Staff Report Item 17
Staff Report Item 17
To: Ava Community Energy Authority
From: Sam Sadle, Principal Legislative Manager
Subject
2026 California Legislative Read-Out and Look Ahead
Date: October 21, 2026
__________________________________________________________________ Summary
This is informational and no action is required.

Since 2019, Ava staff has worked to implement the Board-approved Legislative Program. The Legislative Program provides a framework for staff to identify, assess, track, and (with Board approval) take advocacy-related action regarding proposed legislation.

In March and April of this year, the Board took formal positions on 10 bills (descriptions below based on bill contents in March and April).

Support
• Senate Bill 222 (Wiener) - Streamlines permitting for installations of residential heat pump water and HVAC systems;
• Senate Bill 1138 (Padilla) - Allows load serving entities to transact resource adequacy compliance products;
• Senate Bill 1168 (McNerney) - Establishes new surcharges on natural gas consumption by large data centers, with revenues collected to be directed toward wildfire costs currently embedded in customer rates;
• Assembly Bill 1761 (Rogers) Power Charge Indifference Adjustment (PCIA) transparency; and
Staff Report Item 17
• Assembly Bill 2266 (Schultz) - Requires the use of a consistent method across regulatory proceedings for calculating how much reliability value different energy resources provide, so that short-term, mid-term, and long-term procurement programs all count resources the same way.

Support-if-Amended
• Senate Bill 868 (Wiener) - Sets rules for “plug in” or “balcony” solar systems; • Senate Bill 913 (Becker) - Allows aggregated distributed resources to serve as Resource Adequacy capacity;
• Assembly Bill 1577 (Bauer-Kahan) - Requires monthly reporting on data center energy usage;
• Assembly Bill 1975 (Schultz) - Establishes a “grid utilization metric” that calculates load as a percentage of rated distribution capacity; and
• Assembly Bill 2389 (Irwin) - Extends a property tax exemption for customer-sited solar.

Over the course of the 2026 legislative session, Ava staff were able to secure necessary amendments for SB 913 (Becker) and AB 1577 (Bauer-Kahan) and the Agency subsequently moved from a Support-if-Amended posture to a Support position.

Of these 10 bills, the final disposition (and contents of the bills) is as follows:

Signed into law:
• Senate Bill 222 (Wiener) - Streamlines permitting for installations of residential heat pump water and HVAC systems;
• Senate Bill 868 (Wiener) - Sets rules for “plug in” or “balcony” solar systems through January 1, 2030;
• Senate Bill 913 (Becker) - Allows aggregated distributed resources to serve as Resource Adequacy capacity under certain circumstances;
• Senate Bill 1168 (McNerney) - Requires the California Public Utilities Commission (CPUC) to assess opportunities for rate structures to ensure data centers pay their fair share and alleviate cost pressures on residential ratepayers; • Assembly Bill 1577 (Bauer-Kahan) - Directs the California Energy Commission (CEC) to establish a process for data center owners to submit reports on energy usage.

Separately, data center owners will submit their expected energy consumption to local agencies for planning and environmental review purposes. • Assembly Bill 2266 (Schultz) - Requires the CPUC to consider implementing consistent methodologies across regulatory proceedings.

Vetoed by Governor Newsom:
• Assembly 1761 (Rogers) PCIA transparency.

Did not pass the California legislature
Staff Report Item 17
• Senate Bill 1138 (Padilla) - Allows load serving entities to transact resource adequacy compliance products;
• Assembly Bill 1975 (Schultz) - Establishes a “grid utilization metric” that calculates load as a percentage of rated distribution capacity; and
• Assembly Bill 2389 (Irwin) - Extends a property tax exemption for customer-sited solar.

Financial Impact
Anticipated financial impact for bills signed into law:
• SB 222 (Wiener) – Unlikely to have a direct fiscal impact on Ava. • SB 1168 (McNerney) – No financial impact on Ava.
• AB 2266 (Schultz) – Possible reduction in regulatory reporting costs. • SB 868 (Wiener) – Unlikely to have a direct fiscal impact on Ava. Depending on how the legislation is implemented, it may increase available resources for virtual power plant initiatives.
• SB 913 (Becker) – Depending on how the program is implemented it may lessen Resource Adequacy compliance costs.
• AB 1577 (Bauer-Kahan) – Unlikely to have a direct fiscal impact on Ava.

