CITY OF CATHEDRAL CITY

CITY COUNCIL

CONDITIONS OF APPROVAL
PLANNED UNIT DEVELOPMENT NO. 21-001
TENTATIVE PARCEL MAP NO. 37876
CONDITIONAL USE PERMIT NOS.
21-006, 21-007, 21-008 AND 21-009
DESIGN REVIEW NOS. 21-001, 21-002 AND 21-003
ZONE ORDINANCE AMENDMENT NO. 21-001
MASTER SIGN PROGRAM NO. 22-019

CATHEDRAL COVE CENTER

PROJECT LOCATION:

SOUTHWEST CORNER OF EAST PALM CANYON DRIVE AND

DATE PALM DRIVE
(APN: 674-500-038, 687-500-001, -003, -006 THROUGH -012, - 014 AND -018 THROUGH -020, AND 687-207-003 AND -006)

DATE APPROVED: SEPTEMBER 28, 2022 (SECOND READING)
(CONDITIONS REVISED BY PLANNING COMMISSION
ON AUGUST 3, 2022)

SECTION 1 ADMINISTRATIVE CONDITIONS

1.1 Prior to issuance of a building permit the Applicant or Developer shall sign the approved Condit ions of Approval which shall certify that the Applicant or Developer agrees to implement all Conditions of Approval.

1.2 A copy of the signed Conditions of Approval shall be printed onto the first page of the construction drawings.

1.3 The plans a pproved by the Ar chitectural R eview Committee and Plann ing Commission will be re ferenced as “Exhibit A”. The construction draw ings shall conform substantially to “Exhibit A” as approved by the Planning Commission, with the exception of any detail specifically modified by any of the conditions of approval cont ained herein. Any deviat ion from “ Exhibit A” shall be submitted in writing and approved by the Director of Planning/Building and/or the Director of Engineering/Public Works prior to approval of the construction drawings.

Cathedral Cove Center
September 28, 2022

Page 2 of 53 ends

1.4 This approval shall be valid for two years from date of approval, unless extended pursuant to the Cathedral City Municipal Code and Subdivision Ordinance.

1.5 No Certificate of Occupancy shall be granted until all Conditions of Approval have been completed and approv ed by the Director of Planning/Building, Director of Engineering/Public Works, and Fire Chief unless otherwise identified herein.

1.6 The Final Parcel Map shall be approved by the City Council and recorded prior to the issuance of any building permits.

1.7 The dev elopment of the site shall conform to all ordinances , codes, regulations, policies and development design controls pursuant to the Cathedral City Municipal Code in effect prior to issuance of any building permits.

1.8 All improvements approved for c onstruction are required to be maintained as to comply substantially with the plans approved for construction, unless modifications are approved by the Director of Planning/Building and the Director of Engineering/Public Works . The improvements to be maint ained inclu de, but are not limited to, site improvements: parking and walking surfaces, private drainage control facilities, fence s/walls, signs, and lights; building and accessory structure improvements; paint colors and other finish materials, roofing materi als, mechanical equipment, windows, trellises, canopies, all architectural features , landscaping and landscape irrigation.

1.9 The Developer shall defend, indemnify and hold harmless the City of Cathedral City, its officials, employees and agents, from and against any liability whatsoever related to the approval of this Conditional Use Permit and any other permits or approvals issued related to this Conditional Use Permit.

SECTION 2 FEES

2.1 The Developer shall pa y all applicable City of Cathedral City fees, c harges and other costs such as development impact fees as prescribed by City Ordinance.

The applicant is hereby advised that the fees may change at the time they become due and payable, as permitted by applicable law.

NOTICE TO APPLIC ANT: Pursuant to Government Code Section 66020(d)(1), the 90- day period to protest the imposition of any impact fee, dedication, reservation, or other exacti on described in t his document begins on the effective d ate of this approval and any such protest must be in a manner that complies with Section 66020(a), and failure to timely follow this procedure will bar any subsequent legal action to attack, review, set aside, void or annul imposition.

The right to protes t the fees, dedi cations, reservations, or other exactions does not apply t o plann ing, zoning, grading, or other similar application processing fees or service fees in connecti on with this project.

It further does no t apply to any fees, dedication, reservations, or exacti ons for which the applicant has been given a noti ce simila r to th is, nor does it revive challenges to any fees for which the Statute of Limitations has previously expired.

Cathedral Cove Center
September 28, 2022

Page 3 of 53 ends

SECTION 3 PLANNING

3.1 If the project is proposed to be constructed in phases, a phasing plan shall be submitted for review and approval . The phasing plan shall outline the approximate construction timeline for buildings, infrastructure, landscaping, open space, common amenities, and other site improvements.

3.2 The project shall comp ly with the requirements of Chapter 9.94 (Planned Unit Development), where applicable.

3.3 A Final P lanned Unit Development (P UD) Plan in accordance with Section

9.94.160 of the Cathedral City Municipal Code (CCMC) shall be approved by the City Council prior to the issuance of any building permits.

3.4 Per section 9 .94.110 of the Z oning Ordinance, all s tructures shall be setback a minimum of ten feet from the right -of-way of publ ic or private streets , unless a variance has been granted.

3.5 All drive -through lanes shall be screened from public view along East Palm Canyon Drive. Screening metho ds may include block walls and landscape mounding and hedges.

3.6 Prior to Final Parcel Map approval by the City Council , a Final Site Plan shall be submitted to the Planning Department for review and approval consistent with the following:
a. Plans shall be draw in a minimum scale of 1” = 30’.
b. Show locations of all property lines.
c. Show location of all m echanical and elec trical equipment on exterior of building or ground- mounted equipment. All exterior and ground- mounted equipment is required to be screened.
d. Locations of mailboxes on the site.
e. Decorative paving at key cross ing points on private roads. Include detail of decorative paving material.
f. Show locations of all fire hydrants, catch basins, and gutters.

3.7 Prior to the issuance of building permits, a Final Landscape Construction Plan, prepared by a licensed landscape architec t, and signed by the local water purveyor, shall be submitted to the Planning Department for review and approval.

The Final Landscape Construction Plan shall contain the fol lowing required information:
a. A title block with sheet number, site address and APNs, date of preparation, and name, address, and phone number of Applicant or Developer on all sheets.

Cathedral Cove Center
September 28, 2022

Page 4 of 53 ends

b. A plant landscape legend, including a specific symbol for each plant spec ies used, size ( i.e., caliper, gall on, box , or brown trunk height, and/or quantity) and whether it is deciduous or evergreen.
c. Show use of concrete mow strip between turf and other surfaces. d. Clear indication where landscaping will be used to screen mechanic al, electrical, and irrigation equipment.
e. A plant landscape legend, including a specific symbol for each plant species used, size (i.e., caliper, gallon, box, or brown trunk height, and/or quantity) and whether it is deciduous or evergreen.
f. Show all locati on of mechanical, elect rical, and i rrigation equipment and landscaping that will screen from public view.

g. A detail showing planter design adjacent to walkways and driveways that is designed to prevent soil and/or decomposed granite from flowing onto walkways and driveways. There shall be a minimum two -inch vertical separation between the pavement and the soil.

h. Plant and tree installation and staking details. Plant and tree installation and staking details that require single trunk trees to be double stak ed and multi - trunk trees to be staked appropriate to the species of tree. i. Details, specifications, and location of all pavers and decorative surface materials used on the site. Samples of crushed rock material or decomposed granite materials shall be submitted to the Planning Department for approval. j. All decorative surface materials shall be approved by the Director of Planning/Building before issuance of any permits.
k. Landscaping and irrigation shall be provided along the street frontage. l. Landscape plans shall meet the r equirements of the City of Cathedral City’s Water Efficient Landscape Ordinance.

m. All plant materials used on the project site shall be those listed in the most recent version of Coachella Valley Water Distri ct’s “Lush & Efficient Landscape Gardening in the Coachella Valley”.

n. An Irrigation Plan with equipment details.

3.8 Site landscaping shall compl y with the City Design Guidelines and Water Conservation policies and rules regardless of whether the items are il lustrated on the Construction Landscape Plans:

a. Plants and trees shall be primarily of drought tolerant species compatible with the desert environment.

Cathedral Cove Center
September 28, 2022

Page 5 of 53 ends

b. At least 50% of the trees shall be evergreen species.

c. All trees in parking lots shall be centered betw een parking spaces to provide optimal shading.

d. All single trunk trees shall be double staked and multi -trunk trees shall be staked appropriate to the species of tree.

e. Arbor guards shall be installed around trees in turf areas.

f. Projects located along maj or arterials and/or streets shal l comply with th e street tree requirements of the City’s Design Guidelines.

g. Planter areas shall be surrounded by a conc rete mow strip or other hard surface.

h. All ground-mounted equipment, such as mechanical, electrical, and irrigation equipment (backflow preventers), shall be located within a landscape planter.

This equipment shall not be located within a turf area and sh all not be visible from public view.

i. Any drain that terminates in a planter shall have a splash guard.

j. All palm trees shall have a br own trunk height of between a minimum of 10 – 20 feet, varied to the satisfaction of City staff.

k. All 36 -inch box trees or greater shall b e ve rified as to size by the projec t planner prior to being planted. It is the respons ibility of the contractor and/or Applicant to make an appointment with the project planner to conduct this verification.

3.9 All landscaping shall be continuously maintained. Trees, shrubs, groun d covers, etcetera, shall be watered and permanently maintained. All dead vegetation shall be removed and replaced in a timely manner.

3.10 Where landscaping is required for off -street parking areas, or in other vehicular parking areas, concrete curbing and/or bumper blocks shall be required to regulate vehicular traffic and to protect plant mat erials fr om vehicles. Suc h curbing height shall be at l east six inches. Curbing of six inches or more shall be required where a public planter slopes toward a sidewalk an d said curbing is needed to retain water. Overflow devices whic h drain under sidewalks may be required to assur e that water does not overflow planters. I n no event shall the finished grade of the irrigated planter be less than three inches below a public sidewalk and/or curb.

3.11 The Applicant shall contact the Planning Department 90 days after issuance of a Certificate of Occupanc y to arrange for a follow -up on-site inspection to ensure Cathedral Cove Center
September 28, 2022

Page 6 of 53 ends

that all plant material is being maintained consistent with the approved Exhibit “A”.

3.12 Redwood headers are spec ifically prohibited from use on the project site for landscaping or as a permanent condition for other uses.

3.13 The property owner shall record a maintenance co venant over the property that guarantees the removal of weeds, dust, blow sand, and debr is, and ensures that the property is maintained in a weed, dust, blowsand, and debris -free condition per the approved plans and conditions of approval.

3.14 Building and landscaping shall be maintained in a condition that substantially complies with this approval.

3.15 A final fence and wall plan shall be submitted to the Planning Department for review and approval that includes at minimum, the height, color , materials and location of all fences and walls proposed for the project.

3.16 All lighting on site shall comply with Chapter 9.89 of the Municipal C ode relative to outdoor lighting including fixtures that direct lighting downward.

3.17 An exterior Lighting Plan, that includes landscape and pedestrian lighting, shall be submitted in compliance with CCMC Section 9.89, including a photometric analysis, for re view and appr oval prior to issuance of a building permit. The Lighting Plan shall also identify the following:
a. The type of fixtures, including height, material, and color.

b. That the total height of all freestanding lighting fixtures will not exceed 18 feet.

c. That all concrete fixture bases will have a decorative finish. At a mi nimum, a trowel finish shall be provided.

d. That the bolts connecting the light fixture to the base will be covered.

3.18 Property addresses or building identification signs shall be plac ed on all new and existing buildings so as to be plainly visible from the public s treet. Said sign s shall be a minimum of 12 inches in hei ght. Numbers shall be eith er internally or externally illuminated consistent with Municipal Code Section 9.02 and desi gned to illuminate automatically during periods of darkness.

3.19 All mechanical equipment, either roof or ground mounted, shall be screened from public view. All such equipme nt shall be fully screened by the roof structur e, a parapet wall, appropriate ground m ounted w alls, berming, or landscapin g. All walls shall architecturally match the building. If after construction, but prior to the issuance of a C ertificate of Occupancy, it is determined by the D irector of Planning/Building that equipment can be viewed fr om the public right -of-way a plan for screening the equipment shall be submitted to the Planning Department for a pproval. Once app roved, said scre ening shall be construct ed prior to issuance of a Certificate of Occupancy.

Cathedral Cove Center
September 28, 2022

Page 7 of 53 ends

3.20 Outdoor display and storage of mer chandise is strictly prohibited, unl ess approved in compliance with the Cathedral City Municipal Code.

3.21 Signage for the propo sed project is not par t of this approval and shall require a sign permit, prior to the issuance of a Certificate of Occupancy.

3.22 All signage shall comply with the approved Master Sign Program for the project.

Any deviations from the Program will req uire an amendment approved by t he Planning Commission.

