Iteris. Moving smarter, together

Local Roadway Safety Plan Update
City of Cathedral City
Draft Report
May 6, 2026

Submitted to:

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | i

TABLE OF CONTENTS

1. Project Overview ...................................................................................................................................... 3

2. Background Review .................................................................................................................................. 6 Local Road Safety Plan ........................................................................................................................ 6 Engineering and Traffic Survey ........................................................................................................... 6 Active Transportation Plan ................................................................................................................. 6 North City Extended Specific Plan ...................................................................................................... 7

3. Methodology ............................................................................................................................................ 8 Stakeholder Identification and Engagement ...................................................................................... 9 Use Safety Data ................................................................................................................................... 9

4. Collision Data analysis ............................................................................................................................ 10 Collision Trends................................................................................................................................. 10 Type of Collisions .............................................................................................................................. 17 High Collision Intersections by PCF ................................................................................................... 17 High Collision Corridors by Primary Collision Factor ........................................................................ 18 Driving Under the Influence ............................................................................................................. 19

5. Demographics ......................................................................................................................................... 20 Population Density ........................................................................................................................... 20 Household-Income ........................................................................................................................... 20 Disability Status ................................................................................................................................ 20

6. Countermeasures ................................................................................................................................... 20

7. Countermeasure Identification and Prioritization ................................................................................. 23 Countermeasure Identification and Evaluation ................................................................................ 23 Improvement Project Evaluation: Benefit-to-Cost Analysis ............................................................. 26

8. Priority Projects ...................................................................................................................................... 27 Project 1: Cathedral City Intersection Safety Program ..................................................................... 28 Project 2: Ramon Road Safety Improvements .................................................................................. 28 Project 3: Date Palm Safety Improvements ...................................................................................... 28 Project 4: Santoro Drive Bicycle Lanes and Traffic Calming Elements .............................................. 28

9. Policy and Process Changes .................................................................................................................... 29

10. Next Steps .............................................................................................................................................. 32

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | ii

TABLES
Table 1: High Collision Intersections by PCF ....................................................................................................... 18 Table 2: High Collision Corridors by PCF ............................................................................................................. 19 Table 3: Proposed Spot Location Improvements ................................................................................................ 23 Table 4: Benefit-Cost Ratio Analysis ................................................................................................................... 27 Table 4: Policy Changes for Improved Safety...................................................................................................... 30

FIGURES
Figure 1: The Five E’s of Traffic Safety .................................................................................................................. 3 Figure 2: Safe System Approach ........................................................................................................................... 4 Figure 3: Safe System Elements ............................................................................................................................ 5 Figure 4: Collision Data Analysis Process .............................................................................................................. 9 Figure 6: Total Collision Annual Trend (January 2020 – December 2024) .......................................................... 10 Figure 5: Collision Locations ............................................................................................................................... 11 Figure 7: Annual Collisions by Year and Mode (January 2020 – December 2024) ............................................. 12 Figure 8: Collisions by Location and Mode (January 2020 – December 2024) ................................................... 12 Figure 9: Fatal and Severe Injury Collisions involving Vulnerable Road Users ................................................... 14 Figure 10: Fatal and Severe Injury Collision Locations ........................................................................................ 15 Figure 11: Collisions based on Severity Index ..................................................................................................... 16 Figure 12: Type of Collisions (January 2020 – December 2024) ......................................................................... 17 Figure 13: Countermeasure Locations ................................................................................................................ 25

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 3

1. PROJECT OVERVIEW
The Local Roadway Safety Plan (LRSP) is a traffic safety planning document developed to proactively address safety needs and challenges in the City of Cathedral City. The document sets forth a comprehensive framework to identify, prioritize, and pursue improvements that mitigate traffic collisions and enhance road safety. By analyzing traffic and co llision data alongside Caltrans and Federal Highway Administration (FHWA) guidelines, the LRSP addresses defined needs and will allow eligibility for funding of these improvements in future Caltrans Highway Safety Improvement Program (HSIP) calls-for-projects cycles and other funding sources.

A total of 464 injury collisions were recorded over the past five years of data (2020-2024) resulting in 824 injuries, of which 30 were fatal injuries and 59 were serious, incapacitating injuries. While collisions involving vulnerable users (pedestrians and bicyclis ts) only accounted for 12 percent of injury collisions (54 of 464 collisions), they accounted for 36 percent of tr affic fatalities. The LRSP is particularly focused on safeguarding those at higher risk. The City of Ca thedral City’s LRSP includes elements for the Federal Safe Streets and Roads for All Program to allow the City to self-certify its eligibility for Safe Streets for All (SS4A) Implementation grants.

Understanding transportation system safety to prevent life-changing injuries or loss of life is of the utmost importance to the City of Cathedral City, the City prepared this LRSP to facilitate the development of local agency partnerships and collaboration, resulting in a prioritized list of improvements and actions that can demonstrate a defined need and contribute to California’s Strategic Highway Safety Plan (SHSP) overall vision and goals.

The LRSP focuses on reducing fatal and severe injury collisions (FSI collisions) with focused challenge areas adopting the Five “E’s” of Traffic Safety, as illustrated in Figure 1 and summarized below.

1. Education: Educate all road users on safe behaviors

2. Enforcement: Enforce actions that reduce high-risk behavior

3. Engineering: Apply effective and/or innovative countermeasures

4. Emergency Response: Improve emergency response times and actions

5. Emerging Technologies: Apply emerging technologies to roadway, vehicle, and user Figure 1: The Five E’s of Traffic Safety
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 4
This plan aims to prevent serious injuries and
fatalities on the roads, supporting the US
Department of Transportation's (US DOT) objective
of having no traffic fatalities across the country. The Safe Systems Approach, often known as Vision Zero,
is the strategy that the US DOT has chosen to
accomplish the transportation safety objective.

Building a transportation system with the
understanding "humans make mistakes and that
humans have limited ability to tolerate crash
impacts" is the goal of the safe system approach. The
Safe System Approach develops plans to reduce
human mistakes in advance of it happening. Figure
2 shows the principles and elements of the Safe
System Approach.

A Safe System Approach provides a safety net for the
user by adhering to the following principles:

1. Death/serious injury is unacceptable: While
no crashes are desirable, the Safe System Approa ch prioritizes crashes th at result in death and serious injuries, since no one should experience either when using the transportation system.

2. Humans make mistakes : People will inevitably make mistakes that can lead to crashes, but the transportation system can be designed and operated to accommodate human mistakes and injury tolerances and avoid death and serious injuries.

3. Humans are vulnerable : People have limits for tolerating crash forces before death and serious injury occurs; therefore, it is critical to design and operate a transportation system that is human- centric and accommodates human vulnerabilities.

4. Responsibility is shared : All stakeholders (transportation system users and managers, vehicle manufacturers, etc.) must ensure that crashes do not lead to fatal or serious injuries.

5. Safety is proactive : Proactive tools should be used to identify and mitigate latent risks in the transportation system, rather than waiting for crashes to occur and reacting afterwards.

6. Redundancy is crucial : Reducing risks requires that all parts of the transportation system are strengthened, so if one part fails, the other parts still protect people.

Achieving a zero-death target requires addressing all accident risk factors using the five components of a safe system, as illustrated in Figure 3.

Figure 2: Safe System Approach
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 5

In addition to supporting the City's transportation goals, the plan gives the City the ability to apply for grants and federal funding. Specifically, projects must be included in an approved safety action plan in order to be eligible for implementation money under the SS4A program.

Figure 3: Safe System Elements
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 6

2. BACKGROUND REVIEW
In updating the City of Cathedral City’s LRSP, other related transportation planning efforts were reviewed.

This section presents key takeaways from multiple documents.

Local Road Safety Plan
The City of Cathedral City Local Road Safety Plan (LRSP), adopted in June 2021, identified the safety needs and recommended projects to address these needs in the City. The LRSP analyzed crash data, identified infrastructure deficiencies, and provided safety countermeasures for high-risk corridors and intersections.

The following is a summary of relevant portions of the LRSP that provides background information for the preparation of the LRSP Update:
• A total of 1,126 collisions were recorded from 2015 to 2019, with 85 crashes resulting in fatal or severe injuries.
o Most common injury and fatality collision types were broadside, rear-end, and head-on. o Most common primary collision factors were unsafe speed, automobile right-of-way, improper turning, and driving or bicycling under the influence of alcohol or drugs (DUI). o Motorcycle collisions represented 9% of tota l fatal collisions and 19% of total severe injury collisions.
o Most common property damage collision types were rear end, hit object, and sideswipe. • Engineering countermeasures recommended for multiple locations in the City include:
o Intersection LED lighting upgrades
o Pedestrian hybrid beacons (HAWK) installations
o Pedestrian crosswalk upgrades
Engineering and Traffic Survey
The City of Cathedral City Engineering and Traffic Survey (E&TS), prepared in May 2025, provided the City with a basis for establishment and enforcement of speed limits for selected streets within Cathedral City.

A total of 73 locations were surveyed within the City. In establishing the appropriate posted speed limits, the analysis took into consideration of CA MUTCD st andard, collision history, and other statistical factors such as 85th-percentile speed and 10-mph pace. The following is a summary of relevant portions of the E&TS that provides background information for the preparation of the LRSP Update:
• Most of the surveyed street segments were recommended to remain at their currently established speed limits as documented and would not require any changes to the existing posted regulatory signage or speed limit pavement markings.
o Spot radar speed surveys were conducted to determine the prevailing speed of drivers on each of the 73 segment locations during January and February 2025. The surveys were performed during typical weekdays with a minimum sample size of 100 vehicles. o 3 out of 73 segments had collision rates that exceeded those of the expected collision rates.

Active Transportation Plan
The City of Cathedral City Active Transportation Plan (ATP), adopted in February 2023, establishes Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 7
strategies to improve mobility conditions for pedest rians, bicyclists, and transit riders. The ATP builds upon local and regional efforts to support active tran sportation, create safer streets for pedestrians and bicyclists, and connect people through infrastructure improvements, with a focus on the most vulnerable users of the roadway. Those active transportati on strategies represent citywide and localized improvements to enhance walking, bicycling, and tran sit conditions for all residents and visitors. The following is a summary of relevant portions of the ATP:
• There are scattered gaps in existing sidewalk network throughout the City, most notably on existing arterials adjoining gated residential co mmunities or adjacent to properties without development. Throughout the City, there are sidewalks in need of repair, which force pedestrians to walk in the street or on uneven surfaces. These circumstances limit the ability of people — particularly people with mobility challenges — to walk in comfort and security. • There are 29.8 centerline miles of existing bike fa cilities in the City, with over 44 centerline miles of proposed bikeways and shared-use trails within the City and its sphere of influence. • Cars were observed not coming to a complete stop at stop signs or stoppi ng in pedestrian walk zones, making it unsafe to cross the street.
• Bicyclists were observed riding on the sidewalk, where dedicated and connected bike lanes were not present. High vehicular volumes and speeds al ong streets also encourage bicyclists to travel on the sidewalk, which creates conflict points between bicyclists and pedestrians. Bike lanes are often too narrow and not buffered or separated from moving vehicles. • To improve pedestrian safety and encourage walking, specific improvements can be made based on site-specific issues:
o New and improved sidewalks
o New and improved crosswalks
o New shade
o Leading pedestrian interval
o Traffic calming (bulb-outs, speed cushion, and medians) • To improve bicyclist safety and encourage biking , specific improvements can be made based on the site-specific issues:
o Class I off-street bike path
o Class II striped lane
o Class III bike boulevard
o Class IV protected lane
o Bicycle parking
o Bicycle-friendly intersection
• Safety elements are proposed throughout Cathedral City in major arterials, collectors, streets adjacent to key destinations. Improved accessib ility and connectivity have shown to add more users to the active transportation system, improve user safety, and allow for greater accommodation for all.

