CA Review GH
Meeting Date: Feb. 6, 2024
To: Mayor and City Council
From: Scott Chadwick, City Manager
Staff Contacts: Dave Padilla, Utilities Assistant Director [email protected], 442-339-2356
Daniel Zimny, Senior Engineer
[email protected], 442-339-2233
Subject: Approval of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the Poinsettia Lift Station Generator Replacement Project
District: 2
Rec
ommended Action
Adopt a resolution approving the plans, specifications and contract documents and authorizing the City Clerk to advertise for bids for the Poinsettia Lift Station Generator Replacement Project.
Executive Summary
The backup generator at the Poinsettia Lift Station is at the end of its service life and requires replacement to ensure the station’s operability in the event of a power outage. A reliable supply of electricity is needed at the lift station to pump wastewater flows uphill and to the wastewater treatment plant. Power outages without generator backup could result in wastewater spills. The total construction cost estimate including contingency, construction management and staff costs is $905,000.
City Council approval of these plans, specifications and contract documents is required under Carlsbad Municipal Code Section 3.28.080(E) because the expected value of work is more than $200,000.
Staff recommend that the City Council approve the project plans, specifications and contract documents and authorize the City Clerk to advertise and receive construction bids.
Explanation & Analysis
The city operates 12 sewer lift stations that pump wastewater flow uphill and to higher elevations and are equipped with emergency generators to provide a backup power source to the pumping system during power outages.
Feb. 6, 2024
Item #2 Page 1 of 7
The emergency backup generator at the Poinsettia Lift Station was installed in 1999 and is the second largest generator of the lift station sites operated by the city. The generator is at the end of its service life and needs replacement. The scope of the project includes:
• Replacement of the existing 250-kilowatt diesel-fueled generator • Associated power system controls and communication upgrades • Upgrades to the generator housing structure to achieve compliance with current building and fire codes
Staff recommend that the City Council approve the plans, specifications and contract documents and authorize the City Clerk to advertise for construction bids for the project.
Fiscal An
alysis
The project is a component of the Sewer Lift Station Repairs and Upgrades Program, Capital Improvement Program Project No. 3840, which is funded by the city’s sewer replacement fund.
Sufficient funds are available to complete the project. Available funds and estimated construction costs to complete the project are presented in the table below:
Sewer Lift Station Repairs and Upgrade Program
Capital Improvement Program Project No. 3840
Total appropriation to date $4,535,380
Total expenditures/encumbrances to date -$3,143,659
Total available balance $1,391,721
Poinsettia Lift Station Generator Replacement
Capital Improvement Program Project No. 3840-23
Construction contract (engineer’s estimate) -$615,000
Construction contingency (estimated) -$120,000
Construction management, inspection and testing (estimated) -$120,000 Staff time and engineering construction services -$50,000 Total estimated construction costs -$905,000
Remaining balance $486,721
Next Steps
With the City Council’s approval, the City Clerk will advertise a request for bids for the project.
Staff will then evaluate the bids received and identify the lowest responsive and responsible bidder. Staff will then return to the City Council with a recommendation to award a construction contract to the identified lowest responsible and responsive bidder, which is expected to be in spring 2024.
Environmental E
valuation
The City Planner has determined the project is exempt from the California Environmental Quality Act under CEQA Guidelines Section 15302(c), which applies to the replacement or reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity.
Feb. 6, 2024
Item #2 Page 2 of 7
Exhibits
1. City Council resolution
2. Location map
3. Plans, specifications and contract documents ( on file in the Office of the City Clerk) Feb. 6, 2024
Item #2 Page 3 of 7
RESOLUTION NO. 2024-019
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE PLANS, SPECIFICATIONS AND CONTRACT
DOCUMENTS AND AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS
FOR THE POINSETTIA LIFT STATION GENERATOR REPLACEMENT PROJECT WHEREAS, the City Council of the City of Carlsbad, California has determined it necessary, desirable and in the public interest to replace the emergency backup generator at the Poinsettia Lift Station; and
WHEREAS, the plans, specifications and contract documents for the Poinsettia Lift Station Generator Replacement Project, Capital Improvement Program Project No. 3840-23, have been prepared, are on file at the City Clerk's office and are incorporated by reference; and WHEREAS, Carlsbad Municipal Code Section 3.28.080(E) requires City Council approval of plans, specifications and contract documents for all construction projects that are to be formally bid upon when the value exceeds $200,000; and
WHEREAS, the cost of the project is estimated to be $905,000, including construction contingency, construction management and staff costs; and WHEREAS, the City Planner has determined that the project is exempt from the California Environmental Quality Act, or CEQA, per CEQA Guidelines Section 15302(c) - replacement or reconstruction of existing structures and/or facilities involving negligible or no expansion of capacity.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the plans, specifications and contract documents for the Poinsettia Lift Station Generator Replacement Project, Capital Improvement Program Project No. 3840-23, are approved and are on file at the City Clerk's Office.
3. That the City Clerk is hereby authorized and directed to publish, in accordance with state law and Carlsbad Municipal Code Section 3.28.0S0(C), a notice to contractors inviting bids for construction of the project in accordance with plans, specifications and contract documents referred to herein.
Exhibit 1
Feb. 6, 2024 Item #2 Page 4 of 7
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 6th day of February, 2024, by the following vote, to wit:
AYES:
NAYS:
Blackburn, Bhat-Patel, Acosta, Burkholder.
None.
ABSTAIN: None.
ABSENT: Luna.
KEITH BLACKBURN, Mayor
SHERRY FREISINGER, City Clerk
{SEAL)
Feb. 6, 2024 Item #2 Page 5 of 7
5503-142
POINSETTIA
LN.
EL
CAMINO
REAL
ALICANTE
RD.
EL
FUERTE
ST.
ALGA
RD.
ESTRELLA
DE
MAR
RD.
MELROSE
DR.
UNICORNIO ST.
QUARTZLN.
GEODE LN.
MICA RD.
HALITE
PL.
SITE
SITE
MAIN
FORCE
3840-12
POINSETTIA LIFT STATION
GENERATOR REPLACEMENT PROJECT
Exhibit 2
Feb. 6, 2024
Item #2 Page 6 of 7
Exhibit 3
Plans, Specifications & Contract Documents
(on file in the Office of the City Clerk)
Feb. 6, 2024
Item #2 Page 7 of 7
Revised 6/12/18 Contract No. 3840-23 Page 1 of 134
City of Carlsbad
San Diego County
California
CONTRACT DOCUMENTS,
GENERAL PROVISIONS, SUPPLEMENTAL
PROVISIONS, AND TECHNICAL SPECIFICATIONS
FOR
POINSETTIA LIFT STATION
GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
BID NO. PWS24-2361
Revised 6/12/18 Contract No. 3840-23 Page 2 of 134
TABLE OF CONTENTS
Item Page
Notice Inviting Bids ................................ ................................ ................................ ..................... 7
Contractor's Proposal ................................ ................................ ................................ ................ 14
Listing of Manufacturers ................................ ................................ ................................ ............ 18
Bid Security Form ................................ ................................ ................................ ..................... 19
Bidder’s Bond to Accompany Proposal ................................ ................................ ..................... 20
Guide for Completing the “Designation of Subcontractors” Form ................................ .............. 21
Designation of Subcontractor and Amount of Subcontractor’s Bid Items ................................ .. 23
Bidder's Statement of Technical Ability and Experience ................................ ............................ 24
Bidder’s Certificate of Insurance for General Liability, Employers’ Liability, Automotive Liability and Workers’ Compensation ................................ ................................ ........................ 25
Bidder’s Statement Re Debarment ................................ ................................ ............................ 26
Bidder's Disclosure of Discipline Record …………………………………………… ...................... 27
Noncollusion Declaration to Be Executed by Bidder and Submitted with Bid ............................. 29
Contract Public Works ................................ ................................ ................................ ............... 30
Labor and Materials Bond ................................ ................................ ................................ ......... 37
Faithful Performance/Warranty Bond ................................ ................................ ........................ 39
Optional Escrow Agreement for Surety Deposits in Lieu of Retention ................................ ....... 41
Revised 6/12/18 Contract No. 3840-23 Page 3 of 134
GENERAL PROVISIONS
Section 1 Terms, Definitions Abbreviations and Symbols
1-1 Terms ................................ .......................... ................................ ..................... 44 1-2 Definitions ................................ .................... ................................ ..................... 44 1-3 Abbreviations ................................ ............... ................................ ..................... 50 1-4 Units of Measure ................................ .......... ................................ ..................... 53 1-5 Symbols ................................ ....................... ................................ ..................... 54
Section 2 Scope and Control of The Work
2-1 Award and Execution of Contract ................. ................................ ..................... 55 2-2 Assignment ................................ .................. ................................ ..................... 55 2-3 Subcontracts ................................ ................ ................................ ..................... 55 2-4 Contract Bonds ................................ ............ ................................ ..................... 56 2-5 Plans and Specifications .............................. ................................ ..................... 57 2-6 Work to be Done ................................ .......... ................................ ..................... 61 2-7 Subsurface Data ................................ .......... ................................ ..................... 62 2-8 Right-of-Way ................................ ................ ................................ ..................... 62 2-9 Surveying ................................ ..................... ................................ ..................... 62 2-10 Authority of Board and Engineer .................. ................................ ..................... 63 2-11 Inspection ................................ .................... ................................ ..................... 64
Section 3 Changes in Work
3-1 Changes Requested by the Contractor ........ ................................ ..................... 65 3-2 Changes Initiated by the Agency .................. ................................ ..................... 65 3-3 Extra Work ................................ ................... ................................ ..................... 66 3-4 Changed Conditions ................................ .... ................................ ..................... 69 3-5 Disputed Work ................................ ............. ................................ ..................... 70
Section 4 Control of Materials
4-1 Materials and Workmanship ......................... ................................ ..................... 76 4-2 Materials Transportation, Handling and Storage ................................ ................ 80
Section 5 Utilities
5-1 Location ................................ ....................... ................................ ..................... 81 5-2 Protection ................................ .................... ................................ ..................... 81 5-3 Removal ................................ ...................... ................................ ..................... 82 5-4 Relocation ................................ .................... ................................ ..................... 82 5-5 Delays ................................ .......................... ................................ ..................... 83 5-6 Cooperation ................................ ................. ................................ ..................... 83
Section 6 Prosecution, Progress and Acceptance of the Work 6-1 Construction Schedule and Commencement of Work ................................ ........ 84 6-2 Prosecution of Work ................................ ..... ................................ ..................... 86 6-3 Suspension of Work ................................ ..... ................................ ..................... 88 6-4 Default by Contractor ................................ ... ................................ ..................... 89 6-5 Termination of Contract................................ ................................ ..................... 90 6-6 Delays and Extensions of Time .................... ................................ ..................... 90 6-7 Time of Completion ................................ ...... ................................ ..................... 91 6-8 Completion, Acceptance, and Warranty ....... ................................ ..................... 92 6-9 Liquidated Damages ................................ .... ................................ ..................... 93 Revised 6/12/18 Contract No. 3840-23 Page 4 of 134
6-10 Use of Improvement During Construction .... ................................ ..................... 93
Section 7 Responsibilities of the Contractor
7-1 Contractor’s Equipment and Facilities .......... ................................ ..................... 95 7-2 Labor ................................ ........................... ................................ ..................... 95 7-3 Liability Insurance ................................ ........ ................................ ..................... 95 7-4 Workers' Compensation Insurance .............. ................................ ..................... 95 7-5 Permits ................................ ........................ ................................ ..................... 96 7-6 The Contractor’s Representative .................. ................................ ..................... 97 7-7 Cooperation and Collateral Work ................. ................................ ..................... 98 7-8 Project Site Maintenance ............................. ................................ ..................... 99 7-9 Protection and Restoration of Existing Improvements ................................ ...... 101 7-10 Public Convenience and Safety ................... ................................ ................... 102 7-11 Patent Fees or Royalties .............................. ................................ ................... 110 7-12 Advertising ................................ ................... ................................ ................... 110 7-13 Laws to be Observed ................................ ... ................................ ................... 110 7-14 Antitrust Claims ................................ ............ ................................ ................... 110
Section 8 Facilities for Agency Personnel
8-1 General ................................ ........................ ................................ ................... 111
Section 9 Measurement and Payment
9-1 Measurement of Quantities for Unit Price Work ................................ ............... 112 9-2 Lump Sum Work ................................ .......... ................................ ................... 112 9-3 Payment ................................ ...................... ................................ ................... 112 9-4 Bid Items ................................ ...................... ................................ ................... 116
SUPPLEMENTAL PROVISIONS TO PART 2, 3, 4 AND 6 OF THE SSPWC
Part 2 Construction Materials
Section 200 Rock Materials
200-2 Untreated Base Materials ............................. ................................ ................... 118
Section 201 Concrete, Mortar and Related Materials
201-1 Portland Cement Concrete .......................... ................................ ................... 118
Section 203 Bituminous Materials
203-6 Asphalt Concrete ................................ ......... ................................ ................... 119
Section 213 Engineering Fabrics
213-5 Geotextiles and Geogrids ............................. ................................ ................... 120
Part 3 Construction Methods
Section 300 Earthwork
300-2 Unclassified Excavation ................................ ................................ ................... 121 300-12 Storm Water Pollution Prevention Plan ................................ ............................ 121
Section 301 Treated Soil, Subgrade Preparation and Placement of Base Materials 301-1 Subgrade Preparation ................................ ................................ ...................... 124
Section 302 Roadway Surfacing
302-5 Asphalt Concrete Pavement ................................ ................................ ............ 124 302-15 Public Convenience and Traffic Control ................................ ........................... 125 Revised 6/12/18 Contract No. 3840-23 Page 5 of 134
Section 303 Concrete and Masonry Construction.
303-1 Concrete Structures ................................ ................................ ......................... 126 303-5 Concrete Curbs, Walks, Gutters, Cross Gutters, Alley Intersections, Access Ramps, And Driveways ................................ ................................ ....... 126
Section 306 Underground Conduit Construction
306-3 Open Trench Operations ................................ ................................ .................. 127 306-12 Backfill ................................ ................................ ................................ ............. 128 306-13 Trench Resurfacing ................................ ................................ .......................... 128
Part 4 Existing Improvements
Section 400 Protection and Restoration
400-1 General ................................ ................................ ................................ ............ 129 400-2 Permanent Survey Markers ................................ ................................ ............. 129 400-3 Payment ................................ ................................ ................................ .......... 129
Section 401 Removal
401-3 Concrete and Masonry Improvements ................................ ............................. 129
Part 6 Temporary Traffic Control
Section 601 Temporary Traffic Control for Construction and Maintenance Work Zones 601-1 General ................................ ................................ ................................ ............ 130 601-3 Temporary Traffic Control (TTC) Zone Devices ................................ ............... 130 601-4 Temporary Traffic Striping and Pavement Markings ................................ ......... 134 Revised 6/12/18 Contract No. 3840-23 Page 6 of 134
TECHNICAL SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
01190 Structural Design Requirements
01650 Facility Commissioning, Testing and Startup
01700 Contract Closeout
DIVISION 2 – SITE WORK
02050 Demolition
02223 Earthwork
02516 Disinfection
02700 Paving and Surfacing
DIVISION 10 – SPECIALTIES
10200 Louvers
10400 Identifying Devices
DIVISION 15 - MECHANICAL
15050 Piping, Valves, and Accessories
15800 Heating, Ventilating, and Air Conditioning Air Distribution
DIVISION 16 – ELECTRICAL
16010 General Electrical Requirements
16110 Electrical Raceway Systems
16120 Low Voltage Wire and Cable
16124 Signal Cable
16205 Standby Diesel Engine-Generator Sets
16250 Automatic and Manual Transfer Switches
16402 Underground Electrical Work
16450 Electrical Grounding
16950 Electrical Test
16961 Power System Studies
APPENDICES
A - Building Permit Application Template
B - Station As-Built Drawings for Reference Only
C - CARB Fleet Compliance Certification
Revised 6/12/18 Contract No. 3840-23 Page 7 of 134
CITY OF CARLSBAD, CALIFORNIA
NOTICE INVITING BIDS
Until 11 a.m. on March 14, 2024, the City shall accept bids via electronic format via the City of Carlsbad Electronic Bidding Site , PlanetBids, which may be acc essed at https://www.carlsbadca.gov/departments/finance/contracting-purchasing, f or performi ng the work as follows: replacement of a 250 kilowatt standby diesel engine -generator set and associated electrical and control system improvements at the Poinsettia Sewer Lift Station.
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
PWS24-2361UTIL
ELECTRONIC FO RMAT RECEIPT AND OPENING OF BIDS: Bids will be received in electronic format (eBi ds) EXCL USIVELY at the City o f Carlsbad ’s electronic bidding (eBidding) site, at: Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) and are due by the date and time shown on the cover of this solicitation.
BIDDERS MUST BE PR E-REGISTERED with the Ci ty’s bidding system and posse ss a system-assigned Digital ID in order to submit an electronic bid.
The City’s electronic bidding (eBidding) system will automatically track information submitted to the site including IP addresses, browsers being used and the URLs from which information was submitted. In addition, the Cit y’s bidding system will keep a history of every log in instance including the time of lo gin, and other information about the use r's computer configuration such as the operating system, browser type, version, an d more. Because of these security features, Bidders who disable their browsers’ cookies will not be able to log in and use the City’s bidding system.
The City ’s electronic b idding system is responsible for bid ta bulations. Upon the bidd er’s or proposer’s entry of t heir b id, the system will ensure that all required fields ar e entered. The system will n ot accept a bid for which any requir ed i nformation is missing. This includes all necessary pricing, subcontractor l isting(s) and any other essential documenta tion and supporting materials and forms requested or contained in these solicitation documents.
BIDS REMAIN SEALED UNTIL DUE DATE AND TIME
eBids are transmitted into the City’s bidding system via hypertext transfer protocol secure (https) mechanism using SSL 128 -256-bit security certificates issued f rom Verisign/Thawte whi ch encrypts data being transferred from client to server. Bids s ubmitted prior to the Due Date and Time are not available for review by anyone other than the submitter , who will have unt il the Due Date and Time to change, rescind or retrieve its bid should they desire to do so.
BIDS MUST BE SUBMITTED BY DUE DATE AND TIME
Once the dea dline is reached, no fur ther submissions are accepted into the system. Once the Due Date and Time has pas sed, bidders, proposers, the general public, an d City staff are able to immediately see the result s online. City staff may then begin reviewing the submissions for responsiveness, compliance and other issues.
Revised 6/12/18 Contract No. 3840-23 Page 8 of 134
RECAPITULATION OF THE WORK
Bids shall not contain any recapitulation of the Work. Conditional Bids may be rejected as being non-responsive. Alternative proposals will not be considered unless called for.
BIDS MAY BE WITHDRAWN by the Bidder prior to, but not after, the time set as Due Date and Time.
Important Note: Submission of the electronic b id into the system may not be instantan eous.
Due to the speed and capabilities of the u ser’s internet service pr ovider (ISP), ba ndwidth, computer hardware and other v ariables, it may take ti me for the bidder’s submission to u pload and be received by the Ci ty’s eBidding system. I t is the bidder’ s sole respo nsibility to ensure their bids are r eceived on time b y the Ci ty’s eBidding sy stem. The City of Carlsbad is not responsible for bids that do not arrive by the Due Date and Time.
ELECTRONIC SUBMISSIONS CARRY FULL FORCE AND EFFECT
The Bidder , by submitting their electronic proposal, agrees to and certifies under pena lty of perjury under the laws of the State of Californ ia, that the certificati on, forms and affid avits submitted as part of this proposal are tr ue and c orrect. The bid der, by subm itting its electronic bid, acknowledges that doing s o ca rries the sam e force and full legal effect as a paper submission with a longhand (wet) signature. By submitting an electronic bid, the bidder certifies that the bidd er has thoroughly exami ned and unde rstands the entire Contract Documents (which consist of the plans and specifications, drawings, fo rms, affidavits and the solicitat ion documents), and that by submitting the eBid as it s bid proposal, the bidder acknowledg es, agrees to and is bo und by the e ntire Contract Documents, including any addenda issu ed thereto, and incorporated by reference in the Contract Documents.
BIDS ARE PUBLIC RECORDS
Upon receipt by the City, bi ds shall become public records subject to publi c disclosure. It is the responsibility of the Bidder to clearly identify any confidenti al, proprietary, trade se cret o r otherwise legally privileged information conta ined within the proposal ’s General referenc es to sections o f the California Public Records Act (PR A) will not suf fice. If the Bidder does not provide applicable case law that cl early establishes that th e requested information is exempt from the disclosure requirements of the PRA, the City shall be free to re lease the information when required in accordance with the PRA, pursuant to any other applicable law, or by order of any court or government agency, and the Bidder agrees to hold the City harmless for an y such release of this information.
INSTRUCTIONS TO BIDDERS AND BID REQUIREMENTS
This bid and the terms of the C ontract Docu ments and General Provisions constitute an irrevocable o ffer that sha ll rem ain valid and in full f orce for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder.
No bid will be r eceived unless it is made on a proposal fo rm furnis hed by the Purchasing Department. Each bid must be accompanied by security in a form and amount required by law.
The bidder's security of t he second and third next lowest responsive bidd ers may be withheld until the Contract has been fully execute d. The se curity submitted by all other unsu ccessful bidders shall be ret urned to them, o r deemed void, within ten (10) days after the Contract is awarded. Pursuant to the provisions of law (Publi c Contract Code sec tion 10263), appropriate securities may be substituted for any obligation required by this notice o r for any monie s withheld by th e City to ensure performance under this C ontract. Section 10 263 of the Public Contract Code requires monies or securities to be deposited with the City or a state or federally Revised 6/12/18 Contract No. 3840-23 Page 9 of 134
chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and o missions of the age nt in conn ection with the handling of retention s under this section in an amount not less than $100,000 per contract.
The City of Carlsbad may disqualify a contract or or subcontractor from participating in bidding when a contractor or s ubcontractor has be en debarre d by t he City of Carlsba d or another jurisdiction in the State of California as an irresponsible bidder.
The work shall be performed in strict conformity with the plans, provisions, and specifications as approved by the City C ouncil of the City of Carlsbad on f ile with t he City Clerk’s Offic e. The specifications f or th e wo rk inc lude City of Carlsbad Technical Specifications and the 2021 Standard Specifications for Public Works Construction, Parts 2 - 8, all hereinafter designated “SSPWC”, as amended. Specification Reference is hereby made to the plans and specifications for full particulars and de scription of the work. The General Provisi ons (Part 1 ) to the SSPWC do not apply.
The City of Carlsbad encourages the participation of minority and women-owned businesses.
The City of Carlsbad encourages all bidders, sup pliers, manufacturers, fabricators and contractors to ut ilize recycled and r ecyclable m aterials when available, appr opriate and approved by the Engineer.
BID DOCUMENTS
The bid documents comprise the fo llowing documents which must be completed and properly executed including notarization, where indicated.
1. Contractor's Proposal
2. Bidder's Bond ( at time of Bid submit PDF copy via PlanetBids / All Bidders). Bid B ond (Original) within two (2) business days of bid Opening / three (3) Apparent Low Bidders.
3. Noncollusion Declaration
4. Designation of Subcontractor and Amount of Subcontractor’s Bid
5. Bidder's Statement of Technical Ability and Experience
6. Acknowledgement of Addendum(a)
7. Certificate o f Insu rance. The riders coverin g th e City, its officia ls, employees and volunteers may be omitted at the time of bi d submittal but shall be p rovided by the Bidder prior to award of this contract.
8. Bidder’s Statement Re Debarment
9. Bidder's Disclosure of Discipline Record
10. CARB Fleet Compliance Certification (Appendix C)
11. Escrow Agreement for Security D eposits - (optional, must be completed if the Bidder wishes to use the Escrow Agreement for Security)
BIDDER’S GUARANTEE OF GOOD FAITH (BID SECURITY)
At the time of bid sub mission, bidders mu st upload and submit an electronic PDF copy of the aforementioned bid security. Whether in the form of a cashier's check, a properly certified check or an approved corporate surety bond payable to the City of Carlsbad, the bid security m ust be uploaded to the City’s eBidding system. Within two (2) business days after the bid opening date, the first three (3) apparent low bidders must provide the City with the original bid security.
Failure to submit the electro nic version of the bid security at time of bid sub mission shall cause the bid to be rejected and deemed non-responsive. Only the three (3) apparent low bidders are Revised 6/12/18 Contract No. 3840-23 Page 10 of 134
required to submit original bid security to the City within two (2) business days after bid opening date. Failure to provide th e original within t wo (2) bus iness days may deem t he bidder non- responsive.
ENGINEER’S ESTIMATE
All bids will be compared on the basis of the Eng ineer's Estimate. The estimated quantities are approximate and serve solely as a basis for the comparison of b ids. The Engineer's Estimate is $615,000.
TIME OF COMPLETION
The Contractor shall complete the Work within the time set in the cont ract as def ined in the General Provisions Section 6-7.
SPECIALTY CONTRACTORS:
ACCEPTABLE LICENSE TYPES
Except as provided herein a bid submitted to the City by a Contractor who is not l icensed as a contractor pursuant to the Business and P rofessions Code shall be considered nonres ponsive and shall be rejected by the City. In all contracts w here federal funds are involved, no bid submitted shall be inv alidated by the failure of the bidder to be licen sed in accorda nce with California law. Where federal funds are involved the contractor shall be properly licensed at the time the contract is awa rded. In all other cases the cont ractor shall state the ir license number, expiration date and class ification in the proposal, under penalty of perjury. This invitation to bid does not use federal funds. The following classifications are acceptable for this contract: A - General Engineering or C-10 - Electrical.
ESCROW AGREEMENT
If the Contractor intends to utilize the esc row agreement included in the contract documents i n lieu of the usual 5% retention from each pay ment, these documents must be completed and submitted with th e signed contract. The escrow agreement may not be subs tituted at a later date.
OBTAINING PLANS AND SPECIFICATIONS
Sets of plans, various supplemental provisions, and Contract documents may be obtained from the City of Carlsbad website at https://www.carlsbadca.gov/departments/finance/contracting- purchasing Paper copies will not be sold.
INTENT OF PLANS AND SPECIFICATIONS
Any prospective bidder who is in doubt as to the intended meaning of any part of the drawings, specifications or o ther contract documents, or finds discrepancies in or omissi ons from the drawings a nd specifications may s ubmit to th e Engineer a written r equest for clarification or correction. Any response will be made only by a written addendum duly issued by the Engineer a copy of which will be mailed or deli vered to each pers on receiving a set of t he contract documents. No oral response will be made to such inquiry. Prior to the award of the contract, no addition to, modificati on o f or int erpretation of any provision in the contract documents will be given by any agent, employee or contractor of the City of Carlsbad except as herein before specified. No bidder may rely on di rections given by any agent, employee or contractor of the City of Carlsbad except as hereinbefore specified.
BIDDER’S INQUIRIES
Questions on the bid docume nts during t he bid period shall be submit ted in writing, via the eBidding website.
Revised 6/12/18 Contract No. 3840-23 Page 11 of 134
Questions shall be d efinite and certain and sh all reference a pplicable drawing shee ts, notes, details or specification sheets.
The cutoff date to sub mit questions is February 28, 2024, at 5 p.m. No questions will be entertained after that date.
The answers to questions submitted during the bidding period will be published in an addendum and provided to those bidding on the project no later than March 4, 2024.
REJECTION OF BIDS
The City o f Carlsbad reserves th e right to r eject any or all bids and to waive any minor irregularity or informality in such bids.
PREVAILING WAGE TO BE PAID
The general prevailing rat e of wages f or each craft or ty pe o f worker needed to execute t he Contract shall be those as determined by the Director of Industrial Relations pursua nt to the sections 1770, 1773, and 1 773.1 of the Labor Code. Pursuant to sec tion 1773.2 of the Labor Code, a current copy of applicable w age rates is on file in the Office of the City Engineer. The Contractor to whom the Contract is awarded shall not pay less than the said specified prevailing rates of wages to all workers employed by him or her in the execution of the Contract.
The Prime Contractor shall be responsible for insuri ng compl iance with provisions of section 1777.5 of the Labor Code and section 4100 et s eq. of the Public Contract s Code, "Subletting and Subcontracting Fair Practices Act." The City E ngineer is the City’s "duly authorized officer" for the purposes of section 4107 and 4107.5.
The provisions of Part 7, Chapter 1, of the Labor Code c ommencing with se ction 1720 shall apply to the Contract for work.
A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the perform ance of any contract for public work , unless currently registered and q ualified to perform public work pursuant to Section 1725.5. This project is sub ject to compliance monitoring and enforcement by the Department of Industrial Relations.
The Prime Contractor and all subcontractors shall comply with Section 1776 of the Labor Code, which g enerally requires keeping accura te payroll re cords, verifying and cert ifying payrol l records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776.
CALIFORNIA AIR RESOURCES BOARD (CARB) ADVANCED CLEAN FLEETS
REGULATIONS
Contractor’s vehicles with a gross vehicle we ight rating greater than 8,500 lbs. and light -duty package delivery vehicles operated in California may be subject to the California Air Resources Board (CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, please see Appendix C and visit the CARB Advanced Clean Fleets webpage at https://ww2.arb.ca.gov/our- work/programs/advanced-clean-fleets.
Revised 6/12/18 Contract No. 3840-23 Page 12 of 134
MANDATORY PRE BID MEETING
A mandatory Pre-Bid Meeting will be held at the project site at the below address on February 21, 2024 at 10:00 a.m.
Address: 2351 Geode Lane, Carlsbad CA 92009
Bidders will be provided access to the facility and portions of the site subject to improvement.
Representatives of the Agency will be present. Questions asked by Bidders at the Pre -Bid Meeting not specifically addressed within the Contract Documents shall be answered in writing and shall be sent to all Bidders present at the Pre -Bid Meeting and be posted on the online bidding portal. Bids will not be accepted from any bidder who di d not attend the mandatory Pre- Bid Meeting.
UNIT PRICES AND COMPUTATION OF BIDS
All bids are to be computed on the basis of the given estimated quantities of work, as indicated in this proposal, times the unit price as submitted by the bidder.
ADDENDA
Bidders are advise d to v erify the issuance of all addenda and receipt thereof on e day prior to bidd ing. Submission of bids without acknowledgment of addenda ma y be cause of rejection of bid.
BOND AND INSURANCE REQUIREMENTS
The Contractor shall p rovide bonds to secure faithful pe rformance and warranty of the wor k in an amount equal to one h undred percen t (100 %) of th e Contract pri ce on this project. The Contractor shall provide bonds to secure payment of laborers and materi als suppliers, in an amount equal to one hundred per cent (100%) of the total amount payable by the terms of the contract. These bonds shall be kept in full force and effect during the course of this project and shall extend in full force and effect and be retained by the City until they are released as stated Revised 6/12/18 Contract No. 3840-23 Page 13 of 134
February 7, 2024
in the General Provisions section o f this contract. A ll bonds ar e to be p laced with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed the ir liabilities in an amount equal to o r in excess of the amount of the bond. The bonds are to be accompanied by the following documents:
1. An or iginal, or a certified copy, of t he u nrevoked appo intment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
2. A cert ified copy of the cert ificate of author ity of th e insur er issued by the ins urance commissioner.
If the bid is accepted, the City may require copies of the insurer's most recent annual statement and quarterly statement filed wi th the Depa rtment of Insurance pursuant to Arti cle 10 (commencing wi th se ction 9 00) of Chapter 1 of P art 2 of Division 1 of the Insur ance Cod e, within 10 calendar days of the insurer's receipt of a request to submit the statements.
Insurance is to be placed with insurers that:
1. Have a rating in the most recent Best's Key Rating Guide of at least A-:VII
2. Are a dmitted and authorize d to tra nsact th e busines s of insurance in the State of California by the Insurance Commissioner.
Auto policies offered to meet the specification of this contract must:
1. Meet the conditions stated above for all insurance companies.
2. Cover any vehicle used in the pe rformance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.
Workers' compensation insurance re quired under this contract mu st be offered by a company meeting the above standards wit h the exception that the Best's rating condition is waived. The City does accept policies issued by the State Co mpensation Fund meeting the r equirement for workers' compensation insurance.
The Cont ractor s hall be req uired to m aintain insurance as specified i n the Contra ct. A ny additional cost of said insurance shall be included in the bid price.
The award of the contract by the City is contingent upon the Contractor sub mitting the required bonds and in surance, as des cribed in the con tract, within twenty days of bid open ing. If th e Contractor fails to comply with these requirements, the City may award the contract t o the second or third lowest bidder and the bid security of the lowest bidder may be forfeited.
BUSINESS LICENSE
The prime contractor and all subcontractors are required to h ave and maintain a valid City of Carlsbad Business License for the duration of the contract.
Approved by the City Council of the City of Carlsbad, California, by Re solution No. 2024-XXX, adopted on the 6th day of February 2024.
Date Graham Jordan, Deputy Clerk
Revised 6/12/18 Contract No. 3840-23 Page 14 of 134
CITY OF CARLSBAD
LIFT STATION IMPROVEMENT PROGRAM
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
CONTRACTOR'S PROPOSAL
City Council
City of Carlsbad
1200 Carlsbad Village Drive
Carlsbad, California 92008
The undersigned declares h e/she h as care fully exam ined the location of the work, read t he Notice Inviting Bids, examined the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto, and here by proposes to furn ish all labo r, m aterials, equipment, transportation, and ser vices required to do all the work to complete C ontract No. 3840-23 in accordance with the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto and that he/she will take in full payment therefore the following unit prices for each item complete, to wit (refer to Section 9-4 for bid item descriptions):
SCHEDULE “A”
Item
No. Description
Approximate
Quantity
And Unit
Unit Price
(Figures)
Total Amount
(Figures)
1 Mobilization and Preparatory
Work (not to exceed 5% of
Total Bid)
LS $___________
2 Permitting and Design Services LS $___________
3 Furnish and Install Temporary
Back Up Generator
LS $___________
4 Demolition LS $___________
5 Furnish and Install Automatic
and Manual Transfer Switches
LS $___________
6 Furnish and Install Generator
Set (250-kW)
LS $___________
7 Building and Site
Improvements
LS $___________
Revised 6/12/18 Contract No. 3840-23 Page 15 of 134
Total amount of bid (in figures) for Schedule “A”: $
Total amount of bid (in words) for Schedule “A”:
The City shall determine the low bid based on the sum of Schedule “A”.
Price(s) given above are firm for 90 days after the date of bid opening.
Addendum(a) No(s). ___________________ has/have been received and is/are included in this proposal.
The Undersigned has carefully checked all of the above figur es and understands that the City will not be responsible for any error or omission on the part of the Undersigned in preparing this bid.
The Undersigned agrees that in case of defau lt in execut ing th e required Contr act with necessary bonds and insurance p olicies within twe nty (20) days from the date of a ward of Contract by the City Council of the City of Carlsba d, the City may administratively auth orize award of the con tract to the second or third lowest bidder and t he bid security o f the lowest bidder may be forfeited.
The Undersigned bidder declares, under penalty of pe rjury, that the undersigned is licensed t o do business or act in the capacity of a contractor within the State of California, validly licensed under license number _________________________, classification ________________ which expires on _____________________, and Department of Industrial Relations PWC registration number ___________________________________ which expires on ____________________, and that this statement is true and correct and has the legal effect of an affidavit.
A bid submitted to th e City by a Contractor who is not licensed as a co ntractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the City § 7028.15(e). In all co ntracts where federal funds are involved, no bid submitted s hall be invalidated by the failure of the bidder t o b e licensed in accordance wit h Cali fornia l aw.
However, at the time the contract is awarded, the contractor shall be properly licensed.
The Undersigned bidder hereby represents as follows:
1. That no Council member, officer agent, or employee of the City of Carlsbad is personally interested, directly or indirectly, in this Contract, or the compensation to be paid hereunder; that no representation, oral or in writing, of th e City Council, its office rs, agents, or employees has inducted him /her to enter into this Con tract, ex cepting on ly those c ontained in this f orm of Contract and the papers made a part hereof by its terms; and
2. That this bid is made without connection with any person, firm, or co rporation making a bid for the same work, and is in all respects fair and without collusion or fraud.
Accompanying this proposa l is _______ _______________________ (Cash, Certified Chec k, Bond or Cashier's Check) for ten percent (10%) of the amount bid.
Revised 6/12/18 Contract No. 3840-23 Page 16 of 134
The Undersigned is aware of the provisions of section 370 0 of the Labo r Code which requires every employer to be insured against liability for workers' c ompensation or t o undertake self - insurance in accorda nce wi th t he provisions o f that code and agrees to comply with suc h provisions before commencing the perfo rmance of the work of this Contr act and continue to comply until the contract is complete.
The Undersigned is aw are of the provi sions of the Labor Code, P art 7, Chapter 1, Article 2 , relative to the g eneral prevailing r ate of wages for each craft or type of worker nee ded to execute the Contract and agrees to comply with its provisions.
IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:
(1) Name under which business is conducted _____________________________________
(2) Signature (given and surname) of proprietor ____________________________________
(3) Place of Business ________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
IF A PARTNERSHIP, SIGN HERE:
(1) Name under which business is conducted _______________________________________
(2) Signature (given and surname and character of partner) (Note: Signature must be made by a general partner)
_________________________________________________________________________
_________________________________________________________________________
(3) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
Revised 6/12/18 Contract No. 3840-23 Page 17 of 134
IF A CORPORATION, SIGN HERE:
(1) Name under which business is conducted _______________________________________
__________________________________________________________________________
(2) _________________________________________________________________________ (Signature)
____________________________________________________________________________ (Title)
Impress Corporate Seal here
(3) Incorporated under the laws of the State of _______________________________________
(4) Place of Business ________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(5) Zip Code _____________________ Telephone No. _______________________________
(6) E-Mail ___________________________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE
ATTACHED
List below nam es of president, vice president, secre tary and a ssistant secretary, i f a corporation; if a partnership, list names of all general partners, and managing partners:
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________ Revised 6/12/18 Contract No. 3840-23 Page 18 of 134
LISTING OF MANUFACTURERS
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
The Contractor shall submit this completed form with the bid to identify the products, equipment, or materials and their manufacturers proposed for use in the Work. If the Contractor elects to list products, equipment, or materials not li sted in the Specifications, the Contractor shall provide substantiating data to demon strate that the substitute products, equipment, or materials are of equal quality, durability, functional character, and efficiency as determined by the Engineer .
Only one manufacturer shall be listed for each item.
Item or Material Manufacturer
250 Kw Generator Set (Section 16205)
Automatic and Manual Transfer Switches
(Section16250)
Substitutions for products, equipment, or materials listed above shall be al lowed only if submitted for approval at least two weeks prior to the Bid Due Date or, for products, equipment, or materials not listed above, in accordance with Article 4 -1.6 of th e General Provisions and within 35 calendar days following Contract award.
Revised 6/12/18 Contract No. 3840-23 Page 19 of 134
BID SECURITY FORM
(Check to Accompany Bid)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
(NOTE: The following form shall be used if check accompanies bid.)
Accompanying this proposal is a *Certified * Cashier’s check payable to th e order of City o f Carlsbad, in the s um of _______________________________________ dollars ($________________), this amount being ten percent (10%) of the total amount of the bid. The proceeds of this check shall become the property of the City provided this pro posal shal l be accepted by t he City through action of its legally constituted c ontracting auth orities and the undersigned shall fail to execute a contract and furnish the required Performance, Warranty and Payment B onds and proof of i nsurance co verage within the stipulated time; otherwise, the check shall be returned to the undersigned. The proceeds of this check shal l also become the property of t he City if the undersigned shall withdraw his or her bid within the pe riod of fifteen (15) days after t he date se t for the opening thereof, u nless other wise required by law, and notwithstanding the award of the contract to another bidder.
_______________________________________
_______________________________________
BIDDER
_________________
*Delete the inapplicable word.
(NOTE: If the Bidder desires to use a bond instead of check, the Bid Bond form on the following pages shall be executed--the sum of this bond shall be not less than ten percent (10%) of the total amount of the bid.)
Revised 6/12/18 Contract No. 3840-23 Page 20 of 134
BIDDER'S BOND TO ACCOMPANY PROPOSAL
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
KNOW ALL PERSONS BY THESE PRESENTS:
That w e, __________________________ _____________________________, as Principal, and _____________________________________, a s Surety are hel d and firmly bound unto the City of Carlsbad, California, in an amount as follows: (must be at least ten percent (10%) of the bid amount) _____________ _____________ for which payment, w ell and tru ly made, we bind ours elves, our he irs, execu tors and adminis trators, succe ssors or assigns, jointly and severally, firmly by these presents.
THE CON DITION OF TH E FOREGOING OBLIGATIO N IS SUCH that if the proposa l of the above-bounden Principal for:
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
in the City of Carlsbad, is accepted by the City Council, and if the Principal shall duly ent er into and execute a Contract including required bonds and insurance policies within twenty (20) days from the date o f award of Contract by t he City Co uncil of t he City of Carlsbad, being duly notified of said award, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect, and the amount specified herein shall be forfeited to the said City.
In the event Principal executed this bond as an individual, it is agreed that the death of Principal shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ____________ day of ___________________________, 20_____
________________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: __________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name/Title) (Print Name/Title)
(SEAL AND NOTARIAL ACKNOWLEDG EMENT OF SURE TY – ATTACH ATTORNEY-IN-FACT
CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: __________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 3840-23 Page 21 of 134
GUIDE FOR COMPLETING
THE “DESIGNATION OF SUBCONTRACTORS” FORM
REFERENCES Prior to preparation of the follo wing “Subcontractor Disclosure F orm” Bidders are urged to revie w the definitions in s ection 1 -2 of the Genera l Provisions to this Contra ct, especially, “Bid”, “Bidder”, “Contract”, “Con tractor”, “Contract Price”, “Contract Unit Pri ce”, “Engineer”, “Own Org anization”, “Subcontractor”, and “Wo rk”. Bidders are further u rged t o review sections 2-3 SUBCONTRACTS of the General Provisions.
CAUTIONS This form will be used by the Agency to determine the percentage of work that the Bidder proposes to perform. Bidders are cautioned that failure to pro vide complete and correct information may r esult in rejection of the bid as n on-responsive. Any bid that propose s performance of more than 50 percent of the wo rk by su bcontractors or otherwise to be performed by forces o ther th an the Bidder’s own organizat ion w ill be r ejected as non - responsive. Specialty items of wor k that may be s o designated by the Eng ineer on the “Contractor’s Proposal” are not included in computing the percentage of work propo sed to be performed by the Bidder.
INSTRUCTIONS The Bidder s hall set fort h the name and location of bus iness of each and every subcontractor whom the Bidder proposes to perform work or labor or render service in or about the work or improvement, and every subcontractor licensed as a contractor by the State of California whom the Bidder proposes to specially fabricate and install any portion of the work or improve ment accordi ng t o detailed drawin gs con tained in the plans and specifications in excess of one-half of one percent (0.5%) of the Bidder’s total bid or, in the case of bids or offers for the construction of streets and highways, i ncluding bridges, in excess of one-half of one percent (0.5% ) or t en thousand do llars ($10,000) whichever is greater. Said name(s) and location(s) of business of subcontractor(s) shal l be set forth and included as an integral part of the bid offer.
The Designation of Subcontractors form must be submitted as a part of the Bidder’s sealed bid.
Failure to provide complete and c orrect information may re sult in rejection of the bid as non - responsive.
Suppliers of materials from sources outside the limits of work are not subcontractors. The value of materials and transport of materials from sources outside the limits of work, as s hown on the plans, shall be assigned to the Contractor or the Subcontractor as the case may be, that the Bidder proposes as installer of s aid materials. The valu e o f materia l in corporated in any Subcontractor-installed bid item that is supplied by the Bidd er shall be included as a part of the work that the Bidder proposes to be performed by the Subcontractor installing said item.
When a Subcontractor has a Carlsb ad business license, the number m ust be entered on the proper form. If the Subcontractor does n ot have a val id business license, enter “NONE” in the appropriate space.
When the Bidder proposes using a Subcontractor to construct or install less than 100 percent of a b id i tem, t he Bidder s hall a ttach an e xplanation sheet t o the Designation of Subcont ractor form. The explanat ion sheet shall clearly apprise the City of t he specific fa cts th at s how the Bidder proposes to perform no less than fifty percent (50%) of the work with its own forces.
Revised 6/12/18 Contract No. 3840-23 Page 22 of 134
Determination of the sub contract amounts for purposes of awa rd of the contract shall be determined by the City Council in conformance with the provisions of the contract documents and the various supplemental provisions. The decision of the City Council shall be final.
Contractor is prohibited from performing an y work on this project with a subcontractor who is ineligible to perform work on a public works project pursuant to Labor Code Sections 1771.1 or 1777.7.
Bidders shall make a ny ad ditional copies of t he disclosure forms as may be necessary to provide the r equired information. The pa ge number and total number of add itional form pages shall be entered in the location provided on each type of form so duplicated.
Revised 6/12/18 Contract No. 3840-23 Page 23 of 134
DESIGNATION OF SUBCONTRACTOR AND
AMOUNT OF SUBCONTRACTOR'S BID ITEMS
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
The Bi dder certifi es that it has used the s ub-bid of t he followin g li sted subcon tractors in preparing this bid for the Work and that the l isted subcontractors will be used to pe rform the portions of the Work as de signated in this list in accordance with applicable provisions of the specifications a nd sec tion 4100 et seq . of the Publ ic Contract Code , "Subletting an d Subcontracting Fair Practices Act." The Bid der further certifies that no additional subcontractor will be allowed to perform any portion of the Work in excess of one-half of one percent (0.5%) of the Bidder’s total bid, or i n the case of bids or offers for construction of streets and highways, including bridges, in excess of one-half of one percent (0.5%) or ten thousand dollars ($10,000), whichever is greater, and that no changes in the subcontractors listed work will be made except upon the prior approval of the Agency.
SUBCONTRACTOR’S BID ITEMS
Portion of
Work
Subcontractor Name and
Location of Business
Phone No.
and Email
Address
DIR
Registration
No.
Subcontractor’s
License No. and
Classification*
Amount of
Work by
Subcontractor
in Dollars*
Page _____ of _____ pages of this Subcontractor Designation form
_________________
* Pursuant to sect ion 4104 (a)(3)(A) California Public Contract Code, receipt of the informatio n preceded by an aster isk may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the “Notice Inviting Bids.” Revised 6/12/18 Contract No. 3840-23 Page 24 of 134
BIDDER'S STATEMENT OF
TECHNICAL ABILITY AND EXPERIENCE
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
The Bidder is required to state what work of a similar character to that included in the proposed Contract he/sh e has succ essfully performed and give ref erences, with telephone n umbers, which will enable the Cit y to judge his/her responsibility, experi ence and skill. An attachment can be used.
The bidder shall demonstrate at least five years of experience successfully completing at least five projects involving diesel fueled generator installations with a val ue of $100,000 or greater and similar in type and size to the Work of th e proposed Contract. Bidder must also submit the qual ifications of its Representatives in accordance with Section 7 -6. The propo sal shall be deemed non-responsive if the required technical ability and experience for the Bidder or its representative is not demonstrated.
Date Contract
Completed
Name and Address
of the Employer
Name and Phone
No. of Person to
Contract
Type of Work Amount of
Contract
Revised 6/12/18 Contract No. 3840-23 Page 25 of 134
BIDDER’S CERTIFICATE OF INSURANCE FOR
GENERAL LIABILITY, EMPLOYERS’ LIABILITY,
AUTOMOTIVE
LIABILITY AND WORKERS’ COMPENSATION
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
As a required part of the Bidder’s proposal the Bidder must attach either of the following to this page.
1) Certificates of insurance showing conformance with the requirements herein for each of:
Comprehensive General Liability
Automobile Liability
Workers Compensation
Employer’s Liability
2) Statement with an insu rance carrier’s notarized signature stating that the carrier can, and upon payment of fees and/or premiums by t he Bidder, will issue t o the Bidder Policies of insurance for Comprehensive General Liability, Automobile Liability, Workers Compensation and Emp loyer’s Li ability in confor mance with the requiremen ts h erein and Certifica tes of insurance to the Agency showing conformance with the requirements herein.
All certificates of insurance and statements of will ingness to is sue insurance for aut o policies offered to meet the specification of this contract must:
1) Meet the conditions stated in The Notice Inviting Bids and the General Provisions for this project for each insurance company that the Contractor proposes.
2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.
Revised 6/12/18 Contract No. 3840-23 Page 26 of 134
BIDDER'S STATEMENT RE DEBARMENT
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
1) Have you or any of you r subcontractors ever been d ebarred as an irresponsibl e bidder by another jurisdiction in the State of California?
______ ______
yes no
2) If yes, w hat was/were the name(s) of the agency(ies) and what was/were the period (s) of debarment(s)? Attach additi onal copi es o f this page to accommodate more than two debarments.
party debarred
agency
period of debarment
party debarred
agency
period of debarment
BY CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name/title)
Page _____ of _____ pages of this Re Debarment form
Revised 6/12/18 Contract No. 3840-23 Page 27 of 134
BIDDER'S DISCLOSURE OF DISCIPLINE RECORD
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
Contractors are required by law to be licensed and re gulated by the Contractors’ State License Board w hich h as jur isdiction to investigate complain ts against con tractors if a comp laint regarding a patent act or omission is filed within four years of the date of the alleged violation. A complaint regarding a latent act or o mission pertaining to structural defects must be filed within 10 years of the d ate of the all eged v iolation. Any questi ons con cerning a contractor may be referred to th e Registrar, Contr actors’ St ate Li cense Board, P.O. Box 26000, Sacramento , California 95826.
1) Have you ever had y our contractor’s license s uspended or revoked by the C alifornia Contractors’ State License Board two or more times within an eight year period?
______ ______
yes no
2) Has the suspension or revocation of your contractor’s license ever been stayed?
______ ______
yes no
3) Have any subcontractors that you propose to perform any portion of the Work ever had their contractor’s license suspen ded or revoked by the Ca lifornia C ontractors’ Stat e License Board two or more times within an eight year period?
______ ______
yes no
4) Has the suspension or revocation of the license of any subcontractor’s that you propose to perform any portion of the Work ever been stayed?
______ ______
yes no
5) If the answer to either of 1. or 3. above is yes fully identify, in each and every case, the party disciplined, the date of an d violation th at the disciplinary action pertains to, d escribe the nature of the violation and the disciplinary action taken therefore.
(If needed attach additional sheets to provide full disclosure.)
Page _____ of _____ pages of this Disclosure of Discipline form
Revised 6/12/18 Contract No. 3840-23 Page 28 of 134
BIDDER'S DISCLOSURE OF DISCIPLINE RECORD
(CONTINUED)
(To Accompany Proposal)
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
6) If the answer to either of 2. or 4. above is yes fully identify, in each and every case, the party whose discipline was stayed, the date of the violation that the disciplinary action pertains to, describe the nature o f the v iolation and the condition (if any) upon whic h the disciplinary action was stayed.
(If needed attach additional sheets to provide full disclosure.)
BY CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name/title)
Page _____ of _____ pages of this Disclosure of Discipline form
Revised 6/12/18 Contract No. 3840-23 Page 29 of 134
NONCOLLUSION DECLARATION TO BE EXECUTED BY
BIDDER AND SUBMITTED WITH BID
PUBLIC CONTRACT CODE SECTION 7106
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
The undersigned declares:
I am the ____________ of ______________, the party making the foregoing bid.
The bid is not made i n the i nterest of, o r on behalf of, any undisclosed person, partnership, company, asso ciation, organization, or corporatio n. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any o ther bidder to pu t in a false or sham bid. The bidder has no t directly or indirectly colluded, conspired, c onnived, or agreed with any bidd er or a nyone else to put in a sham bid, or to refrain from bidding. The bidder ha s not i n any manner , directly or ind irectly, sought b y agreement, communication, or conference w ith anyone to fix the bid price of the bidd er o r any other bidder, or to fix an y overhead, profit, or co st element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint v enture, limited liability company, l imited liability partnership, or any othe r entity, hereby represents that he or she ha s full power to execute, and d oes exec ute, thi s decla ration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on _____________ ______________, 20____ at _________ [city], ________ [state].
________________________________________________
Signature of Bidder
Revised 6/12/18 Contract No. 3840-23 Page 30 of 134
CONTRACT
PUBLIC WORKS
This agreement is made this ____________ day of ____________ ________________, 2024, by and betwe en the City o f Carlsbad, California, a m unicipal corporation, (hereinafter called "City"), and __________________________________ whose pri ncipal place of business is _______________________________________________ (hereinafter called "Contractor").
City and Contractor agree as follows:
1. Description of Wor k. Contractor sh all perform all work spe cified in the Contract documents for:
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
(hereinafter called "project")
2. Provisions of Labor and Materials. Contractor shall provide all labor, materials, tools, equipment, and personnel to perform the work specified by the Contract Documents.
3. Contract Documents. The Contract Documents consist of this Contract, Notice Inviting Bids, Co ntractor's Proposal, Bi dder's Bond, Noncollusion Declaration, D esignation of Subcontractors, Technical Ability and Exper ience, Bidder’s Statement Re Debarment, Es crow Agreement, Release Form, the Plans and Specifications, the General Provisions, addendum(s) to said P lans a nd Specific ations an d General Provisions, and all proper amendments and changes made thereto in accordance with this Contract or the Plans and Specifications, and all bonds for the project; all of which are incorporated herein by this reference.
Contractor, her/his subcontractors, and materials suppliers shall provide and install the work as indicated, specified, and implied by the Contract Documents. Any items of work not indicated or specified, bu t whic h ar e essential to the com pletion o f the work, shall be provide d at the Contractor's expense to fulfill the intent of said documents. In all instances through the life of the Contract, the City will be the interpre ter of the intent of t he Contract Documents, and the City’s decision relative to said intent will be final and bindin g. Failure of the Contractor to apprise subcontractors and materials sup pliers of t his condition of th e Co ntract will not relieve responsibility of compliance.
4. Payment. For all compensation for Contracto r's perfo rmance of work under this Contract, City shall make payment to the Contractor per section 9-3 PAYMENT of the General Provisions section of thi s contract. The Engi neer will close the estimate of wo rk completed for progress payments on the last work ing day of each month. The City shall withhold retention as required by Public Contract Code Section 9203.
5. Independent Investigation. Contractor has made an independen t investigation of the jobsite, the soil conditions at the jobsite, and all other conditions that might affect the progress of the work and is aware of those conditions. The Contract price includes payment for all work that may be done by C ontractor, wheth er anticipated or not, in or der to overcome u nderground conditions. Any information t hat may have been fur nished to C ontractor by City about underground conditions or other job conditions is f or Contractor's convenience only, and City
Revised 6/12/18 Contract No. 3840-23 Page 31 of 134
does not warrant that the conditions are as thus indicated. Contractor is satisfied with all job conditions, includ ing underground condit ions and h as not relied on info rmation f urnished b y City.
6. Hazardous Wast e or Ot her Unusual Conditions. If the contra ct i nvolves digging trenches or othe r excavations that extend deeper than four feet below the s urface Contractor shall promptly, and before the following conditions are disturbed, notify City, in writing, of any:
A. Hazardous Waste. Material that Contractor believes may be mate rial that is hazardous waste, as define d in se ction 25117 of the Health and S afety Co de, t hat is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
B. Differing Conditions. Subsurface or latent physical conditions at the site differing from those indicated.
C. Unknown Physical Conditions. Unknown physical conditions at the site of any unusual nature, different m aterially fr om those ordin arily encou ntered an d generall y re cognized as inherent in work of the character provided for in the contract.
City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in contractor's costs of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in this contract.
In the event that a dispute arises between City and Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time required for, performance of any part of the work, contractor shall not be excused from any scheduled completion date provided for by t he contract, but shall proceed with all w ork to be performed under th e contract. Contractor s hall r etain any and all rights provided ei ther by contract or by law whi ch pertain t o the r esolution of disputes and protest s bet ween t he contracting parties.
7. Immigration Re form and Control Act. Contractor certifies it is aware of the requirements of t he Immigration Reform and Control Act of 1986 (8 USC sections 1101-1525) and has complied and will comply with these requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors, and consultants that are included in this Contract.
8. Prevailing Wage. Pursuant to the California Labor Code, the director of the Department of Industrial Relation s has det ermined th e ge neral prevailing rate of pe r diem wages in accordance with California Labor Code, section 1773 and a copy of a schedule of said general prevailing wage rates is on file in the office of the City Engineer and is incorporated by reference herein. Pursuant to California Labor Code, section 1775, Contractor shall pay prevailing wages.