Analysis and Context
• SB 222 (Wiener) – SB 222 will standardize and streamline local permitting for residential heat pump water heaters and heat pump HVAC systems, in part, by requiring an option for remote inspections and online automated permitting. The bill supports the State’s target of installing six million heat pump systems by 2030, an objective the State is currently set to miss by roughly two million units. The bill was passed by the state legislature signed by the Governor.
• SB 868 (Wiener) – SB 868 legalizes small-scale “plug in” or “balcony” solar installations and under certain conditions and exempts these installations from participating in the interconnection process. During the legislative session, the bill was amended to sunset on January 1, 2030. Ava conditioned its support for the bill on amendments that would require eligible portable solar devices to be paired with storage. These amendments were not accepted by the Author. The bill was passed by the state legislature signed by the Governor.
• SB 913 (Becker) – SB 913 requires the CPUC to "enhance existing market-integrated pathways" for distributed energy resources (DERs) to qualify as Resource Adequacy (RA) capacity and authorize load serving entities (LSEs), such as Ava, to include distributed capacity resources in RA filings and CPUC-ordered procurement. Over the course of the legislative session, Ava staff were able to amend the bill to ensure DERs are eligible to be used for RA compliance obligations with the same status as traditional RA products. The bill was passed by the state legislature signed by the Governor.

Staff Report Item 17
• SB 1138 (Padilla) - Sponsored by CalCCA, SB 1138 required the CPUC to permit LSEs to demonstrate compliance with Resource Adequacy (RA) requirements by selling to, or otherwise making transactions with, another LSE to meet not more than 25% of our compliance obligation, on a short-term basis, and to permit those transactions to be denominated in the same unit of time used to denominate RA compliance requirements.

The bill did not pass through the state legislature.
• SB 1168 (McNerney) – When introduced, SB 1168 imposed annually set surcharges on electricity and natural gas consumed by data centers, required utilities to collect these charges and deposit the revenues into a fund to help offset wildfire costs currently embedded in customer rates. During the session, the bill was amended, and all language imposing annual surcharges was removed. As adopted, SB 1168 requires the CPUC to assess opportunities for rate structures to ensure data centers pay their fair share and alleviate cost pressures on residential ratepayers. The bill was passed by the state legislature signed by the Governor.
• AB 1577 (Bauer-Kahan) – AB 1577 requires the CEC to establish a process for data centers to submit specified energy and water usage data and to include this information as part of the 2029 edition (and subsequent editions) of the Integrated Energy Policy Report, among other changes. Over the course of the legislative session, Ava staff were able to amend the bill to ensure reporting timelines account for IOU-to-CCA data sharing processes. The bill was passed by the state legislature signed by the Governor. • AB 1761 (Rogers) - Sponsored by CalCCA, AB 1761 would have required the CPUC to ensure that all data relied on in any decision or ruling, or in any proposal or analysis provided by an investor-owned utility (IOU), CPUC staff, or any other party, for the determination or application of a calculation methodology (e.g., PCIA) be made available to LSEs and ratepayer advocates. The bill was passed by the state legislature but vetoed by the Governor.
• AB 1975 (Schultz) – AB 1975 would have required the PUC to establish a “grid utilization metric” that calculates electrical load as a percentage of rated distribution capacity and creates performance-based incentives and Investor-Owned Utility (“IOU”)- run programs for utilities to meet annual minimum grid utilization metrics. The bill did not pass through the state legislature.
• AB 2266 (Schultz) – When introduced, the bill required the CPUC to consolidate specified reporting requirements into a single procurement plan, and (when feasible) consolidate compliance reporting for reliability requirements. However, the language was narrowed, and the CPUC now retains flexibility to use different methodologies for system planning reserve margin and evaluating short-term, mid-term, and long-term reliability needs. Ava supports this type of standardization as it contributes to reducing compliance costs. The bill was passed by the state legislature signed by the Governor. • AB 2389 (Irwin) – AB 2389 would have extended the “newly constructed” property tax exemption for customer-sited solar systems of 2MW or less and for new systems that are sited on the property of a public entity from 2026 to 2031. Ava conditioned its support for the bill on amendments that would require newly installed solar installations to be paired with storage. These amendments were not accepted by the Author. The bill did not pass through the state legislature.