North City Extended Specific Plan
The overall purpose of the North City Extended Spec ific Plan, adopted in January 2014, is to establish a development framework that is fully coordinated with the original North City Specific Plan, as an extension of that plan, to facilitate and encourage improvements to help realize the community’s vision for this area.

The objectives of this Specific Plan are to:
o Direct the location and intensity of new development
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 8
o Guide associated infrastructure and public services
o Balance the provision of job creation and housing opportunities o Implement the conservation criteria estab lished under the Coachella Valley Multiple Species Habitat Conservation Plan (MSHCP) as they may apply to this delineated Specific Plan
o Guide all elements of design for appropriate use in this unique desert environment o Capitalize on the natural resources that exist in this Specific Plan o Encourage sustainable, energy-efficient community development, such as natural scenic vistas
The North City Extended Specific Plan encompasses approximately 590 acres of vacant land located north of Interstate Highway 10 along the Varner Road corridor, and it stretches out to Bob Hope Dr/Rio Del Sol Road on the east and DaVall Dr in the west. The plan could accommodate a unique blend of the following Mixed-Use Development:
• 200,000 square feet of retail/commercial buildings
• 595,000 square feet of restaurants
• 190,000 square feet of office/service buildings
• 595,000 square feet of light industrial
• 400 hotel rooms
• 3,200 residential units
• 240.44 acres of Open Space would be preserved and maintained for use as storm water retention basins, community and neighborhood parks with pub lic recreational facilities, and a network of bikeways, multi-use pathways and pedestrian walkways.

3. METHODOLOGY
The Cathedral City Local Roadway Safety Plan Update focuses on updating and revalidating the LRSP adopted in June 2021. The LRSP update reassesses the lo cal safety needs, analyzes new traffic data and collision data, evaluates the effectiveness of prev ious countermeasures, and implements safety improvements on local roadways that aligns with the Caltrans SHSP and FHWA guidelines. The LRSP Update will provide the City with a strategic plan for implementation which will strive to reduce fatalities and injuries on local roadways, consistent with the goal of the Caltrans HSIP.

The following items were the primary steps used to create this plan:

1. Stakeholder Engagement
a. City staff identified relevant stakeholders and interested representatives that could have input in the LRSP development process. Key stakeholders included public safety departments, schools, regional partners, and community-based organizations.

2. Safety Analysis
a. Past ten (10) years of collision data was used for the analysis. Collision data from January 2015 through December 2024 was used for the analysis.

3. Identify and Prioritize Strategies
a. FHWA Proven Countermeasures and Caltrans safety countermeasures were used in mitigating collision trends and risk characteri stics. Countermeasures were evaluated for Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 9
feasibility, cost-effectiveness, and expected safety benefits.

4. LRSP Documentation
a. High priority locations were identified for specific safety improvements. A specific project list based on benefit/cost analysis was developed.

Stakeholder Identification and Engagement
A project such as this requires establishing the le adership and stakeholders responsible for contributing to the plan. Involving stakeholders in the decision-making process is essential because it enables thoughtful consideration and input from interested parties. Stakeholders can provide insightful thoughts, observations, and relevant viewpoints regarding the needs and performance of the transportation system because they are regular users of local roadways. Stakeholders may be able to identify important hotspots and safety zones by participating in the LRSP development process.

An established working group with important players from the "5E's" of highway safety, engineering, enforcement, education, emergency response, a nd emerging technologies—is emphasized as being crucial by the FHWA. During the process, Iteris met with representatives from Public Works Department, Police Department, Fire Department, Agua Caliente Band of Cahuilla Indians Planning Department, and Palm Springs Unified School District (PSUSD) to gain feedback on safety concerns.

Use Safety Data
As mentioned, relevant background
information, data and documents were
gathered during the background review
and safety data analysis effort.

Following gathering of the data from the
City and relevant data sources, the data
was collated and organized to locate the
City’s collision “hot spots” or emphasis
areas (i.e. corridors, intersections, etc.).

This analysis narrowed down the data to
key emphasis areas which were then
analyzed with much finer detail to
determine collision causes and other
collision factors contributing to the
safety of the location. The approach to
the data review is illustrated by the simple flowchart shown in Figure 4.

Figure 4: Collision Data Analysis Process

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 10

4. COLLISION DATA ANALYSIS
The City of Cathedral City collision data was gathered using collisions from the SWITRS collision database.

The data set contains five complete years’ wort h of collisions spanning from January 2020 through December 2024. During this period, a total of 464 co llisions were reported in the City. These collisions were classified based on location : intersection and corridor segment. Figure 5 (on the following page) shows the locations of all intersection collisions.

Collision Trends
Collision trends in terms of annual magnitude and severity are presented in this section. Figures 6 and 7 illustrate the annual collisions in the City during the data evaluation period by severity and mode of travel, with the highest number of collisions recorded in 2023 with 118 crashes
totaling 200 victims, including 9 victims that experienced fatal injury and 20 victims that experienced severe injury.

There were 32 pedestrian-related and 22 bicycle-related collisions during the data analysis period, also known as collisions involving vulnerable road users.

Figure 6: Total Collision Annual Trend (January 2020 – December 2024)

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 12
Figure 7: Annual Collisions by Year and Mode (January 2020 – December 2024)

A total of 228 collisions (or 49%) occurred at intersec tions, a total of 86 collisions (or 19%) occurred near intersections, and a total of 150 collisions (or 32%) occurred at corridors (midblock, driveways or traffic/light poles). For the purpose of categorizi ng the collisions, a collisio n was considered to be associated with an intersection if it was recorded within 100 feet of an inte rsection. Outside of that distance, a collision was considered to be a midblock/corridor-related collision. Figure 8 illustrates collisions by location and mode.

Figure 8: Collisions by Location and Mode (January 2020 – December 2024)

65 66 68
104 107
88 1
9 65 3 4 55
0 20
40 60
80 100
120
2020 2021 2022 2023 2024
Collisions
Motor Vehicle Only Pedestrian Bicycle
272
23 19
138
9 3
0 50
100
150
200
250
300
Motor Vehicle Pedestrian Bicycle
Collisions
At Intersection Not At Intersection
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 13
Of the 314 collisions associated with intersections, 23 involved pedest rians and 19 involved bicycles. Of the 150 collisions that occurred midblock/on corridors , 9 involved pedestrians and 3 involved bicycles.

Figure 9 (on the following page) presents the locations of fatal and severe injury collisions involving vulnerable road users.

In order to help understand where safety countermeasures may be most needed, Figure 10 presents the collision locations in terms of highest severity injury. This measure of severity is further broken down and presented as severity index and shown in Figure 11. Severity index is based on the monetized cost from federal benefit/cost guidance.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 17
Type of Collisions
In addition to the most frequent collision locations, evaluation of the type of collisions helps identify collision patterns and traffic/travel behavior in the City which will lead to effective safety countermeasures. High number of rear-end collisions could indicate speeding within the City, whereas high number of broadside collisions could indicate nonadherence to existing traffic control devices, improper turning decisions and/or insufficient traffic signal timing settings. Sideswipe collisions could be attributed to distracted or aggressive driving, merging and lane switching, and driving under influence.

As illustrated in Figure 12, broadside collisions were the most commo n type of collisions within the City, followed by rear end collisions and hit object collisions.

Figure 12: Type of Collisions (January 2020 – December 2024)

High Collision Intersections by PCF
The collision data was further analyzed to identify in tersections with the highest number of collisions by primary collision factor (PCF). Table 1 summarizes the 10 intersections with the highest number of collisions citywide between January 2020 and December 2024, along with the most prevalent PCFs at each intersection. This analysis includes collisions that oc curred at or near an inters ection at a distance less than 100 feet. Appendix A summarizes all collision data by intersection by PCF.

Unsafe speed, driving or bicycling under the influence of alcohol or drug, and automobile right-of-way were generally the most prevalent causes of collisions at the 10 high-collision intersections.

1.1%

3.0%

3.2%

7.3%

8.8%

11.4%

12.3%

17.0%

35.8%

0.0% 5.0% 10.0% 15.0% 20.0% 25.0% 30.0% 35.0% 40.0%
Not Stated
Other
Overturned
Vehicle/Pedestrian
Sideswipe
Head-On
Hit Object
Rear End
Broadside
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 18
Table 1: High Collision Intersections by PCF
Intersection Total
Collisions
Fatal + Severe
Injury
Collisions
Prevalent PCFs
Cathedral Canyon Dr/E Palm Canyon Dr 17 3
Traffic signals and signs; Driving or bicycling under the influence of alcohol or drug; Automobile right-of-way
Note: Current planned improvement project by City
Cathedral Canyon Dr/Dinah Shore Dr 16 3
Unsafe speed; Driving or bicycling under the influence
of alcohol or drug
Note: Current planned improvement project by City
Ramon Road/Date Palm Dr 13 1
Unsafe speed; Automobile right-of-way; Improper
turning; Driving or bicycling under the influence of
alcohol or drug
Date Palm Dr/Vista Chino 13 2 Unsafe speed; Driving or bicycling under the influence of alcohol or drug; Traffic signals and signs
Ramon Rd/Cathedral Canyon Dr 13 5 Unsafe speed; Driving or bicycling under the influence of alcohol or drug; Automobile right-of-way
Ramon Rd/Desert Vista Rd 12 0 Automobile right-of-way; Traffic signals and signs; Improper turning
Date Palm Dr/Varner Rd 12 6
Unsafe speed; Driving or bicycling under the influence
of alcohol or drug; Improper turning
Note: Current planned improvement project by City
Landau Blvd/Ramon Rd 12 4 Improper turning; Automobile right-of-way Note: Current planned improvement project by City
E Palm Canyon Dr/Canyon Plaza 10 2 Driving or bicycling under the influence of alcohol or drug; Improper turning
Landau Blvd/Vista Chino 10 2 Driving or bicycling under the influence of alcohol or drug; Automobile right-of-way; Improper turning
As shown, the Cathedral Canyon Drive/East Palm Ca nyon Drive and Cathedral Canyon Drive/Dinah Shore Drive intersections experienced the highest collision frequency over the data collection period.

High Collision Corridors by Primary Collision Factor
Similar to the intersection analysis, the collision data was further analyzed to identify corridors with the highest number of collisions by PCF. This analysis includes collisions that occurred along a corridor at a distance greater than 100 feet from an intersecti on and collisions with utilities and at driveways.

Identifying collisions along the corridor by PC F allows us to recommend corridor-specific countermeasures. Appendix B summarizes all collision data by corridor by PCF.

Table 2 summarizes corridors with the highest number of collisions citywide (greater than ten collisions) between January 2020 and December 2024. Unsafe spee d, automobile right-of-way, and driving or bicycling under the influence of alcohol or drug were the most prevalent causes of corridor collisions in the City.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 19
Table 2: High Collision Corridors by PCF
Corridor (City Limits) Total
Collisions F+SI Prevalent PCFs
Date Palm Dr 97 24 Driving or bicycling under the influence of alcohol or drug; Unsafe speed; Traffic signals and signs
Ramon Rd 84 24 Unsafe speed; Automob ile right-of-way; Improper Turning East Palm Canyon Dr 70 15 Driving or bicycling under the influence of alcohol or drug; Automobile right-of-way; Improper Turning
Vista Chino 32 5 Automobile right-of-way; Traffic signals and signs; Unsafe speed; Driving or bicycling under the influence of alcohol or drug Varner Rd 26 5 Unsafe speed; Improper turning
Cathedral Canyon Dr 22 5 Automobile right-of-way; Unsafe speed; Driving or bicycling under the influence of alcohol or drug
Dinah Shore Dr 22 4 Unsafe speed; Traffic signals and signs; Driving or bicycling under the influence of alcohol or drug

Driving Under the Influence
Review of primary collision factors highlighted a concentration of collisions due to vehicle operators driving under the influence of alcohol or drugs. Citywide, impaired driving was the primary factor in 24 percent of collisions and injuries but involved in 55% of fatal collisions in the City. Most of the impaired driving collisions (63 percent) occurred in three corridors:
• Date Palm Drive – 26 in five years
• Ramon Road – 16 in five years
• East Palm Canyon Drive – 14 in five years

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 20

5. DEMOGRAPHICS
Cathedral City will give equitable solutions for road sa fety priority, considering the higher risk of traffic- related injuries and fatalities that marginalized an d underprivileged communities experience. In order to better inform the solutions that will be proposed th rough the plan, the equity analysis in this chapter provides information on the location and size of marginalized populations. The American Community Survey (ACS) provided the data used in this equity an alysis. In order to establish fair solutions, it is imperative to identify groups of concern and solicit public feedback. For example, due to budgetary constraints, low-income groups could need more transportation accommodation. This is especially crucial if a sizable portion of households in this area don't own any vehicles.