3.23 No loading or unloading shall occur within the public right -of-way, except those activities approved by the Director of Pl anning/Building or Director of Engineering/Public Works.

3.24 For each parcel that contains a building, a trash enclosure shall be provided.

3.25 Trash enclosures shall be constructed to C ity stand ard and have a decorative wall surface and a decorative cap that are consistent with the overall architecture of the project.

3.26 The trash enclosures shall accommodate an organic w aste bin in compliance with SB 1383.

3.27 All breaker boxes, fire sprinkler risers, and utility conduits shall be i nterior to the building or within an enclosure that is in integrated into the building design as approved by the Planning Department.

3.28 All roof drains and downspouts shall be on the interior of the building or within an enclosure that is in integrated into the building design as approved by t he Planning Department with decorative drain terminations. Exposed drainpipes are specifically prohibited.

3.29 All drain terminations shall be the Watts Drainage Product RD -940 or a product of equal value.

3.30 Contractor must divert at leas t 75 percent of all demolition waste to a recycling facility. The reuse of materials is considered an acceptable recycling program but must be documented and approved by the Environmental Conservation Manager

3.31 Prior to the issuance of a Certificate of Occupancy , the applicant shall submit all weight tickets associated with trash and recycling disposal to be approved by the Environmental Conservation Manager.

3.32 If during excavation, grading or construction, arti facts or other archaeological resources are discov ered, all work in the im mediate area of the find shall be halted and the applicant shall immediately notify the Director of Planning/Building. A qualified archaeologist, meeting the Secretary of the Interior’s professional qualifications standards for archaeology, shall be called to the site by, and at the expense of, the applicant to identify the find and propose mitigation if the resource is culturally significant.

Cathedral Cove Center
September 28, 2022

Page 8 of 53 ends

3.33 The project shall comply with the following Mitigation Measures as identified in the Final Initial Stu dy/Mitigated Negative Declaration for the project:

1. BIO-1: A qualified biologist shall conduct two (2) take avoidance pre- construction burrowing owl surveys onsite. The first shall occur between 14 and 30 days prior to ground disturbance, and the second shall occur within 24 hours of ground disturbance. If burrowing owls are detected, the project proponent shall consult with C DFW to determine what course of action is needed, such as the use of exc lusion devices (if applicable) to discourage owls from using burrows that are believed to be in jeopardy of being impacted by implementation of the project.

2. BIO-2: For any grubbing, grading or other site disturbance or tr ee or vegetation removal occurring during the nesting season between January 15th and August 31 st, a qualifi ed biologist shall conduct at least one nesting bird survey, and more if deemed necessary by the consulting bi ologist, immediately prior to initiati on of project -related ground disturbing activities. If nesting birds are present, no work shall be permitted near the nest(s) until the young birds have fledged. While there is no established protocol for nest avoidance, when consulted, the CDFW generally recommends avoidance buffers of about 500 feet for birds-of-prey, and 100 – 300 feet for songbirds. If ground disturbance occurs outside the nesting season, this requirement shall be waived.

3. CUL-1: Earth-moving activi ties including grading, grubbing, trenching, or excavations at the site shall be monitored by a qualified archaeol ogist and approved Tribal Monitor(s).

Should cultural materials be discovered, they shall be recorded and evaluated in the field. The monitors shall be prepared to recover artifacts quickly to avoid construction delays but must have the power to tem porarily halt or divert construction equipment to allow for controlled archaeological recovery if a substantial cultural deposit is encountered. The Native American Monitor may request that destructive construction halt and the Monitor shall notify a Qualified Archaeologist (Secretary of the I nterior’s Standards and Guidelines) to investigate and, if necessary, prepare a mitigation plan for submission to the State Historic Preservation Officer and the Agua Caliente Tribal Historic Preservation Office. If art ifacts are discovered, these shall be processed, catalogued, analyzed, and prepared for permanent curation in a repository with permanent retrievable storage that would allow for additional research in Cathedral Cove Center
September 28, 2022

Page 9 of 53 ends

the future. Archaeological site records shall be prepar ed t o document the cultural remains discovered during monitoring and submitted to the California Historical Resources Information System.

4. GEO-1: Development of the Project shall adhere to the recommendations set forth in the Project specific Geotechnical Engineering Investigation (see Appendix D of this d ocument), including but not limited to removal and recompaction of collapsible or weak soils during the grading phase and completion of additional geotechnical/soil i nvestigations on the southern portion of the site proposed for the future residential development.

5. HAZ-1: Per the Geophysical Anomaly Investigation Report, the existing UST located onsite shall be cleaned, removed, and disposed prior to redevelopment of the subject property.

6. TRA-1: The Project is required to pay the requisite CVAG TUMF fee.

7. TRA-2: Each drive -through occupant shall prepare a vehicle stacking management plan demonstrating appropriate emergency vehicle access and access to handicap parking stalls are retained in the event of overflow vehicle stacking.

8. TRA-3: In order to assure that the intersections of Cathedral Canyon/Dinah Shore and Date Palm/Ramon operate at acceptable levels of service at General Plan build out, the following condition of approval shall be implemented:

The City shall be responsible for monit oring conditions at the intersections of Cathedral Canyon/Dinah Shore and D ate Palm/Ramon and providing improvements to those intersections through its Capital Improvement Program, a nd local, State or federal funding at such time as the improvements are warranted.

3.34 Vehicular a ccess and parking for the existing building at 68783 East Palm Canyon Drive (APN: 687 -207-004), adjacent to the project site, shall be maintained at all times including during construction. (Condition added by the Planning Commission on August 3, 2022)

SECTION 4 ENGINEERING / PUBLIC WORKS

Cathedral Cove Center
September 28, 2022

Page 10 of 53 ends

4.1 The Applicant (aka Developer) agrees to defend, indemnify and hold harmless the City of Cathedral City (“City”), its agents, officers and employees from any claim, action or proceeding to at tack, set aside, void, or annul the approv al of this Planned Unit De velopment No. 21-001 (PUD), corresponding Tentative Parcel Map No. 37876 (TPM) and corresponding entitlement Site Plans (Plans). The City shall have sole discretion in selecting its defense counsel. The City sha ll promptly notify the Developer of any claim, action or proceeding and shall cooperate fully in the defense.

4.2 This TPM shall expire two years after the City C ouncil approval date, unless recorded or granted a time extension pursuant to Cat hedral City Ordi nance 659; Section 3; Paragraph 8.4(A).

4.3 This TPM and any Final Parcel M ap recorded there under, shall comply with the requirements and s tandards of Government Code §§ 66410 through 66499.58 (“the Subdivision Map Act”), and Cathedral City Ordinance No. 629, 659, 691 and 830.

4.4 This TPM shall (and incorporate by reference) comply with all app licable terms, conditions and/or mitigation measures for the following approvals:

A. PUD No. 21-001
B. CUP Nos. 21-006, 21-007, 21-008 & 21-009.

C. Design Review Nos. 21-001, 21-002 & 21-003.

D. Zoning Ordinance Amendment No. 21-001.

E. Cathedral City Downtown Design Guidelines and Zoning Designations.

F. Cathedral City Water Conservation Policies and Rules.

G. Cathedral City Municipal Codes and Ordinances.

H. Project Phasing (TPM Phasing Map attached as reference) as follows:

1) Phase I: Parcels No. 1 through 5 and APN 674-500-038. 2) Phase II - Residential: Parcel 9
3) Phase II - Commercial: Parcels No. 6 through 8.

When cited within these Co nditions of Approval , “each phase ”, incorporated by reference, represents the Phases cited above in 4.4.A., 4.4.B. and 4.4.C.

In the event of any conflict( s) between approval conditions and/or provisions of these approvals, the Director o f Engineering/Pu blic Works and/or Director of Planning/Building shall determine precedence.

4.5 All conditions herein for the TPM shall be met prior to:

A. The Final Parcel Map approval; and/or,
B. Grading Permit issuance; and/or,
C. Encroachment Permit issuance; or,
Cathedral Cove Center
September 28, 2022

Page 11 of 53 ends

D. As specifically modified by item as linked to a Cer tificate of Occupancy (COO) issuance; and/or,
E. Time limit from the date of issuance of the Grad ing and/or E ncroachment Permit.

4.6 Prior to issuance of any Grading, Encroachment or Building Permit by the City, the Developer shall obtain any necessary clearances and/or permits from the following agencies, if required:

A. City of Cathedral City Fire Marshal.

B. Cathedral City Engineering Department.

C. Cathedral City Planning Department.

D. Cathedral City Building Department.

E. Riverside County Environmental Health Department.

F. Riverside County Flood Control District (RCFCD).

G. Palm Springs Unified School District.

H. Desert Water Agency (DWA).

I. Southern California Edison (SCE).

J. Frontier Communications.

K. Spectrum Cable (TW).

L. California Regional Water Quality Control Board (CRWQCB).

M. State Water Resources Control Board.

N. Sunline Transit Agency (SunLine).

O. South Coast Air Quality Management District – Coachella Valley (SCAQMD).

The Developer is responsible for all the requirements of the permits and/or clearances from the above listed a gencies. When t he re quirements include approval of improvement plans, the Applicant shall furnish proof o f such approvals when submitting those improvement plans for City approval.

4.7 If applicable, the Developer shall be responsible for completing all TPM approved Phase I Study recommendations, all City and Riverside County r equirements and Riverside County De partment of Environmental Health requirements. Proof of compliance shall be submitted to the City before issuance of Building Permits for the CUP.

4.8 Coverage under the State of California Cons truction General Permit must be obtained by the Applicant, who th en shall submit a copy of the Californ ia Regional Water Quality Control Board’s (“ CRWQCB”) acknowledgement of the Applicant’s Notice of Intent (“NOI”) and Waste Discharge Identification (”WDID”) number to the City prior to the issuance of a Grading, Encroachment or Building permit.

4.9 Prior to construction, during construction and up to TPM acceptance the Applicant shall comply with applicable provisions of the City’s NPDES Stormwater Discharge Permit and Riverside County Ordinance No. 457; the CRWQCB – Colorado River Cathedral Cove Center
September 28, 2022

Page 12 of 53 ends

Basin Regional Board Order No. R7- 2013-0011 and the C RWQCB’s Or der No. 2009-009-DWQ, Order No. 2010-0014-DWQ and Order No. 2012-0006-DWQ.

A. F or construction activities including clearing, grading or excavation of land that disturbs one (1) acre or more of land, or that disturbs less than one (1) acre of land, but which is a part of a construction project that encompasses more than one (1) ac re of land, the Applicant (“Permitee”) shall be required to submit a Storm Water Pollution Protection Plan (“SWPPP”) to the CRWQCB.

B. The Appli cant or design professional can obtain the California Stormwater Quality Association SWPPP template at www.cabmphandbooks.com for use in their SWPPP preparation.

C. Prior to the Applicant submitting the SWPPP to the CRWQCB, the Applicant shall submit a copy of the SWPPP to the Director of Engineering/Publi c Works for review.

D. The Applican t sh all d eliver a complete copy of the CRWQCB approved SWPPP to the Director of Engineering/Pu blic Works prior to issuance of the Grading Permit for City records.

E. The Applicant shall ensure that the required SWPPP is available for inspection at the projec t si te at all times through and including acceptance of all improvements by the City.

F. The Applicant’s SWPPP shall include provisions for all of the following Best Management Practices (“BMPs”), but not limited to:

1) Temporary Soil Stabilization (erosion control).

2) Temporary Sediment Control.

3) Wind Erosion Control.

4) Track-Out Control.

5) Non-Storm Water Management.

6) Waste Management and Materials Pollution Control.

7) Retention and Infiltration Basins Management.

G. All erosion and sediment control BMPs proposed by t he Applicant shall be approved by the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 13 of 53 ends

H. The SWPPP and BMPs shall remain in effect for the entire duration of Project construction until all improvements are completed and accepted by the City.

4.10 Erosion C ontrol BMPs shal l rem ain in effect for the entire duration of Project construction until all improvements are completed and accepted by the City.

4.11 The Developer sh all be respo nsible for blow sand, debris, trash, rubbish and deleterious material removal in all areas of the TPM’s driveways, parking lots, access aisle s, and East Palm Canyon Drive, Van Fleet Street, D Stre et and frontages. This includes frontage areas at the intersections of East Palm Canyon Drive and Date Palm Drive, East Palm Canyon Drive and Allen Avenue, East Palm Canyon and Van Fleet Street, Van Fleet Street and B Street, Van Fleet Street and C Street, Van Fleet Street and D Street and the D Street cul -de-sac.

Responsibilities include all frontage gutter pans, sidewalks, parkways, right-of-way and all interior areas within walled areas and all areas outside the walled areas of the TPM. T his will also include all d riveways and drive ais les providing ingress and egress to and from all the TPM ’s frontage roadways . The Developer shall include these responsibilities into a City approv ed routine maintenance schedule of the sit e for pe rpetuity a nd incorporate thes e in to the TPM ’s CC&Rs for all Parcels within each phase of the TPM, respectively.

