AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Construction Award: Consent Calendar
Project Manager: Jimmy Leong
Award Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements:
Phase 1A
Summary of
Proposed
Commission
Action:
Approve the plans and specifications and award Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A , in the amount of $ 10,799,504, and with a duration of 852 consecutive calendar days (approximately two years and four months) to the responsible bidder submitting the lowest responsive bid, Sierra Mountain Construction, Inc., to replace a 60- inch diameter butterfly valve on San Joaquin Pipeline Number 2 (SJPL 2) at Tesla Valvehouse with a new, higher -pressure-rated 60-inch diameter butterfly valve; replace crossover butterfly valves connected to SJPL 2 with double knife gate valves in the Pelican, Roselle, and Emery Crossover Vaults ; and install Removable Spool Pieces (RSPs) and new vaults for SJPL 2 at Tesla and Oakdale Portals.
Background: San Joaquin Pipeline Nos. 1, 2 , and 3 (SJPLs 1,2,3) consist of three parallel transmission pipelines (completed in 1932, 1953, and 1968) that cross the San Joaquin Valley from the east of Foothill Tunnel at Oakdale Portal to the west of Coast Range Tunnel at Tesla Portal, a distance of approximately 48 miles. A fourth partial pipeline (SJPL 4 completed in 2012) consists of a 6.4 mile segment of pipe downstream of Oakdale and another 11 mile segment upstream of Tesla Portal. SJPLs deliver Hetch Hetchy water to the San Francisco Bay Area. They have been in ser vice ranging from 10 to 90 years. SFPUC staff members and contractors need to enter the pipelines regularly to perform condition assessment, maintenance, and repair work. A recent hydraulic study shows that a number of the existing valves in the SJPLs are under-rated for the surge pressures that could be triggered from an unplanned closure of the valves at the downstream Tesla Ultraviolet Treatment Facility . For safety reasons, this capital project , ‘ San Joaquin Pipeline Valve and Safe Entry Improvements,’ was initiated to replace the under-rated valves; provide pipeline isolations for safe personnel entry; and allow shutdown of any and all sections of the SJPLs without a complete system shutdown. The project will be implemented in phases , specifically Phases 1A, Contract: HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A Commission Meeting Date: March 8, 2022
1B, 2, and 3. This construction contract, HH-1005, is for the improvement work of Phase 1A.
Description of
Scope of Work:
The contract work locations are at Oakdale Portal and the Emery, Roselle, and Pelican Crossover Vaults in Stanislaus County; and at Tesla Portal and Tesla Valve House in San Joaquin County.
The contract work consists of:
• @ Tesla and Oakdale Portals
o Site grading, excavation, and shoring.
o Furnishing and install ing SJPL 2 RSP vault, thrust block, related facilities, and drainage systems at each location.
o Replacing a 12.5-foot-long section of SJPL 2 with a RSP at each location.
• @ Tesla Valve House
o Replacing existing 60-inch diameter butterfly valve, gearbox, and actuator with a new AWWA CL 250 60- inch diameter metal seated triple offset butterfly valve, gearbox, and actuator.
o Replacing existing 24-inch diameter gate valve with a new ASME/ANSI CL 300 24-inch diameter gate valve, flanges, gear box, and actuator.
o Replacing existing SJPL 2 main concrete pipe support saddle. o Installing new SJPL 2 bypass steel pipe support.
o Performing associated electrical work.
o Performing software programming for operation of the new butterfly and bypass valves.
• @ Emery, Roselle, and Pelican Crossover Vaults
o Replacing existing 36-inch diameter butterfly valves on the crossover line between SJPL 2 and SJPL 3 with two (2) modified AWWA CL E 36-inch diameter knife gate valves at each location.
o Replacing existing 42-inch diameter butterfly valves on the crossover line between SJPL 2 and SJPL 3 with two (2) modified AWWA CL E 42-inch diameter knife gate valves at each location.
o Installing new crossover steel pipe supports, platform framing, grating, and railing at each location.
o Performing associated electrical work.
o Performing software programming for operation of the new knife gate valves.
