AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
DEPARTMENT Business Services AGENDA NO. 9
MEETING DATE February 14 , 2023
Adopt the SFPUC 10-Year Capital Plan for FY 2023-24 to FY 2032-33: Regular Calendar Manager: Laura Busch
Summary of
Proposed
Commission Action:

Public Hearing to consider and possible action to adopt the San Francisco Public Utilities Commission 10 -Year Capital Plan for FY 202 3-24 through FY 2032-33 totaling $8,788,740,352.

Background &
Description:

Background
Under Charter Section 8B.123, this Commission must hold public hearings on an annual basis to review, update, and adopt a Long- Term Capital Improvement Program (the “10 -Year Capital Plan” or “Capital Plan”) and a Long-Range Financial Plan (“10- Year Financial Plan” or “Financial Plan”). The Capital Plan is to contain a list of projects to be executed during the 10- year planning horizon, including cost estimates and schedules. The Financial Plan is to contain estimates of operations and maintenance expenses, repair and replacement costs, debt costs, and projected rate increases. Together, the two plans provide visibility into the capital investment required to meet service levels and the rate impacts of these investments. In addition, they serve as a basis and supporting documentation for the Commission’s capital budget and the issuance of revenue bonds and other indebtedness to support the SFPUC capital program.

The SFPUC General Manager and staff presented the preliminary proposed SFPUC 10-Year Capital Plan for FY 2023-24 through FY 2032- 33 to the Commission at a duly noticed public meeting on January 30, 2023, for the Water Enterprise, Wastewater Enterprise, and Hetch Hetchy Water and Power (including CleanPowerSF). The project details presented at those public meetings, including a list of projects, cost estimates, and schedules are attached.

A Capital Plan report describing the SFPUC’s final adopted 10- year Capital Plans has also been prepared and is attached (see attachment B).

This is the first time such a document has been prepared, and it describes the evolution of the C apital Plan, the process to develop the plan, the context and challenges that were addressed and how costs were constrained. It also contains project overviews and details of deprioritized projects not included in the plan.

APPROVAL:

COMMISSION
SECRETARY Donna Hood

Authorize: Adoption of 10-Year Capital Plan
Commission Meeting Date: February 14, 2023

Capital Plan Approach
The SFPUC 10-Year Capital Plan provides an assessment of the agency’s capital needs aligned with the Commission’s Strategic Plan goals and the required investments to meet those needs.

During the Capital Budget discussions in January 2022, SFPUC committed to developing a balanced FY 2023- 24 Capital Budget and a 10-Year Capital Plan for Commission review and approval in February 2023. The SFPUC has undertaken an extensive effort over the past year to develop a capital budget and 10 -year plan that is both deliverable and affordable to our ratepayers. Staff from across the agency have been working diligently and collaboratively over the last year to build capital plan proposals that are both realistically deliverable and financially prudent. Work continues across the agency to improve our capital planning and delivery in the long term.

This 10 Year Capital P lan update represents an 11% reduction in total size from last year’s proposed expendi tures, going from $9.9 Billion last year to $8.8 Billion this year. This significant reduction shows the many hard choices and tradeoffs we made as an agency to constrain capital spending, taking into account our ability to spend the money and keep our rate growth affordable in the long term. These choices included reviewing existing project balances to ensure there was a plan in place to spend those funds before new funding was requested, prioritizing projects based on risk metrics, and rightsizing budgets based on delivery capacity.

Capital Plan Development Process
Between July -August 2022, the Budget, Project Controls and Strategy, Innovation & Change (SIC) teams rolled out enhanced guidance to support the development of a balanced FY 2023 -24 Capital Budget and a 10-Year Capital Plan by February 2023.

Beginning in September through mid- November 2022, weekly Budget Steering Committee meetings were held. These meetings were chaired by the Deputy General Manager, AGM of Infrastructure, and the Chief Financial Officer and attended by the AGMs of each enterprise plus staff.

The Steering Committee jointly reviewed the capital plans as they were developed. Discussions included overall financial planning and strategy, project priorities, and ultimately the hard choices to develop plans that were deliverable and affordable. The final recommendation of the Steering Committee was brought to the General Manager for his review and approval at the end of November.

