CA Review TL
Meeting Date: Sept. 29, 2026
To: Mayor and City Council
From: Geoff Patnoe, City Manager
Staff Contacts: Sean Diaz, Utilities Senior Engineer
[email protected], 442-339-2350
Keri Martinez, Utilities Principal Engineer
[email protected], 442-339-2354
Subject: Chinquapin Lift Station Improvements Project
District: 1
Reco
mmended Action
Adopt a resolution adopting the plans, specifications and contract documents, accepting bids and awarding a contract to Mehta Mechanical Company, Inc., and appropriating additional funds in the amount of $493,000 for the construction of the Chinquapin Lift Station Improvements Project.
Executive Summary
The city operates 11 sewer lift stations that convey wastewater to higher elevations within the sewer collection system. The Chinquapin Lift Station, located on the east side of Carlsbad Boulevard north of the Agua Hedionda Lagoon, as shown in Exhibit 2, requires improvements to maintain reliable wastewater conveyance.
The Chinquapin Lift Station Improvements Project, Capital Improvement Program Project No. 5554, will construct a replacement building to house a new generator and electrical equipment, replace aging mechanical piping and valves, and replace landscaping and surface improvements. These improvements will increase the operational efficiency, safety and long-term reliability of the lift station.
Staff recommend adopting the plans, specifications, and contract documents; accepting the bids; and awarding a contract to the lowest responsible and responsive bidder, Mehta Mechanical Company Inc. in an amount not to exceed $1,284,000. To complete this project, an additional appropriation of $493,000 is required from the Sewer Replacement Fund, in which there is adequate funding available for the requested amount.
The Carlsbad Municipal Code sections 3.28.080(C), 3.28.080(E) and 3.28.080(I)(6) require the City Council to adopt the plans, specifications and contract documents and approve all formally bid construction contracts when the value exceeds $220,000.
Sept. 29, 2026
Item #5 Page 1 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Explanation & Analysis
The Chinquapin Lift Station is equipped with an emergency generator to provide a backup power source to the pumping system during power outages. The emergency backup generator at the lift station is at the end of its service life and requires replacement to ensure the station’s operability in the event of a power outage. A reliable supply of electricity is needed at the lift station to pump wastewater flows. Power outages without generator backup could result in wastewater spills.
The existing generator and electrical equipment are near the beach and exposed to the ocean air. This marine environment with salt-laden air causes premature corrosion of the electrical equipment. The project will construct a new climate-controlled building for the generator and electrical equipment, replace aging mechanical and structural components in the existing underground vaults and replace landscaping and surface improvements. These improvements are necessary to meet the California Electrical Code and improve operational efficiency and reliability of the lift station.
On Oct. 9, 2024, the California Coastal Commission, which reserves the permitting authority for the area, reported Coastal Development Permit Waiver 6-24-0581-W. No public comment was received at the hearing.
On July 13, 2026, the City Manager authorized staff to advertise for bids to construct the project. The project’s probable construction cost estimate is $1.2 million based on an engineer’s estimate, which is an opinion of a project’s probable construction cost given by an experienced and qualified professional engineer generally familiar with the construction industry. Staff use engineer’s estimates to determine the actual costs as close as possible. The plans, specifications and contract documents are included in Exhibit 3.
On Aug. 11, 2026, nine bids were received ranging from $1,284,000 to $2,370,500. Staff evaluated bids and found Mehta Mechanical Company Inc. to be the lowest responsive and responsible bidder. Staff determined the bid to be responsive to the city’s bid request and that Mehta Mechanical Company Inc. is a responsible bidder, meeting the technical ability and experience requirements of the bidding documents.
Staff recommend adopting the plans, specifications and contract documents; accepting the bids; awarding a contract to the lowest responsive and responsible bidder on the project, Mehta Mechanical Company Inc. in an amount not to exceed $1,284,000; and authorizing an additional appropriation of $493,000 from the Sewer Replacement Fund to Capital Improvement Program Project No. 5554.
Fiscal Analysis
The total cost of $1,956,000 for Capital Improvement Program Project No. 5554 is detailed in the table below.
Appropriation from the Sewer Replacement Fund totaling $493,000 is required to fully fund the project. Sufficient funding is available in the Sewer Replacement Fund.
Sept. 29, 2026
Item #5 Page 2 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Chinquapin Lift Station Improvements Project
Capital Improvement Project No. 5554
Total appropriation to date $1,870,000
Total expenditures and encumbrances to date -$406,058
Total available balance $1,463,942
Construction contract – Mehta Mechanical Company Inc. -$1,284,000 Construction contingency (25%) -$321,000
Construction management, inspection and testing, public outreach, engineering and administration (estimated)
-$321,000
Community outreach during construction (estimated) -$15,000 Engineering and administrative costs (estimated) -$15,000 Total estimated costs -$1,956,000
Remaining balance -$492,058
Additional appropriation requested $493,000
Carlsbad Municipal Code Section 3.28.040(C)(5) authorizes the City Manager or designee to approve change orders in the amount equal to the contingency set at the time the project is awarded. For this project, the contingency amount is a total of $321,000.
Next Steps
Once the City Council adopts the plans, specifications and contract documents, accepts the bids and awards a construction contract to Mehta Mechanical Company Inc., staff will issue a purchase order, schedule a pre-construction meeting with the contractor and issue a notice to proceed to construct the project.
Staff will engage the consultants for community outreach and construction management and inspection services during construction upon execution of the agreements for those services.
The duration of the construction contract is an estimated six months, not including rainy days and delays from change orders that may extend the contract duration. The project is expected to be completed by spring 2027. A notice of completion to release bonds issued for the project will be recorded at that time.
Environmental Evaluation
The proposed action to construct a replacement building to house a new generator and electrical equipment, replace aging mechanical piping and valves, and replace landscaping and surface improvements at Chinquapin Lift Station is categorically exempt from environmental review under California Environmental Quality Act, or CEQA, Guidelines Section 15301 because it involves the maintenance, repair or minor alteration of existing facilities with negligible or no expansion of the existing or former use. No exceptions to the categorical exemption as set forth in CEQA Guidelines Section 15300.2 or Carlsbad Municipal Code Section 19.04.070(C) apply.
Sept. 29, 2026
Item #5 Page 3 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Exhibits
1. City Council resolution
2. Location map
3. Plans, specifications and contract documents (on file in the Office of the City Clerk) Sept. 29, 2026
Item #5 Page 4 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Exhibit 1
RESOLUTION NO. 2026-176 .
A R
ESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, ADOPTING THE PLANS, SPECIFICATIONS AND CONTRACT
DOCUMENTS, ACCEPTING BIDS AND AWARDING A CONTRACT TO MEHTA MECHANICAL COMPANY, INC. , AND APPROPRIATING ADDITIONAL FUNDS IN THE AMOUNT OF $ 493,000 FOR THE CONSTRUCTION OF THE
CHINQUAPIN LIFT STATION IMPROVEMENTS PROJECT
WHE
REAS, the City Council of the City of Carlsbad, California has determined it is necessary, desirable and in the public interest to construct the Chinquapin Lift Station Improvements Project , Capital Improvement Program, or CIP, Project No. 5554, or Project; and WHEREAS, on July 13, 2026, the City Manager authorized staff to advertise for bids to construct the Project; and
WHEREAS, on Aug. 11, 2026, staff received nine bids in response to the bid advertisement; and WHEREAS, staff evaluated the bids and found Mehta Mechanical Company, Inc., who submitted a bid in an amount of $1,284,000, to be the lowest responsive and responsible bidder; and WHEREAS, Carlsbad Municipal Code , or CMC, Section 3.28.080( C), Section 3.28.080(E) , and Section 3.28.080( I)(6) require the City Council to adopt the plans, specifications, and contract documents for construction projects and approve all formally bid contracts when the value exceeds $220,000 and such documents are incorporated herein; and WHEREAS, Carlsbad Municipal Code Section 3.28.040(C)(5) authorize s the City Manager or designee to approve change orders in an amount equal to the contingency set at the time of contract award, which is $321,000; and
WHEREAS, the Project requires an additional appropriation o f $ 493,000 from the Sewer Replacement Fund to CIP Project No. 5554, and sufficient funding is available in this fund.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the City Council has determined that t he proposed action to construct a replacement building to house a new generator and electrical equipment, replace aging mechanical piping and valves, and replace landscaping and surface improvements at Chinquapin Lift Station is categorically exempt from e nvironmental review under California Environmental Quality Act, or CEQA , Guidelines Section 15301 because it Sept. 29, 2026
Item #5 Page 5 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF involves the maintenance, repair or minor alteration of existing facilities with negligible or no expansion of the existing or former use. No exceptions to the categorical exemption as set forth in CEQA Guidelines Section 15300.2 or Carlsbad Municipal Code Section 19.04.070(C) apply.
3. That the City Council adopts the plans, specifications and contract documents for the Chinquapin Lift Station Improvements Project, CIP Project No. 5554.
4. That the bid in an amount not to exceed $1,284,000 submitted by Mehta Mechanical Company, Inc., is accepted, and the Mayor is hereby authorized to execute a contract.
5. That the City Manager or designee is hereby authorized to approve construction change orders up to $321,000.
6. That the City Manager or designee is authorized to appropriate additional funds in the amount of $493,000 from the Sewer Replacement Fund to CIP Project No. 5554.
7. That the City Manager or designee is authorized to sign all other documents necessary for regulatory compliance, to extend funding opportunities, or to otherwise implement and finalize the project, all of which are subject to review and approval as to form by the City Attorney’s office.
8. That the award of this contract is contingent upon Mehta Mechanical Company , Inc. executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within 20 calendar days after adoption of this Resolution. The City Manager may grant reasonable extensions of time to execute the contract and assemble the required bonds and insurance policies.
Sept. 29, 2026
Item #5 Page 6 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 29th day of September, 2026, by the following vote, to wit:
AYES: Blackburn, Bhat-Patel, Acosta, Burkholder, Shin.
NAYS: None.
ABSTAIN: None.
ABSENT: None.
_______
_______________________________
KEITH BLACKBURN, Mayor
_______
_______________________________
SHERRY FREISINGER, City Clerk
(SEAL)
Sept. 29, 2026
Item #5 Page 7 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF
3 2
Exhibit 2
Sept. 29, 2026
Item #5 Page 8 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Exhibit 3
Plans, specifications and contract documents
(on file in the Office of the City Clerk)
Sept. 29, 2026
Item #5 Page 9 of 9
Docusign Envelope ID: 7E90B9F3-6387-80DB-82A1-D988842724DF Public Works
Contract Administration 1635 Faraday Avenue Carlsbad, CA 92008 760-602-4677 t July 22, 2026
ADDENDUM NO. 1
RE: CHINQUAPIN LIFT STATION IMPROVEMENTS
PROJECT NO.: 5554
Please include the attached addendum in the Notice to Bidder/Request for Bids you have for the above project.
Please note change of date and time for the pre-bid meeting for the above-mentioned bid.
New date and time for the pre-bid meeting:
Monday, July 27, 2026 at 10 a.m.
Carlsbad Municipal Water District
5950 El Camino Real, Carlsbad, CA 92008
This addendum--receipt acknowledged--must be attached to your Request for Bid when your bid is submitted.
GRAHAM JORDAN
Contract Administrator
I ACKNOWLEDGE RECEIPT OF ADDENDUM NO. 1
__________________________________
Bidder's Signature
Exhibit 3
Contract No. 5554 - PWS27-4091UTIL 1
Addendum No. 1
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION IMPROVEMENTS
Contract No. 5554
Bid No. PWS27-4091UTIL
Addendum No. 1
From: Graham Jordan, Contract Administrator
Phone: 442-339-2462
[email protected]
No. of Pages: 1 page
Date: July 21, 2026
Bid Opening Date: August 11, 2026 - 11 a.m. (unchanged)
NOTICE:
This Addendum forms a part of the Contract Documents for the above identified project and modifies portions of the original Contract Specifications and/or Plans. Documents not specifically mentioned in this Addendum remain in full force.
Acknowledge receipt of this Addendum on the Bid Form. Failure to do so may subject bidder to disqualification.
Please note change in pre-bid meeting date for the above-mentioned bid.
New date and time for pre-bid meeting is:
Monday, July 27, 2026, 10 a.m.
ITEM NO. 1: MODIFICATIONS, DELETIONS, AND ADDITIONS TO THE NOTICE INVITING BIDS
Edit the first paragraph of Pre-Bid Meeting section of t he Notice Inviting Bids (Page 13) to read as follows:
“A pre-bid meeting will be held at the Carlsbad Municipal Water District office building located at 5950 El Camino Real, Carlsbad, CA on July 23, 2026, at 1 p.m. July 27, 2026, at 10 a.m.”
Public Works
Contract Administration 1635 Faraday Avenue Carlsbad, CA 92008 760-602-4677 t
July 30, 2026
ADDENDUM NO. 2
RE: CHINQUAPIN LIFT STATION IMPROVEMENTS
PROJECT NO.: 5554
Please include the attached addendum in the Notice to Bidder/Request for Bids you have for the above project.
This addendum--receipt acknowledged--must be attached to your Request for Bid when your bid is submitted.
GRAHAM JORDAN
Contract Administrator
I ACKNOWLEDGE RECEIPT OF ADDENDUM NO. 2
__________________________________
Bidder's Signature
Contract No. 5554 - PWS27-4091UTIL 1
Addendum No. 2
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION IMPROVEMENTS
Contract No. 5554
Bid No. PWS27-4091UTIL
Addendum No. 1
From: Graham Jordan, Contract Administrator
Phone: 442-339-2462
[email protected]
No. of Pages: 10 pages
Date: July 30, 2026
Bid Opening Date: August 11, 2026 - 11 a.m. (unchanged)
NOTICE:
This Addendum forms a part of the Contract Documents for the above identified project and modifies portions of the original Contract Specifications and/or Plans. Documents not specifically mentioned in this Addendum remain in full force.
Acknowledge receipt of this Addendum on the Bid Form. Failure to do so may subject bidder to disqualification.
MODIFICATIONS, DELETIONS, AND ADDITIONS TO THE APPENDICES
ITEM NO. 1: APPENDIX A
Replace Appendix A in its entirety with the attached revised Appendix A (Attachment A).
ITEM NO. 2: APPENDIX G
Add the attached Appendix G (Attachment B) to the bid documents.
QUESTIONS AND ANSWERS
Questions relating to the project must go directly to the City’s Public Works Contract Administration Division. The City is not responsible for any information obtained through other means.
Contract No. 5554 - PWS27-4091UTIL 2
Addendum No. 2
1. [We] would like to know if the steel cover can be designed for bolt together instead of field welding? This will save time to make weldments in the shop and then deliver to powder zinc rich primer powder coat with Super Durable Top Coat powder coat.
We need clarification on the question. It’s not clear as to which “steel cover” the bidder is referring.
The trash equipment enclosure.
The only enclosure on the Plans is the generator and electrical building. The roof for the building shall be constructed as shown on the Plans or specified in the Specifications, as revised per addenda.
2. Can steel subcontractors with Los Angeles City Certification be used in lieu of AISC? This certification meets or exceeds equivalent quality safety standards.
Yes.
3. Soffit of Generator Enclosure: Note 43 on Sheet 548 -3 calls for “18 ga. HSB -36 Classic Green”; however, HSB-36 is a steel decking profile not typically available with a factory pre - finished color for exposed soffit applications —please confirm whether the s offit at the generator enclosure is intended to be constructed using HSB -36 steel decking or a pre - finished architectural standing seam metal system? If the standing seam metal system, provide the required panel profile and color and confirm whether 22 ga material is acceptable in lieu of 18 ga due to high cost and extremely long lead time considerations.
Use MBCI PBU EXPOSED FASTENING SYSTEM ROOF PANELS, GALVANUME PLUS, 22 GA, COLOR: CLASSIC GREEN in lieu of the 18 GA HSB 36. Within approximately 5 miles of the coastline, use a marine-grade coating system and verify the warranty for the environment.
Accordingly, Note 43 on A-101, Sheet 9 of the plans is changed.
4. Generator Exhaust: Detail 3 on Sheet 12 indicates the engine generator exhaust. Please confirm whether the exhaust system is being pre -purchased with the generator under the City's procurement or if it will need to be included in the Contractor's scope of work. 3.
Inspection Costs: Please confirm that the City will be responsible for all inspection costs, including any required special inspections and third-party inspection services.
There is a flexible exhaust connector and silencer provided with the unit as it’s an indoor installation. All other work items required as shown in Detail 3 on Sheet 12, connection between the provided flex connector and the silencer, as well as the connection fro m the silencer out of the building, shall be furnished and installed by the Contractor.
5. What is the operating pressure of the lift station?
Operating pressure is approximately 30 psi.
6. Please provide required force main pressure for the bypass system.
See answer to question 5. Also, refer to Technical Specification 02960 Temporary Bypass Pumping for further information. The Contractor is responsible for the design of the sewer bypass system during construction.
7. The specifications identify Owner-furnished equipment, including the pre-purchased MCC and generator. Please confirm whether any or all Owner-furnished equipment will be delivered to the project site when required for installation, or if Contractor receiving, transportation, off-site storage, and redistribution of Owner-furnished equipment is required under this contract.
Refer to Section 9-4 Bid Items, Generator Installation and Motor Control Center Installation.
Refer to Plans, Sheet 19 (Drawing E1), Pre -Purchased Items General Note. The Contractor is responsible for inspecting owner -furnished equipment at the city’s yard, 5950 El Camino Contract No. 5554 - PWS27-4091UTIL 3
Addendum No. 2
Real, loading, transport/delivery to the project site, and off -loading Owner -furnished equipment.
8. Please confirm whether temporary power requirements are limited to normal construction power and lighting, OR if temporary utility service, generators, bypass pumping support, lift station operation, fuel, monitoring, or other temporary operational systems are required under this contract.
Refer to Section 6 -2.1 Order of Work and 6 -2.2 Construction Phasing. The Contractor shall provide temporary power system(s) necessary to conduct all phases of work.
9. Section 26 24 13 references contractor responsibility for SDG&E fees and service establishment costs. Please confirm all SDG&E costs that are required to be included in Contractor scope.
SDGE electrical service exists now. The City has filed the SDGE request for service relocation; see new Appendix G – SDGE Electric Service Request. The City will pay SDGE fees related to the relocation request, including inspection fees. The Contractor will pay for repeat inspec tions, if required, or fees and costs to correct non -conforming work at no additional cost to the City.
10. Sections 40 61 21 and 40 63 43 reference the Owner's System Integrator. Please define the exact division of responsibilities between the Contractor and Owner's System Integrator.
The Contractor is responsible for all panel fabrication, materials, installation, field wiring, power, grounding, instrumentation terminations, labeling, testing support, and startup coordination necessary to provide a complete and functional installation ready for SCADA integration.
The Owner’s System Integrator will be responsible for SCADA integration into the City’s existing SCADA system, including PLC/OIT programming coordination, Ignition integration, SCADA screens, alarm/tag configuration, communications coordination, and final SCADA checkout.
The Contractor shall coordinate with the Owner and Owner’s System Integrator for FAT/WFAT, startup, loop checks, signal verification, and commissioning. The Contractor remains responsible for correcting installation, wiring, panel, instrumentation, or equi pment issues identified during testing and commissioning.
In general, the Contractor provides and installs the complete functioning panel and field installation; the Owner’s System Integrator integrates the completed installation into the City’s SCADA platform.
11. Please identify the division of responsibilities for furnishing, assembly, installation, testing, programming, startup, commissioning, and integration of the instrumentation and control system, including any Owner-furnished controls equipment.
The Owner has pre-purchased the MCC and standby generator in configurations intended to match the final design documents, control requirements, and City standardization needs.
These items will be inspected prior to site delivery.
Upon delivery to the site, the Contractor is responsible for receipt, unloading, storage, protection, assembly as required, installation, anchorage, conduit, wiring, terminations, grounding, testing, startup, commissioning support, and integration support for the Owner - furnished MCC and standby generator.
Contract No. 5554 - PWS27-4091UTIL 4
Addendum No. 2
The Contractor is also responsible for all other electrical, instrumentation, controls, and related work shown in the design documents, unless specifically identified otherwise. This includes furnishing, assembly, installation, field wiring, terminations, labeling, calibration, equipment - specific configuration/programming, loop checks, startup, commissioning, and integration support for the instrumentation and control system.
The Owner’s System Integrator responsibilities are limited to the items identified in response to Question 10, including PLC/OIT programming, SCADA integration, and testing/commissioning activities directly associated with that programming and SCADA integration scope.
In general, equipment or systems installed by the Contractor remain the Contractor’s responsibility through startup and commissioning. The Contractor shall correct installation, wiring, configuration, equipment, instrumentation, or field issues identified during testing and commissioning.
If an issue is identified with Owner-furnished equipment and is determined to be a pre-existing equipment defect or issue not caused by Contractor handling, storage, installation, wiring, configuration, or operation, the Owner will be responsible for addressing that specific issue.
12. Does the temporary path to the Agua Hedionda Lagoon Trail need to be ADA compliant or can it be stairs descending from the work site to the path? The temporary path need not be compliant with Americans with Disabilities Act (ADA) compliant, but it must be compliant with the requirements for temporary stairs in California Code of Regulations, Title 8, Section 1626 Stairwells and Stairs ( California Code of Regulations, Title 8, Section 1626. Stairwells and Stairs ) and Section 1620 for railings (California Code of Regulations, Title 8, Section 1620. Design and Construction of Railings).
The temporary stairway shall have at least one landing near mid -height of the stairway in accordance with Section 1626(b)1.
13. Does the new AC in the parking lot need a finish course per the standard or is a base pave to finish surface okay?
Yes, provide Base Course and Finish Course consisting of C2 aggregate gradation per City of Carlsbad Standard GS-28 and Greenbook Section 302-5.9.
Contract No. 5554 - PWS27-4091UTIL 5
Addendum No. 2
ATTACHMENT A
Revised Appendix A
APPROX. (200'X15')
3,000 SF
TEMPORARY
CONSTRUCTION
STAGING AREA
INSTALL TEMPORARY
FENCE TO SECURE
AREA. SEE NOTES.
GARFIELD ST. CONSTRUCTION STAGING
(OPTIONAL)
(EXHIBIT 1)
NOTES:
1. TEMPORARY CONSTRUCTION STAGING, FENCING, TRAFFIC CONTROL, AND ALL OTHER
ITEMS OF WORK SHALL BE CONSIDERED INCIDENTAL TO THE BID ITEM FOR MOBILIZATION AND OTHER ITEMS OF WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS. 2 . STAGING AREA SHALL BE IN PARKING SPACES, AC PAVEMENT, AND DISTURBED AREAS, AS APPROVED BY THE CITY. MAINTAIN TRAFFIC IN BOTH DIRECTIONS. ADHERE TO
REQUIREMENTS AS APPROVED BY THE CITY RIGHT OF WAY PERMIT, INCLUDING TRAFFIC CONTROL PLANS.
DATE AVE.
GARFIELD ST.
APPROX.
1,500 SF
TEMPORARY
CONSTRUCTION
STAGING AREA
INSTALL
TEMPORARY FENCE
TO SECURE AREA.
SEE NOTES.
HOME PLANT LIFT STATION
CONSTRUCTION STAGING (OPTIONAL)
(EXHIBIT 2)
NOTES:
1. TEMPORARY CONSTRUCTION STAGING, FENCING,AND ALL OTHER ITEMS OF WORK SHALL
BE CONSIDERED INCIDENTAL TO THE BID ITEM FOR MOBILIZATION AND OTHER ITEMS OF WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS.
2 . MAINTAIN CITY ACCESS TO NORTH GATE TO LIFT STATION AT ALL TIMES.
3. MAINTAIN ACCEES TO WESTERLY GATE FOR SDGE ACCESS AT ALL TIMES.
4. STAGING AREA SHALL BE IN AC PAVEMENT, AND DISTURBED AREAS, AS APPROVED BY THE CITY. ANY DAMAGES TO EXISTING CONDITIONS SHALL BE REPAIRED TO PREVIOUS OR BETTER CONDITION, AT THE CONTRACTOR'S COST, AND NO ADDITIONAL COST TO THE CITY.
STATE ST.
CARLSBAD BLVD.
Contract No. 5554 - PWS27-4091UTIL 6
Addendum No. 2
ATTACHMENT B
Appendix G
SDGE Electric Service Request
Additional Address Info:
PROCEDURE FOR INSTALLATION
1. PHONE DIG ALERT "811" AT LEAST TWO DAYS PRIOR TO TRENCHING FOR LOCATION OF UNDERGROUND UTILITIES.
2. Phone Operations Assistant at 760-432-5805 for the following:
- 3 Working days prior to trenching to arrange pre-meet with inspector and initiate trenching process. - After excavation of trench, installation of conduit and service entrance equipment at meter location, CALL FOR INSPECTION. Do not cover conduit without inspector's written approval to backfill. - When trench is backfilled and compacted, CALL FOR INSPECTION. - If service entrance equipment is installed after backfill, CALL FOR INSPECTION OF THE EQUIPMENT.
3. Meter cannot be set until inspector has approved installation, including service equipment, and receipt of city/county/state inspection Metering: CT Meter Clips: 15
Utilities Maximum Contribution to Fault Current: 42000Phase: 3# of Wires: 4 Voltage: 120/240
Bend Info: 4" 90 DEG 36"R DB100Bend Type: HANDHOLE
Riser Quad: Stop Trench: from PoleLadder Arms:
Standards Page: Handhole Lid Shall Read:
Structure #: SCUSTOMER HHStation ID #: 303-470
Temp Service Charge Due $ 0.00
Assessor's Parcel Number: Additional Information:
Please call your Operations Assistant at 760-432-5805 with questions about application, inspection, construction installation and to schedule a crew.
Number/Size of Main Switch: 400Service Panel Rating: 400 Conduit Size: 1-4"Conduit Installed By: CUSTOMER
Customer Phone #: 442-339-2305Customer POC: Neil Irani
Wanted Date: ON INSPECTION
Job #:
ELECTRIC UNDERGROUND METER & SERVICE LOCATION
Customer Copy
Project Title: 4010 CARLSBAD BLVD
Notification #: 300000706400
Project Address: 4020 CARLSBAD BLVD
Customer Type: Commercial
Date Prepared: 06/24/2024
Project City: CARLSBAD
SDGE Contact: Operations Assistant Contact Info: OPERATIONS ASSISTANT,760-432-5805 Service Type: UG SERVICE REWIRE/RELOCATION
TB: -
SERVICE ATTACHMENT POINT AND/OR METER LOCATION:
Locate the new 400 amp NEMA 3R gear at location shown on sketch. Customer is to provide all excavation, trench, 1-4" conduit, backfill, compaction, 3/4" pulling and measuring tape in conduit and surface repair from customer handhole to new meter panel. Customer to provide & maintain 3'X3' clear and level workspace in front of meter, brush needs to be removed. Take conduit to within distance as instructed by SDG&E inspector. Prior to digging, please contact the Operations Assistant at 760-432- 5805 to schedule a pre-construction meeting with your trench inspector.
SDG&E Application Required-Call: 1-800-411-7343
Municipal Inspection required By: CITY OF CARLSBAD
Bend Installed By: CUSTOMER
Handhole Installed By:
Traffic Control Permit Required
Excavation/Encroachment Permits Required By: Customer
Joint Trench With: Electric
Right of Way Required
Meter height -- 4'0'' min. (3'0" min. for multiple installation) -- 6'3" max. From finish grade to centerline of meter base. Meters are required to be readily accessible 24 hours per day. Meters must be located in a safe area free of any potentially hazardous or dangerous condition.
Provide 3-ft. x 3-ft. clear and level working space in front of meter. Where meter room is proposed, contact the planner at the nearest SDG&E office. Meter bases and meter service disconnects must be located at or immediately adjacent to each other and be identified with address and unit number.
If SDG&E encounters hazardous or toxic material while performing construction of your project, SDG&E will halt work immediately and it will be your responsibility to remove and or clean up all hazardous or toxic material prior to SDG&E continuing construction. SDG&E shall have no liability or obligation whatsoever to cleanup, remove or remediate any hazardous or toxic materials discovered during the course of construction unless it is through negligence of SDG&E.
Customer-owned facilities to receive gas service are subject to all applicable local and state of California inspection authority requirements.
Building address and/or houseline must be permanently identified prior to meter set. Barrier posts may be required based on field conditions at any time prior to meter set as determined by the SDG&E Representative. Per Rule 16.A.1.a. In compliance with Section 783 of the Public Utilities Code, SDG&E will apply only those construction and design specifications, standards, terms, and conditions that are applicable to a new extension of service project for the 18 months following the date the application for a new extension of service project is approved. Keep this notice with your building permit.
All installations performed under this order must meet SDG&E standards unless a written deviation has been approved.
Planned By: Douglas Pearce Phone#: 8586540236
Public Works
Contract Administration 1635 Faraday Avenue Carlsbad, CA 92008 760-602-4677 t
August 5, 2026
ADDENDUM NO. 3
RE: CHINQUAPIN LIFT STATION IMPROVEMENTS
PROJECT NO.: 5554
Please include the attached addendum in the Notice to Bidder/Request for Bids you have for the above project.
This addendum--receipt acknowledged--must be attached to your Request for Bid when your bid is submitted.
GRAHAM JORDAN
Contract Administrator
I ACKNOWLEDGE RECEIPT OF ADDENDUM NO. 3
__________________________________
Bidder's Signature
Contract No. 5554 - PWS27-4091UTIL 1
Addendum No. 3
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION IMPROVEMENTS
Contract No. 5554
Bid No. PWS27-4091UTIL
Addendum No. 3
From: Graham Jordan, Contract Administrator
Phone: 442-339-2462
[email protected]
No. of Pages: 59 pages
Date: August 5, 2026
Bid Opening Date: August 11, 2026 - 11 a.m. (unchanged)
NOTICE:
This Addendum forms a part of the Contract Documents for the above identified project and modifies portions of the original Contract Specifications and/or Plans. Documents not specifically mentioned in this Addendum remain in full force.
Acknowledge receipt of this Addendum on the Bid Form. Failure to do so may subject bidder to disqualification.
MODIFICATIONS, DELETIONS, AND/OR ADDITIONS TO SPECIFICATIONS
ITEM NO. 1: CONTRACTOR’S PROPOSAL
Replace the Contractor’s Proposal with the revised proposal in Attachment A.
ITEM NO. 2: GENERAL PROVISIONS, 9-4 BID ITEMS
Add the following bid item description as shown:
Furnish and Install Polymer Concrete Sewer Manhole
The contract price paid for this bid item shall constitute full compensation for all labor, materials, and equipment to construct sewer manhole per City of Carlsbad Standard DWG S -1 and in accordance with the city Approved Materials List, Section 03000 , and Section 03460. This bid item shall include pavement saw -cutting, sewer cleanout removal, pipe and fitting removal, demolition and disposal; excavation; dewatering and any required water disposal; preparation of subgrade beneath manhole base; base, shaft, cone, grade rings and frame and cover assemblies; placement and compaction of crushed rock bedding and soil backfill; manhole adapters, disposal of surplus materials , pavement structural section restoration , adjustment of frame and cover Contract No. 5554 - PWS27-4091UTIL 2
Addendum No. 3
assemblies to final grade , and all incidental work and services in accordance with the Contract Documents.
MODIFICATIONS, DELETIONS, AND ADDITIONS TO THE APPENDICES
ITEM NO. 3: APPENDIX G
Replace Appendix G in its entirety with the attached revised Appendix G in Attachment B.
ITEM NO. 4: APPENDIX H
Add the attached Appendix H (Attachment C) to the bid documents.
MODIFICATIONS, DELETIONS, AND/OR ADDITIONS TO THE PLANS
ITEM NO. 5: REVISED DRAWING SHEETS
Replace drawing sheets C -03, C -04, A-101, A-201, and A -501, with revised drawing sheets provided in Attachment D.
QUESTIONS AND ANSWERS
Questions relating to the project must go directly to the City’s Public Works Contract Administration Division. The City is not responsible for any information obtained through other means.
1. Ductile-Iron Pipe and Fittings Section 15056 -1.10 Corrosion Protection. C. Ductile -Iron Pipe in vault or structures shall be fusion -bonded epoxy lined and coated per Section 09961. D.
Ductile-Iron Pipe and Fittings for wastewater service shall be ceramic e poxy lined. Can you please confirm the lining and coating that is required for Ductile-Iron Pipe and Fittings? The ductile iron pipe and fittings for wastewater service shall be ceramic epoxy lined and coated per City Standard Specification 09900 2.4 PIPE AND FITTINGS – WASTEWATER SERVICE.
2. Will a plug valve specification be provided?
Plug valves shall conform with the Approved Materials List for Sewer Facilities in Volume 2 of the Carlsbad Engineering Standards. See Appendix D:
Eng_Standards_Vol2_2024.05.30.docx
3. Will a knife gate valve specification be provided?
Knife gate shall be ITT Series C67S as shown on the plans, Detail 1 of Sheet 5. See Addendum 3, revised drawing C-04 for further specification.
4. Please confirm that the staging areas shown in Exhibit 1 & 2 of Addendum 2 will be provided at no cost to the contractor. There is no additional fee to use these areas. However, see Notes 1 and 4 of Exhibits 1 & 2, Appendix A, of Addendum 2. “TEMPORARY CONSTRUCTION
STAGING, FENCING, AND ALL OTHER ITEMS OF WORK SHALL BE CONSIDERED
INCIDENTAL TO THE BID ITEM FOR MOBILIZATION AND OTHER ITEMS OF WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS.” “STAGING AREA SHALL BE IN AC PAVEMENT, AND DISTURBED AREAS, AS APPROVED BY THE CITY. ANY DAMAGES
TO EXISTING CONDITIONS SHALL BE REPAIRED TO PREVIOUS OR BETTER Contract No. 5554 - PWS27-4091UTIL 3
Addendum No. 3
CONDITION, AT THE CONTRACTOR'S COST, AND NO ADDITIONAL COST TO THE CITY.”
5. Drawing E-3 shows a new 200A Meter Pedestal. The new SDG&E drawing that was received via Addendum #2 shows a 400A Meter Pedestal. Please advise if a 200A of 400A Meter Pedestal is required.
The 200A Meter per drawing E-3 is correct and is required. SD&E has updated their drawing.
See Addendum 3 for the new revised Appendix G with the correction to the SDG&E sketch and documents.
6. The SLD, note 3 mentions MCC startup. MCC startup is also mentioned in Addendum #2, answer #11. It is expected that the Electrical Contractor will be onsite to start the MCC, test, and ensure everything is working as expected. Actual MCC startup services are typically provided by the MCC manufacturer. They will send a representative out for a day or two for actual startup. Please advise if the owner is including the Manufacturers MCC startup services. Also, please confirm the manufacturer of the owner provided MCC.
The contractor shall include the Manufacturer MCC startup services in with the bid item for MCC installation, MCC Start -up services (1-Day minimum) and Virtual Witness Test (1 Day minimum). The city is not providing these services. Refer to the bid documents, Appendix F - MCC submittal, for additional manufacturer information on Rockwell Automation.
7. Is there a geotech report?
See Addendum 3 for the added Appendix H – Geotechnical Report.
Contract No. 5554 - PWS27-4091UTIL 4
Addendum No. 3
ATTACHMENT A
(Revised)
CONTRACTOR’S PROPOSAL
Contract No. 5554 - PWS27-4091UTIL 5
Addendum No. 3
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
CONTRACTOR'S PROPOSAL
City Council
City of Carlsbad
1200 Carlsbad Village Drive
Carlsbad, California 92008
The undersigned declares he/she has carefully examined the location of the work, read the Notice Inviting Bids, examined the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto, and hereby proposes to furnish all labor, materials, equipment, and incidental services required to do all the work to complete Contract No. 5554 in accordance with the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto and that he/she will take in full payment therefore the following unit prices for each item complete, to wit (refer to Section 9-4 for bid item descriptions):
SCHEDULE “A”
Item
No. Description
Approximate
Quantity
and Unit
Unit Price
(Figures)
Total Amount
(Figures)
1 Mobilization and Preparatory
Work (not to exceed 5% of Total
Bid)
LS $___________
2 Temporary Traffic Control LS $___________
3 Preconstruction Survey LS $___________
4 Storm Water Pollution Control
(SWPPP)
LS $___________
5 Temporary Pedestrian Detour LS $___________
6 Utility Locating and Potholing LS $___________
7 Excavation Support System LS $___________
8 Demolition – Civil/Mechanical LS $___________
9 Demolition – Electrical LS $___________
10 Temporary Sewer Bypass LS $___________
Contract No. 5554 - PWS27-4091UTIL 6
Addendum No. 3
Item
No. Description
Approximate
Quantity
and Unit
Unit Price
(Figures)
Total Amount
(Figures)
11 Furnish and Install Wet Well Roof
Slab and Hatch
LS $___________
12 Furnish and Install 4” DIP and
Appurtenances
LS $___________
13 Furnish and Install 6” DIP and
Appurtenances
LS $___________
14 Furnish and Install 8” SCH 80
PVC Pipe and Appurtenances
LS $___________
15 Furnish and Install 4” Plug Valve 2 EA $___________ $___________
16 Furnish and Install 6” Plug Valve 1 EA $___________ $___________
17 Furnish and Install 6” Plug Valve
(3-way)
1 EA $___________ $___________
18 Furnish and Install 6” Knife Gate
Valve
1 EA $___________ $___________
19 Furnish and Install 4” Check Valve 2 EA $___________ $___________
20 Furnish and Install 6" Flow Meter 1 EA $___________ $___________
21 Furnish and Install Wet Well Liner
Repairs
LS $___________
22 Furnish and Install Hatch Safety
Railing
LS $___________
23 Furnish and Install Building
Structure Expansion
LS $___________
24 Furnish and Install Electrical Work LS $___________
25 Generator Installation LS $___________
26 Motor Control Center Installation LS $___________
Contract No. 5554 - PWS27-4091UTIL 7
Addendum No. 3
Item
No. Description
Approximate
Quantity
and Unit
Unit Price
(Figures)
Total Amount
(Figures)
27 Furnish and Install Concrete and
Curb Replacement
LS $___________
28 Furnish and Install Decorative
Concrete Walkway Replacement
LS $___________
29 Furnish and Install Asphalt
Concrete
LS $___________
30 Furnish and Install Landscaping &
Irrigation
LS $___________
31 Furnish and Install 4-ft. Diameter
Polymer Concrete Sewer Manhole
LS $___________
Total amount of bid (in figures) for Schedule “A”: $
Total amount of bid (in words) for Schedule “A”:
The City shall determine the low bid based on the sum of Schedule “A”.
Price(s) given above are firm for 90 days after the date of bid opening.
Addendum(a) No(s). ___________________ has/have been received and is/are included in this proposal.
The Undersigned has carefully checked all of the above figures and understands that the City will not be responsible for any error or omission on the part of the Undersigned in preparing this bid.
The Undersigned agrees that in case of default in executing the required Contract with necessary bonds and insurance policies within twenty (20) days from the date of award of Contract by the City Council of the City of Carlsbad, the City may administratively authorize award of the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited.
The Undersigned bidder declares, under penalty of perjury, that the undersigned is licensed to do business or act in the capacity of a contractor within the State of California, validly licensed under license number _________________________, classification ________________ which expires on _____________________, and Department of Industrial Relations PWC registration number ___________________________________ which expires on ____________________, and that this statement is true and correct and has the legal effect of an affidavit.
A bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the City § 7028.15(e). In all contracts where federal funds are involved, no bid submitted shall be Contract No. 5554 - PWS27-4091UTIL 8
Addendum No. 3
invalidated by the failure of the bidder to be licensed in accordance with California law. However, at the time the contract is awarded, the contractor shall be properly licensed.
The Undersigned bidder hereby represents as follows:
1. That no Council member, officer agent, or employee of the City of Carlsbad is personally interested, directly or indirectly, in this Contract, or the compensation to be paid hereunder; that no representation, oral or in writing, of the City Council, its of ficers, agents, or employees has inducted him/her to enter into this Contract, excepting only those contained in this form of Contract and the papers made a part hereof by its terms; and
2. That this bid is made without connection with any person, firm, or corporation making a bid for the same work, and is in all respects fair and without collusion or fraud.
Accompanying this proposal is _____________________________ _ (Cash, Certified Check, Bond or Cashier's Check) for ten percent (10%) of the amount bid.
The Undersigned is aware of the provisions of section 3700 of the Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self - insurance in accordance with the provisions of that code and agrees to comply with such provisions before commencing the performance of the work of this Contract and continue to comply until the contract is complete.
The Undersigned is aware of the provisions of the Labor Code, Part 7, Chapter 1, Article 2, relative to the general prevailing rate of wages for each craft or type of worker needed to execute the Contract and agrees to comply with its provisions.
Contract No. 5554 - PWS27-4091UTIL 9
Addendum No. 3
IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:
(1) Name under which business is conducted _______________________________________
(2) Signature (given and surname) of proprietor ______________________________________
(3) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
IF A PARTNERSHIP, SIGN HERE:
(1) Name under which business is conducted _______________________________________
(2) Signature (given and surname and character of partner) (Note: Signature must be made by a general partner)
_________________________________________________________________________
_________________________________________________________________________
(3) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
Contract No. 5554 - PWS27-4091UTIL 10
Addendum No. 3
IF A CORPORATION, SIGN HERE:
(1) Name under which business is conducted _______________________________________
__________________________________________________________________________
(2) _________________________________________________________________________ (Signature)
____________________________________________________________________________ (Title)
Impress Corporate Seal here
(3) Incorporated under the laws of the State of _______________________________________
(4) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(5) Zip Code _____________________ Telephone No. _______________________________
(6) E-Mail ___________________________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE
ATTACHED
List below names of president, vice president, secretary and assistant secretary, if a corporation; if a partnership, list names of all general partners, and managing partners:
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
Contract No. 5554 - PWS27-4091UTIL 11
Addendum No. 3
ATTACHMENT B
(Revised)
Appendix G
SDGE Electric Service Request
Additional Address Info:
PROCEDURE FOR INSTALLATION
1. PHONE DIG ALERT "811" AT LEAST TWO DAYS PRIOR TO TRENCHING FOR LOCATION OF UNDERGROUND UTILITIES.
2. Phone Operations Assistant at 760-432-5805 for the following:
- 3 Working days prior to trenching to arrange pre-meet with inspector and initiate trenching process. - After excavation of trench, installation of conduit and service entrance equipment at meter location, CALL FOR INSPECTION. Do not cover conduit without inspector's written approval to backfill. - When trench is backfilled and compacted, CALL FOR INSPECTION. - If service entrance equipment is installed after backfill, CALL FOR INSPECTION OF THE EQUIPMENT.
3. Meter cannot be set until inspector has approved installation, including service equipment, and receipt of city/county/state inspection Metering: Self-Contained Meter Clips: 7
Utilities Maximum Contribution to Fault Current: 42000Phase: 3# of Wires: 4 Voltage: 120/240
Bend Info: 4" 90 DEG 36"R DB100Bend Type: HANDHOLE
Riser Quad: Stop Trench: from PoleLadder Arms:
Standards Page: Handhole Lid Shall Read:
Structure #: SCUSTOMER HHStation ID #: 303-470
Temp Service Charge Due $ 0.00
Assessor's Parcel Number: Additional Information:
Please call your Operations Assistant at 760-432-5805 with questions about application, inspection, construction installation and to schedule a crew.
Number/Size of Main Switch: 200Service Panel Rating: 200 Conduit Size: 1-4"Conduit Installed By: CUSTOMER
Customer Phone #: 442-339-2305Customer POC: Neil Irani
Wanted Date: ON INSPECTION
Job #:
ELECTRIC UNDERGROUND METER & SERVICE LOCATION
Customer Copy
Project Title: 4010 CARLSBAD BLVD
Notification #: 300000706400
Project Address: 4020 CARLSBAD BLVD
Customer Type: Commercial
Date Prepared: 08/11/2025
Project City: CARLSBAD
SDGE Contact: Operations Assistant Contact Info: OPERATIONS ASSISTANT,760-432-5805 Service Type: UG SERVICE REWIRE/RELOCATION
TB: -
SERVICE ATTACHMENT POINT AND/OR METER LOCATION:
Locate the new 200 amp NEMA 3R gear at location shown on sketch. Customer is to provide all excavation, trench, 1-4" conduit, backfill, compaction, 3/4" pulling and measuring tape in conduit and surface repair from customer handhole to new meter panel. Customer to provide & maintain 3'X3' clear and level workspace in front of meter, brush needs to be removed. Take conduit to within distance as instructed by SDG&E inspector. Prior to digging, please contact the Operations Assistant at 760-432- 5805 to schedule a pre-construction meeting with your trench inspector.
SDG&E Application Required-Call: 1-800-411-7343
Municipal Inspection required By: CITY OF CARLSBAD
Bend Installed By: CUSTOMER
Handhole Installed By:
Traffic Control Permit Required
Excavation/Encroachment Permits Required By: Customer
Joint Trench With: Electric
Right of Way Required
Meter height -- 4'0'' min. (3'0" min. for multiple installation) -- 6'3" max. From finish grade to centerline of meter base. Meters are required to be readily accessible 24 hours per day. Meters must be located in a safe area free of any potentially hazardous or dangerous condition.
Provide 3-ft. x 3-ft. clear and level working space in front of meter. Where meter room is proposed, contact the planner at the nearest SDG&E office. Meter bases and meter service disconnects must be located at or immediately adjacent to each other and be identified with address and unit number.
If SDG&E encounters hazardous or toxic material while performing construction of your project, SDG&E will halt work immediately and it will be your responsibility to remove and or clean up all hazardous or toxic material prior to SDG&E continuing construction. SDG&E shall have no liability or obligation whatsoever to cleanup, remove or remediate any hazardous or toxic materials discovered during the course of construction unless it is through negligence of SDG&E.
Customer-owned facilities to receive gas service are subject to all applicable local and state of California inspection authority requirements.
Building address and/or houseline must be permanently identified prior to meter set. Barrier posts may be required based on field conditions at any time prior to meter set as determined by the SDG&E Representative. Per Rule 16.A.1.a. In compliance with Section 783 of the Public Utilities Code, SDG&E will apply only those construction and design specifications, standards, terms, and conditions that are applicable to a new extension of service project for the 18 months following the date the application for a new extension of service project is approved. Keep this notice with your building permit.
All installations performed under this order must meet SDG&E standards unless a written deviation has been approved.
Planned By: Douglas Pearce Phone#: 8586540236
Contract No. 5554 - PWS27-4091UTIL 12
Addendum No. 3
ATTACHMENT C
(Add)
Appendix H
Geotechnical Report
i
KLEINFELDER
I
I
I
I
I
A report prepared for:
Carlsbad Municipal Water District
5950 El Camino Real
Carlsbad, California 92008
Attn: Mr. Randy Klaahsen, Associate Engineer
LIMITED SOILS EXPLORATION
CHINQUAPIN LIFT STATION
CARLSBAD, CALIFORNIA
Kleinfelder Job No. 51-521902
Prepared by:
Kevin R. Wells
Staff Engineer
KLEINFELDER, INC.
5015ShorehamPlace
San Diego, California 92122
(619)320-2000
May 21, 1999
Rick E. Larson
Senior Engineer
51-521902/5119R258.doc
Copyright 1999 Kleinfelder, Inc.
Page ii of iv May 21, 1999
c
C
51-521902/51iyK2D8.aoc
Copyright 1999 Kleinfelder, Inc.
I
I
c
c
E
E
i
c
c
KLEINFELDER
TABLE OF CONTENTS
Section Page
1.0 INTRODUCTION 1
2.0 PROJECT DESCRIPTION 2
3.0 FIELD EXPLORATION 3
4.0 LABORATORY TESTING 4
5.0 SUBSURFACE CONDITIONS 5
6.0 CONCLUSIONS 6
7.0 RECOMMENDATIONS 7
7.1 SITE PREPARATION AND EARTHWORK 7
7.1.1 Subgrade Preparation 7
7.1.2 Subgrade Preparation - Below Grade Structures 7
7.1.3 Remedial Grading Requirements 8
7.2 REVIEW OF PROPOSED PAVEMENTS/PAVEMENT SUBGRADE
PREPARATION 8
7.3 CONSTRUCTION DEWATERING 9
7.4 EXCAVATIONS 10
7.4.1 Excavations and Stability 10
7.4.2 Buried Vault and Wetwell Excavation 11
7.4.3 Pipe Bedding for Utilities 11
7.4.4 Backfill 12
7.5 SHORING '. 12
7.5.1 General 12
7.5.2 Lagging 12
7.5.3 Active Earth Pressures 13
7.5.4 Surcharge Pressures 13
7.5.5 Lateral Resistance 13
7.5.6 Estimated Lateral Displacements 14
7.6 BUILDING FOUNDATIONS AND FLOOR SLABS 14
7.6.1 Wetwell and Utility Vault Foundations and Floor Slabs 14
7.6.2 Generator Enclosure Foundation and Floor Slab 15
7.6.3 Exterior Slabs 16
7.6.4 Foundations for Free Standing Posts 16
7.7 UNIFORM BUILDING CODE SEISMIC DESIGN PARAMETERS 16
7.8 LATERAL EARTH PRESSURES 17
7.8.1 Lateral Earth Pressures for Utility Vault and Wetwell 17
7.8.2 Lateral Earth Pressures for Above-Grade Retaining Walls 17
7.9 BURIED UTILITY PIPE SOIL PARAMETERS 19
8.0 LIMITATIONS 20
IP*
51-521902/5119R258.doc Pageiiiofiv May 21, 1999
m Copyright 1999 Kleinfelder, Inc.
rL
KLEINFELDER
TABLE OF CONTENTS (continued)
P, FIGURES
fa* Figure 1 - Vicinity Map
r Figure 2 - Boring Location Plan
APPENDICES
ry Appendix A - Boring Logs
Appendix B - Laboratory Testing
Appendix C - Suggested Guidelines for Earthwork Construction C Appendix D - ASFE Insert
C
C
E
C
i
E
i
G
E
E
C
51-521902/5119R258.doc Pageivofiv May 21, 1999
Copyright 1999 Kleinfelder, Inc.
E
KLEINFELDER
r
E
E
C
c
2.0 PROJECT DESCRIPTION
*-< We understand that the project will consists of a new lift station to be developed at an unimproved site located at the west end of Chinquapin Avenue, adjacent to Carlsbad Boulevard. *•« The new lift station will include an at-grade electrical generator enclosure (12 feet by 14 feet in —« plan area), a valve and meter vault (10 feet deep and 8 feet by 8 feet in plan area), and a wetwell — (16 feet deep and 8 feet in diameter). In addition, a new concrete driveway, paved parking, and I-* associated hardscaped areas will be incorporated into the project. «"• We anticipate that the generator enclosure will be constructed of cast-in-place concrete or *" reinforced masonry block retaining walls set against an existing hillside in the northern part of ** the site. Wetwell and vault structures are expected to have sidewalls constructed of cast-in-place ta concrete that are tied into a conventional slab-on-grade designs. The proposed finished grade f elevation for the project is expected to be at an approximate elevation of 24 feet to 25 feet MSL.
The majority of the proposed plan area is relatively flat. An existing hillside, sloping downward f into the proposed site area, exists within the northern edge of the site.
L
51 -521902/5119R258.doc Page 2 of 20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
r
r
c
E
E
3.0 FIELD EXPLORATION
M A single test boring was completed at the approximate location shown on Figure 2. We had .-, intended to complete the boring to a depth of approximately 25 feet below the existing ground — surface, but we encountered effective auger refusal at a depth of 14 feet in both locations we _ attempted to drill. The test boring was advanced using an Ingersoll-Rand A-300 truck-mounted *M drill equipped with an 8-inch hollow-stem auger. Soil samples were obtained at nominal 5-foot •* intervals with a 3-inch outside diameter California sampler. The California sampler was lined *«" with 2.5-inch diameter brass sleeves. The sampler was driven 18 inches using a 140-pound m» hammer falling 30 inches.
to
f» The number of blows required to drive each 6-inch increment was recorded, and the blow counts ^ for each foot of drive is reported on the boring log. In addition to the blow counts, the boring log p» describes the earth materials encountered. The boundaries between soil layers shown on the log •* are approximate because the transitions between different soil layers are likely to be gradual. 51-52190275119R258.doc Page 3 of 20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
I 4.0 LABORATORY TESTING
H The geotechnical laboratory program included tests for gradation, moisture content, and dry unit _ weight. The gradation test results are included in Appendix B; the moisture content and unit m
rL
rL
C
L
r*
L
weight test results are also included in Appendix B.
L
P»
C
C
51-521902/5119R258.doc Page4of20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
C
|jp| KLEIN FELDER
c
c
r
c
c
c
5.0 SUBSURFACE CONDITIONS
AH The subsurface conditions encountered during our field exploration consisted of medium dense p to dense, medium to coarse grained silty sands (SM) within the upper ten feet of subgrade.
Itf Below ten feet the subgrade primarily consists of dense, relatively clean, coarse-grained sands (SP). These soils represent the dense to very dense terrace deposits exposed along the shore.
Effective auger refusal was encountered in very dense terrace deposits at 14 feet of drilling depth. An identical refusal depth was achieved in a subsequent exploratory boring. We anticipate these terrace deposits may be partially cemented to some degree.
No groundwater was encountered within 14 feet of the ground surface at the boring location.
However, based on known elevations of the local water table, we anticipate that the local groundwater table should be at or below a depth of 18 feet (6 feet MSL), which is about 2 feet below the bottom of the wetwell. If groundwater is encountered at a higher elevation, we anticipate that it will likely be a light seepage from a localized strata within the terrace deposit. 51-521902/5119R258.doc Page5of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
E
C
r
r
C
C
E
C
6.0 CONCLUSIONS
f*
if Based on limited exploration, the site appears generally suitable for the proposed projects from a geotechnical standpoint. The project can be supported on conventional foundations and floor slabs. The only anticipated impact to the construction of the project may be that the terrace deposits found below a depth of 14 feet have the potential for difficult excavation. Use of a jackhammer to break cemented portions of the terrace deposits may be required.
If seepage is encountered in the bottom of the deeper excavations, we anticipate that the flows will be low enough for use of conventional sumping. The bottom of the excavation is expected to be founded in material that should not lose any significant stability if seepage is encountered. 51-521902/5119R258.doc Page6of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
i
C
C
C
C
C
7.0 RECOMMENDATIONS
7.1 SITE PREPARATION AND EARTHWORK
Prior to site preparation, all surficial organic material and debris should be removed in general accordance with the recommendations presented in Appendix C.
7.1.1 Subgrade Preparation
Subgrade preparation for the generator enclosure may be achieved by scarifying the top six P inches of subgrade underlying the generator slab. Scarified soils should then be moisture conditioned to within 1 percent below to 3 percent above optimum moisture content and ^* compacted to at least 90 percent of ASTM D1557. Any material encountered larger than 3 IM inches in diameter should be removed. Wall/retaining wall footings enclosing the generator pad P may be excavated into the existing native subgrade without further improvement provided that the excavated footing subgrade meets minimum bearing requirements. A Kleinfelder staff P representative should be attained by the Contractor for inspection of the excavated footings.
P 7.1.2 Subgrade Preparation — Below Grade Structures
„, Foundation subgrades for below-grade structures (i.e., wetwell and utility vault) will not require to any improvement to undisturbed soils immediately underlying the subgrade for footings and P* concrete slab support. Subgrades for these structures should be excavated to proposed footing to and slab elevations with little or no disturbance to the underlying native soil conditions. Any p. excavation below these elevations should be recompacted with on-site soils in general *• accordance with the recommendations contained in Appendix C. However, if groundwater is resent that will not allow construction of a firm, stable foundation bottom, then the underlying soils should be overexcavated to a depth of 18 inches below the foundation level. This 18 inches of additional removal should be replaced with 3/4-inch crushed drain rock (5% maximum passing the No. 4 sieve). The drain rock should be placed in two 9-inch thick lifts. Each lift should be compacted with 3 passes of a vibratory baseplate compactor to seat the drain rock. r
Copyright 1999 Kleinfelder, Inc.
I 51-521902/5119R258.doc Page7of20 May 21, 1999
c
KLEINFELDER
7.1.3 Remedial Grading Requirements
Existing subgrades to receive fill should be scarified to a depth of 6 inches and recompacted to 90 percent of ASTM D1557. All subsequent placement of engineered fill should be placed in loose horizontal lifts no greater than eight inches in thickness, moisture conditioned between 1 percent above to 3 percent above optimum moisture content, and compacted to a minimum of 90 t* percent relative compaction. The exposed faces of fill slopes should be constructed at a slope of 2 horizontal to 1 vertical or flatter. Free standing permanent cut slopes should be cut back at a slope f* of 2 horizontal to 1 vertical, or flatter. Steeper cut slopes may require construction of retaining walls and/or a specific case-by-case slope stability analysis. r
L When properly moisture conditioned, the on-site soils can be used as engineered fill. If import fill is ^ required, we recommend that it be a granular soil meeting the following requirements:
f* Liquid Limit: Less than 30
Plasticity Index: Less than or equal to 15
i Percent passing No. 200 sieve: Less than 30
b
Maximum particle dimension: Less than three inches
I
C
Proposed import fill should be submitted to the geotechnical engineer for review and testing to verify conformance to these requirements. All imported fill should be compacted to the general recommendations provided for engineered fill.
All site preparation and fill placement should be observed and tested by a representative of our firm.
This is especially true during the scarification process so that we cai undesirable material or conditions are encountered in the construction area.
I This is especially true during the scarification process so that we can observe whether anyIw rL
7.2 REVIEW OF PROPOSED PAVEMENTS/PAVEMENT SUBGRADE PREPARATION *»
i
** The proposed pavement sections (4-inch asphaltic concrete over 6 inches Class 2 aggregate base P as referenced in the Construction Plans for the Chinquapin Sewer Lift Station - Sheet No. 7) p
Copyright 1999 Kleinfelder, Inc.
I 51-521902/5119R258.doc Page 8 of 20 May 21, 1999
c
i
c
c
KLEINFELDER
should be adequate to support wheel loads for driveway and parking areas provided that subgrade soil are consistent with what we encountered in our test boring.
Pavement subgrades founded on native material or engineered fill soils should be processed to a depth of 6 inches below grade and should consist of soils exhibiting a low expansion potential.
Subsequent compaction of subgrade soils should be placed in lifts no greater than eight-inch uniform loose thickness and compacted to a minimum of 95 percent of ASTM D1557 maximum dry density at a moisture content of 1 percent below to 3 percent above optimum.
E
E
E
p»i
to
Asphalt concrete pavement and aggregate base materials used should conform to Section 02510, IP Parts 2 and 3 of the standard specification referred in Section 1.4 of the Standard Specifications for Construction of Public Works (Green Book), current edition.
7.3 CONSTRUCTION DEWATERING
Based on the information provided, the maximum depth of excavation for the wetwell is I expected to be about 16 feet. Since we anticipate groundwater will be at or below a depth of 18 In
feet we do not expect that groundwater should be a significant issue. Excavations which extend i near or below the site groundwater level (currently estimated to be at approximately 18 feet to 19 feet below existing grade, but subject to future variations) may need to be dewatered in order to f" . .i maintain the stability of the excavation bottom. If at the time of excavation of below-grade structures the stability of the excavated bottom is compromised, groundwater levels should be IP*f drawn down a minimum of two feet below the lowest portion of the excavation. The groundwater level should be maintained below the recommended level until the backfill has been f*»| completed to an elevation of at least five feet above the pre-dewatering elevation.
Analysis of contractor dewatering needs or the design of contractor dewatering systems were not within the scope of our services. This work is best accomplished by a competent dewatering contractor. However, we have included some discussions of potential dewatering methods in the following paragraphs.
51-521902/5119R258.doc Page9of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
c
[
c
c
c
C
c
E
E
KLEINFELDER
The most common method of dewatering used in the removal of nuisance seepage water from terrace deposits/formations is conventional sump pumping. The method ultimately selected is dependent on a number of factors, e.g., quantity of groundwater to be removed, cone of depression (zone of influence) of dewatering measures within the excavation, stability of the silty sands, the presence of potential seepage zones which will pipe water from distant sources after the groundwater table is lowered, and cost.
The Regional Water Quality Control Board is likely to restrict the discharge of water pumped from excavations. Temporary construction dewatering will require an NPDES permit for discharge unless the water is discharged to a sanitary sewer system, which will still require approval from the City.
L 7.4 EXCAVATIONS
i 7.4.1 Excavations and Stability
IP* All excavation work should comply with the current requirements of OSHA. The onsite soils are •» generally classified as the Type B soils for evaluating OSHA sloping or shoring requirements. ^I
*• All discussion in this section regarding stable excavation slopes assumes minimal equipment f« vibration and adequate setback of excavated materials and construction equipment from the •* foundation excavation. We recommend the minimum setback distance from the near edge of he excavation be equivalent to the adjacent excavation depth. If excavated materials are stockpiled adjacent to the excavation, the weight of this material should be considered as a surcharge load f* for lateral earth pressure calculations. Configuration values presented in the OSHA regulations I** assume that the soils in the cut face do not change in moisture content significantly. Slope f" configuration estimates should not be considered applicable for personnel safety. The contractor must determine slopes for safety of personnel and meet all regulations covering excavation stability and safety.
51-521902/5119R258.doc PagelOof20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
C Ml KLEINFELDER
c
c
c
7.4.2 Buried Vault and Wetwell Excavation
Excavations made below a depth of 14 feet may be difficult for light to medium backhoes and may require jacking or ripping. If wet or unstable subgrade conditions are encountered at the bottom of the excavation, we recommend the bottom of the vault or wetwell area be overexcavated by at least 18 inches below the design elevation of the bottom of the structure.
P The bottom of the excavation should then be cleaned of any loose debris and backfilled with 3/4-inch crushed aggregate drain rock as described earlier. The 3/4-inch drain rock should be P placed in two 9-inch thick loose lifts and compacted with three passes of a vibratory base plate compactor. The vibrating compactor should have a minimum weight of 200 pounds and a P minimum vibrating frequency of 1,600 cycles per minute. The initial lift may be increased to 12 inches if "pumping" of the aggregate base occurs during initial compaction.
P
7.4.3 Pipe Bedding for Utilities
f»
i» Granular pipe bedding should be sand, gravel, or crushed aggregate with a sand equivalent of not p. less than 30. Onsite materials are generally too silty to meet this requirement. Bedding should be i* extended the full width of the trench to one foot above the top of the pipe. The pipe bedding should pi be densified to 90 percent relative compaction prior to backfilling. Densification of pipe bedding i
^ can be accomplished by either jetting with water or by mechanical compaction. If water jetting is P» permitted, the size and length of jet pipe, quantities of water, and jetting locations should be •• established in the field at the time of construction and should be sufficient to thoroughly saturate P» and densify the bedding material around the pipe. Jetting should be accomplished by use of a jet •* pipe (1-1/2 inch minimum diameter pipe) to which a minimum 2-inch diameter hose is attached f» carrying a continuous supply of water under pressure. The bedding should be allowed to drain •* thoroughly until the surface of the bedding is in a firm and unyielding condition prior to commencement of any subsequent improvements. The specifications should require the contractor to provide an sump and pump to remove any accumulated water which remains. Compaction of the pipe bedding by mechanical means is acceptable provided the specifications require compacting with pneumatic "powder puffs" and periodic density testing (which will require the contractor to provide special excavation for access and shoring).
C
c
E
51-521902/5119R258.doc Page 11 of 20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
E
E
C
KLEINFELDER
7.4.4 Backfill
The onsite soils can be used as backfill above the pipe zone; however, the soils excavated from below the water table may be too moist in their present condition to allow proper compaction f" within deep excavations without allowing them to dry out. If imported backfill is required, we •w recommend that it meet the following requirements:
F*i
Liquid Limit: Less than 30%
** Plasticity Index: Less than or equal to 15%
to
Percent Soil Passing No. 200 Sieve: Less than 30%
f" Maximum Particle Dimension: Less than 3 inches
UBC Expansion Index: Less than 30
r Soluble Sulfates: Less than 0.10%
IM
P Trench backfill should be placed in uniform layers not exceeding 8 inches in loose thickness, moisture conditioned to within two percentage points of optimum, and mechanically compacted. f* The relative compaction should be to at least 90 percent. f 7.5 SHORING
IP* 7.5.1 General
to
Shoring may be required where space or other restrictions do not allow a sloped embankment. A rL conventional shoring system consisting of closely spaced soldier piles or sheet piles may be used.
7.5.2 Lagging
f*
L Timber lagging may be used between the soldier piles to support loose or soft soils. If lagging is to f™ be left in place, treated lumber should be used. Lagging should be designed for the full lateral pressure recommended below. If possible, structural walls should be cast directly against the shoring, eliminating the need for backfilling a narrow space. However, special provisions for wall c
E
r
51-521902/5119R258.doc Pagel2of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
c
E
i
L
I
C
c
E
C
KLEINFELDER
drainage (such as the use of prefabricated composite drain) may be required where this type of construction is used.
7.5.3 Active Earth Pressures
Cantilevered shoring systems should be designed to resist an active earth pressure equivalent to a fluid weighing 35 pounds per cubic foot (pcf). Braced excavations should be designed to resist a uniform horizontal soil pressure of 22H (in pounds per square foot, psf), where H is the wall height in feet.
7.5.4 Surcharge Pressures
_. Thirty percent of any area surcharge placed adjacent to the shoring may be assumed to act as a L uniform horizontal pressure against the shoring. Special cases such as combinations of sloping and p» shoring or other surcharge loads (not specified above) may require an increase in the design values i
i» recommended above. These conditions should be evaluated by the project geotechnical engineer on p. a case-by-case basis.
IH
P. The above pressures do not include hydrostatic pressures; it is assumed that temporary hydrostatic •» pressures will be relieved by dewatering outside the excavation or that drainage will be provided by weep holes or spaces in the lagging.
P» 7.5.5 Lateral Resistance
!•
All soldier or sheet piles should extend to a sufficient depth below the excavation bottom to rL provide the required lateral resistance. We recommend required, embedment depths be calculated using methods for evaluating sheet pile walls and based on the principles of force and moment equilibrium. For this method, the allowable passive pressure against soldier piles which extend below the level of excavation may be assumed to be equivalent to a fluid weighing 250 pcf above the groundwater table and 125 pcf below the groundwater table. To account for three- dimensional effects, the passive pressure may be assumed to act on an area two times the width of the embedded portion of the pile, provided adjacent piles are spaced at least three diameters, mI 51-521902/5119R258.doc Page 13 of 20 May 21,1999
• Copyright 1999 Kleinfelder, Inc.
E
C
C
C
C
C
KLEINFELDER
center-to-center. Additionally, we recommend a factor of safety of 1.2 to be applied to the calculated embedment depth and that the passive pressure be limited to 2,500 psf.
Alternatively, lateral capacity of a soldier pile extending below the excavation bottom may be evaluated using the "Pole Formula" given in Section 1806.8 of the Uniform Building Code, 1997 edition. For this method, we recommend a lateral soil bearing pressure of 150 pounds per square foot of embedment may be used to estimate the required embedment depth. The 100 percent increase allowed by the Code for isolated poles (which are not adversely affected by a 1/2 inch horizontal deflection at the ground surface due to short-term lateral loads) may be used.
