Staff Report
City Council
Item No.

Meeting Date: October 28, 2026
From: Nishant Seoni, Contract Associate Planner
Title: Foothill Cove PUD (Planned Unit Development) - Request of GHA Companies to subdivide a 7.86-acre lot at Van Fleet and D Streets, into residential lots including private streets, open space, and stormwater retention to construct 75 townhomes; along with a Tentative Tract Map and a Zoning Ordinance Amendment to provide additional flexibility in PUD development standards.

RECOMMENDATION:

Find Zoning Ordinance Amendment 26-0001, Planned Unit Development 25-0001, and Tentative Tract Map 25-0001 exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15162. Introduce an ordinance approving Zoning Ordinance Amendment 25-0002 amending Chapter 9.94 of Title 9 of the Cathedral City Municipal Code to modify setback, parking, and open space requirements in the PUD development standards. Approve a Planned Unit Development and Tentative Tract Map to subdivide an existing 7.86-acre lot into four residential condominium lots and eight lots for private streets, open space, stormwater retention to construct 75 townhomes.

BACKGROUND:

The Applicant (Mario Gonzales/GHA Companies) submitted applications for a Zoning Ordinance Amendment (ZOA), Tentative Tract Map (TTM), and Planned Unit Development (PUD) on December 11, 2025. The TTM (TTM No. 39447) proposes to subdivide the 7.86 acre site into four residential condominium lots and eight lettered lots reserved for streets, open space, and stormwater retention. The PUD proposes the development of 75 residential units clustered in three-unit townhouses.

The ZOA provides additional flexibility in the PUD development standards and supports the intent and purpose of the PUD, which is to facilitate comprehensive and site-responsive development by allowing greater flexibility in design than is possible through the strict application of zoning regulations. The amendment proposes the following modifications to CCMC Sec. 9.94.110:
• Delete the minimum structure and garage setback requirements set forth in Sec.

9.94.110(C);
• Modify Sec. 9.94.110(E) to delete the requirement for residential PUDs to provide an additional one guest parking per unit, and to allow a reduction of up to ten percent of the total required parking for residential PUDs;
• Amend Sec. 9.94.110(G) to allow private yards and patios of at least 50 square feet to satisfy up to 30% of the open space requirement.

The Project site is located immediately south of the Cathedral Cove Center, east of Van Fleet Avenue, and north of D Street. The Project will have a primary gated entry and exit on Van Fleet Avenue, with a secondary entry and exit on D Street.

Previous Approval
In 2022, the adjacent Cathedral Cove Center was approved by the City Council under Planned Unit Development 21-001 and Tentative Parcel Map No. 37876, along with a Mitigated Negative Declaration (MND). These approvals contemplated the subject project site for a future phase of multi-family residential development, which must be approved through a separate entitlement project. That project specified:
• A Tentative Parcel Map, which has been recorded, assembling underlying lots. • 13.93 acres, including 5.8 acres of commercial development and 8.05 acres of multi-family development. • 24,375 square feet of retail commercial development, including fast food restaurants and a gas station with convenience store.
• Up to 200 residential units at 25 units per acre density and with an undetermined layout and design which were to be designed and approved under subsequent entitlement.

The Project addresses the residential component of the prior approved PUD, specifies layout and design, and reduces unit count from 200 to 75 units.

Planning Commission
The Project was presented to the Planning Commission in a public hearing on September 9, 2026. Staff reviewed the site history, proposed amendments, and the previous Architectural Review Committee (ARC) discussion. ARC unanimously approved the project’s architecture and landscaping at its August 5, 2026 meeting.

The Planning Commission asked clarifying questions, and two members of the public spoke in support of the project and one expressed privacy concerns for neighboring residences.

The applicant clarified the Project’s proposed residences will be far enough from neighboring residences to avoid privacy impacts. The Planning Commission recommended to the City Council that Zoning Ordinance Amendment 26-0001, Planned Unit Development 25-0001, and Tentative Tract Map 25-0001 be approved.

