RESOLUTION NO. 2022- 16
RESOLUTION ADOPTING A LIST OF PROJECTS FOR
FISCAL YEAR 2022-23 FUNDED BY SB 1: THE ROAD
REPAIR AND ACCOUNTABILITY ACT OF 2017
W
HEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi -modal transportation funding shortfalls statewide; and
W
HEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of Cathedral City (“CITY”) are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and W
HEREAS, the CITY must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
W
HEREAS, t he CITY, will receive an estimated $ 900,000 in RMRA funding in Fiscal Year 2022-23 from SB 1; and
W
HEREAS, this is the sixth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
W
HEREAS, the CITY has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and W
HEREAS, the CITY used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high- priority and cost - effective projects that also meet the community’s priorities for transportation investment; and
W
HEREAS, the funding from SB 1 will help the C ITY maintain and rehabilitate streets throughout the CITY this year and in the future; and WHEREAS, the 2018 California Statewide Local Streets and Roads Needs Assessment found that the CITY’s st reets and roads are in a poor condition and this revenue will help us increase the overall quality of our road system and over the next decade will bring our streets and roads into a “good condition” condition; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-e dge technology, materials and practices, w ill have significant positive co-benefits statewide.
NO
W, THEREFORE IT IS HEREBY RES OLVED, O RDERED AND FOUND by the C ity Council of the City of Cathedral City, State of California, as follows:
1. The foregoing recitals are true and correct.
2. T
he following Proposed Project will be funded in-part or solely with fiscal year 2022-23 Road Maintenance and Rehabilitation Account revenues:
Proposed Project 1: Landau Boulevard and McCallum Way Intersection Traffic Signal Construction
Description: The Proposed Pr oject will convert an existing four-w ay intersection into a signalized intersection and pavement improvements north and south bou
nd on Landau Boulevard. This intersection is located at the southwest corner o
f Mt. San Jacinto High School, wh ich gets significant pedestrian traffic from students. This intersection was also the location of a 2015 pedestrian fatality.
Location:
Intersection of Landau Boulevard and McCallum Way
Estimated Useful Life: Twenty (20) years
Project Start: Spring 2022
Project Completion: Spring 2023
Estimated Cost: $600,000.00
Proposed Project 2: Century Park Neighborhood Street Pavement Rehabilitation Description
: The Century Park Neighborhood includes rehabilitation and/or reconditioning
of various residential streets within the Century Park Neighborhood area.
Location:
The Century Park Neighborhood is bound between Avenue 30 to the north, McCallum Way to the south, Date Palm Drive to the west, and Da Vall Drive to
the east.
Estimated Useful Life: Twenty (20) years
Project Start: Spring 2022
Project Completion: Summer 2022
Estimated Cost: $1,700,000.00
3. The following previously proposed and adopted Project may utilize fiscal year 2022-23 Road Maintenance and Rehabilitation Account rev enues in its delivery.
With the relisti
ng of this Proposed Project in the adopted fiscal year resolution, t
he City is reaffirming to the public and the State our intent to fund this project w
ith Road Maintenance and Rehabilitation Account revenues:
Proposed Project 3: La Pasada Neighborhood Street Pavement Rehabilitation The streets to be selected for rehabilitation and REAS will be based on the latest PCI.
Description: The La Pasada Neighborhood includes rehabilitation and/or reconditioning of various residential streets within the La Pasada Neighborhood area.
Location: The La Pasada Neighborhood is north of Vista Chino and east and west of
Avenida Maravilla. Streets include Santiago Road, Posada Road, Madrid Road, Riviera Road,
Avenida Maravilla, San Martin Street, Calle Prado, La Medera Road, and Tangelo Street.
E
stimated Useful Life: Twenty (20) years
Project
Completion: Summer 2024
Estimated Cost: $8 00,000 .00
PASSED AND ADOPTED by the City Council of the City of Cathedral City, State of California this 23rd day of March 2022, by the following vote:
Ayes: Councilmembers Gregory, Ross and Carnevale;Mayor Pro Tem Lamb an Mayor Gutierrez Noes: None
Absent: None
Abstain: None
______
________________________________
Ernesto M. Gutierrez, Mayor
AT
TEST:
______
_____________________________
Tracey R. Hermosillo, City Clerk
APP
ROVED AS TO FORM:
______
_____________________________
Eric S. Vail, City Attorney