Population Density
The total population of Cathedral City per the 2025 Census estimate was 52,517. The median age range in Cathedral City is 41 to 42 years of age. Around 19 percent of the population is older than 65 years of age. The majority of those 65 years of age and over live in the northern and southern part of the city.

Household-Income
The median household income in Cathedral City is $73,572 which is 27 percent below the California median household income of $100,149. 13.1 percent of Cathedral City re sidents are estimated to live in poverty.

Disability Status

7.4 percent of the population in Cathedral City has some form of disability, with the majority having some form of ambulatory difficulty. 11.1 percent of the population under 65 years old live without health insurance in Cathedral City.

6. COUNTERMEASURES
With the thorough evaluation of available collision da ta, Iteris has a solid understanding of the most common collision locations, roads, and significant coll ision trends and issues, along with the hotspots for collisions involving bicycles and pedestrians. In or der to accomplish the goal of eradicating collisions resulting in fatalities and serious injuries, countermea sures can be put in place to make roadways safer for all forms of transportation. Physical changes are frequently undertaken to address hazardous intersections, vehicle speeds, and pedestrian and bicyclist safety.

The Local Roadway Safety Manual (April 2024) 1, Highway Safety Improvement Program (HSIP) Analyzer Manual, April 2024 2 and Crash Modification Factors (CMF) Clearinghouse 3 were utilized in the countermeasure identification process. Additionally, the US Department of Transportation, Federal

1 Local Roadway Safety Manual, April 2024: https://dot.ca.gov/-/media/dot-media/programs/local- assistance/documents/hsip/2024/lrsm2024-v2.pdf
2 HSIP Analyzer Manual, April 2024: https://dot.ca.gov/-/media/dot-media/programs/local- assistance/documents/hsip/2024/hsip-analyzer-manual-bcr2024.pdf 3 Crash Modification Factors (CMF) Clearinghouse: https://cmfclearinghouse.fhwa.dot.gov Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 21
Highway Administration released a list of twenty-eight proven safety countermeasures 4 that support the goal of eliminating fatalities and serious injuries. These countermeasu res were also reviewed during the selection process. Countermeasures and spot improv ements were developed for the identified hotspot locations with a history of collisions within the City.

A list of countermeasures was compiled, separated by types of collisions they can reduce, and sorted by effectiveness in terms of Crash Reduction Factor (CRF). The following is a list of countermeasures grouped with the applicable types of collisions they address and locations (signalized intersections, non-signalized intersections, and roadways). The corresponding countermeasure “code” is provided, where SI = signalized intersection, NS = non-signalized intersection, and R = roadway:

Lights and Night collisions:
• SI01NT/NS01NT: Add intersection lighting, CRF=0.40
• R01NT: Add segment lighting, CRF=0.35

Pedestrian right-of-way and Pedestrian collisions:
• SI03: Improve signal timing, CRF=0.15
• SI21PB: Install advance stop bar before crosswalk, CRF=0.15 • SI22PB: Modify signal phasing to implement a Leading Pedestrian Interval (LPI), CRF=0.60 • R34PB: Install separated bike lanes, CRF=0.45
• R36PB: Install/upgrade pedestrian crossing (with enhanced safety features), CRF=0.35

Following too closely collisions:
• SI02: Improve signal hardware: lenses, back-plates with retroreflective borders, mounting, size, and number, CRF=0.15
• NS10: Install flashing beacons at stop-controlled intersections, CRF=0.15

Automobile right-of-way collisions:
• SI03: Improve signal timing (coordination, phases, red, yellow, or operation), CRF=0.15 • SI06: Provide protected left turn phase (left turn lane already exists), CRF=0.30 • NS03: Install signals, CRF=0.30
• NS08: Install/upgrade larger or additional stop signs or other intersection warning/regulatory signs, CRF=0.15
• NS13: Improve sight distance to intersection (clear sight triangles), CRF=0.20 • R02: Remove or relocate fixed objects outside of clear recovery zone, CRF=0.35 • R14: Road diet (reduce travel lanes and add a two way left-turn and bike lanes), CRF=0.35 • R22: Install/upgrade signs with new fluorescent sheeting (regulatory or warning), CRF=0.15

Traffic signals and signs collisions (Note that this fact or refers to drivers disregarding traffic signals or signs):
• SI03: Improve signal timing (coordination, phases, red, yellow, or operation), CRF=0.15 • NS08: Install/upgrade larger or additional stop signs or other intersection warning/regulatory signs, CRF=0.15
• R22: Install/upgrade signs with new fluorescent sheeting (regulatory or warning), CRF=0.15

4 Proven Safety Countermeasures, Federal Highway Administration:https://highways.dot.gov/safety/proven-safety- countermeasures
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 22

Improper turning collisions:
• SI03: Improve signal timing (coordination, phases, red, yellow, or operation), CRF=0.15 • SI06: Provide protected left turn phase (left turn lane already exists), CRF=0.30 • SI08: Install raised pavement markers and striping (through intersection), CRF=0.10 • SI11: Install raised median on approaches, CRF=0.25
• SI13: Create directional median openings to allow (and restrict) left-turns and U-turns, CRF=0.50 • NS02: Convert to all-way STOP control (from 2-way or yield control), CRF=0.50 • NS08: Install/upgrade larger or additional stop signs or other intersection warning/regulatory signs, CRF=0.15
• NS13: Improve sight distance to intersection (clear sight triangles), CRF=0.20 • NS16: Install raised median on approaches, CRF=0.25
• R08: Install raised median, CRF=0.25
• R14: Road diet (reduce travel lanes and add a two way left-turn and bike lanes), CRF=0.35

Unsafe speed collisions:
• NS02: Convert to all-way STOP control (from 2-way or yield control), CRF=0.50 • NS09: Upgrade intersection pavement markings, CRF=0.25 • R26: Install dynamic/variable speed warning signs, CRF=0.30 • R28: Install edge-lines and centerlines, CRF=0.25

Wrong side of road collisions:
• SI11: Install raised median on approaches, CRF=0.25
• NS16: Install raised median on approaches, CRF=0.25
• R08: Install raised median, CRF=0.25
• R28: Install edge-lines and centerlines, CRF=0.25

Improper passing collisions:
• R28: Install edge-lines and centerlines, CRF=0.25

Driving or bicycling under the influence of alcohol or drug collisions:
• Other: DUI Enforcement, CRF varies

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 23

7. COUNTERMEASURE IDENTIFICATION AND

PRIORITIZATION
Upon development of countermeasures for locations in the City of Cathedral City with a history of collisions, projects and their prioritization for implementation of the recommended countermeasures were developed. Prioritization was built on the safety analysis to identify high-risk locations as well as those which will be most effectively addressed by feasible countermeasures and cost effectiveness.

Countermeasure Identification and Evaluation
The following safety improvement projects were identified based on the recommended countermeasures at the high collision frequency intersections, whereas a toolkit of applicable countermeasures was identified for high collision frequency corridors.

7.1.1 Identified Countermeasures
Based on the countermeasures’ applicable collision history, a set of safety improvements at the intersections identified as having the highest collision frequency was developed, along with each project’s total effectiveness to reduce collisions (as a percentage of all collisions recorded at that location). Table 3 presents the proposed improvements at 17 locations throughout the City. Figure 13 presents the locations of each intersection and also denotes locations where the City is currently designing or constructing safety improvements (separate from this LRSP effort).

Table 3: Proposed Spot Location Improvements
ID Intersection Proposed Improvement Project
Collision
Reduction
Effectiveness
%
1 Cathedral Canyon Dr/East Palm
Canyon Dr · Update signal timing with protected NB/SB left turn phases 18% 2 Ramon Rd/Whispering Palms
Trail
· Modify signal phasing to implement a leading pedestrian interval (LPI) (ATP Project) 13%
3 Ramon Rd/Crossley Rd · Prohibit on-street parking along the east side of Crossley Road, north of Ramon Road 9%
4 Date Palm Dr/Victoria Dr
· Move westbound stop line closer to the intersection to improve the sight line and improve crosswalk on the east leg add LPI (ATP project)
7%
5 Cathedral Canyon Dr/33rd Ave · Convert the intersection from two-way stop control to all- way stop control 50%
6 Date Palm Dr/35th Ave
· Install traffic signal at the intersection, add protected phasing for southbound left turns
· Add marked crosswalks on the south leg and east leg · Add street lights in blocks north and south of the intersection
37%
7 Date Palm Dr/Tachevah Dr · Install traffic signal at the intersection, add protected phasing for northbound left turns 30%
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 24
ID Intersection Proposed Improvement Project
Collision
Reduction
Effectiveness
%
8 Ramon Rd/Avenida
Maravilla/Cathedral Canyon Dr
· Improve the sight line for northbound approach with raised pavement marker and striping
· Install dynamic/variable speed warning signs for the northbound approach
· Modify signal phasing to implement a leading pedestrian interval (LPI) (ATP project)
17%
9 Vista Chino/Landau Blvd · Install raised median on the west leg and east leg 10% 10 Date Palm Dr/Vista Chino · SBR, EBL improvements, improve signal timing · Install dynamic/variable speed warning signs 13%
11 Ramon Rd/Date Palm Dr
· Update signal timing for more clearance time
· Improve sight line at the north leg for gas station driveway egress movements
· Modify signal phasing to implement a leading pedestrian interval (LPI) (ATP project)
14%
12 East Palm Canyon Dr/Perez Rd · Convert the two-way left turn lane (TWLTL) on the west leg to prohibit turns (not raised median for emergency services access) 22% 13 Ramon Rd/Avenida Del Yermo/
Desert Vista Rd
· Modify the intersection to a four-leg signalized intersection, with Avenida Del Yermo being the north leg and Desert Vista Road being the south leg
· Implement split phasing for northbound and southbound movements
· Remove raised median on Ramon Road between Avenida Del Yermo and Desert Vista Road, shift eastbound stop line to the west side of Avenida Del Yermo
· Modify signal phasing to implement a leading pedestrian interval (LPI) (ATP project)
35%
14 Mountain View Rd/Varner Rd
· Upgrade westbound right turn “STOP” sign to larger size and add “WATCH FOR ONCOMING TRAFFIC” warning sign
· Upgrade pavement marking for “STOP” and stop line
· Add guardrail along the northeast corner for westbound right turn movements
7%
15 Date Palm Dr/McCallum Way
· Update signal timing with protected eastbound/westbound left turn phases
· Modify signal phasing to implement a leading pedestrian interval (LPI) (ATP project)
21%
16 San Luis Rey Dr/Mission Dr · Install dynamic/variable speed warning signs · Install flashing beacons for the “STOP” sign for all approaches 15% 17 Santoro Dr/Cypress Rd
· Install Class II bike lane along both sides of Santoro Drive, between 30th Avenue and McCallum Way
· Add bike lane pavement marking
· Convert Two-Way Stop Control to All-Way Stop Control 50%
18 Ramon Rd Bicycle Lanes · Install Class IV Bicycle Lanes (ATP project) 55%

