1 MOBILIZATION LS 1 15,000.00$ 15,000.00$ 20,000.00$ 20,000.00$ 8,850.00$ 8,850.00$ 14,158.75$ 14,158.75$ 4,200.00$ 4,200.00$ 2 TRAFFIC CONTROL LS 1 15,000.00$ 15,000.00$ 34,000.00$ 34,000.00$ 35,120.00$ 35,120.00$ 6,729.09$ 6,729.09$ 15,000.00$ 15,000.00$ 3 SIGNING AND STRIPING LS 1 5,000.00$ 5,000.00$ 4,000.00$ 4,000.00$ 4,070.00$ 4,070.00$ 5,450.68$ 5,450.68$ 3,904.00$ 3,904.00$ 4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 109,035 0.75$ 81,776.25$ 0.70$ 76,324.50$ 0.75$ 81,776.25$ 0.40$ 43,614.00$ 0.65$ 70,872.75$ 5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 2,044 125.00$ 255,500.00$ 120.00$ 245,280.00$ 107.00$ 218,708.00$ 114.57$ 234,181.08$ 135.00$ 275,940.00$ 6 REMOVE AND DISPOSE EXISTING CURB RAMP EA 4 3,000.00$ 12,000.00$ 2,600.00$ 10,400.00$ 2,080.00$ 8,320.00$ 3,025.59$ 12,102.36$ 8,000.00$ 32,000.00$ 7 CONSTRUCT CURB RAMP PER CALTRANS
STANDARD PLAN A88A (MODIFIED; SEE PLANS) EA 4 4,000.00$ 16,000.00$ 6,900.00$ 27,600.00$ 6,250.00$ 25,000.00$ 8,847.97$ 35,391.88$ 8,200.00$ 32,800.00$ 400,276.25$ 417,604.50$ 381,844.25$ 351,627.84$ 434,716.75$ 1 MOBILIZATION LS 1 15,000.00$ 15,000.00$ 18,000.00$ 18,000.00$ 8,850.00$ 8,850.00$ 14,124.00$ 14,124.00$ 4,200.00$ 4,200.00$ 2 TRAFFIC CONTROL LS 1 15,000.00$ 15,000.00$ 33,000.00$ 33,000.00$ 33,845.00$ 33,845.00$ 6,760.00$ 6,760.00$ 15,000.00$ 15,000.00$ 3 SIGNING AND STRIPING LS 1 5,000.00$ 5,000.00$ 3,200.00$ 3,200.00$ 3,240.00$ 3,240.00$ 4,599.22$ 4,599.22$ 3,112.00$ 3,112.00$ 4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 98,892 0.75$ 74,169.00$ 0.70$ 69,224.40$ 0.80$ 79,113.60$ 0.43$ 42,523.56$ 0.65$ 64,279.80$ 5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 1,855 125.00$ 231,875.00$ 120.00$ 222,600.00$ 107.00$ 198,485.00$ 106.91$ 198,318.05$ 135.00$ 250,425.00$ 6 REMOVE AND DISPOSE EXISTING CURB RAMP
AND ALL CONCRETE FROM ECR TO BCR EA 4 3,000.00$ 12,000.00$ 2,600.00$ 10,400.00$ 2,080.00$ 8,320.00$ 3,025.59$ 12,102.36$ 8,000.00$ 32,000.00$ 7 CONSTRUCT CURB RAMP PER CALTRANS
STANDARD PLAN A88A (MODIFIED; SEE PLANS) EA 4 4,000.00$ 16,000.00$ 6,900.00$ 27,600.00$ 6,250.00$ 25,000.00$ 8,847.97$ 35,391.88$ 8,200.00$ 32,800.00$ 369,044.00$ 384,024.40$ 356,853.60$ 313,819.07$ 401,816.80$ 1 MOBILIZATION LS 1 15,000.00$ 15,000.00$ 10,000.00$ 10,000.00$ 8,850.00$ 8,850.00$ 8,872.00$ 8,872.00$ 4,200.00$ 4,200.00$ 2 TRAFFIC CONTROL LS 1 15,000.00$ 15,000.00$ 16,000.00$ 16,000.00$ 15,240.00$ 15,240.00$ 12,014.00$ 12,014.00$ 15,000.00$ 15,000.00$ 3 SIGNING AND STRIPING LS 1 5,000.00$ 5,000.00$ 1,700.00$ 1,700.00$ 1,650.00$ 1,650.00$ 2,959.74$ 2,959.74$ 1,587.00$ 1,587.00$ 4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 62,190 0.75$ 46,642.50$ 0.70$ 43,533.00$ 1.00$ 62,190.00$ 0.61$ 37,935.90$ 0.65$ 40,423.50$ 5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 1,166 125.00$ 145,750.00$ 120.00$ 139,920.00$ 108.00$ 125,928.00$ 111.58$ 130,102.28$ 135.00$ 157,410.00$ 8 REMOVE AND REPLACE CROSS GUTTER SECTION
