Proposal for Professional Construction Engineering Support Services for HSIP Cycle 11B: Signalized Pedestrian Crossing Cathedral City Upgrades State Project No. HSIPL-5430(010), CIP NO. C08755 Submitted by:
SEG
SPECS ENGINEERING GROUP
CC
Riallo CA 92376
United States
TABLE OF CONTENTS
1. Cover letter... 1
2. Statement of Qualifications.. .3
Resumes... 4
3. Scope of Work. .10
SEG
SPECS ENGINEERING GROUP
SEG I. Cover Letter
October 28, 2025
Attn: Mr. Andrew Lee
Engineering Department REFERENCE: Proposal for Professional Construction Engineering Support City of Cathedral City Services for HSIP Cycle 11B: Signalized Pedestrian Crossing Upgrades 68700 Avenida Lala Guerrero State Project No. HSIPL-5430(040), CIP No. 08755 Cathedral City, CA 92234
Dear Mr. Lee,
SPECS Engineering Group (SEG) proudly present our proposal to the city of Cathedral City for the above mentioned project.
SEG is a certified Disadvantaged Business Enterprise/Small Business Enterprise (DBE/SBE) specializing in construction management and inspection services for various types of public work/capital improvement projects.
SEG provides expert Construction Management, Project Management, Construction Inspection, and a full range of Engineering Consulting Services tailored to local agency projects. We are resourceful in managing large-scale projects as well as flexible in adapting to the needs of a smaller scale project. Our proven track record for Caltrans' districts 7,8, and 12 demonstrates our ability to deliver high-quality results efficiently, meet deadlines, and consistently exceed client expectations. We have also established professional working relationships with various other stakeholders and utilities including but not limited to Southern California Edison, SoCal Gas, MWD, Kinder Morgan, US Army Corps of Engineers, and more. We are a disadvantaged and small business enterprise (D/SBE) with an office in Ontario, CA, which positions us to be responsive to the project's needs. The proposed Project Manager/Construction Manager, Jose Burbano, has previously supported Caltrans District 8 on many projects including but not limited to: 60-90-215 Interchange and SR210 Alder Avenue Interchange Project. His roles have included assisting the client with successful federal/state administration and reimbursement, on various projects.
OUR TEAM
People, not companies, deliver projects, so we matched the needs of the projects with proposed personnel from SEG and our subconsultants. We started with familiarizing ourselves with the plans, specifications and other RFP documents, performed a thorough constructability review and developed our project approach. This enables us to propose the most qualified personnel for each task for an appropriate time in a key or supporting role. All our key personnel are 100% committed and available for the project. SPECS' team also includes the following local and highly respectable subconsultants: Ninyo and Moore
OUR APPROACH:
Our approach for the successful delivery of this project is that of collaboration - amongst the stakeholders, the City, and the contractor to seamlessly resolve issues/concerns. Our efforts will be focused on a variety of key project elements including but not limited to: Federal funding/LAPM, Traffic Signal Intersection, Concrete/ADA Compliance, Electrical/Lighting Improvements, Utility Coordination/Relocation Management, Complex Traffic Control Staging, and Environmental Compliance
SEG's CM team delivers complex, scheduled-driven projects safely, on budget, with minimal community impacts, backed by rigorous QA/QC and a strong claims-avoidance record. As Project/Construction Manager, I, Jose Burbano, will be your single point of contact. We are honored to partner with the City of Cathedral City and appreciate the opportunity to submit our qualifications. We pledge our full commitment. I am authorized to commit SPECS Engineering Group, Inc. (SEG), and confirm our proposal is valid for 120 days. Thank you for your consideration. Please contact me at 626.497.8124 or via email at [email protected] with any questions or to discuss next steps.
Sincerely,
Jose Burbano, PE
Principal/Project Manager
Office: 135 S. State College Blvd. Suite 200, Brea, CA 92821 Office: 4375 E. Lowell Street, Suites D&E, Ontario, CA 91761 JI. STATEMENT OF QUALIFICATIONS
FIRM INTRODUCTION
SEG COMPANY PROFILE
SPECS Engineering Group (SEG) is a certified
Disavantaged Business Enterprise (DBE No. 52799)
and Small Business Enterprise (SBE No. 2046643) firm.
• OFFICE TYPE OF ENTITY
We bring extensive expertise in construction management, 135 S. State College Blvd, S-Corporation
construction engineering, inspection services, and staging coordination for CIP projects across Southern California Suite 205 Brea, CA 92821 SEG is certified under NAICS Codes 541330 (Engineering CLIENTS Services) and 237310 (Highway, Street,and Bridge City of Rialto Public Works Construction), qualifying us to support federally funded • Rialto Fire Department projects in full compliance with Caltrans Local Assitance • San Bernardino County MA PROJECT PRINCIPAL Procedures Manual (LAPM). Our team brings directs Flocd Control Jose Burbano, PE experience managing complex capital improvement • San Gabriel Valley COG 4375 E. Lowell Street, Suite projects involving structures, utility coordination, aerial • Caltrans Distnet 8 oversight • City of Alhambra D and E. Ontario. CA 91761
deposit lead, roadway enbankments, on/off ramp C: 626.497.8124 improvements, federally funded contract O: 949.629.5831 administration. We have proven a record of delivering SERVICES Caltrans-compliant construction management • Construction Management • Construction Inspection inspection services under the Local Assistance Project Management Constructability Reviews Procedures Manual (LAPM) and Highway Bridge Resident Engineenng Public Relations & Outreach Program (HBP). Jose Burbano has successfully managed • Structural & Electrical • Office Engineering Document over 18 roadway, bridge structure, and widening Engineering Control/Labor Compliance improvements and assisted with reimbursement of state • Federal & State Funding • Claims Analysis, CPM Scheduling and federal funding.
