2025-09-09; City Council; 05; Adoption of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble

Carlsbad City Council
September 9, 2025

Document
2025-09-09; City Council; 05; Adoption of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble
Meeting
September 9, 2025
Body
Carlsbad City Council
Pages
286
Original file
765 KB
Text extracted from the city's file for reading and search. Open the original on records.carlsbadca.gov. That file is the official record.

CA Review TL
Meeting Date: Sept. 9, 2025
To: Mayor and City Council
From: Geoff Patnoe, City Manager
Staff Contact: Brandon Miles, Associate Engineer
[email protected], 442-339-2745
Subject: Adoption of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble Project
District: 2
Reco
mmended Action
Adopt a resolution adopting the plans, specifications and contract documents and authorizing the City Clerk to advertise for bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble Project.

Ex
ecutive Summary
This project, Capital Improvement Program Project No. 6072, will widen the northbound segment of El Camino Real from Poinsettia Lane to Camino Vida Roble and add a third vehicle lane, consistent with the city’s design standards and the city’s General Plan and Growth Management Plan. The project also includes new sidewalks, a landscaped median, streetlights and enhanced buffered bike lanes.

The city received authorization to proceed with construction from the California Department of Transportation on July 17, 2025, which allows the city to use approximately $1.44 million of federal grant funding for the project. The next step is to advertise for construction bids.

The estimated construction cost including contingency, construction management and inspection, public outreach, and engineering and administration is $3,493,521. The City Council’s adoption of these plans, specifications and contract documents is required under Carlsbad Municipal Code Section 3.28.080(E) because the expected value of the work exceeds $220,000.

Staff recommend that the City Council adopt the plans, specifications and contract documents and authorize the City Clerk to advertise for construction bids for the project.

Sept. 9, 2025
Item #5 Page 1 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Explanation & Analysis
This project will widen northbound El
Camino Real for approximately 1,500 feet
from Cinnabar Way to Camino Vida Roble
and restripe the northbound segment of El
Camino Real from Poinsettia Lane to Camino
Vida Roble to add a third vehicle through
lane, improve bicycle lanes, curbs, gutters
and sidewalks to current city standards.

The project supports the city’s efforts to
improve traffic safety while improving
circulation and mobility for people using all
forms of transportation by constructing:
• New sidewalk consistent with the
Americans with Disabilities Act, or
ADA
• Enhanced bike lanes with painted
buffers
• Restriped vehicular lanes to provide
three northbound lanes from Cassia
Road to Camino Vida Roble
• A new landscaped median
Staff presented this project to the Traffic Safety & Mobility Commission (formerly known as the Traffic & Mobility Commission), the Planning Commission and the City Council, as outlined below:

Nov. 2, 2020 – The Traffic & Mobility Commission voted to support staff’s recommendation to implement the project because it will provide operational improvements consistent with the city’s General Plan Mobility Element. Staff received and noted comments from the commission on the improvement plans. The approved minutes of the meeting are included as Exhibit 2.

June 1, 2022 – The Planning Commission recommended that the City Council approve a coastal development permit, special use permit - floodplain, and habitat management plan for the project. (These permits and plans have been approved as CDP 2020-0032, SUP 2020-0003, and HMP 2020-0007, respectively.) The approved minutes of the meeting are included as Exhibit 3.

Oct. 3, 2022 – The Traffic & Mobility Commission voted to support staff’s recommendation to adopt the plans, specifications and contract documents. The approved minutes of the meeting are included as Exhibit 4.

Nov. 15, 2022 – The City Council adopted Resolution No. 2022-259, shown in Exhibit 5, authorizing city staff and its consultant to negotiate with the owners of assessor parcel number (APN) 213-050-16, or their agents, for acquisition of real property and a temporary construction easement giving the city access it needs to complete the project.

The project area. (Exhibit 9 is a more detailed project map.)
Sept. 9, 2025
Item #5 Page 2 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1

July 25, 2023 – The City Council adopted Resolution No. 2023-209, shown in Exhibit 6, accepting a grant deed and a temporary construction easement with the owners of APN 213-050-16-00 and authorizing the City Manager to execute a joint use agreement and consent agreement and covenant with San Diego Gas & Electric that is needed for utilities and the road widening.

May 6, 2024 – The Traffic Safety & Mobility Commission voted to support staff’s recommendation to adopt the plans, specifications and contract documents for the project. The approved minutes of the meeting are included as Exhibit 7.

Fiscal Analysis
Project funding has been appropriated from TransNet funds1 and approximately $1.44 million from federal earmark funds. The available funds and estimated costs for the project are shown in the following table:

Environmental Evaluation
In accordance with the California Environmental Quality Act and the Environmental Protection Ordinance (Title 19) of the Carlsbad Municipal Code, staff conducted an environmental impact assessment (an initial study) for the project. Project details, including analysis of potential environmental impacts, were described in the assessment. The Planning Commission reviewed and adopted the final mitigated negative declaration, initial study, and mitigation monitoring and reporting program for the proposed transportation improvements on June 1, 2022 (Planning Commission Resolution No. 7450).

The project is exempt from the National Environmental Policy Act review as outlined in the National Environmental Policy Act Regulation 23, which applies to federally funded projects receiving less than $5 million or with a total estimated cost of not more than $30 million.

Caltrans’ determination of exclusion is recorded in a categorical exclusion determination form dated June 28, 2022. Additionally, the categorical exclusion determination was revalidated by Caltrans on May 13, 2024, and May 27, 2025, to verify the environmental documents and decisions remained valid.

El Camino Real Widening from Poinsettia Lane to Camino Vida Roble Project Capital Improvement Program Project No. 6072
Total appropriated TransNet and federal funds to date $4,595,000 Total expenditures and encumbrances to date -$953,050
Total available funding $3,641,950
Construction contract (engineer’s estimate) -$2,293,521 Construction contingency (estimated) -$550,000
Construction management, inspection, material testing and support services (estimated) -$650,000
Total estimated construction costs -$3,493,521
Remaining balance $148,429
Additional appropriation needed $0
Sept. 9, 2025
Item #5 Page 3 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1

Next Steps
With the City Council’s approval, the City Clerk will advertise a request for bids to construct the project improvements. Staff will evaluate the bids received and identify the lowest responsive and responsible bidder. Staff will then return to the City Council with a recommendation to award a construction contract to the identified bidder, which is expected to be in late 2025.

The construction contract documents for the project provide for 12 months to complete the improvements. Construction is expected to begin in early 2026 and be completed by early 2027.
1 TransNet is a countywide sales tax collected to fund regional transportation projects.

Exhibits

1. City Council resolution

2. Minutes from Nov. 2, 2020, Traffic and Mobility Commission meeting (on file in the Office of the City Clerk)

3. Minutes from June 1, 2022, Planning Commission meeting (on file in the Office of the City Clerk)

4. Minutes from Oct. 3, 2022, Traffic and Mobility Commission meeting (on file in the Office of the City Clerk)

5. City Council Resolution No. 2022-259 (on file in the Office of the City Clerk)

6. City Council Resolution No. 2023-209 (on file in the Office of the City Clerk)

7. Minutes from May 6, 2024, Traffic Safety & Mobility Commission meeting (on file in the Office of the City Clerk)

8. Plans, specifications, and contract documents (on file in the Office of the City Clerk)

9. Location map

Sept. 9, 2025
Item #5 Page 4 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 1
RESOLUTION NO. 2025-197
A RE

SOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,

CALIFORNIA, ADOPTING THE PLANS, SPECIFICATIONS AND CONTRACT

DOCUMENTS AND AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS

FOR THE EL CAMINO REAL WIDENING FROM POINSETTIA LANE TO CAMINO

VIDA ROBLE PROJECT
WHE
REAS, the City Council of the City of Carlsbad, California has determined it necessary, desirable and in the public interest to widen and restripe El Camino Real from Poinsettia Lane to Camino Vida Roble, Capital Improvement Program, or CIP, Project No. 6072, or Project; and WHEREAS, in keeping with the city’s General Plan Mobility Element and Growth Management Plan, the P roject will widen and restripe the northbound segment of El Camino Real from Poinsettia Lane to Camino Vida Roble to add a third vehicular through lane; and WHEREAS, on Nov. 15, 2022, the City Council adopted Resolution No. 2022-259, authorizing city staff and its consultant to negotiate with the owners of Assessor Parcel Number, or APN, 213 -050-16 or their agents, for acquisition of real property and a temporary construction easement for the Project; and
WHE
REAS, on July 25, 2023, the City Council adopted Resolution No. 2023 -209, accepting a grant deed and a temporary construction easement with the owners of A PN 213-050-16-00 and authorizing the City Manager to execute a joint use agreement and consent agreement and covenant with San Diego Gas & Electric for the Project; and
WHEREAS, on July 17, 2025, the California Department of Transportation, or Caltrans, issued the Authorization to Proceed with Construction, which authorizes the city to utilize $1.44 million of federal earmark funds and proceed with the construction phase of the Project that begins with advertising for construction bids; and
WHEREAS, the plans, specifications, and contract documents for the Project have been prepared, are on file at the City Clerk’s office and are incorporated herein by reference; and WHEREAS, Carlsbad Municipal Code Section 3.28.080 (E) requires the City Council to adopt plans, specifications and contract documents for all construction projects that are to be formally bid upon when the value exceeds $220,000; and
WHEREAS, the cost of the Project is estimated to be $3,493,521, which includes a construction contingency and construction management and inspection costs; and Sept. 9, 2025
Item #5 Page 5 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 W HEREAS, in addition to $1.44 million of federal grant funding, sufficient funding from TransNet local funds is available to complete the Project.

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows:

1. That the above recitations are true and correct.

2. That the City Council has determined that consistent with the California Environmental Quality Act and the Environmental Protection Ordinance (Title 19) of the Carlsbad Municipal Code, staff conducted an environmental impact assessment for the P roject, including an analysis of potential environmental impacts. The Planning Commission reviewed and adopted the final mitigated negative declaration, initial study, and mitigation monitoring and reporting program for the proposed transportation improvements on June 1, 2022 (Planning Commission Res olution No. 7450), and the proposed acquisitions are consistent with the findings and mitigation measures included and adopted as part of that document.

3. That the City Council has determined that the Project is exempt from the National Environmental Policy Act, or NEPA, review pursuant to NEPA Regulations 23 CFR 771.117(c): activity (c)(23) - federally funded projects receiving less than $5 million or with a total estimated cost of not more than $30 million and the California Department of Transportation's determination of exclusion is recorded in a categorical exclusion determination form dated June 28, 2022.

Additionally, the categorical exclusion
determination was revalidated on May 13, 2024, and May 27, 2025, to verify the environmental documents and decisions remained valid.

4. That the plans, specifications and contract documents for El Camino Real Widening from Poinsettia Lane to Camino Vida Roble, CIP Project No. 6072, are hereby adopted.

5. That the City Clerk is authorized and directed to publish in accordance with state law, a Notice to Contractors Inviting Bids for construction of the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble Project, CIP Project No. 6072, in accordance with the plans, specifications and contract documents referred to herein.

Sept. 9, 2025
Item #5 Page 6 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of t he City of
Carlsbad on the 9th day of September, 2025, by the following vote, to wit:

AYES: Bhat-Patel, Acosta, Burkholder, Shin.

N
AYS:

ABSTAIN:

ABSENT:

None.

Blackburn.

None.
______________________________________
KEITH BLACKBURN, Mayor
______________________________________
SHERRY FREISINGER, City Clerk
(SEAL)
Sept. 9, 2025
Item #5 Page 7 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1

Exhibit 2

Minutes from Nov. 2, 2020, Traffic and Mobility
Commission meeting
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 8 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 3

Minutes from June 1, 2022, Planning Commission
meeting
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 9 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 4

Minutes from Oct. 3, 2022, Traffic and Mobility
Commission meeting
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 10 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 5

City Council Resolution No. 2022-259
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 11 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 6

City Council Resolution No. 2023-209
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 12 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 7

Minutes from May 6, 2024, Traffic Safety & Mobility
Commission meeting
(on file in the Office of the City Clerk)

Sept. 9, 2025
Item #5 Page 13 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1 Exhibit 8
Pl
ans, specifications and contract documents
(on file in the Office of the City Clerk)
Sept. 9, 2025
Item #5 Page 14 of 15
Docusign Envelope ID: 9F52BD35-0DDA-4261-922C-D7545BF15FA1

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

City of Carlsbad

CONTRACT DOCUMENTS
FOR:

El Camino Real Widening from Poinsettia Lane to Camino Vida Roble FERPL-5308(021) FUNDED PROJECT
Project No. 6072
<INSERT CONTRACT NUMBER>

THIS PROJECT IS A FEDERAL PREVAILING WAGE JOB
Federal Wage Determination Applies

THIS CONTRACT WILL BE SUBJECT TO THE FOLLOWING:
o PREVAILING WAGE RATES: STATE
o FEDERAL TRAINEE REQUIREMENT OF (4) FOUR
o APPRENTICESHIP
o CALTRANS DIVISION OF LOCAL ASSISTANCE (DLA)
o LOCAL ASSISTANCE PROCEDURES MANUAL (LAPM)

1635 Faraday Ave, Carlsbad, CA 92008
Email: [email protected]

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023
Table of Contents
SECTION 1 .................................................................................................................................... 1 00 11 10 NOTICE INVITING BIDS .................................................................................................. 1

1. RECEIPT OF BIDS. ................................................................................................................. 1

2. DESCRIPTION OF WORK. ...................................................................................................... 1

3. COMPLETION OF WORK. ..................................................................................................... 1

4. OPENING AND AWARD OF BIDS. ......................................................................................... 1

5. PERIOD FOR AWARD. ........................................................................................................... 1

6. BIDDER QUALIFICATIONS..................................................................................................... 1

7. PRE-BID CONFERENCE. ........................................................................................................ 2

8. OBTAINING CONTRACT DOCUMENTS. ................................................................................ 2

9. BID GUARANTEE AND BONDS. ............................................................................................ 2

10. CALIFORNIA AIR RESOURCES BOARD ADVANCED CLEAN FLEETS REGULATIONS. ............ 3

11. PREVAILING WAGE RATES AND LABOR COMPLIANCE. ..................................................... 3

12. PROJECT ADMINISTRATION/QUESTIONS. ......................................................................... 3 00 21 10 INSTRUCTIONS TO BIDDERS .......................................................................................... 4

1. SECURING CONTRACT DOCUMENTS. .................................................................................. 4

2. EXAMINATION OF SITE AND CONTRACT DOCUMENTS. ...................................................... 4

3. INTERPRETATION OF DRAWINGS AND DOCUMENTS. ........................................................ 4

4. QUESTIONS. ......................................................................................................................... 5

5. PRE-BID CONFERENCE. ........................................................................................................ 5

6. ADDENDA. ............................................................................................................................ 6

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

7. ALTERNATE BIDS. ................................................................................................................. 6

8. COMPLETION OF BID FORMS. ............................................................................................. 6

9. GOVERNING GENERAL PROVISIONS. ................................................................................... 7

10. MODIFICATIONS OF BIDS. .................................................................................................. 7

11. BID GUARANTEE. ............................................................................................................... 8

12. LABOR & MATERIAL BOND AND PERFORMANCE & WARRANTY BOND REQUIREMENTS. 8

13. SUBSTITUTION OF SECURITY. ............................................................................................ 9

14. OPTIONAL ESCROW FOR SECURITY DEPOSIT. ................................................................... 9

15. INSURANCE REQUIREMENTS. ............................................................................................ 9

16. LICENSING REQUIREMENTS. ............................................................................................ 10

17. SUBCONTRACTORS. ......................................................................................................... 10

18. BIDDER INFORMATION AND EXPERIENCE FORM. ........................................................... 11

19. NON-COLLUSION AFFIDAVIT. .......................................................................................... 12

20. IRAN CONTRACTING ACT OF 2010. .................................................................................. 12

21. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION. ..................................... 12

22. PREVAILING WAGES. ........................................................................................................ 13

23. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS. ............................................ 13

24. SIGNING OF BIDS. ............................................................................................................ 13

25. SUBMISSION OF SEALED BIDS. ........................................................................................ 14

26. OPENING OF BIDS. ........................................................................................................... 14

27. WITHDRAWAL OF BID. ..................................................................................................... 15

28. BIDDERS INTERESTED IN MORE THAN ONE BID. ............................................................. 15

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

29. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES, AND FEES. ........................ 15

30. PERMIT AND INSPECTION FEE ALLOWANCE. .................................................................. 15

31. BASIS OF AWARD; BALANCED BID. .................................................................................. 16

32. AWARD PROCESS. ............................................................................................................ 16

33. EXECUTION OF CONTRACT. ............................................................................................. 16

34. BUSINESS LICENSE ........................................................................................................... 16

35. PARTICIPATION OF MINORITY AND WOMEN-OWNED BUSINESSES. .............................. 16

36. USE OF RECYCLED MATERIALS ......................................................................................... 17

37. STATUTORY REFERENCES ................................................................................................ 17 00 41 00 BID FORM .................................................................................................................... 18

1. BID SCHEDULE ................................................................................................................ 19

2. TOTAL BID PRICE ............................................................................................................ 20

3. RECITALS ........................................................................................................................ 21 00 43 10 BID BOND FORM ......................................................................................................... 27 00 43 20 BID SECURITY............................................................................................................... 29 00 43 30 PROPOSED SUBCONTRACTORS FORM ........................................................................ 30 00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM ....................................................... 32

1. INFORMATION ABOUT BIDDER ...................................................................................... 32

2. LIST OF CURRENT PROJECTS (BACKLOG) ....................................................................... 34

3. VERIFICATION AND EXECUTION ..................................................................................... 38 00 45 10 NON-COLLUSION AFFIDAVIT ....................................................................................... 39 00 45 15 IRAN CONTRACTING ACT CERTIFICATION ................................................................... 40

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023
00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION .................................. 41 00 45 25 CERTIFICATE OF INSURANCE ....................................................................................... 42 00 45 30 STATEMENT REGARDING DEBARMENT ...................................................................... 43 00 45 35 DISCLOSURE OF DISCIPLINE RECORD .......................................................................... 44 00 52 00 CONTRACT ................................................................................................................... 46 00 61 10 LABOR AND MATERIALS BOND ................................................................................... 50 00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND .................................................... 54 00 61 30 OPTIONAL ESCROW AGREEMENT ............................................................................... 58 00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS ....................................................... 62 INTRODUCTION ..................................................................................................................... 62 00 74 00 AGENCY SUPPLEMENTAL PROVISIONS TO GREENBOOK .......................................... 177 INTRODUCTION ................................................................................................................... 177 PART 2 CONSTRUCTION MATERIALS ................................................................................... 178 PART 3 CONSTRUCTION METHODS ..................................................................................... 210 PART 4 EXISTING IMPROVEMENTS ...................................................................................... 223 PART 5 PIPELINE SYSTEM REHABILITATION......................................................................... 229 PART 6 TEMPORARY TRAFFIC CONTROL ............................................................................. 240 PART 7 STREET LIGHTING AND TRAFFIC SIGNALS ............................................................... 241 PART 8 LANDSCAPING AND IRRIGATION ............................................................................. 255 SECTION 2 ................................................................................................................................ 286 01 11 00 SUMMARY OF WORK ................................................................................................ 286 PART 1 GENERAL .................................................................................................................. 286

TABLE OF CONTENTS Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

APPENDICES

Appendix A – Vallecitos Water District Technical Specifications ............................................... 287 Appendix B – Grant Deed and Temporary Construction Easement .......................................... 287 Appendix C – Geotechnical Investigation Report Prepared by Earth Mechanics, Inc. .............. 287 Appendix D – Storm Water Quality Technical Memo ................................................................. 287 Appendix E – Resident Notification Example .............................................................................. 287 Appendix F – CALTRANS Local Area Procedures Manual Exhibit 12-G ....................................... 287 Appendix G – FHWA 1273 ........................................................................................................... 287 Appendix H – CARB Fleet Compliance Certification ................................................................... 287

00 11 10 NOTICE INVITING BIDS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 1 of 284 ends

SECTION 1
00 11 10 NOTICE INVITING BIDS

1. RECEIPT OF BIDS.

The City of Carlsbad / Carlsbad Municipal Water District (“Agency”) will accept Bids via electronic format via the City of Carlsbad Electronic Bidding Site up to and no later than <insert Date and Time> through the online bidding portal ( Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov)) for the construction of the Work entitled:

El Camino Real Widening From Poinsettia Lane to Camino Vida Roble <insert contract number>
Project No. 6072

2. DESCRIPTION OF WORK.

The Work includes the provision of all equipment, labor, materials, tools, services, transportation, permits, utilities, and all other items necessary to complete the construction of the following, as specified and shown in the Construction Documents: widen northbound El Camino Real for approximately 1,400 linear feet with adjacent curb, gutter, and sidewalk between Cinnabar Way and Camino Vida Roble, which includes median improvements.

The Work Site is located in the City of Carlsbad, in the County of San Diego, California.

3. COMPLETION OF WORK.

The Contract Time is established as two hundred sixty (260) Days. The Contract Time shall begin on the date of receipt of the Notice to Proceed. The Engineers’ estimate for this Project is $2,085,019.00.

4. OPENING AND AWARD OF BIDS.

Agency shall consider awarding the Contract for the Project to the lowest, responsive, responsible Bidder as determined by the Agency from the base Bid alone. The Agency has the right to reject any or all Bids or to waive any irregularities or informalities in any Bids or in the Bidding process.

5. PERIOD FOR AWARD.

A period of ninety (90) Calendar Days from the time of Bid opening may be required to award the Contract. No Bidder may withdraw its Bid or Bid G uarantee during this period. Bidders shall assume full responsibility for their Bid Price during this period and shall make certain that such delay does not restrict the Bid Guarantee.

6. BIDDER QUALIFICATIONS.

Bidders shall be licensed contractors pursuant to Business and Professions Code Sections 7000 et seq. under the classification of A – General Engineering as of the date of submittal of the Bid

00 11 10 NOTICE INVITING BIDS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 2 of 284 ends

Documents and shall maintain such license until final acceptance of the Work. Additional qualifications are included in the Contract Documents.

7. PRE-BID CONFERENCE.

The Agency will not conduct a pre-Bid Conference

8. OBTAINING CONTRACT DOCUMENTS.

Bidders may obtain a copy of the Contract Documents from Agency’s website (Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) ). To the extent required by Public Contract Code Section 20103.7, upon request from a contractor plan room service, the Agency shall provide an electronic copy of the Contract Documents at no charge to the contractor plan room. It is the responsibility of each prospective Bidder to download and print all Bid Documents for review and to verify the completeness of Bid Documents before submitting a Bid. All Addenda will be posted on the online bidding portal. It is the responsibility of each prospective Bidder to check the online bidding portal on a daily basis through the close of the bidding period for any applicable Addenda.

The Agency does not assume any liability or responsibility for any defective or incomplete copying, excerpting, scanning, faxing, downloading or printing of the Bid Documents. Information on the online bidding portal may change without notice to prospective Bidders. The Contract Documents shall supersede any information posted or transmitted by the online bidding portal.

No time extensions or other consideration will be given for non- receipt or other circumstance associated with the review or acquisition of Contract Documents. Bids must be submitted on the Agency’s Bid Forms in the Contract Documents.

9. BID GUARANTEE AND BONDS.

Each Bid shall be accompanied by cash, a certified or cashier’s check or Bid Bond secured from a surety company satisfactory to the Agency, the amount of which shall not be less than 10% of the submitted Total Bid Price, made payable to the Agency as bid security. The bid security shall be provided as a guarantee that within 10 Working Days after the Agency provides the successful bidder the Notice of Award, the successful Bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful Bidder fails to comply within these 10 Working Days. No interest will be paid on funds deposited with the Agency.

All Bidders must upload Bidder’s Bond to the online bidding portal. The original Bid Bond for the 3 apparent low Bidders must be submitted to the city within 2 Business Days of Bid opening.

The successful Bidder will be required to furnish a Faithful Performance Bond and a Labor and Material Bond each in an amount equal to 100% of the Contract Price. Each bond shall be in the forms set forth in the Contract Documents, shall be secured from a surety company that meets all State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer. Pursuant to Public Contract Code Section 22300, the successful Bidder may substitute certain securities for funds withheld by Agency to ensure its performance under the Contract.

00 11 10 NOTICE INVITING BIDS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 3 of 284 ends

10. PREVAILING WAGE RATES AND LABOR COMPLIANCE.

This Project is subject to prevailing wages and labor compliance per the Labor Code. To this end, Bidder shall sign and submit with its Bid the California Department of Industrial Relations (DIR) Public Works Contractor Registration Certification on the form 00 45 00 provided. Failure to submit this form may render the bid non- responsive. In addition, each Bidder shall provide the registration number for each listed S ubcontractor in the space provided in the Proposed Subcontractors form. In bidding this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this Contract and applicable law in its Bid. A copy of the prevailing wage rates may be obtained via the internet at: www.dir.ca.gov/dlsr/.

11. CALIFORNIA AIR RESOURCES BOARD ADVANCED CLEAN FLEETS REGULATIONS Contractor’s vehicles with a gross vehicle weight rating greater than 8,500 lbs. and light-duty package delivery vehicles operated in California may be subject to the California Air Resources Board (CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, please see Attachment E and visit the CARB Advanced Clean Fleets webpage at https://ww2.arb.ca.gov/our- work/programs/advanced-clean-fleets.

