staff of all Subcontractors to this Contract. At any time during normal business hours and as often as the Engineer may deem necessary, upon reasonable advance notice, Contractor shall make available to the Engineer for examination, all of its, and all of its Subcontractors’ records with respect to all matters covered by this Contract and will permit the Engineer to audit, examine, copy and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, payrolls, records of personnel, and other data relating to all matters covered by this Contract. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
However, any such activities shall be carried out in a manner so as to not unreasonably interfere with Contractor’s ongoing business operations. Contractor and all Subcontractors to this Contract shall maintain such data and records for as long as may be r equired by applicable laws and regulations.
3-6 THE CONTRACTOR’S REPRESENTATIVE
ADD the following:
1. Both the representative and alternative representative shall be the Contractor’s employees and shall not be assigned to a Subcontractor unless otherwise approved by the Agency in writing.
2. The Contractor’s Project team shall attend scheduled construction meetings as required by the Engineer. If any of Contractor’s staff cannot attend, the Contractor shall notify the Engineer a minimum of 24 hours in advance, prior to the start of the scheduled meeting. If the Contractor does not provide the required notification, the Contractor shall pay for the costs of the Agency’s staff, consultants, or both that attended. The Contractor shall be charged a minimum of 2 hours of the attendee’s time.
3. The payment for the Contractor’s attendance at Project meetings is included in the Contract Price. The Engineer shall deduct costs assessed to the Contractor for not attending the meetings from the monthly progress payment via Change Order. 3-7 CONTRACT DOCUMENTS
3-7.1 General.
ADD the following:
1. Specifications and Plans are divided into groups by engineering discipline for the Agency’s convenience. These divisions are not for the purpose of apportioning the Work or responsibility for the Work among Subcontractors and Suppliers.
2. The Contractor shall supply any Work that may reasonably be inferred from the Specifications or Plans as being required to produce the intended result whether or not it is specifically called for, at no additional cost to the Agency.
3. If referenced documents have been discontinued or updated by the issuing organization, the replacement documents issued or otherwise identified by that organization shall be used or, if there are no replacement documents, the last version of the document b efore it was discontinued.
4. Scaled dimensions on Contract Documents are approximate. Before ordering materials or commencing the Work, the Contractor shall measure the Site for proper size and fit and verify dimensions and quantities by taking measurements in the field. The Contracto r shall be responsible for their accuracy.
5. The Contractor shall verify any conditions affecting the cost of the Work through a reasonable examination of the Work Site prior to submitting the Bid.
6. Existing improvements visible at the Work Site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed, and disposed of by the Contractor.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
7. The Plans, Specifications, and other Contract Documents shall govern the Work. The Contract Documents are intended to be complementary and cooperative. Anything specified in the Specifications and not shown on the Plans or shown on the Plans and not specif ied in the Specifications, shall be as though shown on or specified in both.
8. The Plans shall be supplemented by such working drawings and shop drawings as are necessary to adequately control the Work.
9. The Contractor shall ascertain the existence of any conditions affecting the cost of the Work through a reasonable examination of the Work Site prior to submitting the Bid.
10. Existing improvements visible at the Work Site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed, and disposed of by the Contractor.
11. The Contractor shall, upon discovering any error or omission in the Plans or Specifications, immediately call it to the attention of the Engineer.
3-7.2 Precedence of the Contract Documents.
DELETE in its entirety and REPLACE with the following:
1. If there is a conflict between any of the Contract Documents, the document highest in the order of precedence, and most recent in edition, shall control. The order of precedence, from highest to lowest, shall be as follows:
a. Permits (issued by jurisdictional regulatory agencies including environmental documents).
b. Change Orders and supplemental agreements; whichever occurs last. c. Contract Addenda, whichever occurs last.
d. The signed written Contract.
e. Bid/Proposal.
f. Project Plans.
g. Technical Specifications.
h. Standard Drawings.
i. Agency Supplemental General Provisions (Section 00 73 00). j. Agency Supplemental Technical Provisions (Section 00 74 00). k. Standard Plans
i. City of Carlsbad Standard Drawings.
ii. Carlsbad Municipal Water District Standard Drawings. iii. City of Carlsbad modifications to the San Diego Area Regional Standard Drawings.
iv. Traffic Signal Design Guidelines and Standards.
v. State of California Department of Transportation Standard Plans. vi. California Manual on Uniform Traffic Control Devices (CA MUTCD). l. “Greenbook” (Standard Specifications for Public Works Construction). m. Reference Specifications.
2. When additional small business/minority/women -owned/veteran or other special requirements by funding sources are included in the Contract Documents, the funding source’s requirements shall govern.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
a. With reference to the Drawings, the order of precedence shall be as follows: Figures govern over scaled dimensions.
b. Detail Drawings govern over general Drawings.
c. Addenda and Change Order Drawings govern over Plans. d. Plans govern over Standard Drawings.
3. When a conflict exists between the ADA requirements of Title 24, and the Agency Supplemental Provisions, the most restrictive requirement shall be followed.
ADD: 3-7.3 Red-lines and Record Documents.
3-7.3.1 General.
1. The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor’s or Subcontractor’s possession pertaining to the Work that the Engineer may request.
2. The Contractor shall keep the Red -lines current with entries checked by the Engineer before the Work is covered. Contractor’s failure to update and deliver Red -lines information monthly to the Engineer for review and approval may result in the withholding of monthly progress payments.
3. The Contractor shall note the source identification, such as RFI numbers and Change Order numbers, as required identifying the source of the change to the Contract Documents.
4. The Contractor shall deliver the Red -lines to the Engineer upon completion of the Construction Work.
5. The Contractor shall legibly annotate a full -size set of Plans daily, in red ink, to record additions, deletions or changes to the Work and changes in location, elevation or character of the Work not otherwise shown or noted in the Contract Documents. This “redline” set of drawings shall be kept on the Job Site, shall be used only as a record set, and shall be delivered to the Engineer within 10 Calendar Days of completion of the Work.