SEG is highly experienced with documentation and compliance tasks required on federal-aid projects, including:
/ Resident Engineer field oversight and daily
reporting
• DBE, Buy America, and Certified Payroll
Verification
/ Certified Payroll and DIR
/ Change Order Review and Cost Negotiation
• As-Built Tracking and Final Project Closeout
Funding Deadline and Schedule Compliance
We are well versed in Caltrans Standards and Specifications, Local Assistance Procedures Manual, Army Core of Engineers, and Greenbook Standards, and we understand the adminsitrative requirements that can be rigorois for projects under state and federal funding.
LIST OF RELEVANT PROJECTS
SR210 Alder Avenue interchange Improvements, Caltrans & City of Rialto Interstate-5 Carmenita Road OC, Caltrans & City of Santa Fe Springs Interstate-5 Valley View Interchange, Caltrans & City of La Mirada Gene Autry Way Interchange Improvements Caltrans and City of Anaheim Stewart Street Underpass Grade Separation, City of Loma Linda SR-22 HOV Lane Expansion - Design, Build, Caltrans, OCTA Bradford Avenue over BNSF. City of Placentia
Terra Vista Safe Routes to School, City of Rialto
166'h Street Rehabilitation, City of Cerritos
Mountain View Avenue Widening over San Timoteo Creek, City of Loma Linda North Firestone Boulevard/Trojan Way Bridge, Caltrans and City of Santa Fe Springs Alondra Avenue OC over Coyote Creek Channel. Caltrans Federal/State Funds: C City of Cathedral City
SEG Professional Constriction Engineering Support Services for HSIP Cycle 1 Signalized Pedestrian Crossing Upgrades
State Project No: HSIPL 5430(040) CIP No. 09755
2 II. STATEMENT OF QUALIFICATIONS
SPECS Engineering Group will statf this assignment with a lean, cost-efficient team. Jose Burbano will serve as both Project Manager and Construction Manager, consolidating leadership to reduce overhead and maintain clear accountability. Our inspectors and technical staff bring deep experience in traffic signal upgrades, pedestrian safety enhancements, and ADA compliance across
Southern California. Just as important, our team is
known for strong communication and stakeholder
coordination-critical in today's public-sensitive
construction environment. Cathedral City
CONSTRUCTION/ PROJECT MANAGER
* Jose Burbano, PE (S)
MATERIAL TESTING
Our team is cross-trained across labor compliance,
outreach, office engineering, and admin support, CONSTRUCTION INSPECTOR Garreth Saiki, GE, PE (N) allowing us to reallocate instantly when workloads
spike or staff are unavailable. This delivers rapid Armando Contreras (S) backfill, fewer delays, and efficient use of
ADDITIONAL RESOURCE * Key Staff
resources, with one integrated team maintaining AS NEEDED (S) Specs Engineering Group
quality and momentum. Omar Lopez (S) (N) Ninyo and Moore Team Member / Role Educatio Licenses /
Certification Years of Experience Federally Funded Electrical Systems SWPPP/Environmental Compliance Traffic Control/ Complex Staging ADA Compliance Caltrans Standards/ LAPM / Greenbook Availability
Jose Burbano, PE, QSD/P (S) CA, Civil PE
BS, Civil Eng 27 100% X
Project/Construction Manager No. 91031
Armando Contreras (S) BS. PCI No. 17264
Construction Inspector Industrial ACI Concrete 15 100% X X X X X Engineering
Garreth Saike, GE, PE (N) MS, Geotech PE C49665,
26 100% X X
Materials Testing Engineering GE C2509
Omar Lopez (S) UAS Drone Safety
BS. Civil Eng 4 100% X
Labor Compliance/Administrative Support
PRINCIPAL STAFF MEMBERS QUALIFICATIONS AND EXPERIENCE
Jose Burbano, PE, QSD/P, Project/Construction Manager, brings over 27 years of experience of extensive Professional Engineering and project delivery experience in government infrastructure. Jose is responsible for ensuring SEG team administers the contract between the Contractor, the City of Cathedral City, and Caltrans, while also coordinating subconsultant services to meet the project's needs. As an ex Caltrans employee, Jose has a proven track record as a Construction Manager on federally funded projects.
Armando Contreras, Construction Inspector, has 15 years of experience in contract administration and construction inspection for CIP and Caltrans-funded initiatives. His scope of work includes street rehabilitation, intersection improvements, and effective coordination with local agencies and utlity companies. Armando is well- versed in LAPM procedures, Caltrans standard specifications, and Greebook standards, ensuring projects meet all technical and regulatory requirements.
SEG Profess Services for HSIP
a Upgrades
No. 08755
3 II. STATEMENT OF QUALIFICATIONS
JOSE BURBANO, PE, QSD/P
Project / Construction Manager
EDUCATION Mr. Burbano has 27 years of experience as a Senior Construction Manager, Resident BS. Civil Engineering. Engineer, Principal Assistant, Structure Rep, Utility Coordinator, and Designer, California State specializing in Caltrans and public works infrastructure projects. He has extensive Polytechnic University. expertise in administering federally funded projects in compliance with LAPM.
Pomona His project management responsibilities include quality assurance, contract management, CPM (P6) scheduling, cost estimating, partnering, DRB claims REGISTRATION resolution, regulatory compliance, materials testing coordination, traffic control plans, SWPPP, public outreach, and ensuring project safety. He has worked on a variety of CA, Professional Civil involving temporary and permanent easements, freeways, highways, Engineer, No. 91031 interchanges, traffic signal intersections, and various infrastructure improvements. He Qualified SWPPP has successfully delivered projects for federal, state, county, and municipal Developer demonstrating a deep understanding of multi-jurisdictional 30-Hour Cal/OSHA coordination and compliance with funding and regulatory requirements. Mr.
Burbano is experienced in utilizing Caltrans Standard Specifications, the Caltrans CTM Construction Manual, Bridge Construction Records and Procedures manual, CERTIFICATIONS Greenbook standard plans, Cal/OSHA Construction Safety Orders, encroachment 125, 533, 539, 540 permits, constructability reviews, ADA permanent and temporary pedestrian facilities, railroad coordination, and funding reimbursements. He has served clients in Caltrans AWARDS & HONORS Districts 7, 8 and 12 & various other municipalities, including Hesperia, Victorville, Anaheim, Placentia, La Mirada, Cerritos, Santa Fe Springs, Carmenita project in City Best Improved Norwalk, Loma Linda, and others across Riverside and San Bernardino counties.