Contractor shall post copies of a ll applicable prevailing wages on the job site. Contractor shall comply with California Labor Code , section 1776, which gen erally re quires kee ping accurate payroll r ecords, verifying and certifying pay roll re cords, and makin g them available for inspection. Contractor shall require all subcontractors to comply with Section 1776.
9. Indemnification. Contractor shall assume the defense of, pay all expenses of defense, and indemnify and hold harmless the City, and its officers and employees, from all claims, loss,
Revised 6/12/18 Contract No. 3840-23 Page 32 of 134
damage, injury and liability of ever y kind, nature an d description, directly or ind irectly ar ising from or in connecti on with t he perform ance of the Contrac t or wo rk; or from any failure or alleged failure of Contra ctor t o comply with any applicable law, ru les or regulations including those relating to safety an d healt h; and from any and all claims, loss, damages, injury and liability, howsoever the same may be caused, resulting directly or indirec tly from the nature of the work covered by th e Contract, except fo r loss or da mage caused by the sole or act ive negligence o r w illful misconduc t of the City. The expenses of defe nse inclu de all cos ts a nd expenses including attorneys' fees for litigation, arbitration, or other dispute resolution method.
Contractor shall also defend and indemnify the City against any challenges to the award of the contract to Contractor, and Contra ctor will pay all c osts, including defense costs for the City.
Defense costs include the cost of separate counsel for City, if City requests separate counsel.
Contractor shall also defend and indemnify the City against any challenges to the award of the contract to Contractor, arising in whole or in part from alleged inaccuracies or misrepresentation by the Contr actor, whether intentional or otherwise, an d Contractor will pay all costs, including defense costs for the City. Defense costs include the cost o f separate counsel for City, if City requests separate counsel.
10. Insurance. Contractor shall p rocure and maintain for the duration of the contract insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his or her a gents, representatives, employees or subcontractors. Said insurance shall meet the City of Carlsbad’s policy for insurance as stated in City Council Policy # 70.
(A) Coverages and Limits Contractor shall maintain the types of coverages an d minimum limits indicted herein:
a. Commercial General Liability (GLC) Insurance: Insurance written on an “occurrence” basis, including products-completed operations, personal & advertising injury, with limits no less than $2,000,000 per occurrence. If a general aggregat e l imit applies, eit her t he ge neral aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.
b. Business Aut omobile L iability Insura nce: $ 2,000,000 combin ed sin gle limit p er accident for bodi ly in jury and pr operty damage. In a ddition, the auto policy mus t cover a ny vehicle used in the performance of the contract, used onsi te or offsite, whether ow ned, no n- owned or hired, and whether scheduled or non-scheduled.
c. Workers' Compensation and Employers' Liability Insurance: Workers' compensation limits as required by the Labor Code of the State of California and Employers’ Liability limits of $1,000,000 per incident. Workers' compensation offered by the State C ompensation Insurance Fund is acceptable to the City.
(B) Additional Provisions: Contractor shall ensure that the policies of insurance require d under this agreement wit h the exception of Work ers’ Compensation and Business Automobile Liability Insurance contain, or are endorsed to contain, the following provisions.
a. The City, its officials, employees and volunteers are to be covered as additional insured as respe cts: l iability arising ou t of a ctivities performed by o r on behalf of the Contractor ; products and compl eted operations o f the contractor; premises owned, leased, h ired or
Revised 6/12/18 Contract No. 3840-23 Page 33 of 134
borrowed by the contractor. The c overage shall contain no specia l limitations on the scope of protection affo rded t o the City, its off icials, employees or volunteers. All additional in sured endorsements must be evidenced usi ng separate d ocuments at tached to the certificate of insurance; one for each company affording general liability, and employers’ liability coverage.
b. The Contractor's insurance coverage shall be primary insurance as respects the City, its officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officials, employees or volunteers shal l be in excess of the contractor's insurance and shall not contribute with it.
c. Any failure to compl y with reporting provisions of the p olicies shall not affect coverage provided to the City, its officials, employees or volunteers.
d. Coverage sh all st ate that t he con tractor's insurance shall ap ply s eparately to each insured against whom claim is ma de or suit is brought, except with r espect to the limits of the insurer's liability.
(C) Notice of Cancellation. Each insurance po licy required by this agre ement shal l be endorsed t o state that covera ge sh all not be no nrenewed, suspended, voided, canceled , or reduced in coverage or limits except after ten (10) days' prior written notice has been sent to the City by certified mail, return receipt requested.
(D) Deductibles and Self -Insured Retention (S .I.R.) Levels. Any d eductibles or self- insured retention levels must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate suc h deductibles or self-insured retention levels as respects the City, i ts officials and emp loyees; or the cont ractor sha ll procure a bond guaranteeing pa yment of l osses and rel ated i nvestigation, c laim administrat ion and defen se expenses.
(E) Waiver of Subrogation. All policies of insurance required under this agreement shall contain a waiver o f all rights of sub rogation the insurer may have or may acquire against the City or any of its officials or employees.
(F) Subcontractors. Contractor shall include all subcontractors as insured under its policies or shall furnish separate certificates and endorsements for each subcontractor. Coverages for subcontractors shall be subject to all of the requirements stated herein.
(G) Acceptability of Insurers. Insurance is to b e placed with insurers that have a rating in Best's Key Rat ing Gu ide of at leas t A-:VII. Insurer s must als o be a uthorized to transact the business of insurance by the State of California Insurance C ommissioner as adm itted carriers as evidenced by a listing in the official publication of the Department of Insurance of the State of California and/or under the standards specified by City Council Policy # 70.
(H) Verification of Coverage. Contractor shall furnish the City with certificates of insurance and original end orsements affecting coverage requ ired by this clause. The certificates a nd endorsements for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificates and endorsements are to be in f orms approved by the City and are to be received and approved by the City before the Contract is executed by the City.
Revised 6/12/18 Contract No. 3840-23 Page 34 of 134
(I) Cost of In surance. The Cost of all insu rance required under this agreement s hall be included in the Contractor's bid.
11. Claims and Lawsuits. All claims by Contractor shall be resolved in accordance with Public Contract Code section 9204, which is incorporated by reference. A co py of Section 9204 is included in Section 3 of the General Provi sions. In a ddition, all claims by Co ntractor for $375,000 or less shall be resolv ed in a ccordance wi th the p rovisions i n the Public Contract Code, Division 2, Part 3, Chapter 1 , Article 1.5 ( commencing wit h section 20104) which are incorporated by referen ce. A copy of Articl e 1 .5 is i ncluded in Section 3 of th e General Provisions. In the event of a con flict between Section 9204 and Article 1.5, Section 9204 sh all apply. Notwithstanding the provisions of this section of the contract, all claims shall comply with the Government Tort Claim Act (section 900 et seq., of the California Government Code) for any claim or cause of action fo r money or da mages prior to fi ling an y laws uit for breach of t his agreement.
(A) Assertion of Claims. Contractor hereby agrees that any contract claim submitted to the City must be a sserted as part of the contract process as set forth in this agreement and not in anticipation of litigation or in conjunction with litigation.
(B) False Claims. Contractor acknowledges that if a fa lse claim is submitted to t he City, it may be considered fraud and the Contractor may be subject to criminal prosecution.
(C) Government Code. Contractor acknowledges that California Government Code sections 12650 et seq., the False Clai ms Ac t, provides f or civil pen alties wh ere a pe rson knowingly submits a false claim to a publ ic entity. These provisions include false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of the information.
(D) Penalty Recove ry. If the City of Carlsbad seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attorney's fees.
(E) Debarment for False Claims. Contractor hereby acknowledges that the filing of a false claim may subject th e Contractor to an a dministrative debarment pro ceeding where in t he Contractor may be prevented from further bidding on public contracts for a period of up to five years.
(F) Carlsbad Municipal Code. The pro visions of Car lsbad Municipal Code sections
3.32.025, 3.32.026, 3.32.027 and 3.32.028 pertaining to false claims are incorporated herein by reference.
(G) Debarment from Other J urisdictions. Contractor hereby acknowledges t hat debarment b y another jurisdiction is groun ds for the City Council of the City of Carlsba d to disqualify the Contractor or subcontractor from participating in future contract bidding.
(H) Jurisdiction. Contractor agrees and hereby stipulates that the p roper ven ue and jurisdiction for resolution of any disputes between the parties a rising out of thi s agreement is San Diego County, California.
I have read and understand all provisions of Section 11 above. ________ init ________ init
Revised 6/12/18 Contract No. 3840-23 Page 35 of 134
12. Maintenance of Records. Contractor shall maintain and make avail able at no cost to the City, upon request, records in accordance with sections 1776 and 1812 of Part 7, Chapter 1, Article 2, of th e Labor Code. If the Contract or does not maintain the records at Contract or's principal place of business as specified above, Contractor shall so inform the City by certified letter accompanying the return o f this Contract. Contractor shall notify the City by certified mail of any change of address of such records.
13. Labor Code Provisions. The provisions of Part 7, Chapter 1, commencing with section 1720 of the Labor Code are incorporated herein by reference.
14. Security. Securities in the fo rm of cash, cashier's check, or certifi ed check may be substituted for any monies withheld by the City to secure pe rformance of th is contract for a ny obligation estab lished by t his co ntract. Any other security that is mutually agreed to by the Contractor and the City may be substituted for moni es withheld t o ensure perfor mance under this Contract.
15. Unfair Business Practices. In entering into a public works contract or a subcontract to supply goods, services, or ma terials pu rsuant to a pub lic works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and intere st in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchase s of go ods, services, or materials pursuant to t he public works contract or the subcontract. This ass ignment shall be ma de and become effective at the time the awarding body tender s final payment to the contr actor, without further acknowledgment by the parties.
16. Provisions Required by Law Deemed Inserted. Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and included herein, and if, through mistake or oth erwise, any such prov ision is not inserted, or is not correctly inserted, then upon a pplication of either p arty, the Contr act shall forthwith be physically amended to make such insertion or correction.
17. Additional Provisions. Any additional provisions of this agreement are set forth in t he "General Provisions" or "Supplemental Provisions" attached hereto and made a part hereof.
[signatures on the following page]
Revised 6/12/18 Contract No. 3840-23 Page 36 of 134
NOTARIAL ACKNOWLEDG MENT OF EXECUTION BY ALL SIGNATORIES MUST BE
ATTACHED
(CORPORATE SEAL)
CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name and title)
By:
(sign here)
(print name and title)
CITY OF CAR LSBAD, a munici pal
corporation of the State of California
By:
KEITH BLACKBURN, Mayor
ATTEST:
SHERRI FREISINGER, City Clerk
President or vice -president and secretary or assistant secretary must sign for corporations. If only one officer signs, the corporation m ust at tach a resoluti on cert ified by the s ecretary or assistant secretary under the corporate seal empowering that officer to bind the corporation.
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By:
Assistant City Attorney
Revised 6/12/18 Contract No. 3840-23 Page 37 of 134
LABOR AND MATERIALS BOND
WHEREAS, the City Counci l of the City of Carlsbad located in the Stat e o f Califo rnia has awarded to ________________________________________________________ (hereinafter designated as the "Principal"), a Contract for:
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
in the City of Carlsbad, in stric t conformi ty with the drawings and spe cifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated herein by this reference.
WHEREAS, Principal has ex ecuted or is abo ut to exe cute said Contract and the terms thereof require the furnishing of a bond, providing that if Principal or any of their subcontractors shall fail to p ay for any materials, provisions, provender or other supplies or tea ms used in, up on o r about the performance of the work agreed to be done, or for any work or labor done thereon of any kind, the Surety on this bond will pay the same to the extent hereinafter set forth.
NOW, THEREFORE, WE, _____________________ as Principal, (hereinaft er designated as the "Con tractor"), and ______________________ _________________________________ as Surety, are held firmly bound unt o the City of Carlsbad in the sum __________________, said sum being an amount equal to: One hundred percent (100%) of the t otal amount payable under the terms of the contract by the Cit y of Carlsbad, and for which pay ment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.
THE C ONDITION OF THIS OBLIGATION IS SUC H that if the Contract or or his/ her subcontractors fail to pay for any materials, provisi ons, provender, supplies, or teams used in, upon, for, or about the performance of the work contracted to be done, or for any other work or labor thereon of any kind, consistent with California Civil Code section 9100, or for amounts due under the Unemployment Insurance Code with respect to the work or labor performed under this Contract, o r for any amoun ts required to b e deducted, withheld, and paid o ver t o the Employment D evelopment Depart ment from the wages of employees of the contractor and subcontractors pursuant to section 13020 of the Unemployment Insurance Code with respect to the work and labor, that the Surety will pay for the same, and, also, in case suit is brought upon the bond, reasonable attorney's fees, to be fixed by the court consistent wit h California Civil Code section 9554.
This bond shall inure to the benefit of any of the persons named in California Civil Code section 9100, so as to give a right of action to those perso ns or their assigns in any suit brought upon the bond.
Surety stip ulates and a grees th at no change, extension of t ime, alterati on or additi on to t he terms of the Contr act, or to t he w ork t o be pe rformed hereunder or the specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any change, extension of time, alterations or ad dition to th e terms of the contract or t o the work or to the specifications.
Revised 6/12/18 Contract No. 3840-23 Page 38 of 134
In the eve nt that Contractor is an individual, it is agreed that the dea th of any such Contractor shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ______________ day of __________________________, 20____
_______________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: _________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name & Title) (Print Name & Title)
(SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY – ATTACH ATTORNEY-IN-FACT CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: _________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 3840-23 Page 39 of 134
FAITHFUL PERFORMANCE/WARRANTY BOND
WHEREAS, the City Council of the City of Car lsbad, State of Calif ornia has a warded to _____________________________________________________ (hereinafter designated as the "Principal"), a Contract for:
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
in the City of Carlsbad , in s trict conformity with the contract, the drawings and sp ecifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad, all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is abo ut to execute said Contract and the terms thereof require the furnishing of a bond for the faithful performance and warranty of said Contract;
NOW, THEREFORE, WE, _____________________ as Principal, (hereinafter designated as the "Contractor"), a nd _______________________________________________________ as Surety, are held firmly bound unto the City of Carlsbad in the sum __________________, said sum being an amount equal to: One hundred percent (100%) of the total amount payable under the terms o f the contract by the City of Carlsbad, and f or which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if the above bounden Contractor, their heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions, and agreements in the Contract and any alteration thereof made as therein provided on their part, to be ke pt and performed at the time and in the m anner therein specified, and in all respects according to their true intent and m eaning, and shall indemni fy and save harml ess the City of Carlsbad , its officers, employees and a gents, as therein st ipulated, then th is obligation sh all become null and void; otherwise it shall remain in full force and effect.
As a part of the obli gation secured hereby and in ad dition to the face amount specified therefore, there shall b e included c osts and reasonable expenses and fees , including reasonable attorney's fees, i ncurred by the City in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered.
Surety stipulates and agrees that no change, e xtension of time, al teration or addition to the terms of the Contract, or to the w ork to be performed there under or th e specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any chan ge, extension of time, a lterations or addition to the terms of the co ntract or to the work or to the specifications.
Revised 6/12/18 Contract No. 3840-23 Page 40 of 134
In the event that Co ntractor is an individual, it is agr eed that the death of any such Contractor shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ______________ day of __________________________, 20____
_______________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: _________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name & Title) (Print Name & Title)
(SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY – ATTACH ATTORNEY-IN-FACT CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: _________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 3840-23 Page 41 of 134
OPTIONAL ESCROW AGREEMENT FOR
SECURITY DEPOSITS IN LIEU OF RETENTION
This Escrow Agreement is made and entered into by and between the City of Carlsbad whose address is 1200 Carlsbad Village Drive , Carlsbad, California, 9 2008, her einafter c alled "City" and ___________________________________________________________, whose address is __________ _______________________________________________________ hereinafter called "Contractor" and ___________________________________________________, whose address is __________________________________________________________ hereinafter called "Escrow Agent."
For the co nsideration hereinafter s et fort h, the City, Con tractor and Esc row Agent agree as follows:
1. Pursuant to section 22300 o f the Pub lic Contract Code of the State of California, the Contractor has t he option to deposit securities with the Escrow Agent as a substitute for retention ear nings required to be withheld by th e City pursuant t o the C onstruction Contract entered into between the City and Contractor for
POINSETTIA LIFT STATION GENERATOR REPLACEMENT
CONTRACT NO. 3840-23
in the amount of ___________________________ dated ______________ (hereinafter referred to as the "Contract"). Alternatively, on written request of the Contractor, t he City shall make payments of the retention earnings directly to the Escrow Agent. When the Contractor deposits the securities as a substitute for Contract earnings, the Escrow Agent shall notify the City within 10 days of the deposit. The market value of the securities at the time of the substitution shall be a least equal to the cash amount then required to be withheld as retention under the terms of the contract between the City and Contractor. Securities shall be held in the name of the City and shall designate the Contractor as the beneficial owner.
2. The City shall make progress payments to the Contractor for such funds which otherwise would be withheld from progress payments pursuant to the Contract provision s, provided that the Escrow Agent holds securities in the form and amount specified above.
3. When the City makes payment of retentions earned directly to the Esc row Agent, t he Escrow Agent shall hold them for t he benefit of the Contractor until such time as the escr ow created under this contract i s termina ted. The C ontractor may dire ct the investment of th e payments into s ecurities. All terms and cond itions of thi s agreement and the r ights and responsibilities o f th e parties shall be equally applicabl e and binding wh en t he City pays the Escrow Agent directly.
4. The Contractor shall be responsible for paying all fees for the expenses incurred by the Escrow Age nt i n administering t he Escrow Account and all ex penses of the City. Th ese expenses and payment terms shall be determined by the City, Contractor and Escrow Agent.
5. The interest earned on the securities or the money market accounts held in escrow and all in terest ea rned on that int erest shall be f or the sole account of Con tractor an d shall be subject to withdrawal by Contractor at any time and from time to time without notice to the City.
Revised 6/12/18 Contract No. 3840-23 Page 42 of 134
6. Contractor shall h ave the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow A gent accompanied by written authorization from City to the Escrow Agent that City consents to the withdrawal of the amount sought to be withdrawn by Contractor.
7. The City shall have a rig ht to dr aw u pon the securities i n the event of default by th e Contractor. Upon seven days' written notice to the Escrow Agent from the City of the default, the Escrow Agent shall immediately convert the securities to cash a nd shall distribute the cash as instructed by the City.
8. Upon receipt of written n otification from the City certifying that the Contrac t is final and complete and that the Contractor has complied with all requirements and procedures applicable to th e Cont ract, the Escro w A gent shall re lease to Con tractor all se curities and interest on deposit less es crow f ees and charges of the Escrow Acc ount. The e scrow shall be close d immediately upon disbursement of all moneys and securities on deposit and payments of f ees and charges.
9. The Escrow Agent shall rely on the written notifications from the City and the Contractor pursuant to sections (1) to (8), inclusive, of this agr eement and the City and Contractor shall hold Escrow Agent harmless from Escrow Agent's release, conversion and disbursement of the securities and interest as set forth above.
10. The names of the persons who are authorized t o give written notices or to re ceive written notice on behalf of the City and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:
For City:
Title FINANCE DIRECTOR
Name
Signature
Address 1635 Faraday Avenue, Carlsbad, CA 92008
For Contractor:
Title
Name
Signature
Address
For Escrow Agent:
Title
Name
Signature
Address
Revised 6/12/18 Contract No. 3840-23 Page 43 of 134
At the time the Escrow Account i s opened, the City and Contractor shall deliver to the Escrow Agent a fully executed counterpart of this Agreement.
IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers on the date first set forth above.
For City:
Title MAYOR
Name
Signature
Address 1200 Car lsbad Village Drive, Carlsbad , CA
92008
For Contractor:
Title
Name
Signature
Address
For Escrow Agent:
Title
Name
Signature
Address
Revised 6/15/17 Contract No. 3840-23 Page 44 of 134
GENERAL PROVISIONS
FOR
POINSETTIA LIFT STATION GENERATOR
REPLACEMENT
CONTRACT NO. 3840-23
CITY OF CARLSBAD
BIDDERS ARE ADVISED THAT THIS SECTION REPLACES PART 1,
GENERAL PROVISIONS, OF THE STANDARD SPECIFICATIONS FOR
PUBLIC WORKS CONSTRUCTION
SECTION 1 -- TERMS, DEFINITIONS, ABBREVIATIONS, AND
SYMBOLS
1-1 TERMS. Unless otherwise st ated, the words directed, required, pe rmitted, ordered , instructed, designated, considered necessary, prescribed, approved, acceptable, satisfactory, or words of like meaning, refer to actions, expressions, and prerogatives of the Engineer.
1-1.1 Reference to Dr awings. Where words “shown”, “indicated”, “detailed”, “noted”, “scheduled”, or words of similar import are used, it shall be understood that reference is made to the plans accompanying these provisions, unless stated otherwise.
1-1.2 Directions. Where words “directed”, “designated”, “selected”, or words of similar import are used, it shall be understood that the d irection, designation or selection of the Engineer is intended, unless st ated otherwise. The word “required” and words of similar import shall b e understood to mean “as required to properly complete the work as required and as approved by the Engineer,” unless stated otherwise.
1-1.3 Equals and Approvals. Where the words “equal”, “approved equal”, “equivalent”, and such words of similar im port are used, it shall be understood such words are followed by the expression “in the opinion of the Eng ineer”, unle ss other wise stat ed. Where the words “approved”, “approval”, “acceptance”, or words of similar import are used, it shall be understood that the approval, acceptance, or similar import of the Engineer is intended.
1-1.4 Perform. The word “perform” shall be understood to mean th at the Contractor, at its expense, shal l perform al l oper ations, labor, tools and equipment , an d further, including the furnishing and installing of mater ials that are indicated, specified or r equired to mean that the Contractor, at its expense, shall furnish and install the work, complete and in-place and ready to use, including furnishing of necessary labor, materials, tools, equipment, and transportation.
1-2 DEFINITIONS. The following words, or groups of words, shall be exclusively defined by the definitions assigned to them herein.
Revised 6/15/17 Contract No. 3840-23 Page 45 of 134
Addendum – Written or graphic instrument issued prior to t he opening of Bids which clarifies, corrects, or c hanges the bi dding o r Contr act Document s. The term Addendum shall include bulletins and all o ther typ es of writ ten n otices issued to potential bidders pri or to openin g of Bids.
Agency – The City of Carlsbad, California.
Agreement – See Contract.
Assessment Act C ontract – A Contract financed by special ass essments authorized un der a State Act or procedural ordinance of a City or County.
Average Sound Level – The level, in decibels, of the mean-square A-weighted sound pressure during a stated time pe riod, with referen ce to t he square of the st andard reference soun d pressure of 20 mi cropascals. The "average sound level" is equival ent to the industry standard Leq. See Equivalent Continuous Sound Level.
Base – A lay er of specified materia l of planned thickness placed imm ediately below the pavement or surfacing.
Bid – The offer o r propo sal of the Bidder submitted on the pr escribed form setti ng forth the prices for the Work.
Bidder – Any individual, firm, partnership, corporation, or combination thereof, submitting a Bid for the Work, acting directly or through a duly authorized representative.
Board – The officer or body constituting the awarding authority of the Agency, which is the City Council for the City of Carlsbad or the Board of Directors of Carlsbad Municipal Water District.
Bond – Bid, performance, and payment bond or other instrument of security.
Caltrans – The State of California, Department of Transportation.
Cash Contract – A Contract financed by means other than special assessments.
Certificate of Com pliance – A writ ten do cument signed and submi tted by a s upplier or manufacturer that certifies that the mater ial or assembled mat erial supplied to the Wo rk sit e conforms to the requirements of the Contract Documents.
Change Order – A written order to the Contrac tor signed by t he Agency directing an addition, deletion, or r evision in the Work, or an adj ustment in the Contract Price or the Contract t ime issued after the effective date of the Contract. A Change Order may or may not also be s igned by the Contractor.
Code – The terms Government Code, Labor Code, etc., refer to codes of the State of California.
Construction Manager– the Project Inspector’s immediate supervisor and first l evel of appeal for informal dispute resolution.
Contract – The written agreement between the Agency and the Contractor covering the Work.
Revised 6/15/17 Contract No. 3840-23 Page 46 of 134
Contract Documents – Including but not limited to; the Contract, any Addendum (which pertain to the Contract Documen ts), Notice Inviting Bids , Instructi ons to Bidders; Bid (including documentation accompanying th e Bi d and any post -bid documentation submitted prior to the Notice of Award) when attac hed as an exhibit to the Contract, th e Bonds , the General Provisions, per mits, the T echnical Speci fications, the Supplemental Pro visions, the Plans, Standard Plans, Standard Specifications, Reference Specifications, and all Modifications issued after the execution of the Contract.
Contractor – The individual, partnership, corporation, joint venture, or other legal entity having a Contract with the A gency to perform the Work. In the case of wor k being done under permit issued by the Agency, the permittee sh all be constructed to be the Contractor. The term “prime contractor” shall mean Contractor.
Contract Time - The n umber of Work ing Days to complete the Wo rk as spe cified in the Contract Documents.
Contract Price – The total amount of money for which the Contract is awarded.
Contract Unit Price – The amount stated in the Bid for a single unit of an item of work.
County Sealer – The Sealer of Weight s and M easures of the coun ty in which the Con tract is let.
Critical Path – In th e construction schedule, the sequence of activit ies t hat represen ts the longest path through the Project network of activities and the shortest possible Project duration.
Days – Days shall mean consecutive calendar’s days unless otherwise specified.
Decibel – A unit for measuri ng the amplitude of sound, equal to 20 times the logarithm to the base 10 of the ratio of the pressure of the sound measured to the r eference pressure, which is 20 micropascals.
Defective Work - Work that does not conform to the requirements of the Contract Documents.
Deputy City Engineer – The Engineering Manager of the Construction Management & Inspection Department, the Construction Manager’s im mediate supervisor and the Engineer’s designated representative. The Deputy City Engineer is the second level of appeal for informal dispute resolution.
Dispute Board – Persons designated by the City Manager of the City of Carlsbad or Executive Manager of the Carlsbad Munici pal Water District, to hear and advise the City Manager on claims submitted by the Contractor. The City Manager for the City of Carlsbad or the Executive Manager for the Carlsba d Municipal Water District is the last appe al level for inf ormal dispute resolution.
Disputed Work – Work in which the Agency and the Contractor are in disagreement.
Electrolier – Street light assembly compl ete, in cluding foundation, standard, luminaire arm, luminaire, etc.
Revised 6/15/17 Contract No. 3840-23 Page 47 of 134
Engineer – The City Engineer of the City of Carlsbad or his/her approved representative. The Engineer is the third level of appeal for informal dispute resolution.
Engineer of R ecord/Design En gineer – A registered professional engin eer licensed in the State of California who i s qualified to act as an agent of a project owner or to prepare plans for facilities to be accepted by the City of Carlsbad. The term includes persons licensed in the State of California as Civil Engineers or Structural Engineers.
Equivalent Continuous So und L evel (Leq) – The average sound level which, over a given period of time, has the same total energy as the fluctuating noise and is also known as the time- average sound level.
Extra Work – New or unforeseen work not covered by a Contract Unit Price or Stipulated Unit Price.
Float – The number of days by which an a ctivity in the construction schedule may be delayed from either its earliest start date or earliest completion date without extending the Contract Time (total float). Total float belongs to the Project and to any Party to accommodate changes in the Work or to mitigate the effect of events which may delay completion.
Holiday – Holidays and the days observed are listed below. If a holiday falls on a Saturday, the holiday is observed on the preceding Friday. If the holiday falls on a Sunday, it is observed the following Monday. Unless specified otherwise in the Contract Docu ments or authori zed by the Engineer, do not work on holidays.
New Year’s Day January 1
Martin Luther King Day 3rd Monday in January
Presidents’ Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1st Monday in September
Indigenous People’s Day 2nd Monday in October
Veteran’s Day November 11
Thanksgiving Day 4th Thursday in November
Thanksgiving Friday Day after Thanksgiving
Christmas Day December 25
House Co nnection Sew er – A sewer , within a public street or right -of-way, proposed to connect any parcel, lot, or part of a lot with a mainline sewer.
House Sewer – A sewer, wholly within private property, proposed to connect any building to a house connection sewer.
Luminaire – The lamp housing including the optical a nd socket assemb lies (and ballast if so specified).
Luminaire Arm – The struc tural member, brac ket, or mast arm, wh ich, mo unted on the standard, supports the luminaire.
Minor Bid Item – a single contract item constituting less than 10 percent (10%) of th e original Contract Price bid.
Revised 6/15/17 Contract No. 3840-23 Page 48 of 134
Modification – Includes Change Orders and Supp lemental Agreements. A Modifica tion may only be used after the effective date of the Contract.
Night Work – See Working Night.
Notice of Award – The written notice by the Agenc y to the successful Bidder stating that upon compliance by it with the required conditions, the Agency will execute the Contract.
Notice to Proceed – A written notice given by the Agency to the Contractor fixing the date on which the Contract time will start.
Own Organization - When used i n Sections 2-3.1 and 2-3.2 – Employees of the Contractor who are hired, directed, supervised and paid by the Contractor to accomplish the completion of the Work. Further, such employees have their employment taxes, State disability insu rance payments, Stat e and Fe deral inco me taxes paid a nd admini stered, as app licable, by the Contractor. Further, “own organization” means construction equipment that the Contractor owns or leases and uses t o accomplish the Work. Equipment t hat is owner ope rated or leased equipment with an oper ator is not part of the Contractor's Own O rganization a nd will not be included for the purpose of compliance with Sections 2-3.1 and 2-3.2.
Person – Any individual, firm, association, partnership, corporation, trust, joint venture, or other legal entity.
Plans – The drawings, profiles, cross sections, working drawings, and supplemental drawings, or repro ductions t hereof, approved by t he Enginee r, wh ich sho w the locati on, character, dimensions, or details of the Work.
Private Contract – Work subject to Agency inspection, control, and approval, involving private funds, not administered by the Agency.
Project I nspector – the Engineer’s designated representative for insp ection, contract administration and first level for informal dispute resolution.
Proposal – See Bid.
Reference Specifications – Those bulleti ns, standards, rules, methods of ana lysis or tes t, codes, and specifications of other age ncies, engineering socie ties, or industrial associations referred to in th e Contract Documents. These refer to the latest edition, including amendments in effect and p ublished at th e time of advertis ing the project or is suing the permit, unless specifically referred to by edition, volume, or date.
Roadway – The portion of a street reserved for vehicular use.
Service Connection – Service connections are all or any portion of the conduit, cable, or duct, including meter, between a utility distribution line and an individual consumer.
Sewer – Any conduit intended for the receptio n and transfer of sewage and fluid ind ustrial waste.
Revised 6/15/17 Contract No. 3840-23 Page 49 of 134
Shop Dra wings – Drawings s howing the de tails of manuf actured or assembl ed p roducts proposed to be incorporated into the Work.
Sound Level – The weighted sound pressure level obta ined us ing a sound level meter and frequency weighting network as provided in the Ame rican National Standards Institute (ANSI) specifications for sound level meters. "Sound level" means the same as "noise level."
Special Provisions – Revisions to the Standard S pecifications se tting forth conditions and requirements peculiar to the Work.
Specifications – General Provisions, Stan dard Specifications, Technical Specif ications, Reference Speci fications, Supplemental Pro visions, and specifications in Supplemental Agreements between the Contractor and the Board.
Standard – The shaft or pole used to support street lighting luminaire, traffic signal heads, mast arms, etc.
Standard Plans – Details of st andard structures, de vices, or ins tructions ref erred to on the Plans or in Specifications by title or number.
Standard Specification s – The Standard Specifications for Pu blic Works Constr uction (SSPWC), the “Greenbook”.
State – State of California.
Stipulated Unit Price – Unit prices established by the Agency in the Contract Documents.
Storm Drain – Any conduit and appurtenances intended for the reception and transfer of storm water.
Street – Any road, highway, parkway, freeway, alley, walk, or way.
Subbase – A layer of s pecified mate rial of plann ed thickness between a base and the subgrade.
Subcontractor – An individual, firm, or corporation having a direct contract with the Contractor or with any other Subcontractor for the performance of a part of the Work.
Subgrade – For roadways, that portion of the roadbed on w hich pavement, s urfacing, base, subbase, or a layer of other mate rial is placed. For structures, the so il prepared to su pport a structure.
Supervision – Supervision, where used to indicate supervision by the Engineer, shall mean the performance of obligations, and the exercise of rights, specifically imposed upon and granted to the Agency in becoming a par ty t o the Contrac t. Except as specifi cally stated here in, supervision by the Ag ency shall not mean active and direct superintendence of details of the Work.
Supplemental Agreement – A written amendment of the Contract Documents signed by both parties.
Revised 6/15/17 Contract No. 3840-23 Page 50 of 134
Supplemental Provisions – See Special Provisions.
Surety – Any in dividual, firm, or co rporation, bound with and for the Contractor fo r the acceptable performance, execution, and completion of the Work, and for the satis faction of all obligations incurred.
Tonne – Also refe rred to as “metric to n”. Represents a unit of m easure in the I nternational System of Units equal to 1,000 kilograms.
Utility – Tracks, overhead or unde rground wires, pipelines, co nduits, ducts, or str uctures, sewers, or s torm drains owned , operated, or ma intained in or across a p ublic right of way or easement.
Work – That which is proposed t o be constructed or done u nder the Contract or permit, including the furnishing of all labor, materials, equipment, and services.
Working Drawings – Drawings showing the details not shown on the Plans which are required to be designed by the Contractor.
Working Night – A period o f night -time work, al lowed only on Su nday through Thursday, excluding holidays.
1-3 ABBREVIATIONS.
1-3.1 General. The abbreviation herein, together with others in g eneral use, are applicable to these Standard Specifications and to project Plans or other Contract Documents.
All abbreviations and symbols used on Plans for structural steel c onstruction shall conform to those given by the “M anual of Steel Construction” published by the American Institute of Steel Construction, Inc.
1-3.2 Common Usage
Abbreviation Word or Words Abbreviation Word or Words
ABAN .............................................................Abandon ABAND .......................................................Abandoned ABS ........................ Acrylonitrile – butadiene – styrene AC .................................................... Asphalt Concrete ACP ........................................... Asbestos cement pipe ACWS ..................... Asphalt concrete wearing surface ALT ................................................................Alternate APTS ................................. Apartment and Apartments AMER STD ................................... American Standard AWG ............... American Wire Gage (nonferrous wire) BC .................................................. Beginning of curve BCR ....................................... Beginning of curb return BDRY ............................................................Boundary BF ..................................................... Bottom of footing BLDG ........................................ Building and Buildings BM .............................................................. Benchmark BVC .................................... Beginning of vertical curve B/W ........................................................... Back of wall C/C ..................................................... Center to center CAB ...................................... Crushed aggregate base CAL/OSHA ............ California Occupational Safety and Health Administration
CalTrans ....... California Department of Transportation CAP .................................... Corrugated aluminum pipe CB ............................................................. Catch Basin Cb ........................................................................ Curb CBP ............................... Catch Basin Connection Pipe CBR ....................................... California Bearing Ratio CCR ............................ California Code of Regulations CCTV ............................................... Closed Circuit TV CES .......................... Carlsbad Engineering Standards CF ................................................................ Curb face CF ................................................................ Cubic foot C&G .................................................... Curb and gutter CFR ................................ Code of Federal Regulations CFS ......................................... Cubic Feet per Second CIP ......................................................... Cast iron pipe CIPP ................................................ Cast-in place pipe CL ............................................. Clearance, center line CLF .................................................... Chain link fence
Revised 6/15/17 Contract No. 3840-23 Page 51 of 134
CMB ............................... Crushed miscellaneous base CMC ......................................... Cement mortar-coated CML ............................................ Cement mortar-lined CMWD .................... Carlsbad Municipal Water District CO .................................................... Cleanout (Sewer) COL ..................................................................Column COMM ....................................................... Commercial CONC ........................................................... Concrete CONN ........................................................ Connection CONST .................................. Construct, Construction COORD ...................................................... Coordinate CSP ............................................ Corrugated steel pipe CSD ............................... Carlsbad Standard Drawings CTB ............................................ Cement treated base CV ............................................................ Check valve CY ............................................................... Cubic yard D .............................................................. Load of pipe dB ................................................................... Decibels DBL .................................................................. Double DF ............................................................... Douglas fir DIA ................................................................ Diameter DIP ..................................................... Ductile iron pipe DL ................................................................Dead load DR ...................................................... Dimension Ratio DT .................................................................Drain Tile DWG ............................................................... Drawing DWY .............................................................. Driveway DWY APPR ................................... Driveway approach E ....................................................................... Electric EA ........................................................................ Each EC ............................................................ End of curve ECR ................................................ End of curb return EF ................................................................ Each face EG ......................................................... Edge of gutter EGL .................................................. Energy grade line EI ................................................................... Elevation ELC ..................................... Electrolier lighting conduit ELT ........................................................ Extra long ton ENGR ....................................... Engineer, Engineering EP ................................................... Edge of pavement ESMT ........................................................... Easement ETB .......................................... Emulsion-treated base EVC ............................................... End of vertical curb EWA ............................... Encina Wastewater Authority EXC ............................................................ Excavation EXP JT ................................................. Expansion joint EXST ............................................................... Existing F .................................................................. Fahrenheit F&C ................................................... Frame and cover F&I .................................................. Furnish and install FAB ............................................................... Fabricate FAS ............................................... Flashing arrow sign FD ............................................................... Floor drain FDN ............................................................ Foundation FED SPEC ................................. Federal Specification FG ........................................................ Finished grade FH ............................................................. Fire hydrant FL ................................................................... Flow line FS ...................................................... Finished surface FT-LB .........................................................Foot-pound FTG .................................................................. Footing FW ............................................................ Face of wall G ........................................................................... Gas GA ..................................................................... Gauge GAL ............................................... Gallon and Gallons GALV ......................................................... Galvanized GAR ........................................... Garage and Garages GIP .............................................. Galvanized iron pipe GL ........................................ Ground line or grade line GM .............................................................. Gas meter GNV ............................................... Ground Not Visible GP ..................................................................Guy pole GPM ................................................ gallons per minute GR ...................................................................... Grade GRTG ............................................................... Grating GSP ........................................... Galvanized steel pipe H ............................................................ High or height HB .................................................................. Hose bib HC ................................................... House connection HDWL ........................................................... Headwall HGL .............................................. Hydraulic grade line HORIZ .......................................................... Horizontal HP ............................................................. Horsepower HPG ................................................ High pressure gas HPS ................................ High pressure sodium (Light) HYDR ............................................................ Hydraulic IE ......................................................... Invert Elevation ID ........................................................ Inside diameter INCL ...............................................................Including INSP .............................................................Inspection INV ...................................................................... Invert IP .................................................................... Iron pipe JC ..................................................... Junction chamber JCT .................................................................Junction JS ..................................................... Junction structure JT ......................................................................... Joint L ........................................................................ Length LAB ............................................................. Laboratory LAT ................................................................... Lateral LB ...................................................................... Pound LD ..................................................... Local depression LF ................................................................ Linear foot LH ............................................................... Lamp hole LL ...................................................................Live load LOL .............................................................Layout line LONG ........................................................Longitudinal LP ................................................................ Lamp post LPS ................................. Low pressure sodium (Light) LS ................................................................ Lump sum LTS .................................................... Lime treated soil LWD ............................... Leucadia Wastewater District MAINT ..................................................... Maintenance MAX ............................................................. Maximum MCR ............................................ Middle of curb return MEAS ............................................................. Measure MH ................................... Manhole, maintenance hole MIL SPEC .................................... Military specification MISC ..................................................... Miscellaneous MOD ................................................... Modified, modify MON ............................................................ Monument MSL .. Mean Sea Level (Reg. Standard Drawing M-12)
MTBM ......................... Microtunneling Boring Machine MULT ...............................................................Multiple MUTCD .....Manual on Uniform Traffic Control Devices
MVL ............................................... Mercury vapor light NCTD .............................. North County Transit District
Revised 6/15/17 Contract No. 3840-23 Page 52 of 134
NRCP .............................. Nonreinforced concrete pipe OBS ...............................................................Obsolete OC ................................................................ On center OD ..................................................... Outside diameter OE .............................................................. Outer edge OHE ................................................ Overhead Electric OMWD ................. Olivenhain Municipal Water District OPP ...............................................................Opposite ORIG ................................................................Original PB ................................................................... Pull box PC .................................................... Point of curvature PCC ....................... Portland cement concrete or point of compound curvature
PCVC ....................... Point of compound vertical curve PE ........................................................... Polyethylene PI .................................................. Point of intersection PL ............................................................. Property line PMB ............................ Processed miscellaneous base POC ...................................................... Point on curve POT .................................................... Point on tangent PP .............................................................. Power pole PRC .......................................... Point of reverse curve PRVC ............................ Point of reverse vertical curve PSI ......................................... Pounds per square inch PT .................................................... Point of tangency PVC .................................................. Polyvinyl chloride PVMT ........................................................... Pavement PVT R/W ....................................... Private right-of-way Q ........................ Rate of flow in cubic feet per second QUAD ....................................... Quadrangle, Quadrant R ....................................................................... Radius R&O ......................................................... Rock and oil R/W .......................................................... Right-of-way RA ...................................................... Recycling agent RAC ................................... Recycled asphalt concrete RAP ................................ Reclaimed asphalt pavement RBAC ............................. Rubberized asphalt concrete RC ................................................ Reinforced concrete RCB ...................................... Reinforced concrete box RCE ...................................... Registered civil engineer RCP ..................................... Reinforced concrete pipe RCV ........................................... Remote control valve REF ............................................................. Reference REINF ..............................Reinforced or reinforcement RES ...............................................................Reservoir RGE ........................ Registered geotechnical engineer ROW ....................................................... Right-of-Way RR ...................................................................Railroad RSE .............................. Registered structural engineer RTE .................................... Registered traffic engineer S .................................... Sewer or Slope, as applicable SCCP ............................... Steel cylinder concrete pipe SD ............................................................. Storm drain SDNR .............................. San Diego Northern Railway SDR ....... Standard thermoplastic pipe dimension ratio (ratio of pipe O.D. to minimum wall thickness)
SDRSD ......... San Diego Regional Standard Drawings
SE ...................................................... Sand Equivalent SEC .................................................................. Section SF ............................................................. Square foot SFM ................................................ Sewer Force Main SI ....................... International System of Units (Metric) SPEC ..................................................... Specifications SPPWC .......................................... Standard Plans for Public Works Construction
SSPWC ............................. Standard Specifications for Public Works Construction
ST HWY ................................................ State highway STA ................................................................... Station STD ............................................................... Standard STR ..................................................................Straight STR GR ................................................ Straight grade STRUC .......................................... Structural/Structure SW .................................................................Sidewalk SWD ...................................................... Sidewalk drain SY ............................................................ Square yard T .................................................................. Telephone TAN ................................................................. Tangent TC .............................................................. Top of curb TEL ............................................................. Telephone TF ........................................................... Top of footing TOPO ........................................................ Topography TR ........................................................................ Tract TRANS ......................................................... Transition TS ......................... Traffic signal or transition structure TSC ............................................. Traffic signal conduit TSS ........................................... Traffic signal standard TW ..............................................................Top of wall TYP .................................................................. Typical UE .............................................. Underground Electric USA .................................... Underground Service Alert VAR ..................................................... Varies, Variable VB ................................................................ Valve box VC .......................................................... Vertical curve VCP ................................................... Vitrified clay pipe VERT ............................................................... Vertical VOL .................................................................. Volume VWD ....................................... Vallecitos Water District W ........................ Water, Wider or Width, as applicable WATCH .............. Work Area Traffic Control Handbook WI ............................................................ Wrought iron WM ........................................................... Water meter WPJ .......................................... Weakened plane joint XCONN ............................................ Cross connection XSEC ..................................................... Cross section
Revised 6/15/17 Contract No. 3840-23 Page 53 of 134
1-3.3 Institutions.
Abbreviation Word or Words
AASHTO ............................. American Association of State Highway and Transportation Officials ACI ................................ ................................ ................................ .... American Concrete Institute AISC ................................ ................................ ...............American Institute of Steel Construction ANSI ................................ ................................ ................. American National Standards Institute AREA ................................ ................................ ........ American Railway Engineering Association ASME ................................ ................................ ........ American Society of Mechanical Engineers ASQ ................................ ................................ ................................ . American Society for Quality ASTM ................................ ................................ ........ American Society for Testing and Materials AWPA ................................ ................................ ............ American Wood Preservers Association AWS ................................ ................................ ................................ ... American Welding Society AWWA ................................ ................................ .................. American Water Works Association EEI ................................ ................................ ................................ ........... Edison Electric Institute EIA ................................ ................................ ................................ ...Electronic Industries Alliance EPA ................................ ................................ ......................... Environmental Protection Agency ETL ................................ ................................ ............................... Electrical Testing Laboratories FCC ................................ ................................ .................. Federal Communications Commission FHWA ................................ ................................ ......................... Federal Highway Administration GRI ................................ ................................ ............................ Geosynthetic Research Institute IEEE ................................ ................................ ... Institute of Electrical and Electronics Engineers IMSA ................................ ................................ ............International Municipal Signal Association ISSA ................................ ................................ ............ International Slurry Surfacing Association ITE ................................ ................................ ....................... Institute of Transportation Engineers NCHRP ................................ ........................... National Cooperative Highway Research Program NEMA ................................ ................................ .... National Electrical Manufacturers Association NSF ................................ ................................ ................................ .National Science Foundation OSHA ................................ ................................ ..Occupational Safety and Health Administration PPI ................................ ................................ ................................ .............. Plastics Pipe Institute RUS ................................ ................................ ................................ ............ Rural Utilities Service SAE ................................ ................................ ........................... Society of Automotive Engineers SSPC ................................ ................................ ........................... Society for Protective Coatings UL ................................ ................................ ................................ . Underwriters' Laboratories Inc.
1-4 UNITS OF MEASURE.
1-4.1 General. U.S. Standard Measures, also called U.S. Customary System, are the principal measurement system in these sp ecifications. However, certain material specifications and test requirements co ntained he rein use SI units specifically an d conversio ns to U.S. St andard Measures may or may not have been included in these circ umstances. When U.S. Standard Measures are not included in parent hesis, then the SI units shall contr ol. S.I. units and U.S.
Standard Measures in parenthesis may or may not be exactly equivalent.
Reference is also made to ASTM E 380 for definitions of various un its of th e SI syste m and a more extensive set of conversion factors.
Revised 6/15/17 Contract No. 3840-23 Page 54 of 134
1-4.2 Units of Measure and Their Abbreviations.
U.S. Customary Unit (Equal To) SI Unit
(Abbreviations) (Abbreviations)
1 mil (=0.001 in) ....................................................................................25.4 micrometer (m) 1 inch (in) ..............................................................................................25.4 millimeter (mm) 1 inch (in) ..............................................................................................2.54 centimeter (cm) 1 foot (ft) ................................................................................................0.3048 meter (m) 1 yard (yd) .............................................................................................0.9144 meter (m) 1 mile (mi) .............................................................................................1.6093 kilometer (km) 1 square foot (ft2) ..................................................................................0.0929 square meter (m2) 1 square yard (yd2) ................................................................................0.8361 square meter (m2) 1 cubic foot (ft3) .....................................................................................0.0283 cubic meter (m3) 1 cubic yard (yd3) ..................................................................................0.7646 cubic meter (m3) 1 acre ....................................................................................................0.4047 hectare (ha) 1 U.S. gallon (gal) .................................................................................3.7854 Liter (L) 1 fluid ounce (fl. oz.) ..............................................................................29.5735 millileter (mL) 1 pound mass (lb) (avoirdupois) ...........................................................0.4536 kilogram (kg) 1 ounce mass (oz) .................................................................................0.02835 kilogram (kg) 1 Ton (=2000 lb avoirdupois) ................................................................0.9072 Tonne (= 907 kg) 1 Poise ..................................................................................................0.1 pascal . second (Pa . s) 1 centistoke (cs) ....................................................................................1 square millimeters per second (mm2/s)
1 pound force (lbf) .................................................................................4.4482 Newton (N) 1 pounds per square inch (psi) .............................................................6.8948 Kilopascal (kPa) 1 pound force per foot (lbf/ft) .................................................................1.4594 Newton per meter (N/m)
1 foot-pound force (ft-lbf).......................................................................1.3558 Joules (J) 1 foot-pound force per second ([ft-lbf]/s) ...............................................1.3558 Watt (W) 1 part per million (ppm) .........................................................................1 milligram/liter (mg/L)
Temperature Units and Abbreviations
Degree Fahrenheit (°F): ........................................................................Degree Celsius (°C):
°F = (1.8 x °C) + 32 ...............................................................................°C = (°F – 32)/1.8
SI Units (abbreviation) Commonly Used in Both Systems
1 Ampere (A)
1 Volt (V)
1 Candela (cd)
1 Lumen (lm)
1 second (s)
Common Metric Prefixes
kilo (k) ....................................................................................................103 centi (c)..................................................................................................10-2 milli (m) ..................................................................................................10-3 micro () ................................................................................................10-6 nano (n) .................................................................................................10-9 pico (p) ..................................................................................................10-12
1-5 SYMBOLS.
Delta, the central angle or angle between tangents
Angle
% Percent
‘ Feet or minutes
“ Inches or seconds
1 Number
/ per or (between words)
° Degree
PL Property line
CL Centerline
SL Survey line or station line
Revised 6/15/17 Contract No. 3840-23 Page 55 of 134
SECTION 2 – SCOPE AND CONTROL OF WORK
2-1 AWARD AND EXECUTION OF CONTRACT. Award and execution of Contract will be as provided for in the Specifications, Instruction to Bidders, or Notice Inviting Bids.
2-2 ASSIGNMENT. No Contract or portion thereof may be as signed without consent of the board, except that the contractor may assign money due or whic h will accrue to it under t he contract. If given written notice, such assignment will be recognized by the Board to the extent permitted by law. Any assignment of money shall be subject to all proper withholdings in favor of the Agency and to all deduction s p rovided for in the Contract. All money wit hheld, whether assigned or not, shall be subject to being used by the Agency for completion of the work, should the Contractor be in default.
2-3 SUBCONTRACTS.
2-3.1 General. Each Bidder shall compl y with the Chapter of the Public Co ntract Code including Sections 4100 thr ough 41 13. The f ollowing e xcerpts or summaries of some of the requirements of this Chapter are included below for information:
The Bidder shall set forth in the Bid, as provided in 4104:
“(a) The name and location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of t he work or i mprovements, or a subcontra ctor l icensed by t he State of California who, under subcontract to the prime co ntractor, s pecially fabricates and installs a portion of the work or improvement according to detailed drawings containe d in the plans and specifications, in an amount in excess of one-half of 1 percent of the prime contractor’s total bid, or, in the case of bids or offers for the const ruction of streets or highways, including bridges, in exce ss of one-half of 1 percent of the p rime contractor’s total b id or ten thousand dollars ($10,000), whichever is greater.”
“(b) The portion of the work which will be done by each such subcontractor under this act. The prime contractor sha ll list only one s ubcontractor f or each such portion as is defined by the prime contractor in his bid.”
If the Contractor fails to spe cify a Subc ontractor or specifies more than one Subcontractor for the same portio n of the work to be performed under the Contract (in exces s of one-half of 1 percent of the Co ntractor’s total Bid), th e Contractor shall be quali fied to perform that portion itself, and shall perform that portion itself, except as otherwise provided in the Code.
As provided in Se ction 4107, no Contractor whose Bid is accepted shall substitut e any person as Subcontractor in place of the Subcontract or listed in the original Bid, except for causes and by procedu res established in Section 4107.5. This section provides procedures to co rrect a clerical error in the listing of a Subcontractor.
Section 4110 provides that a Contr actor violating any of the provisions of the Chapter violates the Contract and the Board may exercise the option either to cancel the Contract or assess the Contractor a penalty in an amount of not more than 10 percent of the subcontract involved, after a public hearing.
Revised 6/15/17 Contract No. 3840-23 Page 56 of 134
Should the Contractor fail to adhere t o the provisions requiring the Cont ractor to complete 50 percent of the contract p rice with its own o rganization, the Agen cy may at its sole discretion elect to cancel the cont ract or deduc t an amount equal to 10 percent of the value of the work performed in excess of 50 percent of the cont ract price by other than th e Contractor’s own organization. The Board shall be the sole body for determin ation o f a vi olation of these provisions. In any proceedings under this section, the pri me con tractor sh all be enti tled to a public hearing before the Board and shall be notified ten (10) days in ad vance of the time a nd location of said hearing. The determination of the Board shall be final.
2-3.2 Additional Responsibility. The Contractor shall give personal attention to the fulfillment of the Contract and shall keep the Work under its control.
The Contractor sh all p erform, with its own organization, Contract work amounting to at least 50 percent of the Contract Price except that any designated “Specialty Items” may be performed by subcontract, and th e amount of any suc h “Specialty Items” so perform ed may be deducted from the Contract Pri ce before computin g the amount required to be performe d by the Contractor with its o wn organization. “Specialty Items” will be ident ified by the A gency in the Bid or Proposal. Where an entire item is subcontracted, the value of work subcontracted will be based on the Contract Unit Price. When a portion of an item is subcontracted, the value of work subcontracted will be based on the estimated percentage of the Contract Unit Price. This will be determined from informat ion submi tted by th e Con tractor, and sub ject to approval b y the Engineer.
Before the work of any Subcontractor is started, the Contractor shall submit to the Engineer for approval a wri tten statement showin g the work to be su bcontracted giving the name an d business of each Subcontractor and description and value of each portion of the work to be so subcontracted.
2-3.3 Status of Subcontractors. Subcontractors sh all be cons idered employe es of the Contractor, and the Contractor shall be responsible for their work.
2-4 CONTRACT BONDS. Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below.
Bonds issued by a sure ty, who is authori zed to issue bonds in California, and whose bonding limitation shown in said circul ar is su fficient to provide bon ds in the amount r equired by t he Contract shall be deemed to be approved unless specifically rejected by the Agency. Bonds from all other sure ties shall be accompanied by all o f the docu ments enumerated in Code of Civil Procedure 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.
Before exec ution of the Contrac t, the Bidder shall file surety bonds wit h the Agency to be approved by the B oard in the amounts and for the pur poses noted below. Bonds issue d by a surety, who is au thorized to issue bonds i n California, and whose bonding limitation shown in said circular is sufficient to provide bonds in the am ount required by t he Co ntract shall be deemed to be approved unless spe cifically re jected by the Agen cy. Bonds from all other sureties shall be accompanied by all of the documents enumerated in Code of Civil Procedure 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.
Each bond sh all incorporate, by reference, the Contract and b e signed by both the Bid der and Surety and the signature of the authorized agent of the Surety shall be notarized.
Revised 6/15/17 Contract No. 3840-23 Page 57 of 134
The Contractor shall provide a faithful performance/warranty bond and payment bond (labor and materials bond) for this contract. The faithful performance/warranty bond shall be in a sum not less than o ne hundred percent of the t otal amount payable by th e terms of this contract. The Contractor shall provide bonds to secure payment of laborers and materials suppliers in a sum not less than one hundred percent of the total amount payable by the terms of this contract.
Both bonds shall extend in full force and effect and be retained by the Agency during this project until they are released according to the provisions of this section.
The faithful performance/warranty bond will be r educed to 25 percent of the original amount 30 days after recordation of the Notice of Completion and will remain in fu ll force and effect for the one-year warranty period and until all warranty repairs are completed to the satisfaction of th e Engineer. The bonds to se cure payment of laborers and materials suppliers shall be rele ased six months p lus 30 days after recordati on of the Notice o f Completion if all claim s have be en paid.
All bonds are to be p laced with a suret y insurance carrier a dmitted and aut horized to tr ansact the business of insurance in Cal ifornia and whose asset s exceed their li abilities in an amount equal to or in excess of th e amount of t he b ond. The bon ds ar e to contain the following documents:
1. An original, or a certified copy, of the un-revoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
2. A c ertified copy of the certificate o f aut hority of the insurer issued by the ins urance commissioner.
If the bid is accepted, the Agency may require a financial statement of the assets and liabilities of the insurer at the end of the quarter calendar year prior to 30 days next preceding the date of the execution of t he bond. The financial statement shall be made by an o fficer's certificate as defined in Sec tion 173 of th e Corporations Code. In the case of a fo reign insurer, the financia l statement may be verified by the oath of the princ ipal offic er o r manager residing within the United States.
