Water System Improvement Program Status of Construction Change Orders

CleanPowerSF Sfpuc Commission
May 24, 2022

Document
Water System Improvement Program Status of Construction Change Orders
Meeting
May 24, 2022
Body
CleanPowerSF Sfpuc Commission
Pages
2
Original file
723 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.
525 Golden Gate Avenue, 6th Floor
San Francisco, CA 94102
T 415.554.1853
F 415.554.1877

MEMORANDUM

DATE: May 16, 2022

TO: The Honorable Anson Moran, President
The Honorable Newsha Ajami, Vice President
The Honorable Sophie Maxwell
The Honorable Tim Paulson

THROUGH: Dennis J. Herrera, General Manager
Alan Johanson, Acting Assistant General Manager –
Infrastructure

FROM: Katie Miller, Director
Water Capital Programs - Infrastructure

SUBJECT: Water System Improvement Program (WSIP)
Status of Construction Change Orders
Q3/FY2021-2022 (January 1, 2022 – March 31, 2022)

Attached for your review is the Q3/FY2021-2022 quarterly update report on WSIP construction Change Orders (COs). The attached summary tables show the status of construction COs for all WSIP regional project contracts awarded as of March 31, 2022.

The costs for approved COs increased from $526.8 million to $526.9 million, an increase of approximately 0.02%. This increase was due to the processing and approval of potential and pending COs during the quarter. The total value of approved COs as of March 31, 2022 remained the same as last quarter at 28.0% of the total awarded contract amount essential to meeting the established Level of Service (LOS) goals and objectives of the various WSIP projects. The costs for approved COs on all WSIP construction contracts excluding the Calaveras Dam Replacement Project (CDRP) have increased from $218.6 million to $218.7 million. The total value of approved COs on all WSIP construction contracts excluding the CDRP as of March 31, 2022 remained the same as last quarter at 13.5% of the total awarded contract amount of the non-CDRP WSIP projects.

WSIP Status of Construction Change Orders
Q3/FY2021-2022 (January 1, 2022 – March 31, 2022)

Page 2 ends

During the reporting quarter, the overall percent completion of all construction contracts increased from 99.1% to 99.2%1. The value (and percent of the original contract value) of approved, pending, and potential COs for all regional projects increased from $528.0 million (or 28.1% of the original contract value) at the end of December 2021 to $528.5 million (or 28.1% of the original contract value) at the end of March 2022. The value of approved, pending, and potential COs for all regional projects excluding the CDRP (and percent of the original contract value excluding the CDRP) increased from $219.8 million (or

13.5% of the original contract value) to $220.3 million (or 13.6% of the original contract value) over the same period.

During the reporting period, January through March 2022, no new Contracts have been issued NTP. During the reporting period, Fish Passage Facilities at Alameda Creek Diversion Dam (Contract No. WD-2729), achieved Final Construction Completion.

Should you have any questions regarding the two attached tables, please contact me at [email protected].

(Attachments: Appendix A - Table 7a and Table 7b)

cc: Alan Johanson
Steve Ritchie
Algynon Collymore
Howard Fung
Emad Mansour

1 Based on the weighted average of the percent completion of all contracts awarded to date. This percentage excludes non-WSIP funded projects.