Infrastructure Project of
the Year 2010. RELEVANT EXPERIENCE
ASCE Region 9 Award City of Rialto / Caltrans District 8 Oversight, SR210 / Alder Avenue Interchange, the SR22 Project "2007 Rialto, CA
Project of the Year. Construction Manager/Resident Engineer/Structures Representative. A complex Calif Transportation roadway and structures project with San Bernardino flood control elements. The scope Foundation (CTF) included on-ramp widening for both EB/WB off-ramps with lean concrete base (LCB), Award: jointed plain concrete pavement (JPCP), CRCP, RHMA, and HMA-A asphalt. Key Freeway/Expressway features included retaining walls type 1 and 5, SCE coordination & relocation, ADA- Project of the Year. compliant curb ramps, three (3) new traffic signal systems, Midwest Guardrail System 2016 (MGS), anchor blocks, and alternate in-line terminal systems (AITS). Final pavement delineations, bike lane and upgraded lighting poles were also completed. The project also addressed major drainage and utility improvements, including storm drain systems, bioswale installations, and flood control enhancements on the WB ramps. Mr.
Burbano managed the reconstruction of reinforced concrete box culverts inside San Bernardino Flood Control and coordinated work on associated water and sewer components. All work was performed in compliance with Environmental Protection Agency (EPA) regulations, with a strong focus on environmental protection and ECR Environmental commitment records, construction safety, and stakeholder coordination.
Project Cost: $8 Million.
City of Rialto Bloomington, Casa Grande and Maple Avenue Improvements, Rialto, CA Construction Manager/Resident Engineer. The Bloomington, Casa Grande, and Maple Improvements Project encompassed work at three distinct locations. At the intersection of Bloomington Avenue, Randall Avenue, and Lilac Avenue-a major six-legged intersection-the project included full pavement reconstruction along with the installation of traffic loops, signal coordination, bike lanes, preformed thermoplastic markings, thermoplastic striping, and utility coordination. Additional scopes included cold milling, hot mix asphalt (HMA) paving, and public outreach.
Casa Grande Drive improvements involved the installation of bike lanes, preformed bike lane markings, thermoplastic striping, signage, cold milling, and rubberized hot mix asphalt (RHMA). The project also included SEG Profess
4 II. STATEMENT OF QUALIFICATIONS
Jose Burbano
(Continuation of Bloomington, Casa Grande, and Maple Avenue Improvements) concrete work such as cross gutters, spandrels, and ADA-compliant curb ramps. The South Maple Avenue portion ot the project focused on pavement rehabilitation and included the installation of new curb and gutter, driveway approaches, sidewalks, water meter relocation, HMA paving, and utility coordination. Project Cost: $1.8 Millior City of Rialto, Traffic Signal Improvements at Senior Way, Rialto, CA Construction Manager/Resident Engineer. Mr. Burbano served as the Construction Manager/Resident Engineer for the traffic signalization improvements at Senior Way in the City of Rialto. The project included the installation of new traffic signals, electrical systems, and center median modifications at Riverside Avenue and Senior Way. The project consisted of the removal and relocation of major palm trees in the center median and coordination with developer and senior living area. This project also included inspection for the installation of video image and vehicle detection systems, controller cabinets, detectable warning surfaces, curb ramps and HMA. Other elements include the construction of a new commercial driveway, curb and gutter, stamped concrete median, and sidewalk. Project Cost:
City of Rialto, Traffic Signal Improvements at Cedar and Etiwanda, Rialto, CA Construction Manager/Resident Engineer. Mr. Burbano served as the Construction Manager/Resident Engineer for the Riverside Avenue & Senior Way Intersection Improvements, overseeing new traffic signals, center median modifications, ADA-compliant pedestrian upgrades, and video image / vehicle detection systems. He managed construction staging, traffic control, and utility/electrical relocations in a congested intersection while maintaining access to an adjacent senior living facility. Mr. Burbano enforced SWPPP BMPs, monitored contractor performance, and kept the work on schedule and in compliance with City standards. Project Cost:
City of Loma Linda, Stewart Street Underpass Grade Separation, Loma Linda, CA holes reinforced with steel spiral cages, timber lagging used for temporary shoring, 9 cantilever retaining walls constructed with spread footings. The bridge spanned the entire roadbed; supported by 18 - 36-inch diameter CIDH embedded 56 feet deep into the ground. Project also required the relocation of existing utilities such as Verizon overhead lines, Gas main, 2 water lines, relocation of existing sewer lines, tunnel drains, to name a few. Kinder Morgan was located near the premises and required some coordination with this facility as well. Mr. Burbano assisted the city with federal and state reimbursement with administrative work as well as ensuring that the project met the timeline to qualify for the federal reimbursement. Project Cost: $40 Million Caltrans District 7, Carmenita Bridge OC over I-5, Santa Fe Springs, CA Principal Assistant Resident Engineer. Mr. Burbano was responsible for all aspects of contract administration including the inspection, documentation of pertinent field items, addressing field changes and full inspection of this complex project as well as assisting with state/federal reimbursement. Mr. Burbano led the team in field with daily potential issues and proposed effective solutions without delays to the controlling operation. Project consisted of a bridge interchange spanning over UPRR, a frontage road and the I-5 freeway. The Santa Ana Freeway (I-5) Carmenita Road Interchange Project, located in the cities of Santa Fe Springs and Norwalk replaced reconstructed the existing two-lane overcrossing with a 10-lane (five lanes in each direction) structure. The project reconfigured the on- and off-ramps and realigned the following frontage roads: Firestone Boulevard, Freeway Drive, Carmenita Road, Arctic Circle, Molette Street and Excelsior Drive./ The project also widened I-5 from Alondra Boulevard to Shoemaker Avenue by adding one High Occupancy Vehicle (HOV) or carpool lane, and one general purpose lane in each direction, as well as widening the shoulder and constructing a median barrier. In addition to the daily administrative task, Jose managed multi-agency utility relocation efforts for UPRR, SCE, AT&T, SoCal Gas Co. and Kinder Morgan Pipelines, ensuring timely adjustments to accommodate the bridge construction. Project Cost: $160 Million. Calif Transportation Foundation (CTF) Award: Freeway/Expressway Project of the Year, City of Cat
SEG Professiona ruction Engineer services
alized Pedes
State
5 Il. STATEMENT OF QUALIFICATIONS
ARMANDO CONTRERAS
Construction Inspector
EDUCATION Armando Contreras has over 15 years of field-tested experience in contract administration and construction inspection for Capital Improvement Programs BS, Industrial Engineering,
California State University, and Caltrans-funded projects. His technical proficiency involves bridge structures, roadway & interchanges, streets, electrical systems, storm drain and East Bay, California, 2015 flood control installations, intersection improvements, with street rehabilitation.
