Read from the councils' own documents — check the source. Each figure was copied from a staff report, budget, financial statement or set of minutes, by a person or by a language model whose quote had to be found word for word in the document. Every figure links to the passage it came from; the city's original file is the official record. Updated 2026-10-20.
6figures
Studies the council was shown
- 2024-09-24 GDS Associates / EES Consulting team (Tenaska, Calpine Energy Solutions, Best Best & Krieger …): — document
Studying, joining or starting a CCA
| Date | CCA | Kind | Figure | What it is | Source |
|---|---|---|---|---|---|
| 2024-09-24 | Study / start-up | $450,000 | The other bidder, Ascend Analytics, proposed a $450,000 study (not selected). | passage · city original | |
| 2024-09-24 | Study / start-up | $120,000 a year · city pays · estimate / proposal | Estimated legal/regulatory consulting cost of $120,000 in the start-up phase (2026 column) for a proposed Fontana CCA, from GDS Associates' conceptual non-power operating cost table. | passage · city original | |
| 2024-09-24 | Study / start-up | $40,000 a year · city pays · estimate / proposal | GDS Associates estimates $40,000 for legal/regulatory consulting in 2025, the post-feasibility phase, as part of non-power costs to form a Fontana CCA. | passage · city original | |
| 2024-09-24 | Study / start-up | $5.47 a year · city pays · estimate / proposal | Estimated 2031 non-power operating cost of a proposed Fontana CCA, about $5.47 per MWh of retail sales, from a consultant proposal; a per-unit estimate, not a city payment. | passage · city original | |
| 2024-09-24 | Study / start-up | $1.50 a month · city pays · estimate / proposal | Estimated 2026 start-up non-power operating cost for a proposed Fontana CCA, about $1.50 per customer per month, to be financed; a rough estimate from a consultant proposal. | passage · city original | |
| 2024-09-24 | Study / start-up | $0.00 | Fontana engages GDS Associates for a no-cost feasibility study of a city-run CCA. | passage · city original |