Contractor shall immediately give written notice of any conflicts betwee n these documents to the Engineer.
6. As-built information shall represent field measurements, approved Shop Drawings, Working Drawings, samples, product data, and other pertinent data discovered during the performance of the Work. The Contractor shall note the source of the change such as RFI or Change Order numbers, as required. The Contractor shall clearly record additions or changes in the Work and depth of underground facilities by dimensioning from 2, known, fixed points.
7. Payment for Record Drawings and Documents shall be included in the various Bid items and no additional payment will be made therefore.
3-7.3.2 Asset Specific Red-lines.
1. Utility Red-lines: Utility Red-lines shall show any changes from the Plan for the following:
a. Horizontal and vertical bends
b. Changes in pipe material or pressure class
c. Isolation valves
d. Insulating joints
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
e. Blow off valves by stationing and offsets.
f. Air vacuum valves by stationing and offsets.
g. Water and recycled water meter boxes replaced.
h. Water sampling stations
i. Cathodic test stations
j. Locations of all sewer laterals and cleanouts.
k. Items abandoned in place following dewatering operation.
2. Building Red -lines: Building Red -lines shall show any changes from the Plans for the following:
a. Location by dimension and the depth by elevation of underground lines, valves, plugged tees, and capped ends.
b. By dimension or scale Plans, wiring, conduits, and pull boxes as installed. c. Information necessary to maintain and service concealed items of Work. d. Dimensional changes to the Drawings.
e. Revisions to details shown on the Drawings.
f. Depths of foundations below the first floor.
g. Locations and depths of underground utilities.
h. Revisions to the routing of piping and conduits.
i. Revisions to electrical circuitry.
j. Actual equipment locations.
k. Duct size and routing.
l. Locations of concealed internal utilities.
m. Changes made by Change Orders.
n. Details not shown on original Plans.
3-7.3.3 Payment.
1. The payment for Red-lines Drawings shall be included in the Contract Price.
ADD 3-7.4 Measurement and Dimensions.
1. Scaled dimensions are approximate. Before ordering materials or commencing the Work, the Contractor shall measure the Site for proper size and fit and verify dimensions and quantities by taking measurements in the field. Contractor shall be responsible for their accuracy. 3-8 SUBMITTALS
3-8.1 General
Add the following:
1. Shop Drawings and engineering data (submittals) covering all equipment and all fabricated components and building materials which will become a permanent part of the Goods and Special Services under this Contract shall be submitted to Engineer for review, as required.
Submittals shall verify compliance with the Contract Documents and shall include Drawings and descriptive information in sufficient detail to show the kind, size, arrangement, and the operation of component materials and devices; the external connections, anchorages, and
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
supports required; the performance characteristics; and dimensions needed for installation and correlation with other materials and equipment.
2. Each submittal shall cover items from only one section of the specification unless the item consists of components from several sources. Contractor shall submit a complete initial submittal including all components. When an item consists of components fro m several sources, Contractor's initial submittal shall be complete including all components.
3. All submittals, regardless of origin, shall be approved by Contractor and clearly identified with the name and number of this Contract, Contractor's name, and references to applicable specification paragraphs and Contract Drawings. Each copy of all submitt als, regardless of origin, shall be stamped or affixed with an approval statement of Contractor. Each submittal shall indicate the intended use of the item in the Goods and Special Services. When catalog pages are submitted, applicable items shall be clearly identified and inapplicable data crossed out. The current revision, issue number, and date shall be indicated on all Drawings and other descriptive data.
4. Contractor shall be solely responsible for the completeness of each submittal. Contractor's stamp or affixed approval statement of a submittal, is a representation to Engineer that Contractor accepts sole responsibility for determining and verifying all qu antities, dimensions, field construction criteria, materials, catalog numbers, and similar data, and that Contractor has reviewed and coordinated each submittal with the requirements of the Goods and Special Services and the Contract Documents.
5. All deviations from the Contract Documents shall be identified as deviations on each submittal and shall be tabulated in Contractor's letter of transmittal using Figure P -01300-2.
Such submittals shall, as pertinent to the deviation, indicate essential details of all changes proposed by Contractor (including modifications to other facilities that may be a result of the deviation) and all required piping and wiring diagrams.
6. Engineer will not accept submittals from anyone but Contractor. Submittals shall be consecutively numbered in direct sequence of submittal and without division by subcontracts or trades.
7. For electronic submittals, drawings and the necessary data shall be submitted electronically to Engineer as specified below. Submittal documents shall be in black and white unless color is required for the review of the submittal. All electronic files shall be in PDF as generated by Adobe Acrobat Professional latest version. The PDF file(s) shall be fully indexed using the Table of Contents, searchable with thumbnails generated. PDF images must be at a readable resolution. For most documents, they should be scanned or generated at 300 dots per inch (dpi). Optical Character Recognition (OCR) capture must be performed on these images so that text can be searched, selected and copied from the generated PDF file. The PDF documents shall have a bookmark created i n the navigation frame for each major entry (“Section” or “Chapter”) in the Table of Contents. Thumbnails shall be generated for each page or graphic in the PDF file. The opening view for each PDF document shall be as follows:
1. Initial View: Bookmarks and Page
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2. Magnification: Fit In Window
3. The file shall open to the Contractor’s transmittal letter, with bookmarks to the left.
The first bookmark shall be linked to the Table of Contents.
PDF document properties shall include the submittal number for the document title and the Contractor’s name for the author.
8. Electronic submittal file sizes shall be limited to 10 MB. When multiple files are required for a submittal the least number of files possible shall be created.
9. The Contractor shall post submittals and retrieve the Engineer’s submittal review comments through the Engineer’s (Consulting Engineer’s) Project website accessible through the Internet. Instruction on procedures for posting and retrieving submittals will be provided after award of the Contract.
10. Facsimiles (fax) will not be acceptable. Engineer will not accept submittals from anyone but Contractor. Submittals shall be consecutively numbered in direct sequence of submittal and without division by subcontracts or trades.