SF 36 70.00$ 2,520.00$ 60.00$ 2,160.00$ 52.00$ 1,872.00$ 146.85$ 5,286.60$ 60.00$ 2,160.00$ 229,912.50$ 213,313.00$ 215,730.00$ 197,170.52$ 220,780.50$ Engineer Estimate
UNIT COST TOTAL
BID SCHEDULE NO. 3: 33RD AVENUE
TOTAL AMOUNT BID SCHEDULE NO.1 (BID ITEMS 1-7)
TOTAL BID SCHEDULE NO.2 (BID ITEMS 1-7)
TOTAL BID SCHEDULE NO.3 (BID ITEMS 1-5, 8)
ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL UNIT COST TOTAL All American Asphalt Calmex Engineering, Inc. Vance Corporation Granite Construction Company BID SCHEDULE NO. 1: SHIFTING SANDS TRAIL
BID SCHEDULE NO. 2: SKY BLUE WATER TRL.
UNIT COST TOTAL UNIT COST TOTAL
CITY OF CATHEDRAL CITY
2024-2025 CITY STREETSPAVEMENT RECONSTRUCTION PROJECTS
Bid Tabulation/ Analysis
CITY PROJECT No.: 8688 - 8692
UNIT COST TOTAL UNIT COST TOTAL ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL UNIT COST TOTAL All American Asphalt Calmex Engineering, Inc. Vance Corporation Granite Construction CompanyEngineer Estimate
UNIT COST TOTAL
1 MOBILIZATION LS 1 15,000.00$ 15,000.00$ 8,000.00$ 8,000.00$ 8,850.00$ 8,850.00$ 8,517.00$ 8,517.00$ 3,962.95$ 3,962.95$ 2 TRAFFIC CONTROL LS 1 15,000.00$ 15,000.00$ 22,000.00$ 22,000.00$ 29,570.00$ 29,570.00$ 12,370.00$ 12,370.00$ 15,000.00$ 15,000.00$ 3 SIGNING AND STRIPING LS 1 2,000.00$ 2,000.00$ 700.00$ 700.00$ 706.00$ 706.00$ 1,982.50$ 1,982.50$ 678.00$ 678.00$ 9 GRIND 0.12' (1.5") AC PAVEMENT AND DISPOSE SF 91,618 0.40$ 36,647.20$ 0.30$ 27,485.40$ 0.60$ 54,970.80$ 0.27$ 24,736.86$ 0.40$ 36,647.20$ 10 CONSTRUCT 0.12' (1.5") TYPE III C-3 PG 70-10 AC
PAVEMENT SECTION TON 859 125.00$ 107,375.00$ 125.00$ 107,375.00$ 117.00$ 100,503.00$ 114.72$ 98,544.48$ 135.00$ 115,965.00$ 11 CRACK SEAL LF 4,792 3.00$ 14,376.00$ 3.00$ 14,376.00$ 4.00$ 19,168.00$ 9.00$ 43,128.00$ 1.50$ 7,188.00$ 190,398.20$ 179,936.40$ 213,767.80$ 189,278.84$ 179,441.15$ 1 MOBILIZATION LS 1 15,000.00$ 15,000.00$ 9,000.00$ 9,000.00$ 8,850.00$ 8,850.00$ 8,809.00$ 8,809.00$ 4,200.00$ 4,200.00$ 2 TRAFFIC CONTROL LS 1 15,000.00$ 15,000.00$ 18,000.00$ 18,000.00$ 17,300.00$ 17,300.00$ 12,078.00$ 12,078.00$ 15,000.00$ 15,000.00$ 3 SIGNING AND STRIPING LS 1 2,000.00$ 2,000.00$ 2,300.00$ 2,300.00$ 2,280.00$ 2,280.00$ 2,352.26$ 2,352.26$ 2,188.00$ 2,188.00$ 9 GRIND 0.12' (1.5") AC PAVEMENT AND DISPOSE SF 106,542 0.40$ 42,616.80$ 0.30$ 31,962.60$ 0.55$ 58,598.10$ 0.23$ 24,504.66$ 0.40$ 42,616.80$ 10 CONSTRUCT 0.12' (1.5") TYPE III C-3 PG 70-10 AC