7.5.6 Estimated Lateral Displacements
f* Lateral movement of a shored excavation will depend on the type and relative stiffness of the system used and other factors beyond the scope of this study. However, based on our experience f" with projects with similar shoring requirements, we anticipate maximum lateral movement of the shoring system should generally be less than two inches. r
L
7.6 BUILDING FOUNDATIONS AND FLOOR SLABS
r
J*» 7.6.1 Wetwell and Utility Vault Foundations and Floor Slabs 1 Conventional spread footings supported on native soils compacted as recommended in Section
7.3.2 can be sized using a nominal bearing pressure of 2,000 psf. This value may be increased r[ by one third for seismic or wind loads. The foundations should be a minimum of 12 inches wide.
The allowable soil bearing pressure may be increased by 1/3 for wind and seismic loading. i Unless the average applied load of the structure exceeds the weight of the displaced soil significantly, we do not anticipate static settlement in excess of 1/2 to one inch. We recommend that the footings be provided with at least minimal reinforcement consisting of four No. 4 reinforcing bars, two placed at the top and two at the bottom.
Resistance to lateral loads on foundation footings may be calculated using a passive equivalent fluid unit weight of 250 pcf and a coefficient of friction of 0.35. Uplift resistance may be 51-521902/5119R258.doc Pagel4of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
r
i.
c
c
KLEINFELDER
calculated using the dead weight of the structure plus the friction along the walls of the structure.
An average value of 500 psf can be used to calculate frictional resistance to uplift. In actuality, the frictional resistance increases in a triangular fashion with depth to a critical point below which the frictional resistance is assumed to be constant. However, for general design purposes, the recommended average value can be used regardless of depth. The surface area of the upper two feet of the structure should be neglected in these calculations. , We recommend the concrete floor slabs for buried structures be at least five inches thick and be ?*jy reinforced with at least No. 3 steel reinforcing bars at 18-inch centers (both ways) or No. 4 steel reinforcing bars at 24-inch centers (both ways). These reinforcement guidelines should not L supercede the reinforcement requirements calculated by the structural engineer. ^ 7.6.2 Generator Enclosure Foundation and Floor Slab
', Conventional shallow spread footings may be used to support the intended foundation loads.
Footings and sidewalls for the north and east sides of the enclosure are expected to be of F* retaining wall type. Footings may be designed for support upon engineered fill using an allowable soil contact pressure of 2,000 pounds per square foot for dead load plus normal live j load. This value may be increased by one third for seismic or wind loads. Resistance to lateral forces may be computed using lateral bearing and lateral sliding combined. Lateral bearing may | be computed as 150 pounds per square foot per foot of depth below natural grade. Lateral sliding resistance can be obtained by multiplying 0.35 by the dead load.
I
All footings should be trenched at least 12 inches below the lowest adjacent finished grade and i should be a minimum of 1 foot in width. Reinforcement steel requirements for foundations should be designed by the structural engineer. As a minimum, we recommend that continuous [ footing reinforcement consist of at least two No. 4 bars placed at the top and two placed at the bottom of the foundation. These reinforcement guidelines should not supersede the•»-» [ reinforcement requirements calculated by the structural engineer. rL
51-521902/5119R258.doc Page 15 of 20 May 21,1999
Copyright 1999 Kleinfelder, Inc.
c
c
KLEINFELDER
G
C
Total and differential static settlements are expected to be less than 1/2 inch for these loading conditions. We further expect that settlements will occur rather quickly as the loads are applied.
Therefore, the majority of the settlement should occur during the construction phase when the loads on the structures often reach their average maximum.
The floor slab for the generator enclosure should be prepared in accordance with the recommendations presented in Section 7.5.3.
y 7.6.3 Exterior Slabs
P Exterior concrete non-vehicular hardscape areas supported on select soil, as specified earlier in this report, should be at least 5 inches thick and reinforced with No. 3 rebars at 18-inch spacing f" in both directions. To reduce the effects of cracking, we recommend that expansion relief joints be placed at maximum distances of approximately 15 feet in both directions in large sections f" (such as courtyards), and every 5 feet for narrow sections (such as sidewalks). Use of a slab h. underlay, as described above for interior slabs, would only be required if moisture-sensitive slab I treatments are used.
to
| 7.6.4 Foundations for Free Standing Posts
P« Construction employing posts or poles as columns embedded in earth or embedded in concrete ** footings in the earth to resist both axial and lateral loads (such as for light standards) can be P" designed in general accordance with Section 1806.8 of the Uniform Building Code. However, we l- recommend that a lateral soil-bearing pressure of 200 psf per foot of depth below natural grade be p« used for parameter Si and 83 rather than one of the values given in Table 18-I-A. An allowable soil- ** bearing pressure of 2,500 psf may be used to support vertical loads. ^ 7.7 UNIFORM BUILDING CODE SEISMIC DESIGN PARAMETERS
^ Since this site is located in the seismically active Southern California region, we recommend that, as a minimum, the proposed development be designed in accordance with the requirements ^ of the latest (1997) edition of the Uniform Building Code (UBC) for Seismic Zone 4. We L
51-521902/5119R258.doc Page 16 of 20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
P»
i
IH
c
I
c
f*
L
L
r
r
L
KLEINFELDER
recommend that a soil profile factor of SD be used with the UBC design procedure (Table 16-J).
Near source seismic coefficients for acceleration and velocity, Na=1.0 and Nv=l.l (UBC Tables 16-S and 16-T), should be used in design.
7.8 LATERAL EARTH PRESSURES
7.8.1 Lateral Earth Pressures for Utility Vault and Wetwell L
_ Lateral earth pressures acting against buried walls can be calculated assuming that the retained ^^
IH soils act as a fluid. The equivalent fluid weight (efw) for walls which are restrained at the top or p. are sensitive to movement and tilting should be designed for the at-rest efw. If on-site or L imported non-expansive sandy soils with a Unified Soil Classification of SP, SM, or SC are used p. as backfill, an at-rest efw value of 60 pcf can be used above the water table and 90 pcf below the in water table (if encountered).
c«
*• Fifty and thirty percent of any uniform area surcharge placed at the top of the wall may be _ assumed to act as a uniform horizontal pressure over the entire wall. We should be contactedi *• where point or live loads are expected so we can provide recommendations for additional wall *• stresses. Also, permanent walls should be designed for seismic loading. The resultant seismic >*• force (in pounds) can be calculated as 13H2 where H is the height of the wall (in feet) above its P» base. The resultant seismic force acts at 0.6H above the wall base. For combined effects of **• static and seismic forces, a minimum factor of safety of 1 .2 is recommended. r*
i
•* 7.8.2 Lateral Earth Pressures for Above-Grade Retaining Walls For planning purposes, the following lateral earth pressures values for. level or sloping backfill are provided for walls backfilled with drainage materials and imported nonexpansive soils. 51-52190275119R258.doc Pagel7of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
EQUIVALENT FLUID WEIGHT (pcf)
E
r
E
r
c
L
f*
I
Conditions
Active
At-Rest
Passive (Fill Soils)
Passive
(Formational Materials)
'"'•"<' LeveP-'
35 55
300
(Maximum of 3 ksf)
400
(Maximum of 3 ksf)
2:1 Slope
50 70
150*
200*
3:1 Slope
45 65
200*
300*
Passive values for slope conditions are for a descending (sloping down) slope condition.
Unrestrained (yielding) cantilever walls should be designed for an active equivalent fluid weight value provided above. In the design of restrained (nonyielding) walls where the top of the wall is not expected to move laterally more than 0.001H, (where H is the unbalanced wall height), the at-rest pressures should be used. The above values assume nonexpansive backfill and free- draining conditions. The native silty sands should be suitable for wall backfill provided they meet the general backfill requirements presented in Section 7.1.3.
All retaining wall structures should be provided with appropriate drainage. Since the design retaining walls are to enclose the generator slab area, drainage design may incorporate the use of a manufactured drain panel behind the retaining wall in addition to normal waterproofing. This system generally consists of a drain panel lined with filter fabric. At the wall base, we recommend that a minimum of the bottom 24 inches of the drain panel and the gravel surrounding the perforated PVC drain be wrapped in filter cloth (Mirafi 140N or equivalent).
The pipe should be surrounded by approximately two cubic feet of clean gravel per foot of wall length. The pipe should be sloped to drain to a suitable outlet or cleanouts should be provided at appropriate intervals.
C
Wall backfill should be compacted by mechanical methods to at least 90 percent relative compaction in accordance with ASTM D1557.
L
C
Retaining walls that incorporate slab-on-grade support for the general enclosure may be designed for support upon engineered fill using an allowable soil contact pressure of 2,000 pound per square foot for dead load plus normal live load. This value may be increased by one third for 51-521902/5119R258.doc
Copyright 1999 Kleinfelder, Inc.
pL
E
1 KLEINFELDER
seismic or wind loads. Resistance to lateral forces may be computed using lateral bearing and lateral sliding combined. Lateral bearing may be computed as 150 pounds per square foot per foot of depth below natural grade. Lateral sliding resistance can be obtained by multiplying 0.35 by the dead load.
i
E
E
C
p
Surcharge loading may be calculated according to the City of San Diego Building Inspection Department Newsletter 23-3 or other equivalent methods. We should be contacted if unusual surcharge loadings are anticipated. Wall footings should be designed in accordance with the foundation design recommendations and reinforced in accordance with local codes and structure considerations.
7.9 BURIED UTILITY PIPE SOIL PARAMETERS
We recommend the following soil parameters for use in buried utility pipe design:
Total soil unit weight, yt =
Modulus of soil reaction, E' =
HOpcf
1,000 psi for pipe provided with gravel bedding (4 inch minimum thickness) and gravel pipe zone to one foot
over pipe.
400 psi where the pipe is constructed on native fill
without the gravel pipe zone and bedding.
L
C
C
C
E
51-52190275119R258.doc
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
E
I
I
E
8.0 LIMITATIONS
Recommendations contained in this report are based on our literature research, field observations, data from the field exploration, laboratory tests, and our present knowledge of the proposed construction. It is possible that soil conditions could vary between or beyond the points explored. If soil conditions are encountered during construction which differ from those described herein, our firm should be notified immediately in order that a review may be made and any supplemental recommendations provided.
P» If the scope of the proposed construction, including the proposed loads or structural locations, •• changes from that described in this report, we should also review our recommendations. f» Additionally, if information from this report is used in a way not described under the project "• description portion of this report, it is understood that it is being done at the designer's and P* owner's own risk.
IH
*•• Our firm has prepared this report for the use of Carlsbad Municipal Water District, on this •" project in substantial accordance with the generally accepted geotechnical engineering practice •• as it exists in the site area at the time of our study. No warranty is made or intended. The recommendations provided in this report are based on the assumption that an adequate program F« of tests and observations will be conducted by our firm during the construction phase in order to evaluate compliance with our recommendations.
This report may be used only by the client and only for the purposes stated, within a reasonable ^* time from its issuance. Land use, site conditions (both on-site and offsite) or other factors may change over time, and additional work may be required with the passage of time. Based on the ^ intended use of the report, Kleinfelder may require that additional work be performed and that an updated report be issued. Non-compliance with any of these requirements by the client or f* anyone else will release Kleinfelder from any liability resulting from the use of this report by any unauthorized party.
f*
L
L
51-521902/5119R258.doc Page20of20 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
pi
M
m
it
p
li
P
III
Pacific
Ocean
AGUA HEDIONDA
LAGOON
PALOMAR
COLLEGE
BLVD
APPROXIMATE GRAPHIC SCALE
(FEET)
VICINITY MAPKLEINFELDEU
CHINQUAPIN SEWER LIFT STATION
CARLSBAD MUNICIPAL WATER DISTRICT
CARLSBAD, CALIFORNIA
5015 SHOREHAM PLACE
SAN DIEGO, CALIFORNIA 92122
CHECKED BY:
DATE: . 5/20/99PROJECT NO. 51-4219-01
i i f i ii r i f i f i r i r i i i n 'i n ri rt
GENERATOR
ENCLOSURE METER AND
VALVE VAULT
LIFT STATION
WET WELL
Carlsbad Blvd.
100 200
APPROXIMATE GRAPHIC SCALE
(FEET)
LEGEND:
B1
APPROXIMATE BORING LOCATION
KLEINFELDER
5015 SHOREHAM PLACE
SAN DIEGO, CALIFORNIA 92122
CHECKED BY: : 5219SITE-1
PROJECT NO. 51-5219-01 [DATE: 5/20/99
SITE PLAN
CHINQUAPIN SEWER LIFT STATION
CARLSBAD MUNICIPAL WATER DISTRICT
CARLSBAD, CALIFORNIA
FIGURE
c
APPENDIX A
PROJECT NO.
51-5219-01 LOG OF BORING LEGEND SHEET 1 OF 1
DRILLING
EQUIPMENT
PROJECT NAME
PUMP STATION - CHINQUAPIN SITE
LOCATION
TYPE OF BIT HAMMER DATA: WT. LBS. DROP INCHES SURFACE
ELEVATION
TOP OF CASING
ELEVATION
STARTED:
COMPLETED:
BACKFILLED:
DRILLING AGENCY
LOGGED BY
SURFACE CONDITIONS
GROUNDWATER
ELEVATION DATE
SOIL DESCRIPTION
SAMPLE
NO. imo oo
NOTES
5-
6-
7-
8-
9-
10-
11-
12-
13-
14-
15-
16-
17-
18-
19-
20-
21-
22-
23-
24-
25-
26-
27-
28-
29-
•30-
FN: 5219LOG
WELL-GRADED GRAVELS AND GRAVEL-SAND
MIXTURES, LITTLE OR NO FINES
POORLY GRADED GRAVELS AND GRAVEL-SAND
MIXTURES, LITTLE OR NO FINES
SILTY GRAVELS, GRAVEL-SAND-SILT MIXTURES
CLAYEY GRAVELS, GRAVEL-SAND-CLAY MIXTURES
WELL-GRADED SANDS AND GRAVELLY SANDS,
LITTLE OR NO FINES
POORLY GRADED SANDS AND GRAVELLY SANDS,
LITTLE OR NO FINES
SILTY SANDS, SAND-SILT MIXTURES
CLAYEY SANDS, SAND-CLAY MIXTURES
INORGANIC SILTS, VERY FINE SANDS, ROCK
FLOUR, SILTY OR CLAYEY FINE SANDS
INORGANIC CLAYS OF LOW TO MEDIUM
PLASTICITY, GRAVELLY CLAYS, SANDY CLAYS,
SILTY CLAYS, LEAN CLAYS
ORGANIC SILTS AND ORGANIC SILTY CLAYS
OF LOW PLASTICITY
INORGANIC SILTS, MICACEOUS OR DIATOMACEOUS
FINE SANDS OR SILTS, ELASTIC SILTS
INORGANIC CLAYS OF HIGH PLASTICITY,
FAT CLAYS
ORGANIC CLAYS OF MEDIUM TO
HIGH PLASTICITY
PEAT, MUCK AND OTHER HIGHLY
ORGANIC SOILS
\7ATD WATER LEVEL AT TIME OF DRILLING
•= - WATER LEVEL MEASURED IN WELL
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
OL
MH
CH
OH
PT
BENTONITE
CAVED
AREA
CEMENT
CONCRETE
NATURAL
BACKFILL
BENTONITE
PACKER
SAND
BACKFILL
SAND
VOLCLAY
GROUT
PIPE
SLOTTED
PIPE
CONTINUOUS
SAMPLER
GRAB
SAMPLE
CALIFORNIA
I SAMPLER
MODIFIED
CALIFORNIA
SAMPLER
NO
RECOVERY
PITCHER
SAMPLER
SHELBY
TUBE
SAMPLER
STANDARD
PENETRATION
SAMPLER
KLEINFELDER
5015 SHOREHAM PLACE
SAN DIEGO, CALIFORNIA 92122 FIGURE NO. A1
PROJECT NO.
51-5219-01 LOG OF BORING 1 SHEET 1 OF
DRILLING
EQUIPMENT
IR A-300
PROJECT NAME
PUMP STATION - CHINQUAPIN SITE
LOCATION
SEE SITE PUN
TYPE OF BIT 8" HSA HAMMER DATA: WT. 1 40 LBS. DROP 30 INCHES SURFACE ELEVATION -24.5'
TOTAL DEPTH
OF HOLE 14'
STARTED: 4/27/99
COMPLETED: 4/27/99
BACKFILLED: 4/27/99
DRILLING AGENCY SCOTT'S DRILLING
LOGGED BY RMG
SURFACE CONDITIONS
BARE GOUND
GROUNDWATER
DEPTH DATE
Om
I
-0-
1-
2-
3-
4-
5-
6-
7-
8-
9-
10-
11-
12-
13-
14-
15-
16-
17-
18-
19-
20-
21-
22-
23-
24-
25-
26-
27-
28-
29-
'30-
FN: 5219LOG
LOG OF MATERIAL
SAMPLE
NO. m oo
LJ|
co 2:-:
00 NOTES
SILTY SAND, brown, moist, dense, medium to
coarse grained
SM
52 Medium dense, medium grained 31
SAND, yellow brown, moist, dense, with trace
gravel, coarse grained
Hard drilling noted @ 13 ft. (grinding on auger)
SP 45
Bottom of borehole @ 14' (refusal)
No free water observed
No caving observed
Boring backfilled with soil cuttings
KLEINFELDER
5015 SHOREHAM PLACE
SAN DIEGO, CALIFORNIA 92122 FIGURE NO.: A2
KLEINFELDER
APPENDIX B
LABORATORY TESTING
Chinquapin Lift Station
Carlsbad, California
GENERAL
Laboratory tests were performed on selected, representative samples as an aid in classifying the soils and to evaluate physical properties of the soils which may affect foundation design and construction procedures. A description of the laboratory testing program is presented below.
MOISTURE AND DENSITY
Moisture content and dry unit weight tests were performed on a number of samples recovered from the test borings. Moisture content and dry unit weight were evaluated in general accordance with ASTM Test Methods D2216 and D2937, respectively. Results of these tests are presented on the test boring logs in Appendix A.
SIEVE ANALYSES
Sieve analyses were performed on thirteen samples of the materials encountered at the site to evaluate the gradation characteristics of the soils and to aid in their classification. Tests were performed in general accordance with ASTM Test Method D422. Results of these tests are presented on Figures Bl through B13.
51-521902/5119R258.doc PageB-1 May 21,1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
TABLE B-l
MOISTURE CONTENT AND DRY UNIT WEIGHT
ASTM D216 AND D2937
Sample
B1-1C
Description
Tan Silty Sand
Moisture (%)
13.9 Dry Density (pcf)
110.0
51-521902/5119R258.doc
Copyright 1999 Kleinfelder, Inc.
Page B-2 May 21,1999
PERCENT FINER BY WEIGHT |
•
•
]
100
9 5
90 85
80 75
70 65
60 55
50 45
40 35
30 25
20 15
10 5
0 U.S. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS I HYDROMETER 6 4 3 2 1.5 1 3/4 1/23/8 3 4. 6 810 14 16 20 30 40 50 60 100140200 I I
\
!
-^
^ \i
\
1 \
\
\
\
\
\
1 '
\\
\
\
\
V.1
100 10 1 0.1 0.01
GRAIN SIZE IN MILLIMETERS
COBBLES GRAVEL
coarse fine
SAND
coarse medium fine SILT OR CLAY
Sample ID Depth
B1 8.0
Sample ID Depth
B1 8.0
Classification
BROWN, MEDIUM GRAINED SAND (SP-SM)
D100
4.75 D60
0.398
D30
0.258
••_• Kiel nfelder, Inc.
HdfH 5015 Shoreham Place
•>m-™ San Diego, CA 92122
Telephone: (619)320-2000
Fax: (619)320-2001
D10
0.152
LL PL
%Gravel %Sand
0.0 94.3
PI Cc
1.11 %Silt
0.001
Cu
2.63 %Clay
5.6 GRAIN SIZE DISTRIBUTION
CHINQUAPIN SEWER LIFT STATION FIGURE
CARLSBAD, CALIFORNIA _.
PROJECT NUMBER: 51-5219-02
KLEINFELDER
APPENDIX C
SUGGESTED GUIDELINES FOR EARTHWORK CONSTRUCTION
Chinquapin Lift Station
Carlsbad, California
1.0 GENERAL
1.1 Scope - The work done under these specifications shall include clearing, stripping, removal of unsuitable material, excavation, installation of subsurface drainage, preparation of natural soils, placement and compaction of on-site and imported fill material, and placement and compaction of pavement materials.
1.2 Contractor's Responsibility - A geotechnical investigation was performed for the project by Kleinfelder and presented in a report dated May 21, 1999.
The Contractor shall attentively examine the site in such a manner that he can correlate existing surface conditions with those presented in the geotechnical investigation report. He shall satisfy himself that the quality and quantity of exposed materials and subsurface soil or rock deposits have been satisfactorily represented by the Geotechnical Engineer's report and project drawings. Any discrepancy of prior knowledge to the Contractor or that is revealed through his investigations shall be made known to the Owner. It is the Contractor's responsibility to review the report prior to construction. The selection of equipment for use on the project and the order of work shall similarly be the Contractor's responsibility. The Contractor shall be responsible for providing equipment capable of completing the requirements included hi following sections.
1.3 Geotechnical Engineer - The work covered by these specifications shall be observed and tested by Kleinfelder, the Geotechnical Engineer, who shall be hired by the Owner. The Geotechnical Engineer will be present during the 51-521902/5119R258.doc
Copyright 1999 Kleinfelder, Inc.
PageC-1 May 21, 1999
KLEINFELDER
site preparation and grading to observe the work and to perform the tests necessary to evaluate material quality and compaction. The Geotechnical Engineer shall submit a report to the Owner, including a tabulation of tests performed. The costs of retesting unsuitable work installed by the Contractor shall be deducted by the Owner from the payments to the Contractor.
1.4 Standard Specifications - Where referred to in these specifications, "Standard Specifications" shall mean the current State of California Standard Specifications for Public Works Construction, 1994 Edition, with Regional Supplement Amendments.
1.5 Compaction Test Method - Where referred to herein, relative compaction shall mean the in-place dry density of soil expressed as a percentage of the maximum dry density of the same material, as determined by the ASTM D1557 Compaction Test Procedure. Optimum moisture content shall mean the moisture content at the maximum dry density determined above.
2.0 SITE PREPARATION
2.1 Clearing - Areas to be graded shall be cleared and grubbed of all vegetation and debris. These materials shall be removed from the site by the Contractor.
2.2 Stripping - Surface soils containing roots and organic matter shall be stripped from areas to be graded and stockpiled or discarded as directed by the Owner. In general, the depth of stripping of the topsoil will be approximately 6 inches. Deeper stripping, where required to remove weak soils or accumulations of organic matter, shall be performed when determined necessary by the Geotechnical Engineer. Stripped material shall be removed from the site or stockpiled at a location designated by the 51-521902/5119R258.doc Page C-2 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
Owner. Material should be evaluated for petroleum hydrocarbon impact.
After such analyses, the material should be handled as directed by the regulating authority.
2.3 Removal of Debris- Any existing, trash and debris encountered in the areas to be graded shall be removed prior to the placing of any compacted fill.
Portions of any existing fills that are suitable for use in new compacted fill may be stockpiled for future use. All organic materials, topsoil, expansive soils, oversized rock, or other unsuitable material shall be removed from the site by the Contractor or disposed of at a location on-site, if so designated by the Owner. Material should be evaluated for petroleum hydrocarbon impact and handled as directed by the regulating authority after such evaluation.
2.4 Ground Surface - The ground surface exposed by stripping shall be scarified to a depth of 6 inches, moisture conditioned to the proper moisture content for compaction, and compacted as required for compacted fill. Ground surface preparation shall be approved by the Geotechnical Engineer prior to placing fill.
3.0 EXCAVATION
3.1 General - Excavations shall be made to the lines and grades indicated on the plans.
The data presented in the Geotechnical Engineer's report is for information only and the Contractor shall make his own interpretation with regard to the methods and equipment necessary to perform the excavation and to obtain material suitable for fill.
3.2 Materials - Soils which are removed and are unsuitable for fill shall be placed in nonstructural areas of the project, or in deeper fills at locations 51 -521902/5119R258.doc Page C-3 May 21,1999
Copyright 1999 Kleinfelder, Inc.
KLEINFELDER
designated by the Geotechnical Engineer, provided the soils have been evaluated for petroleum hydrocarbon impact, and such soil is handled in accordance with the directions of the regulating authority.
3.3 Treatment of Exposed Surface - The ground surface exposed by excavation shall be scarified to a depth of 6 inches, moisture conditioned to the proper moisture content for compaction, and compacted as required for compacted fill. Compaction shall be approved by the Geotechnical Engineer prior to placing fill.
3.4 Rock Excavation - Where solid rock is encountered in areas to be excavated, it shall be loosened and broken up so that no solid ribs, projections, or large fragments will be within 6 inches of the surface of the final subgrade.
4.0 COMPACTED FILL
4.1 Materials - Fill material shall consist of suitable on-site or imported soil. All materials used for structural fill shall be reasonably free of organic material, have a liquid limit less than 30, a plasticity index less than 15, 100% passing the 3 inch sieve and less than 30 percent passing the #200 sieve.
4.2 Placement - All fill materials shall be placed in layers of 8 inches or less in loose thickness and uniformly moisture conditioned. Each lift should then be compacted with a sheepsfoot roller or other approved compaction equipment to at least 90 percent relative compaction in areas under structures, utilities, roadways and parking areas, and to at least 85 percent in undeveloped areas. No fill material shall be placed, spread, or rolled while it is frozen or thawing, or during unfavorable weather conditions.
4.3 Benching - Fill placed on slopes steeper than 5 horizontal to 1 vertical shall be keyed into firm, native soils or rock by a series of benches. Benching can 51-521902/5119R258.doc Page C-4 May 21,1999
Copyright 1999 Kleinfelder, Inc.
** Ml KLEI NFELDER
m
be conducted simultaneously with placement of fill. However, the methodm and extent of benching shall be checked by the Geotechnical Engineer.
4.4 Compaction Equipment - The Contractor shall provide and use sufficient equipment of a type and weight suitable for the conditions encountered in the field. The equipment shall be capable of obtaining the required compaction in all areas.m
4.5 Recompaction - When, in the judgment of the Geotechnical Engineer, sufficient compactive effort has not been used, or where the field density Pi
,y tests indicate that the required compaction or moisture content has not been obtained, or if pumping or other indications of instability are noted, the fill pn
j^ shall be reworked and recompacted as needed to obtain a stable fill at the required density and moisture content before additional fill is placed.
P*
4.6 Responsibility - The Contractor shall be responsible for the maintenance and M
• protection of all embankments and fills made during the contract period and shall bear the expense of replacing any portion which has become displaced ta due to carelessness, negligent work, or failure to take proper precautions. ta 5.0 UTILITY TRENCH BEDDING AND BACKFILL
m 5.1 Material - Pipe bedding shall be defined as all material within 4 inches of the perimeter and 12 inches over the top of the pipe. Material for use as bedding m shall be clean sand, gravel, crushed aggregate, or native free-draining material, having a Sand Equivalent of not less than 30. •
m Backfill should be classified as all material within the remainder of the M trench. Backfill shall meet the requirements set forth in Section 4.1 for _ compacted fill.
51-521902/5119R258.doc PageC-5 May 21, 1999
Copyright 1999 Kleinfeider, Inc.
KLEI NFELDER
V 5.2 Placement and Compaction - Pipe bedding shall be placed in layers not exceeding 8 inches in loose thickness, conditioned to the proper moisture p*
content for compaction, and compacted to at least 90 percent relative compaction. All other trench backfill shall be placed and compacted in pi
accordance with Section 306-1.3.2 of the Standard Specifications forM V Mechanically Compacted Backfill. Backfill shall be compacted as required m
for adjacent fill. If not specified, backfill shall be compacted to at least 90 percent relative compaction in areas under structures, utilities, and concrete m
flatwork, to 85 percent relative compaction in undeveloped areas, and at least 95 percent relative compaction under roadways and pavements. 51-521902/5119R258.doc PageC-6 May 21, 1999
Copyright 1999 Kleinfelder, Inc.
APPENDIX D
I
I
IMPORTANT INFORMATION ABOUT YOUR GEOTECHNICAL
ENGINEERING REPORT
As the client of a consulting geotechnical engineer, you should know that site subsurface conditions cause more
construction problems than any other factor. ASFE/The
Association of Engineering Firms Practicing in the
Geosciences offers the following suggestions and
observations to help you manage your risks.
A GEOTECHNICAL ENGINEERING REPORT IS BASED
ON A UNIQUE SET OF PROJECT-SPECIFIC FACTORS
Your geotechnical engineering report is based on a
subsurface exploration plan designed to consider a
unique set of project-specific factors. These factors
typically include: the general nature of the structure
involved, its size, and configuration; the location of the structure on the site; other improvements, such as
access roads, parking lots, and underground utilities;
and the additional risk created by scope-of-service
limitations imposed by the client. To help avoid costly problems, ask your geotechnical engineer to evaluate
how factors that change subsequent to the date of the
report may affect the report's recommendations.
Unless your geotechnical engineer indicates otherwise,
do not use your geotechnical engineering report:
when the nature of the proposed structure is
changed, for example, if an office building will be
erected instead of a parking garage, or a refrigerated
warehouse will be built instead of an unrefrigerated
one;
when the size, elevation, or configuration of the
proposed structure is altered;
when the location or orientation of the proposed
structure is modified;
when there is a change of ownership; or
for application to an adjacent site.
Geotechnical engineers cannot accept responsibility for problems that may occur if they are not consulted after factors considered in their report's development have
changed.
SUBSURFACE CONDITIONS CAN CHANGE
A geotechnical engineering report is based on condi-
tions that existed at the time of subsurface exploration.
Do not base construction decisions on a geotechnical
engineering report whose adequacy may have been
affected by time. Speak with your geotechnical consult- ant to learn if additional tests are advisable before
construction starts.Note, too, that additional tests may be required when subsurface conditions are affected by
construction operations at or adjacent to the site, or by natural events such as floods, earthquakes, or ground
water fluctuations. Keep your geotechnical consultant
apprised of any such events.
MOST GEOTECHNICAL FINDINGS ARE
PROFESSIONAL JUDGMENTS
Site exploration identifies actual subsurface conditions only at those points where samples are taken. The data
were extrapolated by your geotechnical engineer who
then applied judgment to render an opinion about
overall subsurface conditions. The actual interface
between materials may be far more gradual or abrupt
than your report indicates. Actual conditions in areas
not sampled may differ from those predicted in your
report. While nothing can be done to prevent such
situations, you and your geotechnical engineer can work together to help minimize their impact. Retaining your
geotechnical engineer to observe construction can be
particularly beneficial in this respect.
A REPORT'S RECOMMENDATIONS
CAN ONLY BE PRELIMINARY
The construction recommendations included in your
geotechnical engineer's report are preliminary, because they must be based on the assumption that conditions
revealed through selective exploratory sampling are
indicative of actual conditions throughout a site.
Because actual subsurface conditions can be discerned
only during earthwork, you should retain your geo-
technical engineer to observe actual conditions and to
finalize recommendations. Only the geotechnical
engineer who prepared the report is fully familiar with the background information needed to determine
whether or not the report's recommendations are valid
and whether or not the contractor is abiding by appli-
cable recommendations. The geotechnical engineer who
developed your report cannot assume responsibility or
liability for the adequacy of the report's recommenda-
tions if another party is retained to observe construction.
GEOTECHNICAL SERVICES ARE PERFORMED
FOR SPECIFIC PURPOSES AND PERSONS
Consulting geotechnical engineers prepare reports to
meet the specific needs of specific individuals. A report prepared for a civil engineer may not be adequate for a construction contractor or even another civil engineer.
Unless indicated otherwise, your geotechnical engineer
prepared your report expressly for you and expressly for purposes you indicated. No one other than you should
apply this report for its intended purpose without first conferring with the geotechnical engineer. No party
should apply this report for any purpose other than that originally contemplated without first conferring with the geotechnical engineer.
GEOENVIRONMENTAL CONCERNS
ARE NOT AT ISSUE
Your geotechnical engineering report is not likely to
relate any findings, conclusions, or recommendations
about the potential for hazardous materials existing at the site. The equipment, techniques; and personnel
used to perform a geoenvironmental exploration differ
substantially from those applied in geotechnical
engineering. Contamination can create major risks. If
you have no information about the potential for your
site being contaminated, you are advised to speak with
your geotechnical consultant for information relating to geoenvironmental issues.
A GEOTECHNICAL ENGINEERING REPORT IS
SUBJECT TO MISINTERPRETATION
Costly problems can occur when other design profes-
sionals develop their plans based on misinterpretations of a geotechnical engineering report. To help avoid
misinterpretations, retain your geotechnical engineer to work with other project design professionals who are
affected by the geotechnical report. Have your geotech- nical engineer explain report implications to design
professionals affected by them, and then review those
design professionals' plans and specifications to see
how they have incorporated geotechnical factors.
Although certain other design professionals may be fam- iliar with geotechnical concerns, none knows as much
about them as a competent geotechnical engineer.
BORING LOGS SHOULD NOT BE SEPARATED
FROM THE REPORT
Geotechnical engineers develop final boring logs based
upon their interpretation of the field logs (assembled by site personnel) and laboratory evaluation of field
samples. Geotechnical engineers customarily include
only final boring logs in their reports. Final boring logs should not under any circumstances be redrawn for
inclusion in architectural or other design drawings,
because drafters may commit errors or omissions in the
transfer process. Although photographic reproduction
eliminates this problem, it does nothing to minimize the possibility of contractors misinterpreting the logs during bid preparation. When this occurs, delays, disputes, and unanticipated costs are the all-too-frequent result.
To minimize the likelihood of boring log misinterpreta- tion, give contractors ready access to the complete
geotechnical engineering report prepared or authorized
for their use. (If access is provided only to the report prepared for you, you should advise contractors of the
report's limitations, assuming that a contractor was not one of the specific persons for whom the report was
prepared and that developing construction cost esti-
mates was not one of the specific purposes for which it was prepared. In other words, while a contractor may
gain important knowledge from a report prepared for
another party, the contractor would be well-advised to
discuss the report with your geotechnical engineer and
to perform the additional or alternative work that the
contractor believes may be needed to obtain the data
specifically appropriate for construction cost estimating purposes.) Some clients believe that it is unwise or
unnecessary to give contractors access to their geo-
technical engineering reports because they hold the
mistaken impression that simply disclaiming responsi-
bility for the accuracy of subsurface information always insulates them from attendant liability. Providing the
best available information to contractors helps prevent costly construction problems. It also helps reduce the
adversarial attitudes that can aggravate problems to
disproportionate scale.
READ RESPONSIBILITY CLAUSES CLOSELY
Because geotechnical engineering is based extensively
on judgment and opinion, it is far less exact than other design disciplines. This situation has resulted in wholly unwarranted claims being lodged against geotechnical
engineers. To help prevent this problem, geotechnical
engineers have developed a number of clauses for use in their contracts, reports, and other documents. Responsi- bility clauses are not exculpatory clauses designed to
transfer geotechnical engineers' liabilities to other
parties. Instead, they are definitive clauses that identify where geotechnical engineers' responsibilities begin and end. Their use helps all parties involved recognize their individual responsibilities and take appropriate action.
Some of these definitive clauses are likely to appear in your geotechnical engineering report. Read them
closely. Your geotechnical engineer will be pleased to
give full and frank answers to any questions.
RELY ON THE GEOTECHNICAL ENGINEER
FOR ADDITIONAL ASSISTANCE
Most ASFE-member consulting geotechnical engineer-
ing firms are familiar with a variety of techniques and approaches that can be used to help reduce risks for all parties to a construction project, from design through
construction. Speak with your geotechnical engineer not only about geotechnical issues, but others as well, to
learn about approaches that may be of genuine benefit.
You may also wish to obtain certain ASFE publications.
Contact a member of ASFE or ASFE fora complimentary
directory of ASFE publications.
PROFESSIONAL
FIRMS PRACTICING
IN THE GEOSCIENCES
8811 COLESVILLE ROAD/SUITE G106/SILVER SPRING, MD 20910 TELEPHONE: 301/565-2733 FACSIMILE: 301/589-2017
Copyright 1992 by ASFE, Inc. Unless ASFE grants specific permission to do so, duplication of this document by any means whatsoever is expressly prohibited.
Re-use of the wording in this document, in whole or in part, also is expressly prohibited, and may be done only with the express permission of ASFE or for purposes of review or scholarly research.
IIGR0294
Contract No. 5554 - PWS27-4091UTIL 13
Addendum No. 3
ATTACHMENT D
(Revised)
DRAWING SHEETS
(P) 48"X48" SINGLE LEAF
ALUMINUM HATCH. BILCO
TYPE JD-AL, OR EQUAL,
WITH LIFT ASSIST. RUN
HATCH DRAIN TO CURB
10' DIAMETER WET WELL SLAB.
REMOVE EXISTING CONCRETE
AND REPLACE WITH NEW
POLYMER CONCRETE, OLSEN
POLYMER ROCK HARD OR
EQUAL. SEE DETAIL 4.
(RR) EXISTING CONCRETE WITH NEW
CONCRETE PER CITY STANDARDS
(RR) EXISTING CURB WITH
NEW 6" CONCRETE CURB
PER SDRSD G-1(P) NEW BUILDING
TOTAL 240SF. SEE
STRUCTURAL PLANS.
(RR) 4-INCH THICK AC
PAVEMENT
(E) BUILDING
STRUCTURE 160SF
20.0'
13'4"
38'3"
(E) 22' DRIVEWAY
18'3.25"
(RR) 4-INCH THICK AC
PAVEMENT PER CITY
STANDARD GS-24
THROUGH GS-28
(P) CONTRACTOR SHALL DESIGN
AND INSTALL TEMPORARY
ACCESS PATH AND STAIRCASE
FOR SAFE ACCESS DURING
CONSTRUCTION. TEMPORARY
ACCESS TO BE REMOVED UPON
PROJECT COMPLETION.
RR (E) FENCE FOR
TEMPORARY ACCESS
PATH. REPLACE IN KIND
TO MATCH EXISTING
EXISTING ACCESS
PATH TO LAGOON DETOUR ACCESS PATH
TO LAGOON
TEMPORARY SITE FENCING (TYP)
PEDESTRIAN ACCESS PATH DETOUR
AND STAIRCASE SHALL BE INSTALLED
PRIOR TO RESTRICTING ACCESS
THROUGH SITE.
(P) NEW BUILDING WITH
ADDITIONAL 80 SF
(PIP) EXISTING
CITY SURVEY
CONTROL
STATION
(RR) EXISTING
BACKFLOW WITH
ENCLOSURE PER
CMWD DWG W-6.
SEE L-SHEETS.
(RR) EXISTING CONCRETE WALKWAY JOINT
TO JOINT WITH NEW ENHANCED CONCRETE
(SCOFIELD C-15 COACHELLA SAND COLOR,
MEDIUM SANDBLAST FINISH, WITH 6" SMOOTH
TROWL BANDS) TO MATCH EXISTING
(RR) REMOVE EXISTING SEWER CLEAN OUT
(RIM=24.50'; IE=14.27' PER DWG 124-6A)
INSTALL NEW 4-FT DIA SEWER MANHOLE PER
MODIFIED CITY STANDARD S-1 AND CITY
SPECIFICATION SECTION 03460. CONSTRUCT
CENTERLINE OF MANHOLE 1-FT OFFSET FROM
EXISTING PIPE BEND AT SCO. CONSTRUCT SMOOTH
LONG RADIUS CHANNEL TO ACCOMMODATE OFFSET.
1'
4'
6.64'
(PIP) EXISTING 12"
AC WATER MAIN
(PIP) EXISTING 6"
SEWER FM
PIPE SHELLNOTES
1. ALL PRESSURE GAUGE ASSEMBLY, PIPE, VALVES SHALL BE TYPE 316 SS.
STAINLESS STEEL PRESSURE
GAUGE (MIN. 3-1/2" DIA.
CALIBRATED IN APPLICABLE
UNITS) OR PRESSURE SWITCH
DIAPHRAGM SEAL, WITH
STAINLESS STEEL DIAPHRAGM
AND LOWER HOUSING
1" SCH. 80 S.S. NIPPLE (TYP.)
1" SCH. 80 S.S. BALL VALVE
1" SS DIELECTRIC UNION
COAT WITH EPOXY
1 2" BALL VALVE
1 4" SCH. 80 S.S. BALL VALVE
1 4" SCH. 80 S.S. NIPPLE
CONNECTION FOR OIL FILL
DIP SPOOL CLASS 53
WITH THREADED OUTLET
NOTES
1. INSIDE DIAMETER OF EACH WALL OPENING SHALL BE OF
THE SIZE RECOMMENDED BY THE SEAL MANUFACTURER TO
FIT THE PIPE OR CONDUIT AND TO ENSURE A WATER-TIGHT
JOINT.
2. WALL SEAL ASSEMBLY SHALL BE OF THE MODULAR
MECHANICAL TYPE, CONSISTING OF INTERLOCKING
SYNTHETIC RUBBER LINKS SHAPED TO FILL THE ANNULAR
SPACE BETWEEN THE PIPE AND THE WALL OPENING. A
PRESSURE PLATE SHALL BE PROVIDED UNDER EACH BOLT
HEAD AND NUT, WITH THE SEAL CONSTRUCTED TO
PROVIDE ELECTRICAL INSULATION BETWEEN WALL AND
PIPE. WALL SEAL ASSEMBLY SHALL BE LINK SEAL AS
MANUFACTURED BY GPT INDUSTRIES OR APPROVED
EQUAL. ALL HARDWARE SHALL BE STAINLESS STEEL,
GRADE 316.
3. FOR PENETRATIONS THROUGH THE EXISTING WET WELL
WALL, THE INTERIOR WALL LINER SHALL BE REPAIRED
AFTER THE WALL PENETRATION PER SPECIFICATION
SECTION 06621.
(E) INTERIOR
CONCRETE
WALL
BOLT AND NUT,
TYPE 316 SS
MODEL "C" LINK-SEAL
MODULAR SEAL
MANUFACTURED BY
GPT INDUSTRIES OR
APPROVED EQUAL
WALL SEAL
ASSEMBLYNON-SHRINK
GROUT (TYP)
PIPE OR
CONDUIT
CORE DRILL
(E) EXTERIOR
CONCRETE
WALL
INSTALL PUMP GUIDE RAIL TO CLEAR HATCH
SUPPORT SHELF PER MANUFACTURER'S
RECOMMENDATIONS; MOUNTING HARDWARE
SHALL BE 316 STAINLESS STEEL
10' DIAMETER REINFORCED POLYMER
CONCRETE PRECAST TOP SLAB. MATCH
EXISTING TOP SLAB THICKNESS. TO BE
DESIGNED BY MANUFACTURER, H20-RATED,
OLSON PRECAST OR APPROVED EQUAL.
1 4" ALUMINUM
CHANNEL FRAME
WITH RECESSED
ANCHORS (TYP)
AUTOMATIC HOLD OPEN ARM
REMOVABLE COVER PLUG
REMOVABLE SQUARE KEY WRENCH
4' X 4' SINGLE LEAF HINGED H20-RATED HATCH (BILCO
TYPE J-AL CUSTOM SIZE) WITH TYPE 316 STAINLESS
STEEL HARDWARE. HATCH TO DRAIN TO CURB.
HEAVY DUTY FORGED 316 STAINLESS STEEL
HINGES WITH 316 STAINLESS STEEL PINS
316 STAINLESS STEEL LIFTING
MECHANISM WITH REINFORCED
COMPOSITE TUBES AND
COMPRESSION SPRINGS
1 4" SUPPORT PLATE
WELDED TO FRAME
(PIP) EXISTING WET WELL
(PIP) EXISTING WET WELL LINER;
REPAIR ALL LINER DAMAGES PER
SPEC SECTION 06621. SEE C-04
DETAIL 2 FOR LINER REPAIR DETAIL.
REPAIR LINER PER SPEC
SECTION 06621; TURN BACK
LINER AT LEAST 2 INCHES (TYP)
APPLY SIKA 31 HI MOD GEL JOINT
SEALANT OR APPROVED EQUAL PER
MANUFACTURER'S RECOMMENDATIONS
BETWEEN POLYMER CONCRETE SLAB
AND EXISTING WET WELL WALL PER
ASTM C990 (TYP)
HEAVY DUTY CHECK CHAIN
SLAM LOCK
MIN 2"
48"
FRAME CLEAR
OPENING
12" 24"24"
8" SCHEDULE 80 PVC PIPE BLIND FLANGE
A
-
4' X 4' SINGLE LEAF
HATCH. SEE SECTION A.
POLYMER CONCRETE SLAB TO BE
DESIGNED BY MANUFACTURER;
H-20-RATED; OLSON PRECAST OR
APPROVED EQUAL
TOP SLAB 10'
DIAMETER
WET WELL 8' DIAMETER
29"
36"
43"
36"
8" SCHEDULE 80 PVC
PIPE BLIND FLANGE
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
4 38
SITE PLAN
AND DETAILS
NI/ZT
SD
KM
C-03
CHINQUAPIN LIFT STATION CIVIL SITE PLAN
SCALE: 1" = 5'1
N
TOP SLAB AND HATCH FOR WET WELL SECTION VIEW
SCALE: NTSA
WALL PENETRATION
SCALE: NTS2 PRESSURE GAUGE WITH DIAPHRAGM SEAL
SCALE: NTS3
TOP SLAB AND HATCH FOR WET WELL PLAN VIEW
SCALE: NTS4
N
Q:\Public Works\PW Common\Capital Improvement Program Projects\5554 Chinquapin Lift Station\Design\CAD\Design_Template_Addendum 1.dwg Aug 05, 2026 - 8:12am
FILE:
PLOT:
08/05/26 BC ADDENDUM 3 08/05/26 SD 08/05/26 KM
RR (E) PRESSURE GAUGE.
SEE SHEET C-03 DETAIL 3
18"
PIP (E) PUMP (TYP OF 2). COORDINATE
WITH CITY OPERATIONS TO APPROVE
OF REMOVAL, HANDLING, AND
STORAGE DURING CONSTRUCTION.
RR (E) 4" DIP
DISCHARGE PIPE AND
FITTINGS (TYP OF 2)
PUMP GUIDE RAIL SYSTEM (TYP OF 2)
WITH 316 STAINLESS STEEL GUIDE RAIL,
MOUNTING KIT, AND HARDWARE PER
FLYGT. INSTALL PER MANUFACTURER'S
RECOMMENDATIONS AND VERTICALLY
PLUMB.
RR (E) MOUNTING ASSEMBLY (TYP
OF 2). REPAIR CONCRETE AND
WET WELL LINER AS REQUIRED
RR (E) DISCHARGE ELBOWS
WITH NEW FLYGT #540-13-05,
4" DISCHARGE ELBOW
CONNECTIONS (TYP OF 2)
2'-7"
10'-2"
95"
8'
18'-5"
CHECK VALVE (TYP OF 2)
316 SS PIPE SUPPORT 4" PER
DETAIL 3 (TYP OF 2)
316 SS PIPE SUPPORT 6" PER
DETAIL 3 (TYP OF 3)
21"
IE 14.00'4" PLUG VALVE (TYP OF 2)
REPAIR EXISTING WET WELL LINER.
SEE DETAIL 2 (TYP).
SEE SHEET C-03
DETAIL 2 FOR WALL
PENETRATION (TYP)
3'-11"
1'-5"
315 SS WALL BRACKET
MOUNT PIPE BRACING
(TYP OF 2)
SEE SHEET C-01 DETAIL 1 FOR
HATCH GUARDRAILS
4" VICTAULIC
COUPLING
(TYP OF 4)
A
C-04
(E) WEST PUMP (WP)
(E) EAST PUMP (EP)
6" DIP (PE X GE/VIC) WITH
VIC FLANGE STYLE 341
6" FLOW METER ENDRESS
& HAUSER PROLINE
PROMAG W400 OR EQUAL
WITH INSULATING
FLANGE KIT PER WC-3
6" X 4" DI TEE (FL)
6" DIP (GE/VIC X GE/VIC)
6 X 4 REDUCING 90 BEND
RR (E) 4" DIP (PE X FL)
(TYP OF 2)
SEE SHEET C-03 DETAIL 4 FOR
TOP SLAB AND HATCH
4" ECCENTRIC
PLUG VALVE
(TYP OF 2)
4" CHECK VALVE SURGEBUSTER BY
VAL-MATIC OR EQUAL (TYP OF 2)
4" VICTAULIC
COUPLING STYLE 341
(TYP OF 4)
6" DIP TEE WITH 6" PLUG
VALVE AND BLIND FLANGE
94.75"
24" 44.5"26.25"
4" DIP (PE
X GE/VIC)
(TYP OF 2)
SEE SHEET C-03 DETAIL 2 FOR
WALL PENETRATION (TYP OF 6)
REPAIR EXISTING WET WELL
LINER. SEE DETAIL 2 (TYP)
4" DIP (FL X GE/VIC) (TYP OF 2)
3-WAY PLUG VALVE (FL)
6" VIC FLANGE STYLE 3416" DIP (FL X GE/VIC)
WITH BLIND FLANGE
6" DIP TEE (FL X FL)
8" SCHEDULE 80 PVC PIPE BLIND FLANGE.
SEE DETAIL 4 FOR SUCTION PIPE DETAIL.
12"
6" VIC FLANGE STYLE 341
PIP (E) LADDER
6" RESTRAINED COUPLING PER
ROMAC ALPHA OR EQUAL
(E) 6" PVC
PRESSURE GAUGE (TYP OF 2)
12"
316 SS PIPE SUPPORT 6"
PER DETAIL 3 (TYP OF 3)
316 SS PIPE SUPPORT 4"
PER DETAIL 3 (TYP OF 2)
B
C-04
5.25"
6" DIP 90 BEND
6" ECCENTRIC PLUG
VALVE WITH BLIND
FLANGE
3-WAY PLUG
VALVE (FL)
316 SS PIPE
SUPPORT 6"
PER DETAIL 36" DIP TEE (FL X FL)
NOTES:
1. UNDER VALVES, METERS, OR OTHER SPECIAL
APPURTENANCES A FABRICATED SUPPORT PIECE MAY
BE BE UTILIZED AS ACCEPTABLE TO ENGINEER.
2. WHERE SHOWN UNDER PIPE OR VALVE FLANGE,
PROVIDE FLANGE CRADLE SUPPORT BY MATERIAL
RESOURCES OR ENGINEER APPROVED EQUAL.
3. PROVIDE TYPE 316 STAINLESS STEEL UNITS.
4. SIZE OF SUPPORT COMPONENTS AND THEIR
CONNECTIONS SHOWN FOR PIPE, DUCT, HVAC, AND
EQUIPMENT ANCHORAGE SYSTEM ARE MINIMUM
REQUIREMENTS (INCLUDING ANCHOR BOLT SIZE,
SPACING, AND EMBEDMENT LENGTH). CONTRACTOR
SHALL DESIGN ALL SUPPORT COMPONENTS AND THEIR
CONNECTIONS PER SPECIFICATIONS AND INCREASE
SIZES AS REQUIRED BY DESIGN CALCULATIONS.
5. AS AN ALTERNATIVE, CONTRACTOR MAY USE
ADJUSTABLE PIPE SUPPORT WITH BASE BY PIPELINE
PRODUCTS, MODEL PS-S
ADJUSTABLE PIPE SUPPORT
150 LB. THREADED
REDUCING FLANGE,
GALVANIZED
SS ANCHOR BOLT OR SS
ADHESIVE CAPSULE ANCHOR
WITH (2) NUTS EACH, SIZE TO
SUIT FLANGE. TYPICAL OF (4)
ADJUSTABLE PIPE SUPPORT
APPROXIMATE DIMENSION IN INCHES
PIPE
SIZE A B C D
MIN
D
MAX
4" & 6" 3 2 1/2 9 11 5/8 15 1/4
PIPE SIZE
18'-5"
24"
316 SS OFFSET PIPE
CLAMP AND
FASTENERS PER ANVIL
INTERNATIONAL OR
APPROVED EQUAL
(TYP OF 2)
8" SCHEDULE
80 PVC PIPE
8" SCHEDULE
80 PVC PIPE
BLIND FLANGE
8" SCHEDULE
80 PVC FITTING
45° BEND
2"
10" DIAMETER PIPE
OPENING WITH LINK SEAL.
EPOXY SEAL UNDER SLAB
PER SIKADUR 31 OR EQUAL
4"
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
5 38
WET WELL AND VALVE VAULT
IMPROVEMENTS AND DETAILS
NI/ZT
SD
KM
C-04
PLAN VIEW
SCALE: 1" = 2'1
SECTION VIEW
SCALE: 1" = 2'A
NOTE:
DIMENSIONS PROVIDED FOR REFERENCE ONLY.
CONTRACTOR TO FIELD VERIFY ALL
DIMENSIONS PRIOR TO ORDERING MATERIALS.
LINER REPAIR DETAILS
SCALE: NTS2
LINER REPAIR NOTES:
1. REPAIR EXISTING T-LOCK PVC LINER PER LINABOND REPAIR PRODUCTS OR APPROVED EQUAL. REPAIR ALL LINER OPEN SEAM TEARS, PIPE PENETRATIONS,
PIPE BRACING, LINER TURNBACK UNDER NEW TOP SLAB, AND OTHER LINER DEFECTS, IN ACCORDANCE WITH SPECIFICATIONS AND MANUFACTURER'S RECOMMENDATIONS. SEE LINER REPAIR DETAILS.
2. CONTRACTOR SHALL INSPECT WET WELL, IDENTIFY ALL REPAIRS, AND SUBMIT REQUIRED PRODUCT AND INSTALLATION INFORMATION FOR CITY APPROVAL.
ADJUSTABLE PIPE SUPPORT
SCALE: NTS3
SUCTION PIPE
SCALE: NTS4
SECTION VIEW
SCALE: 1" = 2'B
6" FABRICATED KNIFE GATE PER ITT SERIES C67S, ANSI CLASS 150# LUG STYLE ENDS, CAST 316SS BODY, 304SS STEM, 316SS GATE, EPDM SEAT, 18-8SS FASTENERS, ACRYLIC/ SILICONE PACKING, 304SS UNIVERSAL YOKE, 150 PSI BI-DIRECTIONAL OR EQUAL 08/05/26 BC ADDENDUM 3 08/05/26 SD 08/05/26 KM
A
1 4
A-2012
A-201 4
A-201
3 A-201
5 20' - 0"
V.I.F
1 2' - 0"
6 A-201
______________
7 A-201
______________
D1
DIESEL
GENERATOR
ROOM
101
4' - 2" 10' - 10" 5' - 0"
31 32
35 39
01 31
B
33 DIESEL
GENERATOR
51 3
2 01
1' - 6" 9' - 4" 1' - 6"
05 0.5%
SLOPE
30 52
52 3137 54
38 55
TYP.
0.5%
SLOPE
57 57
57 59
59 60
61 7' - 10"
7' - 4"2' - 7"
3' - 8" 4' - 2"
GENERAL NOTES
1. SEE SHEET G-100 FOR ADDITIONAL NOTES AND ABBREVIATIONS.
2. PARTITIONS DIMENSIONED TO FINISH FACE U.N.O. DO NOT ADJUST DIMENSIONS INDICATED AS “CLEAR” WITHOUT WRITTEN DIRECTION FROM ARCHITECT. DRAWINGS SHALL NOT BE SCALED. VERIFY ALL DIMENSIONS AND EXISTING AS BUILT FIELD CONDITIONS, INCLUDING
FIELD MEASUREMENTS PRIOR TO START OF WORK, NOTIFY ARCHITECT WHERE DISCREPANCIES OCCUR.
3. LARGE SCALE DRAWINGS TAKE PRECEDENCE OVER SMALL SCALE DRAWINGS. DETAILS
TAKE PRECEDENCE OVERALL, NOTIFY ARCHITECT IN WRITING WHERE DISCREPANCIES OCCUR.
4. PATCH FLOOR AND WALL AREAS DAMAGED DUE TO NEW CONSTRUCTION OR WHERE PENETRATIONS HAVE BEEN MADE FOR MECHANICAL, ELECTRICAL AND PLUMBING WORK.
FIRESAFE AT UL RATED ASSEMBLIES CONSISTENT WITH EXISTING UL RATING.
5. WHERE EXISTING RATED ASSEMBLIES ARE SHOWN, CONTRACTOR IS REQUESTED TO FIELD VERIFY AS BUILT FIELD CONDITIONS TO CONFIRM RATINGS SHOWN. IF NON-COMPLIANT
CONDITIONS ARE FOUND, REPORT FINDINGS TO OWNER/ARCHITECT IN WRITING WHO WILL PROVIDE WRITTEN DIRECTION.
6. PATCH AND REPAIR ALL EXISTING CONCRETING, SLABS, WALLS, CURBS & OTHER PORTION
OF THE STRUCTURE, REPAIR & LEVEL WITH TWO COMPONENT POLYMER MODIFIED, PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL AFTER DEMOLITION WHERE DAMAGE HAS OCCURRED AT UNPROTECTED LOCATIONS. PLEASE
NOTE THAT DEMOLITION ACTIVITY MAY OCCUR BEYOND WORK LIMITS SHOWN ON DEMOLITION PLAN DUE TO CONCEALED CONDITIONS.
7. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL INSPECTIONS AND APPROVAL REQUIRED BY THE APPLICABLE DEPARTMENTS OF THE CITY OF CARLSBAD.
8. CONTRACTOR TO MAINTAIN PUBLIC ACCESS TO THE TRAIL DURING CONSTRUCTION.
EXISTING CMU WALL TO REMAIN
LEGEND
KEYNOTE TAGX
DOOR TAGXX
NEW CMU WALL, SEE STRUCTURAL PLANS
NEW CONCRETE SLAB, SEE STRUCTURAL PLANS
A
1 4
6 A-201
______________
7 A-201
______________
DIESEL
GENERATOR
ROOM
101
B
3 2
08 TYP.
4349
5' - 4" 5' - 1"
6' - 0" 7' - 5" 5' - 3"
2' - 6" 5' - 8" 2' - 7"
A
1 4
A-2012
A-201 4
A-201
3 A-201
5 6
A-201
______________
7 A-201
______________
1' - 6" 1 2' - 0" 1' - 6"
B
43 3
2 1' - 6" 20' - 0" 1' - 6"
43 15' - 0"
23' - 0"
59 59
SLOPE
DIESEL TANK VENTING NOTES
1. VENT PIPE OUTLETS FOR TANKS STORAGE CLASS-I, II OR III-A LIQUIDS SHALL BE LOCATED SUCH THAT THE VAPORS ARE RELEASED AT A SAFE POINT OUTSIDE OF BUILDINGS AND NOT LESS THAN 12 FEET ABOVE THE ADJACENT GROUND LEVEL. VAPORS SHALL BE DISCHARGED UPWARD AWAY FROM CLOSELY ADJACENT WALLS TO ASSIST IN VAPOR DISPERSION. VENT OUTLETS SHALL BE LOCATED SUCH THAT FLAMMABLE VAPORS WILL NOT BE TRAPPED BY EAVES OR OTHER OBSTUCTIONS AND SHALL BE AT LEAST 5 FEET FROM BUILDING OPENINGS OR PROPERTY LINES OF PROPERTIES THAT CAN BE BUILT ON. TERMINATE THE VENT OUTLETS WITH AN OPW 623V PRESSURE VACUUM VENT
2. TANK VENTS FOR NORMAL AND EMERGENCY VENTING SHALL BE INSTALLED AND MAINTAINED IN ACCORDANCE WITH CALIFORNIA FIRE CODE -2022, NFPA-30 AND WITH LOCAL AUTHORITY HAVING JURISDICTION.
3. NORMAL AND EMERGENCY VENT OUTLETS SHALL BE ATLEAST 10 FEET AWAY FROM ANY FRESH AIR INTAKE FROM MECHANICAL EQUIPMENT. COORDINATE WITH MECHANICAL CONTRACTOR.
4. VENT PIPES SHALL BE INSTALLED SUCH THAT THEY WILL DRAIN TOWARD THE TANK WITHOUT SAGS OR TRAPS IN WHICH LIQUID CAN COLLECT. VENT PIPES SHALL BE INSTALLED IN SUCH A MANNER AS TO NOT BE SUBJECT TO PHYSICAL DAMAGE OR VIBRATION.
5. NORMAL AND EMERGENCY VENT PIPE SIZES, PIPE MATERIALS AND PIPE FITTINGS , FUEL OIL SYSTEM DESIGN SHOP DRAWINGS AND SPECIFICATIONS (DESIGNED BY OTHERS) AND DIESEL TANK MANUFACTURER'S SPECIFICATIONS (DESIGNED BY OTHERS).
6. VENTING DEVICES SHALL BE INSTALLED IN ACCORDANCE WITH THEIR LISTINGS AND DIESEL TANK MANUFACTURER'S SPECIFICATIONS. USE OF FLAME ARRESTERS IN PIPING SYSTEMS SHALL BE IN ACCORDANCE WITH NATIONALLY RECOGNIZED CODES AND STANDARDS.
7. TANK INSTALLATION, PIPE MATERIAL AND FITTINGS, VENTING, FUEL OIL SYSTEM DESIGN SHOP DRAWINGS/SPECIFICATIONS AND MANUFACTURER'S SPECIFICATIONS SHALL BE APPROVED BY FIRE MARSHALL AND LOCAL FIRE AUTHORITY.
8. FUEL OIL SYSTEM PIPE MATERIAL SHALL COMPLY WITH CITY OF CARLSBAD FIRE DEPARTMENT MATERIALS AND INSTALLATION REQUIREMENT AND SUBJECT TO APPROVAL WITH AUTHORITY HAVING
JURISDICTION
FUEL OIL TANK VENT PIPING
A. STEEL PIPE: ASTM A53 OR ASME B36.10, SCHEDULE 40 BLACK. OUTDOOR RATED CORROSION RESISTANCE COATING FOR OUTDOOR PIPE ONLY.
1. FITTINGS: ASTM B16.3, BLACK MALLEABLE IRON, CLASS 150 (300 LB. WOG), THREADED.
2. JOINTS: NFPA 30, THREADED ANSI B31.4.
3. THREAD SEALANT: MAKE UP ALL THREADED CONNECTIONS UTILIZING SEALANT THAT IS COMPATIBLE WITH INTENDED SERVICE.
4. PIPE SHALL BE LABELED WITH PLASTIC WRAP AROUND LABELS IN ACCORDANCE WITH ANSI A13.1. THE LABELS SHALL HAVE PROPER IDENTIFICATION FOR FUEL OIL VENT, FUEL OIL FILL AND FUEL OIL DRAIN, ETC.
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set
07302026 1 Addendum on Bid Set
PROPOSED PLANS
A-101
1/4" = 1'-0"GENERATOR ENCLOSURE PLAN 1
KEYNOTES
V
ALUE DESCRIPTIONS
01 EXISTING 8" THICK CMU RETAINING WALL TO REMAIN, PATCH & REPAIR AS REQUIRED. APPLY SMOOTH PLASTER FINISH; COLOR: ICY WHITE DEHW 10
MATTE OR EQUAL & ELASTOMERIC SEALANT ON THE EXTERIOR SIDE 05 PORTION OF EXISTING CONCRETE SLAB TO REMAIN. PATCH & REPAIR AS
REQUIRED, LEVEL WITH TWO-COMPONENT POLYMER-MODIFIED,
PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL.
0.5% SLOPE V.I.F
08 NEW LIGHTING FIXTURE. SEE ELECTRICAL DRAWINGS.
30 NEW CONCRETE SLAB TO RECEIVE CONCRETE SEALER. 0.5% SLOPE. SEE
STRUCTURAL PLANS
31 NEW 8" THK CMU WALL PER STRUCTURAL PLANS. APPLY SMOOTH PLASTER; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL & ELASTOMERIC
SEALANT ON THE EXTERIOR SIDE
32 NEW DIESEL EMERGENCY GENERATOR & FUEL TANK ON A CONCRETE SLAB PER STRUCTURAL PLANS. CITY TO SUPPLY GENERATOR (20KW REHLKO/KOHLER, 20REOZK, OPEN UNIT SKID, 53 GALLON
TANK)CONTRACTOR TO INSTALL. SEE ELECTRICAL & STRUCTURAL PLANS 33 NEW MCC UNIT ON HOUSE KEEPING PAD PER ELECTRICAL PLANS 35 NEW SCADA CABINET ON HOUSE KEEPING PAD PER ELECTRICAL PLANS 37 RELOCATED EXISTING IRRIGATION CONTROL SYSTEM. SEE ELECTRICAL PLANS
38 NEW ATS PER ELECTRICAL PLANS
39 NEW HOLLOW METAL DOOR, SEE DOOR SCHEDULE ON SHEET A-300 43 NEW MBCI PBU EXPOSED FASTENING SYSTEM ROOF PANELS,
GALVANUME PLUS, 22 GA, COLOR: CLASSIC GREEN, PROVIDE
MARINE-GREEN COATING SYSTEM FOR MARINE ENVIRONMENT ON METAL PANELS OVER 18GA HSB-36 METAL ROOF DECK PER STRUCTURAL PLANS.
SEE DETAIL 8/A-501
49 OPEN CEILING
51 PROVIDE NEW HOSE BIBB WITH VACUMM BREAKER, EXTEND EXISTING
COLD WATER LINE TO NEW HOSE BIBB LOCATION
52 16"X12" CMU PILASTER PER STRUCTURAL PLANS
54 NEW DARK ANODIZED - GRAY, 30" WIDE x 36" HIGH RADIATOR LOUVER
WITH INSECT SCREEN
55 NEW HSS POST ABOVE PER STRUCTURAL PLANS
57 ELECTRICAL UNITS PER ELECTRICAL PLANS
59 3" DIESEL TANK VENT UP THROUGH ROOF. REFER TO VENTING NOTES BELOW AND DETAIL 6/A-501
60 GALVANIZED SHEET METAL RADIATOR DISCHARGE DUCT WITH FABRIC FLEX CONNECTOR REFER TO DETAIL 2/A-501
61 ENGINE EXHAUST, REFER TO DETAIL 3/A-501
1/4" = 1'-0"REFLECTED CEILING PLAN 4
1/4" = 1'-0"ROOF PLAN 2
9 1
08/05/26 SD 08/05/26 KM
TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
39 3 2
434531
TOP OF CMU
7' - 6"
41 3146
B C
5757 57
A
FINISH FLOOR LEVEL
0"
TOP OF BEAM
10' - 6"
B
314143 15
A
TOP OF CMU
7' - 6"
4554
D
1"
56 56
37 61
PER GEN. SET RQT.
+/- 2' - 0"
TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
10' - 6"
V.I.F
8' - 0" 2' - 6"
01 31
32 4345
EXISTING
1 3' - 4 1/2"
NEW
6' - 7 3/4"
35'
30'
58 61
TOP OF (E) CMU
8' - 0"
A
FINISH FLOOR LEVEL
0"
TOP OF BEAM
10' - 6"
B
0115 4345
35'
28'
31 FINISH FLOOR LEVEL.
0"
TOP OF (E) CMU
8' - 0"
A
TOP OF BEAM
10' - 6"
B
32 39
4341 45
TOP OF CMU
7' - 6"
46 31
01 TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
SLOPE (TYP)
01 01 3532
3 2
2%
4345 31
TYP. TYP.