Armando is a detail-oriented professional who excels in coordinating with local
REGISTRATION /
agencies and utility companies to ensure seamless project delivery across
TRAININGS
multiple jurisdictions. He is well versed with regulatory guidelines-including the PCI Quality Control Inspector Local Assistance Procedures Manual, Caltrans Standard Specifications, and the Level Il, No. 17264 Greenbook-ensures each project aligns with all compliance, quality, and PCI Quality Control Inspector performance standards. Mr. Contreras is also experienced with engineers' Level I, No. 17263 estimates, bid schedule, EEO interviews, labor compliance monitoring, tracks ACI Concrete Field-Testing change orders with his detailed diaries, and quantity calculations. His role has Technician - Grade I, No. successfully supported execution of public works spanning roadways, bridge 01541669 infrastructure, drainage systems, and traffic signal construction projects. 30-Hour Cal/OSHA
RELEVANT EXPERIENCE
City of Rialto / Caltrans District 8 Oversight, SR210 / Alder Avenue Interchange, Rialto, CA Roadway Inspector. Mr. Contreras performed construction inspection and assisted the Resident Engineer with contract administration for all items of work, including the widening of both EB/WB off ramps with lean concrete base (LCB), jointed plain concrete pavement (JPCP), slab replacement, CRCP, RHMA, HMA-A asphalt pavement, and the construction of retaining walls, ADA-compliant ramps, and three (3) traffic signal installations. He also oversaw the installation of Midwest Guardrail System (MGS), Alternative In-Line Terminal System (AITS) end treatments, and concrete barriers. Additional work included the reconstruction of reinforced concrete box culverts, drainage systems, and bioswale installations on WB on/off ramps, contributing to flood control and stormwater management. Final traffic signal and lighting pole upgrades were completed in accordance with the 2023 Caltrans standards. All other work, including storm drain systems and access curb ramps, was carried out in strict adherence to Caltrans Standard Specifications and ADA compliance. Project Cost: $8 Million.
City of Rialto, Various Streets Phase | (SCH A-B-C), Rialto, CA Construction Inspector. Mr. Contreras performed construction inspection for the completed street rehabilitation of fifteen (15) streets. Major arterial, secondary arterial and collector streets that included reconstruction of subgrade, HMA-A base course layer RHMA rubberized asphalt surface layer. Improvements also included reconstruction of concrete flatwork for updated compliance of ADA curb ramps. Traffic striping and regulatory signs were installed according to the latest Caltrans standards and MUTCD specifications. Other items of improvement are replacemer f traffic loop detectors, installation of traffic video detection system and installation of accessible pedestrian signal (Polara) to benefit people by improving accessibility for all pedestrians. Project Cost: $28 Million.
City of Rialto, Various Streets Phase II (SCH-D), Rialto, CA Construction Inspector. Mr. Contreras provided construction inspection and field oversight for traffic loop detectors, new pedestrian push buttons, and associated signal/communication work, including coordination of utility modifications and relocations to support those upgrades. The project also delivered ADA-compliant curb ramps, sidewalks, and driveways, along with roadway rehabilitation (subgrade reconstruction, mill and overlay, HMA-A base, and RHMA surface), thermoplastic striping, and regulatory signage. Project Cost: $10 Million.
City of Rialto, Terra Vista Safe Routes to School, Rialto, CA Construction Inspector. This federally funded project included pedestrian improvements: ADA curb ramps, sidewalks, and flashing beacon systems. Armando played a crucial role in assisting with federal reimbursement.
Project Cost: $500K
SEG Professional Construction E
6 II. STATEMENT OF QUALIFICATIONS
The Cathedral City project includes traffic signal improvements and pedestrian/multimodal improvements. SEG has successfully managed similar scopes across Southern California, delivering complex roadway and intersection projects under live traffic while ensuring regulatory compliance. Our proven experience with federally funded projects positions us to deliver Cathedral City's improvements efficiently and with minimal disruption to the community. The projects listed below all hold a similar scope of work and complexity:
SR210 / Alder Avenue Interchange Improvements Project, Caltrans District 8 / City This project delivered three new traffic signals and one signal modification, including video image vehicle detection, APS push buttons, new controllers, metered service, and conduit/pull box upgrades. Work also covered relocating an existing signal pole with a new foundation and completing final signal and lighting upgrades per 2023 Caltrans standards, with ADA compliance. Minor roadway and drainage improvements were performed to accommodate the new signal installations. Traffic Signalization - 3 intersections.
Reference: Art Cervantes, PMP, Engineering Manager | 951.550.1502 Key Staff: Jose Burbano, PE, Armando Contreras, Omar Lopez Bloomington, Casa Grande, and Maple Avenue Improvement Project, City of Delivered three new traffic signals and one modification to improve pedestrian safety. integrating video image vehicle detection, APS push buttons, new controllers and metered service, and upgraded conduit/pull boxes. Work included relocating an existing signal pole on a new foundation with anchor bolts, plus ADA-compliant curb ramps and targeted roadway/drainage tie-ins to support the signal work. Final signal and lighting conformed to 2023 Caltrans standards and were administered in accordance with Caltrans LAPM requirements.