PAVEMENT SECTION TON 999 125.00$ 124,875.00$ 125.00$ 124,875.00$ 117.00$ 116,883.00$ 112.57$ 112,457.43$ 135.00$ 134,865.00$ 11 CRACK SEAL
LF 4,000 3.00$ 12,000.00$ 4.00$ 16,000.00$ 4.00$ 16,000.00$ 8.89$ 35,560.00$ 1.75$ 7,000.00$ 211,491.80$ 202,137.60$ 219,911.10$ 195,761.35$ 205,869.80$ 1,401,122.75$ 1,397,015.90$ 1,388,106.75$ 1,247,657.62$ 1,442,625.00$ A-1 LOWER AND RAISE WATER VALVE TO GRADE PER
CVWD STANDARDS EA 85 1,500.00$ 127,500.00$ 1,560.00$ 132,600.00$ 2,800.00$ 238,000.00$ 2,774.18$ 235,805.30$ 2,750.00$ 233,750.00$ A-2 LOWER AND RAISE SEWER MANHOLE TO GRADE
PER CVWD STANDARDS EA 35 2,000.00$ 70,000.00$ 1,600.00$ 56,000.00$ 2,300.00$ 80,500.00$ 2,211.89$ 77,416.15$ 2,275.00$ 79,625.00$ 197,500.00$ 188,600.00$ 318,500.00$ 313,221.45$ 313,375.00$ 1,598,622.75$ 1,585,615.90$ 1,706,606.75$ 1,560,879.07$ 1,756,000.00$ ADDITIVE ALTERNATE BID SCHEDULE A:
UTILITY ADJUSTMENT
TOTAL ADDITIVE ALTERNATE BID SCHEDULE A
TOTAL ALL BID ITEMS AND ALL ALTERNATIVES
TOTAL ALL BASE BID ITEMS
TOTAL BID SCHEDULE NO.4 (BID ITEMS 1-3, 9-11)
TOTAL BID SCHEDULE NO.5 (BID ITEMS 1-3, 9-11)
BID SCHEDULE NO.4: VENTURA DRIVE
BID SCHEDULE NO.5 AVENIDA QUINTANA
CITY OF CATHEDRAL CITY
2024-2025 CITY STREETSPAVEMENT RECONSTRUCTION PROJECTS
Bid Tabulation/ Analysis
CITY PROJECT No.: 8688 - 8692
1 MOBILIZATION LS 1
2 TRAFFIC CONTROL LS 1
3 SIGNING AND STRIPING LS 1
4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 109,035
5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 2,044
6 REMOVE AND DISPOSE EXISTING CURB RAMP EA 4
7 CONSTRUCT CURB RAMP PER CALTRANS
STANDARD PLAN A88A (MODIFIED; SEE PLANS) EA 4
1 MOBILIZATION LS 1
2 TRAFFIC CONTROL LS 1
3 SIGNING AND STRIPING LS 1
4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 98,892
5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 1,855
6 REMOVE AND DISPOSE EXISTING CURB RAMP
AND ALL CONCRETE FROM ECR TO BCR EA 4
7 CONSTRUCT CURB RAMP PER CALTRANS
STANDARD PLAN A88A (MODIFIED; SEE PLANS) EA 4
1 MOBILIZATION
LS 1
2 TRAFFIC CONTROL LS 1
3 SIGNING AND STRIPING LS 1
4 COLD MILL 3" AC PAVEMENT AND DISPOSE SF 62,190
5 CONSTRUCT 3" TYPE III C-3 PG 70-10 AC PAVEMENT
SECTION TON 1,166
8 REMOVE AND REPLACE CROSS GUTTER SECTION
SF 36
BID SCHEDULE NO. 3: 33RD AVENUE
TOTAL AMOUNT BID SCHEDULE NO.1 (BID ITEMS 1-7)
TOTAL BID SCHEDULE NO.2 (BID ITEMS 1-7)
TOTAL BID SCHEDULE NO.3 (BID ITEMS 1-5, 8)
ITEM DESCRIPTION UNIT QUANTITY
BID SCHEDULE NO. 1: SHIFTING SANDS TRAIL
BID SCHEDULE NO. 2: SKY BLUE WATER TRL.
