2025-09-09; City Council; 05; Adoption of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble

Carlsbad City Council
September 9, 2025

Document
2025-09-09; City Council; 05; Adoption of Plans, Specifications and Contract Documents and Authorization to Advertise for Bids for the El Camino Real Widening from Poinsettia Lane to Camino Vida Roble
Meeting
September 9, 2025
Body
Carlsbad City Council
Pages
286
Original file
765 KB
Text extracted from the city's file for reading and search. Open the original on records.carlsbadca.gov. That file is the official record.

6. Loss, damage or deterioration of all stored materials shall be the Contractor’s responsibility.

Conformance to the requirements of this section, both within and outside the limits of work is a part of the Work. The Engineer shall have the right to verify the suitability of materials and their proper storage at any time during the Work.

7. The Contractor shall furnish and maintain in good condition all equipment and facilities as required for the proper execution and inspection of the Work. Such equipment and facilities shall meet all requirements of applicable ordinances and laws.

8. Restore the storage area to an equal or better condition as deemed necessary by the Engineer and at no additional cost to the Agency.

10. When required by the Engineer, the Contractor shall furnish and operate a self-loading motor sweeper with spray nozzles at least once each Working Day for the purpose of keeping paved areas acceptably clean wherever construction, including restoration, is incomplete.

11. Care shall be taken to prevent spillage on haul routes. Any such spillage shall be removed immediately, and the area cleaned.

12. Excess excavation material from catch basins or similar structures shall be removed from the Site immediately. Sufficient material may remain for use as backfill if permitted by the Specifications. Forms and form lumber shall be removed from the Site as soon as practicable after stripping.

13. Failure of the Contractor to comply with the Engineer’s cleanup orders may result in an order to suspend Work until the condition is corrected. No additional compensation will be allowed because of such suspension.

14. Cleanup and dust control required in the Contract shall also be executed on weekends and other non-Working Days when needed to preserve the health safety or welfare of the public.

The Contractor shall conduct effective cleanup and dust control throughout the duration of the Contract. The Engineer may require increased levels of cleanup and dust control that, in his/her sole discretion, are necessary to preserve the health, safety and welfare of the public.

Cleanup and dust control shall be considered incidental to the items of W ork that they are associated with and no additional payment will be made for them.

15. Vermin Control. At the time of acceptance, structures entirely constructed under the Contract shall be free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contra ct time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors resulting from extermination operations.

16. Temporary Light, Power, and Water. The Contractor shall furnish, install, maintain, and remove all temporary light, power, and water at its own expense. These include piping, wiring, lamps, and other equipment necessary for the Work. The Contractor shall n ot draw water from any fire hydrant (except to extinguish a fire), without obtaining permission from the water agency concerned. The Contractor shall obtain a construction meter for water used for the construction, plant establishment, maintenance, cleanup, testing and all other work requiring water related to this Contract. The Contractor shall contact the appropriate water agency for requirements. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter and any, and all, other charges, deposits and/or fees

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 115 of 284 ends

for them . These costs shall be considered incidental to the items of W ork that they are associated with and no additional payment will be made for them. 3-12.4.2 Storage in Public Streets.

DELETE in its entirety and SUBSTITUTE with the following:

1. Construction materials shall not be stored in streets, roads, or highways for more than 5 Calendar Days after unloading. All materials not installed or used in construction within 5 Calendar Days after unloading shall be stored at a location approved by the Engineer.

2. Construction equipment shall not be stored at the Work Site before its actual use nor for more than 5 Calendar Days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer.

3. Excavated material, except that which is to be used as backfill in the adjacent trench, shall not be stored in public streets unless otherwise permitted. Immediately after placing backfill, all excess material shall be removed.

4. The Contractor shall not store equipment for traffic control in right of way.

ADD 3- 12.4.3 Storage and Staging Areas.

1. Storage and staging areas are the Contractor’s responsibility. If the Plans designate a staging location within the Project or in close proximity, the Contractor may utilize such area for their use. The storage and staging areas shall be as close as possible to the Site. Contractor is responsible for obtaining any permits, leases, or any other items necessary to obtain staging areas.

2. Storage of hazardous wastes, construction equipment material, and parking and fueling of equipment shall not be allowed in the MHPA or other biologically sensitive areas. Ensure the fueling of vehicles occurs only within designated staging areas using appropriate catch basins and devices.

3. Return the storage and staging area and the adjacent area to an equal or better condition as deemed necessary by the Engineer, at no additional cost to the Agency.

4. The Contractor shall provide the Engineer a copy of the lease agreement for any property to be used for the storage of materials or equipment prior to delivery or storage of any materials or equipment. Each lease agreement shall clearly state the term of the lease and a description of the materials or equipment allowed to be stored and shall provide for the removal of the materials or equipment and restoration of the storage site within the time allowed for the Work.

5. Construction equipment shall not be stored at the Work Site before its actual use on the Work nor for more than 5 Calendar Days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer. 3-12.6 Water Pollution Controls
3-12.6.2 Best Management Practices (BMPs).

ADD the following:

1. Contractor shall submit a BMP plan as a submittal to the Agency.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 116 of 284 ends

3-12.6.3 Storm Water Pollution Prevention Plan (SWPPP).

ADD the following:

1. The Contractor shall evaluate the requirements for the preparation of a SWPPP for Work within the City’s boundary by reviewing the Determination of SWPPP Tier Level and Construction Threat Level (form E-32), which may be obtained at:

https://www.carlsbadca.gov/departments/community-development/permits-applications- forms

2. The Contractor shall review the criteria requiring the preparation of a SWPPP conforming with the State Water Resources Control Board Order No. 2022-0057-DWQ, NPDES General Permit No. CAS000002, Waste Discharge Requirements for Discharges of Storm Water Runoff Associated with Construction and Land Disturbance Activities (the Construction General Permit or CGP). The CGP and other information are available at:

https://www.waterboards.ca.gov/water_issues/programs/stormwater/construction/ge neral_permit_reissuance.html

3. If a SWPPP has been prepared specifically for the Project and is included as a part of the Contract Documents, the Contractor shall use the SWPPP as a baseline document and shall amend the SWPPP, with the Engineer’s approval, as necessary to include the Co ntractor’s proposed Construction Schedule, construction operations, and the S ite conditions encountered or created during the Work.

4. If the Agency has not prepared a SWPPP for the Project and the Project is subject to coverage under the CGP, the Contractor shall prepare and implement the SWPPP conforming with the CGP requirements.

5. The Contractor shall comply with all requirements of the approved SWPPP and the CGP including implementation during construction by a QSP, The Contractor shall provide all information necessary for the Agency to obtain coverage under the CGP during the electronic submittal of Permit Registration Documents and supporting data necessary for the filing of the storm water Notice of Intent and Notice of Termination. The Contractor shall be responsible for conducting all monitoring and inspections and filing all reports required by and in accordance with the CGP.
3-12.6.3 .1 Storm Water Pollution Prevention Plan (SWPPP) Tier 1 or Tier 2 Project .

Not applicable
3-12.6.3 .2 Storm Water Pollution Prevention Plan (SWPPP) Tier 3 Project .

PROJECTS GREATER THAN ONE ACRE (TIER 3) – Not Maintenance Only Projects Water Pollution Prevention. The Contractor shall plan for and implement temporary construction BMPs to mitigate the water quality impacts of land disturbance and non- storm water discharges related to construction activities. BMPs are the schedules of activities, prohibitions of practices, maintenance pr ocedures and other management practices employed

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 117 of 284 ends

during construction activities to prevent or reduce pollution of bodies of water protected by the federal Clean Water Act (33 U.S.C. § 1251 , et seq.) and the state Porter -Cologne Water Quality Control Act (Water Code , § 13000, et seq.), which include oceans, lagoons, lakes, streams and other sensitive water bodies and water courses. Construction BMPs also include physical devices and structural construction control measures designed to prevent soil erosion from occurring on the Work S ite, or that are designed to prevent sediment from leaving the Work S ite, both of which are referred to hereafter as “Water Pollution .” BMPs are also intended to protect the health, safety and welfare of the public and to prevent damage to adjoining public and private property resulting from construction.

This Project, and all P roject Work, requires compliance with Carlsbad Municipal Code Chapter

15.12 and coverage under the California Storm Water Discharges Associated with Construction and Land Disturbance Activities, Order No. 2022 -0057-DWQ, NPDES No. CAS000002, or subsequent order, and any amendment, revision or re -issuance of it (Construction General Permit).

STORM WATER POLLUTION PREVENTION PLAN DEVELOPMENT AND IMPLEMENTATION The Contractor shall prepare and submit to the Engineer a SWPPP in accordance with the current requirements established by the Construction General Permit. As used in this section, “Engineer” shall have the same meaning as “Construction Manager. ” The Contractor shall n ot initiate any land disturbance activities, until the final SWPPP has been accepted by the Engineer. At least 1 copy of the final SWPPP shall be kept at the construction Site and shall be available upon request of a representative of the Regional Water Quality Control Board, State Water Resources Control Board, U.S. Environmental Protection Agency or local storm water management agency.

Requests for a copy of the final SWPPP by members of the public shall be forwarded to the Engineer.

SWPPP Template Availability. A model SWPPP, if available, is provided to the Contractor, for use in preparing the Project SWPPP for approval by the Agency. The Contractor shall be responsible for the preparation and implementation of the SWPPP and coordination with the Agency and the Regional Water Quality Control Board. All costs for preparing and implementing the Storm Water Pollution Prevention and Monitoring Plans and coordination with the Agency and the Regional Water Quality Control Board shall be included as part of the contract bid price.

SWPPP Delivery. Within 15 Calendar Days after the execution of the Contract, the Contractor shall submit 3 copies of the SWPPP to the Engineer. Contractor will be provided the digital format for SWPPP to complete required sections . If revisions are required, as determined by the Engineer, the Contractor shall revise and resubmit the SWPPP within 15 Calendar Days of receipt of the Engineer’s comments and shall allow 5 Calendar D ays for the Engineer to review the revisions. Upon the Engineer’s acceptance of the SWPPP, 3 additional copies of the SWPPP, incorporating the required changes, shall be submitted to the Engineer. To allow construction

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 118 of 284 ends

activities to proceed, the Engineer may conditionally approve the SWPPP while minor revisions are being completed.

QSD/QSP Designation. The Contractor shall designate a QSD and a QSP who has satisfied the certification requirements and received approval by the SWRCB as specified in Construction General Permit. The QSD and QSP shall provide and maintain levels of insurance, and comply with all other insurance -related requirements, as required in Agency Supplemental General Provisions Section 5-4.

SWPPP Amendments. All amendments to the SWPPP shall be completed by the Contractor's QSD in a timely manner and provided to the Engin eer within 7 Calendar Days. All amendments must be signed and dated by the Contractor's QSD and directly attached to the SWPPP once accepted by the Engineer.

Accepted amendments shall be dated and logged in the SWPPP. Upon acceptance of the amendment, the Contractor shall implement the additional control measures or revised operations. The SWPPP amendment log in the SWPPP shall be maintained by the C ontractor's QSD.

The SWPPP shall also be amended if it violates any condition or has not effectively achieved the objective of reducing pollution in storm water discharges. Amendments shall show additional control measures or revised operations, including those in areas no t shown in the initially accepted SWPPP, which are required on the P roject to control Water Pollution effectively.

Amendments to the SWPPP shall be submitted for review and acceptance by the Engineer in the same manner specified for the initially accepted SWPPP.

SWPPP Implementation. Upon acceptance of the SWPPP, the Contractor shall be responsible throughout the duration of the Project for installing, constructing, inspecting and maintaining the control measures included in the SWPPP and any amendments thereto and for removing and disposing of temporary control measures. Unless otherwise directed by the Engineer or specified in these supplemental provisions, the Contractor's responsibility for SWPPP implementation shall continue throughout any temporary suspension of Work ordered in accordance with Section 6 - 6, “Suspension of the Work .” Requirements for installation, construction, inspection, maintenance, removal and disposal of control measures are specified in the “Handbook” and these supplemental provisions.

Permit Registration Documents . The Contractor's QSD shall then complete final SWPPP , and other required Permit Registration Documents (PRDs) , and submit them to the Engineer for review and subsequent submittal to the SWRCB via the Stormwater Multi-Application, Reporting, and Tracking System (SMARTS System).

PRD Item Responsible Party Notes
NOI Filing Agency Project Engineer/MPM
NOI Fee Agency Project Engineer/MPM
Annual Permit Fee Agency Project Engineer/MPM
Legally Responsible Person Agency Project Engineer/MPM
Assigned Signatory Agency Project Engineer/MPM

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 119 of 284 ends

Data Submitter Contractor/QSD/QSP

SWPPP QSD
Risk Determination QSD
SWPPP Certification
Statement
QSD
SWPPP Amendments QSD Must be approved by the
Project Engineer/MPM
Site Map Contractor/QSD
BMP Exhibit/Erosion Control
Notes
Contractor/QSD
Inspections/Training Records QSP
Water Quality Monitoring
Reports
QSP
NOT Preparation and
Submittal
Contractor/QSD Submitted as part of Project
Completion Tasks. No later
than 90 Calendar Days after
Project
completion
NOT Certification Agency Project Engineer/MPM
Annual Report Preparation
and Submittal to SMARTS
Contractor/QSD By July 15th for prior year
period of July 1st through
June 30th
Annual Report Certification Agency Project Engineer/MPM. No later than September 1st
Non-Compliance. The Engineer may suspend the Work, as provided in Agency Supplemental General Provisions Section 6 -6, at the Contractor’s cost, if the Engineer determines that the Contractor has failed to satisfy all requirements of this Section. I f the Contractor violates any provisions of t his subsection, or if Water Pollution occurs in the Work Site for any reason, the Contractor shall immediately notify the Engineer.

The Contractor s hall also submit a written report to the Engineer describing the incident and corrective actions taken within 24 hours of the occurrence of the incident. If for any reason the Engineer detects Water Pollution before notification by the Contractor, the required written report shall also include an explanation of why the Contractor had not timely notified the Engineer.

Implementation Costs. Preparation, implementation and management of Water Pollution prevention activities are incidental to the items of Work and Agency shall not make additional payment to Contractor for these costs.

Project Completion. Within 7 Calendar Days of Project completion, the P roject-specific SWPPP shall be relinquished to the Agency. In addition, the Contractor shall submit the NOT to the SWRCB. The NOT shall be submitted to the Agency at the same time it is submitted to the SWRCB.

The Contractor shall only submit the NOT once the Project has been accepted by the Agency. If

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 120 of 284 ends

the Contractor fails to submit the NOT to the SWRCB, the Contractor shall continue to be responsible for paying the annual fee associated with the “General Permit” until the NOT is submitted and accepted by the SWRCB.
3-12.6.5 Payment.

DELETE in its entirety and SUBSTITUTE with the following:

1. Unless otherwise specified, payment for water pollution control, including implementation and maintenance of BMPs, shall be considered as included in the Contract Unit Price for each item in the Bid.

Payment for dewatering shall be as specified in the Special Provisions.

ADD 3- 12.7 Vermin Control.

1. The Site and structures constructed under the Contract shall be kept free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contract time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors resulting from extermination operations.
3-13 COMPLETION, ACCEPTANCE, AND WARRANTY
3-13.1 Completion.

DELETE in its entirety and SUBSTITUTE with the following:

1. The Contractor shall comply with the following prior to requesting a Pre -Final inspection of the Work and filing of a written assertion that the Work has been completed:
a. Provide completed and signed redline drawings and record documents including installation, maintenance and operation instructions, manuals and/or tools for installed equipment.
b. Provide and properly label all keys for existing facilities or new permanent work. c. Provide all items specified to be supplied as extra stock and spare parts. Wrap, seal, or place in a container all items as necessary to allow for storage by the Agency for future use. Verify the specified quantities.
d. Provide all final Special Inspection reports and certifications required by equipment manufacturers to demonstrate compliance with applicable codes and standards. e. Obtain any required certifications from the Engineer of Record for permanent BMPs. f. Comply with all requirements of permits issued by jurisdictional agencies. g. Remove temporary facilities from the Site.
h. Thoroughly clean the Site and remove all mark-outs and construction staking.

2. The Agency Inspector will schedule the Pre-Final inspection within 5 Working Days of receipt of the Contractor’s request. The Inspector will generate a list of deficiencies (Punchlist) within 5 Working Days after the Pre-Final inspection.

3. The Contractor shall have 30 Working Days to correct the deficiencies and provide a written response to each Punchlist item. The Inspector will review the corrective work within 5

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 121 of 284 ends

Working Days of receipt of the Contractor’s written response to each Punchlist item. Any outstanding deficiencies will be considered incomplete Work and the Punchlist will be returned to Contractor. Full payment will not be made for any Bid item with outstanding deficiencies and a Final Inspection will not be scheduled until all deficiencies are completed to the satisfaction of the Inspector.

4. The Contractor shall submit a request for Final Inspection which shall include a written assertion that the Work has been completed in accordance with the Contract Documents and a written response describing the corrective Work completed for all punch list items identified in the Pre -Final inspection(s). The request for Final Inspection will not be considered without the Contractor’s written response to the punch list items. The Inspector will schedule the Final Inspection within 10 Working Days of receipt of the Contractor’s request and invitees will include the Construction Manager, Engineer and representatives from agencies or utility companies having jurisdiction over the Work. The Contractor’s attendance is mandatory.

5. If, in the Engineer’s judgment, the Work has been completed in accordance with the Contract Documents, the Engineer will set forth in writing the date the Work was completed. This will be the date when the Contractor is relieved from responsibility to protect and maintain the Work, and to which liquidated damages will be computed.

ADD 3- 13.1.1 Requirements Before Requesting a Walk-through.

1. The following items are required prior to requesting a Walk-through:
a. Remove temporary facilities from the Site.
b. Thoroughly cleaning the Site and removing all mark outs and construction staking. c. Submit proposed r ed-line record drawing s in accordance with Contract Document requirements.
d. Provide all material and equipment maintenance and operation instructions and/or manuals.
e. Provide all tools which are a permanent part of the equipment installed in the Project. f. Provide and properly identify all keys for construction and all keys for permanent work.
g. Provide all final Special Inspection reports required by the applicable building code. h. Provide all items specified to be supplied as extra stock. Wrap, seal, or place in a container all items as necessary to allow for storage by the Agency for future use.

Verify the specified quantities.
i. Ensure that all specified equal opportunity (if applicable) and certified wage rate documentations covering the Contract Time have been submitted. j. Provide the spare parts for the proposed irrigation system as specified in the Special Provisions.

2. Contractor shall notify the Engineer to arrange a final inspection of permanent BMPs installed and shall obtain the completed, signed, and stamped DS-563 Form 30 Calendar Days prior to the issuance of the Notice of Completion.

ADD 3- 13.1.2 Walk-through and Punchlist Procedure.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 122 of 284 ends

1. When Contractor considers that the Work and Services are complete, notify the Engineer in writing that the Project is complete and request that the Contractor and the Engineer perform a Walk -through for the generation of a Punchlist. Contractor shall request the final walkthrough at least 7 Working Days in advance.

2. The Engineer will first determine if the Project is ready for a Walk -through by verifying whether the Contractor have completed all items as required by 3 -13.1.1, “Requirements Before Requesting a Walk-through.”

3. If the Work includes sewer and storm drain installations, the inspection shall include televising in accordance with the requirements in the Contract Documents.

4. The Engineer shall facilitate the Walk-through.

5. Contractor shall make Plans, specifications, and technical data, such as submittals and equipment manuals, available at the Site for the Walk-through attendees.

6. The Engineer will provide the Contractor with the Punchlist within 15 Working Days after the date of the Walk -through and submit it to the Contractor. The Agency shall not provide a preliminary Punchlist.

7. If the Engineer finds that the Project is not substantially complete as defined in the Contract, the Engineer will terminate the Walk-through and notify the Contractor in writing.

8. If, at any time during the Engineer’s evaluation of the corrective Work required by the Punchlist, the Engineer discovers that additional corrective Work is required, the Engineer may include that corrective Work in the Punchlist. Contractor shall remain solely responsible for the Project Site until the Project is completely operational, all Punchlist items have been corrected, and all operation and maintenance manuals have been accepted by the Agency.

9. The Engineer shall meet with the Contractor until all Punchlist items are corrected. If Contractor takes longer than 30 Working Days to complete the corrective Work, the Project shall be subject to re-evaluation.

10. Upon acceptance of the Work, Contractor shall assemble and deliver to the Engineer all records, documents, warranties, material certifications, bonds, guarantees, maintenance and service agreements, and maintenance and operating manuals. Written warranties , except manufacturer’s standard printed warranties, shall be on a letterhead addressed to the Contractor. Warranties shall be submitted in the format described in this section, modified as approved by the Agency, to suit the conditions pertaining to the warranty. 3-13.2 Acceptance
DELETE in its entirety and SUBSTITUTE with the following:

1. Acceptance of the Work will occur after all the requirements of the Contract Documents have been fulfilled. If, in the Engineer’s judgment, the Contractor has fully performed the Contract, the Engineer will recommend to the City Manager for the City of Car lsbad or Executive Manager for the Carlsbad Municipal Water District that the Contractor’s performance of the Contract be accepted. Upon such certification by the Engineer, the City Manager or Executive Manager may accept the Work. Upon the acceptance of the Work by the City Manager or Executive Manager, a “Notice of Completion” will be filed in the office of the San Diego County Recorder. The date of recordation shall be the date of acceptance of the Work.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 123 of 284 ends

3-13.3 Warranty.

DELETE in its entirety and SUBSTITUTE with the following:

1. Contractor shall warranty and repair all defective materials and workmanship for a period of 1 year. This warranty period shall start on the date the Work was recorded by the “Notice of Completion” unless the Agency has beneficial use of the Project (excluding water, sewer, and storm drain projects). In addition, Contractor shall warranty the Work against all latent and patent defects for a period of 10 years.

2. The warranty period for specific items covered under manufacturers’ or suppliers’ warranties shall commence on the date they are placed into service at the direction of or as approved by the Engineer in writing.

3. All warranties, express or implied, from Subcontractors, manufacturers, or suppliers, of any tier, for the materials furnished and work performed shall be assigned, in writing, to the Agency, and shall be delivered to the Engineer prior to the acceptance of the Contractor’s performance of the Contract.

4. Replace or repair defective materials and workmanship in a manner satisfactory to the Engineer after notice to do so from the Engineer and within the time specified in the notice.

If Contractor fails to make such replacements or repairs within the time spe cified in the notice, the Agency may perform the replacement or repairs at Contractor’s expense. If Contractor fails to reimburse the Agency for the actual costs, Contractor’s Surety shall be liable for the cost.

5. The warranty period shall be extended with respect to portions of the Work corrected under warranty. Items that shall be warrantied free from defective workmanship and materials for a period longer than 1 year are as follows:

Specified Item Minimum Warranty Period
Detectable Warning Tile
Construction
3 Years of Manufacturer’s Warranty
All Work Under SECTION 500 – PIPELINE

REHABILITATION
3 Years
Fiber Optic Interconnect Cables 2 Years
Luminaires1 10 Years of Manufacturer’s Warranty
LED Signal Modules 3 Years of Manufacturer’s Warranty
1 Provide documentation verifying that the induction luminaire models being offered for the Project are covered by the 10-year warranty.

6. Contractor shall provide the Agency a copy of the manufacturer’s warranty for private sewer pumps, including the alarm panel and all other accessories. a. Contractor shall involve the manufacturer in the installation and startup as needed to secure any extended warranty required.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 124 of 284 ends

b. This section is not intended to limit any manufacturer’s warranty which provides the Agency with greater warranty rights than set forth in this section or the Contract Documents.
c. The warranty shall include all components. The form of the warranty shall be approved by the Engineer in accordance with 3 -13.3.2, “Warranty Format Requirements.”

7. If, during the warranty period, any item of the Work is found to be Defective Work, Contractor shall correct it promptly after receipt of written notice from the Agency to do so. The warranty period shall be extended with respect to portions of the Work co rrected as part of the warranty requirements.

ADD 3- 13.3.1 Defective Work.

1. If the Engineer finds any part of the Work, to be defective or not in compliance with the Contract Documents, the Contractor shall correct the Defective Work in accordance with the Engineer’s written instructions and within the specified time limits.

2. The Engineer may order Contractor to stop all or part of the Project if, upon notice, Contractor fails to immediately correct the Defective Work in conformance with the Contract Documents. The Contractor bears all direct and indirect costs and damages that result from the Agency’s Stop Work notice.

3. The Engineer may determine in its sole discretion to accept Defective Work instead of having the Contractor correct the Defective Work. However, the Contractor will still be financially responsible for the Defective Work. The Engineer shall issue a deductive Change Order and will incorporate the necessary revisions in the Contract Documents for the Defective Work, the diminished value to the Project, or for the cost to repair the Defective Work.

4. If the Contractor fails to correct Defective Work within the specified time limits, the Engineer may correct the Contractor’s Defective Work. The Agency has the right to correct any Defective Work without notice in the event of an emergency. Contractor sha ll bear all direct and indirect costs of the Defective Work that the Agency corrects.

5. When undertaking remedial action under this section, the Agency may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s Work and or services, and incorporate into the Project all materials and equipment stored at the Site or for which the Agency has paid but Contractor has stored elsewhere.

6. For Building Projects which require a certificate of occupancy, not including sewer and water facilities, if the Contractor fails to correct the Defective Work listed on the Agency’s Punchlist within 30 Working Days in accordance with 6 -1.1, “Construction Schedule,” the Contractor shall reimburse the Agency for all costs to provide inspection services required to monitor the Contractor’s Work beyond the 30 Working Days. The Agency shall bill the Contractor for the additional inspection at the Agency’s established rates.

7. If the Contractor completes the Project or portions of the Project prior to NOC, the Contractor shall preserve equipment by developing and implementing a preventive maintenance program in compliance with manufacturer’s recommendations.

ADD 3- 13.3.2 Warranty Format Requirements.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 125 of 284 ends

1. Written warranties, except manufacturer’s standard printed warranties, shall be on the Contractor’s and Contractor’s agents’, material suppliers’, installers’, or manufacturers’ own letterhead, addressed to and for the Agency’s benefit. Submit warranties i n the format described in this section, modified as approved by Engineer to suit the conditions pertaining to the warranty.

2. The Contractor shall obtain warranties, executed in triplicate by responsible Subcontractors and Suppliers, within 10 Working Days after completion of the applicable item of Work.

Except for items put into use with the Engineer’s permission with date mutually agreed upon in writing, ensure that the beginning time of the warranty is the Project completion date.

3. The Contractor shall verify that the documents are in proper form, contain full information, and are notarized.

4. The Contractor shall verify that warranties are signed by both the Contractor and the appropriate party.

5. The Contractor shall provide warranties to the Engineer with a neatly typed table of contents, identifying each warranty with the number and title of the applicable specification section requiring the warranty and the name of the product or work item.

6. The Contractor shall separate each warranty with index tab sheets keyed to the table of contents listing. Provide complete information using separate typed sheets as necessary. The information shall include a list of Subcontractors and Suppliers with the name, address, and telephone number of the responsible principals.
3-13.3.3 Long-Term Warranty Contract (LTWC).

1. If specified in the Special Provisions and when a LTWC is included in the Contract Documents, the Contractor shall execute and submit the supplemental agreement for the extended Project warranty (the LTWC covering the workmanship and materials).

2. The first 3 years of warranty protection after installation shall be secured by the faithful performance and payment bonds in accordance with 1-7.2, “Contract Bonds.”

3. At the conclusion of the initial 3 -year bonded warranty period, an “n” -year subsequent manufacturer’s warranty for labor and materials shall commence and run concurrently with the LTWC, where “n” is the number of additional years beyond the initial 3 years as specified in the Special Provisions. Alternatively, and with respect to the 3 -year bonded warranty, the Contractor may submit a 2 -year bond followed by 1 -year bond. If the alternate option is selected, the 1-year bond shall be submitted to the Agency at least 90 Calendar Days before the expiration of the original 2 -year bond. Contractor shall clearly inform the Contract Specialist of the option selected. The protection provided shall not be for less than 3 + “n” years continuously.

4. The manufacturer’s warranty for parts and labor shall secure performance of the LTWC by the Contractor. Additional security in the form of bonds for both the LTWC and the manufacturer’s extended “n” -year warranty (in years 4 and on following Acceptance) for labor and materials may, but is not required to be, provided per the compensation provisions of the LTWC.