Should any bond become in sufficient, the Contractor shall renew the bond with in 10 days after receiving notice from the Agency.
Should any Surety at any time be unsatisfactory to the Board, notice will be given the Contractor to that effect. No further payments shall be deemed due or will be made under the contract until a new Surety shall qualify and be accepted by the Board.
Changes in the Wor k or extensions of time, made pursuant to t he Contract, shall in n o way release the Contractor or Surety from its obligations. Notice of such changes or extensions shall be waived by the Surety.
2-5 PLANS AND SPECIFICATIONS.
2-5.1 General. The Contractor shall keep at the Work site a copy of t he Plans and Specifications, to which the Engineer shall have access at all times.
The specifica tions for the work includ e the General Provisions, Supplemental Provisions, Project Technica l Specifications , Carlsbad Engineering Standa rds ( CES), Standard Specifications for Pub lic Works C onstruction (SSPWC) and the la test supplements ther eto,
Revised 6/15/17 Contract No. 3840-23 Page 58 of 134
2021 edition as publish ed by the "G reenbook" Committee of Publ ic Wor ks Standards, In c., hereinafter designated "SSPWC", as amended.
The Plans shall consist of the c onstruction draw ings, Drawing No. 540-9 issued under this Contract.
The Standard Drawings consist of the latest ed ition of the San Diego Area Regional S tandard Drawings, hereinafter designated SDRSD, as issued by th e San Diego County Department of Public Works, together with the m ost recen t ed itions o f the City of Carlsbad Engineering Standards and Carlsba d Standard D rawings, as issued by the City of Carl sbad and the Carlsbad M unicipal Water Di strict, hereinafter des ignated as CES and CSD, respectively.
Modified standard drawings, if applicable, are en closed in the append ices to these General Provisions.
The Plans, Specifications, and other Contract Documents shall govern the Work. The Contract Documents are intended to be complementary and co operative. Anything specified in the Specifications and not shown on the Plans or shown on the Pl ans and not specifi ed in the Specifications, shall be as though shown on or specified in both.
The Plans sha ll be supplemen ted by s uch wo rking drawi ngs and sh op drawings a s ar e necessary to adequately control the Work.
The Contractor sha ll ascertain the existence of any co nditions affecting the c ost of the Work through a reasonable examination of the Work site prior to submitting the Bid.
Existing improvements visible at the Wor k site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed and disposed of by the Contractor.
The Contractor s hall, upon disc overing any er ror or omis sion in th e Plans or Sp ecifications, immediately call it to the attention of the Engineer.
2-5.2 Precedence of Contract Documents.
If th ere is a co nflict in the Contract Docu ments, the document highest in precedenc e shall control. The p recedence shall be the most recent edition of t he following documents listed in order of highest to lowest precedence:
1. Permits from other agencies as may be required by law.
2. Change orders, whichever occurs last.
3. Contract addenda, whichever occurs last.
4. Contract.
5. Carlsbad General and Supplemental Provisions.
6. Carlsbad Engineering Standards.
7. Technical Specifications.
8. Plans.
9. Standards Plans.
a. City of Carlsbad Standard Drawings.
b. City of Carlsbad Standard Drawings.
c. City of Carlsbad modifications to the San Diego Area Regional Standard Drawings. d. San Diego Area Regional Standard Drawings.
Revised 6/15/17 Contract No. 3840-23 Page 59 of 134
e. Traffic Signal Design Guidelines and Standards.
f. State of California Department of Transportation Standard Plans. g. State of California Department of Transportation Standard Specifications. h. California Manual on Uniform Traffic Control Devices (CA MUTCD).
10. Standard Specifications for Public Works Construction, as amended.
11. Reference Specifications.
12. Manufacturer’s Installation Recommendations
Detail drawings shall take precedence over general drawings.
Detailed plans and plan views shall have precedence over general plans.
2-5.2.1 Precedence of Caltrans Specifications . Where Caltrans specifications a re used to modify the SSPWC or are added to the SSPWC by the Contract Documen ts, the Caltrans specifications shall have preceden ce o nly in re ference to th e ma terials referred to in t he Caltrans specifications. The documents listed in Section 2 -5.2 above, in their order of precedence above, shall prevail over the Caltrans specifications in all other matters.
2-5.3 Submittals.
2-5.3.1 General. Submittals sh all be p rovided, at t he Contractor’s expe nse, as required i n 2-5.3.2, 2 -5.3.3 and 2 -5.3.4, when requir ed by the Plans o r Specia l Prov isions, or when requested by the Engineer.
One electronic (PDF) file shall be submitted. If revi sions are required, the En gineer will return one redlined copy for resubmission. Upon acceptance, the Engineer will return one e lectronic copy to the Contractor.
Materials shall nei ther be furnished nor f abricated, nor shall any work fo r which submittals are required be performed, before the required submittals have been reviewed and accepted by the Engineer. Neither review nor ac ceptance of submi ttals by the E ngineer shall reliev e the Contractor from responsibility for errors, omissions, or deviations from the Contract Documents, unless such deviations were specifically called to the atte ntion of the Engineer in the l etter of transmittal. The Contractor shall be responsible for the correctness of the submittals.
The Contractor shall all ow a m inimum of 20 working days for review of submittals u nless otherwise specified in the Special Provisions. Each submittal shall be accompanied by a letter of transmittal.
Each submittal shall be consecutively numbered. Resubmittals shall be labeled with the number of the original submittal followed by an ascending alphabetical designation (e.g. The label ‘4-C’ would indicate the third instance that the fourth submittal had been given to the Engineer). Each sheet of each submittal s hall be consecutively numbered. Each set of sho p drawin gs and submittals shall be accom panied by a lett er of transmittal on the Contractor’s letterhead. The letter of transmittal shall contain the following:
1. Project title and Agency contract number.
2. Number of complete sets.
3. Contractor’s certification statement.
4. Specification section number(s) pertaining to material submitted for review.
Revised 6/15/17 Contract No. 3840-23 Page 60 of 134
5. Submittal number (Su bmittal nu mbers shall be conse cutive i ncluding subsequent submittals for the same materials.)
6. Description of the contents of the submittal.
7. Identification of deviations from the Contract Documents.
8. The signature, printed name, title and company name of the Contractor’s representative.
The Contractor shall subscribe to and shall place the following certification on all submittals:
“I hereby ce rtify t hat the (equipment, material, procedure(s)) shown and marked in this submittal is that proposed to be incorporated into this Project, is i n compli ance w ith the Contract Documents, can be installed i n the allocated spaces, and is submitted for approval.”
Or
“
I hereby certify that the (equipment, material, procedure(s)) contained herein meet all requirements shown or specified in the Contract Documents, except for the following deviation(s):
.”
2-5.3.2 Working Drawings. Working drawings are drawings showing details not shown on the Plans which are required to be designed by the Contractor. Working drawings shall be of a size and scale to clearly show all necessary details.
Working drawings are required in the following sections:
TABLE 2-5.3.2
Item Section Number Title Subject
1 7-8.6.1 Dewatering Excavation Dewatering
2 7-10.4.1 Safety Orders Trench Shoring
3 7-10.4.8 Steel Plate Covers Steel Plate Bridging
4 300-3.2 Cofferdams Structure Excavation & Backfill
5 300-12.1 SWPPP SWPPP
6 303-1.6.1 General Falsework
7 303-1.7.1 General Placing Reinforcement
8 303-3.1 General Prestressed Concrete Construction
9 304-1.1.2 Falsework Plans Structural Steel
10 307-1.1 General Jacking Operations
11 307-2.1 General Tunneling Operations
12 306-8 Microtunneling Microtunneling Operations
13 601-2 Temporary Traffic Control Plan Traffic Control 14 02690 Temporary Sewer Bypass Pumping Sewer Bypassing
Working drawings listed above as Items 2, 3, 4, 7, 8, 9, 10, 11, 12, and 13 shall be prepared by a Civil or Structural Engineer registered by the State of California.
2-5.3.3 Shop Drawings. Shop draw ings are draw ings showing de tails of m anufactured or assembled products proposed to be incorporated into the Work. Shop drawings are required in the following sections and as specified in the Special Provisions:
Revised 6/15/17 Contract No. 3840-23 Page 61 of 134
TABLE 2-5.3.3
Item Section Number Title Subject
1 207-2.5 Joints Reinforced Concrete Pipe
2 207-8.4 Joints Vitrified Clay Pipe
3 304-1.1.1 Shop Drawings Structural Steel
4 304-2.1 General Metal Hand Railings
2-5.3.4 Supporting In formation. Supporting i nformation is information required b y the Specifications for the purposes of a dministration of the Contract, analysis for veri fication of conformance with the Specifications, the operation and maintenance of a manufactured product or system to be co nstructed as pa rt of the Work, an d other information as ma y be required by the Engineer. Three hard copies and one electronic (PDF) file of the supporting information shall be submitted to the En gineer prior to the start of the Work unless otherwise specif ied in the Special P rovisions or directed b y the Engineer. Supporting information for systems s hall be bound together and include all manufactured items for the system. If resubmittal is not required, one red lined copy will be returned to the Contractor. Supporting information shall consist of the following and is required unless otherwise specified in the Special Provisions:
1. List of Subcontractors per 2-3.2.
2. List of Materials per 4-1.4.
3. Certifications per 4-1.5.
4. Construction Schedule per 6-1 and Work Plan per 6-2.2.
5. Confined Space Entry Program per 7-10.4.4.
6. Concrete mix designs per 201-1.1.
7. Asphalt concrete mix designs per 203-6.1.
8. Controller Cabinet Wiring Diagrams per 701-17.2.2
9. Data, including, but n ot limited to, catalog sheets, m anufacturer’s brochures, technical bulletins, specifications, diagrams, product samples, and other information necessary to describe a system, product or item. Th is information is required f or irrigation systems, street li ghting systems, and traf fic si gnals, and may also be required for an y product, manufactured item, or system.
10. Temporary highline plan per Carlsbad Engineering Standards.
2-5.4 Record Dra wings. The Contractor shall maintain a complete "as -built" re cord set of blue-line prints, which shal l be corrected in red ink daily and s how every change from the original drawings and s pecifications and th e exact "as-built" locations, sizes a nd k inds of equipment, underground piping, conduits, valves, and all other work not visible at surface grade.
Prints for this purpose may be obt ained from the Agency at cost. The official record draw ing shall accurately reflect all changes and modi fications to the original plan. The Contractor shall formally submit the final record drawing at the final walk-through meeting. At the direction of the Engineer, the Contractor shall correct and revise the Record Drawings to accurately reflect field conditions. Re -submittal of th e Record Drawings shall be comple ted w ithin ten ( 10) working days of the fina l w alk-through mee ting date and sha ll reflect any add itional punch list items.
Payment for the upkeep, revision, and submittal of the record drawings shall be included in the lump sum price for mobilization.
2-6 WORK TO BE D ONE. The Contractor shall perform all work necessary to complete the Contract in a sati sfactory manner. Unl ess otherwise provided, the Contractor shall furnish all materials, equipment, tools, labor, and incidentals necessary to complete the Work.
Revised 6/15/17 Contract No. 3840-23 Page 62 of 134
2-7 SUBSURFACE DATA. All s oil and test hole data, water table elevations, and soil or groundwater analyses shown on the drawings or included in the Specifications apply only at the location of the test holes and to the depths indicated. Soil test reports for test holes which have been drilled are available for inspection at the office of the Engineer.
The Contractor may make independent investigations of the project site, including evaluation of the s oil o r groundwater con ditions and/or th e presence of ro ck, in order to characterize the subsurface conditions that may be enco untered to the Con tractor’s satisfaction. The costs for such investigations shall be considered included in the bid price and no additional compensation will be made therefor.
The indicated elevation of the water table is that which existed on the date when test hole data was determined. It is the Contractor’s responsibility to determine and allow for the elevation of groundwater at the time of project construction. A difference in elevation between groundwater shown in soil boring logs a nd groundwater actually encountered during construction will not be considered as a basis for extra work.
2-8 RIGHT-OF-WAY. Rights-of-way, easements, or rights-of-entry for the Work, when indicated on the Plans, will be provided by the Agency. Unless otherwise provided, the Contractor shall make arrangements, pay for, and assume all responsibility for acquiring, using, and restoring additional work area s and removing an d/or disposing of facilities temporarily required. T he Contractor shall indemnify and hold the agency harmless from all claims for damages caused by such actions.
2-9 SURVEYING.
2-9.1 General. The Contractor will perform and be responsible for the accura cy of surveying adequate for construction. Th e Contra ctor shal l set and preserve construction survey stak es and marks for the d uration of thei r usefulness. If any construction s urvey stakes are lost or disturbed and need to be replaced, such replacement shall be performed at the expense of the Contractor.
The Contractor shall notify the Engineer in writing a t least 2 Working Days before survey services in connection with the laying out of any portion of the Work. The Contractor shall set all stakes for line and grade.
Unless otherwi se s pecified in the Speci al Provisions, stak es wi ll be set and st ationed for alignments for pipelines (sewers, stor m d rains, potable water, recycled water) and their appurtenances, curbs, headers, structures, rough g rade, finish grade and right -of-way or easement boundaries. A corresponding cut or fill to finished grade (or flowline) will be indicated on a grade sheet.
2-9.2 Permanent Survey Mar kers. The Contractor sh all n ot cov er or d isturb perma nent survey mon uments or benchma rks without the c onsent of t he Engineer. Where the En gineer concurs, in writing, with the Contrac tor tha t protecting an existing monument in pl ace is impractical, the Contractor shall employ a licensed land surveyor or a reg istered civil e ngineer authorized to practice la nd surveying within the Stat e of Cali fornia, hereinafter Surveyor, to establish t he loca tion of the monument before it is distu rbed. The Con tractor shall h ave the monument replaced by the Surveyor no later than thirty (30) days after construction at the site of the replacement is co mpleted. The Surveyor shall file corner record(s) as required by §§ 8772 and 8773, et seq. of the California Business and Professions Code.
Revised 6/15/17 Contract No. 3840-23 Page 63 of 134
The Contractor shall have a Record of Survey prepared by the Surveyor and file it in conformance with §8700 - 8805 of the State of California Business and Professions Code when the Surveyor performs any surveying th at such map is required under §8762 of the State of California Business and Professions Code and whenever the Surveyor shall establish, set or construct any permanent survey monument. SDRS Drawing No. M -10 type monuments, bolts, spikes, leade d tacks and nails (when set in concrete), iron pipes, r einforcing steel and all monuments and marks that are at, or accessory to, property c orners and street centerlines are permanent survey monuments. The Record of Survey shall show all monuments set, control monuments used, the basis of bearings and all other data needed to determine the procedure of survey and the degree of accuracy attained by the field surveying including the unadjusted ratio of closure. The unadjusted ratio of closure shall not exceed 1 part in 40,000. The Record of Survey shall show the location and justification of location of all permanent monuments set and their relat ion to the street right -of-way. Record(s) of Survey (s) shall be submitted for the Engineer’s review and approval before submittal to the County Surveyor and before submittal to the County Recorder.
When a change is made in the finished elevation of the pavement of any roadway in whic h a permanent survey monument is locate d, the Contractor shall adjust the monument frame and cover to the new grade within 7 days of paving unless the Engineer shall approve oth erwise.
Monument frames and covers shall be protected during street sealing or painting projects or be cleaned to the satisfaction of the Engineer.
2-9.3 Line and Grade. All work shall conform to the lines, elevations, and grades shown on the Plans.
Three consecutive points set on the s ame slope shall be used together so that any v ariation from a straight grade can be d etected. Any such variation shall be reported to the Engineer. In the absence of such report, the Contractor shall be responsible for any error in the grade of the Work.
Grades for underground conduits will be set at the surface of the ground. The Contractor shall transfer them to the bottom of the trench.
2-9.4 Payment for Survey, Payment fo r survey work shal l be inclu ded in the bi d ite ms requiring the survey work and no additional payment will be made . Extension of unit prices for extra work shall include full compensation for attendant survey work and no additional payment will be made. Payment for the replacement of disturbed monuments and the filing of records of survey and/or corner records, including filing fe es, shall be i ncidental to the work necessitating the disturbance of said monuments and no additional payment will be made.
2-10 AUTHORITY OF BOAR D AND ENGI NEER. The Board has the fina l auth ority i n all matters affecting the Work. Within the scope of the Contract, the Engineer has the authorit y to enforce compliance with the Plans and Specifications. The Contractor shall promptly comply with instructions from the Engineer or an authorized representative.
The d ecision of the Engineer is final and binding o n all question s relating to : quantities; acceptability of material, equipment, or work ; execution, progress or sequence of work; and interpretation of the Pl ans, Specifications, or othe r draw ings. T his shall be precedent to a ny payment under the Contract, unless otherwise ordered by the Board.
Revised 6/15/17 Contract No. 3840-23 Page 64 of 134
2-10.1 Availability o f Records, The Con tractor shall, at no charge to the Agency, provide copies of all records in th e Contractor’s or subcontractor’s possession pertaining to the work that the Engineer may request.
2-10.2 Audit and Inspection, Contractor a grees to maintai n and /or m ake availab le, to the Engineer, within San Diego County, accu rate books and accounting records relative to all its activities and to contractually require al l subcontractors to this Contr act to do the s ame. The Engineer shall have the right to m onitor, as sess, and e valuate Contractor’s and its subcontractors’ performance pur suant to this Agre ement, said monit oring, asse ssments, and evaluations to include, but not be limited to, audits, in spection of pre mises, reports, contracts, subcontracts and interviews of Contrac tor’s s taff and the staff of all sub contractors to this contract. At any time during normal business hours and as often as the Engi neer may deem necessary, upon r easonable advance notice, Con tractor shall make availa ble to the Engineer for examination, all of its , and all subcontractors to this con tract, records wi th respe ct to all matters covered by this Contract and will permit the Engineer to audit, examine, copy and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, payrolls, records o f personnel, and other data relating to all matters covered by this Contract.
However, any such activities sha ll be carried ou t in a manner so as to not un reasonably interfere with Contractor’s ongoi ng business operation s. Cont ractor and all subcontractor s to this contract shall maintain such data and records for as long as may be required by applicable laws and regulations.
2-11 INSPECTION. The Work is sub ject to inspection and ap proval by the Engineer. The Contractor shall notify the Engineer before noon of the working day before inspection is required.
Work shall be done only in the presence of the Engineer, unless otherwise authorized. Any work done without p roper inspection wil l b e subj ect to rej ection. The Engineer and an y authorized representatives shall at all ti mes have access to the Work during its construction at s hops and yards as well as the project si te. The Contractor shall provide every reason able facility for ascertaining that the mate rials and workmanship are in accordance with these Specifications.
Inspection of the Work shall not relieve the Contractor of the obligation to fulfill all conditions of the Contract.
Revised 6/15/17 Contract No. 3840-23 Page 65 of 134
SECTION 3 – CHANGES IN WORK
3-1 CHANGES REQUESTED BY THE CONTRACTOR.
3-1.1 General. Changes in t he Plans and Specifications, requested in w riting by the Contractor, which do not materially affect the Work and which are not detrimental to the Work or to the interest s of the Agency , may be grant ed by the E ngineer. Nothing he rein shall b e construed as granting a right to the Contractor to demand acceptance of such changes.
3-1.2 Payment fo r Changes Requested by the Contract or. If such cha nges are granted, they shall be made at a reduction in cost or no additional cost to the Agency.
3-2 CHANGES INITIATED BY THE AGENCY.
3-2.1 General. The Agency may change the Plans, Specifications, character of the work, or quantity of work provided the total arithmetic dollar value of all such changes, both additive and deductive, does not exceed 25 pe rcent of th e Contract Price. Should it be come necessary to exceed this limitation, the change shall be by written S upplemental A greement bet ween the Contractor and Agency, unless both parties agree to proceed with the change by Change Order.
Change Orders shall be i n writ ing and state the dollar value of the chan ge o r estab lished method of payment, any adjustment in contract time of completion, and when negotiated prices are involved, shall provide for the Contractor’s signature indicating acceptance.
3-2.2 Payment.
3-2.2.1 Contract Unit Prices. If a change is o rdered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the work from that shown on the Plans or specified in the Specifications, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price.
If the actual quan tity of an it em of work covere d by a Contract Unit Pric e and constructed in conformance with t he Plans an d Specifications varie s from the Bid qua ntity by 50 percent or less, payment will be made at the Contract Unit Price. If the actual quantity of said item of work varies from the Bid quantity by more than 50 percent, payment will be made per Section 3-2.2.2 or 3-2.2.3 as appropriate.
If a change is ordered in an item of work covered by a Contract Unit Price, and such change does involve a substantial change in the character of the work from that shown on the Plans or specified in the Specifications, an adjustment in payment will be made per Section 3-2.4.
3-2.2.2 Increases of Mo re Than 50 Percent. Should t he actu al quantity of an item of w ork covered by a Contract U nit Price and con structed in conformance wi th the Plans and Specifications, exceed the Bid quantity by more than 5 0 percent, payment for the quantity in excess of 150 percent of the Bid qua ntity will be made on the basis of an ad justment in th e Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Ex tra Work per Section 3-3. The Extra Work per Section 3-3, basis of payment, shall not include fixed costs. Fixed costs shall be deemed to have been recovered by the Contractor through payment for 150 percent of the Bid quantity at the Contract Unit Price.
Revised 6/15/17 Contract No. 3840-23 Page 66 of 134
3-2.2.3 Decreases of More Than 50 Percent. Should the actual quantity of a n item of work covered by a Contract Uni t Price, and constructed in conformance wit h the P lans and Specifications, be less than 50 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If t he Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and t he Agency, or at the option of th e Engineer, on the b asis of Extra Work per Section 3 -3; howeve r, in no case will p ayment be less than would be made for the actua l quantity at the Contract Uni t Price nor more than would be made for 5 0 percent of the Bid quantity at the Contract Unit Price.
3-2.3 Stipulated Unit Prices. Stipulated Unit Prices are unit prices established by the Agency in the Contract Do cuments as di stinguished fr om Contract Unit Prices submitted by the Contractor. Stipulated Unit Prices may be used for the adjustment of Contract changes when so specified in the Special Provisions.
3-2.4 Agreed Prices. Agreed Prices are prices for new or unforeseen work, or adjustments in Contract Unit Prices per Section 3-2.2, established b y mut ual agreement between the Contractor and the A gency. If mutual agr eement cannot be reached, the Engineer may direct the Contractor to proceed on the basis of Extra Work in accordance per Section 3-3, except as otherwise specified in Sections 3-2.2.2 and 3-2.2.3.
3.2.4.1 Schedule of Values. Prior to construction, Contractor shall provide a schedule of values for all lump sum bid items that shall be used for the pur pose of progress payments. The prices shall be valid for the purpose of change orders to the project.
3.2.5 Eliminated Items. Should any Bid item be eliminated in its entirety, payment will be made to the Contractor for its actual costs incurred in connection with the eliminated item prior to notification in writing from the Engineer so stating its elimination. If material conforming to the Plans and Specifications is ordered by the Contractor for use in the eliminated item prior to the date of notification of elimination by the Eng ineer, and if th e order for that material cannot be canceled, payment will b e ma de to t he Con tractor for the actual cost of the mater ial. In this case, the ma terial sh all beco me the propert y of t he Agen cy. Payment will be made to the Contractor for its actual costs for an y further handling. If the material is returnable, the material shall b e returned a nd payment will be made to the Con tractor for the ac tual co st of charges made by the supplier for returning the material and for handling by the Contractor. Actual costs, as used herein, shall be computed on the basis of Extra Work per Section 3-3.
3-3 EXTRA WORK.
3-3.1 General. New or u nforeseen work wil l be classified as “extra work” when t he Engineer determines that it is not covered by Contract Unit Prices or stipulated unit prices.
3-3.2 Payment.
3-3.2.1 General. When the price for the extra work cannot be agreed upon, the Agency will pay for the extra work based on the accumulation of costs as provided herein.
Revised 6/15/17 Contract No. 3840-23 Page 67 of 134
3-3.2.2 Basis for Establishing Costs.
(a) Labor. The costs of labor will be the a ctual cost for wages of workers performing the extra work at the time the extra work is done, plus employer payments o f payr oll taxes, workers compensation ins urance, liab ility insurance , health and welf are, pe nsion, vacati on, apprenticeship funds, and other direct costs, resulting from Federal, State, or local laws, as well as assessments or benefits required by lawful collective bargaining agreements.
The use of a labor classification which would increase the extra work cost will not be permitted unless the Contractor esta blishes the n ecessity for such a dditional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equ ipment re ntal. T he labor cost for for emen shall be proportione d to all of their assigned work and only that applicable to extra work will be paid.
Nondirect labor costs, including superintendence, shall be c onsidered par t of the mar kup of Section 3-3.2.3 (a).
(b) Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available and de livered to the job si te in the quantities involved, plus sales tax, freight, and delivery.
The Age ncy rese rves the right t o approve mat erials a nd s ources of supply, or to supply materials to the Contr actor if necessary, for the progress of the Work. No ma rkup s hall be applied to any material provided by the Agency.
(c) Tool and Equipment Rental. No payment will be made for the use of to ols which have a replacement value of $200 or less.
Regardless o f ownersh ip, the ra tes and right -of-way delay factors t o b e u sed in determin ing rental and d elay costs shall be th e edit ion of the, “Labor Surcharge and E quipment Rental Rates” published by Caltrans, current at the time of the actual use of the tool or equipment. The right-of-way delay factors therein shall b e used as multipliers of the rental rates for determining the value of c osts for del ay to the Contr actor and subcontractors, if any. The labor surcharge rates published therein are not a part of this contract.
The renta l rates paid shall include the cost of fuel, oil, lubrica tion, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Necessary loading and transportation costs for equipment used on the extra work shall be included.
If equipment is used intermittently and, when not in use, could be returned to its rental source at less ex pense to the Agency t han hol ding it at the Work site, it shall be return ed, u nless the Contractor elects to keep it at the Work site, at no expense to the Agency.
All equipment shall be acceptable t o the Engineer, in good w orking condition, and suitable for the purpose for which it is to be used. Manufacturer’s ratings and approved modifications shall be used to classify equipment and it shal l be powered by a uni t of at least the minimum rating recommended by the manufacturer.
Revised 6/15/17 Contract No. 3840-23 Page 68 of 134
The reported rental time for equipment already at the Work site shall be the dur ation of its use on the extra work. This time begins when equipment is first put into actual operation on the extra work, plus the time required to move it from its previous site and back, or to a closer site.
(d) Other Items. The Agency may authorize ot her items which may be required on the ext ra work, including labor, services, material, and equipment. These items must be different in their nature from those required for the Work and be of a type not o rdinarily available from the Contractor or Subcontractors.
Invoices covering all such items in detail shall be submitted with the request for payment.
(e) Invoices. Vendors’ invoices for material, equipment rental and other expenditures shall be submitted wi th the request for paym ent. If the request for payment is not subst antiated by invoices or other documentation, the Agency may establis h the cost of the ite m involved at the lowest price which was current at the time of the report.
3-3.2.3 Markup.
(a) Work by Contract or. The f ollowing percentages s hall b e adde d to the Contractor's costs and shall constitute the markup for all overhead and profits:
1. Labor …………………………..… 20
2. Materials .……………………….. 15
3. Equipment Rental ……………… 15
4. Other Items and Expenditures .. 15
To the sum of the c osts and markups provided for in this section, 1 percent shall be add ed as compensation for bonding.
(b) Work by S ubcontractor. When all or an y part of the extra work is performed by a Subcontractor, the markup established in Section 3-3.2.3(a) shall be a pplied to the Subcontractor's actual cost of such work. A markup of 10 percent on the first $ 5,000 of the subcontracted portion of the extra work and a markup of 5 percent on work added in excess of $5,000 of the subcontracted portion of the extra work may be added by the Contractor.
3-3.3 Daily Re ports by Contr actor. When the price for the extra work cannot be agreed upon, the Contra ctor shall submit a daily report to the Engineer on forms approv ed by the Agency. Included are a pplicable de livery tickets, listing all labor, materi als, and equipment involved for that day, and other services and exp enditures when authorized. Payment for extra work will not be made until such time that the Contractor submits completed daily reports and all supporting documents to the Engineer. Failure to submit the daily report by the close of the next working day may waive any rights for that day. An attempt shall be made to reconcile the report daily, and it shall be signed by the Engineer and the Contractor. In the event of disagreement, pertinent n otes shall be enter ed by each par ty to exp lain points which cannot b e res olved immediately. Each party shall retain a signed copy of the report. R eports by Subcontractors or others shall be submitted through the Contractor.
The report shall:
1. Show names of workers, classifications, and hours worked.
2. Describe and list quantities of materials used.
Revised 6/15/17 Contract No. 3840-23 Page 69 of 134
3. Show type of e quipment, size, identification number, and hours of operation, including loading and transportation, if applicable.
4. Describe other services and expenditures in such detail as the Agency may require.
3-4 CHANGED CONDITIONS . The Contractor shall promptly no tify the Engineer of the following wor k site conditions (herein after called ch anged conditions) , in writing, upon their discovery and before they are disturbed:
1. Subsurface or latent physical conditions differing materially from those re presented in the Contract Documents;
2. Unknown physical con ditions of an unusual n ature differi ng m aterially from th ose ordinarily encountered a nd g enerally recognized a s i nherent in work of th e character being performed; and
3. Material differing from that represented in the Con tract whic h the Contractor believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be re moved t o a Class I, Cla ss II, or Class III dis posal site in accordance with provisions of existing law.
The Engineer will promptly investigate conditions which appear to be changed conditions. If the Engineer dete rmines that condition s are changed conditi ons and they will mater ially affect performance tim e, the Contractor , upon submitting a written request, will be granted a n extension of time subject to the provisions of 6-6.
If the Engineer determines that the conditions do not justify an adjustment in compensation, the Contractor will be notified in writing. This notice will also advise the Contractor of its obligation to notify the Engineer in writing if the Contractor disagrees.
The Contractor’s failure to give notice of changed conditions promptly upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith.
The Contractor shall not be entitl ed to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, or for the happening of any event, thing, occurrence, or other cause, unless the Contractor shall have first given th e Engineer due wri tten noti ce of potential c laim a s hereinafter specified. Compliance with this s ection sh all not be required as a prereq uisite to notice provi sions in Section 6-7.3 Contract Time Accountin g, nor to any cl aim that is based on d ifferences in measurement or errors of computation as to contract quantities. The written notice of potential claim for changed conditions shall be submitted by the Contractor to the Engineer upon their discovery and prior to the time that the Contractor p erforms the w ork giving r ise t o the pote ntial claim. The Contractor’s failure to give written notice of potential claim for changed conditions to the agency upon their dis covery and before they are di sturbed shall cons titute a w aiver of all claims in connection therewith.
The Contractor shall p rovide the City with a written documen t c ontaining a description of th e particular circumstances giving rise to the potential claim, the reasons for which the Contractor believes additional compensation may be due and nature of any and all costs involved within 20 working days of the date of s ervice of th e written notice of potential claim for changed conditions. Verbal notifications are disallowed.
The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-12655:
Revised 6/15/17 Contract No. 3840-23 Page 70 of 134
“The un dersigned cer tifies tha t the above statements a re made in f ull cognizance of the California False Claims Act, Government Code Sections 12650-12655. The undersigned further understands and agrees that this potential claim, unless resolved, must be r estated as a claim in response to the City’s proposed final estimate in order for it to be further considered.”
By: ___________________________________ Title: ______________________________
Date: _________________________________
Company Name: ______________________________________________________________
The Contractor’s est imate of costs m ay be updated when actual costs are known. The Contractor shall submit substantiation of its actual costs to the Engineer within 20 working days after the affected work is completed. Failure to do so shall be sufficient cause for denial of any claim subsequently filed on the basis of said notice of potential claim.
It is the intention of this section that differences between the parties arising under and by virtue of the contract be brought to the attention of the Engineer at the earliest p ossible time in order that such matters be settled, if possible, or other appropriate action promptly taken.
3-5 DISPUTED WORK. The Contractor shall give the Agency written notice of potential claim prior to commencing any disputed work. Failure to give said notice shall constitute a waiver of all claims in connection therewith. If the Contractor and the Agency are unable to reach agreement on disputed work, the Agency may direct the Contractor to proceed with the Work.
Prior to pro ceeding with dispute r esolution pursua nt to Public Contract Code provis ions specified hereinafter, the contractor shall att empt to resolve all disputes informally through the following dispute resolution chain of command:
1. Project Inspector
2. Construction Manager
3. Deputy City Engineer
4. City Engineer
5. City Manager
The Contractor shall submit a complete report within 20 wor king days after completion of the disputed work stating its position on the claim, the contract ual basis for the claim, along with all documentation supporting the costs and all other evidentiary materials. At each level of claim or appeal of claim the City will, within 10 working days of receipt of said claim or appeal of claim, review the Contract or’s report and respond with a pos ition, req uest additional information or request that the Contr actor meet and present its r eport. When additional information o r a meeting is requested, the City will provide its position within 10 working days of receip t of said additional information or Contractor’s presentation of its report. The Contractor may appeal each level’s p osition up to th e City Manager aft er whic h the Contra ctor may proceed under the provisions of the Public Contract Code.
The authority within the dispute res olution c hain of command is limited to recommending a resolution to a claim to t he City Manager. Actual approval of the claim is subject to the change order provisions in the contract.
Revised 6/15/17 Contract No. 3840-23 Page 71 of 134
All claims by the -Contractor shall be resolved in accordance with Public Contract Code section 9204, which is set forth below:
9204. (a) The Legislature finds and declares that it is in the best interests of the sta te and i ts citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b) Notwithstanding any other l aw, incl uding, but not l imited to, Art icle 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (comme ncing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c) For purposes of this section:
(1) “Claim” means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief fr om damages or penalties for delay assessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. (2) “Contractor” means any typ e of cont ractor within the meaning of Chapter 9 ( commencing with Section 7000) of D ivision 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project. (3) (A) “Public entity” means, without limitation, except as provided in su bparagraph (B), a state agency, department, of fice, division, bureau, board, or c ommission, the Calif ornia State University, the University of California, a city, including a charter city, county, including a charter county, cit y and county, including a ch arter city a nd county, district, special district, public authority, political subdivision, public corporation, or nonprofit t ransit corporation who lly owned by a public agency and formed to carry out the purposes of the public agency. (B) “Public entity” shall not include the following:
(i) The Depar tment of Wa ter Resources a s to any project under the ju risdiction of that department.
(ii) The Department of Transportation as to any project under the jurisdiction of that department. (iii) The Department of P arks and Rec reation as to any project under th e j urisdiction of that department.
(iv) The Department of Corrections and Rehabi litation with respect to any project under its jurisdiction pursuant to Chapt er 11 (commencing with Se ction 7000) of Title 7 of Pa rt 3 of the Penal Code.
(v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority.
(4) “Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind. (5) “Subcontractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Div ision 3 of t he Business and Professions Code w ho either is in direct contract with a contractor or is a lower tier subcontractor. (d) (1) (A) Upon receipt of a cl aim pursuant to this section, the public entity to which the claim applies shall conduct a rea sonable review of the claim and, within a peri od not to exceed 45 days, shall pro vide the claimant a written statement identif ying what portion of t he claim is
Revised 6/15/17 Contract No. 3840-23 Page 72 of 134
disputed and wh at port ion is u ndisputed. Up on receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision. (B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a writte n statement identifying the disputed portion a nd the undisputed port ion of the cl aim, and the governing body does not meet wit hin the 45 days or wit hin the mutually agreed to extension of time following receipt of a claim sent b y registered mail or certifi ed mail, ret urn receipt requested, the public entity shall have up to three days following the next d uly publicly noticed meeting of the governing b ody after the 45-day period, or ex tension, expires to p rovide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the pub lic entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2) (A) If the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an info rmal conference to meet and confer for settlem ent of the issues in dispute. Upon receipt of a demand in writing sent by regist ered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in di spute and the portion that is undisputed. Any payment due on an undisputed porti on of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed port ion of the claim, as identified by the contrac tor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sh aring the asso ciated costs equally. The pu blic entity and claimant s hall mutuall y agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the part ies cannot agree upon a m ediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regar d to the dis puted portion of the claim. Each p arty shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.
If media tion is unsuccessful, the p arts of the claim r emaining in dispute shall be subject to applicable procedures outside this section.
(C) For purposes of this section, mediation includes any nonbinding pr ocess, including, but not limited to, neutral evaluation or a di spute review board, in which an independent third party or board a ssists the p arties in dispute resolution throu gh negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section. (D) Unless otherwise agreed to by the public entity and the contractor in writing, the med iation conducted pursuant to this section shal l excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E) This section does not preclude a public entity from requiring ar bitration of disputes under private arbi tration or t he Public Works Contract Arbitrati on Program, if mediation u nder this section does not resolve the parties’ dispute.
(3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherw ise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied b y reason of the public enti ty’s fa ilure to have respond ed to a claim, or its fai lure t o otherwise meet the t ime requirements of this section, shall not co nstitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant. (4) Amounts not paid in a timely manner as req uired by thi s section shall bear interes t at 7 percent per annum.
Revised 6/15/17 Contract No. 3840-23 Page 73 of 134
(5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity becaus e privity of c ontract does not exi st, the contractor ma y p resent to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier sub contractor on behalf of the subcon tractor. The subcontractor requesting that the claim be presented to the public entity shall furnish r easonable documentation to support the claim. Within 45 days of receipt of this written request, the contrac tor shall no tify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f) A waiver of the rig hts granted by this section is void and contrary to p ublic policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed direct ly to the comm encement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contrac tual provisions do n ot confl ict with or o therwise impair the timef rames and procedures set forth in this section.
(g) This section applies to contracts entered into on or after January 1, 2017.
(h) Nothing in this section shall impose liabi lity upon a pu blic entity that makes loans or grants available through a competitive a pplication process, fo r the failur e of an awardee to meet its contractual obligations.
(i) This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extend s that date.
In addition, all claims by Contr actor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code, Division 2, P art 3, C hapter 1, Artic le 1.5 (commencing with Section 20104) which is set forth below.
ARTICLE 1.5 RESOLUTION OF CONSTRUCTION CLAIMS
20104. (a)(1) This ar ticle applies to all public works claims of three hundred s eventy-five thousand dollars ($375,000) or less which arise between a contractor and a local agency. (2) This article shall not apply to any claims resulting from a contract between a contractor and a public agency when the public agency has elected to resolve any disputes pur suant to Article
7.1 (commencing with Section 10240) of Chapter 1 of Part 2. (b)(1) "Public work" has the same meaning as in Sections 3100 and 3106 of the Civil Code, except that "public work" does not include any work or improvement contracted for by the state or the Regents of the University of California.
(2) "Claim" means a separate demand by the contractor for (A) a time extension, (B) payment of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public work and payment of w hich is not oth erwise expressly provided for or the
Revised 6/15/17 Contract No. 3840-23 Page 74 of 134
claimant is not otherwise entitled to, or (C) an amount the payment of whi ch is disputed by the local agency.
(c) The provisions o f t his article or a summa ry thereof shall be s et forth in the plans or specifications for any work which may give rise to a claim under this article. (d) This article applies only to contracts entered into on or after January 1, 1991.
20104.2. For any claim subject to this article, the following requirements apply:
(a) The claim shall be in writing and include the documents necessary to substantiate the claim.
Claims must be filed on or before the date of final payment. Nothing in this sub division is intended to extend the time limit or supersede notice r equirements oth erwise provided by contract for the filing of claims.
(b)(1) For claims of less than fifty th ousand dollars ($50,000), the local agency sha ll respond in writing to any written claim within 45 day s of receipt of the claim, or may request, in writing, within 30 d ays of r eceipt of the c laim, any add itional documentation sup porting the claim or relating to defenses to the claim the local agency may have against the claimant. (2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the claimant within 15 days after receipt of the f urther documentation or within a p eriod of time no great er than that taken by the claimant in producing th e additional in formation, whichever is greater.
(c)(1) For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the c laim or relatin g to defenses to the claim the local agency may have against the claimant.
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the claimant within 30 days after receipt of the f urther documentation, or within a p eriod of time no grea ter than that taken by the claimant in produci ng the addition al in formation or requested documentation, whichever is greater.
(d) If the claimant disput es the local ag ency's written response, or the l ocal agency fails to respond within the time prescribed, the claimant may so notify the local agency, in writing, either within 15 days of receipt of the local agency's response or within 15 days of the local a gency's failure to respond within the time pre scribed, respectively, and demand an informal conference to meet and confer for settlement of the issu es in dispute. Upon a demand, the local agency shall schedule a meet and confer conference within 30 days for settlement of the dispute. (e) Following the meet and confer conference, if the claim or any portion remains in dispute, the claimant may file a claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of P art 3 of Divi sion 3.6 of Title 1 of the Govern ment Code.
For purposes of those provisions, the running of the period of time within which a claim mu st be filed sha ll be tolled from t he time t he claimant s ubmits his or her written claim pursuant to subdivision (a) until the time that claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process. (f) This article does not apply to t ort claims an d nothing in this article is intended nor shall be construed to c hange the time periods for filing tort claims or actions specified b y Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 9 10) o f Part 3 of Division 3.6 of Title 1 of the Government Code.
Revised 6/15/17 Contract No. 3840-23 Page 75 of 134
20104.4. The following pr ocedures are es tablished for all civil actions f iled to resolve claims subject to this article:
(a) Within 60 days, but no earlie r than 30 days, follo wing the filing or responsive pleadings, the court shall submit the matter to non -binding mediation unless w aived by mutu al stipulation of both parties. T he m ediation process s hall provide for the selection wit hin 15 days by both parties of a disinterested third person a s mediator, shall be commenced within 30 days of the submittal, an d shall be concluded with in 15 days from the commencement of the mediatio n unless a time requirement is extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to select a mediator within the 15-day period, any party may petition the court to appoint the mediator.
(b)(1) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (c ommencing with Section 1141.10) of Title 3 of Part 3 of the Code of C ivil Procedure, no twithstanding Secti on 1141.11 of t hat code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Par t 4 of the Code of Ci vil procedure) shall apply to any proceeding brought under the subdivision consistent with the rules pertaining to judicial arbitration.
(2) Notwithstandi ng a ny other provision of law, upon stipulation of the p arties, arbitrators appointed for purposes of this article sh all b e experienced in constr uction law, a nd, upon stipulation of t he parties, mediators and arbitrators sh all be paid necessary and reasona ble hourly rates of pay not to exce ed their customary rate, and such fees and exp enses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no event shall these fe es or expenses be paid by state or county funds.
(3) In addition to Chapter 2.5 (commencing with Section 1141.10) Title 3 of Part 3 of the Code of Civil Procedure, any party who after receiving an arbitration award requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, pay the attorney's fees of the other party arising out of the trial de novo. (c) The cour t may, upon request by any party, order any witnesses to participate in t he mediation or arbitration process.
20104.6. (a) No lo cal agency shall fail to pay money as to any p ortion of a cla im wh ich is undisputed except as otherwise provided in the contract. (b) In any suit filed under Section 20104.4, the local agency shall pa y interest at the legal rate on any arbitration award or judgment. The interest s hall begin to accrue on the date the suit is filed in a court of law.
Although not to be construed as proceeding under extra wor k provisions, the Contractor shall keep and furnish records of disputed work in accordance with Section 3-3.
Revised 6/15/17 Contract No. 3840-23 Page 76 of 134
SECTION 4 – CONTROL OF MATERIALS
4-1 MATERIALS AND WORKMANSHIP.
4-1.1. General. All materials, parts, an d equipment furnished by the Contract or in the Work shall be new, high grade, and fre e from defects. Quality of work shall be in accordance with the generally accepte d standards. Material and work qua lity sh all be s ubject to the E ngineer’s approval.
Materials and wor k quality not conforming to the requirem ents of the Specifications shall be considered defective and will be subject to rejection. Defective work or material, whether in place or not, shall be removed immediately from the site by the Contractor, at its expense, when so directed by the Engineer.
If the Contractor fails to repla ce any defective or damaged work or material a fter reasonable notice, the Enginee r may cause such work or materials to be replaced. The replacement expense will be deducted from the amount to be paid to the Contractor.
Used or secondhand materials, parts, and equipment may be used only if permitted b y the Specifications.
4-1.2 Protection of Work and Mate rials. The Contractor shall provide and mai ntain storage facilities a nd employ su ch measures as will prese rve the specifi ed quality and fitness of materials to be used in the Work. Stored materials shall be reasonably accessible for inspection.
The Contractor shall also adequately protect new and existing work and all items of equipment for the duration of the Contract.
The Contractor shall not, without th e Agency’s consent, assign, sell, mortgage, hypothecate, or remove equipment or materials which have b een in stalled or del ivered a nd whi ch may be necessary for the completion of the Contract.
4-1.3 Inspection Requirements.
4-1.3.1 General. Unless otherwise specified, inspection is required at the source for such typical materials and fabricated items a s bituminous paving m ixtures, structural conc rete, metal fabrication, m etal casting, weld ing, concrete pipe manufacture, pr otective coating a pplication, and similar shop or plant operations.
Steel pipe in sizes less than 6 inches and vitrified clay and cast-iron pipe in a ll s izes are acceptable upon certification as to compliance with the Specifications, subject to sampling a nd testing by t he Agency. Stand ard i tems of e quipment such as elec tric motors, conveyors, elevators, plumbing fixtures, etc., are sub ject to inspection at the job site only. Special items of equipment suc h as designed elec trical panel boards , large pumps, sewage plant eq uipment, etc., a re su bject to inspection a t the sou rce, normally only for performance testing. The Specifications may require inspection at the source for other items not typical of those listed in this section.
The Contractor shall provide the Engineer free and safe acc ess to any and all parts of work at any time. Such free and safe access shall include means of safe access and egress, ventilation, lighting, shoring, dewatering and all elements pertaining to the safety of persons as contained in
Revised 6/15/17 Contract No. 3840-23 Page 77 of 134
the State of California, California Code of Regulations, Title 8, Industrial Relations, Chapter 4, Division of Industrial Safet y, Subchapter 4, Construction Safety Orders a nd such other safety regulations as may apply. Contractor shall furnish Engineer with such information as may be necessary to keep the Engineer fully in formed regardin g p rogress and manner of work and character of materials. Inspection or testing of the whole or any portion of the work or materials incorporated in the work shall not relieve Contractor from any obligation to fulfill this Contract.
4-1.3.2 Inspection of Materials Not Locally Produced. When the Co ntractor intends t o purchase materials, fabricated products, or equipment from sources located more than 50 miles outside th e geographi cal limits of the A gency, an inspe ctor or accredited t esting l aboratory (approved by the Engineer), sha ll be engaged by t he Contractor at i ts expense, to inspect the materials, equipment or process. This approval shall be obtained before producing any material or equipment. The inspector or representative of the testing laboratory shall judge the materials by the requirement s of th e Plans and Specifications. The Contra ctor shall for ward reports required by the Engineer. No material or equipment shall be shipped nor shall any processing, fabrication or treatment of such materials be d one without proper inspec tion by the approv ed agent. Approval by said agent shall not relieve the Contractor of responsibility for complying with the Contract requirements.
4-1.3.3 Inspection by the A gency. The Agency will provide all i nspection and testi ng laboratory services within 50 miles of the geo graphical li mits of the A gency. For pr ivate contracts, all costs of inspection at the source, includi ng salaries and m ileage costs, shall be paid by the permittee.
4-1.4 Test of Material. Before incorporation in the Work, the Contr actor shall submit samples of materi als, as the E ngineer may r equire, at no c ost to the Ag ency. Th e Contractor, at its expense, shall deliver the materials for testing to the place and at the time designated by the Engineer. Unless otherwise provided, all initial testing w ill be performed under the direction of the Engineer, and at no expense to the Contractor. If the Contractor is to provide an d pay for testing, it will be stated in the Specifications. For private contracts, the testing expense shall be borne by the permittee.
The Contractor shall notify the Engineer in writing, at least 15 days in advance, of its intention to use materials for which tes ts are specified, t o allow sufficient time to perform the tests. The notice shall name the proposed supplier and source of material.
If the notice of intent to use is sent before the materials are available for testing or inspection or is sent so far in advance that the materials on hand at the time will not last but will be replaced by a new lot prior to u se on the Work, it will be the Contr actor’s responsibility to renotify the Engineer when samples which are representative may be obtained.
Except as s pecified in these P rovisions, the Ag ency will bear the cost o f testing of locall y produced materials and/or on-site workmanship where the results of such tests meet or exceed the req uirements ind icated in the Stan dard Specificati ons, Technical Spe cification, and any Supplemental Provisions. The cost of all other tests shall be borne by the Contractor.
At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before the delivery is started. All materials proposed for use ma y be inspected or tested at any time during their preparation and use. If, after incorporating such materials into the Work, it is foun d that sourc es of supply tha t have been a pproved do n ot fur nish a uniform product, or if the product from any source proves unacceptable at any time, the Contractor shall
Revised 6/15/17 Contract No. 3840-23 Page 78 of 134
furnish app roved material from other approved source s. I f any product pr oves unacceptable after improper storage, handling or for any other reason it shall be r ejected, not incor porated into the work and shall be removed from the project site all at the Contractor’s expense.
Compaction tests may be made by the Engineer and all costs for tests that meet or exceed the requirements of the specifications shall be borne by the Agency. Said tests may be made at any place along the work as deemed necessary by the Engineer. The costs of any retests made necessary by noncompliance with the specifications shall be borne by the Contractor.
4-1.5 Certification. The Engine er may waive materia ls testing requirements of the Specifications and accept the manufacturer’s wri tten certi fication that the materials to be supplied meet those requirements. Material test data may be required as part of the certification.
4-1.6 Trade Names or Equals. The Contractor may supply any of the materials specified or offer an equivalent. The Engineer shall determine whether the material offered is equivalent to that specified. Adequate time shall be allowed for the Engineer to make this determination.
Whenever any particular material, pro cess, or equipment is indicated by patent, proprietary or brand name, or by name of manufacturer, such wording is used for the purpose of facilitating its description and shall be deemed to be followed by the words “or equal”. A listing of materials is not intended t o be com prehensive, or i n order of prefere nce. The C ontractor may offer any material, proce ss, or equipment cons idered to be equivalent to th at indicated .
The substantiation of offers shall be submitted as provided in the Contract Documents.
The Contractor shall, at its expense, furnish data concerning items offered by it as equivalent to those specified. The Contr actor shall have the mat erial tested as r equired by the Engineer to determine that the quality, strengt h, p hysical, chemical, or othe r cha racteristics, including durability, finish, efficiency, dimensions, service, and su itability are such that the item wi ll fulfill its intended function.
Test methods shall be subject to the approval of the Engineer. Test results shall be reported promptly to the Engineer, who will evaluate the results and determine if the substitute item is equivalent. The Engineer’s findings shall be final. Installation and use of a substitute item shall not be made until approved by the Engineer.
If a substitute off ered by the Contractor is not found to be equal to th e specified material, the Contractor shall furnish and install the specified material.
The specified Contract completion time shall not be affected by any c ircumstance developing from the provisions of this section.
The Contractor is responsible for the satisfactory performance of substituted items. If, in the sole opinion of th e Engin eer, the su bstitution is det ermined to be unsatisfactory in performance, appearance, durab ility, compatibility with asso ciated items, avail ability of repai r parts and suitability of application the Contractor shall remove the substituted item and replace it with the originally specified item at no cost to the Agency.
4-1.7 Weighing and Meterin g Eq uipment. All scales and me tering equipment us ed for proportioning materials shall be insp ected for accuracy and certified within the past 12 months by the State of California Bureau of Weights and Measures, by the County Director or Sealer of Weights and Measures, or by a scale mechanic registered with or licensed by the County.
Revised 6/15/17 Contract No. 3840-23 Page 79 of 134
The accuracy of t he work of a scale ser vice agency, e xcept as stated herei n, shall meet the standards o f the Califo rnia Business and Pro fessions Co de and the Cal ifornia Code of Regulations pertaining to weighing devices. A certificate of compliance shall be presented, prior to operation, to the Engineer for approval and shall be renewed when ever requir ed by the Engineer at no cost to the Agency.
All scales shall be arranged so they may be read easily from th e operator’s platform or area.
They shall indicate the true net weight without the appli cation of any factor. The figures o f the scales shall be clearly legible. Scales shall be accurate to within 1 percent when tested with the plant shut down. Weighing eq uipment shall be so insulated against vibration or moving of other operating equipment in the plant area that the error in weighing with the entire plant running will not exceed 2 percent for any setting nor 1.5 percent for any batch.
4-1.8 Calibration of Testing Eq uipment. Testing equipme nt, such as, but n ot limited to pressure gages, metering devices, hydraulic systems, force (load) measuring instruments, and strain-measuring devices shall be calibrated by a testing agency acceptable to the Engineer at intervals no t to exc eed 12 months an d following repair s, modific ation, or relocation of the equipment. Calibration certificates shall be provided when requested by the Engineer.
4-1.9 Construction Materials Dis pute Resolution (Soils, Rock Materials, Concre te, Mortar and Related Materials, Masonry Materials, Bituminous Materials, Rock Products , and Modified Asphalts). In the interest of safety and public value, whenever credible evidence arises to c ontradict the test values of materials, the Agency and the C ontractor will initiate an immediate and cooperative investigation. Test values of materials are resul ts of the materials’ tests, as def ined by the se Sp ecifications or by the spe cial pr ovisions, r equired to acc ept t he Work. C redible evidence is process obs ervations o r test v alues gathered u sing ind ustry accepted practices. A contradiction exi sts whenever test values or process observations of the same or similar materials are diverse enough such that the work ac ceptance or per formance becomes suspect. The i nvestigation shall allow access to all test results, procedures, and facilities relevant to the disput ed work and consider all av ailable information and , when necessary, g ather new and additional information in an a ttempt to determine the validity, the cause, a nd if necessary, the remedy to the con tradiction. If the c ooperative investigation reaches any re solution mechanism ac ceptable to b oth the Age ncy a nd the Contr actor, the contradiction s hall b e considered r esolved and the cooperative investigation conc luded.
Whenever the cooperative investigation is unable to reach resolution, the investigation may then either conclude wit hout resolution or conti nue by written notification of one party to the other requesting the implementation of a resolution process b y com mittee. The co ntinuance of the investigation shall be contingent upon recipient’s agreement and acknowledged in writing within 3 ca lendar days after receiving a request. Wit hout ac knowledgement, the invest igation shall conclude without resolution. The committee shall consist of three State of California Registered Civil Engineers. Within 7 calendar days after the written request notification, the Agency and the Contractor wil l each select one engineer. With in 14 calendar days of the written request notification, the two selected engineers will select a third engineer. The goal in selectio n of the third member is to complem ent the professional experience of the fi rst two engineers. Should the two engineers fa il to select th e third engineer, the Agency an d the Contractor shall each propose 2 engineers to be the third member within 21 calendar days after t he written request notification. T he first tw o eng ineers previ ously s elected shall then select one of the fo ur proposed engineers in a blind draw. The com mittee shall be a c ontinuance of th e cooperative investigation and will re -consider all available info rmation and if necessary, gather n ew and additional information to determine the validity, the cause, and if necessary, the remedy to the contradiction. The committee will focus upon the performance adequacy of the material(s) using
Revised 6/15/17 Contract No. 3840-23 Page 80 of 134
standard engineering pr inciples and practice s and to ensure public v alue, the committee may provide engineering recommendations as necessary. Unless otherwise agreed, the commit tee will have 30 calendar days from its formation to complete their review and submit their findings.
The final resolution of the committee shall b e by majority opi nion, i n writi ng, sta mped and signed. Should t he final resolu tion not be unanimous, the diss enter may a ttach a written, stamped, and signed minority opinion. Once started, the resolution process by committee shall continue to full conclusion unless:
1. Within 7 days of the formation of the committee, the Agency and the Contractor reach an acceptable resolution mechanism; or
2. Within 14 days of the formation of the committee, the initiating party withdraws its written notification and agrees to bear all investigative related costs thus far incurred; or
3. At any point by the mutu al agreement of the Agency and the C ontractor. Unless otherwise agreed , the Con tractor sh all bear and maintain a reco rd for all the investigative costs until resolution. Should t he investigation discover assignable causes for the contradiction, the assignable party, the Agency or the Contrac tor, shall bear all costs associated with t he investigation. Should assignable causes for the contradi ction extended to both parties, the investigation will assign costs cooperatively with each party or when necessary, equally. Should the investigation substantiate a contradiction without assignable cause, t he investigation will assign costs cooperatively with each pa rty or when necessary, equal ly. Should th e i nvestigation be unable to su bstantiate a contradiction, the initiator of the investigation shall bear all investigative costs. All c laim notification r equirements of the contract pertaining to the con tradiction s hall be suspended until the investigation is concluded.
