Cities Index.
Contract Advertisement Report

CleanPowerSF Sfpuc Commission
January 25, 2022

Document
Contract Advertisement Report
Meeting
January 25, 2022
Body
CleanPowerSF Sfpuc Commission
Original file
222 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

Project Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.554.4603
F 415.554.3225
TTY 415.554.3488

TO: Commissioner Anson Moran, President
Commissioner Newsha Ajami, Vice President
Commissioner Sophie Maxwell
Commissioner Tim Paulson
Commissioner Ed Harrington

THRU: Dennis J. Herrera, General Manager

FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division

Alan Johanson, Acting Assistant General Manager,
Infrastructure Division

DATE: J anuary 13, 2022

SUBJECT: Contract Advertisement Report: January 25, 2022

CONSTRUCTION:

Contract Number and Title:

WW-543 Southeast Water Pollution Control
Plant HVAC and Mechanical Upgrades
Contract Estimate:
$8,000,000-
8,500,000
Program:

Wastewater Enterprise Capital Program, Treatment Facilities Renewal and Replacement
Estimated Date of Advertisement:

February 2022
Description of Contract Work:

The objective of the project is to repair and replace existing wastewater facility HVAC and mechanical equipment. Work to be performed includes selective hazardous material mitigation and abatement work; selective architectural, roof and equipment demolition and repair; replacement of existing facility doors, air handling units, hydraulic actuators, exhaust and supply fans, heat pumps, ducting, drain piping, clarifier shut-off valves and spray system; and providing appurtenant safety fall protection, HVAC, mechanical, plumbing, electrical, and instrumentation and controls equipment and material.

Project Manager:

Daniel Alvarado

Type text here

PROFESSIONAL SERVICES:

Contract Number and Title:

PRO.0142.D Research Services for the Power
Enterprise
Contract Estimate:
$500,000 cumulative
(Two (2) contracts,
each for a not-to-
exceed value of
$250,000)
Program:

Power Enterprise
Estimated Date of Advertisement:

January 2022
Description of Contract Work:

Design and implement focus groups and opinion surveys or polls to gather knowledge, attitudes and insights on the SFPUC, CleanPowerSF and Hetch Hetchy Power, potential and current programs, clean energy, electricity habits, etc; and conduct market research to understand electricity or utility sector market trends, customer
sentiments/motivations/needs based, factors, benefits, or barriers that may contribute to customers choosing to go all-electric, etc.

Project Manager:

Peter Gallotta

Contract Number and Title:

PRO.0142.E Strategic Communications and
Marketing for the Power Enterprise
Contract Estimate:
$1,000,000
cumulative (Four (4)
contracts, each for a
not-to-exceed value
of $250,000)
Program:

Power Enterprise
Estimated Date of Advertisement:

January 2022
Description of Contract Work:

Developing a communications strategy to engage internal and/or external stakeholders and marketing and public
awareness/advertising/social and digital media for the power enterprise.

Project Manager:

Peter Gallotta

Contract Number and Title:

Estimated Cost:

PRO.0214 Industrial Hygiene Laboratory Services $99,000 cumulative (Three (3) contracts,
each for a not-to-exceed
value of $33,000)
Program:

Health and Safety Program
Estimated Date of Advertisement:

February 2022
Description of Contract Work:

This project engages consultants to provide laboratory analyses for industrial hygiene (air, bulk and soil) sample and hazardous waste samples analytical services using generally accepted analytical methods.

Project Manager:

Laura O’ Heir