ITEMDESCRIPTION COMPANY COST
1 Fabrication and Installation of CathedralsHoffman Steel Fabrication Inc 69,431.00$ 2 Foundation Westcon Construction Services Inc24,500.00$ 3 Solar Installation Hot Purple Energy 6,500.00$
100,431.00$
15,064.65$
115,495.65$
CATHEDRALS MONUMENT
EAST PALM CANYON DRIVE BETWEEN SUNGATE WAY AND DATE PALM DRIVE MEDIAN
TOTAL COST (QUOTES)
15% CONTINGENY
TOTAL ESTIMATED COST
OPTION 1: SOLAR INSTALLATION - (DC ELECTRICAL LIGHTING)
ITEMDESCRIPTION COMPANY COST
1 Fabrication and Installation of CathedralsHoffman Steel Fabrication Inc 69,431.00$ 2 Foundation Westcon Construction Services Inc24,500.00$ 3 Trenching Towers Electric 24,582.15$
4 Electrical Rhythm Electric 5,050.00$
123,563.15$
18,534.47$
142,097.62$
TOTAL COST (QUOTES)
TOTAL ESTIMATED COST
15% CONTINGENY
CATHEDRALS MONUMENT
EAST PALM CANYON DRIVE BETWEEN SUNGATE WAY AND DATE PALM DRIVE MEDIAN OPTION 2: AC ELECTRICAL LIGHTING