11. PROJECT ADMINISTRATION/QUESTIONS.

Requests for Information (RFI) or interpretations of Bid Documents during the bid period shall be submitted via Online Q&A in the online bidding portal.

The cutoff date and time to submit questions or substitution request regarding this Project via Online Q&A in the online bidding portal is ENTER DATE, at TIME. No questions will be entertained after that date.

The answers to questions submitted during the bidding period will be published in an addendum and provide to those bidding on the Project no later than DATE.

For further information, see the online bidding portal.

END OF SECTION

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 4 of 284 ends

00 21 10 INSTRUCTIONS TO BIDDERS

1. SECURING CONTRACT DOCUMENTS.

Bids must be submitted to the Agency on the Bid Forms which are a part of the Contract Documents for the Project. The Contract Documents may be obtained from the Agency’s online bidding portal (Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) ). Prospective bidders are encouraged to communicate with the Agency well in advance of the date and time bids are due to the Agency (“Bid Submission Deadline”) to determine the availability of Contract Documents.

The Agency may also make the Contract Documents available for review at one or more plan rooms. Prospective Bidders who choose to review the Contract Documents at a plan room must contact the Agency to obtain the required Contract Documents if they decide to submit a Bid for the Project.

Addenda will be posted on the online bidding portal . Failure to acknowledge all A ddenda may make a Bid nonresponsive and ineligible for award of the Contract. Bidders are advised to verify the issuance of all A ddenda and receipt of them 1 Working D ay prior to bidding. Failure to acknowledge all Addenda may make a Bid nonresponsive and ineligible for award of the Contract.

2. EXAMINATION OF SITE AND CONTRACT DOCUMENTS.

At its own expense and before submitting its Bid, each Bidder shall visit the Site of the proposed Work and fully acquaint itself with the conditions relating to the construction and labor required so that the Bidder may fully understand the Work, including but not limited to, difficulties and restrictions attending the execution of the Work under the Contract. Each Bidder shall carefully examine the Drawings, and shall read the Specifications, Contract Documents, and all other referenced documents. Each Bidder shall also determine the local conditions which may in any way affect the performance of the Work, including local tax structure, contractors’ licensing requirements, availability of required insurance, the prevailing wages and other relevant cost factors. Each Bidder shall also familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the Work, including the cost of permits and licenses required for the Work, and shall make such surveys and investigations, including investigations of subsurface or latent physical conditions at the S ite or where Work is to be performed as may be required. Bidders are responsible for consulting the standards referenced in the Contract. The failure or omission of any Bidder to receive or examine any contract documents, forms, instruments, addenda, or other documents, or to visit the S ite and acquaint itself with conditions there existing shall in no way relieve any Bidder from any obligation with respect to its Bid or to the Contract and no relief for error or omission will be given except as required under California law. The submission of a Bid shall be taken as conclusive evidence of compliance with this Section.

3. INTERPRETATION OF DRAWINGS AND DOCUMENTS.

Prospective Bidders unclear as to the true meaning of any part of the Drawings, Specifications or other parts of the Contract Documents, or discrepancies in or omissions from the Drawings and

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 5 of 284 ends

Specifications, may promptly submit a written request for information, interpretation, clarification, or correction (“RFI”) to the Bid Administrator, the Agencies designated representative for soliciting and conducting bids on the Agencies online ebidding portal. (defined below). The Agency may not respond to RFIs submitted past the Q&A Submission Deadline. The Bidder submitting the RFI is responsible for prompt delivery to the Bid Administrator.

Responses to RFIs will be made only by duly issued written Addenda. The Agency shall not provide verbal responses to RFIs. Copies of written Addenda will be posted on the online bidding portal for each prospective Bidder who has downloaded a set of Contract Documents. The Agency will not be responsible for any other explanation or interpretations of the Drawings, Specifications or other parts of the Contract Documents. If any Prospective Bidder becomes aware of any errors or omissions in any part of the Contract Documents, the Prospective Bidder must promptly notify the Agency of such error or omission.

Before award of the Contract, no addition to, modification of, or interpretation of any provision in the Contract Documents will be given by any agent, employee or contractor of the Agency except as otherwise specified in these Instructions to Bidders. No bidder may rely on verbal directions given by any agent, employee or contractor of the Agency except as specified in these Instructions to Bidders.

4. QUESTIONS.

Questions regarding this Project m ust be submitted through the online e bidding portal .

Questions shall be definite and certain, and shall reference applicable drawing sheets, notes, details or specification sections. The deadline to submit questions is identified in the Notice Inviting Bids. Questions received after the deadline may not be answered. Responses to questions submitted during the bidding period will be published in an A ddendum and provided to those bidding on the Project no later than the date specified in the Notice Inviting Bids.

Except for the Agency’s Bid Administrator, no other members of the Agency’s staff or Board should be contacted about this procurement during the bidding process. All inquiries and comments from Prospective Bidders regarding a proposed Bid must be communicated in writing, unless otherwise instructed by the Agency. The Agency may, in its sole discretion, disqualify any Prospective Bidder who engages in any prohibited communications.

5. PRE-BID CONFERENCE.

The Notice Inviting Bids shall state whether a Pre-Bid Conference will be held and, if so, whether attendance is mandatory . Bids will not be accepted from any bidder who did not attend a Mandatory Pre-Bid Conference. The Conference will commence at the specified start time and the Site visit will begin at the conclusion of the C onference. Prospective Bidders who arrive late and who do not sign the “Sign -In” or attendance sheet, may be disqualified from the bidding process.

Representatives of the Agency and its consultants, if any, will be present to the extent possible.

Questions asked by Bidders at the Pre -Bid Conference not specifically addressed within the

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 6 of 284 ends

Contract Documents shall be answered in writing and shall be sent to all Bidders present at the Pre-Bid Conference.

A Pre -Bid Conference may include a Project S ite visit. Personal Protective Equipment (PPE) is required of all Job Walk attendees. Attendees are required to wear closed toe shoes, long pants, no sleeveless shirts, safety glasses (may be prescription with side shields if in process areas), safety vests and hard hats. Only those possessing such attire will be allowed on the Job Site. The Agency will not provide personal protective equipment to Job Walk attendees.

6. ADDENDA.

The Agency may revise the Contract Documents before the Bid Submission Deadline. Revisions, if any, shall be made by written Addenda. All Addenda will be posted on the online bidding portal.

All Addenda issued by the Agency shall be acknowledged by the Bidder on the online bidding portal and made part of the Contract Documents. The Bidder shall acknowledge the Addenda before submitting its Bid. Bidders are responsible for the receipt of all Addenda. The Agency may reject a Bid if the Bidder fails to acknowledge all Addenda.

Pursuant to Public Contract Code Section 4104.5, if the Agency issues an Addendum which includes material changes to the Project less than 72 hours before the Bid Submission Deadline, the Agency will extend the Bid Submission Deadline by no less than 72 ho urs. The Agency may determine, in its sole discretion, whether an Addendum warrants postponement of the Bid Submission Deadline.

7. ALTERNATE BIDS.

If alternate Bid items are called for in the Notice Inviting Bids and the Contract Documents, the time required for completion of the Work for the alternate Bid items is factored into the Contract duration and no additional Contract time will be awarded. The Agency may elect to include one or more of the alternate Bid items, or to otherwise remove certain work from the Project scope of work. Accordingly, each Bidder must ensure that each Bid item contains a proportionate share of profit, overhead, and other costs or expenses which will be incurred by the Bidder.

If the Agency utilizes alternate Bid items as described above, the Notice Inviting Bids will prescribe predetermined criteria for the Bid package selection or a selection process in which price information and B idder identities are not revealed to the Agency before the Bid Submission Deadline.

8. COMPLETION OF BID FORMS.

Bids shall only be prepared using the Bid Forms which are included in the Contract Documents.

The use of substitute Bid Forms other than legible and correct photocopies of those provided by the Agency are prohibited. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable), and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither de lete, modify, nor supplement the printed matter on the Bid Forms nor make

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 7 of 284 ends

substitutions thereon. Use of black or blue ink, indelible pencil, or a typewriter is required.

Deviations from these instructions may result in the Bid being deemed non-responsive.

The following documents must be completed and properly executed including notarization, where indicated, and submitted as a part of the complete Bid Package:

1. Bid Form (00 41 00)

2. Bid Bond (00 43 10) or Bid Security (00 43 20) with check/cash

3. Proposed Subcontractors Form (00 43 30)

4. Bidder Information and Experience Form (00 43 40)

5. Non-Collusion Affidavit (00 45 10)

6. Iran Contracting Act Certification (00 45 15)

7. Public Works Contractor Registration Certification (00 45 20)

8. Certificate of Insurance (00 45 25)

9. Statement Regarding Debarment (00 45 30)

10. Disclosure of Discipline Record (00 45 35)

11. Acknowledgement of ALL Addenda on the online bidding portal.

12. Optional Escrow Agreement, as applicable (00 61 30)

All Bids shall be computed on the basis of the given estimated quantities of work, as indicated in the Bid, multiplied by the unit price as submitted by the Bidder.

When paper copies are submitted, all prices must be written in ink or typewritten. Changes or corrections may be crossed out and typed or written in with ink and must be initialed in ink by a person authorized to sign for the Contractor.

9. GOVERNING GENERAL PROVISIONS.

The Specifications contained in the Agency Supplemental General Provisions (00 73 00) take precedence over the specification language contained in the Standard Specifications for Public Works Construction, “the Greenbook” latest edition and all errata. The Supplemental General Provisions address the unique conditions in the City of Carlsbad that are not addressed in the Greenbook. Therefore, if there is a conflict between the two, the Supplemental Provisions shall control over the Greenbook.

The Greenbook may be purchased at Bidder’s/Contractor’s local technical bookstore, online or directly from the publisher. The Supplemental Provisions are available only for download from the online bidding portal with Contract Documents. The Agency does not provide hard copies.

10. MODIFICATIONS OF BIDS.

Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions, or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall not delete, modify, or supplement the printed matter on the Bid Forms, or make substitutions thereon. Oral, telephonic, and electronic modifications will not be considered.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 8 of 284 ends

11. BID GUARANTEE.

Each Bid shall be accompanied by: (a) a cashier’s check; or, (b) a certified check made payable to Agency; or, (c) a Bid Bond secured from a surety company satisfactory to the Board, the amount of which shall not be less than 10% of the total bid price, made payable to Agency as bid security.

Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be a California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120.

The bid security shall be provided a s a guarantee that within 10 Working Days after the Agency provides the successful Bidder the Notice of Award, the successful B idder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security may be declared forfeited if the successful Bidder fails to enter into a contract and provide the necessary bonds and certificates of insurance. Any B id received that does not comply with these Bid Guarantee instructions may be rejected as non-responsive, and Agency may enter into a contract with the next lowest, responsive, responsible B idder, or may call for new Bids. No interest shall be paid on funds deposited with the Agency. Copies of B id Bonds submitted to the Agency shall have the same force and effect as the original.

The Bidder’s security of the second and third next lowest responsive B idders may be withheld until the Contract has been fully executed. The security submitted by all other unsuccessful Bidders shall be returned to them, or deemed void, within 10 Working Days after the Contract is awarded

The proceeds of the B idder’s security may also become property of the Agency if the B idder withdraws its Bid within 15 Calendar Days after the Bid opening date, unless otherwise required by law, including Public Contract Code S ection 5100 et. seq., and notwithstanding the award of the Contract to another Bidder.

The Bidder shall submit Bid Bond (00 43 10) or Bid Security (00 43 20) with properly certified check with the Bid Package.

12. LABOR & MATERIAL BOND AND PERFORMANCE & WARRANTY BOND REQUIREMENTS.

The successful B idder shall furnish Agency with a Labor and Material Payment Bond and a Performance and Warranty Bond, each in an amount equal to 100% of the Contract price. Each bond shall be secured from a surety company that meets all State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120 and is admitted by the State of California, and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The Agency shall not accept personal sureties and unregistered surety companies. Each bond shall be accompanied, upon the request of Agency, with all documents required by Code of Civil Procedure Section 995.660 to the extent required by law. All bonding and insurance requirements shall be completed and submitted to Agency within 10 Working Days from the date the Agency provides the successful Bidder with the Notice of Award.

These bonds shall be kept in full force and effect during the course of this Project, and shall extend in full force and effect and be retained by the Agency until they are released as stated in

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 9 of 284 ends

the Contract. The B onds are to be accompanied by an original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.

13. SUBSTITUTION OF SECURITY.

The Contract Documents call for monthly progress payments based upon the percentage of the Work completed. The Agency will retain a percentage of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the Agency will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.

14. OPTIONAL ESCROW FOR SECURITY DEPOSIT.

Pursuant to applicable provisions of law (i.e. , Public Contract Code S ection 10263), appropriate securities may be substituted for any obligation required by these instructions or for any monies withheld by the Agency to ensure performance under the Contract. Public Contract Code Section 10263 requires monies or securities to be deposited with the Agency or a state or federally chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions of the agent in connection with the handling of retentions under this section in an amount not less than $100,000 per contract.

15. INSURANCE REQUIREMENTS.

Before commencing the Work, the successful B idder shall purchase and maintain insurance as set forth in the Agency General Conditions. If the Bid is accepted, and if requested by the Agency, Contractor shall provide Agency or preferred vendor copies of the insurer’s most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Insurance Code Section 900 et seq. within 10 Calendar Days of the insurer’s receipt of a request to submit the statements.

In accordance with the provisions of Labor Code Section 3700, Contractor shall secure the payment of compensation to its employees. Contractor shall sign and file with the Agency the following certificate before performing the Work under the Contract:

I am aware of the provisions of Labor Code Section 3700, which require every employer to be insured against liability for workers’ compensation or to undertake self -insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of the Contract.

The form of such, Certificate of Insurance (00 45 25), shall be submitted as a part of the Bid Package.

Insurance must be placed with insurers that:
1) Have a rating in the most recent Best’s Key Rating Guide of at least A-:VII, or 2) Appear on the List of Approved Surplus Line Insurers, (“LASLI”) with a Best’s Key Rating Guide of at least A: X.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 10 of 284 ends

3) Are admitted to conduct the business of insurance in the State of California by the Insurance Commissioner.
4) Otherwise comply with all other aspects of City Council Policy No. 70.

Auto policies offered to meet the specification of this Contract must:
1) Meet the conditions stated above for all insurance companies. 2) Cover any vehicle used in the performance of the Contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.

Workers’ compensation insurance required under this Contract must be offered by a company meeting the above standards with the exception that the Best’s rating condition may be waived.

The Agency does accept policies issued by the State Compensation Fund m eeting the requirement for workers’ compensation insurance.

The Contractor shall be required to maintain insurance as specified in the Contract. Any additional cost of the insurance shall be included in the Bid price.

The award of the Contract by the Board is contingent upon the Contractor submitting the required bonds and insurance, as described in the Contract Documents, within 10 Working Days of bid opening. If the Contractor fails to comply with these requirements, the Agency may award the Contract to the second or third lowest B idder and the bid security of the lowest B idder may be forfeited.

16. LICENSING REQUIREMENTS.

Pursuant to Business and Professions Code Section 7028.15 and Public Contract Code Section 3300, all Bidders must possess proper licenses for performance of the Contract. Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Business and Professions Code Section 7028.5, the Agency shall consider any B id submitted by a contractor not currently licensed in accordance with California law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the Agency shall reject the Bid. The Agency shall have the right to request, and Bidders shall provide within 10 C alendar Days, evidence satisfactory to the Agency of all valid license(s) currently held by that Bidder and each of the Bidder’s Subcontractors, before awarding the Contract.

Notwithstanding anything contained in this Contract, if the Work involves federal funds, the Contractor shall be properly licensed by the time the Contract is awarded, pursuant to the provisions of Public Contract Code Section 20103.5.

17. SUBCONTRACTORS.

Bidder shall set forth the name, address of the place of business, and contractor license number of each Subcontractor who will perform work, labor, furnish materials or render services to the bidder on the C ontract. This requirement includes each S ubcontractor licensed by the State of California who, under subcontract to Bidder, specially fabricates and installs a portion of the Work described in the Drawings and Specifications in an amount in excess of one -half of one

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 11 of 284 ends

percent (0.5%) of the total Bid price. Additionally, the Bidder shall indicate the portion of the Work to be done by each Subcontractor in accordance with Public Contract Code Section 4104.

Bidder shall submit Proposed Subcontractors Form (00 43 30) with the Bid Package.

This form will be used by the Agency to determine the percentage of work that the Bidder proposes to perform. Bidders are cautioned that failure to provide complete and correct information may result in rejection of the B id as non -responsive. Any B id that proposes performance of more than 50 percent of the Work by S ubcontractors or performance by forces other than the Bidder’s own organization will be rejected as non- responsive. Specialty items of work that may be so designated on the Proposed Subcontractors Form (00 43 30) “Contractor’s Bid” will not be included in computing the percentage of work proposed to be performed by the Bidder.

Suppliers of materials from sources outside the limits of Work are not Subcontractors. The value of materials and transport of materials from sources outside the limits of Work, as shown on the plans, shall be assigned to the Contractor or the Subcontractor, as the case may be, that the Bidder proposes as installer of the materials. The value of material incorporated in any Subcontractor-installed Bid item that is supplied by the Bidder shall be included as a part of the Work that the Bidder proposes to be performed by the Subcontractor installing the item.

When the Bidder proposes to use a Subcontractor to construct or install less than 100 percent of a Bid item, the Bidder shall attach an explanation sheet to the Proposed Subcontractor Form (00 43 30). The explanation sheet shall clearly apprise the Agency of the specific facts that show the Bidder proposes to perform no less than fifty percent (50%) of the Work with its own forces.

Determination of the subcontract amounts for purposes of award of the Contract shall be determined by the Board in conformance with the provisions of the Contract Documents. The decision of the Board shall be final.

Contractor is prohibited from performing any Work on this Project with a Subcontractor who is ineligible to perform work on a public works project pursuant to Labor Code Section 1771.1 or 1777.7.

Bidders shall make copies of the disclosure forms as may be necessary to provide the required information to Subcontractors. The page number and total number of additional form pages shall be entered in the location provided on each type of form so duplicated.

18. BIDDER INFORMATION AND EXPERIENCE FORM.

Each Bidder shall complete the provided questionnaire and shall submit the questionnaire along with its Bid. Failure to provide all information requested within the questionnaire along with the Bid may cause the B id to be rejected as non -responsive. The Agency may reject any Bid if an investigation of the information submitted does not satisfy the Agency that the Bidder is qualified to properly carry out the terms of the Contract.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 12 of 284 ends

The Bidder shall submit Bidder Information and Experience Form (00 43 40) with the Bid Package.

19. NON-COLLUSION AFFIDAVIT.

Bidders on all public works contracts are required to submit an affidavit of non -collusion with their Bid. This form (00 45 10 Non-Collusion Affidavit) is included with the Bid Package and must be signed and dated under penalty of perjury.

20. IRAN CONTRACTING ACT OF 2010.

In accordance with Public Contract Code Section 2200 et seq ., the Agency requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the Agency with respect to goods or services of $1,000,000 or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list cr eated pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.

The form of such Iran Contracting Certificate is included with the Bid Package and must be signed and dated under penalty of perjury.

21. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION.

Pursuant to Labor Code Section 1773, the Agency has obtained the prevailing rate of per diem wages and the prevailing wage rate for holiday and overtime work applicable in San Diego County from the Director of the Department of Industrial Relations for eac h craft, classification, or type of worker needed to execute this Contract. A copy of these prevailing wage rates may be obtained via the internet at www.dir.ca.gov/dlsr/.

In addition, a copy of the prevailing rate of per diem wages is available at the Agency and shall be made available to interested parties upon request. The successful Bidder shall post a copy of the prevailing wage rates at each job site. It shall be mandatory upon the Bidder to whom the Contract is awarded, and upon any S ubcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the specified prevailing wage rates to all workers employed by them in the execution of the Contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors.

Pursuant to Labor Code Sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded the Contract, the Bidder and its S ubcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 13 of 284 ends

This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. In bidding on this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance req uirements under the Contract and applicable law in its Bid.

To this end, Bidder shall sign and submit with its Bid the Public Works Contractor Registration Certification on the form provided, attesting to the facts contained in the registration certificate.

Failure to submit this certificate may render the Bid non-responsive. In addition, each Bidder shall provide the registration number for each listed S ubcontractor in the space provided in the Proposed Subcontractors Form (00 43 30).

22. PREVAILING WAGES.

Pursuant to Labor Code Sections 1720, et. seq. and 1770, et. seq., Contractor shall pay prevailing wages for all Work performed under the Contract. The Agency has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which the Work will be performed for each craft or type of worker needed to execute the Contract. These rates are available at the Agency or may be obtained online at http://www.dir.ca.gov. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).

23. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS.

In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code Section 1777.1 or 1777.7. An y contract on a public works project executed between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the Agency. The Contractor shall be responsible for the payment of wages to workers of a debarred Subcontractor who has been allowed to work on the Project.

The Agency may disqualify a C ontractor or Subcontractor from participating in bidding when a Contractor or Subcontractor has been debarred by the Agency or another jurisdiction in the State of California as an irresponsible bidder.

24. SIGNING OF BIDS.

All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.

If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 14 of 284 ends

joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations that the Bidder assumes under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.

25. SUBMISSION OF SEALED BIDS.

Once the Bid and supporting documents have been completed and signed as set forth in these Instructions to Bidders, they shall be uploaded, along with other required materials, to the online bidding portal before the deadline for submitting bids.

At the time of Bid submission, whether in the form of a cashier’s check, a properly certified check or an approved corporate surety bond payable to the Agency, Bidders must upload an electronic Portable Document Format (PDF) copy of the Bid Guarantee to the online bidding portal. The first 3 apparent low Bidders must provide the Agency with the original Bid Guarantee within 2 Business Days after the Bid opening date.

Failure to submit the electronic version of the Bid Guarantee at time of bid submission shall cause the bid to be rejected and deemed non -responsive. Failure to provide the original within 2 business days may deem the bidder non-responsive.

Original Bid Bond shall be submitted to:

Public Works Contract Administration
Attention: «ContractAdmin», Contract Administrator
1635 Faraday Avenue
Carlsbad, California, 92008

No oral or telephonic B ids will be considered. Pursuant to Public Contract Code S ections 1600 and 1601, only where expressly permitted in these Instructions to Bidders and the Notice Inviting Bids may B idders submit their B ids via electronic transmission ( the online bidding portal ). Bids received after the Bid Submission Deadline will not be accepted. Agency may reject any B id not strictly complying with Agency’s designated methods for delivery.

26. OPENING OF BIDS.

Bids submitted on the online bidding portal will be reviewed by the Agency. Once the Bid Submission Deadline has passed, B idders, proposers, the general public, and Agency staff are able to immediately see the results online. Agency shall consider award of the Contract to the lowest, responsive, responsible Bidder as determined by the Agency consistent with Section 32 below. In case of a discrepancy between the line item entries submitted in the online bidding portal and the Bid Form, the online bidding portal shall prevail. In the event of any discrepancies, written numbers (e.g., fifty, hundred) will govern over numerical numbers (e.g., 50, 100) on the Bid Form.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 15 of 284 ends

In the event of any discrepancies, written numbers (e.g., fifty, hundred) will govern over numerical numbers (e.g., 50, 100) on the Price Proposal Form. Also, the sum of all lump sum line items will govern over the “Total Proposed Lump Sum Price” line item. The Agency may reject any or all Bids or waive any irregularities or informalities in any Bids or in the Bidding process.

The Bid and the terms of the Contract Documents constitute an irrevocable offer that shall remain valid and in full force for a period of 90 Calendar Days from the Bid Submission Deadline and such additional time as may be mutually agreed upon by the Agency and the Bidder.

27. WITHDRAWAL OF BID.

Any Bid may be withdrawn via written letter, incurring no penalty, at any time before the scheduled closing time for receipt of B ids. Requests to withdraw B ids shall be worded to not reveal the amount of the original Bid. Withdrawn B ids may be resubmitted until the Bid Submission Deadline, provided that resubmitted Bids are in conformance with these Instructions to Bidders.

Bids may be withdrawn after bid opening only by providing written notice to Agency within five (5) Working Days of the bid opening and in compliance with Public Contract Code Section 5100 et seq., or as otherwise may be allowed with the consent of the Agency.

28. BIDDERS INTERESTED IN MORE THAN ONE BID.

No Bidder shall be allowed to make, file or be interested in more than 1 Bid for the same work unless alternate Bids are specifically called for. If the Notice Inviting Bids provides for alternate Bids, a person, firm or corporation that has submitted a sub -proposal to a Bidder, or that has quoted prices of materials to a Bidder, is not disqualified from submitting a sub -proposal or quoting prices to other Bidders. No person, firm, corporation, or other entity may submit a sub - proposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.

29. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES, AND FEES.

Contractor and its Subcontractors performing work under the Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the Work will be locate d, unless otherwise expressly provided by the Contract Documents.