4.12 Approval of this TPM and Plans shall not be constr ued as approval for any horizontal dimensions implied by any Plans or exhibits unless specifically identified in the following Conditions of Approval.

4.13 The Developer shall reimburse the City, within thirty (30) days of presentment of the invoice, all costs a nd actual attorney’s fees incurred by the City Attorney to prepare, review, negotiate and/or modify any documents or instruments required by these conditions and/or subsequent modification requests to these Conditions of Approval. This obligation shall be paid in the time noted above without deduction or offse t and Developer ’s failure to make such payment shal l be material breach of the Conditions of Approval.

4.14 The Developer shall reimburse the City, within thirty (30) days of presentment of the invoice, a ll cost and actual co nsultant’s fees incu rred by the Ci ty for engineering, surveying and/or any other technical consultants to review and/or modify any documents or instruments required by these conditions and/or subsequent modification requests. This o bligation shall be paid in the time not ed above without deduction or off set and Developer’s failure to make such payment shall be material breach of the Conditions of Approval.

4.15 The Developer shall reimburse the City, within thirty (30) days of presentment of the invoice, all ac tual costs incur red by the City fo r Engineering, Planning and/or Building Department reviews and/or modify any documents or inst ruments required by these conditions and/or subsequent modification requests. This obligation shall be paid in the time not ed above without deductio n or offset an d Cathedral Cove Center
September 28, 2022

Page 14 of 53 ends

Developer’s f ailure to make such payment shall be material breach of the Conditions of Approval.

PROPERTY RIGHTS AND PRIVATE IMPROVEMENTS

4.16 Prior to issuance of any COO within each phase, the Developer shall acquire or confer easements and other property rights necessar y for the c onstruction or proper functioning of the proposed TPM. Conferred rights shall include irrevocable offers to dedicate or grant access easements to the City for emergency serv ices and for maintenance, construction and reconstruction of essential improvements.

4.17 Pursuant to the aforementioned condition, conferred rights shal l include approvals from all necessary persons or entities over easements and other property rights necessary for construction and proper functioning of the proposed TPM not limited to access rights over proposed and/or existing private streets that access public streets and open space/drainage facilities of all phases of the development.

Specifically:

A. Phase I

i. On the Final Parcel Map, the Owner of Record shall dedicate an additional 8 to 15 feet of right of way to the City along the East Palm Canyon Drive frontage to assure a half street right of way width of 63 feet.

ii. I f not already completed, on the Final Parcel Map, the Owner of Recor d shall dedicate an additional 18 feet of right of way to the City along the Van Fleet St reet frontage to assure a half street right o f way width of 38 feet.

iii. On the Final Parcel Map, the Owner of Recor d shall dedicate additional right of way a t the TPM’s East Palm Canyon Driv e and Van Fleet Street corner to provide for a Corner Cut -Back per Riverside County (RC) Standard No. 805.

iv. On the Final Parcel Map, the Owner of Recor d shall dedicate additional right of way at the TPM’s East Palm Cany on D rive and Allen Avenue corners to provide fo r Corner Cut -Backs per Riverside County (RC) Standard No. 805.

v. On the Final Parcel Map, the Owner of Recor d shall dedicate additional right of way at the TPM ’s East Palm Canyon Drive and Date Palm Drive corners t o pro vide for a Corner Cut-Backs per Riverside County ( RC) Standard No. 805.

vi. On the Final Parcel Map, the Owner of Recor d shall dedicate additional right of way for the new 30-foot-wide driveway located approximately 80 Cathedral Cove Center
September 28, 2022

Page 15 of 53 ends

feet east of Parcel 6’s west property line along the TPM’s East Pa lm Canyon Drive frontage provide for a Corner Cut -Back per Riversid e County (RC) Standard No. 805.

vii. The TMP’s CC&Rs for all parcels within Phase I shall incorporate mutual access for emergency access (if requ ired) and pedest rian access to Phase II – Residential; and, mutual acce ss for emergency vehicles, vehicles and pedestrians to Phase II – Retail, subject to the approval of the Director of Engineering/Public Works.

viii. The TMP’s CC&Rs shall incorporate the Mai ntenance Conditions described in Condition 4.11 for all the parcels in Phase I, subject to the approval of the Director of Engineering/Public Works.

ix. The Developer shall record and the TPM ’s CC&Rs shall incorporate the Street Light Covenant described in C ondition 4.26 and 4.27 against all the parcels in Phase I.

x. The TPM ’s CC&Rs shall incorporate a Mutual Drainage Easement between all parcels in Phase I and Phase II – Retail; and between Phase I and Phase II – Residential for receiving break out stormwa ter, subject to the approval of the Director of Engineering/Public Works.

xi. The Developer shall record and the TPM’s CC&Rs shall incorporate the Water Quality Management Plan and Urban Runoff Best Management Practices Transfer, A ccess and M aintenance Covenant (as part of the WQMP) described in Condition 4.29.iv. against all the parcels in Phases I.

xii. On the Final Parcel Map, the Owner of Recor d shall dedicate the proposed south extension of the Date Palm Drive/East Palm Canyon intersection for public street and public utility p urposes, for a distanc e of approximately 100 ft south o f East Palm Canyon Drive, in an ali gnment, width and configuration as approved by the Director of Engineering/Public Works. The south extension entrance into the TPM’s Phase I area shall be constructed as generally as shown on Plans , with concrete curb and gutter, sidewalks, curb returns, access ramps, and pavement. The TPM’s CC&Rs shall incorporate the ongoing maintenance and upkeep of the street impr ovements within the dedicated publi c portion of the proposed south extension of the Date Palm Drive entrance in a form as approved by Director of Engineering/Public Works.

xiii. On the Final Parcel Map with a certification that a vacation is the intent , the Property Owner of Record shall complete the vacation of a portion of A Street, all of “B” Street and a public alley between. Portions of “A” Street, “B” Street, and a public alley between these streets, were conditional ly Cathedral Cove Center
September 28, 2022

Page 16 of 53 ends

vacated by t he City by Vaca tion C ase No. 2015- 02, as detailed in City Council Resolution No. 2015-60, adopted on November 16, 2015.

The Developers of the P hase II - Residential and Phase II - Retail shall abandon, relocate, underground, or otherwise clear existing utilities in these streets in conjunction these Phases, respectively, to the satisfaction of their own ers, and mee t the other condi tions of the street and alley vacations as outlined in that Resolution, and a final Resolution of Vacation must be adopted and recorded prior to the issuance of Grading and/or Building Permits on any of the portions of stree ts or alley to be vacated.

Abandonment, relocat ion or undergr ounding of any utilities in these vacated streets shall occur prior to the first COO issued for either Phase II – Residential or Phase II - Retail, where such vacation is applicable.

TPM’s CC&Rs shall incorporate th e ongoing maintenance and upkeep of the stre et impr ovements within the non-vacation public portion of “A” Street, east of Van Fleet Street in a form as approved by Director of Engineering/Public Works.

B. Phase II - Residential:

i. If not a lready completed, on the Final Parcel Map, the Owner of Recor d shall dedicate an additional 18 feet of right of way to the City along the Van Fleet St reet frontage to as sure a half street right o f way width of 38 feet.

ii. On the Fin al Parcel Map, the Owner of Record shall dedicate additional right of way at all the TPM’s Van F leet S treet and “D” Street frontage driveways to provide for Corner Cut -Backs per Riverside County (RC) Standard No. 805.

iii. The City will vacate portions of the “D” Street offset cul-de-sac located at the east end of “D” Street as required with the recor dation of the Final Parcel Map (FPM) to complete a reduced size cul-de-sac in accordance with a 56-feet right of way size, shape a nd geometric ali gnment as generally show on the TTM per Riverside County (RC) Standard N o. 800(A) and as final approved by the City Fire Chie f and Director of Engineering/Public Works. Vacation and completion of construction of the “D" Street cul-de-sac shall occur prior to t he issuance of the first permit and CCO of the Phase II – Residential, respectively.

iv. The TMP’s CC&Rs (or by recorded Covenant) for all parcels within Phase II - Residential shall incorporate mutual access for emergency access (if required) and pedestrian access to Ph ase I and Phase II – Retail subject to the approval of the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 17 of 53 ends

v. The TMP’s CC&Rs (or by recorded Covenant ) shall incorporate the Maintenance Conditions described in Condition 4.11 for all the parcels in Phase II - Residential, subject to the approval of the Director of Engineering/Public Works.

vi. The Property Owner of Record shall record the Street Light Covenant described in Con dition 4.26 and 4.27 against all the parcels in Phase II – Residential and ongoing maintenance shall be incorporated in the Phase II recorded CC&Rs.

vii. The TPM’s CC&Rs shall incorporate a Mutual Drainage Easement (or by recorded covenant) between all parcels in Pha se II – Residential and Phase I for receiving break out stormwater, subject to the approval of the Director of Engineering/Public Works.

viii. The Property Owner of Record shall record the Water Quality Management Plan and Urban Runoff Best Management Practices Transfer, Acc ess and M aintenance Covenant (as part of the WQMP ) described in Condition 4. 29.iv. against all the parcel s in Phase II - Residential of the TPM and maintenance shall be incorporated in the Phase II - Residential CC&Rs.

ix. If not already completed, on the Final Parcel Map with a certification that a vacation is the in tent, the Property Owner of Record shall complete the vacation of a portion of “A” Street, all of “ B” Street and a public alley between. Portions of “ A” Street, “B” Street, and a public alley between these streets, were conditionally vacated by the City by Vacation Case No. 2015-02, as detailed in City Council Resolution No. 2015-60, adopted on November 16, 2015.

The Developers of the P hase II - Residential and Phase II - Retail shall abandon, relocate, underground, or otherwise clear existing utilities i n these streets in conjunction these Phases, respectively, to the satisfaction of their owners, and mee t t he other conditions of the street and alley vacations as outlined in that Resolution, and a final Resolution of Vacation must be adopted and recorded prior to the iss uance of Grading and/or Building Permits on any of the portions of stree ts or alley to be vacated.

Abandonment, relocat ion or undergr ounding of any utilities in these vacated streets shall occur prior to the first COO issued for either Phase II – Residential or Phase II - Retail, where such vacation is applicable

C. Phase II - Retail

i. On the Final Parcel Map, the Owner of Record shall dedicate an additional 8 to 15 feet of right of way to the City along the Eas t Palm Canyon Drive frontage to assure a half street right of way width of 63 feet.

Cathedral Cove Center
September 28, 2022

Page 18 of 53 ends

ii. On the Final Parcel Map, the Owner of Record shall dedicate an additional 18 feet of right of way to the City alon g the Van Fleet St reet frontage to assure a half street right of way width of 38 feet.

iii. On the Final Parc el Map, the Property Owner of Record shall dedicate a 10-foot access easement on the west side of Parcel 6 for full ingress and egress access to ab utting Parcel APN No. 687-207-004. The dedicated 10-foot access and egress easement will be constructed as generally as shown on P lans, with concrete curb , gutter, and pavement and will be included in the Maintenance Covenant described in Condition 4.11.

iv. The TPM’s Phase II – Retail recorded CC&Rs shall incorporate a Mutual Trash Enclosure Access Easement to allow the property o wner of Pa rcel APN No. 687-207-004 access to a trash enclosure constructed by the Applicant for the property owner of AP N No. 687-207-004 as part of this TPM at the location g enerally shown on the Plans. The trash enclosure will be located, designed, and constructed per Cathedral Cit y Design Standards at the Developer ’s cost and subject to the approval of the Director of Planning/Building.

v. If not already completed, on the Final Parcel Map with a certification that a vacation is the int ent, the Property Owner of Record shall complete the vacation of a portion of A Street, all of B Street and a public alley between.

Portions of A Street, B Street, and a public alley between these streets, were conditionally vacated by t he City by Vacation Case No. 2015-02, as detailed in City Council Resolution No. 2015 -60, adopted on Nov ember 16, 2015.

The Developers of the P hase II - Residential and Phase II - Retail shall abandon, relocate, underground, or otherwise clear existing uti lities in these streets in conjunction these Phases, respectively, to the satisfaction of their owners, an d mee t the other conditions of the street and alley vacations as outlined in that Resolution, and a final Resolution of Vacation must be adopted and r ecorded prior to the issuance of Grading and/or Building Permits on any of the portions of stree ts or alle y to be vacated.

Abandonment, relocat ion or undergr ounding of any utilities in these vacated streets shall occur prior to the first COO issued for either Phase II – Residential or Phase II - Retail, where such vacation is applicable.