31 TOP OF CMU
7' - 6"
A-501
1 TYP
LEGEND
X LOUVER TAG, SEE SHEET A-300 FOR MORE INFORMATION
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set
07302026 1 Addendum on Bid Set
PROPOSED ELEVATIONS AND SECTIONS
A-2011/4" = 1'-0"SOUTH ELEVATION 2
1/4" = 1'-0"WEST ELEVATION 3
1/4" = 1'-0"NORTH ELEVATION 4
1/4" = 1'-0"EAST ELEVATION 5
1/4" = 1'-0"SECTION - B 6
1/4" = 1'-0"SECTION A 7
KEYNOTES
V
ALUE DESCRIPTIONS
01 EXISTING 8" THICK CMU RETAINING WALL TO REMAIN, PATCH & REPAIR AS REQUIRED. APPLY SMOOTH PLASTER FINISH; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL & ELASTOMERIC SEALANT ON THE
EXTERIOR SIDE
15 EXISTING RAILING TO REMAIN.
31 NEW 8" THK CMU WALL PER STRUCTURAL PLANS. APPLY SMOOTH PLASTER; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL &
ELASTOMERIC SEALANT ON THE EXTERIOR SIDE
32 NEW DIESEL EMERGENCY GENERATOR & FUEL TANK ON A CONCRETE SLAB PER STRUCTURAL PLANS. CITY TO SUPPLY GENERATOR (20KW REHLKO/KOHLER, 20REOZK, OPEN UNIT SKID, 53 GALLON
TANK)CONTRACTOR TO INSTALL. SEE ELECTRICAL & STRUCTURAL PLANS
35 NEW SCADA CABINET ON HOUSE KEEPING PAD PER ELECTRICAL PLANS
37 RELOCATED EXISTING IRRIGATION CONTROL SYSTEM. SEE
ELECTRICAL PLANS
39 NEW HOLLOW METAL DOOR, SEE DOOR SCHEDULE ON SHEET A-300 41 NEW DARK ANODIZED - GRAY ALUMINUM LOUVERS BY GREENHECK, MODEL #AFJ-120 OR APPROVED EQUAL WITH INSECTS SCREEN
43 NEW MBCI PBU EXPOSED FASTENING SYSTEM ROOF PANELS,
GALVANUME PLUS, 22 GA, COLOR: CLASSIC GREEN, PROVIDE
MARINE-GREEN COATING SYSTEM FOR MARINE ENVIRONMENT ON
METAL PANELS OVER 18GA HSB-36 METAL ROOF DECK PER
STRUCTURAL PLANS. SEE DETAIL 8/A-501
45 NEW HSS BEAM TO BE PAINTED. COLOR; BLACK. SEE STRUCTURAL PLANS
46 NEW HSS POST TO BE PAINTED. COLOR; BLACK. SEE STRUCTURAL PLANS
54 NEW DARK ANODIZED - GRAY, 30" WIDE x 36" HIGH RADIATOR LOUVER
WITH INSECT SCREEN
56 NEW 5" WIDE X 3"HIGH WEEP HOLES WITH RODENT SCREEN
57 ELECTRICAL UNITS PER ELECTRICAL PLANS
58 TOP UP WITH GROUT FROM THE LAST CMU MODULE TO THE BOTTOM
OF STRUCTURAL BEAM
61 ENGINE EXHAUST, REFER TO DETAIL 3/A-501
10 08/05/26 SD 08/05/26 KM
EXTERIOR INTERIOR
HEAD DETAIL
SILL DETAIL
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
HSS BEAM PER
STRUCTURAL
PLANS
NEW METAL ROOF
DECK
JAMB DETAIL
NEW DARK ANODIZED - GRAY ALUMINUM
LOUVERS WITH INSECT SCREEN
INSTALL PER MAUFACTURER
RECOMMENDATIONS
SLOPE
HSS COLUMN & STEEL
PLATE PER
STRUCTURAL PLANS
NEW DARK ANODIZED - GRAY
A
LUMINUM LOUVERS WITH
INSECTS SCREEN.
FREE AREA > 45%.
INSTALL PER MAUFACTURER
RECOMMENDATIONS
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
CMU WALL PER
STRUCTURAL PLANS
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
EZ CLIP OR CAULKING
PER MANUFACTURER
RECOMMENDATION
J-MOLDING
2" MIN. @ PAVING
4" MIN.
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
(E) LANDSCAPE TO
REMAIN
CMU WALL PER
STRUCTURAL
PLANS
GALVANIZED
METAL SCREED
EXTERIOR INTERIOR
SILL DETAIL
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
NEW DARK ANODIZED - GRAY ALUMINUM
LOUVERS WITH INSECT SCREEN
INSTALL PER MAUFACTURER
RECOMMENDATIONS
SLOPE
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
EZ CLIP OR CAULKING
PER MANUFACTURER
RECOMMENDATION
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
J-MOLDING
J-MOLDING
HEAD/JAMB DETAIL
NOTE:
THE ENGINE EXHAUST WILL COMPLY WITH NFPA 37 SECTION 8.2.3.1.
SECTION 8.2.3.1
PER NFPA 37
C
BA A. INSTALL A FABRIC FLEX CONNECTION
BETWEEN RADIATOR DISCHARGE FLANGE
AND SHEET METAL DUCT TO ISOLATE
VIBRATION.
B. USE A GRADUAL TRANSITION TO THE
LOUVER OPENING.
C. MOUNT AFJ-120 LOUVER WITH INSECT
SCREEN (REMOVEABLE).PRESSURE LOSS CALCULATION:
MAX. RESTRICTION OF COOLING AIR, INTAKE AND DISCHARGE : O.5 IN.WG.
RADIATOR-COOLED COOLING AIR (CFM): 1300 SCFM
FREE AREA OF AFJ-120 30"X36" : 1.36 SQFT
LOUVER FREE-AREA VELOCITY: V=1300/1.36 , V=956 FPM
BASED ON AIRFLOW RESISTANCE GRAPH FOR GREENHECK AFJ-120 LOUVER: STATIC PRESSURE DROP FOR LOUVER IS 0.085 IN.WG.
AVERAGE AIRFLOW RESISTANCE PERCENTAGE INCREASE FOR INSECT SCREEN : 17% THE TOTAL PRESSURE LOSS FOR LOUVER PLUS INSECT SCREEN : 0.1 IN.WG.
THIS IS BELOW THE GENERATOR ALLOWABLE EXTERNAL STATIC RESTRICTION OF 0.5 IN.WG.,LEAVING APPROXIMATELY 0.4 IN.WG. AVAILABLE FOR DUCT STRAIGHT RUN AND TRANSITIONS.
B. PENETRATION @ RIB ( FLASHING)
A. ROOF JACK
NOTE:
• CONTRACTOR TO VERIFY IN THE FIELD THE EXACT LOCATION OF THE VENT ON THE ROOF • DIESEL TANK VENT SHALL COMPLY WITH NFPA 30
• SEE DIESEL TANK VENTING NOTES ON SHEET A-101
PER NFPA 30 REQUIREMENTS
TERMINATE THE VENT OUTLETS WITH AN OPW
623V PRESSURE VACUUM VENT
HIGH SIDE EAVE TRIM
ROOF PANEL TO BE INSTALLED PER
MANUFACTURER RECOMMENDATIONS.
PROVIDE CLOSURES & TRIMS AS
REQUIRED
ROOF DECK PER STRUCTURAL
PLANS
HSS BEAM PER STRUCTURAL
PLANS
HIGH EAVE
ROOF PANEL TO BE INSTALLED PER
MANUFACTURER RECOMMENDATIONS.
PROVIDE CLOSURES & TRIMS AS
REQUIRED
ROOF DECK PER
STRUCTURAL PLANS
LOW SIDE EAVE TRIM
HSS BEAM PER STRUCTURAL PLANS
RAKE TRIM
ROOF PANEL TO BE INSTALLED PER
MANUFACTURER RECOMMENDATIONS.
PROVIDE CLOSURES & TRIMS AS
REQUIRED
ROOF DECK PER STRUCTURAL
PLANS
RAKELOW EAVE
HSS BEAM PER STRUCTURAL
PLANS
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set
07302026 1 Addendum on Bid Set
DETAIL
A-5013" = 1'-0"LOUVER - HEAD/JAMB & SILL DETAIL 4 3" = 1'-0"WALL BASE 13" = 1'-0"LOUVER - HEAD/JAMB & SILL DETAIL 7 12 12" = 1'-0"ENGINE EXHAUST DETAIL 3
1/4" = 1'-0"RADIATOR DISCHARGE DETAIL 2
12" = 1'-0"VENT THROUGH ROOF DETAILS 6
1 1/2" = 1'-0"ROOF EAVE 8
1 08/05/26 SD 08/05/26 KM
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
1 38
TITLE SHEET
NI/ZT
SD
KM
VICINITY MAP
AVECOSTA
LA
BLVD
CARLSBAD
RD
ALGA
PALOMAR AIRPORT
RD
EL
CAMINO
REAL
RANCHO
SANTA FE
RD
POINSETTIA
LANE
ALICANTE
RD
EL
FUERTE
OLIVENHAIN RD.
MELROSE
DR.
FARADAY
COLLEGE
BLVD
PASEO
DEL
NORTE
AVE
AVENIDA
ENCINAS
CANNON RD
MONROE
ST
CARLSBAD
VILLAGE DR
MARRON
TAMARACK
AVE
RD
LAKE
CALAVERABUENA
VISTA
LAGOON
AGUA HEDIONDA
LAGOON
BATIQUITOSLAGOON
AVIARA
PKWY
POINSETTIA
LANE
LOCATION MAP
PROJECT SITE
CHINQUAPIN LIFT STATION IMPROVEMENTS
CIP 5554
CONSTRUCTION PLANS
FOR THE
CARLSBAD, CALIFORNIA
CITY OF CARLSBAD, UTILITIES DEPARTMENT
KEITH BLACKBURN - MAYOR
CITY COUNCIL MEMBERS
GEOFF PATNOE
PAZ GOMEZ
JUNE 2026
CITY MANAGER
DEPUTY CITY MANAGER, PUBLIC WORKS
TERESA ACOSTA - DISTRICT 4
PRIYA BHAT-PATEL - DISTRICT 3
MELANIE BURKHOLDER - DISTRICT 1
KEVIN SHIN - DISTRICT 2
PROJECT SITE
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
5'
5'
GATE OPENING
WET WELL
9.5'
9.5'
GATE OPENING
VALVE VAULT
42"
3.5" MIN TOEBOARD
(P) SUCTION PIPE
4.5'
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
LEGEND
DESCRIPTION SYMBOL
ABBREVIATIONS
DESCRIPTION ABBREVIATION
2 38
CIVIL NOTES, LEGEND AND
ABBREVIATIONS
NI/ZT
SD
KM
C-01
NOTES:
1. CONTRACTOR SHALL DESIGN AND INSTALL IN ACCORDANCE WITH OSHA: 1910:29 - FALL PROTECTION SYSTEMS AND FALLING OBJECT PROTECTION-CRITERIA AND PRACTICES. SUBMIT SAFETY RAIL SYSTEM FOR APPROVAL. TUBE SHALL BE ALUMINUM TUBE, SCHEDULE 40, 1-1/2 INCHES, 1.90 INCHES (48 MM) OD.
FITTINGS, INCLUDING ELBOWS, CROSSOVERS, FLANGES, TEES, CLAMPS, COUPLINGS: SHALL BE ALUMINUM ALLOY FITTINGS ASTM A356 T-6, KEE LITE STRUCTURAL PIPE FITTINGS, OR APPROVED EQUAL. ALL BOLTING AND FASTENERS SHALL BE 316 STAINLESS STEEL.
2. DESIGN PARAMETERS SHALL BE:
· TOP RAIL: 42-INCHES ABOVE THE WORKING LEVEL
· MID RAIL: REQUIRED HALFWAY BETWEEN THE TOP RAIL AND THE FLOOR/ROOF · STRENGTH: THE RAILING MUST WITHSTAND A FORCE OF AT LEAST 200
POUNDS APPLIED IN ANY DIRECTION TO THE TOP RAIL
· MAXIMUM LENGTH: MAXIMUM SINGLE RAIL LENGTH OF 8 FEET BETWEEN
STANCHIONS
· TOEBOARDS: AT LEAST 3.5-INCHES HIGH
HATCH GUARDRAIL
SCALE: NTS1
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
(E) WET WELL WALL
STRUCTURE TO
REMAIN(E) VALVE VAULT
STRUCTURE, LADDER,
AND HATCH TO REMAIN
ITEM REMOVED
BY OTHERS
REMOVE AND DISPOSE
OF ALL ITEMS, EXCEPT
PUMPS AND SUMP
DISCHARGE PIPE
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
3 38
LOCATION MAP, CIVIL SITE PLAN
AND DEMOLITION PLAN
NI/ZT
SD
KM
C-02
CARLSBAD BLVD
PROJECT SITE,
SEE SHEET C-03
FOR SITE PLAN CITY OF CARLSBAD R/W
EXISTING SEWER AND LOCATION MAP
SCALE: 1" = 20'2
CHINQUAPIN LIFT STATION (EXISTING) CIVIL SITE MAP
SCALE: 1" = 10'1
CHINQUAPIN LIFT STATION GENERATOR AND
ENCLOSURE IMPROVEMENTS. SEE ELECTRICAL,
STRUCTURAL, AND ARCHITECTURAL SHEETS,
SERIES G, D, A, S & E
CHINQUAPIN LIFT STATION WET WELL AND
CHECK VALVE VAULT IMPROVEMENTS. SEE
CIVIL SHEETS, SERIES C
CHINQUAPIN LIFT STATION LANDSCAPE AND
IRRIGATION IMPROVEMENTS. SEE LANDSCAPE
SHEETS, SERIES L
SITE MAP LEGEND
65'1
2"
N N
(E) LIFT STATION
WET WELL
(E) LIFT STATION
VALVE VAULT
(E) SEWER MH 16C-75
(E) 8" VCP SEWER
(E) 8" VCP SEWER
(E) SEWER MH 16C-84
WET WELL AND VALVE VAULT PLAN VIEW
SCALE: 1" = 4'3
DEMOLITION NOTES:
1. REMOVE ALL MECHANICAL ITEMS WITHIN
THE LIMITS HATCHED AS SHOWN AND
OTHER ITEMS INDICATED FOR DEMOLITION.
2. SEE SHEET C-03 FOR OTHER SURFACE
DEMOLITION AND REPLACEMENT LIMITS.
3. PROTECT ALL OTHER ITEMS NOT INDICATED
FOR DEMOLITION
WET WELL AND VALVE VAULT SECTION VIEW
SCALE: 1" = 4'A
REMOVE AND DISPOSE
OF ALL DISCHARGE
PIPING AND VALVES
EXCEPT SUMP PUMP
REMOVE AND DISPOSE OF
ALL ITEMS EXCEPT PUMPS,
WET WELL, AND SUMP
DISCHARGE PIPE
WET WELL DEMOLITION
VALVE VAULT DEMOLITION
WET WELL SLAB DEMOLITION
REMOVE AND DISPOSE
OF CONCRETE TOP SLAB,
HATCH, CONTROL
EQUIPMENT, AND
CONCRETE CURB
SEWER GRAVITY FLOW
DIRECTION (TYP)
FORCE MAIN FLOW
DIRECTION
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
(P) 48"X48" SINGLE LEAF
ALUMINUM HATCH. BILCO
TYPE JD-AL, OR EQUAL,
WITH LIFT ASSIST. RUN
HATCH DRAIN TO CURB 10' DIAMETER WET WELL SLAB.
REMOVE EXISTING CONCRETE
AND REPLACE WITH NEW
POLYMER CONCRETE, OLSEN
POLYMER ROCK HARD OR
EQUAL. SEE DETAIL 4.
(RR) EXISTING CONCRETE WITH NEW
CONCRETE PER CITY STANDARDS
(RR) EXISTING CURB WITH NEW 6"
CONCRETE CURB PER SDRSD G-1
(RR) EXISTING CONCRETE WALKWAY JOINT
TO JOINT WITH NEW ENHANCED CONCRETE
(SCOFIELD C-15 COACHELLA SAND COLOR,
MEDIUM SANDBLAST FINISH, WITH 6" SMOOTH
TROWL BANDS) TO MATCH EXISTING
(P) NEW BUILDING TOTAL
240SF. SEE STRUCTURAL
PLANS.
(RR) 4-INCH THICK AC
PAVEMENT
(E) BUILDING
STRUCTURE 160SF
20.0'
13'4"
38'3"
(E) 22' DRIVEWAY
18'3.25"
(RR) 4-INCH THICK AC
PAVEMENT PER CITY
STANDARD GS-24
THROUGH GS-28
(P) CONTRACTOR SHALL DESIGN
AND INSTALL TEMPORARY
ACCESS PATH AND STAIRCASE
FOR SAFE ACCESS DURING
CONSTRUCTION. TEMPORARY
ACCESS TO BE REMOVED UPON
PROJECT COMPLETION.
RR (E) FENCE FOR
TEMPORARY ACCESS
PATH. REPLACE IN KIND
TO MATCH EXISTING
EXISTING ACCESS
PATH TO LAGOON DETOUR ACCESS PATH
TO LAGOON
TEMPORARY SITE FENCING (TYP)
PEDESTRIAN ACCESS PATH DETOUR
AND STAIRCASE SHALL BE INSTALLED
PRIOR TO RESTRICTING ACCESS
THROUGH SITE.
(P) NEW BUILDING WITH
ADDITIONAL 80 SF
(PIP) EXISTING
CITY SURVEY
CONTROL
STATION
(RR) EXISTING
BACKFLOW WITH
ENCLOSURE PER
CMWD DWG W-6.
SEE L-SHEETS.
PIPE SHELLNOTES
1. ALL PRESSURE GAUGE ASSEMBLY, PIPE, VALVES SHALL BE TYPE 316 SS.
STAINLESS STEEL PRESSURE
GAUGE (MIN. 3-1/2" DIA.
CALIBRATED IN APPLICABLE
UNITS) OR PRESSURE SWITCH
DIAPHRAGM SEAL, WITH
STAINLESS STEEL DIAPHRAGM
AND LOWER HOUSING
1" SCH. 80 S.S. NIPPLE (TYP.)
1" SCH. 80 S.S. BALL VALVE
1" SS DIELECTRIC UNION
COAT WITH EPOXY
1 2" BALL VALVE
1 4" SCH. 80 S.S. BALL VALVE
1 4" SCH. 80 S.S. NIPPLE
CONNECTION FOR OIL FILL
DIP SPOOL CLASS 53
WITH THREADED OUTLET
NOTES
1. INSIDE DIAMETER OF EACH WALL OPENING SHALL BE OF
THE SIZE RECOMMENDED BY THE SEAL MANUFACTURER TO
FIT THE PIPE OR CONDUIT AND TO ENSURE A WATER-TIGHT
JOINT.
2. WALL SEAL ASSEMBLY SHALL BE OF THE MODULAR
MECHANICAL TYPE, CONSISTING OF INTERLOCKING
SYNTHETIC RUBBER LINKS SHAPED TO FILL THE ANNULAR
SPACE BETWEEN THE PIPE AND THE WALL OPENING. A
PRESSURE PLATE SHALL BE PROVIDED UNDER EACH BOLT
HEAD AND NUT, WITH THE SEAL CONSTRUCTED TO
PROVIDE ELECTRICAL INSULATION BETWEEN WALL AND
PIPE. WALL SEAL ASSEMBLY SHALL BE LINK SEAL AS
MANUFACTURED BY GPT INDUSTRIES OR APPROVED
EQUAL. ALL HARDWARE SHALL BE STAINLESS STEEL,
GRADE 316.
3. FOR PENETRATIONS THROUGH THE EXISTING WET WELL
WALL, THE INTERIOR WALL LINER SHALL BE REPAIRED
AFTER THE WALL PENETRATION PER SPECIFICATION
SECTION 06621.
(E) INTERIOR
CONCRETE
WALL
BOLT AND NUT,
TYPE 316 SS
MODEL "C" LINK-SEAL
MODULAR SEAL
MANUFACTURED BY
GPT INDUSTRIES OR
APPROVED EQUAL
WALL SEAL
ASSEMBLYNON-SHRINK
GROUT (TYP)
PIPE OR
CONDUIT
CORE DRILL
(E) EXTERIOR
CONCRETE
WALL
INSTALL PUMP GUIDE RAIL TO CLEAR HATCH
SUPPORT SHELF PER MANUFACTURER'S
RECOMMENDATIONS; MOUNTING HARDWARE
SHALL BE 316 STAINLESS STEEL
10' DIAMETER REINFORCED POLYMER
CONCRETE PRECAST TOP SLAB. MATCH
EXISTING TOP SLAB THICKNESS. TO BE
DESIGNED BY MANUFACTURER, H20-RATED,
OLSON PRECAST OR APPROVED EQUAL.
1 4" ALUMINUM
CHANNEL FRAME
WITH RECESSED
ANCHORS (TYP)
AUTOMATIC HOLD OPEN ARM
REMOVABLE COVER PLUG
REMOVABLE SQUARE KEY WRENCH
4' X 4' SINGLE LEAF HINGED H20-RATED HATCH (BILCO
TYPE J-AL CUSTOM SIZE) WITH TYPE 316 STAINLESS
STEEL HARDWARE. HATCH TO DRAIN TO CURB.
HEAVY DUTY FORGED 316 STAINLESS STEEL
HINGES WITH 316 STAINLESS STEEL PINS
316 STAINLESS STEEL LIFTING
MECHANISM WITH REINFORCED
COMPOSITE TUBES AND
COMPRESSION SPRINGS
1 4" SUPPORT PLATE
WELDED TO FRAME
(PIP) EXISTING WET WELL
(PIP) EXISTING WET WELL LINER;
REPAIR ALL LINER DAMAGES PER
SPEC SECTION 06621. SEE C-04
DETAIL 2 FOR LINER REPAIR DETAIL.
REPAIR LINER PER SPEC
SECTION 06621; TURN BACK
LINER AT LEAST 2 INCHES (TYP)
APPLY SIKA 31 HI MOD GEL JOINT
SEALANT OR APPROVED EQUAL PER
MANUFACTURER'S RECOMMENDATIONS
BETWEEN POLYMER CONCRETE SLAB
AND EXISTING WET WELL WALL PER
ASTM C990 (TYP)
HEAVY DUTY CHECK CHAIN
SLAM LOCK
MIN 2"
48"
FRAME CLEAR
OPENING
12" 24"24"
8" SCHEDULE 80 PVC PIPE BLIND FLANGE
A
-
4' X 4' SINGLE LEAF
HATCH. SEE SECTION A.
POLYMER CONCRETE SLAB TO BE
DESIGNED BY MANUFACTURER;
H-20-RATED; OLSON PRECAST OR
APPROVED EQUAL
TOP SLAB 10'
DIAMETER
WET WELL 8' DIAMETER
29"
36"
43"
36"
8" SCHEDULE 80 PVC
PIPE BLIND FLANGE
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
4 38
SITE PLAN
AND DETAILS
NI/ZT
SD
KM
C-03
CHINQUAPIN LIFT STATION CIVIL SITE PLAN
SCALE: 1" = 5'1
N
TOP SLAB AND HATCH FOR WET WELL SECTION VIEW
SCALE: NTSA
WALL PENETRATION
SCALE: NTS2 PRESSURE GAUGE WITH DIAPHRAGM SEAL
SCALE: NTS3
TOP SLAB AND HATCH FOR WET WELL PLAN VIEW
SCALE: NTS4
N
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
RR (E) PRESSURE GAUGE.
SEE SHEET C-03 DETAIL 3
18"
PIP (E) PUMP (TYP OF 2). COORDINATE
WITH CITY OPERATIONS TO APPROVE
OF REMOVAL, HANDLING, AND
STORAGE DURING CONSTRUCTION.
RR (E) 4" DIP
DISCHARGE PIPE AND
FITTINGS (TYP OF 2)
PUMP GUIDE RAIL SYSTEM (TYP OF 2)
WITH 316 STAINLESS STEEL GUIDE RAIL,
MOUNTING KIT, AND HARDWARE PER
FLYGT. INSTALL PER MANUFACTURER'S
RECOMMENDATIONS AND VERTICALLY
PLUMB.
RR (E) MOUNTING ASSEMBLY (TYP
OF 2). REPAIR CONCRETE AND
WET WELL LINER AS REQUIRED
RR (E) DISCHARGE ELBOWS
WITH NEW FLYGT #540-13-05,
4" DISCHARGE ELBOW
CONNECTIONS (TYP OF 2)
2'-7"
10'-2"
95"
8'
18'-5"
CHECK VALVE (TYP OF 2)
316 SS PIPE SUPPORT 4" PER
DETAIL 3 (TYP OF 2)
316 SS PIPE SUPPORT 6" PER
DETAIL 3 (TYP OF 3)
21"
IE 14.00'4" PLUG VALVE (TYP OF 2)
REPAIR EXISTING WET WELL LINER.
SEE DETAIL 2 (TYP).
SEE SHEET C-03
DETAIL 2 FOR WALL
PENETRATION (TYP)
3'-11"
1'-5"
315 SS WALL BRACKET
MOUNT PIPE BRACING
(TYP OF 2)
SEE SHEET C-01 DETAIL 1 FOR
HATCH GUARDRAILS
4" VICTAULIC
COUPLING
(TYP OF 4)
A
C-04
(E) WEST PUMP (WP)
(E) EAST PUMP (EP)
6" DIP (PE X GE/VIC) WITH
VIC FLANGE STYLE 341
6" FLOW METER ENDRESS
& HAUSER PROLINE
PROMAG W400 OR EQUAL
WITH INSULATING
FLANGE KIT PER WC-3
6" X 4" DI TEE (FL)
6" DIP (GE/VIC X GE/VIC)
6 X 4 REDUCING 90 BEND
RR (E) 4" DIP (PE X FL)
(TYP OF 2)
SEE SHEET C-03 DETAIL 4 FOR
TOP SLAB AND HATCH
4" ECCENTRIC
PLUG VALVE
(TYP OF 2)
4" CHECK VALVE SURGEBUSTER BY
VAL-MATIC OR EQUAL (TYP OF 2)
4" VICTAULIC
COUPLING STYLE 341
(TYP OF 4)
6" DIP TEE WITH 6" PLUG
VALVE AND BLIND FLANGE
94.75"
24" 44.5"26.25"
4" DIP (PE
X GE/VIC)
(TYP OF 2)
SEE SHEET C-03 DETAIL 2 FOR
WALL PENETRATION (TYP OF 6)
REPAIR EXISTING WET WELL
LINER. SEE DETAIL 2 (TYP)
4" DIP (FL X GE/VIC) (TYP OF 2)
3-WAY PLUG VALVE (FL)
6" VIC FLANGE STYLE 3416" DIP (FL X GE/VIC)
WITH BLIND FLANGE
6" DIP TEE (FL X FL)
8" SCHEDULE 80 PVC PIPE BLIND FLANGE.
SEE DETAIL 4 FOR SUCTION PIPE DETAIL.
12"
6" VIC FLANGE STYLE 341
PIP (E) LADDER
6" RESTRAINED COUPLING PER
ROMAC ALPHA OR EQUAL
(E) 6" PVC
PRESSURE GAUGE (TYP OF 2)
12"
316 SS PIPE SUPPORT 6"
PER DETAIL 3 (TYP OF 3)
316 SS PIPE SUPPORT 4"
PER DETAIL 3 (TYP OF 2)
6" KNIFE GATE FABRI-VALVE C67
BI-DIRECTIONAL VALVE OR EQUAL
B
C-04
5.25"
6" DIP 90 BEND
6" ECCENTRIC PLUG
VALVE WITH BLIND
FLANGE
3-WAY PLUG
VALVE (FL)
316 SS PIPE
SUPPORT 6"
PER DETAIL 36" DIP TEE (FL X FL)
NOTES:
1. UNDER VALVES, METERS, OR OTHER SPECIAL
APPURTENANCES A FABRICATED SUPPORT PIECE MAY
BE BE UTILIZED AS ACCEPTABLE TO ENGINEER.
2. WHERE SHOWN UNDER PIPE OR VALVE FLANGE,
PROVIDE FLANGE CRADLE SUPPORT BY MATERIAL
RESOURCES OR ENGINEER APPROVED EQUAL.
3. PROVIDE TYPE 316 STAINLESS STEEL UNITS.
4. SIZE OF SUPPORT COMPONENTS AND THEIR
CONNECTIONS SHOWN FOR PIPE, DUCT, HVAC, AND
EQUIPMENT ANCHORAGE SYSTEM ARE MINIMUM
REQUIREMENTS (INCLUDING ANCHOR BOLT SIZE,
SPACING, AND EMBEDMENT LENGTH). CONTRACTOR
SHALL DESIGN ALL SUPPORT COMPONENTS AND THEIR
CONNECTIONS PER SPECIFICATIONS AND INCREASE
SIZES AS REQUIRED BY DESIGN CALCULATIONS.
5. AS AN ALTERNATIVE, CONTRACTOR MAY USE
ADJUSTABLE PIPE SUPPORT WITH BASE BY PIPELINE
PRODUCTS, MODEL PS-S
ADJUSTABLE PIPE SUPPORT
150 LB. THREADED
REDUCING FLANGE,
GALVANIZED
SS ANCHOR BOLT OR SS
ADHESIVE CAPSULE ANCHOR
WITH (2) NUTS EACH, SIZE TO
SUIT FLANGE. TYPICAL OF (4)
ADJUSTABLE PIPE SUPPORT
APPROXIMATE DIMENSION IN INCHES
PIPE
SIZE A B C D
MIN
D
MAX
4" & 6" 3 2 1/2 9 11 5/8 15 1/4
PIPE SIZE
18'-5"
24"
316 SS OFFSET PIPE
CLAMP AND
FASTENERS PER ANVIL
INTERNATIONAL OR
APPROVED EQUAL
(TYP OF 2)
8" SCHEDULE
80 PVC PIPE
8" SCHEDULE
80 PVC PIPE
BLIND FLANGE
8" SCHEDULE
80 PVC FITTING
45° BEND
2"
10" DIAMETER PIPE
OPENING WITH LINK SEAL.
EPOXY SEAL UNDER SLAB
PER SIKADUR 31 OR EQUAL
4"
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
5 38
WET WELL AND VALVE VAULT
IMPROVEMENTS AND DETAILS
NI/ZT
SD
KM
C-04
PLAN VIEW
SCALE: 1" = 2'1
SECTION VIEW
SCALE: 1" = 2'A
NOTE:
DIMENSIONS PROVIDED FOR REFERENCE ONLY.
CONTRACTOR TO FIELD VERIFY ALL
DIMENSIONS PRIOR TO ORDERING MATERIALS.
LINER REPAIR DETAILS
SCALE: NTS2
LINER REPAIR NOTES:
1. REPAIR EXISTING T-LOCK PVC LINER PER LINABOND REPAIR PRODUCTS OR APPROVED EQUAL. REPAIR ALL LINER OPEN SEAM TEARS, PIPE PENETRATIONS,
PIPE BRACING, LINER TURNBACK UNDER NEW TOP SLAB, AND OTHER LINER DEFECTS, IN ACCORDANCE WITH SPECIFICATIONS AND MANUFACTURER'S RECOMMENDATIONS. SEE LINER REPAIR DETAILS.
2. CONTRACTOR SHALL INSPECT WET WELL, IDENTIFY ALL REPAIRS, AND SUBMIT REQUIRED PRODUCT AND INSTALLATION INFORMATION FOR CITY APPROVAL.
ADJUSTABLE PIPE SUPPORT
SCALE: NTS3
SUCTION PIPE
SCALE: NTS4
SECTION VIEW
SCALE: 1" = 2'B
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
ALIGN
AFF ABOVE FINISHED FLOOR
A.G. ACCESSORY GROUP
A.D. ACCESS DOOR
ACOUS ACOUSTICAL
ACT. ACOUSTICAL TILE
ADD ADDENDUM
ADJ ADJACENT
A.C. AIR CONDITION
ALT ALTERNATE
ALUM ALUMINUM
A.B. ANCHOR BOLT
APPROX APPROXIMATE
ARCH ARCHITECTURAL
AD AREA DRAIN
AUTO AUTOMATIC
ASL ABOVE SEA LEVEL
B.E.J. BRICK EXPANSION JOINT
BSMT BASEMENT
B.T. BATH TUB
BM BEAM
BRG BEARING
B.M. BENCH MARK
BET BETWEEN
BIT BITUMINOUS
BLK BLOCK
BLKG BLOCKING
BD BOARD
BS BOTH SIDES
BOT BOTTOM
BRK BRICK
B.C. BRICK COURSE
BLDG BUILDING
BUR BUILT-UP ROOFING
B.O. BY OWNER
CAB CABINET
C.H. CABINET HEATER
CHNL CHANNEL
C.O. CLEAN OUT
C.O. CLEAN OUT
CO2 CARBON DIOXIDE
CARP. CARPET
C.W. CASEWORK
C.I. CAST IRON
C.B. CATCH BASIN
CEM CEMENT
CM CENTIMETER
CT CERAMIC TILE
CHBD CHALK BOARD
CLG. CEILING
CLR CLEAR
COL COLUMN
CONC. CONCRETE
CMU CONCRETE MASONRY UNIT
COND CONDUCTIVE
C.S.V CONDUCTIVE SHEET VINYL
CONT. CONTINUOUS
CLL CONTRACT LIMIT LINE
CONTR CONTRACTOR
C.J. CONTROL JOINT
CONV CONVECTOR
C.G. CORNER GUARD
CORR CORRIDOR
C.S. COUNTER SINK
CRS COURSE
C.R. CURTAIN ROD
C.R.-1 CRASH RAIL
DEM DEMOLISH/DEMOLITION
DET. DETAIL
DIAG DIAGONAL
DIA. DIAMETER
DIFF. DIFFUSER
DIM. DIMENSION
DISP. DISPENSER
DO DITTO
DR DOOR
DBL DOUBLE
DN DOWN
DS DOWNSPOUT
DWG. DRAWING
D.F. DRINKING FOUNTAIN
EA EACH
ELEC. ELECTRICAL
ELEC. CAB ELECTRIC CABINET
EPNL ELECTRIC PANEL
EWC ELECTRIC WATER COOLER
EL ELEVATION
ELEV. ELEVATOR
EQ EQUAL
E.O. EQUIPMENT BY OWNER
EX EQUIPMENT, X-RAY
EX.F EXHAUST FAN
(E) EXISTING
EXP. JT. EXPANSION JOINT
EXP'D EXPOSED
EXT EXTERIOR
E.I.F.S. EXTERIOR INSULATION
& FINISH SYSTEM
FB FACE BRICK
F.C.U. FAN COIL UNIT
F.D.C. FIRE DEPARTMENT
CONNECTIONS
F.N.V. FEM. NAPKIN VENDOR
FIN.RAD. FIN TUBE RADIATION
FIN FINISH
F.A. FIRE ALARM
FEC FIRE EXTINGUISHER CAB
FHC FIRE HOSE CABINET
F.H. FIRE HYDRANT
F.P. FIRE PROOFING
FHMS FLAT HEAD MACH.SCREW
FHWS FLAT HEAD WOOD SCREW
FL. FLOOR
F.D. FLOOR DRAIN
FR FRAME
F.S. FINISH SLAB
FT FOOT
FTG FOOTING
FDTN FOUNDATION
FUR FURRING
FUR. CH. FURRING CHANNEL/S
F.W. FULL WIDTH
F.W.C. FABRIC WALL COVERING
GAL GALLON
GALV. GALVANIZED
GI GALVANIZED IRON
GA GAGE
G.C. GENERAL CONTRACT
GL GLASS
G.B. GRAB BAR
GSF GROSS SQUARE FEET
G.W.B. GYPSUM WALL BOARD
HR-1 HANDRAIL
HDNR HARDENER
HDW HARDWARE
HD.WD. HARDWOOD
HTR HEATER
HTG HEATING
HVAC HEATING, VENTILATION
& AIR CONDITIONING
HT HEIGHT
HC HOLLOW CORE
HM HOLLOW METAL
HORIZ HORIZONTAL
HB HOSE BIBB
H.C. HOSE CABINET
H.C.U. HOSPITAL CASEWORK UNIT
H.C.T. HOSPITAL CUBICAL TRACK
H.PL. HOT PLATE
H.P.L. HIGH PRESSURE
PLASTIC LAMINATE
H.W. HOT WATER
HR HOUR
INCIN. INCINERATOR
I.D. INSIDE DIAMETER
INSUL. INSULATE(D)(ION)
INS. GL INSULATED GLASS
INT INTERIOR
IV INTRAVENOUS
INV INVERT
JAN JANITOR
JT JOINT
KIT KITCHEN
KO KNOCK OUT
L.C. LABORATORY CASEWORK
LEV LOW EMISSION VEHICLE
LAM LAMINATED
LAV. LAVATORY
L.GL. LEADED GLASS
LH LEFT HAND
LGT LENGTH
LT LIGHT
LT.P LIGHT PANEL
LTWT LIGHT WEIGHT
L.F. LINEAR FEET
LTL LINTEL
LL LIVE LOAD
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LVR LOUVER
L.P. LOW POINT
MACH MACHINE
M.H. MANHOLE
MFR MANUFACTURER
MARB MARBLE
MAS MASONRY
M.O. MASONRY OPENING
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MC MEDICINE CABINET
MEMB MEMBRANE
MET METAL
MTD MOUNTED
M.T.P. METAL TOILET PARTITION
MET. TM METAL TRIM
M.W.U. MILLWORK UNIT
MIN. MINIMUM
MISC. MISCELLANEOUS
MOD MODULAR
M.H. MOP HOPPER
MOV MOVABLE
MULL MULLION
(N) NEW
NAT NATURAL
N.L. NIGHT LIGHT
N2O NITROUS OXIDE
NRC NOISE REDUCTION COEIF.
N.I.C. NOT ON CONTRACT
N.T.S. NOT TO SCALE
NOM NOMINAL
NO. NUMBER
OBS OBSCURE
O.C. ON CENTER
OPNG OPENING
OPP OPPOSITE
OPH OPPOSITE HAND
O.D. OUTSIDE DIAMETER
OHMS OVAL HEAD MACH. SCREW
OHWS OVAL HEAD WOOD SCREW
OA OVERALL
OH OVERHEAD
O2 OXYGEN
PNT PAINT(ED)
PNL PANEL
P.T.D PAPER TOWEL DISPENSER
P.T.R. PAPER TOWEL RECEPTACLE
P.BD. PARTICLE BOARD
PTN PARTITION
PVMT PAVEMENT
PG.BD. PEG BOARD
PLAS. PLASTER
P.LAM PLASTIC LAMINATE
PL PLATE
PL.GL. PLATE GLASS
PLMB PLUMBING
PMLD PREMOLDED
PWD PLYWOOD
PT POINT
PPGL POLISHED PLATE GLASS
PPTGL POLISHED PLATE
TEMPERED GLASS
PPWGL POLISHED PLATE
WIRE GLASS
PVC POLYVINYL CHLORIDE
PCF POUNDS PER CU.FT.
PSI POUNDS PER SQ. INCH
PSF POUNDS PER SQ.FT.
P.P. POWER PANEL
PCP PRECAST CONCRETE PANEL
PRE. FAB. PREFABRICATED
PREF. PREFINISHED
PSC PRE-STRESS CONC.
PROJ PROJECTION
PL PROPERTY LINE
PTDF PRESSURE TREATED
DOUGLAS FIR
QTY QUANTITY
QT QUARRY TILE
RAD RADIUS
R.W.L. RAIN WATER LEADER
RECPT. RECEPTACLE, ELECTRIC
REC. RECESS(ED)
RE: REFER TO
R.C.P. REFLECTED CEILING PLAN
REFR. REFRIGERATOR
REG. REGISTER
REINF. REINFORCE(D)(ING)
REQ'D REQUIRED
RES RESILIENT
R.C.P. REINF. CONC. PIPE
RET RETURN
RA RETURN AIR
RVS REVERSE
REV REVISION
RH RIGHT HAND
ROW RIGHT OF WAY
R RISER
RVT RIVET
R.D. ROOF DRAIN
RFH ROOF HATCH
R.V. ROOF VENT
RFG ROOFING
RM ROOM
R.F.S. ROOM FINISH SCHEDULE
RO ROOF OPENING
RND ROUND
RBL RUBBLE STONE
S.A.M.F. SELF-ADHERED MEMBRANE
FLASHING
SDL SADDLE
S.N.C. SAN. NAP. CABINET
S.N.D. SAN.NAP.DISPOSER
STC SEALANT
STG SEATING
SECT. SECTION
S.S. SERVICE SINK
S.B. SHAMPOO BOWL
SHTH SHEATHING
SHT SHEET
SH SHELF, SHELVING
SHR SHOWER
SIM. SIMILAR
S SINK
S.DI. SOAP DISPENSER
SPKR SPEAKER
S.F.C. SPECIAL FLR. COATING
S.W.C. SPECIAL WALL COATING
S.O.G SLAB ON GRADE
SPEC. SPECIFICATIONS
SQ SQUARE
SST STAINLESS STEEL
SP STAND PIPE
STD STANDARD
STL STEEL
STER STERILIZER
SD STORM DRAIN
S.G.T. STRUCTURAL GLAZED TILE
STRUCT STRUCTURAL
SUSP. SUSPENDED
S.V. SHEET VINYL
SW SWITCH
SWBD SWITCH BOARD
SYM SYMMETRICAL
T.B. TACKBOARD
T.P. TANGENT POINT
TEL TELEPHONE
TEMP TEMPERATURE
TEMP. GL. TEMPERED GLASS
TER. TERRAZZO
TEX. TEXTURE
THK THICK(NESS)
THR THRESHOLD
T.D. TISSUE DISPENSER
T TOILET (FIXTURE)
TPH TOILET PAPER HOLDER
T&G TONGUE & GROOVE
T.O.S. TOP OF STEEL
T.O.B TOP OF BEAM
T.O.C. TOP OF COLUMN
T.O.F. TOP OF FASCIA
T.O.FTG TOP OF FOOTING
T.O.P. TOP OF PARAPET
T.O.W. TOP OF WALL
TB TOWEL BAR
TYP TYPICAL
U.C. UNDERCUT
U/C UNDER COUNTER
U.C.L. UNDER COUNTER LIGHT
U.L. UNDERWRITERS
LABORATORIES INC.
UNGND UNDERGROUND
U.H. UNIT HEATER
U.V. UNIT VENTILATOR
U.N.O. UNLESS NOTED OTHERWISE
UR URINAL
UPH. UPHOLSTERY
V.T.R. VENT THROUGH ROOF
VENT VENTILATOR
V.I.F. VERIFY IN FIELD PRIOR TO
FABRICATION
VERT VERTICAL
VEST VESTIBULE
V.C.T. VINYL COMPOSITION TILE
V.W.C. VINYL WALL COVERING
V VINYL
VT VINYL TILE
WSCT WAINSCOT
W WASTE
WC WATER CLOSET
W.L. WATER LINE
WS WEATHER STRIP
WT WEIGHT
WWF WELDED WIRE FABRIC
W.C.D.F. WHEELCHAIR DRINKING
FOUNTAIN
WG WIRE GLASS
W.M.P. WIRE MESH PARTITION
W/ WITH
W/O WITHOUT
WD WOOD
W.R.B. WATER-RESISTANT BARRIER
(WEATHER-RESISTANT
BARRIER)
CHINQUAPIN LIFT STATION EMERGENCY GENERATOR
REPLACEMENT
COUNTY HWY S21,CARLSBAD, CA
CHINQUAPIN LIFT STATION EMERGENCY GENERATOR REPLACEMENT AND STRUCTURE IMPROVEMENTS.
ADDRESS: SOUTHEASTERLY CURB RETURN OF GARFIELD
STREET AND CHINQUAPIN AVENUE,CITY OF
CARLSBAD
ZONING: ZONE TYPE OF CONSTRUCTION: IIIB
OCCUPANCY: U
PROPOSED S.F.: 247 SF
APPLICABLE CODE
PROJECT INFORMATION
AUTHORITY HAVING JURISDICTION (AHJ): CITY OF CARLSBAD
ALL WORK SHALL COMPLY WITH THE FOLLOWING CODES:
CITY OF CARLSBAD MUNICIPAL CODE
2022 CALIFORNIA BUILDING CODE
2022 CALIFORNIA ELECTRICAL CODE
2022 CALIFORNIA PLUMBING CODE
2022 CALIFORNIA ENERGY CODE
2022 CALIFORNIA FIRE CODE
ALL CONSTRUCTION SHALL CONFORM TO THE 2022 CALIFORNIA BUILDING, FIRE, MECHANICAL, PLUMBING, ELECTRICAL, ENERGY CODE AND GREEN BUILDING CODE. ?
?
?
?
?
?
?
?
? ELEVATION
ALIGN
DIMENSION
CENTERLINE
DIMENSION
REVISION CLOUD
KEY NOTE
COLUMN GRID LINE
ROOM REFERENCE
SECTION
REFERENCE
DETAIL SECTION
REFERENCE
DETAIL OR ENLARGED
PLAN
DATUM
7'-6"
7'-6"
CL
3'-9" 3'-9"
A-8.6
1 SHEET NUMBER
VIEW NUMBER
VIEW NAME
DRAWING SCALE
VIEW NUMBER
?
NORTH ARROW
(PROJECT NORTH U.O.N.)
101
?
?
?
?
?
?
______________
? ??
LEGEND AND SYMBOLS
CLIENT: CITY OF CARLSBAD
PROJECT MANAGER: SEAN B. DIAZ, PE, QSD
E-MAIL: [email protected]
TEL: 442-200-7222
ARCHITECTURAL: IDS GROUP
PROJECT MANAGER: ANNIE BACTOL
E-MAIL: [email protected]
TEL: 949-387-8500 EXT. 146
ARCHITECTURAL: IDS GROUP
CONTACT: JOHN SILBER
E-MAIL: [email protected]
TEL: 949-387-8500 EXT.154
STRUCTURAL: IDS GROUP
CONTACT: VICTOR MERCADO
E-MAIL: [email protected]
TEL: 949-387-8500 EXT. 112
VICINITY MAP
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set PROJECT INFORMATION
G-100
PERSPECTIVE
PROJECT
LOCATION
SCOPE OF WORK
PROJECT TEAM
SHEET INDEX
S
HEET # SHEET NAME
GENERAL
G-
100 PROJECT INFORMATION
G-200 OVERALL SITE PLAN
DEMOLITION
D-200 DEMOLITION PLAN
ARCHITECTURAL
A-101 PROPOSED PLANS
A-201 PROPOSED ELEVATIONS AND SECTIONS
A-300 DETAILS - DOORS & LOUVERS
A-501 DETAIL
STRUCTURAL
S-001 STRUCTURAL GENERAL NOTES
S-002 STRUCTURAL GENERAL NOTES
S-200 FOUNDATION, FRAMING AND SECTION
S-201 ELEVATIONS
S-500 DETAILS
S-501 DETAILS
6 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
LINE OF SCOPE OF WORK
PATH OF EMERGENCY EGRESS
NOT IN SCOPE WORK
PROPOSED
NEW LIFT
STATION
CARLSBAD BOULEVARD
12 15
15 EXISTING SDG&E
PULLBOX PER
ELECTRICAL PLANS NEMA 3RX SST
METER PEDESTAL
PER ELECTRICAL
PLANS. SEE
STRUCTURAL PLANS
PROPOSED LIFT
STATION
PROPOSED
LIFT
STATION
12 15
15 12
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set OVERALL SITE PLAN
G-200
LEGEND - SITE PLAN
KEYNOTES
V
ALUE DESCRIPTIONS
12 EXISTING LIGHT POST TO REMAIN. PROTECT IN PLACE
15 EXISTING RAILING TO REMAIN.
3/16" = 1'-0"OVERALL SITE PLAN 2
247 S.F.
NOT IN SCOPE OF
W
ORK
3D - OVERALL SITE PLAN 1
(E) LANDSCAPE
(E) SERVICE
PARKING
7 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
EXISTING CMU WALL TO BE REMOVED
SHEET NOTES
DEMOLITION LEGEND
EXISTING CMU WALL TO REMAIN
1. SEE SHEET G-100 FOR ADDITIONAL NOTES AND ABBREVIATIONS.
2. REMOVE AND DISCARD ALL FLOOR FINISHES AND WALL BASE AS WELL AS FLASH PATCH,
MASTIC AND ADHESIVES DOWN TO THE STRUCTURAL CONCRETE FLOOR SLAB AND PREPARE FOR NEW FINISHES.
3. ALL LIFE SAFETY DEVICES SHALL REMAIN ACTIVE DURING DEMOLITION AND CONSTRUCTION.
EXISTING CONCRETE SLAB TO BE
REMOVED. SEE STRUCTURAL PLANS
A
1 01 07
04 B
11 PEDESTRIAN
ACCESS MUST BE
MAINTAINED DURING
CONSTRUCTION
06 04
02 03
06 07
0109
01 EXISTING MAIN
SERVICE CENTER
04 06
16 3
2 V.I.F
13' - 4"
03 02
V.I.F
1 2' - 0"
13 03
V.I.F
8' - 0"
16 0407
09 09
15 02
06 06
0101
01 07
07 16 03
09 16
EXISTING EMERGENCY
GENERATOR
05 1420 10
2013
10 0706 03 150409
+/- 7' - 10"
+/- 3' - 11"
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set DEMOLITION PLAN
D-200
1/4" = 1'-0"DEMOLITION PLAN 1
1/8" = 1'-0"01 DEMO PICTURES 2
KEYNOTES
V
ALUE DESCRIPTIONS
01 EXISTING 8" THICK CMU RETAINING WALL TO REMAIN, PATCH & REPAIR AS REQUIRED. APPLY SMOOTH PLASTER FINISH; COLOR: ICY WHITE DEHW 10
MATTE OR EQUAL & ELASTOMERIC SEALANT ON THE EXTERIOR SIDE 02 REMOVE EXISTING SWITCH BOARD, METER & CONTROL CABINET. SEE
ELECTRICAL PLANS
03 REMOVE & DISPOSE EXISTING EMERGENCY DIESEL GENERATOR. SEE
PER ELECTRICAL PLANS
04 REMOVE EXISTING WROUGHT IRON GATE
05 PORTION OF EXISTING CONCRETE SLAB TO REMAIN. PATCH & REPAIR AS
REQUIRED, LEVEL WITH TWO-COMPONENT POLYMER-MODIFIED,
PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL.
0.5% SLOPE V.I.F
06 EXISTING CONCRETE CURB TO REMAIN, PROTECT IN PLACE. SEE GENERAL NOTES #6 ON SHEET A-101
07 REMOVE EXISTING METAL ROOF AND ROOF SUPPORT
09 REMOVE EXISTING 8" THICK CMU RETAINING WALL
10 REMOVE EXISTING HOSE BIBB
11 REMOVE & DISPOSE EXISTING DISCONNECT SWITCH AND STAINLESS
STEEL CABINET
13 EXISTING BACKFLOW PREVENTION DEVICE ENCLOSURE TO BE REMOVED AND RELOCATED. REFER TO IRRIGATION SERIES FOR FUTURE LOCATION. (SEE LANDSCAPE PLAN)
14 REMOVE PORTION OF EXISTING CONCRETE SLAB. REPAIR, LEVEL WITH
TWO-COMPONENT POLYMER-MODIFIED, PORTLAND CEMENT BASED
MORTAR. USE SIKA TOP-122 PLUS OR EQUAL. SEE STRUCTURAL
15 EXISTING RAILING TO REMAIN.
16 GRIND EXISTING CONCRETE PAD TO LEVEL TO THE TOP OF EXISITNG CONCRETE SLAB. CUT REBARS 1" BELOW THE TOP OF THE SLAB. REPAIR,
LEVEL WITH TWO-COMPONENT POLYMER-MODIFIED, PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL
20 REMOVE & RELOCATE EXISTING IRRIGATION CONTROL SYSTEM 8 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
A
1 4
A-2012
A-201 4
A-201
3 A-201
5 20' - 0"
V.I.F
1 2' - 0"
6 A-201
______________
7 A-201
______________
D1
DIESEL
GENERATOR
ROOM
101
4' - 2" 10' - 10" 5' - 0"
31 32
35 39
01 31
B
33 DIESEL
GENERATOR
51 3
2 01
1' - 6" 9' - 4" 1' - 6"
05 0.5%
SLOPE
30 52
52 3137 54
38 55
TYP.
0.5%
SLOPE
57 57
57 59
59 60
61 7' - 10"
7' - 4"2' - 7"
3' - 8" 4' - 2"
GENERAL NOTES
1. SEE SHEET G-100 FOR ADDITIONAL NOTES AND ABBREVIATIONS.
2. PARTITIONS DIMENSIONED TO FINISH FACE U.N.O. DO NOT ADJUST DIMENSIONS INDICATED AS “CLEAR” WITHOUT WRITTEN DIRECTION FROM ARCHITECT. DRAWINGS SHALL NOT BE SCALED. VERIFY ALL DIMENSIONS AND EXISTING AS BUILT FIELD CONDITIONS, INCLUDING
FIELD MEASUREMENTS PRIOR TO START OF WORK, NOTIFY ARCHITECT WHERE DISCREPANCIES OCCUR.
3. LARGE SCALE DRAWINGS TAKE PRECEDENCE OVER SMALL SCALE DRAWINGS. DETAILS
TAKE PRECEDENCE OVERALL, NOTIFY ARCHITECT IN WRITING WHERE DISCREPANCIES OCCUR.
4. PATCH FLOOR AND WALL AREAS DAMAGED DUE TO NEW CONSTRUCTION OR WHERE PENETRATIONS HAVE BEEN MADE FOR MECHANICAL, ELECTRICAL AND PLUMBING WORK.
FIRESAFE AT UL RATED ASSEMBLIES CONSISTENT WITH EXISTING UL RATING.
5. WHERE EXISTING RATED ASSEMBLIES ARE SHOWN, CONTRACTOR IS REQUESTED TO FIELD VERIFY AS BUILT FIELD CONDITIONS TO CONFIRM RATINGS SHOWN. IF NON-COMPLIANT
CONDITIONS ARE FOUND, REPORT FINDINGS TO OWNER/ARCHITECT IN WRITING WHO WILL PROVIDE WRITTEN DIRECTION.
6. PATCH AND REPAIR ALL EXISTING CONCRETING, SLABS, WALLS, CURBS & OTHER PORTION
OF THE STRUCTURE, REPAIR & LEVEL WITH TWO COMPONENT POLYMER MODIFIED, PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL AFTER DEMOLITION WHERE DAMAGE HAS OCCURRED AT UNPROTECTED LOCATIONS. PLEASE
NOTE THAT DEMOLITION ACTIVITY MAY OCCUR BEYOND WORK LIMITS SHOWN ON DEMOLITION PLAN DUE TO CONCEALED CONDITIONS.
7. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL INSPECTIONS AND APPROVAL REQUIRED BY THE APPLICABLE DEPARTMENTS OF THE CITY OF CARLSBAD.
8. CONTRACTOR TO MAINTAIN PUBLIC ACCESS TO THE TRAIL DURING CONSTRUCTION.
EXISTING CMU WALL TO REMAIN
LEGEND
KEYNOTE TAGX
DOOR TAGXX
NEW CMU WALL, SEE STRUCTURAL PLANS
NEW CONCRETE SLAB, SEE STRUCTURAL PLANS
A
1 4
6 A-201
______________
7 A-201
______________
DIESEL
GENERATOR
ROOM
101
B
3 2
08 TYP.
4349
5' - 4" 5' - 1"
6' - 0" 7' - 5" 5' - 3"
2' - 6" 5' - 8" 2' - 7"
A
1 4
A-2012
A-201 4
A-201
3 A-201
5 6
A-201
______________
7 A-201
______________
1' - 6" 1 2' - 0" 1' - 6"
B
43 3
2 1' - 6" 20' - 0" 1' - 6"
43 15' - 0"
23' - 0"
59 59
DIESEL TANK VENTING NOTES
1. VENT PIPE OUTLETS FOR TANKS STORAGE CLASS-I, II OR III-A LIQUIDS SHALL BE LOCATED SUCH THAT THE VAPORS ARE RELEASED AT A SAFE POINT OUTSIDE OF BUILDINGS AND NOT LESS THAN 12 FEET ABOVE THE ADJACENT GROUND LEVEL. VAPORS SHALL BE DISCHARGED UPWARD AWAY FROM CLOSELY ADJACENT WALLS TO ASSIST IN VAPOR DISPERSION. VENT OUTLETS SHALL BE LOCATED SUCH THAT FLAMMABLE VAPORS WILL NOT BE TRAPPED BY EAVES OR OTHER OBSTUCTIONS AND SHALL BE AT LEAST 5 FEET FROM BUILDING OPENINGS OR PROPERTY LINES OF PROPERTIES THAT CAN BE BUILT ON. TERMINATE THE VENT OUTLETS WITH AN OPW 623V PRESSURE VACUUM VENT
2. TANK VENTS FOR NORMAL AND EMERGENCY VENTING SHALL BE INSTALLED AND MAINTAINED IN ACCORDANCE WITH CALIFORNIA FIRE CODE -2022, NFPA-30 AND WITH LOCAL AUTHORITY HAVING JURISDICTION.
3. NORMAL AND EMERGENCY VENT OUTLETS SHALL BE ATLEAST 10 FEET AWAY FROM ANY FRESH AIR INTAKE FROM MECHANICAL EQUIPMENT. COORDINATE WITH MECHANICAL CONTRACTOR.
4. VENT PIPES SHALL BE INSTALLED SUCH THAT THEY WILL DRAIN TOWARD THE TANK WITHOUT SAGS OR TRAPS IN WHICH LIQUID CAN COLLECT. VENT PIPES SHALL BE INSTALLED IN SUCH A MANNER AS TO NOT BE SUBJECT TO PHYSICAL DAMAGE OR VIBRATION.
5. NORMAL AND EMERGENCY VENT PIPE SIZES, PIPE MATERIALS AND PIPE FITTINGS , FUEL OIL SYSTEM DESIGN SHOP DRAWINGS AND SPECIFICATIONS (DESIGNED BY OTHERS) AND DIESEL TANK MANUFACTURER'S SPECIFICATIONS (DESIGNED BY OTHERS).
6. VENTING DEVICES SHALL BE INSTALLED IN ACCORDANCE WITH THEIR LISTINGS AND DIESEL TANK MANUFACTURER'S SPECIFICATIONS. USE OF FLAME ARRESTERS IN PIPING SYSTEMS SHALL BE IN ACCORDANCE WITH NATIONALLY RECOGNIZED CODES AND STANDARDS.
7. TANK INSTALLATION, PIPE MATERIAL AND FITTINGS, VENTING, FUEL OIL SYSTEM DESIGN SHOP DRAWINGS/SPECIFICATIONS AND MANUFACTURER'S SPECIFICATIONS SHALL BE APPROVED BY FIRE MARSHALL AND LOCAL FIRE AUTHORITY.
8. FUEL OIL SYSTEM PIPE MATERIAL SHALL COMPLY WITH CITY OF CARLSBAD FIRE DEPARTMENT MATERIALS AND INSTALLATION REQUIREMENT AND SUBJECT TO APPROVAL WITH AUTHORITY HAVING
JURISDICTION
FUEL OIL TANK VENT PIPING
A. STEEL PIPE: ASTM A53 OR ASME B36.10, SCHEDULE 40 BLACK. OUTDOOR RATED CORROSION RESISTANCE COATING FOR OUTDOOR PIPE ONLY.
1. FITTINGS: ASTM B16.3, BLACK MALLEABLE IRON, CLASS 150 (300 LB. WOG), THREADED.
2. JOINTS: NFPA 30, THREADED ANSI B31.4.
3. THREAD SEALANT: MAKE UP ALL THREADED CONNECTIONS UTILIZING SEALANT THAT IS COMPATIBLE WITH INTENDED SERVICE.
4. PIPE SHALL BE LABELED WITH PLASTIC WRAP AROUND LABELS IN ACCORDANCE WITH ANSI A13.1. THE LABELS SHALL HAVE PROPER IDENTIFICATION FOR FUEL OIL VENT, FUEL OIL FILL AND FUEL OIL DRAIN, ETC.
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set PROPOSED PLANS
A-101
1/4" = 1'-0"GENERATOR ENCLOSURE PLAN 1
KEYNOTES
V
ALUE DESCRIPTIONS
01 EXISTING 8" THICK CMU RETAINING WALL TO REMAIN, PATCH & REPAIR AS REQUIRED. APPLY SMOOTH PLASTER FINISH; COLOR: ICY WHITE DEHW 10
MATTE OR EQUAL & ELASTOMERIC SEALANT ON THE EXTERIOR SIDE 05 PORTION OF EXISTING CONCRETE SLAB TO REMAIN. PATCH & REPAIR AS
REQUIRED, LEVEL WITH TWO-COMPONENT POLYMER-MODIFIED,
PORTLAND CEMENT BASED MORTAR. USE SIKA TOP-122 PLUS OR EQUAL.
0.5% SLOPE V.I.F
08 NEW LIGHTING FIXTURE. SEE ELECTRICAL DRAWINGS.
30 NEW CONCRETE SLAB TO RECEIVE CONCRETE SEALER. 0.5% SLOPE. SEE
STRUCTURAL PLANS
31 NEW 8" THK CMU WALL PER STRUCTURAL PLANS. APPLY SMOOTH PLASTER; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL & ELASTOMERIC
SEALANT ON THE EXTERIOR SIDE
32 NEW DIESEL EMERGENCY GENERATOR & FUEL TANK ON A CONCRETE SLAB PER STRUCTURAL PLANS. CITY TO SUPPLY GENERATOR (20KW REHLKO/KOHLER, 20REOZK, OPEN UNIT SKID, 53 GALLON
TANK)CONTRACTOR TO INSTALL. SEE ELECTRICAL & STRUCTURAL PLANS 33 NEW MCC UNIT ON HOUSE KEEPING PAD PER ELECTRICAL PLANS 35 NEW SCADA CABINET ON HOUSE KEEPING PAD PER ELECTRICAL PLANS 37 RELOCATED EXISTING IRRIGATION CONTROL SYSTEM. SEE ELECTRICAL PLANS
38 NEW ATS PER ELECTRICAL PLANS
39 NEW HOLLOW METAL DOOR, SEE DOOR SCHEDULE ON SHEET A-300 43 NEW 18GA HSB-36 METAL ROOF DECK, COLOR: CLASSIC GREEN 49 OPEN CEILING
51 PROVIDE NEW HOSE BIBB WITH VACUMM BREAKER, EXTEND EXISTING
COLD WATER LINE TO NEW HOSE BIBB LOCATION
52 16"X12" CMU PILASTER PER STRUCTURAL PLANS
54 NEW DARK ANODIZED - GRAY, 30" WIDE x 36" HIGH RADIATOR LOUVER
WITH INSECT SCREEN
55 NEW HSS POST ABOVE PER STRUCTURAL PLANS
57 ELECTRICAL UNITS PER ELECTRICAL PLANS
59 3" DIESEL TANK VENT UP THROUGH ROOF. REFER TO VENTING NOTES BELOW AND DETAIL 6/A-501
60 GALVANIZED SHEET METAL RADIATOR DISCHARGE DUCT WITH FABRIC FLEX CONNECTOR REFER TO DETAIL 2/A-501
61 ENGINE EXHAUST, REFER TO DETAIL 3/A-501
1/4" = 1'-0"REFLECTED CEILING PLAN 4
1/4" = 1'-0"ROOF PLAN 2
9 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
39 3 2
434531
TOP OF CMU
7' - 6"
41 3146
B C
5757 57
A
FINISH FLOOR LEVEL
0"
TOP OF BEAM
10' - 6"
B
314143 15
A
TOP OF CMU
7' - 6"
4554
D
1"
56 56
37 61
PER GEN. SET RQT.
+/- 2' - 0"
TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
10' - 6"
V.I.F
8' - 0" 2' - 6"
01 31
32 4345
EXISTING
1 3' - 4 1/2"
NEW
6' - 7 3/4"
35'
30'
58 61
TOP OF (E) CMU
8' - 0"
A
FINISH FLOOR LEVEL
0"
TOP OF BEAM
10' - 6"
B
0115 4345
35'
28'
31 FINISH FLOOR LEVEL.
0"
TOP OF (E) CMU
8' - 0"
A
TOP OF BEAM
10' - 6"
B
32 39
4341 45
TOP OF CMU
7' - 6"
46 31
01 TOP OF (E) CMU
8' - 0"
1 FINISH FLOOR LEVEL
0"
4 TOP OF BEAM
10' - 6"
SLOPE (TYP)
01 01 3532
3 2
2%
4345 31
TYP. TYP.
31 TOP OF CMU
7' - 6"
A-501
1 TYP
LEGEND
X LOUVER TAG, SEE SHEET A-300 FOR MORE INFORMATION
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set PROPOSED ELEVATIONS AND SECTIONS
A-2011/4" = 1'-0"SOUTH ELEVATION 2
1/4" = 1'-0"WEST ELEVATION 3
1/4" = 1'-0"NORTH ELEVATION 4
1/4" = 1'-0"EAST ELEVATION 5
1/4" = 1'-0"SECTION - B 6
1/4" = 1'-0"SECTION A 7
KEYNOTES
V
ALUE DESCRIPTIONS
01 EXISTING 8" THICK CMU RETAINING WALL TO REMAIN, PATCH & REPAIR AS REQUIRED. APPLY SMOOTH PLASTER FINISH; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL & ELASTOMERIC SEALANT ON THE
EXTERIOR SIDE
15 EXISTING RAILING TO REMAIN.
31 NEW 8" THK CMU WALL PER STRUCTURAL PLANS. APPLY SMOOTH PLASTER; COLOR: ICY WHITE DEHW 10 MATTE OR EQUAL &
ELASTOMERIC SEALANT ON THE EXTERIOR SIDE
32 NEW DIESEL EMERGENCY GENERATOR & FUEL TANK ON A CONCRETE SLAB PER STRUCTURAL PLANS. CITY TO SUPPLY GENERATOR (20KW REHLKO/KOHLER, 20REOZK, OPEN UNIT SKID, 53 GALLON
TANK)CONTRACTOR TO INSTALL. SEE ELECTRICAL & STRUCTURAL PLANS
35 NEW SCADA CABINET ON HOUSE KEEPING PAD PER ELECTRICAL PLANS
37 RELOCATED EXISTING IRRIGATION CONTROL SYSTEM. SEE
ELECTRICAL PLANS
39 NEW HOLLOW METAL DOOR, SEE DOOR SCHEDULE ON SHEET A-300 41 NEW DARK ANODIZED - GRAY ALUMINUM LOUVERS BY GREENHECK, MODEL #AFJ-120 OR APPROVED EQUAL WITH INSECTS SCREEN
43 NEW 18GA HSB-36 METAL ROOF DECK, COLOR: CLASSIC GREEN 45 NEW HSS BEAM TO BE PAINTED. COLOR; BLACK. SEE STRUCTURAL PLANS
46 NEW HSS POST TO BE PAINTED. COLOR; BLACK. SEE STRUCTURAL PLANS
54 NEW DARK ANODIZED - GRAY, 30" WIDE x 36" HIGH RADIATOR LOUVER
WITH INSECT SCREEN
56 NEW 5" WIDE X 3"HIGH WEEP HOLES WITH RODENT SCREEN
57 ELECTRICAL UNITS PER ELECTRICAL PLANS
58 TOP UP WITH GROUT FROM THE LAST CMU MODULE TO THE BOTTOM
OF STRUCTURAL BEAM
61 ENGINE EXHAUST, REFER TO DETAIL 3/A-501
10 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
TYPE A
PER SCHEDULE
1 A-300
4 A-300
7 A-300
PER SCHEDULE
1. ALL (E) DOORS REQUIRING HARDWARE UPDATE/MODIFICATION: REPLACE DOOR AS
REQUIRED TO MATCH (E) WITH NEWLY PREPARED DOORS AS SCHEDULED FOR NEW WORK. G.C. TO BE RESPONSIBLE TO MAINTAIN (E) UL-RATING OF DOOR AND FRAME ASSEMBLY AT RATED LOCATIONS.
