City Council Update
May 2026

PROJECT OVERVIEW
Ramon Road is one of the
most heavily traveled
corridors in the Coachella
Valley with over 40,000
vehicles daily.

The Ramon Road Bridge at the Whitewater River serves as the gateway between the cities of Palm Springs and Cathedral City, providing critical access for residents, businesses, and commuters.

COMMUNICATIONS & OUTREACH
Be Proactive
 Engage early and often
 Generate local/regional awareness
 Robust stakeholder database
Be Highly Communicative
 Regular updates on our website, e-mail
newsletter, social media
 Press releases
 Live traffic alerts
 Message boards

COMMUNICATIONS & OUTREACH
Be Equitable & Inclusive
 Meet community where they are
o In-person distribution of notices
o Regular updates at PS & CC Council
Meetings
o Community presentations & meetings
Be Prepared & Responsive
 Plan ahead for major events
 Quickly resolve concerns
 Forecast weather-related closures

BUSINESS IS OPEN
Supporting local businesses is a key priority and
our campaign will include:
 Directory of participating businesses on our
website and maps
 Spotlight “feature” of businesses on social
media & construction updates
 Wayfinding signage
 Business Liaison to proactively identify issues
and resolve concerns
 Project goal is to maintain two lanes of traffic in each direction  Maintaining access to all driveways
 Work primarily scheduled during the day with nightwork as needed  Signal timing optimization to support traffic flow
 Hands on proactive construction management team

MINIMIZING CONSTRUCTION DURATION & IMPACTS

OUTREACH TIMELINE
Pre-Construction
Outreach
Spring/Summer 2026 Community
Meetings
Fall 2026 Groundbreaking
Dec 2026
Project
Completion
Dec 2028
On-going Outreach
Dec 2026-Dec 2028

PROJECT WEBSITE
www.RamonRoadBridgeProject.com

FOLLOW US FOR CONSTURCTION

UPDATES & TRAFFIC ALERTS
Project Website: www.RamonRoadBridgeProject.com
24/7 Hotline: (760) 933-9944
Email: [email protected]
Social: @RamonRoadBridge