3.8.1.2 Resubmittal of Drawings and Data
1. Contractor shall accept full responsibility for the completeness of each resubmittal.
Contractor shall verify that all corrected data and additional information previously requested by Engineer are provided on the resubmittal.
2. When corrected copies are resubmitted, Contractor shall direct specific attention to all revisions in writing and shall list separately any revisions made other than those called for by Engineer on previous submittals. Requirements specified for initial submittals shall also apply to resubmittals. Resubmittals shall bear the number of the first submittal followed by a letter (A, B, etc.) or a unique identification that indicates the initial submittal and correct sequence of each resubmittal.
3. If more than 1 resubmittal is required because of failure of Contractor to provide all previously requested corrected data or additional information, Contractor shall reimburse Agency for the charges of Engineer for review of the additional resubmittals. T his does not include initial submittal data such as shop tests and field tests that are submitted after initial submittal.
4. Resubmittals shall be made within 30 Calendar Days of the date of the letter returning the material to be modified or corrected, unless within 14 Calendar Days Contractor submits an acceptable request for an extension of the stipulated time period, listing the reasons the resubmittal cannot be completed within that time.
5. The need for more than 1 resubmittal, or any other delay in obtaining Engineer's review of submittals, will not entitle Contractor to extension of the Contract Times unless delay of the Work is the direct result of a change in the Work authorized by a Chan ge Order or failure of Engineer to review and return any submittal to Contractor within the specified review period. 3-8.1.3 Color Selection
a. Contractor shall submit samples of colors and finishes for all accepted products before Engineer will coordinate the selection of colors and finishes with Agency. Engineer will ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
prepare a schedule of finishes that include the colors and finishes selected for both manufactured products and for surfaces to be field painted or finished and will furnish this schedule to Contractor within 60 Calendar Days after the date of acceptance of the last color or finish sample.
3-8.1.4 Operations and Maintenance Data and Manuals
1. Adequate operation and maintenance information shall be supplied for all equipment requiring maintenance or other attention. The equipment supplier shall prepare a Project specific operation and maintenance manual for each type of equipment indicated in th e individual equipment sections or the equipment schedule.
2. Parts lists and operating and maintenance instructions shall be furnished for other equipment not listed in the individual equipment sections or the equipment schedule.
3. Operation and maintenance manuals shall include the following:
a) Equipment function, normal operating characteristics, and limiting conditions. b) Assembly, installation, alignment, adjustment, and checking instructions. c) Operating instructions for startup, routine and normal operation, regulation and control, shutdown, and emergency conditions.
d) Lubrication and maintenance instructions.
e) Guide to troubleshooting.
f) Parts lists and predicted life of parts subject to wear. g) Outline, cross section, and assembly drawings; engineering data; and wiring diagrams. h) Test data and performance curves, where applicable.
4. The operation and maintenance manuals shall be in addition to any instructions or parts lists packed with or attached to the equipment when delivered, or which may be required by Contractor.
5. Manuals shall be submitted in electronic format to the Engineer prior to the date of shipment of the equipment. The manuals shall be submitted and the Engineer’s review comments retrieved, through the Project website accessible through the Internet. Instr uction on procedures for posting and retrieving O&M submittals and review comments will be provided after award of the Contract. When the O&M manuals are reviewed "RETURNED FOR CORRECTION,” the corrections shall be made as instructed by the Engineer or Con sulting Engineer, and corrected manuals resubmitted to the Engineer or Consulting Engineer. When review by the Engineer is complete, 3 copies of each electronic O&M manual shall be delivered on CD-ROM to the Engineer. Each CD shall contain only 1 copy of 1 manual. Delivery of the final O&M shall be made 30 Calendar Days prior to placing the equipment in operation.
6. All material shall be marked with Project identification, and inapplicable information shall be marked out or deleted.
7. Shipment of equipment will not be considered complete until all required manuals and data have been received.
3-8.1.5 Electronic Operations and Maintenance Manuals
1. Electronic manuals shall be in Adobe Acrobat’s PDF and shall be prepared at a resolution between 300 and 600 dpi, depending on document type. OCR capture shall be performed on ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
these documents. OCR settings shall be performed with the “original image with hidden text” option in Adobe Acrobat Exchange.
2. File size shall be limited to 10 MB. When multiple files are required the least number of files possible shall be created. File names shall be in the format OMXXXXX -YYYZ-V.pdf, where XXXXX is the 5-digit number corresponding to the specification section, YYY is a 3-digit O&M manual number, e.g., 001, Z is the letter signifying a resubmittal, A, B, C, etc, and V is a number used only when more than one 10 MB file is required for an O&M manual.
3. Documents prepared in PDF format shall be processed as follows:
Pages shall be searchable (processed for optical character recognition) and indexed when multiple files are required.
a) Of material to update the manual provided by the manufacturer. Pages shall be rotated for viewing in proper orientation.
b) A bookmark shall be provided in the navigation frame for each entry in the Table of Contents.
c) Embedded thumbnails shall be generated for each completed PDF file. d) The opening view for PDF files shall be as follows:
e) Initial View: Bookmarks and Page
f) Page Number: Title Page (usually Page 1)
g) Magnification: Set to Fit in Window
h) Page: Single Page
i) Where the bookmark structure is longer than 1 page, the bookmarks shall be collapsed to show the chapter headings only.
j) When multiple files are required the first file of the series (the parent file) shall list every major topic in the Table of Contents. The parent file shall also include minor headings bookmarked based on the Table of Contents. Major headings, whose content is contained in subsequent files (children) shall be linked to be called from the parent to the specific location in the child file. The child file shall contain bookmark entries for both major and minor headings contained in the child file. The first bookmark of any child file shall link back to the parent file and shall read as follows "Return to the Equipment Name Table of Contents," e.g., Return to the Polymer Feed System Table of Contents.
k) Drawings shall be bookmarked individually.
l) Files shall be delivered without security settings to permit editing, insertion and deletion
3-8.1.6 Labeling
a. At a minimum, the following information shall be included on all final O&M manual materials, including thumb drives and hard copy manuals:
a) Equipment name and/or O&M title spelled out in complete words. b) Project Name.
c) Agency Project/Contract Number.
d) Specification Section Number. Example: “Section 15 55 00” ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
e) Manufacturer’s name.
f) File Name and Date.