Approved Change
Order Amount
Percent of
Awarded
Contract
Revised Contract
Amount
Pending Change
Order Amount
Percent of
Awarded
Contract
Potential Change
Order Amount
Percent of
Awarded
Contract
Total Change Order
Amount
Percent of
Awarded Contract
(Col 1) (Col 2) (Col 3) (Col 4) (Col 5) (Col 6) (Col 7) (Col 8) (Col 9) (Col 10) (Col 11) (Col 12) (Col 13) (Col 14) (Col 15) (Col 16) San Joaquin Region
CUW37301 San Joaquin Pipeline System - Crossovers HH-935A WestBay Builders, Inc. 2-Jun-10 100% $11,723,817 $3,620,160 30.88% $15,343,977 $0 0.00% $0 0.00% $3,620,160 30.88% CUW37301 San Joaquin Pipeline System Eastern Segment HH-935C Contri Construction 7/11/2011 Phase 1 100% $45,329,416 $8,631,642 19.04% $53,961,058 $0 0.00% $0 0.00% $8,631,642 19.04% CUW37301 Tesla Portal Protection HH-953 Azul Works Inc. 21-Mar-12 100% $2,760,000 $591,307 21.42% $3,351,307 $0 0.00% $0 0.00% $591,307 21.42% CUW37301 San Joaquin Pipeline System West Reaches HH-935B Mountain Cascade 3/1/2011 Phase I 100% $48,706,379 $1,749,280 3.59% $50,455,659 $0 0.00% $0 0.00% $1,749,280 3.59% CUW38401 Tesla Treatment Facility DB-116 PCL Constructors, Inc. Ph. 1 10/6/2008 PH. 2B 3/31/2009 100% $81,420,562 $6,161,561 7.57% $87,582,123 $0 0.00% $0 0.00% $6,161,561 7.57% CUW37302 Roselle Crossover Package HH-914 Mountain Cascade 26-Aug-09 100% $2,837,000 $695,626 24.52% $3,532,626 $0 0.00% $0 0.00% $695,626 24.52% CUW36401 Lawrence Livermore Water Quality Improvement 1 WD-2597 NTK Construction 26-Aug-09 100% $1,267,900 $213,901 16.87% $1,481,801 $0 0.00% $0 0.00% $213,901 16.87% Sunol Valley Region
CUW37403 San Antonio Backup Pipeline WD-2575 Ranger Pipelines 29-Mar-13 Phase 2 100.00% $31,372,335 $1,591,731 5.07% $32,964,066 $0 0.00% $0 0.00% $1,591,731 5.07% CUW37401 Calaveras Dam Replacement Project WD-2551 Dragados/Flatiron West/Sukut JV 15-Aug-11 100% $259,571,850 $308,208,510 118.74% $567,780,360 $0 0.00% $0 0.00% $308,208,510 118.74% CUW35901 New Irvington Tunnel WD-2581 Southland/Tutor Perini JV 22 July 2010 Phase 1 100% $226,657,700 $38,860,601 17.15% $265,518,301 $0 0.00% $0 0.00% $38,860,601 17.15% CUW37401 Alameda Creek Diversion Dam WD-2729 Shimmick Construction 4/19/2016 Phase 2 100% $28,939,300 $14,483,640 50.05% $43,422,940 $0 0.00% $0 0.00% $14,483,640 50.05% CUW35201 Alameda Creek Recapture Project WD-2581R Anvil Builders Inc. 21-Jun-21 10% $19,511,500 $139,190 0.71% $19,650,690 $60,000 0.31% $90,000 0.46% $289,190 1.48% CUW38101
Sunol Valley Water Treatment Plant Expansion and Treated Water Reservoir ³ WD-2582 Shimmick Construction 23-Jun-10 100% $78,202,160 $15,685,261 20.06% $93,887,421 $0 0.00% $0 0.00% $15,685,261 20.06% CUW35902 Alameda Siphon No. 4 WD-2552 Steve Rados Construction 26-Aug-09 100% $31,933,695 $6,802,599 21.30% $38,736,294 $0 0.00% $0 0.00% $6,802,599 21.30% CUW38601 San Antonio Pump Station Upgrade WD-2566 Mountain Cascade 2-Nov-09 100% $6,991,000 $525,865 7.52% $7,516,865 $0 0.00% $0 0.00% $525,865 7.52% CUW3701 Pipeline Repair & Readiness Improvements WD-2530 NTK Construction 24-Jun-07 100% $1,047,600 $101,491 9.69% $1,149,091 $0 0.00% $0 0.00% $101,491 9.69% CUW37402 Calaveras Reservoir Oxygenation WD-2488 NCCI, Inc. 27-Jun-05 100% $977,250 $92,344 9.45% $1,069,594 $0 0.00% $0 0.00% $92,344 9.45% CUW35501 Standby Power Facilities WD-2511 Power Engineering Contractors, Inc. 14-Jan-08 100% $8,419,000 $924,767 10.98% $9,343,767 $0 0.00% $0 0.00% $924,767 10.98% Bay Division Region
