CITY OF CATHEDRAL CITY
HSIP CYCLE 11C
Bid Tabulation/ Analysis
CITY PROJECT No.: 8756
1 MOBILIZATION 1 LS 15,777.00 $ 15,777.00 $ 34,040.00 $ 34,040.00 $ 44,000.00 $ 44,000.00 $ 12,000.00 $ 12,000.00 $ 70,000.00 $ 70,000.00 $ 2 TRAFFIC CONTROL 1 LS 14,000.00 $ 14,000.00 $ 32,760.00 $ 32,760.00 $ 9,000.00 $ 9,000.00 $ 14,500.00 $ 14,500.00 $ 25,000.00 $ 25,000.00 $ 3 CONSTRUCTION SURVEY

AND MONUMENT

PERPETUATION
1 LS 8,000.00 $ 8,000.00 $ 20,000.00 $ 20,000.00 $ 6,500.00 $ 6,500.00 $ 6,500.00 $ 6,500.00 $ 26,000.00 $ 26,000.00 $ 4 WATER POLLUTION
CONTROL 1 LS 1,138.00 $ 1,138.00 $ 2,500.00 $ 2,500.00 $ 2,500.00 $ 2,500.00 $ 1,500.00 $ 1,500.00 $ 15,000.00 $ 15,000.00 $ 5 CLEARING AND GRUBBING 1 LS 13,115.00 $ 13,115.00 $ 14,000.00 $ 14,000.00 $ 17,000.00 $ 17,000.00 $ 10,000.00 $ 10,000.00 $ 80,000.00 $ 80,000.00 $ 6 TYPE A-6 CURB & GUTTER

PER COUNTY OF RIVERSIDE
STANDARD PLAN NO. 200
130 LF 80.00 $ 10,400.00$ 81.00 $ 10,530.00$ 70.00 $ 9,100.00$ 80.00 $ 10,400.00$ 125.00 $ 16,250.00$ 7 ASPHALT CONCRETE
PAVEMENT (4" MIN) 30 TON 370.00 $ 11,100.00$ 377.00 $ 11,310.00$ 500.00 $ 15,000.00$ 350.00 $ 10,500.00$ 400.00 $ 12,000.00$ 8 AGGREGATE BASE (6" MIN) 58 CY 109.00 $ 6,322.00 $ 110.00 $ 6,380.00 $ 90.00 $ 5,220.00$ 110.00 $ 6,380.00 $ 150.00 $ 8,700.00 $ 9 PCC CROSS GUTTER PER

COUNTY OF RIVERSIDE
STANDARD PLAN NO. 209
450 SF 29.00 $ 13,050.00$ 29.00 $ 13,050.00$ 23.00 $ 10,350.00$ 27.00 $ 12,150.00$ 60.00 $ 27,000.00$ 10 CASE A CURB RAMP WITH

YELLOW TRUNCATED

DOMES PER CALTRANS
STANDARD PLAN A88
A 3 EA 10,811.00 $ 32,433.00 $ 11,020.00 $ 33,060.00 $ 7,000.00 $ 21,000.00 $ 12,500.00 $ 37,500.00 $ 16,500.00 $ 49,500.00 $ 11 4" PCC SIDEWALK PER

COUNTY OF RIVERSIDE
STANDARD PLAN NO. 400
AND NO. 401
1470 SF 8.00 $ 11,760.00$ 8.12 $ 11,936.40$ 14.00 $ 20,580.00$ 8.50 $ 12,495.00$ 22.00 $ 32,340.00$ 12 CONSTRUCT TRENCH DRAIN 85 LF 643.00 $ 54,655.00$ 655.00 $ 55,675.00$ 230.00 $ 19,550.00$ 360.00 $ 30,600.00$ 160.00 $ 13,600.00$ 13 COLD MILL 2" AC PAVEMENT,
DISPOSE, AND OVERLAY 9,900 SF 5.15 $ 50,985.00$ 5.22 $ 51,678.00$ 7.50 $ 74,250.00$ 6.20 $ 61,380.00$ 10.50 $ 103,950.00$ 14 TRAFFIC SIGNAL

IMPROVEMENTS
(CATHEDRAL CANYON &
ORTEGA
) 1 LS 245,000.00$ 245,000.00 $ 278,472.00 $ 278,472.00 $ 327,000.00 $ 327,000.00 $ 276,299.00 $ 276,299.00 $ 265,000.00 $ 265,000.00 $ 15 TRAFFIC SIGNAL
IMPROVEMENTS (30TH AVE
& AVENIDA LA PAZ
) 1 LS 242,000.00$ 242,000.00 $ 277,518.00 $ 277,518.00 $ 307,000.00 $ 307,000.00 $ 282,211.00 $ 282,211.00 $ 285,000.00 $ 285,000.00 $ 16 SIGNING AND STRIPING 1 LS 55,627.00 $ 55,627.00 $ 56,707.00 $ 56,707.00 $ 27,000.00 $ 27,000.00 $ 58,885.00 $ 58,885.00 $ 35,000.00 $ 35,000.00 $ 785,362.00$ 909,616.40 $ 915,050.00 $ 843,300.00 $ 1,064,340.00 $

MARJANI BUILDERS

UNIT COST TOTAL TOTAL
DBX

UNIT COST TOTAL DESCRIPTION TOTAL QTY

CALPROMAX ENGINEERING

UNIT COST TOTAL

CALIFORNIA PROFESSIONAL

ENGINEERING

UNIT COST
BID SCHEDULE NO. 1: HSIP 11B
SUB-TOTAL BID SCHEDULE NO.1

ELECNOR BELCO ELECTRIC

UNIT COSTUNITITEM