DISCUSSION:

Zoning Ordinance Amendment
The ZOA is consistent with the General Plan's residential land use, housing, and neighborhood development policies. It provides flexibility for future PUD developments while maintaining compatibility with surrounding development and supporting thoughtful site design. It does not change permitted uses or allowed density, create land use incompatibilities, or create additional environmental impacts not already analyzed in the Cathedral Cove Mitigated Negative Declaration.

Planned Unit Development, General Plan and Zoning
The Project is designated as DTC (Downtown Commercial) on the City’s General Plan and located within the DRN (Downtown Residential Neighborhood) zoning district. The Project must comply with DRN (CCMC Sec. 9.25) and PUD (CCMC Sec. 9.94) standards and requirements. Further analysis of individual standards and requirements is found in Attachment 8 (September 9, 2026 Planning Commission Staff Report).

Tentative Tract Map
The proposed subdivision is consistent with the site’s General Plan land use designation, prior planned residential development of the site, and applicable development standards.

The site can accommodate the proposed subdivision, and the associated Project accommodates applicable public access, utility, and easement requirements and does not create additional environmental impacts not already analyzed in the Cathedral Cove Mitigated Negative Declaration. The proposed subdivision would not conflict with the Subdivision Map Act.

Public Outreach
The applicant held a Community Engagement Meeting on January 8, 2026, inviting residents to discuss the Project with the City and the Applicant. Residents generally expressed support for the Project and development of the site. Discussion focused on connectivity, security, amenities, sustainability, and housing cost. The applicant described proposed gated access points and lighting, financial feasibility of additional sustainability features, and noted that pricing would be market responsive. The City also informed residents of ongoing plans to improve bicycle, trail, and CV Link connections in the area.

Environmental Review
In accordance with CEQA Guidelines Sec. 15162, no additional CEQA review is required for the Project as there is no substantial evidence in the record that the Project would require “major revisions” to the Cathedral Cove Mitigated Negative Declaration “due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects.”
The Cathedral Cove Center Mitigated Negative Declaration (approved on September 28, 2022) contained the 3 Mitigation Measures listed below, which have also been included as Conditions of Approval.

BIO-1: A qualified biologist shall conduct two (2) take avoidance pre-construction burrowing owl surveys onsite. The first shall occur between 14 and 30 days prior to ground disturbance, and the second shall occur within 24 hours of ground disturbance. If burrowing owls are detected, the project proponent shall consult with California Department of Fish and Wildlife (CDFW) to determine what course of action is needed, such as the use of exclusion devices (if applicable) to discourage owls from using burrows that are believed to be in jeopardy of being impacted by implementation of the project.

BIO-2: For any grubbing, grading or other site disturbance or tree or vegetation removal occurring during the nesting season between January 15 – August 31, a qualified biologist shall conduct at least one nesting bird survey, and more if deemed necessary by the consulting biologist, immediately prior to initiation of project-related ground disturbing activities. If nesting birds are present, no work shall be permitted near the nest(s) until the young birds have fledged. While there is no established protocol for nest avoidance, when consulted, the CDFW generally recommends avoidance buffers of about 500 feet for birds- of-prey, and 100 – 300 feet for songbirds. If ground disturbance occurs outside the nesting season, this requirement shall be waived.

BIO-A: Prior to the issuance of any permit to allow ground disturbance on the site, the Project Proponent shall furnish the City with pre-construction surveys for burrowing owl and Migratory Bird Treaty Act (MBTA) covered birds.

FINDINGS:

FIND THAT NO FURTHER ENVIRONMENTAL REVIEW IS REQUIRED UNDER THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) BASED ON THE FOLLOWING FINDINGS:

1. Pursuant to CEQA Guideline 15162, no additional CEQA review is required for the Project as there is no substantial evidence in the record that the Project would require “major revisions” to the Cathedral Cove Mitigated Negative Declaration “due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects.”