Rocky Kaw, Public Works Engineering | 909.419.9511
Jose Burbano, PE, Armando Contreras, Omar Lopez
Traffic Signal Improvements at Senior Way, City of Rialto The project was composed of various construction activities with key elements in traffic signals, utility relocations, electrical systems, video image and vehicle detection systems. The project was in a congested intersection, which included sequential monitoring of traffic management. The project included traffic, implementation and maintenance of Best Management Practices SWPPP, the installation of traffic signals and center median modification at Riverside Avenue and Senior Way. PPB was required to meet ADA compliance standards, including those related to crosswalks.
Coordination within senior living facility.
Reference: Rudy Victorio, City Project Manager, 909.820.2532 Key Staff: Jose Burbano, PE, Armando Contreras
Traffic Signal Improvements at Cedar and Etiwanda, City of Rialto The project was composed of various construction activities with key elements in traffic signals, utility relocations, electrical systems, video image and vehicle detection systems. The project was in a congested intersection, which included sequential monitoring of traffic management. The project included traffic, implementation and maintenance of Best Management Practices SWPPP, the installation of traffic signals and center median modification at Riverside Avenue and Senior Way. PPB was required to meet ADA compliance standards, including those related to crosswalks.
Coordination within senior living facility.
Art Cervantes, PMP, Engineering Manager | 951.550.1502
Key Staff: Jose Burbano, PE, Armando Contreras
City of Cathedral City
SEG Professional Construction Engineering Support Services for HSIF Cydle 11B: Signalized Pedestrian Crossing Uparades
State Project: No HSIPI-5430(040 CIP No 08755
7 II. STATEMENT OF QUALIFICATIONS
PROJECT UNDERSTANDING
The City of Cathedral City is seeking Professional Construction Engineering Support Services that include Construction Management, Inspection, Labor Compliance, and Materials Testing for the HSIP Cycle 11B: Signalized Pedestrian Crossing Upgrades. This project enhances pedestrian and vehicular safety through the installation of two new signalized pedestrian crossings located at the intersections of 30t Avenue and Avenida La Paz as well as Cathedral Canyon Drive and Ortega Road.
The construction scope is anticipated to include:
rADA Accessibility Improvements: The work will involve new curb bulb-outs, curb and gutter, cross gutters, and will be constructed to shorten pedestrian crossing distances at the points of crossing. The sidewalk and drive-way tie ins will be reconstructed to meet ADA slopes and cross-slopes per Couty of Riverside Standard Plan 400 & 401. The curb and gutter will be constructed per County of Riverside standard plan 200 and the cross gutters per Standard Plan 209. New Case A curb ramps will be constructed per Caltrans standard plan A88A with yellow truncated domes.
Pedestrian Signal / HAWK Systems: Each crossing will have a new HAWK pedestrian signal system which includes pedestrian push buttons, APS audible push buttons, LED vehicle heads, countdown signals, illuminated street signs, and safety lighting. The HAWK signal is activated when the pedestrian call button is pressed. The sequence will begin with flashing yellow for drivers to slow down and prepare to stop and will become a steady red for several
seconds for the pedestrians to cross safely.
The signal systems will also include an
Opticom 721 Emergency Vehicle Detector
head that will be mounted on the mast (CROSSWALK
arms. This detector identifies IR STOP
STOP EN FLASHIN
ON RE KID MI
strobe/LED signals coming from an DEN PROCEE
+ CLEAR
approaching emergency vehicle's Opticom
emitter and converts the light signal into an
electrical call. The call is then sent back to
the control cabinet to request the
emergency vehicle continue and clear the
intersection.
Pavement Resurfacing: At the intersection of 30t Avenue and Avenida La Paz, the existing concrete sidewalk will be removed completely and replaced with an AC pavement section with a 4" minimum AC over 6" minimum aggregate base. This same section will be applied for areas where saw cutting will be done to construct the new ADA ramps. Approximately 9,900 SF of the intersection will be cold milled and overlayed at a 2" depth at the 30"h Ave. and Avenida La Paz intersection. • Traffic Signing and Striping: New ladder crosswalks will be installed per Caltrans standard plan A24F with two coats of traffic rated yellow paint. New striping will be installed to match the existing lanes and bike lanes. The existing slow school crossing markings will be removed and replaced with new yellow pavement markings. New advanced warning signs and regulatory signs will be installed with the addition of an LED enhanced sign for a SW24-3(CA) pedestrian crossing sign that will only flash when a pedestrian pushes the button for the HAWK crossing.
SPECS Engineering Group has knowledge of City, County, State, and Federal regulations and procedures for projects with traffic signals, pavement resurfacing, and ADA compliance, etc.
SEG Profposionali Servisac for HISIE
@ Uprade
State 1 No 19755
8 II. STATEMENT OF QUALIFICATIONS
PROJECT APPROACH
Our team has experience delivering federally funded pedestrian safety and traffic signal projects, as well as large- scale infrastructure improvement projects. We have provided CM agency delivery on a wide range of assignments, developing procedures that emphasize collaboration, risk management, and quality assurance.
MANAGEMENT APPROACH
SEG manages projects using the Caltrans Construction Manual, LAPM, and CAT filing standards to keep responsibilities clear between the City and the contractor. Our PM/CM controls time, cost, information, and quality, and drives early issue resolution to protect schedule and budget.
TIME MANAGEMENT
/ Review and validate the contractor's baseline CPM schedule. • Track three-week look-ahead against the baseline to catch conflicts early. ~ Document daily progress, flag delays, and require recovery measures. • Apply the same process across multiple task orders to limit public impact.
