Contract No. WW-706

CleanPowerSF Sfpuc Commission
July 12, 2022

Document
Contract No. WW-706
Meeting
July 12, 2022
Body
CleanPowerSF Sfpuc Commission
Original file
504 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

DEPARTMENT

Infrastructure Division

AGENDA NO.

9e

MEETING DATE

July 12, 2022

APPROVAL:

COMMISSION

SECRETARY

Donna Hood

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Construction Closeout with Modification: Consent Calendar Project Manager: Brian Carlomagno

Accept Closeout with Modifications for Contract No. WW-706, Oceanside Water Pollution Control Plant Egg-Shaped Digester Interior Liner Rehabilitation

Summary of
Proposed
Commission Action:

Accept work performed by Trinet Construction, Inc. under Contract No. WW-706, Oceanside Water Pollution Control Plant Egg- Shaped Digester Interior Liner Rehabilitation ; approve Modification No. 2 (Final), increasing the contract by $20,607 for a total contract amount of, $2,689,318, and decreasing the contract duration by 98 consecutive calendar days, for a total contract duration of 622 consecutive calendar days (approximately one year and nine months); and authorize final payment to the contractor.

Background: On June 23, 2020, by Resolution No. 20-0134, the San Francisco Public Utilities Commission (SFPUC) a warded Contract No. WW -706, Oceanside Water Pollution Control Plant Egg-Shaped Digester Interior Liner Rehabilitation, to Trinet Construction, Inc. The original contract amount was $2,461,000 and the original contract duration was 720 consecutive calendar days.

The objective of the project at t he Oceanside Water Pollution Control Plant was to repair defective and failed interior liner system materials within three of the egg-shaped digesters and to increase the reliability of the supporting ancillary system by replacing s pecified mechanical valves and appurtenances.

Description of Scope
of Work:

The contract work location was at the Oceanside Water Pollution Control Plant at 3500 Great Highway. The contract work consisted of:
• Cleaning and removing existing failed interior liners and installing new liners inside three Egg-Shaped Digesterss (No. 1, No. 2, & No.4);
• Performing interior liner review and inspection inside one Egg- Shaped Disgester (No. 3); and
Contract: WW-706, Oceanside Water Pollution Control Plant Egg-Shaped Digester Interior Liner Rehabilitation Commission Meeting Date: July 12, 2022

• Replacing various mechanical valves at each digester
including digester gas plug valves, digester sludge knife gate valves and plug valves.

Changes to the
Contract under
Modification(s):

San Francisco Administrative Code s ection 6.22(h) requires that any cumulative increases in contract amount or duration in excess of 10% of the original contract amount or duration or any decrease in the contract amount in excess of 10% be approved by this Commission.

Modification No. 1 increased the contract amount by $207,711 (within the original 10% cost contingency) due to additional mechanical and plumbing modifications and additional digester cleaning , for a total contract amount of $2,668,711

Modification No. 2 (Final): Staff recommends approval of Modification No. 2 (Final) to increase the contract amount by $20,607 (within the original 10% cost contingency) and decrease the contract duration by 98 consecutive calendar days, due to additional pipe and valve repairs, unclogging and flushing process piping associated with the digesters, and to reconcile unused allowance bid items , for a total contract amount of $2,689,318 and a total contract duration of 622 consecutive calendar days.

Budget & Costs: Funding: Project No. 10035390, OSP Egg Shaped Digester Project Original Award Amount: $2,461,000
Modification 1 Amount: $207,711
Modification No. 2 (Final) Amount: $20,607
Total Revised Contract Amount: $2,689,318

Schedule: Notice-to-Proceed Date: October 1, 2020
Original Duration: 720 consecutive calendar days
Modification No. 1 Duration: 0 consecutive calendar days Modification No. 2 Duration (Final): -98 consecutive calendar days Total Revised Contract Duration: 622 consecutive calendar days

Compliance With
Chapter 14B: Local
Business Enterprise
Utilization And Non-
Discrimination In
Contracting
Ordinance:

The Contract Monitoring Division (CMD) established a Local Business Enterprise (LBE) goal of 13% for this co ntract. The C ontractor committed to a LBE participation of 13.16% with its bid submittal. The CMD has determined that that the contractor complied with its LBE subcontracting goal by achieving a final LBE participation of 12.77%.

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

Attachments: 1. CMD Memorandum
Contract: WW-706, Oceanside Water Pollution Control Plant Egg-Shaped Digester Interior Liner Rehabilitation Commission Meeting Date: July 12, 2022

Oceanside Water Pollution Control Plant (OSP)
3500 Great Highway, San Francisco, CA 94132

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, On June 23, 2020, by Resolution No. 20- 0134, this Commission awarded Contract No. WW- 706, Oceanside Water Pollution Control Plant Egg- Shaped Digester Interior Liner Rehabilitation, in the amount of $2,461,000 to the responsible bidder that submitted the lowest responsive bid, Trinet Construction, Inc.; and
WHEREAS, The purpose for the Contract No. WW-706 project was to make repairs at the Oceanside Water Pollution Control Plant by removing defective and failed interior liner system materials within Egg-Shaped Digesters No. 1, No. 2 & No. 4 and applying a new liner system and replacing specified mechanical valves and associated process piping; and WHEREAS, Contractor Trinet Construction, Inc. has completed its work for Contract No.