3-8.2 Working Drawings.
Section not used.
3-8.3 Shop Drawings.
Section not used.
3-8.4 Supporting Information.
ADD the following:
The Contractor shall provide and keep up-to-date a complete “As-Built” record set of blue-line prints, which shall be corrected in red daily and show every change from the original Drawings and Specifications and the exact “As-Built” locations, sizes and kinds of equipment, underground piping, valves, and all other Work not visible at surface grade.
Prints for this purpose may be obtained from the Agency at cost. This set of Drawings shall be kept on the job and shall be used only as a Record Set and shall be delivered to the Engineer within 10 Calendar Days of completion of the Work. Payment for performing the Work required by Section 2-5.4 shall be included in the various Bid items and no additional payment will be made therefore.
3-8.6 Manufacturer’s Operation, Maintenance, and Warranty Instructions.
Section not used.
3-9 SUBSURFACE DATA
Section not used.
3-10 SURVEYING
Section not used.
3-12 WORK SITE MAINTENANCE
3-12.1 General.
ADD the following:
1. Maintain Site improvements including any temporary facilities, equipment, or other materials. Remove graffiti encountered on the Site within 24 hours. See also SECTION 400 - PROTECTION AND RESTORATION.
2. As a condition of Final Payment, the Contractor shall submit a signed and notarized affidavit stating that all brush, trash, debris, and surplus materials resulting from this Project have been disposed of in a legal manner. The cost of disposal is the Contractor’s responsibility.
3. The Contractor shall provide and maintain enclosed toilets for the use of their employees.
Toilets must be kept in a neat and sanitary condition and ensure that they comply with all applicable laws, ordinances, and regulations pertaining to public health a nd sanitation of dwellings and camps. The cost of such is the Contractor’s responsibility. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
4. If required in the Special Provisions, the Contractor shall provide and maintain enclosed toilets for the use of the Agency’s and Contractor’s officers, employees, or agents. Toilets must be kept in a neat and sanitary condition and ensure that they comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps. The cost of such is the Contractor’s responsibility.
5. The Contractor shall maintain drainage within and through the work areas. Earth dams will not be permitted in paved areas. Temporary dams of sandbags, asphaltic concrete, or other acceptable material will be permitted, when necessary, by the SWPPP and/ or BMP plan. Such dams shall be removed from the Site as soon as their use is no longer necessary.
6. Work Site maintenance shall be conducted on non -workdays when increased levels of maintenance are deemed necessary, in the opinion of the Engineer, to preserve the health safety or welfare of the public and or to comply with applicable regulations.
7. Disposal of all rubbish and surplus materials is incidental to Work Site maintenance. Disposal shall be made off the Site and shall be in accordance with:
a. Local codes and ordinances that govern locations and methods of disposal. b. All applicable safety laws.
c. Requirements of Subpart H, Section 1926.252 of the OSHA Safety and Health Standards for Construction.
8. Work Site maintenance is considered incidental to the items of work that they are associated with and no additional payment will be made.
9. Cleanup and Dust Control. Throughout all phases of construction, including suspension of the Work, and until the final acceptance, the Contractor shall keep the Site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by cleaning, sweeping, and sprinkling with water, or other means as necessary. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods. 3-12.2 Air Pollution Control.
ADD the following:
1. Contractor shall carry out effective measures whenever and as often as necessary to prevent Contractor’s operation from producing dust in amounts damaging to property, cultivated vegetation, domestic animals, or causing a nuisance to persons living or occupying buildings in the vici nity. Contractor shall be responsible for any damage resulting from any dust originating from Contractor’s operations. The dust abatement measures shall be continued until Contractor is relieved of further responsibility by the Engineer.
2. Contractor shall adhere to Air Pollution Control District County of San Diego regulations for equipment used on the Job Site.
3-12.3 Noise Control.
ADD the following:
1. All internal combustion engines used in the Work shall be equipped with mufflers in good repair and are subject to the City Noise Control Ordinance, Carlsbad Municipal Code Chapter
8.48. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3-12.4 Storage of Equipment and Materials.
3-12.4.1 General.
ADD the following:
1. Equipment and material storage shall be confined to areas approved by the Engineer.
Disposal of all rubbish and surplus materials shall be at the Contractor’s expense.
2. The Contractor shall order, purchase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, prepare storage area(s), store, handle, protect, move, relocate, remove and dispose excess of all materials used to accomplish the Work.
3. Materials shall be delivered to the Work Site only during Working Hours, and shall be accompanied by bills of lading that shall clearly state for each delivery: the name of the Contractor as consignee, the Project name and number, address of delivery and name of consignor and a description of the material(s) shipped.
4. Prior to storage of any materials which ha ve been shipped to or by the Contractor to any location within the City’s boundaries the Contractor shall provide the Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored and shall provide for the removal of the materials and restoration of the storage site within the time allowed for the Work.
5. All such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the location of the site on which the materials are stored. Storage of hazardous wastes, construction equipment ma terial, and parking and fueling of equipment shall not occur in biologically sensitive areas.
6. Loss, damage or deterioration of all stored materials shall be the Contractor’s responsibility.
Conformance to the requirements of this section, both within and outside the limits of work is a part of the Work. The Engineer shall have the right to verify t he suitability of materials and their proper storage at any time during the Work.
7. The Contractor shall furnish and maintain in good condition all equipment and facilities as required for the proper execution and inspection of the Work. Such equipment and facilities shall meet all requirements of applicable ordinances and laws.
8. Restore the storage area to an equal or better condition as deemed necessary by the Engineer and at no additional cost to the Agency.