Figure 13 - Countermeasure Locations
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 26

7.1.2 Systemic Corridor Countermeasures
In the last five years, 61 percent of all injury outcomes occurred in three corridors. Based on analysis of the collision factors and types of collisions in the corridors, systemic improvements were reviewed:
• Date Palm Drive – high levels of driving under the influence factors (22 percent) and high speeding (20 percent) due to is role as providing regional access to/from Interstate 10 and East Palm Canyon Drive. The Cathedral City Police Department conducts driving under the influence (DUI)
che
ckpoint on a rolling basis, this corridor is a strong candidate for future deployments. Many of the proposed safety countermeasures for spot locations are along Date Palm Drive and include elements which could reduce speeds. Feedback speed signs and programs to encourage lo wer speeds cou
ld also be deployed in the corridor.
• Ramon
Road – high levels of speeding (20 percent) and high levels of improper turning/yielding right of way (34 percent) are major factors for collisions in this corri dor. The corrido r is characterized by offset intersections w
here north/south roadways do not meet directly ac ross
Ramon Road. The corridor also has several uns ig
nalized left-turns, which must cross three
opposing lan
es of traffic. Proposed Class IV bicycle lanes and leading pedestri an intervals from the A
ctive Transportation Plan would have a role in improving conditions for walking and biking in
the corridor. Spot location improvements re commended as part of this LRSP would also improve over
all corridor safety conditions. The installation of Class IV Bicycle Lanes and LPIs was included as a corridor-wide project based on the Active Transportation Plan recommended project.
• East Palm
Canyon Drive – high levels of driving under the influence factors (24 percent) and high levels of improper turning/yielding right of way (36 percent) are major factors for collisions in this corridor. There are several current and planned projects to improve medians and intersection in the corridor. Similar to Date Palm Drive, East Palm Canyon Drive is a strong candidate for DUI checkpoints
due to its role as a regional connector.

Improvement Projec t Evaluation: Benefit-to-Cost Analysis Benefit-Cost Analysis is a standardized methodology for evaluating pr oject effectiveness. The safety benefit for intersections was calculated using USDOT’s Benefit-Cost Analysis Guidance for Discretionary Grant Programs (December 2025) , which outlined the estimated safety cost for fatalities, injuries, and crashes. KABCO level indicates the seriousness of co llisions, with K being the highest (killed), followed by serious/incapacitating injuries, visible injuries, and complaint of pain. The coll ision reduction factor for each countermeasure was applied to each location’s collision history to evaluate its effectiveness in reducing injuries from those collisions.

The costs of improvements were based on unit costs in 2026 dollars. These unit costs were escalated by 200 percent to account for project development, mobilizat ion, soft costs, and contingency. The result of comparing these two monetized values is a Benefit-Cost Ratio (BCR). For the purposes of this report, the BCR was used for comparison purposes. A more advan ced version of the calculation involves year of expenditure and future benefit periods is used in federal grant applications where a BCR greater than 1.0 indicates the safety benefit cost outweighs the cons truction cost for proposed countermeasures and an BCR less than 1.0 indicates the construction cost outweighs the safety benefit cost.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 27
Table 4 summarizes the results of the benefit-to-cost analysis.

Table 4: Benefit-Cost Ratio Analysis
ID Location
Collision
Reduction Benefit
(Five Year)
Cost
Estimate B/C Ratio
1 Cathedral Canyon Dr/East Palm Canyon Dr $948,390 $600,000 1.6 2 Ramon Rd/Whispering Palms Trail $8,373,780 $21,000 398.8 3 Ramon Rd/Crossley Rd $153,780 $17,382 8.8
4 Date Palm Dr/Victoria Dr $2,813,440 $4,650 605.0
5 Cathedral Canyon Dr/33rd Ave $7,874,100 $17,766 443.2 6 Date Palm Dr/35th Ave $4,146,720 $2,921,002 1.4
7 Date Palm Dr/Tachevah Dr $4,110,000 $2,146,851 1.9
8 Ramon Rd/Avenida Maravilla/Cathedral Canyon Dr $398,580 $121,800 3.3 9 Vista Chino/Landau Blvd $542,650 $162,000 3.3
10 Date Palm Dr/Vista Chino $1,100,400 $102,000 10.8
11 Ramon Rd/Date Palm Dr $1,098,675 $52,567 20.9
12 East Palm Canyon Dr/Perez Rd $439,900 $108,000 4.1 13 Ramon Rd/Desert Vista Rd $655,620 $674,925 1.0
14 Mountain View Rd/Varner Rd $399,155 $36,777 10.9
15 Date Palm Dr/McCallum Way $183,600 $621,000 0.3
16 San Luis Rey Dr/Mission Dr $110,160 $464,702 0.2
17 Santoro Dr/Cypress Rd $61,200 $213,060 0.3
* Ramon Rd Improvements (Bicycle Lanes) $22,204,515 $4,125,000 16.1 *Note that the Ramon Road Corridor Improvements for the installation of Class IV Bicycle Lanes and LPIs does not double count improvements by Ramon Road spot location improvements.

8. PRIORITY PROJECTS
The identified safety countermeasures for locations identified in Section 7 were consolidated into recommended implementation projects. Four individual projects were identified:
• Project 1: Cathedral City Intersection Safety Program • Project 2: Ramon Road Safety Improvements
• Project 3: Date Palm Safety Improvements
• Project 4: Santoro Drive Bicycle Lanes and Traffic Calming Elements

Projects 1, 2, and 3 are recommended for HSIP applicatio ns due to their collision history and expected safety benefits. Project 4 could be funded under the HSIP bicycle safety set-aside or an Active Transportation Program (ATP) grant.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 28
Project 1: Cathedral City Intersection Safety Program
The Cathedral City Intersection Safety Program is composed of improvements to eight locations in the City. The safety goals of the project are to improve conditions for vehicles and vulnerable users based on collision history and factors experienced at project lo cations. The project cost estimate is $2.5 million.

Based on the previous five-year collision history and th e safety countermeasures of the project, there is an expected reduction in collisions of 3.5 per year resu lting in a reduction of 0.4 fatal or severe injuries and 2.8 other injuries per year. These benefits ar e monetized to $32 million, resu lting in a benefit-cost ratio of 12.6 per the Cycle 12 HSIP Analyzer tool.

Project 2: Ramon Road Safety Improvements
The Ramon Road Safety Improvements is composed of improvements to five intersections and corridor- wide protected bicycle lanes. The safety goals of the project are to improve conditions for vulnerable users and improve intersection conditions at off-set inte rsection locations. The project cost estimate is $4.8 million. Based on the previous five-year collis ion history and the safety countermeasures of the project, there is an expected reduct ion in collisions of 6.4 per year resulting in a reduction of 0.8 fatal or severe injuries and 3.6 other injuries per year. These benefits are monetized to $41.8 million, resulting in a benefit-cost ratio of 8.8 per the Cycle 12 HSIP Analyzer tool.

Project 3: Date Palm Safety Improvements
The Date Palm Safety Improvements is composed of improvements to three locations. The safety goals of the project are to address high speeds, unprotected left-turns, and poor lighting in the corridor. The project cost estimate is $4.7 million. Based on th e previous five-year collision history and the safety countermeasures of the project, there is an expected reduction in collisions of 1.0 per year resulting in a reduction of 0.3 fatal or severe injuries and 0.5 othe r injuries per year. These benefits are monetized to $19.6 million, resulting in a benefit-cost ratio of 4.1 per the Cycle 12 HSIP Analyzer tool.

Project 4: Santoro Drive Bicycle Lanes and Traffic Calming Elements The Santoro Drive Bicycle Lanes and Traffic Calming El ements is composed of a comprehensive bicycle mobility and speed reduction program from McCallum Way to 30 th Avenue with connections to James Workman Middle School. The goals of the project ar e to improve conditions for vulnerable users and reduce vehicle speeds in the corridor while providing an improved, safe bicycle route to school. The project cost estimate is $212,000. Based on the prev ious five-year collision history and the safety countermeasures of the project, there is an expected reduction in collisions of 0.5 per year resulting in a reduction of 0.1 injuries per year. While the study area does not have an ex tensive reported collision history, speeding in the corridor was identified as a major issue in stakeholder engagement. This project is a candidate for the bicycle safety set-aside of $350,000 per community, which was included in the HSIP Cycle 12. This set-aside did not require a BCR value. If the bicycle safety set-aside is not included in future Cycles of HSIP, it is a candidate for an ATP grant.

Appendix C presents conceptual improvement plan “cut sheets” for the four projects. Appendix D provides cost estimate worksheets for each project.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 29

9. POLICY AND PROCESS CHANGES
In addition to physical improvements, policy and
process changes are considered, which include
assessment of current policies, plans, guidelines,
and/or standards (i.e., manuals) to identify
opportunities to improve how processes prioritize
transportation safety. A list of potential policies
developed by the National Highway Traffic Safety
Administration to improve safety conditions as specific countermeasures for the City to consider are shown in
Table 5, including each policy’s potential effectiveness and rough cost range (low, medium, or high) which are
described after the table.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 30
Table 5: Policy Changes for Improved Safety
Policy Based
Countermeasure
Category
Countermeasure Effectiveness
(1 to 5)
Cost
($ to $$$)
Alcohol-Impaired
Driving
Publicized Sobriety Checkpoints 5 $$$
High-Visibility Saturation Patrols 4 $$
Drug-Impaired Driving Enforcemen t of Drug-Impaired Driving 3 $$ Seat Belt and Child
Restraints
Short-Term, High-Visibility Seat Belt Law Enforcement 5 $$$ Sustained Seat Belt Enforcement 3 Varies
Speeding and Speed
Management
Lower Speed Limits 5 $
Speed Safety Camera Enforcement 5 Varies
High-Visibility Enforcement 5 $$$
Distracted Driving High-Visibil ity Cell Phone Enforcement 4 $$$ Motorcycle Safety
Motorcycle Rider Training 2 $$
Strategies to Increase Rider Conspicuity and Use of
Protective Clothing 1 Varies
Alcohol-Impaired Motorcyclists: Detection,
Enforcement, and Sanctions 3 Varies
Young Drivers
Enforcement of Graduated Driver Licensing (GDL) 2 $
Hazard Perception Training 2 Varies
Pedestrian Safety
Lower Speed Limits 4 $
High-Visibility Enforcement at Pedestrian Crossings 3 $$ Pedestrian Safety Zones 4 $$$
Elementary-Age Child Pedestrian Training 3 $
Safe Routes to School 3 $
Bicycle Safety
Promote Bicycle Helmet Use with Education 3 $$$
Safe Routes to School 3 $
Bicycle Safety Education for Children 2 $
Cycling Skills Clinics, Bike Fairs, Bike Rodeos 1 $
Source: National Highway Traffic Safety Administration Countermeasures That Work.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 31
The evaluation metrics mentioned in Table 5 are described as follows:

Effectiveness:
• 5: Demonstrated to be effective by several high-quality evaluations with consistent results.
• 4: Demonstrated to be effective in certain situations. • 3: Likely to be effective based on balance of evidence from high-quality evaluations. • 2: Limited evaluation evidence, but adheres to principles of human behavior and may be effective if implemented well.
• 1: No evaluation evidence, but adheres to principles of human behavior and may be effective if implemented well.

Cost to implement:
• $$$ Requires extensive new facilities, staff, equipment, or publicity, or makes heavy demands on current resources.
• $$ Requires some additional staff time, equipment, facilities, and/or publicity. • $ Can be implemented with current staff, perhaps with training; limited costs for equipment or facilities.