Staff Report Item 17
Committee Recommendation
This matter was discussed at the September 18 Marketing, Regulatory, and Legislative Subcommittee meeting. However, this meeting occurred before the Governor announced many of his signature and veto decisions.

Attachment
A. Presentation - “2026-10-21 Board Item XX 2026 Legislative Wrap-Up – Slide Deck” 2026 California Legislative Wrap-Up
Ava Community Energy Board of Directors
October 21, 2026
Attachment Staff Report Item 17A
2026 End of Session Legislative Update
2 AB 1761
PCIA
Data Transparency
SB 1138
RA Transactability
CalCCA Sponsored Bills Other Ava Supported Bills
SB 222
Heat pump
permitting
SB 868
Plug-in solar
SB 913
RA for DERs
AB 1975
Grid utilization
AB 2389
Solar property tax
exclusion
AB 2266
Standard RA
valuation
AB 1577
Data center
reporting
SB 1168
Data center tariff
study
Signed into law Did not pass legislature
Successfully amended
Ava SIA Bills
Vetoed
Attachment Staff Report Item 17A
Resource Adequacy (RA) Transactability
3 SB 1138 Padilla – Requires the California Public Utilities Commission (CPUC) to permit Load Serving Entities (LSE) to demonstrate compliance with RA requirements by transacting RA obligations on an hourly basis up to 25% of an LSEs
obligations.
o Passed Senate Energy Committee 13-0-4
o Passed Senate 31-0-9
o Passed Assembly Energy Committee 18-0-0
o Failed Assembly Appropriations suspense
1st Chamber -
Policy
1st Chamber -
Approps
1st Chamber -
Floor
2nd Chamber -
Policy
2nd Chamber -
Approps
2nd Chamber -
Floor
Governor's
Desk Signed into law
Support
SB 1138
(Padilla)
Attachment Staff Report Item 17A
Power Charge Indifference Adjustment (PCIA) Transparency 4 1st Chamber -
Policy
1st Chamber -
Approps
1st Chamber -
Floor
2nd Chamber -
Policy
2nd Chamber -
Approps
2nd Chamber -
Floor
Governor's
Desk Signed into law
AB 1761 Rogers – Requires the CPUC to ensure that all data relied on to determine the PCIA be made available to LSEs and ratepayer advocates. o Passed Assembly 61-8
o Passed Senate 40-0
o Vetoed by Governor Newsom
Support
AB 1761
(Rogers)
Attachment Staff Report Item 17A
PCIA Rulemaking
5 Track 1 – June 2025
Changes to RA MPBs
• Market Price Benchmark (MPB)
methodology change to benefit
IOU customers
• CalCCA has appealed; The
Supreme Court granted
CalCCA's writ and the case is
now before the Court of Appeal
on remand
Track 3a ~ Q3 2027
Changes to existing PCIA
framework
• MPBs: Renewable Portfolio
Standard (RPS), GHG-free,
energy
• GHG-free attribute
allocation/pricing
• Re-vintaging of PCIA portfolio
assets
Track 4 ~ 2028
Outstanding issues after
3a and 3b concluded
• RA MPB for slice-of-day
• Energy Resource Recovery
Account (ERRA) process
refinements
• Negative PCIA
• Other proposals?
Track 2 – Sept 2026
• IOUs keep pre-2019 banked
Renewable Energy Certificates
(RECs) for bundled RPS for free
• Increases cost for CCA
customers (~$1 billion)
• Potential Voluntary Allocation
Market Offer (VAMO) RPS
exposure
• Rehearings due Oct 22, 2026
• Appeal possible 4 months later
Track 3b ~ Q4 2027
Broader changes to PCIA
framework
• Structural changes to
indifference
• Schedule expected by EOY
Tracks 1 & 2 - "Complete" Track 3 - Ongoing Track 4 - Forthcoming Attachment Staff Report Item 17A
Large Loads
6 Ava Support Bills
AB 1577
Data center energy
use reporting
SB 1168
Data center tariff
study
Signed into law Signed into law; not relevant Successfully amended Ava Neutral Bills
AB 2383
New LL tariff
SB 887
Data center CEQA
changes
AB 2619
Data center water
use planning
SB 886
LL interconnection
changes
AB 2469
Data center water
use reporting
Attachment Staff Report Item 17A
Large Load - Legislation
7 AB 1577 Bauer-Kahan — Directs the California Energy Commission (CEC) to establish a process for data center owners to submit reports on energy usage, including specified operational metrics. The CEC will then publish aggregated data and incorporate data center load trends into future energy policy reports. Separately, data center owners will submit their expected energy consumption to local agencies for planning and environmental review purposes (while protecting confidential customer information).