Result of Inaction: A delay or denial awarding this contract will impede planned maintenance work for SJPL 2 and reduce reliability of water delivery to the San Francisco Bay Area.
Funding, Budget
and Costs:
Funding: Project No. 10035575, SJPL Valve and Safe Entry Improvements Engineer’s Estimate: $16,000,000
Award: $10,799,504
Contract: HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A Commission Meeting Date: March 8, 2022
Schedule: Estimated Notice-to-Proceed Date: May 2022
Estimated Completion Date: September 2024
Contract Duration: Eight hundred fifty -two (852) consecutive calendar days (approximately two years and four months) (792 consecutive calendar days to Substantial Completion and an additional 60 consecutive calendar days to Final Completion)
Compliance with
Chapter 14B:
Local Business
Enterprise
Utilization and
Non-
Discrimination in
Contracting
Ordinance:
Set: The Contract Monitoring Division (CMD) established a Local Business Enterprise (LBE) subcontracting requirement of 8.0% for this contract.
Submitted: The contractor committed to a LBE subcontracting participation of
11.03% with its bid submittal.
Environmental
Review:
On July 9, 2009, the Planning Commission certified the Final Environmental Impact Report (FEIR) for the San Joaquin Pipeline System Project (Case Number 2007.0118E). On July 14, 2009, by Resolution No. 09- 0119, this Commission approved the San Joaquin Pipeline System Project and adopted findings (CEQA Findings), including the Statement of Overriding Considerations and a Mitigation Monitoring and Reporting Program (MMRP) required by the California Environmental Quality Act (CEQA).
On January 27, 2022, the Planning Department issued a Minor Project Modification (MPM) to the FEIR to include work associated with the San Joaquin Valve and Safe Entry Improvements Phase 1A. The work under Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements Phase 1A is within the scope of the project authorized under the FEIR and MPM.
The FEIR, MPM to the FEIR, Resolution No. 09-0119, CEQA Findings, and the MMRP can be found here:
https://sfpuc.sharefile.com/d-s6d1e909a956141eab188fde5eef920f5
Contract: HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A Commission Meeting Date: March 8, 2022
Bid History: Advertised: December 8, 2021
Bids Received: SFPUC received sealed bids from five (5) firms on January 20, 2022, as follows:
Bid Rank Base Bid
Amount
Bid
Preference
Compensable
Delay
Adjusted Bid Final
Rank
1. Sierra Mountain
Construction,
Inc.
$10,799,504 N/A $60 $10,799,564 1
2. Ranger
Pipelines
Incorporated
$12,822,150 N/A $36,000 $12,858,150 2
3. Kiewit
Infrastructure
West Co.
$13,400,304 N/A $60,000 $13,460,304 3
4. Anvil Builders
Inc $13,589,904 N/A $90,000 $13,679,904 4
5. Mountain
Cascade, Inc. $14,645,454 N/A $60,000 $14,705,454 5
Application of bid preferences do not apply to this contract as the engineer’s estimate is in excess of $10,000,000.
There were no timely protests of this bid ranking. Ranger Pipelines Inc. attempted to assert a protest but it was rejected for failing to meet the protest deadline set forth in the advertisement for bids.
Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.
Attachments: 1. CMD Memorandum
Contract: HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A Commission Meeting Date: March 8, 2022
SITE LOCATION MAP – HH-1005 SAN JOAQUIN PIPELINE VALVE AND SAFE ENTRY IMPROVEMENTS - PHASE 1A
Legend
Site Locations
San Joaquin Pipeline Configuration
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) owns and operates four San Joaquin Pipelines (SJPLs) that have been in service ranging from 10 to 90 years. SFPUC must enter the pipelines regularly to perform condition assessment, maintenance, and repair work.