5. The manufacturer warranty shall extend to performance of the LTWC by the Contractor, including without limitation the performance of periodic inspections, preparation of periodic reports, and performance of repairs or replacements including parts and labor. If the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 126 of 284 ends

manufacturer warranty does not expressly extend to the LTWC or is qualified in any way to exclude warranty of the performance of the LTWC by the Contractor, the surety bond shall be provided for the LTWC in accordance with 1-7.2, “Contract Bonds.”

6. If the Contractor is unable to obtain a bond which extends the “n”-year term of the LTWC, to obtain a manufacturer warranty or both which clearly and unambiguously extends to secure performance of the LTWC by the Contractor for the “n” - year term, the Agency shall accept either form of security provided that at least 1 of these forms is provided before award.

7. Provision of the manufacturer’s warranty, bonds, or both as specified is a pre -condition to award of the Contract.

8. Refer to the LTWC for additional information. The provisions of 3 -3, “SUBCONTRACTORS” shall not apply to LTWC.

ADD 3- 14 PARTNERING

1. Contractor may request the formation of a formal partnering relationship (Partnering) by submitting a request in writing to the Engineer after approval of the Contract. If Contractor’s request for Partnering is approved by the Engineer, scheduling of a Partnering workshop, selecting the Partnering facilitator and workshop, selecting the Partnering facilitator and workshop site, and other administrative details shall be as agreed to by both Parties.

2. The establishment of a Partnering shall not change or modify the terms and conditions of the Contract and shall not relieve either party of the legal requirements of the Contract.

3. The goals of Partnering include the following:
a. The Engineer and Contractor’s representatives, including Contractor’s Subcontractors, actively working together as partners.
b. Avoidance of destructive confrontation and litigation among the parties. c. Mutual understanding on how the Work is to be conducted. d. Establishment of mutual key results to facilitate Project success. e. Establishment of an atmosphere of teamwork, trust, and open communication. 3-14.1 Payment.

1. The payment for providing a facilitator and a workshop site shall be borne equally by the Agency and Contractor. Contractor shall pay in advance all compensation for the costs of the facilitator and for the costs of obtaining the workshop site.

2. Unless a Bid item has been provided for “Partnering,” the Agency’s share of such costs shall be reimbursed to Contractor as Extra Work. Markups shall not be added. Other costs associated with the Partnering relationship shall be borne separately by the par ty incurring the costs.

ADD 3- 15 PUBLIC CONVENIENCE

1. The Contractor shall provide and maintain safe and adequate pedestrian and vehicular access to fire hydrants; hospitals; police and fire stations; commercial and industrial establishments including churches, schools and parking lots; service stations; public transportation; pedestrian crossing; motels and establishments of similar nature. Access shall be continuous and unobstructed unless otherwise approved by the Engineer.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 127 of 284 ends

2. The Contractor shall provide access for emergency vehicles and mail delivery and trash collection services. The trash hauling schedule can be obtained by contacting Republic Services at Customer Support | Republic Services.

3. During paving operations, the Contractor shall provide paved parking within 800 feet of the affected residences or businesses unless otherwise approved by the Engineer.

4. The Contractor shall provide notification 72 hours prior to the start of construction in the public right-of-way that affects vehicular traffic, parking, or pedestrian routes. For a full street closure, all residences and/or businesses on the affected street or alley shall be notified. For partial street closures or for curb, sidewalk or driveway repairs, the residences and/or businesses directly affected by the Work shall be notified. The notice shall:
a. Be written and hand delivered.
b. State the date and time the Work will begin and its anticipated duration. c. Provide a brief description of the Work and simple instructions to the home or business owner on actions to facilitate the construction. d. List 2 telephone numbers to obtain additional information. One number shall be the Contractor’s permanent office or field office and the other number shall be a 24-hour number answered by someone who is knowledgeable about the Project. An answering machine shall not be connected to either number. e. For residences, be prepared on 65 -lb. brightly colored card stock or equivalent durability with contrasting, 12 -point font or larger printing; pre -cut in a manner for hanging on a doorknob; and minimum size of 3 -1/2 inches wide by 8-1/2 inches long (refer to the appendices for an example).
f. Be approved by the Engineer prior to distribution.

5. The Contractor shall post “No Parking” signs 72 hours in advance of the Work. The signs shall state the date and time of parking restriction for a duration not to exceed the time necessary to complete the Work at that location. If the Work is delayed or rescheduled, the signs shall be removed and re-posted 72 hours in advance of the rescheduled Work.

6. Payment for public convenience shall be considered as included in the Contract Price for each item in the Bid and no additional payment will be made.

ADD 3- 16 SITE ACTIVITIES BY THE AGENCY OR SEPARATE CONTRACTORS 3-16.1 The Agency’s Right to Award Separate Contracts.

1. The Agency reserves the right to perform work or operations outside the Scope of Work of the Contract related to the Project with Agency Forces, Separate Contractors, or both. If work to be performed by another party was not noted in the Contract, the Agency shall give written notice to Contractor 10 Working Days prior to the start of any Work. If Contractor determines that the work being performed by the Agency or others may interfere with or cause damage to Work being performed by Contractor, notify the Engineer in writing within 3 Working Days of the Engineer’s notice.
3-16.2 Integration of the Work with Separate Contractors.

1. When specified in the Contract Documents, prepare a plan to integrate the work performed by Separate Contractors, Agency Forces, or both with the performance of the Work and submit the plan to the Engineer for approval. The plan shall be fair and reasonable for

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 128 of 284 ends

Contractor and the Separate Contractors. Work with Separate Contractors to reach an agreement for the prepared plan. Arrange the performance of the work so that the Work and the work of the Separate Contractors are, to the extent applicable, properly integ rated and jointed in a manner that avoids any damage to the Work or to the work of the Separate Contractors.
3-16.3 Coordination.

1. Coordinate Contractor’s activities and the Schedule with the activities and schedules of the Separate Contractors and make any revisions to the Schedule deemed necessary to avoid any disruption to the Work or to the work of the Separate Contractors.

2. NCTD requests that the contractor provide notice two (2) weeks prior to starting work so that they may send a supervisor to meet with the construction crew to determine if traffic control methods affect NCTD’s stops. Notice should be provided via e-mail to [email protected]. 3-16.4 Use of Site.

1. Provide the Agency and the Separate Contractors reasonable opportunities for the storage of materials and equipment and performance of their work. Connect and coordinate work and operations with the work and operations of the Agency and the Separate Contractors as required by the Contract Documents.

2. Coordinate traffic control with the Separate Contractors for other projects and minimize the impact to the community. Prior to the start of construction, submit Contractor’s plan for coordination.

3-16.5 Deficiency in Work of Separate Contractors.

1. If part of Contractor’s Work depends on proper execution or results upon construction or operations by the Agency or a Separate Contractor, prior to proceeding with that portion of the Work, promptly report to the Separate Contractor and the Engineer any a pparent discrepancies or defects in construction that would render it unsuitable for proper execution and results. Use good faith efforts to resolve any such discrepancies or defects or any related disagreements. Contractor’s failure to report constitutes Contractor’s acceptance of the Work of Separate Contractors as fit, proper, and coordinated with the Work. 3-16.6 Payment.

1. Payment for reporting deficiencies, coordinating, and resolving discrepancies shall be included in the Contract Price.

SECTION 4 – CONTROL OF MATERIALS
4-2 PROTECTION
ADD the following:

1. The Contractor shall repair or replace any equipment and materials in the event of vandalism, damage, or theft at no additional cost to the Agency.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 129 of 284 ends

2. The Contractor shall be responsible for the protection of public and private property adjacent to the Work and shall exercise due caution to avoid damage to such property.

3. All costs to the Contractor for protecting, removing, and restoring existing improvements shall be included in the Bid.

4. The Agency and affected utility companies have, by a search of known records, endeavored to locate and indicate on the Plans, all utilities which exist within the limits of the Work.

However, the accuracy and/or completeness of the nature, size and/or loc ation of utilities indicated on the Plans is not guaranteed.

5. The Contractor shall determine the location and depth of all utilities, including service connections, which have been marked by the respective owners and which may affect or be affected by its operations. If no pay item is provided in the Contract for thi s Work, full compensation for such Work shall be considered as included in the prices Bid for other items of Work.

6. The Contractor shall not interrupt the service function or disturb the support of any utility without authority from the owner or order from the Agency. All valves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff.

7. Where protection is required to ensure support of utilities located as shown on the Plans or in accordance with Section 402, the Contractor shall, unless otherwise provided, furnish, and place the necessary protection at its expense.

8. Upon learning of the existence and location of any utility omitted from or shown incorrectly on the Plans, the Contractor shall immediately notify the Engineer in writing. When authorized by the Engineer, support or protection of the utility will be paid for.

9. The Contractor shall immediately notify the Engineer and the utility owner if any utility is disturbed or damaged. The Contractor shall bear the costs of repair or replacement of any utility damaged if located.

10. When placing concrete around or contiguous to any non -metallic utility installation, the Contractor shall at its expense:
a. Furnish and install a 2 -inch cushion of expansion joint material or other similar resilient material; or
b. Provide a sleeve or other opening which will result in a 2-inch minimum-clear annular space between the concrete and the utility; or
c. Provide other acceptable means to prevent embedment in or bonding to the concrete.

11. Where concrete is used for backfill or for structures which would result in embedment, or partial embedment, of a metallic utility installation; or where the coating, bedding or other cathodic protection system is exposed or damaged by the Contractor’s ope rations, the Contractor shall notify the Engineer and arrange to secure the advice of the affected utility owner regarding the procedures required to maintain or restore the integrity of the system.

12. Unless otherwise specified, the Contractor shall remove all interfering portions of utilities shown on the Plans or indicated in the Bid documents as “abandoned” or “to be abandoned in place.” Before starting removal operations, the Contractor shall ascertain from the Agency whether the abandonment is co mplete, and the costs involved in the removal and disposal shall be included in the Bid for the items of Work necessitating such removals.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 130 of 284 ends

13. When feasible, the owner is responsible for utilities within the area affected by the Work will complete their necessary installations, relocations, repairs, or replacements before commencement of Work by the Contractor. When the Plans or Specifications indicate that a utility installation is to be relocated, altered, or constructed by others, the Agency will conduct all negotiations with the owners and work will be done at no cost to the Contractor, except for manhole frame and cover sets to be brought to grade as provided in the Contract Documents. Utilities which are relocated to avoid interference shall be protected in their position and the cost of such protection shall be included in the Bid for the items of Work necessitating such relocation.

14. After award of the Contract, portions of utilities which are found to interfere with the Work will be relocated, altered, or reconstructed by the owners, or the Engineer may order changes in the Work to avoid interference. Such changes will be paid.

15. When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such Work shall be included in the Bid for the items of Work necessitating such Work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience shall be its responsibility and it shall make all arrangements and bear all costs.

16. The utility owner will relocate service connections as necessary within the limits of the Work or within temporary construction or slope easements. When directed by the Engineer, the Contractor shall arrange for the relocation of service connections as nec essary between the meter and property line, or between a meter and the limits of temporary construction or slope easements. The relocation of such service connections will be paid and will include the restoration of all existing improvements which may be affected by the relocation . The Contractor may agree with the owner of any utility to disconnect and reconnect interfering service connections. The Agency will not be involved in any such agreement.

17. Contractor shall coordinate the Work with utility agencies and companies. Prior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contractor, the Contractor shall place all curb or curb and gutter that is a part of the Work and adjacent to the location where such utility structures are shown on the Plans and are noted as being located, relocated or are otherwise shown as installed by others. In order to minimize delays to the Contractor caused by the failure of other parties to relocate utilities that interfere with the construction, the Contractor, upon the Engineer’s approval, may be permitted to temporarily omit the portion of Work affected by the utility. If such temporary omission is approved by the Engineer, the Contractor shall place survey or other physical control markers sufficient to locate the curb or curb and gutter to the satisfaction of the utility agency or company. Such temporary omission shall be for the Contractor’s convenience and no additional compensation will be allowed therefore or for additional work, materials or delay associated with the temporary omission. The portion thus omitted shall be constructed by the Contractor immediately following the relocation of the utility involved unless otherwise directed by the Engineer.

18. The Contractor shall notify the Engineer of its Construction Schedule insofar as it affects the protection, removal, or relocation of utilities. The notification shall be included as a part of the Construction Schedule. The Contractor shall notify the Engineer in writing of any

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 131 of 284 ends

subsequent changes in the Construction Schedule which will affect the time available for protection, removal, or relocation of utilities.

19. The Contractor will not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, noted, and completed.

20. The Contractor may be given an extension of time for unforeseen delays attributable to unreasonably protracted interference by utilities in performing the Work correctly shown on the Plans.

21. The Agency will assume responsibility for the timely removal, relocation, or protection of existing main or trunkline utility facilities within the area affected by the Work if such utilities are not identified in the Contract Documents. The Contractor will not be assessed liquidated damages for any delay caused by failure of Agency to provide for the timely removal, relocation, or protection of such existing facilities.

22. The Contractor will be compensated for damages incurred due to delays for which the Agency is responsible or for delays attributable to interferences, relocations, or alterations not covered by the Contract Documents. These damages for delay will be determ ined by the Engineer. The Agency shall not be liable for damages which could have been avoided by the judicious handling of forces, equipment, or plant. These avoidable damages will be determined by the Engineer. The Engineer may grant Contractor an extens ion of time for damages due to delay.

23. When necessary, the Contractor shall so conduct its operations as to permit access to the Work Site and provide time for utility work to be accomplished during the progress of the Work.
4-3 INSPECTION
4-3.1 General
ADD the following:

1. All costs of inspection at the source, including salaries and mileage costs, shall be paid by the Contractor.

2. Materials typically accepted by Certificate of Compliance shall not require inspection at the source unless specified in the Contract Documents. For a list of these items or materials, Contractor may refer to the Summary of Work.

3. Location changes to the source of materials requiring inspection without the required 24 - hour notification may result in non -compliant material subject to rejection. Contractor shall be responsible for staff charges resulting from last minute changes or cancellations once staff has been deployed. The Engineer shall issue a deductive Field Order for a minimum of 2 hours of staff time to reimburse the Agency for misdirected staff charges. The Contractor shall be notified in writing of the additional staff charges incurred.

4. Steel pipe in sizes larger than 18 inches shall require inspection at the source of production.

5. Agency staff or a qualified inspection agency approved by the Engineer shall witness all welding, lining, coating, and testing. Contractor shall incur additional inspection costs outlined in 4-2.3, “Inspection of Items Not Locally Produced.”

6. All parts of production (including but not limited to product fabrication, welding, testing, lining, and coating of straight pieces and specials) shall be performed or produced in the United States.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 132 of 284 ends

7. Welding and all testing shall be performed by certified welders and testing staff with credentials traceable in the United States.

8. The Contractor shall provide the Engineer free and safe access to any and all parts of Work at any time. Such free and safe access shall include means of safe access and egress, ventilation, lighting, shoring, dewatering and all elements pertaining to the safety of persons as contained in the California Code of Regulations, Title 8, Industrial Relations, Chapter 4, Division of Industrial Safety, Subchapter 4, Construction Safety Orders and such other safety regulations as may apply. Contractor shall furnish Engineer with such information as may be necessary to keep the Engineer fully informed regarding progress and manner of work and character of materials. Inspection or testing of the whole or any portion of the Work or materials incorporated in the Work shall not relieve Contractor from any obligation to fulfill this Contract.
4-3.2 Inspection by the Agency.

DELETE this section in its entirety and replace with the following:

Inspection and testing laboratory services shall be proposed by the Contractor and subject to the approval of the engineer.

ADD 4-3 .4 Specialty Inspection Paid for by the Contractor

1. Contractor shall employ and pay for the services of a qualified inspection agency to perform specialty inspection services as required by the Contract Documents.

2. The payment for the specialty inspection service Work shall be included under the Bid item for “Specialty Inspection Paid For By the Contractor.”

3. When an Allowance Bid item for “Specialty Testing Under the Direction of the Engineer” is provided, Contractor shall employ and pay for the services of a qualified third party independent laboratory to perform the required testing. Contractor shall be reimbursed f or the cost of testing under this Bid item.

4. The cost for specialty inspections shall be included in the Contractor’s bid price for the item requiring the specialty inspection.
4-4 TESTING
ADD the following:

1. Except as specified in these Special Provisions, the Agency will bear the cost of testing of locally produced materials and/or on-site workmanship where the results of such tests meet or exceed the requirements indicated in the Standard Specifications, Technical Specification, and any Supplemental Provisions. The cost of all other tests shall be borne by the Contractor.

2. At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before the delivery is started. All materials proposed for use may be inspected or tested at any time during their preparation and use. If, after incorporating such materials into the Work, it is found that sources of supply that have been approved do not furnish a uniform product, or if the product from any source proves unacceptable at any time, the Contractor shall furnish approved material from other approved sources. If any product proves unacceptable after improper storage, handling or for any other reason it shall be

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 133 of 284 ends

rejected, not incorporated into the Work and shall be removed from the Project Site all at the Contractor’s expense.

3. Compaction tests may be made by the Engineer and all costs for tests that meet or exceed the requirements of the specifications shall be borne by the Agency. The tests may be made at any place along the Work as deemed necessary by the Engineer. The costs of any retests made necessary by noncompliance with the specifications shall be borne by the Contractor. 4-6 TRADE NAMES
ADD the following:

1. Whenever materials or equipment are indicated in the Contract Documents by using the name of a proprietary item or the name of a particular s upplier, the naming of the item is intended to establish the type, function, and quality required.

2. Unless stated otherwise, materials or equipment of other s uppliers may be accepted if sufficient information is submitted to the Engineer for review to determine whether the material or equipment proposed is equivalent or equal to that named.

3. For reviews prior to Bid:
a. The Engineer shall respond to Contractor’s substitution proposal by the last date for issuing an Addendum for the Contract. If the Engineer fails to respond to Contractor’s substitution proposal before the Bid due date, the substitution proposal shall be deemed denied.
b. Contractor may bring forward a substitution proposal after Award that was denied based on the Engineer’s failure to respond by submitting a Cost Reduction Proposal in accordance with 2-6.1, “Cost Reduction Proposal.”

4. For reviews prior to Bid:
a. The Engineer shall respond to Contractor’s substitution proposal by the last date for issuing an Addendum for the Contract. If the Engineer fails to respond to Contractor’s substitution proposal before the Bid due date, the substitution proposal shall be deemed denied.
b. Contractor may bring forward a substitution proposal after Award that was denied based on the Engineer’s failure to respond by submitting a Cost Reduction Proposal in accordance with 2-6.1, “Cost Reduction Proposal.”

5. Include the following information in the request for substitution:
a. Whether or not acceptance of the substitute for use in the Work shall require a change in any of the Contract Documents to adopt the design to the proposed substitute. b. Whether or not incorporation or use of the substitute in connection with the Work is subject to the payment of any license fee or royalty.
c. All variations of the proposed substitute from the items originally specified shall be identified.
d. Available maintenance, repair, and replacement service requirements. The manufacturer shall have a local service agency within 50 miles (80.5 km) of the S ite which maintains properly trained personnel and adequate spare parts and is able to respond and complete repairs within 24 hours.
e. Certifications from the manufacturer or service provider that the proposed substitute shall perform the intended function adequately under the expected service

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 134 of 284 ends

conditions, achieve the results called for by the general design, and be similar and of equal substance to that indicated.

6. There is no guaranteed time frame for the Engineer’s review of the substitution requests. Any lack of action on the Engineer’s side within Contractor’s requested time does not constitute acceptance of the substitution.

7. If, in the opinion of the Engineer, substitute items are determined to be unsatisfactory in performance, appearance, durability, compatibility with existing equipment or systems, availability of repair parts and suitability of application, the Contractor shall remove the substituted item and replace it with the originally specified item at no cost to the Agency.

8. The burden of proof as to the type, function, and quality of any such substitute product, material or equipment shall be upon Contractor. The Engineer may require at Contractor’s expense additional data about the proposed substitute.

9. Acceptance by the Engineer of a substitute item does not relieve Contractor of the responsibility for full compliance with the Contract Documents. If the Engineer takes no exceptions to the proposed substitution, it shall not relieve Contractor from Contractor’s responsibility to the efficiency, sufficiency, quality, and performance of the substitute material or equipment in the same manner and degree as the material and equipment specified by name.

10. The Bid submittal shall be based on the material and equipment specified by name in the Contract. If the proposal is rejected by the Engineer, Contractor shall not be entitled to either an extension in Contract Time, an increase in the Contract Price, or both.

11. As applicable, no Shop Drawing or Working Drawing submittals shall be made for a substitute item nor shall any substitute item be ordered, installed, or utilized without the Engineer’s prior written approval.

12. The Contractor is responsible for the satisfactory performance of substituted items. If, in the sole opinion of the Engineer, the substitution is determined to be unsatisfactory in performance, appearance, durability, compatibility with associated items, availability of repair parts and suitability of application the Contractor shall remove the substituted item and replace it with the originally specified item at no cost to the Agency. 4-7 WEIGHING AND METERING EQUIPMENT
REPLACE the first paragraph with the following:

All scales and metering equipment used for proportioning materials shall be inspected for accuracy and certified within the past 12 months by the State of California Bureau of Weights and Measures, by the County Director or Sealer of Weights and Measures, or by a scale mechanic registered with or licensed by the County.

SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES
5-1 LAWS AND REGULATIONS
ADD the following:

1. Each worker shall be paid subsistence and travel as required by the collective bargaining agreement on file with the State of California Department of Industrial Relations.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 135 of 284 ends

2. Municipal ordinances that affect this Work include Chapter 11.06. Excavation and Grading. If this notice specifies locations or possible materials, such as borrow pits or gravel beds, for use in the proposed construction Project which would be subject to Fish and Game Code Section 1601 or 1603, the conditions established in Fish and Game Code Section 1601 et seq. shall become conditions of the Contract.
5-3.3 Payroll Records.

ADD the following:

1. The Contractor and its Subcontractors shall maintain and furnish to the Agency, at a designated time, a certified copy of each weekly payroll reflecting the wages containing all of Contractor’s and Subcontractors’ employees engaged in the Work and a statement of compliance signed under penalty of perjury.
5-3.4 Hours of Labor
ADD the following:

1. Unless otherwise approved in writing by the Engineer, the hours of work shall be between the hours of 7:00 AM and 4:00 PM on Mondays through Fridays, excluding Agency holidays.

The Contractor shall obtain the written approval of the Engineer if the Contractor desires to work outside these hours or at any time during weekends and/or holidays. This written permission must be obtained at least 48 hours prior to such work. The Engineer may approve work outside the stated hours and/or days when, in his/her sole opinion, such work conducted by the Contractor is beneficial to the best interests of the Agency. The Contractor shall pay the inspection costs of such work.

5-4 INSURANCE
5-4.1 General.

ADD the following:

1. Contractor shall procure and maintain for the duration of the Contract insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the Work by the Contractor, his or her agents, representatives, employees or Subcontractors. The insurance shall meet the City’s policy for insurance as stated in City Council Policy No. 70.
a. Coverages and Limits: Contractor shall maintain the types of coverages and minimum limits specified in these Agency Supplemental General Provisions (00 73 00):
b. Additional Provisions: Contractor shall ensure that the policies of insurance required under this Contract with the exception of Workers’ Compensation and Business Automobile Liability Insurance contain, or are endorsed to contain, the following provisions.
i. The Agency, its officials, employees and volunteers must be covered as additional insured as respects: liability arising out of activities performed by or on behalf of the Contractor; products and completed operations of the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 136 of 284 ends

Contractor; premises owned, leased, hired or borrowed by the Contractor. The coverage shall contain no special limitations on the scope of protection afforded to the Agency, its officials, employees or volunteers. All additional insured endorsements must be evidenced using separate documents attached to the certificate of insurance; 1 for each company affording general liability, and employers’ liability coverage.
ii. The Contractor’s insurance coverage shall be primary insurance as respects the Agency, its officials, employees and volunteers. Any insurance or self - insurance maintained by the Agency, its officials, employees or volunteers shall be in excess of the Contr actor's insurance and shall not contribute with it.
iii. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the Agency, its officials, employees or volunteers. iv. Coverage shall state that the Contractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer’s liability.
c. Notice of Cancellation. Each insurance policy required by this Contract shall be endorsed to state that coverage shall not be nonrenewed, suspended, voided, canceled, or reduced in coverage or limits except after 10 Calendar Days’ prior written notice has been sent to the Agency by certified mail, return receipt requested. d. Deductibles and Self -Insured Retention (S.I.R.) Levels. Any deductibles or self - insured retention levels must be declared to and approved by the Agency. At the option of the Agency, either: the insurer shall reduce or eliminate such deductibles or self-insured retention levels as respects the Agency, its officials and employees; or the Contractor shall procure a bond guaranteeing payment of losses and related investigation, claim administration and defense expenses. e. Waiver of Subrogation. All policies of insurance required under this Contract shall contain a waiver of all rights of subrogation the insurer may have or may acquire against the Agency or any of its officials or employees. f. Subcontractors. Contractor shall include all Subcontractors as insured under its policies or shall furnish separate certificates and endorsements for each Subcontractor. Coverages for Subcontractors shall be subject to all of the requirements stated in these Agency Supplemental General Provisions (00 73 00). g. Acceptability of Insurers. Insurance must be placed with insurers that have a rating in Best’s Key Rating Guide of at least A -:VII. Insurers must also be authorized to transact the business of insurance by the State of California Insurance Commissioner as admitted carriers as evidenced by a listing in the official publication of the Department of Insurance of the State of California and/or under the standards specified by City Council Policy No. 70.
h. Verification of Coverage. Contractor shall furnish the Agency with certificates of insurance and original endorsements affecting coverage required by this clause. The certificates and endorsements for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificates and

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 137 of 284 ends

endorsements are to be in forms approved by the Agency and are to be received and approved by the Agency before the Contract is executed by the Agency. i. Coverage and Limits . Contractor will maintain the types of coverage and minimum limits indicated below unless the Risk Manager or City Manager or Executive Manager approves a lower amount. These minimum amounts of coverage will not constitute any limitations or cap on Contractor’s indemnification obligations under this Contract.

Agency, its officers, agents, and employees make no representation that the limits of the insurance specified to be carried by Contractor pursuant to this Contract are adequate to protect Contractor. If Contractor believes that any required insurance coverage is inadequate, Contractor will obtain such additional insurance coverage, as Contractor deems adequate, at Contractor’s sole expense. The full limits available to the named insured shall also be a vailable and applicable to the Agency as an additional insured.
j. Cost of Insurance. The Cost of all insurance required under this Contract shall be included in the Contractor’s Bid.
5-4.2 General Liability Insurance.

ADD the following:

Commercial General Liability (CGL) Insurance : Insurance written on an “occurrence” basis, including products-completed operations, personal & advertising injury, with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.
5-4.3 Worker’s Compensation Insurance.

ADD the following:

Workers’ Compensation and Employers’ Liability Insurance : Workers’ compensation limits as required by the Labor Code and Employers’ Liability limits of $1,000,000 per incident. Workers’ compensation offered by the State Compensation Insurance Fund is acceptable to the City. 5-4.4 Auto Liability Insurance.

ADD the following:

Business Automobile Liability Insurance : $2,000,000 combined single limit per accident for bodily injury and property damage. In addition, the auto policy must cover any vehicle used in the performance of the Contract, used onsite or offsite, whether owned, non- owned or hired, and whether scheduled or non-scheduled.

5-6 PATENTS FEES AND ROYALTIES.

DELETE in its entirety and SUBSTITUTE with the following:

1. Contractor shall pay, at no additional cost to the Agency, all applicable royalties and license fees arising from the Work. Contractor shall indemnify and defend all claims and lawsuits for

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 138 of 284 ends

infringement of patent, trademark, and copyright against the Agency and shall hold the Agency harmless from any loss.
5-7 SAFETY
5-7.1.1 General.

ADD the following:

1. When conducting grading or excavation, place Contractor’s name and emergency telephone number adjacent to the Work at intervals and locations approved by the Engineer. The method of posting shall be approved by the Engineer.

2. The Contractor shall respond and initiate corrective action in accordance with OSHA and within 24 hours of the notice of the nonconforming Work that poses an imminent threat to person or property.

3. The Contractor shall erect and properly maintain at all times, as required by the conditions and progress of the Work, all necessary safeguards for the protection of workers and public, and shall use danger signs warning against hazards created by such features of construction as protruding nails, hoists, well holes, and falling materials.

ADD: 5-7.1.3 Health and Safety Plan (HSP).

1. The Contractor is ultimately responsible for the health and safety of Contractor’s employees.

These specifications shall not be construed to limit Contractor’s liability nor to assume that the Agency, its employees, or designees shall assume any of Contractor’s liability associated with Site safety considerations.

