Cathedral City
Landau Boulevard Public Alley
Reconstruction Project (C02607)
Proposal
68-955 Adelina Road
NAI
Cathedral City, CA 92234
Consulting (760) 323-5344
www.naiconsulting.com
NAI
Consulting
September 19, 2025
City of Cathedral City Engineering Department
68700 Avenida Lalo Guerrero
Cathedral City, CA 92234
Subject: ENGINEERING DESIGN SERVICES - LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION (C02607)
Dear Members of the Evaluation Team,
NAI Consulting, Inc. (NAI) welcomes the opportunity to submit this proposal to provide Engineering Design Services for the City of Cathedral City. NAI offers an outstanding project team specializing in civil engineering and project management. Our team possesses the qualifications, experience, enthusiasm, and a positive approach to meet the City's Engineering Department's goals and objectives. These tools will ensure the successful delivery of the City's project and related work objectives.
Established in 1996, NAI is a team of professionals with over 50 years of combined planning and engineering experience. The NAI Team has successfully delivered a vast assortment of local, regional, state, and federally funded projects for numerous agencies within the valley, including the City of Cathedral City.
Lorissa Gruehi, P.E., will serve as Principal-in-Charge and Project Manager. She is a civil engineer by training, has in-depth knowledge of the public works project process, and is an experienced designer and plan checker. Our full office of professional staff supports her to provide as much or as little time as necessary to meet assigned work objectives. We are confident that our experience at NAI will successfully blend with the City of Cathedral City's project needs.
We are teaming with NV5 for survey services. NAI and NV5 have worked together on many projects throughout our Company's history, which will allow us to work together seamlessly to deliver this project.
This proposal will remain valid for 120 days from the proposal due date, September 19, 2025. We look forward to providing the City of Cathedral City with the absolute best services our firm offers. The contact information for this proposal is:
Contact Information:
Lorissa Gruehl
68-955 Adelina Road
Cathedral City, CA 92234
Email: [email protected]
Office: (760) 323-5344
Direct: (760) 799-0066
Respectfully submitted,
Loussa Grishl
Lorissa Gruehl, P.E.
Principal in Charge, Senior Civil Engineering
- 1-
Table of Contents
Proposal
Cover Letter
Statement of Qualifications
• Background
• Key Personnel
• Experience
• Project Understanding and Approach
Scope of Work
Project Schedule
Cost Proposal
• Project Cost Proposal 10
• Copy of April 16, 2025 NAI Rates
NAI
Consulting
PROPOSAL: PROFESSIONAL ENGINEERING DESIGN SERVICES FOR THE LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION PROJECT (C02607)
Cathedral City
Il. STATEMENT OF QUALIFICATIONS
NAI's Unique Quality
Our unique strength lies in our ability to deliver constructible and reliable civil engineering designs tailored to the Coachella Valley's specific conditions. Unlike larger firms, we maintain a flexible, hands-on approach that allows us to integrate seamlessly with City staff while maintaining full responsibility for technical design deliverables.
For this project, our value is in our ability to:
• Coordinate effectively with utilities to ensure smooth design review and approval. • Develop clear construction documents that minimize contractor ambiguity and reduce the potential for change orders.
Experience
Project Management Administration and Engineering Support Experience NAI has delivered a wide range of public works design projects, including:
• Pavement rehabilitation and reconstruction projects with complete roadway plans, demolition sheets, construction details, and utility coordination.
• ADA accessibility improvements, including driveway apron reconstruction, curb ramps, and sidewalk modifications.
• Drainage improvements, such as ribbon gutter design and grading to promote positive drainage. • Traffic signing and striping plans integrated with roadway improvements.
Our team has successfully managed projects from initial survey and utility research through PS&E delivery and construction-phase support. For the Landau Boulevard Public Alley Reconstruction Project, this experience translates directly into preparing:
• Surveying-based road maps.
• Geometric approval drawings and roadway profiles.
• Utility conflict maps and coordination with franchise utilities. • Final design drawings, specifications, and engineer's estimates. • Bid and construction-phase support, including RFI responses and record drawing preparation.
Project Staffing
Lorissa Gruehl, P.E., is a registered Civil Engineer in the State of California and will serve as the Project/Design Engineer for this project. She brings over 20 years of experience in roadway improvement projects, including sidewalk gap closures, and will be responsible for overall design oversight and technical direction.
