Cities Index.
2023_08_22 01 - Fountain of Life ROM Costs

Cathedral City City Council
September 27, 2023

Document
2023_08_22 01 - Fountain of Life ROM Costs
Meeting
September 27, 2023
Body
Cathedral City City Council
Original file
69 KB
Text extracted from the city's file for reading and search. Open the original on cathedralcity.primegov.com. That file is the official record.

01 FOUNTAIN OF LIFE | CITY OF CATHEDRAL CITY 8/22/2023
ROUGH ORDER OF MAGNITUDE (ROM) PROJECT CONSTRUCTION COSTSCompleted by: GA Reviewed by: CG

ITEM QUANTITY UNIT UNIT COST BASE ESTIMATE

SITE PREPARATION
Construction Fencing 100 lf $9.00 $900

DEMOLITION GRADING, DRAINAGE, UTILITIES
Removal of Concrete Paving 800 sf $2.00 $1,600
Remove Rubber Surfacing 2,800 sf $2.25 $6,300
Rough / Fine Grading 3,000 sf $2.00 $6,000

CONSTRUCTION ITEMS
3,000 sf $15.00 $45,000
42" Tall Alluminum Guardrail 126 lf $150.00 $18,900
Graphic Metal Panels at Guard Rail 8 ea $1,000.00 $8,000 12" Wide x 6" Deep Edgeband (Underneath Guardrail) 126 lf $45.00 $5,670 SUBTOTAL - ESTIMATED CONSTRUCTION COST $92,400

CONTRACTOR MOBILIZATION, BONDING & PERMIT COSTS
Contractor Bonding, General Conditions, Mobilization, Project Management - 6% 6% $5,544.00 Construction Survey, Permit, Security - 2% 2% $1,848.00

CONTINGENCIES
Construction Contingency - 10% 10% $9,240.00
Design Contingency - 10% 10% $9,240.00
TOTAL ESTIMATED COST OF MOBILIZATION, BONDING, PERMIT, CONTINGENCIES, & DEVELOPMENT COSTS$25,900 TOTAL PROJECT ESTIMATED COST: $118,300
Notes: 1) Construction Contingency is provided to cover for site conditions and additional work not anticipated for upgrades. 2) In Providing opinions of probable construction cost, the Client understands that the Landscape Architect has no control over costs or the price of labor equipment or materials, or over the Contractor's method of pricing, and that the opinions of probable construction costs provided herein are to be made on the basis of the Landscape Architect's qualifications and experience. The Landscape Architect makes no warranty, expressed or implied, as to the accuracy of such opinions as compared to bid or actual costs.
3) Construction costs are based on current market prices. 4" Thick Colored Conc. Paving with Reinforcement & Scoring (Fountain Assumed 4")

← All documents from this meeting