4-2 MATERIALS TRANSPORTATION, HANDLING AND STORAGE. The Contractor shall order, purchase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, prepare storage a rea(s), store, handle, protect, move, relocate, remove and dispose excess of all materials used to accomplish the Work. Materials shall be deli vered to the site of the work only during working hours, as defined in Sectio n 6-7.2, and shall be accompanied by bills of lad ing that shall clearly state for e ach del ivery: the n ame of the Contractor as consignee, the project name and number, address of d elivery and name of consignor and a description of t he material(s) shipped. Prior to storage of any materials whi ch ha ve been shipped to or b y the Contractor to any location within the Agency’s boundaries the Contractor shall provide the Engineer a copy of lease agreements for each property where such materials are stored. The leas e agreement shall clearly state the term of the l ease, the descr iption of materials allowed to be stored and shall provide for the removal of the materials and restoration of the storage site within the time allo wed for t he Work. A ll such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the locatio n of the site o n which the materials are stored. Los s, da mage or deterioration of all stored materials shall be the Contractor’s responsibility. Conformance to the requirements of this section, both within and outside the limits of work are a part of the Work.
The Engineer shall have the right to verify the suitability of materials and their proper storage at any time during the Work.
Revised 6/15/17 Contract No. 3840-23 Page 81 of 134
SECTION 5 – UTILITIES
5-1 LOCATION. The Agency and affected utility comp anies have, b y a search o f know n records, endeavored to locate an d indicate on the Plans, all utilities which are known to exist within the limi ts of the work. However, the accura cy and/or completeness of the nature , siz e and/or location of utilities indicated on the Plans is not guaranteed.
Where underground main dist ribution cond uits such as water, gas, sewer, electric po wer, telephone, or cabl e television are shown on th e Plans, the Contractor shall assume that every property parcel will be served by a service connection for each type of utility.
As provided in Section 4216 of the California Government Code, at least 2 working days prior to commencing a ny excavation, the Contractor shall contact the regional not ification c enter (Underground Service Alert of Southern California) and obtain an inquiry identification number.
The Ca lifornia Department of Transportation is no t required by Section 4 216 to bec ome a member of th e region al notification cente r. The Contra ctor s hall contact it for lo cation of its subsurface installations.
Prior to pipeline excavation, t he Cont ractor shall deter mine, by potholing, the location s and depths of all utilities which are shown on the Contract Documents or have been marked by the utility owners and which may affect or be affected by its operations. The Contractor shall pothole all service connections, utilities that cross or parallel (within 5 feet) the proposed construction, and all connection points to exi sting utilities. T he Contractor shall reco rd th e material size (outside diameter), type, and horizontal and vertical locations (bearing and slope) and submit the data and allow time for the Engineer’s review in accordance with Section 2-5.3.
If no separate pay item is provided in the Contract for potholing, full compensation for such work shall be considered included in the bid item of work requiring th e potholing and no sep arate payment shall be made therefor.
5-2 PROTECTION. The Contractor sh all n ot inter rupt the servic e function or disturb the support of a ny uti lity without authority from the ow ner or order from the Agency. A ll val ves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff.
Where protection is required to ensure suppo rt of ut ilities located as shown on th e Plans or in accordance with Section 5-1, the Contractor shall, unless otherwise provided, furnish and place the necessary protection at its expense.
Upon learning of the exi stence and location of any utility omitted from or shown incorrectly on the Plans, the Contractor shall immedia tely notify the Engineer in writing. When authorized by the Engineer, support or protection of the utility will be paid for as provided in Section 3-2.2.3 or 3-3.
The Contractor shall im mediately not ify the Engin eer and the utility owner if any utility is disturbed or damaged. The Contractor shall bear the costs of repair or replacement of any utility damaged if located as noted in Section 5-1.
When placi ng concrete around or contiguous to any n on-metallic utility installation, th e Contractor shall at its expense:
Revised 6/15/17 Contract No. 3840-23 Page 82 of 134
1. Furnish and install a 2-inch cushion of exp ansion joint material or other similar resilient material; or
2. Provide a sleeve or ot her opening which will result in a 2-inch minimum-clear annular space between the concrete and the utility; or
3. Provide other acceptable means to prevent embedment in or bonding to the concrete.
Where concrete is used for backfill or for structures which would result in embedment, or partial embedment, o f a metallic utility insta llation; or where the coating, be dding or other cathodic protection system is exposed or damaged by the Contractor’s operations, the Contractor shall notify the Engineer and arr ange to secure the advice of the affected utility owner regarding the procedures required to maintain or restore the integrity of the system.
5-3 REMOVAL. Unless other wise spe cified, the Contractor sh all remov e all inte rfering portions of utilities shown on the Plans or indicated in the Bid documents as “abandoned” or “to be abandoned in place”. Before starting removal operations, the Contractor shall ascertain from the Agency whether the abandonment is complete, and the costs involved in the removal and disposal shall be included in the Bid for the items of work necessitating such removals.
The costs involved in the removal and disposal shall be considered incidental to the bid items of work necessitating such removals and no separate payment shall be made therefor, unless a bid item for “Removal” is specifically included in the bid proposal.
5-4 RELOCATION. When feasible, the owner s responsible for utilities within th e area affected by the Work will complete their nece ssary installations, relocations, repairs, or replacements before commencement of work by the Contract or. When the Plans or Specifications indicate that a utility inst allation is to be relocated , altered, or cons tructed by others, the Agency will conduct all negotiations with the owners and work will be done at no cost to the Contractor, except for manhole frame and cover sets to be brought to grade as directed and approved by the City. Utilities which are relocated in order to avoid in terference shall be protected in their position and the cost of such protection shall be included in the Bid for the items of work necessitating such relocation.
After award of the Contract, portions of utilities which are found to interfere with the Work will be relocated, altered or reconstructed by the owne rs, or the Engineer may order changes in the Work to avoid interference. Such changes will be paid for in accordance with Section 3-2.
When the Plans or Specifications provide for the Contractor to a lter, relocate, or r econstruct a utility, all costs for such work shall b e included in the Bid for the items of work necessitating such work. Tempo rary o r permanent relocation or alteration of utilitie s requested b y the Contractor for its convenience shall be its responsibility and it shall make all arrangement s and bear all costs.
The utility owner will relocate service connections as necessary within the limits of the Work or within tem porary constru ction or slope easement s. Wh en directed by the Engineer , the Contractor sha ll arrange for the relocation of ser vice connections as necessary between the meter and property line, or between a meter and t he limits of temporary construct ion or s lope easements. The relocat ion of suc h ser vice connections will be pa id for in accordance with provisions of Section 3-3. Pay ment will include the res toration of a ll ex isting imp rovements which may be aff ected thereb y. The Contractor may agree with the own er of any util ity to disconnect and r econnect interfering service con nections. The Agency will not be involved in any such agreement.
Revised 6/15/17 Contract No. 3840-23 Page 83 of 134
In conformance with Section 5-6 the Contractor shall coordinate the w ork with uti lity agencies and companies. P rior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contrac tor, the Contractor shall place all curb or curb and gutter that is a part of the work and adjacent to the location where such utility structures are shown on the plans and are noted as being located, relocated or are oth erwise shown as installed by others. In order to minimize delays to the Contractor caused by the failure of other parties to re locate utilities that interfere with th e construction, the Contract or, upon t he Engineer’s approval, may be pe rmitted to temporarily omit the portion of work affect ed by the utility. If such temporary omission is approved by the Engineer, the Contractor shall place survey or other physi cal cont rol markers su fficient to locate the c urb or c urb and gutter to the satisfaction of the ut ility agency or company. Such tempo rary omission shal l be f or the Contractor’s convenience and no addi tional compensation will be allowed therefore or for additional work, materials or delay ass ociated with the t emporary omission. The po rtion th us omitted shall be constructed by the Contrac tor immediately following the relocation of the utility involved unless otherwise directed by the Engineer.
5-5 DELAYS. The Contractor shall notify the Engineer of its construction schedule insofar as it affects the prot ection, removal, or relocation of utilities. Said notificat ion shall be in cluded as a par t of the cons truction schedule required in S ection 6-1. The Contra ctor shall n otify the Engineer in writing of any subsequent changes in the construction schedule which will affect the time available for protection, removal, or relocation of utilities.
The Contractor will not be e ntitled to d amages or additional payment fo r delays attributable to utility relocations o r alterations if correctly locat ed, noted , and compl eted in accordance with Section 5-1.
The Contractor may be given an extension of t ime fo r unforeseen delays attributable to unreasonably protracted interfere nce by u tilities in pe rforming work correctly shown on the Plans.
The Agency will assume responsibility for the timely removal, relocation, or protection of existing main or t runkline ut ility facilit ies within th e area affec ted by the Work if such utiliti es are n ot identified in the Contract Document s. The Contractor will not be as sessed liquidated damages for any delay caused by failu re o f A gency to pr ovide for the timely removal, relocation, or protection of such existing facilities.
If the Contractor s ustains loss due to de lays attributa ble to int erferences, relocations, or alterations n ot covered by Section 5-1, which could not hav e be en avoided by the jud icious handling of forces, equipment, or plant, there shall be paid to the Contractor such amount as the Engineer may fi nd to be fair and reason able com pensation for such part of the Co ntractor’s actual loss as was unavoidable and the Contractor may be granted an extension of time.
5-6 COOPERATION. When necessary, the Contractor shall so conduct its operations as to permit access to the Work site and provide time for utility wor k to be a ccomplished during the progress of the Work. C ooperation with CMW D and City staff w ill be required for all wor k affecting existing utilit y systems or facilities and prior to water utility shutdowns, sewer bypass operations, testing and inspections, and project completion.
Revised 6/15/17 Contract No. 3840-23 Page 84 of 134
SECTION 6 – PROSECUTION, PROGRESS,
AND ACCEPTANCE OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COM MENCEMENT OF WORK . Except as otherwise provided herein and unless otherwise prohib ited by permits from other agencies as may be requ ired by l aw the Con tractor shall begin work with in t en (10) cal endar days afte r receipt of the "Notice to Proceed".
6-1.1 Pre-Construction Meeting. After, or up on, notification of contract award, the Engin eer will set the time and location for the Preconstruction Meeting. Attendance of the Contractor’s management personnel responsible for the man agement, administration, and execution of th e project is mandatory f or t he me eting to be conv ened. Failure of the Contractor t o have the Contractor’s responsible project personnel attend the Preconstruction Meeting will be grounds for default by Contractor per Section 6-4. No separate payment will be made for the Contractor’s attendance at the meeting. The notice to proceed will only be issued on or after the completion of the preconstruction meeting.
6-1.1.1 Baseline Construc tion S chedule. The Contr actor shall prepare t he Baseli ne Construction Schedule as a Critical Path Method (CPM) Schedule in the precedence d iagram method (ac tivity-on-node) f ormat and su bmit the schedule in accord ance with 2 -5.3. The schedule shall:
A. Be pre pared u sing a commercially available, Windows compatible software program, “Suretrak” by Primavera or “Project” by Microsoft Corporation or approved equal.
B. Be prepared in hard copy (p aper) and electronic (Adobe PDF) format and free of file locking, encryption or any other protocol that would impede full access to the data and labeled wi th the project n ame and number, the Contractor’s name and th e date of preparation.
C. Begin with the date projec ted for the Notice to Proceed and conclude with the date of final completion conforming with the Contract time.
D. Depict a time-scaled n etwork diagram of all ac tivities, l ogic r elationships of interdependent activities, and milestones comprising the comple te period of Work with tasks on the vertical axis and their d urations o n the horizontal ax is. Use distinctive texture patterns or line types to show the critical path within the Contract time. Include a tabular listing of each activity and its identification number, description, duration, early start, early finish, late st art, late finish, t otal float , and all p redecessor and successor activities. The numb er of a ctivities w ill co mmunicate the Contractor’s pla n fo r project execution, accurately describe the project work and allow monitoring and evaluation of progress and time impacts. Activity descriptions shall accurately define the work planned for the activity. Activity durations shall not be shorter than 1 working day or longer than 15 working days unless approved by the Engineer.
E. Include detail of all pro ject phasin g, st aging and sequencing i ncluding all miles tones necessary to define beginning and ending of each phase or stage and constraints which may impact any activity. Include time allowances for coordination with utility companies and other agencies, equipment and material deliveries, submittal reviews and approvals,
Revised 6/15/17 Contract No. 3840-23 Page 85 of 134
traffic contro l setup and phasing, Work p erformed by othe rs, inspections, testing and commissioning, corrective work, and any non-work periods.
Float or slack time within the schedule is available without charge or compe nsation to the party or contingency that first exhausts it. A schedule which shows a project duration longer than the Contract time will not be accepted by the Engineer.
If the Baseline Construction Schedule does not meet the requirements of these specifications, the Contractor shall revise the schedule and resubmit it to the Engineer. Failure to obtain the Engineer’s approval of the schedule within twenty-five (25) Working Days after the date of the Preconstruction Meeting shall be grounds to consider the Contractor in default of the Contract per 6-4. The time required by the Engineer to review the initial Baseline Construction Schedule submittal will not be included in the 25 Working Days. The Engineer shall complete subsequent reviews of the revised schedule and progress updates within 5 working days of receipt.
The Contractor shall not be permitted to commence any excavation o r demolition activities until the Engineer accepts the Baseline Construction Schedule. For each day of delay beyond the 25 Working Days after the Preconstruction Meeting that the Baseline Construction Schedule is not accepted by the Engineer, the Contractor shall be charged $100 through a deductive Change Order.
The Engineer’s response to each review will consist of one of the following:
“Accepted.” The Contractor may proceed with the Work.
“Accepted with Comments.” The Contractor may proceed with the Work, but must revise and resubmit the schedule prior to submittal of the first progress payment application.
The Engineer’s acceptance of the schedule is a condition precedent to payment of any progress payment.
“Not Accepted.” The Contractor may not proceed with the Work and must revise and resubmit the schedule.
6-1.1.2 Schedule Updates and Revisions. The Contractor shall meet with the Engineer during the last week of each month to agree upon the completion level of each activity as a b asis for progress payments. Schedule updates shall conform wi th th e requirements for t he initia l submittal in 6-1.1.1 and shall:
A. Show the actual dates of each activity start and/or finish during the month. The schedule update shall include specific notation for any changes in actual dates after they are first reported.
B. Report the p ercent complete for each activity in progress at t he end o f the month as determined by the Engineer.
C. Include a list and explanation of all changes made to the activities, dates or interconnecting logic.
D. Include activity and network rev isions reflecting the Chan ge Orders approved in the previous month as a greed u pon d uring the r eview a nd acceptance of t he Change Orders.
Revised 6/15/17 Contract No. 3840-23 Page 86 of 134
The Engineer’s responses to the progress schedule updates shall be as described in 6 -1.1.1.
The Contractor shall proceed with Work and request payment fo r the progress schedule updates as described therein.
Should the actual or projected progress of the Work exceed 5 percent of the Contract time, the Contractor shall prepare and submit a revised Baseline Construction Schedule independently of and prior to the next progress schedule update. The Contractor shall provide an explanation for each change made to the schedule.
If the Contrac tor fails to submit the progress schedule updates as required herein, the Contractor may elect to pr oceed with the Work at its o wn risk and shall forfeit payment for t he progress schedule update until compliance is met. If the Con tractor elects to delay or cease Work after failure to submit the pr ogress sche dule upd ates, a ny res ulting delay, impact, or disruption to the Work will be the Contractor’s responsibility.
6-1.1.3 Interim Revisio ns. Should the actual or project ed progress of the Work exceed 5 percent of the Contract Time, the Contractor shall prepare and submit a revised Ba seline Construction Schedule independently of and prior to the next progress schedule update with a list and explanation of each change made to the schedule. The submittal, schedule review and acceptance requirements of 6-1.1.2 shall apply,
6-1.1.4 Late Completion or Milestone Dates. If a schedule update indicates a completion date later than the Contract time or contrac tually required milest one completion date, t he Agency may withhold Liquidated Damages fo r the number of days late. Should a subsequent schedule update which removes all or a portion of th e delay be “Accepted” by the Engineer, all or the allocated portion of the p reviously held Liquidated Damages shall be released in the monthly payment to the Contractor immediately following such acceptance.
6-1.1.5 Final Sched ule Upda te. The Contractor s hall p repare and submit a final schedule update when one hu ndred perc ent of the Work is com pleted. The update must accurately represent the actual dates for all activities. The fina l schedule upda te sha ll b e prepare d and reviewed in ac cordance with 6-1.1.2. Acceptance of the final schedule update is requi red for release of funds retained per 9-3.2.
6-1.1.6 Three-Week Look Ahead Schedules. The Contractor shall submit a detailed 3-week look ahead schedule prior to each progress meeting throughout project duration. The schedules shall be revised weekly to identify the construction activities and durations for each bid it em of work for the current week and the succeeding two weeks. The Contractor shall revise the schedule to include additional activities or actual progress when so requested by the Engineer.
6-1.1.7 Measurement and Payment. The Contractor’s preparation, revision and maintenance of the Construction Schedule are incidental to the Work and no separate payment will be made therefor.
6-2 PROSECUTION OF WORK. To minimize public inconvenience and possible hazard and to restore street and other work areas to their original condition and state of usefulness as soon as practicable, the Contractor shall diligently prosecute the Work to completion. If the Engineer determines that the C ontractor is failing to p rosecute th e W ork to the proper extent, the Contractor shall, upon orders from the Engineer, immediately take steps to remedy the situation.
All costs of prosecuting the Work as described herein shall be included in the Contractor’s Bid.
Revised 6/15/17 Contract No. 3840-23 Page 87 of 134
Should the Contractor fail to take the necessary steps to fully accomplish sa id purposes, after orders of the Engineer, the Engineer may suspend the work in whole or part, until the Contractor takes said steps.
As soon as possible under th e provisions of th e Specifications, the Contractor shall backfill all excavations and restore to usefulness all improvements existing prior to the start of the Work.
If Work is suspended through no fault of th e Agency, all ex penses and losses incurred by the Contractor during such suspensions shall be borne by the Contractor. If the Contr actor fails to properly pro vide for public safety, t raffic, an d pro tection of the Work dur ing pe riods o f suspension, the Agency may elect to do so, and deduct the cost the reof from monies due the Contractor. Such actions will not relieve the Contractor from liability.
The Contractor shall incorporate non-work days, moratoriums or special events specified in the Contract Documents in to the Construction Schedule required by Sect ion 6 .1. No additional payment, ad justment o f bid prices or adjustm ents of contract time will be allo wed as a consequence of these events.
6-2.1 Order of Work. The work to be done shall consist of furn ishing all labor, equipment and materials, and performing all operations necessary to complete the Work as shown or specified on the Contract Documents. The work descriptions in this section are an overview only and shall not relieve the Contractor from it s responsibilities to conduct all coordination and perform the Work in acc ordance with the Contract Documents. The Contractor shall conduct the following general work activities:
1. Submit construction schedule, schedule of values, working drawings, submittals, shop drawings, sewer bypass p lan, and/or highlin ing plan . Secure necessary permits and approvals in accordance with the Contract Documents.
2. Conduct surveying and staking of pipeline alignments, locations of appurtenances, limits of right -of-way or easements and pre -construction video an d photographs. Conduct Underground Service Alert (DigAlert) notification and utility mark -out. Mobilize labor force, materials and equipment for subsequent phases of Work and install temporary facilities and BMPs, traffic control and excavation safety measures.
3. Pothole all utilities that cros s or p arallel (within 5 feet of) planned excavations an d immediately notify the Engineer of any p otential conflicts. Submit p otholing data in accordance with Section 2-5.3. Pavement saw-cutting or excavation shall not commence at any construction heading until the project alignments have been staked and existing utilities have been potholed and confirmed by the Contractor to have no conflict with the Work.
4. Furnish and install manual transfer switch and associated receptacle.
5. Permit, furnish and operate temporary standby generator.
6. Decommission, demolish, and remove existing permanent standby generator.
7. Furnish and install new genset for permanent standby assignment and associated electrical improvements.
8. Decommission and remove temporary standby generator upon completion of all start up testing, power system studies and all ACPD permitting requirements to operate the permanent standby generator.
6-2.2 Construction Phasing. The following construction phase guidelines are provided for the Contractor’s use in developing the construction schedule and a Work Plan that describes the labor, materials, equipment and procedures to conduct the Work. The phasing guidelines listed
Revised 6/15/17 Contract No. 3840-23 Page 88 of 134
herein are not intended to be a complete list of all construction activities and shall not relieve the Contractor from its re sponsibilities to coordinate and perform the Wo rk, r evise t he phasing descriptions, or to d evelop additional phases or revise the order of phasing as necessary t o complete the Work in its entirety in accordance with the Contract Documents.
The Con tractor shall d evelop a de tailed Work Plan descr ibing the materials, equip ment and procedures for each phase of the Work and submit the Work Plan in accordance with Section 2-5.3. Any modification of the phasing described below shall be approved by the Engineer.
6-2.2.1 Phasing Criteria . The Contractor shall accommodate the following criteria into the construction schedule and Work Plan:
1. All construction activities s hall me et the sc heduling restrictions identified in these specifications or as determined by the City during review of the Contractor’s Work Plan.
Refer to Section 6-2.
2. Contractor shall su bmit a Site Work Plan. The Work Plan shall identify staging areas; describe the methods f or the protec tion of private imp rovements and existing utilities; and include a listing of materials and equipment and other pertinent details necessary to complete the work.
3. Contractor shall submit a sewer bypass plan and an excavation dewatering plan.
4. Contractor shall maintain two traffic lanes through the project site outside of work hours.
One lane of travel with a flagging operation may be allowed during work hou rs, subject to approval of the Contractor’s traffic control plan submittal.
5. Contractor sh all c oordinate w ith cul tural resources and a rchaeological monitors for observation during all excavation activities.
6. Excavations must be b ackfilled or securely shored and plated at the end of each work day.
7. When water or fire service interruptions are necessary and approved, no customer shall be without water for long er than 8 hours. If a planned water service shutdown duration exceeds 8 hours, the Contractor shall submit a highline plan for approval and provide all highlining prior to the shutdown.
8. Excavations shall be backfilled and base paved within 3 working days of completing the respective pipeline segment.
9. Site restoration shall be completed within ten working days of completion of construction of all improvements.
6-2.3 Project Meetings. The Engineer will establish the time and location of weekly Project Meetings. The C ontractor’s Representative shal l a ttend each Project Meeting. The Project Representative shall be the individ ual determi ned under Section 7-6, “The Contract or’s Representative”. No separate payment f or attend ance of th e C ontractor, the Contract or’s Representative or any other employee or subcontractor or subcontractor’s employee at these meetings will be made. If the Contractor’s Representative cannot attend, the Contractor shall notify the Engineer a minimum of 24 hours prior to the start of the scheduled meeting. If the Contractor does not provide the required notification, the Contractor shall pay the Agency’s costs for staff and consultants that attended. The Contractor sh all be charged a minimum of 2 hours of each attendee’s time via a deductive Change Order.
6-3 SUSPENSION OF WORK.
6-3.1 General. The Work may be suspended in whole or in part when determined by the Engineer that the suspension is necessary in the interest of the Agen cy. The Contractor shall
Revised 6/15/17 Contract No. 3840-23 Page 89 of 134
comply immediately w ith any w ritten order of the Engin eer. Such s uspension shall be wi thout liability to the Contractor on the part o f the Agency except as otherwi se specified in Section 6-6.3.
6-3.2 Archaeological an d Paleontolog ical D iscoveries. The Contractor sha ll coordinate with the Archaeological and Cultural Monitor during excavation activities.
If discovery is made of items of archaeological or paleontological interest, the Contractor s hall immediately cease excavation in the ar ea of discovery and shall not cont inue until ordered by the Engineer. W hen resumed, excavation operati ons within the area of discovery shall be as directed by the Engineer.
Discoveries which may be encountered may include, but not be limited to, dwelling sites, stone implements or other artifacts, animal bones, human bones, and fossils.
The Contractor shall be entitled to an e xtension and compensation in accordance with Section 6-6.
6-4 DEFAULT BY CONTRACTOR. If the Contra ctor fails to promptly begin procurement or delivery of material and equipment, to commence the Work within the time specified, to maintain the rate of delivery of material, to e xecute the Work in t he manner and at such lo cations as specified, or fails to maintain the Work schedule which will insure the Agency’s interest, or, if the Contractor is not carrying out the intent of the Contract, the Agency may serve writ ten notice upon the Contractor and the Surety on its Faithful Performance Bond demanding sati sfactory compliance with the Contract.
The Contract may be cance led by the Bo ard without liability for damage, when in the Board’s opinion the Contractor is not complying in good faith, has become insolvent, or has assigned or subcontracted any part of the W ork wit hout th e Board’s cons ent. In the ev ent o f s uch cancellation, the Contractor will be paid the actual amount due based on Contract Unit Prices or lump sums bid and the quantity of the Work completed at the time of cancellation, less damages caused to the Age ncy by acts of the Co ntractor. The Contractor, in havin g ten dered a Bid, shall be de emed to have waived any a nd all claims for damages b ecause of cancellation o f Contract for any such reason. If the Agency declares the Contract canceled for any of the above reasons, written no tice to that effect shall be serve d upon the Su rety. The S urety shall, within five (5) days, assume control and perform the Work as successor to the Contractor.
If the Surety assumes any part of the Work, it shall take the Contractor’s place in all respects for that part and shall be paid by the Agency for all w ork performed by it in accorda nce with the Contract. If the Surety assumes the entire Contract, all money due the Contractor at the time of its default shall be paya ble to the Surety as the Work pr ogresses, subject to the terms of t he Contract.
If the Surety does not assume control and perform the Work within 5 days after receiving notice of cancellation, or fails to c ontinue t o comply, the Agenc y ma y exc lude the Sur ety f rom th e premises. The Agenc y may then take possession of all m aterial and e quipment and complete the Work by Agency forces, by let ting t he unf inished Wo rk to an other C ontractor, or by a combination of such me thods. In any event, the cost of completing the Work shall be charged against the Contractor and its Surety and may be deducted from a ny money due or becoming due from the Agency . If th e sums due unde r the Co ntract are insufficient for com pletion, the
Revised 6/15/17 Contract No. 3840-23 Page 90 of 134
Contractor or S urety shall pay to t he Agency within 5 days after t he completion, all costs in excess of the sums due.
The provisions of this section shall be in addition to all other rights and remedies available to the Agency under law.
6-5 TERMINATION OF C ONTRACT. The Board may terminate the Contract at its own discretion or when conditions enc ountered during the Work make it impossible or impracticable to proceed, or when the Agency is prevented from proceedi ng with the Contract by act of God, by law, or by official action of a public authority.
6-6 DELAYS AND EXTENSIONS OF TIME.
6-6.1 General. If delays are ca used b y unfores een events beyond t he control of the Contractor, such delays will entitle the Contractor to an extension of time as provided herein, but the Contractor will not be entitled to damages or additional payment due to such delays, except as provided in 6-6.3. Such unforeseen events may include war, government regulations, labor disputes, strik es, fires, floods, ad verse weat her or elem ents n ecessitating cessation of w ork, inability to obtain materials, labor or equipment, required extra work, or other specific events as may be further described in the Specifications.
No extension of ti me will b e granted for a delay caused by the Contractor’s inability to obtain materials unless the Contractor furnishes to the Engineer documentary proof. The proof must be provided in a timely manner in accordance with the sequence of the Contractor’s operations and the approved construction schedule.
If delays beyond the Contractor’s c ontrol are caused by events other t han thos e men tioned above, the Engineer may dee m an e xtension of time to be in the best interest of the Agency.
The Contractor will not be entitled to damages or additional payment due to such delays, except as provided in Section 6-6.3.
If delays beyond the Contractor’s control are caused solely by action or inaction by the Agency, such delays will entitle the Contractor to an extension of time as provided in Section 6-6.2.
6-6.2 Extensions of Time. Extensions of time, when granted, will be based upon the effect of delays to the Wo rk. They will not be granted for noncontrolling delays to minor portions o f the Work unless it can be shown that such delays did or will delay the progress of the Work.
6-6.3 Payment for Delays to Contractor. The Contractor will be co mpensated for damages incurred due to delays for which the Agency is responsible. Such actual costs will be determined by the Eng ineer. The Agency will not be l iable for damages which the Contractor could have avoided by any reason able means, such a s judicious handling of forces, equipment, or plant.
The dete rmination o f wha t da mages the Contractor could have a voided will be made by the Engineer.
6-6.4 Written Notice and Report. The Contractor shall provide written notice to the Engineer within two hours of the beginning of an y period that the Contractor has placed any workers or equipment on standb y for any re ason that the Contract or has det ermined to be c aused by the Agency or by any organization that the Agency may otherwise be obligated by. The Contractor shall provide continuing daily written notice to th e Engineer, each working day, throughout the duration of such period of del ay. The initial a nd conti nuing written no tices shall inclu de the
Revised 6/15/17 Contract No. 3840-23 Page 91 of 134
classification of ea ch w orkman and s upervisor and the m ake a nd model of e ach piece of equipment placed on st andby, the cumulative duration of the standby, th e Contractor’s opinion of the caus e of the d elay and a coge nt explanation of why the C ontractor could not avoid the delay by reasonable means. Should the Contractor fail to provide the notice(s) required by this section the Contractor agrees that no delay has occurred and that it will not submit any claim(s) therefore.
6-7 TIME OF COMPLETION.
6-7.1 General. The Cont ractor shall complete t he Work with in th e time set fo rth i n the Contract. The Contractor shall complete each portion of the Work within such time as set forth in the Contract f or such po rtion. The time of co mpletion o f t he Contr act sh all be ex pressed in calendar days. The Contra ctor shall dilige ntly prosecut e the work to c ompletion within two hundred fifty (250) working days after the starting date specified in the Notice to Proceed.
6-7.2 Working Day. A w orking day is an y day within the period between the st art of the Contract ti me as defined in Section 6-1 a nd the date provi ded f or completion, o r upon field acceptance b y the Engineer for all work provided for i n the Contrac t, whichever occurs fi rst, other than:
1. Saturday, Sunday, and any day designated as a holiday by the Agency;
2. any day identified as a construction moratorium due to special events or holiday periods; 3 . any other day designated as a holiday in a Master Labor Agreement entered into by the Contractor o r on beh alf of the Contracto r as an eligi ble member of a contractor association;
4. any d ay the Contractor is prevented from wo rking at the be ginning of the workday f or cause as defined in Section 6-6.1;
5. any day the Contractor is prevented from working during the first 5 hours wit h at least 60 percent of the normal work force for cause as defined in Section 6-6.1.
In addition to Agency holidays, open excavations and service shutdowns will not b e allowed on the day prior to Thanksgiving and between December 23 and January 1.
Main line or service shutdowns will not be allowed on Mondays and Fridays.
Unless otherwise approved in writing by the Engineer, the hours of work shall be betwe en the hours of 7:00 a.m. and 4:00 p.m. on Mondays through Fridays, excluding Agency holidays and other restricted days or times as specified in 6-2.
The Contractor shall obtain the written approval of the Engineer if the Contractor desires to work outside said hours or a t any ti me du ring weekends and/o r holidays. This w ritten permission must be obtained at least 48 hours prior to such work. The Engineer may approve work outside the hours and/or days stated herein when, in his/her sole opinion, such work conducted by the Contractor is beneficial to the b est intere sts of t he Agency. The Cont ractor shall pay th e inspection costs of such work.
The Contractor shall incorporate the dates, areas and types of work prohibited elsewhere in the Contract Documents into the construction schedule. No additional payment, adjustment of bid prices or adjus tment of contract t ime of completion wi ll be allowed as a consequ ence of the prohibition of work being performed within the dates, areas and/or types of work prohibited in this section.
Revised 6/15/17 Contract No. 3840-23 Page 92 of 134
Contractor is hereby a dvised th at the En gineer may require after hour s or weekend work if required for the protection and safety of existing facilities, workers or the public.
6-7.3 Contract Time A ccounting. The E ngineer wil l make a daily determination of each working day to b e charged against the Contract time. These dete rminations will be discussed and the Contractor will be furnished a periodic statement showing allowable number of working days of Contract time, as adjusted, at the beginning of the repo rting period. The statement will also indicate the number of working days charged during the reporting period and the number of working days of Contract time remaining. If the Contractor does not agree with the statement, it shall file a written protest wi thin 15 days after rec eipt, set ting fort h the fact s of the protest.
Otherwise, the statement will be deemed to have been accepted.
6-8 COMPLETION, ACCEPTANCE, AND WARRANTY.
6-8.1 Site Walk-Through. After the site has been fully restored, the Inspector will schedule an inspection within five d ays of the Contractor’s request. The Contractor and Inspector shall attend the inspection and all outstanding deficiencies shall be identified in a List of Deficiencies.
A review of the red-line record drawings and asset schedule shall also be completed at the Site Walk-Through and all red-line deficiencies will be added to the List of Deficiencies.
6-8.2 List of Defici encies. Following the Site Walk-Through, the Inspector will generate the List of Deficiencies (also known as the punchlist) within five working days. The Contractor shall then have 10 working days to perform corrective work and provide a written response t o each punchlist item.
6-8.3 Site Fol low-Up Walk-Through. Upon receipt of written responses to the List of Deficiencies, the Inspector will complete a follow-up inspection. Any outstanding deficiencies will be noted and returned to the Contractor. Outstanding deficiencies will delay full payment of any relevant bid items.
6-8.4 Request for Final Walk-Through. Once the Contractor asserts they have satisfied the terms of the Contract and with the Inspector’s permission, the Contractor may submit written assertion in the form o f a Request for Fi nal Walk-Through, certifying t hat al l defici encies identified through the Site W alk-Through process hav e been addressed and req uest a Final Inspection to demonstrate pro ject completion to the Agency. Th e Contractor shall provide an attachment to the Request for Final Inspection with the Contractor’s written response to each deficiency. The Requ est for Final Inspection shall not be considered complete without the Contractor’s written response to each deficiency.
6-8.5 Final Walk-Through. Upon receipt of the Request for Final Walk-Through, the Inspector shall sch edule the F inal In spection. The Inspector and C ontractor shall attend the final inspection. Representatives from other Agency departments r eserve the right to be present at the Final Inspection.
The red-line record drawings and asset schedules shall also be reviewed.
If any deficiencies are not satisfactorily addressed or additional deficiencies are identified, th e Contractor will have 10 working days to complete the corrective work.
Revised 6/15/17 Contract No. 3840-23 Page 93 of 134
6-8.6 Request for Completion. The Engineer will not accept the Work or any portion of the Work before all of the Work is completed and all outstanding deficiencies are corrected by th e Contractor, and the Engi neer is satisfied that all of the Work meets the re quirements o f the Contract Documents.
Once the Final Walk-Through has been completed and all outstanding deficiencies satisfactorily completed to Agency’s approval, the Contracto r shall submi t a written a ssertion in the form of Request for Completion letter, certifying that the Work has been completed.
6-8.7 Completion. Upon receipt of the Request for Completion letter, the Agency shall review the written assertion within 2 working days. If, in the Engin eer’s judgment, the Wor k has been completed in accordance w ith the Contract D ocuments, the Agency will issue a Completion Letter.
The completion date will be the date to which liquidated damages will be computed.
Use, temporary, interim or p ermanent, of all, or portions of, th e Work does not co nstitute completion or acceptance of the Work.
6-8.8 Acceptance. Acceptance will occur after all the requirements contained in the Contract Documents have b een f ulfilled. If, in the Engine er’s judgment, the Contrac tor has fully performed the Contract, the Engineer will so certify to the Board. Upon such certification by the Engineer, the Bo ard may accept the Wo rk. Upon the Bo ard’s acceptance of th e Wor k, the Agency will cause a “Notice of C ompletion” to be filed in the office of the San D iego County Recorder. The date of recordation shall be the date of acceptance of the Work.
6-8.9 Warranty. All work shall be warranted for one (1) year after acceptance of the Work and any faulty work or materials discovered during the warranty period shall be repaired or replaced by the Contractor, at its expense. Twenty-five percent of the faithful performance bond shall be retained as a warranty bond for the warranty period. The Contractor shall replace or repair any such defectiv e w ork in a manner sati sfactory to the En gineer, af ter notice t o do so from t he Engineer, and within th e time specified in the n otice. If t he Contractor fails to ma ke s uch replacement or repairs within the time specified in the notice, the Agency may perform this work and the Contractor’s sureties shall be liable for the cost thereof.
6-9 LIQUIDATED DAMAGES. Failure of the Contractor to complete the Work within the time allowed will result in damages being sustained by the Agency. For each con secutive calendar day in excess of t he time specified for completion of Work, as adjusted in acco rdance with Section 6-6, the Contractor shall pay the Agency, or have withheld monies due it, the sum of two thousand dollars ($2,000.00). Such sum is liquidated damages and shall not be construed as a penalty and may be deducted from payments due the Contractor if such delay occurs.
Execution o f the Contract shall co nstitute agre ement by the Agen cy and Contra ctor that the amount specified above per day is the minimum value of costs and actual damages caused by the Contractor to complete the Work within the allotted time. Any progress payments made after the specified completion date shall not constitute a waiver of this paragraph or of any damages.
6-10 USE OF IMPROVEMENT DURING CONSTRUCTION. The Agency reserves the right to take over and utilize all or part of any completed facility or appurtenance. The Contractor will be notified in writing in a dvance of such action. Such action by t he Agency will relieve the Contractor of responsibility for injury or damage to said completed portions of the improvement
Revised 6/15/17 Contract No. 3840-23 Page 94 of 134
resulting from use by public traf fic or from the action of the elements or fr om any other caus e, except Contractor operations or negligence. The Contractor will not be required to reclean such portions of the improvement before field acceptance, except for cleanup made necessary by its operations. Nothing in th is section shall be c onstrued as relie ving the Contractor from full responsibility for correcting defective work or materials.
In the event the Agency ex ercises its right to plac e i nto service and utilize all or part of any completed facility or appurtenance, the Agency will assume t he responsibility and liability for injury to persons or property resultin g from the utilization of the f acility or ap purtenance s o placed into service, except for any such inj ury to persons or property c aused by any willful or negligent act or omission by the Contractor, Subcontractor, their officers, employees, or agents.
Revised 6/15/17 Contract No. 3840-23 Page 95 of 134
SECTION 7 – RESPONSIBILITIES OF THE CONTRACTOR
7-1 CONTRACTOR’S EQUIPMENT AND FACI LITIES. The Contractor shall furnish and maintain in good condition all equipment and facilities as required for the proper execution and inspection of the Work. Such equipmen t and facilities shall meet all requirements of applicable ordinances and laws.
7-2 LABOR.
7-2.1 General. Only com petent workers shall be em ployed on the Work. Any person employed who is fo und to be incompetent, int emperate, troublesome, disorderly, or otherwise objectionable, or who fails o r refuses to perform work pr operly an d ac ceptably, shall be immediately removed from the Work by the Contractor and not be reemployed on the Work.
7-2.2 Laws. The Contractor, its agents, and employees shall be bound b y and c omply with applicable provisions of the Labor Code and Federal, State, and local laws related to labor.
The Contractor sha ll st rictly adhere to the provisions of the Labor Co de regard ing mi nimum wages; the 8 -hour day and 4 0-hour week; overtime; S aturday, Sunday, and holi day work; and nondiscrimination because of race, color, national origin, sex, o r religion. Th e Contractor shall forfeit to the Agency the penalties prescribed in the Labor Code for violations.
In accordan ce with the Labor Code, the Board h as o n file and w ill publ ish a s chedule of prevailing wage rates for the types of work to be done under the Contract. The Contractor shall not pay less than these rates.
Each worker sh all be paid subsistence an d travel as r equired b y the collectiv e bargaining agreement on file with the State of California Department of Industrial Relations.
The Con tractor’s atte ntion is direc ted t o Secti on 1776 o f the Labor C ode which imposes responsibility upon the Contractor for the mai ntenance, c ertification, and availability for inspection of such r ecords for al l persons emplo yed by th e Co ntractor or Subcontractor in connection with the project. The Contractor shall agree through the Contract to comply with this Section and the remaining provisions of the Labor Code.
7-3 LIABILITY INSURANCE. Insurance shall be required as specified in sectio n 10 of the Public Works Contract.
The cost of this insurance shall be included in the Contractor’s Bid.
7-4 WORKERS’ COMPENSATION INSURANCE. Before execution of the Contrac t b y t he Board, the Contractor shall file with the Engineer the following signed certification:
“I am aware of th e provisions o f Section 3700 of the Labor Code which require every employer to be insured against lia bility for wor kers’ co mpensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.”
Revised 6/15/17 Contract No. 3840-23 Page 96 of 134
The Contractor shall also comply with Section 3800 of the Labor Code by securi ng, paying for, and ma intaining in fu ll forc e a nd effect for the d uration of t he con tract, complete W orkers’ Compensation Insuran ce, a nd shal l furnish a Certificate of Insur ance to t he Engine er be fore execution of the Contract. The Agency, its officers, or employees, will not be responsible for any claims in law or equity occasioned by failure of the Contractor to comply with this paragraph.
All compensation insurance policies shall bear an endorsement or shall have attached a rid er whereby it is provided that, in the event of expiration or p roposed cancellation of such policies for any reason whatsoever, the Agency shall be notified by registered mail not less than 30 days before expiration or cancellation is effective.
All insurance is to be placed with insurers that are admitted and authorized to conduct business in the state of California and are listed in the official publication of the Department of Insurance of the Sta te of Cal ifornia. Policies issued by the St ate Compensati on Fund meet the requirement for workers' compensation insurance.
7-5 PERMITS. Except as specified herein the Contractor will obtain, at no cost to the Contractor all City of Car lsbad encroachment, right-of-way, grading and bu ilding permits necessary to perform work for this con tract on Agency property, streets, or other rights-of-way.
Contractor shall not beg in work until all permits incidental to the work are obtained. The Contractor shall obtain and pay for all permits for the disposal of all materials removed from the project. The cost of said permit(s) shall be included in the price bid for the appropriate bi d item and no additional compensation will be allowed therefor. The Contractor shall obtain and pay for all costs incurred for permi ts necessitated by its operations such as, but not limited to, those permits required for night work, oversize load, blasting, and demolition. For private contr acts, the Contractor shall obtain all permi ts inciden tal to the Work or made necessary by its operations, and pay all costs incurred by the permit requirements.
The Contractor shall pay all business taxes or license fees that are required for the work.
7-5.1 Resource Agency Permits. No resource agency permits are required for the Work.
7-5.2 Air Pollution Control Permits. The use of materials or activities that can generate air emissions are regulated by the Calif ornia Air Resource B oard (CARB) and the San Diego County Air Pollution Control District (SDAPCD) and either require permits or are subject to state or local air regulations which establish limitations on equipment or product use or VOC content and requirements for recordkeeping and reporting. These materials and activities include, but are not limited to the following:
• Abrasive blasting
• Adhesives
• Asbestos abatement, removal or disruption
• Coating or painting
• Concrete curing compounds
• Demolition of buildings, equipment or structures
• Fiberglass/polyester resin layup or machining
• Operation of non-road diesel engines greater than 49 hp (including generator s, compressors, pumps, hydro blasters, etc.)
• Operation of off-road diesel engines greater than 25 hp (including forklifts, construction equipment, load handlers, etc.)
Revised 6/15/17 Contract No. 3840-23 Page 97 of 134
• Solvents
• Welding
Operators of p ortable engines and other types of equipment can registe r their units under the CARB Stat ewide Portable E quipment Registrati on Program (PERP) in order to operat e th eir equipment throughout California. However, the use of portable equipment (e.g., bypass pumps) to perform the function of permitted stationary equ ipment is subject to SDAPCD regul ation in addition to CARB requirements.
Diesel-engine driven generators or eq uipment sh all have a valid per mit or registra tion in accordance with the California Air Resources Board and/or the San Diego County Air Pollution Control District regulations prior to mobilization to the site. The Contractor shall submit a copy of the p ermit or regi stration documents f or all equipmen t subject to state or l ocal air po llution control regulations and maintain t he permit or registratio n documents in valid standing dur ing the performance of the Work.
Products such as paints, adhesives, resins, solvents and other products s hall comply wit h the Volatile Organic Compound (V OC) conten t limits established by CARB and /or t he SDAPCD.
The Contractor shall be responsib le for d etermining that such products can b e used legally in the performance of the Work. The Co ntractor shall maint ain and submit records to the City Engineer on th e quantiti es of paints or solvents used as may be required by appl icable regulations.
Prior to starting any activity that is required to have an air pollution control permit or registration, the Contractor shall verify the applicability of the latest air pollution control regulations pertaining to the proposed materials, equipment and operation s and ob tain and comply with applicable requirements:
• Rule 11 – Exemptions from Rule 10 Permit Requirements Rule 12 – Registration of Specified Equipment
• Rule 12.1 – Portable Equipment Registration
• Rule 51 – Nuisance
• Rule 67.0.1 – Architectural Coatings
• Rule 67.17 – Storage of Materials Containing Volatile Organic Compounds • Rule 71 – Abrasive Blasting
San Diego Air Pollution Control District: 858-586-2600
https://www.sdapcd.org/content/sdapcd/permits.html
California Air Resource Board:
https://ww2.arb.ca.gov/our-work/programs/portable-equipment-registration-program-perp/about
7-6 THE CONTRACTOR’S REPRESENTATIVE. Before starting work, the Contractor shall designate in writing a representative who shall have complete authority to act for it. An alternative representative may be desig nated as well. The representative or alternate shall be present a t the Work s ite whenever work i s i n progress o r whenever actions of the elements necessitate its presence to take measures necessary to protect the Work, persons, or property.
Any order or co mmunication given to this representative shall be deeme d d elivered to the Contractor. A joint venture shall designate only one representative and alternate. In the absence of the Contractor or its representative, instructions or directions may be given by the Engineer to
Revised 6/15/17 Contract No. 3840-23 Page 98 of 134
the superintendent or person in charg e of the specific work t o which t he order a pplies. Such order shall be complied with promptly and referred to the Contractor or its representative.
In order to communicate with the Agency, the Contractor’s representative, superintendent, or person in charge of specific work shall be able to speak, read, and write the English language.
The qualifications for the Contractor's Representative shall include at a minimum:
1. At least five years of experience in a superintendent capacity for projects that are similar in scope and cost to the projects identified in the Contractor’s Statement of Technical Ability and Experience submitted with the bid, and successful completion of at least five projects involving diesel generator installations with contract values over $100,000. The Contractor shall be responsible for submitting verifiable experience records.
2. Completion of OSHA 30 -hour Construction Train ing Course. Submit ce rtification as proof.
The City reserves the right to d isqualify bidders if the re quired technical ability and experience for the Contractor's Representative is not established.
In t he e vent that the Contractor proposes to c hange t he Contractor's Representative prior to Project completion, the Contractor shall notify the Agency and submit the qualifications of the proposed Contractor's Representative for the Engineer's review at least two weeks prior to the proposed change. The qualifications shall demonstrate that the minimum r equirements of th e position, as described herein, are satisfied. The Engineer will review the qualifications o f proposed Contractor's Representative within 5 working days of receipt.
No change in Contractor's Representative will be allowed without the Agency's approval. In the event of a change in Contractor's Representative without prior approval, Agency reserves the right to suspend work, at the Contractor's cost, until a qualified Contractor's Representative is approved for the Project.
7-7 COOPERATION AND COLLATERAL WORK. The Contractor shall be responsible for ascertaining the nature and extent of any simultaneous, collateral, and essential work by others.
The Agency, its workers and contr actors and others, shall have the right to operate within or adjacent to the Work site during the performance of such work.
The Agency, the Contractor, and each of such workers, contractors and others, shall coordinate their operations and cooperate to minimize interference.
The Contractor shall include in its Bid all costs involved as a result of coordinating its work with others. the C ontractor will n ot be enti tled to ad ditional co mpensation f rom the Agency f or damages resulting from such simultaneous, collateral, and essential work. If necessary to avoid or minimize such damage or delay, the Contractor shall redeploy its work force to other parts of the Work.
Should the Contractor be delayed by the Agency, a nd suc h delay co uld not h ave bee n reasonably foreseen or prevented by the Contractor, the Engineer will determine the extent of the delay, the effect on the project, and any extension of time.
7-7.1 Coordination. The Contractor shall coordinate a nd co operate with all utility companies during the mark-out and locating of th eir line s or during their relocation or construction if
Revised 6/15/17 Contract No. 3840-23 Page 99 of 134
necessary. The Contractor may be granted a time extension if, in the opinion of the Engineer, a delay is c aused by the utility company. No additional c ompensation will be made to the Contractor for any such delay.
7-8 PROJECT SITE MAINTENANCE.
7-8.1 Cleanup and Dust Co ntrol. Throughout all p hases of con struction, including suspension of work, and until the final acceptance, the Contractor shall keep the site clean and free fro m rubbish and deb ris. T he Contr actor shall also abate dus t n uisance by cleanin g, sweeping and sprinkling with water, or other means as necessary. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods.
When required by th e Plans or S pecifications, the Contractor shall furnish and oper ate a self- loading motor sweeper with spray nozzles at least once e ach working day for t he purpose of keeping p aved areas ac ceptably clean wh erever construction, including restor ation, is incomplete.
Materials and equ ipment sha ll be remov ed from the site as so on as th ey are no longer necessary. Before the final inspection, the site shall be cleared of equipment, unused materials, and rubbish so as to present a satisfactory clean and neat appearance. All cleanup costs shall be included in the Contractor’s Bid.
Care sha ll be take n to p revent spillage on h aul routes. Any su ch s pillage shall be removed immediately and the area cleaned.
Excess excavation material from catch b asins or similar structures shall be removed from the site immediately. Sufficient mat erial may rem ain for us e as b ackfill if permi tted by the Specifications. Forms and form lum ber shall be removed from the site as so on as practicable after stripping.
Failure of the Contractor to comply with the Engineer’s cleanup orders may result in an order to suspend work until the condition is corrected. No additional compensation will be allowed as a result of such suspension.
Cleanup an d dust control required herei n shall also b e executed on weeken ds and other non-working days when needed to preserv e the health safety or welfare of t he public. The Contractor shall conduct effective cleanu p and du st co ntrol throughout the durat ion of the Contract. The Engineer may require increased levels of cleanup and dust control that, in his/her sole discretion, are necessary to preserve the health, safety and welfare of the public. Cleanup and dust control shall be considered incidental to the items of work that they are associated with and no additional payment will be made therefore.
7-8.2 Air Pollution Control. The Contractor shall not discharge smoke, dust, or any other air contaminants into the at mosphere in such quantity as will violate the regulations of any legally constituted authority.
7-8.3 Vermin Control. At t he time of acceptance, structures entirel y constructed under the Contract shall be free of rodents, insects, vermin, and pests. Ne cessary e xtermination work shall be arranged and paid for by the Contractor as par t of the Work within the Contr act time and shall be pe rformed by a licensed extermina tor in accor dance wi th require ments of
Revised 6/15/17 Contract No. 3840-23 Page 100 of 134
governing authorities. The Contractor shall be liabl e for i njury to persons o r property a nd responsible for the elimination of offensive odors resulting from extermination operations.
7-8.4 Sanitation. The Contractor shall provi de and m aintain en closed toile ts f or t he use of employees en gaged in the Work . These a ccommodations shal l be main tained in a neat and sanitary condition. They shall also comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps.
Wastewater shall not be interrupted. Should the C ontractor di srupt existi ng sewer facilities, sewage shall be convey ed i n cl osed condu its and disp osed of in a s anitary se wer system.
Sewage shall not be permitted to flow in trenches or be covered by backfill.
7-8.5 Temporary Light, Power, and Water. The Contractor s hall furn ish, install, maintain, and remove al l temporary l ight, power, a nd water at its own expense. These i nclude pipi ng, wiring, lamps, and other equipment necessary for the Work. The Contractor shall not draw water from any fir e hydrant (except to extinguish a fir e), without obtaining permission from the w ater agency concerned. The Co ntractor shall obtain a construction meter for water use d for the construction, plant establishment, maintenance, cleanup, testing and all other work req uiring water relate d to this contract. The Co ntractor shall conta ct the ap propriate water agency for requirements. The Contractor shall pay all costs of tempo rary light, p ower and water i ncluding hookup, service, meter and any, and all, other charges, deposits and/or fees therefor. Said costs shall be cons idered inciden tal to t he ite ms of work that they are associated w ith and no additional payment will be made therefor.
7-8.6 Water Pollution Control. The Contractor shall exercise every reasonable precaution to protect channels, storm drains, and bodies of water from pollution. It shall conduct and schedule operations so as to minimize or avoid muddying and silting of said channels, drains, and waters.
Water pollution control work shall consist of con structing those facilities which may be required to provide prevention, control, and abatement of water pollution.
The Contractor shall comply with the California State Water Resources Control Board (SWRCB) Order Num ber R9-2013-0001, National Pollutant Discharge Elimination System (NPDES) Permit and Waste Discharge Requirements for D ischarges from the Municipal Separate Storm Sewer Systems (MS4s) Draining the Watersheds within the San Diego Regio n, and amendments thereto, and with all requirements of the Storm Water Pollution Prevention Plan for this project in accordance with these regulations.
A Tier 2 Storm Water Pollution Pre vention Plan (S WPPP) is p rovided to the Contractor, in Appendix “B”, for use in preparing the Project SWPPP for approval by the City. The Contractor shall be respo nsible f or the pr eparation and impleme ntation of the SWPPP an d coordination with the City and the Regional Water Quality Control Board. Refer to Section 300-12.
7-8.6.1 Dewatering. Dewatering shall be perform ed by the Cont ractor when specifically required by the Plans or Specifications or specified in the bid schedule , and as n ecessary for construction of the W ork. Dewat ering shall be performed in conformance with all applic able local, state and Federal laws and permits issued by jurisdictional regulatory agencies.
Permits necessary for the discharge of groundwater to land or the sanitary sewer system shall be obtained by the Contractor unless provided by the City . Water shall be treated prior to disposal if so specified in the Special Provisions or required by a permit.
Revised 6/15/17 Contract No. 3840-23 Page 101 of 134
The Contractor shall submit a Dewatering Plan and related supporting information detailing its proposed plan and methodology of dewatering , treatment/pretreatment (when required for permit compliance) and disposal of accumulated water. The plan shall identify the following:
1. location, type and size of dewatering devices and related equipment,
2. size and type of materials composing the collection system,
3. size and type of equipment to be used to retain and, if required, treat accumulated water,
4. the proposed disposal locations, and
5. any other information required by the jurisdictional agency.
If the proposed disposal location is a sanitary sewer, the Con tractor shall comply with the Special Us e Dischar ge Permit from the Encina W astewater Authority (Appendix C). If the proposed disposal loca tion is a storm drain system or receiving body of water, the Contractor shall submit written evidence of permission from the owner of the storm drain system and, if not obtained by the Agency, original signed permits from jurisdictional regulatory agencies or written evidence that such permits are not required.
The City will install a groundwater monitoring well and provide the results of any tests conducted by the City to the Contractor prior to the start of construction . The Contractor sh all perform additional sampling and testing to demonstrate compliance with the Special Use Dischar ge Permit or any other permit, or to support the application for any other permit as required.
All costs for dewatering including sample co llection, testing, permit application fees and installation, testing and operation of the dewatering system shall be made at the contract price specified in the bid sc hedule for Dewaterin g. If no such bid i tem is listed, payment shall be considered included in the bid item of work requir ing dewatering and no s eparate or additional payment shall be made therefor.
7-8.7 Drainage Control. The Contractor shall maintain drainage within and through the work areas. Earth dams will not be permitted in paved areas. Temporary dams of sandbags, asphaltic concrete, or other acceptable material will be permitted when necessary. Such dams shall be removed from the site as soon as their use is no longer necessary.
7-8.8 Noise Control. All in ternal combustio n engines used in the construct ion sha ll be equipped with mufflers in good repair when in u se on the project with special attention to the City Noise Control Ordinance, Carlsbad Municipal Code Chapter 8.48.
7-9 PROTECTION AND RESTORATION OF EXISTING IMPRO VEMENTS. The Contractor shall be responsible for t he protection of public and pr ivate property adjacent to the Work and shall exercise due caution to avoid damage to such property.