2. SEE DETAIL ( ) FOR TYPICAL DOOR CLEARANCES. ALL HARDWARE SHALL BE UNLOCKED IN THE DIRECTION OF EGRESS, REGARDLESS OF OTHER LOCK FUNCTIONS.
3. ALL 20 MIN. UL RATED DOORS AND FRAME ASSEMBLIES TO HAVE S-LABEL.
4. ALL RATED DOOR ASSEMBLIES SHALL BE U.L. AND NFPA APPROVED.
5. ALL DOORS AND FRAMES TO BE INSTALLED PLUMB, STRAIGHT AND TRUE. MAINTAIN
ADEQUATE TOLERANCES AND CLEARANCES SO THAT ALL DOORS FIT AS SPECIFIED AND SWING/SLIDE PROPERLY. ANY DEVIATION FROM THIS WILL BE REJECTED BY
OWNER AS UNACCEPTABLE AND WILL BE REPLACED AT SUPPLIER'S AND INSTALLER'S SOLE COST.
6. PROVIDE ALL PARTS NECESSARY FOR PROPER OPERATION OF ALL DOORS.
7. MAXIMUM DOOR OPENING EFFORT OF 5 LBS. AT INTERIOR DOORS AND EXTERIOR DOORS, 15 LBS. AT FIRE RATED DOORS.
8. ALL DOORS IN THE REQUIRED PATH OF EGRESS EQUIPPED WITH ELECTRONIC
LOCKING DEVICES SHALL HAVE THESE DEVICES RELEASE IN THE EVENT OF A FIRE
ALARM ACTIVATION
9. ALL DOORS ARE EQUIPPED WITH SINGLE-EFFORT, NON-GRASP HARDWARE (I.E., LEVER OR LOOP) CENTERED BETWEEN 34" AND 44" ABOVE THE FLOOR.
10. ALL DOORS MUST BE OPERABLE FROM THE INSIDE WITHOUT THE USE OF KEY, SPECIAL KNOWLEDGE OR EFFORT.
11. ALL GLAZING AND SIDELITES TO BE CLEAR TEMPERED GLASS, U.O.N.
12. ALL KEYED LOCKETS TO BE SUPPLIED WITH BUILDING STANDARD CYLINDER.
13. SUBMIT SHOP DRAWINGS FOR ALL DOORS, FRAMES, AND HARDWARE PRIOR TO FABRICATION.
14. FIRE RATED DOORS AND FRAMES TO HAVE APPROVED FIRE RETARDANT BACKING.
CONTRACTOR TO PROVIDE CERTIFICATION OF FIRE RETARDANT TREATMENT TO THE FIRE MARSHAL.
15. DOOR HEIGHTS GIVEN IN THE DOOR SCHEDULE DO NOT INCLUDE THE DOOR FRAME.
16. DO NOT UNDERCUT UL RATED DOORS, PROVIDE MINIMUM CLEARANCE ABOVE THRESHOLD OR ABOVE FINISHED FLOOR.
17. SEE AN-SERIES SHEETS FOR ADDITIONAL NOTES AND ABBREVIATIONS.
18. CONTRACTOR TO PREP ALL DOORS AND FRAMES TO RECEIVE ELECTRIFIED
HARDWARE AS REQUIRED FOR CARD READERS, INCLUDING CABLING, PROVIDING A
RACEWAY FROM ELECTRIFIED HINGE TO POWER TRANSFER AND PROVIDING ALL HARDWARE INCLUDING ELECTRIFIED HINGES. ALL CARD READER DEVICES ARE FAIL- SAFE UNLESS OTHERWISE NOTED. ALL DOORS SCHEDULED TO RECEIVE CARD READERS PROVIDE FREE EGRESS AT ALL TIMES. CARD KEY ACCESS IS NEVER REQUIRED TO EXIT/EGRESS OUT OF ANY AREA OF THE BUILDING.
19. AT PAINTED WOOD DOORS, PAINT DOOR AND FRAME TO MATCH ADJACENT WALL FINISH, U.O.N.
20. PROVIDE THREE JAMB ANCHORS MINIMUM AT APPROXIMATE HINGE POINTS FOR DOORS UP TO 7'-6" H MAX. AND ONE BASE ANCHOR WITH TWO POWER ACTUATED FASTENERS PER JAMB.
21. PROVIDE FRAME ROUGH OPENING DIMENSIONS AS RECOMMENDED BY FRAME MANUFACTURER.
22. PROVIDE STANDARD FRAME PROFILE THROAT DIMENSIONS COMPATIBLE WITH AND AS DETERMINED BY SCHEDULED PARTITION TYPES.
23. PROVIDE STRAPS, ANCHORS AND FRAMING ACCESSORIES AS REQUIRED FOR AS-BUILT
FIELD CONDITIONS AS RECOMMENDED BY THE MANUFACTURER AND INDUSTRY STANDARDS.
24. DOOR FRAMES SHALL BE SECURED IN PLACE WITH TWO FULL HEIGHT STUDS PER JAMB MIN.
25. DOOR UNDERCUTS SHALL BE KEPT TO A MINIMAL DIMENSION BASED ON FLOOR FINISH MATERIAL, AND SHALL BE UNIFORM THROUGHOUT PROJECT, U.O.N.
26. THROUGH-BOLTING WILL NOT BE ACCEPTED. REINFORCE DOORS INTERNALLY.
27. ALL DOORS SHALL COMPLY WITH THE DOOR LANDING CLEARANCES FOR APPROACHES MEETING MINIMUM ADA REQUIREMENTS.
28. SEQUENCE OF OPERATIONS FOR CARD READERS AT EXIT DOORS:
1. NORMAL BUSINESS HOURS: - DOORS OPEN WITH CARD READER, FREE EGRESS
2. AFTER HOURS: - DOORS OPEN WITH CARD READER, FREE EGRESS
3. FIRE ALARM: - FREE EGRESS
DOOR & HARDWARE NOTES
/- ---
EXT.
INT.
ANCHOR AS REQUIRED PER
MANUFACTURER'S
REQUIREMENTS
BACKER ROD AND SEALANT
CMU WALL PER STRUCTURAL
PLANS
DOOR PER DOOR SCHEDULE
J-MOLD TRIM
16 GA. HOLLOW METAL FRAME
SMOOTH PLASTER &
ELASTOMERIC SEALANT
2' - 0"
V.I.F
10' - 11"
TYPE A TYPE B
TYPE C
2' - 0"
V.I.F
3' - 7"
V.I.F
2' - 1"
V.I.F
2' - 2"
V.I.F
15' - 0"
EQ. EQ.
V.I.F
2' - 6"
4 A-501
4 A-501
4 A-501
4 A-501
4 A-501
4 A-501
TYPE D
2' - 6"
3' - 0"
7 A-501
7 A-501
EXTERIORINTERIOR
THRESHOLD SET IN FULL BED
OF SEALANT
DOOR PER DOOR SCHEDULE
LINE OF JAMB
CONCRETE FLOOR SLAB PER
STRUCTURAL
1/2" THK. CONT. BITUMINOUS FILLER
W/SEALANT & BACKER ROD AT
PERIMETER OF FLOOR SLAB
2% MAX. SLOPE AWAY
FROM BLDG.
.
TYP. AT ALL
DOOR THRESHOLDS
1/2" MAX.
1/4"1
2 ..
MAX.
1/2" MAX.
LEVEL 1
0' - 0"
EXT.
INT.
CMU WALL PER STRUCTURAL PLANS
BACKER ROD AND SEALANT
ANCHOR AS REQUIRED PER
MANUFACTURER'S REQUIREMENTS
26 GA.G.I. DRIP TO MATCH
FRAME
16 GA. HOLLOW METAL FRAME
DOOR PER DOOR SCHEDULE
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
J MOLD TRIM
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set DETAILS - DOORS & LOUVERS
A-300
1/2" = 1'-0"DOOR TYPE
DOOR SCHEDULE
NUMBER TYPE ROOM WIDTH HEIGHT THICKNESS FIRE RATING DOOR MATERIAL DOOR FINISH FRAME MATERIAL FRAME FINISH REMARKS D1 A 9' - 4" 6' - 8" 1 3/4" HOLLOW METAL PAINT - GRAY HOLLOW METAL PAINT BLACK HARDWARE PER THE CITY STANDARDS 3" = 1'-0"HM DOOR @ CMU - JAMB 1
1/2" = 1'-0"LOUVER TYPES
3" = 1'-0"HM DOOR THRESHOLD 7 3" = 1'-0"HM DOOR @ CMU - HEAD 4 11 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
EXTERIOR INTERIOR
HEAD DETAIL
SILL DETAIL
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
HSS BEAM PER
STRUCTURAL
PLANS
NEW METAL ROOF
DECK
JAMB DETAIL
NEW DARK ANODIZED - GRAY ALUMINUM
LOUVERS WITH INSECT SCREEN
INSTALL PER MAUFACTURER
RECOMMENDATIONS
SLOPE
HSS COLUMN & STEEL
PLATE PER
STRUCTURAL PLANS
NEW DARK ANODIZED - GRAY
A
LUMINUM LOUVERS WITH
INSECTS SCREEN.
FREE AREA > 45%.
INSTALL PER MAUFACTURER
RECOMMENDATIONS
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
CMU WALL PER
STRUCTURAL PLANS
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
EZ CLIP OR CAULKING
PER MANUFACTURER
RECOMMENDATION
J-MOLDING
2" MIN. @ PAVING
4" MIN.
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
(E) LANDSCAPE TO
REMAIN
CMU WALL PER
STRUCTURAL
PLANS
GALVANIZED
METAL SCREED
EXTERIOR INTERIOR
SILL DETAIL
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
NEW DARK ANODIZED - GRAY ALUMINUM
LOUVERS WITH INSECT SCREEN
INSTALL PER MAUFACTURER
RECOMMENDATIONS
SLOPE
EZ CLIP PER
MANUFACTURER
RECOMMENDATION
EZ CLIP OR CAULKING
PER MANUFACTURER
RECOMMENDATION
SMOOTH PLASTER &
ELASTOMERIC
SEALANT
CMU WALL PER
STRUCTURAL
PLANS
J-MOLDING
J-MOLDING
HEAD/JAMB DETAIL
NOTE:
THE ENGINE EXHAUST WILL COMPLY WITH NFPA 37 SECTION 8.2.3.1.
SECTION 8.2.3.1
PER NFPA 37
C
BA A. INSTALL A FABRIC FLEX CONNECTION
BETWEEN RADIATOR DISCHARGE FLANGE
AND SHEET METAL DUCT TO ISOLATE
VIBRATION.
B. USE A GRADUAL TRANSITION TO THE
LOUVER OPENING.
C. MOUNT AFJ-120 LOUVER WITH INSECT
SCREEN (REMOVEABLE).PRESSURE LOSS CALCULATION:
MAX. RESTRICTION OF COOLING AIR, INTAKE AND DISCHARGE : O.5 IN.WG.
RADIATOR-COOLED COOLING AIR (CFM): 1300 SCFM
FREE AREA OF AFJ-120 30"X36" : 1.36 SQFT
LOUVER FREE-AREA VELOCITY: V=1300/1.36 , V=956 FPM
BASED ON AIRFLOW RESISTANCE GRAPH FOR GREENHECK AFJ-120 LOUVER: STATIC PRESSURE DROP FOR LOUVER IS 0.085 IN.WG.
AVERAGE AIRFLOW RESISTANCE PERCENTAGE INCREASE FOR INSECT SCREEN : 17% THE TOTAL PRESSURE LOSS FOR LOUVER PLUS INSECT SCREEN : 0.1 IN.WG.
THIS IS BELOW THE GENERATOR ALLOWABLE EXTERNAL STATIC RESTRICTION OF 0.5 IN.WG.,LEAVING APPROXIMATELY 0.4 IN.WG. AVAILABLE FOR DUCT STRAIGHT RUN AND TRANSITIONS.
B. PENETRATION @ RIB ( FLASHING)
A. ROOF JACK
NOTE:
• CONTRACTOR TO VERIFY IN THE FIELD THE EXACT LOCATION OF THE VENT ON THE ROOF • DIESEL TANK VENT SHALL COMPLY WITH NFPA 30
• SEE DIESEL TANK VENTING NOTES ON SHEET A-101
PER NFPA 30 REQUIREMENTS
TERMINATE THE VENT OUTLETS WITH AN OPW
623V PRESSURE VACUUM VENT
TE
HED ARC I
T
IA
R
A L I FOF C
O
N
CCEN
L
ST
E
AT
I
S E
J
OJ
NHO
S
REBLISHP
No. C 15573
REN. 7-31-27
PROJECT NO.
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED: KERI MARTINEZ
PRINCIPAL ENGINEER
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
DATE
DRAWING No.
SHEET
EF
AB
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
02212024
04092024
30% Client Review
06122024
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL CIP 5554
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
IDS GROUP
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
548-3
60% Resubmittal
JS
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
03252026 Plan Check ResubmittalB
RCE 57189 EXPIRES 12/31/27
05112026 Bid Set DETAIL
A-5013" = 1'-0"LOUVER - HEAD/JAMB & SILL DETAIL 4 3" = 1'-0"WALL BASE 13" = 1'-0"LOUVER - HEAD/JAMB & SILL DETAIL 7 12 12" = 1'-0"ENGINE EXHAUST DETAIL 3
1/4" = 1'-0"RADIATOR DISCHARGE DETAIL 2
12" = 1'-0"VENT THROUGH ROOF DETAILS 6
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
1. THE CONTRACTOR SHALL SUBMIT ALL STRUCTURAL STEEL AND MISCELLANEOUS STEEL SHOP DRAWINGS TO THE ENGINEER FOR REVIEW PRIOR TO FABRICATION.
2. MATERIAL TEST OR REPORTS FOR HOT-ROLLED STRUCTURAL SHAPES, PLATES, AND BARS SHALL BE MADE IN ACCORDANCE WITH ASTM A6. FOR SHEET MATERIAL, TEST SHALL BE MADE IN ACCORDANCE WITH ASTM A568. FOR TUBING AND PIPE, SUCH TEST SHALL BE MADE IN ACCORDANCE WITH REQUIREMENTS OF THE APPLICABLE ASTM STANDARDS.
3. STEEL MATERIALS SHALL CONFORM TO THE FOLLOWING, UNLESS OTHERWISE NOTED:
A. ANGLES, PLATES AND BARS: ASTM A36 (Fy=36ksi, Fu=58ksi) B. RECTANGULAR AND SQUARE HSS: ASTM A500, GRADE C (Fy=50ksi, Fu=65ksi) C. PIPES: ASTM A53, GRADE B (Fy=35ksi, Fu=60ksi)
D. BOLTS AT STEEL-TO-STEEL CONNECTIONS: ASTM A325 ST (SNUG-TIGHTENED), TYPE 1 7/8" ∅ TYP. U.O.N.
E. BOLTS AT OTHER APPLICATIONS: ASTM A307
F. NUTS: ASTM A563
G. WASHERS: ASTM F436
H. TWIST-OFF-TYPE TENSION-CONTROL BOLT ASSEMBLIES: ASTM F1852 I. COMPRESSIBLE-WASHER-TYPE DIRECT-TENSION INDICATORS: ASTM F959
4. HEAVY-HEX STRUCTURAL BOLT AND NUT DIMENSIONS SHALL MEET REQUIREMENTS OF ANSI/ASME B18.2.6. ALL BOLTS SHALL HAVE A 3 THREAD ENGAGEMENT MINIMUM.
5. DIAMETER OF BOLT HOLE SHALL BE 1/16" LARGER THAN THE BOLT'S DIAMETER UNLESS OTHERWISE NOTED.
6. IF DRILLING HOLES AT STEEL MEMBERS TO ACCOMMODATE THE CONCRETE ANCHORS IS REQUIRED, THE DRILLING MUST BE DONE AFTER THE ANCHORS HAVE BEEN INSTALLED. THE HOLES AT STEEL MEMBERS SHALL MATCH THE LOCATION OF INSTALLED ANCHORS.
7. PROVIDE BEVELED WASHERS ON SLOPING SURFACE OF CONNECTIONS FOR FULL BEARING.
8. MINIMUM BOLT SPACING FROM CENTER OF STANDARD AISC HOLE AS FOLLOWS, U.N.O.:
CENTER-TO-CENTER = 3 BOLT DIAMETER
CENTER-TO-EDGE = VARIES PER AISC 360-16 TABLE J3.4
9. THE NATURAL CAMBER IN BEAMS SHALL BE ORIENTED UP, UNLESS NOTED OTHERWISE. AT CANTILEVERS, THE NATURAL CAMBER SHALL BE ORIENTED SO THAT THE FREE END IS ABOVE THE CONNECTED END. THE TOP OF ALL MEMBERS SHALL BE CLEARLY IDENTIFIED. ALL BEAM CAMBERS SHOWN ON THE PLANS SHALL INCLUDE NATURAL CAMBER.
10. GALVANIZE ALL STEEL EXPOSED TO WEATHER, UNLESS OTHERWISE NOTED. REPAIR GALVANIZING AT FIELD WELDS WITH CARBOLINE CARBOMASTIC 15 REPAIR PAINT (10 MILS), TYPICAL.
11. UNDER NO CIRCUMSTANCES SHALL DRAWINGS BE SCALED OR REFERENCE ELECTRONIC BUILDING INFORMATION BE USED TO DETERMINE ELEVATIONS OR DIMENSIONS.
12. THE CONTRACTOR SHALL ESTABLISH A MASTER SET OF TOP-OF-STEEL DRAWINGS FOR ALL AREAS OF THE BUILDING OR STRUCTURE FOR APPROVAL BY THE ARCHITECT BEFORE BEGINNING FABRICATION OF STRUCTURAL STEEL. THE
CONTRACTOR'S MASTER SET OF TOP-OF-STEEL DRAWINGS SHALL BE SUBMITTED AT THE BEGINNING OF THE SHOP DRAWING SUBMITTAL PROCESS. THIS SET OF DRAWINGS SHALL SHOW ALL TOP-OF-STEEL ELEVATIONS, ALL EDGE OF
STEEL INFORMATION FOR FLOOR AND ROOF LEVELS, AND ALL STEEL FRAMING DIMENSIONS AT FLOOR AND WALL OPENINGS.
1. ALL WELDING SHALL BE IN CONFORMANCE WITH THE AWS D1.1 AND AWS D1.8.
2. ALL WELDING MUST BE APPROVED BY AN AWS CERTIFIED INSPECTOR.
3. ALL WELDING OF STEEL SHALL CONFORM TO AWS D1.1 AND AWS D1.8 AND SHALL BE PERFORMED BY AWS CERTIFIED WELDERS USING E-70XX LOW HYDROGEN MOISTURE RESISTING ELECTRODES UNLESS OTHERWISE NOTED.
4. ALL WELDS USED IN MEMBERS AND CONNECTIONS IN THE SEISMIC LOAD RESISTING SYSTEM (SLRS) SHALL BE MADE WITH FILLER METALS MEETING THE REQUIREMENTS SPECIFIED IN AWS D1.8 CLAUSE 6.3. ALL WELDING ELECTRODES AND ELECTRODE-FLUX COMBINATIONS SHALL MEET DIFFUSIBLE HYDROGEN TESTING REQUIREMENTS OF TABLE 6.3 OF AWS D1.8. WELDS DESIGNATED AS DEMAND 'CRITICAL WELDS' SHALL BE MADE WITH FILLER METALS MEETING THE REQUIREMENTS SPECIFIED IN AWS D1.8 CLAUSES 6.3.5, 6.3.6, 6.3.7 AND 6.3.8.
5. ALL WELDS USED IN MEMBERS AND CONNECTIONS IN THE SLRS SHALL BE MADE WITH A FILLER METAL THAT CAN PRODUCE WELDS THAT HAVE A MINIMUM CHARPY V-NOTCH TOUGNESS OF 20 FT-LB AT 0 °F, AS DETERMINED BY THE APPROPRIATE AWS A5 CLASSIFICATION OR MANUFACTURER CERTIFICATION.
6. USE THE MINIMUM SIZE OF WELDING IN ACCORDANCE WITH AISC 360-16 SECTION J2 AT STEEL-TO-STEEL JOINTS UNLESS A LARGER WELDING SIZE IS SPECIFIED ON THE PLANS.
7. WHERE LENGTH OF WELDING IS NOT SHOWN, IT SHALL BE FULL LENGTH OF JOINT. ALL BUTT WELDS SHALL BE COMPLETE PENETRATION WELDS UNLESS OTHERWISE NOTED.
8. THE CONTRACTOR SHALL PROVIDE WELDING PROCEDURE SPECIFICATION (WPS) AND DETAILED SEQUENCE OF WELDING SKETCH FOR REVIEW PRIOR TO STARTING FABRICATION. THE SEQUENCE OF WELDING SHALL BE PLANNED TO MINIMIZE LOCKED IN STRESSES AND DISTORTION. EACH WPS SHALL BE STAMPED WITH AN AWS INSPECTOR'S STAMP INDICATING THAT INSPECTOR'S CERTIFICATION THAT THE WPS CONFORMS TO AWS D1.1 AND D1.8, AND ALL REQUIREMENTS SET FORTH IN THE DRAWINGS AND SPECIFICATIONS. EACH WPS SHALL BE FORMATTED TO FIT ON LETTER SIZED PAPER BUT
SHALL BE SUBMITTED ON THE UPPER PORTION OF LEGAL SIZED PAPER ALLOWING FOR AWS INSPECTOR, CONTRACTOR REVIEW, AND DESIGNER REVIEW STAMPS TO BE PLACED ON THE BLANK BOTTOM PORTION OF EACH LEGAL SIZED SHEET.
9. COMPLETE PENETRATION GROOVE WELDS SHALL HAVE A FILLER METAL WITH CHARPY V-NOTCH TOUGHNESS OF 20 FT-LBS AVERAGE AT -20 DEGREES FAHRENHEIT. FOR DEMAND CRITICAL WELDS OF THE SEISMIC LOAD RESISTING SYSTEM SUBJECTED TO SERVICE TEMPERATURES BELOW +50 °F, THE MINIMUM CHARPY V-NOTCH OF 40 FT-LBS SHALL BE PROVIDED AT A SERVICE TEMPERATURE NOT MORE THAN 20 °F ABOVE THE LOWEST ANTICIPATED SERVICE TEMPERATURE.
10. FACES OF FILLET WELDS NOT EXPOSED TO VIEW SHALL HAVE AS-WELDED SURFACES THAT ARE REASONABLY SMOOTH AND UNIFORM. NO FINISHING OR GRINDING SHALL BE REQUIRED EXCEPT WHERE CLEARANCES OR FIT OF OTHER ITEMS MAY SO NECESSITATE.
11. ALL COMPLETE AND PARTIAL PENETRATION WELDS WHICH ARE EXPOSED TO VIEW SHALL BE GROUND SMOOTH AND FLUSH WITH FINISH SURFACE OF STEEL. HOLES SHALL BE FILLED WITH WELD METAL AND SMOOTHED BY GRINDING OR FILING.
12. FINISH GROOVE PREPARATION THERMAL CUTS BY GRINDING.
13. WELDS SHALL BE TERMINATED AT THE END OF A JOINT IN A MANNER THAT WILL ENSURE SOUND WELDS. THIS SHALL BE DONE BY USE OF EXTENSION BARS AND RUN OFF TABS IF NECESSARY.
14. TO ASSURE THE PROPER AMPERAGE AND VOLTAGE OF THE WELDING PROCESS, A HAND HELD CALIBRATED AMP AND VOLT METER SHALL BE USED. AMPERAGE AND VOLTAGE SHALL BE MEASURED AT THE ARC WITH THIS EQUIPMENT. TRAVEL
SPEED AND ELECTRODE STICK OUT SHALL BE VERIFIED TO BE IN COMPLIANCE WITH THE ELECTRODE MANUFACTURER'S RECOMMENDATIONS AND WITH THE APPROVED WELDING PROCEDURE SPECIFICATION.
1. ANCHORAGE SHALL BE INSTALLED PER MANUFACTURER'S WRITTEN INSTRUCTIONS, AND SHALL COMPLY WITH ACI 318 CHAPTER 17 AND CBC.
2. ADHESIVE ANCHOR INSTALLERS SHALL BE CERTIFIED IN ACCORDANCE WITH THE ACI-CRSI ADHESIVE ANCHOR INSTALLER CERTIFICATION PROGRAM.
3. THE CONTRACTOR SHALL PREPARE A WRITTEN PROCEDURE PRIOR TO CONSTRUCTION FOR AN INSTALLATION METHOD TO AVOID DRILLING INTO OR CONTACTING IN ANY WAY REINFORCING STEEL AND OTHER EMBEDDED ITEMS. APPROVED METHODS COULD INCLUDE
PLASTIC MARKINGS FORMED INTO THE CONCRETE SURFACE, OR USE OF GROUND PENETRATING RADAR EQUIPMENT SUCH AS HILTI FERROSCAN PS300. ANCHORS SHALL CLEAR EXISTING REBAR BY 1" MIN.
4. CONFORM WITH ICC RECOMMENDED VALUES FOR ANCHOR SPACING AND EDGE DISTANCE TO DEVELOP FULL (100%) ALLOWABLE TENSION/SHEAR LOADS LISTED IN ICC REPORTS. DO NOT USE REDUCED SPACING AND EDGE DISTANCE UNLESS SPECIFICALLY NOTED OTHERWISE BY THE DETAILS.
5. ANCHORS SHALL BE INSTALLED ACCORDING TO THE ANCHORING SYSTEM'S SPECIFICATIONS. DO NOT DAMAGE REINFORCING STEEL OR OTHER EMBEDDED ITEMS. FILL UNUSED HOLES WITH NON-SHRINK GROUT.
6. DRILLED HOLE SHALL BE CLEANED WITH A BRUSH AND CLEAN COMPRESSED AIR IN COMPLIANCE WITH ICC ESR REQUIREMENTS.
7. CONTRACTOR SHALL DETERMINE LOCATION OF EXISTING REINFORCING STEEL PRIOR TO DRILLING FOR ANCHORS, AND DRILL THE ANCHOR HOLES TO CLEAR THE REINFORCING STEEL PER THESE NOTES. NO REINFORCING STEEL SHALL BE NICKED, CUT OR DAMAGED IN ANY WAY. DAMAGED REINFORCING WILL BE REPLACED BY THE CONTRACTOR AT NO ADDITIONAL COST. IF THE LOCATION OF
ANCHORS MUST BE MOVED SLIGHTLY TO ACCOMMODATE THE LOCATION OF EXISTING REINFORCING STEEL, THE CONTRACTOR SHALL
PREPARED A SLIGHTLY MODIFIED DESIGN OF THE ITEM TO BE ANCHORED AND SUBMIT TO THE ENGINEER FOR APPROVAL PRIOR TO FABRICATION. THE MODIFIED DESIGN SUGGESTED BY THE CONTRACTOR SHALL INVOLVE THE ABSOLUTE MINIMUM RELOCATION OF
ANCHORS TO MEET THE DETAILS AND REQUIREMENTS HEREIN, AND SHALL BE BASED ON A TEMPLATE BY THE CONTRACTOR WHICH ACCURATELY PORTRAYS THE POSITION OF THE ANCHORS.
8. WHILE ANCHORING STEEL MEMBERS AGAINST CONCRETE, PROVIDE LOCK-WASHER AND NUT AT EACH ANCHOR ROD.
ACCEPTABLE PRODUCTS
HILTI - KWIK BOLT TZ2
SIMPSON - STRONG-BOLT 2
AN EQUIVALENT PRODUCT ACCEPTABLE TO ENGINEER
ICC-ES EVALUATION REPORT
ESR-4266
ESR-3037
BOLT DIAMETER DEPTH (U.N.O.)
3/8" 2 1/2"
1/2"
HILTI KWIK BOLT TZ2
3 3/8"
BOLT DIAMETER EFFECTIVE MIN.
DEPTH (U.N.O.)
3/8" 2" 30
1/2" 50 3 1/4"
INSTALLATION TORQUE (FT-LB)
INSTALLATION TORQUE (FT-LB)
SIMPSON STRONG-TIE STRONG-BOLT 2
* ANCHORS MUST ATTAIN SPECIFIED TORQUE WITHIN 1/2 TURN OF THE NUT. INSTALLATION TORQUE APPLIES TO CARBON STEEL ANCHORS. REFER TO ICC REPORT FOR INSTALLATION TORQUE REQUIRED FOR STAINLESS STEEL ANCHORS.
ANCHORS MUST ATTAIN SPECIFIED TORQUE WITHIN 1/2 TURN OF THE NUT. INSTALLATION T
ORQUE APPLIES TO CARBON STEEL ANCHORS. REFER TO ICC REPORT FOR INSTALLATION TORQUE REQUIRED FOR STAINLESS STEEL ANCHORS.
*
5/8"
3/4"
4 1/2"
5"
5/8"
3/4"
4"
4 3/4"
40 110
CARBON STEEL STAINLESS STEEL
30 40
60 125
30 60
90 150
CARBON STEEL STAINLESS STEEL
30 65
80 150
ADHESIVE ANCHOR SYSTEM FOR THREADED ROD OR REBAR IN CONCRETE HILTI HIT - RE 500 V3
SIMPSON - SET-XP
ACCEPTABLE PRODUCTS
ESR-3814
ESR-2508
ICC-ES EVALUATION REPORT
9. CONCRETE SCREW ANCHORS MAY BE HILTI KH-EZ (ICC ESR-3027), SIMPSON TITEN HD SCREW ANCHORS (ICC ESR-2713), RED HEAD TAPCON+ SCREW ANCHOR (ICC ESR-3699), OR AN EQUIVALENT PRODUCT ACCEPTABLE TO ENGINEER. AT ENDS OF LATERAL SEISMIC BRACING, USE EXPANSION BOLTS IN LIEU OF SCREW ANCHORS.
10. TEST POST-INSTALLED ANCHORS IN CONCRETE PER CBC. TENSION-TEST BOLTS TO TWICE THE ALLOWABLE TENSION VALUE LISTED IN THE APPLICABLE ICC REPORT FOR BOLTS OF THE SAME DIAMETER. TEST 100-PERCENT OF BOLTS USED FOR STRUCTURAL APPLICATIONS. TEST 50-PERCENT OF BOLTS USED FOR NON-STRUCTURAL APPLICATIONS SUCH AS EQUIPMENT ANCHORAGE, INCLUDING HALF OF THE BOLTS IN EACH GROUP. TEST 10-PERCENT OF BOLTS USED FOR SILL-PLATE BOLTING APPLICATIONS.
11. ALL BOLTS AND ANCHORS (INCLUDING NUTS AND WASHERS) EXPOSED TO WEATHER SHALL BE STAINLESS STEEL.
MINIMUM EMBEDMENT
DEPTH (U.N.O.)
5/8" DIA #5
THREAD ROD
DIAMETER
1/2" DIA #4
9,300 LB6"
4 1/2"
5,600 LB
TESTING FORCEREBAR SIZE
3 1/2"
7"
8"
9"
#3
#6
#7
#8
3/8" DIA
3/4" DIA
7/8" DIA
1" DIA
3,400 LB
13,450 LB
16,800 LB
22,600 LB
12. THE EMBEDMENT DEPTH OF POST-INSTALLED ANCHORS SPECIFIED IN THE
INDIVIDUAL DRAWING DETAILS SHALL GOVERN OVER THE MINIMUM EMBEDMENTS SHOWN IN THE TABLES ABOVE. WHERE THE INDIVIDUAL
DRAWING DETAIL SPECIFIES A CERTAIN PRODUCT AND THE CONTRACTOR
WISHES TO USE AN ACCEPTABLE ALTERNATIVE PRODUCT, THE EMBEDMENT
DEPTH FOR THAT ALTERNATIVE PRODUCT SHALL BE INCREASED AS
REQUIRED BEYOND THE EMBEDMENT DEPTH SHOWN FOR THE SPECIFIED
PRODUCT IN ORDER TO ACHIEVE THE SAME CAPACITIES IN SHEAR AND
TENSION AS PUBLISHED IN THE ICC-ESR REPORT FOR THE PRODUCT AND EMBEDMENT DEPTH SPECIFIED IN THE DETAIL. IF THE EMBEDMENT DEPTH
OF THE ALTERNATIVE PRODUCT MUST BE INCREASED TO MATCH THE
CAPACITIES OF THE PRODUCT SPECIFIED IN THE DETAIL, THE LIMITATION ON
CONCRETE THICKNESS SPECIFIED IN THE ICC-ESR REPORT FOR THE ALTERNATIVE PRODUCT MAY NOT BE VIOLATED. THE EMBEDMENT DEPTH
FOR THE ALTERNATIVE PRODUCT MAY NOT BE LESSENED BELOW THE VALUE SHOWN IN THE DETAIL.
AN EQUIVALENT PRODUCT ACCEPTABLE TO ENGINEER
HILTI HIT-HY 270 ESR-4143
DESIGN CONFORMS TO THE 2022 CALIFORNIA BUILDING CODE .
1. DEAD LOADS:
ROOF 10 PSF
2. LIVE LOADS:
ROOF 20 PSF (REDUCIBLE)
3. WIND ANALYSIS: WIND LOADS ARE BASED ON CBC WITH THE FOLLOWING FACTORS:
· EXPOSURE CATEGORY = C
· V = 102 MPH
· V ASD = 82.88 MPH
·
G = 0.85
· Kz = 0.90
· Kzt = 1.0
· Kd = 0.85
· Ke = 1.0
· RISK CATEGORY = III
4. SEISMIC ANALYSIS: EQUIVALENT LATERAL FORCE PROCEDURE · SITE CLASS = D (DEFAULT)
· SEISMIC DESIGN CATEGORY = D
· RISK OCCUPANCY CATEGORY = III
· I e = 1.25
·
Ss = 1.105 g
·
S1 = 0.398 g
·
Fa = 1.2
·
SDS = 0.884g
·
2. SOIL BEARING CAPACITIES AND RECOMMENDATIONS:
THESE VALUES ARE ALLOWED TO BE INCREASED BY 1/3 FOR SHORT SEISMIC AND WIND EFFECTS PROVIDED THE LOAD REDUCTION OF 0.75 IS NOT APPLIED TO WIND OR SEISMIC LOAD COMBINATIONS.
A. ALLOWABLE SOIL BEARING PRESSURES
B. ALLOWABLE LATERAL RESISTANCE:
• CONTINUOUS FOOTINGS: 1,500 PSF
• ACTIVE PRESSURE: 36PCF
• PASSIVE PRESSURE: 390PCF
• COEFFICIENT OF FRICTION: 0.3
1. GEOTECHNICAL AND GEOLOGICAL ENGINEERING INVESTIGATION REPORT:
1. COMPANY NAME: EARTH MECHANICS, INC.
2. ADDRESS: 820 LOS VALLECITOS, SUITE H,
SAN MARCOS, CA 92069.
3. PHONE: (760) - 736 - 8222
4. PROJECT #: 22-108
5. DATE: OCTOBER 13, 2023
• ENLARGE THE EXISTING GENERATOR HOUSE
• REMOVE AND REPLACE THE EXISTING GENERATOR
• REMOVE AND REPLACE PORTION OF THE EXISTING 12" S.O.G.
1. REFER TO PROJECT SPECIFICATIONS FOR PROJECT REQUIREMENTS.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE SAFETY OF WORK AREA DURING CONSTRUCTION PERIOD. THE
CONTRACTOR SHALL PROTECT ADJACENT PROPERTY AND UTILITIES IN ACCORDANCE WITH ALL NATIONAL, STATE, AND LOCAL SAFETY ORDINANCES.
3. DRAWINGS INDICATE GENERAL AND TYPICAL DETAILS OF CONSTRUCTION. WHERE CONDITIONS ARE NOT SPECIFICALLY
INDICATED BUT ARE OF SIMILAR CHARACTER TO DETAILS SHOWN, SIMILAR DETAILS OF CONSTRUCTION SHALL BE USED SUBJECT TO PRIOR REVIEW BY THE SEOR.
4. THE CONTRACTOR SHALL SUPERVISE AND DIRECT THE WORK, AND SHALL BE SOLELY RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES AND PROCEDURES. THE SUPPORTING SERVICES BY THE
SEOR, WHETHER PERFORMED PRIOR TO, DURING, OR AFTER CONSTRUCTION, ARE PERFORMED SOLELY FOR THE
PURPOSE OF ASSISTING IN QUALITY CONTROL AND IN ACHIEVING CONFORMANCE WITH CONTRACT DRAWINGS AND PROJECT SPECIFICATIONS; BUT THEY DO NOT GUARANTEE THE CONTRACTOR'S PERFORMANCE AND SHALL NOT BE CONSIDERED AS SUPERVISION OF CONSTRUCTION.
5. SHOP DRAWINGS REQUIRED BY THE PROJECT SPECIFICATIONS SHALL BE SUBMITTED TO THE SEOR FOR REVIEW PRIOR TO FABRICATION. DRAWINGS ARE REVIEWED BY THE SEOR FOR GENERAL CONFORMANCE TO THE DESIGN.
REGARDLESS OF THE SEOR'S REVIEW, THE CONTRACTOR IS FULLY AND SOLELY RESPONSIBLE FOR COMPLETE AND SATISFACTORY SUBMITTAL AND CONFORMANCE TO THE CONTRACT DOCUMENTS. SHOP DRAWINGS WILL BE REJECTED FOR INCOMPLETENESS, LACK OF CALCULATIONS (IF REQUIRED) OR CHANGES WITHOUT PRE-APPROVAL. ALL
STRUCTURAL CALCULATIONS AND DRAWINGS AS PART OF THE SHOP DRAWINGS SUBMITTAL SHALL BE SIGNED AND STAMPED BY A CALIFORNIA REGISTERED STRUCTURAL ENGINEER.
6. ANY PARTS OF WORK AREA WHICH ARE TO BE BARRICADED OR SEALED TO NON-CONSTRUCTION INDIVIDUALS MUST BE COORDINATED WITH AND APPROVED BY THE OWNER BEFORE PROCEEDING WITH THE WORK.
7. THE CONTRACTOR SHALL EXERT EVERY EFFORT TO PREVENT DUST AND CONSTRUCTION DEBRIS FROM CONTAMINATING THE WORK AREA. THESE EFFORTS SHALL INCLUDE BUT NOT BE LIMITED TO PROVIDING A DAILY CLEANUP OF THE CONSTRUCTION AREA. THE CONTRACTOR SHALL REFER TO THE PROJECT SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.
8. THE CONTRACTOR SHALL EXERT EVERY EFFORT TO MINIMIZE THE CONSTRUCTION NOISE AND DISTURBANCE DURING CONSTRUCTION.
9. THE CONTRACTOR SHALL BE RESPONSIBLE TO SECURE THE CONSTRUCTION SITE.
10. CUTTING, BORING, SAW-CUTTING OR DRILLING THROUGH NEW STRUCTURAL MEMBERS OTHER THAN THOSE DETAILED ON STRUCTURAL DRAWINGS SHALL NOT BE DONE WITHOUT THE SEOR'S APPROVAL.
11. THE CONTRACTOR SHALL:
12. ALL MATERIALS, FEATURES OR CONDITIONS NOT IDENTIFIED AS (E) WHICH MEANS "EXISTING," SHALL BE CONSIDERED AS NEW AND PART OF THE PROJECT SCOPE OF WORK.
13. THE CONTRACTOR IS FULLY AND SOLELY RESPONSIBLE FOR ALL SHORING REQUIRED IN ORDER TO SAFELY ACHIEVE THE FINAL CONSTRUCTION SHOWN ON THE DRAWINGS. THIS INCLUDES, BUT IS NOT LIMITED TO, ANY TYPES OF SHORING REQUIRED FOR SOILS EXCAVATION AND BACKFILL WORK; SUPPORT OF STRUCTURAL ELEMENTS UNTIL THEY
HAVE ACHIEVED THE NECESSARY STRENGTH TO PERFORM IN THE FINAL POSITION AND MANNER SHOWN ON THE DRAWINGS; AND SUPPORT OF STRUCTURAL ELEMENTS THAT ARE MODIFIED AND THEREBY REDUCED IN STRENGTH IN
ANY WAY DURING CONSTRUCTION AS REQUIRED TO ACHIEVE THE FINAL CONSTRUCTION AS SHOWN ON THE DRAWINGS. ALL SHORING CALCULATIONS AND DRAWINGS SHALL BE STAMPED BY A CALIFORNIA REGISTERED STRUCTURAL ENGINEER AND SUBMITTED FOR REVIEW PRIOR TO PERFORMING THE WORK.
14. WHERE NOT INDICATED OTHERWISE, THE LATEST EDITION OF ALL CITED DOCUMENTS SHALL GOVERN.
15. THE TERM CBC IN THESE DRAWINGS MEANS 2022 CALIFORNIA BUILDING CODE, CALIFORNIA CODE OF REGULATIONS, TITLE 24, ALL PARTS AND VOLUMES.
16. ALL CONSTRUCTION AND WORKMANSHIP, INCLUDING MATERIALS, SHALL CONFORM TO THESE DRAWINGS, PROJECT SPECIFICATIONS, AND THE CBC.
17. PROVIDE ALL MEASURES NECESSARY TO PROTECT THE STRUCTURE AND ADJACENT STRUCTURE, AND THEIR FINISHES AND UTILITIES, DURING CONSTRUCTION.
18. THE CONTRACTOR SHALL COORDINATE ALL UTILITY LOCATIONS WITH OTHER DRAWINGS AND SHALL CONDUCT A DETAILED SURVEY OF EXISTING UTILITIES TO IDENTIFY INTERFERENCES WITH THE NEW CONSTRUCTION. PROMPTLY NOTIFY THE ARCHITECT OF ANY INTERFERENCES PRIOR TO PERFORMING THE WORK.
19. CORING, TRENCHING & EXCAVATIONS
PRIOR TO CORING, TRENCHING, AND EXCAVATIONS, THE CONTRACTOR IS RESPONSIBLE FOR AND IS REQUIRED TO USE AN INDEPENDENT UTILITY LOCATING SERVICE TO LOCATION ALL UTILITIES WITHIN THE IMPACTED AREA(S). THE
INDEPENDENT UTILITY LOCATING SERVICE SHALL PROVIDE CERTIFICATION THAT IT HAS LOCATED ALL UTILITIES IN THE
IMPACTED AREA(S) AND THE CONTRACTOR MUST DEPICT ALL DISCOVERED UTILITIES ACCURATELY ON REDLINES/AS-
BUILT PLANS FOR SUBMISSION TO THE COUNTY FOR REVIEW AND APPROVAL PRIOR TO COMMENCEMENT OF CORING, TRENCHING, OR EXCAVATIONS. IN ADDITION, FOR UTILITIES REQUIRING EXTERNAL AGENCY NOTIFICATION,
COORDINATION, AND APPROVALS, THE CONTRACTOR MUST PROVIDE PROOF OF NOTIFICATION, COORDINATION, AND REVIEWS BY EXTERNAL AGENCIES.
20. ALL SPECIAL/DEPUTY INSPECTION REPORTS AND TESTS SHALL INCLUDE: JOB NAME AND JOB NUMBER, SITE LOCATION, PLAN PAGE AND DETAILS, ANY RFI , AND CODE REFERENCES.
A. CHECK ALL DIMENSIONS.
B. BE RESPONSIBLE FOR COORDINATING THE WORK OF ALL TRADES.ALL DISCREPANCIES
SHALL BE CALLED TO THE ATTENTION OF THE SEOR AND SHALL BE RESOLVED BEFORE
PROCEEDING WITH THE WORK
1. PERMITTED TOLERANCE SHALL BE ACCORDING TO 2022 CALIFORNIA BUILDING CODE.
1. PORTLAND CEMENT SHALL BE ASTM C150 TYPE V UNLESS OTHERWISE NOTED.
2. ALL CONCRETE SHALL BE NORMAL WEIGHT (145 PCF) HARD ROCK TYPE ASTM C33
3. CONCRETE SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH (f'c) AT 28 DAYS AS FOLLOWS, UNLESS OTHERWISE NOTED:
A. SLAB-ON-GRADE: 4,000 PSI UNLESS OTHERWISE NOTED.
B. EQUIPMENT PAD: 4,000 PSI UNLESS OTHERWISE NOTED.
4. CONCRETE MIXES SHALL BE DESIGNED BY A QUALIFIED TESTING LABORATORY, BEARING A REGISTERED CIVIL ENGINEER'S STAMP, AND REVIEWED AND APPROVED BY THE SEOR PRIOR TO USE.
5. MAXIMUM RATIO OF WATER TO CEMENTITIOUS MATERIALS, BY WEIGHT, SHALL BE 0.45 UNLESS OTHERWISE NOTED. USE MINIMUM 6 SACKS OF CEMENT PER CUBIC YARD OF CONCRETE.
6. ALL CONSTRUCTION JOINTS SHALL BE KEYED AND SHALL BE THOROUGHLY CLEANED. SEE CAST-IN-PLACE CONCRETE NOTE 10.
7. THE CONTRACTOR SHALL SUBMIT THE PROPOSED LOCATION OF ALL CONSTRUCTION JOINTS TO THE ENGINEER FOR REVIEW PRIOR PLACING OF CONCRETE. POUR JOINTS SHALL BE LOCATED TO MINIMIZE EFFECTS OF SHRINKAGE AS WELL AS PLACED AT POINTS OF LOW STRESS. REFER TO ACI 318, SEC. 26.5.6.
8. CONCRETE COVERAGE OF REINFORCING STEEL SHALL BE AS FOLLOWS, UNLESS OTHERWISE NOTED:
9. ALL EXPOSED CONCRETE EDGES SHALL BE FORMED WITH A 3/4" CHAMFER UNLESS OTHERWISE NOTED.
10. ALL NEW CONCRETE PLACED AGAINST HARDENED CONCRETE SHALL BE PREPARED PER THE FOLLOWING PROCEDURE:
11. BONDING AGENT WHEN SPECIFIED SHALL BE CHEMREX CONCRESIVE LIQUID LPL, OR SIKA ARMATEC 110
EPOCEM, OR APPROVED EQUAL AND SHALL BE APPLIED FOLLOWING THE MANUFACTURER'S RECOMMENDATIONS.
12. THE NOMINAL MAXIMUM SIZE OF COARSE AGGREGATES SHALL BE 1" UNLESS OTHERWISE NOTED.
13. ALL CRACKS WIDER THAN 1/64" IN NEW CONCRETE APPEARING WITHIN 6 MONTHS OF CONCRETE PLACEMENT SHALL BE REPAIRED USING EPOXY ADHESIVE INJECTION BY THE CONTRACTOR AT NO COST TO THE OWNER.
14. CONCRETE SHALL BE MIXED, PLACED AND CURED PER ACI 318, LATEST EDITION AND PROJECT SPECIFICATION.
A. ROUGHEN HARDENED SURFACE TO AN AMPLITUDE OF 1/4" WITH BUSH HAMMER, SAND BLASTING, OR OTHER APPROVED METHOD.
B. CLEAN SURFACES OF DUST AND DEBRIS USING CLEAN COMPRESSED AIR AND WATER.
C. THE SURFACE OF ALL HORIZONTAL CONSTRUCTION JOINTS SHALL BE CLEANED AND ROUGHED BY EXPOSING CLEAN AGGREGATE SOLIDLY EMBEDDED IN MORTAR MATRIX. IN THE EVENT THAT THE CONTACT SURFACE BECOMES COATED WITH EARTH, SAWDUST, ETC., AFTER BEING CLEANED, THE ENTIRE SURFACE SO COATED SHALL BE RECLEANED.
D. REFER TO OTHER NOTES FOR DUST CONTROL DURING CONSTRUCTION.
E. BONDING AGENTS ARE NOT ACCEPTABLE OR A SUBSTITUTE FOR PROCEDURES A, B. AND C.
A. CONCRETE CAST AGAINST AND PERMANENTLY EXPOSED TO EARTH: 3" B. CONCRETE EXPOSED TO EARTH OR WEATHER:
a. #6 THROUGH #18 REBAR: 2”
b. #5 REBAR, W31 OR D31 WIRE, AND SMALLER: 1 1/2"
C. CONCRETE NOT EXPOSED TO WEATHER OR IN CONTACT WITH GROUND:
· SLABS, WALLS AND JOISTS (#11 REBAR AND SMALLER): 1"
· BEAMS AND COLUMNS: 1-1/2"
D. SLABS-ON-GRADE: MID-DEPTH
STRUCTURAL STEEL
STRUCTURAL STEEL WELDING
POST-INSTALLED ANCHORAGE INTO CONCRETE DESIGN CRITERIA
SOIL AND FOUNDATION
SCOPE OF WORK
GENERAL
TOLERANCE
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set STRUCTURAL GENERAL NOTES
S-001
S-001 STRUCTURAL GENERAL NOTES
S-002 STRUCTURAL GENERAL NOTES
S-200 FOUNDATION, FRAMING AND SECTION
S-201 ELEVATIONS
S-500 DETAILS
S-501 DETAILS
DRAWING INDEX
CAST-IN-PLACE CONCRETE
13 B
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
@ AT
& AND
A.B. ANCHOR BOLT
ABV. ABOVE
ADD'L. (ADDL.) ADDITIONAL
ADJ. ADJACENT
ALT. ALTERNATE
ALUM. ALUMINUM
APPRX. (APPROX.) APPROXIMATE(LY)
ARCH. ARCHITECT(URAL)
BLDG. BUILDING
BLKG. BLOCKING
BLW. BELOW
BM. BEAM
B.N. BOUNDARY NAILING
BNDRY. BOUNDARY
B.O.C. BOTTOM OF CONCRETE
B.O.F. BOTTOM OF FOOTING
BOT. (B) BOTTOM
BRCG. BRACING
BRDG. BRIDGE (ING)
BRG. BEARING
BTWN. BETWEEN
CAMB. (C) CAMBER(ED)
CBC CALIFORNIA BUILDING CODE
CANT. CANTILEVER(ED)
C.F. CUBIC FEET (FOOT)
C.I.P. CAST-IN-PLACE
C.I.D.H. CAST-IN-DRILLED HOLE
C.J. CONTROL JOINT;
CONSTRUCTION JOINT
C.L. (℄) CENTER LINE
CLG. CEILING
CLR. CLEAR
COL. COLUMN
CONC. CONCRETE
CONN. CONNECTION
CONST. CONSTRUCTION
CONT. CONTINUOUS
C.P. COMPLETE-
PENETRATION
CTSK. COUNTERSINK
CTR. CENTER(ED)
C.P. CUBIC YARD
d d PENNY NAIL
DBA DEFORMED BAR ANCHOR
DBL. DOUBLE
DEPT. DEPARTMENT
D.F. DOUGLAS FIR
DIA. (∅) DIAMETER
DIAG. DIAGONAL
DIAPH. DIAPHRAGM
DIM. DIMENSION
DN. DOWN
DO DITTO (REPEAT)
DWG. (DWGS.) DRAWING(S)
DWL. DOWEL
EA. EACH
E.F. EACH FACE
E.J. EXPANSION JOINT
EL. ELEVATION
ELEC. ELECTRICAL
ELEV. ELEVATOR
EMB. EMBED(MENT)
E.N. EDGE NAIL
ENG. ENGINEER
EQ. EQUAL
EQPT. EQUIPMENT
EQUIV. EQUIVALENT
EXP. EXPANSION
EXIST. (E) EXISTING
EXT. EXTERIOR
FDN. FOUNDATION
FIN. FINISH(ED)
FLR. FLOOR
F.N. FIELD NAIL; FACE NAIL
F.O.C. FACE OF CONCRETE
F.O.M. FACE OF MASONRY
F.O.S. FACE OF STUD
F.O.W. FACE OF WALL
F.P. FULL PENETRATION
FRP FIBER REINFORCED POLYMER
FRT FIRE-RETARDANT-TREATED
F.S. FAR SIDE
FT. (') FOOT (FEET)
FTG. FOOTING
F.V. FIELD VERIFY
GA. GAUGE
GALV. GALVANIZE(D)
GLB. GLUED LAMINATED
BEAM (GLU-LAM)
GRD. GRADE
GYP. GYPSUM
HD. HOLDOWN; HAND
HDR. HEADER
HGR. HANGER
HORIZ. (H) HORIZONTAL
H.S. HEADED STUD
H.S.B. HIGH STRENGTH BOLT
HT. HEIGHT
I.D. INSIDE DIAMETER
IN. (") INCH(ES)
INFO. INFORMATION
JST. JOIST
JT. JOINT
K KIPS; 1000
K.P. KING POST
LAT. LATERAL
L.B. LAG BOLT
LB (#) POUND
L.F. LINEAL FEET (FOOT)
LDGR. LEDGER
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LT.WT. LIGHT WEIGHT
MAX. MAXIMUM
M.B. MACHINE BOLT
MECH. MECHANICAL
M.E.P. MECHANICAL, ELECTRICAL
AND PLUMBING
MEZZ. MEZZANINE
MFR. MANUFACTURER
MIN. MINIMUM
MISC. MISCELLANEOUS
MTL. METAL
(N) NEW
N.O.(#) NUMBER
N.S. NEAR SIDE
N.T.S. NOT TO SCALE
O/C (O.C.) ON CENTER
O.D. OUTSIDE DIAMETER
O.H. OPPOSITE HAND
OPNG. OPENING
OPP. OPPOSITE
ORTH. ORTHOGONAL
O.W.J. OPEN WEB JOIST
PC PILE CAP
PCF POUNDS PER CU.FT.
PL. PLATE
PLYWD. PLYWOOD
P.P. PARTIAL-
PENETRATION
P.S.F. POUNDS PER SQUARE FOOT
P.S.I. POUNDS PER SQUARE INCH
PT PRETENSIONED
P.T. PRESSURE TREATED
QTY. QUANTITY
RAD.(R) RADIUS
RBS REDUCED BEAM SECTION
REF. REFERENCE
REINF. REINFORCEMENT (ING)
REQ'D. (REQD.) REQUIRED
RF. ROOF
R.O. ROUGH OPENING
S.A.D. SEE ARCHITECTURAL
DRAWINGS
SC SLIP-CRITICAL
S.C.D. SEE CIVIL DRAWINGS
SCH. SCHEDULE
SEP. SEPARATION
SHT. SHEET
SIM. SIMILAR
SKW. SKEW(ED)
S..G. SLAB-ON-GRADE
SPEC. SPECIFICATION
SQ. SQUARE
ST SNUG-TIGHTENED
STD. STANDARD
STAGG. STAGGER(ED)
STIFF. STIFFENER
STIR. STIRRUP
STL. STEEL
STRUC(T). STRUCTURAL
SUSP. SUSPENDED
SYMM. SYMMETRICAL
T&B TOP AND BOTTOM
T&G TONGUE AND GROOVE
TEMP. TEMPORARY
THK. THICK(NESS)
T.N. TOE NAIL
T.O. TOP OF
T.O.C. TOP OF CONCRETE
T.O.S. TOP OF STEEL;
TOP OF SHEATHING
T.O.W. TOP OF WALL
TRANS. TRANSVERSE
T.S.G. TAPERED STEEL GIRDER
TYP. TYPICAL
U.N.O. UNLESS OTHERWISE NOTED
UTL. UTILITY
VERT. (V) VERTICAL
V.I.F. VERIFY IN FIELD
W/ WITH
(W) WIDE; WIDTH
WD. WOOD
W.P. WORK POINT
WT. WEIGHT
W.W.F. WELDED WIRE FABRIC
X-STG EXTRA STRONG
XX-STG DOUBLE EXTRA STRONG
CBC 2022 TABLE 1705.3: REQUIRED SPECIAL INSPECTIONS AND TESTS OF CONCRETE CONSTRUCTION ACI 318 Ch. 20, 25.2,
25.3, 26.6.1-26.6.3- X
- X
-X
-X
X
X
AWS D1.4,
ACI 318: 26.6.4
ACI 318: 17.8.2
-
-
1904.1, 1904.2,ACI 318: Ch. 19,
26.4.3., 26.4.4
ASTM C172,
ASTM C 31
ACI 318: 26.5,
26.12 ACI 318:
26. 5
ACI 318: 26.5.3-26.5.5
TYPE
CONTINUOUS
SPECIAL
INSPECTION
PERIODIC
SPECIAL
INSPECTION
REFERENCE
STANDARDa
CBC
REFERENCE
10. INSPECT ERECTION OF PRECAST CONCRETE MEMBERS.
X
X
-
-
ACI 318: 26.10 -
3. INSPECT ANCHORS CAST IN CONCRETE.
9. INSPECT PRESTRESSED CONCRETE FOR:
a. APPLICATION OF PRESTRESSING FORCES, AND
b. GROUTING OF BONDED PRESTRESSING TENDONDS.
X-
X
X
-
X-5. VERIFY USE OF REQUIRED DESIGN MIX.
ACI 318: Ch. 26.9
X
- -
X
ACI 318: 17.8.2
ACI 318: 17.8.2.4
X-
-
ACI 318: 26.11.2
ACI 318:
26.11.1.2 (b)X
a. WHERE APPLICABLE, SEE ALSO CBC SECTION 1705.13.
b. SPECIFIC REQUIREMENTS FOR SPECIAL INSPECTION SHALL BE INCLUDED IN THE RESEARCH REPORT FOR THE ANCHOR ISSUED BY AN APPROVED SOURCE IN ACCORDANCE WITH 17.8.2. IN ACI318 OR OTHER QUALIFICATIONS PROCEDURES. WHERE SPECIFIC REQUIREMENTS ARE NOT PROVIDED,
SPECIAL INSPECTION REQUIREMENTS SHALL BE SPECIFIED BY THE REGISTERED DESIGN PROFESSIONAL AND SHALL BE APPROVED BY THE BUILDING OFFICIAL PRIOR TO THE COMMENCEMENT OF THE WORK.
c. INSTALLATION OF ALL ADHESIVE ANCHORS IN HORIZONTAL AND UPWARDLY INCLINED POSITION SHALL BE PERFORMED BY AN ACI/CRSI CERTIFIED ADHESIVE ANCHOR INSTALLER, EXCEPT WHERE THE FACTORED DESIGN TENSION ON THE ANCHORS IS LESS THAN 100 POUNDS AND THOSE
ANCHORS ARE CLEARLY NOTED ON THE APPROVED CONSTRUCTION DOCUMENTS OR WHERE THE ANCHORS ARE SHEAR DOWELS ACROSS COLD JOINTS IN SLAB ON GRADE WHERE THE SLAB IS NOT A PART OF THE LATERAL FORCE-RESISTING SYSTEM.
1. INSPECT REINFORCEMENT INCLUDING PRESTRESSING
TENDONS, AND VERIFY PLACEMENT.
2. REINFORCING BAR WELDING:
a. VERIFY WELDABILITY OF REINFORCING BARS OTHER THAN
ASTM A706.
b. INSPECT SINGLE-PASS FILLET WELDS, MAXIMUM 5/16" ; AND c. INSPECT ALL OTHER WELDS.
4. INSPECT ANCHORS POST-INSTALLED IN HARDENED
CONCRETE MEMBERS.b
a. ADHESIVE ANCHORS INSTALLED IN HORIZONTAL OR
UPWARDLY INCLINED ORIENTATIONS TO RESIST
SUSTAINED TENSION LOADS.c
b. MECHANICAL ANCHORS AND ADHESIVE NOT DEFINED IN
4.a.
6. PRIOR TO CONCRETE PLACEMENT,FABRICATE SPECIMENS
FOR STRENGTH TESTS, PERFORM SLUMP AND AIR CONTENT
TESTS, AND DETERMINE THE TEMPERATURE OF THE
CONCRETE.
7. INSPECT CONCRETE FOR PROPER APPLICATION TECHNIQUES.
8. VERIFY MAINTENANCE OF SPECIFIED CURING TEMPERATURE
AND TECHNIQUES.
11. VERIFY IN-SITU CONCRETE STRENGTH, PRIOR TO STRESSING
TENDONS IN POST-TENSIONED CONCRETE AND PRIOR TO REMOVAL OF SHORES AND FORMS FROM BEAMS AND STRUCTURAL SLABS.
12. INSPECT FORMWORK FOR SHAPE, LOCATION AND DIMENSIONS OF THE CONCRETE MEMBER BEING FORMED.
-
-
-
-
-
-
-
-
-
CBC 2022 - TABLE 1705.6: REQUIRED SPECIAL INSPECTIONS AND TESTS OF SOILS
VERIFY MATERIAL BELOW SHALLOW FOUNDATIONS ARE
ADEQUATE TO ACHIEVE THE DESIGN BEARING CAPACITY.
VERIFY EXCAVATIONS ARE EXTENDED TO PROPER
DEPTH AND HAVE REACHED PROPER MATERIAL.
PERFORM CLASSIFICATION AND TESTING OF COMPACTED FILL
MATERIALS.
PRIOR TO PLACEMENT OF COMPACTED FILL, INSPECT SUBGRADE
AND VERIFY THAT SITE HAS BEEN PREPARED PROPERLY.
CONTINUOUS
SPECIAL INSPECTION
X
-
PERIODICALLY
SPECIAL INSPECTION
X
X
X
X
-
-
-
-
VERIFICATION AND INSPECTION TASK
DURING FILL PLACEMENT, VERIFY USE OF PROPER
MATERIALS AND PROCEDURES IN ACCORDANCE WITH THE
PROVISIONS OF THE APPROVED GROTECHINCAL REPORT.
VERIFY DENSITIES AND LIFT THICKNESS DURING
PLACEMENT AND COMPACTION OF COMPACTED FILL.
1. STRUCTURAL OBSERVATION IS REQUIRED FOR THE STRUCTURAL SYSTEM IN ACCORDANCE WITH SECTION 1704A.6 OF THE 2022 CALIFORNIA BUILDING CODE. STRUCTURAL OBSERVATION IS THE VISUAL OBSERVATION
AT THE CONSTRUCTION STAGES AND THE COMPLETE STRUCTURE FOR GENERAL CONFORMANCE TO THE APPROVED PLANS AND SPECIFICATIONS. STRUCTURAL OBSERVATION DOES NOT WAIVE THE RESPONSIBILITY FOR THE INSPECTIONS REQUIRED OF THE BUILDING INSPECTOR OR THE SPECIAL INSPECTOR.
2. THE OWNER SHALL EMPLOY THE REGISTERED DESIGN PROFESSIONAL RESPONSIBLE FOR THE STRUCTURAL
DESIGN, OR ANOTHER REGISTERED DESIGN PROFESSIONAL DESIGNATED BY THE REGISTERED DESIGN PROFESSIONAL RESPONSIBLE FOR THE STRUCTURAL DESIGN TO PERFORM STRUCTURAL OBSERVATIONS.
NAME OF SE: SAID HILMY
3. THE STRUCTURAL OBSERVER SHALL PROVIDE EVIDENCE OF EMPLOYMENT BY THE OWNER OR THE OWNER'S REPRESENTATIVE. A LETTER FROM THE OWNER, THE OWNER'S REPRESENTATIVE, OR A COPY OF THE AGREEMENT FOR SERVICES SHALL BE SENT TO THE BUILDING INSPECTOR BEFORE THE FIRST SITE VISIT.
4. THE OWNER OR OWNER'S REPRESENTATIVE SHALL COORDINATE AND CALL FOR A MEETING BETWEEN THE
ENGINEER OR ARCHITECT RESPONSIBLE FOR THE STRUCTURAL DESIGN, STRUCTURAL OBSERVER, CONTRACTOR, AFFECTED SUBCONTRACTORS AND SPECIAL INSPECTORS. THE PURPOSE OF THE MEETING
SHALL BE TO IDENTIFY THE MAJOR STRUCTURAL ELEMENTS AND CONNECTIONS THAT AFFECT THE VERTICAL
AND LATERAL LOAD SYSTEMS OF THE STRUCTURE AND TO REVIEW SCHEDULING OF THE REQUIRED OBSERVATIONS. A RECORD OF THE MEETING SHALL BE INCLUDED IN THE FIRST OBSERVATION REPORT SUBMITTED TO THE BUILDING INSPECTOR.
5. THE STRUCTURAL OBSERVER SHALL PERFORM SITE VISITS AT THOSE STEPS IN THE PROGRESS OF THE
WORK THAT ALLOW FOR CORRECTION OF DEFICIENCIES WITHOUT SUBSTANTIAL EFFORT OR UNCOVERING OF THE WORK INVOLVED. AT A MINIMUM, THE LISTED SIGNIFICANT CONSTRUCTION STAGES ON THE "STRUCTURAL OBSERVATION/SIGNIFICANT CONSTRUCTION STAGES" FORM REQUIRE A SITE VISIT AND AN OBSERVATION REPORT FROM THE STRUCTURAL OBSERVER.
6. THE STRUCTURAL OBSERVER SHALL PREPARE A REPORT OF THE STRUCTURAL OBSERVATION REPORT FORM FOR EACH SIGNIFICANT STAGE OF CONSTRUCTION OBSERVED. THE ORIGINAL OF THE STRUCTURAL
OBSERVATION REPORT SHALL BE SHALL BE SEALED AND SIGNED BY THE RESPONSIBLE STRUCTURAL OBSERVER. COPIES OF THE REPORT SHALL ALSO BE GIVEN TO THE OWNER, CONTRACTOR, AND SPECIAL INSPECTOR. ANY DEFICIENCY NOTED ON THE OBSERVATION REPORT WILL BECOME THE RESPONSIBILITY OF
THE STRUCTURAL ENGINEER OF RECORD TO VERIFY ITS COMPLETION BY HIM (HER), OR BY A REGISTERED SPECIAL INSPECTOR AT THE DISCRETION OF THE STRUCTURAL OBSERVER.
CONSTRUCTION STAGE ELEMENTS / CONNECTIONS TO BE OBSERVED; A. FOUNDATION AND SLAB ON GRADE: DEPTH AND WIDTH OF FOOTING, REINFORCING PLACEMENT, SIZE AND GRADE OF REINFORCING STEEL.
B. CONCRETE MASONRY WALLS: WALL REINFORCING, SIZE AND GRADE OF REINFORCING STEEL, EMBEDS.
7. A FINAL OBSERVATION REPORT MUST BE SUBMITTED WHICH SHOWS THAT ALL OBSERVED DEFICIENCIES
WERE RESOLVED AND STRUCTURAL SYSTEM GENERALLY CONFORMS WITH THE APPROVED PLANS AND SPECIFICATIONS.
1. ALL CONCRETE SHALL BE REINFORCED. REINFORCING STEEL SHALL BE NEW DEFORMED STEEL BARS CONFORMING TO ASTM A615, GRADE 60 UNLESS OTHERWISE NOTED.
2. REINFORCING STEEL SHALL BE ACCURATELY PLACED AND FIRMLY SUPPORTED DURING CONCRETE POUR.
3. COMPLETE REINFORCING STEEL PLACEMENT DRAWINGS SHALL BE PREPARED IN ACCORDANCE WITH ACI 315 BY THE CONTRACTOR AND REVIEWED BY THE SEOR AND SHALL BE AVAILABLE ON THE JOB SITE PRIOR TO INSPECTION AND THE PLACING OF CONCRETE.
4. ANCHOR BOLTS, DOWELS AND OTHER EMBEDDED ITEMS SHALL BE SECURELY ANCHORED AND/OR TIED IN PLACE BEFORE CONCRETE IS PLACED.