2. Contractor shall have a HSP in effect at least 1 week prior to the commencement of the Work.

The HSP shall comply with all OSHA and other applicable requirements.

3. The HSP shall specifically address procedures and protocols that shall be followed to monitor for or respond to the presence of hazardous atmosphere, possibility for engulfment, gasses due to organic soils or proximity to landfills, exposure to hazardous products such as may be released when grinding, cutting, or torching galvanized or painted surfaces or asbestos containing materials, contaminated soil, and groundwater. Identify response actions that shall be taken when these conditions are encountered.

4. The Agency shall not assume any role in determining the adequacy of the HSP on Contractor’s behalf.
5-7.3 Use of Explosives.

ADD the following:

1. Explosives may be used only when authorized in writing by the Engineer. The Contractor shall prepare and submit an application for blasting permit to the City of Carlsbad Engineering Department and comply with the City’s blasting policy.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 139 of 284 ends

5-7.7 Security and Protective Devices.
5-7.7.1 General.

DELETE in its entirety and SUBSTITUTE with the following:

1. Security and protective devices shall consist of fencing, railing, steel plates, or other devices for the protection of workers or the public from hazards posed by open excavations or any work in progress. Security and protective devices shall remain in place until the Work is accepted.

2. Unless otherwise specified, no separate or additional payment will be made for security and protective devices. Payment shall be included in the Contract price for the various Bid items requiring such devices.

ADD: 5-7.7.3 Playground Safety.

1. Provide a secured fence around the playground to prevent use or access. Do not remove the fence until the independent Playground Safety Audit has been done by the Contractor and the Engineer, the Engineer has accepted the playground design and installation, and the Punchlist items have been completed.

2. Provide certification by a NPSI certified playground inspector that confirms that the installed equipment is compliant with all applicable codes.

3. The payment for the fencing around the playground and the playground safety audit is included in the Contract Price.
5-7.7.2 Security Fencing

1. The payment for security fencing Work for open excavations shall be included in the Contract Price.
5-7.8 Steel Plate Covers
5-7.8.1 General.

ADD the following:

1. The Contractor shall protect transverse or longitudinal cuts, voids, trenches, holes, and excavations in the right-of-way that cannot be properly completed within 1 Working Day by adequately designed barricades and structural steel plates (plates) that shall support legal vehicle loads in such a way as to preserve unobstructed traffic flow.

2. For trench widths exceeding those in Table 5-7.8.2, a structural design shall be prepared by a California registered civil or structural engineer regularly engaged in the design of shoring systems.

3. The Contractor shall secure approval in advance from authorities concerning the use of any bridging proposed on the Work.

4. The Contractor shall shore the trench adequately to support the bridging and traffic loads.

5. The Contractor shall design plates for HS 20 -44 truck loading in accordance with Caltrans Bridge Design Specifications Manual and evaluate soil conditions and ensure that the plate extends enough beyond the trench walls to support traffic loads.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 140 of 284 ends

6. The Contractor shall use the plates skid -resistant with a nominal COF of 0.35 as determined by California Test Method 342. If a different test method is used, the Contractor may utilize standard test plates with known coefficients of friction available fro m each Caltrans District Materials Engineer to correlate skid resistance results to California Test Method 342.

7. Plates shall provide complete coverage to prevent any person, bicycle, motorcycle, or motor vehicle from being endangered due to plate movement causing separations or gaps.

8. Alternative installation methods may be submitted in accordance with 3 -8, “SUBMITTALS” for the Engineer’s approval.

9. Contractor shall install signage and postings with a 2 inch (50.8 mm) minimum letter height indicating the steel plate cover load limit, the Company’s name, and a 24 -hour emergency contact phone number. See 601-1, “GENERAL.”

10. Contractor is responsible for the maintenance of the plates, shoring, and asphalt concrete ramps or any other approved device used to secure the plates. Contractor shall immediately mobilize necessary personnel and equipment after being notified by the Eng ineer, the Agency, or a member of the public of a repair needed for such items as plate movements, noise, anchors, and asphalt ramps. Failure to respond to the emergency request within 2 hours shall be grounds for the Agency to perform necessary repairs that shall be invoiced at the actual cost including overhead or $500 per incident, whichever is greater. Failure may also result in a “Stop Work” notice.

11. When plates are removed, Contractor shall repair any damage to the pavement with fine graded asphalt concrete mix or slurry seal satisfactory to the Engineer. 5-7.8.3 Installation.

ADD the following:

The pavement shall be cold planed to a depth equal to the thickness of the plate and to a width and length equal to the dimensions of the plate. The cold milling shall produce a flat surface that the plate shall rest on with no horizontal or vertical movement. Horizontal gaps between the unmilled pavement and the plate shall not exceed 25 mm (1 ") and shall be filled with elastomeric sealant material which may, at the contractor's option, be mixed with no more that 50%, by volume, of Type I aggregate conforming to the requirements of tables 203-5.2 and 203-5.3 DELETE method 2 in its entirety. Only method 1 is acceptable within city streets.

ADD 5- 8 INDEMNIFICATION AND HOLD HARMLESS AGREEMENT

1. Contractor agrees to defend, indemnify, and hold harmless Agency, its affiliated and subsidiary entities, and its elected and appointed officials, officers, directors, managers, employees and agents (“Indemnified Parties”) from and against all claims asserted, liability established, or judgments for damages or injuries to any person or property, including to Contractor’s officers, employees, agents, or subcontractors, arising directly or indirectly out of the Work, which arise from, are connected with, or are caused or claimed to be caused by the acts or omissions of Contractor, its officers, employees, agents or subcontractors.

Contractor’s duty to defend, indemnify, and hold harmless shall not include any claims or liabilities arising from the sole negligence or sole willful misconduct of the Indemnified Parties.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 141 of 284 ends

Contractor further agrees that its duty to defend includes all attorney fees and costs associated with enforcement of this indemnification provision, defense of any claims arising from this Contract, and, where a conflict of interest exists or may exist between Contractor and Agency, the reasonable value of attorney fees and costs if Agency chooses, at its own election, to conduct its own defense or participate in its own defense of any claim related to this Contract.

2. Contractor shall also defend and indemnify the Indemnified Parties against any challenges to the Award of the Contract to Contractor, and Contractor will pay all costs, including defense costs for the Agency. Defense costs include the cost of separate counsel for the Indemnified Parties, if the Indemnified Parties request separate counsel.

3. Contractor shall also defend and indemnify the Indemnified Parties against any challenges to the Award of the Contract to Contractor, arising in whole or in part from alleged inaccuracies or misrepresentation by the Contractor, whether intentional or otherwise, and Contractor will pay all costs, including defense costs for the Agency. Defense costs include the cost of separate counsel for the Indemnified Parties , if the Indemnified Parties request separate counsel.

4. Contractor shall defend, indemnify, protect and hold the Indemnified Parties harmless from and against any dispute between Contractor and Contractor’s Subcontractors if the Indemnified Parties are made a party to any judicial or administrative proceeding.

ADD 5- 9 CONFLICT OF INTEREST

1. Establish and make known to Contractor’s employees appropriate safeguards to prohibit employees from using their positions for a purpose that is or gives the appearance of being motivated by desire for private gain for themselves or others and particularly those with whom they have family, business, or other relationships. Project personnel shall not accept gratuities or any other favors from Subcontractors or potential Subcontractors.

2. Contractor is subject to all federal, state, and local conflict of interest laws, regulations, and policies applicable to public contracts and procurement practices (Government Code Sections 1090 et. seq. and 81000 et. seq., the Agency’s Ordinances, and the City of Carlsbad Municipal Code). If, in performing the Work, Contractor make s or participate s in a “governmental decision” in accordance with T itle 2, Section 18701, subdivision (a)(2) of the California Code of Regulations, or performs the same or substantially all the same duties for Agency that would otherwise be performed by an Agency employee holding a position specified in the Agency’s conflict of interest code, Contractor shall be subject to a conflict of interest code requiring the completion of 1 or more statements of economic interests disclosing Contractor’s relevant financial interests.

3. Statements of economic interests shall be made on Fair Political Practices Commission Form 700 and filed with the City of Carlsbad’s City Clerk. Contractor shall file a Form 700 (Assuming Office Statement) within 30 Calendar Days of the Agency’s written determination that Contractor shall be subject to a conflict of interest code and f ile a Form 700 (Annual Statement) on or before April 1st disclosing any financial interests held during the previous calendar year for which Contractor was subject to a conflict of interest code.

4. If the Agency requires Contractor to file a statement of economic interests as a result of the Work performed, Contractor shall be considered a n “Agency Official” for conflict of interest

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 142 of 284 ends

purposes, including the prohibition against lobbying the Agency for 1 year following the expiration or termination of the Contract.

5. Contractor’s personnel employed on the Project shall not accept gratuities or any other favors from any Subcontractors or potential Subcontractors. Contractor shall not recommend or specify any product, supplier, or other Contractor with whom Contractor ha s a direct or indirect financial or organizational interest or relationship that would violate conflict of interest laws, regulations, or policies.

6. If Contractor violates any conflict of interest laws or any of these conflict of interest provisions, the violation shall be grounds for immediate termination of this Contract. Further, the violation subjects Contractor to liability to the Agency for all damages sustained as a result of the violation.

ADD the following: 5- 10 STATUTORY REFERENCES

1. All references in these Agency Supplemental General Provisions (00 73 00) to any statute, rule or regulation are to the statute, rule or regulation as amended, modified, supplemented, or replaced from time to time by the corresponding legislative or regulatory body.

ADD the following: 5-11 RIGHT TO AUDIT
5-11.1 General.

1. The Agency retains the right to review, audit, reasonably access Contractor’s and all Contractor’s Subcontractor’s premises to review and audit Contractor’s compliance with the provisions of the Contract. This includes the right to inspect, photocopy, and retain copies, outside of Contractor’s premises, of all records with appropriate safeguards if such retention is deemed necessary by the Agency in its sole discretion. The Agency will keep this information in strictest confidence.

2. Contractor shall include the Agency’s right to audit in its subcontracts and ensure that these specifications are binding upon all Subcontractors.
5-11.2 Audit.

1. The right to audit includes the right to examine any and all books, records, documents, and any other evidence of procedures and practices that the Agency determines is necessary to discover and verify that Contractor are in compliance with all requirement s under the Contract.

2. If there is a claim for additional compensation or for changes in Work, the right to audit also includes the right to verify all direct and indirect costs which are claimed to have been incurred, anticipated to be incurred, or for which a claim for additio nal compensation or for changes in the Work have been submitted.

3. Contractor shall maintain complete and accurate records in accordance with generally accepted accounting practices in the construction industry. Contractor shall also make available to the Engineer for review and audit all Project -related accounting record s and documents and any other financial data. Upon the Engineer’s request, Contractor shall submit exact duplicates of originals of all requested records to the Engineer.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 143 of 284 ends

5-11.3 Compliance Required Before Mediation and Litigation.

1. As a condition precedent to proceeding with mandatory mediation and further litigation under 2 -10.2, “Dispute Resolution Process” Contractor shall comply with the audit specifications within 60 Calendar Days of the Engineer’s notice to review and audit compliance. See 5-2, “SPECIAL NOTICES.”
5-11.4 Access to Records on Federally Funded Projects.

1. Contractor shall retain all records, books, papers, and documents directly pertinent to the Contract for a minimum of 5 years after the Agency makes final payments and all other pending matters are closed and shall allow access to those records to the Agency, the Federal grantor agency, the Comptroller General of the United States, or any duly authorized representatives.

SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK ADD the following:

1. A Payment for the Construction Schedule shall be included in the Contract Price and no separate payment will be made, therefore.

2. The Contractor shall incorporate the dates, areas and types of work prohibited in this section in the Construction Schedule. No additional payment, adjustment of bid prices or adjustment of contract time of completion will be allowed as a consequence of th e prohibition of work being performed within the dates, areas and/or types of work prohibited in this section.

ADD the following subsection: 6- 1.3 Pre-Construction Meeting After, or upon, notification of Contract award, the Engineer will set the time and location for the Preconstruction Meeting. Attendance of the Contractor’s management personnel responsible for the management, administration, and execution of the Project is mandatory for the meeting to be convened. Failure of the Contractor to have the Contractor’s responsible Project personnel attend the Preconstruction Meeting will be grounds for default by Contractor per Supplemental General Provisions Section 6 -7. No sep arate payment will be made for the Contractor’s attendance at the meeting. The Notice to Proceed will only be issued on or after the completion of the Preconstruction Meeting.

ADD the following subsection: 6- 1.3.1 Baseline Construction Schedule.

Prior to the start of any work, the Contractor shall submit its Baseline Construction Schedule to the Engineer for approval and shall present the schedule at the Preconstruction Meeting . The Contractor shall prepare the s chedule as a Critical Path Method (CPM) s chedule in the precedence diagram method (activity -on-node) format and submit the schedule in accordance with 3-8. The schedule shall:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 144 of 284 ends

1. Be prepared using commercially available, Windows compatible scheduling software program such as, Primavera, Microsoft Project, or approved equal.

2. Be prepared in hard copy (paper) and electronic (Adobe PDF) format and free of file locking, encryption or any other protocol that would impede full access to the data.

Identify the project name and number, the Contractor’s name and the date of preparation or revision.

3. Begin with the date of the Notice to Proceed and conclude with the date of final completion conforming with the Contract time.

4. Depict a time -scaled network diagram of all activities, logic relationships of interdependent activities, and milestones comprising the complete period of Work with tasks on the vertical axis and their durations on the horizontal axis. Use distinctive texture patterns or line types to show the critical path within the Contract time. Include a tabular listing of each activity and its identification number, description, duration, early start, early finish, late start, late finish, total float, and all predecessor and successor activities.

The number of activities will communicate the Contractor’s plan for project execution, accurately describe the project work and allow monitoring and evaluation of progress and time impacts. Activity descriptions shall accurately define the work planned for the activity. Activity durations shall not be shorter than 1 working day or longer than 15 working days unless approved by the Engineer.

5. Include detail of all project phasing including all milestones necessary to define the beginning and end of each phase and constraints which may impact any activity. Include time allowances for coordination with utility companies and other agencies, pre - construction surveys and investigations, equipment and material deliveries, submittal reviews and approvals, traffic control setup and phasing, Work performed by others, inspections, testing and commissioning, corrective work, and any non-work periods.

Float or slack time within the schedule is available without charge or compensation to the party or contingency that first exhausts it. A schedule which shows a project duration longer than the Contract time will not be accepted by the Engineer.

If the Baseline Construction Schedule does not meet the requirements of these specifications, the Contractor shall revise the schedule and resubmit it to the Engineer. Failure to obtain the Engineer’s approval of the schedule within twenty five (25) Working Days after the date of the Preconstruction Meeting shall be grounds to consider the Contractor in default of the Contract per 6-7. The time required by the Engineer to review the initial Baseline Construction Schedule submittal will not be included in the 25 Working Days. The Engineer shall complete subsequent reviews of the revised schedule and progress updates within 5 working days of receipt.

The Contractor shall not be permitted to commence any excavation or demolition activities until the Engineer accepts the Baseline Construction Schedule. For each day of delay beyond the 25 Working Days after the Preconstruction Meeting that the Baseline Construction Schedule is not

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 145 of 284 ends

accepted by the Engineer, the Contractor shall be charged $100 through a deductive Change Order.

The Engineer’s response to each review will consist of one of the following:
“Accepted.” The Contractor may proceed with the Work.
“Accepted with Comments.” The Contractor may proceed with the Work, but must revise and resubmit the schedule prior to submittal of the first progress payment application. The Engineer’s acceptance of the schedule is a condition precedent to payment of any progress payment.
“Not Accepted.” The Contractor may not proceed with the Work and must revise and resubmit the schedule.

ADD the following subsection: 6- 1.3.2 Schedule Updates and Revisions.

The Contractor shall meet with the Agency’s Construction Manager during the last week of each month to agree upon the completion level of each activity as a basis for progress payments.

Schedule updates shall conform with the requirements for the initial submittal in 6 -1.1.1 and shall:

1. Show the actual dates of each activity start and/or finish during the month. The schedule update shall include specific notation for any changes in a ctual dates after they are first reported.

2. Report the percent complete for each activity in progress at the end of the month as determined by the Engineer.

3. Include a list and explanation of all changes made to the activities, dates or interconnecting logic.

4. Include activity and network revisions reflecting the Change Orders approved in the previous month.

The Engineer’s responses to the construction schedule updates shall be as described in 6-1.1.1.

If the Contractor fails to submit schedule updates as required herein, the Contractor may elect to proceed with the Work at its own risk and shall forfeit the progress payment for Work completed until compliance is met. If the Contractor elects to delay or cease Work after failure to submit the schedule updates, any resulting delay, impact, or disruption to the Work will be the Contractor’s responsibility.

Should the actual or projected progress of the W ork exceed 5 percent of the Contract time, the Contractor shall prepare and submit a revised Baseline Construction Schedule independently of and prior to the next progress schedule update. The Contractor shall provide an explanation for each change made to the schedule.

If the Contractor desires to make a major change in the method of operations after commencing construction, the Contractor shall submit to the Engineer a revised Baseline Construction Schedule in advance of beginning revised operations.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 146 of 284 ends

ADD the following subsection: 6- 1.3.3 Late Completion or Milestone Dates.

If a s chedule update indicates a completion date later than the C ontract time or contractually required milestone completion date , the Agency may withhold Liquidated Damages for the number of days late. Should a subsequent schedule update which removes all or a portion of the delay be “Accepted” by the Engineer, all or the allocated portion of the previously held Liquidated Damages shall be released in the monthly progress payment to the Contractor immediately following such acceptance.

ADD the following subsection: 6- 1.3.4 Final Schedule Update.

The Contractor shall prepare and submit a final schedule update when one hundred percent of the Work is completed. The update must accurately represent the actual dates for all activities.

The final schedule update shall be prepared and reviewed in accordance with 6-1.1.2. Acceptance of the final schedule update is required for release of funds retained per 9-3.2.

ADD the following subsection: 6- 1.3.5 Measurement and Payment.

If a Bid item for Construction Schedule is not listed in the Bid Schedule, payment shall be considered included in the various Bid items and no separate payment will be made.

6-2 PROSECUTION OF WORK
ADD the following:

1. When a Subcontractor fails to prosecute a portion of the Work in a manner satisfactory to the Agency, Contractor shall remove such Subcontractor immediately upon written request of the Agency, and shall request approval of a replacement Subcontractor to perform the Work in accordance with the Subletting and Subcontracting Fair Practices Act (Pub. Contract Code, § 4100 et seq.) at no added cost to the Agency.

ADD the following: 6- 2.1 Order of Work.

1. The Contractor shall incorporate the requirements of the c ity, utility companies or agencies having jurisdiction over the Work in accordance with 2-4 Cooperation and Collateral Work.The work to be done shall consist of furnishing, all labor, equipment, and materials, and performing all operations necessary to complete the Project Work as shown on the Plans or Special Provisions.

2. Specific sequencing constraints include, but are not limited to, the following phases unless otherwise authorized by the agency.

ADD the following: 6- 2.2 Moratoriums.

1. When moratorium periods are specified in the Special Provisions, Contractor shall stop Work and completely demobilize all construction related activity, equipment, and materials within the stated limits prior to the beginning of the moratorium periods at no additional cost to the Agency. The Contractor shall complete any Work that has been started prior to the start of the moratorium.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 147 of 284 ends

2. Contractor shall restore and clean the Site prior to each moratorium. The Contractor shall not leave equipment, materials, or traffic control on the Site during the moratorium periods.

Trenches shall be backfilled during moratorium periods. Temporary resurfacing or steel plate covers over trenches shall not be used.

3. The payment for complying with moratorium requirements shall be included in the Contract Bid. Contractor shall not be entitled to any additional costs for repeated mobilization and demobilization to continue the Work after the moratorium periods. 6-3 TIME OF COMPLETION
6-3.1 General.

ADD the following:

1. Unless otherwise specified in the Contract, the time of completion of the Contract shall be expressed in Working Days.

2. The number of Working Days specified for the walk-through, preparation, and the completion of Punchlist items until acceptance shall be included in the stipulated Contract Time.

3. For pipeline Projects, the following shall be included in the stipulated Contract Time:
a. Complete each street segment within 15 Working Days from the day the final road surfacing is placed. Each completed segment shall include other incidental Work items (weed abatement, damaged asphalt pavement replacement, asphalt patching, resurfacing, striping, markings, raised pavement markers, and inlet markers). b. Where shutdowns of 16 -inch and larger pipes are required, there is a shutdown moratorium from May until October. The Contractor shall plan and schedule Work accordingly. No additional payment or Working Days will be granted for delays due to the moratorium.

4. When specified in the Contract Documents, the Plant Establishment Period (PEP) is included in the stipulated Contract Time and shall begin with the acceptance of the installation of the vegetation plan in accordance with Part 8 – LANDSCAPING AND IRRIGATION.

5. The Contractor shall obtain the written approval of the Engineer to perform any Work outside of normal Work hours. This approval must be obtained at least 48 hours prior to commencement of such Work. The Contractor shall pay any additional costs for inspection or testing of such Work.

6. Work that is required by the Engineer to occur outside of normal Work hours will be identified in the Special Provisions.

7. The Contractor shall not perform Work during moratoriums per 6 -2.2 or during any periods of restriction identified in agency permits or Project environmental documents and shall include all such schedule constraints in the Construction Schedule.

8. No additional payment or adjustment of Bid item prices or adjustment of Contract Time will be made for the Contractor’s inability to work outside of normal Work hours if Contractor’s request is denied by the Engineer or during prohibited periods.

9. Contractor’s schedule shall plan for a minimum of 2 weeks after final walk-through to receive a final punch list from the Agency.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 148 of 284 ends

6-4 DELAYS AND EXTENSIONS OF TIME
6-4.1 General.

ADD the following:

1. The Agency shall only grant an extension of time if the Extra Work or unforeseen condition impacts the Project’s critical path. All requests for an extension in Contract Time for any Extra Work or unforeseen event shall be demonstrated by using the CPM. No other scheduling method shall be used to calculate the Project’s schedule. 6-4.2 Extensions of Time.

DELETE in its entirety and SUBSTITUTE with the following:

1. The Contract Time shall be modified only by Change Order.

2. Contractor shall immediately submit to the Agency a written request for a Change Order to modify the Contract Time, but in no event later than 1 Working Day after the occurrence and discovery of the events giving rise to the request. Contractor shall include in Contractor’s request a general description of the basis for and the estimated length of any extension and submit supporting data, including a time impact analysis setting forth the claimed Critical Path impacts to the Construction Schedule consistent with Section 1.14 (Change Orders, Delays, and Extensions of Time).

3. The Engineer shall not grant an extension of Contract Time unless Contractor demonstrates, through an analysis of the critical path, the following:
a. The event causing the delay impacted the activities along the Project’s critical path. b. The increases in the time to perform all or part of the Project beyond the Contract Time arose from unforeseeable causes beyond Contractor’s control and without Contractor’s fault or negligence.
c. All Project float has been used.

4. The Engineer shall issue a weekly document that stipulates the Contract Time. If Contractor does not agree with this document, Contractor shall submit to the Engineer for review a written protest supporting Contractor’s objections to the document within 15 Working Days after receipt of the weekly document. Contractor’s failure to file a timely protest shall constitute Contractor’s acceptance of the Engineer’s weekly document. a. Contractor’s protest will be considered a claim for time extension and shall be subject to 2-10.1, “Claims.”
6-4.4 Written Notice and Report.

DELETE in its entirety and SUBSTITUTE with the following:

1. Contractor’s failure to file with the Engineer a written request and report of cause within 24 hours will be considered grounds for refusal by the Agency to consider such request.

2. The Contractor shall provide written notice to the Engineer within 2 hours after the beginning of the delay, or when the Contractor has placed any workers or equipment on standby for any reason that the Contractor has determined to be caused by the Agency or by any organization that the Agency may otherwise be obligated by. The Contractor shall provide continuing daily

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 149 of 284 ends

written notice to the Engineer, each Working Day, throughout the duration of such period of delay. The initial and continuing written notices shall include the classification of each worker and supervisor and the make and model of all equipment placed on standby, the cumulative duration of the standby, the Contractor’s opinion of the cause of the delay and a cogent explanation of why the Contractor could not avoid the delay by reasonable means. Should the Contractor fail to provide the notice(s) required by this section the Contractor agrees that no delay has occurred and that it will not submit any claim(s) therefore.

3. The request for payment or extension must be made at least 15 Calendar Days prior to the specified completion date . Failure by the Contractor to provide notices and reports as specified in the Contract will be considered grounds for refusal by the Agency to consider such request.
6-6 SUSPENSION OF THE WORK
6-6.1 General.

ADD the following:

1. The Agency reserves the right to issue a stop work notice for any trenching operation if Contractor is not proceeding within a reasonable period of time to restore the pavement and Site cleanup. A reasonable period of time is considered to be 5 to 10 Working Days after backfilling any 1 block, approximately 600 feet, of pipeline. The Engineer shall determine the period of time allowed which shall not be subject to dispute.

2. During periods when the Work is suspended, Contractor shall be prepared for any emergency Work that shall be supervised by Contractor’s representative.

3. Trenching operations are subject to suspension if the Contractor does not comply with the requirements for the maximum length of open trench specified in 306-3.5. 6-7 TERMINATION OF THE CONTRACT FOR DEFAULT
6-7.1 General.

Add the following:

Contractor fails to notify the Engineer upon discovery of items of Native American, Archaeological, or Paleontological interests.
6-8 TERMINATION OF THE CONTRACT FOR CONVENIENCE.

DELETE in its entirety and SUBSTITUTE with the following:

1. At any time, the Agency may at its sole discretion terminate this Contract in whole or in part.

If the Agency decides to terminate this Contract for convenience, the Agency shall issue a written notice of termination for convenience in accordance with 5 -2, “SPECIAL NOTICES.” Upon receipt of this notice, Contractor shall immediately proceed as follows:
a. Stop Work immediately or in accordance with the Notice of Termination. b. Notify Subcontractors and Suppliers to immediately cease their Work and place no further subcontracts for materials, services, or facilities except as necessary to complete any authorized continued portion of the Contract. c. Terminate all subcontracts to the extent that they relate to the Work terminated.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 150 of 284 ends

d. With approval by the Engineer, settle all outstanding obligations arising from the termination of subcontracts. This approval shall be final for the purposes of this section.
e. As directed by the Engineer, transfer and deliver completed or partially completed drawings, plans, calculations, specifications, and any other documents and records that, if the Contract had been completed, would be required to be furnished to the Agency.
f. Complete the performance of the Work not terminated. g. Take all necessary steps and actions to minimize all costs to the Agency as a result of the termination.
h. Take any action that may be necessary or that the Engineer may direct for the protection and preservation of the property related to the Contract that is in Contractor’s possession and in which the Agency has or may acquire an interest. 6-8.1 Termination Cost.

1. The Agency shall determine and pay Contractor the fair and reasonable amounts for Contractor’s termination cost as follows:
a. The Contract Price for completed services accepted by the Engineer not previously paid or adjusted for any saving of freight and other charges. b. The fair and reasonable cost of settling and paying termination settlements for terminated subcontracts that are chargeable to the terminated portion of the Contract.
c. The Agency shall pay Contractor a prorated amount of profit for Work that Contractor performed. The Agency shall not pay for lost profit on Work that was not performed by Contractor.
6-8.2 Termination Settlement.

1. After termination, Contractor shall submit a final termination settlement proposal to the Engineer no later than 3 months from the effective date of termination, unless extended in writing by the Engineer.

2. If Contractor fails to submit the proposal within the time allowed, the Agency may determine and pay the fair and reasonable amount that may be due Contractor as a result of the termination. If Contractor does not agree that the amount determined by the Engineer is fair and reasonable, Contractor must notify the Engineer within 30 Calendar Days of receipt of payment.
6-8.3 Determination of Amount Due the Contractor.

1. In determining the amount due Contractor, the Agency shall deduct the following:
a. The fair value of property destroyed, lost, stolen, or damaged that has become undeliverable to the Agency.
b. Any claim which the Agency has against Contractor under the Contract. 6-8.4 Records and Documents Relating to Termination.

1. The Engineer will file an Agreement of Mutual Rescission of Contract with the Board. Once the Agreement is executed and a Notice of Completion is recorded, retention can be released.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 151 of 284 ends

2. Unless otherwise specified or required by statute, Contractor shall maintain all records and documents relating to the terminated portion of the Contract for 3 years after final settlement. This includes all books and other evidence bearing on Contractor’s costs, expenses, and settlement under the Contract. Contractor shall make these records and documents available to the Agency, at Contractor’s office, at all reasonable times, without any direct charge. If approved by the Engineer, Contractor may maintain photographs, microphotographs, and other authentic reproductions instead of original records and documents.
6-8.5 The Agency’s Right to Terminate or Suspend for Loss of Project Funds.