Ava proposed amendments – adopted: Align reporting timelines with IOU-to-CCA data flows.

Energy Use Reporting
Support
AB 1577
(Bauer-Kahan)
Support
SB 1168
(McNerney)
"Fair Share" Study
SB 1168 McNerney — When introduced, the bill imposed annually set surcharges on electricity and natural gas consumed by data centers , required utilities to collect these charges and deposit the revenues into a fund to help offset wildfire costs currently embedded in customer rates.

Major changes since initial drafting: Removed all language imposing annual surcharges, instead requires the PUC to assess opportunities for rate structures to ensure data centers pay their fair share and alleviate cost pressures on residential ratepayers.

Attachment Staff Report Item 17A
Large Loads – Legislative Takeaways
8 Cost shift protections
• Must protect other rate classes from data
center generation costs ("no cost shift") - AB
2383
• Must establish a mechanism to ensure data
centers pays ALL incremental generation
costs for at least 10 years – AB 2383
• Creates a standardized transmission level
interconnection tariff – SB 886
Environmental and local protections
• No CEQA exemption for data centers without
100% hourly GHG-free energy (>75% new
generation) - SB 887
• Required pre-operation energy and water use
projections – AB 1577, AB 2619
• Required ongoing energy and water use
reporting – AB 1577, AB 2469
Stranded cost protections
• All data center tariffs must prevent stranded
costs – SB 886
• Requires data centers to pay all costs up front
for all needed transmission facility upgrades
and interconnection costs – SB 886
• Assesses early termination fees if data center
leaves within 10 years or fails to meet
electricity demand projections – SB 886
Attachment Staff Report Item 17A
Large Loads - Next steps
9 Data sharing
• Ongoing: PG&E's Rule 30 data
sharing agreement – Potentially
moving toward a pause given
FERC's Order to Show Cause
and recent legislation.
• Forthcoming: CEC rules
implementing AB 1577 – to be
incorporated into 2029
Integrated Energy Policy Report
(IEPR).

Tariff
• Ongoing: California Advanced
Rate Design (CARD) - In
response to SB 57 (2025), broad
consideration of all things LL in
Track 1 of the proceeding.
• Forthcoming: CPUC rules
implementing SB 1168 study
and AB 2383 tariff – might get
rolled into CARD.

Interconnection
• Ongoing: California
Independent System Operator
(CAISO) LL Straw Proposal – In
response to FERC "show cause"
order, draft proposal under
review with comments in
process. Will be finalized by Oct
28, 2026.
• Forthcoming: CPUC rules
implementing SB 886.

Attachment Staff Report Item 17A
2026
• IOUs and CAISO
Finalize response to
FERC "Show Cause"
order
• CPUC may pause
PG&E Rule 30 process
(large load
interconnection
proceeding) after
addressing
CalCCA/PG&E
settlement on data
sharing
2027
• CEC issues
regulations
implementing AB 1577
data sharing
requirements. CPUC
does the same for SB
886 interconnection
requirements and AB
2383 tariff
• CPUC undertakes SB
1168 large load study
(or integrates it into
existing proceeding –
potentially CARD)
• CARD proceeding
continues
• Ava develops tariff
that meets AB 2383
requirements
2028
• Ava must offer AB
2383-compliant tariff
• IOUs must offer CPUC
approved AB 2383-
compliant tariff
• All LL interconnection
tariffs must be SB 886
compliant
• 2029 IEPR must
include assessment of
electrical load trends
for data centers
Large Loads - Timeline
10 Attachment Staff Report Item 17A
Distributed Energy Resources (DERs)
11 SB 222 Wiener — Standardizes and streamlines local permitting for residential heat pump water heaters and heat pump HVAC systems, including by requiring an option for asynchronous inspections (by July 2027) and online automated permitting (by July 2028).

Major changes since initial drafting: Localities can offer "remote" inspections in lieu of "asynchronous"
Heat Pump Water Heater and HVAC Streamlining
Support
SB 222
(Wiener)
Support-if-Amended
SB 868
(Wiener)
SB 913 Becker — Requires the CPUC to enhance pathways for aggregated DERs to qualify as RA capacity and to allow LSEs to include those resources in RA compliance and procurement.