A recent hydraulic study shows that a number of the existing valves in the SJPLs are under -rated for the surge pressures that could be triggered from an unplanned closure of the valves at the downstream Tesla Ultraviolet Treatment Facility. For safety reasons, the SFPUC initiated the capital project, San Joaquin Pipeline Valve and Safe Entry Improvements, to replace the under - rated valves; provide pipeline isolations for safe personnel entry; and allow shutdown of any and all sections of the SJPLs without a complete system shutdown. The project will be implemented in phases, specifically Phases 1A, 1B, 2, and 3. This construction contract, HH -1005, is for the improvement work of Phase 1A.
WHEREAS, On December 8, 2021, San Francisco Public Utilities Commission (SFPUC) staff advertised Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements:
Phase 1A; and
WHEREAS, The Engineer’s Estimate is $ 16,000,000 for this construction contract work to replace a 60-inch diameter butterfly valve on San Joaquin Pipeline No. 2 (SJPL 2) at Tesla Valvehouse with a new, higher-pressure-rated 60-inch diameter butterfly valve; replace crossover butterfly valves connected to SJPL 2 with double knife gate valves in the Pelican, Roselle, and Emery Crossover Vaults; and install Removable Spool Pieces (RSPs) and new vaults for SJPL 2 at Tesla and Oakdale Portals; and
WHEREAS, The contract duration is 852 consecutive calendar days; and WHEREAS, On January 20, 2022, SFPUC received and publicly opened five bids; and WHEREAS, SFPUC staff and Contract Monitoring Division (CMD) review of the bids for qualifications, responsiveness, and application of bid preferences resulted in the establishment of Sierra Mountain Construction, Inc. as the responsible bidder with the lowest responsive bid; and WHEREAS, CMD established a Local Business Enterprise ( LBE) subcontracting participation of 8.0% for this contract , and the contractor committed to a LBE subcontracting participation of 11.03% with its bid submittal; and
WHEREAS, The firm awarded this contract must be in compliance with the Equal Benefits Provisions of Chapter 12B of the City’s Administrative Code either at the time of the award, or within two weeks of the date of the Commission award. If the bidder fails to meet the compliance requirement, Staff will return to the Commission for recission of this award; and WHEREAS. On July 9, 2009, the Planning Commission certified the Final Environmental Impact Report (FEIR) for the San Joaquin Pipeline System Project (Case Number 2007.0118E); and
WHEREAS, On July 14, 2009, by Resolution No. 09-0119, this Commission approved the San Joaquin Pipeline System Project and adopted findings (CEQA Findings), including the Statement of Overriding Considerations and a Mitigation Monitoring and Reporting Program (MMRP) required by the California Environmental Quality Act (CEQA); and
WHEREAS, On January 27, 2022, the Planning Department issued a Minor Project Modification (MPM) to the FEIR to include work associated with the San Joaquin Valve and Safe Entry Improvements Phase 1A; and
WHEREAS, The work under Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements Phase 1A is within the scope of the project authorized under the FEIR and MPM; and
WHEREAS, The Planning Department is the custodian of records, located in File No. 2007.0118E, at 49 South Van Ness Avenue, Suite 1400, San Francisco, California; and WHEREAS, The Project files, including the FEIR, MPM to the FEIR, Resolution No. 09- 0119, CEQA Findings and the MMRP have been made available for review by this Commission and the public, and those files are part of the record before this Commission; and WHEREAS, This Commission has reviewed and considered the information contained in the FEIR, the findings contained in SFPUC Resolution Number 09- 0119, the MPM to the FEIR and all written and oral information provided by the Planning Department, the public, relevant public agencies, SFPUC and other experts and the administrative files for the Project; now, therefore, be it
RESOLVED, This Commission has reviewed and considered the FEIR and the MPM and the record as a whole, finds that the FEIR is adequate for its use as the decision –making body for the Project and incorporates the CEQA findings contained in Resolution Number 09-0119 by this reference thereto as though set forth in this Resolution; and be it FURTHER RESOLVED, That this Commission hereby approves the plans and specifications and awards Contract No. HH-1005, San Joaquin Pipeline Valve and Safe Entry Improvements: Phase 1A, in the amount of $ 10,799,504, for a duration of 852 consecutive calendar days, to the responsible bidder submitting the lowest responsive bid, Sierra Mountain Construction, Inc.
