DEPARTMENT

Infrastructure

AGENDA NO.

9j

MEETING DATE

January 11, 2022

APPROVAL:

COMMISSION

SECRETARY

Donna Hood

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Construction Modification: Consent Calendar
Contract Manager: Aileen Caylao

Approve Increase to Construction Duration Contingency for WW-697, As-Needed Main Sewer Replacement No. 8

Summary of Proposed
Commission Action:

Approve an increase of 325 calendar days to the contract duration contingency for Wastewater Enterprise, Renewal and Replacement Program-funded Contract No. WW-697, As-Needed Main Sewer Replacement No. 8, with JDB & Sons Construction, Inc.; and authorize the General Manager to approve future modifications to the contract for a total contract duration of up to 765 consecutive calendar days (approximately two years and one month), with no change to contract amount. This action constitutes the Approval Action for the three Contract Service Orders described below (work on Front Street from California Street to Pine Street, work on Minna Street from 5 th
Street to Mary Street, and work on Elizabeth Street from Diamond Street to Castro Street)
for the purposes of the California
Environmental Quality Act (CEQA) pursuant to Section 31.04(h) of the San Francisco Administrative Code. The Planning Department has determined that this action is exempt from the CEQA. If the item is approved, the Commission will rely on that determination to make its decision.

Background: The Contractor requires additional time to complete work for three Contract Service Orders due to ongoing project coordination impacts:

1. Work on Front Street from California Street to Pine Street will begin earliest in January 2022 due to the City’s holiday moratorium work requirements;

2. The schedule for work at Minna Street from 5 th Street to Mary Street requires adjustment to coordinate street access with ongoing private development activities; and

3. The schedule for work at Elizabeth Street from Diamond Street to Castro Street requires adjustment to coordinate work scope with City CD D project WD -
2765 and the SF Public Works
Paving Program.

Contract: WW-697, As-Needed Main Sewer Replacement No. 8 Commission Meeting Date: January 11, 2022

On August 25, 2020 , by Resolution No. 20-0179, this Commission approved the award of Wastewater Enterprise, Renewal and Replacement Program -funded Contract No. WW -697, As -Needed Main Sewer Replacement No. 8 to JDB & Sons Construction, Inc. The original contract amount was $7,373,000 , and the original contract duration was 400 consecutive calendar days.

Description of Scope of
Work:

The contract work consists of as-needed replacement of sewer pipelines ranging in size from 12-inch to 48-inch diameter.

Changes and Modifications to the Contract:

Section 6.22(h) of the Administrative Code requires that any cumulative increase of the contract amount or duration in excess of 10% of the original contract amount or duration be approved by this Commission.

Requested Increase to Contract Duration Contingency:

SFPUC staff recommends Commission approval of a 325 calendar day increase to the existing contract duration contingency to permit scheduling adjustments for coordination with other projects and to complete work scope listed above, with no change to the contract amount.

Result of Inaction: A delay or denial approving this request will prevent issuance and replacement of additional sewer pipeline replacement work.

Budget & Costs: Funding: Project No. 10034813, As-Needed Main Sewer Replacement No. 8
Original Contract Amount: $7,373,000
Original 10% Cost Contingency: $737,000

Schedule: Notice-to-Proceed Date: November 30, 2020
Original Contract Duration: 400 consecutive calendar days Original 10% Duration Contingency: 40 calendar days
Requested Additional Duration Contingency: 325 calendar days Total Revised Contract Duration Limit : 765 consecutive calendar days

Environmental Review: On December 29, 2021, the San Francisco Planning Department determined three Contract Service Orders ( work on Front Street from California Street to Pine Street, work on Minna Street from 5th Street to Mary Street, and work on Elizabeth Street from Diamond Street to Castro Street) to be statutorily exempt under the CEQA S ection 21080.21 and CEQA Guidelines Section 15282(k), under Case Number 2021-012918ENV, because the pipeline replacement would be in the public right of way and does not exceed one mile in length. The exemption can be found here: https://sfpuc.sharefile.com/d- s3e879895ecb74d33878c5ec804958fc7
Contract: WW-697, As-Needed Main Sewer Replacement No. 8 Commission Meeting Date: January 11, 2022

This action constitutes the Approval Action for the se three Contract Service Orders for the purposes of the CEQA pursuant to Section

31.04(h) of the San Francisco Administrative Code.

Compliance with
Chapter 14B: Local
Business Enterprise
Utilization and Non-
Discrimination In
Contracting Ordinance:

The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting requirement of 14% for this contract.

The contractor committed to LBE participation of 21.47% in its bid submittal.

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, On August 25, 2020, by Resolution No. 20-0179, this Commission awarded Wastewater Enterprise, Renewal and Replacement Program -funded Contract No. WW-697, As- Needed Main Sewer Replacement No. 8 to JDB & Sons Construction, Inc., and WHEREAS, The construction cont ract notice-to-proceed date was November 30, 2020; and
WHEREAS, The original contract amount was for $7,373,000 and the original contract duration was 400 consecutive calendar days; and
WHEREAS, Section 6.22(h) of the San Francisco Administrative Code require s Commission approval for any cumulative increase in contract amount or duration in excess of 10% of the original contract amount or duration; and
WHEREAS, San Francisco Public Utilities Commission (SFPUC) staff recommends a 325 calendar day increase to the contract duration contingency to permit schedule adjustments necessary for coordination with other projects and to complete the work; and WHEREAS, Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation requirement of 14% for this contract, and the contractor committed to a LBE participation of 21.47% in its bid submittal; and WHEREAS, Funds are available from Project No. 10034813, As-Needed Main Sewer Replacement No. 8; and
WHEREAS, On December 29, 2021, the San Francisco Planning Department determined three Contract Service Orders (work on Front Street from California Street to Pine Street, work on Minna Street from 5th Street to Mary Street, and work on Elizabeth Street from Diamond Street to Castro Street) to be statutorily exempt under the California Environmental Quality Act ( CEQA) Section 21080.21 and CEQA Guidelines S ection 15282(k), under Case Number 2021 - 012918ENV, because the pipeline replacement would be in the public right of way and does not exceed one mile in length; and
WHEREAS, This action constitutes the Approval Action for these three Contract Service Orders for the purposes of the CEQA pursuant to Section 31.04(h) of the San Francisco Administrative Code; now, therefore, be it
RESOLVED, That this Commission hereby approves an increase of 325 calendar days to the existing contract duration contingency for Wastewater Enterprise, Renewal and Replacement Program-funded Contract No. WW- 697, As-Needed Main Sewer Replacement No. 8 , for a total contract duration contingency amount of up to 365 calendar days; and be it

FURTHER RESOLVED, That this Commission hereby authorizes the General Manager, or his or her designee, to consider, and, if appropriate, to approve any future modifications to the contract duration for a total contract duration of up to 765 consecutive calendar days, with no change to the contract amount.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of January 11, 2022

Secretary, Public Utilities Commission