Additionally, the SFPUC Infrastructure Bureau performed an assessment of SFPUC’s ability to deliver proposed projects looking at historic versus planned spending and aligning project plans with available delivery resources.

Overview of Proposed Capital Plan
The attached proposed 10-Year Capital Plan for FY 2023-24 through FY 2032-33 (Attachment A), contains project summaries for each Enterprise, as well as the individual project data sheets describing each project’s projected scope, schedule, and cost over the 10 -year period.

The table below compares the Proposed FYE 2024-2033 Capital Plan and the prior year’s FYE 2023-2032 approved plan. The costs included in this proposed Capital Plan update have decreased $1.1 billion (11.3%) as compared to last year’s plan.

10-Year Capital
Plan
FYE 2023-2032 FYE 2024-2033 Change
Amount
Change
Wastewater 6,126,993,323 4,879,378,510 (1,247,614,813) (20.4) Water 2,127,938,750 2,263,905,780 135,967,030 6.4
Hetch Hetchy
Water
974,442,211 976,897,145 2,454,934 0.3
Hetch Hetchy
Power
611,048,936 595,522,989 (15,525,947) (2.5)
CleanPowerSF 64,529,992 73,035,928 8,505,936 13.2
Total $9,904,953,212 $8,788,740,352 $(1,116,212,860) (11.3)

Wastewater Enterprise: The 10- year Capital Plan for Wastewater is $4.9 billion and is comprised of $2.9 billion for the SSIP, $1.6 billion for the Collection System and Treatment Facilities Renewal and Replacement Programs, and $400 million for other facil ities improvements The $1.2 billion decrease includes $636 million in the Sewer System Improvement program (SSIP) overall budget, $599 million in Renewal and Replacement Programs Collection System and Treatment Facil ities Projects and $13 million for other Wastewater Facilities Improvement Projects.

Water Enterprise: The 10-year Capital Plan for Water is $2.3 billion and is comprised of $ 1.2 billion for Regional projects and $1.1 billion for Local projects. The $135 million increase includes $80 million in the Regional Program of which $70 million is for the Palo Alto Pipeline Replacement Project in FY 32 -33 to be paid by wholesale water customers and $55 million for local Water Supply ($23 million), Reservoirs ($21 million) and other Local projects ($11 million).

Hetch Hetchy – The Hetch Hetchy 10 -year Capital Plan is $1.6 billion and is comprised of $977 million for Hetchy Water and $595 million for Local Power projects. The re is a $2.5 million increase to Hetchy Water up-country Water, Power and J oint asset projects. Local Power Projects decreased $15.5 million including a $35 million decrease to Grid Connection Distribution projects offset by a $20 million increase to other Hetchy Power projects including the PG&E Assets Acquisition project of $11.2 million, which is due to the consolidation of the entire project budget into the capital budget when previously this was in the operating budget.

CleanPowerSF: The CleanPowerSF 10- year Capital Plan is $73 million and includes a $8.5 million increase to fund the new Disadvantage Communities and Community Solar Green Tariff Programs.

Capital Plan Approval
If approved by the Commission, the SFPUC 10- Year Capital Plan will be submitted to the Mayor. The plans were presented to the Citywide Capital Planning Committee (CPC) on January 23, 2023.

The first year of the 10 -Year Capital Plan forms the SFPUC’s FY 2023 - 24 capital budget and is covered under a separate action item sche duled for February 14, 2023. Th e FY 2023- 24 Capital Budget Supplemental Appropriation Ordinances will be presented to the CPC at a future date. If necessary, changes to the capital plans will be presented at that time.

Result of Inaction: SFPUC would not be in compliance with Charter Section 8B.123.