The TPM’s CC&Rs shall incorporate the ongoing maintenance and upkeep of the street impr ovements within the non-vacation public portion of “A” Street, east of Van Fleet Street in a form as approved by Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 19 of 53 ends

vi. The TMP’s CC&Rs for all parcels within Phase II - Retail shall incorporate mutual access for emergency access (if required) and pedestrian access to Phase II – Residential; and mutual acc ess for emergenc y vehicles, vehicles and pedestrians to Phase I, subject to the approval of the Director of Engineering/Public Works.

vii. The TMP’s CC&Rs shall incorporate the Maintenance Conditions described in Condition 4.11 for all the parcels in Phase II - Retail, subject to the approval of the Director of Engineering/Public Works.

viii. The Developer shall record and the TPM’s CC&Rs shall incorporate the Street Light Covenant described in Condition 4.26 and 4.27 against all the parcels in Phase II - Retail.

ix. The TPM’s CC&Rs shall incorporate a Mutual Drainage Easement between all parcels in Phase II – Retail and Phase I , subject to the approval of the Director of Engineering/Public Works.

x. The Developer shall record and the TPM ’s CC&Rs shall incorporate the Water Quality Management Plan and Urban Runoff Best Management Practices Transfer, A ccess and M aintenance Covenant (as part of the WQMP) described in Condition 4.29.iv. against all the parcels in Phase II - Retail.

4.18 The Developer shall retain for private use on this TPM all private street rights-of- way, parking lots, ac cess ways, entry points, and rights -of-way in confor mance with the City’s General Pla n, Municipal Code, TPM and/or as required by the Director of Engineering/Public Works.

4.19 The Developer shall design the onsite private parki ng lot and drive ai sles pavement sections using Cal T rans’s design procedure for 20-year life pavement, and the site-specific data for soils strength and anticipated traffic loading (including construction traffic). Minimum structural sections shall be as follows:

a. Parking Lot and Drive Aisles:

i. Asphalt (a.c.): Placed in one (1) lift: 3.0” a.c./4.0” class II base. Applicant will provide pavement and base section thicknesses and will be subject to the approval of the Director of Engineering/Public Works.

ii. Portland Cement Concrete (PCC): 5.0” PCC w/wire mesh /4.0” class II base. Applicant will pro vide pavement and bas e section thicknesses and will be subject to the approval of the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 20 of 53 ends

b. Apply striping, legends and signage over the entire p arking lot and drive aisles.

Final striping, legend and signa ge layout shall be approved by the Dir ector of Engineering/Public Works.

c. Parking lot lighting shall com ply with the lighting , photometric , B uilding and/or Engineering Site Plans to the satisfaction of the Director of Planning/Building and Director of Engineering/Public Works.

4.20 The Developer shall include on the following frontages:

a. Phase I:

i. East Pa lm Can yon Drive and Allen Av enue: Construct one (1) approximately 42-foot-wide signalized intersection driveway entrance to comply with ADA standards and to be shown on the Engineering Plans, to the satisfaction of the Director of Engineering.

1) The ingress and egress driveway at Allen Avenue cited above and as shown on the TPM and Plan and as part of these Conditions of Approval, shall provide ingress and egres s for the retail development.

2) Any modification to these driveways will require the approval of the Director of Engineering/Public Works.

3) The entry drives, interior circulation r outes, setbacks and other features generally shown on the TPM’s Plans, may r equire additional street w idths as determ ined by the Director of Engineering/Public Works . T he City shall determin e any such additional requirements during the plan check process prior to the issuance of a Grading Permit for Phase I.

ii. East Palm Ca nyon Dri ve and Date Palm Drive : Construct one (1) approximately 60-foot-wide signalized intersection street entrance to comply with ADA standards and to be shown on the Engineering Plans, to the satisfaction of the Director of Engineering.

1) The ingress and egress driveway at Date Palm Drive cited above and as shown on the TPM and Plan and as part of these Conditions of Approval, shall provide ingress and egres s for the retail development.

2) Any modification to these driveways will require the approval of the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 21 of 53 ends

3) The entry drives, interior circula tion routes, setbacks and other features generally shown on the TPM ’s Plans, may r equire additional str eet w idths a s determined by the Director of Engineering/Public Works. The City shall determin e any such additional requirements during the plan check process prior to the issuance of a Grading Permit for Phase I.

B. Phase II - Residential:

i. Driveway and access points located in Pha se II – Residential are to be submitted with the Applicant’s application documents for the entitlement for Phase II - Residential.

C. Phase II - Retail:

i. East Palm Can yon Drive approximately 80 feet east of Parcel 6’s west property line as generally shown on the TPM’s Plans : Construct one (1) approximately 30-foot-wide City St andard 200- B driveway entrance to comply with ADA standards and to be shown on the Engineering Plans, to the satisfaction of the Director of Engineering/Public Works.

1) The ingress and egress driveway on East Palm Canyon cited above and as shown on the TPM and Plan and as part of these Conditions of Approval, shall provide ingress and egress for the Phase II - Retail development.

2) Any modification to the se driveways will require the approval of the Director of Engineering/Public Works.

3) The entry drives, interior circ ulation routes, setbacks and o ther features generally shown on the TPM ’s Plans, may require additional street w idths as determined by the Director of Engineering/Public Works . The City shall determin e any such additional requirements during the plan check process prior to the issuance of a Grading Permit for Phase I.

ii. Van Fleet Street/ A Street inters ection: Construct one (1) 30-foot-wide Riverside Cou nty Stan dard Driveway Standard No. 207A driveway to comply with ADA st andards and to be shown on the Engineering Plans to the satisfaction of the Director of Engineering/Public Works.

1) The ingress and egress driveway on Van Fleet Street cited above and as shown on the TPM and Plan and as part of these Conditions of Approval, shall provide ingress and egr ess for the retail development.

Cathedral Cove Center
September 28, 2022

Page 22 of 53 ends

2) Any modification to these driveways will require the approval of the Director of Engineering/Public Works.

3) The ent ry drives, inte rior circul ation routes, setbacks and other features generally shown on the T PM’s Plans, may req uire additional street w idths as determined by the Director of Engineering/Public Works . T he City shall determin e any such additional requirements during the plan check process prior to the issuance of a Grading Permit for Phase I.

4.21 Curve Radii for curbs at all street intersections and driveways shall not be less than 35 feet . All radii less than 35 feet will require the individual approval of the Director of Engineering/Public Works.

4.22 All commercial driveways shall be RC Commercial Driveway Standard No. 207A or as specifically cited in these Conditions of Approval with final approval by the Director of Engineering/Public Works.

4.23 Install Type A -6, A-8 and/or Type “D” curbs per RC Standards, whi ch will co nvey water without ponding, and pr ovide lateral containment of dust and residue during street sw eeping operations, subject to the approval of the Director of Engineering/Public Works.

4.24 Construct all roadways, parking lots, drive aisles, curbs and gutters, sidewalks and driveways to uniforml y connect t o existing adjacent public and/or private improvements within and adjacent TPM as shown on the Plans to the sat isfaction of the Director of Engineering/Public Works.

4.25 Construct all appurtenant roadway components such as, but not lim ited to: cur b, gutter, sidewalk, ADA ramps, traffic control striping, legends, traffic control signs and street name signs to the satisfaction of the Direct or of Engineering/Public Works.

4.26 Existing Decorative Street Lights:

a. P hase I:

i. The Developer shall coor dinate an d pay all cost necess ary for the refurbishment, LED ret rofit and re- installation of the below detailed City owned street lights ; and coordinate with S CE and the City for t he Developer (and subsequent assi gnees to be inc orporated in the CC& Rs) to take over the monthly electrical expense for the street lights ; and coordinate with the City for the Developer (and subsequent assignees to be incorporated in the CC&Rs) to take over all future related maintenance, refurbishment an d replac ement costs, prior to the i ssuance of the first COO. The Developer shall execute a Street Light Covenant covering all Cathedral Cove Center
September 28, 2022

Page 23 of 53 ends

the above, to be incorporated int o the CC &Rs, and be review ed and approved by the Director of Engineering/Public Works prior to recordation.

1) Remove, refresh with ne w purple coating, c onvert to LED, and reinstall the eight (8) e xisting decorative street lights along the Phase I East Palm Canyon Drive fro ntage f rom the eastern boundary of Phase I (east property line of APN 674-500-038) to the west boundary of Phase I, per City Standards, with the final locations subject to approval by the Director of Engineering/Public Works prior to the issuance of the first COO.

B. P hase II – Retail

i. The Developer shall coor dinate and pay all cost nece ssary for the refurbishment, LED re trofit and re- installation of the below detailed City owned street light; and coordinate with SCE and the City for the Developer (and subsequent assignees to be incorporated in the CC&Rs) to take over the monthly electrical expense for the street light; and coordinate with the City for the Developer ( and subsequent assi gnees to be inc orporated in the CC&Rs) to take over all future related maintenance, refurbishment and replacement costs, prior to the issuance of the first COO. The Developer shall execute a Street Light Covenant covering all the above, to be incorporated int o the CC &Rs, and be reviewed and approved by the Director of Engineering/Public Works prior to recordation.

1) Remove, refresh with new purple coating, convert to LED, and reinstall the one (1) existing decorative street light along the Phase III East Palm Canyon Drive frontage from the eastern boundary of Phase II - Retail to the west boundary of Phase II - Retail, per City Standards, with the final locations subj ect to approval by the Director of Engineering/Public Works prior to the iss uance of the first COO.

4.27 New Standard Street Lights:

a. Phase II - Residential:

i. The Developer shall coordin ate and pay all c ost necessary for the installation of the below detailed City and Southern California E dison (SCE) approved standard LED street lights with SCE and the Developer (and subsequent assignees to be incorporated in the CC&Rs) to take over all related expense s, including the monthly electrical expense for the street lights installed prior to the issuance of the first COO. The Developer shall execute a Street Light Covenant, to be incorporated into the CC& Rs, and be reviewed and approved by the Dire ctor of Engineering/Public Works prior to recordation.

Cathedral Cove Center
September 28, 2022

Page 24 of 53 ends

1. Install three (3 ) 5,800 lumen shielded LED street light s along the Van Fleet Street frontage of the TPM, per City and SCE Standards, with the final locations su bject to approval by the Director of Engineering/Public Works prior to the issuance of the first COO.

2. Install three (3 ) 5,800 lumen shielded LED street light s along the “D” Street frontage of the TPM, per City and SCE Standards, with the final location s subject to approval by the Direct or of Engineering/Public Works prior to the issuance of the first COO.

b. Phase II- Retail:

i. The Developer shall coordin ate and pay all cost necessary for the installation of t he below detailed City and Southern California Edison (SCE) approved st andard LED street lights wit h SCE and the Developer (and subsequent assignees to be incorporated in the CC&Rs) to take over all rela ted expenses, including the monthly electrical expense for the street lights installed prior to the issuance of the first COO. The Developer shall execute a Street Light Covenant, to be incorporated into the CC& Rs, and be reviewed and app roved by the Dir ector of Engineering/P ublic Works prior to recordation.

1. Install one (1) 5,800 lumen shielded LED street light along the Van Fleet Street frontage of the TPM, per City and SCE Standards, with the final loca tions subject to approval by the D irector of Engineering/Public Works prior to the issuance of the first COO.

4.28 If applicable, t he Developer of each phase shall coordinate and pay all cost necessary for the undergrounding and removal of all, and not limited to, aerial wires, power line s, telephone wires, c able lines, communication equipment, pole under burden and respective poles that are within this TPM, per CC Municipal Code 8.30.050, p rior to the issuance of the first COO within each phase to the satisfaction of the Director of Engineering/Public Works.

4.29 The Developer of each phase will design a nd install on site stormwa ter drainage facilities for each phase:

i. Within the paved and lands caped areas o f each phase of the TPM, the Developer will design facilities to capture all onsite nuisance and stormwater , with breakout facil ities, per Cathedral City Municipal Code require ments and other conditions specified herein to the satisfaction of the Director of Engineering/Public Works.

ii. T he Developer of Pha se I will install facilities du ring the TPM’s Phase I construction to temporarily either capture and/or pass-through all stormwater Cathedral Cove Center
September 28, 2022

Page 25 of 53 ends

from the Phase II - Residential Parcels immediately to the so uth to a stormwater inlet and/or outlet drain on the eastern boundary of Phase I to the satisfaction of th e Director of E ngineering/Public Works . Phase I will be required to pass receive and/or pass through breakout stormwater from Phase II – Residential.

iii. T he Developer of Ph ase II – Residential will design permanent facilities to capture all required nuisance and 100-year stormwater on the Phase II – Residential parcel(s) and only pass through to Phase I breakout stormwater.

iv. T he Developer of each p hase shall offer for dedica tion to t he City tho se easements necessary for acc ess to drainage facilities and basi ns, by separate instrument. The Developer of each phase required to execute a Water Quality Management Plan and Urban Runoff Best Management Practices Transfer, Access an d Maintenance Covenant with the City (as part of the WQMP) and incorporate in each phase’s CC&Rs prior to issuance of the Grading Permit.

