Staff Report
City Council
Item No. 4.A
Meeting Date: November 10, 2026
From: Andres D. Perez, Assistant Engineer
Title: Construction Contract Award for the Tropical Storm Hilary: Vista Chino Pavement Reconstruction Project, City Project No. C08685 RECOMMENDATION:
To award a construction contract to LCR Earthwork & Engineering Corporation in the amount of $245,495.00 for the Tropical Storm Hilary: Vista Chino Pavement Reconstruction Project, City Project No. C08685; and, approve a twenty percent (20%) contingency in the amount of $49,099.00 for unforeseeable construction cost; thereby bringing the total construction budget to the amount of $294,594.00; and, approve the allocation of available Fiscal Year 2026/2027 CalRecycle Grant Funds in the amount of $12,485.00 for the construction of the Project; and, authorize the City Manager to execute the required contract documents; and, authorize the City Engineer to request bonds and insurance for the project and issue the Notice to Proceed.
BACKGROUND:
On August 20, 2023, Tropical Storm Hilary brought heavy rainfall to the Inland Empire region of Southern California. This rainfall resulted in significant offsite regional floodwater consisting of mud and debris, originating approximately 22 miles northeast of Cathedral City limits, which ultimately inundated and ponded throughout the northeastern portion of the Panorama neighborhood. As a result of the debris flow floodwaters, Vista Chino Drive (Vista Chino) was closed to traffic between Panorama Road and Date Palm Drive.
A 1,275-foot segment of Vista Chino, extending west from its intersection with Date Palm Drive, experienced substantial pavement deterioration due to sediment accumulation and subsequent cleanup operations (see Attachment 1 – Vicinity Map). The resulting pavement damage exceeded normal roadway wear and deterioration associated with previous flooding events. The affected roadway segment currently has a Pavement Condition Index (PCI) of 50, indicating pavement conditions at the threshold between fair and poor.
Following Tropical Storm Hilary, the city prepared and submitted a Damage Assessment Form (DAF) to the California Department of Transportation (Caltrans), requesting federal emergency relief funding to restore Vista Chino to its pre-storm condition. Vista Chino is classified as a federal-aid minor arterial roadway by the Federal Highway Administration (FHWA), making it eligible for federal emergency relief funding. Caltrans subsequently approved funding for the project's preliminary engineering (design and environmental) and construction phases. Federal funds administered through FHWA will cover 88.53% of eligible project costs, with the remaining 11.47% provided by the city as the local match.
On May 14, 2025, the City Council approved a professional services agreement with BCR Consulting, LLC, to prepare the environmental documentation required under the National Environmental Policy Act (NEPA) for the federally funded project. The environmental documentation was completed and submitted to Caltrans for review on December 11, 2025, and subsequently approved on May 12, 2026.
Following NEPA clearance, city staff finalized the project plans and specifications and submitted a request to Caltrans for construction funding authorization. On July 26, 2026, Caltrans issued the E-76 Authorization and Finance Letter, approving $431,000 in construction funding consistent with the approved DAF.
In addition to federal emergency relief funding, city staff secured supplemental funding through the California Department of Resources Recycling and Recovery (CalRecycle) Rubberized Pavement Grant Program. On May 1, 2026, the city was awarded a grant of up to $40,425.00 for the use of Asphalt Rubber Hot Mix (ARHM) in eligible pavement improvement projects. Of this amount, $13,200.00 was allocated to the Vista Chino Pavement Reconstruction Project. The CalRecycle grant award is included as Attachment No. 2 to this staff report.
As part of the federal funding requirements, the city also prepared and submitted the right-of-way certification and quality assurance documentation to Caltrans for review. On September 3, 2026, Caltrans approved the documentation, completing the project's preliminary engineering phase and authorizing the city to advertise the project for construction bids.
DISCUSSION:
On September 17, 2026, the city advertised an invitation to bid for Bid No. B26-123E, seeking qualified contractors to perform the work described in the project plans and specifications.
The bid specifications include an additive alternate for lowering and raising to grade Coachella Valley Water District’s (CVWD) facilities. The bid solicitation was available to contractors for twenty-six (26) calendar days and was advertised in the following locations:
• The Desert Sun – published on September 17, 2026, and September 24, 2026 • Planit Print Works - from September 17, 2026, through October 13, 2026 • City’s Website - from September 17, 2026, through October 13, 2026 On October 13, 2026, the city received seven (7) bid proposals. The following table ranks the bidders based on their respective base bid amounts.
Rank Contractor Amount
1 LCR Earthwork & Engineering Corp. – Jurupa Valley, CA $245,495.00 2 Granite Construction Company – Indio, CA $272,272.00
3 Vance Corporation – Beamont, CA $272,319.00
4 All American Asphalt – Corona, CA $274,435.00
5 Hardy & Harper, Inc. – Lake Forest $293,800.00
6 Onyx Paving Company – Yorba Linda, CA $310,000.00
7 Romero General Construction Corp. – Escondido, CA $355,528.00 The bid tabulation prepared by the Engineering Division is included in Attachment No.3.
CVWD reviewed the proposed costs for adjusting its facilities and declined the amount submitted by the lowest bidder, electing instead to perform the work through its own on-call contractor during construction. Accordingly, the city will not proceed with the additive alternate, and the proposed construction contract will be based solely on the base bid.