She will be supported by Jose Cortez, who will serve as an Associate Engineer. Jose has been with NAI for more than five years and has contributed to numerous design projects during his tenure. He will assist with the preparation of design documents and coordination to ensure project obiectives are met.
PROJECT UNDERSTANDING AND APPROACH
Introduction
infrastructure by reconstructing the asphalt and concrete pavement section, correcting existing drainage deficiencies, a comprehensive PS&E package. Our methodology emphasizes durability, safety, and compliance while aligning with City workflows and community expectations, ensuring a reliable and cost-effective solution from concept through construction support.
Project Challenges
The Alley does not currently have a consistent cross-section including: driveway locations, pavement width, grade, existing right-of way. The existing right-of-way may pose the largest potential challenge when it comes to utility conflict.
There appears to be properties that have the original property lines that did not include a road easement for the alley.
Instead, they have a 5' public utility easement.
STATEMENT OF QAULIFICATIONS - 2- NAI Consulting
PROPOSAL: PROFESSIONAL ENGINEERING DESIGN SERVICES FOR THE LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION PROJECT (C02607)
Cathedral City
The grade of the road is also inconsistent, though generally grades toward the main streets. There appears to be at least one location where there may be a low spot.
Approach
Our goal will be to make the alley as consistent as possible with the road-way cross-section. In areas that allow it, we will modify the existing residential driveways to bring them into compliance with the new section. We will also attempt to avoid above ground utilities where possible. If there are situations where this is not feasible, we will work with the City to determine the best solution, which may include changing the section or working with the affected utility company. Prior rights will be reviewed during that process to help guide the decision.
Our initial approach will be to surface flow all drainage water through the center ribbon gutter toward the main roads.
In areas where there are low spots that cannot be graded we will work with the City to place a drywell or combination drywell with drainage pipe that outlets through the curb at the main entrance.
To help determine all the constraints we are subcontracting with NV5 to conduct field survey. They will perform cross- sections every 50 feet, take spot elevations at driveways, grade breaks, and utilities.
1. Project Initiation & Alignment
NAI begins each project with a collaborative initiation phase to establish clarity and alignment. For this project, we will meet with City staff to confirm objectives, gather available reference documents, and establish data exchange and submittal procedures. A detailed schedule, decision log, and communication protocol will be developed to maintain accountability. This disciplined framework ensures that priorities are clearly defined and that design milestones are achieved on time and within budget.
2. Stakeholder & Agency Coordination
Successful delivery depends on early and sustained coordination with stakeholders and utility providers. NAI will consult with affected utility agencies to identify potential conflicts, confirm relocation responsibilities, and incorporate adjustments into the design. By maintaining open communication with both the City and the community, we help minimize disruptions during construction and support timely approvals.
3. Technical Design Tasks
Our design process is built around structured milestones that provide transparency and allow for progressive refinement of the PS&E package. Key tasks include:
• Survey & Base Mapping - NV5 will conduct topographic surveys to capture existing conditions and utility locations, forming the foundation of the design.
• Geometric Design - Development of base maps, roadway profiles, and typical sections to guide alignment and grading
• Drainage & ADA Improvements - Refinement of the centerline profile to establish positive drainage and redesign of non-compliant driveway aprons to meet ADA requirements. • Roadway Plans - Preparation of demolition plans, roadway layouts, construction details, and signing/striping plans to define all improvements.
• Specification and Estimates - Preparation of technical specifications, special provisions, and detailed construction cost estimates that provide the City with a reliable bidding package.
4. Quality Assurance / Quality Control (QA/QC)
A rigorous QA/QC process is integrated at each design milestone. All plans, specifications, and estimates will be independently reviewed by a senior engineer not involved in day-to-day production. This review process ensures compliance with City, Caltrans, and ADA standards, verifies constructability, and safeguards accuracy in quantities and costs. By embedding QA/QC throughout the project, NAI reduces risk during bidding and construction.
5. Construction-Phase Support
Our responsibility extends beyond design completion. During bidding and construction, NAI will provide timely responses to Requests for Information (RFls), review shop drawings and submittals, attend site visits and construction meetings, and assist with change order evaluations. Upon completion, we will prepare record drawings incorporating contractor redlines to provide the City with accurate documentation of the final built condition.