5. ALL REINFORCING STEEL TO BE WELDED SHALL CONFORM TO ASTM A706, GRADE 60. DEFORMATIONS SHALL BE IN ACCORDANCE WITH ASTM A615.
6. ALL WELDING OF REINFORCING STEEL SHALL CONFORM TO AWS D1.4 AND SHALL BE PERFORMED BY CERTIFIED WELDERS USING AWS A5.5 E80XX FOR ASTM A706 GRADE 60 (TABLE 7.1 AWS D1.4) LOW HYDROGEN MOISTURE RESISTING ELECTRODES UNLESS OTHERWISE NOTED.
7. NO HEATING SHALL BE ALLOWED FOR BENDING OF REINFORCING STEEL UNLESS APPROVED BY THE ENGINEER.
8. ALL MECHANICAL SPLICES SHALL BE APPROVED BY THE SEOR AND INSPECTED DURING CONSTRUCTION AND SHALL HAVE AN ICC-ES/IAPMO NUMBER.
9. ALL HEADED BAR SYSTEMS (TERMINATORS) SHALL BE APPROVED BY THE SEOR AND INSPECTED DURING CONSTRUCTION AND SHALL HAVE AN ICC-ES/IAPMO NUMBER.
10. ALL REINFORCING STEEL INTERRUPTED BY STRUCTURAL STEEL SHALL TERMINATE WITHIN 1" OF STEEL SURFACE WITH A 90° STANDARD HOOK UNLESS OTHERWISE NOTED.
11. ALL REINFORCING BEND SHALL BE MADE COLD. RE-BENDING OR PREVIOUSLY BENT REINFORCING IS NOT PERMITTED.
A. GROUTED MASONRY SHALL BE CONSTRUCTED IN SUCH A MANNER THAT ALL ELEMENTS OF THE MASONRY ACT TOGETHER AS A STRUCTURAL ELEMENT. AT THE TIME OF LAYING, ALL MASONRY UNITS SHALL BE FREE OF DUST AND DIRT. PRIOR TO GROUTING, THE GROUT SPACE SHALL BE
CLEAN SO THAT ALL SPACES TO BE FILLED WITH GROUT DO NOT CONTAIN MORTAR PROJECTIONS GREATER THAN 1/4 INCH (6.4 MM), MORTAR DROPPINGS AND OTHER FOREIGN MATERIAL. GROUT SHALL BE PLACED SO THAT ALL SPACES TO BE GROUTED DO NOT CONTAIN VOIDS.
B. VERTICAL CELLS TO BE FILLED SHALL HAVE VERTICAL ALIGNMENT SUFFICIENT TO MAINTAIN A CLEAR GROUT SPACE DIMENSION OF NOT LESS THAN 2 INCHES BY 3 INCHES (51 MM BY 76 MM), EXCEPT THE MINIMUM CELL DIMENSION FOR HIGH-LIFT GROUT SHALL BE 3 INCHES (76 MM), AS DETERMINED IN ACCORDANCE WITH TMS 602 TABLE 7, FOOTNOTE 3.
C. GROUT ALL CELLS. GROUT SHALL BE A WORKABLE MIX SUITABLE FOR PLACING WITHOUT SEGREGATION AND SHALL BE THOROUGHLY MIXED. GROUT SHALL BE PLACED BY PUMPING OR AN
APPROVED ALTERNATE METHOD AND SHALL BE PLACED BEFORE INITIAL SET OR HARDENING OCCURS. GROUT SHALL BE CONSOLIDATED BY MECHANICAL VIBRATION DURING PLACING AND
RECONSOLIDATED AFTER EXCESS MOISTURE HAS BEEN ABSORBED, BUT BEFORE WORKABILITY IS LOST.
D. GROUT MATERIALS AND WATER CONTENT SHALL BE CONTROLLED TO PROVIDE ADEQUATE
FLUIDITY FOR PLACEMENT WITHOUT SEGREGATION OF THE CONSTITUENTS, AND SHALL BE MIXED THOROUGHLY. SEGREGATION OF THE GROUT MATERIALS AND DAMAGE TO THE MASONRY SHALL BE AVOIDED DURING THE GROUTING PROCESS.
E. REINFORCEMENT AND EMBEDDED ITEMS SHALL BE CLEAN, PROPERLY POSITIONED AND SECURELY ANCHORED AGAINST MOVEMENT PRIOR TO GROUTING. BOLTS SHALL BE ACCURATELY
SET WITH TEMPLATES OR BY APPROVED EQUIVALENT MEANS AND HELD IN PLACE TO PREVENT DISLOCATION DURING GROUTING. REINFORCEMENT, EMBEDDED ITEMS AND BOLTS SHALL BE SOLIDLY EMBEDDED IN GROUT. ANCHOR BOLTS IN THE FACE SHELLS OF HOLLOW MASONRY UNITS SHALL BE POSITIONED TO MAINTAIN A MINIMUM OF 1/2 INCH OF GROUT BETWEEN THE BOLT AND THE FACE SHELL.
F. ALL REINFORCEMENT AND WIRE TIES SHALL BE EMBEDDED IN THE GROUT. THE SPACE BETWEEN MASONRY UNIT SURFACES AND REINFORCEMENT SHALL BE A MINIMUM OF ONE BAR DIAMETER.
G. HORIZONTAL REINFORCEMENT SHALL BE PLACED IN BOND BEAM UNITS WITH A MINIMUM GROUT COVER OF 1 INCH (25 MM) ABOVE STEEL FOR EACH GROUT POUR. THE DEPTH OF THE BOND BEAM CHANNEL BELOW THE TOP OF THE UNIT SHALL BE A MINIMUM OF 11/2 INCHES (38 MM) AND THE WIDTH SHALL BE 3 INCHES (76 MM) MINIMUM
H. CONSOLIDATE GROUT POURS EXCEEDING 12 INCH (305 mm) IN HEIGHT BY MECHANICAL
VIBRATION, AND RECONSOLIDATION BY MECHANICAL VIBRATION AFTER INITIAL WATER LOSS AND SETTLEMENT HAS OCCURRED, BUT BEFORE PLASTICITY IS LOST.
I. BETWEEN GROUT POURS OR WHERE GROUTING HAS BEEN STOPPED MORE THAN AN HOUR, A
HORIZONTAL CONSTRUCTION JOINT SHALL BE FORMED BY TERMINATING GROUT A MINIMUM OF 11/2" (38 mm) BELOW A MORTAR JOINT, EXCEPT AT THE TOP OF THE WALL. WHERE BOND BEAMS OCCUR, THE GROUT POUR SHALL BE TERMINATED OF 1/2" (12.7 mm) BELOW THE MORTAR JOINT.
HORIZONTAL REINFORCEMENT SHALL BE PLACED IN BOND BEAM UNITS WITH A MINIMUM GROUT COVER OF 1 INCH (25 mm) ABOVE REINFORCING STEEL FOR EACH GROUT POUR.
J. GROUT SHALL NOT BE HANDLED NOR PUMPED UTILIZING ALUMINUM EQUIPMENT UNLESS IT CAN
BE DEMONSTRATED WITH THE MATERIALS AND EQUIPMENT TO BE USED THAT THERE WILL BE NO DELETERIOUS EFFECT ON THE STRENGTH OF THE GROUT.
1. MASONRY (ASSEMBLY OF MASONRY UNITS, MORTAR, AND GROUT) SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF 1,500 PSI AND SHALL BE RUNNING BOND CONSTRUCTION WITH SPECIAL INSPECTION.
2. MASONRY UNITS SHALL BE MEDIUM WEIGHT UNIT CONFORMING TO ASTM C90 AND SHALL HAVE A MINIMUM NET COMPRESSIVE STRENGTH OF 1,500 PSI. USE DOUBLE OPEN END, BOND BEAM UNITS UNLESS OTHERWISE NOTED.
3. MORTAR SHALL BE TYPE S OF CEMENT-LIME MORTAR WITH A MINIMUM COMPRESSIVE STRENGTH OF 1,800 PSI AND COMPLY WITH ASTM C270. MASONRY CEMENT MORTAR SHALL NOT BE USED.
4. GROUT SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF 1,500 PSI AND COMPLY WITH ASTM C476 AND ARTICLE 2.2 OF TMS 402/602-16.
5. AGGREGATES SHALL CONFORM TO ASTM C144 FOR MORTAR AND ASTM C404 FOR GROUT.
6. GROUTED MASONRY GENERAL CONDITIONS.
A. WATER CONTENT SHALL BE ADJUSTED TO PROVIDE PROPER WORKABILITY AND TO ENABLE PROPER PLACEMENT UNDER EXISTING FIELD CONDITIONS, WITHOUT SEGREGATION.
B. KB. PROPORTIONS OF INGREDIENTS AND ANY ADDITIVES SHALL BE BASED ON LABORATORY OR FIELD EXPERIENCE WITH THE GROUT INGREDIENTS AND THE MASONRY UNITS TO BE USED.
COARSE GROUT PROPORTIONED BY WEIGHT SHALL CONTAIN NOT LESS THAN 564 POUNDS OF CEMENTITIOUS MATERIAL PER CUBIC YARD (335 KG/M3/).
C. COARSE GROUT SHALL BE USED IN GROUT SPACES BETWEEN WYTHES OF 2 INCHES (51 MM) OR MORE IN WIDTH AS DETERMINED IN ACCORDANCE WITH TMS 602 TABLE 6, FOOTNOTE 3, AND IN ALL GROUTED CELLS OF HOLLOW UNIT MASONRY CONSTRUCTION.
D. AIR-ENTRAINING SUBSTANCES SHALL NOT BE USED IN GROUT.
7. THE COLD WEATHER CONSTRUCTION PROVISIONS OF TMS 602/402-16, ARTICLE 1.8 C, SHALL BE IMPLEMENTED WHEN THE AMBIENT TEMPERATURE FALLS BELOW 40° F (4.4°C).
8. THE HOT WEATHER CONSTRUCTION PROVISIONS OF TMS 602/402-16, ARTICLE 1.8 D, SHALL BE IMPLEMENTED WHEN THE AMBIENT AIR TEMPERATURE EXCEEDS 100° F (37.8°C), OR 90° F (32.2°C) WITH A WIND VELOCITY GREATER THAN 8 MPH (12.9 KM/HR).
GROUT POUR HEIGHT: COMPLY WITH REQUIREMENTS IN TMS 602 ARTICLE 3.5C AS MODIFIED HEREIN.
ADD TO TMS 602, ARTICLE 3.5 C THE FOLLOWING:
10. NO PIPES OR DUCTS SHALL BE PLACED IN MASONRY WALLS UNLESS SPECIFICALLY NOTED OR DETAILED ON APPROVED STRUCTURAL DRAWINGS.
11. ELECTRICAL CONDUIT/PIPE MAY BE ROUTED IN CMU WALLS AS FOLLOWS. • GROUTING SHALL BE DONE IN A CONTINUOUS POUR IN LIFTS NOT EXCEEDING 4 FEET (1219 MM) OR 5 FEET 4 INCHES (1651 MM) FOR 10-INCH (254 MM) NOMINAL OR WIDER HOLLOW UNIT MASONRY.
• AN APPROVED ADMIXTURE OF A TYPE THAT REDUCES EARLY WATER LOSS AND PRODUCES AN EXPANSIVE ACTION SHALL BE USED.
• THE GROUTING OF ANY SECTION OF WALL SHALL BE COMPLETED IN ONE DAY WITH NO INTERRUPTIONS GREATER THAN ONE HOUR.
• FOR MULTIPLE GROUT LIFTS WITHIN A GROUT POUR, EACH GROUT LIFT HEIGHT OF WALL, COLUMN, PIER OR BEAM SHALL BE INSPECTED BEFORE PLACEMENT OF ADDITIONAL UNITS. • CLEANOUT OPENINGS SHALL BE PROVIDED AT THE BOTTOM OF EACH POUR OF GROUT A. MAXIMUM SIZE AND QUANTITY OF CONDUIT PER CELL (EXCEPT AT JUNCTION BOXES) SHALL BE (1) 1" DIAMETER OR (2) 3/4" DIAMETER (BUNDLED TOGETHER).
B. CONDUIT SHALL NOT BE PLACED IN A MASONRY CELL CONTAINING REINFORCING.
C. CONDUIT/PIPE/SLEEVES SHALL NOT BE PLACED IN THE PILASTER OR COLUMNS.
D. CONDUIT SHALL BE PLACED AT THE CENTERLINE OF THE WALL.
E. CONDUIT, PIPE, AND SLEEVES IN MASONRY SHALL BE NO CLOSER THAN 3 DIAMETERS ON CENTER. MINIMUM SPACING OF CONDUITS, PIPES OR SLEEVES OF DIFFERENT DIAMETERS SHALL BE DETERMINED USING THE LARGER DIAMETER.
PIPES/CONDUITS/SLEEVES NOT PERMITTED IN PILASTERS/COLUMNS.
1. PROVIDE NON-SHRINK, NON-METALLIC, NON-CORROSIVE PORTLAND CEMENT BASED MATERIAL CONFORMING WITH ALL PROPERTIES OF ASTM C1107 AND WITH A CURRENT CODE EVALUATION REPORT FROM ONE OF THE FOLLOWING MANUFACTURER'S:
a. SIKA
b. QUIKRETE
c. BASF
d. APPROVED EQUAL
2. GROUT SHALL COMPLY WITH THE FOLLOWING PERFORMANCE REQUIREMENTS:
EXPANSION: 0.4 PERCENT MAXIMUM AT 28 DAYS. GROUT WILL EXHIBIT NO DISPLACEMENT WHEN TESTED IN ACCORDANCE WITHASTM C157/C157M.
SHRINKAGE: NONE (0.0 PERCENT SHRINKAGE AT 28 DAYS WHEN TESTED IN ACCORDANCE WITH ASTM C827 AND ASTM C 1090). THERE SHALL BE NO VOLUME SHRINKAGE OF GROUT IN THE PLASTIC OR HARDENED STAGE AT ANY TIME.
COMPRESSIVE STRENGTH: 5,000 PSI MINIMUM AT 28 DAYS WHEN TESTED IN ACCORDANCE WITH ASTM C109/C109M.
3. SURFACE PREPARATION AND INSTALLATION SHALL BE IN CONFORMANCE WITH THE MANUFACTURER'S WRITTEN INSTALLATION INSTRUCTIONS.
4. ADD THE MINIMUM AMOUNT OF WATER NECESSARY TO PRODUCE THE DESIRED FLOW CHARACTERISTICS.
DO NOT EXCEED A FLOW OF 20 SECONDS PER ASTM C939.
5. SUBMIT MANUFACTURER'S PRODUCT LITERATURE, WRITTEN INSTALLATION INSTRUCTIONS, AND MATERIAL SAFETY DATA SHEETS (MSDS) FOR REVIEW. DO NOT USE ANY CONCRETE OR GROUT CONTAINING CHLORIDES. WATER USED IN MIX SHALL BE CLEAN AND POTABLE.
6. REPAIR UNUSED CORED OR DRILLED HOLES BY FILLING WITH NON-SHRINK GROUT AT CONCRETE AND MASONRY, FINISH SURFACE TO MATCH THE ADJACENT CONDITION.
7. FOR THICK GROUT LAYERS FOLLOW MANUFACTURER'S GUIDELINES TO ATTAIN THE REQUIRED STRENGTH, WHICH MAY INCLUDE THE ADDITION OF 3/8" AGGREGATE.
ABBREVIATURE
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set STRUCTURAL GENERAL NOTES
S-002
CBC 2022 - TABLESSTRUCTURAL OBSERVATION PROGRAM
REINFORCING STEEL
MASONRY
NON-SHRINK GROUT
14 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
3 S-200
S-200
4 S-200
6 GENERATOR
MAX. OP. WT. =
2,200 LBS. SEE
N
3 2
4' - 3" 10' - 10"
MIN.
5' - 1"
1 (E) CMU WALL
TO BE REMOVED
7 S-501
TYP.
4 1' - 4"
16"x12"
CMU PILASTER
PER
16"x12" CMU
PILASTER PER
A
S-501
12 2' - 6"
POST ABV.
12"
EQEQ
EQEQ
B
12'-0 "
EQEQEQEQ
12' - 0"
POST ABV.
(N) LEVEL
CONC. PAD W/
#5 @ 12"O.C.
T&B EA. WAY
CONDUIT
SEE ELEC.
DWGS.
(9'-8" MAX.)
OPENING PER ARCH'L
POST ABV.
POST ABV.
POST ABV.
POST ABV.
CONTROLLER
UNIT, MAX.
W.T. = 40 LBS
ELECTRICAL UNITS,
MAX W.T. = 60 LBS
ATS UNIT,
MAX. W.T. = 75 LBS
(E) PULLBOX
BELOW GRADE
METER PEDESTAL,
MAX. W.T = 75 LBS
SEE ---
14 S-501
14 S-501
15 S-501
S-201
2 S-201
1 MCC UNIT WITH MAX. DIMENSIONS OF
90" H x 60" W x 20" D AND MAX. WT. 500 LBS
CONNECTED TO THE (E) SLAB WITH (4) 1/2"
Φ THREADED ROD SS 316, ASTM F1554 GR.
36 AT EQ. SPACING W/ HIT-RE 500 V3
EPOXY AND MIN. 5" EFFEC. EMBED. DEPTH,
(ICC ESR-3814)
SCADA CABINET UNIT WITH MAX.
DIMENSIONS OF 72" H X 48" W X 24" D AND
MAX WT. 500 LBS CONNECTED TO THE (E)
SLAB WITH (4) 1/2" ⌀ THREADED ROD SS
316, ASTM F1554 GR. 36 W/ HIT -RE 500 V3
EPOXY AND MIN. 5" EFFEC. EMBED. DEPTH,
(ICC ESR-3814)
~
/11 S-501
/10 S-501
/1 S-501
(4) 3/4"⌀ SS316 HILTI KB-TZ2
W/ 4 3/4" EFFECTIVE EMBED
(ICC ESR-4266), LOCATION
PER MFR.
8"
MIN.
TYP.
(E) GENERATOR
PAD, SEE ARCH.
DWGS. FOR REPAIR
MEASURES
HSS6x2x3/16
8" CMU WALL
BELOW
3 S-200
S-200
4 S-200
6 N
HSS6x2x3/16
HSS6x2x3/16 HSS6x2x3/16
3 HSS4x4x1/4
POST
HSS4x4x1/4
POST HSS4x4x1/4
POST
HSS6x2x3/16
HSS6x2x3/16
HSS6x2x3/16
HSS6x2x3/16
HSS6x2x3/16
HSS6x2x3/16
2 HSS4x4x1/4
POST
HSS6x2x3/16
HSS6x2x3/16HSS6x2x3/16
HSS6x2x3/16
HSS6x2x3/16
1 HSS4x4x1/4
POST HSS4x4x1/4
POST
4 A
4' - 3" 10' - 10" 5' - 1"
B
11' - 4"
EQ
1½"x18GA HSB -36
ROOF DECK
PILASTER BELOW
PER FOUND. PLAN
PILASTER BELOW
PER FOUND. PLAN
HSS6x2x3/16
S-201
2 S-201
1 HSS6x2x3/16
T.O.CMU
8' - 0"
#4 @ 16" O.C.
CONT' ANGLE PER
COL. BEYOND
PER PLAN, TYP.
ROOF DECK
PER PLAN
HSS BEAM PER PLAN
#5 @ 16" O.C.
8" CMU WALL PER PLAN
S.O.G. REBAR
PER PLAN
PORTION
OF S.O.G. TO
REMAIN
T.O.S.
(E) #4 @ 16" O.C. EA. WAY
(E) #4 HORIZ. BAR
(E) #4 @ 16" O.C.
VERT. BAR
(E) 8" CMU WALL
PER PLAN
S-501
3 (E) (2) #4 HORIZ BAR
PAVEMENT BY OTHERS
S-501
5 A
TYP.
(E) 4" PERFORATED PVC
DRAIN PIPE W/ 1/2"
CRUSHED ROCK
AROUND TO REMAIN. F.V.
KEY TO MATCH EXISTING(1) #4 HOR. BAR T&B
#3 TIE W/180° PER
@ 18"O.C.
14" 12"
(E) KEY TO REMAIN
LAP SPLICE
B
VARIES (6'-0" MAX.)
(E) #4 HORIZ. BAR
12" 14"
/7 S-501PER
/5 S-501
/2 S-500
WELDED DOWEL
#
4 x 3'-6", TYP.
6"
(N) CONC.
LEVEL PAD
2" CLR.
3" CLR.
TYP.
TYP.
DOWEL
PER
TYP.
/7 S-501
T.O.CMU
8' - 0"
HSS BEAM
PER PLAN
(E) 8" CMU
PER PLAN
LOUVER
PER ARCH'L
CORER BAR
PER
11 S-501HORIZ. BAR PER
SECTION , TYP.
VERTICAL BAR PER
SECTION , TYP.
HSS COL.
PER PLAN
8 S-500
ROOF DECK
PER PLAN
3 2 1
2' - 0"
4 (E) FINISH GRADE
S-200
5 SIM.
S.O.G.
PER PLAN
CMU PILASTER
PER PLAN
(5) #5 DOWEL
W/90° HOOK PER
10 S-501
2' - 6"
36" MIN. SPLICE
36" MIN. EMBED
CMU PILASTER
PER PLAN
OPNG./3 S-200
/3 S-200
/13 S-500 /2 S-500
S-501
7 KEY BEYOND
T.O.CMU
8' - 0"
HSS COL.
PER PLAN
8" CMU PER PLAN
8 S-500
DOWEL REBAR
PER
S-200
5 HSS BEAM
PER PLAN
ROOF DECK PER PLANHSS BEAM
PER PLANS-501
5 (E) FINISH GRADE
TYP.
8" CMU WALL
BEYOND
A B
OPNG.
~
HORIZ. BAR
PER SECTION ,
TYP.
(2) JAM BAR PER
DETAIL
/3 S-200
/3 S-200
/13 S-500
VERTICAL BAR
PER SECTION , TYP. /3 S-200
KEY BEYOND
13 S-500
(2) JAMB BAR PER
DETAIL
(5) #5 CORNER BAR
SPLICE PER
(5) #5 LINTEL BAR
PER
LINTEL TIES PER
8 S-500 8
S-500
/13 S-500
/13 S-500
/8 S-500
INDICATES (E) 8" CMU WALL
TO REMAIN
INDICATES 8" CMU WALL, U.N.O.
INDICATES 12" CONC. S.O.G.
W/ (2) LAYERS #5@12" O.C. T&B EA. WAY.
LEGEND:
INDICATES HSS POST ABOVE
INDICATES (E) CONCRETE SLAB
TO REMAIN
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set FOUNDATION, FRAMING AND SECTION
S-200
1/4" = 1'-0"FOUNDATION PLAN 1
1/4" = 1'-0"ROOF FRAMING PLAN 2
3/8" = 1'-0"SECTION 3
3/8" = 1'-0"EAST ELEVATION 43/8" = 1'-0"SOUTH ELEVATION 6 1" = 1'-0"LINTEL AT CORNER WALL 5
15 B
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
Level 1
0' - 0"
ROOF PLAN
10' - 1"
T.O.CMU
8' - 0"
3 S-200
321 4
12 S-501
(N) CMU WALL
(E) CMU WALL
~
~
KEY BEYOND
S-501
7 Level 1
0' - 0"
ROOF PLAN
10' - 1"
T.O.CMU
8' - 0"
AB
~
VERT. BAR TO MATCH
(E) VERT. REINF.
(E) VERT. BAR.
NOTES
1. REMOVE TOP COURSE OF (E) C.M.U. BLOCKS TO EXPOSE
VERTICAL BARS WITHOUT DAMAGING THEM AND EXTEND
EXISTING LONGITUDINAL BARS WITH COUPLERS
2. FOR COUPLERS, REFER TO DETAILS &
HORIZ. BARS
PER DETAIL /3 S-200
/3 S-201 /4 S-201
COUPLER
KEY BEYOND
NOTES:
1. THREADED MECHANICAL COUPLERS SHALL BE ONE OF THE FOLLOWING SYSTEMS,
OR AN APPROVED EQUAL HEADED REINFORCEMENT CORPORATION,
HRC 500/510 XTENDER (ICC ESR-2764)
ERICO, LENTON COUPLER (IAPMO ER-0129)
BARSPLICE PRODUCTS, GRIP-TWIST (ICC ESR-2299)
DAYTON SUPERIOR, TAPERLOCK (ICC ESR-2481)
1. COUPLER SHALL DEVELOP 160 PERCENT OF THE BAR YIELD STRENGTH.
MECHANICAL COUPLERS SHALL OCCUR @ LOCATIONS IDENTIFIED PER PLAN AND COLUMN SCHEDULE.
2. COUPLERS ARE ACI 318-11 TYPE 2 CONNECTORS FOR USE IN SEISMIC FRAMES.
3. INSTALLATION PROCEDURE SHALL FOLLOW MANUFACTURES RECOMMENDATIONS.
4. MAINTAIN COVER PER GENERAL NOTES SHEETS.
NOTES:
1. LOCK-BOLT MECHANICAL COUPLERS SHALL BE ONE OF THE
FOLLOWING SYSTEMS, OR AN APPROVED EQUAL
DAYTON SUPERIOR, BAR-LOCK, L-SERIES (ICC
ESR-2495)
ERICO, LENTON LOCK, B1 SERIES (IAPMO
ER-0129)
BARSPLICE PRODUCTS, ZAP SCREWLOCK (ICC ER-3517)
2. COUPLER SHALL DEVELOP 160 PERCENT OF THE BAR YIELD
STRENGTH.
3. MECHANICAL COUPLERS SHALL OCCUR @ LOCATIONS IDENTIFIED PER PLAN AND COLUMN SCHEDULE.
4. COUPLERS ARE TYPE 2 CONNECTORS FOR USE IN SEISMIC FRAMES.
5. INSTALLATION PROCEDURE SHALL FOLLOW MANUFACTURES
RECOMMENDATIONS.
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set ELEVATIONS
S-201
3/8" = 1'-0"WEST ELEVATION 13/8" = 1'-0"NORTH ELEVATION 2 6" = 1'-0"TYP. MECH. COUPLER, THREADED 3
6" = 1'-0"TYP. MECH. COUPLER, LOCK-BOLT 4
16 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
#5 OR WALL VERT.
REINF.; WHICHEVER IS
GREATER; 3 TOTAL
(20'-0" MIN.)
48db
CUT SHELL TO
MATCH UNIT WIDTH
(2) #6 JAMB BAR
2'-6" MAX.
SINGLE CURTAIN CONDITION
SECTION ATJAMB REINF. OR REINF. AT WALL ENDS
(PLAN VIEWS)
ADD #3x24" MATCHING WALL
HORIZ. REINF. SPACING
AT OPENING, PROVIDE JAMB REINF. PER
JAMB & LINTEL REINF. SCH. U.N.O.; AT
WALL ENDS, PROVIDE 2-#6 U.N.O.
24"
NOTE:
1. db INDICATES DIAMETER OF REINFORCEMENT.
WHICHEVER IS GREATER
1" CLR. OR 1 1/2db MIN.
#5 OR WALL VERT.
REINF.; WHICHEVER IS
GREATER; 3 TOTAL
(20'-0" MIN.)
48db
CUT SHELL TO
MATCH UNIT WIDTH
TYP. WALL SECTION
SINGLE CURTAIN CONDITION
SOLID GROUTED
MASONRY
WALL W/ SPECIAL
INSPECTION
TYP. VERT. REINF.
TYP. HORIZ. REINF.
DISTANCE, d, FROM
FACE OF CMU TO THE
CENTER OF REINF.
ALLOWABLE
TOLERANCE
± 1/2"
8" < d < 24"
TOLERANCES FOR PLACING REINF.
d < 8"
±1"
d < 24" ±1 1/4"
db
IS THE GREATER
1" CLR. OR 1 1/2 db
MIN. WHICHEVER
3/4" CLR. BENEATH TOP
OF MASONRY UNIT
NOTE:
1. db INDICATES DIAMETER OF REINFORCEMENT.
TYP. WALL PLAN VIEW
SINGLE CURTAIN CONDITION
LOCATE VERT.
REINF. AT CENTER
OF WALL
STAGGER PLACEMENT OF
HORIZ. REINF. EA. SIDE OF
VERT. REINF.
SPACING ±2"
SPECIFIED
SEE SCH.
TOLERANCE,
TOLERANCE ± 2"
#5
#7
#6
REINF. SIZE
#3
#4
54"
63"
27"
36"
45"
f'm = 1,500 PSI
fy = 60,000 PSI
(TYP. U.N.O.)
SEE SCH.
CONTRACT LAP SPLICE
4 1/2" MIN. (#9 THROUGH #11) U.O.N.
3" MIN. (#3 THROUGH #8) U.O.N.
SEE SCH.
LAP SPLICE
0"
#8 72"
SINGLE CURTAIN CONDITION
#3 TIES @ 12" O.C. W/ 180°
HOOK EA. END
16" MIN.
(5) #5 HORIZ. BARS AS
SHOWS
CONC.
SLAB-ON-GRADE
1 1TYP. REINF.
#4 CONT.
8"
CLR.
3"
CLR.
3"
MIN.
6"
VAPOR BARRIER
AS REQ'D, SEE
ARCH. DRAWINGS
SUBGRADE
1/2" THK.
COMPRESSIBLE
MATERIAL TYP.
T.O. CONC. S.O.G.
4d
(212" MIN.)
"D" "D" "D" "D"
12d
D
135°
6d(3" MIN.)
HOOK DEVELOPMENT
LENGTH "Ldh" SEE TABLE
HOOK DEVELOPMENT
LENGTH "Ldh" SEE TABLE
"G"
"J"
TENSION DEVELOPMENT (Ldh) LENGTHS OF STANDARD HOOKS LEGEND:
d = BAR DIAMETER
D = 6d FOR #3 THROUGH #8
D = 8d FOR #9 THROUGH #11
135° STD. HOOK
6 1
180° STD. HOOK 90° STD.
HOOK
STANDARD HOOK NOTES:
1. ALL HOOK BARS SHALL EXTEND AS FAR AS POSSIBLE WITH A MINIMUM 2"
END COVER AND WITH EMBEDMENT NOT LESS THAN SHOWN ON THE SCHEDULE U.N.O. ON PLANS.
2. SEE GENERAL NOTES MINIMUM SIDE COVER.
BAR SIZE
0'-8"
0'-10"
1'-0"
1'-5"
1'-7"
1'-10"
2'-1"
3"
"J" 180° HOOK
#3
4"#4
5"#5
6"#6
7"#7
8"#8
#9
#10
"G" 90°
HOOK
113 4"
1'-114"
"D"
214"
3"
33 4"
412"
514"
6"
912"
103 4" 1'-10"
1'-712"
1'-4"
1'-2"
12"
10"
8"
6"
1'-3"
STANDARD HOOK DEVELOPMENT LENGTH "Ldh"
NORMAL WEIGHT
4000 psi
2 1
LOCATE PIPE
TRENCH SO
FOOTING WILL NOT
BE UNDERMINED
PROVIDE METAL
SLEEVES W/ I.D. 2"
LARGER THAN THE
O.D. OF THE PIPE TYP.
NO EXCAVATION
BELOW THIS LINE
BACKFILL
PIPE TYP.
9".
MIN.
4 "
3'-0"
MAX.MIN.
6 "
SPECIFICATIONS
1'-6" MIN.
BACKFILL AS PER
4"
MIN.
BOTTOM
OF FOOTING
PLACE CONCRETE FILL
AROUND SLEEVES
BEFORE POURING FOOTING.
FILL SHALL BE
SAME WIDTH AS FOOTING
POUR JOINT
FOOTING
PIPE TYP.
1 1
TYP.
1'-6".
THE FOOTING
NO PIPE SHALL
PASS THROUGH
NOTE:
1. MAXIMUM PIPE DIAMETER SHALL BE 6" AND SPACED MINIMUM 18" APART. #10
#5
#9
#8
#7
#6
BAR SIZE
#3
#4
STRENGTH
CLASS OF
LAP SPLICE
BASIC
CLASS "B"
BASIC BASIC
38"29"
62"
55"
70"
79"
48"
42"
54"
61"
31"
20"
25"
TOP
BAR
24"
15"
19"
CLASS "A"
f'c = 3,000 PSI
fy = 60,000 PSI
50"
71"
81"
91"
103"
26"
41"
33"
TOP
BAR
NOTES:
1. THE SCHEDULED LAP SPLICE LENGTHS ARE FOR EITHER OF THE FOLLOWING CASES:
2. MULTIPLY LAP SPLICE LENGTHS BY 1.5 FOR CASES NOT MEETING THE CONDITIONS AS DESCRIBED IN NOTE 1.
3. USE CLASS "B" SPLICES FOR VERTICAL & HORIZONTAL BARS TYP. (U.N.O.)
4. TOP BARS ARE HORIZONTAL BARS PLACED SO THAT 12-INCHES OR MORE OF CONCRETE IS CAST IN THE MEMBER BELOW THE BAR.
5. VALUES SHOWN ARE FOR NORMAL WEIGHT CONCRETE. IF LIGHTWEIGHT CONCRETE, MULTIPY LAP SPLICE LENGTHS BY 1.3. (REFER TO NOTE 2 FOR ANY ADDITIONAL INCREASES IN LAP SPLICE LENGTHS).
6. VALUES SHOWN ARE FOR UNCOATED GRADE 60 REINFORCEMENT.
CLEAR SPACING OF BARS BEING DEVELOPED OR SPLICED NOT LESS THAN (2db) OR 1", AND CLEAR COVER NOT LESS THAN (db).
CLEAR SPACING OF BARS BEING DEVELOPED OR SPLICED SHALL NOT BE LESS THAN (db) OR 1", CLEAR COVER NOT LESS THAN (db), AND
STIRRUPS/TIES THROUGHOUT LAP SPLICE NOT LESS THAN CODE
PRESCRIBED MAXIMUM.
1.1 1.2
LEGEND:
db - BAR DIAMETER
A - CLEAR COVER
B - CLEAR SPACING OF BARS
DIAGRAM @ STAGGERED SPLICES
BAR SPACING DIAGRAM
SPLICE OR
LAPPING BAR
B
db
SEE SCH.
LAP SPLICE
STAGGER
24" MIN.
SEE SCH.
LAP SPLICE
AA A
38"
62"
55"
70"
79"
31"
20"
25"
3 1/2" MIN. STARTER
WALL REQUIRED FOR
FOOTINGS BELOW
GRADE
FORM WORK NOT
PERMITTED BELOW
GRADE UNLESS
FULLY FORMED
FORM WORK SPECIFICATIONS
APPLICABLE
CUT BACK
SPALL TYP.
CURB OR
STARTER WALL
2x PLANKING
TYP.
STAKES NOT
PERMITTED WITHIN
FOOTING SECTION
CENTERLINE
WIDTH PER PLAN + 2"
CLEAN OUT6" MIN.
CONTINUOUS
NOTES:
1. USE THIS STARTER WALL DETAIL FOR ALL CONC. WALLS UNLESS FULLY FORMED.
2. FOUNDATION CONC. MAY BE PLACED DIRECTLY INTO NEAT EXCAVATIONS PROVIDED THE FOUNDATION TRENCH WALLS ARE STABLE AS DETERMINED BY THE SOIL ENGINEER. IN SUCH
CASE, THE MINIMUM FORM WORK SHOWN ON THE DRAWINGS IS MANDATORY TO INSURE CLEAN EXCAVATIONS IMMEDIATELY PRIOR TO AND DURING THE PLACING OF CONC.
3. CLEAN ALL PROPOSED CONC. CONTACT SURFACES AFTER CONC. HAS SET.
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set DETAILS
S-500
1" = 1'-0"TYP. MASONRY AT WALL ENDS AND CORNERS 13
1" = 1'-0"TYP. MASONRY WALL REINF. PLACEMENT DETAIL 11
1" = 1'-0"REINF. LAP SPLICE AT MASONRY WALL 7
1" = 1'-0"TYP. MASONRY WALL LINTEL REINF. 8
1" = 1'-0"TYP. EDGE AT PAVING SLAB-ON-GRADE 14
1" = 1'-0"TYP. BENDS AT REINF. 2
1" = 1'-0"TYP. PIPE & TRENCH FOOTING 1
1" = 1'-0"TYP. REINF. LAP SPLICE AT CONC. 3
3/4" = 1'-0"TYP. UNFORMED FOOTING 10
17 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
A A
AA
/7 S-501
GENERATOR
UNIT PER PLAN
(4) 3/4"⌀ SS316 HILTI KB-TZ2
W/ 4 3/4" EFFECTIVE EMBED
(ICC ESR-4266), LOCATION
PER MFR.
(N) CONC.
LEVEL PAD
(E) S.O.G.
PER PLAN
6"
DOWEL PER
TYP.
DISTANCE
MIN. 8"
EMBED
TYP.
2" CLR.
TYP.
4 3/4" EMBED.
TYP.
3" CLR.
TYP.
8" CMU WALL
PER PLAN
PAVEMENT
BY OTHERS
14" 12"
KEY TO MATCH
EXISTING
(1) #4 HOR. BAR T&B
#4 @ 16"O.C.
#5 @ 16"O.C.
S.O.G. REBAR
PER PLAN
#3 TIE W/ 180°
PER
@ 18"O.C.
/2 S-500
LAP SPLICE
PER /7 S-501
PLAN
EMBED
8" MIN.
SCHEDULE
LAP SPLICE PER
2"3"
DOWEL SIZE AND SPACING TO
MATCH SLAB REBAR W/ HILTI
HIT RE 500V3 EPOXY. INSTALL
PER ICC ESR 3814
S.O.G. PER PLAN
REBAR PER PLAN
3" CLR.
5/8" Ø WELD STUDS
HSS POST (GALV.)
PER PLAN
CP, TYP. 3/16
PL. 1/2" THK. (GALV.)
5/16
A-A
HSS POST (GALV.)
PER PLAN
PL. 1/2" THK.
(GALV.)
5"
EQ EQ
A-A
HSS POST
PL. 1/2" THK. GALV.)
5"
EQ EQ
AT CORNER
1 1/2"1 1/2"
8" MIN.
T.O. CMU WALL
1 1/2" 1 1/2"
1 1/2" 6" 1 1/2"
LOCATION A
STEEL DECK SCREW AND SIDE LAP SCHEDULE
LOCATION B LOCATION C REMARKS
ROOF
DECK
STL.
DECK
TYPE
NOTES:
1. SEE 6/- FOR DECK PROFILE.
2. FOR VERCO DECK LISTED, BASED ON IAPMO ER-2018.
3. FOR TEK SCREWS LISTED, BASED ON ITW BUILDEX ICC ESR-3223. 1/4- 20 TEK SCREW EA. BOTTOM
FLUTE (36/7) PATTERN
1/4 - 20 TEK SCREW @
12" O.C. VSC2 @ 12" O.C.
CASE ACASE BCASE C
BC A
STL BM. STL BM.
CASE E CASE D
B A
STL. BM.STL. BM.
HSS BM. PER PLAN
1/4" THK. (MIN.)
STL. PL.
HSS COL. PER
PLAN
3/16
3/16"
HSS GIRDER
PER PLAN
STL. PL.
HSS BM. PER
PLAN, TYP.
1/2" TYP.
1/2"
TYP
.
T&B
3/16
HSS BM PER PLAN
HSS GIRDER
PER PLAN
3/16
3/16
HSS COL.
PER PLAN
PER PLAN
L150x150x20GA
CONT' ANGLE
ROOF DECK PER PLAN
3/16
T&B 3/16
3/16
SECTION A-A
(E) 8" CMU WALL
(E) CMU WALL REBAR PER
3 S-200
SCHEDULE
LAP SPLICE PER
#4 DOWEL @ 16" O.C.
W/HILTI HIT HY 270 EPOXY.
INSTALL PER ICC ESR 4143
CMU WALL REBAR PER
3 S-200
8" MIN.
NOTE:
1. CONTRACT TO SCAN THE EXISTING REBAR PRIOR ANY CONSTRUCTION TO AVOID DAMAGING THE EXISTING REBAR.
PLAN VIEW
(E) 8" CMU WALL
(3) #6 VERT. REBAR
EA. FACE
CMU PILASTER
PER PLAN
#4 TIES @ 12" O.C.
EMBED
6"
4"
MIN.
4"
(E) REBAR
PER DETAIL
3 S-200
#4 DOWEL @ 12" O.C.
W/HILTI HIT HY 270
EPOXY. INSTALL PER
ICC ESR 4143
NOTE:
1. CONTRACT TO SCAN THE EXISTING REBAR PRIOR ANY CONSTRUCTION TO AVOID DAMAGING THE EXISTING REBAR.
8" CMU WALL PER PLAN"U" BAR PER
13 S-500
WALL REINF. PER
3 S-200
JAMB BAR PER
13 S-500
(3) #6 VERTICAL
REBAR EA. FACE
CMU PILASTER
PER PLAN
#4 TIES @ 12" O.C.
PER PLAN
0.302 0.306
EFFECTIVE MOMENT
OF INERTIA AT
SERVICE LOAD
I/d=(2I/e+I/g)/3
I/d+ (in4//ft) I/d- (in4//ft)
18 DECK
GAGE
BASE
METAL
THICKNESS
t (in.)
YIELD
STRENGTH
Fy (ksi)
2.9 0.0478 50
DECK
WEIGHT
W/dd (psf)
0.314 0.331
EFFECTIVE SECTION
MODULUS AT
Fy=50 ksi
S/e+ (in3//ft) S/e- (in3//ft)
2181
VERTICAL WEB
SHEAR
V/n/Ω (lb/ft)
3 1/2" 2 1/2" 6"
1 3/4"
1 1/2"
VERCO PLB™-36 OR HSB-36
36"
NOTE:
1. CONTRACTOR TO LOCATE THE EXISTING REBAR PRIOR TO CONSTRUCTION AND AVOID
DAMAGING THE EXISTING REBAR
(E) WALL REBAR
WHERE OCCURS
(E) 8" CMU WALLCLR.
3" MIN.
CLR.
3" MIN.
EDGE CLR.
6" MIN.
3"Ø MAX EXHAUST PIPE
PER MEP DRAWING
FACE SHELL, TYP.
HSS PER PLAN. SAND
BLASTED SURFACES
NON- SHRINK,
NON- METALIC GROUT
AT HSS
~
8" S. G. CMU WALL
PER PLANS &
ELEVATIONS, TYP.
#4 x 3'-6" WELDED DOWELS, TYP.
SPACING TO MATCH HORZ. REBAR
~
~
TYP. WALL REINF.
C.P.
HSS PER PLAN.
SAND BLASTED
SURFACES
NON- SHRINK,
NON- METALIC GROUT
AT HSS
~
8" S. G. CMU WALL
PER PLANS &
ELEVATIONS, TYP.
~
~
#4 x 3'-6" WELDED DOWELS, TYP.
SPACING TO MATCH HORZ. REBAR
CUT SHEL TO MATCH
UNIT WIDTH
TYP. WALL REINF.C.P.
3/4" = 1'-0"GENERATOR ANCHOR DETAIL 11" = 1'-0"S.O.G. TO EXISTING S.O.G. 7 1 1/2" = 1'-0"DETAIL 3
1" = 1'-0"TYP. STEEL DECK CONNECTION 21 1/2" = 1'-0"OVERHANG DETAIL 5
UNDERGROUND SERVICE ALERT
1-800-227-2600
YOU DIG
DAYS BEFORE
TWO WORKING
A PUBLIC SERVICE BY
DIAL
BEFORE
YOU DIG
TOLL FREE
DATE SIGNED:
NAS
NGI
ALONSI
EL ERP O EF
M.TRE
DE
S
EER
S
RGE
I
No. 3930
S NAH
AMI
R
LRAUTCRTS
U IA
ORFIAL
NTE OF
S AT
C
PUBLIC WORKS DEPARTMENT
IMPROVEMENT PLANS FOR:
REVIEWED BY:
INSPECTOR: DATE
P.E. EXP. DATE
APPROVED:
DWN BY:
CHKD BY:
RVWD BY:
DATE INITIAL
ENGINEER OF WORK
SHEETS
06.12.24 DATE
DRAWING No.
SHEET
Y.YKEDA
CK/VM
ENGINEER/ARCHITECT
IDS
1 PETERS CANYON ROAD, SUITE 130
IRVINE, CA. 92606
TEL: 949-387-8500, FAX: 949-387-0800
04092024
30% Client Review
Project# 22X005.05
60% Client Review
REVISION DESCRIPTION OTHER APPROVAL
DATE INITIAL DATE INITIAL
CITY APPROVAL
"AS BUILT"
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION
SHEET NAME:
IDS GROUP
02212024
06122024
CIP 5554
PROJECT NO.
548-3
60% Resubmittal
09182025 90% Resubmittal
38 02182026 100% CD Set & Plan Check ResponsesA
CITY OF CARLSBAD - CHINQUAPIN LIFT STATION IMPROVEMENT
03252026 Plan Check ResubmittalB
PRINCIPAL ENGINEER REC 57189 EXPIRES 12/31/27
KERI MARTINEZ
05112026 Bid Set DETAILS
S-501
1" = 1'-0"NEW CMU WALL TO EXISTING CMU WALL 12
1" = 1'-0"CMU PILASTER TO EXISTING CMU WALL 10
1" = 1'-0"CMU PILASTER TO NEW CMU WALL 11
1" = 1'-0"ROOF DECK PROFILE 4
1" = 1'-0"PIPE PENETRATION (E) CMU WALL DETAIL 13
1 1/2" = 1'-0"HSS & CMU WALL CONN. DETAIL 15
1 1/2" = 1'-0"HSS & CMU WALL CONN. DETAIL 14
18 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
1938
STANDARD ELECTRICAL SYMBOLS
AND ABBREVIATIONS
AH
JM
GG
E1
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2038
SITE ELECTRICAL PLAN
AH
JM
GG
E2
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
GRAPHIC SCALE
GRAPHIC SCALE
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2138
NEW SINGLE LINE DIAGRAM
AH
JM
GG
E3
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
GRAPHIC SCALE
PCC FOUNDATION
PER CALTRANS
EQUIPMENT
ENCLOSURE
DETAIL ES-2D
24"
24"
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2238
ELECTRICAL DEMOLITION PLANS
AH
JM
GG
E4
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
PEDESTRIAN
ACCESS MUST BE
MAINTAINED DURING
CONSTRUCTION
GRAPHIC SCALE
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
GRAPHIC SCALE
2338
GENERATOR BUILDING
ELECTRICAL PLAN - NEW LAYOUT
AH
JM
GG
E5
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2438
ELECTRICAL DETAILS 1
AH
JM
GG
E6
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2538
ELECTRICAL DETAILS 2
AH
JM
GG
E7
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
2638
CONTROLS 1
AH
JM
GG
E8
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
NOTC
NOTC
2738
CONTROLS 2
AH
JM
GG
E9
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
IMPROVEMENT PLAN FOR:
CIP 5554 548-3
CHINQUAPIN LIFT STATION IMPROVEMENTS
2838
SCHEDULES
AH
JM
GG
E10
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
5 CHINQUAPIN
LIFT STATION
5 PROJECT DIRECTORY
CONSTRUCTION OBSERVATION SCHEDULE
SHEET INDEX
DWG NO. SHEET NO. DESCRIPTION
29 L.1-0TITLE SHEET
30 L.1-1EXISTING & DEOMLITION PLAN
31 L.2-0LANDSCAPE & PLANTING NOTES
32 L.2-1PLANTING PLAN & LEGEND
33 L.2-2PLANT IMAGES
34 L.2-3PLANTING DETAILS
35 L.3-1IRRIGATION PLAN
36 L.3-2IRRIGATION LEGEND, CALCS, & DETAILS
37 L.3-3IRRIGATION DETAILS
38 L.3-4IRRIGATION DETAILS
CONTINUED LANDSCAPE MAINTENANCE PROVIDED BY:
CITY OF CARLSBAD
HOLD HARMLESS & INDEMNIFICATION CLAUSE
CONTRACTOR AGREES TO ASSUME SOLE RESPONSIBILITY FOR JOB SITE
CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS
REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO
NORMAL WORKING HOURS, AND THAT THE CONTRACTOR SHALL DEFEND,
INDEMNIFY, AND HOLD THE OWNER/DEVELOPER, THE COUNTY/ CITY OF
LOCAL JURISDICTION AND THE LANDSCAPE ARCHITECT AND IT'S
CONSULTANTS HARMLESS FROM ANY AND ALL LIABILITY REAL OR ALLEGED
IN CONNECTION WITH THE PERFORMANCE OF WORK ON THIS PROJECT,
EXCEPTING FOR LIABILITY ARISING FROM SOLE NEGLIGENCE OF THE
OWNER/DEVELOPER, COUNTY/ CITY OF LOCAL JURISDICTION AND THE LANDSCAPE ARCHITECT AND IT'S CONSULTANTS.
IRRIGATION OBSERVATIONS:
1. PRE-CONSTRUCTION CONFERENCE
2. MAINLINE/VALVE LAYOUT
3. PRESSURE LINE/WIRING INSTALLATION AND TESTING
4. LATERAL LINE AND SPRINKLER INSTALLATION
5. COVERAGE TEST
7. FINAL PUNCH WALK
PLANTING OBSERVATIONS:
1. FINISH GRADING
2. SOIL PREPARATION & WEED-ABATEMENT
3. TREE AND SHRUB LAYOUT
4. PLANT MATERIAL REVIEW
5. TREE AND SHRUB LOCATIONS (IN THEIR CONTAINERS)
6. FINAL GRADE PRIOR TO MULCHING OR SEEDING
7. FINAL PUNCH WALK
90-DAY MAINTENANCE OBSERVATIONS
1. 90-DAY FINAL PUNCH WALK
CONTRACTOR MUST BE ON SITE FOR ALL OBSERVATIONS.
AT THEIR DISCRETION, THE LANDSCAPE ARCHITECT MAY WAIVE OBSERVATIONS AND MAY INSTEAD REQUEST DIGITAL PHOTOS FROM THE CONTRACTOR.
NOTIFICATION TIME
7 DAYS
48 HOURS
48 HOURS
48 HOURS
48 HOURS
7 DAYS
NOTIFICATION TIME
48 HOURS
48 HOURS
48 HOURS
48 HOURS
48 HOURS
48 HOURS
7 DAYS
NOTIFICATION TIME
7 DAYS
CLIENT:
CITY OF CARLSBAD
PROJECT MANAGER: SEAN B. DIAZ, PE
E-MAIL: [email protected]
442-200-7222
LANDSCAPE ARCHITECT:
IN-SITE LANDSCAPE ARCHITECTURE, INC.
2907 SHELTER ISLAND DRIVE #105-417
SAN DIEGO, CA 92106
619.795.7603
TIM JACHLEWSKI
EMAIL: [email protected]
ALEX KOUTZOUKIS
EMAIL: [email protected]
PHONE: 714-519-1027
ARCHITECTURAL:
IDS GROUP
PROJECT MANAGER: ANNIE BACTOL
EMAIL: [email protected]
949-387-8500 EXT. 146
BUILDING:
IDS GROUP
CONTACT: JOHN SILBER
EMAIL: [email protected]
949.387.8500 EXT.154
STRUCTURAL:
IDS GROUP
CONTACT: VICTOR MERCADO
EMAIL: [email protected]
949.387.8500 ext. 112
ELECTRICAL:
GERRY GREEN INC.
CONSULTING ELECTRICAL ENGINEERS
CONTACT: GERRY GREEN
EMAIL:[email protected]
619.962.2356
PLUMBING:
IDS GROUP
CONTACT: RON MAGNO
EMAIL: [email protected]
949.387.8500 EXT. 417
TITLE SHEET
29 L.1-0
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
1 2
2 2
2 2
2 3
3 3
4 4
4 5
SYMBOL
DEMOLITION LEGEND
DESCRIPTION
LIMIT OF DEMOLITION WORK
EXISTING RHUS INTEGRIFOLIA
TO BE REMOVED
APPROX. QTY
1 NOTE: CONTRACTOR SHALL FIELD VERIFY
ALL QUANTITIES PRIOR TO BIDDING
AND CONSTRUCTION
6 EXISTING STRELITZIA REGINAE
TO BE REMOVED
3 EXISTING PENNISETUM
TO BE REMOVED
3 EXISTING LIMONIUM PEREZII
TO BE REMOVED
EXISTING ICE PLANT
TO BE REMOVED
46 SQ FT
EXISTING ANNUAL
NON-NATIVE GRASSES,
GROUNDCOVERS, & MULCH
TO BE REMOVED
498 SQ FT
1 2
3 4
5 6
EXISTING ATRIPLEX TO BE
CUT TO WITHIN 12" OF THE
GROUND AND ALLOWED TO
GROW BACK
164 SQ FT
SYMBOL
EXISTING LEGEND
DESCRIPTIONAPPROX. QTY
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
EXISTING CONDITIONS & DEMOLITION PLAN
CARLSBAD BOULEVARD S-21
METAL PICKET FENCE /
GUARD RAIL TO REMAIN
EXISTING METAL
ACCESS HATCH
DOORS
EXISTING
ASPHALT
PAVING
EXISTING
CONCRETE PAVING
TO REMAIN
VEHICULAR CURB RAMP
EXISTING
SIDEWALK
EXISTING
POLE LIGHT
EXISTING
ASPHALT
PAVING
EXISTING
GENERATOR
ENCLOSURE
TO BE REMOVED
REFER TO
ARCHITECTS
DOCUMENTS
EXISTING
WET
WELL
EXISTING
POLE LIGHT
TO REMAIN
SIDEWALK
ON BRIDGE
EXISTING
CONCRETE
BRIDGE
EXISTING
TRAIL HEAD
CARLSBAD BLVD RIGHT OF WAY LIMIT LINE
DEMOLITION NOTES
1. QUANTITIES ARE FOR CONVENIENCE ONLY AND SHALL BE
FIELD VERIFIED BY CONTRACTOR ON SITE.
2. TREES AND SHRUBS SCHEDULED TO BE REMOVED SHALL BE
LEGALLY DISPOSED OF OFF-SITE. STUMPS AND ROOT MASSING
SHALL BE REMOVED OR GROUND OUT TO A DEPTH SUFFICIENT
ENOUGH FOR NEW PLANTINGS TO NOT BE IMPEDED. STUMPS,
ROOT MASSING, AND/ OR STUMP GRINDINGS SHALL BE
LEGALLY DISPOSED OF OFF-SITE AND THE VOID SHALL BE
FILLED WITH TOPSOIL TO MEET GRADE.
3. REFER TO PLANTING SPECIFICATIONS FOR UTILITY
PROTECTION.
DEMOLITION LIMIT OF WORK
EXISTING BACKFLOW PREVENTION
DEVICE ENCLOSURE TO BE
REMOVED AND RELOCATED
REFER TO IRRIGATION SERIES FOR
FUTURE LOCATION
DEMOLITION LIMIT OF WORK
30 L.1-1
DEMOLITION PLAN
6 EXISTING ATRIPLEX TO
REMAIN. CUT DOWN TO
WITHIN 12" OF THE
GROUND AND ALLOW
TO REGROW
6 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
LANDSCAPE NOTES
1. THE WORK SHALL BE CONSTRUCTED IN ACCORDANCE WITH THE CONTRACT
DOCUMENTS INCLUDING THE PLANS, SPECIAL PROVISIONS, THE CITY'S IRRIGATION AND LANDSCAPE STANDARD DRAWINGS; THE CITY'S APPROVED
MATERIALS LIST, THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION, AND THESE STANDARD PLANTING NOTES.
2. FOR CAPITAL IIMPOROVEMENT PROJECTS, THE CONTRACTOR SHALL REQUEST INSPECTIONS THROUGH THE PROJECT CONSTRUCTION MANAGER 24 HOURS IN ADVANCE. ON LAND DEVELOPMENT PROJECTS, THE CONTRACTOR SHALL
REQUEST AN INSPECTION DIRECTLY THROUGH THE ASSIGNED LANDSCAPE
INSPECTOR OR CALL THE CITY OF CARLSBAD LANDSCAPE INSPECTOR (760)436-7327 TO SCHEDULE INSPECTIONS. IF THE WORK IS NOT READY FOR
INSPECTION ON THE SCHEDULED DATE AND TIME, THE CONTRACTOR SHALL RESCHEDULE THE INSPECTION AS ABOVE. THE CITY MAY CHARGE THE
CONTRACTOR FOR RESCHEDULED INSPECTIONS AND WITHHOLD FURTHER
INSPECTIONS UNTIL SUCH TIME AS THE CONTRACTOR PAYS THE
RE-INSPECTION FEE.
3. PLANTING INSPECTIONS ARE REQUIRED FOR THE FOLLOWING:
A. TREE PLANTING PIT PERCOLATION TESTS (BOTH FILLS).
B. PLANT MATERIAL LAYOUT PRIOR TO PLANTING.
C. PLANT MATERIAL QUALITY PRIOR TO PLANTING.
D. AMENDMENT VERIFICATION (PRIOR TO APPLICATION)
E. PLANT MATERIAL INSTALLATION.
F. FINAL PLANT MATERIAL INSPECTION (PUNCH LIST DEVELOPED).
G. FINAL IRRIGATION AND LANDSCAPE PUNCH LIST COMPLETION INSPECTION.
4. PRIOR TO INSTALLING PLANT MATERIAL, THE CONTRACTOR SHALL CONTROL
WEEDS BY WATERING FOR THREE WEEKS TO ADEQUATELY GERMINATE THE
SEEDBED AND THEN REMOVE THE WEEDS USING HAND / MECHANICAL
METHODS BEFORE PLANTING (NO HERBICIDES SHALL BE USED AT THIS PROJECT).
5. SOIL SAMPLES FOR AMENDMENT TESTING SHALL BE TAKEN AFTER
COMPLETION OF GRADING AND PRIOR TO WEED CONTROL AND SOIL
PREPARATION AT A MINIMUM OF THREE LOCATIONS APPROVED BY THE PUBLIC WORKS DEPARTMENT. TESTS SHALL BE PERFORMED BY AN APPROVED LABORATORY. TESTS PERFORMED SHALL INCLUDE, BUT ARE NOT LIMITED TO:
ORGANIC MATTER CONTENT, N.P.K., PH, E.C., AND PERCENT SILT, SAND, & CLAY. RECOMMENDATIONS SHALL BE BASED ON COASTAL SAGE SCRUB NATIVE PLANTS AND NOT ORNAMENTAL HORTICULTURAL PLANTS. TEST
RESULTS AND APPLICATION RECOMMENDATIONS SHALL BE SUBMITTED TO THE PUBLIC WORKS DEPARTMENT PRIOR TO APPLICATION OF AMENDMENTS.
AMENDMENTS SHALL BE APPLIED PURSUANT TO THE LABORATORY AND MANUFACTURERS RECOMMENDATIONS. THE LABORATORY SHALL PROVIDE NON-CHAMICAL, ORGANIC RECOMMENDATIONS ONLY FOR THIS PROJECT.
6. PERCOLATION TESTS SHALL BE PERFORMED ON ALL TREE PLANTING PITS FOR 15 GALLON AND LARGER TREES PRIOR TO HARDSCAPE INSTALLATION. PITS SHALL BE FILLED WITH 18 INCHES OF WATER AND ALLOWED TO COMPLETELY DRAIN. PITS SHALL THEN BE FILLED WITH 12 INCHES OF WATER AND ALLOWED TO DRAIN. THE SECOND FILL MUST DRAIN AT A MINIMUM RATE OF ONE INCH PER HOUR, FOR FOUR HOURS.
7. TREE WELL DRAIN SYSTEMS SHALL BE INSTALLED PURSUANT TO CITY OF CARLSBAD STANDARD DRAWINGS WHEN PERCOLATION TESTS FAIL.
8. THE CONTRACTOR SHALL PROVIDE POSITIVE DRAINAGE IN ALL LANDSCAPE AREAS.
9. TREES SUPPLIED TO THE PROJECT SHALL MEET THE FOLLOWING MINIMUM STANDARDS:
A. SPECIAL PROVISIONS.
B. TREES SHALL HAVE A STRAIGHT TRUNK WITH A SYMMETRICAL CROWN.
C. TREES SHALL HAVE A SUBSTANTIAL, SINGLE, CENTRAL LEADER.
D. TREE BARK SHALL NOT BE DISCOLORED, SUNKEN, OR SWOLLEN, AND SHALL BE FREE OF CUTS, SCRAPES, OR OTHER DAMAGE.
E. TREES SHOWING GALLERIES, SUN SCALD, OR FROST DAMAGE WILL NOT BE ACCEPTED.
F. THE CALIPER OF THE TREE SHALL BE IN PROPORTION TO THE ROOTBALL.
G. TREES WITH GIRDLING ROOTS WRAPPING AROUND THE TRUNK OR OTHERWISE ROOTBOUND WILL NOT BE ACCEPTED.
H. TREE TRUNKS MORE THAN 10 PERCENT OFF CENTER WILL NOT BE ACCEPTED.
I. TREES SHALL BE FREE OF CROSSING BRANCHES AND BRANCHES GROWING TOO CLOSE TO ONE ANOTHER.
J. FRESHLY PRUNED TREES WILL NOT BE ACCEPTED.
10.TREES SHALL NOT BE PRUNED UNLESS OTHERWISE APPROVED BY THE PUBLIC WORKS DEPARTMENT.
11.MAINTENANCE OF IMPROVEMENTS ON CAPITAL IMPROVEMENT PROJECTS
STREETSCAPES - THE CITY WILL ASSUME MAINTENANCE OF ALL IRRIGATION
AND LANDSCAPING UPON SUCCESSFUL COMPLETION BY THE CONTRACTOR
AND ACCEPTANCE BY THE CITY OF THE FINAL IRRIGATION AND LANDSCAPE
PUNCH LIST AND COMPLETION OF THE FINAL PROJECT PUNCH LIST AND RECEIPT OF END OF PROJECT SUBMITTALS. THE CONTRACTOR, AT ITS
EXPENSE, SHALL PERFORM ALL IRRIGATION AND LANDSCAPE MAINTENANCE UNTIL SUCH TIME AS THESE CONDITIONS ARE MET.
12.THE CONTRACTOR WILL BE NOTIFIED BY THE CITY IMMEDIATELY UPON
DISCOVERY OF DEFECTS IN IRRIGATION AND LANDSCAPE MATERIALS AND
WORKMANSHIP AND THE CONTRACTOR SHALL TAKE IMMEDIATE ACTION, AS DEMANDED BY THE CITY, TO REMEDY SAID DEFECTS. FAILURE OF THE
CONTRACTOR TO RESPOND WITHIN THE REQUIRED TIME SHALL BE CAUSE FOR THE CITY TO SUSPEND THE 60-DAY MAINTENANCE PERIOD UNTIL ALL IDENTIFIED DEFICIENCIES ARE ADDRESSED AND APPROVED BY THE CITY.
THE ABOVE REQUIREMENTS ARE IN ADDITION TO ANY WARRANTY REQUIREMENTS
SET FORTH IN THE
CONTRACT DOCUMENTS.
ROUTINE MAINTENANCE SHALL INCLUDE BUT NOT BE LIMITED TO:
A. REGULAR MONITORING, ADJUSTMENT, AND REPAIR OF THE IRRIGATION SYSTEM.
B. APPROPRIATE WATERING OF PLANT MATERIAL.
C. REGULAR WEEDING.
D. PROMPT REPLACEMENT OF DEAD, DYING OR DAMAGED PLANT MATERIAL.
E. FILLING AND COMPACTING SETTLED TRENCHES AND ERODED AREAS.
F. DAILY (SEVEN DAYS PER WEEK) REMOVAL AND DISPOSAL OF TRASH, LITTER, AND FOREIGN DEBRIS.
G. NECESSARY PEST CONTROL BY A LICENSED PEST CONTROL
APPLICATOR. (USING NON-CHEMICAL / NON-PESTICIDE / NON-HERBICIDE
METHODS ONLY FOR THIS PROJECT)
H. FERTILIZING AS NECESSARY TO MAINTAIN PLANT MATERIAL IN A HEALTHY, VIGOROUS CONDITION. (USING NON-CHEMICAL / ORGANIC FERTILIZERS ONLY IF NECESSARY).
I. REGULAR CLEANING OF DRAINAGE STRUCTURES WITHIN THE SITE.
J. PROPER TRIMMING OF SHRUBS TO LEAVE THEM IN A NATURAL FORM TYPICAL OF THE PARTICULAR PLANT. POODLING, BOXING, OR BALLING OF SHRUBS IS NOT PERMITTED.
K. MAINTENANCE OF ALL APPURTENANT IMPROVEMENTS INCLUDED IN THE PROJECT.
PLANTING NOTES
1.ALL LANDSCAPE AND IRRIGATION SHALL CONFORM TO THE DESIGN GUIDELINES
AND THE DEVELOPMENT STANDARDS OF THE CITY OF CARLSBAD, AND ALL OTHER LANDSCAPE RELATED CITY AND REGIONAL STANDARDS.
2. THESE PLANS WERE PREPARED USING THE SURVEY AND BASE INFORMATION
PROVIDED BY THE CITY OF CARLSBAD (NEIL IRANI) BASIS OF COORDINATES AND ELEVATIONS - NAD 83 (1991.35 EPOCH), THE CONTRACTOR IS RESPONSIBLE
FOR VERIFYING THE ACCURACY OF THE PLANS COMPARED TO ACTUAL FIELD CONDITIONS PRIOR TO ORDERING MATERIALS AND BEGINNING WORK. IF THERE
ARE DISCREPANCIES BETWEEN THE PLANS AND FIELD CONDITIONS, THE
CONTRACTOR SHALL NOTIFY THE LANDSCAPE ARCHITECT AND CITY OF CARLSBAD TO WORK OUT A SOLUTION AGREEABLE TO THE CITY OF CARLSBAD.
IF THE CONTRACTOR FAILS TO NOTIFY THE LANDSCAPE ARCHITECT AND CITY
OF CARLSBAD OF THE DISCREPANCIES PRIOR TO BEGINNING WORK, THE
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY ADDITIONAL LABOR AND
MATERIALS AS DIRECTED BY THE LANDSCAPE ARCHITECT OR CITY OF
CARLSBAD TO RESOLVE SUCH DISCREPANCIES AT NO ADDITIONAL COST TO THE CITY OF CARLSBAD.
3. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING THE LOCATION OF ALL UTILITIES PRIOR TO ORDERING MATERIALS AND BEGINNING WORK. THE
CONTRACTOR SHALL CLEARLY MARK ALL UTILITIES AND SHALL BE RESPONSIBLE FOR PRESERVING ALL UTILITIES THROUGHOUT CONSTRUCTION.
THE CONTRACTOR SHALL ASSUME FULL RESPONSIBILITY FOR REPAIRING DAMAGED UTILITIES AT NO ADDITIONAL COST TO CITY OF CARLSBAD.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIRING OR REPLACING ANY
EQUIPMENT AND MATERIALS DAMAGED DURING CONSTRUCTION WITHIN OR OUTSIDE THE PROJECT LIMIT OF WORK.
5. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND VERIFYING ALL
CONDUIT AND IRRIGATION SLEEVES WITH OTHER CONSTRUCTION TRADE CONTRACTORS.