1. The Agency may terminate or suspend the Contract at its sole discretion if the State of California or its agents render the funds being used to fund this Project unavailable. If the Agency chooses to suspend the Contract, that suspension shall last until funds are identified and approved by the Board, whichever is appropriate, to be used to complete this Project. If the Agency elects under this provision to terminate the Contract, neither Party is entitled to compensation from the other Party for any costs arising from such termination. The Agency may also elect to terminate after invoking a suspension under this provision. 6-9 LIQUIDATED DAMAGES
DELETE in its entirety and SUBSTITUTE with the following:

1. Contractor’s failure to complete the Work within the time allowed shall result in damages being sustained by the Agency. Such damages are, and shall continue to be, impracticable and extremely difficult to determine. For each consecutive Working Day in excess of the time specified for the completion of the Work, as adjusted in accordance with 6 -4, “DELAYS AND EXTENSIONS OF TIME,” Contractor shall pay to the Agency, or have withheld from monies due it, the sum described in the table below, along with any other damages that may be sustained by the Agency during the Project , unless otherwise specified in the Special Provisions.

2. The execution of the Contract shall constitute agreement between Contractor and the Agency that the liquidated damage amount described in the table below is the value of the damage caused by Contractor’s failure to complete the Work within the allotted time. Such sum shall not be construed as a penalty and may be deducted from Contractor’s payments if such delay occurs.

Contract Value Liquidated Damage Daily Amount
Less than $100,000 $1,000
$100,000 and more $2,500

3. Any progress payments made to Contractor after the specified completion date shall not constitute a waiver of payment for damages sustained by the Agency under this section.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 152 of 284 ends

ADD 6-10 ELECTRONIC COMMUNICATION

1. When specified in the Contract Documents, Contractor shall post all communications addressed to the Engineer concerning construction including RFIs, submittals, daily logs, and transmittals to the Project management website established for the Project. The Contractor shall maintain a list of scheduled activities including planned and actual execution dates for all major construction activities and milestones defined in the approved Schedule. The Contractor shall review and act on all communications addressed to the Contractor in the Project management website. A user’s guide to the Project management system may be available on the City’s website and shall be provided to Contractor at the Pre -construction Meeting.

2. The payment for electronic communications shall be included in the Contract Price.

ADD the following:
6-11 PROCORE PROJECT MANAGEMENT AND COLLABORATION SYSTEM a. This project will utilize the Owner’s Procore (www.procore.com) online project management and document control platform. The intent of utilizing Procore is to reduce cost and schedule risk, improve quality and safety, and maintain a healthy team dynamic by improving information flow, reducing non- productive activities, reducing rework and decreasing turnaround times. The Contractor is required to create a free web -based Procore user account(s) and utilize web-based training / tutorials (as needed) to become familiar with the system. Unless the Engineer approves otherwise, the Contractor shall process all project documents through Procore because this platform will be used to submit, track, distribute and collaborate on project. If unfamiliar or not otherwise trained with Procore, Contractor and applicable team members shall complete a free training certification course located at http://learn.procore.com/procore-certification-subcontractor. The Contractor is responsible for attaining their own Procore support, as needed, either through the online training or reaching out to the Procore support team. It will be the responsibility of the Contractor to regularly check Procore and review update d documents as they are added. There will be no cost to the Contractor for use of Procore.

b. It is recommended that the Contractor provide mobile access for Windows, iOS located at https://apps.apple.com/us/app/procore-construction-management/id374930542 or Android devices located at
https://play.google.com/store/apps/details?id=com.procore.activities with the Procore App installed to at least one on -site individual to provide real -time access to current posted drawings, specifications, RFIs, submittals, schedules, change orders, project documents, as well as any deficient observations or punch list it ems. Providing mobile access will improve communication, efficiency, and productivity for all parties. The use of Procore for project management does not relieve the contractor of any other requirements as may be specified in the contract documents.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 153 of 284 ends

SECTION 7 – MEASUREMENT AND PAYMENT
7-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK
7-1.2 Methods of Measurement.

ADD the following:

The system of measure for this contract shall be the U.S. Standard Measures. 7-2 LUMP SUM WORK
ADD the following: 7- 2.1 Schedule of Values (SOV).

1. Submit a SOV for the lump sum Bid items of the Work to the Engineer for review and approval at the pre-construction meeting.

2. The SOV shall:
a. Subdivide the Work into its respective parts.
b. Include values for all items comprising the Work.
c. Serve as the basis for monthly progress payments.

3. The Engineer is the sole judge of acceptable numbers, details, and description of values established. If, in the opinion of the Engineer, a greater number of SOV items than proposed by Contractor is necessary, add the additional items identified by the Eng ineer. When requested by the Engineer, provide substantiating data in support of the SOV.

4. The Contractor shall incorporate the SOV into the cost loading function of the Schedule in accordance with 6 -1, “CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK.” Monthly progress payment amounts for Lump Sum items shall be determined from the monthly updates of the Schedule activities.

5. The Contractor shall develop the SOV independently but simultaneously with the development of the Schedule activities and logic. Incorporate phase funding impacts, if applicable, into the Schedule.

6. The Contractor shall break down the Work not specifically included in the Bid as necessary for establishment of cost and Schedule activity.

7. Following acceptance of the SOV, the Contractor shall incorporate the changes (if any) into the cost loading portion of the Schedule. Where coordination of the Schedule and the SOV requires changes made to 1 or both documents, the Contractor shall propose changes to the SOV and to the Schedule activities to satisfy the Schedule cost loading requirements.

8. The Contractor shall update and submit these listings in conjunction with the Schedule monthly submittals.

9. The Contractor shall incorporate issued Change Orders or Field Orders in the Schedule into the SOV as single units identified by the Change Order or Field Order number.

10. Changes to the Schedule which add activities not included in the original Schedule but included in the original Work (schedule omissions) shall have values assigned as accepted by the Engineer. Other activity values shall be reduced to provide equal value adjustment increases for added activities as accepted by the Engineer.

11. In the event that the Contractor and the Engineer agree to make adjustments to the original SOV because of inequities discovered in the original accepted SOV, increases and equal decreases to values for activities may be made.

12. The payment for the preparation of the SOV shall be included in the Contract Price.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 154 of 284 ends

7-3 PAYMENT
7-3.1 General.

DELETE the last paragraph in its entirety and SUBSTITUTE with the following:

If, within the time fixed by law, a properly executed notice to stop payment is filed with the Agency, due to the Contractor’s failure to pay for labor or materials used in the Work, all money plus 25 percent due for such labor or materials will be withheld from payment in accordance with applicable laws. At the expiration of 30 Calendar Days from the date of recording the NOC, the amount deducted from the final estimate and retained by the Agency shall be paid to Contractor except such amounts as are required by law to be withheld by properly executed and filed notices to stop payment.

ADD the following:

1. Unless specified otherwise, the Contract Price includes use, consumer, and other taxes mandated by applicable legal requirements. The Contract Price is not subject to adjustment for tax increases.

2. As provided in California Public Contract Code Section 7105, if the Contract is not financed by revenue bonds, Contractor is not responsible for the cost of repairing or restoring damage to the Project when damage was proximately caused by an A ct of God, in excess of 5% of the Contract Price, if the following occur:
a. The damaged portion of the Project was built in accordance with the Contract requirements.
b. There are no insurance requirements in the Contract for the damages.

3. Guarantee periods shall not be affected by any payment but shall commence on the date of recordation of the Notice of Completion.
7-3.2 Partial and Final Payment.

DELETE the last paragraph in its entirety and SUBSTITUTE with the following:

Pursuant to Public Contract Code Section 22300, Contractor shall have the option, at Contractor’s expense, to substitute for any money withheld by the Agency, securities equivalent to the amount being withheld. Securities eligible for such substitution are bank or savings and loans certificates of deposit or such securities which are eligible for investment pursuant to Government Code Section 16430. As to any such security or securities so substituted for monies withheld, Contractor shall be the beneficial owner of same and shall receive any accrued interest.

Such security shall, at Contractor’s request and expense, be deposited with the Agency or with a State or Federally Chartered bank as the escrow agent who shall pay such monies to Contractor upon notification by the Engineer that payment can be made. Such notification shall be given at the expiration of 30 Calendar Days from the date of NOC, or as prescribed by law, provided however, that there shall be a continued retention of the necessary securities to cover such amounts as are required by law to be withheld by properly executed and filed notices to stop payment, or as may be authorized by the Contract to be further retained.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 155 of 284 ends

ADD the following:

1. After final inspection, the Engineer will make a Final Payment Estimate and process a corresponding payment. This estimate will be in writing and shall be for the total amount owed the Contractor as determined by the Engineer and shall be itemized by the Contract Bid item and Change Order item with quantities and payment amounts and shall show all deductions made or to be made for prior payments and amounts to be deducted under provisions of the Contract. All prior estimates and progress payments shall be s ubject to correction in the Final Payment Estimate.

The Contractor shall have 30 C alendar Days from receipt of the Final Payment Estimate to make a written statement disputing any Bid item or Change Order item quantity or payment amount. The Contractor shall provide all documentation at the time of submitting the statement supporting its position. Should the Contractor fail to submit the statement and supporting documentation within the time specified, the Contractor acknowledges that full and final payment has been made for all Contract Bid items and Change Order items.

If the Contractor submits a written statement with supporting documents within 30 Calendar Days from receipt of the Final Payment Estimate, the Engineer will review the disputed item within 30 C alendar Days and make any appropriate adjustments on the Final Payment.

Remaining disputed quantities or amounts not approved by the Engineer will be subject to resolution as specified in Section 2-10.1.1, Initiation of Claim.

The written statement filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of the disputed items. The Engineer will consider the merits of the Contractor’s claims. It will be the responsibility of the Contractor to furnish within a reasonable time such further information and details as may be required by the Engineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying payment for the disputed items.

2. Final Payment and release of Retention shall be paid after Contractor submits the following:
a. An affidavit that payrolls and bills for materials, equipment, and other indebtedness connected with the Work for which the Agency or the Agency’s property might be responsible for or encumbered by. Fewer amounts withheld by the Agency shall have been paid for or otherwise satisfied.
b. A certificate evidencing that insurances required by the Contract Documents shall remain in force after Final Payment is currently in effect and shall not be canceled or allowed to expire until at least a 30 Calendar Days prior written notice has been given to the Engineer.
c. Consent of Surety to Final Payment.
d. If required by the Engineer, other data establishing payment or satisfaction of obligations such as receipts, releases and waivers of liens, claims, and security interests or encumbrances arising out of the Contract Documents. If a Subcontractor

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 156 of 284 ends

refuses to furnish a release or waiver required by the Agency, Contractor may furnish a bond satisfactory to the Engineer to indemnify the Agency against such lien. e. If required in the Contract Documents, the successful completion and submittal of the required reports such as construction demolition, waste recycling, and hydrostatic discharge reports.
f. Required documentation, record drawings, operations manuals, test reports, warranty documentation, and UL labels shall be submitted before requesting the release of retention.

ADD the following: 7- 3.2.1 Application for Progress Payment.

1. By the 5th day of each month, sign, fill out, and submit to the Engineer a partial payment estimate that identifies acceptable Work performed during the previous month, or since the last partial payment estimate was submitted. If requested by the Engineer, provide such additional data as may be required to support the payment estimate. Such data may include submission of signed field orders and satisfactory evidence of payment for equipment, materials, and labor, including payments to Subcontractors and Suppliers.

2. For application for progress payments, Contractor shall use the format required by the Agency. An electronic copy of the invoice form is available from the Engineer upon request.

Progress payments shall be signed, and the date of the invoice shall be the date that the invoice is submitted.

3. The Agency shall not pay progress or partial payments until Contractor submits to the Engineer an updated Schedule. It is solely the Contractor’s responsibility to prepare and submit the Schedule updates.

4. Disputed or incorrect applications shall be returned to the Contractor within 7 Calendar Days with documentation describing the reason for the rejection of the payment request.

ADD the following: 7- 3.2.2 Amount of Progress Payments.

1. If an undisputed and properly submitted application for payment is received by the Engineer, the Agency shall pay Contractor within 30 Calendar Days after the Engineer receives the application for Payment consistent with Public Contract Code S ection 20104.50. The Agency shall pay Contractor for the Work performed, including the payment for offsite stored materials per section 7-3.3.1.2, through the period covered by the application for payment if the payment amount before Retention does not exceed the percentage of completion of the Work as set forth in the SOV.

ADD the following: 7- 3.2.2.1 Progress Payment for Pipelines.

1. Progress payments for pipelines shall be determined by multiplying the total number of linear feet of each of the following operations completed during the payment period, by the corresponding percentage given below, and the Contract Unit Price for the particular main(s) or drain(s).

2. The progress payment may include payment for items in the Bid proposal, other than mains, which have been installed complete during the payment period.

3. Payment breakdown shall be as follows:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 157 of 284 ends

OPERATION PERCENTAGE
WATER:

Trench Excavation, Pipe in Place, Backfill and Cleanup. 80% Hydrostatic and Bacterial Testing, Pavement Restoration and Final Cleanup
20%
SEWER:

Trench Excavation, Pipe in Place, Backfill and Cleanup. 80% Testing (Wayneball and/or Mandrel), Pavement Restoration and Final Cleanup.
20%
STORM DRAIN:

Trench Excavation, Pipe in Place, Backfill and Cleanup. 80% Pavement Restoration and Final Cleanup. 20%
SEWER MAIN REHABILITATION:

Cleaning, Televising, liner installation, point repairs, and lateral reinstatements.
80%
Approval of pipeline rehabilitation verified by Final Video. 20%

4. In asphalt-surfaced streets, the Agency shall pay 15% for hydrostatic and bacterial testing, Wayneball and Mandrelling (where necessary), for water and sewer utility constructions respectively, and operational testing for storm drains, including the trench cap and cleanup.

The Agency shall pay the remaining 5% after completing the asphalt wearing surface and final cleanup.

5. Trench excavation, pipe in place, backfill, and cleanup of construction debris are 1 operation that shall be complete before the Agency pays the first 80%.

ADD the following: 7- 3.2.3 Waiver of Claims at Final Payment.

1. Contractor’s acceptance of Final Payment constitutes a waiver of affirmative c laims by Contractor, except those previously made in writing and identified as unsettled at the time of Final Payment, which are expressly reserved by Contractor from operation of its Release of Claims pursuant to Public Contract Code Section 7100 or other Applicable Law.

ADD the following: 7- 3.2.4 Withholding of Payment and Back Charge.

1. The Engineer may withhold payment for any of the following reasons:
a. Defective or incomplete Work.
b. Stop notices, wage orders, or other withholdings required by Applicable Law. c. Contractor’s failure to comply with 5 -3.3, “Payroll Records” and the Contractor Registration and Electronic Reporting System requirements of the Contract Documents.
d. Failure to submit monthly Construction Schedule updates.

2. The Engineer may back charge the Contractor for any of the following reasons:
a. Defective or incorrect Work not remedied.
b. Damage to Agency property or a third party’s property that was caused by Contractor. c. Liquidated Damages.
d. Non-attendance at meetings without prior cancellation notice.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 158 of 284 ends

e. Failed inspections or re-inspections paid by the Agency. 7-3.3 Delivered Materials
DELETE in its entirety and SUBSTITUTE with the following:

1. The cost of materials and equipment delivered but not incorporated into the Work will not be included in the progress estimate.

ADD the following: 7- 3.3.1 Payment for Stored Materials on Site.

ADD the following: 7- 3.3.1.1 General.

1. When authorized, Contractor may request payment for materials and equipment which has not been incorporated into the Work but will be at a later date and will be delivered and stored at the Project Site.

2. The material shall meet the Contract requirements and the material’s required test results and certifications shall be filed with the Engineer.

3. Only non -perishable materials for major items of Work or Materials Subject to Price Adjustment shall be considered for payment for on- site storage. However, each individual item has a value of more than 1% of the Contract Price and shall become a permanent part of the Work.

4. Materials cost shall be evidenced by the manufacturer’s paid invoice bearing the statement that Contractor has paid all invoices in full.

5. The payments for the stored materials shall not exceed the invoice price or 60% of the Bid prices for the pay items into which the materials are to be incorporated, whichever is less, unless otherwise approved by the Engineer.

6. Apply for the payment for materials stored on a form provided by the Engineer and attach documentation to show the following:
a. The amount paid on the invoice (or other record of production cost) for the stored items.
b. The dollar amount of the material incorporated into each of the various Work items for the month.
c. The amount that should be retained for stored materials. d. That Contractor ha s received the materials and equipment free and are clear of all liens, charges, secured interests, and encumbrances.
e. That the materials and equipment are covered by the appropriate property insurance in accordance with the insurance provisions and other arrangements that protect the Agency’s interest.

7. Contractor shall provide the Engineer, upon request and prior to any partial payment, documentation which transfers full legal title to such materials to the Agency conditional only upon receipt of the Final Payment. Such transfer of title or any partial payment shall not constitute acceptance by the Agency of the materials nor shall it void the right to reject materials subsequently found to be unsatisfactory in accordance with SECTION 4 – CONTROL OF MATERIALS. This shall also not relieve Contractor of any obligation arising under the Contract Documents.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 159 of 284 ends

8. The payments for materials on-site are subject to retention as set forth in 7-3.2, “Partial and Final Payment.”

9. Contractor shall assume all risks associated with the loss or damage to the stored products for which payment has or has not been received.

10. Equipment and materials shall be stored in accordance with manufacturer’s recommendations. The stored products shall be in a form ready for installation. The Agency shall not pay for raw materials or parts and pieces of equipment.

11. Any and all surplus materials that are not incorporated in the Work shall become Contractor’s property at no additional cost to the Agency.

12. Unless specifically provided in the Contract, payment for the materials on hand shall not be included when determining the percentage of Work completed.

13. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus sales tax, freight, and delivery.

The Agency reserves the right to approve materials and sources of supply, or to supply materials to the Contractor if necessary, for the progress of the Work. No markup shall be applied to any material provided by the Agency.

ADD the following: 7- 3.3.1.2 Payment for Stored Materials Offsite.

1. The payment of materials and equipment delivered and stored offsite shall be contingent upon Contractor’s compliance with the storage and protective maintenance requirements set forth in the Contract Documents and all other requirements necessary to preserve equipment warranties for the benefit of the Agency.

2. The Agency reserves the right to refuse approval for the payment of any equipment or materials suitably stored offsite in its sole discretion, regardless of whether all conditions in the Contract Documents have been met.

3. Partial payment may be made for products eligible for offsite delivery and storage only upon Contractor’s presentation of a bill of sale, a paid invoice, or an affidavit certifying that the material is received by the Contractor free and clear of all liens, encumbrances, and secured interest of any kind including offsite delivery.

4. Partial payment for products delivered and stored offsite shall be contingent upon Contractor’s compliance with the storage and protective maintenance requirements set forth in the Contract Documents and all other requirements necessary to preserve equipme nt warranties for the benefit of the Agency.

5. The cost of materials and equipment delivered but not incorporated into the Work will not be included in the progress estimate.

6. Costs associated with the delivery to and storage at an offsite facility shall be at Contractor’s expense regardless of the Engineer’s approval to deliver and store the materials.

7. Contractor shall provide written evidence to the Engineer of having made arrangements for unrestricted access by the Agency and the Agency’s authorized representatives to the materials wherever stored, including provisions for the Agency to take control and possession of such materials at any time and without restriction. Contractor shall furnish the Engineer a permit of entry, from the owner of the property, for at least 6 months after the NOC has been filed. The permit of entry shall contain information similar to the following:

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 160 of 284 ends

PERMIT OF ENTRY: Permission is granted to the Agency and its designated employees or agents to enter upon the property described in this permit for a period of not less than 6 months after the NOC has been filed for ( El Camino Real Widening From Poinsettia Lane to Camino Vida Roble) for the purpose of removing materials for which advance materials on hand payment has been made to (Contractor’s Name). The property is owned by (Owner’s Name) and is described as follows: (Address and Description of Property). (Include signature(s) and date(s) for owner and lessee or purchaser, and, if appropriate, attach a copy of a warehouse receipt or contract for storage.

8. The material shall be clearly marked and identified as being specifically fabricated, produced, and reserved for use on the Project. The Contractor shall provide payment documentation for the materials.
7-3.4 Mobilization.

ADD the following:

When a Bid item is included for Mobilization, and subject to the conditions and limitations set forth herein, the costs of work in advance of construction operations and not directly attributable to any specific Bid item will be included in the progress estimate. When no such Bid item is provided, payment for such costs will be considered as included in the other Bid items of Work.

Mobilization includes furnishing all insurance, bonds, and licenses and all Work necessary for the movement of personnel, equipment, supplies, and incidentals to and from the Site; for establishment of all offices, buildings, storage yards, and temporary utilities or facilities necessary for the Work; and for all other Work and operations which shall be performed prior to beginning the Work or after completion of the Work, excepting those specifically paid for under separate Bid items. Such operations shall include, but are not limited to, coordination with Agency forces; securing permits; surveying and staking; utility mark-out; securing construction water supply and temporary power necessary for construction; temporary construction fencing; installing, maintaining and removing project signs; providing on -site sanitary facilities; posting OSHA and labor compliance notices and establishing safety programs; preparing, maintaining and submitting the project record drawings; and any other Work or services not included in any other Bid item.

The complete dismantling and removal of the Contractor’s temporary facilities, equipment, materials, construction wastes, and personnel from the Site at the completion of the Work, referred to as demobilization, is included in the payment for Mobilization.

When price for this Bid item is limited to a percentage of the total Contract price, it shall be so indicated in the Bid Form.

The Contract price paid for Mobilization shall include all items and operations as described in this subsection and no additional payment shall be made.

Progress payments for Mobilization will be made as follows:
a) First progress payment (after the issuance of the Notice to Proceed): payment will be made at forty percent (40%) of the amount bid for Mobilization.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 161 of 284 ends

b) Second progress payment: payment will be made at fifty percent (50%) of the amount bid for Mobilization.
c) The remaining 10% of the Bid price for Mobilization will be made when all punch list items are completed to the satisfaction of the Engineer and the Contractor has demobilized from the Project Site.

7-3.5 Contract Unit Prices
7-3.5.1 General.

DELETE the second to fourth paragraph and REPLACE with the following:

1. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the Work from that shown on the Plans or specified in the Specifications, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price.

2. If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications varies from the Bid quantity by 50 percent or less, payment will be made at the Contract Unit Price. If the actual q uantity of the item of work varies from the Bid quantity by more than 50 percent, payment will be made per Section 2-7.3 or 2-7.4 as appropriate.

3. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does involve a substantial change in the character of the Work from that shown on the Plans or specified in the Specifications, an adjustment in payment will be made per Section 2-7.6.

ADD the following:

1. Unit Bid prices shall not be subject to adjustment regardless of quantity used or if none is used for the following Bid items:
a. additional bedding
b. imported backfill
c. shoring
d. water services and connections
e. water pollution control items
f. point repairs for existing sewer mains
g. additional point repairs for existing sewer mains
h. sewer lateral connections
i. sewer lateral linings
j. traffic control
k. additional equipment

2. .

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 162 of 284 ends

7-3.5.2 Increases of More Than 50 Percent.

DELETE in its entirety and REPLACE with the following:

Should the actual quantity of an item of Work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 50 percent, payment for the quantity in excess of 150 percent of the Bid quantity wil l be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 2-8. The Extra Work per Section 2-8, basis of payment, shall not include fixed costs. Fixed costs shall be deemed to have been recovered by the Contractor through payment for 150 percent of the Bid quantity at the Contract Unit Price.
7-3.5.3 Decreases of More Than 50 Percent.

DELETE in its entirety and REPLACE with the following:

Should the actual quantity of an item of Work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less than 50 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 2-8; however, in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 50 percent of the Bid quantity at the Contract Unit Price. 7-3.6 Stipulated Unit Prices.

DELETE in its entirety and REPLACE with the following:

Stipulated Unit Prices are unit prices established by the Agency in the Contract Documents as distinguished from Contract Unit Prices submitted by the Contractor. Stipulated Unit Prices may be used for the adjustment of Contract changes when so specified in the Supplemental General Provisions.
7-3.7 Agreed Prices.

DELETE in its entirety and REPLACE with the following:

Agreed Prices are prices for new or unforeseen Work, or adjustments in Contract Unit Prices per Section 7-3.5, established by mutual agreement between the Contractor and the Agency. If mutual agreement cannot be reached, the Engineer may direct the Contractor to proceed on the basis of Extra Work in accordance with Section 2 -8, except as otherwise specified in Se ctions 7-

3.5.2 and 7-3.5.3.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 163 of 284 ends

7-3.8 Eliminated Items.

DELETE in its entirety and REPLACE with the following:

Should any Bid item be eliminated in its entirety, payment will be made to the Contractor for its actual costs incurred in connection with the eliminated item prior to notification in writing from the Engineer so stating its elimination. If material conforming to the Plans and S pecifications is ordered by the Contractor for use in the eliminated item prior to the date of notification of elimination by the Engineer, and if the order for that material cannot be canceled, payment will be made to the Contractor for the actual cost of the material. In this case, the material shall become the property of the Agency. Payment will be made to the Contractor for its actual costs for any further handling. If the material is returnable, the material shall be returned, and payment will be made to the Contractor for the actual cost of charges made by the supplier for returning the material and for handling by the Contractor. Actual costs, as used in this Agency Supplement, shall be computed on the basis of Extra Work per Section 2-8.

ADD the following: 7- 3.9 Field Orders.

1. The Agency shall pay Field Order items of the Work in accordance with the limits below if the cumulative total of Field Orders does not exceed the Field Orders” Bid Item:

Contract Price Maximum Field Order Amount
Less than $100,001 $2,500
$100,001 to $1,000,000 $5,000
$1,000,001 to $5,000,000 $10,000
Greater than $5,000,000 $20,000
ADD the following: 7- 3.10 Compensation Adjustments for Price Index Fluctuations.

1. Unless otherwise specified, the provisions of this section apply only to the paving asphalt used in the following:
a. Asphalt Concrete Pavement
b. Asphalt Pavement Repair
c. Scheduled and Unscheduled Base Repair
d. Slurry Seal or any other asphalt emulsion

2. The compensation for paving asphalt shall be increased or decreased for paving asphalt price fluctuations in accordance with 9- 1.07 “Payment Adjustments for Price Index Fluctuations” in the Caltrans Standard Specifications.

3. The adjustment in compensation shall also be subject to the following:
a. Show the provided compensation adjustments separately on payment estimates.

Contractor is liable to the Agency for decreased compensation adjustments and the Engineer may deduct the amount from moneys payable or that may become payable to Contractor.
b. In the event of an overrun of Contract Time, adjustment in compensation for asphalt binder included in estimates during the overrun period shall be determined using the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 164 of 284 ends

California Statewide Crude Oil Price Index in effect on the first business day of the month within the pay period in which the overrun began. c. In the event that the companies discontinue posting their prices for a field, the Engineer shall determine an index from the remaining posted prices. The Agency reserves the right to include in the index determination the posted prices of additional fields.

4. Contractor may opt out of the payment adjustments for price index fluctuations when specified in the Contract Documents by submitting a letter with the Bid. 7-4 PAYMENT FOR EXTRA WORK
7-4.1 General.

ADD the following:

1. With every request for payment, Contractor shall submit to the Engineer a breakdown showing monthly and cumulative amounts of the Work performed under the Change Order by Contractor and Contractor’s Subcontractors. The reporting format shall be approved by the Engineer.

2. 7-4.2 Basis for Establishing Costs.
7-4.2.1 Labor.

ADD the following:

1. The Agency reserves the right to request the following:
a. Financial records of salaries for an employee.
b. Wage rates/Certified Payroll.
c. Bonuses and deductions.

2. Contractor shall list the labor rates of its personnel and Subcontractors who work on the Project. The payment for payroll records is included in the Contract Price.

3. If Contractor’s proposal for Extra Work is based upon services and Work to be performed outside Normal Working Hours, the labor charges associated with the Extra Work shall consist of straight time wages and burdens plus the appropriate overtime or shift premium with no additional burdens, such as fringe benefits, on the premium portion. 7-4.2.3 Tool and Equipment Rental.