Ava proposed amendments – adopted: Allows (but does not require) CCAs to use DERs to meet RA obligations.

Major changes since initial drafting: Strengthens language "putting the burden" on DER providers to ensure they can deliver promised DR or supply when called upon.

Resource Adequacy for Aggregated Distributed Energy Resources Support
SB 913
(Becker)
Attachment Staff Report Item 17A
Solar
12 AB 2389 Irwin — Extends the property tax exclusion for certain customer-sited solar energy systems, including systems up to 10 kilowatts and those located on public property, through January 2032.

Ava proposed amendments – not adopted: Require new solar systems to include battery storage to qualify for the exemption, while preserving eligibility for existing and resilience-focused projects.

Solar Property Tax Exclusion
SB 868 Wiener — Exempts portable solar generation devices from interconnection requirements and prohibits IOUs and POUs from imposing fees or other related requirements. Authorizes utilities to require basic notification of device installation through a simple registration process, as specified. Sunsets on January 1, 2030.

Ava proposed amendments – not adopted: Require storage pairing and modern inverter standards for plug-in solar while maintaining basic oversight to protect grid reliability and mitigate cost impacts.

Portable (or "Plug In") Solar Interconnection Exemption Support-if-Amended
SB 868
(Wiener)
Support-if-Amended
AB 2389
(Irwin)
Attachment Staff Report Item 17A
Other
13 Support-if-Amended
AB 1975
(Schultz)
AB 1975 Schultz — Requires the CPUC to establish a grid utilization metric to measure electrical load as a percentage of system capacity; requires IOUs to publicly report on that metric; sets increasing minimum utilization targets; and establishes performance-based incentives or disincentives, while requiring utilities to propose programs to meet those targets.

Ava proposed amendments – not adopted: Ensure CCAs can participate in and benefit from grid utilization programs while preventing IOU-only implementation.

Grid Utilization Metric
AB 2266 Schultz — When introduced, the bill required the CPUC to consolidate specified reporting requirements into a single procurement plan, and (when feasible) consolidate compliance reporting for reliability requirements.

Major changes since initial drafting: Narrowed its mandate from aligning broader planning frameworks to ensuring consistent standards for LSE compliance. Under the new language CPUC now retains flexibility to use different methodologies for system planning reserve margin and evaluating short-term, mid-term, and long-term reliability needs.

Consistent reliability methodology
Support
AB 2266
(Schultz)
Attachment Staff Report Item 17A
State Budget Update
14 June Budget
Agreement
New incentives for
first-time ZEV buyers
($135.5 million)
Transfer ~$22 million
from DEBA to DSGS
(funds DSGS thru 2026)
CalFIRE
($1.25 billion from
GGRF)
August Budget
Trailers
Prop 4 Climate Bond
funding plan
($2.3 billion)
• $55 million for
community
resilience centers
• $20 million for
microgrids via DEBA
No change to existing
GGRF spending plan
• $1 billion for high
speed rail
• $1 billion for
legislature's
discretion
• ~$2 billion for variety
of 'Tier 3' programs
DSGS - No additional
funding beyond 2026
Transmission
Accelerator Revolving
Fund
($322.5 million)
Zero-emission truck
and bus incentives
($135.5 million)
Attachment Staff Report Item 17A
Looking Forward
15 December 7:
27/28 legislature sworn in
January 1:

New state statutes take effect
January 4:

New Governor takes office
27/28 legislative session begins in earnest
November 3:

Election day
Expect New Senate Pro Tem
Senator Monique Limon is termed out in 28'
Major Turnover in Makeup of Senate Energy
Sens. Wahab, Allen, Caballero, and Grove
not returning in January
New Chair for Senate Energy Committee
Senator Ben Allen termed out this year
Legislative Impact of
Administrative Turnover
New Governor takes office and two CPUC
and one CEC commissioners' terms
are coming to an end in 27'
Attachment Staff Report Item 17A
Full Universe of Ava Monitored Bills
AB 13 Ransom (D) PUC membership and reporting
AB 34 Patterson (R) Extends the authority of POUs to count large hydro towards RPS AB 61 Pacheco (D) Require PAO to analyze ratepayer impacts of mandated programs AB 705 Boerner (D) Creates independent PUC audit office AB 706 Aguiar-Curry (D) Fire fuel reduction procurement program AB 710 Irwin (D) POU dynamic pricing and advanced metering mandate AB 942 Calderon (D) Changes climate credit
AB 1020 Schiavo (D) Requires IOUs to report taxpayer funding AB 1156 Wicks (D) Reforms Williamson Act contract cancellation fees AB 1577 Bauer-Kahan (D) Data center monthly reporting
AB 1738 Carillo (D) Requires local governments to offer remote inspections AB 1761 Rogers (D) PCIA data transparency
AB 1787 Schultz (D) Require IOUs to offer a dynamic tariff if smart meter infrastructure is in place AB 1813 Ward (D) Require CEC evaluation of community solar re classification AB 1975 Schultz (D) Grid utilization metric 16
Bold Signed into law Italic Vetoed by Governor Strikethrough Did not advance Attachment Staff Report Item 17A
Full Universe of Bills
AB 2111 Papan (D) Transmission plan alignment with affordability and FERC Order 1920 AB 2175 Garcia (D) Allows aggregation of multiple meters for NBT AB 2182 Irwin (D) Creates IOU run industrial decarbonization program AB 2234 Papan (D) CEQA exemptions for some geothermal exploratory projects AB 2266 Schultz (D) CPUC to consider RA valuation standardization AB 2313 Berman (D) Require gas corporations to offer electrification incentives AB 2369 Rogers (D) Enables partial RA, allowing energy-only resources earn RA value AB 2383 Zbur (D) Require creation of a large load customer class and rate schedule AB 2463 Petrie-Norris (D) Require PUC to adopt standard formula for IOU return on equity AB 2464 Wicks (D) Require PUC to study clean firm's role in 2045 goal AB 2493 Petrie-Norris (D) Require IOUs to have an interconnection auditor AB 2516 Petrie-Norris (D) California Grid Manufacturing Initiative AB 2518 Sharp-Collins (D) Requires SDG&E to fast-track affordable housing energization AB 2589 Irwin (D) Requires PUC to analyze OBBBA and adjust rates to reflect impacts AB 2612 Schultz (D) Building standards for plug-in solar systems AB 2647 Calderon (D) Requires CEC to evaluate future of nuclear power in California 17 Attachment Staff Report Item 17A
Full Universe of Bills
AB 2748 Quirk-Silva (D) Revert EV regulations to 2022 state building code for BMR housing SB 222 Weiner (D) Heat pump water heater and HVAC system permitting streamlining SB 327 McNerney (D)
Prohibits IOUs from using ratepayer funds for advocacy activities related to municipalization
SB 332 Wahab (D) Study breaking up IOUs
SB 453 Stern (D) Microgrid incentive program
SB 742 Perez (D) IOUs to remove unused transmission facilities SB 842 Stern (D) Report on firm zero-carbon resources
SB 868 Wiener (D) Plug-in solar interconnection exemption SB 886 Padilla (D) Large load interconnection requirements SB 887 Padilla (D) Large load CEQA application
SB 905 Becker (D)
IOU ROE reduction, alternative financing, and distribution grid data sharing
SB 913 Becker (D) Resource Adequacy for aggregated distributed capacity resources SB 924 Hurtado (D) PUC to consider affordability when looking at home weatherization SB 925 McNerney (D)
Requires state strategy and permitting framework to advance fusion 18
Attachment Staff Report Item 17A
Full Universe of Bills
SB 943 Becker (D) Industrial billing and NBC/TAC reform SB 1138 Padilla (D) RA transactability
SB 1158 Stern (D)
Adds status of utility transmission upgrades and electrical grid infrastructure to Reliability Planning Assessment
SB 1167 Blakespear (D) Clarifies ebike definition and bans advertising of non-eligible bikes SB 1168 McNerney (D) Data center tariff study
SB 1233 Allen (D) Requires enhanced justification of CPUC findings tied to utility returns SB 1295 Stern (D)
Requires IOUs to evaluate distributed storage and nonwire alternatives and authorizes them to own distributed storage assets
Budget
Trailer Dept of Finance
Reallocates outstanding funding from the Distributed Energy Backup Assets (DEBA) program to the Demand Side Grid Support (DSGS) program
Budget
Trailer Dept of Finance
Transitions 2026 DSGS participants to the Emergency Load Reduction Program (ELRP) or an equivalent CPUC load reduction program. 19 Attachment Staff Report Item 17A