COST MANAGEMENT
~ Verify installed quantities and process accurate monthly pay estimates. ~ Maintain a live change order log and prepare independent cost estimates. • Tie billing to the cost-loaded schedule so pay matches progress. ~ Compare actual costs to the engineer's estimate and funding limits. / Give the City clear cost summaries for reimbursement and audit
QUALITY MANAGEMENT
SEG provides quality assurance by verifying that the contractor's work, materials, and field QC meet the plans and specifications. We review the contractor's QC approach early, track deficiencies, and make sure documentation (RFls, tests, reports) supports what is being built. Strong documentation supports a compliant, durable product in the field
STATE / FEDERAL FUNDING MANAGEMENT
SEG is experienced with federally funded work subject to Caltrans and FHWA oversight. We manage documentation, labor compliance, DBE participation, Buy America, and audit readiness so the project remains eligible for reimbursement.
/ Labor Compliance: Interview workers, review certified payroll, verify prevailing wage, track DBE/trucking participation, and prepare required labor reports.
DBE Oversight: Monitor CUF, prompt payment, substitutions, and required Caltrans Local Assistance DBE forms through closeout.
/ Buy America: Collect and track steel/iron certifications. ~ Change Orders / Force Account: Prepare CEM forms, keep daily T&M records, and support reimbursement.
~ Documentation & Audit File: Maintain submittals, RFls, test results, daily reports, and material certifications in an audit-ready Federal-Aid Project File. ~ Environmental / Permit Compliance: Track SWPPP/BMPs, special environmental conditions, and permit requirements in the field.
• Daily RE Reports: Complete Caltrans-style daily diaries to support pay, change orders, and final closeout.
Materials Testing Oversight: Confirm required test frequencies, document failures/retests, and keep all materials acceptance records in compliance with LAPM and Caltrans IA requirements.
SEG HSIP
9 III. SCOPE OF WORK
SCOPE OF WORK
SEG will deliver organized and responsive construction management services across all project phases.
Before construction, SEG will perform a focused PS&E constructability/biddability review and risk workshop and coordinate with the City of Cathedral City and stakeholders to ensure contract documents are clear, accurate, and aligned with project goals, minimizing risk, delays, and cost impacts. Our team will oversee construction and post- construction activities with a focus on quality, safety, compliance, and minimal disruption. We will also support final closeout and any unresolved issues. SEG is prepared to provide comprehensive services, including construction management, inspection, contract administration, materials testing per the City's QAP with accredited lab and Independent Assurance coordination, utility coordination (with SCE for HAWK power service), scheduling, and document control, ensuring the City's expectations are met from start to finish.
PRE-CONSTRUCTION SERVICES
CONSTRUCTABILITY REVIEW: Prior to the preconstruction conference, Specs Engineering Group will complete a constructability/biddability review of the final PS&E, develop a risk register (cost/schedule/permit/traffic), and provide a short memo of recommended clarifications and preconstruction action items.
PRE-CONSTRUCTION MEETING: Before construction begins, the SEG team will organize and facilitate a pre- construction meeting. SEG will develop a comprehensive agenda to cover key topics, including the project timeline, safety protocols, and any specific concerns. To ensure thorough preparation, we will identify local stakeholders and gather input from all parties regarding issues they feel should be addressed. During the meeting, our team will ensure all concerns and questions are fully addressed. Following the meeting, we will prepare and distribute detailed meeting minutes to attendees for accurate documentation and future reference.
PRE-CONSTRUCTION CONDITIONS: Our team will take aerial drone footage and video documentation of the pre- construction conditions. This effort will capture detailed visual records of existing infrastructure, utility locations, and environmental features. The collected documentation will provide backup for construction monitoring, claims avoidance, and verification of existing conditions.
TIME MANAGEMENT AND TIME DELIVERY SEG will actively manage the construction schedule to protect funding, public access, and agency coordination. We will track the baseline and monthly updates, verify logic and progress, and provide early warning of potential delays. Through real-time coordination with the City, designer, and Contractor, we align inspections, reviews, and approvals with critical milestones to keep the project on schedule.
CONSTRUCTION DOCUMENTATION: SEG will implement document control in accordance with the LAPM and Caltrans Construction Manual, using the Caltrans CAT filing system to maintain audit-ready records and ensure State and Federal compliance. All correspondence, submittals/RFls, quantities, progress payments, change orders, certified payrolls, permits, testing/lA logs (QAP), Title VI/DBE/Buy America documentation, and prompt-payment tracking will be organized, filed, and maintained under this system.
Given HSIP funding, document control is essential to ensure the City's eligibility for reimbursement and to meet FHWA and State audit standards. Our Construction Manager will prepare and distribute weekly statements of working days, detailed status reports, and construction change orders in real time.
SEG will maintain PM-10/WPCP compliance records consistent with the Coachella Valley SIP and NPDES requirements and a log of labor compliance documents, including EEO interviews and certified payroll reviews, ensuring adherence to Davis-Bacon prevailing wage requirements and DBE participation goals, if any.
CONSTRUCTION SERVICES
MULTI-AGENCY COORDINATION AND FEDERAL FUNDING COMPLIANCE: As an HSIP-funded, locally under LAPM and FHWA requirements. SEG will ensure federal-aid eligibility by managing compliance under LAPM SEG Profession
10 III. SCOPE OF WORK
and FHWA requirements. We will track Title VI, DBE, Buy America, and prompt-payment reporting; prepare Exhibit submittals; and keep funding deadlines visible on the schedule's critical path.
WEEKLY MEETINGS AND WEEKLY STATUS REPORTS: SEG will lead weekly :.:
progress meetings with the agency and contractor to review field issues, safety, schedule, submittals/RFls, and potential change orders; our inspectors will participate to resolve jobsite concerns in real time. We will issue meeting minutes and file them in the CAT system, along with a weekly statement of working days and a status report documenting progress, cost and change order exposure, photo documentation, and labor compliance verification.
1. SUBMITTAL REVIEW: As we prepare to begin construction, our PM/CM will verify that all submittals are approved and ready to go which includes traffic control, signal/cabinet/equipment, service/energization coordination with SCE, etc. By reviewing all submittals, our team can ensure that the contractor's submittals follow the plans, specifications and estimates. Our team will keep a live submittal log to track dates of receipt, review and response to ensure prompt approval and mitigate potential delays.