DELETE in its entirety and SUBSTITUTE with the following:

1. No payment shall be made for the use of tools which have a replacement value of $200 or less.

2. Regardless of ownership, the rates and delay factors to be used in determining equipment rental costs shall not exceed those listed in the latest edition of the Caltrans publication entitled “Labor Surcharge and Equipment Rental Rates” preceding the date t he Work is accomplished. The latest edition of the Caltrans publication is available at www.dot.ca.gov.

The delay factors therein shall be used as multipliers of the rental rates for determining the

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 165 of 284 ends

value of costs for delay to the Contractor and Subcontractors, if any. The labor surcharge rates published therein are not a part of this Contract.

3. Contractor shall be entitled to a rental rate adjustment when Contractor can substantiate that the rental rates prevailing locally exceed the published rates by more than 15%. For equipment not listed in the Caltrans publication, rental rates shall not exceed listed rates prevailing locally at equipment rental agencies or distributors at the time the Work is performed.

4. Whenever possible, Extra Work shall be accomplished using equipment available on Site or owned by Contractor. If a specific piece of equipment shall be rented to be used exclusively for the Extra Work, the rental rate shall be the invoiced rate. The rental rates paid shall include the cost of fuel, oil, lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Necessary loading and transportation costs for equipment used on the Extra Work shall be included.

5. If rental equipment is not being used or used intermittently and could be returned to its rental source rather than holding it at the Work S ite, the Contractor shall return the equipment at no expense to the Agency unless Contractor elects to keep it at the Work Site at Contractor’s expense.

6. The reported rental time for equipment already at the Work S ite shall be the duration of its use on the Extra Work. This time shall begin when equipment is first used on Extra Work, plus the time required to move it from its previous site and back or from its previous site to a closer site.

7. All equipment shall be acceptable to the Engineer, in good working condition, and suitable for the purpose for which it is to be used.
7-4.3 Markup.
7-4.3.1 Work by the Contractor.

DELETE in its entirety and REPLACE with the following:

The following percentages shall be added to the Contractor’s costs and shall constitute the markup for all overhead and profits:

Labor 20
Materials 15
Equipment Rental 15
Other Items and Expenditures 15
To the sum of the costs and markups provided for in this section, 1 % shall be added as compensation for bonding.
7-4.3.2 Work by a Subcontractor.

DELETE in its entirety and REPLACE with the following:

When all or any part of the Extra Work is performed by a Subcontractor, the markup established in 7-4.3.1 shall be applied to the Subcontractor’s actual cost of such Work. A markup of 10 percent on the first $5,000 of the subcontracted portion of the Extra Work and a markup of 5 percent on

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 166 of 284 ends

Work added in excess of $5,000 of the subcontracted portion of the Extra Work may be added by the Contractor.

7-4.4 Daily Reports.

ADD the following:

Payment for Extra Work will not be made until such time that the Contractor submits completed daily reports and all supporting documents to the Engineer.

ADD 7-6 BID ITEM DESCRIPTIONS
Payment for each Bid Item shall be made at the quantity and type as listed in the Contractor’s Proposal. All work shown or mentioned on the plans, in the Contract Documents, General Provisions, or Technical Specifications shall be considered as included in the Bid Items.

Bid Item 1. Mobilization: Payment for “Mobilization” will be made at the stipulated lump -sum price bid therefore in the bid schedule, and includes full compensation for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment and incidentals, and for doing all the work involved in mobilization and preparatory work and operations, including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidental to preparing to conduct work on and off the project site and other offsite facilities necessary for work on the project; for all other facilities, suretie s, work and operations which must be performed or costs incurred prior to beginning work on various contract items on or off the project site, excepting those specifically paid for under separate sections of these specifications. The Contractor hereby agr ees that the stipulated lump sum amount is sufficient for Mobilization and Preparatory Work, as described in this section, and that the Contractor shall have no right to additional compensation for Mobilization and Preparatory Work.

Bid Item 2. Construction Schedule : Payment for “ Construction Schedule ” will be paid for at the stipulated lump sum price. The stipulated lump sum price paid for Construction Schedule shall include full compensation for furnishing all labor, materials including, but not limited to, the computer hardware and software, tools, equipment, and incidentals; and for doing all the Work involved in attending meetings, preparing, furnishing, updating, revising the tabular, bar and flow chart Construction Schedules and narrative reports required by these supplemental provisions and as directed by the Engineer. The Engineer’s determination that each and any Construction Schedule proposed by the Contractor complies with the requirements of these supplemental provisions shall be prece dent to each and any payment for the Construction Schedule. Payments for Construction Schedule will be made as per Sections 6-1.8.1 through 6-1.8.3.

Bid Item 3. Erosion Control and Water Pollution Control : Payment for “Erosion Control and Water Pollution Control” shall be made at the contract lump sum price and shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals for doing the work involved in installing a nd maintaining any and all storm water BMPs for

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 167 of 284 ends

the duration of the project, as specified herein, and as directed by the Engineer and no additional compensation shall be allowed therefor. This work shall include preparing, obtaining approvals, revising and amending the project SWPPP, installing, constru cting, maintaining, removing and disposing of all Best Management Practices (BMPs) specified in the SWPPP and as required by applicable codes and in strict accordance with the State Water Board, maintenance of storm water and non -storm water best managemen t practices (BMPs) throughout the duration of all Work, implementing a rain action plan, storm water sampling and analysis day, preparing a storm water annual report, and job site management. These requirements shall also apply to any offsite storage yards or construction laydown areas utilized for this project. The lump sum bid price shall include payment of application and annual fees required by the SDRWCB until the date of the projects’ substantial completion and no additional compensation shall be allo wed therefor.

Bid Item 4. Temporary Traffic Control: Payment for “Temporary Traffic Control” shall be made at the contract lump sump price. This shall include all t emporary traffic pavement markers, temporary channelizers, temporary signing, temporary railing (type K), temporary crash cushions, temporary barricades, temporary plastic drums, portable flashing beacons, and temporary appurtenances thereto shown on the plans or required in the specifications and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in applying, installing, maintaining, and removing temporary traffic pavement markers, channelizers, signing, railing (type K), crash cushions and appurtenances, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as directed by the Engineer. Payment for temporary crash cushions, concrete barriers and the signs and reflectors marking them shall include the inst allation, grading for installation, grading for the approach path, maintenance, painting and re -painting, replacement of damaged units and removal and shall also be included in the lump -sum price bid for traffic control. Payment for installation and/or relocation of K-rails and crash cushions when not shown on the plans and requested by the Engineer shall be made per section 2-8, Extra Work, SSPWC.

Bid Item 5. Clearing and Grubbing: Payment for “Clearing and Grubbing” shall be made at the contract lump sum price for clearing and grubbing within the project limits and at stockpile locations and no other payments will be made. Unless otherwise noted on plans, the Contractor shall remove all existing abandoned pipelines and conduits of any type, or use, and pipelines and conduits of any type, or use, that are abandoned during the course of the work and shall replace said pipelines and conduits with properly compacte d soils.

Payment for removal and disposal of abandoned utilities shall be included in the lump- sum bid for Clearing and Grubbing, and no additional payment will be made.

Bid Item 6. Asphalt Concrete: Payment for “Asphalt Concrete” shall be at the unit price bid per ton.

No additional payment shall be made for any tack coat or sand blotter. Unit price bid shall include full compensation for furnishing all labor, materials, tools, equipment, and all related and appurtenant work to complete the work in place.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 168 of 284 ends

Bid Item 7. Colored Stamped Concrete: Payment for “ Colored Stamped Concrete ” paving shall be paid under the contract unit price bid per square foot for median concrete paving. Said payment shall include compensation for all excavation, grading, backfill, permeable material, forming, mesh, reinforcing steel, concrete, integral color, texture sealers, and other material necessary to construct the specific paving.

Bid Item 8. Aggregate Base : Payment for “Aggregate Base” shall be measured and paid for on a compacted cubic yard basis at the thickness shown in the Bid Schedule. Unit price bid shall include full compensation for furnishing all labor, materials, tools, equipment, hauling, excavation, removal and disposal of surplus materials, compaction and all related and appurtenant work to complete the work in place.

Bid Item 9. Slurry Seal: Payment for the contract unit price of square yard paid for this bid item shall constitute full compensation for polymer modified, T ype II slurry seal conforming to the requirements of Sections 203 and 302 of the Standard Specifications. Asphalt Concrete (AC) shall be Type II-C2-PG 64-10 slurry seal will be placed in vehicular travel lanes as illustrated on the project Plans and as described in these Special Provisions. No more than 15% RAP shall be used in the AC mix used for patching. No additional compensation shall be allowed. This Bid shall include all labor, tools, equipment, materials, preparation and incidentals for doing all Work in installing slurry, including any crack fill or removal of existing striping and thermoplastic.

Bid Item 10. Unclassified Excavation: Payment for “Unclassified Excavation” will be made at the unit price per cubic yard. Only the quantity of unclassified excavation measured shall be paid for. No excavated material which is re-excavated will be paid for. For progress payments, the quantity of unclassified excavation shall be estimated by the Engineer . The Engineer's calculations shall be considered the definitive determinant for quantities for final payment. All topographic surveying and calculations necessary t o quantify payment quantities for Unclassified Excavation shall be performed by the Engineer.

Bid Item 11. Concrete Sidewalk: Payment for “Concrete Sidewalk” shall be measured and paid for on a cubic yard basis and shall include full compensation for all labor, materials, tools, equipment, including but not limited to; saw cutting, removal & disposal of existing materials, forming, compaction, joints, and all related incidentals re quired to complete the work in place. Payment shall also include the repair or replacement of landscaping, irrigation, or other private improvements adjacent to areas of work.

Bid Item 12. Concrete Driveway:

Payment for “Concrete Driveway” shall be measured and paid for on a cubic yard basis and shall include full compensation for all labor, materials, tools, equipment, including but not limited to; saw cutting, removal & disposal of materials, dowels, forming, compaction, adjacent asphalt paving and all related incidentals required to complete the work in place.

Bid Item 13. Concrete Curb and Gutter : Payment for “ Concrete Curb and Gutter ” shall be measured and paid for on a linear foot basis and shall include full compensation for all labor, materials, tools, equipment, including but not limited to; saw cutting, removal & disposal

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 169 of 284 ends

of existing materials, forming, compaction, adjacent asphalt paving and all related incidentals required to complete the work in place.

Bid Item 14. Modified Concrete Curb and Gutter: Payment for “Modified Concrete Curb and Gutter” shall be measured and paid for on a linear foot basis and shall include full compensation for all labor, materials, tools, equipment, including but not limited to; saw cutting, removal & disposal of existing materials, forming, compaction, adjacent asphalt paving and all related incidentals required to complete the work in place.

Bid Item 15. Cold Mill Asphalt Concrete: Payment for “Cold Mill Asphalt Concrete” shall be measured and paid for on a square yard basis and shall include full compensation for cold milling, removal of asphalt concrete and slurry seal material from adjacent concrete gutters, construction and removal of pavement transitions, disposal of millings, and all other necessary work.

Bid Item 16. Gravity Retaining Wall: Payment for “Gravity Retaining Wall” shall be measured and paid for on a cubic yard basis per the type shown on the plans and shall include full compensation for all labor, materials, equipment, tools, and incidentals necessary to install the gravity retaining walls as shown on the Plans and Bid Schedule. This item shall include all costs for the excavation, forming, compaction, installation, removal and disposal of materials, and all related incidentals required to complete the work in place.

Bid Item 17. Temporary High Visibility Fence: Payment for “Temporary High-Visibility Fence” shall be measured and paid for a linear foot basis and shall include full compensation for all labor, materials, tools, equipment, and all related incidentals required to install the THVF in place.

Bid Item 18. 18” RCP (1350-D): Payment for “18” RCP (1350-D)” will be made at the Contract Unit Price per linear foot. The Contract Unit Price shall include payment for:
• All wyes, tees, bends, monolithic catch basin connections, and specials as shown on the Plans
• Removal of interfering portions of existing pipelines, sewers, storm drains, and improvements
• Closing or removing of abandoned conduit and structures • Trench excavation
• Disposal of excess excavation
• Control of surface waters
• Preparation of subgrade
• Placing and joining pipe or box culvert
• Erection and removal of forms
• Reinforcing steel
• Pressure testing
• Disinfection sample collection and delivery

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 170 of 284 ends

• Backfilling the trench
• Permanent resurfacing
• Trench shoring and plans, excluding engineered shoring and engineered shoring plans • All other Work (excluding temporary resurfacing) necessary to install the pipe, conduit, or box culvert, complete in-place.

No separate or additional payment shall be made for additional bedding or a higher strength of pipe necessitated by the Contractor exceeding the maximum trench width, unless a bid item has been provided.

Bid Item 19. 24” RCP (1350-D): Payment for “24” RCP (1350-D)” will be made at the Contract Unit Price per linear foot. The Contract Unit Price shall include payment for:
• All wyes, tees, bends, monolithic catch basin connections, and specials as shown on the Plans
• Removal of interfering portions of existing pipelines, sewers, storm drains, and improvements
• Closing or removing of abandoned conduit and structures • Trench excavation
• Disposal of excess excavation
• Control of surface waters
• Preparation of subgrade
• Placing and joining pipe or box culvert
• Erection and removal of forms
• Reinforcing steel
• Pressure testing
• Disinfection sample collection and delivery
• Backfilling the trench
• Permanent resurfacing
• Trench shoring and plans, excluding engineered shoring and engineered shoring plans • All other Work (excluding temporary resurfacing) necessary to install the pipe, conduit, or box culvert, complete in-place.

No separate or additional payment shall be made for additional bedding or a higher strength of pipe necessitated by the Contractor exceeding the maximum trench width, unless a bid item has been provided.

Bid Item 20. Pipe Collar: Payment for “Pipe Collar” shall be measure and paid for an each basis and shall include full compensation for all labor, materials, equipment, tools, and incidentals necessary to install concrete pipe collar as shown on the Plans including but not limited

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 171 of 284 ends

to; sawcutting, finishing, mortar, removal and disposal of materials, connections to storm drain conduit, excavation, compaction, and all related incidentals required to complete the work in place.

Bid Item 21. Straight Headwall: Payment for “Straight Headwall” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment necessary to construct the headwall as shown on the plans and in the Bid Schedule.

Payment shall also include excavation, fill, grading, compaction, disposal of excess material, forming, connections to the storm drain, and all related incidentals required to complete the work in place
Bid Item 22. Biofiltration BMP: Payment for “Biofiltration BMP” shall be measured and paid for on a square foot basis and shall include full compensation for all labor, materials, equipment, tools, and incidentals necessary to install the biofiltration BMPs as shown in the Plans and the Bid Schedule. This item shall include all costs associated with excavation, compaction, gravel, engineered soil media (supplying, testing, amending, mixing and installing various planting soil categories for use in stormwater management and horticultural plantings), choker layer, shredded hardwood mulch, 30 mil impermeable liner, splash pads, concrete check dams, curb cuts, and all other related items necessary to complete the work in place that do not have a unique bid item.

Bid Item 23. 8” PVC (Perforated): Payment for “8” PVC (Perforated)” will be made at the Contract Unit Price per linear foot. The Contract Unit Price shall include payment for:
• All wyes, tees, bends, monolithic catch basin connections, and specials as shown on the Plans
• Removal of interfering portions of existing pipelines, sewers, storm drains, and improvements
• Closing or removing of abandoned conduit and structures • Trench excavation
• Disposal of excess excavation
• Control of surface waters
• Preparation of subgrade
• Placing and joining pipe or box culvert
• Erection and removal of forms
• Reinforcing steel
• Pressure testing
• Disinfection sample collection and delivery
• Backfilling the trench
• Permanent resurfacing
• Trench shoring and plans, excluding engineered shoring and engineered shoring plans • All other Work (excluding temporary resurfacing) necessary to install the pipe, conduit, or box culvert, complete in-place.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 172 of 284 ends

No separate or additional payment shall be made for additional bedding or a higher strength of pipe necessitated by the Contractor exceeding the maximum trench width, unless a bid item has been provided.

Bid Item 24. 8” PVC (Non -Perforated): Payment for “ 8” PVC (Non -Perforated)” will be made at the Contract Unit Price per linear foot. The Contract Unit Price shall include payment for:
• All wyes, tees, bends, monolithic catch basin connections, and specials as shown on the Plans
• Removal of interfering portions of existing pipelines, sewers, storm drains, and improvements
• Closing or removing of abandoned conduit and structures • Trench excavation
• Disposal of excess excavation
• Control of surface waters
• Preparation of subgrade
• Placing and joining pipe or box culvert
• Erection and removal of forms
• Reinforcing steel
• Pressure testing
• Disinfection sample collection and delivery
• Backfilling the trench
• Permanent resurfacing
• Trench shoring and plans, excluding engineered shoring and engineered shoring plans • All other Work (excluding temporary resurfacing) necessary to install the pipe, conduit, or box culvert, complete in-place.

Bid Item 25. Curb Inlet – Type C-2 L(L=15’): P ayment for “Curb Inlet – Type C-2 (L=15’)” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment, tools, and incidentals necessary to install standard and modified concrete curb inlets at the size and type indicated in the Plans and the Bid Schedule. This item shall include all costs for the installation, forming, removal and disposal of materials as necessary, connections to the storm drain conduits, curb inlet stenciling, and all related incidentals required to complete the work in place.

Bid Item 26. 24” x 24” Cleanout: Payment for “24” x 24” Cleanout” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment, tools, and incidentals necessary to install cleanouts at the size and type indicated in the Plans and the Bid Schedule. This item shall include all costs for the installation, forming, removal and disposal of materials as necessary, connections to the storm drain conduits, covers, and all related incidentals required to complete the work in place.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 173 of 284 ends

Bid Item 27. 8” Subdrain Cleanout: Payment for “8” Subdrain Cleanout” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment, tools and incidentals necessary but not limited to; backfill, compaction, installation of cleanout including wyes and jointing, pipe ri sers, elbows, gaskets, frames and covers or screw caps, and concrete encasements, and all related and appurtenant work to complete in place
Bid Item 28. Observation Well: Payment for “Observation Well” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment, tools and incidentals necessary but not limited to; backfill, compaction, installation of observation well including wyes and jointing, pipe risers, elbows, gaskets, frames and covers or screw caps, and concrete encasements, and all related and appurtenant work to complete in place
Bid Item 29. Striping and Markings: Payment for “Striping and Markings” shall be made at the contract lump sum price for thermoplastic traffic striping and pavement markings as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the final traffic striping.

Bid Item 30. Striping Removal: Payment for removal of traffic striping , curb markings, and pavement markers as shown on the plans and required by the specifications shall be included in the lump-sum price bid for “ Striping Removal ”, and no additional compensation will be allowed therefore. The lump sum prices bid shall include all labor, tools, equipment, materials, and incidentals for doing all work for the removal of traffic striping , pavement markings, and pavement markers.

Bid Item 31. Signing: Permanent signing and appurtenances shall be made at the contract lump sum price for "Signing” and payment therefore shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in supplying and installing permanent signing and appurtenances, to relocate roadside signs, and to remove roadside signs, complete in place, as shown on the plans, as specified in the Standard Specification and these special provisions, and as di rected by the Engineer.

Bid Item 32. Adjust Sewer Manhole to Grade and Replace Manhole Frame and Cover with New locking composite Frame and Cover: Payment for “Adjust Sewer Manhole to Grade and Replace Manhole Frame and Cover with New locking composite Frame and Cover” shall be measured and paid for on an each basis. This item consists of providing all labor, materials, tools, and equipment and performing all work involved in furnishing and installing complete, in place and operational, all pipe, fittings, adjust exist ing sewer manhole to match final grade as detailed and specified in Vallecitos Water District Standard Drawing S-1.

This item includes, but is not limited to, potholing the locations/pothole information, traffic control, Clearing and grubbing, safety measures, trench excavation, removal of material,

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 174 of 284 ends

bedding, backfill, compaction, testing, clean up, concrete curb/gutter and sidewalk removal and replacement, and surface restoration.

These sewer facilities are connected to occupied residences and businesses. The contractor shall be responsible for maintaining sewer service during construction unless a main line or temporary shutdown is approved. “Highlining” shall be considered included in this item of Work.

Bid Item 33. Replace Manhole Frame and Cover with New Locking Composite Frame and Cover and Install Concrete Sewer Reinforcement: Payment for “Replace Manhole Frame and Cover with New Locking Composite Frame and Cover and Install Concrete Sewer Reinforcement” shall be measured and paid for on an each basis. This item consists of providing all labor, materials, tools and equipment a nd performing all work involved in furnishing and installing complete, in place and operational, all pipe, fittings, adjust existing sewer manhole to match final grade as detailed and specified in Vallecitos Water District Standard Drawing S-1 & S-14.

This item includes, but is not limited to, potholing the locations/pothole information, traffic control, clearing and grubbing, safety measures, trench excavation, removal of material, bedding, backfill, compaction, testing, clean up, concrete curb/gutter and sidewalk removal and replacement, and surface restoration.

These sewer facilities are connected to occupied residences and businesses. The contractor shall be responsible for maintaining sewer service during construction unless a main line or temporary shutdown is approved. “Highlining” shall be considered included in this item of Work.

Bid Item 34. Relocate Fire Hydrant: Payment for “Relocate Fire Hydrant” shall be measured and paid for on an each basis and shall include full compensation for all labor, materials, equipment, tools and incidentals necessary to remove and relocate the fire hydrant as shown on the Plans. Payment shall include all excavation, and any work relating to the hydrant, hydrant lateral, fire service connection, hydrant shutoff valve and actuator, thrust restraint, gaskets and fasteners, valve cans, risers, extensions, and lid, backfill restoration of the street surface, and all other work necessary to complete the work as shown on the Plans.

Bid Item 35. Relocate Water Meter:

Payment for “Relocate Water Meter” shall be measured and paid for an each basis and shall include full compensation for all labor, materials, equipment, tools and incidentals to relocate water meter in place as shown on the Plans. Payment shall include the service tap, corporation stop, l ateral, riser, angle meter valve, service saddle, meter installation, meter box or vault, meter box lid, appurtenant couplings, and all other service materials required to complete the work as shown on the Plans.

Bid Item 36. Lighting System: Payment for “Lighting System” shall be made at the contract lump sum price for all components of the lighting system as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 175 of 284 ends

Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the lighting system.

Bid Item 37. Fiber Optic Cable System: Payment for “Fiber Optic Cable System” shall be made at the contract lump sum price for all components of the fiber optic system as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the fiber optic cable system.

Bid Item 38. Traffic Signal: Payment for “Traffic Signal” shall be made at the contract lump sum price for all components of the traffic signal system as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the lighting system.

Bid Item 39. Irrigation: Payment for “Irrigation” shall be made at the contract lump sum price for all components of the irrigation system as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the irrigation system.

Bid Item 40. Planting: Payment for “Planting” shall be made at the contract lump sum price for all components of the planting as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work in installing the planting.

Bid Item 41. Initial 120 Day Maintenance : Payment for “Initial 120 Day Maintenance” shall be made at the contract lump sum price for all components of the 120-day maintenance as shown on the Plans and required by the Specifications and no additional compensation will be allowed, therefore. The lump sum Bid shall include all labor, tools, equipment, materials, and incidentals for doing all Work for the 120-day maintenance.

Bid Item 42. Staging: The contract price paid for this bid item is lump sum. Primary staging areas are to minimize impact to the right-of-way and should be within various less utilized areas near the construction area, outside of a bike lane with minimal removal of parking.

Staging areas are available on public streets (Jasper Way and Camino Vida Roble cul-de- sac) nearby construction areas only and shall have temporary 6’ high chain link security fencing to keep traveling public safely away from the equipment. Chain link fence with fabric shall be constructed and secured with a black or dark green fabric attached securely to the chain link fence and shall have holes to sufficiently resist damage during windstorms. Staging area shall be indicated on submittals for traffic control plans per Section 3-12.4.3 and SWPPP per Section 803-6. The contractor is responsible for the area will be restored to its original condition.

00 73 00 AGENCY SUPPLEMENTAL GENERAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 176 of 284 ends

The city does not compensate the contractor if construction storage is not available on or off site. The contractor must find off-site storage that complies with city zoning ordinance and policies and submit land use permit for off-site storage and incorporate area into their SWPPP plan. Prior to storage of any materials on any private property within the City’s boundaries, the Contractor shall provide to the Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored, and shall provide for the removal of the materials and restoration of the storage site within the Contract time allowed for the Work.

Employees working on the project should park within the construction area or at another location that does not include the immediately adjacent streets, unless approved by the city. Loading or unloading equipment/materials shall be done in the staging area and/or within the Traffic Control plan.

SECTION 8 – FACILITIES FOR AGENCY PERSONNEL
8-1 GENERAL

END OF SECTION

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 177 ends

00 74 00 AGENCY SUPPLEMENTAL PROVISIONS TO GREENBOOK

INTRODUCTION
The Specifications contained in this 00 7400 Agency Supplemental Technical Provisions take precedence over the specification language contained in the Standard Specifications for Public Works Construction, "The Greenbook " latest edition and all errata. This specification addresses the unique conditions in Carlsbad that are not addressed in The Greenbook . Therefore, if there is a conflict, these Specifications shall control.

The Greenbook may be purchased at Bidder/Contractors local technical bookstore or directly from the publisher. These Agency Supplemental General Provisions are available only for download from the online bidding portal with Contract Documents. The Agency does not provide hard copies.

When used in the Contract Documents, statements or command phrases (active voice and imperative mood) refer to and are directed at the “Bidder” or “Contractor” as applicable. The Specifications are written to the “Bidder” before award and the “Contractor” after award. Before award, interpret sentences written in the imperative mood as starting with “The Bidder shall .” Interpret the term “you” as “the Bidder” and interpret the term “your” as “the Bidder’s .” After award, interpret sentences written in the imperative mood starting with “The Contractor shall. ” Interpret the term “you” as “the Contractor” and interpret the term “your” as “the Contractor’s.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 178 ends

PART 2 CONSTRUCTION MATERIALS
SECTION 200 – ROCK MATERIALS
200-2 UNTREATED BASE MATERIALS
200-2.1 General.

ADD the following:

1. Aggregate base shall be Class 2 Aggregate Base per Caltrans Standard Specification, 2018, Section 26: Aggregate Bases, Subsection 26 -1.02A Class 2 Aggregate Base and as specified herein.
200-2.2 Crushed Aggregate Base.
200-2.2.1 General.

ADD the following:

Crushed Aggregate Base shall be free from organic matter and other deleterious substances, and shall be of such nature that it can be compacted readily under watering and rolling to form a firm, stable base.

1. The aggregate shall not be treated with lime, cement or other chemical material before tests are performed.

2. Samples for testing shall represent every 500 cubic yards or one day's production, whichever is smaller. If the results of the aggregate grading tests do not meet the requirements for Percentage Passing Sieve as specified in Table 200-2.2.2, but meet the Quality Requirements as specified in Table 200 -2.2.3, placement of the aggregate base may be continued for the remainder of that day. However, another day's Work may not be started until test results indicate to the satisfaction of the Engineer that the next material to be used in the Work will comply with the requirements specified for Percentage Passing Sieve.

3. If the results of both the aggregate grading and Sand Equivalent tests do not meet the requirements of Section 200-2.2, the aggregate base which is represented by these tests shall be removed. However, if requested by the Contractor, and approved at the sole discretion of the Engineer, the aggregate base may remain in place and the Contractor shall pay to the Agency $50 per cubic yard for such aggregate base left in place. The Agency may deduct this amount from any moneys due, or that may be come due, to the Contractor under the Contract.

ADD 200-2.9 Class 2 Aggregate Base.

Aggregate for Class 2 aggregate base shall be free from organic matter and other deleterious substances, and shall be of such nature that it can be compacted readily under watering and rolling to form a firm, stable base. Aggregate may include material p rocessed from reclaimed asphalt concrete, portland cement concrete, lean concrete base, cement treated base or a combination of any of these materials.

Aggregate shall conform to the grading and quality requirements shown in the following tables.

At the option of the Contractor, the grading for either the 11/2 -inch maximum or 3/4 inch maximum shall be used, except that once a grading is selected it shall not be changed without the Engineer's written approval.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 179 ends

AGGREGATE GRADING REQUIREMENTS

Percentage Passing

11/2" Maximum 3/4" Maximum
_____________________ ________________________
Operating Operating
Sieve Sizes Range Range
2" .................................... 100 —
11/2" ............................... 90-100 —
1" .................................... — 100
3/4" ................................. 50-85 90-100
No. 4 ............................... 25-45 35-60
No. 30 .............................. 10-25 10-30
No. 200 ........................... 2-9 2-9

QUALITY REQUIREMENTS

Operating
Tests Range
Resistance (R-value) 78 Min.

Sand Equivalent 25 Min.