Given that this report is an LRSP, a Leadership Co mmitment and Goal Setting component is not formally required at this time. However, this commitment will be required as part of a future Safety Action Plan (SAP). This is an official public commitment (i.e., resolution, policy, ordinance) by a high ranking official and/or governing body (i.e., Mayor or City Council) to an eventual goal of zero roadway fatalities and serious injuries. The commitment must include a goal and timeline for eliminating roadway fatalities and serious injuries achieved through one, or both, of the following:

1. The target date for achieving zero roadway fatalities and serious injuries, or

2. A percentage reduction of roadway fatalities and serious injuries by a specific date with an eventual goal of eliminating roadway fatalities and serious injuries.

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | 32

10. NEXT STEPS
For the next five years, the City's needs for road safety will be guided by this living comprehensive safety action plan. The objectives will be tracked and updated as necessary. While longer-term, more expensive projects will be included in the Cathedral City Ca pital Improvement Program (CIP), low-cost, easily implemented projects will be given priority for implementation within the City. Comprehending the forthcoming funding opportunities is crucial for the e ffective execution of these safety initiatives. The majority of the suggested countermeasures would likely be funded by HSIP. Countermeasures, however, can be put into place using other financing sources, such as:

1. The ATP, or Active Transportation Program

2. The program for Congestion Mitigation and Air Quality (CMAQ)

3. Sustainable Communities' Sustainable Transportation Planning Grant

4. Sources of stimulus financing

5. Capital Improvement Program (CIP)
Iteris. Moving smarter, together

Local Roadway Safety Plan Update
City of Cathedral City
Technical Appendix

Submitted to:

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix A
APPENDIX A – INTERSECTION COLLISION PCF
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 21 22 23 24 - Unknown
Driving Or
Bicycling
Under
Influence Of
Alcohol Or
Drug
Impeding
Traffic Unsafe SpeedFollowing Too
Closely
Wrong Side Of
Road
Improper
Passing
Unsafe Lane
Change
Improper
Turning
Automobile
Right-Of-Way
Pedestrian
Right-Of-Way
Pedestrian
Violation
Traffic Signals
And Signs
Hazardous
Parking Lights Brakes Other
Equipment
Other
Hazardous
Violation
Other Than
Driver
Unsafe
Starting Or
Backing
Other
Improper
Driving
Pedestrian or
"Other" Under
the Influence
of Alcohol or
Drug
Fell Asleep NOT STATED
1 RAMON RD DATE PALM DR - 2 - 3 - - - - 2 3 - 1 1 - - - - - - - - - - - 13 2 E PALM CANYON DR CANYON PLZ 1 3 - 1 - - - - 3 - 1 1 - - - - - - - - - - - - 10 3 RAMON RD CROSSLEY RD - - - - - - - - - 5 - 1 1 - - - - - - - - - - - 7 4 E PALM CANYON DR PEREZ RD - - - 2 1 - - - 2 4 - - - - - - - - - - - - - - 9 5 RAMON RD DESERT VISTA RD - - - 1 - - - - 2 4 - - 3 - - - - 1 1 - - - - - 12 6 DATE PALM DR VARNER RD 1 3 - 3 - 1 - - 3 - - - 1 - - - - - - - - - - - 12 7 DATE PALM DR VISTA CHINO - 4 - 5 - - - - - 1 - - 2 - - - - - - - - - - - 13 8 VISTA CHINO AVENIDA QUINTANA - - - 1 - 1 - 1 1 1 - - 3 - - - - - - - - - - - 8 9 DATE PALM DR VICTORIA DR - 1 - 1 - - - - - - - 1 2 - - - - - - - - - - - 5 10LANDAU BL RAMON RD 1 1 - 1 - - - 1 4 2 1 1 - - - - - - - - - - - - 12 11VARNER RD MOUNTAIN VIEW RD - - - 3 - - - - 3 1 - - - - - - - - - - - - - - 7 12LANDAU BL VISTA CHINO - 3 - - 1 - - - 2 3 - - 1 - - - - - - - - - - - 10 13CATHEDRAL CANYON DR E PALM CANYON DR - 3 - 2 - - - - 1 3 1 1 6 - - - - - - - - - - - 17 14RAMON RD CATHEDRAL CANYON DR - 4 - 5 - - - - 1 2 - - 1 - - - - - - - - - - - 13 15RAMON RD WHISPERING PALMS TR - 3 - 2 - - - - - - 1 1 2 - - - - - - - - - - - 9 16CATHEDRAL CANYON DR DINAH SHORE DR - 3 - 6 - - - - 1 2 - - 2 - - - - 1 1 - - - - - 16 17DATE PALM DR MCCALLUM WY - 1 - 1 - - - - - - 1 - 3 - - - - - - - - - - - 7 18VARNER RD EDOM HILL RD - 2 - 4 - - - - 1 - - - - - - - - - - - - - - - 7 19VISTA CHINO HORIZON RD - - - 1 - - - - - 3 - - - - - - - - - - 1 - - - 5 20DATE PALM DR 30TH AV - - - 2 - - - - - - - - 2 - - - - - - - - - - - 4 21RAMON RD DA VALL DR - 1 - - - - - - 3 1 - - - - - - - - - - - - - - 5 22DATE PALM DR BARISTO RD 1 2 - 1 - - - - 1 - 1 - 2 - - - - - - - - - - - 8 23DATE PALM DR DINAH SHORE DR - 1 - - - - - - 4 - - 1 - - - - - - - - - - - - 6 24E PALM CANYON DR MELROSE DR - 2 - - - - - - - 2 - - - - - - - - - - - - - - 4 25PALM DR PAUL RD - 2 - 1 - - - - 1 - - - 1 - - - - - - - - - - - 5 26CATHEDRAL CANYON DR 33RD AV - - - 1 - - - - - 2 - - - - - - - - - - - - - - 3 27DATE PALM DR CONVERSE RD - - - - - - - - - 2 - - - - - - - - - - - - - - 2 28E PALM CANYON DR DATE PALM DR - 3 - 3 - - - - - - - - 1 - - - - - - - - - - - 7 29LANDAU BL MCCALLUM WY - 2 - - - - - - - 2 1 - - - - - - - - - - - - - 5 30RAMON RD CATHEDRAL VILLAGE E - - - - - - - - - - - - 2 - - - - - - - - - - - 3 31E PALM CANYON DR CREE RD - 1 - - - - - - 2 1 - 1 - - - - - - - - - - - - 5 32VISTA CHINO AVENIDA MARAVILLA - - - 1 - - - - - - - - 1 - - - - - - - 1 - - - 3 33CATHEDRAL CANYON DR ORTEGA RD - 1 - - - - - - - 4 - - - - - - - - - - - - - - 5 34CATHEDRAL CANYON DR PEREZ RD - - - - - - - - 1 - - - 1 - - - - - - - - - - - 2 35DATE PALM DR TACHEVAH DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 36E PALM CANYON DR E PALM CANYON DR - - - - - - - - - 1 - - - - - - - - - - - - - - 1 37RAMON RD NEUMA DR - - - 2 - - - - 2 - - 1 - - - - - - - - - - - - 5 38VISTA CHINO AVENIDA LA PAZ - - - - - - - - - 2 - - - - - - - - - - - - - - 2 39DATE PALM DR BUDDY ROGERS AV - 1 - - - 1 - - - - - - 2 - - - - - - - - - - - 4 40DATE PALM DR DAVE KELLEY RD - 2 - 2 - - - - - 1 1 - 2 - - - - - - - - - - - 8 41DATE PALM DR GERALD FORD DR - - - - - - - - - - - - - - - - - - 1 - - - - - 1 42DATE PALM DR MARKET PL - - - - - - - - - - - - 1 - - - - - - - - - - - 1 43DATE PALM DR TORTUGA RD - - - 1 - - - - 1 2 - - - - - - - - - - - - - - 4 44DATE PALM DR CATHEDRAL VILLAGE E - 1 - 1 1 - - - 1 - - - 1 - - - - - - - - - - - 5 45SAN LUIS REY DR MISSION DR - - - 2 - - - - 1 1 - - - - - - - - - - - - - - 4 46CATHEDRAL CANYON DR CORRAL RD - 1 - - - - - - - 1 - - - - - - - - - 1 - - - - 3 47DATE PALM DR 35TH AV - 2 - - - - - - - 1 - - - - - - - - - - - - - - 3 48DATE PALM DR I-10 - 1 - - - - - - 1 1 - - - - - - - - - - - - - - 3 49DATE PALM DR VIA ESTRADA - - - - - 1 - - - 2 - - - - - - - - - - - - - - 3 50E PALM CANYON DR ALLEN AV - 1 - 1 - - - - 1 - - - - - - - - - - - - - - - 3 51E PALM CANYON DR AUTO PARK DR - 1 - - - - - - - - - - - - - 1 - - - - - - - - 2 52E PALM CANYON DR OFFICER JERMAINE GIBSON AV - - - - - - - 1 - - - - - - - - - - - - - - - - 1 53DA VALL DR GERALD FORD DR 2 1 - - - - - - - - - - - - - - - - - - - - - - 4 54PALM DR VARNER RD - - - 2 - - 1 - - 1 - - - - - - - - - - - - - - 4 55DATE PALM DR PEREZ RD - 1 - 1 - - - - - - - - - - - - - - - - - - - - 3 56RAMON RD CANDLEWOOD DR 1 1 - - - - - - - 1 - - - - - - - - - - - - - - 3 57SHIFTING SANDS TR MISSION INDIAN TR - - - - - - - - - - - - 2 - - - - - - - - - - - 2 58VARNER RD BOB HOPE DR 1 - - 1 - - - - 1 - - - - - - - - - - - - - - - 3 59CARMELA DR VISTA CHINO - 1 - - - - - - - - - - - - - - - - - - - - - - 2 60DATE PALM DR ADELINA RD - - - - - - - - 1 1 - - - - - - - - - - - - - - 2 Grand
TotalInt ID CROSS STREET A CROSS STREET B
Intersection Analysis by Primary Collision Factor (Violation Category) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 21 22 23 24 - Unknown
Driving Or
Bicycling
Under
Influence Of
Alcohol Or
Drug
Impeding
Traffic Unsafe SpeedFollowing Too
Closely
Wrong Side Of
Road
Improper
Passing
Unsafe Lane
Change
Improper
Turning
Automobile
Right-Of-Way
Pedestrian
Right-Of-Way
Pedestrian
Violation
Traffic Signals
And Signs
Hazardous
Parking Lights Brakes Other
Equipment
Other
Hazardous
Violation
Other Than
Driver
Unsafe
Starting Or
Backing
Other
Improper
Driving
Pedestrian or
"Other" Under
the Influence
of Alcohol or
Drug
Fell Asleep NOT STATED
Grand
TotalInt ID CROSS STREET A CROSS STREET B
Intersection Analysis by Primary Collision Factor (Violation Category) 61DATE PALM DR CORRAL RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 62DATE PALM DR LOS GATOS RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 63DINAH SHORE DR VAQUERO RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 64DINAH SHORE DR VIA DE ANZA - - - - - - - - - - - - 1 - - - - - - - - - - - 1 65E PALM CANYON DR GOLF CLUB DR - 1 - - - - - - - - - - - - - - - - - - - - - - 2 66E PALM CANYON DR W BUDDY ROGERS AV - - - 1 - - - - - 1 - - - - - - - - - - - - - - 2 67GERALD FORD DR PLUMLEY RD - - - - - - - - - 1 - - 1 - - - - - - - - - - - 2 68LANDAU BL 30TH AV - 1 - - - - - - - - - - - - - - - - - - - - - - 1 69BARISTO RD LANDAU BL - - - - - 1 - - 1 - - - - - - - - - - - - - - - 2 70LANDAU BL TACHEVAH DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 71RAMON RD AVENIDA ALVERA - - - 1 - - - - - 1 - 2 - - - - - - - - - - - - 4 72RAMON RD AVENIDA EL MUNDO - - - 1 - - - - - - - 1 - - - - - - - - - - - - 2 73RAMON RD SAN ELJAY AV - 1 - 1 - - - - - - - - - - - - - - - - - - - - 2 74RAMON RD SAN LUIS REY DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 75RAMON RD VIA CAMPANILE - - - 1 1 - - - - - - - - - - - - - - - - - - - 2 76AVENIDA LA PAZ 30TH AV - - - 1 - - - - 1 - - - - - - - - - - - - - - - 2 7730TH AV SAN ELJAY AV - - - 1 - - - - - - - - - - - - - - - - - - - - 1 78AVENIDA LA GAVIOTA BARISTO RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 79BARISTO RD AVENIDA JUAREZ - 1 - - - - - - - 1 - - - - - - - - - - - - - - 2 80CORRAL RD MONTE VISTA RD - 1 - - - - - - 1 - - - - - - - - - - - - - - - 2 81DATE PALM DR 33RD AV - - - - - - - - - 1 - - - - - - - - - - - - - - 1 82DATE PALM DR EYTEL RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 83DINAH SHORE DR DA VALL DR - - - - - - - - - - - - 2 - - - - - - - - - - - 2 84DINAH SHORE DR PLUMLEY RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 85DINAH SHORE DR VIA ALTAMIRA - - - - - - - - 1 1 - - - - - - - - - - - - - - 2 86E PALM CANYON DR MONTY HALL DR - - - - 1 - - - 1 - - - 1 - - - - - - - - - - - 4 87E PALM CANYON DR PALO VERDE DR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 88E PALM CANYON DR SUNGATE WY - - - - - - - - 1 - - - 1 - - - - - - - - - - - 2 89LANDAU BL DESERT PRINCESS DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 90LANDAU BL VEGA RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 91MCCALLUM WY SAN ELJAY AV - 1 - 1 - - - - - - - - - - - - - - - - - - - - 2 92PEREZ RD CAMPBELL ST - - - - - - - - - - - - - - - - - - - - - - - - 1 93PLAZA DR PEREZ RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 94RAMON RD AVENIDA EL PUEBLO - - - - - - - - - - - - - - - - - - 1 - - - - - 1 95RAMON RD AVENIDA XIMINO - - - - - - - - - 1 - - - - - - - - - - - - - - 1 96RAMON RD MEMORIAL DR - - - - - - - - 1 - - - - - - - - - - - - - - - 1 97SAN ANTONIO DR SAN JOSE DR - - - 1 - - - - 1 - - - - - - - - - - - - - - - 2 9833RD AV SHIFTING SANDS TR - 1 - - - - - - 1 - - - - - - - - - 1 - - - - - 3 99VICTORIA DR EAGLE CANYON DR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 100WHISPERING PALMS TR MCCALLUM WY - 1 - - - - - - - - - - - - - - - - - - - - - - 1 10133RD AV WISHING WELL TR - - - - - - - - - 1 - - - - - - - - - - - - - - 1 10230TH AV ALEXANDER DR - - - - - - - - - 1 - - - - - - - - - - - - - - 1 10333RD AV CAMPUS LN - - - - - - - - - 1 - - - - - - - - - - - - - - 1 10434603 PLUMLEY RD VICTORIA DR - - - - - - - - - - - - - - - - - - - - 1 - - - 1 10535TH AV CORREGIDOR DR - - - - - - - - 1 - - - - - - - - - - - - - - - 1 106AURORA VISTA RD RAMON RD - - - - - - - - - - - - - - - - - - - - - - - - 1 107AVENIDA DEL YERMO ALISO RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 108AVENIDA LA PAZ SANTELMO RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 109AVENIDA LA VISTA CONCEPCION RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 110AVENIDA MARAVILLA JOAQUINE WY - 1 - - - - - - - - - - - - - - - - - - - - - - 1 111AVENIDA MARAVILLA TORTUGA RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 112AVENIDA QUINTANA VERONA RD - - - - - - - - - - - - - - - - - - - - - - - - 1 113BANKSIDE DR COMMERCIAL RD 1 - - - - - - - - - - - - - - - - - - - - - - - 1 114BARISTO RD AVENIDA EL MUNDO - - - - - 1 - - - - - - - - - - - - - - - - - - 1 115BARISTO RD AVENIDA EL PUEBLO - - - - - - 1 - - - - - - - - - - - - - - - - - 1 116BOB HOPE DR I-10 1 - - - - - - - - - - - - - - - - - - - - - - - 1 117CATHEDRAL CANYON DR CALLE TRUJILLO - - - 1 - - - - - - - - - - - - - - - - - - - - 1 118CATHEDRAL CANYON DR OFFICER DAVID VASQUEZ RD - - - - - - - - - - - - 1 - - - - - - - - - - - 1 119CONVERSE RD CORREGIDOR DR 1 - - - - - - - - - - - - - - - - - - - - - - - 1 120CORRAL RD AURORA VISTA RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 21 22 23 24 - Unknown
Driving Or
Bicycling
Under
Influence Of
Alcohol Or
Drug
Impeding
Traffic Unsafe SpeedFollowing Too
Closely
Wrong Side Of
Road
Improper
Passing
Unsafe Lane
Change
Improper
Turning
Automobile
Right-Of-Way
Pedestrian
Right-Of-Way
Pedestrian
Violation
Traffic Signals
And Signs
Hazardous
Parking Lights Brakes Other
Equipment
Other
Hazardous
Violation
Other Than
Driver
Unsafe
Starting Or
Backing
Other
Improper
Driving
Pedestrian or
"Other" Under
the Influence
of Alcohol or
Drug
Fell Asleep NOT STATED
Grand
TotalInt ID CROSS STREET A CROSS STREET B
Intersection Analysis by Primary Collision Factor (Violation Category) 121CORRAL RD NAVAJO TR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 122CORRAL RD RANCHO VISTA DR - - - - - - - - - - 1 - - - - - - - - - - - - - 1 123CORREGIDOR DR DINAH SHORE DR - - - - - - - - - - 1 - - - - - - - - - - - - - 1 124DA VALL DR SUNNY LN - - - - - - - - 1 - - - - - - - - - - - - - - - 1 125DATE PALM DR 2113857E - - - 1 - - - - - - - - - - - - - - - - - - - - 1 126DATE PALM DR EDISON POLE #2207518E - 1 - - - - - - - - - - - - - - - - - - - - - - 1 127DATE PALM DR POLE# 2113856E - - - 1 - - - - - - - - - - - - - - - - - - - - 1 128DINAH SHORE DR EDISON POLE #4290039E - - - 1 - - - - - - - - - - - - - - - - - - - - 1 129E PALM CANYON DR MARGOT MURPHY WAY - - - - - - - - 1 - - - - - - - - - - - - - - - 1 130E ST F ST - - - - - - - - 1 - - - - - - - - - - - - - - - 1 131RAMON RD EL TORO RD - - - - - - - - 1 - - - 1 - - - - - - - - - - - 2 132HORIZON RD PANORAMA RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 133KATHY DR VICKI LN - 1 - - - - - - - - - - - - - - - - - - - - - - 1 134MCCALLUM WY AVENIDA ALVERA - - - - - - - - - - - - 1 - - - - - - - - - - - 1 135MISSION DR MISSION DR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 136NORTH PALM CANYON DR VIA OLIVERA - - - - - - - - 1 - - - - - - - - - - - - - - - 1 137ORTEGA RD PUEBLO TR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 138PASADA RD VALENCIA ST - 1 - - - - - - - - - - - - - - - - - - - - - - 1 139PLAZA DR PLAZA DR - - - - - - - - - - - - - - - - - - - - - - - - 1 140PUEBLO TR 33RD AV - - - - - - - - - 1 - - - - - - - - - - - - - - 1 141QUIJO RD ABRIL DR - - - - - - - - 1 - - - - - - - - - - - - - - - 1 142RAMON RD AVENIDA VALDEZ - - - - - - - - - - - 1 - - - - - - - - - - - - 1 143RAMON RD DESERT VIEW RD - - - - - - - - - - - - 1 - - - - - - - - - - - 1 144RAMON RD RATTLER RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 145RAMON RD SHIFTING SANDS TR - - - - - - - - - - 1 - - - - - - - - - - - - - 1 146RIO VISTA DR RIO COLORADO RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 147ROCHESTER RD FLORAL GROVE - - - - - - - - 1 - - - - - - - - - - - - - - - 1 148SAN ELJAY AV DORAL WY - - - - - 1 - - - - - - - - - - - - - - - - - - 1 149SANTIAGO RD VALENCIA ST - - - 1 - - - - - - - - - - - - - - - - - - - - 1 150SANTORO DR 30TH AV - - - - - - - - - - 1 - - - - - - - - - - - - - 1 151SANTORO DR CYPRESS RD - - - - - - - - - - - - 1 - - - - - - - - - - - 1 152SANTORO DR TORTUGA RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 153SARAH ST CROSSLEY RD - - - - - - - - - - - 1 - - - - - - - - - - - - 1 154VAQUERO RD 35TH AV - 1 - - - - - - - - - - - - - - - - - - - - - - 1 155VARDON CT BOB HOPE DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 156VARNER RD EDISON POLE #16320E - - - - - - - 1 - - - - - - - - - - - - - - - - 1 157VARNER RD EDISON POLE 1632223E - - - - - - - - 1 - - - - - - - - - - - - - - - 1 158VARNER RD EDISON POLE 4629849E - - - - - 1 - - - - - - - - - - - - - - - - - - 1 159VERONA RD NORTADA DR - - - - - - - - 1 - - - - - - - - - - - - - - - 1 160VIA DE ANZA CEDAR RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 161VICTORIA DR MARCIA RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 162VISTA CHINO AVENIDA TERRAZO - - - - - 1 - - - - - - - - - - - - - - - - - - 1 163VISTA CHINO VAL YERMO TR - - - - - 1 - - - - - - - - - - - - - - - - - - 1 164WHISPERING PALMS TR CORTA RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 11 83 - 87 5 10 2 4 69 84 12 15 57 - - 1 - 2 5 1 3 - - - 464Grand Total Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix B
APPENDIX B – CORRIDOR COLLISION PCF
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 21 22 23 24 - Unknown
Driving Or
Bicycling
Under
Influence Of
Alcohol Or
Drug
Impeding
Traffic Unsafe SpeedFollowing Too
Closely
Wrong Side Of
Road
Improper
Passing
Unsafe Lane
Change
Improper
Turning
Automobile
Right-Of-Way
Pedestrian
Right-Of-Way
Pedestrian
Violation
Traffic Signals
And Signs
Hazardous
Parking Lights Brakes Other
Equipment
Other
Hazardous
Violation
Other Than
Driver
Unsafe
Starting Or
Backing
Other
Improper
Driving
Pedestrian or
"Other" Under
the Influence
of Alcohol or
Drug
Fell Asleep NOT STATED
1 DATE PALM DR 1 18 - 19 1 3 - - 10 16 3 3 17 - - - - - 1 - - - - - 94 2 RAMON RD 1 10 - 12 1 - - 1 13 14 2 8 10 - - - - 1 1 - - - - - 75 3 E PALM CANYON DR 1 16 - 8 2 - - 1 12 9 1 3 5 - - 1 - - - - - - - - 61 4 CROSSLEY RD - - - - - - - - - - - - 1 - - - - - - - - - - - 1 5 DESERT VISTA RD - - - - - - - - - 1 - - - - - - - - - - - - - - 1 6 AVENIDA DEL YERMO - - - - - - - - - 1 - - - - - - - - 1 - - - - - 2 7 VARNER RD 2 3 - 10 - 1 - 1 7 1 - - 1 - - - - - - - - - - - 26 8 VISTA CHINO - 3 - 5 1 3 - 1 1 9 - - 5 - - - - - - - 2 - - - 31 9 LANDAU BL - 6 - 2 - 1 - - 4 2 2 - - - - - - - - - - - - - 17 10 CATHEDRAL CANYON DR- 2 - 7 - - - - - 13 1 - 6 - - - - 1 1 1 - - - - 32 11 AVENIDA MARAVILLA - 1 - - - - - - - 2 - - - - - - - - - - - - - - 3 12 WHISPERING PALMS TR - 3 - 1 - - - - - 1 - - 1 - - - - - - - - - - - 6 13 DINAH SHORE DR - 4 - 5 - - - - 3 2 - - 5 - - - - - - - - - - - 19 14 PALM DR - 2 - 2 - - 1 - 1 1 - - 1 - - - - - - - - - - - 8 15 ORTEGA RD - 3 - - - - - - - 1 - - - - - - - - - - - - - - 4 16 PEREZ RD - - - 1 - - - - 1 - - - - - - - - - - - - - - - 4 17 NEUMA DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 18 DAVE KELLEY RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 19 TORTUGA RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 20 VIA OLIVERA - - - - - - - - 1 - - - - - - - - - - - - - - - 1 21 SAN LUIS REY DR - - - 2 - - - - 1 1 - - - - - - - - - - - - - - 4 22 DA VALL DR 1 - - - - - - - 1 - - - - - - - - - - - - - - - 2 23 GERALD FORD DR 1 1 - - - - - - - 1 - - 1 - - - - - - - - - - - 5 24 CANDLEWOOD DR 1 - - - - - - - - - - - - - - - - - - - - - - - 1 25 SHIFTING SANDS TR - 1 - - - - - - - - - - 2 - - - - - 1 - - - - - 4 26 CARMELA DR - - - - - - - - - - - - - - - - - - - - - - - - 1 27 BARISTO RD - 1 - - - 1 1 - 1 1 - - - - - - - - - - - - - - 5 28 SAN ELJAY AV - - - 1 - 1 - - - - - - - - - - - - - - - - - - 2 29 AVENIDA LA PAZ - - - 1 - - - - - 1 - - - - - - - - - - - - - - 2 30 30TH AV - - - 1 - - - - 1 1 - - - - - - - - - - - - - - 3 31 AVENIDA LA GAVIOTA - - - 1 - - - - - - - - - - - - - - - - - - - - 1 32 CORRAL RD - 1 - 1 - - - - 1 1 1 - - - - - - - - - - - - - 5 33 MCCALLUM WY - 1 - 1 - - - - - - - - 1 - - - - - - - - - - - 3 34 PLAZA DR - - - - - - - - 1 - - - - - - - - - - - - - - - 2 35 SAN ANTONIO DR - - - 1 - - - - 1 - - - - - - - - - - - - - - - 2 36 33RD AV - - - - - - - - 1 2 - - - - - - - - - - - - - - 3 37 VICTORIA DR - 1 - - - - - - 1 - - - - - - - - - - - - - - - 2 38 34603 PLUMLEY RD - - - - - - - - - - - - - - - - - - - - 1 - - - 1 39 35TH AV - - - - - - - - 1 - - - - - - - - - - - - - - - 1 40 AURORA VISTA RD - - - - - - - - - - - - - - - - - - - - - - - - 1 41 AVENIDA LA VISTA - - - - - - - - - 1 - - - - - - - - - - - - - - 1 42 AVENIDA QUINTANA - - - - - - - - - - - - - - - - - - - - - - - - 1 43 BANKSIDE DR 1 - - - - - - - - - - - - - - - - - - - - - - - 1 44 BOB HOPE DR 1 - - - - - - - - - - - - - - - - - - - - - - - 1 45 CONVERSE RD 1 - - - - - - - - - - - - - - - - - - - - - - - 1 46 CORREGIDOR DR - - - - - - - - - - 1 - - - - - - - - - - - - - 1 47 E ST - - - - - - - - 1 - - - - - - - - - - - - - - - 1 48 EL TORO RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 49 HORIZON RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 50 KATHY DR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 Grand
Total
Corridor Analysis by Primary Collision Factor (Violation Category) Corridor#
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 21 22 23 24 - Unknown
Driving Or
Bicycling
Under
Influence Of
Alcohol Or
Drug
Impeding
Traffic Unsafe SpeedFollowing Too
Closely
Wrong Side Of
Road
Improper
Passing
Unsafe Lane
Change
Improper
Turning
Automobile
Right-Of-Way
Pedestrian
Right-Of-Way
Pedestrian
Violation
Traffic Signals
And Signs
Hazardous
Parking Lights Brakes Other
Equipment
Other
Hazardous
Violation
Other Than
Driver
Unsafe
Starting Or
Backing
Other
Improper
Driving
Pedestrian or
"Other" Under
the Influence
of Alcohol or
Drug
Fell Asleep NOT STATED
Grand
Total
Corridor Analysis by Primary Collision Factor (Violation Category) Corridor#
51 MISSION DR - 1 - - - - - - - - - - - - - - - - - - - - - - 1 52 NORTH PALM CANYON DR- - - - - - - - 1 - - - - - - - - - - - - - - - 1 53 PASADA RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 54 PUEBLO TR - - - - - - - - - 1 - - - - - - - - - - - - - - 1 55 QUIJO RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 56 RIO VISTA DR - - - 1 - - - - - - - - - - - - - - - - - - - - 1 57 ROCHESTER RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 58 SANTIAGO RD - - - 1 - - - - - - - - - - - - - - - - - - - - 1 59 SANTORO DR - 1 - - - - - - - - 1 - 1 - - - - - - - - - - - 3 60 SARAH ST - - - - - - - - - - - 1 - - - - - - - - - - - - 1 61 VAQUERO RD - 1 - - - - - - - - - - - - - - - - - - - - - - 1 62 VARDON CT - - - 1 - - - - - - - - - - - - - - - - - - - - 1 63 VERONA RD - - - - - - - - 1 - - - - - - - - - - - - - - - 1 64 VIA DE ANZA - - - - - - - - - 1 - - - - - - - - - - - - - - 1 11 83 - 87 5 10 2 4 69 84 12 15 57 - - 1 - 2 5 1 3 - - - 464Grand Total Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix C
APPENDIX C – PROJECT CONCEPTUAL LOCATION