STATEMENT OF QAULIFICATIONS - 3-
NAI Consulting
PROPOSAL: PROFESSIONAL ENGINEERING DESIGN SERVICES FOR THE LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION PROJECT (C02607)
Cathedral City
III. SCOPE OF WORK - DESIGN ENGINEERING SERVICES
The following tasks detail our understanding and approach for the Landau Boulevard Public Alley Reconstruction Project.
Our comprehensive scope of work includes the preparation of final design plans, specifications, and construction cost estimates to reconstruct the asphalt concrete pavement to provide a consistent invert cross-section with a ribbon gutter along the centerline, avoid and incorporate above-ground utilities, where it is not feasible we will discuss with the City on relocating them, and confirm prior rights. Grade the ribbon gutter to drain without the use of an under-ground system to the furthest extent feasible. Bring non-ADA-compliant driveway aprons into ADA compliance on residential streets adjacent to Landau Boulevard Alley. As part of the pavement rehabilitation and re-grading of the alley, we will review existing utilities and provide recommendations for utility potholing.
The following tasks are ones that NAI can fulfill as the lead designer and/or as a project manager:
1. Project Coordination
To facilitate the review and approval process, we will collaborate closely with the key individuals at the City who are responsible for the review of specific elements of the project and will submit draft copies of significant work items before the milestone submittal date. This gives us a clear understanding of what the reviewers expect, and they have a preview of what will be submitted before the actual submittal is made. Our experience working on projects with City oversight has taught us the importance of maintaining accurate and detailed meeting minutes, decision logs, and action item lists during the project development process. Utilizing this technique documents decisions, ensures consistency in decisions, and provides a concise list of tasks to be accomplished by each participant and a specific schedule to complete the task.
The project will be initiated with a Project Development Team (PDT) Kick-Off Meeting with the City before beginning Request and discuss available reference documents (as-builts, etc.) • Establish data exchange and submittal procedures
Discuss preferred invoicing formats, etc.
• Establish and confirm the approach the City would like to take with regards to the existing private improvements/obstructions, including driveways, landscaping, etc.
Project Milestone Meeting will be held at monthly intervals to meet with the City, these meeting can be in person or over the phone as requested by the City. The purpose of these meetings will be to review project status to ensure that the contract objectives and milestones are being achieved.
To supplement these meetings, we will maintain on-going communications with the City and affected utility agencies.
A detailed schedule, action item list and decision log will be developed, maintained, and updated for control of the project. Design review meetings will be held at the Geometric Approval Drawing (GAD) stage, and 90% project completion stage. At the GAD completion meeting, we will request a field inspection with preliminary plans in hand.
During this meeting any special construction details or conflicts will be discussed.
We anticipate a total of three (3) project milestone/monthly meetings. These meetings can be in person or virtual at the request of the City.
2. Review Existing Information
Once we have prepared the final scope documents and are issued a Notice to Proceed, we will begin the design phase of the project. This will consist of research and data collection, reviewing the documents provided by the City, coordination and investigation, field surveying, utility identification, and pavement evaluation.
We will prepare our preliminary plans based on information from our research, data collection, survey, and pavement testing. After 60% review and approval by the City, we will incorporate comments and begin work on the final PS&E.
3. Field Survey
NV5 Global, Inc. will perform the surveying services for the project. The survey scope of work includes topographic field survey of the project area. NV5 will Conduct survey cross sections of at 50' intervals along the existing public alley east of Landau Boulevard from 30th Avenue to Vista Chino locating existing improvements including all apparent grade breaks, center of alley elevations, visible utilities, and existing driveways.
4. Environmental
NAI will perform the Notice of Exemption Form and submit to the City to file with the County. NAI assumes that this project will qualify for categorical exemption through the combination of Title 14, California Code of Regulations, Section 15301, 15303, 15304, and 15332. It is assumed that the city will pay the filing fee.
SCOPE OF WORK - 4-
NAI Consulting
PROPOSAL: PROFESSIONAL ENGINEERING DESIGN SERVICES FOR THE LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION PROJECT (C02607)
Cathedral City
5. Utility Conflict Map/Utility Coordination
NAI will consult, coordinate, and perform related follow-ups with the affected utility agencies regarding the specific project-imposed impact locations to identify design controls and considerations necessary for plan preparation and approvals. Requests for information will include requests for future utility projects that may be affected by the proposed improvements. We will keep the City informed of the contact with the utility companies. Plan submittals will be forwarded to the utility companies for verification of their facilities known by them. The existing franchise agreements with each affected utility will determine whether the plans indicate the necessary modifications/relocations to be performed as a part of the project or whether the utility company must perform and pay for its own work. This will be determined for each utility company and facility.