CUW35302 BDPL No. 3&4 Seismic Upgrade WD-2629 Steve P Rados Inc. 4-Dec-12 100% $31,320,000 $5,737,634 18.32% $37,057,634 $0 0.00% $0 0.00% $5,737,634 18.32% CUW36801 BDPL Reliability Upgrade - Tunnel WD-2531 Michels/Jay Dee/Coluccio 1-Apr-10 100% $215,294,530 $2,324,537 1.08% $217,619,067 $0 0.00% $0 0.00% $2,324,537 1.08% CUW36802 BDPL Reliability Upgrade - Pipeline 5 - Peninsula WD-2542 Mountain Cascade 10-Mar-10 100% $52,183,400 $3,239,578 6.21% $55,422,978 $0 0.00% $0 0.00% $3,239,578 6.21% CUW36802 BDPL 5 Cordilleras Micro-tunnel WD-2665 Steve P Rados Inc. 1-Feb-12 100% $5,251,100 $434,664 8.28% $5,685,764 $0 0.00% $0 0.00% $434,664 8.28% CUW38001 BDLP Nos. 3 & 4 Crossover Facilties WD-2568 Shimmick Construction 13-Jul-09 100% $12,695,000 $552,724 4.35% $13,247,724 $0 0.00% $0 0.00% $552,724 4.35% CUW36802 BDPL Reliability Upgrade - Pipeline 5 - East Bay WD-2541 Ranger Pipeline 7-Jan-10 100% $61,588,008 $22,211,992 36.07% $83,800,000 $0 0.00% $0 0.00% $22,211,992 36.07% CUW36301 SCADA System - Phase II WD-2589 Ranger Pipelines 14-Dec-09 100% $3,847,250 ($1,677,323) -43.60% $2,169,927 $0 0.00% $0 0.00% ($1,677,323) -43.60% CUW35301 BDPL Nos. 3 & 4 Crossovers/Isolation Valves WD-2507 Ranger Pipelines 21-Aug-06 100% $15,190,500 $386,350 2.54% $15,576,850 $0 0.00% $0 0.00% $386,350 2.54% BDL Reliability Upgrade - Relocation - 8-Feb-10 100% $2,251,204 $112,162 4.98% $2,363,366 $0 0.00% $0 0.00% $112,162 4.98% SFPUC/EBMUD Intertie - 18-Jan-05 100% $7,700,000 $178,357 2.32% $7,878,357 $0 0.00% $0 0.00% $178,357 2.32% Peninsula Region
CUW2596 Harry Tracy Water Treatment Plant Lng Term
Imoprovements WD-2596 Kiewit Infrastructure West 16-Mar-11 100% $174,197,000 $22,180,999 12.73% $196,377,999 $0 0.00% $0 0.00% $22,180,999 12.73% CUW35401 Crystal Springs San Andreas Transmission Upgrade WD-2601 Kiewit Infrastructure West 1-Dec-10 100% $99,763,000 $32,658,418 32.74% $132,421,418 $0 0.00% $0 0.00% $32,658,418 32.74% CUW36702 Peninsula Pipeline Seismic Upgrade 3 WD-2727 Ranger Pipelines 28-Apr-14 100% $20,736,380 $1,950,473 9.41% $22,686,853 $0 0.00% $0 0.00% $1,950,473 9.41% CUW37801 Crystal Springs Pipeline No. 2 Replacement Project WD-2555 Ranger Pipeline 28-Feb-11 100% $32,547,350 $1,591,354 4.89% $34,138,704 $0 0.00% $0 0.00% $1,591,354 4.89% CUW35401 Lower Crystal Springs Dam Improvements WD-2591 Kiewit Infrastructure West 31-Jan-11 100% $17,360,400 $2,997,566 17.27% $20,357,966 $0 0.00% $0 0.00% $2,997,566 17.27% CUW36105 Pulgas Balancing - Modifications of Existing
Dechloramination Facility WD-2607 NCCI, Inc. 22-Sep-10 100% $1,864,560 $184,576 9.90% $2,049,136 $0 0.00% $0 0.00% $184,576 9.90% CUW36103 Pulgas Balancing - Structural Rehabilitation & Roof Replacement WD-2573 S J Amaroso Construction 30-Nov-09 100% $12,857,000 $146,429 1.14% $13,003,429 $0 0.00% $0 0.00% $146,429 1.14% CUW36102 Pulgas Balancing - Discharge Channel Modifications WD-2563 6-Apr-09 100% $1,366,000 ($533,581) -39.06% $832,419 $0 0.00% $0 0.00% ($533,581) -39.06% Awarded Contract
Amount
Approved Change Orders Pending Change Orders Total Change Orders Appendix A - Table 7a March Yr 2022
Status of Construction Contract Cost Change Orders (Excludes Non WSIP Funds and Projects Not Covered by WSIP Contingency (BHR))
Project No. Contract Name Construction Contract No. Construction Contractor Notice To Proceed
(NTP) Date
Percent
Construction
Complete
Potential Change Orders
1 of 2
Approved Change
Order Amount
Percent of
Awarded
Contract
Revised Contract
Amount
Pending Change
Order Amount
Percent of
Awarded
Contract
Potential Change
Order Amount
Percent of
Awarded
Contract
Total Change Order
Amount
Percent of
Awarded Contract
(Col 1) (Col 2) (Col 3) (Col 4) (Col 5) (Col 6) (Col 7) (Col 8) (Col 9) (Col 10) (Col 11) (Col 12) (Col 13) (Col 14) (Col 15) (Col 16) Awarded Contract
Amount
Approved Change Orders Pending Change Orders Total Change Orders Appendix A - Table 7a March Yr 2022
Status of Construction Contract Cost Change Orders (Excludes Non WSIP Funds and Projects Not Covered by WSIP Contingency (BHR))
Project No. Contract Name Construction Contract No. Construction Contractor Notice To Proceed
(NTP) Date
Percent
Construction
Complete
Potential Change Orders