RFI COORDINATION: SEG will receive, process, track, and document project Requests for Information (RFI) along with their responses. An RFI log will be set up at the start of the project and continuously updated by our assigned staff. This log will specify the parties responsible for review and response. SEG Engineering Group will provide prompt responses to RFls related to construction issues, per contract requirements. All responses prepared by the Construction Manager or Principal Inspectors will be shared with the city, which will be copied on all RFls. When necessary, we will coordinate and hold meetings with relevant parties to discuss and resolve any complex RFls. In addition, our inspectors will aid by providing on-field measurements and documentation that would be necessary to address the RFl information.
TRAFFIC CONTROL REVIEW AND COMPLIANCE: Our team will review and monitor traffic control weekly for compliance with the approved plans and MUTCD, with a focus on pedestrian/ADA access to the new HAWK crossings, emergency access, school-hour sensitivity, and driveway/business access. We will require the contractor to maintain safe, continuous access for pedestrians, businesses, residents, and emergency vehicles, and manage LABOR COMPLIANCE: The CM/PM and support staff will ensure adherence to contract labor requirements through early surveillance and proactive monitoring, ensuring compliance throughout the project duration. EEO interviews will be conducted for ever classification, DIR reporting, weekly status reports, and certified payrolls spot checks to ensure labor compliance.
CHANGE ORDERS: SEG Engineering Group will review change orders for contractual and technical merit. All CCOs will be recommended to the City (City approval required); federal-aid documentation will follow LAPM forms and procedures to protect reimbursement.
SAFETY PLAN REVIEW AND MONITORING: Our team will review the Contractor's initial submittal of their safety plan for compliance and monitor its implementation throughout the construction. Our inspectors are trained to recognize unsafe conditions, and by conducting routine safety audits, we will work collaboratively with the contractor's Safety Officer to promote a safe work environment for all staff and the public.
PROGRESS PAYMENTS: Our team will capture all quantities and measurements throughout every operation to provide for work completed when submitting progress payments. Our Construction Manager will review the contractor's progress payment applications to verify that the work being charged has been completed and track monthly progress. If any differences are caught upon review, the Contractor will be notified of any changes or negotiations before processing the payments. SEG will provide a monthly Construction Budget Status Report showing actuals vs. budget by component, estimate to complete, forecast at completion, and variance explanations; any risk of overrun will be elevated to the City with recommended mitigation.
SEG Profes Services for HSIP
11 JHI. SCOPE OF WORK
SWPPP: SEG will monitor and verify that the Contractor maintains compliance with the Storm Water Quality Control Plans/NPDES, BMP maintenance, and PM-10 dust control in accordance with the Coachella Valley SIP and NPDES/MS4 requirements, including inspection logs and corrective-action tracking.
REVIEW AND DOCUMENTATION: The SEG team will designate our inspectors to review plans, contracts, permits, and specifications thoroughly. The team will also prepare a checklist for personnel, ensuring that all necessary documents are readily available when conducting inspections. In addition, inspectors will provide daily updates on the project progress by submitting a daily inspector report and photo logs of the operations going on each day. The photo logs will be maintained in a photo documentation system by date and activity type in CAT 14.
Our inspectors will also ensure to maintain testing and IA logs per QAP.
BUDGET AND QUANTITY MONITORING: The inspectors will maintain all quantities for each pay item and provide backup in quantity sheets using CEM 4801. The inspector will compare actuals with the contractor and track the funding source to support reimbursements with logs.
FIELD MONITORING AND INSPECTION: Daily inspections will be conducted with inspectors, monitoring the construction activities and verifying compliance with plans and safety requirements. To maintain consistency, the team will use inspection checklists. The inspectors will also track the construction progress by keeping photographic records of all the work that goes on each day. In the case of any non-conformance occurring, our inspectors are trained to document and report non-compliant work promptly and ensure corrective actions.
GEOTECHNICAL & MATERIAL TESTING: Our team will coordinate and perform all necessary geotechnical and materials testing in accordance with project specifications and industry standards. Jose Burbano will conduct a pre-job meeting with Ninyo and Moore to coordinate all required materials testing, including asphalt core density testing, nuclear gauge compaction testing, plant inspection, and other relevant procedures.
Independent Assurance coordination will be performed as applicable, with monthly summaries. Our team will keep a detailed log of all material testing requests to ensure proper documentation and tracking.
DRONE PROGRESS FLIGHTS: SEG will conduct monthly aerial drone flights to capture construction progress.
High-resolution videos and images will be used to supplement weekly status reports and provide stakeholders with a clear visual record of key milestones. All footage will be stored in digital format and made available for public outreach, progress meetings, and claim resolution.
We are prepared to provide excellent inspection services, ensuring to:
• REVIEWS AND UNDERSTAND SHOP DRAWINGS: Our team will review all shop drawings and material submittals for accuracy and conformance with project specifications, ADA standards, and Caltrans requirements. We will track submittal approvals and ensure timely responses to avoid delays with items such as signal equipment and SCE service.
PROVIDE DAILY INSPECTION AND DOCUMENTATION THROUGHOUT THE PROJECT: A qualified inspector will be present daily to observe construction activities, monitor progress, and ensure compliance with contract
documents. All findings will be documented in detailed daily reports, including photos, labor, and equipment logs, and notes on progress or issues.
WORK WITH CONTRACTOR TO NOTE PROJECT
CHANGES FOR AS-BUILT DOCUMENTATION: We will
coordinate closely with the contractor to document field modifications and changes in real time, ensuring accurate and complete as-built drawings are developed and submitted at project closeout.
SEG Professional Services tor HSIA
Cycie g Upgrades
Sla No. 08755 12
MI. SCOPE OF WORK
• CONDUCT LABOR COMPLIANCE MONITORING: Our labor compliance staff will review certified payrolls, perform work interviews, and prepare compliance reports with every pay application, in accordance with the Caltrans LAPM and DIR requirements.