10. When required by the Engineer, the Contractor shall furnish and operate a self-loading motor sweeper with spray nozzles at least once each Working Day for the purpose of keeping paved areas acceptably clean wherever construction, including restoration, is incomplete.
11. Materials and equipment shall be removed from the Site as soon as they are no longer necessary. Before the final inspection, the Site shall be cleared of equipment, unused materials, and rubbish so as to present a satisfactory clean and neat appearance. All cleanup costs shall be included in the Contractor’s Bid.
12. Care shall be taken to prevent spillage on haul routes. Any such spillage shall be removed immediately, and the area cleaned.
13. Excess excavation material from catch basins or similar structures shall be removed from the Site immediately. Sufficient material may remain for use as backfill if permitted by the ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Specifications. Forms and form lumber shall be removed from the Site as soon as practicable after stripping.
14. Failure of the Contractor to comply with the Engineer’s cleanup orders may result in an order to suspend Work until the condition is corrected. No additional compensation will be allowed because of such suspension.
15. Cleanup and dust control required in the Contract shall also be executed on weekends and other non-Working Days when needed to preserve the health safety or welfare of the public.
The Contractor shall conduct effective cleanup and dust control throughout the duration of the Contract. The Engineer may require increased levels of cleanup and dust control that, in his/her sole discretion, are necessary to preserve the health, safety and welfare of the public.
Cleanup and dust control shall be considered incide ntal to the items of Work that they are associated with and no additional payment will be made for them.
16. Vermin Control. At the time of acceptance, structures entirely constructed under the Contract shall be free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contract time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors resulting from extermination operations.
17. Temporary Light, Power, and Water. The Contractor shall furnish, install, maintain, and remove all temporary light, power, and water at its own expense. These include piping, wiring, lamps, and other equipment necessary for the Work. The Contractor shall n ot draw water from any fire hydrant (except to extinguish a fire), without obtaining permission from the water agency concerned. The Contractor shall obtain a construction meter for water used for the construction, plant establishment, maintenance, cleanup , testing and all other work requiring water related to this Contract. The Contractor shall contact the appropriate water agency for requirements. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter and any, and all, other charges, deposits and/or fees for them . These costs shall be considered incidental to the items of Work that they are associated with and no additional payment will be made for them. 3-12.4.2 Storage in Public Streets.
DELETE in its entirety and SUBSTITUTE with the following:
1. Construction materials shall not be stored in streets, roads, or highways for more than 5 Calendar Days after unloading. All materials not installed or used in construction within 5 Calendar Days after unloading shall be stored at a location approved by the Engineer.
2. Construction equipment shall not be stored at the Work Site before its actual use nor for more than 5 Calendar Days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer.
3. Excavated material, except that which is to be used as backfill in the adjacent trench, shall not be stored in public streets unless otherwise permitted. Immediately after placing backfill, all excess material shall be removed.
4. The Contractor shall not store equipment for traffic control in right of way. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
ADD 3-12.4.3 Storage and Staging Areas.
1. The City has designated a staging location in close proximity to the Project, as shown in Attachment A, that the Contractor may utilize for their use. Additional storage and staging areas are the Contractor’s responsibility. The storage and staging areas shall be as close as possible to the Site. Contractor is responsible for obtaining any permits, leases, or any other items necessary to obtain staging areas.
2. Storage of hazardous wastes, construction equipment material, and parking and fueling of equipment shall not be allowed in the MHPA or other biologically sensitive areas. Ensure the fueling of vehicles occurs only within designated staging areas using appropriate catch basins and devices.
3. Return the storage and staging area and the adjacent area to an equal or better condition as deemed necessary by the Engineer, at no additional cost to the Agency.
4. The Contractor shall provide the Engineer a copy of the lease agreement for any property to be used for the storage of materials or equipment prior to delivery or storage of any materials or equipment. Each lease agreement shall clearly state the term of the lease and a description of the materials or equipment allowed to be stored and shall provide for the removal of the materials or equipment and restoration of the storage site within the time allowed for the Work.
5. Construction equipment shall not be stored at the Work Site before its actual use on the Work nor for more than 5 Calendar Days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer. 3-12.6 Water Pollution Controls
3-12.6.2 Best Management Practices (BMPs).
ADD the following:
1. Contractor shall submit a BMP plan as a submittal to the Agency. 3-12.6.3 Storm Water Pollution Prevention Plan (SWPPP).
ADD the following:
1. The Project is expected to require a Tier 1 SWPPP. The Contractor shall evaluate the requirements for the preparation of a SWPPP for Work within the City’s boundary by reviewing the Determination of SWPPP Tier Level and Construction Threat Level (form E-32), attached as Attachment B.
2. The Contractor shall review the criteria requiring the preparation of a SWPPP conforming with the State Water Resources Control Board Order No. 2022-0057-DWQ, NPDES General Permit No. CAS000002, Waste Discharge Requirements for Discharges of Storm Water Runoff Associated with Construction and Land Disturbance Activities (the Construction General Permit or CGP). The CGP and other information are available at:
https://www.waterboards.ca.gov/water_issues/programs/stormwater/constpermits.shtml
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3. If the Agency has not prepared a SWPPP for the Project and the Project is subject to coverage under the CGP, the Contractor shall prepare and implement the SWPPP conforming with the CGP requirements.
4. The Contractor shall comply with all requirements of the approved SWPPP and the CGP including implementation during construction by a QSP, The Contractor shall provide all information necessary for the Agency to obtain coverage under the CGP during the electronic submittal of Permit Registration Documents and supporting data necessary for the filing of the storm water Notice of Intent and Notice of Termination. The Contractor shall be responsible for conducting all monitoring and inspections and filing all reports required by and in accordance with the CGP.
3-12.6.5 Payment.
DELETE in its entirety and SUBSTITUTE with the following:
1. Unless otherwise specified, payment for water pollution control, including implementation and maintenance of BMPs, shall be considered as included in the Contract Unit Price for each item in the Bid. Payment for dewatering shall be as specified in the Special Provisions.