Durability Index 35 Min.

The aggregate shall not be treated with lime, cement or other chemical material before the Durability Index test is performed.

If the results of either or both the aggregate grading and Sand Equivalent tests do not meet the requirements specified for “Operating Range” but meet the “Contract Compliance” requirements, placement of the aggregate base may be continued for the remainder of that day.

However, another day's work may not be started until tests, or other information, indicate to the satisfaction of the Engineer that the next material to be used in the work will comply with the requirements specified for “Operating Range.”
If the results of either or both the aggregate grading and Sand Equivalent tests do not meet the requirements specified for “Contract Compliance,” the ag gregate base which is represented by these tests shall be removed. However, if requested by the Contr actor and ap proved by the Engineer, the aggregate base may remain in place and the Contractor shall pay to the City $2.25 per cubic yard for such aggregate base left in place. The City may deduct this amount from any moneys due, or that may become due, the Contractor under the contract. If both the aggregate grading and Sand Equivalent do not conform to the “Contract Compliance” requirements, only one adjustment shall apply.

No single aggregate grading or Sand Equivalent test shall represent more than 500 cubic yards or one day's production, whichever is smaller.

SECTION 201 – CONCRETE, MORTAR AND RELATED MATERIALS
201-1 PORTLAND CEMENT CONCRETE
TABLE 201-1.1.2 Modify as follows:

TABLE 201-1.1.2

PORTLAND CEMENT CONCRETE

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 180 ends

Type of Construction Concrete Maximum
Class Slump (Inches)
All Concrete Used Within the Right-of-Way 560-C-3250 (1) (2) Trench Backfill Slurry 190-E-400 8”
Street Light Foundations and Survey Monuments 560-C-3250 4” Traffic Signal Foundations 650-CW-4000 4”
Concreted-Rock Erosion Protection 520-C-2500P per Table 300-11.3.2 (1) Except that concrete required to be of higher strength by Table 201 -1.1.2 SSPWC shall be as per Table 201-1.1.2 SSPWC.
(2) As per Table 201-1.1.2 SSPWC.
201-1.2.1 Cement. Substitute the following:
a) Portland Cement. Portland Cement shall be Type II or V Portland cement conforming to ASTM C150 and the optional requirements of ASTM C150, Table 2 for maximum equivalent alkalis (Na2O + 0.658K2O) of 0.60 percent.

ADD 201-1.2.4(f) Integral Colored Concrete.

Integral color shall consist of colored admixtures developed for use in ready mixed concrete. The product shall be made of the highest quality pigments, as well as other ingredients designed to enhance the color and improve the pigment dispersion, workability and finishing performance of the concrete. Integral color pigments shall meet or exceed ASTM -C-979. The coloring method shall be designed for concrete flatwork applications (salt finished, broom finishes, rotary finishes), as well as vertical surfaces, and other types of architectural concrete. Pigment shall be a permanent coloration, uniform throughout the concrete surface and interior, and shall be highly UV and fade resistant.

Integral colored concrete shall be cured with QC Color Cure color matched to the concrete (see product information bulletin). Provide sample panel submittals of all colors to be used in the installation on identical surfaces for approval by Resident Engineer. Contractor shall provide a maintenance schedule for integral colored concrete.

Admixture for all integral colored concrete paving in medians and other integral colored concrete shall be the following:

Color: To match existing color along El Camino Real and as outlined in the Landscape Manual
Curing: Scofield Colorcure Concrete Sealer (or approved equal). See Section 201 of these Supplemental Provisions for Concrete Curing Materials.

Manufacturer: Scofield Chromix Admixtures for color-conditioned concrete, or approved equal L.M. Scofield Company

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 181 ends

6533 Bandini Boulevard
Los Angeles, CA 90040
1-800-800-9900
Admixture products and procedures for installation shall be in strict accordance with the manufacturer’s specifications and recommendations, and those published by the American Concrete Institute (ACI) and the Portland Cement Association (PCA).

ADD 201-1.6 Finish.

To match existing median paving along El Camino Real.

ADD 201-1.7 Miscellaneous Concrete Finishing Products.

ADD 201-1.7.1 Water Base Penetrating Sealer for Integral Colored Concrete. (Scofield Colorcure Concrete Sealer or approved equal)
Water base penetrating sealer shall be a sealer designed for the protection of imprinted and natural concrete.

Water base penetrating sealer shall be a sealer designed for the protection of imprinted, colored and natural concrete, and other masonry surfaces to preserve the natural appearance of the masonry without darkening or adding gloss to the surface. It shall preserve the natural slip resistance of the concrete, etc. Sealer shall repel spills and soils, minimizing staining and maintenance.

Seal shall leave no visible material on the surface and shall be absorbed and locked into the pores of the masonry, repelling liquids and soils but leaving the top surface natural in appearance.

Install per manufacturer’s directions. Seal shall be compat ible with the surfaces and materials which it is applied. Concrete sealer shall conform to the following specifications:

Color: Clear, non-yellowing
Odor: Mild
Flash Point: None (C.O.C. method)
Specific Grav.: 1.03
Density: 8.6 pounds per gallon
Drying Time: 30 minutes to 60 minutes
Cure Time: 24 to 48 hours
VOC Content: None (0 g/l) excluding water
Polymer Type: Proprietary Reactive Resin System
Coverages (approximate):

Smooth Concrete: 300 to 400 square feet per gallon
Rough Concrete: 200 to 300 square feet per gallon
Note: Coverages vary depending on porosity and condition of surface and method of application.

Method of: Airless sprayer.

Application
Manufacturer: Scofield Chromix Admixtures for color-conditioned concrete, or approved equal L.M. Scofield Company
6533 Bandini Boulevard

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 182 ends

Los Angeles, CA 90040
1- 800-800-9900
All materials shall be furnished, prepared, applied, cured, and stored according to the product manufacturer’s direction.

SECTION 203 – BITUMINOUS MATERIALS
203-6 ASPHALT CONCRETE.
203-6.1 General.

Add the following:

Asphalt Concrete (AC) shall be Type III-C3-PG 64-10. No more than 15% RAP shall be used in the AC mix used for patching.

203-6.3 Job Mix Formula (JMF) and Mix Designs.

Add the following:

Asphalt Concrete (AC) shall be Type III-C3-PG 64-10 for both base course and surface course; both of which with Warm Mix Asphalt (WMA) additive technology optional.

No more than 15% RAP is allowed in any AC mixes used for base course or full width overlay.

If the use of WMA additive is desired, the WMA additive used must be on the Caltrans Authorized Material List for WMA authorized technologies in effect as of the date of advertisement of the contract,
https://mets.dot.ca.gov/aml/WarmMixAsphaltTechnologiesList2.php?print=yes. Only additive technologies are acceptable. No foaming or water injection technology shall be used.

A technical representative for the WMA additive technology must attend the Preconstruction Meeting should WMA be used by the Contractor.

203-6.4.4 Composition and Grading.

ADD the following:

Table 203-6.4.4, design criteria, shall be modified per the following table, the gradation shall stay the same:

Table 203-6.4.4 – Modified (Design Criteria)

Sieve Size
Percentage Passing Sieves
A B C1 C2 D1 D2 E F
Dense
Coarse
Dense
Medium
Coarse
Coarse
Medium
Dense
Medium
Coarse
Fine
Dense
Fine
Extra
Fine
Channel
Liner

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 183 ends

1-1/2” (37.5 mm) 100
1” (25 mm) 90-100 100
¾” (19.0 mm) 78-90 87-100 100 100
½” (12.5 mm) 64-78 70-87 90-100 95-100 100 100
3/8” (9.5 mm) 54-68 55-76 72-88 72-88 90-100 95-100 100 100 No. 4 (4.75 mm) 34-48 35-52 40-54 46-60 40-54 58-72 65-85 95-100 No. 8 (2.36 mm) 25-35 22-40 18-34 28-42 20-32 34-48 45-65 70-84 No. 30 (600 µm) 12-22 8-24 8-20 15-27 6-18 18-32 22-38 36-50 No.50 (300 µm) 8-16 5-18 4-14 10-20 2-12 13-23 16-28 23-35 No. 200 (75 µm) 3-6 0-7 1-6 2-7 0-5 2-9 6-12 6-12
Asphalt Binder % 4.5-6.0 4.7-6.5 5.0-6.5 5.0-6.5 5.3-7.0 5.3-7.0 6.0-8.0 8.0-10.0 Hveem Stability
“S Value” (min.)
37 37 35 35 32 32
Air Voids1 4% 4% 4% 4% 4% 4%

203-6.5.1 Class and Grade.

DELETE the list and REPLACE with the following:
a) No suffix if the mixture contains RAP in an amount up to 20 percent. b) "R0" if the mixture does not contain RAP, e.g., "III-C2-PG 64-10-R0." c) "R" and the percentage of RAP if the mixture contains greater than 20 percent, e.g. "III-C2-PG 64-I0-R25."
d) "WMA" if the mixture uses a warm mix asphalt technology, e.g. , "III-C2-PG 64 -10- WMA."

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 184 ends

203-6.5.1 Class and Grade.

DELETE the list and REPLACE with the following:
a) No suffix if the mixture contains RAP in an amount up to 20 percent. b) "R0" if the mixture does not contain RAP, e.g., "Type II-C2-PG 64-10-R0." c) "R" and the percentage of RAP if the mixture contains greater than 20 percent, e.g. "Type II-C2-PG 64-I0-R25."
d) "WMA" if the mixture uses a warm mix asphalt technology, e.g. , "Type II-C2-PG 64- 10-WMA."

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 185 ends

203-6.5.4 Table.

DELETE in its entirety and REPLACE with the following:

CLASS B2 B3
Sieve Size Individual
Test Result
Moving
Average
Individual
Test Result
Moving
Average
1" (25.0 mm) 100 100 100 100
3/4" (19.0 mm) 87-100 90-100 90-100 95-100
3/8" (9.5 mm) 50-80 60-75 60-84 65-80
No. 4 (4.75 mm) 30-60 40-55 40-60 45-60
No. 8 (2.36 mm) 22-44 27-40 24-50 30-45
No. 30 (600 µm) 8-26 12-22 11-29 15-25
No. 200 (75 µm) 1-8 3-6 1-9 3-7
Asphalt Binder %
Air Voids %

4.8-6.5
4%

4.8-6.5
4%
CLASS C2 C3
Sieve Size Individual
Test Result
Moving
Average
Individual
Test Result
Moving
Average
3/4" (19.0 mm) 100 100 100 100
1/2" (12.5 mm) 89 -100 95 -100 89 -100 95 - 100
3/8" (9.5 mm) 70-94 75-90 74 -100 80-95
No. 4 (4.75 mm) 44-72 50-67 50- 78 55-72
No. 8 (2.36 mm) 30-54 35-50 32-60 38-55
No. 30 (600 µm) 10-34 15 - 30 14 - 38 18 - 33
No. 200 (75 µm) 2-10 4-7 2-10 4-8
Asphalt Binder %
Air Voids %

5.0 - 6.8
4%

5.0 - 7.0
4%

CLASS D F
Sieve Sizes Combined Average Combined Average
1/2" (12.5 mm)
3/8" (9.5 mm)
100
95-100
-
100
No. 4 (4.75 mm) 65-85 95-100
No. 8 (2.36 mm) 50-70 70-80
No. 30 (600 µm) 28-40 35-50
No. 200 (75 µm) 5-14 7-16
Asphalt Binder %
Air Voids

6.0-8.0
4%

8.0-10.0

203-6.8 Storage.

DELETE in its entirety and REPLACE with the following:

1. Storage of asphalt concrete shall not be allowed. Asphalt concrete shall be transferred from the mixer by a method that does not cause segregation.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 186 ends

203-6.10 Sampling.

DELETE in its entirety and REPLACE with the following:

1. Aggregate samples for batch plants shall be taken from the hot bins. Aggregate samples for dryer-dr um plants shall be taken in advance of the dryer -drum using devices conforming to 203-6.7.4.2.

2. Evaluation and acceptance of asphalt concrete shall be determined from samples of final asphalt concrete material. In addition to evaluation of the final asphalt material, samples of aggregate, RAP, and asphalt binder shall be taken for testing. In case of dispute between the Contractor and the Agency, the Engineer has the authority to request core samples for analysis from the placed asphalt concrete for any of the acceptance criteria, at the locations determined by the Engineer. All samples shall be taken in accordance with California Test 125, and the following table:

TABLE 203-6.10
Sampling Location
Asphalt Concrete • Trucks, or
• Mat behind the paver
Aggregate • Cold feed belts, or
• Hot bins prior to addition of asphalt binder
RAP • RAP system, or
• RAP feed belts
Asphalt Binder • Asphalt binder supplier, or
• Storage tanks at the plant during
production

3. When behind the paver or core samples of asphalt concrete are to be used for evaluation, sufficient size samples shall be taken to ensure representative and adequate quantity of material for the required testing.

4. When using core samples, the samples must be properly prepared to safeguard against influx of outside contaminates and so that the cut surfaces do not influence the test results.

5. Material samples of the asphalt concrete shall be on a lot basis. A standard lot shall be equal to 1 day’s production or 750 tons, whichever is smaller. The samples and testing results shall be representative of their entire sample lot.
203-6.11 Acceptance.

DELETE in its entirety and REPLACE with the following:

1. Acceptance of asphalt concrete mixtures will be based upon conformance to the gradation, asphalt binder content, air voids, and minimum stability values shown in Table 203-6.4.4. Air void values shall be between 2% and 6%. The asphalt binder content shall be within +/ - 0.4 percent of the OBC shown on the respective job mix formula.

2. Acceptance of Type III asphalt concrete mixtures will be based upon conformance to the gradation, asphalt binder content, air voids, and minimum stability values shown in Tables 203-6.5.4 (A) and 203 -6.5.4 (B). Air void values shall be between 2% and 6%. The asphalt

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 187 ends

binder content shall be within +/ - 0.4 percent of the OBC shown on the respective job mix formula.

3. Should plant gradation test results be unavailable and allowed by the Engineer, gradation may be determined in accordance with ASTM D2172 or by AASHTO T 308 with adherence to the aggregate correction factor therein. In the case of a continued dispute, fina l acceptance of plant produced mixtures may be based upon binder content, stability and air void values.

4. When dissimilar surface course mix characteristics are the result of production and delivery from multiple plants, the Engineer may require production and delivery from only 1 plant during any 1 day of production, unless approved by the Engineer. 203-11 ASPHALT RUBBER HOT MIX (ARHM).
203-11.3 Composition and Grading.

Delete row 10 of TABLE 203-11.3 and REPLACE with the following:

1. Asphalt Rubber Binder, % by Weight of Dry Aggregate1|7.5-8.5 | 7.5-8.8 | 7.8-9 ADD 203-11.10 Acceptance.

1. Acceptance of asphalt rubber hot mixes will be based upon conformance to the gradation, asphalt binder content, air voids, and minimum stability values shown in Table 203 -11.3. Air void values shall be within +/- 2 percent of the targeted value at the optimum binder content (OBC) shown on the respective job mix formula. The asphalt binder content shall be within +/- 0.4 percent of the OBC shown on the respective job mix formula. 203-14 TIRE RUBBER MODIFIED ASPHALT CONCRETE (TRMAC).
203-14.9 Acceptance.

DELETE in its entirety and REPLACE with the following:

1. Acceptance of dense -graded mixtures will be based upon conformance to the gradation, asphalt binder content, air voids, and minimum stability values shown in Table 203-6.4.4. Air void values shall be between 2% and 6%. The asphalt binder content shall be within +/ - 0.4 percent of the OBC shown on the respective job mix formula.

2. Acceptance of gap-graded mixes will be based upon conformance to the gradation, air voids, and minimum stability requirements shown in Table 203-11.3. Air void values shall be within +/- 2 percent of the targeted value at the OBC shown on the respective jo b mix formula.

Acceptance of gap-graded mixes will also be based upon conformance to the asphalt binder content shown in Table 203-14.4.4. The asphalt binder content shall be within +/- 0.4 percent of the OBC shown on the respective job mix formula.

3. Should plant gradation test results be unavailable and allowed by the Engineer, gradation may be determined in accordance with ASTM D2172 or by AASHTO T 308 with adherence to the aggregate correction factor therein. In the case of a continued dispute, fina l acceptance of plant produced mixtures may be based upon binder content, stability, and air void values.

4. When dissimilar surface course mix characteristics are the result of production and delivery from multiple plants, the Engineer may require production and delivery from only 1 plant during any 1 day of production, unless approved by the Engineer.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 188 ends

203-16 Polymer Modified Asphalt Concrete (PMAC).
203-16.1 General.

DELETE in its entirety and REPLACE with the following:

1. PMAC shall be the product of mixing mineral aggregate and up to 15% RAP with polymer modified paving asphalt at a central mixing plant.
203-16.3 Job Mix Formulas and Mix Designs.

ADD the following:

1. Contractor shall submit for approval an asphalt concrete mix design per Greenbook Section 203-6.3. The asphalt concrete mix design method shall be Hveem with the optimal binder content determined by California Test 367. The mix design shall conform to Greenbook Table 203-6.4.4 for gradation, and the above MODIFIED (DESIGN CRITERIA) table. 203-16.4.3 Composition and Grading.

DELETE in its entirety and REPLACE with the following:

1. Composition and grading shall conform to 203-6.4.4.
203-16.9 Acceptance.

DELETE in its entirety and REPLACE with the following:

1. Acceptance of asphalt concrete mixtures will be based upon conformance to the gradation, asphalt binder content, air voids, and minimum stability requirements shown in Table 203 -

6.4.4. Air void values shall be between 2% and 6%. The asphalt binder content shall be within +/- 0.4 percent of the OBC shown on the respective job mix formula.

2. Material samples of the asphalt concrete shall be on a lot basis. A standard lot shall be equal to 1 day’s production or 750 tons, whichever is smaller. The samples and testing results shall be representative of their entire sample lot.

3. Should plant gradation test results be unavailable and allowed by the Engineer, gradation may be determined in accordance with ASTM D2172 or by AASHTO T 308 with adherence to the aggregate correction factor therein. In the case of a continued dispute, fina l acceptance of plant produced mixtures may be based upon binder content, stability, and air void values.

4. When dissimilar surface course mix characteristics are the result of production and delivery from multiple plants, the Engineer may require production and delivery from only 1 plant during any 1 day of production, unless approved by the Engineer.

SECTION 206 – MISCELLANEOUS METAL ITEMS
ADD the following: 206-7 TRAFFIC SIGNS.
206-7.1 Roadside Signs.

1. This Work shall consist of furnishing and installing roadside signs in accordance with details shown on the Plans, the California Sign Specifications and these special provisions.

Permanent and temporary signs shall be free from blemishes that may affect t he serviceability and detract from the general sign color and appearance when viewing during daytime and nighttime from a distance of 25 feet. The face of each finished sign shall be uniform, flat, smooth, and free of defects, scratches, wrinkles, gel, hard spots, streaks, extrusion marks, and air bubbles. The front, back and edges of the sign panels shall be free of

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 189 ends

router chatter marks, burns, sharp edges, loose rivets, delaminated skins, excessive adhesive overspray, and aluminum marks.
206-7.1.2 Sign Identification.

1. The following notation shall be placed on the lower right side of the back of each sign where the notation shall not be blocked by the sign post or frame:

A. PROPERTY OF THE CITY OF CARLSBAD,
B. Name of the sign manufacturer,
C. Month and year of fabrication,
D. Type of retroreflective sheeting, and
E. Manufacturer’s identification and lot number of retroreflective sheeting.

2. The above notation shall be applied directly to the aluminum sign panels in 1/4 -inch upper case letters and numerals by die -stamp and applied by similar method to the fiberglass reinforced plastic signs. Painting, screening, or engraving of the notation will not be allowed.

The notation shall be applied without damaging the finish of the sign. 206-7.1.3 Drawings.

1. Standard signs shall be as per the most recently approved California Sign Specifications. The date of approval shall be the date most closely preceding the date of manufacture of the sign(s) or the date of the “Notice to Proceed” of this Contract, whichever is most recent. 206-7.1.4 Reflective Sheeting.

1. All advisory signs, warning signs and all regulatory signs shall be fabricated with Type IV prismatic sheeting (High Intensity Prismatic or equivalent) or Type IX prismatic cube lens sheeting (Diamond Grade VIP or equivalent) in accordance to ASTM Designation D4956 and conforming to the requirements of these special provisions. 206-7.1.5 Sign Panel.

1. Sign panels shall be fabricated from sheet aluminum in accordance with ASTM Designation B209. Sheet aluminum shall be pretreated in accordance to ASTM Designation B449. The surface of sheet aluminum shall be cleaned, deoxidized, and coated with a light and tightly adherent chromate conversion coating free of powdery residue. The conversion coating shall be Class 2 with a mass between 10 milligrams per square foot. Following the cleaning and coating process, the sheet aluminum shall be protected from exposure to grease, oils, dust, and contaminants. Sheet aluminum shall be free of buckles, warps, dents, cockles, burrs, and defects resulting from fabrication.
206-7.1.6 Mounting Traffic Signs.

1. Traffic signs shall be installed on 10-gage or 12-gage cold-rolled steel perforated tubing posts as shown on San Diego Regional Standard Drawing M-45 or, when the sign area exceeds the maximum area allowed for on that drawing, on multiple 10-gage or 12-gage cold-rolled steel perforated tubing posts. The number of posts shall be determined by the parameters in SDRS Drawing M-45 or as approved by the Engineer. Traffic signs will be provided with back braces and mounting blocks as approved by the Engineer consisting of 10-gage or 12-gage cold-rolled steel perforated tubing when multiple posts are used.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 190 ends

206-7.1.6 Traffic Sign Posts.

1. Posts shall be constructed of 10-gage or 12-gage cold-rolled steel perforated tubing posts as shown on San Diego Regional Standard Drawing M-45.
206-7.2 Temporary Traffic Signs.

1. Temporary traffic signs shall consist of all signs used for the direction, warning, and regulation of vehicle (including bicycle) and pedestrian traffic during the Contractor’s performance of the Work. Temporary traffic signs include both stationary and portable signs. 206-7.2.1 General.

1. This Work shall consist of furnishing and installing temporary signs in accordance with details shown on the Plans, the California Sign Specifications and these special provisions.

Permanent and temporary signs shall be free from blemishes that may affect the serviceability and detract from the general sign color and appearance when viewing during daytime and nighttime from a distance of 25 feet. The face of each finished sign shall be uniform, flat, smooth, and free of defects, scratches, wrinkles, gel, hard spots, streaks, extrusion marks, and air bubbles. The front, back and edges of the sign panels shall be free of router chatter marks, burns, sharp edges, loose rivets, delaminated skins, excessive adhesive overspray, and aluminum marks.
206-7.2.2 Drawings.

1. Standard signs shall be as per the most recently approved California Sign Specifications. The date of approval shall be the date most closely preceding the date of manufacture of the sign(s) or the date of the “Notice to Proceed” of this contract, whichever is most recent. 206-7.2.3 Reflective Sheeting.

1. All advisory signs, warning signs and all regulatory signs shall be fabricated with Type IV prismatic sheeting (High Intensity Prismatic or equivalent) or Type IX prismatic cube lens sheeting (Diamond Grade VIP or equivalent) in accordance to ASTM Designation D4956 and conforming to the requirements of these special provisions. 206-7.2.4 Sign Panel.

1. Sign panels shall be fabricated from sheet aluminum in accordance with ASTM Designation B209. Sheet aluminum shall be pretreated in accordance to ASTM Designation B449. The surface of sheet aluminum shall be cleaned, deoxidized, and coated with a light and tightly adherent chromate conversion coating free of powdery residue. The conversion coating shall be Class 2 with a mass between 10 milligrams per square foot. Following the cleaning and coating process, the sheet aluminum shall be protected from exposure to grease, oils, dust, and contaminants. Sheet aluminum shall be free of buckles, warps, dents, cockles, burrs, and defects resulting from fabrication.
206-7.2.5 Stationary Mounted Temporary Traffic Signs.

1. Stationary mounted temporary traffic signs shall be installed on 10 -gage and 12 -gage cold- rolled steel perforated tubing posts in the same manner shown on the State of California,

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 191 ends

Department of Transportation Standard Plans RS1, RS2, RS3 and RS4 for installation of roadside signs, except as follows:
a) Wood posts shall not be used.
b) Back braces and blocks for sign panels will not be required. c) The height to the bottom of the sign panel above the edge of traveled way shall be at least 2.1 m (7’).
d) Unless otherwise shown on the Plans , traffic signposts shall conform in materials and installation to SDRS D rawing M-45 and shall have 1 post provided for each 0.48 m 2 (5 ft2) of sign area, or the signs may be installed on existing lighting standards when approved by the Engineer.
e) Sign panels mounted on temporary traffic signposts shall conform to the requirements of these special provisions.
206-7.2.6 Temporary Traffic Sign Posts.

1. Posts shall be 10-gage or 12-gage cold-rolled steel perforated tubing used for the support and stabilization of stationary mounted temporary signs. Post size and number of posts shall be as shown on the Plans, except that when stationary mounted signs are installed and the type of sign installation is not shown on the Plans, post size and the number of posts will be determined by the Engineer. Sign panels for stationary mounted signs shall consist of reflective sheeting applied to a sign substrate.
206-7.2.7 Portable Temporary Traffic Signs.

1. Each portable temporary traffic sign shall consist of a base, standard or framework and a sign panel. The units shall be capable of being delivered to the site of use and placed in immediate operation. Sign panels for portable signs shall conform to the re quirements of these special provisions, or shall be cotton drill fabric, flexible industrial nylon fabric, or other approved fabric. Fabric signs shall not be used during the hours of darkness. Size, color, and legend requirements for portable signs shall be as described for stationary mounted sign panels in section 206-7.2 of these special provisions. The height to the bottom of the sign panel above the edge of traveled way shall be at least 0.3 -m (12”). All parts of the sign standard or framework shall be finished with 2 applications of orange enamel which will match the color of the sign panel background. Testing of paint will not be required.

ADD the following: 206-8 LIGHT GAGE STEEL TUBING AND CONNECTORS. 206-8.1 General.

1. This Section pertains to 10-gage and 12-gage cold-rolled steel perforated tubing used for the support and stabilization of signs. All shapes shall have a galvanized finish and shall be cold - roll-formed steel conforming to ASTM Designation A-446, Grade A. Galvanizing shall conform to ASTM A- 525, Designation G -90. Galvanizing shall be performed after all forming and punching operations have been completed. Cold- rolled steel perforated tubing shall be perforated on all 4 faces with 11mm (7/16”) holes on 25 mm (1”) centers.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 192 ends

206-8.2 Tolerances.

1. Wall thickness tolerance shall not exceed +0.28 mm, -0.13 mm (+0.011”, -0.005”). Convexity and concavity measured in the center of the flat side shall not exceed a tolerance of +0.25 mm (+0.010”) applied to the specific size determined at the corner. Strai ghtness tolerance variation shall not exceed 1.6 mm in 1 m (1/16 “ in 3’). Tolerance for corner radius is 4.0mm (5/32”), plus or minus 0.40 mm (1/64“). Weld flash on corner -welded square tubing shall permit 3.60 mm (9/64”) radius gage to be placed in the corner. Using 10 -gage or 12 -gage square tube, consecutive size tubes shall telescope freely for 3.1m (10’). Tolerance on hole size is plus or minus 0.40 mm (1/64“) on a size. Tolerance on hole spacing is plus or minus 3.2 mm in 6.1 m (1/8” in 20’). In addition, for the following specific sizes of light gage steel tubing, dimensional tolerances shall not exceed those listed in tables 206-8.2 (A) and 206-8.2(B).