REVIEW OF CONTRACTOR PAY APPLICATIONS TO VERIFY
QUANTITIES: Our staff will measure and verify installed quantities and complete work items against the pay applications, ensuring the City only pays for work completed to standard. • GENERAL CONSTRUCTION OBSERVATION: We will observe
all phases of construction-including demolition, concrete flatwork, pad installation, and furniture placement—to confirm that workmanship and materials meet the project's quality standards.
• MONITOR WPCP & PM-C10 AND SWPPP COMPLIANCE: Our
inspectors will verify BMPs, perform erosion control inspections, and document compliance with the MS4 permit, and SWPPP requirements. Dust control and BMP inspections consistent with Coachella Valley SIP and WPCP/SWPPP. Corrective actions will be coordinated immediately with the contractor if non-compliance is identified.
ASSIST CITY PROJECT/CONSTRUCTION MANAGER WITH PROJECT DOCUMENTATION AND CLOSEOUT: We will support the City's Project Manager by maintaining organized project files, assisting with punch lists, preparing closeout packages, collecting warranties, and ensuring all documentation is submitted per federal and local requirements
SUPPORT PUBLIC OUTREACH AND SAFETY OVERSIGHT: We will attend public meetings as requested by the city, monitor traffic control setups, and ensure contractor compliance with approved staging detour plans to minimize impacts to residents, businesses, and commuters. Our team will also keep an "open door" with the public and be available to answer questions and give project updates.
QUALITY CONTROL: Quality assurance and control are essential to our inspection process. Our inspectors will verify PC and other materials by reviewing delivery tickets and coordinating compaction testing prior to concrete placement on the subgrade. Material testing will be performed by our subconsultant, Ninyo & Moore, who will conduct concrete cylinder tests, subgrade compaction tests, plant sampling, and on-site field testing to ensure material compliance.
FEDERAL FUNDING FORMS
FORM DESCRIPTION COMPLETED BY
LAPM Exhibit 3-A Project Authorization/Adjustment Request Local Agency E-76 Caltrans District Local Assistance
Authorization to Proceed with Federal Funds Engineer (DLAE) in coordination with the LPA
LAPM Exhibit 9-F OR 9-P Contractor
DBE Monthly Payment Documentation Resident Engineer
LAPM Exhibit 9-J Contractor
DBE Commercially Useful Function Local Agency
Resident Engineer
LAPM Exhibit 15-A Local Agency Construction Administration Checklist Local Agency LAPM Exhibit 15-B Resident Engineer's Construction Contract Administration Local Agency Checklist Resident Engineer
LAPM Exhibit 15-G Contractor
Construction Contract DBE Commitment
Local Agency
LAPM Exhibit 15-H DBE Information - Good Faith Efforts Contractor LAPM Exhibit 15-M Detail Estimate Local Agency
LAPM Exhibit 16-A Weekly Statement of Working Days Resident Engineer SEG Professions
13 III. SCOPE OF WORK
FEDERAL FUNDING FORMS
FORM DESCRIPTION COMPLETED BY
LAPM Exhibit 16-B Subcontracting Request Contractor / RE LAPM Exhibit 16-C1 Assistant Engineer's Daily Report Inspectors LAPM Exhibit 16-C2 Resident Engineer
Resident Engineer's Daily Report
(or similar)
LAPM Exhibit 16-Y Monthly Progress Payment Item Quantity Calculation Sheet Resident Engineer LAPM Exhibit 16-Z1 Contractor
Monthly DBE Trucking Verification
LAPM Exhibit 17-F Contractor
Final Report - Utilization of DBE and First-Tier Subcontractor Local Agency Resident Engineer
FHWA Form 1637 Resident Engineer / CM Material
Construction Project Material Certification "Buy America" Tester
SIQMP Anticipating CM team
Source Inspection Quality Management Plan
to provide source inspection
FHWA Form 1273 Required contract provisions for federal-aid construction projects Inserted FHWA Form 1637 Construction Project Material Certification (Buy America Contractor compliance Resident Engineer
Form PR-20 Local Agency
Project Agreement between HWA and the local agency
FHWA
Form PR-1 Local Agency
Final voucher for reimbursement
Resident Engineer
Our proposed Project/Construction Manager, Jose Burbano, and support staff have direct experience administering similar federally funded infrastructure projects under Caltrans oversight. We ensure all documentation is audit-ready and acceptable for reimbursement. Our deep familiarity with federally with federal-aid documentation, labor compliance, and Caltrans procedures ensures that project funding is protected and all requirements are met from Notice to Proceed through the final audit.
POST-CONSTRUCTION SERVICES
FINAL INSPECTION, PUNCH-LIST, AND AS-BUILT: Our team will walk the site with the City's representative to flag any remaining punch list items and ensure they align with the Contract scope before our final acceptance.
An itemized punch list with its corresponding log will be created and provided to the Contractor for resolution and tracking purposes. Once the Contractor has addressed all the items on the punch list, a final walkthrough will be scheduled. If the City is satisfied that all issues have been resolved, the Contractor will receive a letter of acceptance, and final payment will be authorized. Throughout this process, SEG will collaborate with all project stakeholders during final inspections to ensure their acceptance of the improvements as required by the agency. SEG will compile all project closeout documents and organize records for audit-ready retrieval; if an audit is initiated, SEG will support the City with document indexing and responses.
REDLINES AND AS-BUILTS: SEG will keep a full-size set of plans to create as-built plans that will be updated to accurately reflect the constructed elements, including any authorized modifications made by the design engineer and adjustments resulting from approved change orders. All changes will be highlighted in red. Upon contract acceptance, these updated plans will be given to the Agency for inclusion in the final as-built documents.
PROJECT CLOSE-OUT: Upon completion of the work and resolution of all punch items, SEG will prepare the closeout package (warranties, O&M manuals, testing/IA records, DBE/pay verifications) and recommend final acceptance; the City will issue acceptance and process final payment/retention release.
SEG Profess