6. THE CONTRACTOR SHALL PROTECT ALL TREES AND THE DRIPLINE AREA OF ALL
TREES FROM FROM STOCKPILING, MATERIAL STORAGE, EQUIPMENT, VEHICLE
PARKING, DRIVING, CHEMICALS, RUNOFF, EXCESS WATER OR ANY OTHER CIRCUMSTANCE THAT WOULD INJURE OR KILL THE TREE. THE CONTRACTOR
SHALL BE RESPONSIBLE FOR WATERING THE TREES DURING THE COURSE OF CONSTRUCTION. ANY TREES THAT ARE DAMAGED OR KILLED SHALL BE
REPLACED BY THE CONTRACTOR WITH A NEW TREE OF EQUAL SPECIES AND SIZE.
7. THE PLANTING PLAN IS DIAGRAMMATIC. ALL PLANT QUANTITIES AND SQUARE FOOTAGES ARE APPROXIMATE AND ARE PROVIDED FOR CONVENIENCE. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING FIELD CONDITIONS AND
SHALL PROVIDE THE NECESSARY PLANTS TO FULFILL THE INTENT OF THE PLANS.
8. PRIOR TO DIGGING HOLES, CONTRACTOR SHALL LOCATE AND SET OUT ALL
PLANT MATERIAL IN BOXES/ CONTAINERS PER PLAN FOR LANDSCAPE ARCHITECT REVIEW PRIOR TO PLANTING. CONTRACTOR SHALL ADJUST PLANT
LOCATIONS, IF-NEEDED, AS DIRECTED BY LANDSCAPE ARCHITECT AND/OR CITY OF CARLSBAD PRIOR TO INSTALLATION.
9. TREES SHALL BE MAINTAINED SO THAT ALL BRANCHES OVER PEDESTRIAN WALKWAYS ARE 7 FEET ABOVE THE WALKWAY GRADE AND SO THAT ALL BRANCHES OVER VEHICULAR TRAVEL WAYS ARE 14 FEET ABOVE THE GRADE OF THE TRAVEL WAY.
10. ROOT BARRIER SHALL BE INSTALLED FOR ALL TREES WITHIN 6' OF HARDSCAPE PER DETAILS.
11. CONTRACTOR SHALL PROVIDE A 3" LAYER OF "EVERBLOOM MULCH" MANUFACTURED BY AGRI-SERVICE, INC. OR APPROVED EQUAL FOR ALL NEW PLANTING AREAS EXCEPT WHERE OTHERWISE NOTED.
12. SEE SHEET L.2-3 FOR PLANTING DETAILS.
13. REFER TO SPECIFICATIONS ON SHEETS L.2-4-L.2-7 FOR ADDITIONAL REQUIREMENTS.
LANDSCAPE & PLANTING NOTES
31 L.2-0
CALIFORNIA COASTAL COMMISSION NOTE:
NO FERTILIZERS OR PESTICIDES SHALL BE USED ON THIS PROJECT Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
PLANT SCHEDULE
SYMBOL SCIENTIFIC NAMECOMMON NAME QUANTITY SIZE SPACINGWATER USE MATURE MATURE (WUCOLS-Z3) HEIGHT WIDTH
ENCELIA CALIFORNICA BUSH SUNFLOWER165 GAL PER PLAN LOW4'-5' 3'-4' SHRUBS
ERIOGONUM FASCICULATUM CALIFORNIA BUCKWHEAT165 GAL PER PLAN LOW1'-6" 6'-8' ARTEMISIA CALIFORNICA CALIFORNIA SAGEBRUSH 6 5 GAL.
PER PLAN V LOW
1.5'-5' 4'-7'
SALVIA MELLIFERABLACK SAGE 95 GAL. PER PLAN VLOW3'-6' 3'-10'
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
PLANTING PLAN0' 2.5' 5' 10' 20'
NORTH N
PLANTING PLAN
32 L.2-1
EXISTING ATRIPLEX TO
REMAIN. CUT DOWN TO
WITHIN 12" OF THE
GROUND AND ALLOW
TO REGROW
INSTALL ROOT BARRIER
ADJACENT TO VAULT IF
ROOTS HAVE
POTENTIAL TO MIGRATE
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
ARTEMESIA CALIFORNICAERIGONUM FASCICULATURMSALVIA MELLIFERA ENCELIA CALIFORNICA 33 L.2-2
PLANT IMAGES
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
1. SHRUB
2. SET TOP OF ROOTBALL 1" ABOVE FINISH GRADE
(5 GAL. SHRUBS AND GREATER)
3. 2" MULCH MATERIAL PER PLANS, PROVIDE 3" CLEARANCE
FROM TRUNK
4. BACKFILL PER NOTES AND SPECIFICATIONS (OMIT
COMPOST BELOW 12" DEPTH)
5. 4" WATERING BERM, FIRMLY COMPACTED
6. NOT USED
7. NATIVE SOIL BACKFILL
8. SCARIFY BOTTOM AND EDGES OF PLANT PIT
SHRUB
ON LEVEL GRADE OR SLOPE
SCALE: 1" = 1'-0"
P-01
2X ROOTBALL DIAMETER
ROOTBALL
DEPTH
1. 2.
3. 4.
5. 1. HARDSCAPE/ PAVEMENT
2. 3" MULCH LAYER (1.5" FOR FLATTED GROUNDCOVER)
3. ORIGINAL GRADE
4. GRADE TRANSITIONS TO ACCOMODATE MULCH LAYER 1/2"
BELOW HARDSCAPE SURFACE
5. PLANTING MIX/ AMENDED SOIL
MULCH/ GRADE TRANSITION
AT HARDSCAPE
SCALE: 1 1/2" = 1'-0"
P-02
2. 3.
4. 24"
1 2"5.
1. 3"
1. SHRUB - TRIANGULAR SPACING UNLESS
OTHERWISE SHOWN ON PLANS
2. EDGE OF HARDSCAPE
3. DISTANCE FROM EDGE OF HARDSCAPE EQUALS 75%
OF THE ON CENTER (O.C.) SPACING
PLANT SPACING
SCALE: NONE
P-03
1. 3.
EQUAL
EQUAL
EQUAL
2. PLANTING DETAILS
34 L.2-3
7. 7.
4"
DETAIL BASED ON SAN DIEGO
REGIONAL STANDARD DEAIL
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
1" 2
SHRUB DRIP2.3
FV
METER
1" 1
SHRUB DRIP0.6
C
EL
3/4" 3/4" 1"
1"
PR
RPDA MV/FS
FV
QC
CONTROLLERCONTROLLER ELECTRICAL POCISOLATION BALL VALVEEXISTING
WATER METER
BACKFLOW PREVENTER
PER CMWD STANDARDS
PRESSURE REGULATORMASTER VALVE/FLOW SENSORDRIP CONTROL VALVEEXISTING MAINLINEPRESSURE SUPPLY LINELATERAL LINEEXISTING SLEEVE OR CONDUITSHRUB DRIPLINE TUBING FLUSH VALVEQUICK COUPLER IRRIGATION LEGEND(ABBREVIATED, SEE SHEET L.3-2 FOR FULL LEGEND) C
FV EL
METER
PR RPDA
XXXX
XXXX
GALLONS PER MINUTEWATER USE/ IRRIGATION TYPE(L=LOW, M=MEDIUM, H=HIGH)VALVE SIZE STATION NUMBER MV/FS
QC
IRRIGATION HYDROZONE
HYDROZONE #1 DRIP - LOW
PIPE SIZING CHART
0 TO 5 GPM 3/4" SCH 40 PVC PIPE
5 TO 10 GPM 1" SCH 40 PVC PIPE
10 TO 15 GPM 1-1/4" SCH 40 PVC PIPE
15 TO 25 GPM 1.5" SCH 40 PVC PIPE
NOTE:
CONTRACTOR SHALL SIZE ALL LATERAL LINES
PER PIPE SIZING CHART, IN NO INSTANCE SHALL
PIPE SIZE EXCEED DESIGNATED GPM RANGE.
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
0' 2.5' 5' 10' 20'
NORTH N
CONTRACTOR TO RECONNECT
THE EXISTING MAINLINE AND
WIRES OUTSIDE OF THE LIMIT
OF WORK TO THE PROPOSED
NEW MAINLINE AND WIRE
ROUTE. MAKE SURE THAT ALL
THE IRRIGATION ZONES
OUTSIDE OF THE LIMIT OF
WORK ARE STILL
OPERATIONAL. CONTRACTOR
SHALL AVOID DISCONNECTING
ANY OF THE EXISTING VALVES
SERVING THE EXISTING
LANDSCAPE TO REMAIN.
IRRIGATION PLAN
L.3-1
35 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
XXXX
XXXX
GALLONS PER MINUTE
WATER USE/ IRRIGATION TYPE
(L=LOW, M=MEDIUM, H=HIGH)
VALVE SIZE
STATION NUMBER
ITEM MANUFACTURERMODELDESCRIPTIONDETAIL
EXISTING IRRIGATION CONTROLLER EXISTING RAINBIRD ESP IRRIGATION CONTROLLER TO BE RELOCATED TO THE EXTERIOR WALL.
TO BE RELOCATEDCONFIRM FINAL LOCATION WITH OWNER REPRESENTATIVE PRIOR TO INSTALLATION.
EXISTING RAIN SENSOR TO BE RELOCATEDFIELD LOCATE RAIN SENSOR IN OPEN LOCATION WITH NO OBSTRUCTIONS (FULL SUN AND EXPOSED TO RAIN) INSTALL AS RECOMMENDED BY MANUFACTURER.
IF AT THE TIME OF INSTALLATION THE EXISTING CONTROLLER ET SENSOR OR CONTROLLER ARE NOT OPERATIONAL REPLACE THE EXISTING CONTROLLER AND ET SENSOR PER THE SPECIFICATION BELOW:
CONTROLLERHUNTER P2C-400/WSS-SENPRO-C WITH PCM-300/PCM-900 MODULES TO PROVIDE REQUIRED STATION QUANTITY. I-01
INDOOR MOUNTED CONTROLLER WITH WIRELESS SOLAR SYNC (SENSOR ONLY) FIELD LOCATE SOLAR SYNC ET SENSOR NOT FARTHER THAN 800' FROM CONTROLLER
IN OPEN LOCATION WITH NO OBSTRUCTIONS (FULL SUN AND EXPOSED TO RAIN) INSTALL PER MANUFACTURES SPECIFICATIONS.
120 VOLT ELECTRICAL POWER POC, VERIFY ACTUAL LOCATION IN FIELD. SEE MEP PLANS WIRE CABLE AS APPROVED IRRIGATION CONTROL WIRE #14UF AWG DIRECT BURIAL (U.L. APPROVED).
WIRE CONNECTIONS 3MDBR/Y-6 "DBY" OR "DBR" DIRECT BURY SPLICE KITS, FOR USE ON ALL WIRE CONNECTIONS.I-03 ISOLATION BALL VALVE NDSBTU OR WLT (SEE DETAILS) LINE SIZEI-04 EXISTING WATER METER TO REMAIN.
BACKFLOW PREVENTER FEBCOLF825Y 3/4" LEAD FREE REDUCED PRESSURE BACKFLOW PREVENTER WITH 3/4" WYE STRAINERI-05 PER CMWD STANDARDS V.I.T. PRODUCTSSTRONGBOX SBBC-30SSSMOOTH TOUCH ENCLOSURE
EXISTING PRESSURE REGULATOR TO BE RELOCATED
MASTER VALVEBUCKNER/SUPERIOR32001001" NORMALLY CLOSED MASTER VALVE I-06 FLOW SENSORFLOWMECQS200-15FLOWMEC FLOW SENSOR , INSTALL PER MANUFACTURER'S INSTRUCTIONSI-07 DRIP VALVES:
BID ALTERNATIVE 1:
DRIP CONTROL VALVEHUNTERICZ-101-LF-401" COMMERCIAL DRIP CONTROL ZONE KIT W/ WYE FILTER AND PR (0.3 TO 20 GPM)I-02, I-08 BID ALTERNATIVE 2:
EXISTING CONTROL VALVEIF THE EXISTING CONTROL VALVE IS OPERATIONAL & IN GOOD WORKING CONDITION,I-02, I-08 USE THE EXISTING VALVE. IF THE EXISTING VALVE DOES NOT HAVE A FILTER, INSTALL
A RAINBIRD RBY PRESSURE REGULATOR FILTER BELOW GRADE INSIDE A VALVE BOX DOWNSTREAM OF THE EXISTING VALVE.
PRESSURE REGULATOR RAINBIRD RBY PRF-075-RBY3/4" MPT REGULATES PRESSURE AT 30 PSI AND °FLOWS 0.20 TO 5.0 GPM FILTER PRF-100-RBY 1" MPT REGULATES PREASSURE AT 40 PSI AND FLOWS 3.0 TO 15.0 GPM EXISTING PRESSURE SUPPLY LINE APPROXIMATE MAINLINE LOCATION SHOWN FOR REFERENCE ONLY.
PRESSURE SUPPLY LINE2" SCH 40 PVC I-09,I-10
LATERAL LINEAS APPROVEDSCH 40 PVC I-09,I-10
EXISTING SLEEVE OR CONDUITSCH 40 PVC I-09,I-10
SUB-SURFACE SHRUB DRIPLINE
DRIPLINE TUBINGNETAFIMTECHLINE TLHCVXR5-18LANDSCAPE DRIPLINE TUBING (0.77 GPH/ 18" EMITTER SPACING) INSTALL TUBING I-11, I-12 ROWS A MAXIMUM OF 18" APART IN PLANTING AREAS. ALL TUBING SHALL BE I-14, I-15 INSTALLED 3" BELOW FINISHED SOIL GRADE W/ 9" WIRE STAKES FIVE (5) FEET ON CENTER; VERIFY THE LAYOUT AND SPACING IN THE FIELD PRIOR TO STARTING WORK. INSTALL PER DETAILS AND MANUFACTURERS SPECIFICATIONS MANUAL FLUSH VALVEMANUAL FLUSH VALVEI-16
QUICK COUPLER VALVE HUNTER HQ44 - LRC-AWHQ VALVE, LOCKING RUBBER YELLOW COVER, ACME KEY SOCKET, I-02, I-13
ANTI-ROTATION WINGS
IRRIGATION LEGEND (POTABLE WATER)
CFV
EL
FV
FV
METER
NO SYMBOLNO SYMBOLNO SYMBOL
PR RPDAMV/FS
QC
STATIC WATER PRESSURE:TO BE CONFIRMED
PRESSURE LOSS CALCULATION
WORST CASE VALVE NO: 2
WORST CASE VALVE SIZE:1"
WORSE CASE VALVE GPM:2.3
A. TOTAL LATERAL SYSTEM LOSS:2
PIPEPIPEPSI
MAINLINESECTION TYPESIZE
LENGTHGPM
LOSS
A
SCH 401"75'2.30.21
B. TOTAL MAINLINE SYSTEM LOSS:0.21
MISCELLANEOUS LOSS/ GAIN
WATER METER:1
BACKFLOW PREVENTER10
MASTER CONTROL VALVE/ FLOW SENSOR:
1.8 BALL VALVE(S)0.5
CONTROL VALVE3.0
HEAD LOSS/ GAIN IN SYSTEM (ELEVATION X 0.433 = PSI 0.9 C. TOTAL MISC. LOSS/ GAIN17.2
D. TOTAL SYSTEM LOSS/ GAIN (A+B+C)19.4
E. FITTING LOSSES (15% OF TOTAL LOSSES)2.9
F.MIN. REQUIRED PRESSURE AVALIABLE AT HEAD
40 G. DESIGN PRESSURE (D+E+F)62.3
PRESSURE LOSS CALCULATIONS
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
“I AM FAMILIAR WITH THE REQUIREMENTS FOR LANDSCAPE
AND IRRIGATION PLANS CONTAINED IN THE CITY OF
CARLSBAD’S LANDSCAPE MANUAL AND WATER EFFICIENT
LANDSCAPE REGULATIONS. I HAVE PREPARED THIS PLAN IN
COMPLIANCE WITH THOSE REGULATIONS AND THE
LANDSCAPE MANUAL AND AGREE TO COMPLY WITH ALL
REQUIREMENTS WHEN SUBMITTING CONSTRUCTION
DOCUMENTS. I CERTIFY THAT THE PLAN IMPLEMENTS THOSE
REGULATIONS TO PROVIDE EFFICIENT USE OF WATER."
1. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING THE ACCURACY OF THE PLANS COMPARED TO ACTUAL FIELD CONDITIONS PRIOR TO ORDERING MATERIALS AND BEGINNING WORK. IF THERE ARE DISCREPANCIES BETWEEN THE PLANS AND FIELD CONDITIONS, THE CONTRACTOR SHALL NOTIFY THE OWNER TO WORK OUT A SOLUTION AGREEABLE TO THE OWNER. IF THE CONTRACTOR FAILS TO NOTIFY THE OWNER OF THE DISCREPANCIES
PRIOR TO BEGINNG WORK, THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY ADDITIONAL LABOR AND MATERIALS AS DIRECTED BY THE OWNER TO RESOLVE SUCH DISCREPANCIES AT NO ADDITIONAL COST TO THE OWNER.
2. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING THE LOCATION OF ALL UTILITIES PRIOR TO ORDERING MATERIALS AND BEGINNING WORK. THE CONTRACTOR SHALL CLEARLY MARK ALL UTILITIES AND SHALL BE RESPONSIBLE FOR PRESERVING ALL UTILITIES THROUGHOUT CONSTRUCTION. THE CONTRACTOR SHALL ASSUME FULL RESPONSIBILITY FOR REPAIRING DAMAGED UTILITIES AT NO ADDITIONAL COST TO OWNER.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIRING OR REPLACING ANY EQUIPMENT AND MATERIALS DAMAGED DURING CONSTRUCTION WITHIN OR OUTSIDE THE PROJECT LIMIT OF WORK.
4. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND VERIFYING ALL CONDUIT AND IRRIGATION SLEEVING WITH OTHER CONSTRUCTION TRADE CONTRACTORS.
5. THE LANDSCAPE IRRIGATION SYSTEM SHALL BE DESIGNED AND MAINTAINED TO PREVENT SPRAY ON STRUCTURES. FIELD ADJUST ALL SPRINKLERS TO ELIMINATE OVERSPRAY ONTO BUILDINGS, STRUCTURES, WALLS, SIDEWALKS, DRIVEWAYS, OR HARDSCAPE.
6. OBTAIN A STATIC WATER PRESSURE READING AT THE POINT-OF-CONNECTION PRIOR TO PROCEEDING WITH INSTALLATION. IF THE WATER PRESSURE FOUND IS DIFFERENT THAN SHOWN ON PLANS, CONTRACTOR SHALL NOTIFY LANDSCAPE ARCHITECT OF RECORD FOR FURTHER INSTRUCTIONS.
7. IRRIGATION PLAN IS DIAGRAMMATIC. CONTRACTOR IS RESPONSIBLE FOR INSTALLING THE IRRIGATION SYSTEM PER MANUFACTURER'S RECOMMENDATIONS AND ADJUSTING THE SYSTEM AS-NEEDED TO ACHIEVE UNIFORM COVERAGE.
8. THE “SMART” CONTROLLER SHALL PROGRAMMED PER MANUFACTURER'S INSTRUCTIONS AND SHALL BE SET TO “AUTOMATICALLY ADJUST” BASED ON WEATHER ON OR PRIOR TO DAY 60 OF THE MAINTENANCE PERIOD. THE CONTRACTOR SHALL CLOSELY MONITOR IRRIGATION AND FINE-TUNE THE CONTROLLER SETTINGS FOR EACH STATION DURING DAYS 61-90 OF THE MAINTENANCE PERIOD.
9. PROVIDE ONE COMMON AND ONE CONTROL SPARE WIRE FROM CONTROLLER TO END OF EACH PRESSURE SUPPLY MAINLINE IN EACH RUN. BUNDLE IN BOX.
10. PROVIDE WIRE SLEEVES AT EACH PRESSURE SUPPLY LINE SLEEVE PER DETAILS AND SPECIFICATIONS.
11. REDUCED PRESSURE BACKFLOW DEVICE SHALL BE CERTIFIED BY A STATE CERTIFIED BACKFLOW TESTOR.
12. REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.
IRRIGATION NOTES
IRRIGATION LEGEND, CALCS & NOTES
L.3-2
36 Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
A-3A-2A-1
BVBVQC
1. PVC SCH 40 MANIFOLD PIPE - SIZE PER PLANS (LOCATE
UNDERNEATH VALVE BOXES)
2. ELECTRIC CONTROL VALVE
3. HEAT BRAND ALL VALVE BOXES PER SPECIFICATIONS
4. PRESSURE SUPPLY MAINLINE (SIZE PER PLANS)
5. CONTROL VALVE MANIFOLD (5 VALVES MAXIMUM)
6. BALL VALVE TO MANIFOLD
7. BALL VALVE TO QUICK COUPLER
8. QUICK COUPLER - PER PLANS
MANIFOLD CONFIGURATION
FOR CONTROL VALVES AND QUICK COUPLERS
SCALE: N.T.S.
I-02
4. 5.
1'-6"1'-6"1'-6"1'-6"1'-6"
6. 7.
3. 2.
1. 8.
NOTE:
1 WIRE CONNECTOR SHALL BE A 3M DBY DIRECT BURY SPLICE KIT.
KIT SHALL INCLUDE A SCOTCHLOK SPRING CONNECTOR, A
POLYPROPYLENE TUBE AND A WATERPROOF SEALING GEL.
TUBE SHALL BE SUPPLIED PREFILLED WITH GEL. DIRECT BURY SPLICE KIT SHALL BE USED TO ELECTRICALLY CONNECT 2 - 3 #14 OR 2 #12 PRE-STRIPPED COPPER WIRES. LARGER WIRES OR
GREATER QUANTITIES OF WIRES SHALL REQUIRE A LARGER
APPROVED WIRE CONNECTION.
1. LOW VOLTAGE WIRES, 3 MAXIMUM
2. WIRES PASS THROUGH GROOVES IN TUBE LID TO ALLOW LID
TO CLOSE
3. CLOSE TUBE LID AFTER WIRE IS INSERTED INTO TUBE
4. POLY TUBE PRE-FILLED WITH WATERPROOF GEL
5. LOCK TABS PREVENT WIRE REMOVAL ONCE CONNECTOR IS
INSERTED
6. SCOTCHLOK ELECTRICAL SPRING CONNECTOR. WIRES
SHALL BE PRE-STRIPPED OF 1/2" OF THE INSULATION PRIOR
TO INSERTION INTO THE CONNECTOR. TWIST CONNECTOR
ONTO WIRES TO SEAT FIRMLY. SCOTCHLOK CONNECTOR
AND WIRES INSERTED INTO TUBE UNTIL THE CONNECTOR
PASSES LOCK TABS
WIRE SPLICE CONNECTION
FOR LOW VOLTAGE CONTROLLER WIRES
SCALE: N.T.S.
I-03
2 3
4 5
6 BACKFLOW PREVENTION DEVICE
PER CITY STANDARD
SCALE: N.T.S.
I-05
1. TOP OF MULCH
2. VALVE BOX WITH COVER
3. SCH. 80 PVC THD. NIPPLE, LENGTH AS REQ., 3" MIN.
4. MASTER CONTROL VALVE, SEE LEGEND FOR SPEC.
5. 30-INCH LENGTH OF WIRE, COILED - PROVIDE WATERPROOF
CONNECTION AT SPLICE
6. SCH. 80 PVC UNION
7. TRANSITION TO CORRECT PIPE DEPTH USING TWO 45 DEGREE SCH. 80 PVC ELLS
8. SCH. 80 PVC T.O.E. NIPPLE
9. PVC MAINLINE TO RCV'S, SEE SPECIFICATIONS
10. BRICK SUPPORT (4) LOCATIONS
11.3-INCH MIN. DEPTH OF 3/4-INCH WASHED GRAVEL
12. CONTROL WIRES IN SCH. 40 PVC ELECTRICAL CONDUIT
CONTINUOUS TO CONTROLLER. (AQUASEAL / VAPOR LOCK OPEN
END OF CONDUIT)
13. BRASS MAINLINE PIPE AND FITTINGS FROM BACKFLOW PER
SPECIFICATIONS
MASTER CONTROL VALVESCALE: N.T.S.
I-06
10. 6.
4"
2"
12. 13.
11. 7.
4. 8.
2. 1.5.
3. 9.
1. FLOW SENSOR - REFER TO LEGEND
2.30-INCH LENGTH OF WIRE, COILED -
PROVIDE WATERPROOF
CONNECTION AT SPLICE, MAX WIRE
DISTANCE RUN 1,000'
3.PLASTIC RECTANGULAR VALVE BOX
4. TOP OF MULCH
5. MAINLINE PIPE
6. BRICK (4) LOCATIONS 7.3-INCH MIN. DEPTH OF 3/4-INCH
WASHED GRAVEL
8. CONTROL WIRES IN SCH. 40 PVC
ELECTRICAL CONDUIT CONTINUOUS
TO CONTROLLER. (AQUASEAL /
VAPOR LOCK OPEN END OF
CONDUIT)
NOTE:
INSTALL FLOW SENSOR AS PER THE
MANUFACTURER'S RECOMMENDATIONS,
WIRE TO IRRIGATION CONTROLLER.
USE 45 DEGREE ELLS TO ACHIEVE
MAINLINE DEPTH ON THE DOWN-STREAM
SIDE OF THE FLOW SENSOR.
FLOW SENSORSCALE: N.T.S.
I-07
4. 4"
MIN.
6. 7.
2"
MIN.
1. 2.3.
5. 8.
1. EXTERIOR WALL MOUNT CONTROLLER. FASTEN TO WALL PER
MANUFACTURER'S SPECIFICATIONS. SEE LEGEND FOR
CONTROLLER INFORMATION.
2. COORDINATE AND CONNECT 110 VOLT POWER SUPPLY
(HARDWIRED OR OUTLET) WITH ELECTRICAL CONTRACTOR PRIOR
TO ORDERING.
3. LOW VOLTAGE WIRE IN GRAY PVC CONDUIT (2" DIA.) WIRE TO BE SLEEVED IN CONDUIT TO 18" BELOW GRADE.
4. SWEEP ELL.
5. FINISH GRADE
6. LOW VOLTAGE WIRE TO REMOTE CONTROL VALVES.
WALL MOUNT CONTROLLER
SCALE: N.T.S.
I-01
1. 2.
NOTE:
ALL WALL PENETRATIONS SHALL BE CLEAN
AND SHALL BE RESEALED WATER TIGHT.
INSTALL PER MANUFACTURER'S
SPECIFICATIONS.
3. 4.
5. 6.
18" 54"
ISOLATION BALL VALVEFOR PRESSURE SUPPLY LINE UP TO 2 1/2"SCALE: N.T.S.
I-04
1. 10" ROUND VALVE BOX (DO NOT CUT)
2. TOP OF MULCH (OR SOIL WHEN TURF)
3. ISOLATION BALL VALVE
4. 8" DIAMETER CL 160 PVC SLEEVE (SET ON TOP OF VALVE)
5. SLIP X MIPT PVC SCH 80 ADAPTER (2 LOCATIONS)
6. SLIP X SLIP 45 DEGREE ELL (4 LOCATIONS)
7. 3/4" GRAVEL UNDER AND AROUND VALVE BOX - FILL TO TOPOF HOLES, WRAP WITH FILTER FABRIC
8. PRESSURE SUPPLY LINE - SEE PLANS FOR SIZE
9. BRICK SUPPORT (4) LOCATIONS
1. 2.
3. 4.
5. 6.
7. 8.
9. 1. TOP OF MULCH
2.VALVE BOX WITH COVER
3. 30-INCH LENGTH OF WIRE, COILED -
PROVIDE WATERPROOF CONNECTIONAT SPLICE
4. REMOTE CONTROL VALVE ZONE KIT
XXX - WITH BASKET FILTER AND
PRESSURE REGULATOR
5. PVC SCH 80 NIPPLE, CLOSE
6. PVC SCH 80 UNION FOR SERVICING
ASSEMBLY
7. PVC SCH 40 MALE ADAPTER
8. PVC LATERAL
9. 3-INCH MIN. DEPTH OF 3/4-INCH
WASHED GRAVEL
10. BRICK (4) LOCATIONS
11. PVC PRESSURE SUPPLY MAINLINE
12. PVC SCH 80 NIPPLE
13. CONTROL WIRES IN SCH. 40 PVC
ELECTRICAL CONDUIT CONTINUOUS TO
CONTROLLER. (AQUASEAL / VAPOR
LOCK OPEN END OF CONDUIT)
DRIP CONTROL VALVE
WITH BASKET FILTER AND PRESSURE REGULATOR
SCALE: N.T.S.
I-08
5. 6.
7. 3"
MIN.
2. 3.
8. 9.10.
11. 13.
12. 12.
1. 4.
37 L.3-3
IRRIGATION DETAILS
NOTE: INSTALL BACKFLOW
ENCLOSURE PER CMWD
STANDARDS
Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
CHINQUAPIN LIFT STATION IMPROVEMENTS
IMPROVEMENT PLAN FOR:
1/2" 01"
CIP 5554 548-3
38 L ICENSED LANDSCAPE ARCHITECT
STATE OF CALIFORNIA
No. 4547
Tim Jachlewski Jr
Signature
Renewal Date
Date
11-30-27
12-18-25
2907 Shelter Island Drive #105-417
San Diego, CA 92106 619-795-7603
www.insitelandarch.com
TRENCH
BELOW HARDSCAPE
SCALE: N.T.S.
I-09
1. HARDSCAPE PAVING
2. BACKFILL MATERIAL (FREE OF ROCKS AND DEBRIS GREATER
THAN 1")
3. NON-PRESSURE LATERAL LINE SLEEVE, SEE
SPECIFICATIONS
4. CONSTRUCTION GRADE SAND
5. DETECTOR TAPE (ABOVE EACH SLEEVE)
6. PRESSURE SUPPLY LINE SLEEVE, SEE SPECIFICATIONS
7. CONTROL WIRES IN SLEEVE, SEE SPECIFICATIONS
2. 3.
4. 1.
5. 6.
7. 36"
24"
6"
WIDTH PER SPECIFICATIONS
6"
TRENCH
IN LANDSCAPE
SCALE: N.T.S.
I-10
1. MULCH
2. FINISH GRADE
3. NON-PRESSURE LATERAL LINE, SEE SPECIFICATIONS
4. BACKFILL MATERIAL (FREE OF ROCKS AND DEBRIS GREATER
THAN 1")
5. DETECTOR TAPE (ABOVE EACH PIPE)
6. PRESSURE SUPPLY LINE, SEE SPECIFICATIONS
7. CONTROL WIRES, SEE SPECIFICATIONS
8. CONSTRUCTION GRADE SAND (6" ABOVE AND BELOW
PRESSURE SUPPLY LINE)
2. 3.
4. 1.
5. 6.
7. 18" FOR MAINLINE 1.5 AND SMALLER
24" FOR MAINLINE 1.5 AND LARGER
12"
6"
WIDTH PER SPECIFICATIONS
8. 6" MIN.
SUBSURFACE DRIPLINE TUBING
BURIAL SECTION
SCALE: N.T.S.
I-11
1. 2.
3. 6.
1. TECHLINE TEE
2. TOP OF MULCH
3. SUBSURFACE DRIPLINE TUBING
4. TOP OF SOIL
5. NETAFIM INLINE DRIP EMITTER
6. TIE DOWN STAKE (NETAFIM TLS6)
NOTES:
1. PLACE TIE DOWN STAKES EVERY 3' IN SAND, 4' IN LOAM, AND 5' IN CLAY.
2. AT FITTINGS WHERE THERE IS A CHANGE OF DIRECTION SUCH AS TEES OR ELBOWS, USE TIE-DOWN STAKES ON EACH LEG OF THE CHANGE OF DIRECTION.
3. INSERTION PLOW AND TRENCHED INSTALLATIONS DO NOT REQUIRE TIE DOWN STAKES.
4. 3"3"
5. SUBSURFACE DRIPLINE TUBING
END FEED LAYOUT
SCALE: N.T.S.
I-14
2"-4"
1. PVC OR POLY SUPPLY HEADER
2. PVC DRIP MANIFOLD FROM CONTROL ZONE VALVE KIT (SIZED TO MEET
LATERAL FLOW DEMAND)
3. TECHLINE START CONNECTION MALE ADAPTER AND TEE
4. ROW SPACING. SEE IRRIGATION LEGEND.
5. TECHLINE CVRW DRIPLINE
6. PERIMTER LATERALS 2" - 4" FROM EDGE OF AREA PERIMETER
7. AREA PERIMETER
8. PVC OR POLY EXHAUST HEADER
9. MANUAL FLUSH VALVE PLUMBED TO PVC OR POLY EXHAUST HEADER
2. 1.
3. 4.
5. 6.
7. 9.
8. INSET A
12"
2. INSET A
4"-6"
SUBSURFACE DRIPLINE TUBING
CENTER FEED LAYOUT
SCALE: N.T.S.
I-12
2"-4"2.
8. 4.
5. 6.
7. 9.
8. INSET A
12"
2. INSET A
4"-6"
9. 1. PVC OR POLY SUPPLY HEADER
2. PVC DRIP MANIFOLD FROM CONTROL ZONE VALVE KIT (SIZED TO MEET
LATERAL FLOW DEMAND)
3. TECHLINE START CONNECTION MALE ADAPTER AND TEE
4. ROW SPACING. SEE IRRIGATION LEGEND.
5. TECHLINE CVRW DRIPLINE
6. PERIMTER LATERALS 2" - 4" FROM EDGE OF AREA PERIMETER
7. AREA PERIMETER
8. PVC OR POLY EXHAUST HEADER
9. MANUAL FLUSH VALVE PLUMBED TO PVC OR POLY EXHAUST HEADER
3. 1.
SUBSURFACE DRIPLINE TUBING
NOTES AND MAXIMUM LATERAL LENGTH TABLE
SCALE: N.T.S.
I-15
NOTES:
1. DISTANCE BETWEEN LATERAL ROWS AND EMITTER
SPACING TO BE BASED ON SOIL TYPE, PLANT MATERIALS
AND CHANGES IN ELEVATION. SEE DRIPLINE
INSTALLATION GUIDE FOR SUGGESTED SPACINGS.
2. LENGTH OF LONGEST DRIPLINE LATERAL SHOULD NOT
EXCEED THE MAXIMUM LENGTH SHOWN IN THE
ACCOMPANYING TABLE.
Techline HCVRX Dripline Maximum Lateral Lengths (Feet)
1. 10" ROUND VALVE BOX (DO NOT CUT)
2. SLIP X MIPT PVC SCH 40 ADAPTER (2 LOCATIONS)
3. 18" LENGTH OF POLYETHYLENE TUBING
4. CLOSED NIPPLE (2 LOCATIONS)
5. PVC SCH 40 BALL VALVE (LINE SIZE)
6. PVC SCH 40 FIPT X FIPT ELL (3 LOCATIONS)
7. 8" PVC SCH 80 RISER
8. 3/4" GRAVEL UNDER AND AROUND VALVE BOX -
FILL TO TOP OF HOLES, WRAP WITH FILTER
FABRIC
9. LATERAL LINE
MANUAL FLUSH VALVE ASSEMBLY
FOR DRIP IRRIGATION
SCALE: N.T.S.
I-16
5. 6.
2. 3.
4. 1.
7. 8.
9. IRRIGATION DETAILS
38 L.3-4
PLANSECTION
QUICK COUPLING VALVESCALE: N.T.S.
I-13
1. 10" ROUND VALVE BOX (DO NOT CUT)
2. QUICK COUPLING VALVE
3. TOP OF MULCH (OR SOIL WHEN TURF)
4. PVC SCH 80 THREADED NIPPLE
5. 1" MIP X FIP SCH 40 90 ELL (2 REQUIRED)
6. 3/4" GRAVEL UNDER AND AROUND VALVE BOX - FILL TO TOP OFHOLES, WRAP WITH FILTER FABRIC
7. PRESSURE SUPPLY LINE AND FITTINGS - SEE PLANS FOR SIZE
8. GALVANIZED (SCH 40) 36" STAKE WITH SPRINKLER TIES
9. 1" X 8" SCH 80 NIPPLE
10. 1" PVC SCH 40 STREET ELL
1.2.3.4.5.6.7. 8.
9.10. Docusign Envelope ID: CE97A834-B2A9-897F-8127-B767EC2C9675 6/3/2026
Revised 6/12/18 Contract No. 5554 Page 1 of 142
City of Carlsbad
San Diego County
California
CONTRACT DOCUMENTS,
GENERAL PROVISIONS, SUPPLEMENTAL
PROVISIONS, AND TECHNICAL SPECIFICATIONS
FOR
CHINQUAPIN LIFT STATION
IMPROVEMENTS
CONTRACT NO. 5554
BID NO. PWS27-4091UTIL
June 2, 2026
Revised 6/12/18 Contract No. 5554 Page 2 of 142
TABLE OF CONTENTS
Item Page
Notice Inviting Bids ................................ ................................ ................................ ..................... 7
Contractor's Proposal ................................ ................................ ................................ ................ 14
Listing of Manufacturers ................................ ................................ ................................ ............ 19
Bid Security Form ................................ ................................ ................................ ..................... 20
Bidder’s Bond to Accompany Proposal ................................ ................................ ..................... 21
Guide for Completing the “Designation of Subcontractors” Form ................................ .............. 22
Designation of Subcontractor and Amount of Subcontractor’s Bid Items ................................ .. 24
Bidder's Statement of Technical Ability and Experience ................................ ............................ 25
Bidder’s Certificate of Insurance for General Liability, Employers’ Liability, Automotive Liability and Workers’ Compensation ................................ ................................ ........................ 26
Bidder’s Statement Re Debarment ................................ ................................ ............................ 27
Bidder's Disclosure of Discipline Record …………………………………………… ...................... 28
Noncollusion Declaration to Be Executed by Bidder and Submitted with Bid ............................. 30
Contract Public Works ................................ ................................ ................................ ............... 31
Labor and Materials Bond ................................ ................................ ................................ ......... 38
Faithful Performance/Warranty Bond ................................ ................................ ........................ 40
Optional Escrow Agreement for Surety Deposits in Lieu of Retention ................................ ....... 42
Revised 6/12/18 Contract No. 5554 Page 3 of 142
GENERAL PROVISIONS
Section 1 Terms, Definitions Abbreviations and Symbols
1-1 Terms ................................ .......................... ................................ ..................... 45 1-2 Definitions ................................ .................... ................................ ..................... 45 1-3 Abbreviations ................................ ............... ................................ ..................... 51 1-4 Units of Measure ................................ .......... ................................ ..................... 54 1-5 Symbols ................................ ....................... ................................ ..................... 55
Section 2 Scope and Control of The Work
2-1 Award and Execution of Contract ................. ................................ ..................... 56 2-2 Assignment ................................ .................. ................................ ..................... 56 2-3 Subcontracts ................................ ................ ................................ ..................... 56 2-4 Contract Bonds ................................ ............ ................................ ..................... 57 2-5 Plans and Specifications .............................. ................................ ..................... 58 2-6 Work to be Done ................................ .......... ................................ ..................... 62 2-7 Subsurface Data ................................ .......... ................................ ..................... 63 2-8 Right-of-Way ................................ ................ ................................ ..................... 63 2-9 Surveying ................................ ..................... ................................ ..................... 63 2-10 Authority of Board and Engineer .................. ................................ ..................... 64 2-11 Inspection ................................ .................... ................................ ..................... 65
Section 3 Changes in Work
3-1 Changes Requested by the Contractor ........ ................................ ..................... 66 3-2 Changes Initiated by the Agency .................. ................................ ..................... 66 3-3 Extra Work ................................ ................... ................................ ..................... 67 3-4 Changed Conditions ................................ .... ................................ ..................... 70 3-5 Disputed Work ................................ ............. ................................ ..................... 71
Section 4 Control of Materials
4-1 Materials and Workmanship ......................... ................................ ..................... 77 4-2 Materials Transportation, Handling and Storage ................................ ................ 81
Section 5 Utilities
5-1 Location ................................ ....................... ................................ ..................... 82 5-2 Protection ................................ .................... ................................ ..................... 82 5-3 Removal ................................ ...................... ................................ ..................... 83 5-4 Relocation ................................ .................... ................................ ..................... 83 5-5 Delays ................................ .......................... ................................ ..................... 84 5-6 Cooperation ................................ ................. ................................ ..................... 84
Section 6 Prosecution, Progress and Acceptance of the Work 6-1 Construction Schedule and Commencement of Work ................................ ........ 85 6-2 Prosecution of Work ................................ ..... ................................ ..................... 87 6-3 Suspension of Work ................................ ..... ................................ ..................... 90 6-4 Default by Contractor ................................ ... ................................ ..................... 90 6-5 Termination of Contract................................ ................................ ..................... 91 6-6 Delays and Extensions of Time .................... ................................ ..................... 91 6-7 Time of Completion ................................ ...... ................................ ..................... 92 6-8 Completion, Acceptance, and Warranty ....... ................................ ..................... 93 6-9 Liquidated Damages ................................ .... ................................ ..................... 94 Revised 6/12/18 Contract No. 5554 Page 4 of 142
6-10 Use of Improvement During Construction .... ................................ ..................... 95
Section 7 Responsibilities of the Contractor
7-1 Contractor’s Equipment and Facilities .......... ................................ ..................... 96 7-2 Labor ................................ ........................... ................................ ..................... 96 7-3 Liability Insurance ................................ ........ ................................ ..................... 96 7-4 Workers' Compensation Insurance .............. ................................ ..................... 96 7-5 Permits ................................ ........................ ................................ ..................... 97 7-6 The Contractor’s Representative .................. ................................ ..................... 98 7-7 Cooperation and Collateral Work ................. ................................ ..................... 99 7-8 Project Site Maintenance ............................. ................................ ................... 100 7-9 Protection and Restoration of Existing Improvements ................................ ...... 103 7-10 Public Convenience and Safety ................... ................................ ................... 104 7-11 Patent Fees or Royalties .............................. ................................ ................... 111 7-12 Advertising ................................ ................... ................................ ................... 112 7-13 Laws to be Observed ................................ ... ................................ ................... 112 7-14 Antitrust Claims ................................ ............ ................................ ................... 112
Section 8 Facilities for Agency Personnel
8-1 General ................................ ........................ ................................ ................... 113
Section 9 Measurement and Payment
9-1 Measurement of Quantities for Unit Price Work ................................ ............... 114 9-2 Lump Sum Work ................................ .......... ................................ ................... 114 9-3 Payment ................................ ...................... ................................ ................... 114 9-4 Bid Items ................................ ...................... ................................ ................... 118
SUPPLEMENTAL PROVISIONS TO PARTS 2, 3, 4 AND 6 OF THE SSPWC
Part 2 Construction Materials
Section 200 Rock Materials
200-2 Untreated Base Materials ............................. ................................ ................... 122
Section 201 Concrete, Mortar and Related Materials
201-1 Portland Cement Concrete .......................... ................................ ................... 122
Section 203 Bituminous Materials
203-6 Asphalt Concrete ................................ ......... ................................ ................... 123
Section 213 Engineering Fabrics
213-5 Geotextiles and Geogrids ............................. ................................ ................... 124
Part 3 Construction Methods
Section 300 Earthwork
300-2 Unclassified Excavation ................................ ................................ ................... 125 300-12 Storm Water Pollution Prevention Plan ................................ ............................ 125
Section 301 Treated Soil, Subgrade Preparation and Placement of Base Materials 301-1 Subgrade Preparation ................................ ................................ ...................... 128
Section 302 Roadway Surfacing
302-5 Asphalt Concrete Pavement ................................ ................................ ............ 128 302-15 Public Convenience and Traffic Control ................................ ........................... 129 Revised 6/12/18 Contract No. 5554 Page 5 of 142
Section 303 Concrete and Masonry Construction
303-1 Concrete Structures ................................ ................................ ......................... 130 303-5 Concrete Curbs, Walks, Gutters, Cross Gutters, Alley Intersections, Access Ramps, And Driveways ................................ ................................ ....... 130
Section 306 Underground Conduit Construction
306-3 Open Trench Operations ................................ ................................ .................. 131 306-12 Backfill ................................ ................................ ................................ ............. 132 306-13 Trench Resurfacing ................................ ................................ .......................... 132
Part 4 Existing Improvements
Section 400 Protection and Restoration
400-1 General ................................ ................................ ................................ ............ 133 400-2 Permanent Survey Markers ................................ ................................ ............. 133 400-3 Payment ................................ ................................ ................................ .......... 133
Section 401 Removal
401-3 Concrete and Masonry Improvements ................................ ............................. 133
Part 6 Temporary Traffic Control
Section 601 Temporary Traffic Control for Construction and Maintenance Work Zones 601-1 General ................................ ................................ ................................ ............ 134 601-3 Temporary Traffic Control (TTC) Zone Devices ................................ ............... 134 601-4 Temporary Traffic Striping and Pavement Markings ................................ ......... 138 Revised 6/12/18 Contract No. 5554 Page 6 of 142
TECHNICAL SPECIFICATIONS
02050 Site Demolition
02960 Temporary Bypass Pumping
06621 Copolymer Lining
15610 Flow Meters
02 41 19 Selective Demolition
03 10 00 Concrete Forming and Accessories
03 20 00 Concrete Reinforcing
03 30 00 Cast-in-Place Concrete
04 22 00 Concrete Unit Masonry
05 12 00 Structural Steel
05 31 00 Steel Decking
05 12 13 Architecturally Exposed Structural Steel Framing 07 62 00 Sheet Metal Flashing and Trim
07 92 00 Joint Sealants
08 11 13 Hollow Metal Doors and Frames
08 71 00 Door Hardware
08 91 19 Fixed Louvers
09 24 00 Cement Plastering
09 91 13 Exterior Painting
09 91 23 Interior Painting
09 96 00 High Performance Coatings
26 00 00 Basic Electrical Requirements
26 05 00 Commissioning For Electrical Systems
26 05 05 Selective Demolition for Electrical
26 05 19 Low-Voltage Electrical Power Conductors And Cables 26 05 23 Control-Voltage Electrical Power Cables
26 05 26 Grounding and Bonding For Electrical Systems
26 05 29 Hangers and Supports For Electrical Systems
26 05 33 Raceways And Boxes For Electrical Systems
26 05 43 Underground System
26 05 53 Identification For Electrical Systems
26 05 73 Short Circuit, Coordination, and Arc Flash Hazard Study 26 24 13 Utility Service Entrance and Meter Pedestal
26 27 26 Wiring Devices
26 32 13 Diesel-Engine Driven Generator Sets
26 36 00 Automatic Transfer Switches
26 44 40 Motor Control Centers
26 44 42 Control Devices
40 61 13 Process Control System General Provisions
40 61 21 Process Control System Testing
40 63 43 Programmable Logic Controllers
40 67 00 Control System Panels And Racks
Revised 6/12/18 Contract No. 5554 Page 7 of 142
Documents Incorporated by Reference:
City of Carlsbad Engineering Standards, Volume 3, Standard Drawings and Specifications:
https://www.carlsbadca.gov/home/showpublisheddocument/334/637980518271200000
City of Carlsbad Engineering Standards, Volume 2, Potable and Recycled Water Standards and Approved Materials List:
https://www.carlsbadca.gov/home/showpublisheddocument/332/637980517690370000
APPENDICES
Appendix A Construction Staging Area Exhibit
Appendix B SWPPP Template
Appendix C Chinquapin Lift Station As-Builts (for reference only) Appendix D CARB Fleet Compliance Certification
Appendix E Generator Submittal
Appendix F MCC Submittal
Revised 6/12/18 Contract No. 5554 Page 8 of 142
CITY OF CARLSBAD, CALIFORNIA
NOTICE INVITING BIDS
Until 11 a.m. on August 11, 2026, the City shall accept bids via electronic format via the City of Carlsbad Electronic Bidding Site, PlanetBids , which may be accessed at https://www.carlsbadca.gov/departments/finance/contracting-purchasing, for performing the work as follows: Demolition of existing structure walls and cover, electrical control systems, cabinets and components, generator, sewer influent wet well top slab, mechanical piping and appurtenances, installation of new building walls and roof, installation of new emergency standby generator, electrical controls, motor control center, cabinets, SDGE meter pedestal, conduits, replacement of wet well top slab, lining repairs, wet well and valve vault mechanical piping and appurtenances, flow meter, plug valve s, check valves, force main piping, together with potholing, stormwater and non -stormwater pollution control , temporary traffic control and pedestrian detour, temporary sewer bypassing, excavation support systems, asphalt pavement, concrete walk, site restoration and landscaping.
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
PWS27-4091UTIL
ELECTRONIC FORMAT RECEIPT AND OPENING OF BIDS: Bids will be received in electronic format (eBids) EXCLUSIVELY at the City of Carlsbad’s electronic bidding (eBidding) site, at: Contracting & Purchasing | Carlsbad, CA (carlsbadca.gov) and are due by the date and time shown on the cover of this solicitation.
BIDDERS MUST BE PRE -REGISTERED with the City’s bidding system and possess a system-assigned Digital ID in order to submit an electronic bid.
The City’s electronic bidding (eBidding) system will automatically track information submitted to the site including IP addresses, browsers being used and the URLs from which information was submitted. In addition, the City’s bidding system will keep a history of every login instance including the time of login, and other information about the user's computer configuration such as the operating system, browser type, version, and more. Because of these security features, Bidders who disable their browsers’ cookies will not be able to log in and use the City’s bidding system.
The City’s electronic bidding system is responsible for bid tabulations. Upon the bidder’s or proposer’s entry of their bid, the system will ensure that all required fields are entered. The system will not accept a bid for which any required information is missing. This includes all necessary pricing, subcontractor listing(s) and any other essential documentation and supporting materials and forms requested or contained in these solicitation documents.
BIDS REMAIN SEALED UNTIL DUE DATE AND TIME
eBids are transmitted into the City’s bidding system via hypertext transfer protocol secure (https) mechanism using SSL 128 -256-bit security certificates issued from Verisign/Thawte which encrypts data being transferred from client to server. Bids submitted prior to the Due Date and Time are not available for review by anyone other than the submitter, who will have until the Due Date and Time to change, rescind or retrieve its bid should they desire to do so.
Revised 6/12/18 Contract No. 5554 Page 9 of 142
BIDS MUST BE SUBMITTED BY DUE DATE AND TIME
Once the deadline is reached, no further submissions are accepted into the system. Once the Due Date and Time has passed, bidders, proposers, the general public, and City staff are able to immediately see the results online. City staff may then begin reviewing the submissions for responsiveness, compliance and other issues.
RECAPITULATION OF THE WORK
Bids shall not contain any recapitulation of the Work. Conditional Bids may be rejected as being non-responsive. Alternative proposals will not be considered unless called for.
BIDS MAY BE WITHDRAWN by the Bidder prior to, but not after, the time set as Due Date and Time.
Important Note: Submission of the electronic bid into the system may not be instantaneous.
Due to the speed and capabilities of the user’s internet service provider (ISP), bandwidth, computer hardware and other variables, it may take time for the bidder’s submission to upload and be received by the City’s eBidding system. It is the bidder’s sole responsibility to ensure their bids are received on time by the City’s eBidding system. The City of Carlsbad is not responsible for bids that do not arrive by the Due Date and Time.
ELECTRONIC SUBMISSIONS CARRY FULL FORCE AND EFFECT
The Bidder, by submitting their electronic proposal, agrees to and certifies under penalty of perjury under the laws of the State of California, that the certification, forms and affidavits submitted as part of this proposal are true and correct. The bidder, by submitting its electronic bid, acknowledges that doing so carries the same force and full legal effect as a paper submission with a longhand (wet) signature. By submitting an electronic bid, the bidder certifies that the bidder has thoroughly examined and understands the entire Contract Documents (which consist of the plans and specifications, drawings, forms, affidavits and the solicitation documents), and that by submitting the eBid as its bid proposal, the bidder acknowledges, agrees to and is bound by the entire Contract Documents, including any addenda issued thereto, and incorporated by reference in the Contract Documents.
BIDS ARE PUBLIC RECORDS
Upon receipt by the City, bids shall become public records subject to public disclosure. It is the responsibility of the Bidder to clearly identify any confidential, proprietary, trade secret or otherwise legally privileged information contained within the proposal’s General references to sections of the California Public Records Act (PRA) will not suffice. If the Bidder does not provide applicable case law that clearly establishes that the requested information is exempt from the disclosure requirements of the PRA, the City shall be free to release the information when required in accordance with the PRA, pursuant to any other applicable law, or by order of any court or government agency, and the Bidder agrees to hold the City harmless for any such release of this information.
INSTRUCTIONS TO BIDDERS AND BID REQUIREMENTS
This bid and the terms of the Contract Documents and General Provisions constitute an irrevocable offer that shall remain valid and in full force for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder.
No bid will be received unless it is made on a proposal form furnished by the Purchasing Department. Each bid must be accompanied by security in a form and amount required by law.
The bidder's security of the second and third next lowest responsive bidders may be withheld Revised 6/12/18 Contract No. 5554 Page 10 of 142
until the Contract has been fully executed. The security submitted by all other unsuccessful bidders shall be returned to them, or deemed void, within ten (10) days after the Contract is awarded. Pursuant to the provisions of law (Public Contract Code section 10263), appropriate securities may be substituted for any obligation required by this notice or for any monies withheld by the City to ensure performance under this Contract. Section 10263 of the Public Contract Code requires monies or securities to be deposited with the City or a state or federally chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions of the agent in connection with the handling of retentions under this section in an amount not less than $100,000 per contract.
The City of Carlsbad may disqualify a contractor or subcontractor from participating in bidding when a contractor or subcontractor has been debarred by the City of Carlsbad or another jurisdiction in the State of California as an irresponsible bidder.
The work shall be performed in strict conformity with the plans, provisions, and specifications as approved by the City Council of the City of Carlsbad on file with the City Clerk’s Office. The specifications for the work include City of Carlsbad Technical Specifications and the 2021 Standard Specifications for Public Works Construction, Parts 2 - 8, all hereinafter designated “SSPWC”, as amended. Specification Reference is hereby made to the plans and specifications for full particulars and description of the work. The General Provisions (Part 1) to the SSPWC do not apply.
The City of Carlsbad encourages the participation of minority and women-owned businesses.
The City of Carlsbad encourages all bidders, suppliers, manufacturers, fabricators and contractors to utilize recycled and recyclable materials when available, appropriate and approved by the Engineer.
BID DOCUMENTS
The bid documents comprise the following documents which must be completed and properly executed including notarization, where indicated.
1. Contractor's Proposal
2. Bidder's Bond ( at time of Bid submit PDF copy via PlanetBids / All Bidders). Bid Bond (Original) within two (2) business days of bid Opening / three (3) Apparent Low Bidders.
3. Noncollusion Declaration
4. Designation of Subcontractor and Amount of Subcontractor’s Bid
5. Bidder's Statement of Technical Ability and Experience
6. Acknowledgement of Addendum(a)
7. Certificate of Insurance. The riders covering the City, its officials, employees and volunteers may be omitted at the time of bid submittal but shall be provided by the Bidder prior to award of this contract.
8. Bidder’s Statement Re Debarment
9. Bidder's Disclosure of Discipline Record
10. Listing of Manufacturers
11. CARB Fleet Compliance Certification (Appendix D)
12. Escrow Agreement for Security Deposits - (optional, must be completed if the Bidder wishes to use the Escrow Agreement for Security)
Revised 6/12/18 Contract No. 5554 Page 11 of 142
BIDDER’S GUARANTEE OF GOOD FAITH (BID SECURITY)
At the time of bid submission, bidders must upload and submit an electronic PDF copy of the aforementioned bid security. Whether in the form of a cashier's check, a properly certified check or an approved corporate surety bond payable to the City of Carlsbad, the bid security must be uploaded to the City’s eBidding system. Within two (2) business days after the bid opening date, the first three (3) apparent low bidders must provide the City with the original bid security.
Failure to submit the electronic version of the bid security at time of bid submission shall cause the bid to be rejected and deemed non-responsive. Only the three (3) apparent low bidders are required to submit original bid security to the City within two (2) business days after bid opening date. Failure to provide the original within two (2) business days may deem the bidder non- responsive.
ENGINEER’S ESTIMATE
All bids will be compared on the basis of the Engineer's Estimate. The estimated quantities are approximate and serve solely as a basis for the comparison of bids. The Engineer's Estimate is $1,280,000.
TIME OF COMPLETION
The Contractor shall complete the Work within the time set in the contract as defined in the General Provisions Section 6-7.
SPECIALTY CONTRACTORS:
ACCEPTABLE LICENSE TYPES
Except as provided herein a bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the City. In all contracts where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with California law. Where federal funds are involved the contractor shall be properly licensed at the time the contract is awarded. In all other cases the contractor shall state their license number, expiration date and classification in the proposal, under penalty of perjury. This invitation to bid does not use federal funds. The following classifications are acceptable for this contract: A - General Engineering.
ESCROW AGREEMENT
If the Contractor intends to utilize the escrow agreement included in the contract documents in lieu of the usual 5% retention from each payment, these documents must be completed and submitted with the signed contract. The escrow agreement may not be substituted at a later date.
OBTAINING PLANS AND SPECIFICATIONS
Sets of plans, various supplemental provisions, and Contract documents may be obtained from the City of Carlsbad website at https://www.carlsbadca.gov/departments/finance/contracting- purchasing Paper copies will not be sold.
INTENT OF PLANS AND SPECIFICATIONS
Any prospective bidder who is in doubt as to the intended meaning of any part of the drawings, specifications or other contract documents, or finds discrepancies in or omissions from the drawings and specifications may submit to the Engineer a written request for clarification or correction. Any response will be made only by a written addendum duly issued by the Engineer a copy of which will be mailed or delivered to each person receiving a set of the contract Revised 6/12/18 Contract No. 5554 Page 12 of 142
documents. No oral response will be made to such inquiry. Prior to the award of the contract, no addition to, modification of or interpretation of any provision in the contract documents will be given by any agent, employee or contractor of the City of Carlsbad except as hereinbefore specified. No bidder may rely on directions given by any agent, employee or contractor of the City of Carlsbad except as hereinbefore specified.
BIDDER’S INQUIRIES
Questions on the bid documents during the bid period shall be submitted in writing, via the eBidding website.
Questions shall be definite and certain and shall reference applicable drawing sheets, notes, details or specification sheets.
The cutoff date to submit questions is July 31, 2026, at 5 p.m. No questions will be entertained after that date.
The answers to questions submitted during the bidding period will be published in an addendum and provided to those bidding on the project no later than August 6, 2026.
REJECTION OF BIDS
The City of Carlsbad reserves the right to reject any or all bids and to waive any minor irregularity or informality in such bids.
PREVAILING WAGE TO BE PAID
The general prevailing rate of wages for each craft or type of worker needed to execute the Contract shall be those as determined by the Director of Industrial Relations pursuant to the sections 1770, 1773, and 1773.1 of the Labor Code. Pursuant to section 1773.2 of the Labor Code, a current copy of applicable wage rates is on file in the Office of the City Engineer. The Contractor to whom the Contract is awarded shall not pay less than the said specified prevailing rates of wages to all workers employed by him or her in the execution of the Contract.
The Prime Contractor shall be responsible for insuring compliance with provisions of section 1777.5 of the Labor Code and section 4100 et seq. of the Public Contracts Code, "Subletting and Subcontracting Fair Practices Act." The City Engineer is the City’s "duly authorized officer" for the purposes of section 4107 and 4107.5.
The provisions of Part 7, Chapter 1, of the Labor Code commencing with section 1720 shall apply to the Contract for work.
A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to Section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
The Prime Contractor and all subcontractors shall comply with Section 1776 of the Labor Code, which generally requires keeping accurate payroll records, verifying and certifying payroll records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776.
Revised 6/12/18 Contract No. 5554 Page 13 of 142
CALIFORNIA AIR RESOURCES BOARD (CARB) ADVANCED CLEAN FLEETS
REGULATIONS
Contractor’s vehicles with a gross vehicle weight rating greater than 8,500 lbs. and light -duty package delivery vehicles operated in California may be subject to the California Air Resources Board (CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, please see Appendix D and visit the CARB Advanced Clean Fleets webpage at https://ww2.arb.ca.gov/our- work/programs/advanced-clean-fleets.
PRE-BID MEETING
A pre-bid meeting will be held at the Carlsbad Municipal Water District office building located at 5950 El Camino Real, Carlsbad, CA on July 23, 2026, at 1 p.m.
Questions asked by Bidders at the Pre -Bid Meeting not specifically addressed within the Contract Documents shall be answered in writing and shall be sent to all Bidders present at the Pre-Bid Meeting and be posted on the online bidding portal.
UNIT PRICES AND COMPUTATION OF BIDS
All bids are to be computed on the basis of the given estimated quantities of work, as indicated in this proposal, times the unit price as submitted by the bidder.
ADDENDA
Bidders are advised to verify the issuance of all addenda and receipt thereof one day prior to bidding. Submission of bids without acknowledgment of addenda may be cause of rejection of bid.
BOND AND INSURANCE REQUIREMENTS
The Contractor shall provide bonds to secure faithful performance and warranty of the work in an amount equal to one hundred percent (100%) of the Contract price on this project. The Contractor shall provide bonds to secure payment of laborers and materials suppliers, in an amount equal to one hundred percent (100%) of the total amount payable by the terms of the contract. These bonds shall be kept in full force and effect during the course of this project and shall extend in full force and effect and be retained by the City until they are released as stated in the General Provisions section of this contract. All bonds are to be placed with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to be accompanied by the following documents:
1. An original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
2. A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.
If the bid is accepted, the City may require copies of the insurer's most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Article 10 (commencing with section 900) of Chapter 1 of Part 2 of Division 1 of the Insurance Code, within 10 calendar days of the insurer's receipt of a request to submit the statements.
Insurance is to be placed with insurers that:
1. Have a rating in the most recent Best's Key Rating Guide of at least A-:VII Revised 6/12/18 Contract No. 5554 Page 14 of 142
July 13, 2026
2. Are admitted and authorized to transact the business of insurance in the State of California by the Insurance Commissioner.
Auto policies offered to meet the specification of this contract must:
1. Meet the conditions stated above for all insurance companies.
2. Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.
Workers' compensation insurance required under this contract must be offered by a company meeting the above standards with the exception that the Best's rating condition is waived. The City does accept policies issued by the State Compensation Fund meeting the requirement for workers' compensation insurance.
The Contractor shall be required to maintain insurance as specified in the Contract. Any additional cost of said insurance shall be included in the bid price.
The award of the contract by the City is contingent upon the Contractor submitting the required bonds and insurance, as described in the contract, within twenty days of bid opening. If the Contractor fails to comply with these requirements, the City may award the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited.
BUSINESS LICENSE
The prime contractor and all subcontractors are required to have and maintain a valid City of Carlsbad Business License for the duration of the contract.
Date Graham Jordan, Deputy Clerk
Revised 6/12/18 Contract No. 5554 Page 15 of 142
CITY OF CARLSBAD
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
CONTRACTOR'S PROPOSAL
City Council
City of Carlsbad
1200 Carlsbad Village Drive
Carlsbad, California 92008
The undersigned declares he/she has carefully examined the location of the work, read the Notice Inviting Bids, examined the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto, and hereby proposes to furnish all labor, materials, equipment, and incidental services required to do all the work to complete Contract No. 5554 in accordance with the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto and that he/she will take in full payment therefore the following unit prices for each item complete, to wit (refer to Section 9-4 for bid item descriptions):
SCHEDULE “A”
Item
No. Description
Approximate
Quantity
And Unit
Unit Price
(Figures)
Total Amount
(Figures)
1 Mobilization and Preparatory
Work (not to exceed 5% of Total
Bid)
LS $___________
2 Temporary Traffic Control LS $___________
3 Preconstruction Survey LS $___________
4 Storm Water Pollution Control
(SWPPP)
LS $___________
5 Temporary Pedestrian Detour LS $___________
6 Utility Locating and Potholing LS $___________
7 Excavation Support System LS $___________
8 Demolition – Civil/Mechanical LS $___________
9 Demolition – Electrical LS $___________
10 Temporary Sewer Bypass LS $___________
Revised 6/12/18 Contract No. 5554 Page 16 of 142
Item
No. Description
Approximate
Quantity
And Unit
Unit Price
(Figures)
Total Amount
(Figures)
11 Furnish and Install Wet Well
Roof Slab and Hatch
LS $___________
12 Furnish and Install 4” DIP and
Appurtenances
LS $___________
13 Furnish and Install 6” DIP and
Appurtenances
LS $___________
14 Furnish and Install 8” SCH 80
PVC Pipe and Appurtenances
LS $___________
15 Furnish and Install 4” Plug Valve 2 EA $___________ $___________
16 Furnish and Install 6” Plug Valve 1 EA $___________ $___________
17 Furnish and Install 6” Plug Valve
(3-way)
1 EA $___________ $___________
18 Furnish and Install 6” Knife Gate
Valve
1 EA $___________ $___________
19 Furnish and Install 4” Check
Valve
2 EA $___________ $___________
20 Furnish and Install 6" Flow
Meter
1 EA $___________ $___________
21 Furnish and Install Wet Well
Liner Repairs
LS $___________
22 Furnish and Install Hatch Safety
Railing
LS $___________
23 Furnish and Install Building
Structure Expansion
LS $___________
24 Furnish and Install Electrical
Work
LS $___________
25 Generator Installation LS $___________
Revised 6/12/18 Contract No. 5554 Page 17 of 142
Item
No. Description
Approximate
Quantity
And Unit
Unit Price
(Figures)
Total Amount
(Figures)
26 Motor Control Center Installation LS $___________
27 Furnish and Install Concrete and
Curb Replacement
LS $___________
28 Furnish and Install Decorative
Concrete Walkway Replacement
LS $___________
29 Furnish and Install Asphalt
Concrete
LS $___________
30 Furnish and Install Landscaping
& Irrigation
LS $___________
Total amount of bid (in figures) for Schedule “A”: $
Total amount of bid (in words) for Schedule “A”:
The City shall determine the low bid based on the sum of Schedule “A”.
Price(s) given above are firm for 90 days after the date of bid opening.
Addendum(a) No(s). ___________________ has/have been received and is/are included in this proposal.
The Undersigned has carefully checked all of the above figures and understands that the City will not be responsible for any error or omission on the part of the Undersigned in preparing this bid.
The Undersigned agrees that in case of default in executing the required Contract with necessary bonds and insurance policies within twenty (20) days from the date of award of Contract by the City Council of the City of Carlsbad , the City may administratively authorize award of the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited.
The Undersigned bidder declares, under penalty of perjury, that the undersigned is licensed to do business or act in the capacity of a contractor within the State of California, validly licensed under license number _________________________, classification ________________ which expires on _____________________, and Department of Industrial Relations PWC registration number ___________________________________ which expires on ____________________, and that this statement is true and correct and has the legal effect of an affidavit.
A bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the Revised 6/12/18 Contract No. 5554 Page 18 of 142
City § 7028.15(e). In all contracts where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with California law.
However, at the time the contract is awarded, the contractor shall be properly licensed.
The Undersigned bidder hereby represents as follows:
1. That no Council member, officer agent, or employee of the City of Carlsbad is personally interested, directly or indirectly, in this Contract, or the compensation to be paid hereunder; that no representation, oral or in writing, of the City Council, its officers, agents, or employees has inducted him/her to enter into this Contract, excepting only those contained in this form of Contract and the papers made a part hereof by its terms; and
2. That this bid is made without connection with any person, firm, or corporation making a bid for the same work, and is in all respects fair and without collusion or fraud.
Accompanying this proposal is _____________________________ _ (Cash, Certified Check, Bond or Cashier's Check) for ten percent (10%) of the amount bid.