CUW39101 Baden and San Pedro Valve Lots Improvements WD-2556 JMB Construction, Inc. 8-Apr-09 100% $11,536,500 $84,935 0.74% $11,621,435 $0 0.00% $0 0.00% $84,935 0.74% CUW35601 New Crystal Springs Bypass Tunnel WD-2498 Shank/Balfour Beatty Joint Venture 1-Dec-08 100% $55,674,000 $1,735,887 3.12% $57,409,887 $0 0.00% $0 0.00% $1,735,887 3.12% CUW36603 HTWTP Short-Term Improvements (Coagulation &
Flocculation/Remaining Filters) WD-2564 NTK Contruction, Inc. 10-Jul-08 100% $13,824,000 $1,136,315 8.22% $14,960,315 $0 0.00% $0 0.00% $1,136,315 8.22% CUW37901 San Andreas Pipeline No. 3 Installation WD-2513 Mountain Cascade 27-Aug-09 100% $16,336,350 $521,001 3.19% $16,857,351 $0 0.00% $0 0.00% $521,001 3.19% CUW35701 Adit Leak Repair WD-2510 NTK Contruction, Inc. 9-Apr-07 100% $1,689,913 $14,844 0.88% $1,704,757 $0 0.00% $0 0.00% $14,844 0.88% CUW36101 Pulgas Balancing Inlet/Outlet WD-2310A NCCI, Inc. 6-Sep-05 100% $499,300 $21,629 4.33% $520,929 $0 0.00% $0 0.00% $21,629 4.33% Cross Connection Controls - 1-Jun-05 100% $3,003,000 ($1,338,211) 0.00% $1,664,789 $0 0.00% $0 0.00% ($1,338,211) -44.56% CUW36601 HTWTP Demo Filters WD-2478 NTK Contruction, Inc. 14-Sep-05 100% $1,515,700 $118,284 7.80% $1,633,984 $0 0.00% $0 0.00% $118,284 7.80% CUW36901 Capuchino Valve Lot WD-2508 NTK Contruction, Inc. 29-Jan-07 100% $1,562,400 $14,333 0.92% $1,576,733 $0 0.00% $0 0.00% $14,333 0.92% San Francisco Regional Sub Region
CUW37201 University Mound Reservoir - North Basin WD-2539 S J Amaroso Construction 3-Aug-09 100% $29,597,000 $1,472,218 4.97% $31,069,218 $0 0.00% $0 0.00% $1,472,218 4.97% CUW35801 Sunset Reservoir - North Basin WD-2406R Shimmick Construction 10-Oct-06 100% $44,114,067 $85,441 0.19% $44,199,508 $0 0.00% $0 0.00% $85,441 0.19% CUW30101 Regional GW Storage and Recovery (Contract B) WD-2668 Ranger Pipelines,Inc. 6-Apr-15 99% $42,980,047 $19,418,730 45.18% $62,398,777 $937,811 2.18% $506,986 1.18% $20,863,526 48.54% Security Projects
CUW36302 System Security Upgrade 00A WD-2653 Various 15-Jun-11 100% $1,431,264 ($201,611) -14.09% $1,229,653 $0 0.00% $0 0.00% ($201,611) -14.09% CUW36302 System Security Upgrade 00B WD-2661 Various 19-Dec-11 100% $1,216,742 $344,051 28.28% $1,560,793 $0 0.00% $0 0.00% $344,051 28.28% CUW36302 System Security Upgrade 00C WD-2707 Various 8-May-14 94% $1,187,648 ($263,661) -22.20% $923,987 $0 0.00% $0 0.00% ($263,661) -22.20% Totals: $1,881,849,077 $526,920,569 28.00% $2,408,769,646 $997,811 0.05% $596,986 0.03% $528,515,366 28.08% BHR Projects
CUW38802 BHR, Homestead Pond, Peninsula Region WD-2641R Yerba Buena Engineering and Construction 30-Jan-12 100% $6,499,000 $604,115 9.30% $7,103,115 $0 0.00% $0 0.00% $604,115 9.30% CUW38802 BHR, SASS & Upper San Mateo Creek, Peninsula Region WD-2651R Shimmick Construction 31-May-12 100% $5,591,750 ($1,151,322) -20.59% $4,440,428 $0 0.00% $0 0.00% ($1,151,322) -20.59% CUW38802 BHR, Goldfish Pond, Sunol Valley Region WD-2640 Yerba Buena Engineering and Construction 19-Sep-11 100% $3,188,000 ($156,173) -4.90% $3,031,827 ($5,163) -0.16% $0 0.00% ($161,336) -5.06% CUW38802 BHR, San Antonio Creek, Sunol Valley Region WD-2652 Gordon N. Ball Inc 27-Dec-11 100% $12,947,400 $2,610,825 20.16% $15,558,225 ($37,881) -0.29% $0 0.00% $2,572,944 19.87% CUW38802 BHR, Sheep Camp Creek, Sunol Valley Region WD-2666 Shimmick Construction 4-Sep-12 100% $3,912,500 $431,403 11.03% $4,343,903 $0 0.00% $0 0.00% $431,403 11.03% CUW38803 BHR, Goat Rock Management Unit, Sunol Valley Region WD-2644I JDB Construction 15-May-13 100% $378,210 ($10,295) -2.72% $367,915 $0 0.00% $0 0.00% ($10,295) -2.72% CUW38802 BHR, Peninsula Vegetation Removal, Peninsula Region WD-2654R NTK 1-Feb-16 100% $11,062,544 $744,646 6.73% $11,807,190 $0 0.00% $0 0.00% $744,646 6.73% TOTAL BHR $43,579,404 $3,073,198 7.05% $46,652,602 ($43,043) -0.10% $0 0.00% $3,030,155 6.95% Notes:

