DEPARTMENT

Infrastructure

AGENDA NO.

10e

MEETING DATE

August 23, 2022

APPROVAL:

COMMISSION

SECRETARY

Donna Hood

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Construction Closeout: Consent Calendar
Contract Manager: Ryan Freeborn

Accept Closeout for Contract No.WD-2693, 8-Inch and 12-Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets

Summary of
Proposed
Commission Action:

Accept work performed by M Squared Construction, Inc., under Contract No.

WD-2693, 8-Inch and 12-Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets, for a final contract amount of $4,187,755, and a final contract duration of 585 consecutive calendar days (approximately one year and seven months); and authorize final payment to the contractor.

Background: To ensure reliable water deliver within San Francisco, the San Francisco Public Utilities Commission (SFPUC) required replacement of approximately 6,000 feet of ductile iron water conveyance pipe and ancillary water service pipe, construction of curb ramps, and restoration of pavement in specified locations.

On December 10, 2019, by Resolution No. 19-0230, this Commission awarded Contract No. WD-2693, 8- Inch and 12 -Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumber land Streets, to M Squared Construction, Inc. The original contract amount was $3,861,835 and the original contract duration was 585 consecutive calendar days.

Description of Scope
of Work:

The contract work was located on 21st Street from Shotwell Street to Potrero Avenue, Ford Street from Noe Street to Sanchez Street, Hancock Street from Noe Street to Church Street, Cumberland Street from Dolores Street to Guerrero Street, Bryant Street from 21st Street to 22nd Street, and Bryant Street from 24th Street to 25th Street in San Francisco, California . The work under this contract consisted of:
• Installation of approximately 3,400 feet of 4-inch, 6-inch, and 8-inch ductile iron pipe (DIP), 2,600 feet of 12-inch DIP, and 3,500 feet of ancillary 1-inch and 2-inch copper water service pipe; and • Curb ramp construction and pavement restoration.

Contract: WD-2693, 8-Inch and 12-Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets
Commission Meeting Date: August 23, 2022

Changes to the
Contract under
Modification(s):

San Francisco Administrati ve Code s ection 6.22(h) requires that any cumulative increases in contract amount or duration in excess of 10% of the original contract amount or duration or any cumulative decrease in the contract amount in excess of 10% of the original contract amount be approved by this Commission.

Modification Nos. 1 to 5 increased the contract amount by $325,920 (within 10% contingency) to complete hand excavation and shoring that supported the SFPUC City Distribution Division staff to perform water main connections at the intersection of Hancock and Church; to complete tree trimming associated with Contractor equipment clearance requirements at the intersection of 21 st
Street and Bryant Street; to procure ductile iron main fittings and gaskets necessary for the water main installation work ; to adjust curb ramp installation quantities associated with incorporating the final curb ramp designs into the contract documents ; and to adjust overall bid quantities based on completed work, for a total contract amount of $4,187,755.

Budget & Costs: Funding: Water Enterprise Local Conveyance/Distribution System Program Original Award Amount: $3,861,835
Modification Nos. 1 to 5 Amount: $325,920
Total Revised Contract Amount: $4,187,755

Schedule: Notice-to-Proceed Date: May 26, 2020
Original Duration: 585 consecutive calendar days
Modification Nos. 1 to 5 Duration: 0 consecutive calendar days Total Contract Duration: 585 consecutive calendar days

Compliance With
Chapter 14B: Local
Business Enterprise
And Non-
Discrimination In
Contracting
Ordinance:

The Contract Monitoring Division (CMD) established a Local Business Enterprise (LBE) goal of 20% for this contract. The contractor committed to a LBE participation of 20.68% with its bid submittal. The CMD has determined that that the contractor has substantially complied with the LBE subcontracting requirements associated with its LBE subcontracting goal by achieving a final LBE participation of 20.16%.

