Sidewalk Improvements Quantity Unit Unit Price Total
DEMOLITION
Remove existing sign 1 EA $300 $300
Remove existing curb and gutter 170 LF $20 $3,400
Remove existing sidewalk 260 SF $10 $2,600
Remove existing trees 4E A $1,200 $4,800
Remove existing portion of concrete driveway 2,300 SF $9 $20,700 Sawcut existing concrete 86 LF $5 $430
Traffic control 1L S $5,000 $5,000
Remove grass 6,065 SF $2 $12,130
Remove block planter wall 65 LF $100 $6,500
Sub-Total $55,860
CONSTRUCTION
Construct 6" concrete flatwork with wire mesh
1,060 SF $25 $26,500
Construct driveway approach per City of Cathedral City Section 200-B 3E A $5,500 $16,500 Install detectable warning plate per CalTrans Standard Plan A88A 8E A $1,000 $8,000 Construct 5' sidewalk per Riverside County Standard Plan 404 2,900 SF $10 $29,000 Transition rolled curb to vertical curb per detail 1 on this sheet 16 LF $120 $1,920 Construct driveway approach per Riverside County Section 207-A 1E A $12,500 $12,500 Proposed 22,000 lumen per County of Riverside Standard Plan 1001 1E A $10,000 $10,000 Proposed R1-1 stop sign and post and post 4E A $500 $2,000 Proposed sidewalk ends sign and post 1E A $500 $500
R:\Admin\MS Office 2000\Calcs\Cost Estimates\102F-001 Perez Road Sidewalk Cost Estimate
Proposed type A-6 curb per Riverside County Standard Plan 200 120 LF $70 $8,400 Proposed stop bar and legend per CalTrans STD No A24D and A24E 4E A $500 $2,000 Grading for curb and gutters, drive approaches, sidewalk, landscape 1L S $25,000 $25,000 Traffic control 1L S $5,000 $5,000
Concrete washout bin 1L S $900 $900
Slurry seal and striping (parking lot) 1L S $20,000 $20,000 Sub-Total $168,220
Grand Total: $224,080