The Contractor shall repair or r eplace all existing improvements within th e right-of-way which are not de signated for removal (e.g., cur bs, sidewalks, dri veways, fen ces, w alls, signs, utility installations, pavement , structures, etc.) whic h are dam aged or removed as a r esult of its operations. When a portion of a sprinkler system within the right-of-way must be removed, the remaining lines shall be ca pped. Repairs and replacements shall be at least equal t o existing improvements and shall match them in finish and dimension.
Maintenance o f street and traffic signal systems that a re damag ed, te mporarily removed or relocated shall be done in conformance with 307-1.5.
Revised 6/15/17 Contract No. 3840-23 Page 102 of 134
Trees, l awns, and shrubbery that are not to be remov ed shall b e p rotected fr om damage or injury. If damaged or removed due to Contractor’s operations, they shall be restored or replaced in as nearly the or iginal condition an d loc ation as is reasonably possib le. La wns shall be restored with sod and unpaved areas covered with suitable mulch.
The Contractor shall give reasonable n otice to occupants o r owners of a djacent property t o permit them to salva ge or r elocate plants, tre es, f ences, sprinklers, and other improvements, within the right-of-way which are designated for removal and would be destroyed because of the Work.
All costs to the Contractor for protecting, removing, and restoring existing imp rovements shall be included in the Bid.
7-9.1 Preconstruction Survey. The Contractor shall perform a preconstruction survey of the project site to provide a record of pr econstruction conditions. This su rvey shall include t he following as a minimum:
1. Video of existing pub lic r ight-of-way, propos ed ali gnment, utility mark-outs, working areas, staging and storage areas. Conduct the survey after construction staking has been completed.
2. Video of construction access roads to be used by the Contractor, including all public and private str eets used for acc ess to and from t he work si te. Indicate a reas of damaged paving.
3. Any other areas as directe d by th e Owner which m ay be disturbed or whi ch are to be protected from the Contractor’s operations.
4. Photographs and video of potential “problem areas”.
5. Notify the Owner seven calendar days in advance and coordinate the scheduling of the video so th at a rep resentative of the O wner may accompany t he Contractor during the videotaping.
6. At the completion of the survey, the Contractor shall present the Owner wi th a report detailing the e xisting conditions at e ach proposed pipeline site, staging, and st ockpile areas. The report shall include the following as a minimum:
a. One copy of the video in color in digital format.
b. One copy of each “potential problem a rea” ph otograph (4 -inch by 6 -inch colored photos).
c. Written summary of “potential problem areas” and the Contractor’s recommendations to address these problem areas.
7. Documentation (including repo rt) of exist ing c onditions s hall be co mpleted within 1 5 days of the Notice to Proceed. The Contractor will not be allowed to begin excavation or dewatering act ivities until the fi nal report has be en submitted and accept ed by the Owner.
7-10 PUBLIC CONVENIENCE AND SAFETY.
7-10.1 Traffic and Ac cess. The Contr actor’s o perations sh all c ause no unnec essary inconvenience. Th e access rig hts o f the public shall be con sidered a t all times . Unless otherwise authorized, traffic shall be permitted to pass through the Work, or an approved detour shall be provided.
Revised 6/15/17 Contract No. 3840-23 Page 103 of 134
In areas where site access is restricted, the Contractor is responsible for coor dinating site access. A ll comm unications shall be made through the City inspector unless o therwise approved.
No excavation or vehicle access will be allowed to occur outside of the easement, outside of the right-of-way, or in vegetate d or landsc aped areas unless otherwise shown on the Plans or as approved by the Engineer.
Safe and adequate pedestrian and vehicular access shall be p rovided and maintained to fire hydrants; commercial and industrial establishments; churches, schools and parking lots; service stations and motels; h ospitals; poli ce and fire s tations; public transportati on sto ps and establishments of similar nature. Access to these facilities shall be continuous and unobstructed unless otherwise approved by the Engineer. Pedestrian crossings of the Work at in tervals not exceeding 300 feet (90 m) shall be provided and maintained unless otherwise approved by the Engineer.
The Contractor shall refer to and comply with the requirements of Section 302-15 and Part 6 of the Supplemental Provisions.
7-10.2 Storage of Equipment and Materials in Public Streets. Construction materials shall not be stored in streets, roads, or highways after unloading. Construction equipment shall not be stored at the Wo rk s ite be fore i ts actual use on the Wor k or after i t is no longer ne eded.
All materials or equipment not installed or used in construction on any given day shall be stored elsewhere by the Contractor at its expense unless otherwise approved by the Engineer.
Excavated material, except th at which is to be u sed as ba ckfill in the adjacent trench on the same day, shall not be stored in public streets. After placing backfill, all excess material shall be removed immediately from the site.
7-10.3 Street Closures, Detours, Barricades. The Contractor shall comply with all applicable State, Cou nty, and City require ments for cl osure of streets. The Contractor shall provide barriers, guards, lights, signs, te mporary bridges, flag persons, and watchp ersons. The Contractor shall be responsible for compliance with additional public safety requirements which may arise. Th e Contractor shall furn ish and install signs and wa rning devi ces and promptly remove them upon completion of the Work.
After obtaining the Engineers approval and at least 5 working d ays before closing, detouring, partially closing or reopening any street, alley or other public thoroughfare the Contractor shall notify the following:
The Engineer................................ ................................ ......................... 442-339-2766 Carlsbad Fire Administration ................................ ................................ . 442-339-2141 Carlsbad Police Department Dispatch ................................ ................... 442-339-2197 Carlsbad Traffic Signals Maintenance ................................ ................... 760-438-2980 Carlsbad Traffic Signals Operations ................................ ...................... 442-339-2736 North County Transit District ................................ ................................ . 760-966-6500 Republic Services ................................ ................................ ................. 760-332-6464
The Contractor shall comply with their requirements. The Contractor shall obtain the Engineer’s written approval prior to deviating from the requirements of 2) through, and including, 7) above.
Revised 6/15/17 Contract No. 3840-23 Page 104 of 134
The Contractor shall obtain the written approval no less than five working days prior to placing any traffic control that affects bus stops.
The Contractor shall secure approval, in advance, from authorities concerned for the use of any bridges proposed by it for public use. Temporary bridges shall be clearly posted as to load limit, with signs and posti ng conforming to current requirements covering “signs” as set forth in the Traffic Manual published by the California Department of Transportation. This manual shall also apply to the street closures, barricades, detours, lights, and other safety devices required.
All costs involved shall be included in the Bid.
Temporary traffic controls shall be in accordance with the Plans, the TCP , the California Manual on Uniform Traffic Control Devices (MUTCD), current edition, and the Contract Documents.
7-10.3.1 Construction Area Signs and Control Devices . All cons truction traffic s igns and control devices shall be maintained throughout the duration of work in good order and according to the approved traffic control plan. All temporary traffic control devices shall conform to Caltrans Standard Specification 12-3.
Warning and advisory signs, lights and devices shall be furnished, installed and maint ained by the Contractor and shall be pr omptly removed by the Contracto r when n o longer required.
Warning and advisor y signs that re main in pl ace overnight shall be stationary mounted signs.
Stationary signs that w arn of non -existent conditions shall be rem oved from the traveled way and from the view of motorists in the trave led way o r shielded from th e view of the trave ling public during such periods that their message does not pertain to existing conditions.
All excavation required to install stationary construction area signs sha ll be performed by hand methods without the use of power equipment. Warning and advisory signs that are used only during working hours may be portable signs. Portable signs shall be removed from the traveled way and shielded from the view of the traveling public during non-working hours.
Personal vehicles of the Contractor's employees shall not b e parked wi thin the t raveled way, including any Section closed to publi c traffic. Whenever the Contractor’s vehicles or equipment are pa rked on t he shoulder w ithin 6’ o f a tra ffic lane, the sho ulder area sh all b e c losed wi th fluorescent traffic co nes or po rtable deli neators pl aced on a taper in a dvance of the parked vehicles or equipment and along the edge of the pavement a t not less than 25’ intervals to a point not les s than 25’ past the last vehicle or eq uipment. A minimum of nine (9) cones or portable delineators shall be used for the taper. A W20-1 (Road Work Ahead) or C24 (Shoulder Work Ahead) sign shall be mounted, as required herein , on a signpost or t elescoping flag tree with flags. The signpost or flag tree shall be placed where directed by the Engineer.
7-10.3.2 Maintaining Traffic. The Contractor’s personnel shall not work closer than 1.8 m (6’) nor operate equipment within 0.6 m (2’) from any traffic lane occupied by traffic. For equipment, the distance shall be measured from the closest approach of any part of the equipment as it is operated and/or maneuvered in performing the work. This requirement may be waived when the Engineer has given written authorization to the reduction in clearance that is specific to the time, duration and location of such waiver, when such reduction is show n on the traffic control plans included in these Contract Documents, when such reduction is shown on the traffic control plans prepared by t he Contractor and appro ved by t he Engineer or for th e work of installing, maintaining and removi ng traffic control d evices. As a co ndition of s uch waiver the Engineer
Revised 6/15/17 Contract No. 3840-23 Page 105 of 134
may require the Contractor to detour traff ic, adjust the width of, or realign the adjacent traffic lane, close the adjacent traffic lane or provide barriers.
During the entire construction, a minimum of one, 12-foot wide paved traffic lane shall be open for use by public traffic in each direction of travel.
7-10.3.3 Traffic Control System for Lane Closure. A traffic control system consists of closing traffic lanes or pedestrian walkway s in accorda nce wit h the de tails s hown on the plans, California Manual on Uniform Traffic Co ntrol Devices (FHWA MUTCD, current ed ition, a s amended for use in Ca lifornia) and provisions under " Maintaining Traffic" elsewhere in these Provisions. The provisions in this section will not relieve the Contractor from its responsibility to provide such additional devices or take such measures as may be necessary to maintain public safety.
When lanes are closed for only the duration of work periods, all components of the traffic control system, except portable delineators placed along o pen trenches or excavation adjacent to the traveled way, shall be r emoved from th e trav eled way and shoulder at the en d work per iod.
If the Contractor so elects, said compo nents may be stored at selec ted cent ral locations, approved by the Engineer, within the limits of the right-of-way.
7-10.3.4 Traffic Control for Permanent and Temporary Traffic Striping. During traffic striping operations, traffic shall be controlled with lane closures, as provided for under "Traffic Control System for Lane Cl osure" of the se Supplemental Provisions or by use of an alternative traffic control plan proposed by the Contractor and approved by the Engineer. The Contractor shall not start traffic striping operations using a n alternative plan u ntil the Contractor has submitted its plan to the Engineer and has received the Engineer's written approval of said plan.
7-10.3.5 Temporary Pav ement Del ineation. Temporary pavement deline ation shall be furnished, p laced, mai ntained an d rem oved in accordance with t he minimum sta ndards specified in the latest California Man ual on Uniform Traffic Con trol D evices (CAMUTCD) published by Caltrans. Whenever the work ca uses oblite ration of pavement deli neation, temporary or permanent pavement delineation shall be in place prior to openi ng the traveled way to public traff ic. Lane line or centerline pavement delineation shall be provided at all times for tr aveled wa ys open to public traffic. All work necessary, including any r equired lines or marks, to establish the alignment of temporary pavement delineation shall be performed by the Contractor. When temporary pav ement delineation i s removed, all li nes and marks us ed to establish the alignment of the temporary pavement delineation shall be removed by grinding.
Surfaces to re ceive temporar y pavement delineation shall be dry and free o f dir t an d loose material. Temp orary pavement deli neation sh all not be applied over existing pavement delineation or other temporary pavement delineation. Temporary pavement delineation shall be maintained until superseded or replaced with permanent pavement delineation.
Temporary pavement delineation shall be removed when, as determined by the Engineer, the temporary pav ement delineation conflicts with the permanent pavement d elineation or with a new traffic pattern for the area and is no longe r required for the direction of public traffic. When temporary pavement delineation is required to be removed, all lines and marks used to establish the alignment of the temporary pavement delineation shall be removed.
7-10.3.6 Preparation of Traffic Control Plans. The Contractor shall submit traffic control plans (TCPs) as a part of the Work for all construction activities that are locat ed within t he traveled
Revised 6/15/17 Contract No. 3840-23 Page 106 of 134
way. TCPs shall be prepared by a professional engineer registered in the State of California and regularly engaged in the preparation of traffic control plans. Design of TCPs f or construction shall m eet the req uirements of the City a nd the Cali fornia Man ual on Uniform Traff ic Control Devices as published by Caltrans. Submittal and review requirements for TCPs shall conform to Section 2-5.3 Shop Drawings and Submittals.
The Contractor must obtain the Engineer’s approval prior to implementing TCPs. The minimum 20-day review period specified in Section 2-5.3.1 for shop drawings and submittals shall pertain to each submittal of TCPs. New or revised TCP submittals shall include all TCPs needed for the entire duration of the Work. Each TCP phase shall be prepared in sufficient scale and detail to show the lane widths, transition lengths, curve radii, s tationing of features affecting the traffic control plan and the methodology proposed to t ransition to the subsequent TCP phase. When the vertical a lignment of the traveled surface di ffers from the finished pavement ele vation, vertical curves must also be shown. The Engineer shall be the sole judge of the suitability and quality of any such TCPs.
7-10.3.7 Payment. The contract price paid for Traffic Control shall include full compensation for furnishing all l abor, materials, to ols, eq uipment and inciden tals, and for performing all work involved to implement the traffic control system, complete in-place, including, but not limited to, preparing a nd revising TCPs, flag persons , installing temporary or perm anent traffic control devices such a s barriers, delineators, lighting, signage, portable changeabl e messa ge signs, striping, pavement markers and markings in accordance with the Contract Documents and as directed by the Engineer. Progress payments for Traffic Control will be based on the percentage of the improvement work necessitating traffic control and completed.
7-10.4 Safety.
7-10.4.1 Safety Orders. The Contractor shall have at the Work site, copies or suitable extracts of: Constru ction Safe ty Ord ers, Tu nnel Sa fety Ord ers an d Genera l I ndustry Safety Orders issued by the Stat e Division of Industrial Safety. The Contractor shall comply with provisions of these and all other applicable laws, ordinances, and regulations.
Before excavating any trench 5 feet or more in depth, the Contractor shall submit a detailed plan to the Agen cy showing the des ign of shoring, bracing, sloping, or o ther provisions to be made for the w orkers’ pr otection fro m the hazard of c aving ground during the excava tion of su ch trench. If the plan varies from the shoring system standards, the plan shall be pr epared by a registered Civil Engineer. No excavation shall start until the Engineer has accepted the plan and the Contractor has obtained a permit from the State Division of Industrial Safety. A copy of the permit shall be submitted to the Engineer.
Payment for performing all work necessary to provide safety measures shall be included in the prices bid for oth er items of w ork except where separate bid items for e xcavation safety are provided or required by law.
7-10.4.2 Use of Explosives. Explosives may be used only when authorized in writing by the Engineer, or as otherwise stated in the Specifications. Explosives shall be handled, used, and stored in accordance with all applicable regulations.
The Engineer’s approval of the use of explosives shall not relieve the Contractor from liability for claims caused by blasting operations.
Revised 6/15/17 Contract No. 3840-23 Page 107 of 134
7-10.4.3 Special Hazardous Substances an d Processes . Materials that contain haza rdous substances or mixtures ma y be required on the W ork. A Mat erial S afety D ata Sheet as described in Section 51 94 of the C alifornia Code of R egulations shall be req uested by the Contractor from the manufacturer of any hazardous products used.
Material usage shall be accomplished with strict adherence to Cal ifornia Division of Industrial Safety re quirements and all manufacturer warnings and application instructions l isted on the Material Safety Data Sheet and on the product container label.
The Contracto r shall not ify t he Engineer if a sp ecified p roduct ca nnot be us ed unde r s afe conditions.
7-10.4.4 Confined Spaces.
(a) Con fined Space Entry Program. The Contractor s hall be responsible f or implementing, administering and maint aining a c onfined space ent ry program (C SEP) in accordance w ith Sections 5156, 5157 and 5158, Title 8, CCR.
Prior to starting the Work, the Contractor shall prepare and submit its comprehensive CSEP to the Engineer. The C SEP shall addre ss all potential physical and environmental hazards and contain procedures for safe entry into confined spaces, including, but not limited to the following:
1. Training of personnel
2. Purging and cleaning the space of materials and residue
3. Potential isolation and control of energy and material inflow
4. Controlled access to the space
5. Atmospheric testing of the space
6. Ventilation of the space
7. Special hazards consideration
8. Personal protective equipment
9. Rescue plan provisions
The Con tractor’s submittal shall in clude the name s of its pe rsonnel, i ncluding s ubcontractor personnel, assigned to the project who will have CSEP responsibilities, their CSEP training, and their specific assignment and responsibility in carrying out the CSEP.
(b) Permit-Required Confined Spaces. Entry into permit-required confined spaces as defined in Section 5157, Title 8, CCR may be required as a part of the Work. All manholes, tanks, vaults, pipelines, excava tions, or other enclosed or partially enclosed spa ces shall be considered permit-required co nfined spac es until t he pre-entry procedu res d emonstrate otherwise. The Contractor shall implement a permit spa ce program prior to perf orming any work in a permit - required co nfined space. A co py of th e permit shall be available at al l times f or review by Contractor and Agency personnel at the Work site.
(c) Pa yment. Pay ment for implementing, administering, and pr oviding all eq uipment an d personnel to perform the CS EP shall b e included in the bid item s for which th e CSEP is required.
7-10.4.5 Safety and P rotection o f Workers and Public. The Cont ractor sha ll tak e all necessary pr ecautions f or the safety of employee s on the work and shall comply with all applicable provisions of Federal, State and Municipal safety laws and building codes to prevent accidents or injury to persons on, about, or adjac ent to the premises where the work is being
Revised 6/15/17 Contract No. 3840-23 Page 108 of 134
performed. The Contractor shall erect a nd properly maintain at a ll times, as r equired by the conditions and progress of the work, all necessary safeguards for the protection of workers and public and shall use da nger signs warning agains t haz ards create d b y such features of construction as protruding nails, hoists, well holes, and falling materials.
7-10.4.6 Flood Lighting.
7-10.4.6.1 Ge neral. When work i s being per formed during hou rs of d arkness, as defined in Division 1, Section 280, of the California Vehicle Code, flood lighting shall be used to il luminate the Work site, flagger stations, equipment crossings and other hazardous areas. Flood lighting shall provide visibility for a distance of 1/2 mile (800 m). Flood lights shall not shine directly into the view of oncoming traffic.
7-10.4.6.2 Payment. No separate or additional payment will be made for flood lighting. Payment shall be in cluded in th e Contract Unit P rice or lump sum price in the Bid for the vari ous Bid items.
7-10.4.7 Security and Protective Devices.
7-10.4.7.1 General. Security and protective devices shal l consis t of fencing, ste el plates, or other devices as specified in the Special Provisions to protect open excavations.
7-10.4.7.2 Security Fencing. The Contractor shall completely fence open excavations. Security fencing shall co nform to 304-5. S ecurity fencing shall rema in in place unles s workers are present an d construction ope rations are in p rogress during wh ich time the Contractor shall provide equivalent security.
7-10.4.7.3 Payment. No separate or additional payme nt will be mad e for security fe ncing or protective devices. Payment shall be included in the Contract Unit Price or lump sum price in the Bid for the various Bid items.
7-10.4.8 Steel Plate Covers.
7-10.4.8.1 General. The Cont ractor shall provide, insta ll, and ma intain ste el plate cove rs as necessary to pr otect from ac cidental en try int o openings, trenches, and excavations. Plates shall provide complete coverage to prevent any person, bicycle, motorcycle, or motor vehicle from being endangered due to pla te movement causing separations or gaps. The Contractor shall submit the design in ac cordance with Section 2 -5.3 which s hall include the following criteria:
1. The approval of steel plate bridging shall be at the sole discretion of the Engineer.
2. Steel plate bridg ing shall be designed t o s upport HS20-44 tr uck lo ading pe r Caltrans Bridge Design Specifications Manual.
3. Surfaces exposed to pedestrian or vehi cular traffic shall be non -skid. The Contractor shall m aintain a non-skid su rface on the s teel plate having a minimum c oefficient of friction equivalent to 0.35 as determined by California Test Method 342. If a different test method is used, the Contractor may utilize standard test pla tes with know n coefficients of fri ction av ailable from each Caltrans District Materials Engineer to cor relate skid resistance results to California Test Method 342.
Revised 6/15/17 Contract No. 3840-23 Page 109 of 134
4. The Contractor shall install signage with a 2 -inch (51 mm) minimum letter hei ght indicating the st eel pla te cover load limit, the C ompany’s name, a nd a 24 -hour emergency contact phone number. The
5. Contractor shall install R ough R oad (W33) sign wi th black l ettering on an o range background in advance of steel plate bridging.
6. The Contractor is respo nsible for the maintenance of t he plates a nd asphalt conc rete ramps or other devices used to secure the plates and shoring of the trench to support all loads.
7. Contractor sha ll immediately mo bilize ne cessary pers onnel and equipment to repai r plate movem ents, s eparation, noi se, anchors, asphalt ramps o r any ot her defici ency.
Failure to respond within 2 h ours after being notified by the Engineer shall be grounds for the City to perform necessary repairs at the expense of the Contractor.
8. When plates are removed, the pavement surface shall be repaired to the satisfaction of the Engineer.
9. For trench wid ths exc eeding those in Table 7-10.4.8.2, a structural design shall be prepared by a California registered civil or structural engineer regularly engaged in t he design of shoring systems.
7-10.4.8.2 Thickness. Steel plate covers shall conform to Table 7-10.4.8.2.
TABLE 7-10.4.8.2
Trench Width Steel Plate Cover Thickness
Less than 10" 1/2" (12.5 mm)
10" (250 mm) to 1'-11" (580 mm) 3/4" (19 mm)
2' (600 mm) to 2'-7" (790 mm) 7/8" (22 mm)
2'-8" (820 mm) to 3'-5" (1040 mm) 1" (25 mm)
3'-6" (1070 mm) to 5'-3" (1600 mm) 1-1/4" (32 mm)
More than 5'-3" (1600 mm) See Note 1
Notes:
The Contractor shall submit a Working Drawing and calculations based on AASHTO H20-44 bridge loading.
7-10.4.8.3 Installation. Steel plate covers shall extend a minimum of 2 feet (600 mm) beyond trench edges. Unless otherwise specified in the Special Provisions or approved by the Engineer for the site conditions prior to use, steel plate covers shall be installed using Method 1. Method 2 shall not be used in a traveled lane.
Method 1. The pavement shall be cold milled to a depth equal to the thickness of the plate and to a width and lengt h e qual to the dimen sions of the plate. The c old m illing sh all produce a flat surface to s upport the p late with no hor izontal or vertical movement.
Horizontal gaps between the unmilled pavement and the plate shall not exceed 1 inch (25 mm) and shall be fil led wi th elastomeric sealant m aterial which may , a t the Contractor’s option, be mixed with no more that 50%, by volume, of Type I aggreg ate conforming to the requirements of Tables 203-5.2(B) and 203-5.3(A).
Method 2. The approach plate and ending plate (in longitudinal placement) shall be attached to the surface by a minimum of 2 dowels, ¾” diameter (19 mm), drilled at the corners of the plate and drilled 6 inches (150 mm) into the pavement. Subsequent plates may be butted next to eac h oth er. Temporary as phalt concrete (D2 -SC 8 00) sha ll be used to co nstruct tapers from the steel plate surface to the existing surface at a 12-inch (300 mm) run for each 1 inch (25 mm) thickness of steel plate. When steel plates are removed, the dowel holes in the pavement section shall be completely filled with elastomeric sealant material.
Revised 6/15/17 Contract No. 3840-23 Page 110 of 134
Advance traffic warning signs shall be installed as specified in the Special Provisions or shown on the TCP.
7-10.4.8.4 Pa yment. Steel plate bridging materials incl uding, but not l imited t o steel plates, anchoring d evices, cold milli ng, elastomeric sealant materia l, asphalt ramping and pad ding, signage, placing, installation, removal, relocation, preparation and processing of shop drawings and submittals to support t he use of steel plate bridging and all othe r materials, labor, supervision, overhead of any type or description will be considered as incidental to the work. No separate or additional payment for steel plate bridging will be made. No extension to contract time will be allowed for, or because of, the use of steel plate bridging.
7-11 PATENT FEES OR ROYALTIES. The Contractor shall absorb in its Bid the patent fees or royalties on any patented article or process furnished or used in the Work. The Contractor shall indemnify and ho ld the Agency harmless from any legal action that may be broug ht for infringement of patents.
7-12 ADVERTISING. The names, addresses and specialties of Contractors, Subcontractors, architects, or engineers may b e displayed on removabl e signs. Th e size and location shall be subject to the Engineer’s approval.
Commercial advertising matter shall not be attached to or painted on the surfaces of buildings, fences, canopies, or barricades.
7-13 LAWS TO BE OBSERVED. The Contractor shall ke ep fully in formed of State and National laws and County and Municipal ordinances and regulations which in any manner affect those employed in the Work or the materials used in the Work or in any way affect the conduct of the Work. The Contractor shall at a ll times observe and comply with such laws, ordinances, and regulations. Municipal ordinances that affect this work incl ude Chapter 1 1.06. Excavation and Grading. If this n otice s pecifies locations or poss ible materi als, such as bor row pits or gravel beds , for use i n the prop osed construction proj ect whic h would be subject t o Section 1601 or Section 1603 of the Fish and Game Code, the conditions established pursuant to Section 1601 et seq. of the Fish and Game Code shall become conditions of the contract.
7-14 ANTITRUST CLAIMS. Section 7103.5 of the Public Contract Code provides:
“In entering into a public work s contract or a subcontract to supply goods, services, or mat erials pursuant to a p ublic works co ntract, th e contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and int erest in an d to all caus es of ac tion it may have under Section 4 of the Clayton Act (15 U.S .C. Sec 15) or Cartwright Act (Chapter 2 [ commencing with Section 16700] of P art 2 of Division 7 of the Business and Professions Code), arising from pu rchases of goo ds, services, or materials pursu ant to the p ublic works contract or subcont ract. The assign ment s hall be made and b ecome effective at the time the awarding body tenders final payment to the c ontractor, without further acknowledgment of the parties.”
Revised 6/15/17 Contract No. 3840-23 Page 111 of 134
SECTION 8 – FACILITIES FOR AGENCY PERSONNEL
8-1 GENERAL. Field Facilities for Agency personnel are not required.
Revised 6/15/17 Contract No. 3840-23 Page 112 of 134
SECTION 9 – MEASUREMENT AND PAYMENT
9-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK.
9-1.1 General. Unless otherwise spec ified, q uantities o f wo rk shall be determined from measurements or di mensions in hor izontal planes. H owever, linear qua ntities o f pipe, piling, fencing and timber s hall be c onsidered as being the tr ue l ength measured along longitudinal axis.
Unless otherw ise provided in Specifications, vo lumetric quantities shall be the pr oduct of the mean area of vertical or horizontal sections and the intervening horizontal or vertical dimension.
The planimeter shall be considered an inst rument of precision adapted to me asurement of all areas.
9-1.2 Methods of Measurement. Materials and items of work w hich ar e t o be paid f or o n basis of measurement shal l be measu red in ac cordance with meth ods stipulated in t he particular sections involved.
9-1.3 Certified Weights. When payment is to be made on the basis of weight, the weighing shall be done on certified platform scales or, when approved by the Engineer, on a completely automated w eighing a nd recording system . The Contractor shall furnish the Engineer wi th duplicate licen sed w eighmaster’s c ertificates sho wing ac tual net weights. The Agency will accept the certificates as evidence of weights delivered.
9-1.4 Units of Measur ement. The system of measure for this contract shall be the U.S.
Standard Measures.
9-2 LUMP SUM WOR K. Items for whi ch quantities are indicated “Lump Sum”, “ L.S.”, or “Job”, shal l be paid for at the pr ice indi cated in the Bid. S uch payment shall be full compensation for the items of work and all work appurtenant thereto.
The Contractor shall submit to t he Engineer within 15 days after award of Contract, a det ailed schedule in triplicate, to be u sed as a basis for determining progress payments on a lump sum contract or designated lump sum bid item. This schedule shall equal the lump sum bid and shall be in such form and sufficiently detailed as to satisfy the Engineer that it correctly represents a reasonable apportionment of the lump sum.
9-3 PAYMENT.
9-3.1 General. The qu antities listed in the Bid s chedule will not govern final payment.
Payment to the Contractor will be made only for actual quantities of Contract items constructed in accordance with the Plans and Specifications. Upon completion of construction, if the actual quantities show either an increase or decrease from the quantities given in the Bid schedule, the Contract Unit Prices will prevail subject to the provisions of Section 3-2.2.1.
The unit and lump sum prices to be paid shall be full compensation for the items of work and all appurtenant work, including furnishing all materials, labor, equipment, tools, and incidentals.
Payment will not be made for materials wasted or disposed of in a manner not called for under the Contract. This includes rejected material not unloaded from vehicles, material rejected after
Revised 6/15/17 Contract No. 3840-23 Page 113 of 134
it has b een pl aced, and ma terial placed ou tside o f the Plan lines. No compensation will be allowed for disposing of rejected or excess material.
Payment for work p erformed or materials furnished under an Assessment Act Con tract will be made as provid ed in particular pr oceedings or legislative act un der which such contract was awarded.
Whenever any portion of the Work is performed by the Agency at the Contractor’s request, the cost thereof shall be ch arged against the Contr actor, and may be deducted f rom any amount due or becoming due from the Agency.
Whenever immediate action is required to prevent violation of any law, injury, death, or property damage, and precautions which are the Contractor’s responsibility have not been taken and are not reasonably expected to be taken, the A gency may, after re asonable attempt to notify the Contractor, cause such precautions to be taken and shall charge the cost thereof against the Contractor, or may ded uct such cost from any amount due or becoming due from the A gency.
Agency action or inactio n und er such cir cumstances shall not be construed as reli eving t he Contractor or its Surety from liability.
Payment shall not relieve the Contractor from its obligations under the Contract; nor shall such payment be construed to be acceptance of any of the Work. Payment shall not be construed as the tr ansfer of ownership of any equipment or materials to the Agen cy. Resp onsibility of ownership shall remain with the Contractor who shall be obligated to store any fully or partia lly completed work or structure for which payme nt has been m ade; or replace any materials or equipment required to be p rovided under the Contract which may be damaged, lost, stolen or otherwise degraded in any way prior to acceptance of the Work, except as provided in Section 6-10.
Guarantee periods shall no t be affected by any payment but s hall commence on t he date of recordation of the “Notice of Completion.”
If, with in the tim e fixed by law, a properly executed notice to sto p payment is filed with the Agency, due to the Contractor’s failure to pay for labor or materials used in the Work, all money due for s uch labor or materials wi ll be wi thheld from payment to the Co ntractor in accordance with applicable laws.
At the expira tion of 35 days from the dat e of a cceptance of the Work by the B oard, or as prescribed by law, the amount deducted from the final estimate and retained by the Agency will be paid to the Contractor except such amounts as are required by law to be withheld by properly executed and file d notices to stop p ayment, or a s may be authorized by the Contract to b e further retained.
9-3.2 Partial a nd Final Payment. The Eng ineer wi ll, afte r a ward of Contract, establish a closure date fo r th e pur pose of m aking monthly progress payments. The Contr actor may request in writing that such monthly closure date be changed. The Engineer may approve such request when it is compatible with the Agency’s payment procedure.
Each month, the Engineer will make an approximate measurement of the work performed to the closure date as basis for making monthly progress payments. The estimated value will be based on cont ract unit prices, complete d change order work and as provided for in Sec tion 9 -2 of these General Provisions. Progress payments shall be made no late r than thirty (30) calendar
Revised 6/15/17 Contract No. 3840-23 Page 114 of 134
days after the closure date. Five (5) working days following the closure date, the Engineer shall complete the detailed progress pay estimate and submit it to the Contractor for the Contractor’s information. Should the Contract or assert that additional payment is due, the Con tractor shall within ten (10) days of receipt of the progress estimate, submit a supplemental payment request to the Eng ineer with adequate justifi cation supporting the amount of su pplemental payment request. Upon r eceipt of t he supplemental payment reques t, the Engineer shall, as soo n as practicable after receipt, d etermine whether the su pplemental pa yment reques t is a pr oper payment reque st. If t he Engine er determines that the supp lemental payment request is not proper, then the request shall be returned to the Contractor as soon as practicable, but not later than seven (7) days after rec eipt. The returned request shall be accompanied by a document setting forth in writing the reaso ns why the supplemental payment request was not proper. In conformance with Public Contract Code Section 20104.50, the City shall make payments within thirty (3 0) days after receipt of an undisputed and proper ly submit ted supplemental p ayment request from the Contractor. If payment of the undisputed supplemental payment request is not made within thirty (30) days after receipt by the Engineer, then the City shall pay interest to the Contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
From each progress estimate, 10 percent will be deducted and retained by the Agency, and the remainder less the am ount of all previous payments will be pa id. After 50 perc ent of th e Work has been completed and if progress on the Work is satisfactory, the deduction to be made from remaining progress estimates and from the fin al estimate may be limited to $500 or 10 percent of the first half of total Contract amount, whichever is greater.
No progress payment made to t he Contractor or its suretie s will constitute a wai ver o f the liquidated damages under 6-9.
As provided in Sec tion 2 2300 of the California Public Contract Code, t he Contractor may substitute securities for any m onies withheld by the Agency to ensure performance under the Contract.
After f inal i nspection, the Engineer w ill make a Final Payment Estimate and process a corresponding payment. This estimate will be in writing and shall be for the total amount owed the Contractor as determined by the Engineer and shall be itemized by the contract bid item and change order item with quantities and payment amounts and shall show all deductions made or to be made for prior payments and amounts to be deduc ted under provisions of th e contract.
All prior estimates and progress payments shall be s ubject to correction in the Final Payment Estimate.
The Contractor shall have 30 calendar days from receipt of the Final Payment Estimate to make written statement disputing any bid item or change order item quantity or payment amount. The Contractor shall provide all documentation at the time of submitting the statement supporting its position. Should the Contractor fail to submit the statement and supporting documentation within the time specified, the Contractor acknowledges that full and final payment has been made for all contract bid items and change order items.
If the Contrac tor submits a written statement with documentat ion in the aforementioned time, the Engineer will review the di sputed item within 30 calendar da ys and make any ap propriate adjustments on the Final Payment. Remaining disputed quantities or amounts not approved by the Engineer will be subject to resolution as specified in Section 3-5, Disputed Work.
Revised 6/15/17 Contract No. 3840-23 Page 115 of 134
The written statement filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said disputed items. The Engineer will consider the merits of the Contrac tor’s claims. It will be t he respons ibility of the Co ntractor to furnish within a reasonable tim e such further in formation and de tails a s may be required by th e E ngineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying payment for the disputed items.
9-3.2.1 Payment fo r Claims. Except for those fin al payment i tems disputed in the written statement required in Section 9-3.2 all claims of any dollar amount shall be submitted i n a written statement by th e Contrac tor no la ter than the date of r eceipt of the final payment estimate. Those final payment items disputed in the written statement required in Section 9-3.2 shall be submitted no la ter than 30 days after rec eipt of the Final Payment estimate. No claim will be considered that was not included in this wr itten statement, nor will any cla im be allowed for whi ch w ritten notice or protest is required under any prov ision o f thi s contract inclu ding Sections 3-4 Changed Conditions, 3-5 Disputed Work, 6-6.3 Payment for Delays to Contractor, 6-6.4 Written Notice and Report, or 6-7.3 Contract Time Accounting, unless the Contractor has complied with notice or protest requirements.
The claims filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said claims. The Engineer will consider and determine the Contractor’s claims and it will be the responsibility of the Contractor to furnish within a reasonable time such further information and details as may be required by the E ngineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying the claims.
Payment for claims shall be pro cessed w ithin 30 cale ndar d ays of their resolution for th ose claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Section 3-5, Disputed Work, for those claims remaining in dispute.
9-3.3 Delivered Materials. The cos t of materials and equipment de livered but not incorporated into the work will not be included in the progress estimate.
9-3.4 Mobilization. When a b id i tem is included in the Pr oposal form for Mobilization and subject to the conditions and limita tions in the Specifications, the costs of work i n advance of construction operations and not dir ectly attributable to any specif ic bid item will be included in the p rogress estimate. When no such bid ite m is prov ided, payme nt for suc h costs will be considered to be included in the other items of work.
9-3.4.1 Mobilization and Preparatory Work. Payment for Mobilization and Preparatory Work will be made at the Contract price and includes full compensation for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment and incidentals, and for doing all the work involved in mobilization and preparatory work and operations, including, but not limited to, those necessary f or the mo vement of personnel, equipment, supplies, and in cidental to preparing to conduct work on and off the project site and other offsite fac ilities necessary for work on the project; for all other facilities, su reties, work an d operations which must be performed or costs i ncurred prior to b eginning work on v arious c ontract items on or off the project site, excepting those specifically paid for under separate bid items. Such activities shall include, but are not limited to, coordination with Agency forces, securing permits, surveying and staking, preconstruction surveys, securing construct ion wa ter supply , providing power necessary for construc tion, providing all tempor ary construction fencing; installing, m aintaining and removing project signs; providing on-site sanitary facilities; posting OSHA requirements and
Revised 6/15/17 Contract No. 3840-23 Page 116 of 134
establishing safety programs, demobilization and any other work or services not included in any other bid item. This work also includes the cost for maintaining and submitting the project record drawings at the end of the project. These record drawings must be reviewed monthly with the Agency to receive progr ess or final payments for any work. The Contractor hereby agrees that the price paid is sufficient for Mobilization and Preparatory Work, as described in this section, and that the Contractor shall h ave no right to addition al compensation f or Mo bilization and Preparatory Work.
Progress payments for Mobilization and Preparatory Work will be made as follows:
For the first progress payment (after the issuance of the Notice to Proceed), payment will be made at thirty percent (30%) of the amount bid for Mobilization and Preparatory Work. For the second progress payment, payment will be made at twenty percent (20%) of the amount bid for Mobilization and Preparatory Work. Also, for the second or subsequent progress payment in which the submittals for the generator set and the manual transfer switch are accepted by the Engineer, payment will be made at thirty percent (30%) of the amount bid for Mobilization and Preparatory Work. The remaini ng twenty (20%) of th e amount bi d for Mobilization and Preparatory Work will be made when all punch list items a re signed-off and completed to the satisfaction o f th e City Inspector, and t he C ontractor has completely d emobilized from th e project site(s).
9-4 BID ITEMS. Payment for each Bid Item shall be made at the qua ntity and type as listed in the Contractor's Proposal. All work shown or mentioned on the plans, in the Contract Documents, General Provisions, or Technical Provisions/Specifications shall be considered as included in the Bid Items. Contractor must protect existing utilities, improvements, landscaping, irrigation systems, and vegetation in place. If damaged during the work, Co ntractor is responsible to repair or replace any utilities, improvements, landscaping, irrigation systems, and vegetation at his expense.
Mobilization
The contract price paid for this bid item shall constitute payment for all mobilization work in accordance with Section 9-3.4.
Permitting and Design Services
The contract price paid for this bid item shall constitute payment for all engineering and permitting services required to prepare and submit shop , working drawings, structural calculations, and power system studies ; procuring necessary permits from the city’s Building Department and San Di ego Co unty Air Pollution Control District (APCD) to construct and operate the proposed improvements; and all services for the start-up testing and commissioning of the completed Work. Specific requirements for permitting and design services are provided in the Project technical specifications.
The permit template for the city ’s Building Perm it is provided in Appendix A. The C ontractor shall complete all forms included in the template and submit to the Building Department Front Counter, per the directions provided within the template, at 1635 Faraday Avenue, Carlsbad CA.
The city bui lding permit fee has been waived . The Contractor shall submit the Hazardous Materials Question naire provi ded in the template to the San Die go County Department of Environmental Health Hazardous Materials Division (HMD) and San Die go County Air Pollution Control District (APCD) and pay all associated fees required to obtain approval from these departments.
Revised 6/15/17 Contract No. 3840-23 Page 117 of 134
Furnish and Install Temporary Back-Up Generator
The contract price paid for this bid item shall constitute payment to permit, furnish, install, test and operate a temporary back-up 250-kilowatt generator throughout the duration of the facility’s permanent backup generator replacement.
Demolition
The contract price paid for this item constitutes payment for all demolition, removals and disposals of the existing generator set, building improvements, conduit, conductors, raceways, pavements, and appurtenances as shown or specified in the Contract Documents.
Furnish and Install Automatic and Manual Transfer Switches The contract price paid for this item constitutes payment to furnish, install, and conduct start-up testing of the automatic and manual transfer switch es, complete with all new conduit, conductors, raceways, concrete encasements, foundation, a ppurtenances, and associated earthwork as shown or specified in the Contract Documents.
Furnish and Install Generator Set (250-kW)
The contract price paid for this item constitutes payment to furnish, install, and conduct start-up testing of the new generator set, complete with structural anchorage system, hangers, supports, and ancillary systems including, but not limited to, controls, fuel, cooling, and exhaust systems.
Building & Civil Site Improvements
The contract price paid for this item constitutes payment to furnish and install the building and site improvements including ventilation systems, door s, drainage, and asphalt or Portland cement concrete pavements as shown or specified in the Contract Documents.
Revised 6/15/17 Contract No. 3840-23 Page 118 of 134
SUPPLEMENTAL PROVISIONS
TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 2, CONSTRUCTION MATERIALS
SECTION 200 - ROCK MATERIALS
200-2 UNTREATED BASE MATERIALS
200-2.2 Crushed Aggregate Base.
200-2.2.1 General.
Add the following:
1. Samples for testing shall represent every 500 cubic yards or one day's production, whichever is less. If the results of the aggregate grading tests do not meet the grading requirements in Table 200 -2.2.2 but meet the Quality Requirements specified in Table 200-2.2.3, placement of the aggregate base may be continued for the remainder of that day. However, another day's Work may not be started until test results indicate that the next material to be used in the Work will comply with the specified gradation and quality requirements.
2. If the results of both the aggregate grading and Sand Equivalent tests do not meet the requirements of Section 200 -2.2, the aggregate base which is represented by these tests shall be removed. However, if requested by the Contractor, and approved at the sole discretion of the Engineer, the aggregate base may remain in place and the Contractor shall pay to the Agency $50 per cubic yard for such aggregate base left in place. The Agency may deduct this amount from any moneys due, or that may be come due, to the Contractor under the Contract.
SECTION 201 - CONCRETE, MORTAR, AND RELATED MATERIALS
201-1 PORTLAND CEMENT CONCRETE
TABLE 201-1.1.2(A) Modify as follows:
TABLE 201-1.1.2(A) (3)
PORTLAND CEMENT CONCRETE
Type of Construction Concrete Maximum
Class Slump Inches
All Concrete Used Within the Right-of-Way 560-C-3250 (1) (2) Trench Backfill Slurry 190-E-400 8”
Street Light Foundations and Survey Monuments 560-C-3250 4” Traffic Signal Foundations 590-C-3750 4”
Concreted-Rock Erosion Protection 520-C-2500P
310-C-17
per Table 300-11.3.1
Revised 6/15/17 Contract No. 3840-23 Page 119 of 134
(1) Except that concrete required to be of higher strength by Table 201-1.1.2(A) SSPWC shall be as per Table 201-1.1.2(A) SSPWC.
(2) As per Table 201-1.1.2(A) SSPWC.
(3) Portions of Table 201-1.1.2(A) of the Standard Specifications for Public Works Construction not shown herein as changed are not affected by this table.
201-1.2.4 Chemical Admixtures.
Substitute the following:
(d) Air-Entraining Adm ixtures. The air con tent shall not deviate from the p ercentage specified or per mitted by more than 1-1/2 percentage points. The air content o f freshl y mixed concrete will be determined by California Test 504.
SECTION 203 - BITUMINOUS MATERIALS
203-6 ASPHALT CONCRETE
203-6.2.1. Asphalt Binder.
Add the following:
Wet Mix or Core sampled asphalt concrete will be co nsidered in conforma nce with the m ix design when the Asp halt Binder content is withi n +/-0.5% of th e design mix and th e gradation conforms to the g rading as shown in Table 203-6.4.4. Deviations in gr adation may be considered in conformance with t he mix des ign p rovided the sta bility of the completed mi x complies with the requirements for Hveem Stability per Table 203-6.4.4.
203-6.4 Asphalt Concrete Mixtures.
Add the following:
Conventional Asphalt concrete shall be class C 2-PG64-10 for a surface course 2 inches in depth and B-PG64-10 for all base co urses. Asp halt con crete shall be class D2-PG70-10 for dikes and class E-PG70-10 ditches.
203-6.4.4 Composition and Grading.
Add the following:
Evaluation of asphalt concrete shall be determined from samples of asphalt concrete taken after completion of all proce ssing ( Wet Mix) or by core sa mple analysi s of the in-place a sphalt concrete or by direct central plant inspection t hat co nfirms the production of a particular m ix design and verifies using samples of aggregate taken before the addition of asphalt and mineral filler (Bin). All samples shall be taken in accordance with Calif. Test 125.
When Wet Mix or Core samples of asphalt concrete are to be used for evaluation, sufficient size samples shall be taken to ensure representative and adequate quantity of material for:
1. Asphalt Content a nd Gradation of Extr action using Calif. Test 38 2 or A STM 2172, and Calif. Test 202.
2. Stability using:
a. Hveem stability Value using Calif. Tests 304 and 366 shall be the average of three individual Values
and/or
b. Marshall Stability1 in accordance wi th the Asphalt Insti tute's MS -2 fabricated and tested for traffic volume and shall be the average of three specimens.
Revised 6/15/17 Contract No. 3840-23 Page 120 of 134
1Only use Ma rshall Stability when the deviation b etween individual Hveem Stabilometer Val ues are greater than +/-5.
When using core sample analysis, the samples must be properly prepared to safeguard against influx of outside contaminates and so that the cut surfaces do not influence the test results.
The amount of asphalt bi nder used in asp halt concrete placed in dikes, gutters, gutter f lares, overside drains and aprons at the ends of drainage structures shall be increased one percent by mass of the aggregate over the amount of asphalt binder determined for use in asphalt concrete placed on the traveled way.
Wet Mix or Core sampled aspha lt concrete will be considered in conf ormance w ith th e mix design when the asphalt content is within +/- .40 of the design mix and the gradation conforms to the grading as shown in Table 203 -6.4.4. Deviations in gradat ion may b e considered in conformance with the mix design p rovided the stability of th e completed mix complies with the requirements for Hveem Stability per Table 203-6.4.4.
SECTION 213 - ENGINEERING GEOSYNTHETICS
213-5 GEOTEXTILES AND GEOGRIDS
Add the following section:
213-5.1 General. Geotextile types shall be used for the applications listed in Table 213-5.1.
Table 213-5.1
GEOTEXTILE APPLICATIONS
Application of Geotextile Type Designation
Separation of Soil and Street Structural Section 90WS
Separation of Soil and Subsurface Aggregate Drain 180N
Reinforcement of Street Structural Section 200WS
Remediation and Separation of Soil 270WS
Reinforcement of Soil 270WS
Drainage at the Interface of Soil Structures N/A
Drainage at the Interface of Soil and Structures N/A
Rock Slope Protection Fabric for Rock Sizes Below 225 kg (¼ Ton) 180N Rock Slope Protection Fabric for Rock Sizes Including and Above 225 kg (¼ Ton) 250N Plant Protection Covering 90N
Erosion C ontrol Fence w ith 14 AWG - 150 mm x 150 mm (6”x6”) Wire and 3 m (10’) Post Spacing
90WS
Erosion Control Fence with 1.8 m (6’) Post Spacing and No Wire Fencing 200WS
Add the following section:
213-5.2 Erosion Control Sp ecialties. Storm wa ter erosio n control plans shal l b e prepared, implemented, and main tained by individuals with t he respective qualifications and certification as specified in the City of Carlsbad Engineering Standards Volume 4.
Revised 6/15/17 Contract No. 3840-23 Page 121 of 134
Add the following section:
213-5.3 Gravel bags. Gravel bags for the use of temporary erosion control shall be burlap type, filled with no l ess than 23 kg (50lbs ) of 19 mm ( 3/4“) crushed rock an d securely tied closed.
Plastic bags are not acceptable.
SECTION 300 – EARTHWORK
Add the following section:
300-2.10 Grading Tolerance. The Contractor s hall f inish excavated areas ot her than sl opes and subgrade below structures, within the roadway and si dewalk areas within 30 mm (0.1’) of the grad es s hown on the plans. Subgrade tolerances s hall confo rm to the requ irements of section 301-1.4.
Add the following section:
300-12 STORM WATER POLLUTION PREVENTION PLAN
300-12.1 Storm Water Pollution Pr evention Plan. As part of the stor m water po llution prevention work, t he Contractor shall prepare and subm it Storm Water Pollution Prevention Plan, hereafter referred to as the "SWPPP,". The SWPPP shall conform to the requirements of the City of Carlsbad Engineering Standards Volume 4 “SWPPP Manual”, “Greenbook” Standard Specifications fo r Public Wor ks Constru ction, the req uirements in t he California Storm Wate r Quality Association, Stormwa ter Best Management Practice Ha ndbook, Construction (“Handbook”), th e requi rements o f the Per mit, the requirements in t he plans and these supplemental provisions.
300-12.2 SWPPP Document. Within 15 calendar days after the exe cution of the contract, the Contractor shall submit 3 copies of the SWPPP to the Engineer, in accordance with Section 2-
5.3. I f revisions are required, the Contractor s hall revise an d resubmit t he SWPPP within 15 days of receipt of the Engineer’s comments and shall allow 5 days for the Engineer to rev iew the revisions. Upon the Engineer’s acceptance of the SW PPP, 3 additional copies of the SWPPP, incorporating the required changes, shall be submitted to the Engineer.
The objectives of the SWPPP shall be to identify pollution sources that may adversely affect the quality o f st orm wa ter d ischarges asso ciated with t he project a nd to ide ntify, con struct, implement and maintain storm wat er pollution prevention measures, he reafter r eferred t o as control measures, to reduce to the extent feasible pollutants in storm water discharges from the construction site both during and after construction is completed under this contract.
The SWPPP shall incorporate control measures in the following categories:
1. Soil stabilization practices;
2. Sediment control practices;
3. Wind erosion control practices;
4. Non-storm water management and waste management and disposal control practices; and
5. Daily street sweeping
Specific ob jectives a nd minimum req uirements for each category of control measures are contained in the Handbook.
Revised 6/15/17 Contract No. 3840-23 Page 122 of 134
The Contractor s hall design ate a Wate r Pollution C ontrol Manager who will have th e responsibilities outlined in the SWPPP.
The SWPPP shall include, but not be limited to, the following items as described in the SWPPP:
1. Source Identification;
2. Erosion and Sediment Controls;
3. Non-Storm Water Management;
4. Waste Management and Disposal;
5. Maintenance, Inspection and Repair;
6. Training;
7. List of Contractors and Subcontractors;
8. Post-Construction Storm Water Management;
9. Preparer;
10. Copy of the local permit;
11. BMP Consideration Checklist;
12. SWPPP Checklist;
13. Schedule of Values; and
14. Storm Water Pollution Prevention Drawings.
The Contractor shall amend the SWPPP, graphically and in narrative form, whenever there is a change in construction activities or o perations whic h m ay af fect the discharge o f significa nt quantities o f pollutants t o surfa ce waters, ground waters, m unicipal s torm drain s ystems, or when deemed necessary by the Engineer. The SWPPP shall also be amended if it is in violation of any condition of the Permit or has not effectively achieved the objective of reducing pollutants in storm water discha rges. Amendments sh all s how additional control measures or revised operations, in cluding those in are as not s hown in the initially ac cepted SW PPP, wh ich are required on the project to control water pollution effectively. Amendments to the SWPPP shall be submitted for review and acceptance by the Engineer in the same manner specified for the initially acce pted SWPPP. Accepted amendments shall be dated a nd l ogged in t he SWPPP.
Upon a cceptance of the amendm ent, the C ontractor shall imp lement the ad ditional con trol measures or revised operations.
The Contractor shall keep a copy of the acc epted SWPPP an d accepted amendments at the project s ite. The SWPPP s hall be made a vailable upon re quest o f a r epresentative o f the Regional Water Qual ity Con trol B oard, State Water Res ources Con trol Board, U.S.
Environmental Protection Agency or local storm water manage ment agency. Requests by the public shall be directed to the Engineer.
300-12.3 SWPPP Implementation. Upon acceptance of the SWPPP, the Contractor shall be responsible t hroughout the d uration of the project for installi ng, c onstructing, insp ecting and maintaining the control measures included in the SWPPP and any amendments thereto and for removing and disposi ng of temp orary control measures. Unless o therwise dir ected by the Engineer or specified in these s upplemental pr ovisions, th e Contract or's responsib ility for SWPPP implementation shall continue throughout any temporary suspension of work ordered in accordance with Section 6-3, "Suspension of Work". Requirements for installation, construction, inspection, maintenance , removal an d disposal of control me asures are specified in the “Handbook” and these supplemental provisions.
Revised 6/15/17 Contract No. 3840-23 Page 123 of 134
Soil stab ilization pr actices and sediment control measures, i ncluding minimum requirements, shall be provided throughout the rainy season, defined as between October 1 and April 30.
Implementation of soil stabilization practices and sediment control measures for s oil-disturbed areas of the project site shall be completed, except as provided for below, no later than 20 days prior to the beginning o f the rainy season or upon start of applicable construction activities for projects which begin either during or within 20 days of the rainy season.
The Contractor shall i mplement, year-round and throughout the duration of the project, control measures in cluded in th e SWPPP fo r sediment tra cking, wind er osion, non-storm water management and waste management and disposal.
The Engineer may order the suspension o f construction opera tions, at the Cont ractor’s cost, which create water pollution if the Contractor fails to conform to the requirements of this section as determined by the Engineer.
300-12.4 Maintenance. To ensure the proper implementati on a nd fun ctioning of control measures, t he C ontractor shall re gularly in spect a nd maintain the construction site for the control measures identified in the SWPPP, as described in Section 7-8. The Contractor shall identify corrective actions and time frames to address any damaged measures or reinitiate any measures that have been discontinued.
The construction site inspection checklist provided in the “Handbook” shall be used to ensure that t he necessary measures are being properly implemented, and to ensu re t hat the control measures are fun ctioning adequately. The Co ntractor s hall su bmit one co py of each site inspection record to the Engineer, within two days of the inspection.
During th e rainy season, inspections of the con struction site shall be conduct ed b y the Contractor to identify deficient measures, as follows:
1. When the five-day rain probability forecast exceeds forty percent (40%).
2. After any precipitation which causes runoff capa ble of ca rrying sediment from the construction site;
3. At 24-hour intervals during extended precipitation events; and
4. Routinely, at a minimum of once every week.
If the Contractor or the Engineer identifies a deficiency in the deployment or functioning of a n identified control measure, the deficiency shall be corrected by th e Contractor immediately, or by a later date and time if requested by the Contractor and accepted by the Engineer in writing, but not l ater than the onset of subsequent precipitation events. The correction of deficien cies shall be at no additional cost to the City.
300-12.5 Payment. The contract lump sum pr ice paid f or th e SWPPP work shall include full compensation for the design, submittal, obtaining approval, and amending the Tier 2 SWPPP and fo r furnishing all labo r, materials, to ols, equipment, and inc identals to install, implemen t, maintain and remove c onstruction BMPs per the ap proved SWPPP. The m ost recent Tie r 2 construction SWPPP Template is a vailable on the City Website and an ex ample is included in Appendix “B”.
Partial payment shall be based on the percentage of the total value of work completed.
Revised 6/15/17 Contract No. 3840-23 Page 124 of 134
SECTION 301 - SUBGRADE PREPARATION, TREATED MATERIALS
AND PLACEMENT OF BASE MATERIALS
301-1 SUBGRADE PREPARATION
301-1.2 Preparation of Subgrade.
Modify the second and third paragraphs as follows:
Change each instance reading “6 inches” to “12 inches”.
301-1.3 Relative Compaction.
Delete the first paragraph and substitute the following:
The Contractor shall compact the upper 300 mm (12”) of subgrade beneath areas to be paved, have base or subbase material placed on them (including pipelines), or curb, gutter, curb and gutter, alley pavement, driveway, sidewalk constructed over them, to no less than 95 percent maximum dry density as determined by ASTM D1557.
