DEPARTMENT

Infrastructure

AGENDA NO.

9d

MEETING DATE

July 12, 2022

APPROVAL:

COMMISSION

SECRETARY

Donna Hood

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Construction Closeout with Modification: Consent Calendar Project Manager: Saed Toloui

Accept Closeout with Modifications for Contract No. WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention

Summary of
Proposed
Commission Action:

Accept work performed by Trinet Construction, Inc., under Contract No. WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention; approve Modification No. 1 (Final), increasing the contract amount by $81,517, for a total contract amount of $3,967,817, and increasing the contract duration by 135 consecutive calendar days, for a total contract duration of 595 consecutive calendar days (approximately one year and eight months); and authorize final payment to the contractor.

Background: On July 14, 2020, by Resolution No. 20-0148, the San Francisco Public Utilities Commission (SFPUC) awarded Wastewater Enterprise Sewer System Improvement (SSIP) Program-funded Contract No. WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention, to Trinet Construction, Inc.

The original contract amount was $3,886,300 and the original contract duration was 460 consecutive calendar days.

Description of Scope
of Work:

The contract work locations are combined sewer discharge (CSD) structures at Jackson, Griffith, and Pierce streets in San Francisco, California. The contract work consisted of:
• Concrete rehabilitation of the CSD structures at Jackson and Griffith streets, including traffic routing work;
• Demolition of damaged concrete;
• Cleaning and treating exposed rebar with corrosion inhibitor; • Patching and coating with solids epoxy system;
• Injecting cracks and all appurtenant work required in accordance with the contract documents;
• Furnishing and installing backflow prevention systems to prevent the inflow from the bay into our system; and

Contract: WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention
Commission Meeting Date: June 28, 2022

• Decommissioning of the Pierce Street CSD in place by filling the structure with cellular concrete.

Changes to the
Contract under
Modification(s):

San Francisco Administrative Code section 6.22(h) requires that any cumulative increases in contract amount or duration in excess of 10% of the original contract amount or duration or any decrease in the contract amount in excess of 10% be approved by this Commission.

Modification No. 1 (Final) : Staff recomments approval of proposed Modification No. 1 (Final) to increase the contract amount by $81,517 (within the original 10% contingency) and increase
the contract
duration by 135 consecutive calendar days (exceeding the original 10% contingency), to add concrete spall and perform crack repair in the three CSDs, demolish more concrete at Pierce Street CSD, remove/re-install Jackson Street CSD bulkhead due to weather conditions, modif y Jackson Street CSD ceiling for installing the backflow prevention system, reconstruct the end walls at Griffith Street CSD, and adjust contract quantities to match actual quantities completed , for a total contract amount of $ 3,967,817 and a total contract duration of 595 consecutive calendar days.

Budget & Costs: Funding: Project No. CWWSIPCSCD04, CSD Backflow Prevention and Monitoring
Original Award Amount: $3,886,300
Modification No. 1 (Final) Amount: $81,517
Total Revised Contract Amount: $3,967,817

Schedule: Notice-To-Proceed Date: October 19, 2020
Original Duration: 460 consecutive calendar days
Modification No. 1 (Final) Duration: 135 consecutive calendar days Total Revised Contract Duration: 595 consecutive calendar days

Compliance With
Chapter 14B: Local
Business Enterprise
And Non-
Discrimination In
Contracting
Ordinance:

The Contract Monitoring Division (CMD) established a Local Business Enterprise (LBE) participation goal of 14% for this contract. T he contractor committed to a LBE participation of 14.15% with its bid submittal. Change orders to the contract added a large portion of work that required performance by a specialty marine/diving subcontractor, for which the LBE subcontractor was not licensed nor experienced to perform. CMD has determined that the contractor made a good faith effort to comply with its LBE subcontracting requirement by achieving a final LBE participation of 13.86% for this contract.