I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of March 8, 2022.
Secretary, Public Utilities Commission
London N. Breed, Mayor
Carmen Chu, City Administrator
Romulus Asenloo, Director
1155 Market Street, 4th Floor, San Francisco, CA 94103
Telephone (415) 581-2310 Fax (415) 581-2351
CONTRACT MONITORING DIVISION
CITY ADMINISTRATOR’S OFFICE
Date: February 3, 2022
To: Jimmy Leong, Project Manager, SFPUC
Joseph Buitrago, Project Manager, SFPUC
From: Vivian Liu, Contract Compliance Officer, CMD
Subject: HH-1005 San Joaquin Valve and Safe Entry Improvements-Phase 1A -CMD Review
The Contract Monitoring Division (“CMD”) has reviewed the bids submitted for the above referenced project, applied the appropriate bid discounts, and determined responsiveness to the Chapter 14B pre- award requirements. An LBE subcontracting requirement of 8.00% was established for this project. The requirement is less than 20% because approximately 40% of the total contract value will be used for purchasing large diameter valves and appurtenances. In addition, constraints such as the location of the work sites (spread across San Joaquin Valley from Tracy to Oakdale) and the construction timeframe (limited to 60-100 days during a yearly water system shut down) reduces the number of subcontractors available to perform work on the contract. Below is a summary of CMD’s review.
Bidder Status Base Bid Compensable
Delay
Total Bid
with
Compensable
Delay
LBE Bid
Discount
Adjusted Bid
with LBE Bid
Discount
Sierra Mountain
Construction, Inc. Non-LBE $10,799,504.00 $1.00 $10,799,564.00 N/A $10,799,564.00 Ranger Pipelines
Incorporated Non-LBE $12,822,150.00 $600.00 $12,858,150.00 N/A $12,858,150.00 Kiewit Infrastructure
West Co. Non-LBE $13,400,304.00 $1,000.00 $13,460,304.00 N/A $13,460,304.00 Anvil Builders, Inc. Non-LBE $13,589,904.00 $1,500.00 $13,679,904.00 N/A $13,678,904.00 Mountain Cascade, Inc. Non-LBE $14,645,454.00 $1000.00 $14,705,454.00 N/A $14,705,454.00
Sierra Mountain Construction, Inc. (“SMCI”) is the lowest responsive bidder. SMCI met the 8.00% LBE subcontracting requirement by listing the following LBE firms on Section 00 43 36 (Subcontractor List):
LBE Subcontractor Scope of Work Status Listed
Amount
Amount
Credited
Participation
(based on
credited
amount)
Pacific
Engineering &
Construction, Inc.
Partial Valve & Pipe
Install
SF LBE-OBE
(micro) $1,080,000.00 $1,080,000.00 10.00%
Mission City Rebar Rebar PUC LBE-OBE
(small) $111,000.00 $111,000.00 1.03%
TOTAL $1,191,000.00 $1,191,000.00 11.03%
SMCI also listed the following non-LBE subcontractors on Section 00 43 36:
Non-LBE Subcontractor Scope of Work Status Listed Amount Dean’s Certified Welding,
Inc. Partial WFP Install Non-LBE $50,000.00
Con J. Franke Electric, Inc. Electrical Non-LBE $1,281,977.00 IMRAE Coating Non-LBE $462,000.00
TOTAL $1,793,977.00
Based on the foregoing, CMD has determined that SMCI has complied with the pre-award Chapter 14B requirements. Should you have any questions, or if I can be of further assistance, please do not hesitate to contact me at (415) 551-4814.