301-1.7 Payment.
Modify the first paragraph as follows:
Payment for subgr ade prepara tion shall be incidental to the contract bid price for wh ich the subgrade is prep ared a nd shall include all labor , materia ls; inc luding water, o perations and equipment to scarify, ad just moisture, compact or recompact the subgrade, both in cut a reas and in fill areas, and no further compensation will be allowed.
SECTION 302 - ROADWAY SURFACING
302-5 ASPHALT CONCRETE PAVEMENT
Add the following section:
302-5.2 Pavement Transitions. The Contractor shall ramp the ap proaches and termini to all structures and vertical joints in the cold-milled area which are transverse to through traffic with temporary asphalt concre te paveme nt as s pecified in Section 306-13.1. Ramps s hall be constructed the sa me day as cold mi lling an d removed the same day as pe rmanent pav ing.
Ramp dimensions and compaction shall be as approved by the Engineer.
302-5.4 Tack Coat. Add the following: If the as phalt concrete pavement is being constructed directly upon an existing hard-surfaced pavement, a tack coat of PG 64-10 paving asphalt at a rate of 0.05 gallon per square yard or S S-1h emulsion at a rat e between 0.05 and 0.10 gal/SY shall be unifor mly applied upon the existing pavement preceding the placement of the asphalt concrete.
The contact surfaces of all cold pavement joints, curbs, gutters, manholes, and the like shall be painted with PG 64 -10 p aving asphalt, or SS -1h emulsion, immediately before th e adjoining asphalt concrete is placed.
The Contractor shall place a tack coat between the successive interfaces of existing pavement and new asphalt concrete.
Revised 6/15/17 Contract No. 3840-23 Page 125 of 134
302-5.5 Distribution and Spreading.
Add after the second sentence of sixth paragraph:
The C ontractor shall provide the self-propelled s preading and fin ishing mach ine used to construct the asphalt concrete surface course with an automatic screed control. The automatic screed control shall be 5 .5 m (18’) min imum length. The paving machine shall be operated by an operator and two full-time screed men during all paving. The Contractor shall provide an on- site backup paving during all paving operations. No conveyor belt system s will be allowed for moving the AC. No AC windrows will be allowed . Only a surge volume/remix material transfer vehicle (MTV) is allowed to receiv e the AC from the haul tr ucks and then place it in th e self- propelled spreading and finishing machine. If the Engineer determines the use of the MTV is not practical for a portion of the project, the Engineer may waive its requirement for that portion.
302-5.6.1 General.
Add to the second paragraph, Part (2):
Pinched joint rolli ng procedures shall be required , and vibratory roller s shall be lim ited t o breakdown, unless otherwise directed by the Engineer.
Add after the last paragraph:
Unless directed o therwise by the Engineer, the initial breakdown rolling shall be followed by a pneumatic-tired roller as described in this section.
302-5.9 Measurement and Payment. Replace the first sentence with the following: Payment for pavement resurfacing shall be made at the unit bid price for the item requiring such work.
Add the following section:
302-15 PUBLIC CONVENIENCE AND TRAFFIC CONTROL
The Contractor shall schedule the work so as to pre vent damage by all traffic. The Contractor shall not sc hedule work so as to conflict with trash pickup. The trash hauling schedule can be obtained by calling the city’s contracte d waste company. The C ontractor shal l acco mmodate mail delivery to residences and businesses during the work.
At least two weeks prior to work, Contractor shall send, by first class mail, notification letters to all property addresses on which resurfacing shall occur. Obtaining the appropriate addresses shall be th e Contractor’s re sponsibility. A sample letter shall be p rovided by the city and the Contractor sh all use the c ity’s sample letter and modify it with the appropriate s treet n ames, dates, times, and phone numbers specific to the work.
The limits and sequencing of the Contractor’s resurfacing operations shall impact no more than 900 lineal feet of street or curb-side parking for residents and business on any given day.
Seventy-two hours prior to t he start of any construction in the public right-of-way that affect s vehicular traffic and/or parking or pedestrian routes, the Contract shall give written notification of the impen ding disruption via door hange rs. For a full street cl osure, all residences and/or businesses on the affected street or alley shall be no tified. For partial street closures, or curb, sidewalk and driveway repairs, the resi dences and/or businesses directly affected by the wor k shall be notified.
The Contractor shall deliver the advance notification door hanger which shall state the date and time th e work will begin and its anticipa ted d uration. The notification shall li st two t elephone numbers that may be calle d to obtain additi onal information. One nu mber shall be the
Revised 6/15/17 Contract No. 3840-23 Page 126 of 134
Contractor’s permanent office or field office and the other number shall be a 24 -hour number answered by a representative of the Contractor who is knowledgeable about the project. At least one of the phone numbers shall be in the 760 area code. An answering machine shall not be connected to either number. The notification shall also gi ve a b rief description of the work and simple instru ctions to the home or business owner on what they need to do t o facilitate the construction. The Contractor shall use the sample do or hanger provided by the city and su bmit door hangars to the Inspector for approval. Notices shall not be distributed until approved by the Inspector.
The notification shall be pre-cut in a manner that enables it to be affixed to a doorknob without adhesives. It shall be a minimum size of 4 inches by 8-1/2 inches and shall be brightly colored with contrasting printing. The material shall be equivalent in strength and durability to 65-lb card stock. The printing on the notice shall be no smaller than 12-point. The door hanger shall list the street name, date, time, phone numbers, and appropriate information specific to the work.
The preparation, materials, printing and distribution of the notifications shall be included in the contract price for the Work r equiring such notifications and no se parate or additional payment shall be made.
SECTION 303 CONCRETE AND MASONRY CONSTRUCTION.
303-1 CONCRETE STRUCTURES
303-1.2 Subgrade for Concrete Structures.
Add the following:
If groundwater is encountered, Contractor shall work a minimum 2’ deep of ¾” gravel into soil to provide an adequate base for construction of concrete structure.
303-1.11 Measurement.
Delete the subsection in its entirety and replace with the following:
Concrete structures will be measured for payment by each structure installed as specified in the bid schedule and in accordance to the plan and any referenced standard drawings.
303-1.12 Payment.
Delete the subsection in its entirety and replace with the following:
Payment for concrete structures will be made a s set forth in the Bid S chedule. Payment shall include comp ensation for furni shing all labor, materi als, tools, and equipme nt necessary to construct the concrete structures complete in place. Items shall include submittal of P CC mix design for appr oval, structure excavation, subgrade and b ase preparation, furnishing PCC and casting-in-place, steel reinforcement, forms, covers, rims, grates, frames, collars, cone and draft sections, bases, steps, c lean up; a nd f or all other work necessary to i nstall the conc rete structure, complete in place, and no additional compensation will be allowed therefor.
303-5 CONCRETE CURBS, WALKS, G UTTERS, CROSS GUTTERS, ALLE Y INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.
303-5.1.1 General.
Revised 6/15/17 Contract No. 3840-23 Page 127 of 134
Add the following:
Portland Cement Concrete construction shall include, but not limited to, curbs, walkways, cross gutters, access ramps , d riveways, concrete curb outlet, terrace ditch es, a nd al l other miscellaneous PCC construction items as indicated on the plans and per these Specifications.
Removal of adjacent asphalt concrete and aggregate ba se removal associated with concrete curb construction shall be replaced with full depth asphalt concrete with a minimum width of one foot perpendicular to the f ace of c oncrete edge. The repl aced sec tion shall conform to the requirements o f Sections 203-6, 302-5, 401-3 and match the depth of the ad jacent concrete gutter.
The Contractor shall verify with a “smart level”, strin g li ne and/or water t esting that positive drainage is maintained upon completion of finishing, and any irregularities causing w ater ponding shall be corr ected an d refinished. T he CITY shall be present t o verify the concrete forms, prior to pouring any PCC construction improvements.
303-5.5.2 Curb.
Add the following:
The Contractor shall stamp the curb fa ce with 75 mm (3”) high block letters directly above the point that it is crossed by underground facilities with the marking specified in Table 303-5.5.2(A)
TABLE 303-5.5.2(A)
Curb Face Markings
Type of underground facilities Marking
Water Service Lateral W
Sewer Service Lateral S
Irrigation Water Lateral or Sleeve RW
303-5.9 Measurement and Payment.
Add the following:
Curb and gutter, and curb, shall be considered as continuing across driveways, access ramps and drainage inlets when constructed adjacent thereto. Neither curb and gutter nor curb will be paid for across the length of local depressions, except that which oc curs in gutter transitions at each side of an inlet.
SECTION 306 – OPEN TRENCH CONDUIT CONSTRUCTION
306-3 TRENCH EXCAVATION
Add the following:
306-3.1 General. When the actual elevation or posi tion of a ny existing pipe, condu it, or other underground appurtenances c annot b e determined without excavation, th e Co ntractor shall excavate and expose the existing i mprovement at the loca tion sh own on the Plans and any other locations deemed nec essary by the Engi neer. Such excavation s hall b e considered as part of the excavation necessary for the work. The Engineer shall be given the o pportunity to inspect the existing improvements when it is exposed. Any adjustments in line or grade which may be necessary to accomplish the intent of the plans shall be made at no additional costs.
Revised 6/15/17 Contract No. 3840-23 Page 128 of 134
Add the following:
306-3.2 Removal of Surface Improvements.
Add the following:
Bituminous pavemen t, concrete pavement, curbs, sid ewalks, o r driveways r emoved in connection wi th construc tion shall be re moved i n accordance with Subsectio n 401 of the Standard Specifications and these Special Provisions and reconstructed in-kind.
306-3.5 Maximum Length of Open Trench.
Delete the first sentence for the first paragraph and replace with the following:
Except by permission of the Engineer, the maximum length of open trench where prefabricated pipe is used shall be the di stance necessary to accommodate the amount of pipe installed in a single day.
306-12 BACKFILL
306-12.1 General.
Add the following:
The Contractor shall install detectable underground utility marking tape above each or, in the case of bundled underground conduit of the same type, the upper underground conduit being installed by the open trench method.
Delete the following section in its entirety and replace with the following:
306-12.3.2 Compaction Requirements. The Contractor shall densify trench bac kfill to a minimum of 90 percent re lative compaction except that in the top 915 mm (36”) of the street right-of-way, compaction shall be 95 percent.
306-13 TRENCH RESURFACING
306-13.1 Temporary Resurfacing.
Add the following:
Temporary bituminous resur facing materials which are placed by the Contractor are for its convenience and shall be at no cost to the Agency. Temporary bituminous resurfacing materials shall be used in lieu of perma nent re surfacing o nly when approved by t he Engineer. When temporary bituminous resurfacing materials are used in lieu of permanent resurfacing it shall be removed and replaced with permanent re surfacing within 7 days of pl acement. No additional payment wil l be ma de for temporary bituminous resurfacing materials. The price bid for the associated conduit or structure shall include full co mpensation for furnishing, placing, maintaining, removing, and disposing of such temporary resurfacing materials.
306-13.2 Permanent Resurfacing.
Add the following:
Except as provided in s ection 306-13.1, “Temporary Resurfacing,” the Contractor shall perform permanent trench resurfacing within 24 hours after the completion of backfill and compaction of backfill and aggregate base materials.
Revised 6/15/17 Contract No. 3840-23 Page 129 of 134
SECTION 400 – PROTECTION AND RESTORATION
400-1 GENERAL
Add the following:
The Contractor shall replace all pavement s triping, markings and markers which are not designated for removal and are damaged as a result of its operations.
400-2 PERMANENT SURVEY MARKERS
Delete the second paragraph and subparagraphs a), b) and c).
400-3 PAYMENT.
Delete in its entirety and replace with the following:
No separate or additional payment will be made for 1) protection of existing improvements, and 2) restoration of existing improvements.
No separate or additional payment will be made to restore permanent survey makers.
SECTION 401 – REMOVAL
401-3 CONCRETE AND MASONRY IMPROVEMENTS
401-3.2 Concrete Cu rb, Walk, Gu tters, Cross Gutters, Curb Ramps, Driveway and Alley Intersections.
Delete the third and fourth sentence and add the following:
All existing concrete shall be removed to the nearest joint. Concrete shall be removed to neatly sawed edges wi th saw cuts ma de to a depth deep enough to produce a clean straight break without loosening, cracking or dama ging adjoining improvements. PCC and al l o ther material unsuitable for use as fill, as determined by the Engineer, shall be removed from the right-of-way and disposed of by the Contractor at a site of his own choice and shall pay all costs incidental to the disposal.
Add the following section:
401-3.2.1 Adjacent Asphalt Concrete Removal. Removal of asphalt c oncrete and aggerate base associated w ith concrete driveway, ramp and curb and gutter construction shall be replaced with full depth asphalt concrete to a minimum width of one foot perpendicular from face of nearest concrete edge. Removal of adjoining asphalt section and the full depth replacement is incidental to the concrete curb and gutter work as described in section 303-5.
Revised 6/15/17 Contract No. 3840-23 Page 130 of 134
SUPPLEMENTAL PROVISIONS
TO
STANDARD SPECIFICATIONS FOR PUBLIC WORKS
CONSTRUCTION
PART 6 TEMPORARY TRAFFIC CONTROL
SECTION 601 – TEMPORARY TRAFFIC CONTROL FOR
CONSTRUCTION AND MAINTENANCE WORK ZONES
Add the following section:
601-1.2 Payment.
The Contract price paid for Temporary Traffic Control shall include full compensation for, but not limited to , d esign, submittal and a pproval of the temporary traffic co ntrol plan (TCP) and furnishing all labor, materials, tools, equipment, and incidentals for storing, placing, maintaining, moving to n ew loc ations, replacing and removing all traffic c ontrol zone device s including flaggers, construction area signs and signage, channelizing devices including traffic barriers and end treatments, traffic sign enhancement devices including portable changeable message signs and flashing arrow signs, temporary traffic striping and pavement markings and as shown on the Plans or approved TCP and in accordance with the Contract Documents.
Full compensation for removing and salvaging the traffic control equipment and materials that are to be reused or reset in the Work shall be considered included in the Contract price paid for Temporary Traffic Control and no additional compensation will be allowed therefor.
Progress payments for Temporary Traffic Control shall be based on the percentage of the total value of work completed.
601-3 TEMPORARY TRAFFIC CONTROL (TTC) ZONE DEVICES
601-3.1 General.
Add the following:
The C ontractor shall furnish an d install tempo rary traffi c pa vement ma rkers, channelizers, signage, railing (type K), barriers, crash cushions and end treatments for railings and barriers at the locations show n on the P lans or the approved TCP and as requ ired b y the Contract Documents.
Add the following section:
601-3.4.1 General.
Add the following:
If temporary traffic signs are displaced or ov erturned by any cause during the progress of the Work, the Contra ctor shall immediately replace the signs in th eir ap proved locations . The Contractor shall maintain all temporary traffic signs used in the Work in a clean, reflective and readable condition. The Co ntractor shall replace or res tore graffit i marked temporar y traffic signs and posts used in the Work within 8 hours of such discovery.
Revised 6/15/17 Contract No. 3840-23 Page 131 of 134
In the e vent that the Cont ractor fails to install and/or maintain barricades or such other tr affic signs, markings, delineation or devices, th e Engineer may, at his/her sole opti on, may co rrect the deficiency and charge the Contractor fifty dollars ($50.00) per day per traffic sign or device, or the actual cost of providing such traffic control facility, whichever is greater.
601-3.5 Signs and Signage
601-3.5.1 General.
Delete in its entirety and replace with the following:
Unless otherwise spe cified, signs shall conform to the C alifornia MUTCD. Portable signs shall consist of a base, standard o r fra mework, and a s ign panel and conform with ap plicable provisions for portable sig ns in Calt rans Standard Specification 12 -3.11. Sign units shall be capable of being delivered to the Work site and placed into immediate operation. The Contractor shall provide and install all temporary traffic control signs, markers, markings, and delineators at locations shown on plans and specified herein.
Signage shall include all temporary signs required for the direction of tra ffic through or a round the Work site. Sign placement shall conform to the California MUTCD and the TCP.
Temporary “No Parki ng” and “N o Stopping” signs shall be installed at le ast 24 hours bef ore enforcement. Public notification of temporary “No Parking” restriction shall be posted at least 72 hours before enforcement of the “No Parking” zone . The notification shall state the d ate and time of parking restriction for a dura tion not to exceed the time necessary to complete the Work at that location. Failure to meet the date s o indicated will require re-posting the no tification in advance of the rescheduled Work.
601-3.5.2 Payment.
Modify this section as follows:
Payment for signs and signage sha ll be included in the con tract price for Temporary Traffic Control as specified in Section 601-2.2.
601-3.6 Channelizing Devices
601-3.6.1 General.
Replace this section with the following:
Channelizers shall be new su rface-mounted type and shall be fu rnished, placed, an d maintained at th e loc ations shown on the plans. Channelizer p osts shall be orang e i n col or.
Channelizers shall have affixed white re flective sheeting a s specified in th e special provisions.
The reflective sheeting shall be 75 mm x 300 mm (3” x 12”) in size. The reflective sheeting shall be visible at 300 m (1000’) at night under illumination of legal high beam headlights, by persons with vision of or cor rected to 20/20. The channelizer bases shall be cemented to the pavement in the same manner as provided for cementing pavement markers to pavement in Section 312- 1, “Placement.” Channelizers shall be appl ied only on a clean, dry surface. Channelizers shall be placed on the alignment and location shown on the plans and as directed by the Engineer.
The channelizers shall be placed uniformly, straight on tangent alignment and on a true arc on curved alignment. All layout work necessary to p lace the channelizers to the proper a lignment shall be perfor med by th e Contractor. If the channelizers are displaced or fail to remain in an upright position, from any cause, the channelizers shall immediately be replaced or restored to their original loca tion, b y the Contra ctor. The Contrac tor shall provide the En gineer wi th a Certificate of Compliance in accordance with the provisions of Section 4-1.5, "Certification”. Said certificate shall certify that the cha nnelizers c omply w ith the plans and specifi cations and
Revised 6/15/17 Contract No. 3840-23 Page 132 of 134
conform to the prequalifi ed design and material r equirements appr oved b y the Engineer a nd were manufactured in accordance with a quality control program approved by the Engineer.
Add the following subsection:
601-3.6.5.1 Temporary Railing and Crash Cushions. Temporary railing (Type K) shall consist of interconnected n ew or u ndamaged used precast concrete b arrier u nits as shown on the plans. Temporary sand-filled crash cushions shall consist of new or undamaged used temporary sand-filled crash cushions units as shown on the plans.
Add the following subsection:
601-3.6.5.2 Appearance. Exposed surfaces of new and used units of temporary railing (Type K) shall be freshly coated with a white color paint prior to the ir first use on the project. The p aint shall conform to the provisions in sectio ns 210 -1.5 “Paint Systems” and 310 “ Painting”.
Contractor shall be responsible for the removal and cleanup or painting over the graffiti from the K-Rails within 48 hours. The Contractor shall replace or repaint units of temporary railing (Type K) or shall remove graffiti, tire or vehicle marks, dirt or other materials that mar the appearance when ordered by the Engineer.
Add the following subsection:
601-3.6.5.3 Manufacture of Temporary Railing. In addi tion to the req uirements he rein, the temporary railing (Type K) shall be manufactured per Caltrans Standard Drawing T3. Concrete used to manufacture Temporary railing (Type K) shall conform to the provisions in sections 201- 1, “Portland Cement Concrete” and 303-1 “Concrete Structures”. Load tickets and a Certificate of Compliance will not be re quired. Reinforcing st eel shall conform to Section 201-1, “Portland Cement Concrete” and Section 303-1 “Concrete Structures”. Steel bars to receive bolts at ends of concrete panels shall conform to ASTM A36/A36M. The bolts shall conform to ASTM A307. A round bar of the same dia meter may be substituted for the end -connecting bolt shown on th e plans. The bar shall conform to ASTM A36/A36M, shall have a minimum length of 660 mm and shall have a 75 mm (3”) diameter by 9 mm (3 /8”) thick plate welde d on the upper end with a 5 mm (3/16”) fillet weld. The final surface finish of temporary railings (Type K) shall conform to the provisions in S ection 303 -1.9.2 “ Ordinary Surface Finish. ” Exposed surfaces of concrete elements shall be cured by the water method, the form s-in-place method, or the pi gmented curing compound method. The pigmented curing compound shall be type 2 curing compound.
Temporary railing (Type K) may have the Contractor’s name or logo on e ach panel. The na me or logo shall not be more tha n 100 mm in he ight and shall be loca ted not more than 300 mm above the bottom of the rail panel.
Add the following subsections:
601-3.6.5.4 Installation of Te mporary Railing. In addition to the requirements herein, the temporary rai ling (Type K) shall be insta lled per Caltrans Standard Draw ing T3. Te mporary railing (Type K) s hall be set o n firm, stab le foundation. The f oundation s hall be graded t o provide a uniform bearing throughout the entire length of the railing. Abutting ends of precast concrete units shall be pla ced and maintained in a lignment without substantial offset to each other. The precast concrete units shall be positioned straight on tangent alignment and on a true arc on cur ved alignment. Each rail unit placed within 3 m (10’) of a traffi c lane s hall hav e a reflector installed on top of the rail as directed by the Engineer. Reflectors and adhesive will be furnished b y the Co ntractor. A Ty pe P mark er panel conforming to the re quirements of t he Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2009 Edition as amended by the MUTCD 2009 California Supplement shall also be installed at each en d o f rai ling i nstalled adjacent to a two -lane, two -way highway and at t he e nd fac ing traffic of r ailing installed a djacent to a one-way roadbed. If the rail ing is placed on a skew, the
Revised 6/15/17 Contract No. 3840-23 Page 133 of 134
marker shall be installed at the end of the skew nearest the traveled way. Type P marker panels shall conform to the provisions of Section 206-7.2, “Temporary Traffic Signs”. Where shown on the plans, threaded rods or dowels shall be bonded in h oles drilled in existing concrete. When temporary railings (Type K) are removed, any area where temporary excavation or embankment was used to accommodate the temporary railing shall be restored to its previous condition or constructed to its planned condition.
601-3.6.5.5 Temporary S and-Filled C rash Cu shions. Temporary sand-filled crash cushion units shall be selected from the latest Caltrans Authorized Material List fo r highway safety features and shall meet NCHRP 350 standards. Other features will be suitability to application, operational charact eristics, durabil ity a nd othe r such cha racteristics t hat th e E ngineer shall determine. T emporary sand -filled cra sh cushions (TSFCC) sh all be of the type and array configurations shown on plans , and installed at every end of, or gap in, the temporary railing (Type K) whenever the closest point of approach of traffic, regardless of direction, is 4.6 m (15’) or le ss to the end of the tempor ary railing (Type K) b eing consider ed. The TSFCC shall be installed per Calt rans St andard Draw ings T1 and T 2 for approach speeds no less th an the posted speed of the street prior to construction or 55 kilometers per hour (35 mph), whichever is the greater. The TSFCC array shall be appropriate to the application as shown on said standard drawings. A Type J and/or P marker pane l co nforming to t he re quirements of the Federal Highway Adm inistration (FHWA) Manual on Uniform Traffic Con trol Devices (MUT CD) 2009 Edition as amended by t he MUTCD 2009 California Supplement shall also be installed at each TSFCC array as shown in Caltrans Standard Drawings T1 and T2. Particular care shall be taken to assure that crash cushio ns are installed with the soil suppo rting them and the adjacent soil leveled to match the elevation of the bottom of the temporary railing immediately adjacent to the crash cushion. All routes of approach to the TSCFF array shall be graded such that any vehicle diverging from the travelled way to strike the TSCFF will travel on a vertical alignment parallel to the segment of the travel lane that it departed from.
601-3.7.5 PORTABLE CHANGEABLE MESSAGE SIGNS (PCMS)
Add the following:
601-3.7.5.1 General. Each portable changeable message sign (PCMS) unit shall consist of a controller unit, a power supply, an d a structural support system all mounted on a trailer. The PCMS unit shall be assembled to form a complete self-contained portable changeable message sign, which ca n be delivered to t he sit e of the w ork an d placed in imme diate operat ion. The complete PCMS unit shall be capable of operating in an ambient air temperature range of -20ºC (-4ºF) to +70ºC (158ºF) and shall not be affected by unauthorized mobile radio transmissions.
The trailer shall be equipped so that it can be leveled an d plumbed. Full operation height shall be with the bottom of the sign at least 2.1 m (7') above the ground and the top no more than 4.4 m (1 4.5') a bove the g round. After i nitial placement, PCM S s hall be mov ed fro m location to location as directed by the Engineer.
601-3.7.5.2 Mess age Bo ard. The mes sage di splayed on the P CMS shal l be visible f rom a distance of 460 m (1500') and shal l be legible from a distance of 230 m (750'), at noon on a cloudless day, by pe rsons with vision corrected to 20/20. The sign pan el shall be 3-line matrix and shall display not less than 7 characters per line. Sign messages to be displayed shall be as approved by the Engineer. The sign face shall be flat black and shall be protected from glare of the sun by a method which does not interfere with the clarity of the sign message. The sign shall be raised and lowered by means of a power driven lifting mechanism. The matrix sign shall be capable of complete alphanumeric selection.
Revised 6/15/17 Contract No. 3840-23 Page 134 of 134
Lamp m atrix type signs shall be e quipped with an automatic dimming operational m ode th at automatically co mpensates for t he influence of a tempo rary light so urce or ot her abnormal lighting conditions. The sign shall have manual dimming operation modes of 3 or more different lamp intensities.
Matrix signs not utilizing lamps shall be either internally or externally illuminated at night.
The controller shall be an all solid-state unit containing all the necessary circuitry for the storage of at least 5 pre-programmed messages. The controller shall be installed in a location allowing the operator to perfo rm al l functions from one position. A keyboard entry s ystem s hall be provided to allo w an operator to generate an infinite number of additional messages over the pre-programmed sto red me ssages. The k eyboard shall b e equipped with a securi ty lockout feature to prevent unauthorized use of the controller. The controller shall contain a nonvol atile memory to hold the keyboard created messages in memory during periods when the power is not activated. The controller shall provide for a variable message display rate which allows the operator to match the information display to the speed of the app roaching traffic. The flashing off time shall be operator adjustable within the control cabinet.
601-3.7.5.3 Op eration and Maint enance. PCMS shall be fu rnished, p laced, o perated, and maintained at locations shown on the plans, specified herein, or designated by the Engineer.
The PCMS will be diligently maintained and repaired by the Contractor throughout the project in accordance w ith the manufacturer's r ecommendations. When owne rship is tr ansferred to the City (at the end of the job), it must be demonstrated to be in good working condition, and meet the provisions of these specifications, including current registration.
601-3.7.5.4 Measurement and Paymen t. Payment for all traffic signs, in cluding Portable Changeable Message Signs, are incidental to the bid item for Temporary Traffic Control and no other compensation will be made therefor.
601-4 TEMPORARY TRAFFIC STRIPING AND PAVEMENT MARKINGS
601-4.2.1 Application of Temporary Pavement Ma rkers. Temporary reflective raised pavement m arkers shall be plac ed in a ccordance with the manufacturer's instructio ns.
Temporary reflective rais ed pavement markers shall be cement ed to the surfacing with the adhesive recommended by the manufacturer, except epoxy adhesive shall not be used to place temporary reflective raised pavement markers in ar eas where removal of the markers will be required. Pavement striping, legends and markers which conflict with any traffic pattern shall be removed by g rinding as determined by the Engineer. The Contractor sh all u se temp orary reflective raised pavement markers for temporary pave ment ma rking, except when the temporary pavement markers are used to replace patterns of temporary traffic stripe that will be in place for less than 30 days. Reflective pavement markers used in place of t he removable- type pavement markers shall conform to the Section 314-3 Removal of Pavement Markers and Section 31 4-5 Pavement Markers, except the 14 -day w aiting p eriod before placing the pavement markers o n new asphalt concrete sur facing as s pecified in Sec tion 31 4-5.4 Placement, shall not apply; and epoxy adhesive shall not be used to place pavement markers in areas where removal of the markers will be required.
Technical Specifications
CITY OF CARLSBAD
POINSETTIA LIFT STATION
GENERATOR REPLACEMENT
PROJECT NO. 3840-23
TECHNICAL SPECIFICATIONS
The Technical Specifications were prepared under the direction of Professional Engineers, registered in the State of California, whose seals and signatures appear below.
PROJECT MANAGER LEAD CIVIL
Signed: 11/22/2023
Signed: 11/22/2023
LEAD STRUCTURAL LEAD MECHANICAL
Signed: 11/22/2023
Signed: 11/22/2023
LEAD ELECTRICAL
Signed: 11/22/2023
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
TC - 1 Table of Contents
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01190 Structural Design Requirements
01650 Facility Commissioning, Testing, and Startup
01700 Contract Closeout
DIVISION 2 - SITE WORK
02050 Demolition
02300 Earthwork
02516 Disinfection
02700 Paving and Surfacing
DIVISION 10 - SPECIALTIES
10200 Louvers
10400 Identifying Devices
DIVISION 15 - MECHANICAL
15050 Piping, Valves, and Accessories
15800 Heating, Ventilating, and Air Conditioning Ai r Distribution
DIVISION 16 - ELECTRICAL
16010 General Electrical Requirements
16110 Electrical Raceway Systems
16120 Low Voltage Wire and Cable
16124 Signal Cable
16205 Standby Diesel Engine-Generator Sets
16250 Automatic and Manual Transfer Switches
16402 Underground Electrical Work
16450 Electrical Grounding
16950 Electrical Tests
16961 Power System Studies
END OF TABLE OF CONTENTS
TABLE OF CONTENTS
(Continued)
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
TC - 2 Table of Contents
THIS PAGE INTENTIONALLY BLANK
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 1 Structural Design Requirements
SECTION 01190
STRUCTURAL DESIGN REQUIREMENTS
PART 1 - GENERAL
1.01 SUMMARY
A. This Section is applicable for nonstructural com ponents, nonbuilding structures, and structural elements of the project that are intended to be designed by others as a deferred submittal including, but not limited to:
1. Mechanical, Electrical, and Plumbing equipment a nd appurtenances including but not limited to:
a. Electrical Equipment: Generator and Fuel Tank, i ncluding the design of the anchorage.
b. Unless otherwise shown: All conduit, piping, cab le trays, raceways, HVAC ducts and similar systems, if applicable. Including the anchorage to the structural support.
1.02 REFERENCES
A. 2022 CBC California Building Code (CBC), CCR Ti tle 24, Part 2, Volume 2, based on the 2021 International Building Code, C alifornia Building Standards Commission, 2022.
B. ACI 318-19 Building Code Requirements for Reinfo rced Concrete and Commentary, American Concrete Institute, 2019.
C. ACI 355.2 Qualification of Post-Installed Mechan ical Anchors in Concrete and Commentary, American Concrete Institute, 201 9.
D. ACI 355.4 Qualification of Post-Installed Adhesi ve Anchors in Concrete and Commentary, American Concrete Institute.
E. AC01 Acceptance Criteria (AC) for Expansion Anc hors in Masonry Elements, International Code Council Evaluation Service.
F. AC58 Acceptance Criteria for Adhesive Anchors i n Cracked and Uncracked Masonry Elements, International Code C ouncil Evaluation Service, 2019
G. AC156 Acceptance Criteria for Seismic Certifica tion by Shake-Table Testing of Nonstructural Components, Internation al Code Council Evaluation Service.
H. ASHRAE American Society of Heating, Refrigeratio n, and Air-Conditioning Engineers, Inc., Practical Guide to Seismic Rest raint, 2 nd Edition,
2012.
I. ASCE 7-16 Minimum Design Loads and Associated Cr iteria for Buildings and Other Structures, American Society of Civil Engi neers (ASCE/SEI 7-16)
J. SMACNA Sheet Metal and Air Conditioning Contract ors National Association, Latest Edition.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 2 Structural Design Requirements
1.03 DEFINITIONS
A. Deferred Submittal: Portions of the design that have yet to be completed at the time of submittal of the Contract Documents. Deferred submittal items shall not be constructed or installed until the deferred submittal documents have been reviewed for general conformance by the Engineer of Record.
B. Specialty Engineer: Professional Civil Engineer or Structural Engineer licensed in the State where the project is being constructed, is responsible for nonstructural components, nonbuilding structures, and/or equipment supported by structures as identified in the Contract Documents as a deferred submittal. The Specialty Engineer shall be provided by the Contractor.
1.04 SUBMITTALS
A. Complete calculations, details, and complete ref erence drawings that are required to be submitted as part of a deferred submittal and as defined in the CBC and the Structural Drawings, shall be prepared, stamped, signed, and furnished by a Professional Civil or Structural Engineer licensed to practice in the State of California.
B. Minimum Calculation and Reference Drawing Requir ements:
1. Calculations shall be comprehensible and complet e. When evaluating the structural strengths, indicate stress for comparing with strengths or show the demand versus capacity ratio in the structural elements. Evaluating the results by stating “Okay by Inspection” is not acceptable.
2. Derivation of forces used, including at least one complete sample calculation, showing the process used so that Engineer of Record may determine general conformance. Printouts of spreadsheets without explanation of calculations used to determine values are not acceptable.
3. The calculations and details shall demonstrate a complete vertical and lateral load path and shall clearly indicate all forces imposed on the supporting structure. Include all load combinations used in the design shall be referenced and include a clear indication whether service level or strength level was used in the design.
4. Reference drawings shall include plans, sections , details, and equipment information as necessary for calculations. Indicate the location of the equipment on plan which is necessary for the development of load calculations.
5. The Engineer of Record's review of the deferred submittal items identified in Contract Documents cannot be completed until all related items have been coordinated and submitted for review. Submittals will be returned without review if:
a. Submittals include only calculations without ref erence drawings. b. Calculations have no sheet numbers or sheets are missing. c. Calculations or reference drawings are illegible .
d. Calculations are made based on wrong information , assumptions, or design parameters.
e. Information in reference drawings is insufficien t for calculations or review.
C. Anchorage Calculations and Details:
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 3 Structural Design Requirements
1. Anchorage calculations and details shall be prov ided for all nonstructural components and nonbuilding structures required as part of the deferred submittal items. Anchorage calculations and details shall be sealed and signed by a Professional Civil or Structural Engineer licensed to practice in the State of California.
2. Submit anchorage calculations for nonstructural components and nonbuilding structures to resist dynamic operational, wind, and seismic forces in both concrete as required for the point of attachment relative to the Contract Documents.
3. Reduction factors associated with edge distance, embedment length, grout and base plate thickness, and bolt spacing shall be considered in the design and clearly indicated on the submittal drawings.
4. Anchorage details shall include the required con crete strength consistent with the Contract Documents, anchor bolt diameter, embed, spacing, and edge distances consistent with the calculations.
5. Include anchoring methods and leveling criteria for equipment consistent with manufacturer’s recommendations.
6. Final dimensions of equipment pads based on equipment size and edge distance required for anchorage. The Contractor shall coordinate the final dimensions of equipment pads, including any revisions required to meet the requirements of the favorably reviewed submittal by the Specialty Engineer at no additional cost to the Owner.
D. Shop Drawings:
1. Contractor is responsible for coordinating the f inal foundation sizes with the final size of equipment and final anchorage calculations, including the coordination required for shop drawings relating to foundations or structures supported by nonbuilding structures and nonstructural components.
2. Shop drawings that require anchor reinforcement or supplementary reinforcement by the Specialty Engineer shall be included in the shop drawing submittals.
3. Shop drawings shall be submitted in accordance w ith the Contract Documents for items specified within their respective Specification Section.
E. Seismic Certification of Equipment: Submit seism ic certifications for equipment identified in the Contract Documents, that state the equipment itself is designed to resist all internal seismic forces based on the seismic design criteria for the project.
Submit Level 1 or Level 2 certification as noted in the equipment specifications or Contract Documents. If no level is indicated, provide Level 1 certification.
1. Level 1 Certification shall consist of a written certification from the manufacturer that the equipment is capable of resisting the internal seismic loads due to the loading conditions noted herein and meeting the requirements of ASCE 7, Chapter 13.
2. Level 2 Certification shall consist of a written certification from the manufacturer, and accompanying test results or experiential evidence, indicating compliance with ASCE 7, Chapter 13.
3. For elements designed in accordance with ASCE 7, Chapter 15, Contractor shall submit complete calculations in accordance with this Section for the nonbuilding structure in lieu of seismic certification unless specifically identified in the Contract Documents.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 4 Structural Design Requirements
F. Quality Assurance Submittals
1. Evaluation Reports: Submit the current and relat ive ICC-ESR or IAPMO-UES reports used in the design of anchorage and other structural elements.
2. Seismic Certification: Submit seismic certificat ion for equipment as identified in the Contract Documents.
3. Verification of Installation: Submit a letter f rom the Contractor’s Specialty Engineer verifying that the installation was performed as required by the Specialty Engineer’s calculations. The Contractor shall be qualified to install post-installed anchors.
4. Test Reports: Submit test reports for testing of anchors in accordance with the Contract Documents.
1.05 QUALITY ASSURANCE
A. Qualifications: The Contractor is responsible fo r submitting sealed and signed structural calculations and detailed drawings from a Specialty Engineer, licensed as Professional Civil or Structural Engineer in the State where the project is being constructed
B. Regulatory Requirements: Comply with the CBC, AS CE 7, applicable reference documents, and Contract Documents.
C. Special Inspection: Special Inspections and test ing shall be performed as referenced in the Contract Documents.
1.06 GENERAL DESIGN REQUIREMENTS
A. Design Basis and Coordination: Contractor shall note that the layout of the structures and equipment pads shown on the Drawings have been developed based on the limits in the Contract Documents .
1. Contractor shall coordinate all attachments and related work and shall provide connections as noted in the favorably reviewed shop drawings.
2. For all suppliers, if the dimensions required by the Contractor’s submitted anchorage calculations deviate from those provided in the Contract Documents, Contractor shall note the deviation in the submittal for review and provide the favorably reviewed pad at no additional cost to the Owner.
3. Contractor shall coordinate all related work and deviations from the Contract Documents.
B. The Contractor is responsible for producing desi gns that resist dynamic operational, wind, seismic forces in accordance with the Contract Documents. The Contractor is responsible for coordinating between the Engineer of Record and the Specialty Engineer.
C. Coordinate the layout so that adequate space is provided between items for relative motion. Provide additional supports and restraints between items of different systems when necessary to prevent lateral impacts or interaction.
D. Structural Design Criteria: For the design of de ferred submittal items, nonstructural components and nonbuilding structures, the Specialty Engineer shall follow the structural design parameters listed on the Structural Drawings Sheet S1: floor live loads, roof live loads, snow and rain load data, wind design data, seismic design data, earth forces, geotechnical information, and flood design data (if applicable).
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 5 Structural Design Requirements
E. The total operating weight of the equipment for nonstructural components and nonbuilding structure shall be considered in the development of the seismic design forces.
F. Nonstructural components, nonbuilding structures , and structural elements shall be designed for a concurrent vertical acceleration force. Where required by ASCE 7, the effects of vertical ground motions for nonbuilding structures shall be used in lieu of the vertical acceleration force.
G. Orthogonal Effects: Nonstructural components and nonbuilding structures shall be designed for orthogonal effects as required in the CBC and ASCE 7.
H. Nonstructural Components:
1. The seismic design for nonstructural components and anchorage shall be in accordance with Chapter 13 of ASCE 7, and the required coefficients and factors for determining the total design seismic forces shall be shown on the deferred submittal drawings.
a. Component Importance Factor, I
P: per Structural Drawings.
b. Component Amplification Factor, a p: per ASCE 7, Chapter 13 c. Component Response Modification Factor, R p: per ASCE 7, Chapter 13 d. Overstrength Factor, Ω O: per ASCE 7, Chapter 13
2. Nonstructural components contained inside modula r systems shall be designed in accordance with ASCE 7, Chapter 13.
I. Nonbuilding Structures:
1. The seismic design for nonbuilding structures an d anchorage shall be in accordance with Chapter 15 of ASCE 7. The required coefficients and factors for determining the total seismic forces shall be shown on the deferred submittal drawings.
a. Seismic Importance Factor, I
E: per Structural Drawings.
b. Response Modification Factor, R: per ASCE 7, Cha pter 15 c. Overstrength Factor, Ω O: per ASCE 7, Chapter 15
d. Deflection Amplification Factor, C d: per ASCE 7, Chapter 15
2. Premanufactured mechanical and electrical module s 6 feet high and taller that are not otherwise prequalified with ASCE 7, Chapter 13 and contain or support mechanical equipment and electrical components shall be designed in accordance with the provisions of ASCE 7, Chapter 15.
J. Nonstructural components and nonbuilding structu res, that are located outside, shall be designed for the condition in which the component or structure is empty, subjecting the component or structure to wind forces while not in operation. This includes the anchorage of nonstructural and nonbuilding structures.
1.07 ANCHORAGE
A. Anchorage of nonstructural components and nonbui lding structures shall be designed to resist static, dynamic operational, seismic, and wind forces.
B. Anchorage calculations in both concrete shall cl early show that the capacity of the anchor and the capacity of the concrete that the anchor is attached to are adequate to resist all applicable load combinations in the CBC and ASCE 7.
1. The design of anchors resisting seismic forces s hall satisfy the ductility requirements stated in the CBC, ASCE 7, and ACI 318.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 6 Structural Design Requirements
2. Post-installed anchors installed in concrete sha ll be prequalified for seismic applications in accordance with ACI 355.2 and ACI 355.4.
C. Anchorage shall be designed for dynamic operatio nal forces and operating torque, if applicable, for vertical turbine pumps / vibratory equipment.
D. Anchorage shall be designed for bending in the a nchor due to eccentricity where raised grout pads will be installed for leveling.
E. Anchor reinforcement or supplementary reinforcem ent deemed necessary to satisfy the anchorage design by the Specialty Engineer, shall be included at no additional cost to the Owner. Contractor is responsible for coordinating any anchor reinforcement or supplementary reinforcement with the shop drawings prior to fabrication. Anchor reinforcement or supplementary reinforcement shall be detailed in accordance with ACI 318-19.
1.08 ELECTRICAL EQUIPMENT FOUNDATIONS AND PADS
A. Electrical equipment foundations and housekeepin g pads shall be coordinated with the Contract Documents and the anchorage requirements determined from the Specialty Engineer. The final dimensions of electrical equipment foundations and housekeeping pads shall not violate the applicable code provisions for the specified equipment, including but not limited to the provisions of the National Electric Code.
B. Electrical equipment housekeeping pads shall be 3.5 inches tall at the front of the equipment, unless otherwise specified within the Contract Documents. Contractor shall coordinate the final elevations with electrical.
C. Contractor shall verify the size and operating w eight of the equipment with the Contract Documents and equipment manufacturer. Notify the Engineer of Record of any discrepancies between the equipment submittal and the Contract Documents prior to construction of the foundations.
1.09 MECHANICAL EQUIPMENT FOUNDATIONS
A. Mechanical equipment foundations and pads shall be coordinated with process equipment and piping elevations.
B. Contractor shall verify the size and operating w eight of the equipment with the Contract Documents and equipment manufacturer. Notify the Engineer of Record of any discrepancies between the equipment submittal and the Contract Documents prior to construction of the foundations.
1.10 DESIGN REQUIREMENTS FOR PIPING, CONDUITS, AND DUCTWORK A. The Contractor is responsible for producing desi gns for support of piping, conduit, duct or other systems to resist total seismic forces based on the seismic design criteria coefficients specified above, unless shown on the Contract Documents.
Except where the technical specifications give specific exemption from resistance of seismic forces, all supports shall be designed to meet seismic criteria. Support systems for piping, conduit, duct or other systems greater than 5 inches in diameter are shown on the Contract Documents.
B. Where possible, pipes, conduit, and their connec tions shall be constructed of ductile materials (e.g., copper, stainless, steel, brass, ductile iron, steel, or Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 7 Structural Design Requirements
aluminum and brazed, welded, or screwed connections). Pipes, conduits, and their connections, constructed of non-ductile materials (e.g., cast iron, no-hub pipe and plastic), shall have the brace spacing reduced to one-half of the spacing allowed for ductile material.
C. Seismic restraints may be omitted for the follow ing conditions, where flexible connections are provided between components and the associated ductwork, piping and conduit:
1. All non-fuel piping less than 2.5 inches inside diameter or all piping suspended by individual hangers 12 inches or less in length from the top of the pipe to the bottom of the structural support for the hanger or electrical conduit less than 2.5 inches trade size.
D. All trapeze assemblies supporting pipes, ducts a nd conduit shall be braced to resist the total seismic forces considering the weight of the elements on the trapeze. Pipes, ducts, and conduit supported by a trapeze where none of those elements would individually be braced need not be braced if connections to the pipe/conduit/ductwork or directional changes do not restrict the movement of the trapeze. If this flexibility is not provided, bracing will be required when the aggregate weight of the pipes and conduit exceed 10 pounds/foot. The weight shall be determined assuming all pipes and conduit are filled with water.
E. As an alternative to designing the supports and anchorage, where an approved national standard provides a basis for the earthquake-resistant design, submit standard, data, and details for piping, conduit, duct, or other systems consistent with the code requirements referenced in the Contract Documents.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 FIELD QUALITY CONTROL
A. Special Inspections and tests of elements, nonst ructural, and nonbuilding structures shall meet the requirements of the Contract Documents and applicable Codes. The owner shall retain a qualified Special Inspector (other than the Contractor), who shall provide all special inspections and testing necessary to meet the Contract Documents and Code requirements during Construction.
Special inspections are in addition to inspections performed by the Authority Having Jurisdiction.
B. Post-Installed Anchors: For post-installed ancho rs in concrete, proof load tests shall be in accordance with the relative and current ICC-ESR / IAPMO-UES report, unless indicated otherwise in the Contract Documents.
C. All testing of anchors shall be performed in the presence of the Special Inspector.
Reports of the testing of anchors shall be submitted directly to the Engineer of Record.
D. Base Bid Estimate: Unless otherwise noted within the Contract Documents, the following shall serve as the basis for the bid estimate for testing of post-installed anchors and high-strength bolts.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01190 - 8 Structural Design Requirements
1. Post-Installed Anchors: Minimum of 10% proof loa d tension testing or ten percent of the post-installed installed anchors.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01650 - 1 Facility Commissioning, Testing,
and Startup
SECTION 01650
FACILITY COMMISSIONING, TESTING, AND STARTUP
PART 1 - GENERAL
1.01 EQUIPMENT AND FACILITY STARTUP
A. Commission all systems and equipment to verify p erformance, function, and correct operation by performing procedures to activate, startup, adjust, test, and demonstrate that the work is in operating order in accordance with the general requirements of this Section and the detailed requirements of the technical sections under the system or equipment specified. To ensure that the work is ready for full-time operation, the procedures shall include verification, balancing, calibration, witness testing, documentation, inspection by equipment manufacturers and operator training where specified.
B. The Contractor shall designate a Project Startup Coordinator. The Startup Coordinator shall oversee preparation of the Startup Plan, coordinate startup activities, ensure proper testing and sign-offs for various mechanical, electrical and instrumentation and controls checks, and oversee the Facility Startup and Testing requirements. The Startup Coordinator shall have experience in the coordination, startup, and testing of similar capacity water treatment or wastewater treatment facilities.
C. Notification: Notify the City and Engineer five (5) days prior to starting each system or piece of equipment.
D. Coordination: During the startup period, coordin ate the operation of the facility with Engineer, subcontractors, City's operators, and manufacturer's representatives.
Provide regular updates of construction schedule and startup activities to the City's PLC/SCADA Programmer (City's Programmer).
E. Furnish test equipment, measuring devices, and s upplies required to conduct tests.
F. Maintain the equipment until acceptance. Provide all lubricants, chemicals, and electricity necessary until acceptance.
G. Furnish all expendable supplies, gas, diesel fue l, water, etc., required for startup, demonstration, and testing, and dispose of all waste or used supplies, water, etc.
H. Favorably reviewed Operations and Maintenance (O &M) Manuals are required fifteen (15) days before the startup of new equipment/facilities.
1.02 SUBMITTALS
A. Startup Plan, Forms, and Schedule: Prepare a fac ility startup plan and schedule.
The plan shall include test methods and procedures and sample forms for recording commission, test, and startup data.
B. Submit qualifications of proposed Project Startu p Coordinator.
C. Provide Affidavits as described in paragraph 1.0 4 B.
D. Submit documentation of tests, balancing reports , and the like.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01650 - 2 Facility Commissioning, Testing,
and Startup
1.03 INITIAL STARTUP AND OPERATION OF FACILITIES
A. The following listing is a general sequence of s tartup activity steps to be used in placing facility systems into operation:
1. Perform initial lubrication of equipment and hav e manufacturers check and adjust equipment. Provide all subsequent lubrication and maintenance, and such staff as required for test operation until the City assumes equipment maintenance responsibility after Step 15 below.
2. Perform satisfactory testing of electrical work required prior to energizing of the electrical system.
3. After completion of Step 2, perform satisfactory electrical testing required after energizing of the electrical system.
4. Complete calibration of instruments.
5. Satisfactorily complete system verification of i nstrumentation work.
6. After completion of Steps 1 and 3, perform a rot ational test of equipment and correct backward rotating drives.
7. After completion of Steps 5 and 6, test operate the equipment by manually initiating the operation. Where manual operation bypasses alarm or safety monitoring, provide continuous supervision of such parameters. Perform this step using water in lieu of chemicals or other process liquids. Use dry air or nitrogen in lieu of hazardous gases. Following testing with water, chemical lines shall be drained and be fully dried, in accordance with the specifications, prior to introduction of chemical.
8. Concurrent with Step 7, perform instrumentation and control testing and adjustments as related to the equipment being tested.
9. Concurrent with Step 7 and where possible at thi s stage of startup, complete the performance testing specified for the equipment.
10. Concurrent with Step 7, perform adjustments of the electrical work as related to the equipment being tested.
11. Repeat Steps 1 through 10 as required for other equipment items and systems until all process components and utility systems are ready for total operation. It may be necessary for the Contractor to put portions of the newly constructed facility in service before constructing other portions of the facility or completing the Work as a whole.
12. Submit the required documentation of testing, c alibration, and equipment affidavits.
13. Notify the City and the Engineer 21 days before total operation is to occur so that the City may order fuel and make other arrangements for full-time operation. This notification shall have an accuracy of plus or minus seven (7) days. Notify the City and Engineer again, exactly seven (7) days before total operation is to begin.
14. Startup and Initial Operation Test: Upon comple tion of all the above steps, the facility shall be started up and operated on a complete full-time basis beginning on the indicated date. The City will provide operating personnel, chemicals and untreated water. For five (5) consecutive days beginning with the start-up day, the Contractor shall have at the site, during the day shift, a mechanic, an electrician and an instrument engineer. Representatives of manufacturers of critical equipment shall also be present for these five (5) days as needed or as required elsewhere in the Specifications. The Contractor shall also provide these personnel, on a 24 hour per day, "on call" basis, if necessary, to adjust, repair, and correct deficiencies as required to
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01650 - 3 Facility Commissioning, Testing,
and Startup
keep the Poinsettia Lift Station in continuous operation for a period of 30 calendar days. The Contractor shall train the operators in the proper operation and the control of the new facilities. The Contractor shall also furnish all such mechanical and electrical workers as required to make adjustments to and perform all required maintenance for the operating equipment until the end of the 30-day initial operation period. Maintenance of operating equipment shall include lubrication, adjustments, replacements, and modifications as required.
15. After successful completion of the 30-day initi al operation period, the City will take over maintenance duties as well as operation and will begin to provide and pay for lubricants. If continuous process operation of the Poinsettia Lift Station is interrupted due to a failure of the equipment or work provided by the Contractor, then the counting of the 5-day and/or 30-day periods, described in Step 14 above, shall be restarted at day one if these periods have not reached satisfactory completion.
16. Following the commencement of Step 14, satisfac torily complete equipment performance testing, electrical testing and adjustments, and instrumentation/control testing and adjustments to the extent that such testing and adjustments could not be made prior to full operation.
17. Submit any remaining documentation of testing, balancing reports, equipment affidavits, and the like commissioning before acceptance.
1.04 MANUFACTURER'S FIELD SERVICE AND AFFIDAVITS
A. Field Service: Where specified, manufacturers of equipment shall provide field service. Field service shall be provided by an authorized factory-trained and qualified manufacturer's representative for the specific equipment. Equipment shall not be considered ready for full-time operation until after the manufacturer's representative has checked and adjusted the equipment, and certified by written affidavit that the equipment has been properly installed, tested, adjusted, lubricated, and calibrated, and is ready for full-time operation.
B. Affidavits: Acceptable affidavits shall be submi tted prior to completion of the work.
1. Affidavits shall contain the following specific wording:
"The [Name of Equipment] has been properly installed, tested, adjusted, lubricated, and calibrated, and is ready for full-time operation. The installation has been inspected and has been found to be in conformance with our (the manufacturer's) standards and requirements."
2. Except for insertion of the equipment name, no a mplification, dilution, or modification of this specific wording will be permitted.
1.05 TRAINING
A. Submit Operation and Maintenance Manuals and Par ts Lists specified in City General Provisions at least fifteen (15) days prior to the first training session.
B. Demonstrate the operation, maintenance and safet y procedures for all systems and equipment to personnel designated by the City.
C. Provide 4 hours of onsite demonstration of syste ms and equipment in accordance with the General Conditions.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01650 - 4 Facility Commissioning, Testing,
and Startup
D. In addition to overall training specified above, provide special demonstration and training for specific pieces of equipment specified in the Technical Specification Sections.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01700 - 1 Contract Closeout
SECTION 01700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1.01 FINAL CLEANUP
A. Just prior to Final Inspection, the Contractor s hall clean the entire construction area including buildings, other structures, landscaping, and site work included in this Contract as well as all other areas affected by the performance of work under this Contract. Perform cleanup work using personnel specializing in and skilled in building cleaning and maintenance work. Perform cleaning to standards considered normal for commercial janitorial work. Accomplish repair work using personnel specializing in performing and repairing the type of work being repaired.
Perform repair work to the highest trade standards applicable to that type of work.
Include:
1. Remove all temporary construction, signs, tools, equipment, excess materials and debris.
2. Repair, patch or replace new or existing work in cluding pavement, sidewalks, curbs, gutters, catch basins, gratings, manholes, covers, landscaping, plant materials and other items that have been damaged, broken, cracked or chipped as a result of performing this Work.
3. Sweep clean and then wash down all exterior pave ment surfaces. Avoid washing sediment or hazardous material into drainage systems. Remove all grease and oil stains on pavement caused by Contractor's equipment.
4. Rake all landscaped area; remove debris and cut lawns. Water and fertilized landscape materials. Replace damaged plant and landscape materials.
5. Clean all glass without scratching. Scratched gl ass shall be replaced.
6. Remove all lumps, splatters, spots and stains ca used by paint, adhesive, asphalt, concrete, mortar, plaster, sealant or other foreign material from all exposed or finished surfaces. Remove all temporary labels.
7. Patch any holes, chips or defects in constructio n including finished surfaces.
8. Touchup painted surfaces that are soiled, chippe d, spotted or otherwise flawed.
9. Wash all floors with cleaner recommended by floo ring manufacturer. Apply sealer and initial application of floor care product recommended by flooring manufacturer. Buff with power floor machine.
10. Remove all dust with treated dust cloth and vac uum.
11. Polish all hardware and non-ferrous metal.
12. Clean all lighting fixtures.
1.02 CONTRACTOR'S ACTION LIST OF ITEMS TO BE CORREC TED AND/OR
COMPLETED
A. During construction, the Contractor shall mainta in an action list of items to be corrected and/or completed. Regularly add items and update the list as information becomes available or as requested by the Engineer. Deliver a current copy of the list to the Engineer at each progress meeting.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01700 - 2 Contract Closeout
1.03 SEMIFINAL INSPECTION/SUBSTANTIAL COMPLETION
A. When the Contractor considers the Work nearly co mplete, the Contractor shall review the Contract Documents, inspect the Work, and use the Contractor's action list to prepare a Contractor's Punch List of all deficient or uncompleted items.
Complete or correct the items on the Punch List. When the Work is Substantially Complete in accordance with General Conditions, notify the Engineer in writing that the Contractor has reviewed the Contract Documents, inspected the Work and believes that the Work is Substantially Complete and ready for Semifinal Inspection.