1. Lawrence Livermore Water Quality Improvement (WD-2597) excludes Non-WSIP funds of $1,766,800 from the Original Contract and $182,118 from Approved COs.

2. Sunol Valley Water Treatment Plant Expansion and Treated Water Reservoir (WD-2582) excludes Non-WSIP funds of $4,900,000 from the Original Contract and $3,930,851 from Approved COs.

4. Peninsula Pipeline Seismic Upgrade (WD-2727) excludes Non-WSIP funds of $1,500,000 from the Original Contract and $1,166,999 from Approved COs.

COLUMN DESCRIPTION:

Columns 1-2: Regional projects with construction activities underway Final Completion Column 10: Revised construction contract amounts – that is, original construction contract award amount plus approved change orders (Column 7 + Column 8) Columns 3-4: Construction contract numbers and name of construction contractors Substantial Completion Column 11: Total amounts of pending changes that are in process as proposed change orders, change order requests, or change orders prior to approval Column 5: Dates of construction notice to proceed Future Projects Column 12: Pending change orders percentages of original construction contract award amounts Column 6: Percent completion of the projects' Construction Phase Column 13: Total amounts of potential changes that are in process as proposed change orders, change order requests, or change orders prior to approval Column 7: Original construction contract award amounts Column 14: Potential change orders percentages of original construction contract award amounts Column 8: Total amounts of change orders that have been approved to date Column 15 - The summation of Columns 8, 11, and 13 Column 9: Approved change orders percentages of original construction contract award amounts Column 16 - Total change orders percentages of original construction contract award amounts This report excludes all non WSIP funds
2 of 2
Approved
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Revised
Contract
Duration
Pending
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Potential
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Total CO Time
Added in
Calendar Days
Percent of
Original
Contract
Duration
(Col 1) (Col 2) (Col 3) (Col 4) (Col 5) (Col 6) (Col 7) (Col 8) (Col 9) (Col 10) (Col 11) (Col 12) (Col 13) (Col 14) (Col 15) (Col 16) San Joaquin Region
CUW37301 San Joaquin Pipeline System - Crossovers HH-935A West Bay Builders, Inc. 2-Jun-10 100% 524 1269 242.18% 1793 0 0.00% 0 0.00% 1269 242.18% CUW37301 San Joaquin Pipeline System East Segment HH935C Contri Constructioon 7/11/2011 Phase 1 100% 590 160 27.12% 750 408 69.15% 0 0.00% 568 96.27% CUW37301 Tesla Portal Protection HH-953 Azul Works Inc. 21-Mar-12 100% 240 126 0.00% 366 589 245.42% 0 0.00% 715 297.92% CUW37301 San Joaquin Pipeline System West Reaches HH-935B Mountain Cascade 3/1/2011 Phase I 100.0% 649 310 47.77% 959 0 0.00% 0 0.00% 310 47.77% CUW38401 Tesla Treatment Facility DB-116 PCL Constructors, Inc. Ph. 1 10/6/2008 PH. 2B 3/31/2009 100.0% 1186 154 12.98% 1340 0 0.00% 0 0.00% 154 12.98% CUW37302 Roselle Crossover Package HH-914 Mountain Cascade 26-Aug-09 100.0% 390 364 93.33% 754 0 0.0% 0 0.0% 364 93.33% CUW36401 Lawrence Livermore Water Quality Improvement HH-2597 NTK Construction 26-Aug-09 100.0% 290 273 94.14% 563 0 0.00% 0 0.00% 273 94.14% Sunol Valley Region