NAI understands comprehensive utility studies will be required to identify and mitigate any utility-impacts during the reconstruction and regarding of the roadway.
6. Right of Way and Permitting
If the project requires right of way, rights of entry, or encroachment permits, NAI will coordinate with the City to prepare Request to Enter Letters to the affected Property Owners so that NV5 or the contractor can complete their work. ROW tasks are not currently included in the scope of work, but NAI does recognize that the existing ROW is not consistent and includes original public utility easements along some of the properties.
7. Geometric Base Maps
This task will include developing plans showing proposed geometry and other pertinent alignment data of the proposed engineering, including typical sections, profiles, superelevations, existing right-of-way limits based on available record drawings, approximate wall locations, and additional clarifying information, as necessary. They will be generated using the project report geometric plans. The geometric base maps (GBM) will be submitted to the City for approval before proceeding with the final design. The GBM will form the basis for the final design's skeleton sheets.
After the base sheets are developed, we will perform a field review to document existing field conditions and determine where additional information or field data may be required to provide adequate information to complete the conceptual widening alternatives and confirm the location and type of utilities and other improvements.
8. Roadway Plans
NAI will prepare roadway design plans to satisfy the project requirements as follows:
Title Sheet/Typical Sections - NAI will prepare a title sheet to include index map, vicinity map, index of drawings, notes to contractor, general notes, and construction notes. Typical Section sheets will also be prepared. We anticipate a total of one (1) Title Sheet and a total of one (1) Typical Section Sheet.
Demolition and Roadway Plan Sheets - NAI will prepare Demolition Plan Sheets to include roadway removals, landscaping removals, and misc hardscape removals. Roadway Plan Sheets to include plan and profile, utilities, and other related improvements required for the project. The profile may be omitted depending on if the profile will be adjusted. The drawings will be prepared on standard base sheets at 1"=20' scale and utilize all base sheet information developed in survey and mapping of the project alignment. We anticipate a total of four (4) Demolition/Roadway Plan Sheets.
• Construction Details - NAl will prepare a construction detail plan for any improvements that require additional detail not shown on the roadway plans. We anticipate that this will include a detail for intersection tie-in, driveway modification, and a detail for a concrete ribbon gutter. We anticipate a total of one (1) Construction Detail Sheet. • Drainage Plans - NAI anticipate that all drainage improvements will be limited to a ribbon gutter. These improvements will be shown on the Roadway Plan Sheets with additional details shown in the Construction Details. There appears to be a potential low spot. We will review the survey and attempt to address it through grading. If grading is not feasible, we will coordinate with the City to evaluate use of drywells. • Utility Plans - NAI will prepare separate 1"=20' scale utility plans using base layout sheets, showing the location of existing utilities, delineating those that will require relocation/adjustment, and designate who will be responsible for any required adjustment/relocation. Plans will be sent to utility companies for confirmation that all facilities and relocation limits are clearly shown. We anticipate a total of three (3) Utility Plan Sheets.
9. Contract Specifications/Bid Documents
Project Specifications will conform to the requirements of the Standard Specifications for Public Works Construction, City, and Caltrans Standard Specifications as applicable.
NAI will use the City's boilerplate front-end documents and prepare final special provisions for items, details, materials, procedures, and other conditions not adequately covered by the City, Caltrans, or Public Works Standard Specifications.
A listing and copy of all standard plans required for the project will be provided in the appendix, and copies of any plans used that are not standard will also be included. After incorporating the first plan check comments, we will prepare final technical specifications and/or special provisions for the proposed construction work.
SCOPE OF WORK - 5-
'NAI Consulting
PROPOSAL: PROFESSIONAL ENGINEERING DESIGN SERVICES FOR THE LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION PROJECT (C02607)
Cathedral City
10. Construction Cost Estimates
NAI will prepare a preliminary estimate of probable construction costs for the project, including a proposed bid item list, estimated quantity, line-item cost estimates, and an estimate of construction working days for the improvements per City format. At the first plan check, NAI will develop a preliminary estimate of probable construction costs for comparison with previous project budget estimates.