B. On receipt of the Contractor's Punch List and no tice that the work is ready for Semifinal Inspection, the Engineer will inspect the Work. The Engineer may add additional items to the Contractor's Punch List, may find that the Work is not ready for inspection, may find that the Work is ready for inspection but not Substantially Complete or may find that the Work is Substantially Complete. When the Engineer finds the Work is Substantially Complete, he/she will prepare a Final Punch List and a notice of Substantial Complete, which will state the date of Substantial Completion and the time agreed to by the City and the Contractor (not to exceed 30 calendar days) in which the Work shall be fully complete and ready for Final Inspection.
1.04 FINAL INSPECTION, FINAL COMPLETION AND FINAL P AYMENT A. When the Contractor has completed or corrected a ll the items on the Engineer's Final Punch List, the Contractor shall give the Engineer written notice that the Work is ready for Final Inspection. When the Engineer finds the Work acceptable and fully complete in accordance with the Contract Documents, and upon receipt of a final Application for Payment and all final submittals, the Engineer will recommend that the City issue a Notice of Final Completion, make Final Payment and Accept the Work stating that to the best of the Engineer's knowledge, information and belief, and on the basis of the Engineer's observations and inspection, the Work has been fully completed in accordance with the terms and conditions of the Contract Documents.
B. Final Submittals include:
1. Operation and Maintenance Manuals and Parts List s
2. Record Drawings
3. Extra Materials
4. Special Guarantees
5. Maintenance Contracts
6. Insurance Certificate showing required continuat ion of coverage beyond Final Payment.
7. Release of Liens.
8. Waiver of Claims by Contractor.
9. And any other submittals required by the Contrac t Documents and not previously received.
C. The City will record the Notice of Final Complet ion at the County Recorders Office.
1.05 RECORD DRAWINGS
A. The Contractor shall maintain on the jobsite, a complete set of Contract Documents and a complete file of all addenda, contract modifications and favorably reviewed submittals. The Contractor shall prepare a set of Record Drawings
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01700 - 3 Contract Closeout
concurrently with the construction of the Work and in accordance with General Conditions and the following:
1. Show the invert elevation of all gravity piping and the top of pipe, top of conduit or top of protective concrete encasement for other utilities. Elevations shall be related to a permanent visible elevation benchmark set at the site by the Contractor.
2. Show the horizontal location of underground util ities measured from permanent visible physical features such as face of building, face of tank, or centerline of manhole.
3. Comply with detailed requirements in technical s pecification sections describing the type of information required on Record Drawings. The Contractor's copy of Contract Documents, Contract modifications and Record Drawings shall be available to the Engineer for weekly verification that the records are being currently updated.
B. Submit Record Drawings and obtain acceptance pri or to completion.
1.06 EXTRA MATERIALS
A. Deliver specified extra materials and parts to C ity. Itemize all items on a transmittal letter in duplicate and obtain signature of receiving party. Submit copies of signed transmittals for all specified extra materials and parts prior to completion.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
01700 - 4 Contract Closeout
THIS PAGE INTENTIONALLY BLANK
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 1 Demolition
SECTION 02050
DEMOLITION
PART 1 - GENERAL
1.01 DESCRIPTION
A. Provide all demolition required to perform the w ork covered under this contract including without limitation:
1. Remove existing construction shown to be removed .
2. Remove and replace existing construction and/or finishes as required to provide access to perform other work included in this contract.
3. Include removal of mechanical and electrical wor k that is to be abandoned and is contained in construction to be removed whether or not the mechanical and electrical work is shown. Disconnect and cap off utilities in accordance with applicable codes and safety regulations.
4. Where utilities that are not shown pass through construction that must be removed and those utilities serve other areas notify the Engineer before disrupting service. If rerouting is required to maintain service, the City may issue a Change Order to accomplish the required work.
5. Store and protect items intended for reuse.
6. Assume ownership of debris and unwanted material s, remove from the site and dispose of legally.
a. Special requirements for waste management during deconstruction and renovation and construction operations.
1) Protect the environment, both onsite and offsite , during deconstruction and renovation and construction operations. 2) Prevent environmental pollution and damage.
3) Maximize source reduction, reuse, and recycling of solid waste.
7. Include the cost of removing and disposing of ha zardous material including without limitation PCBs.
8. Comply with all State permit requirements for de molition. The Contractor shall perform a pre-demolition survey to determine whether hazardous material is present. If material is identified as hazardous, retain qualified and State- licensed Contractor to remove and dispose of the materials legally.
9. If illegal electrical wiring is encountered such as "BX" or nonmetallic sheathed cable, notify the Engineer.
10. Remove and properly dispose of unwanted fixed e quipment, including without limitation unwanted equipment, machinery, and devices built into or attached to the building. Remove all loose items including rubbish, debris, etc.
1.02 NOISE AND DUST CONTROL
A. Perform work in accordance with requirements in Division 1 Sections 01650 and 01700. Particular attention is directed without limitation to paragraphs titled: City’s Continued Operations, Cleanup During Construction, Fire Protection During Construction, Maintenance of Exit Routes for Building Users, Temporary Dust Barriers, Noise Control and Care of Existing Facilities.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 2 Demolition
B. Provide temporary partitions to control dust and noise and exclude unauthorized persons.
C. Perform work in a manner to cause the least dist urbance to building occupants and the least damage to work to remain.
D. Maintain adequate means of safe, clear egress fo r building occupants.
E. Employ all available techniques for construction noise abatement. Use remote, well-mufflered air compressors and newest noise suppressed pneumatic and electric tools.
1.03 WARNING
A. The Contractor is advised that work under this S ection may be hazardous. The Contractor is to take all necessary precautions to ensure the safety of workers and property. Removal of and/or working in areas containing even minor amounts of hazardous material including without limitation, PCBs or other hazardous materials requires special precautions, knowledge, and procedures. If hazardous material is suspected, notify the City.
1.04 QUALITY ASSURANCE
A. Maximize use of source reduction and recycling p rocedures.
1.05 PRECONSTRUCTION MEETING
A. After award of Contract and prior to the commenc ement of the Work, schedule and conduct meeting with City and Engineer to discuss the proposed Waste Management Plan and to develop mutual understanding relative to details of environmental protection.
1.06 SUBMITTALS
A. Information to be submitted in accordance with C ity General Provisions.
B. Submit copies of all executed permits.
C. Solid Waste Management Plan: Not less than 10 da ys before the Pre-construction meeting, prepare and submit a Solid Waste Management Plan including, but not limited to, the following:
1. List of the recycling facilities, reuse faciliti es, municipal solid waste landfills and other disposal area(s) to be used. Include:
a. Name, location, and phone number.
b. Copy of permit or license for each facility.
2. Identify materials that cannot be recycled or re used. Provide explanation or justification.
3. Revise and resubmit Plan as required by City.
a. Approval of Contractor's Plan will not relieve t he Contractor of responsibility for compliance with applicable environmental regulations.
D. Progress Documentation: Document solid waste dis posal and diversion. Include the quantity by weight of waste generated; waste diverted through sale, reuse, or recycling; and waste disposed by landfill or incineration. Identify landfills, recycling centers, waste processors, and other organizations that process or receive the solid waste.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 3 Demolition
1. Document on form in Appendix A of this Section, or similar form as approved by City.
2. With each Application for Payment, submit update d documentation for solid waste disposal and diversion.
3. With each Application for Payment, submit manife sts, weight tickets, receipts, and invoices specifically identifying the Project and waste material.
E. Record Submittals: With Record Submittals as spe cified in Section City General Provisions, submit the following:
1. Summary of solid waste disposal and diversion. S ubmit on form as approved by City.
1.07 PERMITS
A. Contractor shall fill out, submit and pay for th e following permits:
1. California Department of Public Health:
a. Demolition Notification Application Form (minimu m 10 day lead time) PART 2 - PRODUCTS - NOT USED
PART 3 - EXECUTION
3.01 SOLID WASTE MANAGEMENT
A. Develop and implement a waste management program in accordance with ASTM E1609 and as specified herein.
B. Collection: Implement a recycling/reuse program that includes separate collection of waste materials of the following types as appropriate to the project waste and to the available recycling and reuse programs in the project area:
1. Land clearing debris.
2. Asphalt.
3. Concrete and Masonry.
4. Metal.
a. Ferrous.
b. Non-ferrous.
5. Wood, nails, and staples allowed.
6. Debris.
7. Plastic
a. Type 1: Polyethylene Terephthalate (PET, PETE).
b. Type 2: High Density Polyethylene (HDPE).
c. Type 3: Vinyl (Polyvinyl Chloride or PVC).
d. Type 4: Low Density Polyethylene (LDPE).
e. Type 5: Polypropylene (PP).
f. Type 6: Polystyrene (PS).
g. Type 7: Other. Use of this code indicates the pa ckage in question is made with a resin other than the six listed above, or is made of more than one resin listed above, and used in a multi-layer combination.
8. Flooring.
a. Concrete.
9. Others as appropriate
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 4 Demolition
C. Recycling/Reuse: Maximize recycling and reuse of materials.
1. Recycling/Reuse off project site: The following is a partial list for Contractor's information only. For more information, contact the State Department of Environmental Quality and the local Integrated Solid Waste Management Office.
a. Habitat for Humanity, a non-profit housing organ ization that rehabilitates and builds housing for low-income families. Sites requiring donated materials vary. Contact the national hotline (800) HABITAT. b. California Materials Exchange (CAL-MAX) Program sponsored by the California Integrated Waste Management Board; (916) 255-2369.
D. Handling:
1. Clean materials that are contaminated prior to p lacing in collection containers. Deliver materials in accordance with recycling or reuse facility requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to recycling process).
2. Arrange for collection by or delivery to the app ropriate recycling or reuse facility.
3. Hazardous Waste and Hazardous Materials: Handle in accordance with applicable regulations.
E. Composting: In accordance with State Extension S ervice recommendations and as follows:
1. Moisture content: Maintain between 35 percent an d 60 percent.
2. Carbon to nitrogen (C/N) ratio: Maintain at appr oximately 30 to 1 by weight.
3. Do not compost meat or dairy products on site.
4. Where the proposed Waste Management Plan incorpo rates composting of plastics, assess the potential effect of each type of plastic to be included on the composting process in accordance with ASTM D6002.
3.02 REMOVAL OF CONSTRUCTION IN AREAS TO RECEIVE NE W WORK A. In areas intended to receive new work and/or fin ishes, remove all unwanted non- structural partitions, furred walls, chases, suspended or furred ceilings, doors, and finishes.
B. Remove all unwanted mechanical and electrical wo rk (whether shown or not) that is not wanted and is not needed to serve other areas that is in, on, or concealed behind work being removed. Cap off or terminate all mechanical or electrical work in accordance with the requirements of Divisions 15 and 16.
C. Protect mechanical and electrical work that serv es other areas. Relocate concealed mechanical and electrical work that is required to preserve service to other areas.
D. Remove structural work designated for removal. T ake precautions not to damage structural work intended to remain. Where temporary shoring is needed, submit a design prepared by an appropriately licensed engineer for review before proceeding.
E. If structural elements are encountered that were not shown, protect them from damage and report their presence to the Engineer.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 5 Demolition
3.03 REMOVAL OF LIMITED PORTIONS OF EXISTING CONSTR UCTION TO PERMIT
MODIFICATIONS
A. Provide careful, selective cutting and removal o f existing construction as required to permit relocation or modification of partitions, doors, or openings. Cut and remove the least amount of work possible except when a larger area needs to be removed to permit strengthening existing construction or when required to remove finishes to a natural break line such as a corner or change in material.
B. Protect existing construction to remain with tem porary coverings.
C. Treat existing mechanical, electrical, or struct ural work as described in other parts of this Section.
D. When modifications are complete, replace removed work with new construction and finishes to match adjacent existing work. Standards of material and workmanship shall be in accordance with other portions of this Specification or if not covered then in accordance with current practice for this class of work.
Salvaged materials may be used for replacement if in good condition.
3.04 REMOVAL OF EXISTING CONSTRUCTION TO PROVIDE AC CESS TO PERFORM WORK
A. Provide careful selective cutting and removal of existing construction where required to permit installation of new concealed mechanical or electrical work, or installation of equipment, fixtures or devices.
B. Treat existing mechanical, electrical, or struct ural work as described in other parts of this Section.
C. Replace and/or patch removed construction and fi nishes in accordance with other parts of this Section.
3.05 PROTECTION OF WORK TO REMAIN
A. Protect existing Generator/Chemical Storage Buil ding.
B. Protect all work to remain. Repair damage with m aterials, workmanship, and finishes matching existing work when new.
C. Most existing floor finishes will not be replace d in this contract. It is essential these floors be protected from any damage due to impact, dirt, abrasion, paints, and solvents.
3.06 CUTTING HOLES IN CONCRETE AND/OR CONCRETE MASO NRY UNIT (CMU) A. The Contractor is cautioned that electrical cond uits and reinforcing that are not shown on Drawings may be concealed in concrete CMU construction. Use electronic detection equipment to locate concealed items before cutting holes.
Take all required precautions to avoid damage to existing conduits or reinforcing.
B. New openings in existing concrete walls or slabs may be saw cut to opening perimeter lines where Drawings do not call for adding reinforcing trim bars to strengthen openings. Do not run saw kerfs past corners of openings. Complete concrete removal at opening corners by chipping and grinding. Take all required precautions to avoid water damage to existing construction or the City's property.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02050 - 6 Demolition
C. Where Drawings call for adding reinforcing trim bars to strengthen openings, limit saw cutting to a depth of 3/4 inch to avoid cutting existing reinforcing steel.
Carefully chip out concrete to avoid damaging existing reinforcing steel which is to remain.
D. Use chipping guns to chip out small holes for pi pes or conduits. Proceed carefully to avoid damage to concealed conduits. Core drilling is permitted only at the Contractor's risk and only with the City's permission. If core drilling is used, the Contractor shall: 1) use electronic detection equipment to locate conduit before drilling, 2) take precaution to avoid water damage to existing construction or the City's property, and 3) replace, at its own expense, any damaged electrical or signal wiring or conduits.
3.07 REMOVE UNWANTED FIXED EQUIPMENT
A. Remove unwanted items whether shown or not. Cut off protruding bolts or attachment devices flush with existing surfaces.
B. If items are designated on the Drawings to be sa lvaged, remove them carefully without causing damage.
C. Store and protect items to be reused until time of need on jobsite.
3.08 IF HAZARDOUS MATERIALS ARE ENCOUNTERED
A. If hazardous materials are discovered, comply wi th paragraph 1.01 of this Section and all applicable laws.
3.09 REMOVAL AND DISPOSAL OF MATERIAL
A. Use debris chutes with covered tops emptying int o covered containers.
B. Store debris in suitable covered containers loca ted where directed by the Engineer or City and remove from site when full. Burning on the site is not permitted.
C. Removed material (other than material to be reus ed) shall become the property of the Contractor who shall remove it from the site and dispose of it in a legal manner.
3.10 UTILITY LOCATES AND DEMOLITION
A. There are electrical conduits that may nor may n ot be shown on the Drawings.
Locate, demolish, and restore as required for the construction.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 1 Earthwork
SECTION 02300
EARTHWORK
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Perform all excavation, trenching, shoring, dewa tering, backfilling, compaction, grading and disposal of excess material necessary or required for the construction of the work as covered by these Specifications and indicated on the Drawings. The excavation shall include, without classification, the removal and disposal of all materials of whatever nature encountered, including water and all other obstructions that would interfere with the proper construction and completion of the required work.
1.02 REFERENCES
A. American Association of State Highway and Transp ortation Officials (AASHTO)
1. AASHTO T99 Standard Method of Test for Moisture- Density Relations of Soils
2. AASTO T193 Standard Method of Test for The Calif ornia Bearing Ratio B. ASTM International (ASTM).
1. ASTM C131 - Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in
the Los Angeles Machine
2. ASTM D448 - Standard Classification for Sizes o f Aggregate for Road and Bridge Construction
3. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft- lb/ft3).
4. ASTM D1556 - Standard Test Method for Density o f Soil in Place by the Sand-Cone Method.
5. ASTM D1557 - Standard Test Method for Laborator y Compaction Characteristics of Soil Using Modified Effort (56,000 ft- lb/ft3).
6. ASTM D1883 - Standard Test Method for Californi a Bearing Ratio (CBR) of Laboratory-Compacted Soils
7. ASTM D2167 - Standard Test Method for Density a nd Unit Weight of Soil in Place by the Rubber Balloon Method.
8. ASTM D2419 - Standard Test Method for Sand Equi valent Value of Soils and Fine Aggregate
9. ASTM D2487 - Standard Classification of Soils f or Engineering Purposes (Unified Soil Classification System).
10. ASTM D2844 - Standard Test Method for Resistan ce R-Value and Expansion Pressure of Compacted Soils
11. ASTM D2922 - Standard Test Method for Density of Soil and Soil- Aggregate in Place by Nuclear Methods (Shallow Depth).
12. ASTM D3017 - Standard Test Method for Water Co ntent of Soil and Rock in Place by Nuclear Methods (Shallow Depth).
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 2 Earthwork
13. ASTM 3744 - Standard Test Method for Aggregate Durability Index
14. ASTM D4253 - Standard Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table.
15. ASTM D4254 - Standard Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density.
16. ASTM D4318 - Standard Test Method for Liquid L imit, Plastic Limit, and Plasticity Index of Soils.
17. ASTM D6913 - Standard Test Methods for Particl e-Size Distribution (Gradation) of Soils Using Sieve Analysis
18. ASTM D7928 - Standard Test Method of Particle- Size Distribution (Gradation) of Fine-Grained Soils Using the
Sedimentation (Hydrometer) Analysis
Standards listed below apply when no other more stringent standard is referenced. The order of precedence is as follows:
1. Agency Standards: City of Carlsbad Utilities Dep artment
2. Local Standards
: City of Carlsbad
3. Regional Standards: Greenbook
C. Standard Specifications for Public Works Constru ction (SSPWC), aka "Greenbook".
D. City of Carlsbad Standard Specifications (City S tandard Specifications) E. City of Carlsbad Utilities Department Standard S pecifications (Agency Standard Specifications)
1.03 DEFINITIONS
A. Site: Property owned by City of Carlsbad as show n on the Drawings.
B. Fill: Earth used to fill holes, pits, or depress ions necessary to bring the final grade up to the specified elevation or contours.
C. Pipe Zone: Zone of material that extends from 6 inches below the bottom of pipe to 12 inches above the crown of the pipe.
D. Pipe Bedding: Zone of material that extends from the bottom of the pipe to 6 inches below the pipe.
E. Trench Zone: Zone of material that extends from the top of the pipe zone to the bottom of the pavement subgrade in pavement areas or to the top of the trench in earth areas.
F. Subgrade: Zone of material that is improved to c reate a stable, suitable platform for subsequent layers.
1. Finished Subgrade: Finished subgrade indicates t he top of the subgrade section in a cut scenario.
2. Fill Subgrade: Fill subgrade indicates the top o f the subgrade section in a fill scenario.
G. Over excavation: Excavation beyond the limits sh own in the Drawings.
H. Relative Compaction: In-place dry density divide d by the maximum dry density laboratory compaction expressed as percentage.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 3 Earthwork
1.04 SUBMITTALS
A. Submit in accordance with City General Provision s.
B. Contractor shall not excavate, construct embankm ents, or fill until all the required submittals have been reviewed and approved.
C. Submittals for Informational Purposes:
1. Dewatering Plan: Describe methods for dewatering including power source, size of pumps, appurtenances, settlement monitoring program, and dewatering water disposal. Include any SWPPP and NPDES Permit information relevant to discharge of water from dewatering. Prepare and submit a Dewatering Plan in accordance with SSPWC Section 3-8.2 and 3-12.6.5.
D. Product Data:
1. Potholing Report.
2. Gradation report(s) for bedding material and imp ort backfill materials.
3. Test results on bedding and import material indi cating Sand Equivalent, R- value, Durability Index, Liquid Limit, Plastic Limit and Plasticity Index.
4. Compaction Reports indicating results from QC te sting.
E. Samples and Test Results:
1. Furnish, without additional cost to the City, su ch quantities of Bedding material and Import materials, listed herein, as may be necessary for testing.
2. Test bedding and import materials proposed for u se demonstrating that the materials conform to the specified requirements. Perform tests no more than 60 Calendar Days prior to submission. Submit results to the Engineer at least ten (10) days prior to delivery.
3. Submit certifications for each source of all imp orted/borrow materials indicating the location where the imported/borrow material will be obtained, including the street address, town, lot and block, county and state, and a brief history of the site which is the source of the material. a. City may request a copy of the material delivery ticket at delivery of each load each day.
4. Notify the Engineer a minimum of 48 hours before obtaining samples. The Engineer may choose to be present while samples are obtained.
1.05 QUALITY ASSURANCE / QUALITY CONTROL
A. All material furnished and all work performed sh all be subject to rigid inspection.
No material shall be delivered to the site until it has been favorably reviewed by the Engineer and sample test results provided. All material furnished and all work performed shall be subject to inspection, and no material shall be delivered to the site until it has been favorably reviewed by the Engineer or used in the construction work until it has been inspected in the field/source/quarry by the Engineer should the Engineer/City choose to inspect.
B. Source Quality Control: Furnish all bedding mate rial from a single source throughout the work unless otherwise approved.
C. Field Quality Control:
1. The Contractor shall hire an independent soil te sting laboratory approved by the Engineer to perform the following tasks for flatwork, pipeline installation, non-structural fill or items not requiring special inspection as outlined under Special Inspections:
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 4 Earthwork
a. Perform a Particle-Size Distribution (Gradation) Analysis every 5,000 cubic yards of materials delivered.
b. Test Pipe Zone, Pipe Bedding and Trench Zone mat erial for quality and in-place density requirements specified herein. Contractor shall test every 200 feet of trench.
c. Where Special Inspections are not required, test fill materials to verify conformance with material quality every 5,000 cubic yard of materials delivered.
2. Perform re-work and re-testing for non-compliant Work and demonstrate to the City non-compliant work has been addressed. Contractor shall be responsible for costs of additional inspection, rework, and re-testing resulting from non-compliance.
3. Material that does not meet the gradation, quali ty or compaction requirements shall be removed and replaced with material that does comply at no additional cost to the City.
D. Field Quality Assurance
1. The Engineer will:
a. Review materials, not covered under Special Insp ections. b. Observe excavation, not covered under Special In spections, and advise the Contractor should excavation beyond the limits shown in the Drawings be required.
c. Review results of the Contractor’s independent t esting laboratory tests and request additional testing at the Engineer’s discretion.
2. At the City’s discretion, Quality Assurance (QA) testing may be conducted by the Engineer, or a separate independent testing laboratory acceptable to the Engineer, to verify results obtained by the Contractor’s QC third party independent testing laboratory. The Contractor shall provide adequate clearance of areas for testing as recommended by the Engineer. QA testing will be paid for by the City. Areas where QA testing indicates results that do not meet the project specification requirements, shall be recompacted by the Contractor at no additional costs to the City and shall be retested by the Contractor’s QC testing laboratory to verify test results meet project specification requirements.
E. Special Inspections:
1. The City will be responsible for special inspect ions in accordance with the building code CBC Chapter 17 Section 1705.6 and the Drawings. Special inspection is required for work related to constructing buildings, structures, structural work, and roadways, and includes but is not limited to:
a. Verifying materials below foundations are adequa te to achieve the design bearing capacity requirements.
b. Verifying excavations are to the depth identifie d in the Contract Documents and the bottom of excavations are suitable materials. c. Perform classification and testing of compacted fill materials. d. Verifying materials meet quality, lift thickness and in-place density requirements specified herein.
e. Prior to placement of compacted fill, inspect su bgrade and verify the site has been prepared properly.
2. Testing will be performed at the frequency provi ded or as otherwise established by the City prior to Construction:
a. Engineered Fill: Test every 500 square feet for each 2 feet of fill.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 5 Earthwork
b. Subgrade: Test every 200 square feet where in-pl ace materials have been disturbed and recompacted or as recommended by the Engineer. c. Structural Backfill:
a) Test every 200 square feet of building footprint , with no less than two tests per structure.
b) Test every 200 cubic yards of material placed wi thin 10 feet around the building.
d. Aggregate Base: Test every 500 square feet of ea ch layer.
F. Testing Methods:
1. R-Value: California Test 301 or ASTM D2844
2. Durability Index: California Test 229 OR ASTM 3 744.
3. Aggregate Gradation: California Test 202 OR AST M
D6913 and D7928
4. Sand Equivalent: California Test 217 OR ASTM 24 19
5. Specific Gravity: ASTM D854
6. Laboratory Compaction: ASTM D1557, Method A or C
(Modified Proctor) or
ASTM D698 (Standard Proctor)
7. In-place Density: ASTM D1556 or ASTM D6938
1 8. Plastic Limit and Plasticity Index: ASTM D4318.
9. Soil Classification: ASTM D2487.
1If nuclear methods are used for in-place density testing, verify the accuracy with one sand cone test and one maximum laboratory dry density test for every five (5) nuclear tests.
1.06 DELIVERY, STORAGE AND HANDLING
A. Earthwork materials shall be stored in a locatio n confirmed in writing by the City/Engineer or as indicated on the Drawings.
B. Stockpile material so that it’s not contaminated , does not cause damage, does not become saturated and is identifiable.
C. Storage of Excavated Materials:
1. Neatly place excavated materials far enough from the excavation to prevent stability problems. Keep the materials shaped to cause the least possible interference with plant operations and drainage.
2. Excavated materials unsuitable for backfill shal l be disposed of immediately.
1.07 SUBSURFACE INVESTIGATIONS
A. While the records of data obtained may be consid ered by the Contractor to be correct, any conclusions or recommendations made in the reports are for information to the Design Engineer and are not a part of the Contract Documents.
B. The bidders may make additional subsurface inves tigations at the site prior to the bidding of the project at their cost. Prior to making any drillings or excavations, the bidder shall secure permission from the City.
1.08 ADDITIONAL SAFETY RESPONSIBILITIES
A. The Contractor shall select, install, and mainta in shoring, sheeting, bracing, and sloping as necessary to maintain safe excavations. The Contractor shall be
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 6 Earthwork
responsible for ensuring such measures: (1) comply fully with 29 CFR Part 1926 OSHA Subpart P Excavations and Trenches requirements, (2) provide necessary support to the sides of excavations, (3) provide safe access to the Engineer's sampling and testing within the excavation, (4) provide safe access for backfill, compaction, and compaction testing, and (5) otherwise maintain excavations in a safe manner that shall not endanger property, life, health, or the project schedule.
All earthwork shall be performed in strict accordance with applicable law, including local ordinances, applicable OSHA, Cal OSHA, California Civil Code, and California Department of Industrial Safety, Federal Register, 29 CFR, Part 1926, Subpart P; Occupational Safety and Health Standards-Excavations, requirements.
1.09 EXPLOSIVES
A. Do not use explosives unless specifically author ized, in writing, by the Engineer.
PART 2 - PRODUCTS
2.01 MATERIAL DEFINITIONS
A. Engineered Fill: Engineered fill may be Imported Soil or Native Soil that has been processed to meet the below requirements.
1. Native Soil: It shall not contain rocks or lumps larger than 3 inches in greatest dimension or more than 15 percent of the material larger than 1 ½ inches and be free of organics, debris, and other deleterious materials. Wet, soft, or frozen material, organic matter, asphalt chunks, or other deleterious substances shall not be used as backfill. Engineered Fill shall contain at least 20 percent passing the No. 200 sieve and have a low expansion potential as indicated by a Plasticity Index of 15 or less, or Expansion Index of less than
20. Native soil shall have organic material less than 3 percent by weight.
2. Imported Soil: Imported non-expansive soil with liquid limit no greater than 40 percent and a plasticity index no greater than 15 percent, free from clods or rocks larger than 2 inches in greatest dimension. Representative soil samples of proposed import fills shall be approved by the Geotechnical Engineer prior to delivery.
B. Pipe Zone Backfill:
1. Sand: Sand shall conform to the requirements of SSPWC Section 217-1.
C. Trench Zone Backfill:
1. Trench Zone Backfill may be sand, native soil or imported soil meeting the above requirements. When a trench is placed in pavement, the upper 12 inches of trench backfill shall be acceptable native soil.
D. Pipe Bedding Material:
1. Sand: Sand shall conform to the requirements of SSPWC Section 217-1.
2. Excavated native soil, meeting the above require ments, is not suitable to be used as pipe bedding material.
E. Aggregate Base:
1. Refer to Section 02700.
F. Structural Backfill:
1. Structural Backfill shall conform to the require ments of SSPWC Section 217-3, unless specifically indicated on Drawing Sheet S-1.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 7 Earthwork
G. Gravel:
1. Gravel shall conform to the requirements of SSPW C Sections 201-1.2 and 200-1.3.
H. Water: The water used shall be reasonably free o f objectionable quantities of silt, oil, organic matter, alkali, salts, and other impurities. Water quality must be acceptable to the Engineer.
I. Warning Tape: 3-inch-wide, inert, fade-resistant plastic film resistant to acids, alkalis, and other components likely to be encountered in soil. Warning Tape colors shall follow the uniform color code per American Public Works Association (APWA) and shall not be placed more than 12 inches above top of pipe.
1. Provide: Terra Tape® Standard; T. Christy Enterp rises, Inc. T A.ND.3- COLOR-CODE; or equal.
2. Acceptable Manufacturers: Reef Industries, Inc. ; T. Christy Enterprises, Inc.; or equal.
3. Color code per American Public Works Association (APWA).
PART 3 - EXECUTION
3.01 GENERAL CONSTRUCTION REQUIREMENTS
A. Barriers: Barriers shall be placed at each end o f all excavations and at such places along excavations as may be necessary to warn all pedestrian and vehicular traffic of such excavations.
B. Access: Free access must be maintained to all fi re hydrants, water valves and meters, and private driveways.
3.02 CONTROL OF WATER
A. Prepare and submit a Dewatering Plan in accordan ce with Paragraph 1.04.C.
1. It shall be presumed that the presence of ground water will require dewatering operations. Dewatering Systems shall be designed to:
a. Prevent loss of ground as water is removed.
b. Avoid inducing settlement or damage to existing facilities or completed work.
c. Relieve artesian pressures and resultant uplift of excavation bottom.
B. All excavations shall be kept free from water an d all construction shall be in the dry.
1. Furnish, install, maintain, and operate all nece ssary pumping and other equipment for dewatering excavations.
2. Provide a sufficient number of pumps, including standby pumps, for use in case other pumps become inoperable, as to hold the groundwater level at an elevation of not less than 1 foot below the lowest elevation of the pipe, duct structure or other material or feature to be placed.
3. The dewatering operation shall be continuous, so that the excavated areas shall be kept free from water while concrete is setting and achieves full strength, and until backfill has been placed to a sufficient height to anchor the work against possible flotation.
4. Continue dewatering during backfill operations.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 8 Earthwork
5. If the subgrade becomes unsuitable due to failur e of dewatering operations, Contractor shall notify and coordinate with the Engineer as soon as failure is identified. The Engineer shall recommend remedial measures, if deemed necessary in the opinion of the Engineer, based on site conditions, proposed design elements for the area and observations made in the field at the time.
6. If pumping is required on a 24-hour basis, requi ring engine drives, then engines shall be equipped in a manner to keep noise to a minimum. Refer to City General Provisions for noise control requirements.
7. Protect the Work against floatation.
C. The Contractor shall be responsible for any dama ge to the Work or existing foundations and structures caused by dewatering operations. Contractor shall repair damage and/or settlement at the Contractor’s expense and to the City’s satisfaction.
D. During rain events, the Contractor shall take ne cessary precautions to ensure safety of staff and the Work. Divert stormwater runoff away from the excavation.
Direct precipitation within the excavation to a sump and pump it out.
E. The Contractor shall discharge dewatered water i n accordance with City General Provisions.
1. It is the Contractor's responsibility to obtain all necessary Storm Water Discharge Permits.
3.03 EXISTING UTILITIES
A. General: The known existing buried utilities and pipelines are shown on the Drawings in their approximate location. The Contractor shall exercise care in avoiding damage to all utilities as he will be held responsible for their repair if damaged. There is no guarantee that all utilities or obstructions are shown, or that locations indicated are accurate. Utilities are piping, conduits, wire, cable, ducts, manholes, pull boxes, and the like, located at the project site.
B. Potholing:
1. Contact all affected utility owners and request them to locate their respective utilities prior to the start of "potholing" procedures. The utility owner shall be given 7 days written notice prior to commencing potholing. If a utility owner is not equipped to locate its utility, the Contractor shall locate it.
2. Clearly paint the location of all affected utili ty underground pipes, conduits, and other utilities on the pavement or identify the location with suitable markers if not on pavement. In addition to the location of metallic pipes and conduits, non-metallic pipe, ducts, and conduits shall also be similarly located using surface indicators and detection tape if present and shall then be similarly marked.
3. After the utility survey is completed, commence "potholing" to determine the actual location and elevation of all utilities where crossings, interferences, or connections to new pipelines or other facilities are shown on the Drawings, marked by the utility companies, or indicated by surface signs. Prior to the preparation of piping shop drawings, or the excavating for any new pipelines or structures, the Contractor shall locate and uncover these existing utilities including services and laterals to a point 1 foot below the utility. Submit a report identifying each underground utility and its depth and location. Any variation in the actual elevations and the indicated elevations shall be brought to the Engineer's attention.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 9 Earthwork
4. Excavations around underground electrical ducts and conduits shall be performed using extreme caution to prevent injury to workmen or damage to electrical ducts or conduits. Similar precautions shall be exercised around gas lines, telephone, and television cables.
5. Excavations shall have a surface dimension of no more than 18-inch by 18-inch. Air spades and vacuum excavators shall be used to limit the size of the excavation and damage to adjacent facilities. Backfill after completing potholing.
6. City approval is required prior to using slot tr enches.
C. Interferences:
1. If interferences occur at locations other than s hown on the Drawings, the Contractor shall notify the Engineer, and a method for correcting said interferences shall be supplied by the Engineer. Payment for interferences that are not shown on the Drawings, nor which may be inferred from surface indications, shall be in accordance with the provisions of the General Conditions. If the Contractor does not expose all required utilities prior to shop drawing preparation, he shall not be entitled to additional compensation for work necessary to avoid interferences, nor for repair to damaged utilities.
2. Any necessary relocations of utilities, whether shown on the Drawings or not, shall be coordinated with the affected utility. The Contractor shall perform the relocation only if instructed to do so in writing from the Engineer.
D. Shutdowns: Refer to City General Provisions.
3.04 SITE EXCAVATION
A. Remove lumped subsoil and rock up to ½ cubic yar d, measured by volume.
B. The maximum allowable temporary slope during exc avation range is 1 1/2H:1V.
C. Take care not to excavate beyond the limits show n as there shall be no additional payment to the Contractor for excavations beyond the limits shown in the Drawings.
D. If unsatisfactory material is encountered at the bottom of excavation, coordinate with the Engineer steps to remove and replace with material approved by the Engineer. Payment for removal and replacement of unsatisfactory material shall be made in accordance with the provisions of the General Conditions.
E. Backfill and compact excavations, beyond the lim its shown in the Drawings, in accordance with the requirements of Paragraph 3.11 with material approved by the Engineer.
F. Provide erosion control protection in accordance with City General Provisions.
3.05 TRENCH EXCAVATION
A. Excavation for pipe and other utilities such as duct banks shall be in open cut. The trench shall be as wide as necessary for sheeting and bracing and the proper performance of the work up to the maximum width permitted as shown on the Drawings. The sides of the trenches shall be vertical in paved areas. The bottom of the trench shall be constructed to the grades and shapes indicated on the Drawings. Favorable review by the City and Engineer is required prior to use of alternative methods of construction.
B. Remove lumped subsoil and rock up to ½ cubic yar d, measured by volume.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 10 Earthwork
C. Do not advance open trench more than 400 feet ah ead of installed pipe.
D. Accurately grade the bottom of the trenches to p rovide uniform bearing and support for each section of the pipe or conduit at every point along its entire length, except for the portions of the pipe sections where it is necessary to excavate for bell holes and for the proper sealing of pipe joints, and as hereinafter specified. Dig bell holes and depressions for joints after the trench bottom has been graded. For the pipe to rest on the bedding for as nearly its full length as practicable, bell holes and depressions shall be only of such length, depth, and width as required for properly making the joint. Remove stones as necessary to avoid point bearing.
E. The trench shall not be backfilled until the Eng ineer favorably reviews the pipe and bedding installation.
F. Take care not to excavate beyond the limits show n as there shall be no additional payment to the Contractor for excavations beyond the limits shown in the Drawings.
G. If unsatisfactory material is encountered at the bottom of excavation, coordinate with the Engineer steps to remove and replace with material approved by the Engineer . Payment for removal and replacement of unsatisfactory material shall be made in accordance with the provisions of the General Conditions.
H. Backfill and compact excavations, beyond the lim its shown in the Drawings, in accordance with the requirements of Paragraph 3.11 with material approved by the Engineer.
I. If no elevations are shown on the Drawings, prov ide 3 feet of minimum cover.
J. For all piping or conduits to be placed in any e xcavated and backfilled area, such as at manholes or for building connections, the structural backfill shall be first compacted to a level at least 3 feet from the top of the conduit elevation and then retrenched to conduit grade.
K. Provide secured ladders for access to the trench by construction and inspection personnel. Additional secured ladders shall be provided to any structure or pipe that must be inspected and tested. Failure to provide safe inspection access shall void initial inspection and follow up inspection shall not be performed until proper safe access is provided to the items to be inspected.
3.06 EXCAVATION FOR STRUCTURES
A. All excavation for structures shall be done to t he dimensions and levels indicated on the Drawings or specified herein. Excavate to such width outside the lines of the structure to be constructed as may be required for proper working methods, the erection of forms, and the protection of the work.
B. Take care to preserve the foundation surfaces sh own on the Drawings in an undisturbed condition. If the Contractor over excavates or disturbs the foundation surfaces shown on the Drawings or specified herein, without written authorization of the Engineer, they shall replace such foundations with concrete fill or other material approved by the Engineer in a manner that will show by test an equal bearing value with the undisturbed foundation material. No additional payment will be made for the added quantity of concrete fill or other material used because of over excavation.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 11 Earthwork
C. Inspection of Excavation: Notify the Engineer wh en excavation for the structure is complete. No forms, reinforcing steel, concrete, or precast structure shall be placed until the excavation has been inspected and approved by the Engineer.
3.07 SUBGRADE PREPARATION:
A. Finished Subgrade: Finished subgrade material ma y be native soil (following clearing and grubbing) or import material and prepared to be non-yielding when proof-rolled by passing over all areas to receive fille or as required by the Engineer with a minimum 10-ton roller, front-end loader with loaded bucket, or other heavy rubber-tired vehicle with high tire pressure (e.g., loaded tandem dump truck), in the presence of the Engineer. If subgrade is unstable, wet, or soft and air-drying is not an option, Contractor shall coordinate with the Engineer for corrective methods prior to placing subsequent lifts.
B. Fill Subgrade: Fill Subgrade (prior to placement of any fill material) shall be native soil or import material (following clearing and grubbing) prepared to be non-yielding when proof-rolled by passing over all required areas with a minimum 10-ton roller, front-end loader with loaded bucket, or other heavy rubber-tired vehicle with high tire pressure (e.g., loaded tandem dump truck) in the presence of the Engineer. If subgrade is unstable, wet, or soft, Contractor shall coordinate with the Engineer for corrective methods prior to placing subsequent lifts.
C. Unstable Soils
1. If the bottom of the excavation is soft or unsta ble, and in the opinion of the Engineer, cannot satisfactorily support the pipe, structure or other related design elements, the Engineer will determine proper corrective methods.
Payment for removal and replacement or other corrective methods shall be made in accordance with the provisions of the General Conditions.
3.08 SUPPORT OF EXCAVATIONS
A. Adequately support excavation for trenches and s tructures to meet all applicable requirements in the current rules, orders, and regulations. Excavation shall be adequately shored, braced, and sheeted so that the earth will not slide or settle and so that all existing structures and all new pipe and structures will be fully protected from damage. Keep vehicles, equipment, and materials far enough from the excavation to prevent instability.
B. Take all necessary measures to protect excavatio ns and adjacent improvements from running, caving, boiling, settling, or sliding soil resulting from the high groundwater table and the nature of the soil excavated. See Section 832 of the Civil Code of the State of California relating to lateral sub adjacent supports, and wherever structures or improvements adjacent to the excavation may be damaged by such excavation, the Contractor shall comply with this law.
C. The support for excavation shall remain in place until the pipeline or structure has been completed. During the backfilling of the pipeline or structure, the shoring, sheeting, and bracing shall be carefully removed so that there shall be no voids created and no caving, lateral movement, or flowing of the subsoils.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 12 Earthwork
3.09 SITE AND TRENCH BACKFILL
A. Backfill materials shall be compacted by vibrati ng, tamping, or a combination thereof. Compact materials in accordance with Paragraph 3.11unless otherwise specified or shown on the Drawings.
B. Site Backfill
1. Do not place any backfill material until the Eng ineer has inspected, tested to his or her satisfaction, and favorably reviewed the prepared subgrade.
2. Construct fills as shown on the Drawings, true t o line, grade, and cross- section.
3. Construct fills of native soil or imported soil. Place material in uniform, level layers, not exceeding 8 inches thick measured before compaction and carried across the entire width to the required slopes.
4. Soft zones identified during site backfill opera tions shall be addressed as identified under Paragraph 3.08.
C. Trench Backfill:
1. Place trench materials true to the lines, grades , and details indicated on the Drawings.
2. Place trench materials in uniform, level layers, not exceeding 6 inches thick measured before compaction. The difference in level on either side of a pipe shall not to exceed 4 inches.
3. Backfill material shall not be placed over the p ipe or conduit until after the joints have been completed and inspected by the Engineer.
4. Protect the pipe or conduit from damage during t he construction period. It shall be the Contractor’s responsibility to repair broken or damaged pipe at no extra cost to the City. Once repair is inspected and approved by the City, contractor shall retest the line. Carefully place backfill around and over the pipe and do not allow it to fall directly upon the pipe. Tamping of backfill over the pipe shall be done with tampers, vibratory rollers, and other machines that will not injure or disturb the pipe.
5. Do not allow construction traffic over the pipe trench until the trench has been backfilled to be even with the existing adjacent grade, temporary AC pavement has been placed over the backfilled trench and/or a traffic rated metal plate has been placed over the trench.
D. Import Backfill: The removal and replacement lim its and quantity of import backfill material shall be coordinated and accepted by the Engineer and governing authority prior to proceeding with the installation.
3.10 BACKFILL UNDER / ADJACENT TO STRUCTURES
A. Compact materials in accordance with Paragraph 3 .11 unless otherwise specified or shown on the Drawings.
B. Aggregate Base shall be placed in uniform, level layers, not exceeding 6 inches thick measured before compaction under structures, meter vaults, and electrical vaults.
C. Installation of Structure Backfill shall conform to the requirements as indicated on Drawing Sheet S-1.
D. Backfill Adjacent to Structures
1. Do not place backfill against structures until t he concrete has been patched and cured.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 13 Earthwork
2. Do not place backfill against structures until a t least 28 days after the concrete was placed, or until the concrete has achieved a strength of at least 2,500 psi, whichever is earlier. Concrete strength shall be demonstrated by field cured cylinders tested at the Contractor's cost, prepared and tested in accordance with ASTM C31 and ASTM C39.
3. Do not place backfill against hydraulic structur es until the structure has passed the specified leakage tests.
4. Place Structural Backfill within 2 feet of a str ucture or as shown on the Drawings.
5. Place structural backfill in uniform, level laye rs, not exceeding 6-inches thick measured before compaction. Bring backfill up uniformly on all sides of the structure, and on both sides of buried walls.
3.11 COMPACTION
A. Add water to the backfill material or dry the ma terial as necessary to obtain moisture content within 2 percent of optimum. Employ such means as may be necessary to secure a uniform moisture content throughout the material of each layer being compacted.
1. Contractor shall use air-drying to reduce moistu re content and/or achieve compaction before other methods may be considered. Or, where applicable, Contractor shall demonstrate air-drying is not possible before other methods may be considered.
B. When densities of compacted materials do not mee t the requirements, remove and/or recompact the material until the requirements are met. The Contractor will be back charged the cost of retesting all failing tests, including the initial retest.
Such back charges will be deducted from the Contractor's Progress Payments.
C. After the material has been moisture conditioned , compact it with compaction equipment appropriate for the use to achieve specified compaction.
D. If the backfill material becomes saturated throu gh negligence or otherwise, remove the faulty material and replace it with suitable material compacted to the specified density at no additional cost to the City.
E. Compact materials in accordance with AASHTO T99 OR ASTM D1557 (Modified Proctor) unless otherwise specified.
F. Compaction of embankment and backfill materials by flooding, ponding, or jetting is not permitted.
G. Material Requirements
Material Minimum Relative Compaction ¹
1. Engineered Fill:
Native Soil
Import Soil
95 percent
95 percent
2. Pipe Zone Backfill 90 percent
3. Trench Zone Backfill 95 percent in paved areas
90 percent in unpaved areas
4. Pipe Bedding 80 percent
7. Subgrade 95 percent in paved areas
90 percent in unpaved areas
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02300 - 14 Earthwork
Material Minimum Relative Compaction ¹
8. Aggregate Base Refer to Section 02700.
9. Structure Backfill 95 percent
¹ Modified Proctor Test
3.12 SITE GRADING
A. Compact materials in accordance with Paragraph 3 .11 unless otherwise specified or shown on the Drawings.
B. Except where shown otherwise in the Drawings, re store the finish grade to the original contours and to the original drainage patterns. Grade surfaces to drain away from structures at a minimum of 2 percent, unless otherwise noted in the Drawings.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02516 - 1 Disinfection
SECTION 02516
DISINFECTION
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Clean, flush and disinfect all surfaces with whi ch the process water may come in contact in the pipelines, and accessories, including:
a. Small pipelines:
1) Domestic water piping.
2. Dispose of disinfection solution.
1.02 REFERENCES
A. American Water Works Association (AWWA):
1. C651 AWWA Standard for Disinfecting Water Mains
2. C655 AWWA Field Dechlorination
3. C670 AWWA Online Chlorine Analyzer Operation and Maintenance B. Standard Methods for Examination of Water and Wa stewater
1. 9221 - Multiple Tube Fermentation Technique
2. 9222 - Membrane Filter Technique
3. 9223 - Chromogenic Substrate Coliform Test
4. NSF/ANSI Standard 60: Drinking Water Treatment C hemicals - Health Effects
5. NSF/ANSI Standard 61: Drinking Water System Comp onents - Health Effects
1.03 SCHEDULING
A. Schedule and coordinate the work with the City a nd Engineer. Once disinfection has been satisfactorily accomplished, no further entry to the interior of the facilities will be allowed unless entry must be made to perform repairs, in which case repeat disinfection on a localized basis at no additional cost to the City. The Contractor shall be responsible for maintaining security of the disinfected facilities.
B. Disinfect d pipelines following successful press ure testing.
1.04 SUBMITTALS
A. Submit in accordance with City General Provision s.
B. Submit a Disinfection Plan in the Product Review category including the procedures, methods, materials and schedules proposed for disinfecting the required surfaces, and method of disposal of chlorinated water.
1.05 QUALITY ASSURANCE
A. Laboratory testing related to disinfection will be performed by and paid for by the City.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02516 - 2 Disinfection
PART 2 - PRODUCTS
2.01 MATERIALS
A. Potable Water: Use potable water to flush and d isinfect: all other small and ancillary equipment and piping systems.
B. Chlorine: See the respective AWWA Standards and paragraph 3.02 below for forms of chlorine that may be used for disinfecting operations.
PART 3 - EXECUTION
3.01 PREPARATION
A. Provide all necessary appurtenances required for the disinfection procedures including taps, temporary piping, connections and shutoff valves. Submit data on appurtenances which will be permanently installed for review by the Engineer.
B. The Contractor is advised that precautions taken to keep surfaces clean during construction and avoiding the entry of deleterious substances on the work during construction will facilitate achieving the disinfection requirements of this project.
C. Prior to disinfecting, thoroughly clean accessib le surfaces of dust, dirt, foreign matter and deleterious substances. Remove any oil by contact with absorbents.
Use water sprays, steam cleaning, vacuum cleaning, swabbing, hand brushing or a combination of methods and rinsing to effect the cleaning, but do not use any method that will be detrimental to the finish surfaces. Flush inaccessible surfaces clean.
3.02 APPLICATION
A. After completing all construction activities, di sinfect the required surfaces with chlorine solutions in accordance with the following procedures. Following disinfection and flushing, the City will take water samples for chlorine residual and bacteriological analysis of the water. If the specified chlorine residual and bacteriological requirements are not satisfied, repeat disinfection procedure until the requirements are met. The Contractor shall pay for the additional sampling and testing at no additional cost to the City, until disinfection requirements are met.
B. Small Pipelines:
1. Preparation: Provide the system with a 1-inch m inimum service cock or valve or other means to inject chlorine solution at a point within 2 or 3 feet of its junction with the supply source. When system is complete, thoroughly flush it by fully opening every outlet until clear water flows from all of them.
2. Disinfecting Agent: Sodium hypochlorite or calc ium hypochlorite in sufficient quantities to produce chlorine concentration of at least 50 parts per million in the system.
3. Disinfecting Procedure:
a. Connect a hand-operated pump, or other means of injecting the disinfecting agent, to one-inch minimum service cock or valve or other injection device. Pump must provide a pressure greater than that of supply of system.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02516 - 3 Disinfection
b. With system completely full of water and supply valve open, proceed to adjust every outlet of system so that a trickle of water flows from each. c. Inject disinfectant slowly and continuously at a n even rate, not in slugs, until a test at each outlet shows a free chlorine residual concentration of at least 50 parts per million.
d. Close all outlets and valves, including valve co nnecting to supply line and one-inch minimum service cock on solution injection connection.
Maintain condition for 24 hours. After 24 hours, test for residual chlorine at each outlet. The free residual chlorine concentration indicated should be not less than 10 ppm. If the indicated free chlorine concentration is less than 10 ppm, repeat disinfection procedure until an approved result is obtained.
e. When the above procedure has been completed to t he satisfaction of the Engineer, flush out entire system with fresh water until tests at all outlets show a residual of not more than 0.5 ppm.
3.03 FIELD QUALITY CONTROL
A. Chlorine Residual Testing: AWWA C651, Appendix A, DPD Drop Dilution Method, except where otherwise specified. Testing shall be performed by the Contractor.
B. Bacteriological Analyses of Water: After the co mpletion of disinfecting procedure, including the final flushing as described in AWWA C651 and heretofore, the Contractor will obtain water samples from this system for bacteriological analyses.
C. Requirements for satisfactory disinfection of pr ocess equipment, tanks, pipelines and associated elements are:
1. Bacteriological analyses indicate that water sam ples are negative for coliform organisms; and
2. Heterotrophic plate count (standard plate count) is less than 100 colony forming units per milliliter.
3. If bacteriological analyses do not satisfy the a bove requirements, then repeat disinfection procedure until these requirements are met.
D. Dechlorinate and dispose of disinfection solutio n in thesanitary sewer . Take care to assure that chlorinated water is not spilled into drains.
3.04 PROTECTION OF DISINFECTED STRUCTURES
A. If required to re-enter a disinfected structure, the work shall be conducted using techniques and work methods as necessary to maintain the disinfected status. This shall include use of disinfected foot coverings, tools, and the like. In the event the Contractor contaminates the facilities, additional flushing and disinfection of the affected system shall be performed at no additional cost to the City.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02516 - 4 Disinfection
THIS PAGE INTENTIONALLY BLANK
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 1 Paving and Surfacing
SECTION 02700
PAVING AND SURFACING
PART 1 - GENERAL
1.01 SUMMARY
A. Furnish all labor, material, equipment, tools, a nd services required for removing, placing and compacting asphalt concrete pavement for the parking lot/open area to the lines, grades, and dimensions shown on the Drawings and as specified herein.
1. Demolish existing asphalt paving.
2. Repair and resurface existing asphalt pavement d amaged during construction.
3. Install asphalt pavement.
1.02 REFERENCES
A. ASTM International (ASTM):
1. D422 Test Method for Particle-Size Analysis for Soils
2. D1556 Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method
3. D1557 Standard Test Methods for Laboratory Compa ction Characteristics of Soil Using Modified Effort (Modified Proctor)
4. D2922 Test Methods for Density of Soil and Soil- Aggregate in Place by Nuclear Methods (Shallow Depth)
B. California Department of Transportation (Caltran s):
1. California Test 216 Method of Test for Relative Compaction of Untreated and Treated Soils and Aggregates
2. California Test 231 Method of Test for Relative Compaction of Untreated and Treated Soils and Aggregates by the Area
Concept Utilizing Nuclear Gauges
C. Standard Specifications for Public Works Constru ction (SSPWC), aka "Greenbook" D. City of Carlsbad Standard Specifications (City S tandard Specifications) E. City of Carlsbad Utilities Department Standard S pecifications (Agency Standard Specifications)
1.03 DEFINITIONS
A. Base (aggregate base): Layer of material of cert ain thickness placed under the pavement, constructed on subgrade. It provides a working surface for pavement placement, load distribution, and drainage.
B. Leveling course: Lift of asphalt concrete used t o fill and level irregularities prior to placement of the wearing course.
C. PG: Performance graded. The PG system defines th e asphalt binder based on the conditions in which it may be used.
D. Prime Coat: Emulsified asphalt used for water-pr oofing the base layer prior to placing asphalt concrete.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 2 Paving and Surfacing
E. Subgrade: See Section 02300.
F. Tack Coat: Emulsified asphalt used to bond aspha lt concrete to existing asphalt concrete, or to bond between asphalt concrete lifts.
G. Wearing course: Final lift of asphalt concrete.
1.04 SUBMITTALS
A. Submit in accordance with City General Provision s.
B. Submit the following under the Product Data:
1. Submit a signed verification from each source of supply for each construction material employed on this project indicating that the materials meet the Specification requirements.
2. Mix design for asphalt concrete in accordance wi th SSPWC Section 203-6.3.
3. Submit manufacturer's certification of the actua l volatile organic compound (VOC) content for all pavement paints and bituminous pavement sealers proposed for use on this project. Submit certification of the actual VOC content for all coatings. VOC content shall be measured in grams per liter by weight of coating as applied excluding water and color added to the tint base.
4. Submit verification that bituminous pavement sea lers and paint products furnished meet San Diego County Air Pollution Control District (APCD)
regulations as to allowable VOC content for the time and place of application and use intended.
C. Submit the following under Samples and Test Resu lts:
1. Furnish, without additional cost to the Owner, s uch quantities of construction materials as may be required by the Engineer for test purposes. The Contractor shall cooperate with the Engineer and furnish necessary facilities for sampling and testing of all materials and workmanship. All materials furnished and all work performed shall be subject to rigid inspection, and no materials shall be used in the construction work until it has been inspected by the Engineer.
1.05 QUALITY ASSURANCE
A. Storage and transportation of asphalt concrete s hall comply with SSPWC Section 203-6.8 and 203-6.9.
B. All pavement stripe painting shall be performed by competent and experienced Equipment operators and painters using proper equipment, tools, stencils, templates, and shields in a workmanlike manner.
1.06 REGULATORY REQUIREMENTS
A. All work, material, procedures, and practices un der this Section shall conform to requirements of the California Air Resources Board (CARB) and San Diego County Air Pollution Control District (APCD)
PART 2 - PRODUCTS
2.01 ASPHALT CONCRETE
A. Asphalt Concrete Mix shall be in accordance with SSPWC Section 203-6.4.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 3 Paving and Surfacing
2.02 TACK COAT
A. Material for tack coat shall comply with SSPWC S ection 302-5.4.
2.03 AGGREGATE BASE
A. Aggregate base shall conform to SSPWC Section 200- 2. Aggregate base shall conform to that specified for 3/4-inch maximum, unless otherwise indicated.
2.04 DISTRIBUTING EQUIPMENT
A. Distributors shall be of the pressure type with insulated tanks and shall be equipped with the following:
1. A tachometer of the auxiliary wheel type, which registers speed in feet per minute.
2. Charts and devices to provide for accurate and r apid determination and control of the amount of asphalt being applied.
3. A hose and nozzle attachment to be used for area s inaccessible to the spray bar.
4. A pressure gauge for determining application pre ssure.
5. A thermometer for determining temperature of the asphalt.
Distributors and booster tanks shall be so maintained as to prevent dripping of asphalt from any part of the equipment.