30. PERMIT AND INSPECTION FEE ALLOWANCE.

Notwithstanding anything contained in these Instructions to Bidders, the Bid Form contains an allowance for the Contractor’s cost of acquiring traffic control permits and for construction inspection fees that may be charged to the Contractor by the Agency. The allowance is included within the Bid Form to eliminate the need by Bidders to research or estimate the costs of traffic control permits and construction inspection fees before submitting a Bid. The allowance is specifically intended to account for the costs of traffic control permits and construction inspection fees charged by the Agency. No other costs payable by Contractor to the Agency are included within the allowance.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 16 of 284 ends

If such cost is not contained or specified in the Bid Form, the Contractor shall include the costs in the other Bid items on the Bid Form.

31. BASIS OF AWARD; BALANCED BID.

The Agency shall award the Contract to the lowest responsible Bidder submitting a responsive Bid. The lowest Bid will be determined on the basis of the total B id price. In the event of any discrepancies, written numbers (e.g., fifty, hundred) will govern over numerical numbers (e.g., 50, 100) on the Price Proposal Form. Also, the sum of all lump sum line items will govern over the “Total Proposed Lump Sum Price” line item.

The Agency may reject any Bid which, in its opinion when compared to other Bids received or to the Agency’s internal estimates, does not accurately reflect the cost to perform the Work. The Agency may reject as non-responsive any Bid which unevenly weights or allocates costs, including but not limited to overhead and profit to 1 or more particular Bid items or otherwise violates Public Contract Code Section 9203.

32. AWARD PROCESS.

Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the Board may award the Contract. Once notified by Agency staff, the apparent successful Bidder should begin to prepare the following documents: (1) the Labor and Materials Bond; (2) the Performance and Warranty Bond; and (3) the required insurance certificates and endorsements. Once the Agency notifies the Bidder of the award, the Bidder will have 10 Working Days from the date of this notification to execute the Contract and supply the Agency with all of the required documents and certifications or the Bidder may forfeit the Bid security and the Agency may pursue award of the Contract to the next lowest, responsive, responsible Bidder.

Once the Agency receives all properly drafted and executed documents and certifications from the Bidder, the Agency shall issue a Notice to Proceed to that Bidder.

33. EXECUTION OF CONTRACT.

As required in these Instructions to Bidders, the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The Agency may require appropriate evidence that the persons executing the Contract are duly empowered to do so. The Contract and bond forms to be executed by the successful Bidder are included within these Specifications and shall not be detached.

34. BUSINESS LICENSE
The prime C ontractor and all S ubcontractors are required to have and maintain a valid City of Carlsbad Business License for the duration of the Contract.

35. PARTICIPATION OF MINORITY AND WOMEN-OWNED BUSINESSES.

The Agency encourages the participation of minority and women-owned businesses.

00 21 10 INSTRUCTIONS TO BIDDERS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 17 of 284 ends

36. USE OF RECYCLED MATERIALS
The Agency encourages Bidders, suppliers, manufacturers, fabricators and contractors to utilize recycled and recyclable materials when available, appropriate and approved by the Agency’s Engineer.

37. STATUTORY REFERENCES
All references in these Instructions to Bidders (00 21 10) to any statute, rule or regulation are to the statute, rule or regulation as amended, modified, supplemented or replaced from time to time by the corresponding legislative or regulatory body.

END OF SECTION

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 18 of 284 ends

00 41 00 BID FORM
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

AGENCY: City of Carlsbad
1635 Faraday Ave
Carlsbad, CA 92008

The undersigned declares that we have carefully examined the location of the proposed Work, and have read and examined the Contract Documents, including all Plans, Specifications, and Addenda, if any, for the above -mentioned Project. The undersigned has acknowledged receipt, understanding, and full consideration of ANY and ALL Addenda to the Contract Documents via the online bidding portal.

We propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project, as described and in strict conformity with the Drawings, and the se Specifications for TOTAL BID PRICE.

Attached is the required Bid Bond (00 43 10) or Bid Security (00 43 20) in the amount of not less than 10% of the Total Bid Price.
Attached is the completed Proposed Subcontractors form (00 43 30). Attached is the completed Bidder Information and Experience form (00 45 40) Attached is the fully executed Non-collusion Affidavit (00 45 10). Attached is the completed Iran Contracting Act Certification form (00 45 15). Attached is the completed Public Works Contractor Registration Certification form (00 45 20).
Attached is the completed Certificate of Insurance form (00 45 25). Attached is the Statement of Regarding Debarment form (00 45 30) Attached is the Disclosure of Discipline Record (00 45 35) Attached is the Optional Escrow Agreement (if applicable) (00 61 30)

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 19 of 284 ends

1. BID SCHEDULE
Item No. Item
Description
Unit
Of
Measure
Quantity Unit
Price
Total
1 MOBILIZATION 1 LS
2 CONSTRUCTION SCHEDULE 1 LS
3 EROSION CONTROL AND WATER
POLLUTION CONTROL 1 LS
4 TEMPORARY TRAFFIC CONTROL 1 LS
5 CLEARING AND GRUBBING 1 LS
6 ASPHALT CONCRETE 829 TON
7 COLORED STAMPED CONCRETE 11,088 SQFT
8 AGGREGATE BASE 1,297 CY
9 SLURRY SEAL 47,900 SY
10 UNCLASSIFIED EXCAVATION 4,392 CY
11 CONCRETE SIDEWALK 95 CY
12 CONCRETE DRIVEWAY 4 CY
13 CONCRETE CURB AND GUTTER 960 LF
14 MODIFIED CONCRETE CURB AND
GUTTER 482 LF
15 COLD MILL ASPHALT CONCRETE 490 SQYD
16 GRAVITY RETAINING WALL 1 CY
17 TEMPORARY HIGH-VISIBILITY
FENCE 1,418 LF
18 18" RCP (1350-D) 166 LF
19 24" RCP (1350-D) 4 LF
20 PIPE COLLAR 1 EA
21 STRAIGHT HEADWALL 1 EA
22 BIOFILTRATION BMP 2,160 SQFT
23 8" PVC (PERFORATED) 390 LF
24 8" PVC (NON-PERFORATED) 4 LF
25 CURB INLET - TYPE C-2 (L=15') 1 EA
26 24"x24" CLEANOUT 1 EA
27 8" SUBDRAIN CLEANOUT 6 EA
28 OBSERVATION WELL 1 EA
29 STRIPING AND MARKINGS 1 LS
30 STRIPING REMOVAL 1 LS
31 SIGNING 1 LS
32 ADJUST SEWER MANHOLE TO

GRADE AND REPLACE MANHOLE

FRAME AND COVER WITH NEW

LOCKING COMPOSITE FRAME AND
COVER
1 EA

33 REPLACE MANHOLE FRAME AND
COVER WITH NEW LOCKING 3 EA

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 20 of 284 ends

COMPOSITE FRAME AND COVER

AND INSTALL CONCRETE SEWER

REINFORCEMENT
34 RELOCATE FIRE HYDRANT 1 EA
35 RELOCATE WATER METER 2 EA
36 LIGHTING SYSTEM 1 LS
37 FIBER OPTIC CABLE SYSTEMS 1 LS
38 TRAFFIC SIGNAL 1 LS
39 IRRIGATION 1 LS
40 PLANTING 1 LS
41 120 DAY MAINTENANCE 1 LS
42 STAGING 1 LS 1 $2500

The costs for any Work shown or required in the Contract Documents, but not specifically identified as a line item are to be included in the related line items and no additional compensation shall be due to Contractor for the performance of the Work.

The estimated quantities for Unit Price items are for purposes of comparing Bids only and the Agency makes no representation that the actual quantities of Work performed will not vary from the estimates. Final payment shall be determined by the Engineer from measured quantities of Work performed based upon the Unit Price.

2. TOTAL BID PRICE

The undersigned agrees that this Bid Form constitutes a firm offer to the Agency which cannot be withdrawn for ninety (90) C alendar Days from and after the Bid opening, or until a Contract for the Work is fully executed by the Agency and the lowest responsible Bidder, whichever is later.

The Undersigned has carefully checked all the above figures and understands that the Agency will not be responsible for any error or omission on the part of the Undersigned in preparing this Bid.

The TOTAL BID PRICE on Bid Schedule total of Unit Prices:

Total Bid Price in Numbers:

Total Bid Price in Written Form:

In case of discrepancy between the written price, the numerical price, or the price as submitted via the online bidding portal, the online bidding portal price shall prevail.

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 21 of 284 ends

3. RECITALS
The successful Bidder agrees to sign the Contract and furnish the necessary bonds and certificates of insurance within 10 Working Days after the Agency issues the Notice of Award to the successful Bidder.

The Undersigned agrees that in case of failure to execute the required Contract with necessary bonds and insurance policies within this time period, the Agency may pursue award ing the Contract to the next lowest responsible Bidder and the Bid Security of the lowest Bidder may be forfeited.

Upon receipt of the signed Contract and other required documents, the Agency will proceed to execute the Contract and issue a purchase order and the Notice to Proceed. The time of completion shall commence on the date of the Notice to Proceed, unless otherwise specified.

The undersigned agrees to begin the Work within 10 Working Days of the date of the Notice to Proceed, unless otherwise specified.

The Undersigned is aware of the provisions of Labor Code Section 3700, which requires every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and agrees to comply with such provisions before commencing the performance of the Work of this Contract and continue to comply until the Contract is complete.

The Undersigned is aware of the provisions of Labor Code Section 1770 et seq. relative to the general prevailing rate of wages for each craft or type of worker needed to execute the Contract and agrees to comply with its provisions.

The Undersigned Bidder declares, under penalty of perjury, that the undersigned is licensed to do business or act in the capacity of a contractor within the State of California and that this statement is true and correct and has the legal effect of an affidavit. The following are the Bidder’s applicable license number(s), with their expiration date(s) and class of license(s):

______________________________________________________________________________ ______________________________________________________________________________ ______________________________________________________________________________

If the Bidder is a joint venture, each member of the joint venture must include the required licensing information.

A Bid submitted to the Agency by a Contractor who is not licensed as a Contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the Agency. In all contracts where federal funds are involved, no Bid submitted shall be invalidated by the failure of the Bidder to be licensed in accordance with California law. However, at the time the Contract is awarded, the Contractor shall be properly licensed.

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 22 of 284 ends

The Undersigned Bidder represents as follows:

1. That no elected or appointed official, officer, agent, or employee of the Agency is personally interested, directly or indirectly, in this Contract, or the compensation to be paid under it; that no representation, oral or in writing, of the Agency, its officers, agents, or employees has induced Bidder to enter into this Contract, excepting only those contained in this form of Contract and the papers made a part of this Contract by its terms; and

2. That this Bid is made without connection with any person, firm, or corporation making a Bid for the same Work, and is in all respects fair and without collusion or fraud.

Accompanying this Bid is _________________________________ (Cash, Certified Check, Bidder’s Bond or Cashier's Check) for 10% of the amount Bid, payable to Agency as Bid Security and which is given as a guarantee that the undersigned will enter into a Contract and provide the necessary bonds and certificates of insurance if awarded the Contract.

Organized under the laws of the State of ________________________.

an individual
a partnership
a corporation

(Signatures continued on next page)

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 23 of 284 ends

IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:

I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.

1 Name under which
business is
conducted

______________________________________________________

2 Signature (given and
surname) of
proprietor

Printed/Typed Name

______________________________________________________

______________________________________________________

3 Place of Business
(Full Address: street,
number, city, state,
zip)

______________________________________________________

______________________________________________________

______________________________________________________

4 Telephone Number ______________________________________________________

5 Email ______________________________________________________

NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 24 of 284 ends

IF A PARTNERSHIP, SIGN HERE:

I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.

1 Name under which
business is
conducted

______________________________________________________

2 Signature (given and
surname and role)
(Note: Signature
must be made by a
general partner)

Printed/Typed Name

______________________________________________________

______________________________________________________

3 Place of Business
(Full Address: street,
number, city, state,
zip)

______________________________________________________

______________________________________________________

______________________________________________________

4 Telephone Number ______________________________________________________

5 Email ______________________________________________________

NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 25 of 284 ends

IF A CORPORATION, SIGN HERE:

I certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made in this Bid are true and correct.

1 Name under which
business is
conducted

______________________________________________________

2 Signature (given and
surname and Title)
(Note: Signature
must be made by a
someone who can
bind the
corporation)

Printed/Typed Name

______________________________________________________

______________________________________________________

3 Place of Business
(Full Address: street,
number, city, state,
zip)

______________________________________________________

______________________________________________________

______________________________________________________

4 Telephone Number ______________________________________________________

5 Email ______________________________________________________

NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED

00 41 10 BID FORM Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 26 of 284 ends

List below names of president, vice president, CFO, secretary and assistant secretary, if a corporation; if a partnership, list names of all general partners, and managing partners:

Approved as to form this ___________________day of _____________________ 20_______.

______________________________________________
Attorney for Agency

END OF SECTION

00 43 10 BID BOND FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 27 of 284 ends

00 43 10 BID BOND FORM
(Note: This form is not required when other form of Bidder’s Security, e.g. cash, certified check or cashier’s check, accompanies Bid. In that case, use form 00 43 20 Bid Security)

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

The makers of this bond are, as Principal,
and , as Surety and are held and
firmly bound unto the City of Carlsbad (“Agency”) in the penal sum of 10% OF THE TOTAL BID PRICE of the Principal submitted to the Agency for the Work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying Bid dated .

If the Principal does not withdraw its Bid within the time specified in the Contract Documents; and if the Principal provides all required documents to the Agency and is awarded the Contract; then this obligation shall be null and void. Otherwise, this bond will remain in full force and effect.

Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents shall affect its obligation under this bond, and Surety waives notice of any such changes.

In the event a lawsuit is brought upon this bond by the Agency and judgment is recovered, the Surety shall pay all litigation expenses incurred by the Agency in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and expenses.

///

///

///

///

///

00 43 10 BID BOND FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 28 of 284 ends

IN WITNESS WHEREOF, the above -bound parties have executed this instrument under their several seals this_____________ day of _____________________________, 20______, the name and corporate seal of each corporation.

PRINCIPAL:

___________________________________
(Name of Principal)

By:

___________________________________
(sign here)

___________________________________
(Print name here)

___________________________________
(Title and Organization of Signatory)

Executed by SURETY

this ______day of ________________, 20____

SURETY:

_____________________________________
(name of Surety)

_____________________________________
(address of Surety)

_____________________________________
(telephone number of Surety)

By:
_____________________________________
(signature of Attorney-in-Fact)

_____________________________________
(printed name of Attorney-in-Fact)

Required Attachments:
Corporate resolution showing current power of attorney. Proper execution by PRINCIPAL.
Proper notarial acknowledgment of execution by SURETY. President or vice -president and CFO, secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.

END OF SECTION

00 43 20 BID SECURITY Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 29 of 284 ends

00 43 20 BID SECURITY
(Note: This form is required when cash, certified check or cashier’s check, accompanies Bid. If Bid Bond is being provided, use form 00 43 10 Bid Bond)

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

Accompanying this proposal is a Certified / Cashier’s check payable to the order of the City of Carlsbad (“Agency”), in the sum of
dollars ($___________________), this amount being 10% of the total amount of the Bid. The proceeds of this check shall become the property of the Agency, provided this proposal shall be accepted by the Agency through action of its legally constituted contracting authorities and the Undersigned shall fail to execute a Contract and furnish the required Performance, Warranty and Payment Bonds and proof of insurance coverage within the stipulated time; otherwise, the check shall be returned to the Undersigned. The proceeds of this check shall also become the property of the Agency if the Undersigned shall withdraw his or her Bid within the period of 15 Calendar Days after the date set for the opening of the Bid , unless otherwise required by law, and notwithstanding the award of the Contract to another Bidder.

_______________________________________
BIDDER
Required Attachments:

Certified Check or Cashier’s Check

END OF SECTION

00 43 30 PROPOSED SUBCONTRACTORS FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 30 of 284 ends

00 43 30 PROPOSED SUBCONTRACTORS FORM
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

In compliance with the Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.), Bidder shall set forth below: (a) the name and the location of the place of business, (b) the California contractor license number, (c) the DIR public works contractor registration number, and (d) the portion of the Work which will be done by each Subco ntractor who will perform work or labor or render service to the Bidder in or about the construction of the Work or improvement to be performed under this Contract in an amount in excess of one - half of one percent (0.5%) of the Bidder’s Total Bid Price. Notwithstanding the foregoing, if the Work involves the construction of streets and highways, then the Bidder shall list each Subcontractor who will perform work or labor or render service to the Bidder in or about the Work in an amount in excess of one-half of one percent (0.5%) of the Bidder’s Total Bid Price or $10,000, whichever is greater. No additional time shall be granted to provide the below requested information.

If a Bidder fails to specify a Subcontractor or if a Contractor specifies more than one Subcontractor for the same portion of Work, then the Bidder shall be deemed to have agreed that it is fully qualified to perform that portion of Work and that it shall perform that portion itself. No changes in the Subcontractor’s listed Work will be made without the prior approval of the Agency.

Attach additional pages as required.

(Signature of Bidder)

00 43 30 PROPOSED SUBCONTRACTORS FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 31 of 284 ends

Name of
Subcontractor
Location of
Business
CSLB
Contractor
License
No./ Exp
Date
DIR
Registration
Number /
Exp. Date
Type of Work
to be done by
Subcontractor
% of
Work
Amount of
Work by
Subcontractor
in Dollars*

Pursuant to Public Contract Code Section 4104, subdivision (a)(3)(A), receipt of the information preceded by an asterisk (*) may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the “Notice Inviting Bids.”

END OF SECTION

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 32 of 284 ends

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

1. INFORMATION ABOUT BIDDER

(Indicate not applicable (“N/A”) where appropriate.)

NOTE: Where Bidder is a joint venture, pages shall be duplicated, and information provided for all parties to the joint venture.

1. Type, if Entity:

2. Bidder Address:

a. Facsimile Number

b. Telephone Number

c. Email Address

3. How many years has Bidder’s organization been in business as a contractor?

4. How many years has Bidder’s organization been in business under its present name? a. Under what other or former names has Bidder’s organization operated?

5. If Bidder’s organization is a corporation, answer the following:

a. Date of Incorporation:

b. State of Incorporation:

c. President’s Name:

d. Vice-President’s Name(s):

e. Secretary’s Name:

f. Treasurer’s Name:

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 33 of 284 ends

g. CFO’s Name:

6. If an individual or a partnership, answer the following:

a. Date of Organization:

b. Name and address of all partners (state whether general or limited partnership):

7. If other than a corporation or partnership, describe organization and name principals:

8. List other states in which Bidder’s organization is legally qualified to do business.

9. What type of work does the Bidder normally perform with its own forces?

10. Has Bidder ever failed to complete any work awarded to it? If so, note when, where, and why:

11. Within the last 5 years, has any officer or partner of Bidder’s organization ever been an officer or partner of another organization when it failed to complete a contract ? If so, attach a separate sheet of explanation:

12. List Trade References:

13. List Bank References (Bank and Branch Address):

14. Name of Bonding Company and Name and Address of Agent:

[REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK]

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 34 of 284 ends

2. LIST OF CURRENT PROJECTS (BACKLOG)
[**Duplicate or attach additional pages if needed for listing current projects.**] Project Name
Sub or Prime?
Description of Bidder’s Work Client
Name
Completion
Date
Cost of
Bidder’s Work

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 35 of 284 ends

LIST OF COMPLETED PROJECTS (LAST 3 YEARS)
[**Duplicate or attach additional pages if needed for listing completed projects. **]

Please include only those projects which are similar enough to demonstrate Bidder’s ability to perform the required Work.

Project Name
Sub or Prime?
Description of Bidder’s Work Client
Name
Completion
Date
Cost of
Bidder’s Work

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 36 of 284 ends

EXPERIENCE AND TECHNICAL QUALIFICATIONS QUESTIONNAIRE
Personnel:

The Bidder shall identify the key personnel to be assigned to this Project in a management, construction supervision or engineering capacity. Add additional pages to identify ALL key personnel. Bidder may submit a 2-page resume of each key personnel mentioned above.

Bidder agrees that personnel named in this Bid will remain on this Project until completion of all relevant Work, unless substituted by personnel of equivalent experience and qualifications approved in advance by the Agency.

Job Title
Name
% time on this
Project
Specialized
Education
Years of
construction
experience
relevant to the
Project
Summarize the
experience

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 37 of 284 ends

Additional Bidder’s Statements:

If the Bidder feels that there is additional information which has not been included in the questionnaire above, and which would contribute to the qualification review, it may add that information in a statement here or on an attached sheet, appropriately marked:

00 43 40 BIDDER INFORMATION AND EXPERIENCE FORM Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 38 of 284 ends

3. VERIFICATION AND EXECUTION
These Bid Forms shall be executed only by a duly authorized official of the Bidder:

I declare under penalty of perjury under the laws of the State of California that the foregoing information is true and correct:

Name of Bidder:

Signature ________________________________________________________________

Name ______________________________________________________________________

Title ______________________________________________________________________

Date ______________________________________________________________________

END OF SECTION

00 45 10 NON-COLLUSION AFFIDAVIT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 39 of 284 ends

00 45 10 NON-COLLUSION AFFIDAVIT

NONCOLLUSION DECLARATION TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072

NAME OF BIDDER:

Consistent with Public Contract Code Section 7106, t he undersigned declares:

I am the o f , t he
party making the foregoing Bid.

The Bid is not made i n the i nterest of, or on beh alf of, any undi sclosed per son, partner ship, company, association, organization, or corporation. The Bid is genuine and not collusive or sham.

The Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham bid. The Bidder has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or anyone else to put in a sham bid, or to refrain from bidding. The Bidder has not in any manner, dir ectly or indirectly, sought by agreement, communication, or co nference wit h anyone to fix the Bid Price of the Bidder or any other Bidder, or to fix any overhead, profit, or cost element of the Bid Price, or of that of an y other Bidder. All statements contained in the Bid are true. The Bidder has not, directly or indirectly, submitted his or her Bid Price or any breakdown of it, or t he contents of it, or divulg ed information or data relative to it, to any corporation , partnership, company, association, organization, bid deposit ory, or to any member or agent of these, to effectuate a co llusive or sham bid, and ha s not paid, and will not pay, an y person or entity for such purpose.

Any person executing this declaration on behalf of a Bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, repr esents that he or she has ful l power to execute, and do es execute, this decl aration on behalf of t he Bidder.

I declare under pen alty of pe rjury under t he laws of t he State of California that t he foregoing is true an d c orrect a nd that this d eclaration is e xecuted ________________ 20 ____ at _______________ [city], _____ [state].

Signature

Name _________________________________

Title

END OF SECTION

00 45 15 IRAN CONTRACTING ACT CERTIFICATION Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 40 of 284 ends

00 45 15 IRAN CONTRACTING ACT CERTIFICATION
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

As required by Public Contract Code Section 2204, the Contractor certifies subject to penalty of perjury that the option checked below relating to the Contractor’s status in regard to the Iran Contracting Act of 2010 (Public Contract Code Section 2200 et seq.) is true and correct:

The Contractor is not:

1) identified on the current list of persons and entities engaged in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203; or

2) a financial instruction that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code Section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.

The Agency has exempted the Contractor from the requirements of the Iran Contracting Act of 2010 after making a public finding that, absent the exemption, the Agency will be unable to obtain the goods and/or services to be provided pursuant to the Contract.

The amount of the Contract payable to the Contractor for the Project does not exceed $1,000,000.

Signature: Date:

Name: Title:

Note: In accordance with Public Contract Code Section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract amount, termination of the Contract and/or ineligibility to bid on contracts for 3 years.

END OF SECTION

00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 41 of 284 ends

00 45 20 PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

Pursuant to Labor Code S ections 1725.5 and 1771.1, all Contractors and Subcontractors that wish to Bid on, be listed in a Bid proposal, or enter into a Contract to perform public work must be registered with the Department of Industrial Relations. See Public Works (ca.gov) for additional information.

No Bid will be accepted, nor any Contract entered into without proof of the Contractor’s and Subcontractors’ current registration with the Department of Industrial Relations to perform public work.

Bidder certifies that it is aware of the registration requirements set forth in Labor Code Sections 1725.5 and 1771.1 and is currently registered as a Contractor with the Department of Industrial Relations.

Name of Bidder:

DIR Registration Number:

DIR Registration Expiration:

Bidder further certifies:

1. Bidder shall maintain a current DIR registration for the duration of the Project.

2. Bidder shall include the requirements of Labor Code S ections 1725.5 and 1771.1 in its Contract with Subcontractors and ensure that all Subcontractors are registered at the time of Bid opening and maintain registration status for the duration of the Project.

3. Failure to submit this form or comply with any of the above requirements may result in a finding that the Bid is non- responsive.

Signature: Date:

Name: Title:

END OF SECTION

00 45 25 CERTIFICATE OF INSURANCE Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 42 of 284 ends

00 45 25 CERTIFICATE OF INSURANCE
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

Bidder must attach either of the following to this page.

Certificates of insurance showing conformance with the requirements for each of:

a. Comprehensive General Liability
b. Automobile Liability
c. Workers Compensation
d. Employer’s Liability

Statement with an insurance carrier’s notarized signature stating that the carrier can, and upon payment of fees and/or premiums by the Bidder, will issue to the Bidder the required policies of insurance for Comprehensive General Liability, Automobile Liability, Workers Compensation and Employer’s Liability in conformance and the required Certificates of insurance to the Agency.