ADD 3-12.7 Vermin Control.
1. The Site and structures constructed under the Contract shall be kept free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contract time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors resulting from extermination operations.
3-13 COMPLETION, ACCEPTANCE, AND WARRANTY
3-13.1 Completion.
DELETE in its entirety and SUBSTITUTE with the following:
1. The Contractor shall comply with the following prior to requesting a Pre -Final inspection of the Work and filing of a written assertion that the Work has been completed:
a. Provide completed and signed redline drawings and record documents including installation, maintenance and operation instructions, manuals and/or tools for installed equipment.
b. Provide and properly label all keys for existing facilities or new permanent work. c. Provide all items specified to be supplied as extra stock and spare parts. Wrap, seal, or place in a container all items as necessary to allow for storage by the Agency for future use. Verify the specified quantities.
d. Provide all final Special Inspection reports and certifications required by equipment manufacturers to demonstrate compliance with applicable codes and standards. e. Remove temporary facilities from the Site.
f. Thoroughly clean the Site and remove all mark-outs and construction staking. ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
2. The Agency Inspector will schedule the Pre-Final inspection within 5 Working Days of receipt of the Contractor’s request. The Inspector will generate a list of deficiencies (Punchlist) within 5 Working Days after the Pre-Final inspection.
3. The Contractor shall have no more than 30 Working Days to correct the deficiencies and provide a written response to each Punchlist item. The Inspector will review the corrective work within 5 Working Days of receipt of the Contractor’s written response to each Punchlist item. Any outstanding deficiencies will be considered incomplete Work and the Punchlist will be returned to Contractor. Full payment will not be made for any Bid item with outstanding deficiencies and a Final Inspection will not be schedule d until all deficiencies are completed to the satisfaction of the Inspector.
4. The Contractor shall submit a request for Final Inspection which shall include a written assertion that the Work has been completed in accordance with the Contract Documents and a written response describing the corrective Work completed for all punch list items identified in the Pre -Final inspection(s). The request for Final Inspection will not be considered without the Contractor’s written response to the punch list items. The Inspector will schedule the Final Inspection within 10 Working Days of receipt of the Contractor’s request and invitees will include the Construction Manager, Engineer and representatives from agencies or utility companies having jurisdiction over the Work. The Contractor’s attendance is mandatory.
5. If, in the Engineer’s judgment, the Work has been completed in accordance with the Contract Documents, the Engineer will set forth in writing the date the Work was completed. This will be the date when the Contractor is relieved from responsibility to prot ect and maintain the Work, and to which liquidated damages will be computed.
ADD 3-13.1.1 Requirements Before Requesting a Walk-through.
Section not used.
ADD 3-13.1.2 Walk-through and Punchlist Procedure.
Section not used.
3-13.2 Acceptance
DELETE in its entirety and SUBSTITUTE with the following:
1. Acceptance of the Work will occur after all the requirements of the Contract Documents have been fulfilled. If, in the Engineer’s judgment, the Contractor has fully performed the Contract, the Engineer will recommend to the City Manager for the City of Car lsbad or Executive Manager for the Carlsbad Municipal Water District that the Contractor’s performance of the Contract be accepted. Upon such certification by the Engineer, the City Manager or Executive Manager may accept the Work. Upon the acceptance of t he Work by the City Manager or Executive Manager, a “Notice of Completion” will be filed in the office of the San Diego County Recorder. The date of recordation shall be the date of acceptance of the Work.
3-13.3 Warranty.
DELETE in its entirety and SUBSTITUTE with the following:
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
1. Contractor shall warranty and repair all defective materials and workmanship for a period of 2 years. This warranty period shall start on the date the Work was recorded by the “Notice of Completion” unless the Agency has beneficial use of the Project (excluding water, sewer, and storm drain projects). In addition, Contractor shall warranty the Work against all latent and patent defects for a period of 10 years. The Contractor shall warranty the roof system for a period of 30 years, per the terms, conditions and limitations included in Attachment C – City Roof Warranty and document shall be signed, notarized and returned to the City upon completion of the contract work.
2. The warranty period for specific items covered under manufacturers’ or suppliers’ warranties shall commence on the date they are placed into service at the direction of or as approved by the Engineer in writing.
3. All warranties, express or implied, from Subcontractors, manufacturers, or suppliers, of any tier, for the materials furnished and work performed shall be assigned, in writing, to the Agency, and shall be delivered to the Engineer prior to the acceptance o f the Contractor’s performance of the Contract.
4. Replace or repair defective materials and workmanship in a manner satisfactory to the Engineer after notice to do so from the Engineer and within the time specified in the notice.
If Contractor fails to make such replacements or repairs within the time spe cified in the notice, the Agency may perform the replacement or repairs at Contractor’s expense. If Contractor fail s to reimburse the Agency for the actual costs, Contractor’s Surety shall be liable for the cost.
5. If, during the warranty period, any item of the Work is found to be Defective Work, Contractor shall correct it promptly after receipt of written notice from the Agency to do so. The warranty period shall be extended with respect to portions of the Work co rrected as part of the warranty requirements.
ADD 3-13.3.1 Defective Work.
1. If the Engineer finds any part of the Work, to be defective or not in compliance with the Contract Documents, the Contractor shall correct the Defective Work in accordance with the Engineer’s written instructions and within the specified time limits.
2. The Engineer may order Contractor to stop all or part of the Project if, upon notice, Contractor fails to immediately correct the Defective Work in conformance with the Contract Documents. The Contractor bears all direct and indirect costs and damages that result from the Agency’s Stop Work notice.
3. The Engineer may determine in its sole discretion to accept Defective Work instead of having the Contractor correct the Defective Work. However, the Contractor will still be financially responsible for the Defective Work. The Engineer shall issue a deducti ve Change Order and will incorporate the necessary revisions in the Contract Documents for the Defective Work, the diminished value to the Project, or for the cost to repair the Defective Work.