4.30 Dedications shall include additional widths as necessary for dedicated right and left turn lanes , deceleration a nd ac celeration lanes, bus turnouts and other features that may be contained in the TPM’s Plans.

4.31 When the Director of Engineering/Public Works determines that access rights to the proposed street r ights-of-way shown on the T PM’s Plans are necessary prior to the approval of the Fi nal Parcel Map ded icating suc h righ ts-of-way, the Developer shall grant the necessary rights -of-way within 60 days of a written request by the City.

4.32 Where public facilities ( e.g., sidewalks) are plac ed on p rivately owned setbacks, the Applicant shall offer for dedication blanket easements for those purposes by separate instrument prior to the issuance of the first COO.

4.33 The Developer of each phase sha ll cause all missing property corners and survey monuments within the boundaries of the TPM to be set prior to the issuance of the first COO, in accordance with the Subdivision Map Act and City requirements.

4.34 The Developer of each phase shall furnish proof of easements , or written permission, as appropriate, from those owners of all a butting properties on w hich, and not limited to, grading, wall construction, retaining wal l constr uction, permanent slopes, s treet improvements, sidewalks, driveways, utility relocations, other encroachments and other construction activities will occur.

i. F urther, all abutting properties disturbed by the Developer of each phase, and not limited to, grading, wall cons truction, retaining wall co nstruction, permanent slopes, street improve ments, sidewalks, dr iveways, utility relocations, other encroachments and other construction activities Cathedral Cove Center
September 28, 2022

Page 26 of 53 ends

performed by the Developer, will b e restored to original and/or improved conditions subject to the prior rev iew and approval of the Director of Engineering/Public Works and/or Director of Planning/Building.

4.35 The Developer of each phase shall cause no easement to be granted, or recorded, over any portion of the sub ject property between the date of approval of the TPM and the date of issuance of the first COO, unless such easement is approv ed by the Director of Engineering/Public Works.

4.36 The Developer of each phase will coo rdinate all pr ivate roadway improvements and driveway transitions with the adjacent property owners (public and/or private) and coordinate relocation of fire hydrants, water me ters and all o ther appurtenances as required to the satisfaction of the Director of Engineering/Public Works.

4.37 Improvements shall be designed and constructed in accordance with City adopted standards, supplemental drawings and specifications, or as approved by the Director of Engineering/Public Works.

4.38 All impr ovements will be subject to City requirements for i nspection during construction.

4.39 The City will conduct final inspections of structures only when the buildings have improved street and sidewalk acce ss to stre ets, including ADA access. Th e improvements shall include required traffic control devices, pavement mark ings and street name signs.

4.40 The Developer shall be responsible for the vacation and grantin g of easements that address changes in the existing easeme nts over the pr oposed TPM that may be affec ted by proposed improvements. Pursuant this condition, the Developer shall apply to the City for any street vacation requ est of public right -of-way and/or utility easements. The Developer must provide all applicab le exhibits and legal descriptions and perform all necessary abandonments or relocation of easements and/or facilities as required by all affected utility purveyors over the public rights - of-way and/or utility easements, or as approved by the Director of Engineering/Public Works. Typ ically, the r ight-of-way vacation process is up to three (3) months.

PUBLIC IMPROVEMENTS

4.41 The Developer of each phase shall pay all costs to engineer, construct, dedicate and complete the following street and traffic signal modification improvements to conform to these Conditions of Approval, the General Plan and the requirements of the T PM’s Traffic Analysis for the Cathed ral Cove Center, prepared by Urban Crossroads, dated April 8, 2022:

Cathedral Cove Center
September 28, 2022

Page 27 of 53 ends

Exception: The City shall be responsible for monitoring conditio ns at the offsite intersections of Cathedral Canyon Drive/Dinah Shore Drive and Date P alm Drive/Ramon Road and providing improvements to those intersections through its Capital Improvement Program and/or local, State or federal funding at su ch time as the improvements are warranted, thereby mitigating the TMP’s impacts to these intersections.

A. PUBLIC IMPROVEMENTS

i. Phase I:

1. Phase I public improvements for the purposes of these Conditions of Approval, will include the TPM ’s no rth property lin e frontage along E ast Palm Canyon Drive abutting Parcel 6 ’s east p roperty line in Phase II - Retail, east to the eastern boundary of TPM’s APN 674-500-038 and south abutting Parcel 9. Phase I include Parcels I through 5 and APN 674-500-038.

2. All P hase I improvem ents will be com pleted by the Developer of Phase I prior to the issuance of the first COO of Phase I.

3. East Palm Canyon Drive – Public roadway as shown on the Plans and per these Conditions of Approval shall include the following:

a. East Palm Canyon D rive is a public roadway and is
designated as an Arterial Highway with a 126 ft. right of way (half street right of way is 63 feet).

b. Street measured at curb to curb shall have a minimum 94 ft. street width. T he location of the south curb line shall be a minimum of 4 7 feet south of t he East P alm Canyon Drive centerline of improvements as ge nerally s hown on the TPM’s Plans.

c. From Parcel 5’ west proper ty line to the Allen Avenue driveway entrance construct and/or replace:

i. A minimum 8 to 16 feet wi de sidewalk to p rovide
smooth transition an d connectively west and east in
accordance with ADA and RC Standards 401 or 40 4
as generally shown on th e TPM’s Plans to the
satisfaction of the D irector of Engineering/Public
Works.

ii. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutte r, Cathedral Cove Center
September 28, 2022

Page 28 of 53 ends

sidewalk, a.c., ADA ramps, tra ffic control stri ping,
legends, LED traffic control signs and street name
signs to the satisfaction of the Director of
Engineering/Public Works. The City shall identif y all such areas prior to issuance of the Grading Permit.

d. Fronting Parcel 5 remove:

i. The existing eastbound to s outhbound deceleration
lane island at East P alm Canyon Drive and Allen
Avenue and remove all landscaping, electrical, storm
drain, traffic si gnal facilities and all other ancillary accessories. Rep lace asphalt within this area per
these Conditions of Approval to the satisfaction of the Director of Engineering/Public Works. Removed
facilities that a re salvageable and subject to
refurbishment may be r elocated if approved prior by
the Director of Engineering/Public Works.

e. From the Al len A venue driveway entrance east
approximately 430 feet along the frontages of Parc els 4, 3 and 2 construct:

i. New curb, gutter and a.c. as part of street widening to connect t o existing curb, gutter and a.c. within and
east of Parcel 2 with a smooth taper transition
designed and constructed as generally shown on th e
TPM’s Plans to the satisfaction of the Director of
Engineering/Public Works.

f. From the Allen Avenue driveway entrance to the Date Pal m Drive entrance construct and/or replace:

i. A minimum 8 to 16 feet wide si dewalk to provide
smooth transition and connectivity west and east in
accordance with ADA and RC Standards 401 or 404
as generally shown on th e TPM’s Plans to the
satisfaction of the Director of Engineering/Public
Works.

ii. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutter , sidewalk, a.c., ADA ramps, tra ffic control striping,
legends, LED t raffic control signs and street name
signs to the satisfaction of the D irector of
Cathedral Cove Center
September 28, 2022

Page 29 of 53 ends

Engineering/Public Works. The City shall identify all
such areas prior to issuance of the Grading Permit.

g. From the Date Palm entrance to the east TP M lim its including the e ast property line of APN 674- 500-038
construct/modify and/or repair:

i. Non-compliant and/or brok en r oadway and parkway
components such as, and not limited to: curb, gutter , sidewalk, a.c., ADA ramps, t raffic control striping,
legends, LE D traffic control s igns and street name
signs to the satisfaction of the Director of
Engineering/Public Works. The City shall identify all
such areas prior to issuance of the Grading Permit.

h. In all areas where new curb and gutter is constructed as part of stree t widening and as gener ally shown on t he TPM’s Plans along the East Palm Canyon Drive frontage:

i. Replace a.c. to a thi ckness per thes e Conditions of Approval to the satisfaction of the Dir ector of
Engineering/Public Works.

ii. Grind and overlay A minimum of 1- inch a.c. to the centerline of improvements or less as approved by
the Director of Engineering/Public Works to c reate
and/or maint ain a 2% crossfall to the adjacent curb
and gutter and the exte nt of the grind and overlay
meeting these requirements shall be identi fied on the Civil Engineering Street Plans.

i. Along the entire East Palm Can yon Drive frontage of Phase I:

i. Apply Type II REAS (Rubberized Emulsion Aggregate
Slurry) from the gutter pan to the centerline of
improvements to the satisfaction of the Director of
Engineering/Public Works.

ii. Restripe all lanes , crosswalks and turning pocke ts, including legends as generally shown on the TPM’s
Plans to the satisfacti on of the Director of
Engineering/Public Works.

iii. Construct all street, curb and gutter to uniformly connect to existing a djacent improvements east and
Cathedral Cove Center
September 28, 2022

Page 30 of 53 ends

west of the TPM to the satisfaction of the Director of Engineering/Public Works.

iv. East Palm Canyon Drive frontage will be d esignated as “No Stopping” with signs posted as ap proved by
the Director of Engineering/Public Works.

4. East Palm Canyon Drive Intersections:

a. East Palm Canyon Drive/Allen Avenue intersection:

i. Replace, protect in place/refurbish, relocate/refurbish (if meets current standards and approved by the
Director of Engineering/ Public Works ) and/or i nstall new, all traffic signal equipment, lighting equipment
and all related appurtenances making the traffic signal fully operational at the East Palm Canyon Drive/Allen
Avenue intersection to make the in tersection fully
functional adhering to current CA traffic safe ty and
ADA standards to the satis faction o f the Director of
Engineering/Public Works.

1. Appurtenances include and are not limited to:

a. ADA audible pedestrian call buttons
b. Controllers
c. Cabinets
d. Poles
e. Mast arms
f. Signal heads
g. Signage
h. Traffic safety lights
i. Signal timing
j. Etc.

ii. Complete all traffic signal engineering, signal retiming and synchronization coordination modifications
necessary for local and regional signal operation.

iii. Replace existing pedestrian call buttons with ADA
audible pedestrian cal l buttons as approve b y the
Director of Engineering/Public Works.

iv. Replace the existing traffic safety lights with LED traffic safety lights as approve by the Director of
Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 31 of 53 ends

v. Restripe eas t, west , south and north pedestrian
crosswalks and turn pockets to the satisfaction of the
Director of Engineering/Public Works.

vi. Construct and/or reconstruc t ADA pedes trian
sidewalk ramps on the south side of the East Palm
Canyon Drive/Allen Avenue intersection to conform to
Cal Trans A -88-A as approv ed by the Director of
Engineering/Public Works.

b. East Palm Canyon Drive and Date Palm Drive intersection:

i. Replace, protect in place/refurbish, relocate/refurbish (if meets current standards and approved by the
Director of Engineering/Public W orks) and/or install
new, all traffic signal equipment, lighting equipment
and all related appurtenances making the traffic signal fully operational at the East Pal m Canyon Drive /Date
Palm Drive intersection to make the intersection fully
functional adhering to current CA traffic safe ty and
ADA standards to the s atisfaction o f the Director of
Engineering/Public Works.

1. Appurtenances include and are not limited to:

a. ADA audible pedestrian call buttons
b. Controllers
c. Cabinets
d. Poles
e. Mast arms
f. Signal heads
g. Signage
h. Traffic safety lights
i. Signal timing
j. Etc.

ii. Complete all traffic signal engineering, signal retiming and synchronization coordination modifications
necessary for local and regional signal operation.

iii. Replace existing pedestrian call buttons with ADA
audible pedestrian call buttons as approve by the
Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 32 of 53 ends

iv. Replace the existing traffic safety lights with LED traffic safety lights as approve by the Director of
Engineering/Public Works.

v. Install the east pedestrian crosswalk with a ll related equipment and appurtenances.

vi. Construct a minimum 160-foot left lane turn pocket at the east side of East Palm Canyon Dri ve intersection
for west bound traffic to turn left/southbound to enter the TPM’s Date Palm Drive entrance.

1. Left turn pocke t design and construction will
require the removal, relocation and restoration
of the existing med ian art work, signag e and
lighting system as approved by the Director of
Engineering/Public Works.

vii. Restripe eas t, west , south and north pedestrian
crosswalks and turn pockets to the sat isfaction of the Director of Engineering/Public Works.

viii. Construct and/or reconstruc t ADA p edestrian
sidewalk ramp s on the south side of the East Palm
Canyon Driv e/Date Palm Drive intersection to
conform to Cal Trans A -88-A as approved by the
Director of Engineering/Public Works.

ix. Construct Date Palm Drive south of East Palm
Canyon drive to integrate with the proposed privat e
improvements of the TPM.