5,300.00$ 5,300.00$ 48,000.00$ 48,000.00$ 12,000.00$ 12,000.00$ 22,627.25$ 22,627.25$ 16,200.00$ 16,200.00$ 91,000.00$ 91,000.00$ 58,000.00$ 58,000.00$ 74,000.00$ 74,000.00$ 4,140.00$ 4,140.00$ 4,000.00$ 4,000.00$ 6,220.00$ 6,220.00$ 8,000.00$ 8,000.00$
0.50$ 54,517.50$ 0.50$ 54,517.50$ 0.49$ 53,427.15$ 0.65$ 70,872.75$ 118.00$ 241,192.00$ 100.00$ 204,400.00$ 98.00$ 200,312.00$ 125.00$ 255,500.00$ 2,450.00$ 9,800.00$ 2,300.00$ 9,200.00$ 2,000.00$ 8,000.00$ 2,500.00$ 10,000.00$ 6,500.00$ 26,000.00$ 6,300.00$ 25,200.00$ 7,800.00$ 31,200.00$ 7,000.00$ 28,000.00$ 357,149.50$ 436,317.50$ 369,159.15$ 469,000.00$ 5,300.00$ 5,300.00$ 7,200.00$ 7,200.00$ 12,000.00$ 12,000.00$ 18,845.20$ 18,845.20$ 16,200.00$ 16,200.00$ 19,900.00$ 19,900.00$ 37,000.00$ 37,000.00$ 48,000.00$ 48,000.00$ 3,300.00$ 3,300.00$ 3,200.00$ 3,200.00$ 5,275.00$ 5,275.00$ 7,000.00$ 7,000.00$
0.50$ 49,446.00$ 0.66$ 65,268.72$ 0.49$ 48,457.08$ 0.65$ 64,279.80$ 118.00$ 218,890.00$ 88.00$ 163,240.00$ 98.00$ 181,790.00$ 125.00$ 231,875.00$ 2,450.00$ 9,800.00$ 1,960.00$ 7,840.00$ 2,000.00$ 8,000.00$ 2,500.00$ 10,000.00$ 6,500.00$ 26,000.00$ 5,000.00$ 20,000.00$ 7,400.00$ 29,600.00$ 7,000.00$ 28,000.00$ 328,936.00$ 286,648.72$ 322,122.08$ 408,000.00$ 5,300.00$ 5,300.00$ 7,200.00$ 7,200.00$ 12,000.00$ 12,000.00$ 10,846.50$ 10,846.50$ 15,600.00$ 15,600.00$ 19,300.00$ 19,300.00$ 15,500.00$ 15,500.00$ 22,000.00$ 22,000.00$ 1,680.00$ 1,680.00$ 1,630.00$ 1,630.00$ 2,775.00$ 2,775.00$ 4,000.00$ 4,000.00$
0.50$ 31,095.00$ 0.59$ 36,692.10$ 0.49$ 30,473.10$ 0.65$ 40,423.50$ 118.00$ 137,588.00$ 100.00$ 116,600.00$ 98.00$ 114,268.00$ 125.00$ 145,750.00$
70.00$ 2,520.00$ 40.00$ 1,440.00$ 200.00$ 7,200.00$ 55.00$ 1,980.00$ 193,783.00$ 182,862.10$ 182,216.10$ 225,000.00$ Hardy & Harper, Inc.
TOTAL
Martin Marietta San Diego Aggregates
LLC Onyx Paving Company, Inc.
