CITY OF CATHEDRAL CITY
SB 821 - PEREZ ROAD CLASS IV SEPARATED BIKEWAY
Bid Tabulation/ Analysis
CITY PROJECT No.: 8673
1 MOBILIZATION 1 LS 18,550.00$ 18,550.00 $ 15,000.00 $ 15,000.00 $ 12,240.00 $ 12,240.00 $ 2 TRAFFIC CONTROL 1 LS 14,950.00$ 14,950.00 $ 46,000.00 $ 46,000.00 $ 14,000.00 $ 14,000.00 $ 3 SIGNING AND STRIPING 1 LS 74,300.00$ 74,300.00 $ 72,100.00 $ 72,100.00 $ 75,000.00 $ 75,000.00 $ 4 CRACK SEAL AND REAS 215,000 SF 0.78$ 167,700.00$ 0.95 $ 204,250.00$ 0.69 $ 148,350.00$ 275,500.00$ 337,350.00 $ 249,590.00 $ 275,500.00$ 337,350.00 $ 249,590.00 $
DESCRIPTION TOTAL QUANTITY
BID SCHEDULE NO. 1: HSIP 9B
SUB-TOTAL BID SCHEDULE NO.1
TOTAL ALL BID ITEMS
ALL AMERICAN ASPHALT
UNIT COSTUNITITEM
PAVEMENT COATINGS COMPANY
UNIT COST TOTAL
UNION PAVEMENT SERVICES INC.
UNIT COST TOTAL