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 193 ends

TABLE 206 -8.2(A)

LIGHT GAGE STEEL TUBING SIZE TOLERANCE
Nominal Outside
mm
Dimensions
(inches)
Outside Tolerance for
mm
All Sides at Corners
(inches)
25 x 25 (1 x 1) 0.13 0.005
32 x 32 (11/4 x 11/4) 0.15 0.006
38 x 38 (11/2 x 11/2) 0.15 0.006
44 x 44 (13/4 x 13/4) 0.20 0.008
51 x 51 (2 x 2) 0.20 0.008
56 x 56 (23/16 x 23/16) 0.25 0.010
57 x 57 (21/4 x 21/4) 0.25 0.010
64 x 64 (21/2 x 21/2) 0.25 0.010
51 x 76 (2 x 3) 0.25 0.010
TABLE 206 -8.2(B)

LIGHT GAGE STEEL TUBING SQUARENESS OF SIDES AND TWIST
Nominal Outside
mm
Dimension
(Inches)
Squareness(1)
mm

(Inches)
Twist
Permissible
mm(2)
in 900 mm
(3”)
(Inches)(2)
25 x 25 (1 x 1) 0.15 0.006 1.3 0.050
32 x 32 (1-1/4 x 1-1/4) 0.18 0.007 1.3 0.050
38 x 38 (1-1/2 x 1-1/2) 0.20 0.009 1.3 0.050
44 x 44 (1-3/4 x 1-3/4) 0.25 0.010 1.6 0.062
51 x 51 (2 x 2) 0.30 0.012 1.6 0.062
56 x 56 (2-3/16 x 2-3/16) 0.36 0.014 1.6 0.062
57 x 57 (2-1/4 x 2-1/4) 0.36 1.014 1.6 0.062
64 x 64 (2-1/2 x 2-1/2) 0.38 0.015 1.9 0.075
51 x 76 (2 x 3) 0.46 0.018 1.9 0.075
(1) Tubing may have its sides failing to be 90 degrees to each other by the tolerance listed. (2) Twist is measured by holding down the edge of one end of a square tube on a surface plate with the bottom side of the tube parallel to the surface plate, and noting the height that either corner on the opposite end of the bottom side is above the surface plate. 206-8.3 Fasteners.

1. Fasteners used to assemble cold -rolled steel perforated tubing shall be steel “pull -through” electrogalvanized rivets with 9.5 mm (3/8”) diameter shank, 22 mm (7/8”) diameter head, and a grip range of from 5 mm (0.200”) to 0.90 mm (0.356”). The fasteners s hall conform to ASTM B-633, Type III.

ADD 206-9 PORTABLE CHANGEABLE MESSAGE SIGN.
206-9.1 General.

1. Each portable changeable message sign (PCMS) unit shall consist of a controller unit, a power supply, and a structural support system all mounted on a trailer. The PCMS unit shall be

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 194 ends

assembled to form a complete self -contained portable changeable message sign, which can be delivered to the site of the Work and placed in immediate operation. The complete PCMS unit shall be capable of operating in an ambient air temperature range of - 20ºC (-4ºF) to +70ºC (158ºF) and shall not be affected by unauthorized mobile radio transmissions.

2. The trailer shall be equipped so that it can be leveled and plumbed. Full operation height shall be with the bottom of the sign at least 2.1 m (7') above the ground and the top no more than

4.4 m (14.5') above the ground. After initial placement, PCMS shall be moved from location to location as directed by the Engineer
206-9.2 Message Board.

1. The message displayed on the PCMS shall be visible from a distance of 460 m (1500') and shall be legible from a distance of 230 m (750'), at noon on a cloudless day, by persons with vision corrected to 20/20. The sign panel shall be 3 -line matrix and shall display not less than 7 characters per line. Sign messages to be displayed shall be as approved by the Engineer. The sign face shall be flat black and shall be protected from glare of the sun by a method which does not interfere with the clarity of the si gn message. The sign shall be raised and lowered by means of a power driven lifting mechanism. The matrix sign shall be capable of complete alphanumeric selection.

2. Lamp matrix type signs shall be equipped with an automatic dimming operational mode that automatically compensates for the influence of a temporary light source or other abnormal lighting conditions. The sign shall have manual dimming operation modes of 3 or more different lamp intensities.

3. Matrix signs not utilizing lamps shall be either internally or externally illuminated at night.

4. The controller shall be an all solid -state unit containing all the necessary circuitry for the storage of at least 5 pre-programmed messages. The controller shall be installed in a location allowing the operator to perform all functions from 1 position. A keyboard entry system shall be provided to allow an operator to generate an infinite number of additional messages over the pre -programmed stored messages. The keyboard shall be equipped with a security lockout feature to prevent unauthorized use of the controller. The controller shall contain a nonvolatile memory to hold the keyboard created messages in memory during periods when the power is not activated. The controller shall provide for a variable message display rate which allows the operator to match the information display to the speed of the approaching traffic. The flashing off time shall be operator adjustable within the control cabinet. 206-9.3 Operation and Maintenance.

1. PCMS shall be furnished, placed, operated, and maintained at locations shown on the Plans, specified in this section , or designated by the Engineer. The PCMS will be diligently maintained and repaired by the Contractor throughout the Project in accordance with the manufacturer's recommendations. When ownership is transferred to the Agency (at the end of the job), it must be demonstrated to be in good working condition, and meet the provisions of these Specifications, including current registration.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 195 ends

206-9.4 Measurement and Payment.

1. The Contract unit price PCMS shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the Work involved in furnishing, placing, operating, maintaining, repairing, replacing, transporting from location to location, and delivery of the signs to the Agency at the completion of the construction, in good working order, and as directed by the Engineer, and no other compensation will be made. Payment for “PCMS” shall be included in the lump-sum item for “Temporary Traffic Control” SECTION 207 – GRAVITY PIPE
207-2 REINFORCED CONCRETE PIPE (RCP).
207-2.5 Joints.

ADD the following:

1. All RCP joints shall receive a rubber- gasket meeting the requirements of Section 208 -3 Gaskets for Concrete Pipe.
207-2.9 Basis for Acceptance.
207-2.9.1 General.

DELETE in its entirety and REPLACE with the following:

1. The basis for acceptance shall be the D- load bearing strength test, compliance with these Specifications, inspection of the pipe manufacture and inspection of the completed pipe. 207-17 PVC GRAVITY PIPE.
207-17.2.2 Cell Classification
DELETE the first sentence and replace with the following:

1. Pipe shall be made of PVC plastic having a cell classification of 12454 or 12364, as defined in ASTM D1784.
207-17.4.2 Acceptance
DELETE the last sentence and replace with the following:

1. Installation time shall conform to 207-15.6.

ADD 207-17.6 Perforated PVC Pipe.

ADD 207-17.6.1 Materials of Underdrain Pipe.

Perforated plastic pipe shall be smooth-wall PVC plastic pipe or corrugated PVC plastic pipe with a smooth interior surface. All pipes shall comply with 207-17, “PVC GRAVITY PIPE”.

ADD 207-17.6.2 Perforation Requirements
Hole Size 3/8 inch (9 mm) min.

Center to Center
Spacing 5 inches (125 mm) max.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 196 ends

Row of Holes
4 holes per each row and all on the lower half of
the pipe. There shall be 2 holes on each side of
the centerline of the pipe. 1 hole shall be at 45°
from the centerline of the pipe and 1 hole shall
be at 80° from the centerline of the pipe as
indicated on the Drawings.

ADD 207-17.7 Underdrain Cleanout

1. All underdrain cleanout shall conform to 207-17 “PVC GRAVITY PIPE”.

2. Underdrain cleanouts shall have watertight, vandal-proof caps.

ADD 207-17.8 Observation Well

1. All observation wells shall conform to 207-17 “PVC GRAVITY PIPE”.

2. Observation wells shall have watertight, vandal-proof caps.

SECTION 209 – PRESSURE PIPE
209-1 IRON PIPE AND FITTINGS.
209-1.1 Ductile Iron Pipe (DIP).
209.-1.1.1 General
ADD the following:

1. Ductile iron pipe and fittings and installation shall be as shown on the Plans or specified in the Special Provisions and shall conform with the City of Carlsbad Engineering Standards, Volumes 2 and 3.
209-1.1.2 Materials.

DELETE entirely and replace with the following:

1. Unless otherwise specified, ductile iron pipe shall conform to the following:

TABLE 209 -1.1.2
Item Material Reference Specification/Requirements
Pipe Manufacturing
Standards
Conform to AWWA C151/ANSI 21.5 for 3”-64” (75
mm – 1600 mm) pipe.

Design Standards Conform to AWWA C150/ANSI A21.50 and AWWA M41.

NSF Certification NSF 61 certification required for potable water pipe.

Material Ductile iron.

Size As shown on the Plans.

Minimum Wall
Thickness
3”-12” (75 mm – 300 mm)
pipe
Pressure Class 350.
14” – 36” (350 mm – 900
mm) pipe
Pressure Class 250.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 197 ends

Item Material Reference Specification/Requirements
42” – 64” (1050 mm –
1600 mm) pipe
Pressure Class 200.

Pipe with threaded flanges Per AWWA C115/ANSI

21.15. Pipe with grooved
couplings
Thickness Class 53.

Markings Conform to AWWA C151 Section 4.6.

Lengths 18’ or 20’ (5.5 m or 6.1 m) lengths per AWWA
C151/ANSI A21.51.

Shorter lengths may be used to facilitate curves or
fit horizontal or vertical alignment.

Interior Lining
and Exterior
Coating
Buried Exterior
Coatings
Shop coat with 1 prime coat of asphaltic coating
approximately 1 mil (25 µm) thick per AWWA C151.

Exterior Coatings on
Pipe Above Ground
and in Vaults
Conform to 212-12.

Cement-Mortar
Interior Lining
(AWWA C104
“Double Thickness”
Pipe Size Lining Thickness
3” – 12” (75 mm – 300
mm) pipe
1/8” (3 mm)
14” – 24” (350 mm – 0600
mm) pipe
3/16” (5 mm)
30” – 64” (900 mm – 1600
mm) pipe
1/4” (6 mm)
Conform to AWWA C104 using Type II cement
Fusion-Bonded
Epoxy Interior Lining
where shown on the
Plans
Conform to 212-12.

Ceramic Epoxy
Interior Lining,
where shown on the
Plans
Amine cured novalac epoxy lining.

Permeability rating of 0.00.

Abrasion resistance < 4 mils (100 µm) loss after
1,000,000 cycles on ± 22.5° sliding aggregate slurry
abrasion test using a sharp natural siliceous gravel
with particle size between 2 mm and 10 mm.

Joints Standard Push-on
Style
AWWA C111/ANSI 21.11
Mechanical Joint AWWA C111/ANSI 21.11
Flange (threaded) AWWA C115/ANSI 21.15
Restrained Style Special push-on type joint providing longitudinal restraint to full test pressure without relying on
thrust block.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 198 ends

Item Material Reference Specification/Requirements
Boltless, restrained push-on joint design with
positive axial locking restrained system capable of
deflection after assembly.

Use 1 type of restrained joint exclusively for all
Work.

Bell Joint
Gaskets
Material Conform to AWWA C111-ANSI A21.11.

Vulcanized styrene butadiene rubber (SBR).

Material for
Hydrocarbon
Applications and
Contaminated Soils
NBR (Nitrile) (acrylonitrile butadiene), FLUOREL, or
FKM (Viton) (fluorocarbon).

Gasket Age < 180 Calendar Days old or > 2 years old but retested < 60 Calendar Days prior to installation
Flange Gaskets Material 212-2.7.

Fittings Material Ductile iron.

Standards Conform to AWWA C110/ANSI 21.10 or AWWA
C153/ANSI A21.53.

Style Push-on (standard) with restrained joint (as shown), or flanged. Mechanical joint with special approval.

Marking Cast letters “DI” or “DUCTILE” into fittings, unless otherwise specified.

Cast “AWWA C110” or “AWWA C153” depending
on thickness.

Exterior Coatings Use same coating as adjacent pipe, as specified above.

Interior Linings Use same lining as adjacent pipe, as specified above.

Ductile Iron
Pipe Joint
Restraints
Material Ductile iron.

Style Gripping wedge
Design Pressure
Rating
3” – 16” (75 mm – 400
mm)
350 psi (2.4 MPa)
18” – 64” (450 mm – 1600
mm)
250 psi (1.7 MPa)
Pipe Shop Coat Prime Coat 12 mils (300 µm) MDFT.

Polyethylene
PE Encasement
Polyethylene Film
and Tape
Conform to 212-12.1.1.

Color per 212-12.2
Alternate to
Polyethylene
Encasement
Pipe Finish Coat 15 mils (375 µm) MDFT field-applied bitumastic coating.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 199 ends

209-2 STEEL PIPE AND FITTINGS.
209-2.1 General.

ADD the following:

1. Steel pipe and fittings and installation shall conform with the City of Carlsbad Engineering Standards, Volumes 2 and 3.
209-2.3 Mill-Type Steel Pipe.
209-2.3.1 Materials.

DELETE entirely and replace with the following:

1. Unless otherwise specified, mill-type steel pipe shall conform to the following:

TABLE 209 -2.3.1
Item Material Reference Specification/Requirements
Pipe Manufacturing
Standards
Furnace-welded, electrically welded or seamless pipe
conforming to AWWA C200 for pipe 6” (150 mm) and
larger or ANSI B36.10 for pipe smaller than 6” (150 mm) or for pipe with wall thickness specified by strength or schedule on the Plans.

Design
Standards
Conform to AWWA M11.

NSF
Certification
NSF 61 certification required for potable water pipe.

Material ASTM A53 Grade A or B, ASTM A134 (steel plate per ASTM A283 Grades C or D or A36), ASTM A135, or ASTM
A139.

Size As shown on Plans.

Conform to dimensional tolerances of AWWA C200 for
pipe ≥ 6” (150 mm) identified on the Plans by class,
gauge or decimal wall thickness.

Conform to ANSI B36.10 for pipe > 6” (150 mm) or for
pipe specified on the Plans by strength or wall-thickness schedule.

Minimum Wall
Thickness
Where the Plans do not show thickness, submit design
and supporting calculations prepared by the
manufacturer in accordance with AWWA M11 using a
maximum design working stress of 1/2 the yield stress
for the grade of steel used in pipe fabrication. Compute wall thickness using pressure equal to 250 psi (1.72
MPa) or the design pressure shown on the Plans plus 50
psi, whichever is greater.

No pipe 4” (100 mm) and larger outside buildings or
vaults shall have a wall thickness less than 14 -gauge
(1.9 mm)

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 200 ends

Item Material Reference Specification/Requirements
No pipe 4” (100 mm) and larger inside buildings or
vaults shall have a wall thickness less than 3/8” (9.5
mm).

Markings Mark each special and each length of straight pipe at bell end to identify:
• Manufacturer’s name or mark
• Type of steel
• Design pressure
• Diameter and weight of pipe or special
• Proper location of pipe or special by reference
to layout schedule
Lengths Furnish in single random lengths, double random lengths, or in specified cut lengths.

For single random lengths, average length shall not be
less than 17.5’ (5.3 m) and no piece shall be shorter
than 9’ (2.7 m).

For double random lengths average length shall not be
less than 35’ (10.7 m), not less than 10^ of pieces shall be shorter than 26.25’ (8.0 m) and no piece shall be
shorter than 14’ (2.7 m).

For specified cut lengths, the actual pipe length shall not vary from the specified length by more than 1/8” (3 mm).

Interior
Lining and
Exterior
Coating
(Required
on exposed
steel
surfaces and
ring joints)
Cement-
Mortar Interior
Lining and
Exterior
Coating
Conform to AWWA C205 and AWWA C602 using Type
II/V cement.

Trim mortar lining as necessary to allow full operation of butterfly or check valves at connections to steel pipe.

Line exposed portions of pipe interior with hand -
applied epoxy conforming to 212-12.
3/4” (19 mm) min coating thickness unless otherwise
shown or soil is identified as corrosive.

Trim coating 6” to 12” (150 mm to 300 mm) above
grade on spools penetrating to daylight or vault
interiors.

Cold-Applied
Tape Exterior
Coatings
Conform to AWWA C209 for the exterior of specials,
connections, and fittings.

Conform to AWWA C214 for steel pipeline coatings.

Liquid Epoxy
Interior Lining
and Exterior
Coating of
Conform to AWWA C210 and 212-12.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 201 ends

Item Material Reference Specification/Requirements
Above-Ground
Pipe
Fusion-Bonded
Epoxy Interior
Lining and
Exterior
Coating of
Above-Ground
Pipe
Conform to AWWA C213 and 212-12.

Extruded
Polyolefin
Exterior
Coatings
Conform to AWWA C215 for extruded coatings.

Conform to AWWA C216 for heat -shrinkable cross -
linked coatings.

Joints Ends Prepared
for
Mechanical-
Coupled Field
Joints
Conform to AWWA C200 Section 4.13.

Square cut or beveled with no burrs. Outside surfaces
where coupling seats shall be free of indentations,
projections, or roll marks to ensure watertight seal.

Pipe ends shall have the tolerances within limits
required by the mechanical coupling manufacturer.

Field-Butt-
Welded Joints
Pipe with wall thickness 15/64” (6.0 mm) or greater,
intended for field butt welding. Bevel pipe on outside, inside or both sides as shown or specified. Bevel angle shall be 30 to 35 degrees measured from plane
perpendicular to pipe axis. Width of root face at pipe
end shall be 1/32” to 3/32” (0.8 mm to 2.3 mm)
Flanged Joint Forged steel conforming to ASTM A181 Faced and dimensioned in accordance with ASME/ANSI B16.5 for
the pressure class shown on the Plants or specified in
the Special Provisions.

Threads for screwed flanges and companion pipe ends
shall conform to ASME/ANSI B1.20.1.

Pipe ends for welding neck flanges shall be beveled.

Flange
Gaskets
Material 212-2.7
Fittings Material Same steel as pipe.

Standards Manufacture from mill -type steel pipe in accordance with ASME/ANSI B16.9.

Exterior
Coatings
Use same coating as adjacent pipe, as specified above.

Interior Linings Use same lining as adjacent pipe, as specified above.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 202 ends

209-4 PVC PRESSURE PIPE.
209-4.1 General.

ADD the following:

1. PVC pipe and fittings and installation shall conform with the City of Carlsbad Engineering Standards, Volumes 2 and 3.
209-4.2 Materials.

DELETE entirely and replace with the following:

1. Unless otherwise specified, PVC pressure pipe shall conform to the following:

TABLE 209-4.2
Item Material Reference Specification/Requirements
Pipe Manufacturing
Standards
Conform to AWWA C900 for pipe 4” – 60” (100 mm – 1,500
mm).

Design
Standards
Conform to AWWA M23 using hydraulic design basis
below.

NSF
Certification
NSF 61 certification required for potable water pipe.

Material Virgin rigid poly-vinyl-chloride.

Conform to ASTM D1784 Cell Class 12454B or better.

Conform to NSF 13.

Conform to AWWA C900 Section 4.2.

Markings (each
pipe)
Conform to AWWA C900 Section 6.1.

Mark applicable AWWA standard.

Show nominal pipe diameter.

Show AWWA pressure class or DR.

Show NSF 61 stamp (for potable water service).

Show manufacturer and manufacturing date code.

Size As shown on the Plans.

Conform to outside diameter of ductile iron pipe unless otherwise shown.

Minimum Wall
Thickness
(Dimension
Ratio)
Design Pressure and Diameter
Shown on the Plans
Minimum Dimension
Ratio
0-100 psi (.7 MPa)
4” – 16” (100 mm – 400 mm)
DR 18 (Class 235)
100-200 psi (1.0 MPa)
4” – 16” (100 mm – 400 mm)
DR 14 (Class 305)
Greater than 200 psi (1.4 MPa) or
greater than 16”
Use DIP or Steel Pipe
Pipe with Grooved Couplings Use DIP or Steel Pipe
Lengths Laying lengths shall be 20’ with option to supply up to 15% random (minimum length 10’) sections

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 203 ends

Item Material Reference Specification/Requirements
Joints Standard Push -
on Style
Conform to ASTM D3139.

Bell Joint
Gaskets
Material Elastomeric membrane per AWWA C900 Section 4.2.4 (Gaskets and Lubricants) and ASTM F477.

Butadiene styrene (SBR or BR) for potable water.

Ethylene propylene (EPM or EPDM) for recycled water.

Material for
Hydrocarbon
Applications
and
Contaminated
Soils
Elastomeric membrane per AWWA C900 Section 4.2.4
(Gaskets and Lubricants) and ASTM F477.

NBR (Nitrile) (acrylonitrile butadiene), FLUOREL or FKM (Viton) (fluorocarbon).

Gasket Age < 180 Calendar Days old or
< 2 years old but retested < 60 Calendar Days prior to
installation
Fittings Material Ductile iron.

Standards Conform to AWWA C110/ANSI 21.10 or AWWA C153/ANSI A21.53.

Style Push-on (standard) or restrained joint (as shown).

Marking Cast letters “DI” or “DUCTILE” into fittings, unless otherwise specified.

Exterior
Coatings
1 mil (25 µm) petroleum asphaltic coating.

Interior Linings Cement mortar (double thickness).

Plastic Film
Wrap for
Corrosion
Protection
Conform to 212-12.1.1.

Color per 212-12.2.
209-5 HIGH-DENSITY POLYETHYLENE (HDPE) SOLID WALL PRESSURE PIPE. 209-5.1 General.

ADD the following:

1. HDPE pipe and fittings and installation shall conform with the City of Carlsbad Engineering Standards, Volumes 2 and 3.
209-5.2 Materials.

DELETE in its entirety and replace with the following:

1. Unless otherwise specified, HDPE pressure pipe shall conform to the following.

TABLE 209-5.2
Item Material Reference Specification/Requirements
Pipe Manufacturing
Standards
Conform to AWWA C901 for pipe 1/2” – 3” (12.5 mm – 75
mm).

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 204 ends

Item Material Reference Specification/Requirements
(Potable
Water Pipe)
Conform to AWWA C906 for pipe 4” – 63” (100 mm – 1575
mm).

Manufacturing
Standards
(Non-Potable
Water Pipe)
Conform to ASTM F714
Design
Standards
Conform to AWWA M55.

NSF
Certification
NSF 61 certification required for potable water pipe.

Material ASTM D3350 PE 4710 Cell classification 4454 or higher.

Conform to AWWA C901 Section 4.2 or AWWA C906
Section 4.2 as appropriate.

Markings
(each pipe)
Conform to AWWA C901 or C906 Section 6.1.

Mark applicable AWWA standard.

Show nominal pipe diameter.

Show standard material code designation.

Show AWWA pressure class or DR.

Show NSF 61 stamp (for potable water service).

Show manufacturer and manufacturing date code.

Size 1-1/4” – 63” (32 mm – 1575 mm) diameter as shown on the Plans.

Ductile iron pipe size (DIPS) outside diameter for pipe 4” – 48” (100 mm – 1200 mm) unless otherwise shown.

Iron pipe size (IPS) outside diameter for pipe ≤ 4” (100 mm) or > 48” (1200 mm).

Minimum Wall
Thickness
(Dimension
Ratio)
Design Pressure Shown on the
Plans
Minimum Dimension
Ratio
0-80 psi (0.6 MPa) DR 21
80-100 psi (0.7 MPa) DR 17
100-150 psi (1.0 MPa) DR 11
150-200 psi (1.4 MPa) DR 9
Greater than 200 psi Use ductile iron or
steel
Joints Style Thermal butt fusion for joining pipe in accordance with the manufacturer’s recommendations.

Flanged for connections to appurtenances and other pipe materials in accordance with manufacturer’s
recommendations.

Flange Back -
up Ring
Provide flange back -up ring of Type 316 SS or fusion
bonded epoxy coated ductile iron.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 205 ends

Item Material Reference Specification/Requirements
Design
Pressure
Match design pressure rating of pipe shown on the Plans.

Fusion
Fittings
Standards ASTM D2683 socket -type, ASTM D3261 butt -type, or ASTM F1055 electrofusion (fittings shall be marked as
complying).

Material HDPE conforming to pipe specifications.

Pressure
Rating
De-rated pressure of fitting shall meet or exceed design pressure rating of pipe shown on the Plans.

Adaptor
Fittings (For
Connections
to Flanged
Fittings)
Internal
Stiffener Ring
Required for mechanical joint connections.

Backup Ring Stainless steel.

Thrust
Restraint.

HDPE in -line wall anchors and thrust blocks and per
manufacturer’s requirements.
209-7 PIPELINE IDENTIFICATION.
209-7.2 Requirements.

DELETE in its entirety and replace with the following:

1. Pipeline identification shall conform to the following:

TABLE 209-7.2
Function Type Materials/Method
Pipe Contents
Identification
Pipe Color
(Plastic Pipe
or Polywrap)
Blue for Potable Water.

Purple for Recycled Water.

Green for Sewage.

AND
Stenciling Stenciling marked on pipe in contrasting color to background color of pipe stating:
“POTABLE WATER,”
“CAUTION RECYCLED WATER – DO NOT DRINK” or ”CAUTION
SEWER” as appropriate.
5/8” (16 mm) high letters.

Repeated at 1 foot (300 mm) intervals.

OR
Identification
Tape
Polyethylene tape 6” (150 mm) wide and 4 mils (100 µm)
minimum thickness with 2” (50 mm) high letters stating:
“POTABLE WATER ,” “CAUTION RECYCLED WATER – DO NOT
DRINK” or “CAUTION SEWER” as appropriate.

For pipe > 12” (300 mm) diameter, use 12” (300 mm) wide tape.

Color – Blue with black or white letters for potable water, Purple with black or white letters for recycled water,
Green with black or white letters for sewage.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 206 ends

Function Type Materials/Method
Attached to top of pipe with adhesive tape.

Pipe Warning
and Locating
Warning and
Locating
Tape
Polyethylene tape 6” (150 mm) wide and 4 mils (100 µm)
minimum thickness with 2” (50 mm) high letters stating:
“CAUTION: WATERLINE BURIED BELOW ,” “CAUTION:

RECLAIMED WATERLINE BURIED BELOW – DO NOT DRINK,” or
“CAUTION: SEWER BURIED BELOW” as appropriate.

For pipe > 12” (300 mm) diameter, use 12” (300 mm) wide tape.

Color – blue with black or white letters for potable water, Purple with black or white letters for recycled water,
Green with black or white letters for sewage.

Place in pipe trench 18” (450 mm) above pipe.

Tape shall contain metallic strip that can be registered by magnetic field locating device.

OR
Locating
Wire
In lieu of installing metallic warning tape; non -metallic warning tape 18” (450 mm) above pipe and 10 -guage copper wire attached to top of pipe and accessibly terminated may be used.

SECTION 211 – MATERIAL TESTS

211-6 RAP CORRECTION FACTOR.
211-6.1 General.

DELETE in its entirety and REPLACE with the following:

1. A RAP correction factor must be determined for asphalt concrete mixtures containing greater than 20 percent RAP. The RAP correction factor shall be determined in accordance with Caltrans Lab Procedure LP-9 dated May 22, 2006. This factor shall be used in determining the combined gradation of the virgin aggregates and RAP.

SECTION 212 – WATER AND SEWER SYSTEM VALVES AND APPURTENANCES 212-1 GENERAL.
212-1.2 Products Conveying Potable Water
DELETE b) and REPLACE with the following:
b) have an interior lining listed as complying with NSF 61 and certified to be holiday-free 212-2 FLANGED AND THREADED CONNECTIONS.
212-2.8.2 Insulation of Threaded Connections.

DELETE in its entirety and REPLACE with the following:

1. Threaded insulating bushings, couplings or unions shall be furnished and installed where dissimilar threaded piping materials are joined.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 207 ends

212-3 PIPE HANGERS AND SUPPORTS, CASINGS SPACERS, AND WALL PENETRATIONS. 212-3.4 Rubber Annular Hydrostatic Sealing Devices.
212-3.4.1 General.

DELETE the last sentence and REPLACE with the following:

1. The sealing device shall be capable of sealing a minimum hydrostatic pressure of 20 psi. 212-5 VALVES.
212-5.5.1.2 Materials.

DELETE TABLE 212-5.5.1.2 in its entirety and REPLACE with the following:

TABLE 212-5.5.1.2
Item Option Reference
Specification/Requirements
Body and Cover Ductile Iron or ASTM A536 Grade 65-45-12.

Body and Cover for
Pressures over 250 psi
(1.7 MPa)
Ductile Iron ASTM A536 Grade 65-45-12.

Disc and Disc Arm Ductile Iron ASTM A536 Grade 65-45-12.

Seat SAE Type 316 Stainless Steel ASTMA276.

Pivot Shaft SAE Type 316 Stainless Steel ASTMA276.
212-10 SERVICE LATERALS, METERS, AND METER BOXES.
212-10.3 Corporation Stops, Angle Meter Valves, Service Saddles and Other Service Materials.

DELETE the last sentence of the first paragraph and REPLACE with the following:

1. Unless otherwise shown on the Plans or specified in the Special Provisions, service saddles and corporation stop inlets shall be threaded per NPT tapered per ANSI B1.20.1.

ADD the following: 212-13 TRACER WIRE FOR NON-METALLIC PIPE. 212-13.1 General.

1. Tracer wire shall conform to the following:
a) Conductor: Minimum 10 AWG, copper clad steel or solid copper (direct burial) or 8 AWG, copper clad steel (directional drilling), rated for 30 volts. b) Break load: minimum 600-lb (direct burial); 2,500-lb (directional drilling) c) Insulation: High Molecular Weight Polyethylene (HMWPE), minimum 30 -mil (direct burial); 45-mil (directional drilling). Color per the APWA uniform color code. d) Splices and connectors: For direct burial only, moisture displacement and corrosion proof, direct bury splice kits, UL rated for 600 volts.