After incorporating the first plan check comments, NAI will prepare the final estimate of probable construction costs for the project, including a proposed estimate of construction working days for the improvements per City format. NAI will refine the preliminary estimate and provide quantity take-offs with appropriate unit prices and extensions.
11. Quality Assurance/Quality Control
Quality Assurance / Quality Control is crucial to NAI's overall approach to managing and controlling the work. This helps ensure the City receives a successful project on time and within budget.
As part of the program, a competent designer will review the work provided by the project engineer. During this review, the checker will mark up the plans and discuss any proposed changes with the project engineer. Changes to the plans, specifications, and calculations are only made after the differences are reconciled
12. Final PS&E Package
After incorporating review comments for the plans, specifications, and cost estimate, NAI will submit an electronic copy of all documents prepared for the project. At the request of the City, NAI will also submit bond hard copies of the final package.
13. Bid Support/Construction Support
NAI team will perform support services to the City during the advertising, bidding, and construction of the project as requested. These services will include written interpretation and clarification regarding the intent of the plans, specifications, and special provisions. NAI will also provide a professional review of shop drawings and contractor submittals for conformance to the bid documents as well as provide recommendations on progress pay estimates and change requests. Upon completion of construction, NAI will perform a field review and include the contractor's as-built
14. Geotechnical Information
If the project requires a geotechnical recommendation or pavement cores, NAI can obtain a Geotech as needed. Typical information and procedures may include recommendations for the location of borings, review of draft recommendations, and coordination.
15. Hydrology and/or Hydraulics
If the project requires a hydrology study and/or hydraulic calculations, NAI can obtain a firm to conduct the necessary information. Typical information and procedures may include recommendations for the area of impact, proposed and existing roadway profile, recommendations for the size of storm to calculate, and coordination.
SCOPE OF WORK - 6-
° NAI Consulting
City of Cathedral City
Landau Boulevard Public Alley Reconstruction Project
Schedule as of 09/19/2025
November 2025
Task Name Duration Start Date SA SU M T W TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W TH F SA SU Finish Date - 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 a 10 ii ia a ia o o Project Administration 87 days 11/3/2025 1/30/2025
Kick-Off Meeting x x x x x X X X x x x x x x x x x x x x x x x x x x x x 11/3/2025 11/3/2025
1.2 Project Development Team Metings - Monthy 11/3/2025 1/30/2025
1.3 Field Review 11/10/2025 11/11/2025
1.4 Project Management and Coordination 11/3/2025 1/30/2025 x X x x x x Survey & Mapping x x x x x x X X X X X X X x X x x x
10 days 11/10/2025 11/19/2025 *x× x x X
2.1 Field Survey X
11/10/2025 11/14/2025
2.2 Mapping 11/15/2025 11/19/2025
En vironmental Documentation x x x x x x x
1 day 12/8/2025 12/8/2025
3.1 CEQA MPD or NOE - 12/8/2025 12/8/2025
Utility Coordination 1 day 12/9/2025 12/9/2025
4.1 Utiity Notice - Requesting As-Builts - 12/9/2025 12/9/2025 Plans, Specifications, and Estimates 70 days 11/20/2025 1/28/2026
