NEIGHBORHOOD PARK WATER PLAY - OPT 3| CITY OF CATHEDRAL CIT 8/22/2023 ROUGH ORDER OF MAGNITUDE (ROM) PROJECT CONSTRUCTION COSTS Completed by: GA Reviewed by: CG

ITEM QUANTITY UNIT UNIT COST BASE ESTIMATE

SITE PREPARATION
Construction Staking / Erosion Control 1 ls $7,500.00 $7,500 Construction Fencing 560 lf $9.00 $5,040
Filter Roll Barrier 560 lf $3.25 $1,820
Staging Area 2,000 sf $2.00 $4,000
Stabilized Construction Entry 1 ea $5,000.00 $5,000

DEMOLITION GRADING, DRAINAGE, UTILITIES
Clear & Grub In Proposed Splash Pad Area 3,500 sf $2.25 $7,875 Removal of Concrete Paving 500 sf $2.00 $1,000
Rough / Fine Grading 2,600 sf $2.00 $5,200
Tree Protection (Palm Trees) 5 ea $800.00 $4,000
Sewer Line 105 lf $65.00 $6,825
Water Lines 105 lf $175.00 $18,375

CONSTRUCTION ITEMS
2,600 sf $15.00 $39,000
300 sf $15.00 $4,500

1.5' Tall x 1.5' Wide Poured in Place Colored Concrete Seatwall 70 lf $325.00 $22,750 30" Tall x 2' x 2' Poured in Place Conc. Pilaster with Cap 4 ea $2,500.00 $10,000 Relocate Exising Boulders 5 ea $1,000.00 $5,000
6" Wide x 6" Deep Concrete Edgeband 18 lf $25.00 $450
Splash Pad System 1 ea $407,896.00 $407,896
Splash Pad System Equipment Enclosure 1 ea $80,000.00 $80,000 CMU Retaining Wall 40 lf $325.00 $13,000

ELECTRICAL
Electrical Conduit / Pullboxes / Switchgear 1 ls $40,000.00 $40,000

PLANTING & IRRIGATION
Repair Affected Turf Areas 6,000 sf $1.50 $9,000
Repair Irrigation Sytem of Affeted Turf Areas 6,000 sf $2.00 $12,000 Planting Area Repair at Circulation System Area 1,245 sf $2.00 $2,490 SUBTOTAL - ESTIMATED CONSTRUCTION COST $712,700

CONTRACTOR MOBILIZATION, BONDING & PERMIT COSTS
Contractor Bonding, General Conditions, Mobilization, Project Management - 6% 6% $42,762.00 Construction Survey, Permit, Security - 2% 2% $14,254.00

CONTINGENCIES
Construction Contingency - 10% 10% $71,270.00
Design Contingency - 10% 10% $71,270.00

DEVELOPMENT COSTS
City Construction Inspection - .75% 0.75% $5,345.25
City Labor Compliance Program - .50% 0.50% $3,563.50
City Material Testing - .50% 0.50% $3,563.50
City Legal & Bidding Costs - .20% 0.20% $1,425.40
TOTAL ESTIMATED COST OF MOBILIZATION, BONDING, PERMIT, CONTINGENCIES, & DEVELOPMENT COSTS $213,500 TOTAL PROJECT ESTIMATED COST: $926,200
Notes: 1) Construction Contingency is provided to cover for site conditions and additional work not anticipated for upgrades. 2) In Providing opinions of probable construction cost, the Client understands that the Landscape Architect has no control over costs or the price of labor equipment or materials, or over the Contractor's method of pricing, and that the opinions of probable construction costs provided herein are to be made on the basis of the Landscape Architect's qualifications and experience. The Landscape Architect makes no warranty, expressed or implied, as to the accuracy of such opinions as compared to bid or actual costs. 3) Construction costs are based on current market prices. 4" Thick Colored Conc. Paving with Reinforcemet, Base, & Scoring (Splash Pad Area) 6" Thick Conc. Paving (Underneath Splash Pad Equipment Enclosure)