SECTION 213 – ENGINEERING GEOSYNTHETICS
Add the following section:

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 208 ends

213-5.1 General.

Geotextile types shall be used for the applications listed in Table 213-5.1 Table 213-5.1

GEOTEXTILE APPLICATIONS

Application of Geotextile
Type Designation
Separation of Soil and Street Structural Section 90WS
Separation of Soil and Subsurface Aggregate Drain 180N
Reinforcement of Street Structural Section 200WS
Remediation and Separation of Soil 270WS
Reinforcement of Soil 270WS
Drainage at the Interface of Soil Structures N/A
Drainage at the Interface of Soil and Structures N/A
Rock Slope Protection Fabric for Rock Sizes Below ¼ Ton 180N Rock Slope Protection Fabric for Rock Sizes Including and Above ¼ Ton 250N Plant Protection Covering 90N
Erosion Control Fence with 14 AWG - 6”x6” Wire and 10’ Post Spacing 90WS Erosion Control Fence with 6’ Post Spacing and No Wire Fencing 200WS

Add the following section:
213-5.2 Gravel bags.

Gravel bags for the use of temporary erosion control shall be burlap type, filled with no less than 23kg (50 lbs) of 19 mm (3/4“) crushed rock and securely tied closed. Plastic bags are not acceptable. SECTION 216 – PRECAST REINFORCED CONCRETE BOX 216-4 TESTING REQUIREMENTS.
216-4.2.2 Acceptance.

DELETE the first paragraph and REPLACE with the following:

1. When the average compressive strength of all cylinders tested is equal to or greater than the specified compressive strength of the PCC, and not more than 10 percent of the cylinders tested have an average compressive strength less than 90 percent of the s pecified compressive strength, and no cylinder tested has a compressive strength less than 85 percent of the specified compressive strength, the lot will be accepted.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 209 ends

SECTION 217 – BEDDING AND BACKFILL MATERIALS
217-1 BEDDING MATERIAL.
217-1.1 General.

ADD the following:

1. Bedding for pipe lines of any material shall conform with the City of Carlsbad Engineering Standards, Volumes 2 and 3.
217-2 TRENCH BACKFILL.
217-2.1 General.

DELETE TABLE 217-2.1 and replace with the following:

TABLE 217-2.1
Zone Zone Limits Maximum Rock
Size
(greatest
dimension)
Sand Equivalent
(Excluding Rock)
Backfill Zone From subgrade to
12” (300 mm) above
top of pipe or
conduit
4” (150 mm) Not less than 20 unless
otherwise shown on
the Plans or specified in
the Special Provisions.

ADD SECTION 218 - FENCING
ADD 218-1 TEMPORARY HIGH VISIBILTY FENCING
ADD 218-1.1 Materials.

Temporary high -visibility fence (THVF) shall be minimum 4’ high, orange colored plastic construction fencing installed prior to performing any work. THVF shall be constructed of non - toxic, non-conductive polyethylene capable of withstanding temperatures from –58F degrees to 194F degrees. Color shall be non-fading. Posts shall be 6’-6” long, shall be spaced no more than 10’-0” apart and buried portion shall be no less than 2’-6” deep. Used materials may be installed providing the used materials are good, sound, and are suitable for the purpos e intended, as determined by the Engineer. Materials may be commercial quality providing the dimensions and sizes of the materials are equal to, or greater than, the dimensions and sizes specified herein.

Posts shall be either metal or wood at the Contractor's option. Galvanizing and painting of steel items will not be required. Treating wood with wood preservatives will not be required. Concrete footings for metal posts will not be required.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 210 ends

PART 3 CONSTRUCTION METHODS
SECTION 300 – EARTHWORK
300-1 CLEANING AND GRUBBING.
300-1.1 General.

Add the following:

Also included in clearing and grubbing shall be removal and disposal of existing street poles and lights, metal guard rail, fences, retaining walls, asphalt concrete and aggregate base, asphalt dike, concrete curb and gutter, concrete sidewalk, existing gate, e xisting headwalls, rip -rap, traffic signs, sawcutting, and other existing features which interfere with the work. Whether or not such items are shown on the plans they shall be removed as a part of clearing and grubbing. Existing underground pipes and conduits that are shown on the plans and designated to be removed shall be removed by the Contractor as a part of clearing and grubbing.

DELETE 300-1.2 Root Pruning and Tree Trimming.
300-1.3 Measurement.

DELETE in its entirety and REPLACE with the following:

1. Clearing and grubbing, if measured for payment, will be measured by the acre or lump sum. 300-1.4 Payment.

DELETE the second sentence.
300-2 UNCLASSIFIED EXCAVATION.
300-2.1 General.

Add the following:

Unclassified excavation shall include removal and stockpile of suitable material, recompaction, mixing, grading for mitigation work, trenching and backfilling of storm drains, sewers, other utilities, disposal of unsuitable materials not included in the bi d item for clearing and grubbing, all cut and fill including removal and recompaction of unsuitable soil, salvaging clean excavated material and filling areas to the required grades and cross section. Unclassified excavation shall be utilized onsite to mak e all fills shown on the plans. Unclassified excavation shall also include scarification and moisture adjustment and compaction of the top 600 mm (2’) of the subgrade in the roadway prism in cut areas to 95 percent relative compaction, wetland mitigation g rading and attendant work, export of remaining excess material to a disposal site or spoil area acquired by the Contractor and pumping and disposal of storm and ground water. 300-3 STRUCTURE EXCAVATION AND BACKFILL.
300-3.1 General.

Add the following:

The Contractor shall excavate to the lines and levels required and/or shown on the Drawings. The Contractor shall provide all temporary shoring, bracing, cribbing, pumping, and planking required. The Contractor shall excavate and maintain the bottom of all trenches in a condition

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 211 ends

that is level, firm, clean and free from all debris or foreign matter. Excavations shall be kept free from water at all times. The Contractor shall remove any unsuitable material encountered below grade as shown on the plans and as directed by the Engineer. Replace the material with Class 2 AB and compact it as specified for structure backfill in section 19-3.03E, Structure Backfill,” of the State of California Department of Transportation Standard Specifications. The relative compaction must be at least 95 percent.
300-4 UNCLASSIFIED FILL.
300-4.10 Payment.

Replace with the following:

Unclassified fill, grading, shaping, compacting or consolidating, slope rounding, construction of transitions, and all work included in Section 300 -4 shall be included as an incidental to the payment for unclassified excavation and no additional compensation will be made therefore.

300-9 GEOTEXTILES FOR EROSION CONTROL.

ADD 309-9.2 General.

The Contractor shall provide erosion control and water pollution control conforming to the requirements shown on the plans, as specified herein, and as elsewhere required by the Contract Documents. Erosion control and water pollution control shall include the work specified herein, and such additional m easures, as may be directed by the Engineer, to meet Best Management Practices, as defined herein, and to properly control erosion and storm water damage of the limits of work and construction impacts upon areas receiving drainage flows from within the limits of work.

ADD 309-9.2.1 Grading Controls.

The Contractor shall protect all areas that have been graded and/or cleared and grubbed as well as areas that have not been graded and/or cleared and grubbed within the limits of work from erosion. The Contractor shall provide temporary earth berms, gravel bags, silt fences, stabilized construction entrances, fiber rolls, inlet protection, hydraulic mulch, street sweeping, concrete washouts, and similar measures, coordinated with its construction procedures, as necessary and as shown on the plans to control on site and off site erosion during the construction period. The Contractor will be required to protect areas which have been cleared and grubbed prior to excavation or embankment operations, and which are subject to runoff during the duration of the contract. The criteria used to determine the appropriate erosion control measures shall be the “Best Management Practices”, hereinafter BMP, defined and described in the, "Stormwater Best Management Practices Handbook, Construction", Latest edition as publis hed by the California Stormwater Quality Association. The Contractor shall maintain a copy of the "Stormwater Best Management Practices Handbook, Construction", Latest edition on the project site and shall conduct its operations in conformity to said Handbook.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 212 ends

Temporary erosion control measures provided by the Contractor shall include, but not be limited to, the following:
a) Embankment areas, while being brought up to grade and during periods of completion prior to final roadbed construction, shall be graded so as to direct runoff into impoundment areas within the limits of work where such runoff shall have pollutants removed by BMP methods . b) The Contractor shall provide protection by BMP measures to eliminate erosion and the siltation of downstream facilities and adjacent areas. These measures shall include, but shall not be limited to: temporary down drains, either in the form of pipes or pav ed ditches with protected outfall berms; graded berms around areas to eliminate erosion of embankment slopes by surface runoff; confined ponding areas to desilt runoff; and to desilt runoff.

Excavation areas, while being brought to grade, shall be protected from erosion and the resulting siltation of downstream facilities and adjacent areas by the use of BMP measures. These measures shall include, but shall not be limited to, methods shown on the plans and described herein.

SECTION 301 - SUBGRADE PREPARATION, TREATED MATERIALS AND PLACEMENT OF BASE

MATERIALS
301-1 SUBGRADE PREPARATION.
301-1.2 Preparation of Subgrade.

Modify the second and third paragraphs as follows: Change each instance reading “6 inches (150mm)” to “12 inches (300 mm)”.
301-1.3 Relative Compaction.

Delete the first paragraph and substitute the following: The Contractor shall compact the upper 12” (300 mm) of subgrade beneath areas to be paved, have base or subbase material placed on them (including pipelines), or curb, gutter, curb and g utter, alley pavement, driveway, sidewalk constructed over them, to no less than 95 percent maximum dry density as determined by ASTM test D-1557-12.
301-1.7 Payment.

Modify the first paragraph as follows: Payment for subgrade preparation shall be incidental to the contract bid price for which the subgrade is prepared and shall include all labor, materials; including water, operations and equipment to scarify, adjust moisture, compact or recompact the subgrade, both in cut areas and in fill areas, and no further compensation will be allowed.

SECTION 302 - ROADWAY SURFACING
ADD the following: 302-1 GENERAL.
302-1.1 Vegetation Treatment.

1. The Contractor shall treat all vegetation within the limits of the paved area to be surfaced with a n herbicide that complies with the City’s Integrated Pest Management program.

Herbicide shall be applied at least 2 Working Days prior to surfacing the street. Allowance for

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 213 ends

the 2-day period shall be shown in the schedule required per section 6 -1. Payment for pavement surfacing shall include tree trimming and herbicide treatment of the areas to be surfaced and no extra payment will be made for tree trimming and herbicide treatment. 302-1.2 Coordination.

1. The Contractor shall schedule the Work so as to prevent damage by all traffic. The Contractor shall not schedule Work so as to conflict with trash pickup. The trash hauling schedule can be obtained by calling Republic Services at (760) 332 -6464. At least 2 weeks prior to Work, Contractor shall send, by first class mail, notification letters to all property addresses within 500-feet of the Work. Obtaining the appropriate addresses shall be the Contractor’s responsibility. A sample letter may be provided by the Agency to be used as an example. The letter should provide the name of the Contractor and a 24-hour phone number for residents to call if they have any issues or questions.

2. During operations, the Contractor’s schedule for resurfacing shall be designed to provide residents and business owners sufficient paved parking within an 800-foot distance from their homes or businesses.

3. Seventy-two hours prior to the start of any construction in the public right-of-way that affects vehicular traffic and/or parking or pedestrian routes, the Contractor shall give written notification of the impending disruption. For a full street closure, a ll residences and/or businesses on the affected street or alley shall be notified. For partial street closures, or curb, sidewalk and driveway repairs, the residences and/or businesses directly affected by the Work shall be notified.

4. The Contractor shall deliver the notification which shall state the date and time the Work will begin and its anticipated duration. The notification shall list 2 telephone numbers that may be called to obtain additional information. One number shall be the Contractor’s permanent office or field office and the other number shall be a 24 -hour number answered by a representative of the Contractor who is knowledgeable about the Project. At least 1 of the phone numbers shall be in the (760) area code. An answering machine shall not be connected to either number. The notification shall also give a brief description of the Work and simple instructions to the home or business owner on what they need to do to facilitate the construction. The Contractor shall submit the contents of the notification to the Engineer for approval. Notices shall not be distributed until approved by the Engineer.

5. For door hangers, the notification shall be pre-cut in a manner that enables it to be affixed to a doorknob without adhesives. It shall be a minimum size of 3-1/2 inches by 8-1/2 inches and shall be brightly colored with contrasting printing. The material shall be equivalent in strength and durability to 65 lb. card stock. The printing on the notice shall be no smaller than 12 point.

The precut notices shall be as shown on the example provided in Appendix “A,” with the day of the week circled and appropriate information specific to the Work inserted at the locations indicated in the italicized font.

6. The preparation, materials, printing, delivery and distribution of the letters, door hangers and notifications shall be included in the contract price Bid for Traffic Control and the Contractor will not be entitled to any additional compensation for printing and distributing these notices.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 214 ends

302-2 CHIP SEAL.
302-2.6.2 Polymer Modified Emulsified Asphalt.

DELETE the first paragraph and replace with the following:

1. Polymer modified emulsified asphalt shall be applied when the ambient temperature is between 60°F and 105°F (16°C and 41°C), and the roadway pavement surface temperature is a minimum of 55°F (13°C); or as specified by the Engineer. 302-2.6.3 Modified Paving Asphalt.

DELETE the first paragraph and replace with the following:

1. Modified paving asphalt shall be applied when the atmospheric temperature is 65°F (18°F) or above and the existing pavement surface temperature is 80°F (27°C) or above; or as specified by the Engineer.
302-4 SLURRY SEAL.
302-4.2 Mix Design.

DELETE the last paragraph and REPLACE with the following:

When a mix design is more than 30 Calendar Days old, it shall be supplemented with a Certificate of Compliance that states the combined aggregate gradation is within ± 3 percent of the referenced mix design based on a 30-day moving average or the average of a minimum of 10 of the most current laboratory results, whichever is greater. A mix design shall be reformulated if it is more than 6 months old or whenever the combined aggregate gradation changes from that in the previously submitted mix design by ± 3 percentage points on any sieve size shown in Table 203-5.3.2. If the source of any aggregate or emulsified asphalt is changed, or the mix design or supporting laboratory reports are over 6 months old, a new mix design shall be submitted.

302-5 ASPHALT CONCRETE PAVEMENT.

ADD the following: 302-5.8 Manholes and Other Structures.

1. When placing the overlay , the Contractor shall pave over appurtenances in the roadway which includes sanitary and storm access covers, water valve boxes, air vents, sewer dead end boxes and survey monument boxes. Each appurtenance shall be treated or covered to prevent adhesion of the overlay. Each appurtenance shall be located immediately after the overlay is placed and shall be thoroughly cleaned of any and all construction debris which may have entered due to the Contractor’s operation. The Contractor shall adjust all CMWD water valve boxes per CMWD Standard Drawing No. W23. All City of Carlsbad sanitary sewer access covers shall be adjusted per CMWD Drawing No. S1, S-4, or S-6. All storm sewer access covers shall be adjusted per SDRSD D- 10. Riser rings or extensions shall not be used for the adjustment of these appurtenances.

2. Raising and adjusting to grade all City -owned or CMWD -owned appurtenances in the roadway shall be paid for at the Contract Unit Price per each as shown in the Bid. Such price shall constitute full compensation for all labor, materials, and equipment necess ary for completing the Work as described in these Specifications and Plans. Other agencies will be responsible for their own appurtenances.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 215 ends

302-8 SEALCOAT FOR MISCELLANEOUS AREAS.
302-8.2.1 General.

DELETE the second paragraph and REPLACE with the following:

1. Sealcoat material shall be diluted using clean, potable water in an amount not to exceed 20 percent of the total volume.
302-8.2.2. Spreading.

DELETE the first paragraph and REPLACE with the following:

1. Sealcoat shall be applied when the atmospheric temperature is greater than 55°F (13°C) and if rain is not forecast for the period of 24 hours after application; or as specified by the Engineer.

SECTION 303 – CONCRETE AND MASONRY CONSTRUCTION

303-1 CONCRETE STRUCTURES.
303-1.2 Subgrade for Concrete Structures.

Add the following: If groundwater is encountered, Contractor shall work a minimum 2’ deep of ¾” gravel into soil to provide an adequate base for construction of concrete structure. 303-5 CONCRETE CURBS, WALKS, GUTTERS, CROSS GUTTERS, ALLEY INTERSECTIONS, ACCESS RAMPS, AND DRIVEWAYS.
303-5.1.1 General.

Add the following:

Portland Cement Concrete construction shall include, but not limited to, curbs, walkways, cross gutters, access ramps, driveways, concrete curb outlet, terrace ditches , and all other miscellaneous PCC construction items as indicated on the plans and per these Specifications. 6” Curb and Gutter shall conform to the standard referenced on the plan (I.E: SDRSD G-2 (Type G) or CALTRANS A82A) , the details on the plans, and these specifications. Adjacent AC/AB removal associated with concrete curb construction shall be full depth AC replacement and a minimum width of one foot from the face of concrete edge. Removal of AC shall be incidental to Section 401-1 Removals. Replacement of AC shall be considered incidental to this Section and conform to the requirements of Sections 203-6 and 302-5.

The Contractor shall verify with a “smart level”, string line and/or water testing that positive drainage is maintained upon completion of finishing, and any irregularities causing water ponding shall be corrected and refinished. The CITY shall be present to verify the concrete forms, prior to pouring any PCC construction improvements.
303-5.5.2 Curb.
add the following: The Contractor shall stamp the curb face with 75 mm (3”) high block letters directly above the point that it is crossed by underground facilities with the marking specified in

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 216 ends

Table 303-5.5.2(A)
TABLE 303-5.5.2(A)
Curb Face Markings
Type of underground facilities Marking
Water Service Lateral W
Sewer Service Lateral S
Irrigation Water Lateral or Sleeve RW

303-5.9 Measurement and Payment.
add the following: Curb and gutter, and curb, shall be considered as continuing across driveways, access ramps and drainage inlets when constructed adjacent thereto. Neither curb and gutter nor curb will be paid for across the length of local depressions, except that which occurs in gutter transitions at each side of an inlet.
303-6 STAMPED CONCRETE.
303-6.1 General.

Delete the second paragraph and replace with the following:

Prior to installation, the Contractor shall construct a 10 foot x 10 foot square sample at the job site. This sample shall be subject to inspection and approval by the City prior to installation of the median concrete.

Add the following:

Concrete shall be 560-C-3250 with 6”x6” – 10 gauge wire mesh throughout.

ADD 303-6.5 El Camino Real Medians.

Use color application method “B” (integral color). Color shall be per Section 201-1.2.4(a). The pattern shall match the existing median condition adjacent to the proposed construction along El Camino Real.

303-7 COLORED CONCRETE
303-7.1 General.

Add the following: Integral color shall be used to develop colored admixtures developed for use in ready mixed concrete. The product shall be made of the highest quality pigments, as well as other ingredients designed to enhance the color and improve the pigment dispersion, workability and finishing performance of the concrete. Integral color pigments shall meet or exceed ASTM-C-979. The coloring method shall be designed for concrete flatwork applications (salt finished, broom finishes, rotary finishes), as well as vertical surfaces, and other types of

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 217 ends

architectural concrete. Pigment shall be a permanent coloration, uniform throughout the concrete surface and interior, and shall be highly UV and fade resistant.

Integral colored concrete shall be cured with QC Color Cure color matched to the concrete (see product information bulletin). Provide sample panel submittals of all colors to be used in the installation on identical surfaces for approval by the Engineer. Contractor shall provide a maintenance schedule for integral colored concrete.

Admixture for all integral colored concrete paving in medians and other integral colored concrete shall be the following:

Color: As specified on the plans or 2016 City of Carlsbad Landscape Manual. Match existing color if none specified.

Curing: Scofield Colorcure Concrete Sealer (or approved equal). See Section 201 for Concrete Curing Materials.

Manufacturer: Scofield Chromix Admixtures for color-conditioned concrete, or approved equal L.M. Scofield Company
6533 Bandini Boulevard
Los Angeles, CA 90040
1-800-800-9900

Admixture products and procedures for installation shall be in strict accordance with the manufacturer’s specifications and recommendations, and those published by the American Concrete Institute (ACI) and the Portland Cement Association (PCA).

SECTION 306 – OPEN TRENCH CONDUIT CONSTRUCTION
306-5 DEWATERING.

ADD the following:

Dewatering shall be paid for as an incidental to unclassified excavation and no additional compensation will be made therefore. Except for unsuitable materials removed as part of the clearing and grubbing item unsuitable material encountered below grade will be paid for at the unit price bid for unclassified excavation.

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 218 ends

306-7 PREFABRICATED GRAVITY PIPE.
309-7.3 Reinforced Concrete Pipe (RCP).
306-7.3.2 Joints.
add the following:

The Contractor shall provide Gasket-type joints for reinforced concrete pipe (watertight joints) where indicated on plans.
306-8 PREFABRICATED PRESSURE PIPE.
306-8.8 Valves, Hydrants, and Appurtenances.

ADD 306-8.8.6 Water Meter Boxes:

Water meter boxes shall be installed at locations as shown on the plans.

SECTION 307 – JACKING AND TUNNELING
307-1 JACKING OPERATIONS.
307-1.3 Jacking Steel Casing.

DELETE the first paragraph and REPLACE with the following:

1. Unless otherwise shown on the Plans, the size and wall thickness of the casing to be jacked shall be at the Contractor's option, except that the casing thickness shall be not less than 3/8 inch (9.5 mm) and the casing and jacking operation shall meet all o ther requirements of the agency with permit jurisdiction of the installation. The Contractor shall be responsible for the sufficiency of the casing.

SECTION 308 – MICROTUNNELING
308-6 SUBSURFACE CONDITIONS.
308-6.2 Microtunneling Requested by the Contractor.

DELETE in its entirety and REPLACE with the following:

1. When microtunneling is proposed by the Contractor as an alternative to the specified methods of conduit installation, the Contractor shall obtain copies of the information and reports listed in 3 -9 and 308-6.3 and shall conduct independent investigations a s necessary to substantiate the basis for the Contractor’s proposal and submit in accordance with 3 -8.

Microtunneling operations must be approved by the Engineer prior to the start of microtunneling work.

ADD SECTION 312 - SIGNING
ADD 312-1 PERMANENT SIGNING
ADD 312-1.1 General.

The Contractor shall provide and install all permanent traffic control signs at locations shown on the plans and as specified herein.

ADD 313-2 TEMPORARY TRAFFIC SIGNING.

ADD 313-2.1 General.

The Contractor shall provide and install all temporary traffic control signs, markers, markings,

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 219 ends

and delineators at locations shown on plans and specified herein.

ADD 313-2.2 Maintenance of Temporary Traffic Signs.

If temporary traffic signs are displaced or overturned, from any cause, during the progress of the work, the Contractor shall immediately replace the signs in their original approved locations. The Contractor shall maintain all temporary traffic signs use d in the Work in a clean, reflective and readable condition. The Contractor shall replace or restore graffiti marked temporary traffic signs and posts used in the Work within 18 hours of such marking being discovered during non- working hours or, when the marking is discovered during working hours, within 2 hours of such discovery of marking.

ADD 313-3 TEMPORARY RAILING (TYPE K) AND CRASH CUSHIONS.

ADD 313-3.1 Temporary Railing and Crash Cushions.

Temporary railing (Type K) shall consist of interconnected new or undamaged used precast concrete barrier units as shown on the plans. Temporary sand -filled crash cushions shall consist of new or undamaged used temporary sand-filled crash cushions units as shown on the plans.

ADD 313-3.1.1 Appearance.

Exposed surfaces of new and used units of Temporary railing (Type K) shall be freshly coated with a white color paint prior to their first use on the project. The paint shall conform to the provisions in sections 210 -1.5 “Paint Systems” and 310 “Painting” . Contractor shall be responsible for the removal and cleanup or painting over the graffiti from the K-Rails within 48 hours. The Contractor Shall replace or repaint units of Temporary railing (Type K) or shall remove graffiti, tire or vehicle marks, dirt or any and all materials such that said marks or discoloration mar the appearance of said units when ordered by the Engineer after the units are in place.

ADD 313-3.1.2 Manufacture of Temporary Railing.

In addition to the requirements herein the temporary railing (Type K) shall be manufactured per CALTRANS Standard Drawing T3. Concrete used to manufacture Temporary railing (Type K) shall conform to the provisions in sections 201 -1, “Portland Cement Concr ete” and 303-1 “Concrete Structures”.” Load tickets and a Certificate of Compliance will not be required. Reinforcing steel shall conform to the provisions sections 201-1, “Portland Cement Concrete” and 303-1 “Concrete Structures”. Steel bars to receiv e bolts at ends of concrete panels shall conform to ASTM Designation: A 36/A 36M. The bolts shall conform to ASTM Designation: A 307. A round bar of the same diameter may be substituted for the end-connecting bolt shown on the plans. The bar shall conform to ASTM Desig nation: A 36/A 36M, shall have a minimum length of 660 mm and shall have a 75 mm (3”) diameter by 9 mm (
3/8”) thick plate welded on the upper end with a
5-mm (3/16”) fillet weld. The final surface finish of temporary railings (Type K) shall conform to the provisions in section 303 -1.9.2 “Ordinary Surface Finish.” Exposed surfaces of concrete elements shall be cured by the water method, the forms -in-place method, or the pigmented curing compound method. The pigmented curing compound s hall be type 2 curing compound.

Temporary railing (Type K) may have the Contractor’s name or logo on each panel. The name or

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 220 ends

logo shall not be more than 100 mm in height and shall be located not more than 300 mm above the bottom of the rail panel.

ADD 313-3.1.3 Installation of Temporary Railing.

In addition to the requirements herein the temporary railing (Type K) shall be installed per CALTRANS Standard Drawing T3. Temporary railing (Type K) shall be set on firm, stable foundation. The foundation shall be graded to provide a uniform bearing thr oughout the entire length of the railing. Abutting ends of precast concrete units shall be placed and maintained in alignment without substantial offset to each other. The precast concrete units shall be positioned straight on tangent alignment and on a true arc on curved alignment Each rail unit placed within 3 m (10’) of a traffic lane shall have a reflector installed on top of the rail as directed by the Engineer. Reflectors and adhesive will be furnished by the Contractor. A Type P marker panel conforming to the requirements of the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement shall also be installed at each end of railing installed adjacent to a two- lane, two-way highway and at the end facing traffic of railing installed adjacent to a one -way roadbed. If the railing is placed on a skew, the marker shall be installed at the end of the skew nearest the traveled way. Type P marker panels shall conform to the provisions of section 206 -

7.2, “Temporary Traffic Signs”. Where shown on the plans, threaded rods or dowels shall be bonded in holes drilled in existing concrete. When temporary railings (Type K) are removed, any area where temporary excavation or embankment was used to accommodate the temporary railing shall be restored to its previous condition, or constructed to its planned condition.

ADD 313-3.2 Temporary Sand-Filled Crash Cushions.

Temporary sand -filled crash cushion units shall be “Energite III” manufactured by Energy Absorption Systems, “Fitch Inertial Barrier System Modules” manufactured by Roadway Safety Service, or equal. Features required to determine equivalence of any other temporary sand-filled crash cushion units shall be approval of the system by CALTRANS and that the temporary sand - filled crash cushion units meet NCHRP 350 standards. Other features will be suitability to application, operational characteristics, durabilit y and other such characteristics that the Engineer shall determine. Temporary sand-filled crash cushions (TSFCC) shall be of the type and array configurations shown on plans, and installed at every end of, or gap in, the temporary railing (Type K) whenever the closest point of approach of traffic, regardless of direction, is 4.6 m (15’) or less to the end of the temporary railing (Type K) being considered. The TSFCC shall be installed per CALTRANS Standard Drawings T1 and T2 for approach speeds no less than the posted speed of the street prior to construction or 55 kilometers per hour (35 mph), whichever is the greater. The TSFCC array shall be appropriate to the application as shown on said standard drawings. A Type J and/or P marker panel conforming to th e requirements of the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD) 2003 Edition as amended by the MUTCD 2003 California Supplement shall also be installed at each TSFCC array as shown in CALTRANS Standard Drawings T1 and T2. Particular care shall be taken to assure that crash cushions are installed with the soil supporting them and the adjacent soil

00 74 00 AGENCY SUPPLEMENTAL TECHNICAL PROVISIONS Date Printed: September 2, 2025 Document Version: 1.0 Current Update: May 2023

Page 221 ends