HSIP 11C RTEA Revised Cost Proposal

Cathedral City City Council
October 6, 2025

Document
HSIP 11C RTEA Revised Cost Proposal
Meeting
October 6, 2025
Body
Cathedral City City Council
Original file
300 KB
Text extracted from the city's file for reading and search. Open the original on cathedralcity.primegov.com. That file is the official record.

RT Engineering & Associates, Inc. (RTEA) Cost Proposal Breakdown (hours and cost is based on proposed schedule timeline above- RFP states 12 month duration from Oct 2025 - Oct 2026) NTP2 - 50 working days
Post Const - Closeout
NTP1 - Administrative & PreConstruction Phase Direct Rate OHM % Burdened Rate Oct-25 Nov-25 Dec-25 Jan-26 Feb-26 Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26 Total Manhours Total Cost PM/Lead Construction Manager - Regina Talamantez 1 hr / month 115.00$ 2.41087 277.25$ 1 1 2 554.50$ Construction Manager - Javier Barrientos 8 hrs/week 90.00$ 2.41087 216.98$ 32 32 64 13,886.61$ Construction Inspector - Robert Hogan 90.00$ 2.41087 216.98$ 0 -$ Office Engineer - Brandon Freese 4 hrs/week 25.00$ 2.41087 60.27$ 16 16 32 1,928.70$ Labor Compliance Officer - Carol Dubree 46.20$ 2.41087 111.38$ 0 -$ Total Manhours NTP1 49 49 0 NTP1 Total Cost 16,369.81$
NTP2 - Construction
PM/Lead Construction Manager - Regina Talamantez 1 hr / month 115.00$ 2.41087 277.25$ 1 1 1 3 831.75$ Construction Manager - Javier Barrientos 8 hrs/week 90.00$ 2.41087 216.98$ 16 32 32 80 17,358.26$ Construction Inspector - Robert Hogan 40 hrs/week 90.00$ 2.41087 216.98$ 80 160 160 400 86,791.32$ Office Engineer - Brandon Freese 4 hrs/week 25.00$ 2.41087 60.27$ 8 16 16 40 2,410.87$ Labor Compliance Officer - Carol Dubree 6 hrs/month 46.20$ 2.41087 111.38$ 6 6 6 18 2,004.88$ Total Manhours NTP2 111 215 215 NTP2 Total Cost 109,397.08$ Post Construction -$
PM/Lead Construction Manager - Regina Talamantez - 1 hr/month 115.00$ 2.41087 277.25$ 1 1 2 554.50$ Construction Manager - Javier Barrientos 4 hrs/week 90.00$ 2.41087 216.98$ 16 16 32 6,943.31$ Construction Inspector - Robert Hogan 90.00$ 2.41087 216.98$ 0 -$ Office Engineer - Brandon Freese 8 hrs/month 25.00$ 2.41087 60.27$ 8 8 16 964.35$ Labor Compliance Officer - Carol Dubree 46.20$ 2.41087 111.38$ 0 -$ Total Manhours NTP1 1082 25 25 0 0 0 0 0 Post Const TC 8,462.15$ OHM: (1.1917+1)*1.1 (fee) = 2.41087
assumed a 12 week procurement time for iluminaires from Oct 27, 2025 thru Jan 29, 2026 Total Cost Proposal 134,229.04$ assumed no earthwork or concrete work needed on this procurement, but we included RMA's fee schedule information 88 assume 20 working days/month
NTP1
Procurement - 12 weeks
196 Total Manhours NTP2