END OF SECTION

00 45 30 STATEMENT REGARDING DEBARMENT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 43 of 284 ends

00 45 30 STATEMENT REGARDING DEBARMENT
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

1. Have you or any of your Subcontractors ever been debarred as an irresponsible Bidder by another public agency in the State of California?

YES
NO

2. If yes, what was/were the name(s) of the public agency(ies) and what was/were the period(s) of debarment(s)? Attach additional copies of this page to accommodate more than 2 debarments.

__________________________________
party debarred

__________________________________
public agency

__________________________________
period of debarment

___________________________________
party debarred

___________________________________
public agency

___________________________________
period of debarment

BY CONTRACTOR:

By: __________________________________
(sign here)

___________________________________
(print name/title)

Page _____ of _____ pages of this Statement Regarding Debarment form

END OF SECTION

00 45 35 DISCLOSURE OF DISCIPLINE RECORD Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 44 of 284 ends

00 45 35 DISCLOSURE OF DISCIPLINE RECORD
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against c ontractors if a complaint regarding a l atent act or omission is filed within 4 years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation. Any questions concerning a Contractor may be referred to the Registrar, Contractors’ State License B oard, P.O. Box 26000, Sacramento, California 95826.

1. Have you ever had your c ontractor’s license suspended or revoked by the California Contractors’ State license Board 2 or more times within an 8-year period? YES
NO

2. Has the suspension or revocation of your contractor’s license ever been stayed? YES
NO
N/A

3. Have any Subcontractors that you propose to perform any portion of the Work ever had their contractor’s license suspended or revoked by the California Contractors’ State License Board 2 or more times within an 8-year period?
YES
NO

4. Has the suspension or revocation of the license of any Subcontractors that you propose to perform any portion of the Work ever been stayed?
YES
NO
N/A

00 45 35 DISCLOSURE OF DISCIPLINE RECORD Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 45 of 284 ends

5. If the answer to either of 1 or 3 above is “yes,” fully identify, in each and every case, the party disciplined, the date of and violation that the disciplinary action pertains to, the nature of the violation and disciplinary action taken.

(If needed attach additional sheets to provide full disclosure.)

6. If the answer to either of 2 or 4 above is “yes,” fully identify, in each and every case, the party whose discipline was stayed, the date of and the violation that the disciplinary action pertains to, the nature of the violation and the condition (if any) upon which the disciplinary action was stayed.

(If needed attach additional sheets to provide full disclosure.)

BY CONTRACTOR:

By: __________________________________
(sign here)

__________________________________
(print name and title)

END OF SECTION

00 52 00 CONTRACT Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 46 of 284 ends

00 52 00 CONTRACT
This Project No. 6072 (“Contract”) is made and entered into this ____________ day of ________________________________, 20___, by and between the City of Carlsbad (“Agency”) and ____________________________________ (“Contractor”), whose principal place of business is _______________________________________________________.

The parties agree:

1. SCOPE OF WORK.

The Contractor shall perform all Work within the time stipulated in the Contract, and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all the Work required in strict compliance with the Contract Documents for the following Project:

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

The Contractor and its surety shall be liable to the Agency for any damages arising as a result of the Contractor’s failure to comply with the obligation described in this Section 1.

2. TIME OF COMPLETION.

Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the Agency’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within one hundred thirty (130) Days from the commencement date stated in the Notice to Proceed. Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.

3. CONTRACT PRICE.

The Agency shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions made in accordance with the Contract Documents, and including all applicable taxes and costs, the sum of ___________________________________ Dollars ($ _____________________________). Payment shall be made as set forth in the General Conditions.

The Engineer will close the estimate of work completed for progress payments on the last working day of each month. The Agency shall withhold retention as required by Public Contract Code Section 9203.

4. LIQUIDATED DAMAGES.

In accordance with Government Code Section 53069.85, it is agreed that the Contractor will pay the Agency the sum set forth in Section 00 73 00 Supplemental General Provisions for each and every Calendar Day of delay beyond the time of completion prescribed in this Contract as Liquidated Damages and not as a penalty or forfeiture. If this sum is not paid, the Contractor

00 52 00 CONTRACT Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 47 of 284 ends

agrees the Agency may deduct that amount from any money due or that may become due the Contractor under the Contract. This Section does not exclude recovery of other damages specified in the Contract Documents.

5. CONTRACT DOCUMENTS.

The “Contract Documents” include the following:

● 00 11 10 Notice Inviting Bids
● 00 21 10 Instructions to Bidders
● 00 41 00 Bid Form
● 00 42 10 Bid Bond or 00 43 20 Bid Security
● 00 43 30 Proposed Subcontractors
● 00 43 40 Bidder Information and Experience
● 00 45 10 Non-Collusion Affidavit
● 00 45 15 Iran Contracting Act Certification
● 00 45 20 Public Works Contractor Registration Certification ● 00 45 30 Statement of Regarding Debarment
● 00 45 35 Disclosure of Discipline Record
● 00 52 10 Contract
● 00 61 10 Labor and Materials Bond
● 00 61 20 Faithful Performance and Warranty Bond
● 00 61 30 Optional Escrow Agreement (if applicable)
● 00 73 00 Supplemental Provisions to Part 1 of the Standard Specifications for Public Works Construction “Greenbook,” latest edition and including all errata ● Technical Specifications for the Project
● All Addenda
● Plans and Drawings
● Permits
● 00 74 00 Supplemental Provisions to Parts 2- 8 of the Standard Specifications for Public Works Construction “Greenbook,” latest edition and including all errata ● “City of Carlsbad Engineering Standard Drawings and Specifications,” as last revised ● Standard Plans for Public Works Construction, latest edition and including all errata ● Applicable Local Agency Standards and Specifications, as last revised ● Approved and fully executed change orders
● Any other documents contained in or incorporated by reference into the Contract Documents

00 52 00 CONTRACT Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 48 of 284 ends

The Contractor shall complete the Work in strict accordance with the Contract Documents. The requirements of the various sections or documents comprising the Contract Documents are intended to be complementary. Work required by 1 of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.

6. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE.

Every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, in cluding, but not limited to, the provisions of the Labor Code and Public Contract Code which are applicable to the Work.

7. INDEMNIFICATION.

Contractor shall provide indemnification and defense as set forth in the 00 73 00 Agency Supplemental General Provisions.

8. PREVAILING WAGES.

Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates may be obtained online at http://www.dir.ca.gov and which must be posted at the job site.
///

///

///

///

///

///

00 52 00 CONTRACT Date Printed: September 2, 2025
Document Version: 1.0 Current Update: May 2023

Page 49 of 284 ends

NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE ATTACHED

(CORPORATE SEAL)
CONTRACTOR City of Carlsbad

By: By:

(sign here)

[INSERT TITLE OF PERSON AUTHORIZED TO
SIGN]

(print name/title)
ATTEST:

By:

(sign here) for Sherry Freisinger, City Clerk

(print name/title)

If required by the Agency, proper notarial acknowledgment of execution by contractor must be attached. If a corporation, the Contract must be signed by 1 corporate officer from each of the following 2 groups.

Group A Group B
Chairman, Secretary,
President, or Assistant Secretary,
Vice-President CFO or Assistant Treasurer

Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation.

APPROVED AS TO FORM:

CINDIE K. McMAHON, City Attorney

BY: _____________________________
Assistant City Attorney

END OF SECTION

00 61 10 LABOR AND MATERIALS BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 50 of 284 ends

00 61 10 LABOR AND MATERIALS BOND
KNOW ALL PERSONS BY THESE PRESENTS THAT:

WHEREAS, the City of Carlsbad ( “Agency”) has awarded to (“Principal,”) a Contract for the Work described as follows:

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated by this reference; and

WHEREAS, Principal is required to furnish a bond in connection with the Contract providing that if Principal or any of its Subcontractors fail to pay (1) for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the Work contracted to be done, (2) for any Work or labor of any kind performed under the Contract, (3) for amounts due under the Unemployment Insurance Code for any Work or labor of any kind performed under the Contract, or (4) for any amounts required to be deducted, withheld, and paid over to the Employment Development Department under Unemployment Insurance Code Section 13020 or to the Franchise Tax Board under Revenue and Taxation Code Section 18663 from the wages of employees of Principal and its Subcontractors with respect to the Work or labor, the Surety on this bond will pay for the same to the extent set forth below.

NOW THEREFORE, we, Principal and , as Surety, are held and firmly bound unto the Agency in the penal sum of
Dollars ($___________), for the payment of which sum being an amount equal to 100% of the total amount payable under the terms of the Contract by the Agency, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if Principal, or its Subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code Section 9100; fail to pay for any materials, provisions , provender, equipment, or other supplies, used in, upon, for or about the performance of the Work contracted to be done; fail to pay for any Work or labor of any kind performed under the Contract; fail to pay amounts due under the Unemployment Insurance Code for any Work or labor of any kind performed under the Contract; or fail to pay for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of Principal or its Subcontractors pursuant to Unemployment Insurance Code Section 13020 or Revenue and Taxation Code Section 18663, with respect to the Work or labor, then the Surety will pay for the same, in an amount not exceeding the penal sum specified above, and also, in

00 61 10 LABOR AND MATERIALS BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 51 of 284 ends

case suit is brought upon this bond, all litigation expenses incurred by the Agency in the suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses to be fixed by the court consistent with Civil Code Section 9554.

This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond. The Surety stipulates and agrees that this bond shall not be exonerated or released from the obligation of this bond by:

1. Any change, extension of time for performance, addition, alteration or modification in, to, or of any Contract, Plans, Specifications, or agreement pertaining or relating to any scheme or Work of improvement described above, or the furnishing of labor, materials, or equipment pertaining or relating to any scheme or Work of improvement described above.

2. Any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or Work of improvement describe d above.

3. Any rescission or attempted rescission or attempted rescission of the Contract, agreement or bond.

4. Any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such Contract or agreement or under the bond.

5. Any fraud practiced by any person other than the claimant seeking to recover on the bond.

The Surety also stipulates and agrees that this bond shall be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit this bond has been given by reason of any breach of contract between the Agency and Principal or on the part of any obligee named in this bond. Finally, the Surety waives notice of any such change, extension of time, addition, alteration or modification mentioned in this bond, including but not limited to the provisions of Civil Code Sections 2819 and 2845.

If Principal is an individual, it is agreed that the death of any such Principal shall not exonerate the Surety from its obligations under this bond.

00 61 10 LABOR AND MATERIALS BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 52 of 284 ends

[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]

00 61 10 LABOR AND MATERIALS BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 53 of 284 ends

Executed by PRINCIPAL this _________
day of _______________________, 20____.

PRINCIPAL:

____________________________________
(name of Contractor)

By:_________________________________
(sign here)

____________________________________
(print name here)

____________________________________
(title and organization of signatory)

Executed by SURETY this ____________ day
of _______________________, 20____.

SURETY:

____________________________________
(name of Surety)

____________________________________
(address of Surety)

____________________________________
(telephone number of Surety)

By:
____________________________________
(signature of Attorney-in-Fact)

____________________________________
(printed name of Attorney-in-Fact)
(attach corporate resolution showing current
power of attorney)

(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)

(President or vice -president and secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.)

APPROVED AS TO FORM:

CINDIE K. McMAHON, City Attorney

BY: _____________________________
Assistant City Attorney

END OF SECTION

00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 54 of 284 ends

00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND
KNOW ALL PERSONS BY THESE PRESENTS THAT:

WHEREAS, the City of Carlsbad ( “Agency”) has awarded to ________________ ( “Principal,”) a Contract for the Work described as follows:

NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated by this reference; and

WHEREAS, the Work to be performed by the Principal is more particularly set forth in the Contract Documents for the Project dated ____________, (“Contract Documents”), the terms and conditions of which are incorporated by reference; and

WHEREAS, the Principal is required by the Contract Documents to perform the terms of them and to furnish a bond for the faithful performance and warranty of the Contract Documents.

NOW THEREFORE, we, Principal, and
,as Surety, are held and firmly bound unto the Agency in the penal sum of dollars ($ ____________),
which is equal to 100% of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that, if Principal, its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration of the Contract Documents made as provided in the Contract Documents, on its part, to be kept and performed at the time and in the manner specified in the Contract Documents, and in all respects according to their true intent and meaning; and shall indemnify and save harmless the Agency, its Board, members of the Board, officers, directors, managers, employees, agents, and authorized volunteers, as stipulated in the Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a part of the obligation secured by this bond and in addition to the face amount specified in this bond, there shall be included costs and reasonable expenses and fees, including reasonable attorneys’ fees, incurred by Agency in enforcing such obligation, all to be taxed as costs and included in any judgment rendered.

00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 55 of 284 ends

As a condition precedent to the satisfactory completion of the Work unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of 1 year after the acceptance of the Work by the Agency. During this 1-year period, if Contractor fails to make full, complete, and satisfactory repair and replacements and totally protect the Agency from loss or damage resulting from or caused by defective materials or faulty workmanship in connection with Contractor’s Work on the Project, the obligations of Surety under this bond shall continue so long as any obligation of Principal remains to the Agency. Nothing in this bond shall limit the Agency’s rights or the Principal’s or Surety’s obligations under the Contract, law or equity, including, but not limited to, Code of Civil Procedure Section 337.15.

Whenever Principal shall be, and is declared by the Agency to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the Agency’s option:

i. Take over and complete the Project in accordance with all terms and conditions in the Contract Documents;

ii. Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a c ontract between such bidder, the Surety and the Agency, and make available as Work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the Contract Price, including other costs and damages for which Surety may be liable. The term “balance of the Contract Price” as used in this paragraph shall mean the total amount payable to Principal by the Agency under the Contract and any modification to the Contract, less any amount previously paid by the Agency to the Principal and any other set offs pursuant to the Contract Documents.

Or

iii. Permit the Agency to complete the Project in any manner consistent with Applicable Law and make available as Work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the Contract Price, including other costs and damages for which Surety may be liable. The term “balance of the Contract Price” as used in this paragraph shall mean the total amount payable to Principal by the Agency under the Contract and any modification to the Contract, less any amount previously paid by the Agency to the Principal and any other set offs pursuant to the Contract Documents.

Surety expressly agrees that the Agency may reject any c ontractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Principal.

Surety shall not utilize Principal in completing the Project, nor shall Surety accept a bid from Principal for completion of the Project, if the Agency, when declaring the Principal in default, notifies Surety of the Agency’s objection to Principal’s further participation in the completion of the Project.

00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 56 of 284 ends

The Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed under the Contract Documents shall in any way affect Surety’s obligations on this bond, and Surety waives notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project.

If Principal is an individual, it is agreed that the death of any such Principal shall not exonerate the Surety from its obligations under this bond.

[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]

00 61 20 FAITHFUL PERFORMANCE AND WARRANTY BOND Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 57 of 284 ends

Executed by PRINCIPAL this _________ day of
________________________, 20___.

PRINCIPAL:
____________________________________
(name of Contractor)

By:_________________________________
(sign here)
____________________________________
(print name here)
____________________________________
(title and organization of signatory)

Executed by SURETY this ____________ day
of ________________________, 20___.

SURETY:
____________________________________
(name of Surety)
____________________________________
(address of Surety)
____________________________________
(telephone number of Surety)

By: _________________________________
(signature of Attorney-in-Fact)
____________________________________
(printed name of Attorney-in-Fact)

(attach corporate resolution showing current
power of attorney)

(Proper notarial acknowledgment of execution by CONTRACTOR and SURETY must be attached.)

(President or vice -president and secretary or assistant secretary must sign for corporations. If only 1 officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering that officer to bind the corporation.)

APPROVED AS TO FORM:

CINDIE K. McMAHON, City Attorney

BY: _____________________________
Assistant City Attorney

END OF SECTION

00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 58 of 284 ends

00 61 30 OPTIONAL ESCROW AGREEMENT
NAME OF PROJECT: El Camino Real Widening From Poinsettia Lane to Camino Vida Roble CONTRACT NO.: 6072
BID NO.:PWS25-XXXXTRAN

NAME OF BIDDER:

This Escrow Agreement is made and entered into by and between the 1200 Carlsbad Village Drive, Carlsbad, California, 92008 ("Agency"), whose address is
("Contractor") and whose address is
( "Escrow Agent").

Agency, Contractor and Escrow Agent agree as follows:

1. Pursuant Public Contract Code Section 22300, Contractor has the option to deposit securities with Escrow Agent as a substitute for retention earnings required to be withheld by Agency pursuant to the construction contract entered into between Agency and Contractor for El Camino Real Widening From Poinsettia Lane to Camino Vida Roble in the amount of ___________ dated __________ ("Contract"). Alternatively, on written request of Contractor, Agency shall make payments of the retention earnings directly to Escrow Agent.

When the Contractor deposits the securities as a substitute for Contract earnings, Escrow Agent shall notify Agen cy within 10 Calendar D ays of the deposit. The market value of the securities at the time of the substitution shall be at least equal to the cash amount then required to be withheld as retention under the terms of the Contract. Securities shall be held in Agency’s name and shall designate Contractor as the beneficial owner.

2. Agency shall make progress payments to Contractor for those funds which otherwise would be withheld from progress payments pursuant to the Contract provisions, provided that Escrow Agent holds securities in the form and amount specified above.

3. When Agency makes payment of retentions earned directly to Escrow Agent, Escrow Agent shall hold them for the benefit of Contractor until the time that the escrow created under this Escrow Agreement is terminated. The Contractor may direct the investment of the payments into securities. All terms and conditions of this Escrow A greement and the rights and responsibilities of the parties shall be equally applicable and binding when Agency pays Escrow Agent directly.

4. Contractor shall be responsible for paying all fees for the expenses incurred by Escrow Agent in administering the Escrow Account and all expenses of Agency. These expenses and payment terms shall be determined by Agency, Contractor, and Escrow Agent.

5. The interest earned on the securities or the money market accounts held in escrow and all interest earned on that interest shall be for the sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to Agency.

6. Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow Agent accompanied by written authorization from

00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 59 of 284 ends

Agency to Escrow Agent that Agency consents to the withdrawal of the amount sought to be withdrawn by Contractor.

7. Agency shall have a right to draw upon the securities in the event of default by the Contractor.

Upon 7 Calendar Days' written notice to Escrow Agent from Agency of a default, Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as instructed by Agency.

8. Upon receipt of written notification from the Agency certifying that the Work required by the Contract is final and complete and that Contractor has complied with all requirements and procedures applicable to the Contract, Escrow Agent shall release to Contractor all securities and interest on deposit less escrow fees and charges of Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges.

9. Escrow Agent shall rely on the written notifications from Agency and Contractor pursuant to Sections (5) to (8), inclusive, of this Escrow Agreement and Agency and Contractor shall hold Escrow Agent harmless from Escrow Agent's release, conversion and disbursement of the securities and interest as set forth above.

10. The names of the persons who are authorized to give written notices or to receive written notice on behalf of Agency and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:

For Agency
(Finance
Director)

Title _________________________________________________________

Name
_____________________________________________________________

Signature
_____________________________________________________________

Address
_____________________________________________________________

For Contractor

Title
_____________________________________________________________

Name
_____________________________________________________________

Signature
_____________________________________________________________

00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 60 of 284 ends

Address
_____________________________________________________________

For Escrow
Agent

Title
_____________________________________________________________

Name
_____________________________________________________________

Signature
_____________________________________________________________

Address
_____________________________________________________________

At the time the Escrow Account is opened, Agency and Contractor shall deliver to the Escrow Agent a fully executed counterpart of this Escrow Agreement.

IN WITNESS WHEREOF, the parties have executed this Escrow Agreement by their proper officers on the date first set forth above.

For Agency Title
______________________________________________________________

Name
______________________________________________________________

Signature
______________________________________________________________

Address
______________________________________________________________

For Contractor

Title
______________________________________________________________

00 61 30 OPTIONAL ESCROW AGREEMENT Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 61 of 284 ends

Name
______________________________________________________________

Signature
______________________________________________________________

Address
______________________________________________________________

For Escrow
Agent

Title
______________________________________________________________

Name
______________________________________________________________

Signature
______________________________________________________________

Address
______________________________________________________________

APPROVED AS TO FORM:

CINDIE K. McMAHON, City Attorney

BY: _____________________________
Assistant City Attorney

END OF SECTION

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 62 of 284 ends

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS

INTRODUCTION
The specifications contained in this 00 73 00 Agency Supplemental General Provisions take precedence over the specification language contained in the Standard Specifications for Public Works Construction, “The Greenbook,” latest edition and all errata. This specification addresses the unique conditions in Carlsbad that are not addressed in The Greenbook . Therefore, if there is a conflict, these specifications shall control.

The Greenbook may be purchased at Bidder ’s/Contractor’s local technical bookstore or directly from the publisher. These Supplemental General Provisions are available only for download from the online bidding portal with Contract Documents. The Agency does not provide hard copies.

When used in the Contract Documents, statements, or command phrases (active voice and imperative mood) refer to and are directed at the “Bidder” or “Contractor” as applicable. The specifications are written to the “Bidder” before award and the “Contractor” after award. Before award, interpret sentences written in the imperative mood as starting with “The Bidder shall .” Interpret the term “you” as “the Bidder” and interpret the term “your” as “the Bidder’s .” After award, interpret sentences written in the imperative mood starting with “The Contractor shall. ” Interpret the term “you” as “the Contractor” and interpret the term “your” as “the Contractor’s.” PART 1 GENERAL PROVISIONS
SECTION 1 – GENERAL
1-1 GENERAL
ADD the following:

1. The word “provide” shall mean “furnish and install,” unless otherwise stated.

2. In reference to Drawings, where words “shown,” “indicated ,” “detailed ,” “noted ,” “scheduled,” or words of similar import are used, it shall be understood that reference is made to the Plans accompanying these provisions, unless stated otherwise.

3. Where the words “equal ,” “approved equal ,” “equivalent,” and words of similar import are used, it shall be understood such words are followed by the expression “in the opinion of the Engineer,” unless otherwise stated.

4. The word “perform” shall be understood to mean that the Contractor, at its expense, shall “perform all operations and furnish labor, tools and equipment,” and further, “furnish and install materials that are indicated, specified or required” shall be understood to mean that the Contractor, at its expense, shall “furnish and install the Work, complete in place and ready to use, including furnishing of necessary labor, materials, tools, equipment, and transportation.”

5. Where words “directed,” “designated,” “selected,” or words of similar import are used, it shall be understood that the direction, designation, or selection of the Engineer is intended, unless stated otherwise. The word “required” and words of similar import shall be understood to mean “as required to properly complete the Work as required and as approved by the Engineer,” unless stated otherwise.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 63 of 284 ends

Where the words “approved,” “approval,” “acceptance,” or words of similar import are used, it shall be understood that the approval, acceptance, or similar import of the Engineer is intended.
1-2 TERMS AND DEFINITIONS
Where applicable ADD/REPLACE the following:

Agency - The City of Carlsbad or the Carlsbad Municipal Water District, the o wner of the Project.

Agency Approval - Except where stated in this Contract to the contrary, the phrases “Agency approval,” and “Agency’s written approval” or such similar phrases shall mean approval by the City Manager for the City of Carlsbad or the Executive Manager for the Carlsbad Municipal Water District, which approval shall not be unreasonably withheld.

Agency Forces – City of Carlsbad or Carlsbad Municipal Water District employees who perform construction work.

Agency Supplement - 00 73 00 Agency Supplemental General Provisions; and 00 74 00 Agency Supplemental Technical Provisions.

Allowance (AL) - Payment under Allowance Bid items, denoted as “AL,” shall be based on the actual expenditures and for pre -authorized items of the Work in accordance with the Contract Documents. The unused portions of the Allowances shall revert to the Agency upon acceptance of the Project or Work.

Apparent Low Bidder - The Bidder whose Bid having been publicly opened, initially meets the material requirements of the Bid Documents and whose Bid price is the lowest received.

Applicable Laws - Laws, statutes, ordinances, rules, orders, and regulations of governmental authorities and courts having jurisdiction over the Project.

As-Builts - The CADD drawings prepared from the approved Red -lines for record keeping purposes.

Award of Contract (Award) - The date on which the Board or designee executes the Contract.

Bid - Any proposal submitted to the Agency in competitive bidding for the construction, alteration, repair, or improvement of any structure, building, road or other improvement of any kind.

Board – The officer or body constituting the awarding authority of the Agency, which is the City Council for the City of Carlsbad or the Board of Directors for the Carlsbad Municipal Water District.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 64 of 284 ends

Board of Directors for the Carlsbad Municipal Water District – The legislative body that governs the Carlsbad Municipal Water District and has the authority to pass ordinances and appropriate funds.

Business Day - See Working Day.

Calendar Day – Every day on the calendar, including weekends and holidays.

City - The term “City” or “the City” means, City of Carlsbad. See also Agency.

City Council - The legislative body that governs the City of Carlsbad and has the authority to pass ordinances and appropriate funds.

City Engineer - The term “ City E ngineer” is defined as the Transportation Director, or designee, and is the person authorized to perform the functions of the City E ngineer as defined in Government Code Section 66416.5. The City Engineer is the City's "duly authorized officer" for the purposes of Public Contract Code Sections 4107 and 4107.5.