Budget & Costs:
10-Year
Capital Plan
FYE 2024-2033
Uses
FYE 2024-2033
Sources
Wastewater 4,879,378,510 4,879,378,510
Water 2,263,905,780 2,263,905,780
Hetch Hetchy
Water
976,897,145 976,897,145
Hetch Hetchy
Power
595,522,989 595,522,989
CleanPowerSF 73,035,928 73,035,928
Total $8,788,740,352 $8,788,740,352

Environmental
Review:

This action does not constitute a project under the California Environmental Quality Act (CEQA) Guidelines Sections 15060(c) and 15378(b)(4), because adoption of the Capital Plan involves creation of a government funding mechanism or other fiscal activities and does not involve any commitment to any specific project w hich may result in a potentially significant impact on the environment. The SFPUC will consider approval of projects to be funded through this Capital Plan only after completing any environmental review required by CEQA, Administrative Code Chapter 31, and Proposition E (approved by the voters in 2002 for water and wastewater projects).

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

Attachments: Attachment A: SFPUC 10-Year Capital Plan FYE 2023-2032 and Project Datasheets
Attachment B: 10-Year Capital Plan Report

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, Under San Francisco Charter Section 8B.123, the San Francisco Public Utilities Commission must annually hold public hearings to review, update, and adopt a long - term Capital Plan covering projects during the next 10 -year period, including project information, cost estimates and schedules; and

WHEREAS, The SFPUC General Manager and staff presented the proposed SFPUC 10-Year Capital Plan for FY 2023-24 through FY 2032-33 for the Water Enterprise, Wastewater Enterprise, and Hetch Hetchy Water and Power, including the Power Enterprise and CleanPowerSF, to the Commission at a public hearing held on January 30, 2023, and such presentations included a list of projects, cost estimates, and schedules, together comprising the SFPUC 10-Year Capital Plan; and

WHEREAS, On February 14, 2023, staff presented as Attachment A to the staff report the proposed SFPUC 10-Year Capital Plan Summaries FYE 2024-2033 and Project Datasheets, a copy of which is on file with the Commission Secretary; and

WHEREAS, The SFPUC 10-Year Capital Plan provides an assessment of the agency’s capital needs align ed with the Commission’s Strategic Plan goals and the investments to meet those needs; and

WHEREAS, As a preliminary step to 10 -Year Capital Plan development, a baseline review of all existing project appropriations was completed for potential close-out or repurposing to new capital budget needs; and

WHEREAS, The SFPUC Infrastructure Bureau reviewed and validated all 10 -Year Capital Plan project submittals for a consistent and comprehensive capital planning approach across the agency comprised of individual project datasheets describing the project budget, schedule, and scope; and

WHEREAS, Capital Plan project quality review process assured the Capital Plan meets the Enterprise’s infrastructure needs, reflects a sound project prioritization process, and supports affordability by promoting efficient use of ratepayer funds; and

WHEREAS, The SFPUC Capital Plan development process included an assessment of SFPUC’s ability to deliver projects looking at historic versus planned spending and aligning project plans with available delivery resources; and

WHEREAS, SFPUC staff will continue the capital planning review process over the coming year with a focus on project deliverability, prudent prioritization, realistic phasing of projects, and understanding the resources available to implement our plans; and

WHEREAS, This action does not constitute a project under the California Environmental Quality Act (CEQA) Guidelines Sections 15060(c) and 15378(b)(4), because adoption of the Capital Plan involves creation of a government funding mechanism or other fiscal activities and does not involve any commitment to any specific project which may result in a potentially significant impact on the environ ment; and the SFPUC will consider approval of projects to be funded through this Capital Plan only after completing any environmental review required by CEQA, Administrative Code Chapter 31, and Proposition E (approved by the voters in 2002 for water and wastewater projects); and

WHEREAS, The Commission -approved 10-Year Capital Plan for FY 202 3-24 to FY 2032-33 will be submitted to the Mayor and was presented to the City’s Capital Planning Committee on January 23, 2023; and

WHEREAS, The SFPUC’s 10-Year Capital Plan is used to develop the agency’s capital budget, 10- Year Financial Plan, projected debt issuances, and estimated rate changes; now, therefore, be it

RESOLVED, That the Commission hereby adopts the SFPUC 10-Year Capital Plan for FYE 2024-2033 comprised of the project summaries and project datasheets included in Attachment A presented to the Commission on February 14, 2023, which describes project costs, scope, and schedule over the 10-year period with total costs as follows:

10-Year
Capital Plan
FYE 2024-2033
Uses
FYE 2024-2033
Sources
Wastewater 4,879,378,510 4,879,378,510
Water 2,263,905,780 2,263,905,780
Hetch Hetchy
Water
976,897,145 976,897,145
Hetch Hetchy
Power
595,522,989 595,522,989
CleanPowerSF 73,035,928 73,035,928
Total $8,788,740,352 $8,788,740,352

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of February 14, 2023.