5.1 60% Plan Submittal 11/20/2025 12/9/2025 X X X X X X x x x x x
5.1.1 60% Agency Review 12/10/2025 12/16/2025 x x x X X X X X X X X
5.2 90% PS&E Submittal 12/17/2025 12/31/2025
5.2.1 90% Agency Review 1/2/2026 1/8/2026
5.3 100% PS&E Submittal 1/9/2026 1/15/2026
5.3.1 100% Agency Review 1/16/2026 1/23/2026
5.4 Final PS&E Submittal 1/26/2026 1/28/2026
PROJECT SCHEDULE P NAT Consulting
- 7 -
City of Cathedral City
Landau Boulevard Public Alley Reconstruction Project
Schedule as of 09/19/2025
December 2025
Task Name TH F SA SU W TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W Duration Start Date Finish Date
Project Administration 87 days 1/30/2025 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 11/3/2025 x x x x x x x X x x x x x x x x x x x x x x x x x x x x x x
1.1 Kick-Off Meeting 11/3/2025 11/3/2025
1.2 Project Development Team Meetings - Monthly
11/3/2025 1/30/2025
1.3 Field Review
11/10/2025 11/11/2025
1.4 Project Management and Cordination 11/3/2025 1/30/2025 x x x _X X X X X X X X x x X X x x x x X X x x X X x x x x x x Survey & Mapping 10 days 11/10/2025 11/19/2025
2.1 Field Survey 11/14/2025
11/10/2025
2.2 Mapping
11/15/2025 11/19/2025
Environmental Documentation 1 day 12/8/2025 12/8/2025
3.1 CEQA MPD or NOE
- 12/8/2025 12/8/2025
Utility Cordination 1 day 12/9/2025 12/9/2025
4.1 Utilty Notice - Requesting As-Builts x
12/9/2025 12/9/2025 x
Plans, Specifications, and Estimates 70 days 11/20/2025 1/28/2026
5.1 60% Plan Submittal X X X X X X X X X X X X X X X X x X X X X x X X X X X x x x x 20 11/20/2025 12/9/2025 x x x X X X x x x
5.1.1 60% Agency Review 12/10/2025 12/16/2025
5.2 90% PS&E Submittal 15 × X x x x x x
12/17/2025 12/31/2025
5.2.1 90% Agency Review 1/2/2026 1/8/2026 x X X X x x x x x x x x x x x
5.3 100% PS&E Submittal 1/9/2026 1/15/2026
5.3.1 100% Agency Review 1/23/2026
1/16/2026
5.4 Final PS&E Submittal 1/26/2026 1/28/2026
PROJECT SCHEDULE - 8- NAT Consulting
City of Cathedral City
Landau Boulevard Public Alley Reconstruction Project
Schedule as of 09/19/2025
January 2026
Task Name TH F sU M
Duration Start Date Finish Date TH F SA SU M T W TH F SA SU M T W TH F SA SU M T W TH F SA - 3 4 5
Project Administration 87 days 11/3/2025 1/30/2025 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1.1 Kick-Off Meeting x x x X x x x X X x x x x x x x x x x x x x x x x x x x
1.2 11/3/2025 11/3/2025
Project Development Team Meetings - Monthly 11/3/2025 1/30/2025
1.3 Field Review 11/10/2025 11/11/2025
1.4 Project Management and Cordination 11/3/2025 1/30/2025 Survey & Mapping X x X x x X X X X X X X x x x x X X x X x x x x x x x x 10 days 11/10/2025 11/19/2025
2.1 Field Survey 11/10/2025
2.2 11/14/2025
Mapping 11/15/2025 11/19/2025
Environmental Documentation 1 day 12/8/2025 12/8/2025
3.1 CEQA MPD or NOE
- 12/8/2025 12/8/2025
- Utility Coordination 1 day 12/9/2025 12/9/2025
4.1 Utlity Notice - Requesting As-Builts 12/9/2025 12/9/2025 Plans, Specifications, and Estimates 70 days 11/20/2025 1/28/2026 x x x
5.1 60% Plan Submittal X X X XX XX XXXXxXXxxxx
11/20/2025 12/9/2025
5.1.1 |60% Agency Review 12/10/2025 12/16/2025
5.2 90% PS&E Submittal 15 12/17/2025 12/31/2025
5.2.1 90% Agency Review 1/2/2026 1/8/2026
5.3 x x x x X
100% PS&E Submittal 1/9/2026 1/15/2026
5.3.1 100% Agency Review x x X x x x x
1/16/2026 1/23/2026 × x x x X X x X XX
5.4 Final PS&E Submittal 1/26/2026 1/28/2026
x x X
PROJECT SCHEDULE - 9- NAT Consulting
Cost Proposal - 09/19/2025 Price Summary/Totals