2. The proposed Zoning Ordinance Amendment is consistent with the purpose and intent of Title 9 of the Cathedral City Municipal Code and promotes the public health, safety, convenience and general welfare.

APPROVE ZONING ORDINANCE AMENDMENT 26-0001 TO AMEND CHAPTER 9.94 OF THE CATHEDRAL CITY MUNICIPAL CODE BASED ON THE FOLLOWING FINDINGS:

1. The proposed Zoning Ordinance Amendment is consistent with the goals, policies, and land use designations of the Cathedral City General Plan; and

2. The proposed Zoning Ordinance Amendment is consistent with the purpose and intent of Title 9 of the Cathedral City Municipal Code and promotes the public health, safety, convenience and general welfare.

The proposed Zoning Ordinance Amendment is consistent with the purpose and intent of Title 9 of the Cathedral City Municipal Code and promotes the public health, safety, convenience and general welfare.

APPROVE PLANNED UNIT DEVELOPMENT 25-0001 BASED ON THE FOLLOWING FINDINGS:

1. The Project meets the intent of the Planned Unit Development regulations, to facilitate a comprehensively planned development in accordance with applicable Zoning regulations;

2. The design of the Project uses imaginative and innovative planning by offering lot and unit features and details, community recreational amenities, and open space;

3. The use of the Planned Unit Development provides for more open space, both active and passive, and other pertinent amenities while allowing flexibility with setbacks and parking;

4. The Project is compatible with existing and planned land uses and with circulation patterns on adjoining properties, and will not be a disruptive element to the neighborhood or community;

5. The proposed subdivision is consistent with the DTC (Downtown Commercial) designation of the General Plan and the development standards of the DRN (Downtown Residential Neighborhood) zoning district;

6. The site of the proposed subdivision is physically suitable for the proposed development;

7. The design of the proposed subdivision and the proposed improvements have been mitigated to the extent they will have a less than significant impact on the environment;

8. The design of the proposed subdivision and the required improvements will not conflict with easements acquired by the public at large for access through, or use of, property within the proposed subdivision;

9. There is no substantial evidence in the record the Project would require major revisions to the Cathedral Cove Mitigated Negative Declaration due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; and

10.The applicant agrees to comply with any and all the conditions imposed by the City Council or be subject to a revocation hearing.

APPROVE TENTATIVE TRACT MAP 25-0001 BASED ON THE FOLLOWING FINDINGS:

1. The proposed map is consistent with applicable General and Specific Plans;

2. The design or improvement of the subdivision is consistent with applicable General and Specific Plans;

3. The site is physically suitable for the type of development proposed;

4. The site is physically suitable for the proposed density of development;

5. The design of the subdivision or proposed improvements is not likely to cause substantial environmental damage or substantially and avoidably injure fish, wildlife, or their habitat;

6. The design of the subdivision or type of improvements is not likely to cause serious public health problems; and

7. The design of the subdivision or type of improvements will not conflict with easements acquired by the public for access through or use of property within the proposed subdivision.

FISCAL IMPACT:

Other than costs associated with staff time, implementation of the proposed ordinances will have no fiscal impact.

FIVE-YEAR STRATEGIC PLAN:

Goal F – EMBRACING, INCLUSIVE COMMUNITY
Objective: Cathedral City is valued and respected as a community that welcomes and embraces diversity, has an abundance of high quality and affordable housing options and vibrant businesses. Our neighborhoods are attractive, well-maintained, and issues surrounding homelessness have been compassionately addressed with thoughtful, coordinated, and collaborative programs.

ATTACHMENTS:

Attachment 1 – Draft Ordinance Adopting Zoning Ordinance Amendment 26-0001 Attachment 2 – Tentative Tract Map
Attachment 3 – Conditions of Approval
Attachment 4 – Site Plan
Attachment 5 – Renderings and Elevations
Attachment 6 – Landscape Plans
Attachment 7 – Cathedral Cove Mitigated Negative Declaration Attachment 8 – September 9, 2026 Planning Commission Staff Report