City Manager – The appointed official who directs the administration of the City of Carlsbad.

Construction Documents - Plans and details, including Plans showing installation of major systems, equipment, fixed furnishings and graphics, the technical specifications and all other technical drawings, schedules, diagrams and specifications, accepted Shop Drawings, Working Drawings, and submittals that are necessary to set forth in detail the requirements for the Project.

Construction Manager – The Project Inspector’s immediate supervisor and the Engineer’s designated representative for the first level of appeal for informal dispute resolution.

Construction Work - The portion of the Work to construct the Project as set forth in the Contract Documents in conformance with 2-1, “WORK TO BE DONE.”

Contract – The written agreement between the Agency and the Contractor covering the Work.

Contract Documents - Contract Documents include the following: The signed Contract, Addenda, Notice Inviting Bids, funding agency provisions, Bid including documentation accompanying the Bid and any post -Bid documentation submitted prior to the Notice of Award when attached as an exhibit to the Contract, Bonds, Permits, CEQA documents, Standard Specifications (the “ Greenbook”), Agency Supplement, Plans, Standard Plans, Construction Documents, Reference Specifications, and Change Orders. Contract Documents, when applicable, shall also include Site and Coastal development permits, NEPA documents,

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 65 of 284 ends

re-vegetation plans, biological letters or technical reports, habitat mitigation plans, storm water documents, and local, state, and federal resource agency permits.

Contract Time - The number of Working Days to complete the Work as specified in the Contract Documents.

Contractor – The individual, partnership, corporation, joint venture, or other legal entity having a Contract with the Agency to perform the Work. In the case of Work being done under permit issued by the Agency, the permittee shall be constructed to be the Contractor. The term “prime contractor” shall mean Contractor.

Critical Path – In the Construction Schedule, the sequence of activities that represents the longest path through the Project network of activities and the shortest possible Project duration.

Days – Days shall mean consecutive calendar days unless otherwise specified in this Contract.

Defective Work - Work that does not conform to the Contract Documents.

Delay Factor - The Delay Factor may be the basis for compensation for idle equipment time on an excusable delay. The factor has been calculated to include the ownership costs without including operating costs. The Delay Factor recovers all the Contractor’s non-operating costs in an 8-hour day. If payment is made for equipment on an excusable delay, it is limited to 8 hours per day or 40 hours per week maximum.

Deputy City Engineer – The Engineering Manager of the Construction Management & Inspection Division and the Construction Manager’s immediate supervisor and the Engineer’s designated representative for the second level of appeal for informal dispute resolution.

Dispute Board – Persons designated by the City Manager of the City of Carlsbad or Executive Manager of the Carlsbad Municipal Water District, to hear and advise the City Manager or Executive Manager on claims submitted by the Contractor. The City Manager for the City o f Carlsbad or the Executive Manager for the Carlsbad Municipal Water District is the last appeal level for informal dispute resolution.

Drawings - See Plans.

D-size Sheet - “D” size paper for engineering design applications refers to 22” x 34” paper.

Engineer - The Deputy City Manager, Public Works of the City of Carlsbad acting either directly or through designated representatives and the third level of appeal for informal dispute resolution.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 66 of 284 ends

Engineer of Record/Design Engineer – A registered Professional Engineer licensed in the State of California who is qualified to act as an agent of a Project Owner or to prepare Plans for facilities to be accepted by the City of Carlsbad or the Carlsbad Municipal Water District.

The term includes persons licensed in the State of California as Civil Engineers or Structural Engineers, as well as other licensed professionals like Architects and Landscape Architects.

Executive Manager – The appointed official who directs the administration of the Carlsbad Municipal Water District.

Field Book - The Agency field maps showing sewer and water facilities.

Field Order - A Field Order is a written agreement by the Engineer to compensate the Contractor for work items in accordance with 2 -8, “EXTRA WORK” or 2 -9, “CHANGED CONDITIONS.” A Field Order does not change the Contract Price or Contract Time or the intent of the Contract. The unused portions of the Field Orders shall revert to the Agency upon acceptance of the Work.

Final Environmental Document - The CEQA and/or NEPA document issued for the Project, such as certified environmental impact reports, mitigated negative declarations (MNDs), negative declarations, or exemptions.

Final Payment - The last payment for the Contract made to the Contractor, excluding Retention.

Float – The number of days by which an activity in the Construction Schedule may be delayed from either its earliest start date or earliest completion date without extending the Contract Time (total float). Total float belongs to the Project and to any Party to accommodate changes in the Work or to mitigate the effect of events which may delay completion .

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 67 of 284 ends

Holiday - Holidays observed by the Agency are listed below:

Holiday Observed On
New Year’s Day January 1
Martin Luther King Day 3rd Monday in January
Presidents’ Day 3rd Monday in February
Juneteenth June 19
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1st Monday in September
Indigenous Peoples’ Day 2nd Monday in October
Veteran’s Day November 11
Thanksgiving Day 4th Thursday/Friday in
November
Christmas Day December 25
If any Holiday listed falls on a Saturday, the Saturday and the preceding Friday are both legal Holidays. If the Holiday falls on a Sunday, both Sunday and the following Monday shall be legal Holidays. Unless specified otherwise in the Contract Documents or authorized by the Engineer, do not work on Holidays.

Limited Notice to Proceed (LNTP) - A written notice given from the Agency that authorizes the Contractor to start a limited amount of work that, as described in the notice, is not Construction Work.

Minor Bid Item – a single contract item constituting less than 10 percent (10%) of the original Contract Price bid.

Night Work - See Working Night.

Normal Working Hours - Unless specified otherwise, Normal Working Hours core periods shall be 8 :00 AM to 4 :00 PM, Monday through Friday, inclusive. Saturdays, Sundays, and Agency Holidays are excluded. For Traffic Control Permits, Normal Working Hours are defined as 8:30 AM to 3:30 PM, unless specified otherwise.

Notice of Completion (NOC) - A document recorded with the County of San Diego to signify that the Work has been completed and accepted by the Agency.

Party or Parties - The Agency, the Contractor, or both, their respective permitted successors or assigns, and any other future signatories to the Contract.

Plans – The drawings, profiles, cross sections, Standard Plans, working drawings, and shop drawings, or reproductions thereof, approved by the City Engineer, which show the location, character, dimensions or details of the Work.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 68 of 284 ends

Prime Contractor - See Contractor.

Project Inspector – the Engineer’s designated representative for inspection, Contract administration and the first level for informal dispute resolution.

Project Site (Site) - Areas where the Work is performed pursuant to the Contract.

Punchlist - A list of items of Work or corrections generated after a Walk -through that is conducted when the Contractor considers that the Work and Services are complete.

Quality Control Standards and Procedures - The standards and procedures that are stated in a written manual that can be furnished to the Engineer upon request. The standards and procedures are followed by the Supplier in the production of materials supplied for the Work Site.

Red-lines - Plans with annotations of changes made during construction to reflect the actual improvements or facilities built during construction whether concealed or visible.

Retention - The amount withheld from the money due to the Contractor in accordance with 7-3.2, “PARTIAL AND FINAL PAYMENT.”

Samples - Physical examples of the materials, equipment, or workmanship specified or required and which conform with the standards and specifications in the Contract Documents and by which the Work shall be evaluated.

Schedule - A Critical Path Method (CPM) schedule of construction activities and their durations to be performed during the Contract Time and prepared by the Contractor in accordance with 6 -1, “CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK ,” and accepted by the Engineer.

Scope of Work (SOW ) - Labor, materials, equipment, facilities, and services required to be performed or provided by the Contractor to complete the entire Project or the various separately identifiable parts of the Project pursuant to the provisions of the Contract Documents.

Services - Work performed in connection with the layout, construction, testing, inspection, and commissioning of the Work or administration of the Contract and which may include professional services such as engineering, surveying, construction management and lega l services that are required in accordance with the Contract Documents. Services are incidental to the Work.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 69 of 284 ends

Separate Contractors - Those individuals or entities that have entered into arrangements with the Agency for the provision of labor, materials, or other services in connection with the Project who are not under contract with the Contractor.

Signal Pre-Check - The procedure that the City uses to evaluate traffic signal systems prior to Signal Turn-On and generating a Punchlist.

Signal Turn-On - The day the City activates new traffic signals.

SMARTS - Stormwater Multiple Application and Report Tracking System (SMARTS) Resources provides a platform where dischargers, regulators, and the public can enter, manage, and view storm water data including permit registration documents, compliance, and monitoring data associated with California's Storm Water General Permits.

Supplemental Provisions – See Agency Supplement.

Tonne – Also referred to as “metric ton .” Represents a unit of measure in the International System of Units equal to 1,000 kilograms.

Walk-through - The procedure the Agency uses to evaluate the status of the Project and to generate a Punchlist prior to acceptance of the Work.

Work – A ll labor, materials, equipment, tools, and services and other requirements of the Contract Documents as modified by Change Order, whether completed or partially completed, provided or to be provided by Contractor to fulfill Contractor’s obligations. The Work may constitute the whole or a part of the Project.

Working Day - Any day within the period between the start of the Contract time as defined in Section 6-1 and the date provided for completion, or upon field acceptance by the Engineer for all work provided for in the Contract, whichever occurs first, other than:
• Saturday;
• Sunday;
• any day designated as a holiday by the Agency;
• any other day designated as a holiday in a Master Labor Agreement entered into by the Contractor or on behalf of the Contractor as an eligible member of a contractor association;
• any day the Contractor is prevented from working at the beginning of the workday for cause as defined in Section 6-6.1; or
• any day the Contractor is prevented from working during the first 5 hours with at least 60 percent of the normal work force for cause as defined in Section 6-6.1.

Working Night (Night Work) - A period of nighttime work, allowed only on Sunday through Thursday, excluding Holidays.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 70 of 284 ends

Work Site - See Project Site (Site).
1-3 ABBREVIATIONS
1-3.2 Common Usage.

ADD the following:

AML Approved Material List
CADD Computer Aided Design and Drafting
CA MUTCD California Manual on Uniform Traffic Control Devices CCT Correlated Color Temperature
CEQA California Environmental Quality Act.

CFR Code of Federal Regulations
CGP Construction General Permit
CIPM Cured-In-Place-Manhole
CL Centerline
CMS Content Management System Database
CNC Computer Numerical Control
CRI Color Rendering Index
CSA Canadian Standards Association
DBE Disadvantaged Business Enterprise
DCE Data Computer Equipment
DG Decomposed Granite
DVBE Disabled Veteran Business Enterprise
DWT Detectable Warning Tiles
EOW Engineer of Work
ESL Environmentally Sensitive Lands
ESO Electrical Service Orders
FRP Fiberglass Reinforced Plastic
GFE Good Faith Effort
GMT Greenwich Mean Time
GPS Global Positioning System
IDA International Dark Sky Association
IP Ingress Protection
LCD Liquid Crystal Display
LD Laser Diode
LER Luminaire Efficiency Rating
MBE Minority Business Enterprise
MDFT Minimum Dry Film Thickness
MHPA Multiple Habitat Planning Area
MH Manhole
MIL Military
MJ Mechanical Joint
M&M Maintenance and Monitoring

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 71 of 284 ends

MMC Mitigation and Monitoring Coordination
MOV Metal Oxide Varistor
NA Numerical Aperture
NC Not Connected, Normally Closed
NEPA National Environmental Policy Act of 1969
NEXT Near End Crosstalk
NCHRP National Cooperative Highway Research Program
NOC Notice of Completion
NPDES National Pollutant Discharge Elimination System
NTP Notice to Proceed
OC On Center
ODP Open Drip Proof
OFNR Optical Fiber Nonconductive Riser
OTDR Optical Time Domain Reflectometer
PB Pull Box
PCMS Portable Changeable Message Signs
PCU Photoelectric Control Unit
PEP Plant Establishment Period
PIC Polyethylene Insulated Cable
PL Property Line
RFP Request for Proposal
RFI Request for Information
RPMS Rubber Polymer Modified Slurry
SIC Standard Industry Classification
SMS Short Message Service
SMTP Simple Mail Transfer Protocol
SOW Statement of Work, Scope of Work
SOV Schedule of Values
SPDT Single Pole Double Throw
SSD Surge Suppression Devices
TDR Time Domain Reflectometer
TEES Transportation Electrical Equipment Specifications TFFN Thermoplastic Flexible Fixture Wire Nylon Jacketed TIG Tungsten Inert Gas
UF Underground Feeder
UPRR Union Pacific Railroad Company
VAC Volts AC
VPC Vitrified Polymer Composite
WBE Women Business Enterprise
1-3.3 Institutions.

ADD the following:

AMTRACK American Track National Railroad Passenger Corp.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 72 of 284 ends

ANSI American National Standards Institute
AASHTO American Association of State Highway and Transportation Officials AISC American Institute of Steel Construction
ANSI American National Standards Institute
API American Petroleum Institute
AREA American Railway Engineering Association
ASTM American Society for Testing and Materials
AWPA American Wood Preservers Association
AWS American Welding Society
AWWA American Water Works Association
BNSF Burlington Northern Santa Fe Railway
DSD Development Services Department
FHWA Federal Highway Administration
GRI Geosynthetic Research Institute
IPCEA Insulated Power Cable Engineers Association
IES Illuminating Engineering Society (Photometric Data) ISO International Organization for Standardization
MTS San Diego Metropolitan Transit System
NACE National Association of Corrosion Engineers
NAFP National Association of Pipe Fabricators
NCTD North County Transit District
NEMA National Electrical Manufacturers Association
NOAA National Oceanic and Atmospheric Administration (Dept. of Commerce) NFPA National Fire Protection Association
PCI Prestressed Concrete Institute
SANDAG San Diego Association of Governments
SD&AE San Diego & Arizona Eastern Railroad
SDTI San Diego Trolley, Inc.

UL Underwriters’ Laboratories Inc.

USGS United States Geological Survey
UPRR Union Pacific Railroad Company
1-6 BIDDING AND SUBMISSION OF THE BID
1-6.2 Subcontractor Listing.

ADD the following:

Each Bidder shall comply with the Chapter of the Public Contract Code including Sections 4100 through 4113. The use of Subcontractors in no way relieves the Contractor of any obligations or responsibilities under the Contract.

The following excerpts or summaries of some of the requirements of this Chapter are included below for information:

The Bidder shall set forth in the Bid, as provided in Section 4104:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 73 of 284 ends

“(a) The name and location of the place of business of each Subcontractor who will perform Work or Labor or render service to the prime Contractor in or about the construction of the Work or improvements, or a Subcontractor licensed by the State of California who, under Subcontract to the prime Contractor, specially fabricates and installs a portion of the Work or improvement according to detailed Drawings contained in the Plans and Specifications, in an amount in excess of one-half of 1 percent of the prim e Contractor’s total Bid, or, in the case of Bids or offers for the construction of streets or highways, including bridges, in excess of one -half of 1 percent of the prime Contractor’s total Bid or ten thousand dollars ($10,000), whichever is greater.”

“(b) The portion of the Work which will be done by each such Subcontractor under this act. The prime Contractor shall list only one Subcontractor for each such portion as is defined by the prime Contractor in his Bid.”

If the Contractor fails to specify a Subcontractor or specifies more than one Subcontractor for the same portion of the Work to be performed under the Contract (in excess of one-half of 1 percent of the Contractor’s total Bid), the Contractor shall be qualified to perform that portion itself, and shall perform that portion itself, except as otherwise provided in the Code.

As provided in Section 4107, no Contractor whose Bid is accepted shall substitute any person as Subcontractor in place of the Subcontractor listed in the original Bid, except for causes and by procedures established in Section 4107.5. This section provides procedures to correct a clerical error in the listing of a Subcontractor.

Section 4110 provides that a Contractor violating any of the provisions of the Chapter violates the Contract and the Board may exercise the option either to cancel the Contract or assess the Contractor a penalty in an amount of not more than 10 percent of the Subcontract involved, after a public hearing.
1-7 AWARD AND EXECUTION OF THE CONTRACT
1-7.1 General.

DELETE in its entirety and SUBSTITUTE with the following:
1-7.1 Standard Contract Provisions.
1-7.1.1 Successor’s Obligations.

All grants, covenants, provisions and claims, rights, powers, privileges and abilities contained in the Contract Documents shall be read and held as made by and with, and granted to and imposed upon, the Contractor, the Agency, and the Contractor’s and the Agency’s respective heirs, executors, administrators, successors, and assigns. 1-7.1.2 Waiver of Legal Rights.

1. The Agency’s failure to insist, in any 1 or more instances, upon the performance of any provision of the Contract, or to exercise any right therein, shall not be construed as a waiver or relinquishment of such provisions or rights.

2. Any waiver of any breach of the Contract shall not be held to be a waiver of any other or subsequent breach.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 74 of 284 ends

3. Any waiver the Agency issues to any provision of the Contract shall only be effective if it is agreed upon in writing by the Agency and if it is specific to the matter concerned. 1-7.1.3 Requests for Information (RFI).

1. Inquiries from the Contractor seeking clarification of the requirements of the Contract Documents shall be submitted in writing to the Agency as a Request for Information (RFI).
1-7.1.4 Assignment to Awarding Body.

1. In accordance with subdivision (b) of Public Contract Code Section 7 103.5, the Contractor and the Contractor’s Subcontractors shall conform to the following requirements:
a. In entering into a public works c ontract or a subcontract to supply goods, services, or materials pursuant to a public works c ontract, the Contractor or the Contractor’s Subcontractor offer and agree to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Business and Professions Code Section 16700 et seq.) arising from purchases of goods, services, or materials pursuant to the public works c ontract or the subcontract.
b. This assignment shall be made and become effective at the time the awarding body tenders to the Contractor, without further acknowledgment by the Parties.
1-7.2 Contract Bonds.

ADD the following:

1. Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below. Bonds issued by a Surety, who is authorized to issue bonds in California, and whose bonding limitation shown in the circular is enough to provide bonds in the amount required by the Contract shall be deemed approved unless specifically rejected by the Agency. Bonds from all other sureties shall be accompanied by all documents enumerated in Code of Civil Procedure S ection 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.

2. Each bond shall incorporate, by reference, the Contract and be signed by both the Bidder and Surety and the signature of the authorized agent of the Surety shall be notarized.

3. The faithful performance/warranty bond will be reduced to 25 percent of the original amount 30 Calendar Days after recordation of the Notice of Completion and will remain in full force and effect for the 1-year warranty period and until all warranty repairs are completed to the satisfaction of the Engineer. The bond to secure payment of laborers and materials suppliers shall be released 6 months plus 30 Calendar D ays after recordation of the Notice of Completion if all claims have been paid.

4. All bonds are to be placed with a Surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed its liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to contain the following documents:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 75 of 284 ends

a. An original, or a certified copy, of the unrevoked appointment, power of attorney, bylaws, or other instrument entitling or authorizing the person who executed the bond to do so.
b. A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.

5. If the Bid is accepted, the Agency may require a financial statement of the assets and liabilities of the Surety for the quarter calendar year preceding the date of the execution of the bond.

The financial statement shall be made by an officer’s certificate as defined in Corporations Code Section 173. In the case of a foreign Surety, the financial statement may be verified by the oath of the principal officer or manager residing within the United States.

6. If the Surety on any bond furnished by the Contractor is declared bankrupt, becomes insolvent, or its right to do business is terminated in any state where any part of the Project is located, immediately notify the Engineer; and immediately substitute anot her bond and Surety acceptable to the Agency.

7. The Contractor shall require the Surety to mail its standard “Bond Status” form to the Agency.

ADD 1- 7.2.1 Payment.

1. If enumerated in the Contract Documents, the Bid item for “Bonds (Payment and Performance)” includes full compensation for actual costs of payment and performance bonds. The Contractor may submit a request for payment of actual invoiced costs up to the Bid amount, but not to exceed 2.5% of the Contract Price, no less than 10 Working Days after the award of the Contract.

2. If enumerated in the Contract Documents, if the Bid item for “Bonds (Payment and Performance)” exceeds actual invoiced costs, any such differential amount up to the Bid amount shall be paid as a part of the Final Payment.

SECTION 2 – SCOPE OF THE WORK
2-1 WORK TO BE DONE
ADD the following:

1. Where approval or acceptance by the Agency is required, only a general approval is required.

However, such approval does not relieve the Contractor from the Contractor’s responsibility for complying with all applicable laws, codes, and best industry practices. Contractor has its obligation to fulfill all conditions of the Contract.

2. In accordance with the provisions of California Law, the Contractor shall possess or require the Contractor’s Subcontractor(s) to possess valid appropriate license(s) for the Work being performed as conveyed in the Bidding Documents.
2-2 PERMITS
DELETE in its entirety and SUBSTITUTE with the following:
2-2 PERMITS, FEES, AND NOTICES

1. The Contractor shall obtain and pay for all business taxes, business licenses, permits, and fees required for constructing the Project and licenses and inspections necessary for the proper execution and completion of the Work, unless specified otherwise in the Contract Documents.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 76 of 284 ends

a. Resource Agency Permits. (None)
b. To the extent that there is a change in the type or cost of any of such permits, fees, licenses, or inspection occurring after Award of Contract, there shall be an equitable adjustment in the Contract Price on account of such change under the Extra Work provisions.
c. The Contractor shall comply with and give notices required by applicable laws. The Contractor is not entitled to damages or additional payment for delays attributable to the acquisition of permits.
d. The Contractor shall pay the Agency for regulatory fees, fines, or penalties imposed on the Agency arising from the Contractor’s failure to complete the Work in accordance with the Contract Documents.

2. Contractor shall not begin work until all permit’s incidental to the Work are obtained. This includes, and is not limited to, encroachment, right-of-way, grading and building permits necessary to perform Work for this Contract on Agency property, streets, or other rights- of-way. Permits for night work, overload, blasting, demolition, and disposal of all materials removed from the Project are also Contractor’s responsibility.

3. The Contractor shall obtain and pay for all permits for the disposal of all materials removed from the Project. The cost of the permit(s) shall be included in the price Bid for the appropriate Bid item and the Agency shall not pay additional compensation for Contractor to obtain such permits.

4. Permits shall be maintained in valid status until acceptance of the Work by the Agency. 2-2.1 (Intentionally Omitted).

2-2.2 COUNTY OF SAN DIEGO AIR POLLUTION CONTROL DISTRICT (APCD). Diesel-engine driven generators, pumps, or other equipment regulated by air pollution control authorities shall have a valid permit or registration in accordance with the California Air Resources Board (CARB) and the San Diego County Air Pollution Control District (SDAPCD) regulations prior to mobilization to the site.

The Contractor shall pay for and secure an “Authority to Construct” permit from the SDAPCD prior to construction.

2-2.3 TRAFFIC CONTROL PLANS
a. The Contractor shall prepare Project specific traffic control plans, and haul route plan and use such plans to obtain a traffic control permit from the City of Carlsbad Development Services Department.
2-2.4 OTHER PERMITS
The following permits are applicable to the project:
a. CDP 2020-0032
b. SUP 2020-0003

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 77 of 284 ends

c. HMP 2020-0007
d. PUB 2020-0007

2-3 RIGHT-OF-WAY
ADD the following:

1. The Contractor shall coordinate access to private property with the property owners and the timing of accessing private property when the Agency has already obtained rights of entry.

Unless otherwise provided, the Contractor shall coordinate, pay for, and assume all responsibility for acquiring using, and disposing of additional work areas and facilities temporarily required. The Contractor shall indemnify and hold the Agency harmless from all claims for damages caused by such actions. The Contractor shall protect any private and public improvements.
2-4 COOPERATION AND COLLATERAL WORK
ADD the following:

1. The Contractor shall coordinate and cooperate with all the utility companies during the relocation or construction of their lines. The Contractor may be granted a time extension if, in the opinion of the Engineer, a delay is caused by the utility company. No additional compensation will be made to the Contractor for any such delay.

2. If work to be performed by the Agency or its separate Contractors is not shown or specified in the Contract Documents, the Engineer shall notify the Contractor in writing 10 Working Days prior to the start of such work and make available Plans or Specifications for work to be performed by others that may be pertinent to Contractor’s Work. If Contractor determines that the work to be performed by the Agency or its separate Contractors may interfere with or cause damage or delays to Contractor’s Work, notify the Engineer in writing within 3 Working Days of the Engineer’s notice. The Contractor shall diligently pursue with the Engineer resolution of potential conflicts with the work of others.

3. The Contractor shall prepare and submit to the Engineer for approval a plan and schedule to integrate the work of Contractor or its Subcontractors, Agency or the work of others. The plan shall conform to the tasks identified in the Construction Schedule and identify additional tasks as necessary and the sequencing of interrelated activities. 2-5 THE CONTRACTOR’S EQUIPMENT AND FACILITIES
2-5.2 Temporary Utility Services.

ADD the following:

1. The Contractor shall furnish, install, maintain, and remove all temporary utility services, such as light, power, electrical, gas, and water, at its own expense for construction and maintenance activities until acceptance of Work. These include piping, wiring, lamps, and other equipment necessary for the Work.

2. The Contractor shall obtain a construction meter for water used for the construction, testing, disinfection and flushing of new water or sewer facilities, vegetation establishment and

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 78 of 284 ends

maintenance, site maintenance, landscaping, cleanup, and all other work requiring water.

The Contractor shall contact the water agency that serves the Project Site for requirements.

3. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter, and any, and all, other charges, deposits and/or fees. The costs shall be considered incidental to the items of Work that they are associated with and no additional payment will be made for them.

2-5.4 Haul Routes.

DELETE in its entirety and REPLACE with the following:

1. Haul routes shall be determined by the Contractor and permits shall be submitted to the Agency for approval, in accordance with Section 2-2 ‘Permits, Fees and Notices’.

2-6 CHANGES REQUESTED BY THE CONTRACTOR
ADD the following:

1. Any plan or method of work suggested to the Contractor by the Agency, but not specified or required by the Contract or Change Order, which is adopted or followed by the Contractor in whole or in part shall be done at the Contractor’s sole risk and responsibility.

2. The Contract Price is not subject to adjustment for any type of tax increases after the Award.

ADD the following:
2-6.1 Cost Reduction Proposal.

1. The Contractor may submit to the Engineer in writing, proposals for modifying the Plans, Specifications, or other requirements of the Contract for the sole purpose of reducing the total cost of construction.

2. The cost reduction proposal shall not impair, in any manner, the essential functions or characteristics of the Project such as service life, economy of operation, ease of maintenance, quality, desired appearance, or design and safety standards.

3. The following information must be included in the cost reduction proposal:
a. A description of both the existing Contract requirements for performing the Work and the proposed changes.
b. An itemization of the Contract requirements that shall be changed if the proposal is adopted.
c. A detailed estimate of the cost of performing the Work under the existing Contract and under the proposed change.
d. A statement of the time within which the Engineer shall act on the cost reduction proposal.
e. The Contract items of Work affected by the proposed changes, including any quantity variation attributable thereto.

4. This subsection does not require the Engineer to consider any cost reduction proposal. The Agency shall not be liable to the Contractor for not approving or acting upon any cost reduction proposal the Contractor submitted nor for any delays to the Work attributable to the cost reduction proposal.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 79 of 284 ends

5. If a cost reduction proposal is similar to the information included in the Contract Documents or adopted by the Agency after the advertisement and prior to Award of the Contract, the Engineer will not accept such proposal and reserves the right to make suc h changes without compensation to the Contractor under the provisions of this subsection.

6. The Contractor shall continue to perform the Work in accordance with the requirements of the Contract until a Change Order incorporating the cost reduction proposal has been issued.

7. The Engineer is the sole judge of the acceptability of a cost reduction proposal and the estimated net savings. In determining the estimated net savings, the Agency has the right to disregard the Contract Bid prices if, in the judgment of the Engineer, such prices do not represent a fair measure of the value of the Work to be performed or to be deleted.

8. The Agency reserves the right to require the Contractor to share in the Agency’s costs of investigating the Contractor’s cost reduction proposal. When this is required, the Contractor shall indicate the Contractor’s acceptance in writing allowing the Agency to deduct amounts payable to the Contractor.

9. If the Engineer accepts the Contractor’s cost reduction proposal in whole or in part, the Engineer shall issue a Change Order to incorporate the changes in the Plans and Specifications which are necessary to permit the cost reduction proposal or such part of it as has been accepted to be put into effect. If the Engineer’s approval is conditional, the Change Order shall include any conditions upon which the Engineer’s approval is based.

10. The Change Order also includes the estimated net savings in the cost of performing the Work due to the accepted cost reduction proposal and provides that the Contract cost be adjusted by crediting the Agency with 50% of estimated net savings amount.

11. The Contract Time shall not be extended by the acceptance of the cost reduction proposal and the performance of the Work unless specified otherwise in the Change Order.

12. The amount specified as payable to the Contractor in the Change Order is full compensation for the cost reduction proposal and the performance of the Work.

13. The Agency expressly reserves the right to adopt a cost reduction proposal for general use on contracts administered by the Agency when it determines that the proposal is suitable for application to other contracts. When an accepted cost reduction proposal is adopted for general use, only the Contractor who first submitted such proposal shall be eligible for compensation subject to this subsection, and in that case, only for contracts awarded prior to submission of the accepted cost reduction proposal.

14. The cost reduction proposals identical or similar to previously submitted proposals shall be eligible for consideration and compensation under the provisions of this subsection if the identical or similar previously submitted proposals were not adopted for general application to other contracts administered by the Agency.

15. Subject to the provisions contained in the Contract, the Agency or any other public agency shall have the right to use all or any part of any submitted cost reduction proposal without obligation or compensation of any kind to the Contractor.

16. The Contractor shall bear all costs to revise bonds for the Project to include the cost reduction incentive proposal work.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 80 of 284 ends

2-7 CHANGES INITIATED BY THE AGENCY
2-7.1 General.

ADD the following:

Unless expressly set forth in writing in a Change Order signed by the Agency and the Contractor, changes initiated by the Agency shall not be construed as the Agency directing the Contractor’s mean-and-methods in the execution of the Work.

2-8 EXTRA WORK
ADD the following:

1. New or unforeseen Work will be classified as “Extra Work” when the Engineer determines that it is not covered by Contract Unit Prices or stipulated unit prices.

2. Any request by the Contractor for Extra Work shall be in writing to the Engineer and shall include itemized estimates and in accordance with Section 7 -4. The Contractor shall fully itemize the Extra Work cost estimates such as labor and payroll costs, quantities, crew composition, production rates, material costs, Subcontractor and Supplier costs, equipment costs, supplemental costs, and time impact.
2-9 CHANGED CONDITIONS
ADD the following:

The Contractor shall promptly notify the Engineer of the following Work Site conditions (“Changed Conditions”), in writing, upon their discovery and before they are disturbed:

1. Subsurface or latent physical conditions differing materially from those represented in the Contract;

2. Unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in work of the character being performed; and

3. Material differing from that represented in the Contract which the Contractor believes may be hazardous waste, as defined in Health and Safety Code Section 25117, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.

The Engineer will promptly investigate conditions which appear to be Changed Conditions. If the Engineer determines that conditions are Changed Conditions and they will materially affect performance time, the Contractor, upon submitting a written request, will be granted an extension of time subject to Section 6-4.2.

If the Engineer determines that the conditions do not justify an adjustment in compensation, the Contractor will be notified in writing. This notice will also advise the Contractor of its obligation to notify the Engineer in writing if the Contractor disagrees.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 81 of 284 ends

The Contractor’s failure to give notice of Changed Conditions promptly upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection with them.

1. The Contractor shall not be entitled to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a Change Order, or for the occurrence of any event or other cause, unless the Contractor shall have first given the Engineer written notice of potential claim as specified in this Section 2-9. Compliance with this section shall not be required as a prerequisite to notice provisions in Section 6 -4.2(4) Extensions of Time, nor to any claim th at is based on differences in measurement or errors of computation as to Contract quantities.

2. The Contractor shall provide the Agency with a written document containing a description of the particular circumstances giving rise to the potential claim, the reasons for which the Contractor believes additional compensation may be due and the nature of any and all costs involved within 20 Working Days of the date of service of the written notice of potential claim for Changed Conditions. Verbal notifications will not be accepted.

3. The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-12656.

“The undersigned certifies that the above statements are made in full awareness of the California False Claims Act, Government Code Sections 12650 -12656. The undersigned further understands and agrees that this potential claim, unless resolved, must be restated as a claim in response to the Agency’s proposed final estimate for it to be further considered.”

By: Title:

Date:

Company Name:

4. The Contractor’s estimate of costs may be updated when actual costs are known. The Contractor shall submit proof of its actual costs to the Engineer within 20 Working Days after the affected Work is completed. Failure to do so shall be cause to deny any l ater-filed claim regarding a potential claim described in this Section 2-9.

5. The intent of this Section 2 -9 is to have differences between the parties arising under the Contract brought to the attention of the Engineer at the earliest possible time so that such matters can be settled, if possible, or other appropriate action promptly taken. 2-10 DISPUTED WORK
ADD 2- 10.1 Claims.

1. A Claim is a written demand by the Contractor that seeks an adjustment in the Contract Price, Contract Time, or other relief associated with a dispute arising under or relating to the Contract, including a breach of any Contract provision. A voucher, invoice, or other routine request for payment is not a Claim.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 82 of 284 ends

2. A Claim shall conform to these specifications and may be considered after the Agency has previously denied a request by the Contractor for a Change Order seeking the demanded relief.

3. The Contractor shall submit a Claim to the Engineer if a dispute occurs that arises from or relates to the Contract. The Claim shall seek all relief to which the Contractor asserts the Contractor is entitled as a result of the event(s) giving rise to the dispute. The Contractor’s failure to process a Claim in accordance with these specifications shall constitute a waiver of all relief associated with the dispute. Claims are subject to 6-10, “Right to Audit.”

4. The Contractor shall continue to perform the Services and Work and shall maintain the Schedule during any dispute proceedings. The Engineer will continue to make payments for undisputed Services and Work.

5. The Agency’s Claims process specified in the Agency Supplement shall not relieve the Contractor of the Contractor’s statutory obligations to present Claims prior to any action under the Government Code.

6. Except for those final payment items disputed in the written statement required in Section 7-3.2, all Claims of any dollar amount shall be submitted in a written statement by the Contractor no later than the date of receipt of the final payment estimate. Those final payment items disputed in the written statement required in Section 7-3.2 shall be submitted no later than 30 Calendar Days after receipt of the Final Payment estimate. No Claim will be considered that was not included in this written statement, nor will any Claim be allowed for which written notice or protest is required under any provision of this Contract , including Sections 2 -9 Changed Conditions, 2 -10 Disputed Work, 4 -1(22) Protection, 6- 4.4 Written Notice and Report, or 6 -4.2(4) Extensions of Time, unless the Contractor has complied with notice or protest requirements.

7. The Engineer will consider Contractor’s filed Claims, which must be detailed enough so the Engineer can determine the basis and amount of the Claims. Contractor shall provide the Engineer additional information to determine the facts or contentions involved in a Claim if requested by the Engineer. If additional information is needed, Contractor must provide Engineer with this information within a reasonable time of being asked for additional information. Failure to submit such information and details will be sufficient cause for denying the Claims.

8. Payment for Claims shall be processed by the next payment application of their resolution for those Claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Section 2-10, Disputed Work, for those Claims remaining in dispute. 2-10.1.1 Initiation of Claim.

1. A Claim is a written demand by the Contractor that seeks an adjustment in the Contract Price, Contract Time, or other relief associated with a dispute arising under or relating to the Contract, including a breach of any provision of the Contract. A voucher, invoice, payment application or other routine request for payment is not a Claim. A Claim shall conform to these specifications and may be considered after the City has previously denied a request from the Contractor for a Change Order seeking the demanded relief. The Contractor shall, consistent with 2 -10.1.2, give the Agency written notice of Claim prior to commencing any Disputed Work. Failure to give the notice shall constitute a waiver of all Claims in connection

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 83 of 284 ends

with the Disputed Work. If the Contractor and the Agency are unable to reach agreement on Disputed Work, the Agency may direct the Contractor to proceed with the Work and such direction shall not be construed as the Agency directing the Contractor’s mean-and-methods in the execution of the Work. After the Agency has rejected a Change Order request and prior to proceeding with dispute resolution pursuant to the Public Contract Code, applicable provisions of which are specified below, the Contractor shall attempt to resolve all disputes informally through the following dispute resolution chain of command:

For claims with a monetary value of $50,000 or less:
i. Project Inspector
ii. Construction Manager
iii. Deputy City Engineer/Engineering Manager
For claims with a monetary value greater than $50,000:
iv. Project Inspector
v. Construction Manager
vi. Deputy City Engineer/Engineering Manager
vii. City Engineer
viii. City Manager or Executive Manager

2. Consistent with Section 2 -10.1.2, the Contractor shall submit a complete report within 20 Working Days after completion of the Disputed Work stating its position on the Claim, the contractual basis for the Claim, along with all documentation supporting the costs, Contract Time, and all other evidentiary materials. At each level of Claim or appeal of Claim the Agency will, within 10 Working Days of receipt of the Claim or appeal of Claim, review the Contractor’s report and respond with a position, request additional information or request that the Contractor meet and present its report. When additional information or a meeting is requested the Agency will provide its position within 10 Working Days of receipt of the additional information or Contractor’s presentation of its report. The Contractor may appeal each level’s position up to the Deputy City Engineer/Engineering Manager for claims less than $50,000 and/or up to the City Manager for the City of Carlsbad or Executive Manager for the Carlsbad Municipal Water District for claims greater than $50,000 after which the Contractor may proceed under the provisions of the Public Contract Code. The Agency’s failure to state a position or otherwise respond to a Claim with in the timeframes set forth above shall be deemed a rejection of the Claim by the Agency.

3. The authority within the dispute resolution chain of command is limited to recommending a resolution to a Claim to the City Manager for the City of Carlsbad or Executive Manager for the Carlsbad Municipal Water District. Actual approval of the Claim is sub ject to the Change Order provisions in the Contract.

4. Any remaining Claims not resolved by the informal dispute resolution process described above shall be resolved in accordance with Public Contract Code S ection 9204, the relevant portion of which is included below:
(d)(1)(A) Upon receipt of a Claim pursuant to this section, the public entity to which the Claim applies shall conduct a reasonable review of the Claim and, within a period not to exceed 45 days, shall provide the Claimant a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Upon receipt of a

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 84 of 284 ends

Claim, a public entity and a Contractor may, by mutual agreement, extend the time period provided in this subdivision.

(B) The Claimant shall furnish reasonable documentation to support the Claim.

(C) If the public entity needs approval from its governing body to provide the Claimant a written statement identifying the disputed portion and the undisputed portion of the Claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the Claimant a written statement identifying the disputed portion and the undisputed portion.

(D) Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.

(2)(A) If the Claimant disputes the public entity's written response, or if the public entity fails to respond to a Claim issued pursuant to this section within the time prescribed, the Claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.

(B) Within 10 business days following the conclusion of the meet and confer conference, if the Claim or any portion of the Claim remains in dispute, the public entity shall provide the Claimant a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the Claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the Claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the Claimant sharing the associated costs equally. The public entity and Claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this section.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 85 of 284 ends

(C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

(D) Unless otherwise agreed to by the public entity and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.

(E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program if mediation under this section does not resolve the parties' dispute.

(3) Failure by the public entity to respond to a Claim from a Contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the Claim being deemed rejected in its entirety. A Claim that is denied by reason of the public entity's failure to have responded to a Claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the Claim or the responsibility or qualifications of the Claimant.

(4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.

(5) If a Subcontractor or a lower tier Subcontractor lacks legal standing to assert a Claim against a public entity because privity of Contract does not exist, the Contractor may present to the public entity a Claim on behalf of a Subcontractor or lower ti er Subcontractor. A Subcontractor may request in writing, either on their own behalf or on behalf of a lower tier Subcontractor, that the Contractor present a Claim for work which was performed by the Subcontractor or by a lower tier Subcontractor on behalf of the Subcontractor. The Subcontractor requesting that the Claim be presented to the public entity shall furnish reasonable documentation to support the Claim. Within 45 days of receipt of this written request, the Contractor shall notify the Subcontractor in writing as to whether the Contractor presented the Claim to the public entity and, if the original Contractor did not present the Claim, provide the Subcontractor with a statement of the reasons for not having done so.

(e) The text of this section or a summary of it shall be set forth in the Plans or Specifications for any Public Works Project that may give rise to a Claim under this section.

(f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a Claim, the parties may mutually agree

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 86 of 284 ends

to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable Change Order, Claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.

(g) This section applies to contracts entered into on or after January 1, 2017.

(h) Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.

(i) This section shall remain in effect only until January 1, 2027, and as of that date is repealed, unless a later enacted statute that is enacted before January 1, 2027, deletes, or extends that date.

In addition, all Claims by Contractor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code Section 20104 et seq., applicable provisions of which are included below:

20104.2 For any Claim subject to this article, the following requirements apply:

(a) The Claim shall be in writing and include the documents necessary to substantiate the Claim. Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of Claims.

(b)(1) For Claims of less than fifty thousand dollars ($50,000), the local agency shall respond in writing to any written Claim within 45 days of receipt of the Claim, or may request, in writing, within 30 days of receipt of the Claim, any additional documentation supporting the Claim or relating to defenses to the Claim the local agency may have against the Claimant.

(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the Claimant.

(3) The local agency's written response to the Claim, as further documented, shall be submitted to the Claimant within 15 days after receipt of the further documentation or within a period of time no greater than that taken by the Claimant in producing the additional information, whichever is greater.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 87 of 284 ends

(c)(1) For Claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy -five thousand dollars ($375,000), the local agency shall respond in writing to all written Claims within 60 days of receipt of the Claim, or may request, in writing, within 30 days of receipt of the Claim, any additional documentation supporting the Claim or relating to defenses to the Claim the local agency may have against the Claimant.

(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the Claimant.

(3) The local agency's written response to the Claim, as further documented, shall be submitted to the Claimant within 30 days after receipt of the further documentation, or within a period of time no greater than that taken by the Claimant in producing the additional information or requested documentation, whichever is greater.

(d) If the Claimant disputes the local agency's written response, or the local agency fails to respond within the time prescribed, the Claimant may so notify the local agency, in writing, either within 15 days of receipt of the local agency's response or within 15 days of the local agency's failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, the local agency shall schedule a meet and confer conference within 30 days for settlement of the dispute.

(e) Following the meet and confer conference, if the Claim or any portion remains in dispute, the Claimant may file a Claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a Claim must be filed shall be tolled from the time the Claimant submits his or her written Claim pursuant to subdivision (a) until the time that Claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process.

(f) This article does not apply to tort Claims and nothing in this article is intended nor shall be construed to change the time periods for filing tort Claims or actions specified by Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code.

20104.4 The following procedures are established for all civil actions filed to resolve Claims subject to this article:

(a) Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to nonbinding mediation unless waived by mutual stipulation of both parties. The mediation process shall provide for the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 88 of 284 ends

selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to select a mediator within the 15 -day period, any party may petition the court to appoint the mediator.

(b)(1) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code.

The Civil Discovery Act (Title 4 (commencing with Section 2016.010) of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration.

(2) Notwithstanding any other provision of law, upon stipulation of the parties, arbitrators appointed for purposes of this article shall be experienced in construction law, and, upon stipulation of the parties, mediators and arbitrators shall be paid necessary and reasonable hourly rates of pay not to exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no event shall these fees or expenses be paid by state or county funds.

(3) In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, any party who after receiving an arbitration award requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, pay the attorney's fees of the other party arising out of the trial de novo.

(b) The court may, upon request by any party, order any witnesses to participate in the mediation or arbitration process.

20104.6 Payment on undisputed portion of Claim; interest on arbitration awards or judgments:

(a) No local agency shall fail to pay money as to any portion of a Claim which is undisputed except as otherwise provided in the Contract.

(b) In any suit filed under Section 20104.4, the local agency shall pay interest at the legal rate on any arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court of law.

5. Although not to be construed as proceeding under Extra Work provisions, the Contractor shall keep and furnish records of disputed Work in accordance with Section 2-10.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 89 of 284 ends

2-10.1.2 Claim Certification Submittal.

1. If the Contractor’s Claim seeks an increase in the Contract Price, the Contract Time, or both, submit with the Claim an affidavit certifying the following:
a. The Claim is made in good faith and covers all costs and delays to which the Contractor is entitled as a result of the event(s) giving rise to the Claim. b. The amount Claimed accurately reflects the adjustments in the Contract Price, the Contract Time, or both to which the Contractor believes the Contractor is entitled. c. All supporting costs and pricing data are current, accurate, and complete to the best of the Contractor’s knowledge. The Contractor shall supply a cost breakdown per item of Work.
d. The Contractor shall ensure that the affidavit is executed by an official who has the authority to legally bind the Contractor.
2-10.1.3 Agency’s Final Determination.

1. If the Contractor disagrees with the City Manager or Executive Manager’s final determination, as described in 2 -10.1.1(1-2), Contractor must notify the Engineer in writing of the Contractor’s objection within 15 Working Days after receipt of the written determination and file a “Request for Mediation” in accordance with 2-10.2, “Dispute Resolution Process.”

2. Failure to give notice of objection within the 15 Working Days period shall waive the Contractor’s right to pursue the Claim.
2-10.1.6 Mandatory Assistance.

1. If a third-party dispute, litigation, or both, arises out of or relates in any way to the Services provided under the Contract, upon the Agency’s request, the Contractor shall assist in resolving the dispute or litigation. The Contractor’s assistance includes, but is not limited to the following:
a. Providing requested documents in a timely manner.
b. Providing professional consultations.
c. Attending mediations, arbitrations, depositions, trials, or any event related to the dispute resolution and litigation.
2-10.1.6.1 Compensation for Mandatory Assistance.

1. The Agency will reimburse the Contractor for reasonable fees and expenses incurred by the Contractor for any required assistance rendered in accordance with 2 -10.1.6, “Mandatory Assistance” as Extra Work.

2. The Engineer will determine whether these fees and expenses were necessary due to the Contractor’s conduct or failure to act.

3. If the Engineer determines that the basis of the dispute or litigation in which these fees and expenses were incurred were the result of the Contractor’s conduct or the Contractor’s failure to act in part or in whole, the Contractor shall reimburse the Agency for any payments made for these fees and expenses.

Reimbursement may be through any legal means necessary, including the Agency’s withholding of the Contractor’s payment.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 90 of 284 ends

ADD 2- 10.2 Dispute Resolution Process
2-10.2.1 Mandatory Non-binding Mediation.

1. If a dispute arises out of or relates to the Contract, or the breach of it, and if the dispute cannot be settled through those procedures described in Section 2 -10.1.1, the parties must attempt to settle the dispute in an amicable manner, using mandatory mediation under the Construction Industry Mediation Rules of the American Arbitration Association before having recourse in a court of law.

2. To initiate mediation, the initiating party shall serve a Request for Mediation at the American Arbitration Association (AAA).
2-10.2.2 Mandatory Mediation Costs.

1. The expenses of witnesses for either side shall be paid by the party producing such witnesses. All other expenses of the mediation, including required traveling and other expenses of the mediator and the cost of any proofs or expert advice produced at the direct request of the mediator, shall be borne equally by the parties, unless they agree otherwise.
2-10.2.3 Selection of Mediator.

1. A single mediator, knowledgeable in construction aspects and acceptable to both parties, shall be used to mediate the dispute.

2. If AAA is used, the initiating party shall concurrently file with AAA a “Request for Mediation” along with the appropriate fees, a copy of requested mediators marked in preference order, and a preference for available dates.

3. If AAA is selected to coordinate the mediation (Administrator), within 10 Working Days from the receipt of the initiating party’s Request for Mediation, the opposing party shall file the following:
a. A copy of the list of the preferred mediators listed in preference order after striking any mediators to which they have any objection. b. A preference for available dates.
c. Appropriate fees.

4. If the parties cannot agree on a mediator, then each party shall select a mediator and those mediators shall select the neutral third party to mediate the matter. 2-10.2.4 Conduct of Mediation Sessions.

1. Mediation hearings shall be conducted in an informal manner and discovery shall not be allowed.

2. Discussions, statements, or admissions shall be confidential to the proceedings and shall not be used for any other purpose regarding the party’s legal position. The parties may agree to exchange any information they deem necessary.

3. Both parties shall have an authorized representative attend the mediation. Each representative shall have the authority to recommend entering into a settlement. Either

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 91 of 284 ends

party may have attorney(s), witnesses, or expert(s) present. Either party may request a list of witnesses and notifications of whether attorney(s) shall be present.

4. Any resulting agreements from mediation shall be documented in writing. Mediation results and documents, by themselves, shall be “non -binding” and inadmissible for any purpose in any legal proceeding, unless such admission is otherwise agreed upon in writing by both parties. Mediators shall not be subject to any subpoena or liability and their actions shall not be subject to discovery.

ADD 2-10.3 Governing Law & Forum for Litigation.

1. This Contract shall be governed by and construed in accordance with the laws of the State of California. Any lawsuits, at law or in equity, between the parties arising out of this Contract shall be filed in a court of competent jurisdiction in the County of San Diego. With respect to venue, the parties agree that this Contract is made in and will be performed in the County of San Diego. The parties waive all provisions of law providing for a change of venue in these proceedings to any other county.

ADD 2-10.4 Pre-judgment Interest.

1. The parties stipulate that if a judgment is entered against a party for breaching this Contract, the pre-judgment interest shall be 2% per annum.

SECTION 3 – CONTROL OF THE WORK
3-2 SELF-PERFORMANCE
ADD the following:

1. If Contractor fails to satisfy the provisions requiring the Contractor to complete Work amounting to at least 50 percent of the Contract price with its own organization unless stipulated otherwise in the Contract Documents, the Agency may at its sole discr etion elect to cancel the Contract or deduct an amount equal to 10 percent of the value of the Work performed in excess of 50 percent of the Contract Price by other than the Contractor’s own organization. The Board shall be the sole body for determination of a violation of these provisions. In any proceedings under this section, the Contractor, or prime Contractor, shall be entitled to a public hearing before the Board and shall be notified 10 Calendar D ays in advance of the time and location of the hearing. The determination of the Board shall be final. 3-3 SUBCONTRACTORS
ADD the following:

1. The Contractor shall incorporate these Specifications in the Contractor’s subcontracts for the work being performed by the Contractor’s Subcontractor.