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

Attachments: 1. CMD Memorandum

Contract: WD-2693, 8-Inch and 12-Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets
Commission Meeting Date: August 23, 2022

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, To ensure reliable water deliver within San Francisco, the San Francisco Public Utilities Commission (SFPUC) required replacement of approximately 6,000 feet of ductile iron water conveyance pipe and ancillary water service pipe, construction of curb ramps, and restoration of pavement in specified locations; and WHEREAS, On December 10, 2019, by Resolution No. 19- 0230, this Commission awarded Contract No. WD -2693, 8-Inch and 12- Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets , in the amount of $3,861,835, to the lowest, responsible bidder that submitted the lowest responsive bid, M Squared Construction, Inc.; and
WHEREAS, Contractor M Squared Construction, Inc., has completed its work under Contract No. WD -2693, 8- Inch and 12- Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets; and
WHEREAS, The construction contract Notice -To-Proceed date was set for May 26, 2020, with an original schedule of 585 consecutive calendar days and the contractor completed the work in 585 consecutive calendar days on December 30, 2021; and WHEREAS, The original contract amount was for $3,861,835 and the original contract duration was 585 consecutive calendar days; and
WHEREAS, SFPUC issued Modification Nos . 1 to 5 for $325,920, with no change to contract duration, to complete hand excavation and shoring associated with water main connections by the SFPUC City Distribution Division at the intersection of Hancock and Church; to complete tree trimming associated with Contractor equipment clearance requirements at the intersection of 21
st Street and Bryant Street; to procure ductile iron main fittings and gaskets necessary for the water main installation work; to adjust curb ramp installation quantities associated with incorporating the final curb ramp designs into the cont ract documents; and to adjust overall bid quantities based on completed work, increasing the contract amount to $4,187,755; and
WHEREAS, The Contract Monitoring Division has determined that the contractor complied with the established Local Business Enterprise (LBE) subcontracting goal of 20% for this contract by achieving a final LBE participation of 20.16%; and WHEREAS, Funds are avai lable from the Water Enterprise Local Conveyance/Distribution System Program, now, therefore, be it RESOLVED, That this Commission he reby accepts work performed by M Squared Construction, Inc., under Contract No. WD -2693, 8-Inch and 12- Inch Ductile Iron Wa ter Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets , for a total contract amount of $4,187,755, and with a total contract duration of 585 consecutive calendar days; and authorizes final payment to the contractor.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of August 23, 2022.

Secretary, Public Utilities Commission

London N. Breed, Mayor
Carmen Chu, City Administrator

Romulus Asenloo, Director

1155 Market Street, 4th Floor, San Francisco, CA 94103 Telephone (415) 581-2310 Fax (415) 581-2351

CONTRACT MONITORING DIVISION
CITY ADMINISTRATOR’S OFFICE

Date: May 26, 2022

To: Brian Barry, SFPUC

From: Linda Rainaldi, CMD

Subject: Closeout for WD-2693 8-Inch and 12-Inch Ductile Iron Water Main Replacement on 21st, Bryant, Ford, Hancock, and Cumberland Streets

The Contract Monitoring Division (“CMD”) has determined that M Squared Construction Inc. (“MSC”) has substantially complied with the LBE subcontracting requirements associated with this project.

At the time the project was advertised, an LBE subcontracting requirement of 20% was established.

MSC’s Subcontractor List (Document 00 43 36) reflected an LBE subcontractor participation commitment of 20.68%. MSC was awarded the contract in the amount of $3,861,635. After five (5) change orders, the final contract amount is $4,187,754.76. At closeout, the LBE subcontracting participation is as follows:

Firm Status Scope of Work Original Credited
Contract Participation
Final Credited
Contract Participation
Basset
Engineering

SF LBE-OBE
(Micro) Water (partial) $368,500.00 9.54% $368,500.00 8.80% Ronan
Construction

SF LBE-OBE
(Micro)
Concrete
Flatwork, Saw
cutting, Traffic
Control
$430,000.00 11.14% $475,727.74 11.36%
TOTAL $798,500.00 20.68% $844,227.74 20.16%

Per the Prime, as confirmed by the SFPUC, the contract increases did not include Basset Engineering’s scope of work. As a result, Basset Engineering was provided the fullest extent of their scope of work.

Based on the foregoing, CMD concurs with the closeout of this contract. If there are any questions, please contact me at 415.754.3227.