5. Date Palm Drive is a p ublic r oadway as shown on the Plans and per these Conditions of Approval shall include the following:

a. Date Palm Drive is a public roadway and is designated as an Arterial Highway with a 126 ft. right of way (half street right of way is 63 feet).

b. Street measured at curb to curb shall have a minimum 94 ft. street width.

c. Along the TPM ’s Date Palm Drive frontage south of East Palm Canyon Drive reconstruct:

Cathedral Cove Center
September 28, 2022

Page 33 of 53 ends

i. Date Palm Drive to integrate with the proposed
private improvements of the TPM and maintenance to
be assumed by the Applicant under a Maintenance
Performance Agreement.

ii. Restripe all lanes , crosswalks and turning pockets, including legends to be shown on the TPM’s Plans to
the satisfactio n of the Direct or of Engineering/Public Works.

iii. Construct all street, curb and gutter to uniformly connect to existing ad jacent improve ments east and
west of the TPM to the satisfa ction of the Director of Engineering/Public Works.

iv. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutter , sidewalk, a.c., ADA ramps, tra ffic control striping,
legends, LED traffic con trol signs and street na me
signs to the satisfaction of the Director of
Engineering/Public Works . The City shall identify all
such areas prior to issuance of the Grading Permit.

ii. Phase II - Residential

1. Phase II - Residential improvements for the purposes of th ese Conditions of Approval, will include the TPM’s frontages abutting and south of Phase I (Parcels 1 through 5) , Phase II - Retail (Parcels 6 through 8), east along the East Cathedral Canyon Flood Control Channel’s west b ank, abutting and north of “D” Street and abutting and west of Van Fleet Street.

2. All Phase II - Residential improvements will b e completed by the Developer of Phase II - Residential prior to the issuance of the first COO of Phase II - Residential and linked to t he completion of the East Palm C anyon Drive frontage and East Palm Cany on
Drive/Van Fleet Street intersect ion improvements within Phase II - Retail. Further, upon the completion of the purchase and/or sale of Parcel 9, the Developer of Phase 1 will initia te the design and construction of the aforementioned Phase II - Retail improvements (East Palm Canyon Driv e frontage and East Palm Canyon
Drive/Van Fleet Street intersection improvements ) and complete the improvements within eighteen (18) months of the sale date.

3. All future driveway, access points, street and right of way infrastructure currently not i dentified in Phase II - Residential are Cathedral Cove Center
September 28, 2022

Page 34 of 53 ends

required to be submitted with the Phase II – Residential Developer’s application for the entitlement of Phase II - Residential (Parcel 9) and will be subject to additional Conditions of Approval.

4. “D” Street – Public roadway as shown on the Plans and per these Conditions of Approval shall include the following (to be completed in conjunction with the Phase II – Residential construction):

a. “D” Street is a public roadway and is designated as a residential ro adway with a 50 foot right of way (north from centerline is 30 feet and south from centerline is 20 feet).

b. Street measured cur b to curb shall have a 30- foot street width.

c. The existing cul-de-sac along the TPM ’s “D” Street Phase II frontage at the east end of “ D” Street will be reconstr ucted as follows:

i. Existing curb, gutter, sidewalk and a.c. improvements will be removed and replac ed with new curb, gutter,
sidewalk a nd a.c. improvements as required for a
reduced configuration size, shap e and geometric
alignment matching Riverside Count y (RC) Standard
No. 800(A) to be shown on the TPM Plans as final
approved by the City Fire Chief and Director of
Engineering/Public Works.

d. Along the TPM ’s “D” Street Phase II fronta ge replace, rehabilitate and/or modify:

i. Apply Type II REAS (Rubberized Emulsion Aggregate
Slurry) from the gutter pan to the centerline of
improvements to the satisfaction of the Director of
Engineering/Public Works.

ii. Restripe all lanes , c rosswalks and turning pockets, including legends to be shown on the TPM’s Plans to
the satisfaction of the Director of Engineering/Public
Works.

iii. Construct all street, curb and gutter to uniformly connect to existing ad jacent improvements east and
west of the TPM to the satisfaction of the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 35 of 53 ends

iv. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutter,
sidewalk, a.c., ADA ramps, tra ffic control striping,
legends, LED traffic control signs and street name
signs to the satisfaction of the Director of
Engineering/Public Works. The City shall identify all
such areas prior to issuance of the Grading Permit.

5. “D” Street Intersection (to be completed in conjunction with the Phase II – Residential construction):

a. D Street/Van Fleet Intersection:

i. Reconstruct the ADA pedestrian sidewalk ramp at the
southeast corner to conform to Cal Trans A -88-A
Case B Detail B as approved by the Director of
Engineering/Public Works.

6. Van Fleet Street – A public roadway as shown on the Plans and subject to t hese Conditions of Approval shall i nclude the following (to be completed in conjunction with the P hase II – Residential construction):

a. Van Fleet is a public roadway and is designated as a collector with a 58 foot right of way.

b. Van Fleet centerline to east curb is 30 feet.

c. Along the TPM ’s Van Fleet Street Phase III frontage, rehabilitate and/or modify:

i. Apply Type II REAS (Rubberized Emulsion Aggregate
Slurry) from the gutter pan to t he ce nterline of
improvements to the satisfaction of th e Director of
Engineering/Public Works.

ii. Restripe all lanes , c rosswalks and turning pockets, including legends to be shown on the TPM’s Plans to
the satisfaction of the Director of Engineering/Public
Works.

iii. Construct all street, curb and gutter to uniform ly connect to exi sting ad jacent improvements east and
west of the TPM to the satisfaction of the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 36 of 53 ends

iv. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutter , sidewalk, a.c., ADA ramps, tra ffic control striping,
legends, LED t raffic control signs and street name
signs to the satisfaction of the Dir ector of
Engineering/Public Works. T he City shall identify all such areas prior to the issuance of a Grading Permit.

iii. Phase II - Retail

1. Phase II - Retail public improvements for the purposes of these Conditions of Ap proval will include the TPM ’s frontages abutting East Palm Canyon Drive to the north, abutting Phase I (Parcels 1 through 5) to the east , abutting Phase II – Residential to the south (Parcel 9) and excluding Parcel APN 687-207-004.

2. All Phase II - Retail improvements will be completed by the Applicant prior to the i ssuance of the first COO of P hase II - Retail.

Refer t o Phase II - Residential Conditions of Approval 4.43.A.ii.2) for completion of the East Palm Canyon Drive frontage improvements and East Palm Canyon Drive/Van Fleet Street intersection improvements within Phase II – Retail I if Phase II – Residential precedes Phase II - Retail.

3. East Palm Canyon D rive - Public roadway as shown on the Plans and per these Conditions of Approval shall include the following:

a. East Palm Canyon D rive is a public roadway and is
designated as an Arterial Highway with a 126 ft. right of way (half street right of way is 63 feet).

b. Street measured at curb to curb shall have a minimum 94 ft. street width. T he location of the south curb line shall be a minimum of 47 feet south of the East P alm Canyon Drive centerline of improvements as ge nerally shown on the TPM’s Plans.

c. From Van Fleet Street east to the east property line of Parcel 7 construct:

i. New sidewalk, curb , gutter and a.c. as part of street widening to connect t o existing sidewalk, curb, gutter and a.c. east of Parcel 7’s east property line, including and additional interim concrete taper tra nsition curb
designed, constructed and to be shown on the TPM’s
Cathedral Cove Center
September 28, 2022

Page 37 of 53 ends

Plans to the satisfaction of the Director of
Engineering/Public Works.

d. From the west property line of Parc el 6 e ast to the western portion of Parcel 5 construct:

i. New sidewalk, curb, gutter and a.c. as part of st reet widening to connect t o the existing sidewalk, curb,
gutter and a.c. to the west and east to the western
portion of Parcel 5 to be shown on the TPM’s Plans to
the satisfaction of the Director of Engineering/Public
Works.

ii. A ne w 30-foot-wide City Standa rd 200- B drivew ay approximately 80 feet east of Parcel 6’s west property
line as generally shown on th e TPM’s Plans to the
satisfaction of the Directo r of Engineering/Public
Works.

e. In all areas where new curb and gutter is constructed as part of stree t widening and to b e shown on the TPM’s Plans along the East Palm Canyon Drive frontage:

i. Replace a.c. to a thickness per these Conditions of
Approval to the satisfaction of t he Director of
Engineering/Public Works.

ii. Grind and overlay A minimum of 1- inch a.c. to the centerline of improvements or less as approved by
the Director of Engineering/Publi c Works to c reate
and/or maint ain a 2% crossfall to the adjacent curb
and gutter and the exte nt of the grind and overlay
meeting these requirements shall be identi fied on the Civil Engineering Street Plans.

f. Along the entire East Pa lm Canyon frontage of Phase II - Retail:

i. Apply Type II REAS (Rubberized Emulsion Aggregate
Slurry) from the gutter pan to the centerline of
improvements to the satisfaction of the Direct or of
Engineering/Public Works.

ii. Restripe all lanes , c rosswalks and turning p ockets, including legends as generally shown on the TPM’s
Cathedral Cove Center
September 28, 2022

Page 38 of 53 ends

Plans to the satis faction of th e Director of
Engineering/Public Works.

iii. Construct all street, curb and gutter to uniforml y connect to ex isting ad jacent improvements east and
west of the TPM to the s atisfaction of the Director of Engineering/Public Works.

iv. East Palm Can yon Drive frontage will be designated as “No Stopping” with signs posted as ap proved by
the Director of Engineering/Public Works.

4. East Palm Canyon Drive Intersection:

a. East Palm Canyon Drive/Van Fleet Street intersection:

i. Replace, protect in place/refurbish, relocate/refurbish (if meets current standards and approved by the
Director of Engineering/Public Works ) and/or instal l
new, all traffic signal equipment, lighting equipment
and all related appurtenances making the traffic signal fully operational at th e East Pal m Cany on Drive/Van Fleet Street intersection to make the in tersection fully functional adhering to current CA traffic safe ty and
ADA standards to the satisfaction of the Director o f
Engineering/Public Works.

1. Appurtenances include and are not limited to:
a. ADA audible pedestrian call buttons
b. Controllers
c. Cabinets
d. Poles
e. Mast arms
f. Signal heads
g. Signage
h. Traffic safety lights
i. Signal timing
j. Etc.

ii. Complete all traffic signal engineering, signal retiming and synchronization coordination modifications
necessary for local and regional signal operation.

iii. Replace existing pedestri an call buttons with ADA audible pedestrian cal l b uttons as approve by the
Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 39 of 53 ends

iv. Replace the existing traffic safety lights with LED traffic safety lights as approve by the Director of
Engineering/Public Works.

v. Restripe east , west , south and north pedestrian
crosswalks and turn pockets to the sati sfaction of the Director of Engineering/Public Works.

vi. Construct and/or reconstruc t ADA pedestrian
sidewalk r amps on the sout h sid e of the East Palm
Canyon Drive/Allen Avenue intersection to conform to
Cal Trans A -88-A as approved by the Director of
Engineering/Public Works.

5. Van Fleet Street – A public roadway as shown on the Plans and subject to these Conditions of Approval shall include the following:

a. Van Fleet Street is a public roadway and is designated as a collector with a 58 foot right of way.

b. Van Fleet Street centerline to east curb is 30 feet.

c. Along the TPM’s Van Fleet Stree t Phase II - Retail frontage, rehabilitate and/or modify:

i. Apply Type II REAS (Rubberized Emulsion Aggregate
Slurry) from the gutte r pan to the centerline of
improvements to the satisfaction of the Director of
Engineering/Public Works.

ii. Restripe all lanes , c rosswalks and turning p ockets, including legends to be shown on the TPM’s Plans to
the satisfa ction of the Director of Engineering/Public Works.

iii. Construct all street, curb and gutter to uniformly connect to existing ad jacent improveme nts east and
west of the TPM to the satisfac tion of the Dire ctor of Engineering/Public Works.

iv. Non-compliant and/or broken r oadway and parkway
components such as, and not limited to: curb, gutter , sidewalk, a.c., ADA ramps, tra ffic control striping,
legends, L ED traffic control signs and street nam e
signs to the satisfaction of t he Director of
Cathedral Cove Center
September 28, 2022

Page 40 of 53 ends

Engineering/Public Works. City shall identify all such areas prior to the issuance of a Grading Permit.

6. Van Fleet Street Intersection:

a. Van Fleet Street/ ”A” Street intersection (to be completed in conjunction with the Phase II – Retail construction):

i. Construct a 30-foot-wide Riverside County
Commercial Driveway - Standard No. 207A, to comply
with ADA standards as generally show on the Plans
to the sati sfaction of the D irector of
Engineering/Public Works.

