CITY OF CATHEDRAL CITY
HSIP CYCLE 11D
Bid Tabulation/ Analysis
CITY PROJECT No.: 8757

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL UNIT COST TOTAL UNIT COST TOTAL 1 MOBILIZATION 1 LS 11,000.00$ 11,000.00$ 10,000.00$ 10,000.00$ 42,150.00$ 42,150.00$ 2 TRAFFIC CONTROL 1 LS 28,888.00$ 28,888.00$ 44,000.00$ 44,000.00$ 44,500.00$ 44,500.00$ 3 CONSTRUCTION SURVEY AND
MONUMENT PERPETUATION 1 LS 11,000.00$ 11,000.00$ 9,000.00$ 9,000.00$ 18,350.00$ 18,350.00$ 4 WATER POLLUTION CONTROL 1 LS 2,222.00$ 2,222.00$ 8,500.00$ 8,500.00$ 7,650.00$ 7,650.00$ 5 CLEARING AND GRUBBING 1 LS 27,580.00$ 27,580.00$ 49,315.00$ 49,315.00$ 34,200.00$ 34,200.00$ 6 TYPE A-6 CURB & GUTTER PER

COUNTY OF RIVERSIDE STANDARD
PLAN NO. 200 150 LF 82.00$ 12,300.00$ 85.00$ 12,750.00$ 81.00$ 12,150.00$ 7 ASPHALT CONCRETE PAVEMENT (4"
MIN) 14 TON 444.00$ 6,216.00$ 600.00$ 8,400.00$ 450.00$ 6,300.00$ 8 AGGREGATE BASE (6" MIN) 59 CY 282.00$ 16,638.00$ 180.00$ 10,620.00$ 220.00$ 12,980.00$ 9 PCC CROSS GUTTER PER COUNTY OF
RIVERSIDE STANDARD PLAN NO. 209625 SF 28.00$ 17,500.00$ 28.00$ 17,500.00$ 23.50$ 14,687.50$ 10 CASE A CURB RAMP WITH YELLOW

TRUNCATED DOMES PER CALTRANS
STANDARD PLAN A88A 4 EA 6,369.00$ 25,476.00$ 2,500.00$ 10,000.00$ 5,950.00$ 23,800.00$ 11 4" PCC SIDEWALK PER COUNTY OF
RIVERSIDE STANDARD PLAN NO. 400
AND NO. 401 1975 SF 13.00$ 25,675.00$ 13.00$ 25,675.00$ 12.00$ 23,700.00$ 12 CONSTRUCT TRENCH DRAIN 72 LF 444.00$ 31,968.00$ 220.00$ 15,840.00$ 242.00$ 17,424.00$ 13 COLD MILL 2" AC PAVEMENT,
DISPOSE, AND OVERLAY 5,175 SF 4.44 $ 22,977.00$ 8.00 $ 41,400.00$ 9.00 $ 46,575.00$ 14 SOLAR STREET LIGHT WITH
FOUNDATION COMPLETE 1 EA 24,338.00$ 24,338.00$ 25,000.00$ 25,000.00$ 29,750.00$ 29,750.00$ 15 SIGNING AND STRIPING
IMPROVEMENTS 1 LS 42,222.00$ 42,222.00$ 48,000.00$ 48,000.00$ 18,500.00$ 18,500.00$ 306,000.00$ 336,000.00 $ 352,716.50 $ 306,000.00$ 336,000.00 $ 352,716.50 $ BID SCHEDULE NO. 1: HSIP 11D
SUB-TOTAL BID SCHEDULE NO.1

TOTAL ALL BID ITEMS

ONYX PAVING COMPANY LC PAVING AND SEALINGGRANITE CONSTRUCTION