FY 2025-2026 Programmed Capital Improvement Projects
In Progress
CIP PROJECTS: IN PROGRESS PROJECT
NUMBER

CURRENT

PROJECT
PHASE

CURRENT STATUS

PROGRAMMED

BUDGET IN FY
2025-26

PROGRAMMED

BUDGET IN FY
2026-27
Vista Chino Bridge C08899 Design 60% Plans, Specifications, and Estimates (PS&E) 193,180.00$ 193,180.00$
Ramon Road Bridge and Roadway Widening C02500 Design
100% PS&E
Right of Way Acquisition- Temporary
Construction Easements
704,735.00$ 393,627.00$
Edom Hill Truck Climbing C01016 Design 60% PS&E 20,479.00$ 3,115,325.00$ Date Palm Drive North of I-10 Widening C08671 Design 30% PS&E 521,069.00$ 4,737,575.00$ Varner Road from Palm Drive to Date Palm Drive Road Improvements C08674 Design 30% PS&E 947,570.00$ 473,785.00$ East Palm Canyon Drive Widening, MUP, and Traffic Signal at Cree Road C08874 Design 95% PS&E 3,312,000.00$ Downtown Dog Park C07016 Design 100% PS&E
Pursuing funding for construction
$3,349,500.00
(unfunded)
CWSRF Septic to Sewer Planning C01020 Design Environmental Review 1,468,061.00$ 738,286.00$ Cathedral Canyon Drive and CV Link/ Canyon Shores Drive Traffic Signal C06517 Design Traffic Signal Warrant Analysis 605,600.00$ Tropical Storm Hilary Date Palm Drive Pavement Reconstruction C08684 Design Hydrology and Hydraulics Study for Los Gatos Road Intersection 173,500.00$ 173,500.00$
Tropical Storm Hilary Vista Chino Pavement Reconstruciton C08685 Design Pending Tribal Historical Preservation Office Approval 481,000.00$
Landau Boulevard Public Alleyway Reconstruction C02607 Design 60% PS&E 160,000.00$ HSIP 12A: Pedestrian Crossing Enhancements C02602 Design Request for Qualifications/Proposals (RFQ/P):
accepted proposals until March 17, 2026.

Proposals received are under review
55,970.00$ 328,300.00$
HSIP 12B: Pedestrian Crossings at Uncontrolled Locations C02603 Design RFQ/P: accepted proposals until March 17, 2026. Proposals received are under review 54,000.00$ 240,840.00$ HSIP 11A: Pedestrian Crosswalk Upgrades at 18 Unsignalized Intersections C08754 Design 100% PS&E
Requested additional construction funding
from Caltrans
1,630,918.00$
HSIP 9A: Twelve Intersections Safety Improvements C08752 Construction Under construction: estimated completion in April 2026 1,467,409.00$
HSIP 11B: Signalized Pedestrian Crossings C08755 Construction Procuring construction materials
Construction scheduled to begin Summer
2026
875,901.00$ 217,349.00$
HSIP 11C: Citywide Traffic Signal Hardware Upgrades C08756 Construction Under construction: estimated completion by end of June 2026 859,250.00$ 368,250.00$
FY 2025-2026 Programmed Capital Improvement Projects
In Progress
CIP PROJECTS: IN PROGRESS (CONT.) PROJECT
NUMBER

CURRENT

PROJECT
PHASE

CURRENT STATUS

PROGRAMMED

BUDGET IN FY
2025-26

PROGRAMMED

BUDGET IN FY
2026-27
HSIP 11D: Pedestrian Crossing at 30th Avenue and San Eljay Avenue C08757 Construction Procuring construction materials
Construction scheduled to begin Summer
2026
265,340.00$
Panorama Neigborhood Grinding and REAS
Corta Road and Alcita Road Residential Pavement Reconstruction C02605
C02606 Construciton Under construction: construction expected to be completed by end of March 2026 1,325,000.00$
Cypress Road and Santoro Road Rentention Basin C02609 Construction Construction bid opening March 17, 2026:
bids received under review 120,000.00$
Cathedral Canyon Drive Sidewalk from Paseo Azulejo to Kieley Road C02608 Construction Construction bid opening March 11, 2026:
bids received under review 98,000.00$
Whitewater Area Street Rehabilitation Phase II C02610 Construction Construction contract awarded, construction to begin April 2026 1,310,000.00$
Mountain Cathedrals Entryway Monument on East Palm Canyon Drive C02601 Construction Monument under fabrication, construction expected to be completed by June 2026 125,000.00$
Dream Homes Neighborhood Crack Repair C0XXXX Construction Specifications and estimate prepared by
Engineering Department, construction bid
opening to be held early April 2026
300,000.00$
Safe Streets 4 All Planning C06516 Upcoming
On hold- pending grant agreement execution
with Federal Highway Administration (FHWA)
Local Roadway Safety Plan (LRSP) started to
meet July 2026 deadline to update
500,000.00$
Ocotillo Square Neighborhood Streets C0XXXX Upcoming Design on hold 480,000.00$ 120,000.00$ FY 2025-2026 Programmed Capital Improvement Projects
Completed
CIP PROJECTS: COMPLETED PROJECT
NUMBER
FY 2024-25 Citywide Rubberized Emulsion Slurry
C08695
C08696
C08697
C08698
Esperanza Park C07021
Whispering Palms Trail Class III Bike Route C08672
Perez Road Class IV Separated Bikeway C08673
Slurry Seal Maintenance Colaboration Project with Riverside County C08699

CONSTRUCTION TIMELINE
5/27/2025-7/18/2025
37,000.00$

TOTAL CONSTRUCTION COST
$ 1,369,180.55
721,872.60$
381,726.70$
12/26/2023-9/3/2025 $ 10,610,103.36 9/22/2025-11/13/25
10/19/2025-11/19/25
Riverside County Lead: Completed August 2025