Clean Energy Alliance: Regulatory Update
Tim Lindl – Keyes & Fox LLP
July 27, 2023
Overview
● A (Re)introduction
● Resource Adequacy
● Provider of Last Resort
● Power Charge Indifference Adjustment
● Net Billing Tariff
2 Resource Adequacy
● June Decision: Limit on CCA Expansion
○ 1% deficiency threshold will “pause” a CCA’s ability to expand ○ Ability to cure
○ Timing:
■ Accruals begin: July 2023 (August Month-Ahead)
■ Assessments begin: September 2023 (Month-Ahead) and October 2023 (Year-Ahead)
● Next steps: Massive jurisdictional overreach?
3 Provider of Last Resort
● Status: Briefing stage for Phase 1 (October 2023 decision anticipated) ● SDG&E and CalCCA positions on:
○ Service requirements
○ Changes to financial security requirement and reentry fees ● Phase 2: Will build on Phase 1 to set the requirements and application process for non-utility entities to serve as the provider of last resort 4 Quick Hits
● Power Charge Indifference Adjustment: Main rulemaking closed (after six years), but the fight continues: Energy Resource Recovery Account proceedings and General Rate Cases, among others
● Net Billing Tariff: Application for Rehearing denied; appeal persists; new tariff still moving forward
5 QUESTIONS?
Tim Lindl
[email protected]
510-314-8385
6
Item 5 – Regulatory Update
Clean Energy Alliance Board of Directors
July 27, 2023
- Document
- Item 5 – Regulatory Update
- Meeting
- July 27, 2023
- Body
- Clean Energy Alliance Board of Directors
- Original file
- 122 KB
Text extracted from the CCA's file for reading and search. Open the original on thecleanenergyalliance.org. That file is the official record.