WW-706, Oceanside Water Pollution Control Plant Egg- Shaped Digester Interior Liner Rehabilitation; and
WHEREAS, The construction contract Notice To Proceed date was set for October 1, 2020, with an original schedule of 720 consecutive calendar days , and the contractor completed the contract work in 622 consecutive calendar days on June 14, 2022; and WHEREAS, The original contract amount was for $2,461,000 and the original contract duration was 720 consecutive calendar days; and
WHEREAS, S an Francisco Administrative Code s ection 6.22(h) requires that any cumulative increase in contract amount or durati on in excess of 10% of the original contract amount or duration or and decrease in the contract amount in excess of 10% of the original amount be approved by the Commission; and
WHEREAS, Modification No. 1 increased the contract amount by $207,711 (within the original 10% contingency) due to additional mechanical and plumbing modifications and additional digester cleaning, for a total contract amount of $2,668,711; and WHEREAS, Staff recommends approval of proposed Modification No. 2 (Final) to increase the contract amount by $20,607 (within the original 10% contingency) due to additional pipe and valve repairs, unclogging and flushing process piping associated with the digesters, and to liquidate unused allowance bid items, for a total contract amount of $2,689,318, and to decrease the contract duration by 98 consecutive calendar days for a total contract duration of 622 consecutive calendar days; and
WHEREAS, The Contract Monitoring Division has dete rmined that the c ontractor complied with the established Local Business Enterprise (LBE) subcontracting goal of 13% for this contract by achieving a final LBE participation of 12.77%; and WHEREAS, Funds are available from Project No. 10035390, Oceanside Water Pollution Control Plant Egg Shaped Digester Project; now, therefore, be it

RESOLVED, That this Commission hereby accepts work performed by Trinet Construction, Inc. for Wastewater Enterprise, Renewal and Replacement Treatment Faciliti es Program-funded Contract No. WW- 706, Oceanside Water Pollution Control Plant Egg- Shaped Digester Interior Liner Rehabilitation; approves Modification No. 2 (Final), including an increase of $20,607, for a total contract amount of $2,689,318, and a duration decrease of 98 consecutive calendar days, for a total contract duration of 622 consecutive calendar days; and authorizes final payment to the contractor.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of July 12, 2022.

Secretary, Public Utilities Commission

London N. Breed, Mayor
Carmen Chu, City Administrator

Romulus Asenloo, Director

1155 Market Street, 4th Floor, San Francisco, CA 94103 Telephone (415) 581-2310; Fax (415) 581-2351

CONTRACT MONITORING DIVISION

OFFICE OF THE CITY ADMINISTRATOR

MEMORANDUM

Date: June 2, 2022

To: Brian Carlomagno, SFPUC
Daniel Alvarado, SFPUC

From: Jason Chow, CMD

Subject: CMD’s Closeout Review for WW-706 Oceanside Water Pollution Control Plant Egg- Shaped Digester Interior Liner Rehabilitation

The Contract Monitoring Division (“CMD”) has determined that Trinet Construction (“Trinet”), the prime contractor for this project, has complied with the Chapter 14B LBE subcontracting requirements associated with this project.

At the time the project was advertised, a n LBE subcontracting requirement of 13% was established.

Trinet’s Subcontractor List (Document 00 43 36) reflected an LBE subcontractor participation commitment of 13.16%. Trinet was awarded the contract in the amount of $ 2,461,000. After two (2) change orders, the final contract amount is $2,689,317.68. At closeout, the LBE subcontracting participation is as follows:

Firm Status Scope of Work
Original Credited
Contract
Participation
Final Credited
Contract Participation
Kearney
Plumbing

SF LBE- OBE
(Micro) Bid Item #6 Partial $320,000 13.00% $339,450 12.62% Baytech
Engineering

SF LBE- MBE
(Micro) Electrical $4,000 0.16% $4,000 0.15%
TOTAL $324,000 13.16% $343,450 12.77%

The SFPUC informed CMD that the change order work that were executed on this contract was unproportional to (not part of) the anticipated original scope of work. Therefore, the extra work did not fit the listed LBE firms’ expertise—Trinet did utilize its listed LBE firms to the full extent possible. As such, Trinet is short of its original overall LBE subcontracting participation commitment on this contract at contract closeout (referenced in the above table).

Based on the foregoing, CMD concurs with the closeout of this contract.