Project Total Cost: 76,708
CO2607: LANDAU BOULEVARD PUBLIC ALLEY RECONSTRUCTION
To reconstruct approximately 5,100 linear feet of residential road pavement along Landau Boulevard Alley Bill Rate > 222.00 98.00 between Vista Chino and 30th Avenue. The improvements will include full width street section of 20: 70.00 Submitted to: City of Cathedral City
Contract Type: Fixed Fee
Sub-Total NAI Consulting = $55,768.00 Fee
Sub-Total NV5 = $20,940.00 Principal Associate Engineer Administrative Support Total
Labor Hrs Prime Survey Sub Task Pricing Totals
401 146 215 55,668 20,940 76,608
Project Phases / Tasks
Engineering Design - Plans, Specifications and Estimate 401 146 215 40 Task 1: Project Administration 55,668 20,940 76.608
104 40 40 14,480 14,480
Task 1.1: Kick-off Meeting
Task 1.2: Project Development Team Meetings - Monthly 640 Task 1.3: Field Review 1,920
Task 1.4: Project Management and Coordination 5,120
Task 2: Survey & Mapping 6,800
Task 2.1: Field Survey 20,940 23,396
Task 2.2: Mapping 16,080 17,308
Task 3: Environmental Documentation 4,860 6,088
*• ∞ 614
Task 3.1: CEQA NOD & NOE
Task 4: Utility Coordination 614 614
36 3,576 3,576
Task 4.1: Utility Notice - Request As-Builts
Task 5: Project Design and Plan Set Preparation 3,576 3,576 236 139 35,156 35,156
Task 5.1: 60% Plan Submittal 100
45 15,380
Task 5.2: 90% PS&E Submittal
Task 5.3: 100% PS&E Submittal 11,912
Task 5.4: Final PS&E Submittal 4,716 4,716
3.148 1148
Totais 146 215 55,668 20,940
76,608
Reimbursables:
COST PROPOSAL - 10- NAT Consulting
NAI Consulting, Inc.
Compensation for Services
Date: 4/15/2025
Contract No.: TBD Project No.: TBD
Particpation Amount: TBD
El Prime Consultant • Subconsultant • 2nd Tier Subconsultant Combined Rate Combined ICR
Fringe Benefit: 0% Administrative Costs 112.23%
1120%
Fee: 23%
BILLING INFORMATION CALCULATION INFORMATION
Job Title/ Name / Classification Hourly Billing Rates Effective Date of Hourly Rate Actual or Avg.
Straight OT (1.5x) % or $ Hourly Range - for
OT(2x) From To Hourly Rate Increase Classifications Only Principal Civil Engineer* 222.00 N/A N/A 1/1/2025 12/31/2025 85.00 Principal Project Manager* 222.00 N/A Not Applicable
N/A 1/1/2026 12/31/2026 0.0%
- Joshua Nickerson 222.00 N/A N/A 1/1/2027 12/31/2027
- Lorissa Gruehl 0.0%
222.00 N/A N/A 1/1/2028 12/31/2028 0.0%
222.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Project Manager VI* 196.00 N/A N/A 1/1/2025 12/31/2025 75.00 Senior Engineer VI* $70.00 - $80.00
196.00 N/A NIA 1/1/2026 12/31/2026 0.0%
196.00 N/A N/A 1/1/2027 12/31/2027 0.0%
196.00 N/A N/A 1/1/2028 12/31/2028 0.0%
196.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Project Manager V* 176.00 N/A N/A 1/1/2025 12/31/2025 67.50 $65.00 - $70.00 Senior Engineer V* 176.00 N/A N/A 1/1/2026 12/31/2026 0.0% 176.00 N/A N/A 1/1/2027 12/31/2027 0.0%
176.00 N/A N/A 1/1/2028 12/31/2028 0.0%
176.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Project Manager IV* 163.00 N/A N/A 1/1/2025 12/31/2025 62.50 $60.00 - $65.00 Senior Engineer IV* 163.00 N/A N/A 1/1/2026 12/31/2026 0.0% 163.00 N/A N/A 1/1/2027 12/31/2027 0.0%
163.00 N/A N/A 1/1/2028 12/31/2028 0.0%
163.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Project Manager Ill* 150.00 N/A N/A 1/1/2025 12/31/2025 57.50 Senior Engineer III* 150.00 $55.00 - $60.00
N/A N/A 1/1/2026 12/31/2026 0.0%
150.00 N/A N/A 1/1/2027 12/31/2027 0.0%
150.00 N/A N/A 1/1/2028 12/31/2028 0.0%
150.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Cost Proposal
NAI Consulting, Inc.