During the bid evaluation, city staff identified a clerical error in LCR Earthwork & Engineering Corporation's proposal for Bid Item No. 6 (Asphalt Rubber Hot Mix Pavement). The unit price was listed as $1.45 per ton instead of $145.00 per ton. In a letter dated October 20, 2026, the bidder acknowledged the error and provided a corrected bid schedule. The city staff, with city attorney confirmation, determined that the error was immaterial because the correction did not change the total bid amount. The bidder's clarification letter is included as Attachment No. 4 to this staff report.
Based on staff's evaluation of the bid documents, contractor references, and qualifications, LCR Earthwork & Engineering Corporation of Jurupa Valley, California, was determined to be the lowest responsive and responsible bidder, with a base bid of $245,495.00. The contractor has demonstrated the experience and qualifications necessary to complete the project.
Staff recommend that the City Council award a construction contract to LCR Earthwork & Engineering Corporation in the amount of $245,495.00 for the Tropical Storm Hilary: Vista Chino Pavement Reconstruction Project, City Project No. C08685; and, approve a twenty percent (20%) contingency in the amount of $49,099.00 for unforeseeable construction cost; thereby bringing the total construction budget to the amount of $294,594.00; approve the allocation of available Fiscal Year 2026/2027 CalRecycle Grant Funds in the amount of $12,485.00 for the construction of the Project; and, authorize the City Manager to execute the required contract documents; and, authorize the City Engineer to request bonds and insurance for the project and issue the Notice to Proceed.
The Construction Contract with LCR Earthwork & Engineering Corporation is included as Attachment No. 5 to this staff report.
ENVIRONMENTAL ANALYSIS:
The project is categorically excluded under the National Environmental Policy Act (NEPA) process for federally funded projects per 23 CFR 771.117(c): activity (c)(26) and Categorically Exempt under the California Environmental Quality Act (CEQA), Section 15301 for “Existing Facilities”.
FISCAL IMPACT:
Fiscal Year (FY) 2025-2026 and 2026-2027 CIP Biennial Budget The project is included in the city's 5-Year Capital Improvement Program (CIP), with $431,000 programmed for construction in FY 2026-2027. Funding consists of 88.53% from the Federal Highway Administration (FHWA) Emergency Relief funds administered through Caltrans and 11.47% local match provided by the city. The programmed construction funding is summarized below:
Funding Source Percentage Amount
Federal Emergency Relief (Caltrans) 88.53% $381,564.30
Local Match (Cathedral City) 11.47% $49,435.70
Total Programmed Construction Funding 100% $431,000.00
Construction Budget
The proposed construction budget totals $294,594.00, consisting of the lowest responsive and responsible bid of $245,495.00 submitted by LCR Earthwork & Engineering Corporation and a 20% contingency of $49,099.00 to address unforeseen construction costs. The proposed construction budget is summarized below:
Description Amount
Construction Contract - LCR Earthwork & Engineering Corporation. $245,495.00 20% Contingency $49,099.00
Total Construction Budget $294,594.00
Proposed Funding Sources
Staff propose to fund the total construction budget of $294,594.00 through FHWA Emergency Relief funds (88.53%), and the city’s required local match (11.47%) as summarized below:
• Construction Funding Breakdown
Funding Source Amount
Federal Emergency Relief (Caltrans – 88.53%) $260,804.07 Local Match (Cathedral City – 11.47%) $33,789.93
Total Construction Funding $294,594.00
• Local Match Funding Breakdown
The city was awarded $13,200.00 in grant funding through CalRecycle Rubberized Pavement Grant Program for the use of Asphalt Rubber Hot Mix (ARHM) on the project.
Based on the estimated quantity of ARHM to be used, the city anticipates receiving $12,485.00 in grant funds, which can be applied toward the city's required local match.
The required local match of $33,789.93 will be funded through $21,304.93 in City Maintenance of Effort (MOE) funds and $12,485.00 in anticipated grant funding from the CalRecycle Rubberized Pavement Grant Program for the use of Asphalt Rubber Hot Mix (ARHM), as summarized below:
Funding Source Amount
Maintenance of Effort (MOE) funds $21,304.93
CalRecycle Rubberized Pavement Grant Program $12,485.00 Total Local Match $33,789.93
The following table summarizes the budget allocations for the construction of the project.
FISCAL
YEAR DESCRIPTION GENERAL LEDGER ACCOUNT CODES
PROJECT
CODE AMOUNT
ONE TIME
or
ONGOING
2026-
2027
Federal Emergency
Relief (Caltrans) 331-100-150-156-8600-8601 C08685 $260,804.07 One Time 2026-
2027
General Fund (MOE)
(Local Match) 100-100-150-156-8800-8802 C08685 $21,304.93 One Time 2026-
2027 CalRecycle Grant 331-100-150-156-8600-8601 C08685 $12,485.00 One Time Total $294,594.00
FIVE-YEAR STRATEGIC PLAN:
Goal-B: Community Investment
Objective: Cathedral City roads, gateways, public spaces, and other city infrastructure are well planned, designed, constructed, and maintained
ATTACHMENTS:
1. TSH Vista Chino Pavement Reconstruction Project –Vicinity Map
2. CalRecycle 2025-26 Rubberized Pavement Grant Program Award
3. TSH Vista Chino Pavement Reconstruction Project –Bid Tabulation
4. TSH Vista Chino Pavement Reconstruction Project –Bid Clarification Letter
5. TSH Vista Chino Pavement Reconstruction Project –Contract