4. If the Contractor fails to correct Defective Work within the specified time limits, the Engineer may correct the Contractor’s Defective Work. The Agency has the right to correct any ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
Defective Work without notice in the event of an emergency. Contractor shall bear all direct and indirect costs of the Defective Work that the Agency corrects.
5. When undertaking remedial action under this section, the Agency may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s Work and or services, and incorporate into the Project all materials and equipment stored at the Site or for which the Agency has paid but Contractor has stored elsewhere.
6. For Building Projects which require a certificate of occupancy, not including sewer and water facilities, if the Contractor fails to correct the Defective Work listed on the Agency’s Punchlist within 30 Working Days in accordance with 6 -1.1, “Construction Schedule,” the Contractor shall reimburse the Agency for all costs to provide inspection services required to monitor the Contractor’s Work beyond the 30 Working Days. The Agency shall bill the Contractor for the additional inspection at the Agency’s established rates.
7. If the Contractor completes the Project or portions of the Project prior to NOC, the Contractor shall preserve equipment by developing and implementing a preventive maintenance program in compliance with manufacturer’s recommendations.
ADD 3-13.3.2 Warranty Format Requirements.
1. Written warranties, except manufacturer’s standard printed warranties, shall be on the Contractor’s and Contractor’s agents’, material suppliers’, installers’, or manufacturers’ own letterhead, addressed to and for the Agency’s benefit. Submit warranties i n the format described in this section, modified as approved by Engineer to suit the conditions pertaining to the warranty.
2. The Contractor shall obtain warranties, executed in triplicate by responsible Subcontractors and Suppliers, within 10 Working Days after completion of the applicable item of Work.
Except for items put into use with the Engineer’s permission with date mutually agreed upon in writing, ensure that the beginning time of the warranty is the Project completion date.
3. The Contractor shall verify that the documents are in proper form, contain full information, and are notarized.
4. The Contractor shall verify that warranties are signed by both the Contractor and the appropriate party.
5. The Contractor shall provide warranties to the Engineer with a neatly typed table of contents, identifying each warranty with the number and title of the applicable specification section requiring the warranty and the name of the product or work item.
6. The Contractor shall separate each warranty with index tab sheets keyed to the table of contents listing. Provide complete information using separate typed sheets as necessary. The information shall include a list of Subcontractors and Suppliers with the n ame, address, and telephone number of the responsible principals.
3-13.3.3 Long-Term Warranty Contract (LTWC).
Section not used.
ADD 3-14 PARTNERING
Section not used.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
3-14.1 Payment.
Section not used.
ADD 3-15 PUBLIC CONVENIENCE
Section not used.
ADD 3-16 SITE ACTIVITIES BY THE AGENCY OR SEPARATE CONTRACTORS 3-16.1 The Agency’s Right to Award Separate Contracts.
1. The Agency reserves the right to perform work or operations outside the Scope of Work of the Contract related to the Project with Agency Forces, Separate Contractors, or both. If work to be performed by another party was not noted in the Contract, the Agency shall give written notice to Contractor 10 Working Days prior to the start of any Work. If Contractor determines that the work being performed by the Agency or others may interfere with or cause damage to Work being performed by Contractor, notify the Engineer in writing within 3 Working Days of the Engineer’s notice.
3-16.2 Integration of the Work with Separate Contractors.
1. When specified in the Contract Documents, prepare a plan to integrate the work performed by Separate Contractors, Agency Forces, or both with the performance of the Work and submit the plan to the Engineer for approval. The plan shall be fair and reasonabl e for Contractor and the Separate Contractors. Work with Separate Contractors to reach an agreement for the prepared plan. Arrange the performance of the work so that the Work and the work of the Separate Contractors are, to the extent applicable, properly integrated and jointed in a manner that avoids any damage to the Work or to the work of the Separate Contractors.
3-16.3 Coordination.
1. Coordinate Contractor’s activities and the Schedule with the activities and schedules of the Separate Contractors and make any revisions to the Schedule deemed necessary to avoid any disruption to the Work or to the work of the Separate Contractors. 3-16.4 Use of Site.
1. Provide the Agency and the Separate Contractors reasonable opportunities for the storage of materials and equipment and performance of their work. Connect and coordinate work and operations with the work and operations of the Agency and the Separate Contra ctors as required by the Contract Documents.
2. Coordinate traffic control with the Separate Contractors for other projects and minimize the impact to the community. Prior to the start of construction, submit Contractor’s plan for coordination.
3-16.5 Deficiency in Work of Separate Contractors.
1. If part of Contractor’s Work depends on proper execution or results upon construction or operations by the Agency or a Separate Contractor, prior to proceeding with that portion of the Work, promptly report to the Separate Contractor and the Engineer any apparent ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
discrepancies or defects in construction that would render it unsuitable for proper execution and results. Use good faith efforts to resolve any such discrepancies or defects or any related disagreements. Contractor’s failure to report constitutes Contract or’s acceptance of the Work of Separate Contractors as fit, proper, and coordinated with the Work. 3-16.6 Payment.
1. Payment for reporting deficiencies, coordinating, and resolving discrepancies shall be included in the Contract Price.
SECTION 4 – CONTROL OF MATERIALS
4-2 PROTECTION
ADD the following:
1. The Contractor shall repair or replace any equipment and materials in the event of vandalism, damage, or theft at no additional cost to the Agency.
2. The Contractor shall be responsible for the protection of public and private property adjacent to the Work and shall exercise due caution to avoid damage to such property.
3. All costs to the Contractor for protecting, removing, and restoring existing improvements shall be included in the Bid.
4. The Agency and affected utility companies have, by a search of known records, endeavored to locate and indicate on the Plans, all utilities which exist within the limits of the Work.
However, the accuracy and/or completeness of the nature, size and/or loc ation of utilities indicated on the Plans is not guaranteed.