7. “A” Street Public roadway as shown on the Plans and per these Conditions of Approval shall include the following:

a. “A” Street is a public roadway and is designated as
commercial access roa dway with right of way that va ries from 40 to 45 feet and is 200 feet in length.

b. Street measured cur b to cu rb shall be a minimum 30- foot street width (“A” Street centerline to south curb is 14 feet and north curb 16 feet).

c. Along the TPM’s “A” Street frontage reconstruct:

i. The Phase II - Retail CC&Rs shall incorporate the
ongoing maintenance a nd upkeep of the street
improvements within the non-vacation public portion
of “A” Street, east of V an Fleet Street in a form as
approved by Director of Engineering/Public Works.

ii. Restripe all lanes , c rosswalks and turning pockets, including legends to be shown on the TPM’s Plans to
the satisfaction of th e Director of Engineering/Public Works.

iii. Construct all street, curb and gutter to uniformly connect to existing ad jacent improvements east and
west of the TPM to the satisfaction of the Director of Engineering/Public Works.

iv. Non-compliant and/or broken r oadway and parkway
components such as, and not limit ed to: curb, gutter , sidewalk, a.c., ADA ramps, tra ffic control striping,
Cathedral Cove Center
September 28, 2022

Page 41 of 53 ends

legends, LED traffic control signs and street name
signs to the satisfaction of t he Director of
Engineering/Public Works. The City shall identify all such areas prior to the issuance of a Grading Permit.

4.42 Coordinate all public and private roadway improvements and driveway transitions with the ad jacent property owner and coordinat e relocation of fire hydrants, water meters, storm drains, and all other appurtenances as required to the satisfaction of the Director of Engineering/Public Works.

4.43 Streets shall have A-6 or A-8 curbs per County of Riverside (RC) Standards, which will co nvey water with out ponding, and provide lat eral contain ment of dust and residue during street sweeping operations.

4.44 Construct all concrete sidewalk per RC Standards, with all r equired ADA ramps and utility offsets as approved by the Director of Engineering/Public Works.

4.45 Construct all appurtenant roadway component s such as, but not limited to: curb , gutter, sidewalk, ADA ramps, traf fic control striping , legends, traffic control signs and street name signs as approved by the Director of Engineering/Public Works.

4.46 The Developer shall design street pavement sec tions using C al Tra ns’s design procedure for 20- year life pa vement, and the site- specific data for soil strength and anticipated traffic loading (including construction traffic). Replace in kind or minimum structural sections, with asphalt placed in two lifts, shall be as follows:

East Palm Canyon Drive: In kind or minimum 5.5” a.c./6.5” class II base

D Street: 3.0” a.c./4.5” class II base

Van Fleet Street: 4.0” a.c./5.0” class II base

4.47 The Developer will cooperate with all adjacent developers and property own ers to assure that drainage, access and roadway d esigns are constructed to assure that all adjacent public works infrastructure is constructed in a uniform manner as approved by the Director of Engineering/Public Works.

4.48 Curve Radii for curbs at all street intersections shall not be les s than 35 feet or matching opposing ap proved corner curve r adii or as approved by the Director of Engineering/Public Works.

4.49 Right-of-Way ge ometry for property line corner cut -backs at curb returns shall conform to RC Standar d Drawing No. 805 unless otherwise appro ved by the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 42 of 53 ends

4.50 The Developer will remove all existing lan dscaping, monuments and/or structu res that the Director of Engineering/Public Works determines to impair vehicle, bicycle and/or pedestrian line-of-sights along all the frontages associated wit h this TPM and to be shown on the Civil Engineering Plans for each phase.

4.51 The Developer will coordinate all publ ic an d private roadway improvements and driveway transitions with the adjacent property owners (public and/or private) and coordinate relocation of fire hydrants, water meters and all other appurtenances as required to the satisfaction of the Director of Engineering/Public Works.

4.52 The Developer shall construct all stre et, cu rb and gutter to u niformly connect to existing adjacent improvements north, south, east and west of the TPM along the East Palm Canyon Drive, D Street, Van Fleet , A Stree t and Date Palm Drive frontages, respectively, to the satisfaction of the Director of Eng ineering/Public Works prior to the issuance of the first COO of each phase.

4.53 Improvements shall be designed and constructed in accordance with City adopted standards, supplemental dra wings and specifications, or as approved by the Director of Engineering/Public Works.

4.54 All public and pri vate improvements shall be s ubject to City r equirements for inspection during construction.

4.55 The City will conduct final inspections of structures only when the buildings have improved street and sidewalk access to publicly maintained street s. The improvements shall include required traffic control devices, pavement markings and street name signs.

IMPROVEMENT PLANS

As used t hroughout these Cond itions of Approval, professional titles such as “engineer,”’ “surveyor,” and “architect,” refer to persons currently certified or licensed to practice their respective professions in the State of California.

4.56 Improvement plans shall be prepared by or under the direct su pervision of qualified engineers and/or architects, as appropriate, and shall com ply with a ll requirements of the City of Cathedral City.

4.57 The following improvement plans shall be prepared and submitted for review by the Engineering Department. A separate set of plans for each line item specified below, for each phase, shall be prepared. The plans shall utilize the minimum scale specified, unless authorized by the Director of Engineering/Public Wor ks.

Plans may be prepared at larger scale if additional detail or plan clarity is desired.

Cathedral Cove Center
September 28, 2022

Page 43 of 53 ends

NOTE: Th e Developer may be required to prepare other improveme nt plans not listed here pursuant to impr ovements requi red by other ag encies and utility purveyors.

NOTE: All Plans will be prepared by a Civ il E ngineer li censed to practice their profession in the State of California.

A. On-Site Rough Grading Plan 1” = 40’ Horizontal
B. PM 10 Plan 1” = 40’ Horizontal plan and report form C. Erosion Control Plan 1” = 40’ Horizontal
D. WQMP (Plan submitted in report form)

NOTE: A through D to be submitted concurrently.

NOTE: Rough Grading Plan shall normally include perimeter wall with Top of Wall and Top of Footing elevations shown. All footings shall have a minimum of 1-foot of cover, or sufficient cover to clear any adjacent obstructions.

E. Precise Grading Plan 1” = 40’ Horizontal
F. On Site Storm Drain Plan 1” = 40’ Horizontal
G. Off Site Storm Drain Plan 1” = 40’ Horizontal, 1’ = 4’ Vertical H. On Site Street Improvement Plan 1” = 40’ Horizontal, 1’ = 4’ Vertical I. Off Site Street Improvement Plan 1” = 40’ Horizontal, 1’ = 4’ Vertical J. Street Signing and Striping Plan 1” = 40’ Horizontal K. Signal Plan 1” = 40’ Horizontal

NOTE: E through K to be submitted concurrently.

NOTE: The stre et impr ovement plans shall s how the sidew alk in the combined parkway and landscape setback area.

NOTE: Separate Storm Drain Plans are required.

Other engineered improvement plans prepared for City approval that are not listed above shall be prepared in formats approved by the Director of Engineering/Public Works prior to commencing plan preparation.

All Plan and P rofile Street P lans and Signing and Striping plans shall sh ow all existing improvements for a distance of at least 200- feet beyond the project limits, or a distance sufficient to show any required design transitions.

All Signing and Str iping Plans shall s how, at a minim um; Stop Signs, Limit Lines and Le gends, No Parking Signs, Raised Pavement Markers (RPMs) (including Blue RPMs at fire hydrants), curb paint limits and Street Name Signs per Cathedral City Standard Plans an d/or as approved by the Direct or of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 44 of 53 ends

4.58 The Developer shall f urnish accurate Mylars of all improveme nt plans to the Director of Engineering/Public W orks for approval. The improv ement plans shall be of a scale approved by the Director of Engineering/Public Works.

4.59 The Developer shall furnish a copy of all approved i mprovement plans on an electronic storage media acceptable to the Director of Engineering/Public Works.

4.60 Upon completion of construction and prior to final acceptance of the improvements by the City, the Developer shall furnish the City with reproducible record draw ings of all imp rovement plans which were approved by the City. Each sheet sh all be clearly marked “As Buil t” an d shall be stamped and signed by the engineer or surveyor certifyi ng to the accuracy and completenes s of the drawings. The Developer shall have all approved Mylars previously submitted to the City, revised to reflect the as-built conditions. The Dev eloper shall employ or retain t he Engineer of Record (EOR) during the construction phase of the project so that the EOR can make site visit s in support of preparing “As Built”. However , if subsequent approved revisions have been approved by the Director of Engineering/Public Works and reflect said “As Bui lt” conditions, the EOR may submit a letter attesting to said fact to the Director of En gineering/Public Works in lieu of Mylar submittal.

IMPROVEMENT SECURITY AGREEMENTS

4.61 Prior to approval of the Final P arcel Map (FPM) and prior to the issuance of the first COO the Developer shall construct and dedicate all on and off -site improvements and satisfy it s obligations f or same or shall furnish a fully secured and executed Public Works Completion Agreement guaranteeing the construction of such improvements and the satisfaction of it s obligations for same, or shall agree to any combination thereof, as may be required by the City.

4.62 A Public Works Completion Agreement is required prior to issuance o f an Encroachment Per mit o r Building Permit, whichever is issued first . The Public Works Completion Agreement will be entered into by and between the Developer and the City of Cathed ral City, for the purpose of guaranteeing the completion of the public improvements related to this TPM and shall comply with all applicable City Codes and Ordinances.

All required improvement securities shall be in a form and amount as approved by the City Attorney and Director of Engineering/Public Works. Evidence of liability and worker’s compensation insurance coverage shall be submitted as required by the terms of the Public Works Completion Agreement.

4.63 Prior to FPM approval the Developer shall submit for review and City approval Covenants, Conditions and Restrictions (CC &Rs) for the fut ure maintenance and upkeep of (and not limited to) stre et lighting (Street Light Covenant), landscaping Cathedral Cove Center
September 28, 2022

Page 45 of 53 ends

improvements, hardscape improvement s, retention basin improvements and T PM permanent site BMP appurtenances (Water Quality Management Pl an Covenant).

Once approved by the City, Developer shall record the CC&Rs.

4.64 The Developer shall submit ap plicable deposi ts for the cost of reviewing the applicable Public Works Completion Agreem ent(s), Drainage Covenant, Mutual Drainage Easements, Street Light Covenant, PM-10 Cleanup Mitigation Covenant and/or any other requests or form submittals made by the Developer related to this TPM.

4.65 Improvements to be made, or agreed to be made, shall include the removal of any existing structures or other obstruc tions which are not a part of the proposed improvements and shall provide for the setting of the final survey monumentation.

When improvements are phased through a “Phasing Plan,” all improvements (e.g., backbone utilities, retention basins, perimeter wal l, la ndscaping a nd gates) shall be constructed, or secured through a Pu blic Works Completion Agreement, prior to FPM approval or as otherwise approved by t he Director of Engineering/Publ ic Works.

Improvements and obligations required of each subsequent ph ase shall be eit her complete, or secured through a Subdivision Agreement, prior to the is suance of COO of permanent buildings within such latter phase, or as otherwise approved by the Director of Engineering/Public Works.

In the event the Developer fails to construct the improvements for the TPM or fails to satisfy it s oblig ations for the TPM in a timely mann er, pursuant the approved Phasing Plan, the City shall have the right to halt is suance of permits, and/or final inspections, withhold other approvals related to the developm ent of the project, or call upon the surety to complete the improvements.

4.66 Depending on the timing of the developm ent of this TPM , a nd the status of the improvements at the time, the Developer may be required to:

A. Construct certain improvements.

B. Construct additional improvements, subject to the reimbur sement of its cost by others.

C. Reimburse others for those improvem ents previously cons tructed that are considered to be an obligation of this TPM.

D. Secure the costs for future improvements that are to be made by others.

E. To agree to any combination of these means, as the City may require.

Cathedral Cove Center
September 28, 2022

Page 46 of 53 ends

If any of the improvements required for this development ar e constructed by the City, the Developer shall, prior to the approval of the F PM for each phase, or the issuance of any permit related thereto, reimburse the City for the costs of such improvements.

If the Developer elects to utilize the secured agreement alternative, t he Developer sh all submit detailed construction cost estimates for all propose d improvements for each phase, including an estimate for the final survey monumentation, for checking an d approval by t he Director of Engineering/Public Works. Such estimates shall conform to the unit costs schedule as approved by the Director of Engineering/Public Works.

At the time the Developer s ubmits its detailed construction cost est imates for approval of the FPM b y the City Council, the Developer shall also submit an electronic PDF copy of an 8-1/2” x 11” reduction of each page of the FPM, along with an electronic PDF copy of an 8-1/2” x 11” Vicinity Map.

Estimates for improvements under the jurisdi ction of other agencies shall be approved by those agencies and submitted to the City along with the Developer’s detailed cost estimates.

Security w ill not be required for telephone, natural gas, or Cable T.V. improvements.

4.67 The Developer shall provide security to guar antee the final monumentation of t his TPM. All securitie s for fi nal survey monumentat ion will be in the f orm of 100% cash deposits.

GRADING

4.68 The Developer shall comply with all the provisions of Cathedr al City Municipal Codes and Ordinances.

4.69 The Developer shall obtain a Grading Permit approved by the Direct or of Engineering/Public Works prior to initiating any construction or on the TPM site.