CUW37403 San Antonio Backup Pipeline WD-2575 Ranger Pipelines 29-Mar-13 100% 720 13 1.81% 733 275 38.19% 0 0.00% 288 40.00% CUW37401 Calaveras Dam Replacement Project WD-2551 JV-Dragados/Flatiron West/Sukut 15-Aug-11 100% 1460 1429 97.88% 2889 0 0.00% 0 0.00% 1429 97.88% CUW35901 New Irvington Tunnel WD-2581 JV-Southland/Tutor Perini 22 July 2010 Phase 1 100% 1390 522 37.55% 1912 0 0.00% 681 48.99% 1203 86.55% CUW37401 Alameda Creek Diversion Dam WD-2729 Shimmick Construction 19-Apr-16 100% 972 1019 104.84% 1991 0 0.00% 0 0.00% 1019 104.84% CUW35201 Alameda Creek Recapture Project WD-2825R Anvil Builders Inc. 21-Jun-21 10% 547 0 0.00% 547 0 0.00% 0 0.00% 0 0.00% CUW38101 Sunol Valley Water Treatment Plant Expansion and Treated Water Reservoir WD-2582 Shimmick Construction 23-Jun-10 100% 1077 109 10.12% 1186 0 0.00% 0 0.00% 109 10.12% CUW35902 Alameda Siphon No. 4 WD-2552 Steven Rados Construction 26-Aug-09 100% 857 238 27.77% 1095 0 0.00% 0 0.00% 238 27.77% CUW38601 San Antonio Pump Station Upgrade WD-2566 Mountain Cascade 2-Nov-09 100% 669 29 4.33% 698 0 0.00% 0 0.00% 29 4.33% CUW3701 Pipeline Repair & Readiness Improvements WD-2530 NTK Construction 24-Jun-07 100% 270 147 54.44% 417 0 0.00% 0 0.00% 147 54.44% CUW37402 Calaveras Reservoir Oxygenation WD-2488 NCCI, Inc. 27-Jun-05 100% 126 (19) -15.08% 107 0 0.00% 0 0.00% (19) -15.08% CUW35501 Standby Power Facilities WD-2511 Power Engineering Contractors 14-Jan-08 100% 823 0 0.00% 823 0 0.00% 0 0.00% 0 0.00% Bay Division Region
CUW35302 Seismic Upgrade of BDPL3&4 at the Hayward Fault WD-2629 Steven P Rados Inc. 4-Sep-12 100% 858 74 8.62% 932 766 89.28% 0 0.00% 840 97.90% CUW36801 BDPL Reliability Upgrade - Tunnel WD-2531 Michels/Jay Dee/Coluccio 1-Apr-10 100% 1857 396 21.32% 2253 0 0.00% 0 0.00% 396 21.32% CUW36802 BDPL Reliability Upgrade - Pipeline 5 - Peninsula WD-2542 Mountain Cascade 10-Mar-10 100% 764 1336 174.87% 2100 0 0.00% 0 0.00% 1336 174.87% CUW36802 BDPL 5 Cordilleras Micro-tunnel WD-2665 Steven P Rados Inc. 1-Feb-12 100% 353 366 103.68% 719 0 0.00% 0 0.00% 366 103.68% CUW38001 BDLP Nos. 3 & 4 Crossover Facilities WD-2568 Shimmick Construction 13-Jul-09 100% 1160 34 2.93% 1194 0 0.00% 0 0.00% 34 2.93% CUW36802 BDPL Reliability Upgrade - Pipeline 5 - East Bay WD-2541 Ranger Pipeline 7-Jan-10 100% 762 129 16.93% 891 0 0.00% 0 0.00% 129 16.93% CUW36301 SCADA System - Phase II WD-2589 Ranger Pipelines 14-Dec-09 100%** 350 90 25.71% 440 0 0.00% 0 0.00% 90 25.71% CUW35301 BDPL Nos. 3 & 4 Crossovers/Isolation Valves WD-2507 Ranger Pipelines 21-Aug-06 100% 400 30 7.50% 430 0 0.00% 0 0.00% 30 7.50% Pending Change Orders Potential Change Orders Total Change Orders Appendix A - Table 7b (March Yr 2022)
Status of Construction Contract Cost Change Orders (Excludes Non WSIP Funds and Projects Not Covered by WSIP Contingency (BHR))
Project No. Contract Name Construction
Contract No. Construction Contractor Notice To Proceed
(NTP) Date
Percent
Construction
Completion
Awarded
Contract
Duration to
Substantial
Completion
Approved Change Orders
1 of 3
Approved
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Revised
Contract
Duration
Pending
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Potential
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Total CO Time
Added in
Calendar Days
Percent of
Original
Contract
Duration
(Col 1) (Col 2) (Col 3) (Col 4) (Col 5) (Col 6) (Col 7) (Col 8) (Col 9) (Col 10) (Col 11) (Col 12) (Col 13) (Col 14) (Col 15) (Col 16) Pending Change Orders Potential Change Orders Total Change Orders Appendix A - Table 7b (March Yr 2022)