2. The Contractor shall obtain or require that each Subcontractor obtains insurance policies in accordance with 5-4, “INSURANCE” which shall be kept in full force and effect for the duration of the Contract and in any attached supplemental agreements.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 92 of 284 ends

3. In any dispute between the Contractor and the Contractor’s Subcontractors, the Agency shall not be made a party to any judicial or administrative proceeding to resolve the dispute.

4. The Contractor shall ensure that the Contractor’s Subcontractors are appropriately licensed for the duration of the work that is performed under the Subcontracts in accordance with 2- 1, “WORK TO BE DONE.” If a Subcontractor is not properly licensed, the Contractor shall cease payment to the Subcontractor for all work performed when the Subcontractor was not properly licensed. The Contractor shall return to the Agency any payment the Contractor made to a Subcontractor for work performed when the Subcontractor was not licensed.

5. Subcontractors shall be considered employees of the Contractor, and the Contractor shall be responsible for their work.

6. Where the Contract Documents require that a particular product be installed or applied by an applicator approved by the manufacturer, ensure the Subcontractor or Supplier employed for such work is approved by the manufacturer.

7. Before the work of any Subcontractor is started, the Contractor shall submit to the Engineer for approval a written statement showing the Work to be subcontracted giving the name and business of each Subcontractor and description and value of each portion of the Work to be so subcontracted. This submittal will confirm the Subcontractor’s commitments in the Bid. 3-4 AUTHORITY OF THE ENGINEER
ADD the following:

1. The Engineer shall be the single point of contact and shall be included in all communications between Contractor and any Agency representative.
3-5 INSPECTION
ADD the following:

1. Contractor shall make available to the Engineer accurate books and accounting records regarding all its activities. Contractor shall contractually require all Subcontractors to this Contract to do the same. The Engineer shall have access to the Contractor’ s, and any Subcontractors documents described in this Section 3 -5(1) within San Diego County . The Engineer shall have the right to monitor, assess, and evaluate Contractor’s and its Subcontractor’s performance pursuant to this Contract. The Engineer’s monitoring, assessments, and evaluations will include, but shall not be limited to, audits, insp ection of premises, reports, contracts, subcontracts and interviews of Contractor’s staff and the staff of all Subcontractors to this Contract. Upon reasonable advance notice, Contractor shall make available to the Engineer for examination, all of its, and all Subcontractors to this Contract, records with respect to all matters covered by this Contract. Contractor shall also permit the Engineer to audit, examine, copy and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, payrolls, records of personnel, and other data relating to all matters covered by this Contract. Any inspection described in this Section 3 -5(1) shall occur as often as the Engineer deems necessary and during normal business hours. However, any such inspection shall not unreasonably interfere with Contractor’s ongoing business operations. Contractor and all Subcontractors to this Contract

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 93 of 284 ends

shall maintain such data and records for as long as may be required by applicable laws and regulations.

2. The Agency may utilize consultants to assist the Engineer during construction in observing the Contractor’s performance. The consultant shall be the Agency ’s Representative on the Site assisting the Engineer and must not be confused with a building inspector with the Agency or with a Special Inspector.

3. The Agency may utilize a Special Inspector for inspection of specialty work and materials, whose costs the Agency will pay for unless the Contractor fails inspection. If inspections or tests reveal non -compliance with the requirements of the Contract Documents, the Contractor shall pay for all corrective measures deemed necessary by the Engineer and also pay the cost of the Agency’s subsequent re-inspection and re-testing.

4. Inspections required by codes or ordinances are the Contractor’s responsibility.

5. The Contractor’s quality control testing and inspections are the Contractor’s responsibility.

Contractor shall coordinate and schedule all inspections and tests. The Contractor shall give the Engineer notice of tests and inspections made by others. At least 5 Working Days of notice shall be given for offsite inspection s. The Contractor shall wait until the Engineer has responded and agreed to Contractor’s schedule before scheduling test or inspections.

6. The Agency shall schedule any inspections and tests as the Agency deems necessary to ensure the Work is accomplished in accordance with the requirements of the Contract Documents (other than inspections for work performed in accordance with a permit). The Contractor is responsible for the inspection of all Work performed in accordance with the Contract Documents.

7. Contractor shall provide access in accordance with Cal-OSHA Standards as necessary.

8. Contractor shall remove and replace any items of Work performed without the required permit or inspection. For required subsequent inspection, the Contractor shall remove and replace Work at the discretion of Engineer at no additional cost to the Agency. I nspection of the Work does not relieve the Contractor of full compliance with the Contract Documents.

9. Contractor shall not conceal the Work prior to inspection, testing, or approval required by the Contract Documents, the Engineer’s prior written request, or by other agencies. If any item of Work is done prior to obtaining the required approvals when reque sted by the Engineer, Contractor shall expose the Work for inspection, testing, and/or approval. Upon successful completion of the inspection, testing, or approval, the Contractor shall proceed with the Work. The Contractor shall bear all direct and indire ct costs and damages of such uncovering and re-covering and shall not be entitled to an increase in the Contract Price or the Contract Time, unless the Contractor has given the Engineer and any other affected agencies written notice of the Contractor’s intention to cover the Work and the Engineer has not acted in response to such notice.

10. When specified, Contractor shall make arrangements for tests, inspections, and approvals with an independent testing laboratory or entity acceptable to the Engineer, or with the appropriate public authority. The payment for such tests, inspections, and approvals are included in the Contract Price.

11. Unless specified otherwise, the Contractor shall pay the cost of inspections and tests. If inspections or tests reveal non -compliance with the requirements of the Contract

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 94 of 284 ends

Documents, the Contractor shall bear the cost of corrective measures deemed necessary by the Engineer and the cost of the Agency’s subsequent re-inspection and re-testing.

12. The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor’s or Subcontractor’s possession pertaining to the Work that the Engineer may request.

3-6 THE CONTRACTOR’S REPRESENTATIVE
ADD the following:

1. Both the representative and alternative representative shall be the Contractor’s employees and shall not be assigned to a Subcontractor unless otherwise approved by the Agency in writing.

2. The Contractor’s Project team shall attend scheduled construction meetings as required by the Engineer. If any of Contractor’s staff cannot attend, the Contractor shall notify the Engineer a minimum of 24 hours in advance, prior to the start of the scheduled meeting. If the Contractor does not provide the required notification, the Contractor shall pay for the costs of the Agency’s staff, consultants, or both that attended. The Contractor shall be charged a minimum of 2 hours of the attendee’s time.

3. The payment for the Contractor’s attendance at Project meetings is included in the Contract Price. The Engineer shall deduct costs assessed to the Contractor for not attending the meetings from the monthly progress payment via Change Order. 3-7 CONTRACT DOCUMENTS
3-7.1 General.

ADD the following:

1. Specifications and Plans are divided into groups by engineering discipline for the Agency’s convenience. These divisions are not for the purpose of apportioning the Work or responsibility for the Work among Subcontractors and Suppliers.

2. The Contractor shall supply any Work that may reasonably be inferred from the Specifications or Plans as being required to produce the intended result whether or not it is specifically called for, at no additional cost to the Agency.

3. If referenced documents have been discontinued or updated by the issuing organization, the replacement documents issued or otherwise identified by that organization shall be used or, if there are no replacement documents, the last version of the document before it was discontinued.

4. Scaled dimensions on Contract Documents are approximate. Before ordering materials or commencing the Work, the Contractor shall measure the Site for proper size and fit and verify dimensions and quantities by taking measurements in the field. The Contracto r shall be responsible for their accuracy.

5. The Contractor shall verify any conditions affecting the cost of the Work through a reasonable examination of the Work Site prior to submitting the Bid.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 95 of 284 ends

6. Existing improvements visible at the Work Site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed, and disposed of by the Contractor.

7. The Plans, Specifications, and other Contract Documents shall govern the Work. The Contract Documents are intended to be complementary and cooperative. Anything specified in the Specifications and not shown on the Plans or shown on the Plans and not specified in the Specifications, shall be as though shown on or specified in both.

8. The Contractor shall ascertain the existence of any conditions affecting the cost of the Work through a reasonable examination of the Work Site prior to submitting the Bid.

9. Existing improvements visible at the Work Site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed, and disposed of by the Contractor.

3-7.2 Precedence of the Contract Documents.

DELETE in its entirety and REPLACE with the following:

1. If there is a conflict between any of the Contract Documents, the document highest in the order of precedence, and most recent in edition, shall control. The order of precedence, from highest to lowest, shall be as follows:
a. Permits (issued by jurisdictional regulatory agencies including environmental documents).
b. Change Orders and supplemental agreements; whichever occurs last. c. Contract Addenda, whichever occurs last.
d. The signed written Contract.
e. City of Carlsbad General Provisions (00 73 00)
f. Technical Specifications
g. City of Carlsbad Supplemental Provisions (00 74 00)
h. Project Plans.
i. Standard Plans
i. City of Carlsbad Standard Drawings.
ii. Carlsbad Municipal Water District Standard Drawings. iii. City of Carlsbad modifications to the San Diego Area Regional Standard Drawings.
iv. San Diego Standard Regional Standard Drawings.
v. Traffic Signal Design Guidelines and Standards.
vi. State of California Department of Transportation Standard Plans. vii. California Manual on Uniform Traffic Control Devices (CA MUTCD). j. “Greenbook” (Standard Specifications for Public Works Construction). k. Reference Specifications.
l. Manufacturer’s Installation Recommendations

2. When additional small business/minority/women -owned/veteran or other special requirements by funding sources are included in the Contract Documents, the funding source’s requirements shall govern.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 96 of 284 ends

3. When a conflict exists between the ADA requirements of Title 24, and the Agency Supplemental Provisions, the most restrictive requirement shall be followed.

ADD: 3-7.3 Red-lines and Record Documents.
3-7.3.1 General.

1. The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor’s or Subcontractor’s possession pertaining to the Work that the Engineer may request.

2. The Contractor shall keep the Red- lines current with entries checked by the Engineer before the Work is covered. Contractor’s failure to update and deliver Red -lines information monthly to the Engineer for review and approval may result in the withholding of monthly progress payments.

3. The Contractor shall note the source identification, such as RFI numbers and Change Order numbers, as required identifying the source of the change to the Contract Documents.

4. The Contractor shall deliver the Red -lines to the Engineer upon completion of the Construction Work.

5. The Contractor shall legibly annotate a full- size set of Plans daily, in red ink, to record additions, deletions or changes to the Work and changes in location, elevation or character of the Work not otherwise shown or noted in the Contract Documents. This “redline” set of drawings shall be kept on the Job Site, shall be used only as a record set .

Contractor shall immediately give written notice of any conflicts between these documents to the Engineer.

6. The draft final red line set shall be submitted to the Engineer within five (5) Calendar Days of the final walk-through meeting. The Contractor shall review the redline changes with the engineer during this meeting. The engineer will provide submittal review transmittal noting if the red line set has been accepted or requires revision. The Contractor shall revise per the requested c hanges and corrections noted and resubmit within ten (10) calendar days upon receipt of the submittal review transmittal.

7. As-built information shall represent field measurements, approved Shop Drawings, Working Drawings, samples, product data, and other pertinent data discovered during the performance of the Work. The Contractor shall note the source of the change such as RFI or Change Order numbers, as required. The Contractor shall clearly record additions or changes in the Work and depth of underground facilities by dimensioning from 2, known, fixed points.

8. Payment for Record Drawings and Documents shall be included in the various Bid items and no additional payment will be made therefore.
3-7.3.2 Asset Specific Red-lines.

1. Irrigation System Red -lines: Red -lines shall clearly record by dimension from 2 known fixed points and by depth of underground facilities all deviations, modifications, and changes in the Work. Records, deviations, modifications, and changes on the day the Work is performed shall reflect the actual Work location and shall be marked in red at the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 97 of 284 ends

scale of the Plan sheet on which they are recorded. Red -lines shall show any changes to the Plans for the equipment locations and associated information for the following:
a. Potable water mainline and size
b. Water Meter - Size, type of water (potable or reclaimed), and water meter address.
c. Backflow Device - Size, available static pressure in psi, the psi and flow in gallons per minutes for which the irrigation system is designed, and device serial number. d. Master Control Valve.
e. Flow Sensor.
f. Pressure Regulator Valve.
g. Isolation Valves.
h. Remote Control Valves - Size, irrigation controller, valve station number, and flow demand in gallons per minute.
i. Quick Coupling Valves and Size.
j. Electrical Meter, including meter address.
k. Remote Control Valve Wiring.
l. Communication Cables.
m. Pull Boxes.
n. Rain Shut Off Switch.
o. Electrical lines from electrical meter to irrigation controller, including the power disconnect switch.
p. Irrigation Mainline and Size.
q. Irrigation Lateral Line and Size.
r. Irrigation Sleeves and Size.
s. Irrigation Controller - Location, number of stations, identifying call-out. t. Irrigation sprinkler heads which have been added or deleted from the approved Plans. Changes in manufacturer nozzle size shall be noted on the red- lined Drawings including operating pressure, gallons per minute, and radius of throw.

2. Re-vegetation Red-lines:
a. Within 4 weeks of the end of the Plant Establishment Period, as determined and accepted by the Project Biologist or Landscape Architect, furnish and submit to the Engineer 1 full scale Red -lines set showing field changes to grade, erosion control, and seeding for the re-vegetated areas.

3. Utility Red-lines: Utility Red-lines shall show any changes from the Plan for the following:
a. Horizontal and vertical bends
b. Changes in pipe material or pressure class
c. Isolation valves
d. Insulating joints
e. Blow off valves by stationing and offsets.
f. Air vacuum valves by stationing and offsets.
g. Water and recycled water meter boxes replaced.
h. Water sampling stations
i. Cathodic test stations
j. Locations of all sewer laterals and cleanouts.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 98 of 284 ends

k. Items abandoned in place following dewatering operation.

4. Building Red -lines: Building Red- lines shall show any changes from the Plans for the following:
a. Location by dimension and the depth by elevation of underground lines, valves, plugged tees, and capped ends.
b. By dimension or scale Plans, wiring, conduits, and pull boxes as installed. c. Information necessary to maintain and service concealed items of Work. d. Dimensional changes to the Drawings.
e. Revisions to details shown on the Drawings.
f. Depths of foundations below the first floor.
g. Locations and depths of underground utilities.
h. Revisions to the routing of piping and conduits.
i. Revisions to electrical circuitry.
j. Actual equipment locations.
k. Duct size and routing.
l. Locations of concealed internal utilities.
m. Changes made by Change Orders.
n. Details not shown on original Plans.

5. Traffic Signals and Street Lighting:
a. The Contractor shall provide the Engineer with a cable route diagram indicating the actual cable route and meter marks for all intersections, directional change points in the cable routing, and all termination points. The Contractor shall record these points during cable installation, provide cable system Red-lines showing the accurate cable route to the Engineer, and record information such as the location of slack cable and its quantity in the cable route diagram. b. The Contractor shall provide 3 copies of D-Sheet sized Red-lines.

6. SWPPP:
a. Upon completion of construction, the Contractor shall submit the SWPPP and all its appendices, records, reports, maps and records of permanent BMPs to the Engineer with the Red-lines.

7. Slurry Seal and Asphalt Concrete Overlay:
a. The Contractor shall clearly record on the forms the Agency provides in MS Excel format the actual dates and quantity of each Bid item applied to each street segment and comments regarding each segment and record reasons if no work is performed.

8. Fiber Optic and Wi-Fi Device Red-lines: Fiber Optic and Wi-Fi Device Red-lines shall clearly record by dimension from 2 known fixed points and by depth of underground facilities all deviations, modifications, and changes in the Work. Records, deviations, modifications, and changes on the day the Work is performed shall reflect the actual Work location and shall be marked i n red at the scale of the Plan sheet on which they are recorded. Red- lines shall show the equipment locations and associated information for the following:
a. Locations and depths of underground utilities.
b. Revisions to the routing of piping and conduits.
c. Actual equipment locations.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 99 of 284 ends

d. Pull Boxes.
e. Electrical Meter, including meter address.
f. Items abandoned in place.
3-7.3.3 Payment.

1. The payment for Red-lines Drawings shall be included in the Contract Price.

ADD 3- 7.4 Measurement and Dimensions.

1. Scaled dimensions are approximate. Before ordering materials or commencing the Work, the Contractor shall measure the Site for proper size and fit and verify dimensions and quantities by taking measurements in the field. Contractor shall be responsible for their accuracy. 3-8 SUBMITTALS
3-8.1 General
Add the following:
a. Shop Drawings and engineering data (submittals) covering all equipment and all fabricated components and building materials which will become a permanent part of the Goods and Special Services under this Contract shall be submitted to Engineer for review, as required.

Submittals shall verify compliance with the Contract Documents and shall include Drawings and descriptive information in sufficient detail to show the kind, size, arrangement, and the operation of component materials and devices; the external connections, anchorages, and supports required; the performance characteristics; and dimensions needed for installation and correlation with other materials and equipment.
b. Each submittal shall cover items from only one section of the specification unless the item consists of components from several sources. Contractor shall submit a complete initial submittal including all components. When an item consists of components fro m several sources, Contractor's initial submittal shall be complete including all components. c. All submittals, regardless of origin, shall be approved by Contractor and clearly identified with the name and number of this Contract, Contractor's name, and references to applicable specification paragraphs and Contract Drawings. Each copy of all submittals, regardless of origin, shall be stamped or affixed with an approval statement of Contractor. Each submittal shall indicate the intended use of the item in the Goods and Special Services. When catalog pages are submitted, applicable items shall be clearly identified and inapplicable data crossed out. The current revision, issue number, and date shall be indicated on all Drawings and other descriptive data.
d. Contractor shall be solely responsible for the completeness of each submittal. Contractor's stamp or affixed approval statement of a submittal, is a representation to Engineer that Contractor accepts sole responsibility for determining and verifying all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, and that Contractor has reviewed and coordinated each submittal with the requirements of the Goods and Special Services and the Contract Documents.
e. All deviations from the Contract Documents shall be identified as deviations on each submittal and shall be tabulated in Contractor's letter of transmittal. Such submittals shall, as

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 100 of 284 ends

pertinent to the deviation, indicate essential details of all changes proposed by Contractor (including modifications to other facilities that may be a result of the deviation) and all required piping and wiring diagrams.
f. Engineer will not accept submittals from anyone but Contractor. Submittals shall be consecutively numbered in direct sequence of submittal and without division by subcontracts or trades.
g. For electronic submittals, drawings and the necessary data shall be submitted electronically to Engineer as specified below. Submittal documents shall be in black and white unless color is required for the review of the submittal. All electronic files shall be in PDF as generated by Adobe Acrobat Professional latest version. The PDF file(s) shall be fully indexed using the Table of Contents, searchable with thumbnails generated. PDF images must be at a readable resolution. For most documents, they should be scanned or generated at 300 dots per inch (dpi). Optical Character Recognition (OCR) capture must be performed on these images so that text can be searched, selected and copied from the generated PDF file. The PDF documents shall have a bookmark created in the navigation frame for each major entry (“Section” or “Chapter”) in the Table of Contents. Thumbnails shall be generated for each page or graphic in the PDF file. The opening view for each PDF document shall be as follows:

1. Initial View: Bookmarks and Page

2. Magnification: Fit In Window

3. The file shall open to the Contractor’s transmittal letter, with bookmarks to the left.

The first bookmark shall be linked to the Table of Contents.

PDF document properties shall include the submittal number for the document title and the Contractor’s name for the author.
h. Electronic submittal file sizes shall be limited to 10 MB. When multiple files are required for a submittal the least number of files possible shall be created. i. The Contractor shall post submittals and retrieve the Engineer’s submittal review comments through the Engineer’s (Consulting Engineer’s) Project website accessible through the Internet. Instruction on procedures for posting and retrieving submittals will be provided after award of the Contract.
j. Facsimiles (fax) will not be acceptable. Engineer will not accept submittals from anyone but Contractor. Submittals shall be consecutively numbered in direct sequence of submittal and without division by subcontracts or trades.

3.8.1.2 Resubmittal of Drawings and Data

1. Contractor shall accept full responsibility for the completeness of each resubmittal.

Contractor shall verify that all corrected data and additional information previously requested by Engineer are provided on the resubmittal.

2. When corrected copies are resubmitted, Contractor shall direct specific attention to all revisions in writing and shall list separately any revisions made other than those called for by Engineer on previous submittals. Requirements specified for initial submittals shall also apply to resubmittals. Resubmittals shall bear the number of the first submittal followed by a letter

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 101 of 284 ends

(A, B, etc.) or a unique identification that indicates the initial submittal and correct sequence of each resubmittal.

3. If more than 1 resubmittal is required because of failure of Contractor to provide all previously requested corrected data or additional information, Contractor shall reimburse Agency for the charges of Engineer for review of the additional resubmittals. T his does not include initial submittal data such as shop tests and field tests that are submitted after initial submittal.

4. Resubmittals shall be made within 30 Calendar Days of the date of the letter returning the material to be modified or corrected, unless within 14 Calendar Days Contractor submits an acceptable request for an extension of the stipulated time period, listing the reasons the resubmittal cannot be completed within that time.

5. The need for more than 1 resubmittal, or any other delay in obtaining Engineer's review of submittals, will not entitle Contractor to extension of the Contract Times unless delay of the Work is the direct result of a change in the Work authorized by a Change Order or failure of Engineer to review and return any submittal to Contractor within the specified review period. 3-8.1.3 Color Selection
a. Contractor shall submit samples of colors and finishes for all accepted products before Engineer will coordinate the selection of colors and finishes with Agency. Engineer will prepare a schedule of finishes that include the colors and finishes selected fo r both manufactured products and for surfaces to be field painted or finished and will furnish this schedule to Contractor within 60 Calendar Days after the date of acceptance of the last color or finish sample.
3-8.1.4 Operations and Maintenance Data and Manuals

1. Adequate operation and maintenance information shall be supplied for all equipment requiring maintenance or other attention. The equipment supplier shall prepare a Project specific operation and maintenance manual for each type of equipment indicated in th e individual equipment sections or the equipment schedule.

2. Parts lists and operating and maintenance instructions shall be furnished for other equipment not listed in the individual equipment sections or the equipment schedule.

3. Operation and maintenance manuals shall include the following:
a) Equipment function, normal operating characteristics, and limiting conditions. b) Assembly, installation, alignment, adjustment, and checking instructions. c) Operating instructions for startup, routine and normal operation, regulation and control, shutdown, and emergency conditions.
d) Lubrication and maintenance instructions.
e) Guide to troubleshooting.
f) Parts lists and predicted life of parts subject to wear. g) Outline, cross section, and assembly drawings; engineering data; and wiring diagrams. h) Test data and performance curves, where applicable.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 102 of 284 ends

4. The operation and maintenance manuals shall be in addition to any instructions or parts lists packed with or attached to the equipment when delivered, or which may be required by Contractor.

5. Manuals shall be submitted in electronic format to the Engineer prior to the date of shipment of the equipment. The manuals shall be submitted and the Engineer’s review comments retrieved, through the Project website accessible through the Internet. Instr uction on procedures for posting and retrieving O&M submittals and review comments will be provided after award of the Contract. When the O&M manuals are reviewed "RETURNED FOR CORRECTION,” the corrections shall be made as instructed by the Engineer or Consulting Engineer, and corrected manuals resubmitted to the Engineer or Consulting Engineer. When review by the Engineer is complete, 3 copies of each electronic O&M manual shall be delivered on CD-ROM to the Engineer. Each CD shall contain only 1 copy of 1 manual. Delivery of the final O&M shall be made 30 Calendar Days prior to placing the equipment in operation.

6. All material shall be marked with Project identification, and inapplicable information shall be marked out or deleted.

7. Shipment of equipment will not be considered complete until all required manuals and data have been received.
3-8.1.5 Electronic Operations and Maintenance Manuals

1. Electronic manuals shall be in Adobe Acrobat’s PDF and shall be prepared at a resolution between 300 and 600 dpi, depending on document type. OCR capture shall be performed on these documents. OCR settings shall be performed with the “original image with hidden text” option in Adobe Acrobat Exchange.

2. File size shall be limited to 10 MB. When multiple files are required the least number of files possible shall be created. File names shall be in the format OMXXXXX -YYYZ-V.pdf, where XXXXX is the 5-digit number corresponding to the specification section, YYY is a 3-digit O&M manual number, e.g., 001, Z is the letter signifying a resubmittal, A, B, C, etc, and V is a number used only when more than one 10 MB file is required for an O&M manual.