Secretary, Public Utilities Commission
FY 2023-24 to FY 2032-33 10-Year Capital Plan

1 SFPUC FY 2023-24 to FY 2032-33 10-Year
Capital Plan

Adopted February 14, 2023

Contents

1. Executive Summary ....................................................................................... 2

2. Capital Plan Evolution .................................................................................... 4

3. Budget Context and Hard Choices to Constrain Costs ................................... 7

4. Capital Planning Process ............................................................................. 14

5. Water Capital Plan ....................................................................................... 16

6. Hetch Hetchy Water Capital Plan ................................................................. 23

7. Wastewater Capital Plan .............................................................................. 28

8. Hetch Hetchy Power Capital Plan ................................................................ 36

9. CleanPowerSF Capital Plan......................................................................... 41

10. Affordability ............................................................................................... 43

11. Next Steps ................................................................................................ 44

FY 2023-24 to FY 2032-33 10-Year Capital Plan

2 1. Executive Summary
The SFPUC’s balanced FY 2023-24 to FY 2032-33 capital plan totals $8.8 Billion (B). The first year of the capital plan represents SFPUC’s FY 2023-24 capital budget for each of the three enterprises. The Wastewater Enterprise has the largest share of the plan at 55%, followed by Water at 26%, Hetchy Water at 11% and Power (including CleanPowerSF) at 8%. Key projects funded in this capital plan include the completion of the Biosolids Digester Facility Project, the rehabilitation and improvement of Mountain Tunnel, stormwater improvements and flood resistance, assessment of Public Power expansion and repair and replacement of our sewer and water mains throughout the system.

The purpose of capital investments is to extend the useful life of our infrastructure and provide continued reliable and compliant operation of our system. Capital investments are essential for the reliable delivery of clean drinking water, the protection of public health and the environment, including the San Francisco Bay and Pacific Ocean, and the continued delivery of clean energy for municipal services. The SFPUC 10-Year Capital Plan provides an assessment of the agency’s capital needs aligned with the Commission’s strategic goals, as well as the required investments to meet those needs.

Funding capital expenditures is the most significant portion the SFPUC operating budget. The capital plan is 75% debt funded and 25% revenue funded. Debt service to support capital expenditures as well as revenue-funded (i.e. cash-funded) capital expenditures make up over one third of the total operating budget, a share that is projected to grow to half over the 10-year period.

The table below shows the capital plan by enterprise.

Table 1. FY2023-24 to FY 2032-33 SFPUC Capital Plan
$million FY 23-24 FY 24-25 FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 Total Uses
Water 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2,263.9 Wastewater 985.5 894.5 818.4 521.1 353.6 280.5 232.7 214.7 253.2 325.2 4,879.4 Hetchy-Water 85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9 Hetchy-Local
Power

21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5 CleanPowerSF 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0 Total Uses 1,384.5 1,568.1 1,510.3 1,092.2 778.2 556.5 475.6 420.2 450.4 552.9 8,788.7

Sources
Revenue Funded 154.3 217.7 230.5 222.1 216.3 234.6 241.2 237.5 256.4 225.1 2,235.6 Debt Funded 1,230.2 1,350.4 1,279.8 870.1 561.9 322.0 234.4 182.7 193.9 327.7 6,553.1 Total Sources 1,384.5 1,568.1 1,510.3 1,092.2 778.2 556.5 475.6 420.2 450.4 552.9 8,788.7

FY 2023-24 to FY 2032-33 10-Year Capital Plan

3 Because the Capital Plan is SFPUC’s single largest
cost driver, it is the most significant driver of rate
growth for our customers. The SFPUC has
undertaken an extensive effort to develop a capital
budget and 10-year plan that is both deliverable
and affordable to our ratepayers. Staff from across
the agency have been working diligently and
collaboratively over the last year to build capital plan proposals that are both realistically deliverable and
financially prudent.