Status of Construction Contract Cost Change Orders (Excludes Non WSIP Funds and Projects Not Covered by WSIP Contingency (BHR))
Project No. Contract Name Construction
Contract No. Construction Contractor Notice To Proceed
(NTP) Date
Percent
Construction
Completion
Awarded
Contract
Duration to
Substantial
Completion
Approved Change Orders
BDL Reliability Upgrade - Relocation - 8-Feb-10 100% 519 0 0.00% 519 0 0.00% 0 0.00% 0 0.00% SFPUC/EBMUD Intertie - 18-Jan-05 100% 1108 0 0.00% 1108 0 0.00% 0 0.00% 0 0.00% Peninsula Region
CUW2596 Harry Tracy Water Treatment Plant Lng Term
Imoprovements WD-2596 Kiewit Infrastructure West 16-Mar-11 100% 1445 518 35.85% 1963 0 0.00% 0 0.00% 518 35.85% CUW35401 Crystal Springs San Andreas Transmission Upgrade WD-2601 Kiewit Infrastructure West 1-Dec-10 100% 980 512 52.24% 1492 0 0.00% 0 0.00% 512 52.24% CUW36702 Peninsula Pipeline Seismic Upgrade WD-2727 Ranger Pipelines 28-Apr-14 100% 560 113 20.18% 673 0 0.00% 0 0.00% 113 20.18% CUW37801 Crystal Springs Pipeline No. 2 Replacement Project WD-2555 Ranger Pipeline 28-Feb-11 100% 681 59 8.66% 740 0 0.00% 0 0.00% 59 8.66% CUW35401 Lower Crystal Springs Dam Improvements WD-2591 Kiewit Infrastructure West 31-Jan-11 100% 347 110 31.70% 457 0 0.00% 0 0.00% 110 31.70% CUW36105 Pulgas Balancing - Modifications of Existing
Dechloramination Facility WD-2607 NCCI, Inc. 22-Sep-10 100% 405 360 88.89% 765 0 0.00% 0 0.00% 360 88.89% CUW36103 Pulgas Balancing - Structural Rehabilitation & Roof Replacement WD-2573 S J Amaroso Construction 30-Nov-09 100% 587 54 9.20% 641 0 0.00% 0 0.00% 54 9.20% CUW39101 Baden and San Pedro Valve Lots Improvements WD-2556 JMB Construction, Inc. 8-Apr-09 100% 725 272 37.52% 997 0 0.00% 0 0.00% 272 37.52% CUW35601 New Crystal Springs Bypass Tunnel WD-2498 JV-Shank/Balfour Beatty 1-Dec-08 100% 986 0 0.00% 986 0 0.00% 0 0.00% 0 0.00% CUW36102 Pulgas Balancing - Discharge Channel Modifications WD-2563 Anderson Pacific 19-May-09 100% 245 0 0.00% 245 0 0.00% 0 0.00% 0 0.00% CUW36603 HTWTP Short-Term Improvements (Coagulation &
Flocculation/Remaining Filters) WD-2564 NTK Contruction, Inc. 10-Jul-08 100% 603 0 0.00% 603 0 0.00% 0 0.00% 0 0.00% CUW37901 San Andreas Pipeline No. 3 Installation WD-2513 Mountain Cascade 27-Aug-09 100% 610 63 10.33% 673 0 0.00% 0 0.00% 63 10.33% CUW35701 Adit Leak Repair WD-2510 NTK Contruction, Inc. 9-Apr-07 100% 335 -3 -0.90% 332 0 0.00% 0 0.00% (3) -0.90% CUW36101 Pulgas Balancing Inlet/Outlet WD-2310A NCCI, Inc. 6-Sep-05 100% 150 -25 -16.67% 125 0 0.00% 0 0.00% (25) -16.67% Cross Connection Controls - 1-Jun-05 100% 1274 0 0.00% 1274 0 0.00% 0 0.00% 0 0.00% CUW36601 HTWTP Demo Filters WD-2478 NTK Contruction, Inc. 14-Sep-05 100% 150 -4 -2.67% 146 0 0.00% 0 0.00% (4) -2.67% CUW36901 Capuchino Valve Lot WD-2508 NTK Contruction, Inc. 29-Jan-07 100% 495 -94 -18.99% 401 0 0.00% 0 0.00% (94) -18.99% San Francisco Regional Sub Region
CUW37201 University Mound Reservoir - North Basin WD-2539 S J Amaroso Construction 3-Aug-09 100% 690 61 8.84% 751 0 0.00% 0 0.00% 61 8.84% CUW35801 Sunset Reservoir - North Basin WD-2406R Shimmick Construction 10-Oct-06 100% 710 98 13.80% 808 0 0.00% 0 0.00% 42 5.92% CUW 30101 Regional GW Storage and Recovery (Contract B) WD-2668 Ranger Pipelines 6-Apr-15 99% 1,007 1,450 143.99% 2,457 0 0.00% 0 0.00% 1450 143.99% Security Projects