3. Documents prepared in PDF format shall be processed as follows:

Pages shall be searchable (processed for optical character recognition) and indexed when multiple files are required.
a) Of material to update the manual provided by the manufacturer. Pages shall be rotated for viewing in proper orientation.
b) A bookmark shall be provided in the navigation frame for each entry in the Table of Contents.
c) Embedded thumbnails shall be generated for each completed PDF file. d) The opening view for PDF files shall be as follows:
e) Initial View: Bookmarks and Page
f) Page Number: Title Page (usually Page 1)
g) Magnification: Set to Fit in Window
h) Page: Single Page

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 103 of 284 ends

i) Where the bookmark structure is longer than 1 page, the bookmarks shall be collapsed to show the chapter headings only.
j) When multiple files are required the first file of the series (the parent file) shall list every major topic in the Table of Contents. The parent file shall also include minor headings bookmarked based on the Table of Contents. Major headings, whose content is contained in subsequent files (children) shall be linked to be called from the parent to the specific location in the child file. The child file shall contain bookmark entries for both major and minor headings contained in the child file. The first bookmark of any child file shall link back to the parent file and shall read as follows "Return to the Equipment Name Table of Contents," e.g., Return to the Polymer Feed System Table of Contents.
k) Drawings shall be bookmarked individually.
l) Files shall be delivered without security settings to permit editing, insertion and deletion
3-8.1.6 Labeling
a. At a minimum, the following information shall be included on all final O&M manual materials, including thumb drives and hard copy manuals:
a) Equipment name and/or O&M title spelled out in complete words. b) Project Name.
c) Agency Project/Contract Number.
d) Specification Section Number. Example: “Section 15 55 00” e) Manufacturer’s name.
f) File Name and Date.

3-8.2 Working Drawings.

ADD the following:

1. Working Drawings shall be submitted electronically to the Agency.

DELETE Table 3-8.2 in its entirety and REPLACE with following:

Item Section/
Drawing
No.

Title Subject
1 3-12.5.2 Sewage Bypass and Pumping
Plan
Sanitary Sewers
2 3-12.8.2 Dewatering Plan Water Pollution Control
3 5-7.2.2 Shoring Plan Safety
4 300-3.2

Cofferdams Structure Excavation & Backfill
5 303-1.6.1 General Falsework
6 303-1.7.1 General Placing Reinforcement
7 303-3.1 General Prestressed Concrete Construction
8 304-1.1.2 Falsework Plans Structural Steel

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 104 of 284 ends

9 306-8.8
SDW-
154*
Valves, Hydrants, and
Appurtenances
Water Valve Bypass Details for
Mainlines 16-Inch and Larger
10 306-8.8.3 Thrust Blocks and Anchor
Blocks
Unless specified otherwise, design of all
size water main thrust blocks and
anchor blocks
11 307-1.1

General Jacking Operations
12 307-2.1

General Tunneling Operations
13 308-3 Submittals Microtunneling
14 601-2.1.2 Engineered Traffic Control Plan
(TCP)
Temporary Traffic Control for
Construction and Maintenance Work
Zones
15 1001-3 Storm Water Pollution
Prevention Plan (SWPPP)
Water Pollution Control
16 1001-4 Water Pollution Control Plan
(WPCP)
Water Pollution Control
* Note: The distance dimensions shown between the bypass pipes and the mainlines are subject to change to field conditions.

Items listed in Table 3-8.2, except for items 1, 2 and, 5, shall be prepared by a Civil or Structural Engineer registered by the State of California. Item 15 shall be prepared by a Qualified SWPPP Developer (QSD) in accordance with 1001 3, “Storm Water Pollution Prevention Plan (SWPPP) .” Item 16 shall be prepared in accordance with 1001-4, “Water Pollution Control Plan (WPCP).” 3-8.3 Shop Drawings.

ADD the following:

1. Shop Drawings shall be submitted electronically to the Agency.

2. Additional Shop Drawings may be required by the Special Provisions and technical specifications.

DELETE Table 3-8.3 in its entirety and REPLACE with following:

TABLE 3-8.3
Item Subsection Title Subject
1 207-2.5 Joints Reinforced Concrete Pipe
2 207-8.4 Joints Vitrified Clay Pipe
3 209-2.2.2 Shop Drawings Steel Pipe and Fittings
4 216-1 General Precast Reinforced Concrete Box
5 218-1 General Precast Vault
6 304-1.1.1 Shop Drawings Structural Steel
7 304-2.1 General Metal Hand Railings

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 105 of 284 ends

3-8.4 Supporting Information.

ADD the following:

1. The Contractor shall submit samples of the materials with cut sheets of the products. The Contractor shall organize cut sheets for review and approval by the Engineer prior to use on the Project and identify deviation from any of the specified material clearly, including cut sheets and samples of both the specified material and basis for the substitution. Included should be the Agency’s Project Name, Project Number, and the Engineer’s name, Contractor Name, and Submittal Number and clearly indicate the specific product to be used.

2. When photos of material are required, they shall be clear in resolution, identify the specific item for review, and shall indicate the name of the item, source, and date taken. The material shown in the photo shall be currently available for use on the Project.

3. For landscaping and irrigation materials, the Contractor shall submit samples and test results to the Engineer within 15 Working Days of the Notice to Proceed.

4. Test sections (“Mock ups”) of materials as required in the Special Provisions shall be accepted by the Engineer before proceeding with the Work.

5. The Contractor shall provide and keep up -to-date a complete “As -Built” record set of blue - line prints, which shall be corrected in red daily and show every change from the original Drawings and Specifications and the exact “As-Built” locations, sizes and kinds of equipment, underground piping, valves, and all other Work not visible at surface grade. Prints for this purpose may be obtained from the Agency at cost. This set of Drawings shall be kept on the job and shall be used only as a Record Set and shall be delivered to the Engineer within 10 Calendar D ays of completion of the Work. Payment for performing the Work required by Section 2-5.4 shall be included in the various Bid items and no additional payment will be made therefore.
3-8.6 Manufacturer’s Operation, Maintenance, and Warranty Instructions.

To sentence (1), DELETE in its entirety and SUBSTITUTE with the following:

For each pre -manufactured product covered by a manufacturer’s warranty, Contractor shall submit 1 electronic copy and 3 bound original or legal copies prior to acceptance of the Contract. 3-9 SUBSURFACE DATA
DELETE in its entirety and SUBSTITUTE with the following:
3-9 TECHNICAL STUDIES AND SUBSURFACE DATA

1. If reports of explorations and tests of Site conditions are referenced in the Contract Documents, Contractor is encouraged to inspect the Site, acquire, and review these reports, and take other necessary steps to thoroughly familiarize oneself with the Site conditions. If a review of the documents and Site inspection indicate an obstruction or utility conflict with the proposed work, immediately notify the Engineer.

2. Subsurface data shall include geotechnical reports, groundwater elevations, soil analyses and characterization, and other information included or referenced in the Special

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 106 of 284 ends

Provisions and shall apply only at the location of the test holes and to the depths indicated.

3. Contractor is encouraged to review subsurface data, examine the Site and assess the Site conditions pertaining to the Work. If a review of the documents and Site inspection indicate an obstruction or utility conflict with the proposed work, immediately notify the Engineer.

4. Soil test reports for test holes which have been drilled are available for review at the office of the Engineer. Additional exploration may be performed at Contractor’s own expense.

5. The indicated groundwater elevation is that which existed on the date specified in the data. It shall be Contractor’s responsibility to determine and allow for the groundwater elevation on the date the Work is performed. A difference in groundwater elevati on between what is shown in soil boring logs and what is encountered during construction shall not be considered as a basis for Extra Work in accordance with 2-8, “Extra Work.” 3-10 SURVEYING
DELETE this Section in its entirety and replace with the following:
3-10.1 Permanent Survey Markers.

The Contractor shall not cover or disturb permanent survey monuments or benchmarks without the consent of the Engineer. Where the Engineer concurs, in writing, with the Contractor that protecting an existing monument in place is impractical, the Contractor shall employ a licensed land surveyor or a registered civil engineer authorized to practice land surveying within the State of California, hereinafter Surveyor, to establish the location of the monument before it is disturbed. The Contractor shall have the monument replaced by the Surveyor no later than thirty (30) days after construction at the site of the replacement is completed. The Surveyor shall file corner record(s) as required by §§ 8772 and 8773, et seq. of the California Business and Professions Code.

When a change is made in the finished elevation of the pavement of any roadway in which a permanent survey monument is located, the Contractor shall adjust the monument frame and cover to the new grade within 7 days of paving unless the Engineer shall appr ove otherwise.

Monument frames and covers shall be protected during street sealing or painting projects or be cleaned to the satisfaction of the Engineer.
3-10.2 Survey Service.

The Contractor shall hire and pay for the services of a Surveyor, hereinafter Surveyor to perform all work necessary for establishing control, construction staking, records research and all other surveying work necessary to construct the work, provide surv eying services as required herein and provide surveying, drafting and other professional services required to satisfy the requirements of the Land Surveyors Act. Surveyor shall be resident on the site during all surveying operations and shall personally supervise and certify the surveying work. 3-10.2.1 Submittal of Surveying Data.

All surveying data submittals shall conform to the requirements of Section 3 -8, “Submittals”,

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 107 of 284 ends

herein. The Contractor shall submit grade sheets to the Engineer before commencing work in the area affected by the grade sheets. The Contractor shall submit field notes for all surveying required herein to the Engineer within ten days of performing the survey. All surveying field notes, grade sheets and survey calculations shall be submitted in bound form on 215mm by 280 mm (81/2” by 11”) paper. The field notes, calculations and supporting data shall be clear and complete.

Supporting data shall include all maps, affidavits, plats, field notes from earlier surveys and all other evidence used by the Surveyor to determine the location of the monuments set. The field notes and calculations will be labeled with name of the Surveyor, the party chief, the field crewmembers and the author of the field notes or calculations. They shall be annotated with the date of observation or calculation, be numbered with consecutive page numbers and shall be readable without resort to any electronic aid, computer program or docu mentation for any computer program. The field notes shall be prepared in conformance with the CALTRANS “Surveys Manual”. The Contractor shall have a Record of Survey prepared by the Surveyor and file it in conformance with §§ 8700 - 8805 of the State of California Business and Professions Code when the Surveyor performs any surveying that such map is required under §§ 8762 of the State of California Business and Professions Code and whenever the Surveyor shall establish, set or construct any permanent survey monument. SDRS drawing M-10 type monuments, bolts, spikes, leaded tacks and nails (when set in concrete), iron pipes, reinforcing steel and all monuments and marks that are at, or accessory to, property corners and street centerlines are permanent survey monuments. The Record of Survey shall show all monuments set, control monuments used, the basis of bearings and all other data needed to determine the procedure of survey and the degree of accuracy attained by the field surveying including the unadjusted ratio of closure. The unadjusted ratio of closure shall not exceed 1 part in 40,000. The record of survey shall show the location and justification of location of all permanent monuments set and their relation to the street right -of-way. Record(s) of Surve y(s) shall be submitted for the Engineer’s review and approval before submittal to the County Surveyor and before submittal to the County Recorder. 3-10.2.2 Survey Requirements.

Stakes shall be set at offsets approved by the Engineer at no greater intervals than specified in TABLE 3-10.2.2(A) as measured along the project stationing. Stakes shall be set to show the location and grade of future curbs adjacent to traffic signal locations where the curb is not being built as a part of this contract. Staking and marking shall be completed by the Surveyor and inspected and approved by the Engineer before the start of construction in the area marked.

Centerline monument shall have the disk stamped with the date the monument was set and the registration number of the Surveyor. Habitat mitigation sites and other areas to be preserved that are shown on the plans shall be staked and flagged prior to the start of any other activities within the limits of the work. When curb and gutter does not exist and is not being installed as a part of the project the location of adjacent facilities being constructed as a part of the contract the Contractor shall place stakes defining the horizontal and vertical location of such adjacent utility vaults, poles or other facilities that are being installed as parts of, or adjunct to, the project either by the Contractor and/or those noted on the plans as to be installed by others.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 108 of 284 ends

TABLE 3-10.2.2(A)
Survey Requirements for Construction Staking

Feature Staked Stake
Description 
Centerline or Parallel to Centerline Spacing,

Lateral Spacing
, 
Setting Tolerance
(Within)
Street Centerline SDRS M-10
Monument
≤1000’, Street Intersections, Begin and end of
curves, only when shown on the plans
on street
centerline

0.02’
Horizontal, also see
Section 2-9.2.1 herein
Clearing Lath in soil,
painted line
on PCC & AC
surfaces
lath - Intervisible, ≤ 50’ on tangents
& ≤ 25’ on curves, Painted line - continuous
at clearing line 1’ Horizontal
Slope RP + Marker
Stake
Intervisible and ≤ 50’ Grade Breaks &
≤ 25’

0.1’ Vertical &
Horizontal
Fence RP + Marker
Stake
≤ 200’ on tangents, ≤ 50’ on curves when
R≥ 1000’ & 25’ on curves when R≤ 1000’
N/A
( constant
offset)

0.1’ Horizontal
Rough Grade Cuts
or Fills ≥ 10 m (33’)
RP + Marker
Stake
≤ 50’ N/A 0.1’ Vertical &
Horizontal
Final Grade
(includes top of:

Basement soil,
subbase and base)
RP + Marker
Stake, Blue-
top in grading
area
≤ 50’ on tangents & curves when R≥ 1000’ &
≤ 25’ on curves when R ≤ 1000’
≤ 22’ 3/8” Horizontal & 1/4”
Vertical
Asphalt Pavement
Finish Course
RP, paint on
previous
course
≤ 25’ or as per the intersection grid points
shown on the plan whichever provides the
denser information
edge of
pavement,
paving pass
width, crown
line & grade
breaks
3/8” Horizontal & 1/4”
Vertical
Drainage
Structures, Pipes &
similar Facilities,

RP + Marker
Stake
intervisible & ≤ 25’, beginning and end, BC & EC
of facilities, Grade breaks, Alignment breaks,
Junctions, Inlets & similar facilities, Risers &
similar facilities (except plumbing), Skewed cut-
off lines
as appropriate 3/8” Horizontal & 1/4”
Vertical
Curb RP + Marker
Stake
≤ 25’, BC & EC, at ¼∆, ½∆ & ¾∆ on curb returns
& at beginning & end
( constant
offset)
3/8” Horizontal & 1/4”
Vertical
Traffic Signal  Vertical locations shall be based on the ultimate elevation of curb and sidewalk

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 109 of 284 ends

Feature Staked Stake
Description 
Centerline or Parallel to Centerline Spacing,

Lateral Spacing
, 
Setting Tolerance
(Within)
Signal Poles &
Controller 
RP + Marker
Stake
at each pole & controller location as appropriate 3/8” Horizontal & 1/4” Vertical
Junction Box  RP + Marker
Stake
at each junction box location as appropriate 3/8” Horizontal & 1/4” Vertical
Conduit  RP + Marker
Stake
≤ 50’ on tangents & curves when R≥ 1000’ &
≤ 25’ on curves when R ≤ 1000’ or where grade
≤ 0.30%
as appropriate 3/8” Horizontal & when
depth cannot be
measured from existing
pavement 1/4” Vertical
Minor Structure  RP + Marker
Stake + Line
Stake
for catch basins: at centerline of box, ends of
box & wings & at each end of the local
depression 
as appropriate 3/8” Horizontal & 1/4”
Vertical (when vertical
data needed)
Abutment Fill RP + Marker
Stake + Line
Stake
≤ 50’ & along end slopes & conic transitions as appropriate 0.1’ Vertical & Horizontal
Wall  RP + Marker
Stake + Line
Point +Guard
Stake
≤ 50’ and at beginning & end of: each wall, BC
& EC, layout line angle points, changes in
footing dimensions &/or elevation & wall
height
as appropriate 1/4” Horizontal & 1/4”
Vertical
Major Structure 
Footings, Bents,
Abutments &
Wingwalls
RP + Marker
Stake + Line
Point +Guard
Stake
10’ to 33’ as required by the Engineer, BC & EC,
transition points & at beginning & end.

Elevation points on footings at bottom of
columns
as appropriate 3/8” Horizontal & 1/4”
Vertical
Superstructures RP 10’ to 33’ sufficient to use string lines, BC & EC, transition points & at beginning & end.

Elevation points on footings at bottom of
columns
as appropriate 3/8” Horizontal & 1/4”
Vertical
Miscellaneous 
Contour Grading

RP + Marker
Stake
≤ 50’ along contour
line

0.1’ Vertical &
Horizontal
Utilities ,  RP + Marker
Stake
≤ 50’ on tangents & curves when R≥ 1000’ &
≤ 25’ on curves when R ≤ 1000’ or where grade
≤ 0.30%
as appropriate 3/8” Horizontal & 1/4”
Vertical
Channels, Dikes
& Ditches 
RP + Marker
Stake
intervisible & ≤ 100’, BC & EC of facilities, Grade
breaks, Alignment breaks, Junctions, Inlets &
similar facilities
as appropriate 0.1’ Horizontal & 1/4”
Vertical
Signs  RP + Marker
Stake + Line
Point +Guard
Stake
At sign location Line point 0.1’ Vertical &
Horizontal
Subsurface
Drains 
RP + Marker
Stake
intervisible & ≤ 50’, BC & EC of facilities, Grade
breaks, Alignment breaks, Junctions, Inlets &
similar facilities, Risers & similar facilities
as appropriate 0.1’ Horizontal & 1/4”
Vertical

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 110 of 284 ends

Feature Staked Stake
Description 
Centerline or Parallel to Centerline Spacing,

Lateral Spacing
, 
Setting Tolerance
(Within)
Overside Drains

RP + Marker
Stake
longitudinal location At beginning &
end

0.1’ Horizontal & 1/4”
Vertical
Markers  RP + Marker
Stake
for asphalt street surfacing ≤ 50’ on tangents &
curves when R≥ 1000’ & ≤ 25’ on curves when
R ≤ 1000’.

At marker
location(s)
1/4” Horizontal
Railings &
Barriers 
RP + Marker
Stake
At beginning & end and ≤ 50’ on tangents &
curves when R ≥ 1000’ & ≤ 25’ on curves when
R ≤ 1000’
at railing &
barrier
location(s)
3/8” Horizontal &
Vertical
AC Dikes  RP + Marker
Stake
At beginning & end as appropriate 0.1’ Horizontal &
Vertical
Box Culverts 10’ to 33’ as required by the Engineer, BC & EC, transition points & at beginning & end.

Elevation points on footings & at invert
as appropriate 3/8” Horizontal & 1/4”
Vertical
Pavement
Markers
RP 200’ on tangents, 50’ on curves when
R ≥ 1000’ & 25’ on curves when R ≤ 1000’. For
PCC surfaced streets lane cold joints will suffice
at pavement
marker
location(s)
1/4” Horizontal
 Staking for feature may be omitted when adjacent marker stakes reference the offset and elevation of those features and the accuracy requirements of the RP meet the requirements for the feature  Reference points shall be sufficiently durable and set securely enough to survive with accuracy intact throughout the installation & inspection of the features or adjacent facilities for which they provide control. RP means reference point for the purposes of this table
 Perpendicular to centerline.
 Some features are not necessarily parallel to centerline but are referenced thereto  Multi-plane surfaced features shall be staked so as to provide line & grade information for each plane of the feature  ≥ means greater than, or equal to, the number following the symbol. ≤ means less than, or equal to, the number following the symbol.
 The cut datum for storm drainage & sanitary sewer pipes & similar structures shall be their invert. The cut datum for all other utilities shall be the top of their pipe or conduit.

All guard stakes, line stakes and lath shall be flagged. Unless otherwise approved by the Engineer flagging, paint and marking cards shall be the color specified in TABLE 3-9.2.2(B) TABLE 3-10.2.2(B)
Survey Stake Color Code for Construction Staking
Type of Stake Description Color*
Horizontal Control Coordinated control points, control lines, control reference points, centerline, alignments, etc.

White/Red
Vertical Control Bench marks
White/Orange
Clearing Limits of clearing Yellow/Black

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 111 of 284 ends

Grading Slope, intermediate slope, abutment fill, rough grade, contour grading, final grade, etc.

Yellow
Structure Bridges, sound and retaining walls, box culverts, etc. White Drainage, Sewer, Curb Pipe culverts, junction boxes, drop inlets, headwalls, sewer lines, storm drains, slope protection, curbs, gutters, etc.

Blue
Right-of-Way Fences, R/ W lines, easements, property monuments, etc. White/Yellow Miscellaneous Signs, railings, barriers, lighting, etc. Orange * Flagging and marking cards, if used.

3-10.3 Private Engineers.

Surveying by private engineers on the Work shall conform to the quality and practice required by the Engineer.
3-10.4 Line and Grade.

All work shall conform to the lines, elevations, and grades shown on the Plans.

Three consecutive points set on the same slope shall be used together so that any variation from a straight grade can be detected. Any such variation shall be reported to the Engineer. In the absence of such report, the Contractor shall be responsible for any error in the grade of the finished work.

Grades for underground conduits will be set at the surface of the ground. The Contractor shall transfer them to the bottom of the trench.
3-10.5 Payment for Survey.

Payment for work performed to satisfy the requirements of Sections 3-10.1 through 3-10.4 shall be included in the actual bid items requiring the survey work and no additional payment will be made. Extension of unit prices for extra work shall include full compensation for attendant survey work and no additional payment will be made. Payment for the replacement of disturbed monuments and the filing of records of survey and/or corner records, including filing fees, shall be incidental to the work necessitatin g the disturbance of said monuments and no additional payment will be made.
3-12 CONTRACT INFORMATION SIGNS
ADD the following:

Signs shall not be posted until approved by the Engineer. The Contractor shall complete and submit a Review for Sign Permit (form P-11), available at:

https://www.carlsbadca.gov/departments/community-development/permits-applications- forms

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 112 of 284 ends

3-12 WORK SITE MAINTENANCE
3-12.1 General.

ADD the following:

1. Maintain Site improvements including any temporary facilities, equipment, or other materials. Remove graffiti encountered on the Site within 24 hours. See also SECTION 400 - PROTECTION AND RESTORATION.

2. As a condition of Final Payment, the Contractor shall submit a signed and notarized affidavit stating that all brush, trash, debris, and surplus materials resulting from this Project have been disposed of in a legal manner. The cost of disposal is the Contractor’s responsibility.

3. The Contractor shall provide and maintain enclosed toilets for the use of their employees.

Toilets must be kept in a neat and sanitary condition and ensure that they comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps. The cost of such is the Contractor’s responsibility.

4. If required in the Special Provisions, the Contractor shall provide and maintain enclosed toilets for the use of the Agency’s and Contractor’s officers, employees, or agents. Toilets must be kept in a neat and sanitary condition and ensure that they comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps. The cost of such is the Contractor’s responsibility.

5. The Contractor shall maintain drainage within and through the work areas. Earth dams will not be permitted in paved areas. Temporary dams of sandbags, asphaltic concrete, or other acceptable material will be permitted, when necessary, by the SWPPP and/ or BMP plan. Such dams shall be removed from the Site as soon as their use is no longer necessary.

6. Work Site maintenance shall be conducted on non- workdays when increased levels of maintenance are deemed necessary, in the opinion of the Engineer, to preserve the health safety or welfare of the public and or to comply with applicable regulations.

7. Disposal of all rubbish and surplus materials is incidental to Work Site maintenance. Disposal shall be made off the Site and shall be in accordance with:
a. Local codes and ordinances that govern locations and methods of disposal. b. All applicable safety laws.
c. Requirements of Subpart H, S ection 1926.252 of the OSHA Safety and Health Standards for Construction.

8. Work Site maintenance is considered incidental to the items of work that they are associated with and no additional payment will be made.

9. Cleanup and Dust Control. Throughout all phases of construction, including suspension of the Work, and until the final acceptance, the Contractor shall keep the Site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by cleaning, sweeping, and sprinkling with water, or other means as necessary. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods. 3-12.2 Air Pollution Control.

ADD the following:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 113 of 284 ends

1. Contractor shall carry out effective measures whenever and as often as necessary to prevent Contractor’s operation from producing dust in amounts damaging to property, cultivated vegetation, domestic animals, or causing a nuisance to persons living or occupying buildings in the vicinity. Contractor shall be responsible for an y damage resulting from any dust originating from Contractor’s operations. The dust abatement measures shall be continued until Contractor is relieved of further responsibility by the Engineer.

2. Contractor shall adhere to Air Pollution Control District County of San Diego regulations for equipment used on the Job Site.
3-12.3 Noise Control.

ADD the following:

1. All internal combustion engines used in the Work shall be equipped with mufflers in good repair and are subject to the City Noise Control Ordinance, Carlsbad Municipal Code Chapter

8.48. 2. Site mustering is not allowed prior to and after the allowable working hours.

3. The following shall be implemented to control noise and vibration during construction:

Do not exceed 86 dBA Lmax at 50 feet from the job site from 9:00 p.m. to 6:00 a.m. 3-12.4 Storage of Equipment and Materials.
3-12.4.1 General.

ADD the following:

1. Equipment and material storage shall be confined to areas approved by the Engineer.

Disposal of all rubbish and surplus materials shall be at the Contractor’s expense.

2. The Contractor shall order, purchase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, prepare storage area(s), store, handle, protect, move, relocate, remove and dispose excess of all materials used to accomplish the Work.

3. Materials shall be delivered to the Work Site only during Working Hours, and shall be accompanied by bills of lading that shall clearly state for each delivery: the name of the Contractor as consignee, the Project name and number, address of delivery and name of consignor and a description of the material(s) shipped.

4. Prior to storage of any materials which have been shipped to or by the Contractor to any location within the City’s boundaries the Contractor shall provide the Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored and shall provide for the removal of the materials and restoration of the storage site within the time allowed for the Work.

5. All such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the location of the site on which the materials are stored. Storage of hazardous wastes, construction equipment ma terial, and parking and fueling of equipment shall not occur in biologically sensitive areas.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 114 of 284 ends