5. The Contractor shall determine the location and depth of all utilities, including service connections, which have been marked by the respective owners and which may affect or be affected by its operations. If no pay item is provided in the Contract for thi s Work, full compensation for such Work shall be considered as included in the prices Bid for other items of Work.
6. The Contractor shall not interrupt the service function or disturb the support of any utility without authority from the owner or order from the Agency. All valves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff.
7. Where protection is required to ensure support of utilities located as shown on the Plans or in accordance with Section 5-1, the Contractor shall, unless otherwise provided, furnish, and place the necessary protection at its expense.
8. Upon learning of the existence and location of any utility omitted from or shown incorrectly on the Plans, the Contractor shall immediately notify the Engineer in writing. When authorized by the Engineer, support or protection of the utility will be paid for.
9. The Contractor shall immediately notify the Engineer and the utility owner if any utility is disturbed or damaged. The Contractor shall bear the costs of repair or replacement of any utility damaged if located.
10. When placing concrete around or contiguous to any non -metallic utility installation, the Contractor shall at its expense:
a. Furnish and install a 2 -inch cushion of expansion joint material or other similar resilient material; or
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
b. Provide a sleeve or other opening which will result in a 2-inch minimum-clear annular space between the concrete and the utility; or
c. Provide other acceptable means to prevent embedment in or bonding to the concrete.
11. Where concrete is used for backfill or for structures which would result in embedment, or partial embedment, of a metallic utility installation; or where the coating, bedding or other cathodic protection system is exposed or damaged by the Contractor’s ope rations, the Contractor shall notify the Engineer and arrange to secure the advice of the affected utility owner regarding the procedures required to maintain or restore the integrity of the system.
12. Unless otherwise specified, the Contractor shall remove all interfering portions of utilities shown on the Plans or indicated in the Bid documents as “abandoned” or “to be abandoned in place.” Before starting removal operations, the Contractor shall ascertain from the Agency whether the abandonment is complete, and the costs involved in the removal and disposal shall be included in the Bid for the items of Work necessitating such removals.
13. When feasible, the owner is responsible for utilities within the area affected by the Work will complete their necessary installations, relocations, repairs, or replacements before commencement of Work by the Contractor. When the Plans or Specifications indicate that a utility installation is to be relocated, altered, or constructed by others, the Agency will conduct all negotiations with the owners and work will be done at no cost to the Contractor, except for manhole frame and cover sets to be brought to grade as provided in the Contract Documents. Utilities which are relocated to avoid interference shall be protected in their position and the cost of such protection shall be included in the Bid for the items of Work necessitating such relocation.
14. After award of the Contract, portions of utilities which are found to interfere with the Work will be relocated, altered, or reconstructed by the owners, or the Engineer may order changes in the Work to avoid interference. Such changes will be paid.
15. When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such Work shall be included in the Bid for the items of Work necessitating such Work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience shall be its responsibility and it shall make all arrangements and bear all costs.
16. The utility owner will relocate service connections as necessary within the limits of the Work or within temporary construction or slope easements. When directed by the Engineer, the Contractor shall arrange for the relocation of service connections as nec essary between the meter and property line, or between a meter and the limits of temporary construction or slope easements. The relocation of such service connections will be paid and will include the restoration of all existing improvements which may be a ffected by the relocation . The Contractor may agree with the owner of any utility to disconnect and reconnect interfering service connections. The Agency will not be involved in any such agreement.
17. Contractor shall coordinate the Work with utility agencies and companies. Prior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contractor, the Contractor shall place all curb or curb and gutter that is a part of the Work and adjacent to the location where such utility structures are shown on the Plans and are noted as being located, relocated or are otherwise shown as installed by others. In ■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022
order to minimize delays to the Contractor caused by the failure of other parties to relocate utilities that interfere with the construction, the Contractor, upon the Engineer’s approval, may be permitted to temporarily omit the portion of Work affected by the utility. If such temporary omission is approved by the Engineer, the Contractor shall place survey or other physical control markers sufficient to locate the curb or curb and gutter to the satisfaction of the utility agency or company. Such temporary omission shall be for the Contractor’s convenience and no additional compensation will be allowed therefore or for additional work, materials or delay associated with the temporary omission. The portion thus omitted shall be constructed by the Contractor i mmediately following the relocation of the utility involved unless otherwise directed by the Engineer.
18. The Contractor shall notify the Engineer of its Construction Schedule insofar as it affects the protection, removal, or relocation of utilities. The notification shall be included as a part of the Construction Schedule. The Contractor shall notify the Engineer in writing of any subsequent changes in the Construction Schedule which will affect the time available for protection, removal, or relocation of utilities.
19. The Contractor will not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, noted, and completed.
20. The Contractor may be given an extension of time for unforeseen delays attributable to unreasonably protracted interference by utilities in performing the Work correctly shown on the Plans.
21. The Agency will assume responsibility for the timely removal, relocation, or protection of existing main or trunkline utility facilities within the area affected by the Work if such utilities are not identified in the Contract Documents. The Contractor will not be assessed liquidated damages for any delay caused by failure of Agency to provide for the timely removal, relocation, or protection of such existing facilities.
22. The Contractor will be compensated for damages incurred due to delays for which the Agency is responsible or for delays attributable to interferences, relocations, or alterations not covered by the Contract Documents. These damages for delay will be determ ined by the Engineer. The Agency shall not be liable for damages which could have been avoided by the judicious handling of forces, equipment, or plant. These avoidable damages will be determined by the Engineer. The Engineer may grant Contractor an extens ion of time for damages due to delay.
23. When necessary, the Contractor shall so conduct its operations as to permit access to the Work Site and provide time for utility work to be accomplished during the progress of the Work.
4-3 INSPECTION
4-3.1 General
ADD the following:
1. All costs of inspection at the source, including salaries and mileage costs, shall be paid by the Contractor.
■■
01 11 20 MEASUREMENT AND PAYMENT Date Printed: November 8, 2023 Document Version: 1.0 Current Update: October 2022