IMPROVEMENT PLAN SHEETS
Draft Report
Local Roadway Safety Plan Update

Iteris, Inc. | Appendix C

Project 1: Cathedral City Intersection Safety Program

Cathedral Canyon Drive/East Palm Canyon Drive
Cathedral City Intersection Safety Program
Project 1-A
Update signal timing with protected northbound/southbound left-turn phases
Recommended Improvements:
1 Automobile Right-of-Way (3 collisions)
D.U.I (3 collisions)
Traffic Signals and Signs (6 collisions)
Primary Collision Factor:

Complaint of Pain: 14
Other Visible Injury: 4
Severe Injury: 2
Fatal Injury: 1
17 Collisions from January 2020 to December 2024
1 City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Cathedral Canyon Dr
East P
alm Cany
on Dr
Date Palm Drive/Victoria Drive
Cathedral City Intersection Safety Program
Project 1-B
Move westbound stop line closer to the intersection
to improve the sight line and improve crosswalk on the east leg Recommended Improvements:
1 1
Traffic Signals and Signs (2 collisions)
Primary Collision Factor:

Complaint of Pain: 5
Other Visible Injury: 2
Severe Injury: 1
Fatal Injury: 1
5 Collisions from January 2020 to December 2024
Move westbound stop line and crosswalk closer to the intersection City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
Victoria Dr
Cathedral Canyon Drive/33rd Avenue
Cathedral City Intersection Safety Program
Project 1-C
Add intersection lighting2
Convert the intersection from Two-Way Stop
Control to All-Way Stop Control1
Recommended Improvements:
22 22
1 Automobile Right-of-Way (2 collisions)
Primary Collision Factor:

Complaint of Pain: 4
Other Visible Injury: 1
Severe Injury: 1
Fatal Injury: 1
3 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Cathedral Canyon Dr
33rd Ave
Vista Chino/Landau Boulevard
Cathedral City Intersection Safety Program
Project 1-D
Install raised median on the west leg and east leg1
Recommended Improvements:

Install raised median1
Install raised median1
Improper Turning (2 collisions)
D.U.I (3 collisions)
Automobile Right-of-Way (3 collisions)
Primary Collision Factor:

Complaint of Pain: 11
Other Visible Injury: 6
Severe Injury: 2
Fatal Injury: 0
10 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Landau Blvd
Vista Chino
East Palm Canyon Drive/Perez Road
Cathedral City Intersection Safety Program
Project 1-E
Convert the two-way left turn lane (TWLTL) on the west leg to prohibit turns (not raised median for emergency services access) 1 Recommended Improvements:
1 Improper Turning (2 collisions)
Unsafe Speed (2 collisions)
Automobile Right-of-Way (4 collisions)
Primary Collision Factor:

Complaint of Pain: 6
Other Visible Injury: 4
Severe Injury: 1
Fatal Injury: 0
9 Collisions from January 2020 to December 2024
Prohibit turns in the center median
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Perez Road
East Palm Canyon Drive
Varner Road/Mountain View Road
Cathedral City Intersection Safety Program
Project 1-F
Add guardrail along the northeast corner for westbound
right turn movements
2 Add “WATCH FOR ONCOMING TRAFFIC” warning sign1
Recommended Improvements:

Improper Turning (3 collisions)
Unsafe Speed (3 collisions)
Primary Collision Factor:

Complaint of Pain: 6
Other Visible Injury: 3
Severe Injury: 0
Fatal Injury: 0
7 Collisions from January 2020 to December 2024
2 2
1 City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Varner Rd
Mountain View R
d
Date Palm Drive/McCallum Way
Cathedral City Intersection Safety Program
Project 1-G
Modify signal phasing to implement a leading pedestrian interval (LPI)
2 Update signal timing with protected eastbound/westbound left turn phases
1 Recommended Improvements:
2 1
1 Traffic Signals and Signs (3 collisions)
Primary Collision Factor:

Complaint of Pain: 7
Other Visible Injury: 1
Severe Injury: 0
Fatal Injury: 0
7 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
McCallum Way
San Luis Rey Drive/Mission Drive
Cathedral City Intersection Safety Program
Project 1-H
Install flashing beacons for the “STOP” sign for all approaches2 Install dynamic/variable speed warning signs1
Recommended Improvements:
2 2
2 2
1 1
1 1
Unsafe Speed (2 collisions)
Primary Collision Factor:

Complaint of Pain: 4
Other Visible Injury: 1
Severe Injury: 0
Fatal Injury: 0
4 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
San Luis Rey Drive
Mission Drive
Draft Report
Local Roadway Safety Plan Update

Iteris, Inc. | Appendix C

Project 2: Ramon Road Safety Improvements

Ramon Road/Whispering Palms Trail
Ramon Road Safety Improvements
Project 2-A
Prohibit on-street parking along the west side of Whispering Palms Trail, south of Ramon Road
2 Modify signal phasing to implement a leading pedestrian interval (LPI)1 Recommended Improvements:
2 1
Unsafe Speed (2 collisions)
Traffic Signals and Signs (2 collisions)
D.U.I (3 collisions)
Primary Collision Factor:

Complaint of Pain: 10
Other Visible Injury: 4
Severe Injury: 1
Fatal Injury: 1
9 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Whispering Palms Trail
Ramon Rd
Ramon Road/Crossley Road
Ramon Road Safety Improvements
Project 2-B
Prohibit on-street parking along the east side of Crossley Road, north of Ramon Road
1 Recommended Improvements:

Automobile Right-of-Way (5 collisions)
Primary Collision Factor:

Complaint of Pain: 7
Other Visible Injury: 4
Severe Injury: 1
Fatal Injury: 1
7 Collisions from January 2020 to December 2024
Prohibit parking along the east side of Crossley Road1
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Crossley Rd
Ramon Rd
Ramon Road/Cathedral Canyon Drive/Avenida Maravilla
Ramon Road Safety Improvements
Project 2-C
Modify signal phasing to implement a leading
pedestrian interval (LPI)
3 Install dynamic/variable speed warning signs for the
northbound approach
2 Improve the sight line for northbound approach with
raised pavement marker and striping
1 Recommended Improvements:
3 2
1 Automobile Right-of-Way (2 collisions)
D.U.I (4 collisions)
Unsafe Speed (5 collisions)
Primary Collision Factor:

Complaint of Pain: 17
Other Visible Injury: 3
Severe Injury: 5
Fatal Injury: 0
13 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Cathedral Canyon Drive
Ramon Road
Avenida
Maravilla
Ramon Road/Date Palm Drive
Ramon Road Safety Improvements
Project 2-D
Modify signal phasing to implement a leading pedestrian interval (LPI)
Improve sight line at the north leg for gas station
driveway egress movements
Update signal timing for more clearance time
Recommended Improvements:
3 2
1 Improper Turning (2 collisions)
Unsafe Speed (3 collisions)
Automobile Right-of-Way (3 collisions)
Primary Collision Factor:

Complaint of Pain: 12
Other Visible Injury: 5
Severe Injury: 1
Fatal Injury: 0
13 Collisions from January 2020 to December 2024
3 2
1 City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
Ramon Rd
Ramon Road/Desert Vista Road/Avenida Del Yermo
Ramon Road Safety Improvements
Project 2-E
Modify signal phasing to implement a leading pedestrian interval (LPI)
Remove raised median on Ramon Road between
Avenida Del Yermo and Desert Vista Road, shift eastbound stop line to the west side of Avenida Del Yermo
Implement split phasing for northbound and southbound
movements, add protected phasing for eastbound left turns Modify the intersection to a four-leg signalized intersection, with Avenida Del Yermo being the north leg and
Desert Vista Road being the south leg
Recommended Improvements:
4 3
2 1
Automobile Right-of-Way (4 collisions)
Primary Collision Factor:

Complaint of Pain: 12
Other Visible Injury: 2
Severe Injury: 0
Fatal Injury: 0
12 Collisions from January 2020 to December 2024
Add protected left turn phasing
Remove raised median
4 4
3 2
2 1
Traffic Signal and Signs (3 collisions)
Improper Turning (2 collisions)
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Desert Vista Rd
Ramon Rd
Avenida Del Yermo
Ramon Road Corridor
Ramon Road Safety Improvements
Project 2-F
Modify signal phasing to implement a leading
pedestrian interval (LPI)
2 Install Class IV bicycle lanes1
Recommended Improvements:
2 1
1 Automobile Right-of-Way (14 collisions)
Improper Turning (13 collisions)
Unsafe Speed (12 collisions)
Primary Collision Factor:

Complaint of Pain: 41
Other Visible Injury: 16
Severe Injury: 12
Fatal Injury: 6
75 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Cathedral Canyon Drive
Ramon Road
Avenida
Maravilla
Draft Report
Local Roadway Safety Plan Update

Iteris, Inc. | Appendix C

Project 3: Date Palm Safety Improvements

Date Palm Drive/35th Avenue
Date Palm Safety Improvements
Project 3-A
Add street lights in blocks north and south of the intersection3 Add marked crosswalks on the south leg and east leg2
Install traffic signal at the intersection, add protected phasing for southbound left turns
1 Recommended Improvements:
3 33
3 2
1 D.U.I (2 collisions)
Primary Collision Factor:

Complaint of Pain: 2
Other Visible Injury: 0
Severe Injury: 0
Fatal Injury: 1
3 Collisions from January 2020 to December 2024
Add marked crosswalk on the south leg and east leg
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
35th Avenue
Date Palm Drive/Tachevah Drive
Date Palm Safety Improvements
Project 3-B
Install traffic signal at the intersection, add
protected phasing for northbound left turns
Recommended Improvements:
1 1
Unsafe Speed (1 collision)
Primary Collision Factor:

Complaint of Pain: 0
Other Visible Injury: 0
Severe Injury: 0
Fatal Injury: 1
1 Collision from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
Tachevah Dr
Date Palm Drive/Vista Chino
Date Palm Safety Improvements
Project 3-C
Install dynamic/variable speed warning signs2
Improve signal timing for EBL/SBR movement1
Recommended Improvements:
2 2
1 Traffic Signals and Signs (2 collisions)
D.U.I (4 collisions)
Unsafe Speed (5 collisions)
Primary Collision Factor:

Complaint of Pain: 8
Other Visible Injury: 6
Severe Injury: 2
Fatal Injury: 0
13 Collisions from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Date Palm Dr
Vista Chino
Draft Report
Local Roadway Safety Plan Update

Iteris, Inc. | Appendix C

Project 4: Santoro Drive Bicycle Lanes and Traffic Calming Elements

Santoro Drive/Cypress Road
Santoro Drive Bicycle Lanes and Traffic Calming Elements Project 4
Include traffic calming elements for signing and striping4 Convert Two-Way Stop Control to All-Way Stop Control3
Add bike lane pavement marking2
Install Class II bike lane along both sides of Santoro Drive, between 30th Avenue and McCallum Way
1 Recommended Improvements:
4 4
3 3
3 3
2 2
1 1
Traffic Signals and Signs (1 collision)
Primary Collision Factor:

Complaint of Pain: 1
Other Visible Injury: 0
Severe Injury: 0
Fatal Injury: 0
1 Collision from January 2020 to December 2024
City of Cathedral City
Local Roadway Safety Plan
N

NOT TO SCALE
Santoro Drive
Cypress Road
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix D
APPENDIX D – PROJECT COST ESTIMATES
Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix D

Table D-1: Cathedral City Intersection Safety Program

Location No. Item Description Unit Quantity Unit
Cost Total Cost

Cathedral Canyon
Drive/ East Palm
Canyon Drive
1A Update signal timing with protected NB/SB left turn phases EA 1 $ 200,000 $200,000
Date Palm Drive/
Victoria Drive
1B-1 Move westbound stop line closer to the inters ection by removing striping LF 200 $3.00 $600 1B-2 Install new striping to improve sight line an d crosswalk on the east leg LF 200 $7.00 $1,400 1B-3 Modify signal phasing to implement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000 Cathedral Canyon
Drive/ 33rd Avenue
1C-1 Install new signs for all-way stop control EA 8 $598 $4,784 1C-2 Install new striping for all-way stop control LF 200 $7.00 $1,400 1C-3 Add street lights in blocks north and south of the intersection LS 1 $238,050 $238,050 Vista Chino/ Landau
Boulevard 1D Install raised median on the west leg and east leg SF 1,500 $75 $112,500

East Palm Canyon
Drive/ Perez Road 1E Convert the two-way left turn lane (TWLTL) on the west leg to prohibit turns (not raised median for emergency services access) SF 1,000 $75 $75,000 Mountain View Road/
Varner Road
1F-1 Add “WATCH FOR ONCOMING TRAFFIC” sign EA 1 $598 $598 1F-2 Add guardrail along the northeast corner for west bound right turn movements LF 200 $50.00 $10,000 Date Palm Drive/
McCallum Way
1G-1 Update signal timing with pr otected eastbound/westbound left turn phases EA 1 $200,000 $200,000 1G-2 Modify signal phasing to implement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000 San Luis Rey Drive/
Mission Drive
1H-1 Install dynamic/variable speed wa rning signs EA 4 $6,000 $24,000 1H-2 Install flashing beacons for the “STOP” sign for all approaches EA 1 $130,901 $130,901 Total Construction Cost $1,013,233
Soft Cost 150% $1,519,850
Total Cost (including contingencies) $2,533,083

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix D
Table D-2: Cost Estimate for Ramon Road Safety Improvements

Location No. Item Description Unit Quantity Unit
Cost Total Cost

Ramon Road/
Whispering Palms Trail
2A-1 Modify signal phasing to implement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000

2A-2 Paint red curb to prohibit on-street parking along the west side of Whispering Palms Trail, south of Ramon Road SQFT 200 $10 $2,000
2A-3 Install "NO PARKING ANY TIME" signs EA 2 $600 $1,200

Ramon Road/ Crossley
Road
2B-1 Paint red curb to prohibit on-street parking along the east side of Crossley Road, north of Ramon Road SQFT 400 $10 $4,000
2B-2 Install "NO PARKING ANY TIME" signs EA 3 $600 $1,800 Ramon Road/ Avenida
Maravilla/ Cathedral
Canyon Drive
2C-1 Improve the sight line for northbound approach with raised pavement marker and striping SF 600 $75 $45,000
2C-2 Install dynamic/variable speed warning signs fo r the northbound approach EA 2 $6,000 $12,000 2C-3 Modify signal phasing to im plement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000 Ramon Road/ Date
Palm Drive
2D-1 Update signal timing for more cl earance time EA 1 $15,000 $15,000 2D-2 Improve sight line at the north leg for gas st ation driveway egress movements EA 2 $261 $522 2D-3 Modify signal phasing to im plement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000

Ramon Road/ Desert
Vista Road
2E-1 Modify the intersection to a four-leg signalized intersection, remove striping LF 100 $3.00 $300 2E-2 Add new striping for the four-leg signalized intersection LF 100 $7.00 $700 2E-3 Implement split phasing for northbound and southbound movements EA 1 $200,000 $200,000 2E-4 Add protected phasing for eastbound left turns EA 1 $200,000 $200,000

2E-5 Remove raised median on Ramon Road between Avenida Del Yermo and Desert Vista Road, shift eastbound stop line to the west side of Avenida Del Yermo SF 200 $75 $15,000 2E-6 Modify signal phasing to im plement a leading pedestrian interval (LPI) EA 1 $7,000 $7,000

Ramon Road Bicycle
Lanes 2F Install Class IV bicycle lanes MI 2.75 $500,000 $1,375,000 Total Construction Cost $1,900,522
Soft Cost 150% $2,850,783
Total Cost (including contingencies) $4,751,306

Draft Report
Local Roadway Safety Plan Update
Iteris, Inc. | Appendix D

Table D-3: Cost Estimate for Date Palm Drive Safety Improvements

Location No. Item Description Unit Quantity Unit
Cost Total Cost

Date Palm Drive/ 35th
Avenue
3A-1 Install traffic signal at the intersection EA 1 $600,000 $600,000 3A-2 Add protected phasing for southbound left turns EA 1 $200,000 $200,000 3A-3 Add marked crosswalks on the south leg and east leg EA 2 $10,000 $20,000 3A-4 Add street lights in blocks north and south of the intersection LS 1 $238,050 $238,050 Date Palm Drive/
Tachevah Drive
3B-1 Install traffic signal at the intersection EA 1 $600,000 $600,000 3B-2 Add protected phasing for northbound left turns EA 1 $200,000 $200,000 Date Palm Drive/ Vista
Chino
3C-1 Improve signal timing for eastbound left turns and southbound right turns EA 1 $15,000 $15,000 3C-2 Install dynamic/variable speed warning signs EA 4 $6,000 $24,000 Total Construction Cost $1,897,050
Soft Cost 150% $2,845,575
Total Cost (including contingencies) $4,742,626

Table D-4: Cost Estimate for Santoro Drive/Cypress Road

Location No. Item Description Unit Quantity Unit
Cost
Total
Cost

Santoro Drive/ Cypress
Road
4-1 Install "BIKE LANE" signs EA 8 $598 $4,784
4-2
Install Class II bike lane pavement marking along both sides of Santoro, between 30th Ave and McCallum LF 10,400 $7.00 $72,800
4-3 Convert Two-Way Stop Control to All-Way Stop Control with new "STOP" signs EA 8 $598 $4,784 4-4 Install new pavement marking for STOP control LF 400 $7.00 $2,800 Total Construction Cost $85,168
Soft Cost 150% $127,752
Total Cost (including contingencies) $212,920