The Undersigned is aware of the provisions of section 3700 of the Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self - insurance in accordance with the provisions of that code and agrees to comply with such provisions before commencing the performance of the work of this Contract and continue to comply until the contract is complete.
The Undersigned is aware of the provisions of the Labor Code, Part 7, Chapter 1, Article 2, relative to the general prevailing rate of wages for each craft or type of worker needed to execute the Contract and agrees to comply with its provisions.
Revised 6/12/18 Contract No. 5554 Page 19 of 142
IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE:
(1) Name under which business is conducted _______________________________________
(2) Signature (given and surname) of proprietor ______________________________________
(3) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
IF A PARTNERSHIP, SIGN HERE:
(1) Name under which business is conducted _______________________________________
(2) Signature (given and surname and character of partner) (Note: Signature must be made by a general partner)
_________________________________________________________________________
_________________________________________________________________________
(3) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(4) Zip Code ___________________ Telephone No. _________________________________
(5) E-Mail ___________________________________________________________________
Revised 6/12/18 Contract No. 5554 Page 20 of 142
IF A CORPORATION, SIGN HERE:
(1) Name under which business is conducted _______________________________________
__________________________________________________________________________
(2) _________________________________________________________________________ (Signature)
____________________________________________________________________________ (Title)
Impress Corporate Seal here
(3) Incorporated under the laws of the State of _______________________________________
(4) Place of Business __________________________________________________________ (Street and Number)
City and State _____________________________________________________________
(5) Zip Code _____________________ Telephone No. _______________________________
(6) E-Mail ___________________________________________________________________
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE
ATTACHED
List below names of president, vice president, secretary and assistant secretary, if a corporation; if a partnership, list names of all general partners, and managing partners:
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________
____________________________________ ___________________________________ Revised 6/12/18 Contract No. 5554 Page 21 of 142
LISTING OF MANUFACTURERS
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
The Contractor shall submit this completed form with the bid to identify the products, equipment, or materials and their manufacturers proposed for use in the Work. If the Contractor elects to list products, equipment, or materials not listed in the Specifications, Plans, or Carlsbad Engineering Standards, the Contractor shall provide substantiating data to demonstrate that the substitute products, equipment, or materials are of equal quality, durability, functional character, and efficiency as determined by the Engineer . Only one manufacturer shall be listed for each item.
Item or Material Manufacturer
Flow Meter
Substitutions for products, equipment, or materials listed above shall be allowed only if submitted for approval at least two weeks prior to the Bid Due Date or, for products, equipment, or materials not listed above, in accordance with Article 4 -1.6 of the General Provisions and within 35 calendar days following Contract award.
Revised 6/12/18 Contract No. 5554 Page 22 of 142
BID SECURITY FORM
(Check to Accompany Bid)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
(NOTE: The following form shall be used if check accompanies bid.)
Accompanying this proposal is a *Certified * Cashier’s check payable to the order of City of Carlsbad, in the sum of _______________________________________ dollars ($________________), this amount being ten percent (10%) of the total amount of the bid. The proceeds of this check shall become the property of the City provided this proposal shall be accepted by the City through action of its legally constituted contracting authorities and the undersigned shall fail to execute a contract and furnish the required Performance, Warranty and Payment Bonds and proof of insurance coverage within the stipulated time; otherwise, the check shall be returned to the undersigned. The proceeds of this check shall also become the property of the City if the undersigned shall withdraw his or her bid within the period of fifteen (15) days after the date set for the opening thereof, unless otherwise required by law, and notwithstanding the award of the contract to another bidder.
_______________________________________
_______________________________________
BIDDER
_________________
*Delete the inapplicable word.
(NOTE: If the Bidder desires to use a bond instead of check, the Bid Bond form on the following pages shall be executed--the sum of this bond shall be not less than ten percent (10%) of the total amount of the bid.)
Revised 6/12/18 Contract No. 5554 Page 23 of 142
BIDDER'S BOND TO ACCOMPANY PROPOSAL
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
KNOW ALL PERSONS BY THESE PRESENTS:
That we, _______________________________________________________, as Principal, and _____________________________________, as Surety are held and firmly bound unto the City of Carlsbad, California, in an amount as follows: (must be at least ten percent (10%) of the bid amount) __________________________ for which payment, well and truly made, we bind ourselves, our heirs, executors and administrators, successors or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THE FOREGOING OBLIGATION IS SUCH that if the proposal of the above-bounden Principal for:
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
in the City of Carlsbad, is accepted by the City Council, and if the Principal shall duly enter into and execute a Contract including required bonds and insurance policies within twenty (20) days from the date of award of Contract by the City Council of the City of Carlsbad, being duly notified of said award, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect, and the amount specified herein shall be forfeited to the said City.
In the event Principal executed this bond as an individual, it is agreed that the death of Principal shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ____________ day of ___________________________, 20_____
________________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: __________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name/Title) (Print Name/Title)
(SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY – ATTACH ATTORNEY -IN-FACT
CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: __________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 5554 Page 24 of 142
GUIDE FOR COMPLETING
THE “DESIGNATION OF SUBCONTRACTORS” FORM
REFERENCES Prior to preparation of the following “Subcontractor Disclosure F orm” Bidders are urged to review the definiti ons in section 1 -2 of the General Provisions to this Contract, especially, “Bid”, “Bidder”, “Contract”, “Contractor”, “Contract Price”, “Contract Unit Price”, “Engineer”, “Own Organization”, “Subcontractor”, and “Work” . Bidders are further urged to review sections 2-3 SUBCONTRACTS of the General Provisions.
CAUTIONS This form will be used by the Agency to determine the percentage of work that the Bidder proposes to perform. Bidders are cautioned that failure to provide complete and correct information may result in rejection of the bid as non -responsive. Any bid that proposes performance of more than 50 percent of the work by subcontractors or otherwise to be performed by forces other than the Bidder’s own organization will be rejected as non - responsive. Specialty items of work that may be so designated by the Engineer on the “Contractor’s Proposal” are not included in computing the percentage of work proposed to be performed by the Bidder.
INSTRUCTIONS The Bidder shall set forth the name and location of business of each and every subcontractor whom the Bidder proposes to perform work or labor or render service in or about the work or improvement, and every subcontractor licensed as a contractor by the State of California whom the Bidder proposes to specially fabricate and install any portion of the work or improvement according to detailed drawings contained in the plans and specifications in excess of one-half of one percent (0.5%) of the Bidder’s total bid or, in the case of bids or offers for the construction of streets and highways, including bridges, in excess of one -half of one percent (0.5%) or ten thousand dollars ($10,000) whichever is greater. Said name(s) and location(s) of business of subcontractor(s) shall be set forth and included as an integral part of the bid offer.
The Designation of Subcontractors form must be submitted as a part of the Bidder’s sealed bid.
Failure to provide complete and correct information may result in rejection of the bid as non - responsive.
Suppliers of materials from sources outside the limits of work are not subcontractors. The value of materials and transport of materials from sources outside the limits of work, as shown on the plans, shall be assigned to the Contractor or the Subcontractor as the case may be, that the Bidder proposes as installer of said materials. The value of material incorporated in any Subcontractor-installed bid item that is supplied by the Bidder shall be included as a part of the work that the Bidder proposes to be performed by the Subcontractor installing said item.
When a Subcontractor has a Carlsbad business license, the number must be entered on the proper form. If the Subcontractor does not have a valid business license, enter “NONE” in the appropriate space.
When the Bidder proposes using a Subcontractor to construct or install less than 100 percent of a bid item, the Bidder shall attach an explanation sheet to the Designation of Subcontractor form. The explanation sheet shall clearly apprise the City of the specific facts that show the Bidder proposes to perform no less than fifty percent (50%) of the work with its own forces.
Revised 6/12/18 Contract No. 5554 Page 25 of 142
Determination of the subcontract amounts for purposes of award of the contract shall be determined by the City Council in conformance with the provisions of the contract documents and the various supplemental provisions. The decision of the City Council shall be final.
Contractor is prohibited from performing any work on this project with a subcontractor who is ineligible to perform work on a public works project pursuant to Labor Code Sections 1771.1 or 1777.7.
Bidders shall make any additional copies of the disclosure forms as may be necessary to provide the required information. The page number and total number of additional form pages shall be entered in the location provided on each type of form so duplicated.
Revised 6/12/18 Contract No. 5554 Page 26 of 142
DESIGNATION OF SUBCONTRACTOR AND
AMOUNT OF SUBCONTRACTOR'S BID ITEMS
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
The Bidder certifies that it has used the sub -bid of the following listed subcontractors in preparing this bid for the Work and that the listed subcontractors will be used to perform the portions of the Work as designated in this list in accordance with applicable provisions of the specifications and section 4100 et seq. of the Public Contract Code, "Subletting and Subcontracting Fair Practices Act." The Bidder further certifies that no additional subcontractor will be allowed to perform any portion of the Work in excess of one-half of one percent (0.5%) of the Bidder’s total bid, or in the case of bids or offers for construction of streets and highways, including bridges, in excess of one-half of one percent (0.5%) or ten thousand dollars ($10,000), whichever is greater, and that no changes in the subcontractors listed work will be made except upon the prior approval of the Agency.
SUBCONTRACTOR’S BID ITEMS
Portion of
Work
Subcontractor Name and
Location of Business
Phone No.
and Email
Address
DIR
Registration
No.
Subcontractor’s
License No. and
Classification*
Amount of
Work by
Subcontractor
in Dollars*
Page _____ of _____ pages of this Subcontractor Designation form
_________________
* Pursuant to section 4104 (a)( 3)(A) California Public Contract Code, receipt of the information preceded by an asterisk may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the “Notice Inviting Bids.” Revised 6/12/18 Contract No. 5554 Page 27 of 142
BIDDER'S STATEMENT OF
TECHNICAL ABILITY AND EXPERIENCE
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
The Bidder is required to state what work of a similar character to that included in the proposed Contract he/she has successfully performed and give references, with telephone numbers, which will enable the City to judge his/her responsibility, experience and skill. An attachment can be used.
The bidder shall demonstrate at least five (5) years of experience successfully completing as superintendent of sewer lift station projects with at least five projects involving sewer lift station mechanical and electrical improvements with a value of $ 1,000,000 or greater and similar in scope to the Work of this Contract. Bidder must also submit the qualifications of its Representatives in accordance with Section 7-6. The proposal shall be deemed non-responsive if the required technical ability and experience for the Bidder or its representative is not demonstrated.
Date Contract
Completed
Name and Address
of the Employer
Name and Phone
No. of Person to
Contract
Type of Work Amount of
Contract
Revised 6/12/18 Contract No. 5554 Page 28 of 142
BIDDER’S CERTIFICATE OF INSURANCE FOR
GENERAL LIABILITY, EMPLOYERS’ LIABILITY,
AUTOMOTIVE
LIABILITY AND WORKERS’ COMPENSATION
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
As a required part of the Bidder’s proposal the Bidder must attach either of the following to this page.
1) Certificates of insurance showing conformance with the requirements herein for each of:
Comprehensive General Liability
Automobile Liability
Workers Compensation
Employer’s Liability
2) Statement with an insurance carrier’s notarized signature stating that the carrier can, and upon payment of fees and/or premiums by the Bidder, will issue to the Bidder Policies of insurance for Comprehensive General Liability, Automobile Liability, Workers Compensation and Employer’s Liability in conformance with the requirements herein and Certificates of insurance to the Agency showing conformance with the requirements herein.
All certificates of insurance and statements of willingness to issue insurance for auto policies offered to meet the specification of this contract must:
1) Meet the conditions stat ed in The Notice Inviting Bids and the General Provisions for this project for each insurance company that the Contractor proposes.
2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled.
Revised 6/12/18 Contract No. 5554 Page 29 of 142
BIDDER'S STATEMENT RE DEBARMENT
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
1) Have you or any of your subcontractors ever been debarred as an irresponsible bidder by another jurisdiction in the State of California?
______ ______
yes no
2) If yes, what was/were the name(s) of the agency(ies) and what was/were the period(s) of debarment(s)? Attach additional copies of this page to accommodate more than two debarments.
party debarred
agency
period of debarment
party debarred
agency
period of debarment
BY CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name/title)
Page _____ of _____ pages of this Re Debarment form
Revised 6/12/18 Contract No. 5554 Page 30 of 142
BIDDER'S DISCLOSURE OF DISCIPLINE RECORD
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, California 95826.
1) Have you ever had your contractor’s license suspended or revoked by the California Contractors’ State License Board two or more times within an eight year period?
______ ______
yes no
2) Has the suspension or revocation of your contractor’s license ever been stayed?
______ ______
yes no
3) Have any subcontractors that you propose to perform any portion of the Work ever had their contractor’s license suspended or revoked by the California Contractors’ State License Board two or more times within an eight year period?
______ ______
yes no
4) Has the suspension or revocation of the license of any subcontractor’s that you propose to perform any portion of the Work ever been stayed?
______ ______
yes no
5) If the answer to either of 1. or 3. above is yes fully identify, in each and every case, the party disciplined, the date of and violation that the disciplinary action pertain s to, describe the nature of the violation and the disciplinary action taken therefore.
(If needed attach additional sheets to provide full disclosure.)
Page _____ of _____ pages of this Disclosure of Discipline form
Revised 6/12/18 Contract No. 5554 Page 31 of 142
BIDDER'S DISCLOSURE OF DISCIPLINE RECORD
(CONTINUED)
(To Accompany Proposal)
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
6) If the answer to either of 2. or 4. above is yes fully identify, in each and every case, the party whose discipline was stayed, the date of the violation that the disciplinary action pertains to, describe the nature of the violation and the condition (if any) upon which the disciplinary action was stayed.
(If needed attach additional sheets to provide full disclosure.)
BY CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name/title)
Page _____ of _____ pages of this Disclosure of Discipline form
Revised 6/12/18 Contract No. 5554 Page 32 of 142
NONCOLLUSION DECLARATION TO BE EXECUTED BY
BIDDER AND SUBMITTED WITH BID
PUBLIC CONTRACT CODE SECTION 7106
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
The undersigned declares:
I am the ____________ of ______________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on ___________________________, 20____ at _________ [city], ________ [state].
________________________________________________
Signature of Bidder
Revised 6/12/18 Contract No. 5554 Page 33 of 142
CONTRACT
PUBLIC WORKS
This agreement is made this ____________ day of ____________________________, 2026, by and between the City of Carlsbad, California, a municipal corporation, (hereinafter called "City"), and __________________________________ whose principal place of business is _______________________________________________ (hereinafter called "Contractor").
City and Contractor agree as follows:
1. Description of Work. Contractor shall perform all work specified in the Contract documents for:
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
(hereinafter called "project")
2. Provisions of Labor and Materials. Contractor shall provide all labor, materials, tools, equipment, and personnel to perform the work specified by the Contract Documents.
3. Contract Documents. The Contract Documents consist of this Contract, Notice Inviting Bids, Contractor's Proposal, Bidder's Bond, Noncollusion Declaration, D esignation of Subcontractors, Technical Ability and Experience, Bidder’s Statement Re Debarment, Escrow Agreement, Release Form, the Plans and Specifications, the General Provisions, addendum(s) to said Plans and Specifications and General Provisions, and all proper amendments and changes made thereto in accordance with this Contract or the Plans and Specifications, and all bonds for the project; all of which are incorporated herein by this reference.
Contractor, her/his subcontractors, and materials suppliers shall provide and install the work as indicated, specified, and implied by the Contract Documents. Any items of work not indicated or specified, but which are essential to the completion of the work, shall be provided at the Contractor's expense to fulfill the intent of said documents. In all instances through the life of the Contract, the City will be the interpreter of the intent of the Contract Documents, and the City’s decision relative to said intent will be final and binding. Failure of the Contractor to apprise subcontractors and materials suppliers of this condition of the Contract will not relieve responsibility of compliance.
4. Payment. For all compensation for Contractor's performance of work under this Contract, City shall make payment to the Contractor per section 9 -3 PAYMENT of the General Provisions section of this contract. The Engineer will close the estimate of work completed for progress payments on the last working day of each month. The City shall withhold retention as required by Public Contract Code Section 9203.
5. Independent Investigation. Contractor has made an independent investigation of the jobsite, the soil conditions at the jobsite, and all other conditions that might affect the progress of the work and is aware of those conditions. The Contract price includes payment for all work that may be done by Contractor, whether anticipated or not, in order to overcome underground conditions. Any information that may have been furnished to Contractor by City about underground conditions or other job conditions is f or Contractor's convenience only, and City
Revised 6/12/18 Contract No. 5554 Page 34 of 142
does not warrant that the conditions are as thus indicated. Contractor is satisfied with all job conditions, including underground conditions and has not relied on information furnished by City.
6. Hazardous Waste or Other Unusual Conditions. If the contract involves digging trenches or other excavations that extend deeper than four feet below the surface Contractor shall promptly, and before the following conditions are disturbed, notify City, in writing, of any:
A. Hazardous Waste. Material that Contractor believes may be material that is hazardous waste, as defined in section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
B. Differing Conditions. Subsurface or latent physical conditions at the site differing from those indicated.
C. Unknown Physical Conditions. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.
City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in contractor's costs of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in this contract.
In the event that a dispute arises between City and Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time required for, performance of any part of the work, contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. Contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties.
7. Immigration Reform and Control Act. Contractor certifies it is aware of the requirements of the Immigration Reform and Control Act of 1986 (8 USC sections 1101 -1525) and has complied and will comply with these requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors, and consultants that are included in this Contract.
8. Prevailing Wage. Pursuant to the California Labor Code, the director of the Department of Industrial Relations has determined the general prevailing rate of per diem wages in accordance with California Labor Code, section 1773 and a copy of a schedule of said general prevailing wage rates is on file in the office of the City Engineer and is incorporated by reference herein. Pursuant to California Labor Code, section 1775, Contractor shall pay prevailing wages.
Contractor shall post copies of all applicable prevailing wages on the job site. Contractor shall comply with California Labor Code, section 1776, which generally requires keeping accurate payroll records, verifying and certifying payroll records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776.
9. Indemnification. Contractor shall assume the defense of, pay all expenses of defense, and indemnify and hold harmless the City, and its officers and employees, from all claims, loss,
Revised 6/12/18 Contract No. 5554 Page 35 of 142
damage, injury and liability of every kind, nature and description, directly or indirectly arising from or in connection with the performance of the Contract or work; or from any failure or alleged failure of Contractor to comply with any applicable law, rules or regulations including those relating to safety and health; and from any and all claims, loss, damages, injury and liability, howsoever the same may be caused, resulting directly or indirectly from the nature of the work covered by the Contract, except for loss or damage caused by the sole or active negligence or willful misconduct of the City. The expenses of defense include all costs and expenses including attorneys' fees for litigation, arbitration, or other dispute resolution method.
Contractor shall also defend and indemnify the City against any challenges to the award of the contract to Contractor, and Contractor will pay all costs, including defense costs for the City.
Defense costs include the cost of separate counsel for City, if City requests separate counsel.
Contractor shall also defend and indemnify the City against any challenges to the award of the contract to Contractor, arising in whole or in part from alleged inaccuracies or misrepresentation by the Contractor, whether intentional or otherwise, and Contractor will pay all costs, including defense costs for the City. Defense costs include the cost of separate counsel for City, if City requests separate counsel.
10. Insurance. Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his or her agents, representatives, employees or subcontractors. Said insurance shall meet the City of Carlsbad’s policy for insurance as stated in City Council Policy # 70.
(A) Coverages and Limits Contractor shall maintain the types of coverages and minimum limits indicted herein:
a. Commercial General Liability (GLC) Insurance: Insurance written on an “occurrence” basis, including products-completed operations, personal & advertising injury, with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit.
b. Business Automobile Liability Insurance : $ 2,000,000 combined single limit per accident for bodily injury and property damage. In addition, the auto policy must cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non - owned or hired, and whether scheduled or non-scheduled.
c. Workers' Compensation and Employers' Liability Insurance: Workers' compensation limits as required by the Labor Code of the State of California and Employers’ Liability limits of $1,000,000 per incident. Workers' compensation offered by the State Compensation Insurance Fund is acceptable to the City.
(B) Additional Provisions: Contractor shall ensure that the policies of insurance required under this agreement with the exception of Workers’ Compensation and Business Automobile Liability Insurance contain, or are endorsed to contain, the following provisions.
a. The City, its officials, employees and volunteers are to be covered as additional insured as respects: liability arising out of activities performed by or on behalf of the Contractor; products and completed operations of the contractor; premises owned, leased, hired or
Revised 6/12/18 Contract No. 5554 Page 36 of 142
borrowed by the contractor. The coverage shall contain no special limitations on the scope of protection afforded to the City, its officials, employees or volunteers. All additional insured endorsements must be evidenced using separate documents attached to the certificate of insurance; one for each company affording general liability, and employers’ liability coverage.
b. The Contractor's insurance coverage shall be primary insurance as respects the City, its officials, employees and volunteers. Any insurance or self -insurance maintained by the City, its officials, employees or volunteers shall be in excess of the contractor's insurance and shall not contribute with it.
c. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, its officials, employees or volunteers.
d. Coverage shall state that the contractor's insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
(C) Notice of Cancellation. Each insurance policy required by this agreement shall be endorsed to state that coverage shall not be nonrenewed, suspended, voided, canceled, or reduced in coverage or limits except after ten (10) days' prior written notice has been sent to the City by certified mail, return receipt requested.
(D) Deductibles and Self -Insured Retention (S.I.R.) Levels. Any deductibles or self - insured retention levels must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles or self -insured retention levels as respects the City, its officials and employees; or the contractor shall procure a bond guaranteeing payment of losses and related investigation, claim administration and defense expenses.
(E) Waiver of Subrogation. All policies of insurance required under this agreement shall contain a waiver of all rights of subrogation the insurer may have or may acquire against the City or any of its officials or employees.
(F) Subcontractors. Contractor shall include all subcontractors as insured under its policies or shall furnish separate certificates and endorsements for each subcontractor. Coverages for subcontractors shall be subject to all of the requirements stated herein.
(G) Acceptability of Insurers. Insurance is to be placed with insurers that have a rating in Best's Key Rating Guide of at least A -:VII. Insurers must also be authorized to transact the business of insurance by the State of California Insurance Commissioner as admitted carriers as evidenced by a listing in the official publication of the Department of Insurance of the State of California and/or under the standards specified by City Council Policy # 70.
(H) Verification of Coverage. Contractor shall furnish the City with certificates of insurance and original endorsements affecting coverage required by this clause. The certificates and endorsements for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificates and endorsements are to be in forms approved by the City and are to be received and approved by the City before the Contract is executed by the City.
Revised 6/12/18 Contract No. 5554 Page 37 of 142
(I) Cost of Insurance. The Cost of all insurance required under this agreement shall be included in the Contractor's bid.
11. Claims and Lawsuits. All claims by Contractor shall be resolved in accordance with Public Contract Code section 9204, which is incorporated by reference. A copy of Section 9204 is included in Section 3 of the General Provisions. In addition, all claims by Contractor for $375,000 or less shall be resolved in accordance with the provisions in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5 (commencing with section 20104) which are incorporated by reference. A copy of Article 1.5 is included in Section 3 of the General Provisions. In the event of a conflict between Section 9204 and Article 1.5, Section 9204 shall apply. Notwithstanding the provisions of this section of the contract, all claims shall comply with the Government Tort Claim Act (section 900 et seq., of the California Government Code) for any claim or cause of action for money or damages prior to filing any lawsuit for breach of this agreement.
(A) Assertion of Claims. Contractor hereby agrees that any contract claim submitted to the City must be asserted as part of the contract process as set forth in this agreement and not in anticipation of litigation or in conjunction with litigation.
(B) False Claims. Contractor acknowledges that if a false claim is submitted to the City, it may be considered fraud and the Contractor may be subject to criminal prosecution.
(C) Government Code. Contractor acknowledges that California Government Code sections 12650 et seq., the False Claims Act, provides for civil penalties where a person knowingly submits a false claim to a public entity. These provisions include false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of the information.
(D) Penalty Recovery. If the City of Carlsbad seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attorney's fees.
(E) Debarment for False Claims. Contractor hereby acknowledges that the filing of a false claim may subject the Contractor to an administrative debarment proceeding wherein the Contractor may be prevented from further bidding on public contracts for a period of up to five years.
(F) Carlsbad Municipal Code. The provisions of Carlsbad Municipal Code sections
3.32.025, 3.32.026, 3.32.027 and 3.32.028 pertaining to false claims are incorporated herein by reference.
(G) Debarment from Other Jurisdictions. Contractor hereby acknowledges that debarment by another jurisdiction is grounds for the City Council of the City of Carlsbad to disqualify the Contractor or subcontractor from participating in future contract bidding.
(H) Jurisdiction. Contractor agrees and hereby stipulates that the proper venue and jurisdiction for resolution of any disputes between the parties arising out of this agreement is San Diego County, California.
I have read and understand all provisions of Section 11 above. ________ init ________ init
Revised 6/12/18 Contract No. 5554 Page 38 of 142
12. Maintenance of Records. Contractor shall maintain and make available at no cost to the City, upon request, records in accordance with sections 1776 and 1812 of Part 7, Chapter 1, Article 2, of the Labor Code. If the Contractor does not maintain the records at Contractor's principal place of business as specified above, Contractor shall so inform the City by certified letter accompanying the return of this Contract. Contractor shall notify the City by certified mail of any change of address of such records.
13. Labor Code Provisions. The provisions of Part 7, Chapter 1, commencing with section 1720 of the Labor Code are incorporated herein by reference.
14. Security. Securities in the form of cash, cashier's check, or certified check may be substituted for any monies withheld by the City to secure performance of this contract for any obligation established by this contract. Any other security that is mutually agreed to by the Contractor and the City may be substituted for monies withheld to ensure performance under this Contract.
15. Unfair Business Practices. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time the awarding body tenders final payment to the contractor, without further acknowledgment by the parties.
16. Provisions Required by Law Deemed Inserted. Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and included herein, and if, through mistake or otherwise, any such provision is not inserted, or is not correctly inserted, then upon application of either party, the Contract shall forthwith be physically amended to make such insertion or correction.
17. Additional Provisions. Any additional provisions of this agreement are set forth in the "General Provisions" or "Supplemental Provisions" attached hereto and made a part hereof.
[signatures on the following page]
Revised 6/12/18 Contract No. 5554 Page 39 of 142
NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE
ATTACHED
(CORPORATE SEAL)
CONTRACTOR:
(name of Contractor)
By:
(sign here)
(print name and title)
By:
(sign here)
(print name and title)
CITY OF CARLSBAD , a municipal
corporation of the State of California
By:
KEITH BLACKBURN, Mayor
ATTEST:
SHERRY FREISINGER, City Clerk
President or vice -president and secretary or assistant secretary must sign for corporations. If only one officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under the corporate seal empowering that officer to bind the corporation.
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By:
Assistant City Attorney
Revised 6/12/18 Contract No. 5554 Page 40 of 142
LABOR AND MATERIALS BOND
WHEREAS, the City Council of the City of Carlsbad located in the State of California has awarded to _____________________________________________________ ___ (hereinafter designated as the "Principal"), a Contract for:
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
in the City of Carlsbad , in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof require the furnishing of a bond, providing that if Principal or any of their subcontractors shall fail to pay for any materials, provisions, provender or other supplies or teams used in, upon or about the performance of the work agreed to be done, or for any work or labor done thereon of any kind, the Surety on this bond will pay the same to the extent hereinafter set forth.
NOW, THEREFORE, WE, _____________________ as Principal, (hereinafter designated as the "Contractor"), and _______________________________________________________ as Surety, are held firmly bound unto the City of Carlsbad in the sum __________________, said sum being an amount equal to: One hundred percent (100%) of the total amount payable under the terms of the contract by the City of Carlsbad, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if the Contractor or his/her subcontractors fail to pay for any materials, provisions, provender, supplies, or teams used in, upon, for, or about the performance of the work contracted to be done, or for any other work or labor thereon of any kind, consistent with California Civil Code section 9100, or for amounts due under the Unemployment Insurance Code with respect to the work or labor performed under this Contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of the contractor and subcontractors pursuant to section 13020 of the Unemployment Insurance Code with respect to the work and labor, that the Surety will pay for the same, and, also, in case suit is brought upon the bond, reasonable attorney's fees, to be fixed by the court consistent with California Civil Code section 9554.
This bond shall inure to the benefit of any of the persons named in California Civil Code section 9100, so as to give a right of action to those persons or their assigns in any suit brought upon the bond.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed hereunder or the specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any change, extension of time, alterations or addition to the terms of the contract or to the work or to the specifications.
Revised 6/12/18 Contract No. 5554 Page 41 of 142
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ______________ day of __________________________, 20____
_______________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: _________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name & Title) (Print Name & Title)
(SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY – ATTACH ATTORNEY-IN-FACT CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: _________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 5554 Page 42 of 142
FAITHFUL PERFORMANCE/WARRANTY BOND
WHEREAS, the City Council of the City of Carlsbad , State of California has awarded to _____________________________________________________ (hereinafter designated as the "Principal"), a Contract for:
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
in the City of Carlsbad , in strict conformity with the contract, the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad, all of which are incorporated herein by this reference.
WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof require the furnishing of a bond for the faithful performance and warranty of said Contract;
NOW, THEREFORE, WE, _____________________ as Principal, (hereinafter designated as the "Contractor"), and _______________________________________________________ as Surety, are held firmly bound unto the City of Carlsbad in the sum __________________, said sum being an amount equal to: One hundred percent (100%) of the total amount payable under the terms of the contract by the City of Carlsbad, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if the above bounden Contractor, their heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions, and agreements in the Contract and any alteration thereof made as therein provided on their part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save harmless the City of Carlsbad , its officers, employees and agents, as therein stipulated, then this obligation shall become null and void; otherwise it shall remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees, including reasonable attorney's fees, incurred by the City in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered.
Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed there under or the specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any change, extension of time, alterations or addition to the terms of the contract or to the work or to the specifications.
Revised 6/12/18 Contract No. 5554 Page 43 of 142
In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall not exonerate the Surety from its obligations under this bond.
SIGNED AND SEALED, this ______________ day of __________________________, 20____
_______________________________(SEAL) _____________________________(SEAL) (Principal) (Surety)
By: _________________________________ By: ________________________________ (Signature) (Signature)
__________________________________ ________________________________ (Print Name & Title) (Print Name & Title)
(SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY – ATTACH ATTORNEY-IN-FACT CERTIFICATE)
APPROVED AS TO FORM:
CINDIE K. McMAHON
City Attorney
By: _________________________________
Assistant City Attorney
Revised 6/12/18 Contract No. 5554 Page 44 of 142
OPTIONAL ESCROW AGREEMENT FOR
SECURITY DEPOSITS IN LIEU OF RETENTION
This Escrow Agreement is made and entered into by and between the City of Carlsbad whose address is 1200 Carlsbad Village Drive, Carlsbad, California, 92008, hereinafter called "City" and ___________________________________________________________, whose address is _________________________________________________________________ hereinafter called "Contractor" and ___________________________________________________, whose address is __________________________________________________________ hereinafter called "Escrow Agent."
For the consideration hereinafter set forth, the City, Contractor and Escrow Agent agree as follows:
1. Pursuant to section 22300 of the Public Contract Code of the State of California, the Contractor has the option to deposit securities with the Escrow Agent as a substitute for retention earnings required to be withheld by the City pursuant to the Construction Contract entered into between the City and Contractor for
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
in the amount of ___________________________ dated ______________ (hereinafter referred to as the "Contract"). Alternatively, on written request of the Contractor, the City shall make payments of the retention earnings directly to the Escrow Agent. When the Contractor deposits the securities as a substitute for Contract earnings, the Escrow Agent shall notify the City within 10 days of the deposit. The market value of the securities at the time of the substitution shall be a least equal to the cash amount then required to be withheld as retention under the terms of the contract between the City and Contractor. Securities shall be held in the name of the City and shall designate the Contractor as the beneficial owner.
2. The City shall make progress payments to the Contractor for such funds which otherwise would be withheld from progress payments pursuant to the Contract provisions, provided that the Escrow Agent holds securities in the form and amount specified above.
3. When the City makes payment of retentions earned directly to the Escrow Agent, the Escrow Agent shall hold them for the benefit of the Contractor until such time as the escrow created under this contract is terminated. The Contractor may direct the investment of the payments into securities. All terms and conditions of this agreement and the rights and responsibilities of the parties shall be equally applicable and binding when the City pays the Escrow Agent directly.
4. The Contractor shall be responsible for paying all fees for the expenses incurred by the Escrow Agent in administering the Escrow Account and all expenses of the City. These expenses and payment terms shall be determined by the City, Contractor and Escrow Agent.
5. The interest earned on the securities or the money market accounts held in escrow and all interest earned on that interest shall be for the sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to the City.
Revised 6/12/18 Contract No. 5554 Page 45 of 142
6. Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow Agent accompanied by written authorization from City to the Escrow Agent that City consents to the withdrawal of the amount sought to be withdrawn by Contractor.
7. The City shall have a right to draw upon the securities in the event of default by the Contractor. Upon seven days' written notice to the Escrow Agent from the City of the default, the Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as instructed by the City.
8. Upon receipt of written notification from the City certifying that the Contract is final and complete and that the Contractor has complied with all requirements and procedures applicable to the Contract, the Escrow Agent shall release to Contractor all securities and interest on deposit less escrow fees and charges of the Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges.
9. The Escrow Agent shall rely on the written notifications from the City and the Contractor pursuant to sections (1) to (8), inclusive, of this agreement and the City and Contractor shall hold Escrow Agent harmless from Escrow Agent's release, conversion and disbursement of the securities and interest as set forth above.
10. The names of the persons who are authorized to give written notices or to receive written notice on behalf of the City and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:
For City:
Title FINANCE DIRECTOR
Name
Signature
Address 1635 Faraday Avenue, Carlsbad, CA 92008
For Contractor:
Title
Name
Signature
Address
For Escrow Agent:
Title
Name
Signature
Address
Revised 6/12/18 Contract No. 5554 Page 46 of 142
At the time the Escrow Account is opened, the City and Contractor shall deliver to the Escrow Agent a fully executed counterpart of this Agreement.
IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers on the date first set forth above.
For City:
Title MAYOR
Name
Signature
Address 1200 Carlsbad Village Drive, Carlsbad, CA
92008
For Contractor:
Title
Name
Signature
Address
For Escrow Agent:
Title
Name
Signature
Address
Revised 6/15/17 Contract No. 5552 Page 47 of 142
GENERAL PROVISIONS
FOR
CHINQUAPIN LIFT STATION IMPROVEMENTS
CONTRACT NO. 5554
CITY OF CARLSBAD
BIDDERS ARE ADVISED THAT THIS SECTION REPLACES PART 1,
GENERAL PROVISIONS, OF THE STANDARD SPECIFICATIONS FOR
PUBLIC WORKS CONSTRUCTION
SECTION 1 -- TERMS, DEFINITIONS, ABBREVIATIONS, AND
SYMBOLS
1-1 TERMS. Unless otherwise stated, the words directed, required, permitted, ordered, instructed, designated, considered necessary, prescribed, approved, acceptable, satisfactory, or words of like meaning, refer to actions, expressions, and prerogatives of the Engineer.
1-1.1 Reference to Drawings. Where words “shown”, “indicated”, “detailed”, “noted”, “scheduled”, or words of similar import are used, it shall be understood that reference is made to the plans accompanying these provisions, unless stated otherwise.
1-1.2 Directions. Where words “directed”, “designated”, “selected”, or words of similar import are used, it shall be understood that the direction, designation or selection of the Engineer is intended, unless stated otherwise. The word “required” and words of similar import shall be understood to mean “as required to properly complete the work as required and as approved by the Engineer,” unless stated otherwise.
1-1.3 Equals and Approvals. Where the words “equal”, “approved equal”, “equivalent”, and such words of similar import are used, it shall be understood such words are followed by the expression “in the opinion of the Engineer”, unless otherwise stated. Where the words “approved”, “approval”, “acceptance”, or words of similar import are used, it shall be understood that the approval, acceptance, or similar import of the Engineer is intended.
1-1.4 Perform. The word “perform” shall be understood to mean that the Contractor, at its expense, shall perform all operations, labor, tools and equipment, and further, including the furnishing and installing of materials that are indicated, specified or required to mean that the Contractor, at its expense, shall furnish and install the work, complete and in-place and ready to use, including furnishing of necessary labor, materials, tools, equipment, and transportation.
1-2 DEFINITIONS. The following words, or groups of words, shall be exclusively defined by the definitions assigned to them herein.
Revised 6/15/17 Contract No. 5552 Page 48 of 142
Addendum – Written or graphic instrument issued prior to the opening of Bids which clarifies, corrects, or changes the bidding or Contract Documents. The term Addendum shall include bulletins and all other types of written notices issued to potential bidders prior to opening of Bids.
Agency – The City of Carlsbad, California.
Agreement – See Contract.
Assessment Act Contract – A Contract financed by special assessments authorized under a State Act or procedural ordinance of a City or County.
Average Sound Level – The level, in decibels, of the mean-square A-weighted sound pressure during a stated time period, with reference to the square of the standard reference sound pressure of 20 micropascals. The "average sound level" is equivalent to the industry standard Leq. See Equivalent Continuous Sound Level.
Base – A layer of specified material of planned thickness placed immediately below the pavement or surfacing.
Bid – The offer or proposal of the Bidder submitted on the prescribed form setting forth the prices for the Work.
Bidder – Any individual, firm, partnership, corporation, or combination thereof, submitting a Bid for the Work, acting directly or through a duly authorized representative.
Board – The officer or body constituting the awarding authority of the Agency, which is the City Council for the City of Carlsbad or the Board of Directors of Carlsbad Municipal Water District.
Bond – Bid, performance, and payment bond or other instrument of security.
Caltrans – The State of California, Department of Transportation.
Cash Contract – A Contract financed by means other than special assessments.
Certificate of Compliance – A written document signed and submitted by a supplier or manufacturer that certifies that the material or assembled material supplied to the Work site conforms to the requirements of the Contract Documents.
Change Order – A written order to the Contractor signed by the Agency directing an addition, deletion, or revision in the Work, or an adjustment in the Contract Price or the Contract time issued after the effective date of the Contract. A Change Order may or may not also be signed by the Contractor.
Code – The terms Government Code, Labor Code, etc., refer to codes of the State of California.
Construction Manager– the Project Inspector’s immediate supervisor and first level of appeal for informal dispute resolution.
Contract – The written agreement between the Agency and the Contractor covering the Work.
Revised 6/15/17 Contract No. 5552 Page 49 of 142
Contract Documents – Including but not limited to; the Contract, any Addendum (which pertain to the Contract Documents), Notice Inviting Bids, Instructions to Bidders; Bid (including documentation accompanying the Bid and any post -bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Contract, the Bonds, the General Provisions, permits, the Technical Specifications, the Supplemental Provisions, the Plans, Standard Plans, Standard Specifications, Reference Specifications, and all Modifications issued after the execution of the Contract.
Contractor – The individual, partnership, corporation, joint venture, or other legal entity having a Contract with the Agency to perform the Work. In the case of work being done under permit issued by the Agency, the permittee shall be constructed to be the Contractor. The term “prime contractor” shall mean Contractor.
Contract Time - The number of Working Days to complete the Work as specified in the Contract Documents.
Contract Price – The total amount of money for which the Contract is awarded.
Contract Unit Price – The amount stated in the Bid for a single unit of an item of work.
County Sealer – The Sealer of Weights and Measures of the county in which the Contract is let.
Critical Path – In the construction schedule, the sequence of activities that represents the longest path through the Project network of activities and the shortest possible Project duration.
Days – Days shall mean consecutive calendar’s days unless otherwise specified.
Decibel – A unit for measuring the amplitude of sound, equal to 20 times the logarithm to the base 10 of the ratio of the pressure of the sound measured to the reference pressure, which is 20 micropascals.
Defective Work - Work that does not conform to the requirements of the Contract Documents.
Deputy City Engineer – The Engineering Manager of the Construction Management & Inspection Department, the Construction Manager’s immediate supervisor and the Engineer’s designated representative. The Deputy City Engineer is the second level of appeal for informal dispute resolution.
Dispute Board – Persons designated by the City Manager of the City of Carlsbad or Executive Manager of the Carlsbad Municipal Water District, to hear and advise the City Manager on claims submitted by the Contractor. The City Manager for the City of Carlsbad or the Executive Manager for the Carlsbad Municipal Water District is the last appeal level for informal dispute resolution.
Disputed Work – Work in which the Agency and the Contractor are in disagreement.
Electrolier – Street light assembly complete, including foundation, standard, luminaire arm, luminaire, etc.
Revised 6/15/17 Contract No. 5552 Page 50 of 142
Engineer – The City Engineer of the City of Carlsbad or his/her approved representative . The Engineer is the third level of appeal for informal dispute resolution.
Engineer of Record/Design Engineer – A registered professional engineer licensed in the State of California who is qualified to act as an agent of a project owner or to prepare plans for facilities to be accepted by the City of Carlsbad. The term includes persons licensed in the State of California as Civil Engineers or Structural Engineers.
Equivalent Continuous Sound Level (Leq) – The average sound level which, over a given period of time, has the same total energy as the fluctuating noise and is also known as the time- average sound level.
Extra Work – New or unforeseen work not covered by a Contract Unit Price or Stipulated Unit Price.
Float – The number of days by which an activity in the construction schedule may be delayed from either its earliest start date or earliest completion date without extending the Contract Time (total float). Total float belongs to the Project and to any Party to accommodate changes in the Work or to mitigate the effect of events which may delay completion.
Holiday – Holidays and the days observed are listed below. If a holiday falls on a Saturday, the holiday is observed on the preceding Friday. If the holiday falls on a Sunday, it is observed the following Monday. Unless specified otherwise in the Contract Documents or authorized by the Engineer, do not work on holidays.
New Year’s Day January 1
Martin Luther King Day 3rd Monday in January
Presidents’ Day 3rd Monday in February
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1st Monday in September
Indigenous People’s Day 2nd Monday in October
Veteran’s Day November 11
Thanksgiving Day 4th Thursday in November
Thanksgiving Friday Day after Thanksgiving
Christmas Day December 25
House Connection Sewer – A sewer, within a public street or right -of-way, proposed to connect any parcel, lot, or part of a lot with a mainline sewer.
House Sewer – A sewer, wholly within private property, proposed to connect any building to a house connection sewer.
Luminaire – The lamp housing including the optical and socket assemblies (and ballast if so specified).
Luminaire Arm – The structural member, bracket, or mast arm, which, mounted on the standard, supports the luminaire.
Minor Bid Item – a single contract item constituting less than 10 percent (10%) of the original Contract Price bid.
Revised 6/15/17 Contract No. 5552 Page 51 of 142
Modification – Includes Change Orders and Supplemental Agreements. A Modification may only be used after the effective date of the Contract.
Night Work – See Working Night.
Notice of Award – The written notice by the Agency to the successful Bidder stating that upon compliance by it with the required conditions, the Agency will execute the Contract.
Notice to Proceed – A written notice given by the Agency to the Contractor fixing the date on which the Contract time will start.
Own Organization - When used in Sections 2 -3.1 and 2 -3.2 – Employees of the Contractor who are hired, directed, supervised and paid by the Contractor to accomplish the completion of the Work. Further, such employees have their employment taxes, State disability insurance payments, State and Federal income taxes paid and administered, as applicable, by the Contractor. Further, “own organization” means construction equipment that the Contractor owns or leases and uses to accomplish the Work. Equipment that is owner operated or leased equipment with an operator is not part of the Contractor's Own Organization and will not be included for the purpose of compliance with Sections 2-3.1 and 2-3.2.
Person – Any individual, firm, association, partnership, corporation, trust, joint venture, or other legal entity.
Plans – The drawings, profiles, cross sections, working drawings, and supplemental drawings, or reproductions thereof, approved by the Engineer, which show the location, character, dimensions, or details of the Work.
Private Contract – Work subject to Agency inspection, control, and approval, involving private funds, not administered by the Agency.
Project Inspector – the Engineer’s designated representative for inspection, contract administration and first level for informal dispute resolution.
Proposal – See Bid.
Reference Specifications – Those bulletins, standards, rules, methods of analysis or test, codes, and specifications of other agencies, engineering societies, or industrial associations referred to in the Contract Documents. These refer to the latest edition, including amendments in effect and published at the time of advertising the project or issuing the permit, unless specifically referred to by edition, volume, or date.
Roadway – The portion of a street reserved for vehicular use.
Service Connection – Service connections are all or any portion of the conduit, cable, or duct, including meter, between a utility distribution line and an individual consumer.
Sewer – Any conduit intended for the reception and transfer of sewage and fluid industrial waste.
Revised 6/15/17 Contract No. 5552 Page 52 of 142
Shop Drawings – Drawings showing the details of manufactured or assembled products proposed to be incorporated into the Work.
Sound Level – The weighted sound pressure level obtained using a sound level meter and frequency weighting network as provided in the American National Standards Institute (ANSI) specifications for sound level meters. "Sound level" means the same as "noise level."
Special Provisions – Revisions to the Standard Specifications setting forth conditions and requirements peculiar to the Work.
Specifications – General Provisions, Standard Specifications, Technical Specifications, Reference Specifications, Supplemental Provisions, and specifications in Supplemental Agreements between the Contractor and the Board.
Standard – The shaft or pole used to support street lighting luminaire, traffic signal heads, mast arms, etc.
Standard Plans – Details of standard structures, devices, or instructions referred to on the Plans or in Specifications by title or number.
Standard Specifications – The Standard Specifications for Public Works Construction (SSPWC), the “Greenbook”.
State – State of California.
Stipulated Unit Price – Unit prices established by the Agency in the Contract Documents.
Storm Drain – Any conduit and appurtenances intended for the reception and transfer of storm water.
Street – Any road, highway, parkway, freeway, alley, walk, or way.
Subbase – A layer of specified material of planned thickness between a base and the subgrade.
Subcontractor – An individual, firm, or corporation having a direct contract with the Contractor or with any other Subcontractor for the performance of a part of the Work.
Subgrade – For roadways, that portion of the roadbed on which pavement, surfacing, base, subbase, or a layer of other material is placed. For structures, the soil prepared to support a structure.
Supervision – Supervision, where used to indicate supervision by the Engineer, shall mean the performance of obligations, and the exercise of rights, specifically imposed upon and granted to the Agency in becoming a party to the Contract. Except as specifically stated herein, supervision by the Agency shall not mean active and direct superintendence of details of the Work.
Supplemental Agreement – A written amendment of the Contract Documents signed by both parties.
Revised 6/15/17 Contract No. 5552 Page 53 of 142
Supplemental Provisions – See Special Provisions.
Surety – Any individual, firm, or corporation, bound with and for the Contractor for the acceptable performance, execution, and completion of the Work, and for the satisfaction of all obligations incurred.
Tonne – Also referred to as “metric ton”. Represents a unit of measure in the International System of Units equal to 1,000 kilograms.
Utility – Tracks, overhead or underground wires, pipelines, conduits, ducts, or structures, sewers, or storm drains owned, operated, or maintained in or across a public right of way or easement.
Work – That which is proposed to be constructed or done under the Contract or permit, including the furnishing of all labor, materials, equipment, and services.
Working Drawings – Drawings showing the details not shown on the Plans which are required to be designed by the Contractor.
Working Night – A period of night -time work, allowed only on Sunday through Thursday, excluding holidays.
1-3 ABBREVIATIONS.
1-3.1 General. The abbreviation herein, together with others in general use, are applicable to these Standard Specifications and to project Plans or other Contract Documents.
All abbreviations and symbols used on Plans for structural steel construction shall conform to those given by the “Manual of Steel Construction” published by the American Institute of Steel Construction, Inc.
1-3.2 Common Usage
Abbreviation Word or Words Abbreviation Word or Words
ABAN .............................................................Abandon ABAND .......................................................Abandoned ABS ........................ Acrylonitrile – butadiene – styrene AC .................................................... Asphalt Concrete ACP ........................................... Asbestos cement pipe ACWS ..................... Asphalt concrete wearing surface ALT ................................................................Alternate APTS ................................. Apartment and Apartments AMER STD ................................... American Standard AWG ............... American Wire Gage (nonferrous wire) BC .................................................. Beginning of curve BCR ....................................... Beginning of curb return BDRY ............................................................Boundary BF ..................................................... Bottom of footing BLDG ........................................ Building and Buildings BM .............................................................. Benchmark BVC .................................... Beginning of vertical curve B/W ........................................................... Back of wall C/C ..................................................... Center to center CAB ...................................... Crushed aggregate base CAL/OSHA ............ California Occupational Safety and Health Administration
CalTrans ....... California Department of Transportation CAP .................................... Corrugated aluminum pipe CB ............................................................. Catch Basin Cb ........................................................................ Curb CBP ............................... Catch Basin Connection Pipe CBR ....................................... California Bearing Ratio CCR ............................ California Code of Regulations CCTV ............................................... Closed Circuit TV CES .......................... Carlsbad Engineering Standards CF ................................................................ Curb face CF ................................................................ Cubic foot C&G .................................................... Curb and gutter CFR ................................ Code of Federal Regulations CFS ......................................... Cubic Feet per Second CIP ......................................................... Cast iron pipe CIPP ................................................ Cast-in place pipe CL ............................................. Clearance, center line CLF .................................................... Chain link fence
Revised 6/15/17 Contract No. 5552 Page 54 of 142
CMB ............................... Crushed miscellaneous base CMC ......................................... Cement mortar-coated CML ............................................ Cement mortar-lined CMWD .................... Carlsbad Municipal Water District CO .................................................... Cleanout (Sewer) COL ..................................................................Column COMM ....................................................... Commercial CONC ........................................................... Concrete CONN ........................................................ Connection CONST .................................. Construct, Construction COORD ...................................................... Coordinate CSP ............................................ Corrugated steel pipe CSD ............................... Carlsbad Standard Drawings CTB ............................................ Cement treated base CV ............................................................ Check valve CY ............................................................... Cubic yard D .............................................................. Load of pipe dB ................................................................... Decibels DBL .................................................................. Double DF ............................................................... Douglas fir DIA ................................................................ Diameter DIP ..................................................... Ductile iron pipe DL ................................................................Dead load DR ...................................................... Dimension Ratio DT .................................................................Drain Tile DWG ............................................................... Drawing DWY .............................................................. Driveway DWY APPR ................................... Driveway approach E ....................................................................... Electric EA ........................................................................ Each EC ............................................................ End of curve ECR ................................................ End of curb return EF ................................................................ Each face EG ......................................................... Edge of gutter EGL .................................................. Energy grade line EI ................................................................... Elevation ELC ..................................... Electrolier lighting conduit ELT ........................................................ Extra long ton ENGR ....................................... Engineer, Engineering EP ................................................... Edge of pavement ESMT ........................................................... Easement ETB .......................................... Emulsion-treated base EVC ............................................... End of vertical curb EWA ............................... Encina Wastewater Authority EXC ............................................................ Excavation EXP JT ................................................. Expansion joint EXST ............................................................... Existing F .................................................................. Fahrenheit F&C ................................................... Frame and cover F&I .................................................. Furnish and install FAB ............................................................... Fabricate FAS ............................................... Flashing arrow sign FD ............................................................... Floor drain FDN ............................................................ Foundation FED SPEC ................................. Federal Specification FG ........................................................ Finished grade FH ............................................................. Fire hydrant FL ................................................................... Flow line FS ...................................................... Finished surface FT-LB .........................................................Foot-pound FTG .................................................................. Footing FW ............................................................ Face of wall G ........................................................................... Gas GA ..................................................................... Gauge GAL ............................................... Gallon and Gallons GALV ......................................................... Galvanized GAR ........................................... Garage and Garages GIP .............................................. Galvanized iron pipe GL ........................................ Ground line or grade line GM .............................................................. Gas meter GNV ............................................... Ground Not Visible GP ..................................................................Guy pole GPM ................................................ gallons per minute GR ...................................................................... Grade GRTG ............................................................... Grating GSP ........................................... Galvanized steel pipe H ............................................................ High or height HB .................................................................. Hose bib HC ................................................... House connection HDWL ........................................................... Headwall HGL .............................................. Hydraulic grade line HORIZ .......................................................... Horizontal HP ............................................................. Horsepower HPG ................................................ High pressure gas HPS ................................ High pressure sodium (Light) HYDR ............................................................ Hydraulic IE ......................................................... Invert Elevation ID ........................................................ Inside diameter INCL ...............................................................Including INSP .............................................................Inspection INV ...................................................................... Invert IP .................................................................... Iron pipe JC ..................................................... Junction chamber JCT .................................................................Junction JS ..................................................... Junction structure JT ......................................................................... Joint L ........................................................................ Length LAB ............................................................. Laboratory LAT ................................................................... Lateral LB ...................................................................... Pound LD ..................................................... Local depression LF ................................................................ Linear foot LH ............................................................... Lamp hole LL ...................................................................Live load LOL .............................................................Layout line LONG ........................................................Longitudinal LP ................................................................ Lamp post LPS ................................. Low pressure sodium (Light) LS ................................................................ Lump sum LTS .................................................... Lime treated soil LWD ............................... Leucadia Wastewater District MAINT ..................................................... Maintenance MAX ............................................................. Maximum MCR ............................................ Middle of curb return MEAS ............................................................. Measure MH ................................... Manhole, maintenance hole MIL SPEC .................................... Military specification MISC ..................................................... Miscellaneous MOD ................................................... Modified, modify MON ............................................................ Monument MS4 ............. Municipal Separate Storm Sewer System MSL .. Mean Sea Level (Reg. Standard Drawing M-12)
MTBM ......................... Microtunneling Boring Machine MULT ...............................................................Multiple MUTCD .....Manual on Uniform Traffic Control Devices
MVL ............................................... Mercury vapor light
Revised 6/15/17 Contract No. 5552 Page 55 of 142
NCTD .............................. North County Transit District NOI ....................................................... Notice of Intent NOT ........................................... Notice of Termination NRCP .............................. Nonreinforced concrete pipe OBS ...............................................................Obsolete OC ................................................................ On center OD ..................................................... Outside diameter OE .............................................................. Outer edge OHE ................................................ Overhead Electric OMWD ................. Olivenhain Municipal Water District OPP ...............................................................Opposite ORIG ................................................................Original PB ................................................................... Pull box PC .................................................... Point of curvature PCC ....................... Portland cement concrete or point of compound curvature
PCVC ....................... Point of compound vertical curve PE ........................................................... Polyethylene PI .................................................. Point of intersection PL ............................................................. Property line PMB ............................ Processed miscellaneous base POC ...................................................... Point on curve POT .................................................... Point on tangent PP .............................................................. Power pole PRC .......................................... Point of reverse curve PRVC ............................ Point of reverse vertical curve PSI ......................................... Pounds per square inch PT .................................................... Point of tangency PVC .................................................. Polyvinyl chloride PVMT ........................................................... Pavement PVT R/W ....................................... Private right-of-way Q ........................ Rate of flow in cubic feet per second QUAD ....................................... Quadrangle, Quadrant R ....................................................................... Radius R&O ......................................................... Rock and oil R/W .......................................................... Right-of-way RA ...................................................... Recycling agent RAC ................................... Recycled asphalt concrete RAP ................................ Reclaimed asphalt pavement RBAC ............................. Rubberized asphalt concrete RC ................................................ Reinforced concrete RCB ...................................... Reinforced concrete box RCE ...................................... Registered civil engineer RCP ..................................... Reinforced concrete pipe RCV ........................................... Remote control valve REF ............................................................. Reference REINF ..............................Reinforced or reinforcement RES ...............................................................Reservoir RGE ........................ Registered geotechnical engineer ROW ....................................................... Right-of-Way RR ...................................................................Railroad RSE .............................. Registered structural engineer RTE .................................... Registered traffic engineer S .................................... Sewer or Slope, as applicable SCCP ............................... Steel cylinder concrete pipe SD ............................................................. Storm drain SDNR .............................. San Diego Northern Railway SDR ....... Standard thermoplastic pipe dimension ratio (ratio of pipe O.D. to minimum wall thickness)
SDRSD ......... San Diego Regional Standard Drawings
SE ...................................................... Sand Equivalent SEC .................................................................. Section SF ............................................................. Square foot SFM ................................................ Sewer Force Main SI ....................... International System of Units (Metric) SPEC ..................................................... Specifications SPPWC .......................................... Standard Plans for Public Works Construction
SSPWC ............................. Standard Specifications for Public Works Construction
ST HWY ................................................ State highway STA ................................................................... Station STD ............................................................... Standard STR ..................................................................Straight STR GR ................................................ Straight grade STRUC .......................................... Structural/Structure SW .................................................................Sidewalk SWD ...................................................... Sidewalk drain SY ............................................................ Square yard T .................................................................. Telephone TAN ................................................................. Tangent TC .............................................................. Top of curb TEL ............................................................. Telephone TF ........................................................... Top of footing TOPO ........................................................ Topography TR ........................................................................ Tract TRANS ......................................................... Transition TS ......................... Traffic signal or transition structure TSC ............................................. Traffic signal conduit TSS ........................................... Traffic signal standard TW ..............................................................Top of wall TYP .................................................................. Typical UE .............................................. Underground Electric USA .................................... Underground Service Alert VAR ..................................................... Varies, Variable VB ................................................................ Valve box VC .......................................................... Vertical curve VCP ................................................... Vitrified clay pipe VERT ............................................................... Vertical VOL .................................................................. Volume VWD ....................................... Vallecitos Water District W ........................ Water, Wider or Width, as applicable WATCH .............. Work Area Traffic Control Handbook WI ............................................................ Wrought iron WM ........................................................... Water meter WPJ .......................................... Weakened plane joint XCONN ............................................ Cross connection XSEC ..................................................... Cross section
Revised 6/15/17 Contract No. 5552 Page 56 of 142
1-3.3 Institutions.
Abbreviation Word or Words
AASHTO ............................. American Association of State Highway and Transportation Officials ACI ................................ ................................ ................................ .... American Concrete Institute AISC ................................ ................................ ...............American Institute of Steel Construction ANSI ................................ ................................ ................. American National Standards Institute AREA ................................ ................................ ........ American Railway Engineering Association ASME ................................ ................................ ........ American Society of Mechanical Engineers ASQ ................................ ................................ ................................ . American Society for Quality ASTM ................................ ................................ ........ American Society for Testing and Materials AWPA ................................ ................................ ............ American Wood Preservers Association AWS ................................ ................................ ................................ ... American Welding Society AWWA ................................ ................................ .................. American Water Works Association EEI ................................ ................................ ................................ ........... Edison Electric Institute EIA ................................ ................................ ................................ ...Electronic Industries Alliance EPA ................................ ................................ ......................... Environmental Protection Agency ETL ................................ ................................ ............................... Electrical Testing Laboratories FCC ................................ ................................ .................. Federal Communications Commission FHWA ................................ ................................ ......................... Federal Highway Administration GRI ................................ ................................ ............................ Geosynthetic Research Institute IEEE ................................ ................................ ... Institute of Electrical and Electronics Engineers IMSA ................................ ................................ ............International Municipal Signal Association ISSA ................................ ................................ ............ International Slurry Surfacing Association ITE ................................ ................................ ....................... Institute of Transportation Engineers NCHRP ................................ ........................... National Cooperative Highway Research Program NEMA ................................ ................................ .... National Electrical Manufacturers Association NSF ................................ ................................ ................................ .National Science Foundation OSHA ................................ ................................ ..Occupational Safety and Health Administration PPI ................................ ................................ ................................ .............. Plastics Pipe Institute RUS ................................ ................................ ................................ ............ Rural Utilities Service SAE ................................ ................................ ........................... Society of Automotive Engineers SSPC ................................ ................................ ........................... Society for Protective Coatings UL ................................ ................................ ................................ . Underwriters' Laboratories Inc.
1-4 UNITS OF MEASURE.
1-4.1 General. U.S. Standard Measures, also called U.S. Customary System, are the principal measurement system in these specifications. However, certain material specifications and test requirements contained herein use SI units specifically and conversions to U.S. Standard Measures may or may not have been included in these circumstances. When U.S. Standard Measures are not included in parenthesis, then the SI units shall control. S.I. units and U.S.
Standard Measures in parenthesis may or may not be exactly equivalent.
Reference is also made to ASTM E 380 for definitions of various units of the SI system and a more extensive set of conversion factors.
Revised 6/15/17 Contract No. 5552 Page 57 of 142
1-4.2 Units of Measure and Their Abbreviations.
U.S. Customary Unit (Equal To) SI Unit
(Abbreviations) (Abbreviations)
1 mil (=0.001 in) ....................................................................................25.4 micrometer (m) 1 inch (in) ..............................................................................................25.4 millimeter (mm) 1 inch (in) ..............................................................................................2.54 centimeter (cm) 1 foot (ft) ................................................................................................0.3048 meter (m) 1 yard (yd) .............................................................................................0.9144 meter (m) 1 mile (mi) .............................................................................................1.6093 kilometer (km) 1 square foot (ft2) ..................................................................................0.0929 square meter (m2) 1 square yard (yd2) ................................................................................0.8361 square meter (m2) 1 cubic foot (ft3) .....................................................................................0.0283 cubic meter (m3) 1 cubic yard (yd3) ..................................................................................0.7646 cubic meter (m3) 1 acre ....................................................................................................0.4047 hectare (ha) 1 U.S. gallon (gal) .................................................................................3.7854 Liter (L) 1 fluid ounce (fl. oz.) ..............................................................................29.5735 millileter (mL) 1 pound mass (lb) (avoirdupois) ...........................................................0.4536 kilogram (kg) 1 ounce mass (oz) .................................................................................0.02835 kilogram (kg) 1 Ton (=2000 lb avoirdupois) ................................................................0.9072 Tonne (= 907 kg) 1 Poise ..................................................................................................0.1 pascal . second (Pa . s) 1 centistoke (cs) ....................................................................................1 square millimeters per second (mm2/s)
1 pound force (lbf) .................................................................................4.4482 Newton (N) 1 pounds per square inch (psi) .............................................................6.8948 Kilopascal (kPa) 1 pound force per foot (lbf/ft) .................................................................1.4594 Newton per meter (N/m)
1 foot-pound force (ft-lbf).......................................................................1.3558 Joules (J) 1 foot-pound force per second ([ft-lbf]/s) ...............................................1.3558 Watt (W) 1 part per million (ppm) .........................................................................1 milligram/liter (mg/L)
Temperature Units and Abbreviations
Degree Fahrenheit (°F): ........................................................................Degree Celsius (°C):
°F = (1.8 x °C) + 32 ...............................................................................°C = (°F – 32)/1.8
SI Units (abbreviation) Commonly Used in Both Systems
1 Ampere (A)
1 Volt (V)
1 Candela (cd)
1 Lumen (lm)
1 second (s)
Common Metric Prefixes
kilo (k) ....................................................................................................103 centi (c)..................................................................................................10-2 milli (m) ..................................................................................................10-3 micro () ................................................................................................10-6 nano (n) .................................................................................................10-9 pico (p) ..................................................................................................10-12
1-5 SYMBOLS.
Delta, the central angle or angle between tangents
Angle
% Percent
‘ Feet or minutes
“ Inches or seconds
1 Number
/ per or (between words)
° Degree
PL Property line
CL Centerline
SL Survey line or station line
Revised 6/15/17 Contract No. 5552 Page 58 of 142
SECTION 2 – SCOPE AND CONTROL OF WORK
2-1 AWARD AND EXECUTION OF CONTRACT. Award and execution of Contract will be as provided for in the Specifications, Instruction to Bidders, or Notice Inviting Bids.
2-2 ASSIGNMENT. No Contract or portion thereof may be assigned without consent of the board, except that the contractor may assign money due or which will accrue to it under the contract. If given written notice, such assignment will be recognized by the Board to the extent permitted by law. Any assignment of money shall be subject to all proper withholdings in favor of the Agency and to all deductions provided for in the Contract. All money withheld, whether assigned or not, shall be subject to being used by the Agency for completion of the work, should the Contractor be in default.
2-3 SUBCONTRACTS.
2-3.1 General. Each Bidder shall comply with the Chapter of the Public Contract Code including Sections 4100 through 4113. The following excerpts or summaries of some of the requirements of this Chapter are included below for information:
The Bidder shall set forth in the Bid, as provided in 4104:
“(a) The name and location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvements, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications, in an amount in excess of one-half of 1 percent of the prime contractor’s total bid, or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of 1 percent of the prime contractor’s total bid or ten thousand dollars ($10,000), whichever is greater.”
“(b) The portion of the work which will be done by each such subcontractor under this act. The prime contractor shall list only one subcontractor for each such portion as is defined by the prime contractor in his bid.”
If the Contractor fails to specify a Subcontractor or specifies more than one Subcontractor for the same portion of the work to be performed under the Contract (in excess of one -half of 1 percent of the Contractor’s total Bid), the Contractor shall be qualified to perform that portion itself, and shall perform that portion itself, except as otherwise provided in the Code.
As provided in Section 4107, no Contractor whose Bid is accepted shall substitute any person as Subcontractor in place of the Subcontractor listed in the original Bid, except for causes and by procedures established in Section 4107.5. This section provides procedures to correct a clerical error in the listing of a Subcontractor.
Section 4110 provides that a Contractor violating any of the provisions of the Chapter violates the Contract and the Board may exercise the option either to cancel the Contract or assess the Contractor a penalty in an amount of not more than 10 percent of the subcontract involved, after a public hearing.
Revised 6/15/17 Contract No. 5552 Page 59 of 142
Should the Contractor fail to adhere to the provisions requiring the Contractor to complete 50 percent of the contract price with its own organization, the Agency may at its sole discretion elect to cancel the contract or deduct an amount equal to 10 percent of the value of the work performed in excess of 50 percent of the contract price by other than the Contractor’s own organization. The Board shall be the sole body for determination of a violation of these provisions. In any proceedings under this section, the prime contractor shall be entitled to a public hearing before the Board and shall be notified ten (10) days in advance of the time and location of said hearing. The determination of the Board shall be final.
2-3.2 Additional Responsibility. The Contractor shall give personal attention to the fulfillment of the Contract and shall keep the Work under its control.
The Contractor shall perform, with its own organization, Contract work amounting to at least 50 percent of the Contract Price except that any designated “Specialty Items” may be performed by subcontract, and the amount of any such “Specialty Items” so performed may be deducted from the Contract Price before computing the amount required to be performed by the Contractor with its own organization. “Specialty Items” will be identified by the Agency in the Bid or Proposal. Where an entire item is subcontracted, the value of work subcontracted will be based on the Contract Unit Price. When a portion of an item is subcontracted, the value of work subcontracted will be based on the estimated percentage of the Contract Unit Price. This will be determined from information submitted by the Contractor, and subject to approval by the Engineer.
Before the work of any Subcontractor is started, the Contractor shall submit to the Engineer for approval a written statement showing the work to be subcontracted giving the name and business of each Subcontractor and description and value of each portion of the work to be so subcontracted.
2-3.3 Status of Subcontractors. Subcontractors shall be considered employees of the Contractor, and the Contractor shall be responsible for their work.
2-4 CONTRACT BONDS. Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below.
Bonds issued by a surety, who is authorized to issue bonds in California, and whose bonding limitation shown in said circular is sufficient to provide bonds in the amount required by the Contract shall be deemed to be approved unless specifically rejected by the Agency. Bonds from all other sureties shall be accompanied by all of the documents enumerated in Code of Civil Procedure 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.
Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below. Bonds issued by a surety, who is authorized to issue bonds in California, and whose bonding limitation shown in said circular is sufficient to provide bonds in the amount required by the Contract shall be deemed to be approved unless specifically rejected by the Agency. Bonds from all other sureties shall be accompanied by all of the documents enumerated in Code of Civil Procedure 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals.
Each bond shall incorporate, by reference, the Contract and be signed by both the Bidder and Surety and the signature of the authorized agent of the Surety shall be notarized.
Revised 6/15/17 Contract No. 5552 Page 60 of 142
The Contractor shall provide a faithful performance/warranty bond and payment bond (labor and materials bond) for this contract. The faithful performance/warranty bond shall be in a sum not less than one hundred percent of the total amount payable by the terms of this contract. The Contractor shall provide bonds to secure payment of laborers and materials suppliers in a sum not less than one hundred percent of the total amount payable by the terms of this contract.
Both bonds shall extend in full force and effect and be retained by the Agency during this project until they are released according to the provisions of this section.
The faithful performance/warranty bond will be reduced to 25 percent of the original amount 30 days after recordation of the Notice of Completion and will remain in full force and effect for the one-year warranty period and until all warranty repairs are completed to the satisfaction of the Engineer. The bonds to secure payment of laborers and materials suppliers shall be released six months plus 30 days after recordation of the Notice of Completion if all claims have been paid.
All bonds are to be placed with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to contain the following documents:
1. An original, or a certified copy, of the un -revoked appointment, power of attorney, by laws, or other instrument entitling or authorizing the person who executed the bond to do so.
2. A certified copy of the certificate of authority of the insurer issued by the insurance commissioner.
If the bid is accepted, the Agency may require a financial statement of the assets and liabilities of the insurer at the end of the quarter calendar year prior to 30 days next preceding the date of the execution of the bond. The financial statement shall be made by an officer's certificate as defined in Section 173 of the Corporations Code. In the case of a foreign insurer, the financial statement may be verified by the oath of the principal officer or manager residing within the United States.
Should any bond become insufficient, the Contractor shall renew the bond within 10 days after receiving notice from the Agency.
Should any Surety at any time be unsatisfactory to the Board, notice will be given the Contractor to that effect. No further payments shall be deemed due or will be made under the contract until a new Surety shall qualify and be accepted by the Board.
Changes in the Work or extensions of time, made pursuant to the Contract, shall in no way release the Contractor or Surety from its obligations. Notice of such changes or extensions shall be waived by the Surety.
2-5 PLANS AND SPECIFICATIONS.
2-5.1 General. The Contractor shall keep at the Work site a copy of the Plans and Specifications, to which the Engineer shall have access at all times.
The specifications for the work include the General Provisions, Supplemental Provisions, Project Technical Specifications, Carlsbad Engineering Standards (CES), Standard Specifications for Public Works Construction (SSPWC) and the latest supplements thereto,
Revised 6/15/17 Contract No. 5552 Page 61 of 142
2024 edition as published by the "Greenbook" Committee of Public Works Standards, Inc., hereinafter designated "SSPWC", as amended.
The Plans shall consist of the construction drawings, Drawing No. 548-3 issued under this Contract.
The Standard Drawings consist of the latest edition of the San Diego Area Regional Standard Drawings, hereinafter designated SDRSD, as issued by the San Diego County Department of Public Works, together with the most recent editions of the City of Carlsbad Engineering Standards and Carlsbad Standard Drawings, as issued by the City of Carlsbad and the Carlsbad Municipal Water District , hereinafter designated as CES and CSD, respectively.
Modified standard drawings, if applicable, are enclosed in the appendices to these General Provisions.
The Plans, Specifications, and other Contract Documents shall govern the Work. The Contract Documents are intended to be complementary and cooperative. Anything specified in the Specifications and not shown on the Plans or shown on the Plans and not specified in the Specifications, shall be as though shown on or specified in both.
The Plans shall be supplemented by such working drawings and shop drawings as are necessary to adequately control the Work.
The Contractor shall ascertain the existence of any conditions affecting the cost of the Work through a reasonable examination of the Work site prior to submitting the Bid.
Existing improvements visible at the Work site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed and disposed of by the Contractor.
The Contractor shall, upon discovering any error or omission in the Plans or Specifications, immediately call it to the attention of the Engineer.
2-5.2 Precedence of Contract Documents.
If there is a conflict in the Contract Documents, the document highest in precedence shall control. The precedence shall be the most recent edition of the following documents listed in order of highest to lowest precedence:
1. Permits from other agencies as may be required by law.
2. Change orders, whichever occurs last.
3. Contract addenda, whichever occurs last.
4. Contract.
5. Carlsbad General and Supplemental Provisions.
6. Carlsbad Engineering Standards.
7. Technical Specifications.
8. Plans.
9. Standards Plans.
a. City of Carlsbad Standard Drawings.
b. City of Carlsbad modifications to the San Diego Area Regional Standard Drawings. c. San Diego Area Regional Standard Drawings.
d. Traffic Signal Design Guidelines and Standards.
Revised 6/15/17 Contract No. 5552 Page 62 of 142
e. State of California Department of Transportation Standard Plans. f. State of California Department of Transportation Standard Specifications. g. California Manual on Uniform Traffic Control Devices (CA MUTCD).
10. Standard Specifications for Public Works Construction, as amended.
11. Reference Specifications.
12. Manufacturer’s Installation Recommendations
Detail drawings shall take precedence over general drawings.
Detailed plans and plan views shall have precedence over general plans.
2-5.2.1 Precedence of Caltrans Specifications. Where Caltrans specifications are used to modify the SSPWC or are added to the SSPWC by the Contract Documents , the Caltrans specifications shall have precedence only in reference to the materials referred to in the Caltrans specifications. The documents listed in Section 2 -5.2 above, in their order of precedence above, shall prevail over the Caltrans specifications in all other matters.
2-5.3 Submittals.
2-5.3.1 General. Submittals shall be provided, at the Contractor’s expense, as required in 2-5.3.2, 2 -5.3.3 and 2 -5.3.4, when required by the Plans or Special Provisions, or when requested by the Engineer.
One electronic (PDF) file shall be submitted. If revisions are required, the Engineer will return one redlined copy for resubmission. Upon acceptance, the Engineer will return one electronic copy to the Contractor.
Materials shall neither be furnished nor fabricated, nor shall any work for which submittals are required be performed, before the required submittals have been reviewed and accepted by the Engineer. Neither review nor acceptance of submittals by the Engineer shall relieve the Contractor from responsibility for errors, omissions, or deviations from the Contract Documents, unless such deviations were specifically called to the attention of the Engineer in the letter of transmittal. The Contractor shall be responsible for the correctness of the submittals.
The Contractor shall allow a minimum of 20 working days for review of submittals unless otherwise specified in the Special Provisions. Each submittal shall be accompanied by a letter of transmittal.
Each submittal shall be consecutively numbered. Resubmittals shall be labeled with the number of the original submittal followed by an ascending alphabetical designation (e.g. The label ‘4 -C’ would indicate the third instance that the fourth submittal had been given to the Engineer). Each sheet of each submittal shall be consecutively numbered. Each set of shop drawings and submittals shall be accompanied by a letter of transmittal on the Contractor’s letterhead. The letter of transmittal shall contain the following:
1. Project title and Agency contract number.
2. Number of complete sets.
3. Contractor’s certification statement.
4. Specification section number(s) pertaining to material submitted for review.
5. Submittal number (Submittal numbers shall be consecutive including subsequent submittals for the same materials.)
Revised 6/15/17 Contract No. 5552 Page 63 of 142
6. Description of the contents of the submittal.
7. Identification of deviations from the Contract Documents.
8. The signature, printed name, title and company name of the Contractor’s representative.
The Contractor shall subscribe to and shall place the following certification on all submittals:
“I hereby certify that the (equipment, material, procedure(s)) shown and marked in this submittal is that proposed to be incorporated into this Project, is in compliance with the Contract Documents, can be installed in the allocated spaces, and is submitted for approval.”
Or
“
I hereby certify that the (equipment, material, procedure(s)) contained herein meet all requirements shown or specified in the Contract Documents, except for the following deviation(s):
.”
2-5.3.2 Working Drawings. Working drawings are drawings showing details not shown on the Plans which are required to be designed by the Contractor. Working drawings shall be of a size and scale to clearly show all necessary details.
Working drawings are required in the following sections:
TABLE 2-5.3.2
Item Section Number Title Subject
1 7-8.6.1 Dewatering Excavation Dewatering
2 7-10.4.1 Safety Orders Trench Shoring
3 7-10.4.8 Steel Plate Covers Steel Plate Bridging
4 300-3.2 Cofferdams Structure Excavation & Backfill
5 300-12.1 SWPPP SWPPP
6 303-1.6.1 General Falsework
7 303-1.7.1 General Placing Reinforcement
8 303-3.1 General Prestressed Concrete Construction
9 304-1.1.2 Falsework Plans Structural Steel
10 307-1.1 General Jacking Operations
11 307-2.1 General Tunneling Operations
12 306-8 Microtunneling Microtunneling Operations
13 601-2 Temporary Traffic Control Plan Traffic Control 14 02690 Temporary Sewer Bypass Pumping Sewer Bypassing
Working drawings listed above as Items 2, 3, 4, 7, 8, 9, 10, 11, 12, and 13 shall be prepared by a Civil or Structural Engineer registered by the State of California.
2-5.3.3 Shop Drawings. Shop drawings are drawings showing details of manufactured or assembled products proposed to be incorporated into the Work. Shop drawings are required in as specified in the Special Provisions.
2-5.3.4 Supporting Information. Supporting information is information required by the Specifications for the purposes of administration of the Contract, analysis for verification of conformance with the Specifications, the operation and maintenance of a manufactured product
Revised 6/15/17 Contract No. 5552 Page 64 of 142
or system to be constructed as part of the Work, and other information as may be required by the Engineer. Three hard copies and one electronic (PDF) file of the supporting information shall be submitted to the Engineer prior to the start of the Work unless otherwise specified in the Special Provisions or directed by the Engineer. Supporting information for systems shall be bound together and include all manufactured items for the system. If resubmittal is not required, one red lined copy will be returned to the Contractor. Supporting information shall consist of the following and is required unless otherwise specified in the Special Provisions:
1. List of Subcontractors per 2-3.2.
2. List of Materials per 4-1.4.
3. Certifications per 4-1.5.
4. Construction Schedule per 6-1 and Work Plan per 6-2.2.
5. Confined Space Entry Program per 7-10.4.4.
6. Concrete mix designs per 201-1.1.
7. Asphalt concrete mix designs per 203-6.1.
8. Data, including, but not limited to, catalog sheets, manufacturer’s brochures, technical bulletins, specifications, diagrams, product samples, and other information necessary to describe a system, product or item. This information is required for irrigation systems, street lighting systems, and traffic signals, and may also be required for any product, manufactured item, or system.
9. Temporary sewer bypass plan per Technical Specifications.
2-5.4 Record Drawings . The Contractor shall maintain a complete "as -built" record set of blue-line prints, which shall be corrected in red ink daily and show every change from the original drawings and specifications and the exact "as -built" locations, sizes and kinds of equipment, underground piping, conduits, valves, and all other work not visible at surface grade.
Prints for this purpose may be obtained from the Agency at cost. The official record drawing shall accurately reflect all changes and modifications to the original plan. The Contractor shall formally submit the final record drawing at the final walk -through meeting. At the direction of the Engineer, the Contractor shall correct and revise the Record Drawings to accurately reflect field conditions. Re -submittal of the Record Drawings shall be completed within ten (10) working days of the final walk -through meeting date and shall reflect any additional punch list items.
Payment for the upkeep, revision, and submittal of the record drawings shall be included in the lump sum price for mobilization.
2-6 WORK TO BE DONE. The Contractor shall perform all work necessary to complete the Contract in a satisfactory manner. Unless otherwise provided, the Contractor shall furnish all materials, equipment, tools, labor, and incidentals necessary to complete the Work.
2-7 SUBSURFACE DATA. All soil and test hole data, water table elevations, and soil or groundwater analyses shown on the drawings or included in the Specifications apply only at the location of the test holes and to the depths indicated. Soil test reports for test holes which have been drilled are available for inspection at the office of the Engineer.
The Contractor may make independent investigations of the project site, including evaluation of the soil or groundwater conditions and/or the presence of rock, in order to characterize the subsurface conditions that may be encountered to the Contractor’s satisfaction. The costs for such investigations shall be considered included in the bid price and no additional compensation will be made therefor.
Revised 6/15/17 Contract No. 5552 Page 65 of 142
The indicated elevation of the water table is that which existed on the date when test hole data was determined. It is the Contractor’s responsibility to determine and allow for the elevation of groundwater at the time of project construction. A difference in elevation between groundwater shown in soil boring logs and groundwater actually encountered during construction will not be considered as a basis for extra work.
2-8 RIGHT-OF-WAY. Rights-of-way, easements, or rights -of-entry for the Work, when indicated on the Plans, will be provided by the Agency. Unless otherwise provided, the Contractor shall make arrangements, pay for, and assume all responsibility for acquiring, using, and restoring additional work areas and removing and/or disposing of facilities temporarily required. The Contractor shall indemnify and hold the agency harmless from all claims for damages caused by such actions.
2-9 SURVEYING.
2-9.1 General. The Contractor will perform and be responsible for the accuracy of surveying adequate for construction. The Contractor shall set and preserve construction survey stakes and marks for the duration of their usefulness. If any construction survey stakes are lost or disturbed and need to be replaced, such replacement shall be performed at the expense of the Contractor.
The Contractor shall notify the Engineer in writing at least 2 Working Days before survey services in connection with the laying out of any portion of the Work. The Contractor shall set all stakes for line and grade. Setting tolerances for construction staking shall conform with Chapter 12, Construction Surveys of the Caltrans Surveys Manual. Surveying to determine the boundaries of the public right-of-way or easements shall conform with Chapter 10, Right-of-Way Surveys.
Unless otherwise specified in the Special Provisions, stakes will be set and stationed for alignments for pipelines (sewers, storm drains, potable water, recycled water) and their appurtenances, curbs, headers, structures, rough grade, finish grade and right -of-way or easement boundaries. A corresponding cut or fill to finished grade (or flowline) will be indicated on a grade sheet.
2-9.2 Permanent Survey Markers. The Contractor shall not cover or disturb permanent survey monuments or benchmarks without the consent of the Engineer. Where the Engineer concurs, in writing, with the Contractor that protecting an existing monument in place is impractical, the Contractor shall employ a licensed land surveyor or a registered civil engineer authorized to practice land surveying within the State of California, hereinafter Surveyor, to establish the location of the monument before it is disturbed. The Contractor shall have the monument replaced by the Surveyor no later than thirty (30) days after construction at the site of the replacement is completed. The Surveyor shall file corner record(s) as required by §§ 8772 and 8773, et seq. of the California Business and Professions Code.
The Contractor shall have a Record of Survey prepared by the Surveyor and file it in conformance with §8700 - 8805 of the State of California Business and Professions Code when the Surveyor performs any surveying that such map is required under §8762 of the State of California Business and Professions Code and whenever the Surveyor shall establish, set or construct any permanent survey monument. SDRS Drawing No. M -10 type monuments, bolts, spikes, leaded tacks and nails (when set in concrete), iron pipes, reinforcing steel and all monuments and marks that are at, or accessory to, property corners and street centerlines are
Revised 6/15/17 Contract No. 5552 Page 66 of 142
permanent survey monuments. The Record of Survey shall show all monuments set, control monuments used, the basis of bearings and all other data needed to determine the procedure of survey and the degree of accuracy attained by the field surveying including the unadjusted ratio of closure. The unadjusted ratio of closure shall not exceed 1 part in 40,000. The Record of Survey shall show the location and justification of location of all permanent monuments set and their relation to the street right -of-way. Record(s) of Survey(s) shall be submitted for the Engineer’s review and approval before submittal to the County Surveyor and before submittal to the County Recorder.
When a change is made in the finished elevation of the pavement of any roadway in which a permanent survey monument is located, the Contractor shall adjust the monument frame and cover to the new grade within 7 days of paving unless the Engineer shall approve otherwise.
Monument frames and covers shall be protected during street sealing or painting projects or be cleaned to the satisfaction of the Engineer.
2-9.3 Line and Grade. All work shall conform to the lines, elevations, and grades shown on the Plans.
Three consecutive points set on the same slope shall be used together so that any variation from a straight grade can be detected. Any such variation shall be reported to the Engineer. In the absence of such report, the Contractor shall be responsible for any error in the grade of the Work.
Grades for underground conduits will be set at the surface of the ground. The Contractor shall transfer them to the bottom of the trench.
2-9.4 Payment for Survey, Payment for survey work shall be included in the bid items requiring the survey work and no additional payment will be made. Extension of unit prices for extra work shall include full compensation for attendant survey work and no additional payment will be made. Payment for the replacement of disturbed monuments and the filing of records of survey and/or corner records, including filing fees, shall be incidental to the work necessitating the disturbance of said monuments and no additional payment will be made.
2-10 AUTHORITY OF BOARD AND ENGINEER . The Board has the final authority in all matters affecting the Work. Within the scope of the Contract, the Engineer has the authority to enforce compliance with the Plans and Specifications. The Contractor shall promptly comply with instructions from the Engineer or an authorized representative.
The decision of the Engineer is final and binding on all questions relating to: quantities; acceptability of material, equipment, or work; execution, progress or sequence of work; and interpretation of the Plans, Specifications, or other drawings. This shall be precedent to any payment under the Contract, unless otherwise ordered by the Board.
2-10.1 Availability of Records, The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor’s or subcontractor’s possession pertaining to the work that the Engineer may request.
2-10.2 Audit and Inspection, Contractor agrees to maintain and/or make available, to the Engineer, within San Diego County, accurate books and accounting records relative to all its activities and to contractually require all subcontractors to this Contract to do the same. The Engineer shall have the right to monitor, assess, and evaluate Contractor’s and its
Revised 6/15/17 Contract No. 5552 Page 67 of 142
subcontractors’ performance pursuant to this Agreement, said monitoring, assessments, and evaluations to include, but not be limited to, audits, inspection of premises, reports, contracts, subcontracts and interviews of Contractor’s staff and the staff of all subcontractors to this contract. At any time during normal business hours and as often as the Engineer may deem necessary, upon reasonable advance notice, Contractor shall make available to the Engineer for examination, all of its, and all subcontractors to this contract, records with respect to all matters covered by this Contract and will permit the Engineer to audit, examine, copy and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, payrolls, records of personnel, and other data relating to all matters covered by this Contract.
However, any such activities shall be carried out in a manner so as to not unreasonably interfere with Contractor’s ongoing business operations. Contractor and all subcontractors to this contract shall maintain such data and records for as long as may be required by applicable laws and regulations.
2-11 INSPECTION. The Work is subject to inspection and approval by the Engineer. The Contractor shall notify the Engineer before noon of the working day before inspection is required.
Work shall be done only in the presence of the Engineer, unless otherwise authorized. Any work done without proper inspection will be subject to rejection. The Engineer and any authorized representatives shall at all times have access to the Work during its construction at shops and yards as well as the project site. The Contractor shall provide every reasonable facility for ascertaining that the materials and workmanship are in accordance with these Specifications.
Inspection of the Work shall not relieve the Contractor of the obligation to fulfill all conditions of the Contract.
Revised 6/15/17 Contract No. 5552 Page 68 of 142
SECTION 3 – CHANGES IN WORK
3-1 CHANGES REQUESTED BY THE CONTRACTOR.
3-1.1 General. Changes in the Plans and Specifications, requested in writing by the Contractor, which do not materially affect the Work and which are not detrimental to the Work or to the interests of the Agency, may be granted by the Engineer. Nothing herein shall be construed as granting a right to the Contractor to demand acceptance of such changes.
3-1.2 Payment for Changes Requested by the Contractor. If such changes are granted, they shall be made at a reduction in cost or no additional cost to the Agency.
3-2 CHANGES INITIATED BY THE AGENCY.
3-2.1 General. The Agency may change the Plans, Specifications, character of the work, or quantity of work provided the total arithmetic dollar value of all such changes, both additive and deductive, does not exceed 25 percent of the Contract Price. Should it become necessary to exceed this limitation, the change shall be by written Supplemental Agreement between the Contractor and Agency, unless both parties agree to proceed with the change by Change Order.
Change Orders shall be in writing and state the dollar value of the change or established method of payment, any adjustment in contract time of completion, and when negotiated prices are involved, shall provide for the Contractor’s signature indicating acceptance.
3-2.2 Payment.
3-2.2.1 Contract Unit Prices. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the work from that shown on the Plans or specified in the Specifications, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price.
If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications varies from the Bid quantity by 5 0 percent or less, payment will be made at the Contract Unit Price. If the actual quantity of said item of work varies from the Bid quantity by more than 50 percent, payment will be made per Section 3-2.2.2 or 3-2.2.3 as appropriate.
If a change is ordered in an item of work covered by a Contract Unit Price, and such change does involve a substantial change in the character of the work from that shown on the Plans or specified in the Specifications, an adjustment in payment will be made per Section 3-2.4.
3-2.2.2 Increases of More Than 5 0 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 5 0 percent, payment for the quantity in excess of 150 percent of the Bid quantity will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 3-3. The Extra Work per Section 3-3, basis of payment, shall not include fixed costs. Fixed costs shall be deemed to have been recovered by the Contractor through payment for 150 percent of the Bid quantity at the Contract Unit Price.
Revised 6/15/17 Contract No. 5552 Page 69 of 142
3-2.2.3 Decreases of More Than 5 0 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less than 50 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 3 -3; however, in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 5 0 percent of the Bid quantity at the Contract Unit Price.
3-2.3 Stipulated Unit Prices. Stipulated Unit Prices are unit prices established by the Agency in the Contract Documents as distinguished from Contract Unit Prices submitted by the Contractor. Stipulated Unit Prices may be used for the adjustment of Contract changes when so specified in the Special Provisions.
3-2.4 Agreed Prices. Agreed Prices are prices for new or unforeseen work, or adjustments in Contract Unit Prices per Section 3-2.2, established by mutual agreement between the Contractor and the Agency. If mutual agreement cannot be reached, the Engineer may direct the Contractor to proceed on the basis of Extra Work in accordance per Section 3-3, except as otherwise specified in Sections 3-2.2.2 and 3-2.2.3.
3.2.4.1 Schedule of Values. Prior to construction, Contractor shall provide a schedule of values for all lump sum bid items that shall be used for the purpose of progress payments. The prices shall be valid for the purpose of change orders to the project.
3.2.5 Eliminated Items. Should any Bid item be eliminated in its entirety, payment will be made to the Contractor for its actual costs incurred in connection with the eliminated item prior to notification in writing from the Engineer so stating its elimination. If material conforming to the Plans and Specifications is ordered by the Contractor for use in the eliminated item prior to the date of notification of elimination by the Engineer, and if the order for that material cannot be canceled, payment will be made to the Contractor for the actual cost of the material. In this case, the material shall become the property of the Agency. Payment will be made to the Contractor for its actual costs for any further handling. If the material is returnable, the material shall be returned and payment will be made to the Contractor for the actual cost of charges made by the supplier for returning the material and for handling by the Contractor. Actual costs, as used herein, shall be computed on the basis of Extra Work per Section 3-3.
3-3 EXTRA WORK.
3-3.1 General. New or unforeseen work will be classified as “extra work” when the Engineer determines that it is not covered by Contract Unit Prices or stipulated unit prices.
3-3.2 Payment.
3-3.2.1 General. When the price for the extra work cannot be agreed upon, the Agency will pay for the extra work based on the accumulation of costs as provided herein.
Revised 6/15/17 Contract No. 5552 Page 70 of 142
3-3.2.2 Basis for Establishing Costs.
(a) Labor. The costs of labor will be the actual cost for wages of workers performing the extra work at the time the extra work is done, plus employer payments of payroll taxes, workers compensation insurance, liability insurance, health and welfare, pension, vacation, apprenticeship funds, and other direct costs, resulting from Federal, State, or local laws, as well as assessments or benefits required by lawful collective bargaining agreements.
The use of a labor classification which would increase the extra work cost will not be permitted unless the Contractor establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportioned to all of their assigned work and only that applicable to extra work will be paid.
Nondirect labor costs, including superintendence, shall be considered part of the markup of Section 3-3.2.3 (a).
(b) Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus sales tax, freight, and delivery.
The Agency reserves the right to approve materials and sources of supply, or to supply materials to the Contractor if necessary, for the progress of the Work. No markup shall be applied to any material provided by the Agency.
(c) Tool and Equipment Rental. No payment will be made for the use of tools which have a replacement value of $200 or less.
Regardless of ownership, the rates and right -of-way delay factors to be used in determining rental and delay costs shall be the edition of the, “Labor Surcharge and Equipment Rental Rates” published by Caltrans, current at the time of the actual use of the tool or equipment. The right-of-way delay factors therein shall be used as multipliers of the rental rates for determining the value of costs for delay to the Contractor and subcontractors, if any. The labor surcharge rates published therein are not a part of this contract.
The rental rates paid shall include the cost of fuel, oil, lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Necessary loading and transportation costs for equipment used on the extra work shall be included.
If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to the Agency than holding it at the Work site, it shall be returned, unless the Contractor elects to keep it at the Work site, at no expense to the Agency.
All equipment shall be acceptable to the Engineer, in good working condition, and suitable for the purpose for which it is to be used. Manufacturer’s ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer.
Revised 6/15/17 Contract No. 5552 Page 71 of 142
The reported rental time for equipment already at the Work site shall be the duration of its use on the extra work. This time begins when equipment is first put into actual operation on the extra work, plus the time required to move it from its previous site and back, or to a closer site.
(d) Other Items. The Agency may authorize other items which may be required on the extra work, including labor, services, material, and equipment. These items must be different in their nature from those required for the Work and be of a type not ordinarily available from the Contractor or Subcontractors.
Invoices covering all such items in detail shall be submitted with the request for payment.
(e) Invoices. Vendors’ invoices for material, equipment rental and other expenditures shall be submitted with the request for payment. If the request for payment is not substantiated by invoices or other documentation, the Agency may establish the cost of the item involved at the lowest price which was current at the time of the report.
3-3.2.3 Markup.
(a) Work by Contractor. The following percentages shall be added to the Contractor's costs and shall constitute the markup for all overhead and profits:
1. Labor …………………………..… 20
2. Materials .……………………….. 15
3. Equipment Rental ……………… 15
4. Other Items and Expenditures .. 15
To the sum of the costs and markups provided for in this section, 1 percent shall be added as compensation for bonding.
(b) Work by Subcontractor. When all or any part of the extra work is performed by a Subcontractor, the markup established in Section 3 -3.2.3(a) shall be applied to the Subcontractor's actual cost of such work. A markup of 10 percent on the first $5,000 of the subcontracted portion of the extra work and a markup of 5 percent on work added in excess of $5,000 of the subcontracted portion of the extra work may be added by the Contractor.
3-3.3 Daily Reports by Contractor. When the price for the extra work cannot be agreed upon, the Contractor shall submit a daily report to the Engineer on forms approved by the Agency. Included are applicable delivery tickets, listing all labor, materials, and equipment involved for that day, and other services and expenditures when authorized. Payment for extra work will not be made until such time that the Contractor submits completed daily reports and all supporting documents to the Engineer. Failure to submit the daily report by the close of the next working day may waive any rights for that day. An attempt shall be made to reconcile the report daily, and it shall be signed by the Engineer and the Contractor. In the event of disagreement, pertinent notes shall be entered by each party to explain points which cannot be resolved immediately. Each party shall retain a signed copy of the report. Reports by Subcontractors or others shall be submitted through the Contractor.
The report shall:
1. Show names of workers, classifications, and hours worked.
2. Describe and list quantities of materials used.
Revised 6/15/17 Contract No. 5552 Page 72 of 142
3. Show type of equipment, size, identification number, and hours of operation, including loading and transportation, if applicable.
4. Describe other services and expenditures in such detail as the Agency may require.
3-4 CHANGED CONDITIONS. The Contractor shall promptly notify the Engineer of the following work site conditions (hereinafter called changed conditions), in writing, upon their discovery and before they are disturbed:
1. Subsurface or latent physical conditions differing materially from those represented in the Contract Documents;
2. Unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in work of the character being performed; and
3. Material differing from that represented in the Contract which the Contractor believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
The Engineer will promptly investigate conditions which appear to be changed conditions. If the Engineer determines that conditions are changed conditions and they will materially affect performance time, the Contractor, upon submitting a written request, will be granted an extension of time subject to the provisions of 6-6.
If the Engineer determines that the conditions do not justify an adjustment in compensation, the Contractor will be notified in writing. This notice will also advise the Contractor of its obligation to notify the Engineer in writing if the Contractor disagrees.
The Contractor’s failure to give notice of changed conditions promptly upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith.
The Contractor shall not be entitled to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, or for the happening of any event, thing, occurrence, or other cause, unless the Contractor shall have first given the Engineer due written notice of potential claim as hereinafter specified. Compliance with this section shall not be required as a prerequisite to notice provisions in Section 6 -7.3 Contract Time Accounting, nor to any claim that is based on differences in measurement or errors of computation as to contract quantities. The written notice of potential claim for changed conditions shall be submitted by the Contractor to the Engineer upon their discovery and prior to the time that the Contractor performs the work giving rise to the potential claim. The Contractor’s failure to give written notice of potential claim for changed conditions to the agency upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith.
The Contractor shall provide the City with a written document containing a description of the particular circumstances giving rise to the potential claim, the reasons for which the Contractor believes additional compensation may be due and nature of any and all costs involved within 20 working days of the date of service of the written notice of potential claim for changed conditions. Verbal notifications are disallowed.
The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-12655:
Revised 6/15/17 Contract No. 5552 Page 73 of 142
“The undersigned certifies that the above statements are made in full cognizance of the California False Claims Act, Government Code Sections 12650-12655. The undersigned further understands and agrees that this potential claim, unless resolved, must be restated as a claim in response to the City’s proposed final estimate in order for it to be further considered.”
By: ___________________________________ Title: ______________________________
Date: _________________________________
Company Name: ______________________________________________________________
The Contractor’s estimate of costs may be updated when actual costs are known. The Contractor shall submit substantiation of its actual costs to the Engineer within 20 working days after the affected work is completed. Failure to do so shall be sufficient cause for denial of any claim subsequently filed on the basis of said notice of potential claim.
It is the intention of this section that differences between the parties arising under and by virtue of the contract be brought to the attention of the Engineer at the earliest possible time in order that such matters be settled, if possible, or other appropriate action promptly taken.
3-5 DISPUTED WORK. The Contractor shall give the Agency written notice of potential claim prior to commencing any disputed work. Failure to give said notice shall constitute a waiver of all claims in connection therewith. If the Contractor and the Agency are unable to reach agreement on disputed work, the Agency may direct the Contractor to proceed with the Work.
Prior to proceeding with dispute resolution pursuant to Public Contract Code provisions specified hereinafter, the contractor shall attempt to resolve all disputes informally through the following dispute resolution chain of command:
1. Project Inspector
2. Construction Manager
3. Deputy City Engineer
4. City Engineer
5. City Manager
The Contractor shall submit a complete report within 20 working days after completion of the disputed work stating its position on the claim, the contractual basis for the claim, along with all documentation supporting the costs and all other evidentiary materials. At each level of claim or appeal of claim the City will, within 10 working days of receipt of said claim or appeal of claim, review the Contractor’s report and respond with a position, request additional information or request that the Contractor meet and present its report. When additional information or a meeting is requested, the City will provide its position within 10 working days of receipt of said additional information or Contractor’s presentation of its report. The Contractor may appeal each level’s position up to the City Manager after which the Contractor may proceed under the provisions of the Public Contract Code.
The authority within the dispute resolution chain of command is limited to recommending a resolution to a claim to the City Manager. Actual approval of the claim is subject to the change order provisions in the contract.
Revised 6/15/17 Contract No. 5552 Page 74 of 142
All claims by the -Contractor shall be resolved in accordance with Public Contract Code section 9204, which is set forth below:
9204. (a) The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is complete and not in dispute is paid in full and in a timely manner.
(b) Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 (commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project.
(c) For purposes of this section:
(1) “Claim” means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following:
(A) A time extension, including, without limitation, for relief from damages or penalties for delay assessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. (2) “Contractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct contract with a public entity for a public works project. (3) (A) “Public entity” means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, district, special district, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency. (B) “Public entity” shall not include the following:
(i) The Department of Water Resources as to any project under the jurisdiction of that department.
(ii) The Department of Transportation as to any project under the jurisdiction of that department. (iii) The Department of Parks and Recreation as to any project under the jurisdiction of that department.
(iv) The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code.
(v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority.
(4) “Public works project” means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind. (5) “Subcontractor” means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor. (d) (1) (A) Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is
Revised 6/15/17 Contract No. 5552 Page 75 of 142
disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision. (B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45 -day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written statement, paragraph (3) shall apply.
(2) (A) If the claimant disputes the public entity’s written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute.
(B) Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.
If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section.
(C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section. (D) Unless otherwise agreed to by the public entity and the contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.
(E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties’ dispute.
(3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entity’s failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifications of the claimant. (4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum.
Revised 6/15/17 Contract No. 5552 Page 76 of 142
(5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written request, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim, provide the subcontractor with a statement of the reasons for not having done so.
(e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section.
(f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section.
(g) This section applies to contracts entered into on or after January 1, 2017.
(h) Nothing in this section shall impose liability upon a public entity that makes loans or grants available through a competitive application process, for the failure of an awardee to meet its contractual obligations.
(i) This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date.
In addition, all claims by Contractor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5 (commencing with Section 20104) which is set forth below.
ARTICLE 1.5 RESOLUTION OF CONSTRUCTION CLAIMS
20104. (a)(1) This article applies to all public works claims of three hundred seventy -five thousand dollars ($375,000) or less which arise between a contractor and a local agency. (2) This article shall not apply to any claims resulting from a contract between a contractor and a public agency when the public agency has elected to resolve any disputes pursuant to Article
7.1 (commencing with Section 10240) of Chapter 1 of Part 2. (b)(1) "Public work" has the same meaning as in Sections 3100 and 3106 of the Civil Code, except that "public work" does not include any work or improvement contracted for by the state or the Regents of the University of California.
(2) "Claim" means a separate demand by the contractor for (A) a time extension, (B) payment of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public work and payment of which is not otherwise expressly provided for or the
Revised 6/15/17 Contract No. 5552 Page 77 of 142
claimant is not otherwise entitled to, or (C) an amount the payment of which is disputed by the local agency.
(c) The provisions of this article or a summary thereof shall be set forth in the plans or specifications for any work which may give rise to a claim under this article. (d) This article applies only to contracts entered into on or after January 1, 1991.
20104.2. For any claim subject to this article, the following requirements apply:
(a) The claim shall be in writing and include the documents necessary to substantiate the claim.
Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims.
(b)(1) For claims of less than fifty thousand dollars ($50,000), the local agency shall respond in writing to any written claim within 45 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant. (2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the claimant within 15 days after receipt of the further documentation or within a period of time no greater than that taken by the claimant in producing the additional information, whichever is greater.
(c)(1) For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant.
(2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the claimant within 30 days after receipt of the further documentation, or within a period of time no greater than that taken by the claimant in producing the additional information or requested documentation, whichever is greater.
(d) If the claimant disputes the local agency's written response, or the local agency fails to respond within the time prescribed, the claimant may so notify the local agency, in writing, either within 15 days of receipt of the local agency's response or within 15 days of the local agency's failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, the local agency shall schedule a meet and confer conference within 30 days for settlement of the dispute. (e) Following the meet and confer conference, if the claim or any portion remains in dispute, the claimant may file a claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code.
For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the claimant submits his or her written claim pursuant to subdivision (a) until the time that claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process. (f) This article does not apply to tort claims and nothing in this article is intended nor shall be construed to change the time periods for filing tort claims or actions specified by Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code.
Revised 6/15/17 Contract No. 5552 Page 78 of 142
20104.4. The following procedures are established for all civil actions filed to resolve claims subject to this article:
(a) Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to non -binding mediation unless waived by mutual stipulation of both parties. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to select a mediator within the 15 -day period, any party may petition the court to appoint the mediator.
(b)(1) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil procedure) shall apply to any proceeding brought under the subdivision consistent with the rules pertaining to judicial arbitration.
(2) Notwithstanding any other provision of law, upon stipulation of the parties, arbitrators appointed for purposes of this article shall be experienced in construction law, and, upon stipulation of the parties, mediators and arbitrators shall be paid necessary and reasonable hourly rates of pay not to exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no event shall these fees or expenses be paid by state or county funds.
(3) In addition to Chapter 2.5 (commencing with Section 1141.10) Title 3 of Part 3 of the Code of Civil Procedure, any party who after receiving an arbitration award requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, pay the attorney's fees of the other party arising out of the trial de novo. (c) The court may, upon request by any party, order any witnesses to participate in the mediation or arbitration process.
20104.6. (a) No local agency shall fail to pay money as to any portion of a claim which is undisputed except as otherwise provided in the contract. (b) In any suit filed under Section 20104.4, the local agency shall pay interest at the legal rate on any arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court of law.
Although not to be construed as proceeding under extra work provisions, the Contractor shall keep and furnish records of disputed work in accordance with Section 3-3.
Revised 6/15/17 Contract No. 5552 Page 79 of 142
SECTION 4 – CONTROL OF MATERIALS
4-1 MATERIALS AND WORKMANSHIP.
4-1.1. General. All materials, parts, and equipment furnished by the Contractor in the Work shall be new, high grade, and free from defects. Quality of work shall be in accordance with the generally accepted standards. Material and work quality shall be subject to the Engineer’s approval.
Materials and work quality not conforming to the requirements of the Specifications shall be considered defective and will be subject to rejection. Defective work or material, whether in place or not, shall be removed immediately from the site by the Contractor, at its expense, when so directed by the Engineer.
If the Contractor fails to replace any defective or damaged work or material after reasonable notice, the Engineer may cause such work or materials to be replaced. The replacement expense will be deducted from the amount to be paid to the Contractor.
Used or secondhand materials, parts, and equipment may be used only if permitted by the Specifications.
4-1.2 Protection of Work and Materials. The Contractor shall provide and maintain storage facilities and employ such measures as will preserve the specified quality and fitness of materials to be used in the Work. Stored materials shall be reasonably accessible for inspection.
The Contractor shall also adequately protect new and existing work and all items of equipment for the duration of the Contract.
The Contractor shall not, without the Agency’s consent, assign, sell, mortgage, hypothecate, or remove equipment or materials which have been installed or delivered and which may be necessary for the completion of the Contract.
4-1.3 Inspection Requirements.
4-1.3.1 General. Unless otherwise specified, inspection is required at the source for such typical materials and fabricated items as bituminous paving mixtures, structural concrete, metal fabrication, metal casting, welding, concrete pipe manufacture, protective coating application, and similar shop or plant operations.
Steel pipe in sizes less than 6 inches and vitrified clay and cast -iron pipe in all sizes are acceptable upon certification as to compliance with the Specifications, subject to sampling and testing by the Agency. Standard items of equipment such as electric motors, conveyors, elevators, plumbing fixtures, etc., are subject to inspection at the job site only. Special items of equipment such as designed electrical panel boards, large pumps, sewage plant equipment, etc., are subject to inspection at the source, normally only for performance testing. The Specifications may require inspection at the source for other items not typical of those listed in this section.
The Contractor shall provide the Engineer free and safe access to any and all parts of work at any time. Such free and safe access shall include means of safe access and egress, ventilation, lighting, shoring, dewatering and all elements pertaining to the safety of persons as contained in
Revised 6/15/17 Contract No. 5552 Page 80 of 142
the State of California, California Code of Regulations, Title 8, Industrial Relations, Chapter 4, Division of Industrial Safety, Subchapter 4, Construction Safety Orders and such other safety regulations as may apply. Contractor shall furnish Engineer with such information as may be necessary to keep the Engineer fully informed regarding progress and manner of work and character of materials. Inspection or testing of the whole or any portion of the work or materials incorporated in the work shall not relieve Contractor from any obligation to fulfill this Contract.
4-1.3.2 Inspection of Materials Not Locally Produced. When the Contractor intends to purchase materials, fabricated products, or equipment from sources located more than 50 miles outside the geographical limits of the Agency, an inspector or accredited testing laboratory (approved by the Engineer), shall be engaged by the Contractor at its expense, to inspect the materials, equipment or process. This approval shall be obtained before producing any material or equipment. The inspector or representative of the testing laboratory shall judge the materials by the requirements of the Plans and Specifications. The Contractor shall forward reports required by the Engineer. No material or equipment shall be shipped nor shall any processing, fabrication or treatment of such materials be done without proper inspection by the approved agent. Approval by said agent shall not relieve the Contractor of responsibility for complying with the Contract requirements.
4-1.3.3 Inspection by the Agency. The Agency will provide all inspection and testing laboratory services within 50 miles of the geographical limits of the Agency. For private contracts, all costs of inspection at the source, including salaries and mileage costs, shall be paid by the permittee.
4-1.4 Test of Material. Before incorporation in the Work, the Contractor shall submit samples of materials, as the Engineer may require, at no cost to the Agency. The Contractor, at its expense, shall deliver the materials for testing to the place and at the time designated by the Engineer. Unless otherwise provided, all initial testing will be performed under the direction of the Engineer, and at no expense to the Contractor. If the Contractor is to provide and pay for testing, it will be stated in the Specifications. For private contracts, the testing expense shall be borne by the permittee.
The Contractor shall notify the Engineer in writing, at least 15 days in advance, of its intention to use materials for which tests are specified, to allow sufficient time to perform the tests. The notice shall name the proposed supplier and source of material.
If the notice of intent to use is sent before the materials are available for testing or inspection or is sent so far in advance that the materials on hand at the time will not last but will be replaced by a new lot prior to use on the Work, it will be the Contractor’s responsibility to renotify the Engineer when samples which are representative may be obtained.
Except as specified in these Provisions, the Agency will bear the cost of testing of locally produced materials and/or on-site workmanship where the results of such tests meet or exceed the requirements indicated in the Standard Specifications, Technical Specification, and any Supplemental Provisions. The cost of all other tests shall be borne by the Contractor.
At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before the delivery is started. All materials proposed for use may be inspected or tested at any time during their preparation and use. If, after incorporating such materials into the Work, it is found that sources of supply that have been approved do not furnish a uniform product, or if the product from any source proves unacceptable at any time, the Contractor shall
Revised 6/15/17 Contract No. 5552 Page 81 of 142
furnish approved material from other approved sources. If any product proves unacceptable after improper storage, handling or for any other reason it shall be rejected, not incorporated into the work and shall be removed from the project site all at the Contractor’s expense.
Compaction tests may be made by the Engineer and all costs for tests that meet or exceed the requirements of the specifications shall be borne by the Agency. Said tests may be made at any place along the work as deemed necessary by the Engineer. The costs of any retests made necessary by noncompliance with the specifications shall be borne by the Contractor.
4-1.5 Certification. The Engineer may waive materials testing requirements of the Specifications and accept the manufacturer’s written certification that the materials to be supplied meet those requirements. Material test data may be required as part of the certification.
4-1.6 Trade Names or Equals. The Contractor may supply any of the materials specified or offer an equivalent. The Engineer shall determine whether the material offered is equivalent to that specified. Adequate time shall be allowed for the Engineer to make this determination.
Whenever any particular material, process, or equipment is indicated by patent, proprietary or brand name, or by name of manufacturer, such wording is used for the purpose of facilitating its description and shall be deemed to be followed by the words “or equal”. A listing of materials is not intended to be comprehensive, or in order of preference. The Contractor may offer any material, process, or equipment considered to be equivalent to that indicated.
The substantiation of offers shall be submitted as provided in the Contract Documents.
The Contractor shall, at its expense, furnish data concerning items offered by it as equivalent to those specified. The Contractor shall have the material tested as required by the Engineer to determine that the quality, strength, physical, chemical, or other characteristics, including durability, finish, efficiency, dimensions, service, and suitability are such that the item will fulfill its intended function.
Test methods shall be subject to the approval of the Engineer. Test results shall be reported promptly to the Engineer, who will evaluate the results and determine if the substitute item is equivalent. The Engineer’s findings shall be final. Installation and use of a substitute item shall not be made until approved by the Engineer.
If a substitute offered by the Contractor is not found to be equal to the specified material, the Contractor shall furnish and install the specified material.
The specified Contract completion time shall not be affected by any circumstance developing from the provisions of this section.
The Contractor is responsible for the satisfactory performance of substituted items. If, in the sole opinion of the Engineer, the substitution is determined to be unsatisfactory in performance, appearance, durability, compatibility with associated items, availability of repair parts and suitability of application the Contractor shall remove the substituted item and replace it with the originally specified item at no cost to the Agency.
4-1.7 Weighing and Metering Equipment. All scales and metering equipment used for proportioning materials shall be inspected for accuracy and certified within the past 12 months by the State of California Bureau of Weights and Measures, by the County Director or Sealer of Weights and Measures, or by a scale mechanic registered with or licensed by the County.
Revised 6/15/17 Contract No. 5552 Page 82 of 142
The accuracy of the work of a scale service agency, except as stated herein, shall meet the standards of the California Business and Professions Code and the California Code of Regulations pertaining to weighing devices. A certificate of compliance shall be presented, prior to operation, to the Engineer for approval and shall be renewed whenever required by the Engineer at no cost to the Agency.
All scales shall be arranged so they may be read easily from the operator’s platform or area.
They shall indicate the true net weight without the application of any factor. The figures of the scales shall be clearly legible. Scales shall be accurate to within 1 percent when tested with the plant shut down. Weighing equipment shall be so insulated against vibration or moving of other operating equipment in the plant area that the error in weighing with the entire plant running will not exceed 2 percent for any setting nor 1.5 percent for any batch.
4-1.8 Calibration of Testing Equipment. Testing equipment, such as, but not limited to pressure gages, metering devices, hydraulic systems, force (load) measuring instruments, and strain-measuring devices shall be calibrated by a testing agency acceptable to the Engineer at intervals not to exceed 12 months and following repairs, modification, or relocation of the equipment. Calibration certificates shall be provided when requested by the Engineer.
4-1.9 Construction Materials Dispute Resolution (Soils, Rock Materials, Concrete, Mortar and Related Materials, Masonry Materials, Bituminous Materials, Rock Products, and Modified Asphalts). In the interest of safety and public value, whenever credible evidence arises to contradict the test values of materials, the Agency and the Contractor will initiate an immediate and cooperative investigation. Test values of materials are results of the materials’ tests, as defined by these Specifications or by the sp ecial provisions, required to accept the Work. Credible evidence is process observations or test values gathered using industry accepted practices. A contradiction exists whenever test values or process observations of the same or similar materials are diverse enough such that the work acceptance or performance becomes suspect. The investigation shall allow access to all test results, procedures, and facilities relevant to the disputed work and consider all available information and, when necessary, gather new and additional information in an attempt to determine the validity, the cause, and if necessary, the remedy to the contradiction. If the cooperative investigation reaches any resolution mechanism acceptable to both the Agency and the Contractor, the contradiction shall be considered resolved and the cooperative investigation concluded.
Whenever the cooperative investigation is unable to reach resolution, the investigation may then either conclude without resolution or continue by written notification of one party to the other requesting the implementation of a resolution process by committee. The continuance of the investigation shall be contingent upon recipient’s agreement and acknowledged in writing within 3 calendar days after receiving a request. Without acknowledgement, the investigation shall conclude without resolution. The committee shall consist of three State of California Registered Civil Engineers. Within 7 calendar days after the written request notification, the Agency and the Contractor wi ll each select one engineer. Within 14 calendar days of the written request notification, the two selected engineers will select a third engineer. The goal in selection of the third member is to complement the professional experience of the first two engineers. Should the two engineers fail to select the third engineer, the Agency and the Contractor shall each propose 2 engineers to be the third member within 21 calendar days after the written request notification. The first two engineers previously selecte d shall then select one of the four proposed engineers in a blind draw. The committee shall be a continuance of the cooperative investigation and will re -consider all available information and if necessary, gather new and additional information to determine the validity, the cause, and if necessary, the remedy to the contradiction. The committee will focus upon the performance adequacy of the material(s) using
Revised 6/15/17 Contract No. 5552 Page 83 of 142
standard engineering principles and practices and to ensure public value, the committee may provide engineering recommendations as necessary. Unless otherwise agreed, the committee will have 30 calendar days from its formation to complete their review and submit their findings.
The final resolution of the committee shall be by majority opinion, in writing, stamped and signed. Should the final resolution not be unanimous, the dissenter may attach a written, stamped, and signed minority opinion. Once started, the resolution process by committee shall continue to full conclusion unless:
1. Within 7 days of the formation of the committee, the Agency and the Contractor reach an acceptable resolution mechanism; or
2. Within 14 days of the formation of the committee, the initiating party withdraws its written notification and agrees to bear all investigative related costs thus far incurred; or
3. At any point by the mutual agreement of the Agency and the Contractor. Unless otherwise agreed, the Contractor shall bear and maintain a record for all the investigative costs until resolution. Should the investigation discover assignable causes for the contradiction, the assignable party, the Agency or the Contractor, shall bear all costs associated with the investigation. Should assignable causes for the contradiction extended to both parties, the investigation will assign costs cooperatively with each party or when necessary, equally. Should the investigation substantiate a contradiction without assignable cause, the investigation will assign costs cooperatively with each party or when necessary, equally. Should the investigation be unable to substantiate a contradiction, the initiator of the investigation shall bear all investigative costs. All claim notification requirements of the contract pertaining to the contradiction shall be suspended until the investigation is concluded.
4-2 MATERIALS TRANSPORTATION, HANDLING AND STORAGE. The Contractor shall order, purchase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, prepare storage area(s), store, handle, protect, move, relocate, remove and dispose excess of all materials used to accomplish the Work. Materials shall be delivered to the site of the work only during working hours, as defined in Section 6 -7.2, and shall be accompanied by bills of lading that shall clearly state for each delivery: the name of the Contractor as consignee, the project name and number, address of delivery and name of consignor and a description of the material(s) shipped. Prior to storage of any materials which have been shipped to or by the Contractor to any location within the Agency’s boundaries the Contractor shall provide the Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored and shall provide for the removal of the materials and restoration of the storage site within the time allowed for the Work. All such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the location of the site on which the materials are stored. Loss, damage or deterioration of all stored materials shall be the Contractor’s responsibility. Conformance to the requirements of this section, both within and outside the limits of work are a part of the Work.
The Engineer shall have the right to verify the suitability of materials and their proper storage at any time during the Work.
Revised 6/15/17 Contract No. 5552 Page 84 of 142
SECTION 5 – UTILITIES
5-1 LOCATION. The Agency and affected utility companies have, by a search of known records, endeavored to locate and indicate on the Plans, all utilities which are known to exist within the limits of the work. However, the accuracy and/or completeness of the nature, size and/or location of utilities indicated on the Plans is not guaranteed.
Where underground main distribution conduits such as water, gas, sewer, electric power, telephone, or cable television are shown on the Plans, the Contractor shall assume that every property parcel will be served by a service connection for each type of utility.
As provided in Section 4216 of the California Government Code, at least 2 working days prior to commencing any excavation, the Contractor shall contact the regional notification center (Underground Service Alert of Southern California) and obtain an inquiry identification number.
The California Department of Transportation is not required by Section 4216 to become a member of the regional notification center. The Contractor shall contact it for location of its subsurface installations.
Prior to pipeline excavation, t he Contractor shall determine, by potholing, the locations and depths of all utilities which are shown on the Contract Documents or have been marked by the utility owners and which may affect or be affected by its operations. The Contractor shall pothole all service connections, utilities that cross or parallel (within 5 feet) the proposed construction, and all connection points to existing utilities. The Contractor shall record the material size (outside diameter), type, and horizontal and vertical locations (bearing and slope) and submit the data and allow time for the Engineer’s review in accordance with Section 2-5.3.
If no separate pay item is provided in the Contract for potholing, full compensation for such work shall be considered included in the bid item of work requiring the potholing and no separate payment shall be made therefor.
5-2 PROTECTION. The Contractor shall not interrupt the service function or disturb the support of any utility without authority from the owner or order from the Agency. All valves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff.
Where protection is required to ensure support of utilities located as shown on the Plans or in accordance with Section 5-1, the Contractor shall, unless otherwise provided, furnish and place the necessary protection at its expense.
Upon learning of the existence and location of any utility omitted from or shown incorrectly on the Plans, the Contractor shall immediately notify the Engineer in writing. When authorized by the Engineer, support or protection of the utility will be paid for as provided in Section 3-2.2.3 or 3-3.
The Contractor shall immediately notify the Engineer and the utility owner if any utility is disturbed or damaged. The Contractor shall bear the costs of repair or replacement of any utility damaged if located as noted in Section 5-1.
When placing concrete around or contiguous to any non -metallic utility installation, the Contractor shall at its expense:
Revised 6/15/17 Contract No. 5552 Page 85 of 142
1. Furnish and install a 2 -inch cushion of expansion joint material or other similar resilient material; or
2. Provide a sleeve or other opening which will result in a 2 -inch minimum-clear annular space between the concrete and the utility; or
3. Provide other acceptable means to prevent embedment in or bonding to the concrete.
Where concrete is used for backfill or for structures which would result in embedment, or partial embedment, of a metallic utility installation; or where the coating, bedding or other cathodic protection system is exposed or damaged by the Contractor’s operations, the Contractor shall notify the Engineer and arrange to secure the advice of the affected utility owner regarding the procedures required to maintain or restore the integrity of the system.
5-3 REMOVAL. Unless otherwise specified, the Contractor shall remove all interfering portions of utilities shown on the Plans or indicated in the Bid documents as “abandoned” or “to be abandoned in place”. Before starting removal operations, the Contractor shall ascertain from the Agency whether the abandonment is complete, and the costs involved in the removal and disposal shall be included in the Bid for the items of work necessitating such removals.
The costs involved in the removal and disposal shall be considered incidental to the bid items of work necessitating such removals and no separate payment shall be made therefor, unless a bid item for “Removal” is specifically included in the bid proposal.
5-4 RELOCATION. When feasible, the owners responsible for utilities within the area affected by the Work will complete their necessary installations, relocations, repairs, or replacements before commencement of work by the Contractor. When the Plans or Specifications indicate that a utility installation is to be relocated, altered, or constructed by others, the Agency will conduct all negotiations with the owners and work will be done at no cost to the Contractor, except for manhole frame and cover sets to be brought to grade as directed and approved by the City. Utilities which are relocated in order to avoid interference shall be protected in their position and the cost of such protection shall be included in the Bid for the items of work necessitating such relocation.
After award of the Contract, portions of utilities which are found to interfere with the Work will be relocated, altered or reconstructed by the owners, or the Engineer may order changes in the Work to avoid interference. Such changes will be paid for in accordance with Section 3-2.
When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such work shall be included in the Bid for the items of work necessitating such work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its convenience shall be its responsibility and it shall make all arrangements and bear all costs.
The utility owner will relocate service connections as necessary within the limits of the Work or within temporary construction or slope easements. When directed by the Engineer, the Contractor shall arrange for the relocation of service connections as necessary between the meter and property line, or between a meter and the limits of temporary construction or slope easements. The relocation of such service connections will be paid for in accordance with provisions of Section 3 -3. Payment will include the restoration of all existing improvements which may be affected thereby. The Contractor may agree with the owner of any utility to disconnect and reconnect interfering service connections. The Agency will not be involved in any such agreement.
Revised 6/15/17 Contract No. 5552 Page 86 of 142
In conformance with Section 5 -6 the Contractor shall coordinate the work with utility agencies and companies. Prior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contractor, the Contractor shall place all curb or curb and gutter that is a part of the work and adjacent to the location where such utility structures are shown on the plans and are noted as being located, relocated or are otherwise shown as installed by others. In order to minimize delays to the Contractor caused by the failure of other parties to relocate utilities that interfere with the construction, the Contractor, upon the Engineer’s approval, may be permitted to temporarily omit the portion of work affected by the utility. If such temporary omission is approved by the Engineer, the Contractor shall place survey or other physical control markers sufficient to locate the curb or curb and gutter to the satisfaction of the utility agency or company. Such temporary omission shall be for the Contractor’s convenience and no additional compensation will be allowed therefore or for additional work, materials or delay associated with the temporary omission. The portion thus omitted shall be constructed by the Contractor immediately following the relocation of the utility involved unless otherwise directed by the Engineer.
5-5 DELAYS. The Contractor shall notify the Engineer of its construction schedule insofar as it affects the protection, removal, or relocation of utilities. Said notification shall be included as a part of the construction schedule required in Section 6 -1. The Contractor shall notify the Engineer in writing of any subsequent changes in the construction schedule which will affect the time available for protection, removal, or relocation of utilities.
The Contractor will not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, noted, and completed in accordance with Section 5-1.
The Contractor may be given an extension of time for unforeseen delays attributable to unreasonably protracted interference by utilities in performing work correctly shown on the Plans.
The Agency will assume responsibility for the timely removal, relocation, or protection of existing main or trunkline utility facilities within the area affected by the Work if such utilities are not identified in the Contract Documents. The Contractor will not be assessed liquidated damages for any delay caused by failure of Agency to provide for the timely removal, relocation, or protection of such existing facilities.
If the Contractor sustains loss due to delays attributable to interferences, relocations, or alterations not covered by Section 5 -1, which could not have been avoided by the judicious handling of forces, equipment, or plant, there shall be paid to the Contractor such amount as the Engineer may find to be fair and reasonable compensation for such part of the Contractor’s actual loss as was unavoidable and the Contractor may be granted an extension of time.
5-6 COOPERATION. When necessary, the Contractor shall so conduct its operations as to permit access to the Work site and provide time for utility work to be accomplished during the progress of the Work. Cooperation with CMWD and City staff will be required for all work affecting existing utility systems or facilities and prior to water utility shutdowns, sewer bypass operations, testing and inspections, and project completion.
Revised 6/15/17 Contract No. 5552 Page 87 of 142
SECTION 6 – PROSECUTION, PROGRESS,
AND ACCEPTANCE OF THE WORK
6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK . Except as otherwise provided herein and unless otherwise prohibited by permits from other agencies as may be required by law the Contractor shall begin work within ten (10) calendar days after receipt of the "Notice to Proceed".
6-1.1 Pre-Construction Meeting. After, or upon, notification of contract award, the Engineer will set the time and location for the Preconstruction Meeting. Attendance of the Contractor’s management personnel responsible for the management, administration, and execution of the project is mandatory for the meeting to be convened. Failure of the Contractor to have the Contractor’s responsible project personnel attend the Preconstruction Meeting will be grounds for default by Contractor per Section 6-4. No separate payment will be made for the Contractor’s attendance at the meeting. The notice to proceed will only be issued on or after the completion of the preconstruction meeting.
6-1.1.1 Baseline Construction Schedule . The Contractor shall prepare the Baseline Construction Schedule as a Critical Path Method (CPM) Schedule in the precedence diagram method (activity -on-node) format and submit the schedule in accordance with 2 -5.3. The schedule shall:
A. Be prepared using a commercially available, Windows compatible software program, “Suretrak” by Primavera or “Project” by Microsoft Corporation or approved equal.
B. Be prepared in hard copy (paper) and electronic (Adobe PDF) format and free of file locking, encryption or any other protocol that would impede full access to the data and labeled with the project name and number, the Contractor’s name and the date of preparation.
C. Begin with the date projected for the Notice to Proceed and conclude with the date of final completion conforming with the Contract time.
D. Depict a time -scaled network diagram of all activities, logic relationships of interdependent activities, and milestones comprising the complete period of Work with tasks on the vertical axis and their durations on the horizontal axis. Use distinctive texture patterns or line types to show the critical path within the Contract time. Include a tabular listing of each activity and its identification number, description, duration, early start, early finish, late start, late finish, total float, and all predecessor and successor activities. The number of activities will communicate the Contractor’s plan for project execution, accurately describe the project work and allow monitoring and evaluation of progress and time impacts. Activity descriptions shall accurately define the work planned for the activity. Activity durations shall not be shorter than 1 working day or longer than 15 working days unless approved by the Engineer.
E. Include detail of all project phasing, staging and sequencing including all milestones necessary to define beginning and ending of each phase or stage and constraints which may impact any activity. Include time allowances for coordination with utility companies and other agencies, equipment and material deliveries, submittal reviews and approvals,
Revised 6/15/17 Contract No. 5552 Page 88 of 142
traffic control setup and phasing, Work performed by others, inspections, testing and commissioning, corrective work, and any non-work periods.
Float or slack time within the schedule is available without charge or compensation to the party or contingency that first exhausts it. A schedule which shows a project duration longer than the Contract time will not be accepted by the Engineer.
If the Baseline Construction Schedule does not meet the requirements of these specifications, the Contractor shall revise the schedule and resubmit it to the Engineer. Failure to obtain the Engineer’s approval of the schedule within fifteen (15) Working Days after the date of the Preconstruction Meeting shall be grounds to consider the Contractor in default of the Contract per 6-4. The time required by the Engineer to review the initial Baseline Construction Schedule submittal will not be included in the 15 Working Days. The Engineer shall complete subsequent reviews of the revised schedule and progress updates within 5 working days of receipt.
The Contractor shall not be permitted to commence any excavation or demolition activities until the Engineer accepts the Baseline Construction Schedule. For each day of delay beyond the 15 Working Days after the Preconstruction Meeting that the Baseline Construction Schedule is not accepted by the Engineer, the Contractor shall be charged $100 through a deductive Change Order.
The Engineer’s response to each review will consist of one of the following:
“Accepted.” The Contractor may proceed with the Work.
“Accepted with Comments.” The Contractor may proceed with the Work, but must revise and resubmit the schedule prior to submittal of the first progress payment application.
The Engineer’s acceptance of the schedule is a condition precedent to payment of any progress payment.
“Not Accepted.” The Contractor may not proceed with the Work and must revise and resubmit the schedule.
6-1.1.2 Schedule Updates and Revisions. The Contractor shall meet with the Engineer during the last week of each month to agree upon the completion level of each activity as a basis for progress payments. Schedule updates shall conform with the requirements for the initial submittal in 6-1.1.1 and shall:
A. Show the actual dates of each activity start and/or finish during the month. The schedule update shall include specific notation for any changes in a ctual dates after they are first reported.
B. Report the percent complete for each activity in progress at the end of the month as determined by the Engineer.
C. Include a list and explanation of all changes made to the activities, dates or interconnecting logic.
D. Include activity and network revisions reflecting the Change Orders approved in the previous month as agreed upon during the review and acceptance of the Change Orders.
Revised 6/15/17 Contract No. 5552 Page 89 of 142
The Engineer’s responses to the progress schedule updates shall be as described in 6 -1.1.1.
The Contractor shall proceed with Work and request payment for the progress schedule updates as described therein.
Should the actual or projected progress of the Work exceed 5 percent of the Contract time, the Contractor shall prepare and submit a revised Baseline Construction Schedule independently of and prior to the next progress schedule update. The Contractor shall provide an explanation for each change made to the schedule.
If the Contractor fails to submit the progress schedule updates as required herein, the Contractor may elect to proceed with the Work at its own risk and shall forfeit payment for the progress schedule update until compliance is met. If the Contractor elects to delay or cease Work after failure to submit the progress schedule updates, any resulting delay, impact, or disruption to the Work will be the Contractor’s responsibility.
6-1.1.3 Interim Revisions. Should the actual or projected progress of the Work exceed 5 percent of the Contract Time, the Contractor shall prepare and submit a revised Baseline Construction Schedule independently of and prior to the next progress schedule update with a list and explanation of each change made to the schedule. The submittal , schedule review and acceptance requirements of 6-1.1.2 shall apply.
6-1.1.4 Late Completion or Milestone Dates. If a schedule update indicates a completion date later than the Contract time or contractually required milestone completion date , the Agency may withhold Liquidated Damages for the number of days late. Should a subsequent schedule update which removes all or a portion of the delay be “Accepted” by the Engineer , all or the allocated portion of the previously held Liquidated Damages shall be released in the monthly payment to the Contractor immediately following such acceptance.
6-1.1.5 Final Schedule Update. The Contractor shall prepare and submit a final schedule update when one hundred percent of the Work is completed. The update must accurately represent the actual dates for all activities. The final schedule update shall be prepared and reviewed in accordance with 6-1.1.2. Acceptance of the final schedule update is required for release of funds retained per 9-3.2.
6-1.1.6 Three-Week Look Ahead Schedules. The Contractor shall submit a detailed 3-week look ahead schedule prior to each progress meeting throughout project duration. The schedules shall be revised weekly to identify the construction activities and durations for each bid item of work for the current week and the succeeding two weeks. The Contractor shall revise the schedule to include additional activities or actual progress when so requested by the Engineer.
6-1.1.7 Measurement and Payment. The Contractor’s preparation, revision and maintenance of the Construction Schedule are incidental to the Work and no separate payment will be made therefor.
6-2 PROSECUTION OF WORK. To minimize public inconvenience and possible hazard and to restore street and other work areas to their original condition and state of usefulness as soon as practicable, the Contractor shall diligently prosecute the Work to completion. If the Engineer determines that the Contractor is failing to prosecute the Work to the proper extent, the Contractor shall, upon orders from the Engineer, immediately take steps to remedy the situation.
All costs of prosecuting the Work as described herein shall be includ ed in the Contractor’s Bid.
Revised 6/15/17 Contract No. 5552 Page 90 of 142
Should the Contractor fail to take the necessary steps to fully accomplish said purposes, after orders of the Engineer, the Engineer may suspend the work in whole or part, until the Contractor takes said steps.
As soon as possible under the provisions of the Specifications, the Contractor shall backfill all excavations and restore to usefulness all improvements existing prior to the start of the Work.
If Work is suspended through no fault of the Agency, all expenses and losses incurred by the Contractor during such suspensions shall be borne by the Contractor. If the Contractor fails to properly provide for public safety, traffic, and protection of the Work during periods of suspension, the Agency may elect to do so, and deduct the cost thereof from monies due the Contractor. Such actions will not relieve the Contractor from liability.
The Contractor shall incorporate non -workdays, moratoriums or special events specified in the Contract Documents into the Construction Schedule required by Section 6.1. No additional payment, adjustment of bid prices or adjustments of contract time will be allowed as a consequence of these events.
Constraints include, but are not limited to, the following:
• No construction between Memorial Day and Labor Day.
• No work during the Carlsbad Marathon (January 17, 2027). • No work during the Carlsbad 5000 (April 4, 2027).
• No work during the Peace Officers’ Memorial Run
• No work during the Special Olympics’ Law Enforcement Torch Run • No work during the MS Bike Tour (October 17-18, 2026). • No work during the MS 3-Day Challenge Walk (November 6-8, 2026). • No shutdowns during Thanksgiving Week
• No work during Thanksgiving Day and the day after
• No shutdowns during Christmas week through New Year
• No work on Christmas Day, December 25, 2026.
• No work on New Year Day, January 4, 2027.
• Public parking and access to the beach west of the Project site shall be maintained at all times and pedestrian detours, as may be necessary, shall be shown on the traffic control plans.
• Equipment and materials must be staged outside of Carlsbad Boulevard, and as approved by the Agency.
• Traffic control and materials will be demobilized and the site cleaned at the end of each work day.
• All work within City of Carlsbad right-of-way will require approved traffic control plans. • San Diego Gas and Electric (SDG&E) will require monitoring and inspection for the meter and Underground Service Rewire/Relocation and Meter . The Contractor shall coordinate with SDG&E.