CCO NO. DESCRIPTION STATUS ADDITIONAL DAY S APPROVED COST ACTUAL COST PAID 1 CVWD Tie-in Relocation Approved 0 39,705.75$ 39,705.75 $ 2 Additional Tubular Steel Fencing Approved 0 8,228.00$ 8,228.00 $ 3 Additional Asphalt Grinding Approved 0 14,640.00 $ 14,640.00 $ 4 Time Extension Approved 6 -$ - $ 5 Via De Anza Street Utility Potholing Approved 0 4,629.00 $ 4,629.00 $ 6 Failed Compaction Test Approved 0 (1,680.00)$ (1,680.00) $ SUB-TOTAL 6 65,522.75 $ 65,522.75 $
545,167.00$
65,522.75$
610,689.75$
VIA DE ANZA STREET IMPROVEMENTS PROJECT - PHASE II, CIP NO. 8835
CONTRACT CHANGE ORDER SUMMARY LOG
Contract Amount
Approved Change Order Amount
Contract Total Amount