CUW36302 System Security Upgrade 00A WD-2653 Various 15-Jun-11 100% 1828 0 0.00% 1828 0 0.00% 0 0.00% 1828 100.00% CUW36302 System Security Upgrade 00B WD-2661 Various 19-Dec-11 100% 1096 586 53.47% 1682 0 0.00% 0 0.00% 2268 206.93% CUW36302 System Security Upgrade 00C WD-2707 Various 8-May-14 100% 603 839 139.14% 1442 0 0.00% 0 0.00% 2281 378.28% BHR Projects
2 of 3
Approved
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Revised
Contract
Duration
Pending
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Potential
Change Order
Time Added in
Calendar Days
Percent of
Awarded
Contract
Total CO Time
Added in
Calendar Days
Percent of
Original
Contract
Duration
(Col 1) (Col 2) (Col 3) (Col 4) (Col 5) (Col 6) (Col 7) (Col 8) (Col 9) (Col 10) (Col 11) (Col 12) (Col 13) (Col 14) (Col 15) (Col 16) Pending Change Orders Potential Change Orders Total Change Orders Appendix A - Table 7b (March Yr 2022)
Status of Construction Contract Cost Change Orders (Excludes Non WSIP Funds and Projects Not Covered by WSIP Contingency (BHR))
Project No. Contract Name Construction
Contract No. Construction Contractor Notice To Proceed
(NTP) Date
Percent
Construction
Completion
Awarded
Contract
Duration to
Substantial
Completion
Approved Change Orders
CUW38802 BHR, Homestead Pond, Peninsula Region WD-2641R Yerba Buena Engineering and Construction 30-Jan-12 100% 1718 129 7.51% 1847 0 0.00% 0 0.00% 129 7.51% CUW38802 BHR - SSAS & Upper San Mateo Creek, Peninsula
Region WD2651R Shimmick Construction 31-May-12 100% 1645 0 0.00% 1645 0 0.00% 0 0.00% 0 0.00% CUW38802 BHR, Goldfish Pond, Sunol Valley Region WD-2640 Yerba Buena Engineering and Construction 19-Sep-11 100% 1680 0 0.00% 1680 0 0.00% 0 0.00% 0 0.00% CUW38802 BHR, San Antonio Creek, Sunol Valley Region WD-2652 Gordon N. Ball Inc 27-Dec-11 100% 1830 123 6.72% 1953 0 0.00% 0 0.00% 123 6.72% CUW38802 BHR, Sheep Camp Creek, Sunol Valley Region WD-2666 Shimmick Construction 4-Sep-12 100% 1709 0 0.00% 1709 0 0.00% 0 0.00% 0 0.00% CUW38803 BHR, Goat Rock Management Unit, Sunol Valley
Region WD-2644I JDB Construction 15-May-13 100% 180 298 165.56% 478 0 0.00% 0 0.00% 298 165.56% CUW36802 BHR, Peninsula Vegetation Removal, Peninsula
Region WD-2654R NTK Construction,Inc 1-Feb-16 100% 750 0 0.00% 750 0 0.00% 0 0.00% 0 0.00% Final Completion
COLUMN DESCRIPTION: Substantial Completion
Columns 1-2: Regional projects with construction activities underway Future Projects Column 10: Revised construction contract amounts – that is, original construction contract award amount plus approved change orders (Column 7 + Column 8) Columns 3-4: Construction contract numbers and name of construction contractors Column 11: Total amounts of pending changes that are in process as proposed change orders, change order requests, or change orders prior to approval Column 5: Dates of construction notice to proceed Column 12: Pending change orders percentages of original construction contract award amounts Column 6: Percent completion of the projects' Construction Phase Column 13: Total amounts of potential changes that are in process as proposed change orders, change order requests, or change orders prior to approval Column 7: Original construction contract award amounts Column 14: Potential change orders percentages of original construction contract award amounts Column 8: Total amounts of change orders that have been approved to date Column 15 - The summation of Columns 8, 11, and 13 Column 9: Approved change orders percentages of original construction contract award amounts Column 16 - Total change orders percentages of original construction contract award amounts 3 of 3