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

Attachments: CMD Memorandum

Contract: WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention
Commission Meeting Date: June 28, 2022

Site map of CSD locations

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, On July 14, 2020, by Resolution No. 20- 0148, this Commission awarded Wastewater Enterprise (WWE) Contract No. WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention, in the amount of $3,886,300, to the responsible bidder that submitted the lowest responsive bid, Trinet Construction, Inc.; and WHEREAS, The construction cont ract Notice To Proceed date was set for October 19, 2020; and
WHEREAS, The original contract amount was for $3,886,300 and the original contract duration was 460 consecutive calendar days; and
WHEREAS, San Francisco Administrative Code section 6.22(h) requires that any cumulative increase in contract amount or duration in excess of 10% of the original contract amount or duration or a decrease in the contract amount in excess of 10% of the original amount be approved by the Commission; and
WHEREAS, Staff recommends approval of Modification No. 1 (Final) to increase the contract amount by $81,517 (within the original 10% contingency) and to increase the contract duration by 135 consecutive calendar days (exceeding the original 10% duration contingency), to add concrete spall and perform crack repair in the three Combined Sewer Discharches ( CSDs) in the original contract scope , demolish more concrete at Pierce Street CSD, remove/re- install Jackson Street CSD bulkhead due to weather conditions, modify Jacks on Street CSD ceiling for installing the backflow prevention system, reconstruct the end walls at Griffith Street CSD, and adjust contract quantities to match actual quantities completed , for a total contract amount of $3,967,817 and a total contract duration of 595 consecutive calendar days; and WHEREAS, The Contract Monitoring Division has determined that the contractor made a good faith effort to comply with the Local Business Enterprise (LBE) subcontracting goal of 14% for this contract by achieving a final LBE participation of 13.86%; and WHEREAS, Funds are available from Project No. CWWSIPCSCD04, CSD Backflow Prevention and Monitoring; now, therefore, be it
RESOLVED, That this Commission hereby accepts work performed by Trinet Construction, Inc. for Contract No. WW-702R, Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention ; approves Modification No. 1 (Final) that increases the contract amount by $81,517, for a total contract amount of $3,967,817, and increases the contract duration by 135 consecutive calendar days, for a total contract duration of 595 consecutive calendar days; and authorizes final payment to the contractor.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of July 12, 2022.

Secretary, Public Utilities Commission

London N. Breed, Mayor
Carmen Chu, City Administrator

Romulus Asenloo, Director

1155 Market Street, 4th Floor, San Francisco, CA 94103 Telephone (415) 581-2310 Fax (415) 581-2351

CONTRACT MONITORING DIVISION

OFFICE OF THE CITY ADMINISTRATOR

MEMORANDUM
Date: June 10, 2022

To: Saed Touli, SFPUC
Jeff Young, SFPUC

From: Linda Rainaldi, CMD
Subject: Closeout for WW-702R Jackson, Griffith, and Pierce Streets Combined Sewer Discharge Rehabilitation and Backflow Prevention

The Contract Monitoring Division (“CMD”) has determined that Trinet Construction Inc. (“Trinet”) has substantially complied with the LBE subcontracting requirements associated with this project.

At the time the project was advertised, an LBE subcontracting requirement of 14% was established.

Trinet’s Subcontractor List (Section 00 43 36) reflected an LBE subcontractor participation commitment of 14.15%. Trinet was awarded the contract in the amount of $ 3,886,300.00. After two (2) change orders, the final contract amount is $ 3,967,816.10. At closeout, the LBE subcontracting participation is as follows:

Firm Status Scope of Work Original Credited
Contract Participation
Final Credited
Contract Participation
R&S
Construction
Management,
Inc.

SF LBE-
MBE
(Micro)
Concrete,
Furnish &
Install Flap
Gates
$550,000.00 14.15% $550,000.00 13.86%
TOTAL $550,000.00 14.15% $550,000.00 13.86%

Pursuant to the correspondence provided by the Prime and the SFPUC, the contract change orders impacted included a large portion of work which required a specialty marine/diving subcontractor to perform, of which R&S Construction Management, Inc. is not licensed nor experienced to perform. Per the Prime and the SFPUC, the contract increase which did include additional concrete work required that the work be performed by a crew who had 40-hour Hazwoper training. Per the Prime, and as confirmed by R&S, R&S was unable to provide a crew which met this requirement. R&S was provided their full scope of work.

Based on the foregoing, CMD concurs with the closeout of this contract.