Spray bars shall have a minimum length of 9 feet. Spray bars and extensions shall be the full circulating type and shall be adjustable to permit varying height above the surface to be treated.
The nozzles attached to the bar shall be either the conical or flat slotted type. The distance center to center of the nozzles shall not exceed 6 inches. The valves, which control the flow from nozzles, shall be of a positive acting design so as to provide a uniform unbroken spread of asphalt on the surface. Valves shall be operated so that all valves may be simultaneously opened or closed. Each valve shall also be capable of similar independent control.
Spreading equipment shall be so designed and articulated that uniform application of the asphalt, in controlled amounts, may be made ranging from 0.02 to 1.0 gallon per square yard of surface and with a range of pressure from 25 to 75 psi.
B. A trough shall be located under the sprays, prop erly arranged to be swung out of the way after the sprays are operating in a uniform manner at the desired pressure or, in lieu thereof, building paper shall be spread over the treated surface for a sufficient length back so that the sprays are operating properly when the uncovered surface is reached. The building paper shall then be removed and disposed of. If the cutoff is not sufficiently positive, the similar use of paper may be required at the end of the area being covered. The distributor shall be operated in such a manner that liquid asphalt will not be splashed on adjacent guardrails or structures. Any asphalt so splashed may be removed at the expense of and by the Contractor.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 4 Paving and Surfacing
PART 3 - EXECUTION
3.01 GENERAL
A. Where trenching or other construction activity h as resulted in damage to a localized area of pavement, the damaged pavement shall be cut back 6 inches, removed and replaced.
B. Where the demolition or damaged area extends ove r more than 50% of the road width or paved area, as determined by the Engineer, the full pavement width or area shall be removed and replaced.
C. Structures such as valve boxes, manhole frames a nd covers, and electrical vaults shall be adjusted to grade as necessary within paved areas.
D. Existing asphalt pavement islands of 50 square-f eet or less and strips 18 inches or less in width shall be removed and replaced.
E. Adjust existing manholes, meter boxes, cleanouts , etc. to match the new grade.
3.02 PAVEMENT CUTTING
A. Where trenching or excavation occurs in paved ar eas, the existing pavement shall be scored and broken ahead of the trenching or excavation operation. The extent of paving removed shall be limited to the minimum necessary for the excavation.
All existing asphalt or concrete surfacing shall be saw cut vertically in a straight line and removed from the jobsite prior to starting the trench excavation. This material shall not be used in any fill or backfill.
B. Pavement shall be cut accurately and on neat lin es. The asphalt pavement shall be saw cut to a minimum depth equal to or greater than one-half the thickness of the pavement section. Any pavement damaged outside these lines shall be re-cut and restored at the expense of the Contractor. Should voids develop under existing pavements during construction, Contractor shall remove the affected pavement, repair voids and replacement pavement section at the expense of the Contractor.
C. Construct joints between successive runs that ar e vertical and at right angles to the line of the improvement. Exercise care in construction of all joints to ensure that the surface of the pavement is true to grade and cross-section. Lapped joints will not be permitted.
3.03 PLACEMENT OF AGGREGATE BASE
A. Subgrade Preparation: Refer to Section 02300.
B. Aggregate Base Tolerance: The aggregate base sha ll not be placed before the subgrade is approved by the Engineer. The finished aggregate base shall not vary more than 1 inch above or below, the planned grade.
C. Aggregate Base Placing: The aggregate base mater ial shall be spread on the prepared subgrade by means of approved spreading devices subject to approval by the Engineer; the aggregate base material may be dumped in piles upon the subgrade and spread by bulldozing ahead from the dumped material. Each layer shall not exceed 6 inches. Segregation of large or fine particles of aggregate shall be avoided, and the material as spread shall be free from pockets of large and fine material . The aggregate base material shall be in accordance with SSPWC Section 301-2.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 5 Paving and Surfacing
D. Compaction: Compaction shall be in accordance wi th SSPWC Section 301-2.3.
3.04 PRIME COAT APPLICATION
A. Prime Coat: A prime coat shall be applied to all base course surface areas to be covered with asphalt concrete.
1. Preparation: Immediately before applying the pri me coat, the area to be surfaced shall be cleaned of all loose material by means of hand brooms.
2. Application: Place prime coat in accordance with SSPWC Section 302-5.3.
3.05 TACK COAT APPLICATION
A. Tack Coat: In advance of spreading bituminous ma terial upon an existing bituminous or portland cement concrete surface, a tack coat shall be applied to all areas to be surfaced and to all vertical surfaces of existing pavement, curb, gutters and construction joints in the surfacing against which additional material is to be placed. Apply tack coat only as far in advance as necessary for that day’s installation.
1. When two or more lifts of asphalt concrete are r equired, a tack coat shall be applied between each lift unless the lifts are placed in the same work shift if:
a. No dust, dirt or extraneous material is present
b. Surface is at least 140 degrees F
2. Preparation: Immediately before applying a tack coat, the area to be surfaced shall be cleaned of all loose material.
3. Application: The tack coat shall be applied by m eans of pressure distributors by pressure hand-spray equipment. The rate of application shall be
0.05 gallon per square yard for PG 64-10 or 0.05 to 0.10 gal per square yard for SS-1h emulsified asphalt. Emulsified asphalt shall not be applied when the atmospheric temperature is below 40°F. Place tack coat in accordance with SSPWC Section 302-5.4. Cover drain inlets (if applicable), and manholes (if applicable) during the application of tack coats.
3.06 PLACEMENT OF ASPHALT CONCRETE
A. Delivery and Spreading: Delivery, distribution a nd spreading shall be in accordance with SSPWC Section 302-5.5.
B. Compaction: Initial or breakdown rolling and the final rolling of the uppermost layer of the asphalt concrete shall be compacted in accordance with SSPWC Section 302-5.6. Compaction by vehicular traffic shall not be permitted. The Engineer reserves the right to require an adjustment of the temperature of the asphalt concrete at the time of placement.
C. Pavement Thickness: Pavement shall match the exi sting adjoining pavement in thickness, or as indicated on the Drawings, or as specified, whichever is greater.
D. Joining Pavement: The joints between old and new pavements or between successive days' work shall be carefully made in such manner as to ensure a continuous bond between old and new sections of the course. Edges of existing pavement shall be exposed and cleaned and edges cut to straight, vertical surfaces. All joints shall be painted with a uniform coat of tack coat before the fresh mixture is applied.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
02700 - 6 Paving and Surfacing
E. Protection of Pavement: After final rolling, no vehicular traffic of any kind shall be permitted on the pavement until it has cooled and hardened and in no case less than 6 hours.
3.07 REPLACEMENT OF TEMPORARY PAVEMENT
A. Final pavement restoration shall be made as soon as practicable after backfilling.
In that period of time between backfilling and final pavement restoration, the trench shall be maintained level with the adjacent pavement and shall be covered with a 1-inch minimum layer of temporary pavement. Prior to placing the final pavement, the temporary pavement shall be removed, the aggregate base excavated to the lines indicated on the Drawings, and the existing pavement edges saw cut as herein specified. The final asphalt pavement shall not be placed before the aggregate base is approved by the Engineer and a tack coat applied to existing paved surfaces.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 1 Louvers
SECTION 10200
LOUVERS
PART 1 - GENERAL
1.01 SUMMARY
Section Includes:
A. Fixed-Blade Extruded-Aluminum Louvers:
1. Horizontal drainable-blade louver.
B. Fixed Blade Acoustic Louvers.
C. Louver Screens.
1.02 REFERENCES
A. Air Movement and Control Association Internation al, Inc. (AMCA)
1. AMCA 500-L Laboratory Methods of Testing Louvers for Rating
2. Standard 501 Louver Application Manual and Desig n Guide
3. AMCA 511 Certified Ratings Program - Product Rat ing Manual for Air Control Devices.
B. ASTM International (ASTM):
1. B117 Standard Practice for Operating Salt Spray (Fog) Apparatus
2. B221 Standard Specification for Aluminum and Alu minum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
3. D822 Standard Practice for Filtered Open-Flame C arbon-Arc Exposures of Paint and Related Coatings
4. D1187 Standard Specification for Asphalt-Base Em ulsions for Use as Protective Coatings for Metal
5. D1308 Standard Test Method for Effect of Househo ld Chemicals on Clear and Pigmented Organic Finishes
6. D2247 Standard Practice for Testing Water Resist ance of Coatings in 100% Relative Humidity
7. D2794 Standard Test Method for Resistance of Org anic Coatings to the Effects of Rapid Deformation (Impact)
8. D3359 Standard Test Methods for Rating Adhesion by Tape Test
9. E90 Standard Test Method for Laboratory Measurem ent of Airborne Sound Transmission Loss of Building Partitions and Elements
10. E413 Classification for Rating Sound Insulation
C. “Architectural Sheet Metal Standards” by Sheet M etal and Air Conditioning Contractors National Association (SMACNA), latest edition.
D. California Building Standards Commission
1. 2022 California Building Code (CBC) (California Code of Regulations, Title 24)
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 2 Louvers
E. International Code Council (ICC):
1. 2021 International Building Code (IBC)
F. Fenestration & Glazing Industry Alliance (FGIA):
1. AAMA 611 Voluntary Specification for Anodized Ar chitectural Aluminum
1.03 SUBMITTALS
A. Product Data: Manufacturer's data sheets for eac h product and assembly specified.
1. Preparation instructions and recommendations.
2. Storage and handling requirements and recommenda tions.
3. Cleaning methods.
B. Shop Drawings: Custom prepared for this project.
1. Include plans; elevations; sections; and details showing profiles, angles, and spacing of elements. Show unit dimensions related to wall openings and adjacent construction; free area for each size indicated for louvers; profiles of frames at jambs, heads, and sills; and anchorage details and locations.
2. Verify openings by field measurements before fab rication and indicate measurements on Shop Drawings.
C. Product Certificates:
1. Air Performance: Certificates signed by Air Move ment and Control Association International Inc (AMCA) certifying that the manufacturer's stock units are tested in accordance with AMCA Standard 500 and are licensed to bear the AMCA Certified Ratings Seal in accordance with AMCA Standard 511.
2. Water Penetration: Certificates signed by Air Mo vement and Control Association International Inc (AMCA) certifying that the manufacturer's stock units are tested in accordance with AMCA Standard 500 and are licensed to bear the AMCA Certified Ratings Seal in accordance with AMCA Standard 511.
3. Weather Louver Effectiveness: Certificates signe d by Air Movement and Control Association International Inc (AMCA) certifying that the manufacturer's stock units are tested in accordance with AMCA Standard 500-L99, Section 8.3.2 - Wind Driven Rain Water Penetration Test, and are licensed to bear the AMCA Certified Ratings Seal in accordance with AMCA Standard 511.
D. Selection Samples: Two complete color charts sho wing the full range of colors available for units with factory-applied color finishes.
1.04 QUALITY ASSURANCE
A. Manufacturer Qualifications: Minimum 5-year manu facturing similar products.
B. Installer Qualifications: Minimum 2-year experie nce installing similar louvers.
C. Source Limitations: Obtain products through one source from a single manufacturer where alike in one or more respects regarding type, design, or factory-applied color finish.
D. AMCA Standard 500-L: Air performance, water pene tration and air leakage ratings shall be determined in accordance with Air Movement and Control Association
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 3 Louvers
International Inc (AMCA) Standard 500, “Laboratory Methods of Testing Louvers for Rating.”
E. SMACNA Standard: Comply with SMACNA's “Architect ural Sheet Metal Manual” recommendations for fabrication, construction details, and installation procedures.
1.05 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store and handle materials and products in strict compliance with manufacturer's instructions and recommendations, and industry standards.
B. Store products indoors in manufacturer's or fabr icator's original containers and packaging, with labels clearly identifying product name and manufacturer. Protect from damage.
C. Handling: Protect materials and finishes during handling and installation to prevent damage.
1.06 SEQUENCING AND SCHEDULING
A. Field Measurements: Verify openings and adjacent construction by field measurements before fabrication and indicate measurements on Shop Drawings.
Coordinate fabrication schedule with construction progress to avoid delaying the Work.
PART 2 - PRODUCTS
2.01 GENERAL REQUIREMENTS FOR STATIONARY AND ACOUST IC LOUVERS.
A. Provide louvers that have all joints concealed.
B. Continuously weld all joints in the louver assem bly using a shielded arc process.
C. Provide all related break shape and extruded alu minum sills, flashings and sub- frames. Flashings shall be 0.050 or thicker as indicated.
D. Provide matching 1/8-inch thick dark bronze anod ized aluminum backing plates to cover the rear of decorative louvers and portions of louvers outside of air intake or exhaust ductwork.
E. Provide all required aluminum angles, tees, plat es and other shapes required for a complete installation.
2.02 FIXED-BLADE EXTRUDED-ALUMINUM LOUVERS
A. Acceptable Manufacturers: Louver style K6744 exp osed vertical mullion type , manufactured by Airolite; Construction Specialties; Ruskin; or equal.
B. Design Criteria: Design and test louvers to AMCA Standard 500-L and shall bear AMCA certified rating seals for air performance and water penetration. Test a 4x4- foot louver with a minimum free area of 7.89 square feet to pass at least 800 FPM through the free area at a pressure drop not exceeding 0.15 in W.G. Limit water penetration to 10 ounces of water per square foot of free area when tested at 720 FPM for 15 minutes per AMCA Standard 500-L.
C. AMCA Seal: Mark units with AMCA Certified Rating s Seal.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 4 Louvers
D. Provide extruded aluminum framed continuous blad e louvers with exposed jambs and mullions, 4 inches deep with blades spaced 3 inches on center. Use aluminum extrusions; ASTM B 221 alloy 6063-T52 for all parts.
E. Use extruded horizontal drainable blades, 12-gau ge (0.81 inches) thick, having a downward turned stiffening leg along the front bottom edge and an up turned leg with a forward-facing lip to stop water migration along the top rear edge. Use blades that have an extruded hood on their bottom surface to interlock with mullion support brackets. Set louver blades at a 30-degree angle for exhaust and 45-degree angle for intake.
2.03 ACOUSTIC LOUVERS
A. Model: T9112 as manufactured by Airolite; Constr uction Specialties; Ruskin; or equal.
B. Design Criteria: Louvers shall be acoustic type incorporating stationary, parallelogram blades in a single frame. Louvers shall be 12-inches deep and assembled entirely from fabricated aluminum components. Blades and frames shall be 0.080-inch thick aluminum, alloy 5052-H32. Blades shall be positioned at 45-degrees and spaced 5-inches on center. Each blade and top and bottom frame cavity shall be filled with fiberglass acoustic insulation to absorb the transmission of sound. Acoustic insulation shall be held in place by perforated aluminum panels.
Acoustic insulation to be protected by a woven fire-retardant (self-extinguishing) 100% polyester sheeting. Fasteners to be aluminum or stainless steel. Structural supports shall be designed and furnished by the louver manufacturer to carry a wind load of 25 psf.
C. Louver Size: As shown on Drawings.
D. Performance Data:
1. Based on testing 48-inch x 48-inch size unit in accordance with AMCA 500-L.
2. Free Area: 25 percent, nominal.
3. Minimum Free Area Size: 4.07 square feet.
E. Minimum Air Performance & Water
1. Penetration Ratings Standard: Air Movement and C ontrol Association (AMCA) Certified Ratings Seals for air performance and water penetration ratings.
2. Air Performance & Water Penetration Data: A 4' x 4' unit provides 4.07 square feet of free area and shall intake 1,046 FPM free area velocity at a static pressure drop not exceeding 0.13" H2O per AMCA Standard 500-L.
F. Acoustic Performance: Tested in accordance with ASTM E 90 and E413.
1. Acoustic Ratings Data: Octave Band Center Freque ncy (Hz) - Free Field Noise Reduction in Decibels; 63 Hz-16 dB; 125 Hz- 13dB; 250 Hz-15dB; 500 Hz-18 dB; 1,000 Hz-16dB; 2,000 Hz-18dB; 4,000 Hz-18 dB; and 8,000 Hz- 21dB
2.03 ALUMINUM FINISHES
A. Spray-Applied Hylar 5000™/Kynar 500®:
1. Color: Duranar
TM Aged Copper UC54434, or equal. Final selection shall be made by Engineer from manufacturer's standard color list. The manufacturer's list shall consist of a minimum of 5 choices that closely match existing color.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 5 Louvers
2. Coating thickness: 4-coat 2.13-3.1 mils metallic .
3. Painted Finish Performance Standards:
a. Impact:
1) Test Method ASTM D2794.
2) Coating shall withstand direct and reverse impac t of 1.5 inch- pounds/mil substrate thickness.
3) Coating shall adhere tightly to metal when subje cted to #600 Scotch tape pick-off test. Slight micro-cracking is permissible, but no star cracking shall occur.
b. Adhesion:
1) Test Method ASTM D3359.
2) Coating shall not pickoff when subjected to an 1 1 x 11 x 1/16-inch grid with reverse impact of 1.5 inch-pounds/mil substrate thickness and taped with #600 Scotch tape.
c. Humidity Resistance:
1) Test Method ASTM 2247.
2) No formation of blisters shall occur when subjec ted to condensing water fog at 100°F for 1,000 hours.
d. Salt Spray Resistance:
1) Test Method ASTM B117; expose single-coat system to 1,000 hours, using 5% NaCL solution.
2) Corrosion creepage from scribe line shall be 1/1 6 inch. e. Weather Exposure:
1) Accelerated Test Method ASTM D822 for 2,000 hour s in Weather- Ometer.
2) No checking, crazing or adhesion loss shall occu r.
f. Chemical Resistance:
1) Acid Pollutants Test Method ASTM D1308 for 10% m uriatic acid and 20% sulfuric acid.
2) Alkali Resistance Test Method ASTM D1308.
3) No loss of adhesion or gloss and no color change shall occur.
2.04 LOUVER SCREENS
A. General: Provide exterior louvers with louver sc reens.
1. Screen Location for Adjustable Louvers: Interior face, unless otherwise indicated.
2. Screening Type: Insect screening, unless otherwi se indicated.
3. Where ductwork is attached to the interior side of louver provide holder for screen frame that can be built into ductwork and so arranged that by opening a door in duct, screen can be slid out for cleaning without disassembling ductwork. Where there is no ductwork attached to interior of louver, provide a holder for screen frame designed so that screen can be removed for cleaning and replaced without using tools.
B. Attachment: Secure screens to louver frames with stainless-steel machine screws, spaced 18 inches on center.
1. Louver Screen Frames: As manufactured by The Air olite Co; to sizes indicated on Drawings.
2. Fabrication: Mitered corners.
3. Metal: Roll formed aluminum.
4. Finish: Mill finish, unless otherwise indicated.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 6 Louvers
5. Type: Rewirable frames with a driven spline or i nsert for securing screen mesh.
C. Louver Screening for Aluminum Louvers: As manufa ctured by The Airolite Co.
1. Bird Screening: Aluminum, 1/4-inch, 0.047-inch w ire.
2.05 BITUMINOUS PAINT
A. Bituminous Paint: Cold-applied asphalt mastic co mplying with SSPC-Paint 12 but containing no asbestos fibers, or cold-applied asphalt emulsion complying with ASTM D 1187.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Protect all aluminum in contact with concrete, p laster, masonry, steel or galvanized metal with a coating of bituminous paint. Prepare substrates and openings using methods recommended by manufacturer for achieving best result for substrates under project conditions.
B. Install louvers as shown in the Contract Drawing s and as shown in the SMACNA Architectural Sheet Metal manual.
1. Locate and place units level, plumb, and at indi cated alignment with adjacent work.
2. Use concealed anchorages where possible. Provide brass or lead washers fitted to screws where required to protect metal surfaces and to make a weathertight connection.
3. Provide perimeter reveals and openings of unifor m width for sealants and joint fillers as indicated on Drawings.
4. Repair finishes damaged by cutting, welding, sol dering, and grinding. Restore finishes so no evidence remains of corrective work. Return items that cannot be refinished in the field to the factory, make required alterations, and refinish entire unit or provide new units.
C. Provide bird screens on all louvers. Install on the interior side. Use stainless steel screws throughout.
D. Install sill flashing as shown detailed and as r equired to provide a watertight installation.
E. Install sheet metal drip at head of louvers wher e shown.
F. Apply sealant "B" all around frame, inside and o utside. Install concealed gaskets, flashings, joint fillers, and insulation, as installation progresses, where weathertight joints are required.
3.02 ADJUSTING, CLEANING AND PROTECTION
A. Test operation of adjustable louvers and adjust as needed to produce fully functioning units that comply with requirements.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 7 Louvers
B. Protect products from damage until completion of project. Use temporary protective coverings where needed and approved by manufacturer. Remove protective covering at the time of Substantial Completion.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10200 - 8 Louvers
THIS PAGE INTENTIONALLY LEFT BLANK
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10400 - 1 Identifying Devices
SECTION 10400
IDENTIFYING DEVICES
1.01 SUMMARY
A. Section Includes: Signs, decals, tags, and pipe markers.
1.02 REFERENCES
A. American National Standards Institute / American Society of Mechanical Engineers (ANSI/ASME), ASME A13.1 - 2015, "Scheme for the Identification of Piping Systems."
B. American National Standards Institute (ANSI), IC C A117.1 - 2009, "Accessible and Usable Buildings and Facilities".
C. National Fire Protection Association (NFPA) NFPA 704, "Standard System for the Identification of the Hazards of Materials for Emergency Response".
1.03 SUBMITTALS
A. Submit in accordance with City General Provision s.
B. Product Data: Fully describe all items proposed for use.
C. Shop Drawings: Scaled drawings or images of cust om-made signs, showing style and size of lettering and colors.
D. Samples: Provide one full size representative sa mple of each signage type, made of the specified material, from Part 2 of this Specification. Provide manufacturer’s standard color palette for each selection.
1.04 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with the followi ng:
1. Americans with Disabilities Act (ADA).
2. California Building Code, CCR Title 24, especial ly Chapter 11B.
3. California Code of Regulations, CCR Title 8, CAL /OSHA.
4. Federal Occupational Safety and Health Act (OSHA ).
5. Referenced sections, specifications for accident prevention signs and tags, and exit signs.
6. Porcelain Enamel Institute (PEI): Complete Techn ical Manuals 101 through 1301 and Property Bulletin 503 – Resistance to Corrosion.
B. Comply with the manufacturer's published recomme ndation for installation of materials used.
PART 2 - PRODUCTS
2.01 SAFETY SIGNAGE
A. Hazard Alerting Signage (CAUTION, WARNING, DANGE R):
1. General
a. Refer to the Signage Schedule below to identify the sign types and quantities for the project.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10400 - 2 Identifying Devices
b. Manufacturer: Seton Nameplate Company; W.H. Brad y Company; or equal.
Quantity Text Size
2 DANGER
COMBUSTBLE LIQUID
14”W x 10”H
2 DANGER
NO SMOKING
10”W x 7”H
1 (tank label)
DIESEL 24”W x 6H
2. Danger Signage Design:
a. Size: as indicated in Schedule
b. Material: 60-mil rigid plastic, coated for weath er and vandalism protection
c. Text, format, and color:
1) Conforming to OSHA 1910.145(d), Specifications f or Accident Prevention Sign Design.
2) Text as scheduled below.
d. Provide eyelet holes at each corner for mounting .
3. Tank Label Signage:
a. Size: as indicated in Schedule
b. Material: Vinyl with adhesive backing
c. Text, format, and color:
1) Text as indicated in schedule
2) Color: white text on red background
B. Fire Equipment Location Signs:
1. One-way Fire Equipment Location Signs:
a. Manufacturer: Seton Nameplate Company; W.H. Brad y Company; or equal.
b. Size: 4-inch wide, 18-inch height (approximate s ize). c. Material: 60-mil rigid plastic, coated for weath er and vandalism protection
d. Text: Bright, fade-resistant red on white downwa rd facing directional arrow on red field. Text is shown on schedule below.
e. Schedule of signs required:
Text
Quantity
1-way 2-way 3-way
"FIRE
EXTINGUISHER”
1 ___ ___
2.02 CHEMICAL HAZARD AND HAZMAT COMMUNICATION
A. Chemical Hazard and GHS Signs
1. Pictogram Signs
a. Provide signs in ‘diamond’ configuration, black pictogram symbol, red sign border with black trim on white background in conformance with OSHA 1910.1200 of the size and quantity noted in the Table, below.
Seton L3500 series, or equal.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10400 - 3 Identifying Devices
2. NFPA Fire Hazards of Materials Signs (NFPA 704 D iamond Sign):
a. Seton Nameplate Company; W.H. Brady Company; or equal. b. Sign characteristics: Four-color background, blu e, red, yellow, white; diamond shape; 7-1/2 inches by 7-1/2 inches; 3-inch-high black hazard numerals scheduled below; conform to NFPA No. 704, Standard System for the Identification of the Hazards of Materials for Emergency Response.
c. Material: Semi-rigid plastic with adhesive back.
d. Where mounted to concrete or other porous materi als provide 3/4-inch- thick AB Marine grade Douglas Fir plywood backing, sealed edges, and painted. Eyelet holes at corners for mounting.
e. Schedule of signs required:
Quantity
Hazardous
Material
Blue
(Health)
Red
(Fire)
Yellow
(Reactivity)
White
(Specific
Hazard)
1 Diesel Fuel Oil 1 2 0 --
1 Battery Acid 3 0 1 --
PART 3 - EXECUTION
3.01 SIGN INSTALLATION
A. Install signs where directed by the Engineer.
B. Install signs after painting surfaces to receive signs. Follow manufacturer's written installation instructions.
Sign Type (product number) Symbol Material
Quantity
12”x12” 6”x6”
FLAMMABLE (Seton L3506)
Adhesive Vinyl 2 --
HEALTH HAZARD (Seton L3511)
Adhesive Vinyl 2 --
CORROSIVE (Seton L3512)
Adhesive Vinyl 2 --
HARMFUL/IRRITANT (Seton
L3509)
Adhesive Vinyl 2 --
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
10400 - 4 Identifying Devices
C. Use fasteners as follows:
1. To concrete and masonry materials: 4-1/4-inches diameter expansion anchors.
2. To sheet metal (gauges 28 to 6) #10 sheet metal screws.
3. To gypsum board: Adhesive backing tape.
4. To chain link fencing: Wire ties at each corner.
5. To plywood backing boards: #10 wood screws.
6. To machinery: Fasteners as suitable.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 1 Piping, Valves, and Accessories
SECTION 15050
PIPING, VALVES, AND ACCESSORIES
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes: Provide all piping, including fittings, valves, supports, and accessories as shown on the Drawings, described in the Specifications and as required to completely interconnect all equipment with piping for complete and operable systems, including equipment drains.
1.02 REFERENCES
A. ASTM International (ASTM)
B. American Society of Mechanical Engineers (ASME)
C. American National Standards Institute (ANSI)
D. American Water Works Association (AWWA)
E. American Welding Society (AWS)
F. U.S. Department of Transportation (DOT)
G. Manufacturers Standardization Society of the Valve and Fittings Industry (MSS)
1.03 SUBMITTALS
A. Shop Drawings:
1. Verify by excavation, inspection and measurement all installation conditions, including existing utilities and structures, for all pipe before preparation of Shop Drawings. Submit field measurements and photos with Shop Drawings where exposed conditions are significantly different than indicated on the Drawings.
2. Layouts and Schematics: Submit detailed installation drawings of all piping.
Schematics may be submitted for piping 4 inches and smaller. The Drawings and schematics shall include: pipe support locations and types, fittings, valves, other appurtenances. (Product Review)
3. Submit data to show that the following items conform to the Specification requirements:
a. Pipe, fittings and accessories (Product Review).
b. Pipe couplings and flexible pipe pieces (Product Review). c. Valves and Accessories (Product Review).
4. Pipe, fittings and joint fabrication details for shop fabricated and field-welded pipe (Product Review).
5. Submit procedures for welding shop-fabricated and field-welded joints and welder qualifications (Product Review).
6. Submit samples of gaskets and other materials where required by the detailed specifications.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 2 Piping, Valves, and Accessories
7. Submit certified test reports as required herein and by the referenced standard specifications (Product Information).
8. CitySamples: Solder and flux for copper pipe.
9. Submit leak and pressure testing plan in accordance with the requirements in
3.09. 10. Submit shop drawings for leak and pressure testing apparatus including, but not limited to, temporary bulkheads necessary for testing of new pipelines.
B. Affidavits: Furnish affidavits from the manufacturers for the following equipment:
1. Valves.
C. Field test reports as required in Part 3.
1.04 DELIVERY, HANDLING AND STORAGE
A. Exercise great care to prevent injury to or scoring of the pipe, as applicable, during handling, transportation or storage. Do not store pipe on rough ground and do not roll, drag, or otherwise handle the pipe in a manner damaging to the coating.
B. All materials delivered to the job site shall be new, free from defects, and marked to identify the material, class, and other appropriate data such as thickness for piping.
C. Store pipe so that it’s off the ground, adequately supported on suitable supports such as wooden sleepers, rubber tires or sandbags and securely blocked. Avoid compression damage or deformation to the ends.
D. Where possible, store pipe in unit packages provided by the Pipe Manufacturer.
E. Stack pipe in accordance with the Pipe Manufacturer’s recommendations.
F. Do not roll, drag, or drop pipe.
G. Store gaskets in a cool, dark place, out of direct sunlight, preferably in original cartons.
H. Damaged pipe, lining, and coatings shall be repaired or replaced at the expense of the Contractor to the City’s satisfaction.
1.05 QUALITY ASSURANCE
A. Materials and equipment under this Section shall be furnished by manufacturers regularly engaged in the design and manufacture of the materials and equipment for a period of at least 5 years.
B. Pipe installed under this contract may be inspected for compliance by the Engineer, City and/or an independent testing laboratory selected by the City.
1. Pipe rejected by the Engineer or City shall be immediately removed from the job site.
C. Acceptance of materials shall be subject to strength and quality testing in addition to inspection of the completed product. Acceptance of installed piping systems shall be based on inspection and leakage tests as specified hereinafter.
D. Factory Quality Control: The Contractor shall test all products as required herein and by the reference specifications.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 3 Piping, Valves, and Accessories
E. Field Quality Control:
1. The City will:
a. Inspect pipe fabrication and witness any test
2. The Contractor shall:
a. Perform leakage tests
b. Be responsible for the costs of additional inspection and retesting by the City resulting from noncompliance.
1.06 SHUTDOWN OF EXISTING UTILITIES, SERVICES OR OPERATIONS A. Refer to City General Provisions.
1.07 POTHOLING
A. Do not prepare shop drawings, order, or design any piping until potholing has been completed and a potholing report has been favorably reviewed in accordance with City General Provisions.
1.08 PIPING SYSTEMS
PART 2 - PRODUCTS
2.01 GENERAL
A. Pipe and valve sizes are nominal inside diameter unless otherwise noted.
B. All materials delivered to the job site shall be new, free from defects, and marked to identify the material, class, and other appropriate data such as thickness for piping.
C. Acceptance of materials shall be subject to strength and quality testing in addition to inspection of the completed product. Acceptance of installed piping systems shall be based on inspection and leakage tests as specified hereinafter.
D. Cutoff Flanges: Provide at all pipe or sleeve penetrations where cast into wall for pipes 4 inches and greater in nominal diameter, and at all penetrations of 3-inch and smaller nominal diameter pipe in wet or potentially wet locations as indicated on the Drawings. Cutoff flange shall be at least ¼ inch thick and shall be continuously welded onto the pipe.
2.02 GENERAL MATERIAL REQUIREMENTS
A. Bolts and Tie Rods: Unless specified otherwise herein, flange bolts and nuts, coupling bolts and nuts, tie rods, and other hardware shall be as follows:
1. Exposed: Carbon and Alloy Steel Nuts per ASTM A193, Grade B7.
2. Where bolts and tie rods are installed within a corrosive environment, such bolts and tie rods shall be Type 316 stainless steel per ASTM A193, Grade B8M, Class 2. The number and diameter of stainless steel tie rods shall be upsized to accommodate equivalent load ratings stated in AWWA M11.
Apply an anti-galling compound to the threads of stainless steel bolts and tie rods.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 4 Piping, Valves, and Accessories
B. All materials in contact with potable water shall comply with the Safe Drinking Water Act and NSF requirements for use in water systems.
2.03 PIPING MATERIALS
A. Pipe and Fitting Designation: Piping materials are identified by a "Type" designation in these Specifications. The "Type" designation identifies not only the pipe itself but the associated fittings and appurtenances and the installation and test procedures described for that "Type." The designation of a particular type shall indicate a complete installation including fittings, joints, cleaning and testing. The pipe and fitting materials for each type designation shall be as specified herein and summarized in the Pipe Type Schedule.
B. Pipe Type Schedule: Pipe material, joints, and fittings shall be as summarized below. A detailed specification of each pipe type follows. The detailed specification supersedes the schedule in case of any conflicts.
Pipe Type Pipe Description Field Joints Fittings
CUP Copper Solder or Flare Wrought
Copper or
Bronze
C. CUP Pipe:
1. Pipe: Copper, ASTM B88.
a. Buried: Type K (soft drawn).
b. Exposed: Type L (hard drawn).
2. Joints:
a. Buried: Soldered or flared.
b. Exposed: Soldered.
3. Solder: ASTM B32, Alloy Grade SN 94, SN 95 or SN 96. Solder and flux shall contain less than 0.2% lead.
4. Fittings:
a. Soldered: Wrought copper, ASTM B75 for materials and ANSI B16.22 for dimensions; or cast bronze, ASTM B62 for materials and ANSI B16.18 for dimensions.
b. Flared: AWWA C800 and ANSI B16.26.
2.04 VALVES AND ACCESSORIES
A. General Requirements for Valves:
1. All valves of each type shall be the product of one manufacturer.
2. All exposed valves shall be furnished with operators, handwheels, levers, or other suitable type wrench including handles as specified herein or as shown on the Drawings.
3. All threaded stem valves shall open by turning the valve stem counter- clockwise.
4. All exposed valves and valve operators shall have a non-bleeding shop coat, unless otherwise specified.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 5 Piping, Valves, and Accessories
PART 3 - EXECUTION
3.01 PIPING INSTALLATION
A. General Handling and Placing:
1. Carefully inspect each pipe, fitting, valve and accessory before installation to insure there is no defective workmanship or obstructions. Inspect the interior and exterior protective coatings and patch all damaged areas in the field or replace to the satisfaction of the Engineer.
2. Place or erect all piping to accurate line and grade and backfill, support, hang, or brace against movement as specified or shown on the Drawings, or as required for proper installation. Remove all dirt and foreign matter from the pipe interior prior to installation and thoroughly clean all joints before joining.
3. Use reducing fittings where any change in pipe size occurs. Do not use bushings unless specifically noted on the Drawings. Use eccentric reducing fittings wherever necessary to provide free drainage of lines.
4. Prevent damage to the pipe, lining and coating during handling and placement.
5. Remove all dirt and foreign matter from the pipe interior prior to installation and thoroughly clean all joints before joining.
B. General Exposed Piping Installation:
1. Unless shown otherwise, install piping parallel to building lines, plumb and level.
2. Install piping without springing or forcing the pipe in a manner that would set up stresses in the pipe, valves, or connected equipment.
3. Set all pipe flanges level, plumb, and aligned. All flanged fittings shall be true and perpendicular to the axis of the pipe. All bolt holes in flanges shall straddle vertical centerline of pipes.
C. Pipe Welding:
1. General: Unless specified otherwise, shop and field welding of pipe shall conform to ANSI B31.3 as amended by this paragraph.
2. All field and shop welding shall be done by the electric arc process unless otherwise specified. All field welding shall be done in passes not thicker than ¼-inch. Size and type of electrodes, and current and voltages used, shall be subject to the favorable review of the Engineer. Give particular attention to the alignment of edges to be joined, so that complete fusion and penetration will be effected throughout the bottom of the weld. Welds shall contain no valleys or undercuts in the center or edges of the weld. Thoroughly clean each pass, except the final one, of dirt, slag, and flux before the succeeding bead is applied.
3. Clean completed field welds of pipe joints of dirt, slag and flux, and then visually inspect. Completely chip out all defects in welds discovered during field inspection in a manner that will permit proper and complete repair by welding subject to the favorable review of the Engineer. Under no circumstances will caulking of defective welds be permitted.
4. All welding shall be done by experienced, skilled operators familiar with the methods and materials to be used. Hand welding will be done only by welders qualified under the standard qualification procedure of Section IX of the ASME Boiler and Pressure Vessel Code.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 6 Piping, Valves, and Accessories
5. Field welds shall follow as closely as possible to the laying operation. All field welds shall be complete before lining or coating of the joints in steel pipe is begun. Where pipe is fusion epoxy lined and/or coated, follow AWWA C-213 procedures for field welded joints.
6. A single, continuous, watertight, full fillet weld shall be the minimum required at all field joints. Double welded joints are required on all piping specifically noted to be double welded.
7. See also installation specifics for welding of pipe.
D. Installation Specifics:
1. CUP Pipe:
a. Bends shall be made in a manner that does not crimp or flatten pipe. b. Dielectric unions shall be installed at connections with ferrous piping. c. Pipe shall have joints squarely cut clean, soldered joints shall be properly fluxed and heated before solder is placed in the joint. Joints must be driven up tight before solder is added. Compression and flared joints shall be made up in accordance with the fitting manufacturer's installation instructions. Brazing shall be in accordance with ANSI B31.3.
d. Install piping tight to slabs, beams, joists, columns, walls, and other permanent elements of the building. Provide space to permit insulation applications, with 1-inch clearance outside the insulation. Allow sufficient space above removable ceiling panels to allow for panel removal.
e. Install drains at low points in mains, risers, and branch lines consisting of a tee fitting, ¾-inch ball valve, and short ¾-inch threaded nipple and cap.
f. Exterior Wall Penetrations: Seal pipe penetrations through exterior walls using steel sleeves and mechanical sleeve seals.
g. Fire Barrier Penetrations: Where pipes pass through fire rated walls, partitions, ceilings, and floors, maintain the fire rated integrity. h. Install branch connections to mains using tee fittings in main with take- off out the bottom of the main, except for up-feed risers, which shall have take-off out the top of the main line.
i. Install strainers on the supply side of each control valve, pressure reducing valve, pressure regulating valve, solenoid vale, inline pump, and elsewhere as indicated. Install nipple and ball valve in blowdown connection of strainers 2 inches and larger.
3.02 INSTALLATION OF VALVES AND ACCESSORIES
A. Install valves and accessories such that all parts are easily accessible for maintenance and operation.
B. Connections between ferrous and non-ferrous piping, valves, accessories or pipe supports shall be made using a dielectric coupling, union, or flange.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 7 Piping, Valves, and Accessories
3.03 PIPE AND VALVE IDENTIFICATION
A. Exposed Pipe Identification: Before painting, banding and labeling, pipes shall be identified by the Contractor with temporary wired-on cardboard tags showing the proposed marking for review by the Engineer.
3.04 FIELD QUALITY CONTROL
A. The City will:
1. Inspect field welds and test the welds if it is deemed necessary.
2. Perform bacteriological analysis for pipeline to be disinfected.
B. Factory Quality Control: The Contractor shall test all products as required herein and by the reference specifications.
C. The Contractor shall:
1. Perform leakage tests.
2. Be responsible for the costs of additional inspection and retesting by the City resulting from non-compliance.
3.05 CLEANING
A. Prior to testing, thoroughly clean the inside of each completed piping system of all dirt, loose scale, sand and other foreign material. Cleaning shall be by sweeping, flushing with water or blowing with compressed air, as appropriate for the size and type of pipe. Flushing shall achieve a velocity of at least 3 feet per second. The Contractor shall install temporary strainers, temporarily disconnect equipment, or take other appropriate measures to protect equipment while cleaning piping.
Cleaning shall be completed after any pipeline repairs.
3.06 FIELD TESTING
A. General: Perform leakage tests on all pipe installed in this project. Furnish all equipment, material, personnel and supplies to perform the tests and make all taps and other necessary temporary connections. The test pressure, allowable leakage and test medium shall be as specified and as shown in the following Paragraphs.
Test pressure shall be measured at the highest point on the line, except that pressure at lowest point shall not exceed pipe manufacturer’s rated test pressure, unless specifically noted otherwise. Leakage tests shall be performed on all piping at a time agreed upon and in the presence of the Engineer. All visible leaks shall be repaired, regardless of the test results. The Contractor may purchase water for construction, cleaning, testing, and disinfection of the pipelines from the City at a fire hydrants designated by the City. At any connection to the City water system, the Contractor shall provide an air-gap or reduced pressure backflow valve system to prevent backflow into the water source.
B. Buried Piping: The leakage test for buried piping shall be made after all pipes are installed and backfilled. However, the Contractor may conduct preliminary tests prior to backfill. If the Contractor elects to conduct preliminary tests, provide any necessary temporary thrust restraint.
C. Exposed Piping: All supports, anchors and blocks shall be installed prior to the leakage test. No temporary supports or blocking shall be installed for final test.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 8 Piping, Valves, and Accessories
D. Accessories: It shall be the responsibility of the Contractor to block off or remove valves, gauges, etc., which are not designed to withstand the full test pressure.
E. Testing Apparatus: Provide pipe taps, nozzles and connections as necessary in piping to permit testing including valves to isolate the new system, addition of test media, and draining lines and disposal of water, as is necessary. These openings shall be plugged in a manner favorably reviewed by the Engineer after use.
Provide all required temporary bulkheads.
F. Pneumatic Testing: Piping tested by air or another gas shall show no reduction of pressure during the test period after corrections have been made for changes in temperature in conformance with the following relationship:
Where T1 and T2 are the absolute temperatures of the gas in the pipe and P1 and P2 are the absolute pressures. The subscript "1" denotes the starting conditions and the subscript "2" denotes the final conditions.
G. Precautions for Pneumatic Testing: Where air or another gas is called for as the test medium, the Contractor shall take special precautions to protect personnel.
During the initial pressurization of a pipeline to the specified test pressure, personnel shall be protected by suitable barricades or shall remove themselves to locations where portions of the concrete structure itself are between them and the pipeline under test.
H. Correction of Defects: If leakage exceeds the allowable, the installation shall be repaired or replaced and leakage tests shall be repeated as necessary until conformance to the leakage test requirements specified herein have been fulfilled.
All visible leaks shall be repaired even if the pipeline passes the allowable leakage test.
I. Reports: The Contractor shall keep records of each piping test, including:
1. Description and identification of piping tested.
2. Test pressure.
3. Date of test.
4. Witnessing by Contractor and Engineer.
5. Test evaluation.
6. Remarks, to include such items as:
a. Leaks (type, location).
b. Repairs made on leaks.
7. Test reports shall be submitted to the Engineer.
J. Venting: Where not shown on the Drawings, the Contractor may install valved "tees" at high points on piping to permit venting of air. Valves shall be capped after testing is completed.
K. Testing Specifics: Piping shall be tested as indicated in the Pipe Schedule shown on the Drawings. Unless specified otherwise, test each system for 4 hours. 1122PT=PT
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 9 Piping, Valves, and Accessories
3.07 DISINFECTION OF POTABLE WATER SYSTEMS
A. See Specification 02516.
END OF SECTION
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15050 - 10 Piping, Valves, and Accessories
THIS PAGE INTENTIONALLY BLANK
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 1 Heating, Ventilating and Air
Conditioning Air Distribution
SECTION 15800
HEATING, VENTILATING AND AIR CONDITIONING AIR DISTRIBUTION PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Furnish all labor, materials, equipment, services and incidentals required to provide complete, integrated, and operating Heating, Ventilating and Air Conditioning Air Distribution Systems for the buildings and structures in the project. Materials and equipment to be supplied shall be new, of the best quality as specified and as shown on the Drawings.
2. Work Included in This Section:
a. Ductwork and accessories and duct silencers
b. Mechanical insulation.
c. Fans.
d. Vibration control.
e. Testing, adjusting, and balancing.
B. Fans, exhausters and ventilators furnished as a part of the work of this project shall comply with applicable provisions of this Section, and Schedules and Notes on Drawings.
C. All motorized equipment shall be provided with vibration control. Vibration control products furnished as integral part of facility fabricated equipment are specified as part of equipment assembly in other Division 15 sections. Types of vibration control products specified in this Section include the following:
1. Neoprene pads.
2. Vibration isolation springs.
3. Spring isolators, freestanding.
4. Flexible duct connectors.
D. Correction of Conflicts: When ductwork configurations, size, or location conflicts with other work (piping, electrical, structural, ceiling heights or doors) due to failure to coordinate duct layout with respective items, rework of other work and/or rework of ductwork to eliminate conflicts shall be provided as a part of the work of this Section, without additional cost.
E. Following definitions apply to terms as used in this Section:
1. Seams: Joining of two longitudinally (in direction of airflow) oriented edges of duct surface material occurring between two joints. All other duct surface connections made on perimeter are deemed to be joints.
2. Joints: Girth intersections of duct surface material; branch and subbranch intersections; tap-ins (duct collar, etc.)’ fitting subsections; louver and air terminal connections to ducts; access door/panel frames and jambs; duct, plenum, and casing abutments to building structure.
F. System Performance Requirements: Duct system design, as indicated, has been used to select and size air moving and distribution equipment and other components of air systems. Changes or alterations to layout or configuration of duct systems must be specifically approved by Engineer, in writing. Accompany Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 2 Heating, Ventilating and Air
Conditioning Air Distribution
requests for layout modifications with calculations showing that proposed layout will provide original design results without increasing system total pressure.
G. Application and installation provisions for ductwork hangers and supports are included in Part 3 of this Section. Duct hangers and supports are not normally shown on Drawings. However, appropriate hangers and supports shall be provided at proper intervals in compliance with provisions of this Section, with SMACNA standards and applicable code requirements.
H. Except as otherwise indicated, obtain vibration control products from single manufacturer. Engage manufacturer to provide technical supervision of installation of vibration control products.
I. Provide Project Record Documents:
1. Actual locations of ducts and duct fittings showing any additional fittings used.
2. Actual location of each assembly or accessory.
3. As-built HVAC drawings representing actual locations of ducts, fittings, and equipment.
1.02 REFERENCES
A. Standards and document references in text of this Section shall be the edition current at date project manual was issued.
1. AFBMA (Anti-Friction Bearing Manufacturers Association):
a. AFBMA Std 9 Load Ratings and Fatigue Life for Ball Bearings b. AFBMA Std 11 Load Ratings and Fatigue Life for Roller Bearings
2. AMCA (Air Movement and Control Association, Inc.)
a. AMCA 99 Standards Handbook
b. AMCA 210 Laboratory Methods of Testing Fans for Rating Purposes
c. AMCA 300 Test Code for Sound Rating Air Moving Devices d. AMCA 301 Method of Calculating Fan Sound Ratings from Laboratory Test Data
3. NEMA (National Electrical Manufacturers Association):
a. NEMA MG-1 Motors and Generators
4. American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE):
a. ASHRAE Handbook Equipment, CH Duct Construction
b. ASHRAE Handbook Fundamentals, CH Duct Design
5. American Society for Testing and Materials (ASTM):
a. ASTM A36 Standard Specification for Carbon Structural Steel b. ASTM A90 Standard Test Method for Weight of Coating on Iron and Steel Articles with Zinc or Zinc-Alloy Coatings
c. ASTM A653 Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy- Coated (Galvanized)
by the Hot-Dip Process
d. ASTM A924 Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process
e. ASTM E84 Standard Test Method for Surface Burning
Characteristics of Building Materials.
6. National Fire Protection Association (NFPA)
a. NFPA 70 National Electrical Code (NEC)
7. Sheet Metal and Air Conditioning Contractors National Association (SMACNA):
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 3 Heating, Ventilating and Air
Conditioning Air Distribution
a. SMACNA, HVAC Air Duct Leakage Test Manual
b. SMACNA, HVAC Duct Construction Standards, Metal and Flexible c. Seismic Restraint Manual: Guidelines for Mechanical Systems
8. Underwriters Laboratories, Inc. (UL):
a. UL 181, Standard for Safety, Factory-Made Air Ducts and Connectors
9. California Building Code (CBC)
10. California Mechanical Code (CMC)
1.03 SYSTEM DESCRIPTION
A. Single Source Responsibility: In general, all fans, exhausters, and ventilators shall be the products of a single manufacturer. All units of each particular type shall be the products of a single manufacturer.
1. Fabrication: Conform to AMCA 99.
2. Performance Ratings: Based on tests made in conformance with AMCA 210.
3. Sound Ratings: Determined by AMCA 301, tested per AMCA 300.
4. NEMA Compliance: Provide electric motors and components that are NEMA listed and labeled.
5. Performance and Sound Rating Certification: Manufacturers shall certify that their products comply with specified requirements.
1.04 SUBMITTALS
A. Provide shop drawings and technical literature covering all equipment and accessories being furnished under this Section. The data shall include information to demonstrate compliance with all of the requirements of these Specifications.
Submittals shall include but not be limited to the following:
1. Manufacturer’s drawings detailing equipment assemblies and indicating dimensions, weights, required clearances, components, and location of field connections.
2. Fan curves for proposed units, with system operating conditions clearly indicated.
3. Sound power ratings for both fan inlet and outlet at rated capacity.
4. Manufacturer’s installation and maintenance instructions.
5. Complete operation and maintenance (O&M) manuals shall be in accordance with the requirements of Section 01700. It shall be the responsibility of the Contractor to correct deficiencies and provide an overall system manual.
Manuals shall consist of a set of documents containing, but not limited to, the following:
a. A detailed description, both physical and functional, of all devices, including equipment operation.
b. Preventive maintenance instructions.
c. Preventive maintenance shall include instructions for lubrication, motor and drive replacement, spare parts list, schematics, logic, and timing diagrams and wiring diagrams.
d. Corrective maintenance instructions including diagnostic exercises, troubleshooting guides, repair procedures, removal and replacement, and assembly and disassembly instructions. Include drawings of block diagrams, schematics, wiring diagrams, logic and timing diagrams. e. A complete parts list, cross-references, if necessary, to standard component numbers.
6. Motor ratings and electrical characteristics, plus motor and fan accessories.
7. Manufacturer’s product certification, where applicable.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 4 Heating, Ventilating and Air
Conditioning Air Distribution
8. Submit product data for insulation, jackets, coverings, adhesives, sealants, cements and other materials being installed on this project. List materials and thickness for each service application.
a. Provide shop and installation drawings of field fabricated covers. b. Submit samples of products, if requested.
9. Submit product descriptive data for flexible connection materials, sealing materials, access door, duct liner, flexible ducting and factory-fabricated devices.
B. Manuals: Furnish manufacturer's installation, lubrication and maintenance manuals, bulletins and parts lists. Furnish separate list of recommended spare parts, motor and drive replacement part numbers, service depot location and telephone number.
C. Affidavits: Furnish affidavits from the manufacturers stating that the equipment has been properly installed and tested and each is ready for full time operation.
D. One copy of all submittals and construction documents shall be maintained on the construction site.
1.05 QUALITY ASSURANCE
A. Codes: Comply with all rules and regulations of authorities having jurisdiction over the work specified herein.
B. Permits and inspection shall be in accordance with Division 1 of these Specifications.
C. All equipment furnished under this Section shall: (1) be of a design and manufacturer who has been regularly engaged in the design and manufacture of the equipment for a minimum of 3 years; and (2) be demonstrated to the satisfaction of the Engineer that the quality is equal to equipment made by those manufacturers specifically named herein.
D. The Installer shall be a company specializing in performing the work of this Section with a minimum of 3 years of documented experience.
E. The Drawings shall be taken in a sense as diagrammatic. Size of ducts and pipes including general method of running them are shown, but it is not intended to show every offset and fitting nor every structural difficulty that may be encountered.
F. Ductwork construction and air system performance shall be in accordance with:
1. CMC.
2. ASHRAE Handbook Equipment, Chapter 1.
3. ASHRAE Handbook Fundamentals, Chapter 32.
4. SMACNA HVAC Duct Construction Standards, Metal, and Flexible.
G. Provide hangers and support in accordance with SMACNA HVAC Duct Construction Standards:
1. Hangers and support devices shall be designed, suitable, and appropriate for respective application, installed in compliance with product manufacturer’s recommendations.
2. Comply with guidelines for SMACNA seismic restraint manual requirements.
H. Insulation:
1. Applicator: A company specializing in, and experienced in, mechanical equipment and system insulation application.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 5 Heating, Ventilating and Air
Conditioning Air Distribution
2. Fire performance characteristics: Insulation, facings, cements, and adhesives shall have 25/50 maximum flame spread/smoke developed rating in accordance with ASTM E84, except insulation outside may be rated 75/150 maximum. Insulation shall be tested by and bear label of U.L. or other testing organization acceptable to authority having jurisdiction.
I. Design and Performance Requirements:
1. Design Criteria: Drawings indicate sizes, profiles, connections, and dimensional requirements of fans, exhausters, and ventilators, based on referenced products. Products having equivalent performance characteristics by other manufacturers may be considered, provided deviations in dimensions, profiles and efficiencies are suitable for the application and do not change the design concept access, service requirements, or intended performance as judged by the Engineer.
2. Furnished Fans: Capable of accommodating static pressure variations of plus or minus 10% shall have performance that does not vary from specified criteria more than the following:
a. Not have decreased motor size, or increased noise level. b. Not have tip speed increased by more than 20%.
c. Not have inlet air velocity increased by more than 20%.
3. Type, Size, Performance, Characteristics, Arrangement, Accessories: As scheduled or noted on Drawings for respective application; acceptable equivalent to products referenced on Drawings.
4. Fans and Shafts: Statically and dynamically balanced and designed for continuous operation at maximum rated fan speed and motor horsepower.
5. Motors: Comply with applicable general provisions of Section 16050:
a. Designed for continuous operation in 40°C environment. b. For temperature rise in accordance with NEMA MG-1 limits for insulation class, service factor, and motor enclosure type. c. Type specified, scheduled or noted for respective units. d. Open drip proof type, except where specifically specified or noted otherwise for respective fans.
6. Provide ductwork and equipment supports, hangers, guides and anchors as on the Drawings, and as specified herein. When standard hangers, supports, and accessories are not adequate the Contractor shall employ a California registered Structural Engineer to prepare design calculations for all such supports, hangers and accessories for seismic restraint needed for the ductwork and equipment installation. Calculations and shop drawings shall be signed by the above named engineer and submitted to the Engineer.
9. Disconnect Switch: Nonfusible type, with thermal overload protection, unless indicated otherwise for a particular unit.
1.06 SEISMIC PROTECTION
A. Equipment specified in this Section is classified as essential for seismic protection.
See Section 01190 for seismic requirements.
B. Seismic Restraints: All ductwork and piping shall be provided with seismic restraint in accordance with Seismic Hazard Level (SHL) “A” of the Seismic Restraint Manual: Guideline For Mechanical Systems, as published by SMACNA and in accordance with Section 01190.
Job No. 2244100*02
City of Carlsbad
Poinsettia Lift Station Generator
Replacement Project
15800 - 6 Heating, Ventilating and Air
Conditioning Air Distribution
1.07 DELIVERY, STORAGE AND HANDLING
A. The Contractor shall make his own provisions for properly storing and protecting all material and equipment against theft, injury, or damage from any and all causes.
Damaged material and equipment shall not be used in the work.
B. Protect motors, shafts, and bearings from weather and construction dust.
C. If units must be stored outside for a prolonged period, remove motors and belts and store them inside a weathertight structure.
D. Deliver sealants used for ductwork in original unopened containers, clearly labeled with product description and identification. Labeling shall include expiration date for use, pot life, curing time, and mixing instructions when applicable. Store and handle per manufacturer’s instructions.
PART 2 - PRODUCTS
2.01 GENERAL
A. Similar to items of equipment specified herein shall be the end product of one manufacturer.
B. Specific information relative to the various equipment, including identification numbers, capacities, horsepower, and other information shall be as listed on the Drawings.
C. All rooftop unit supply and return ductwork shall be acoustically lined.
2.02 DUCTWORK AND ACCESSORIES
A. Ductwork: Unless otherwise indicated, ductwork shall be galvanized steel.
1. Ductwork shall be of lock forming quality, ASTM A653 and ASTM A924, coating designation G90. Zinc coating in accordance with ASTM A90.
Provide mill phosphatized finish for exposed surfaces of ducts exposed to view.
a. Carbon steel sheets: ASTM A366, cold-rolled sheets, commercial quality, oiled exposed matte finish.
b. Reinforcements shapes and plates: Unless indicated otherwise, galvanized steel where installed on galvanized sheet metal duct.