UNIT COST TOTAL
Matich Corporation
UNIT COST TOTAL UNIT COST TOTAL UNIT COST
CITY OF CATHEDRAL CITY
2024-2025 CITY STREETSPAVEMENT RECONSTRUCTION PROJECTS
Bid Tabulation/ Analysis
CITY PROJECT No.: 8688 - 8692
ITEM DESCRIPTION UNIT QUANTITY
1 MOBILIZATION LS 1
2 TRAFFIC CONTROL LS 1
3 SIGNING AND STRIPING LS 1
9 GRIND 0.12' (1.5") AC PAVEMENT AND DISPOSE SF 91,618
10 CONSTRUCT 0.12' (1.5") TYPE III C-3 PG 70-10 AC
PAVEMENT SECTION TON 859
11 CRACK SEAL LF 4,792
1 MOBILIZATION LS 1
2 TRAFFIC CONTROL LS 1
3 SIGNING AND STRIPING LS 1
9 GRIND 0.12' (1.5") AC PAVEMENT AND DISPOSE SF 106,542 10 CONSTRUCT 0.12' (1.5") TYPE III C-3 PG 70-10 AC
PAVEMENT SECTION TON 999
11 CRACK SEAL
LF 4,000
A-1 LOWER AND RAISE WATER VALVE TO GRADE PER
CVWD STANDARDS EA 85
A-2 LOWER AND RAISE SEWER MANHOLE TO GRADE
PER CVWD STANDARDS EA 35
TOTAL ALL BASE BID ITEMS
TOTAL BID SCHEDULE NO.4 (BID ITEMS 1-3, 9-11)
TOTAL BID SCHEDULE NO.5 (BID ITEMS 1-3, 9-11)
BID SCHEDULE NO.4: VENTURA DRIVE
BID SCHEDULE NO.5 AVENIDA QUINTANA
TOTAL ADDITIVE ALTERNATE BID SCHEDULE A
TOTAL ALL BID ITEMS AND ALL ALTERNATIVES
ADDITIVE ALTERNATE BID SCHEDULE A:
UTILITY ADJUSTMENT
Hardy & Harper, Inc.
TOTAL
Martin Marietta San Diego Aggregates
LLC Onyx Paving Company, Inc.
UNIT COST TOTAL
Matich Corporation
UNIT COST TOTAL UNIT COST TOTAL UNIT COST
5,300.00$ 5,300.00$ 5,600.00$ 5,600.00$ 12,000.00$ 12,000.00$ 8,162.70$ 8,162.70$ 14,191.10$ 14,191.10$ 18,600.00$ 18,600.00$ 19,750.00$ 19,750.00$ 22,000.00$ 22,000.00$ 720.00$ 720.00$ 700.00$ 700.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$
0.30$ 27,485.40$ 0.22$ 20,155.96$ 0.33$ 30,233.94$ 0.35$ 32,066.30$ 123.00$ 105,657.00$ 108.00$ 92,772.00$ 105.00$ 90,195.00$ 125.00$ 107,375.00$
2.70$ 12,938.40$ 0.46$ 2,204.32$ 1.10$ 5,271.20$ 0.50$ 2,396.00$ 166,291.90$ 140,032.28$ 157,950.14$ 173,000.00$ 5,300.00$ 5,300.00$ 8,000.00$ 8,000.00$ 7,500.00$ 7,500.00$ 10,835.30$ 10,835.30$ 15,600.00$ 15,600.00$ 18,800.00$ 18,800.00$ 22,000.00$ 22,000.00$ 35,000.00$ 35,000.00$ 2,320.00$ 2,320.00$ 2,240.00$ 2,240.00$ 3,050.00$ 3,050.00$ 4,000.00$ 4,000.00$
0.30$ 31,962.60$ 0.20$ 21,308.40$ 0.38$ 40,485.96$ 0.35$ 37,289.70$ 123.00$ 122,877.00$ 104.00$ 103,896.00$ 105.00$ 104,895.00$ 125.00$ 124,875.00$
2.70$ 10,800.00$ 0.46$ 1,840.00$ 1.20$ 4,800.00$ 0.50$ 2,000.00$ 188,859.60$ 156,084.40$ 182,730.96$ 214,000.00$ 1,235,020.00$ 1,201,945.00$ 1,214,178.43$ 1,489,000.00$ 1,470.00$ 124,950.00$ 2,800.00$ 238,000.00$ 2,750.00$ 233,750.00$ 800.00$ 68,000.00$ 2,060.00$ 72,100.00$ 2,330.00$ 81,550.00$ 2,275.00$ 79,625.00$ 2,200.00$ 77,000.00$ 197,050.00$ 319,550.00$ 313,375.00$ 145,000.00$ 1,432,070.00$ 1,521,495.00$ 1,527,553.43$ 1,634,000.00$
CITY OF CATHEDRAL CITY
2024-2025 CITY STREETSPAVEMENT RECONSTRUCTION PROJECTS
Bid Tabulation/ Analysis
CITY PROJECT No.: 8688 - 8692