4.70 To o btain an approved Grading Permit, the Developer shall s ubmit and obtain approval of all of the following:

A. A G rading Plan prepared by a civil engineer registered in the State of California,

B. A preliminary geotec hnical (“Soils”) Re port prepared by a profess ional registered in the State of California,

Cathedral Cove Center
September 28, 2022

Page 47 of 53 ends

C. A Fugitiv e Dust Control Plan prepared in acc ordance with Ci ty of Cathedral City requirements,

D. An Erosi on Control Pl an prepared in ac cordance wit h City of Cathedral City requirements,

E. A Best M anagement Practices report prepared in accordance with Cathedral City r equirements (N PDES Stormwater Disch arge Permit and Storm Management and Discharge Controls),

F. A WQMP prep ared by an aut horized professional registered in the State of California, and

G. If applicable, a Conditional Letter of Map Revision – Fill (CLOMR-F) issued by the Federal Emergency Management Agency ( FEMA). If the Appl icant is not securing a CLOMR the Appli cant must verify that the entire P roject limits are outside a FEMA designated Flood Hazard Area and/or Area of Flood Hazard Risk as designated by the latest approved F EMA FIRM Map and in accordance with the City of Cathedral Municipal Code Chapter 8.24.

4.71 All grading shall co nform with the recommendations contained in the Preliminary Soils Report, P hase 1 Environmental Assessment report and shall be cer tified as being ad equate by the soi ls engineer, or engineering geologist registered it the State of California.

4.72 A statement shall appear on the Rough and Precise Grading Plan and FPM that a soils report has been prepared in accordance with the California Health and Safety Code § 17953 and California Government Code § 66490.

4.73 The Developer shall furnish security, in a for m acceptable to the Cit y, and in an amount sufficient to guarantee compliance with the approved Fugitive Dust Control Plan provisions as s ubmitted w ith its application for a Grading Permit .

Additionally, the Developer shall replenish said security if expended by the City of Cathedral City to comply with the Fugitive Dust Control Plan as required by the Director of Engineering/Public Works.

4.74 The Developer shall maintain all o pen graded, und eveloped land in order to prevent wind and/or water erosion of such land. All ope n graded, undeveloped land shall either be planted with interim landscaping, or stabilized with such other erosion control measures, as were approved in the Fugitive Dust Control Plan.

4.75 Grading within the par kway areas shall conform to Cathedral City requi rements except as ot herwise modified by this condition. The maximum slope shall not exceed 3:1 anywhere in the landscape setback area , except for the back slo pe (i.e., the slope at the back of the landsc aped lot) which shall not exceed 2:1 if fully planted with ground cover. The maximum slope in the first six (6) feet adjacent to Cathedral Cove Center
September 28, 2022

Page 48 of 53 ends

the curb shall not exceed 4:1 when the nearest edge of sidewalk is within six fee t (6’) of the c urb, otherwise the maximum slope within the right of way sh all not exceed 3:1. All unpaved parkway areas adjacent to the curb shall be depressed one and one-half inches (1.5”) in the first eighteen inches (18’) behind the curb.

4.76 Building pad elevations on the Rough or Precise Gradi ng Plan submitted for Director of Engineering/Public Works’ approval shall conform to the pad elevations shown on the improvement plans, unless the pad elevations have other requirements imposed elsewhere in the Conditions of Approval.

4.77 Building pad eleva tions of perimet er lots shall n ot diffe r by mo re than one foot higher from the building pads in adjacent deve lopments. The Developer shall minimize the differences in elevation between t he adjoining properties an d this Project.

4.78 Prior to any site grading or re-grading that will raise any portion of the site by more than plus or minus half of a foot (0.5’) from the elevation s hown on the approved Grading Plans, the Developer shall submit the proposed grading changes to the Director of Engineering/Public Works for a substantial conformance review.

4.79 Prior to th e issuance of a B uilding Permit for any building, the Developer shall provide a parcel Pad Certification stamped and signed by a quali fied engineer or surveyor with applicable compaction tests and over excavat ion documentation.

Each pad cert ification shal l list the pad elevation as shown on the approved Grading Plan, the actual pad elevation and the difference between the two, if any.

Such Pad Certification shall also list th e relative compaction of the pad soil. The data shall be organized by parcel number and listed cumul atively if submitte d at different times.

4.80 This FPM shall comply with the Cathedral City Floodplain Management Ordinance.

If any portion of any proposed bu ilding parcel in the FPM is or may be locate d within a Flood Ha zard Area as identified on the City’s Flood Insurance Rate Maps (FIRM Ma ps), the develop ment shall be graded to ensure that all floors and exterior fill (at the foundation) are above the level of the project (100- year) flood and building pads are compacted to 95% Proctor Density as required in Title 44 of the Code of Federal R egulations, Sect ion 6 45.5(a) (6). Prior to issuance of building permit s for parcels whic h are so located, the Applic ant shall furnish Elevation Certifications, as required by FEMA , th at the abov e c onditions have been met.

DRAINAGE

4.81 Stormwater handling s hall conform to the a pproved Hydrology and Drainage Report for the TPM . The design of the Project shall not cause any increase in flood boundaries, levels or frequencies in any area outside the development.

Cathedral Cove Center
September 28, 2022

Page 49 of 53 ends

4.82 Incremental increases in stormwater and nuisanc e wat er (drain age) shall be retained on site and shall be disposed of i n an approved manner. Nuisance water shall be disposed of via on- site storm drains, new and exist ing catch b asins, underground percolation piping chambers, dry wells and ret ention basi n(s) as approved by the Director of Engineering/Public Works.

4.83 All drainage water shall b e conveyed underground to the satisfac tion of the Director of Engineering/Public Works.

4.84 Storm water drainage histor ically received from adjoining properti es sh all be received and retained and/or passed though into the historic downstream drainage relief route.

4.85 The Developer shall comply with applicable provisions for p ost construction runoff per the City’s NPDES Storm water Discharge Permit; Riverside Count y Ordinance No. 457; the Californian Regional Water Quality Control Board – Colorado River Basin (CRW QCB-CRB) Regional Board Order No. R7 -2013-0011 and the State Water Resources Control Board’s Order No. 2009- 009-DWQ, Order No. 2010- 0014-DWQ and Order No. 2012-0006-DWQ.

A. For post -construction, urban runoff from New Dev elopment and Redevelopment Projects, the Developer shall implement re quirements of the NPDES permit for the design, construction and the covenants for the perpetual operation and maintenance of BMP s per t he approved W ater Qua lity Management Plan (WQMP) for the project as require by the California Regional Wat er Quality Cont rol Bo ard – Colorado River Basin ( CWQRCB- CRB) Region Board Order No. R7-2013-0011.

B. The Developer shall implement the WQMP Design Standards per (CR WQCB- CRB) Region Board Order No. R7- 2013-0011 utilizing BMPS approved by the Director of Engineering/Public Works.

UTILITIES

4.86 The Developer shall obt ain the approval of the Direct or of Engi neering/Public Works for the location of all utility lines within a ny ri ght-of-way, and all above- ground utility structure s including, but not limited to, tr affic signal cabinets , electrical vaults, water valves, and telephone stands, to ensure o ptimum placement for practical, ADA and aesthetic purposes.

4.87 Any existing overhead utility lines and overhead under -burden within, o r adjacent to the proposed developm ent, and all pr oposed utilities shall be installe d underground per the utility purveyor standards and as approved by the Director of Engineering/Public Works.

Cathedral Cove Center
September 28, 2022

Page 50 of 53 ends

4.88 All proposed new utilities shall be installed underground pe r the utility purv eyor standards and as approved by the Director of Engineering/Public Works.

4.89 Underground ut ilities shall b e installed prior to overlaying hardscape. For installation of utilities in existing improved streets, the Developer shall comply with trench restoration requirements required by the Director of Engineering/P ublic Works.

4.90 The Developer shall provide certified reports of all utility trench compaction for approval by the Director of Engineering/Public Works.

4.91 All facilities within the TPM shall be served with a gravity sanitary sewer system, a domestic water system and a fire protection system in accordance with DWA and City of Cathedral City Fire Department requirements and standards. The Developer shall pay to the City and DWA all applicable sewer and water service charges, capacity charges and construction reimbursements to ensure all services are complete, in place and operational prior to the respective COO being issued.

4.92 The Developer shall abandon or relocate existing easements over TPM prior to the recordation of the TPM as required by the agency and/or individual favored and as approved by the Director of Engineering/Public Works. Additionally, the Applicant shall relocate existing utility f acilities that are required by all utilit y purveyors prior to issuance of the first building permit or as approved by the Director of Engineering/Public Works.

SECTION 5 FIRE PROTECTION
This project has been reviewed as a Group A and M development, any other use will require further review.

Unless specifically stated herei n, these conditions shall not be construed to permit or allow deviation from any Federal or State la ws nor any of the local codes and ordinances adopt ed by this juris diction. Please contact the City of Cathedral City Fir e Department for any questions rega rding compliance with the applicable codes or following conditions:

Note: All references to the 2019 California Fire Code are shown as CFC, the 2019 California Building Code is shown as CBC and the California Code of Regulations are shown as CCR.

AGENCY APPROVALS

5.1 The Final Conditions of Approval for this project shall be included in any site plan or construction plans submitted for permit issuance. Plans will not be approved without reference to these “conditions”.

Cathedral Cove Center
September 28, 2022

Page 51 of 53 ends

5.2 This project is subject to review and approval in accordance with the CCR, Title 19 for Fire and Life Safety. This project is subject to an annual inspection and permit from the Cathedral City Fire Department for this type of occupancy (use).

FIRE ACCESS

5.3 A Fire lane of twenty feet of unobstructed width is required throughout the development. Fire lanes shall be designed and maintained with a vertical clearance of 13 feet, 6 inches.

5.4 Fire lanes shall be constructed per CFC Section 503.

5.5 "No Parking - Fire L ane" signs, red curbing, street signs and/or other required markings shall be provided to the specifications of the Cathedral City Fir e Department in accordance with the CFC, Section 503.3 and California Vehicle Code Section 22500.1.

FIRE PROTECTION

5.6 Fire service water supply shall be provided per CFC, Section 507.

5.7 Automatic Fire Suppression systems shall be provided in all Group A occupancies, and where required per CFC, Chapter 9, a nd Cathedral City Fire Dept.

Development Guidelines.

MISCELLANEOUS

5.8 Future buildings within the development shall be designed with all required fire service features per the CFC and Cathedral City Fire Dept. Development Guidelines.

SECTION 6 BUILDING DEPARTMENT

6.1 The project shall comply with the latest adopted edition of the following codes as applicable:

A. C alifornia Building Code
B. California Electrical Code
C. California Mechanical Code
D. California Plumbing Code
E. California Energy Code
F. California Fire Code
G. California Green Building Standards Code

6.2 Automatic fire suppression sy stems shall be installed in all new constru ction per Chapter 8.12 of the Municipal Code of the City of Cathedral City . Design and Cathedral Cove Center
September 28, 2022

Page 52 of 53 ends

type of system shall be based upon the requirements of the Building and Fire Codes and the requirements of the Cathedral City Fire Department.

6.3 The requirements of the Air Quality Management District shall be satisfied prior to the issuance of any permit if dust and/or pollutants will be discharged into the atmosphere.

6.4 Any te mporary building, trailer, commercial coach, etc. inst alled and/or used in connection with a construction project shall comply with City Code.

6.5 All perime ter/boundary walls shall be designed and constructed so that the outer/exterior face of the wall is as close as possible to the lot line. In any case, the ou ter/exterior face of the wall shall be within two (2) inches of the lot line.

Distances greater t han two (2) inches may be approved prior to construction by the Building Official on a case by case basis for extenuating circumstances.

6.6 All lot lines, ease ment lines, etc. shall be located and/or relocated in such a manner as to not cause any existing s tructure to become non- conforming with the requirements of the latest adopted edition of the Building Code, or any other applicable law, ordinance, or code.

6.7 The Parcel map shall be recorded prior to the issuance of any permits.

6.8 All signs shall be Underwriters Laboratories approved, or equal.

6.9 Permits are required prior to the removal and/or demolition of an structures.

6.10 In addition to approval from Building & Saf ety, approval is required from the County of Riverside, Department of Public Health for occupancies involving foods and beverages.

6.11 All exterior lighting shall be oriented, directed, and/or shielded as much as possible so that direct illumination does not infringe onto adjoining properties.

6.12 The following items (as applicable) shall be completed and/or submitted to Building & Safety prior to the issuance of building permits for this project:

A. Precise grading plans shall be approved
B. Rough grading completed
C. Compaction certification
D. Pad elevation certification
E. Building location certification
F. Rough grade inspection signed off by City Public Works/Engineering General Comments

6.13 A Construction Waste Management Plan (CWMP) will be required at time of plan check submittal.