Compensation for Services
Project Manager I* 137.00 N/A N/A 1/1/2025 12/31/2025
Senior Engineer II* 52.50 $50.00 - $55.00
137.00 N/A N/A 1/1/2026 12/31/2026 0.0%
137.00 N/A N/A 1/1/2027 12/31/2027 0.0%
137.00 N/A N/A 1/1/2028 12/31/2028 0.0%
137.00 N/A N/A 1/1/2029 12/31/2030 0.0%
Project Manager I* 132.00 N/A N/A 1/1/2025 12/31/2025 50.48 Senior Engineer I* $45.00 - $50.00
139.00 N/A NA 1/1/2026 12/31/2026 5.0%
146.00 N/A N/A 1/1/2027 12/31/2027 5.0%
153.00 N/A N/A 1/1/2028 12/31/2028 5.0%
161.00 N/A N/A 1/1/2029 12/31/2030 5.0%
Associate Project Manager I* 111.00 N/A N/A 1/1/2025 12/31/2025 Associate Engineer II* 42.50 $40.00 - $45.00
117.00 N/A N/A 1/1/2026 12/31/2026 5.0%
123.00 N/A N/A 1/1/2027 12/31/2027 5.0%
129.00 N/A N/A 1/1/2028 12/31/2028 5.0%
135.00 N/A N/A 1/1/2029 12/31/2030 5.0%
Associate Engineer I* 98.00 N/A N/A 1/1/2025 12/31/2025 37.50 $35.00 - $40.00 Associate Project Manager I* 103.00 N/A N/A 1/1/2026 12/31/2026 5.0% 108.00 N/A N/A 1/1/2027 12/31/2027 5.0%
113.00 N/A N/A 1/1/2028 12/31/2028 5.0%
119.00 N/A N/A 1/1/2029 12/31/2030 5.0%
Assistant Project Manager* 85.00 127.50 170.00 1/1/2025 12/31/2025 32.50 Assistant Engineer $30.00 - $35.00
89.00 133.50 60 178.00 1/1/2026 12/31/2026 5.0%
Office Manager 93.00 139.50 186.00 1/1/2027 12/31/2027
5.0%
98.00 147.00 196.00 1/1/2028 12/31/2028
103.00 5.0%
154.50 206.00 1/1/2029 12/31/2030 5.0%
Administrative Support 70.00 105.00 140.00 1/1/2025 12/31/2025 27.00 $25.00 - $30.00
74.00 111.00 148.00 1/1/2026 12/31/2026 5.0%
78.00 117.00 156.00 1/1/2027 12/31/2027 5.0%
82.00 123.00 GA 164.00 1/1/2028 12/31/2028 5.0%
86.00 129.00 172.00 1/1/2029 12/31/2030 5.0%
Administrative Assistant 59.00 88.50 118.00 1/1/2025 12/31/2025
22.50 $20.00 - $25.00
62.00 93.00 124.00 1/1/2026 12/31/2026 5.0%
65.00 97.50 $ 130.00 1/1/2027 12/31/2027 5.0%
68.00 102.00 $ 136.00 1/1/2028 12/31/2028 5.0%
71.00 106.50 $ 142.00 1/1/2029 12/31/2030 5.0%
• Positions are exempt from Overtime Compensation
NOTES:
mos propod must be make win 4) and employe hat ar subject to railing wage roguirements must be mail with to 9) Al cos mut comply with the Podeni cos principles subcontine will rovide their
2. The cost proposal format shall not be amended.
4. For named employees and key personnel enter the actual hourly rate. For classification only, enter the Average Hourly Rate for that classification.
Cost Proposal
-
NAI Consulting, Inc.
Compensation for Services
Date: 4/15/2025
Contract No.: TBD Project No.: TBD
Prime Consultant Subconsultant 2nd Tier Subconsultant
SCHEDULE OF OTHER DIRECT COST ITEMS
Description of Item Quantity Unit Unit Cost
Total
Postage* At Actual
Reprographics* At Actual
Travel > 50 Miles** At Actual
Permits / Fees* At Actual
Additional Insurance* At Actual
Subconsultant 1:
Subconsultant 2:
Subconsultant 3:
Subconsultant 4:
Subconsultant 5:
* Billed at Direct Cost
** - Travel Less than 50 miles will not be billed. Travel over 50 miles will be billed at the federal standard milage rate.
List services the consultant is providing unter the proposed contract:
Project Management
Grant Administration
Professional Design Services
Cost Proposal