During last year’s budget process, it became
apparent that there had been a past mismatch
between capital budgeting and our ability to deliver
projects within the planned timeframe, which led to
large, unencumbered balances being carried forward
from year to year across the agency’s project portfolio.

We began the task of trying to right -size the capital plan in 2021 but realized that the work needed would take
more time than we had available before last year’s
budget was adopted. We ended up moving forward with a one- year FY 2022-23 capital budget appropriation and a 10-year capital plan that was partially unbalanced, recognizing the further work we needed to do. We committed to bringing a balanced FY 2023-24 budget, and 10-year capital plan to the Commission in February 2023.

This year’s balanced budget and capital plan was also developed in the context of several challenges facing the agency. These include ongoing drought coupled with extreme storm events, inflationary pressures, and an unstable economy as we emerge from the pandemic. In addition, we face internal challenges including hiring and retention of staff, and growing capital needs. These factors affect our costs and rates, our customers’ ability to pay, and our ability to deliver our capital program. The proposed capital plans and their associated expenditure plans have been incorporated into the SFPUC’s 10-year financial plans which project rate adjustments for the Water, Wastewater, and Power enterprises. Over the past ten years, the combined water and wastewater bill has increased over 75%.

The financial plans project an increase in the combined water/wastewater bill of 90% over next ten years, underscoring the importance of constraining our capital costs.

Given our commitment to our infrastructure as well as facing these challenges, over the past year the agency refocused on deliverability and affordability. This plan update represents an 11% reduction in total size from last year’s proposed expenditures, going from $9.9 B last year to $8.8 B this year. This significant reduction shows the many hard choices and tradeoffs we made as an agency to rethink capital spending, taking into account our ability to spend the money and keep our rate growth affordable in the long term. These choices included reviewing existing project balances to ensure there was a plan in place to spend those funds before new funding was requested, prioritizing projects based on risk metrics, and rightsizing budgets based on delivery capacity. This report includes detailed information about how the capital plan evolved, the process we followed over the past year and the work that remains to continue improving our capital planning and delivery capabilities. This report also details the main projects that are included in this plan, as well as those that were deprioritized to constrain costs.

Figure 1. FY2023-24 to FY 2032-33 Capital Plan

FY 2023-24 to FY 2032-33 10-Year Capital Plan

4 2. Capital Plan Evolution
During last year’s budget process, we began the process of trying to rightsize the capital plan for deliverability and affordability. However, the plan expenditures still grew due to cost increases, expanding scope and identified investment needs. It became clear during the Fall 2021 that a greater effort was needed to complete a developed plan that could realistically deliver capital projects in the timeframe they were budgeted for, taking affordability factors into account. Instead of balancing the capital plan by simply assuming long term rate increases, we took the decision to move forward with an unbalanced 10-Year Capital Plan and only proposed a one-year balanced capital budget for FY 2022- 23, as we continued to work on refining our capital planning process. Our commitment to the Commission was to revisit the both the FY 2023-24 capital budget and 10-Year Capital Plan.

FY 2022-23 Capital Plan Update (Last Year)
Last year’s Capital Plan had total expenditures (uses) of $9.9 B and total sources of $8.6 B leading to a 13% imbalance. The following table summarizes the entire capital plan.

Table 2. FY2022-23 to FY 2031-32 Capital Plan
$million FY 22-
23 FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 Total
Uses
Water 111.2 389.7 489.7 364.2 219.3 121.3 134.6 109.0 102.0 86.9 2,127.9 Wastewater 687.2 953.1 1,014.8 934.4 580.7 455.2 374.0 352.0 353.0 422.6 6,127.0 Hetchy
Water 114.9 151.8 203.6 146.3 82.7 70.9 60.5 42.5 59.4 41.8 974.4 Hetchy
Power 66.2 32.7 83.1 85.6 85.3 77.9 51.1 45.9 43.2 40.1 611.0 Clean
PowerSF 3.7 2.2 1.9 1.9 1.6 1.6 1.6 1.8 20.0 28.3 64.5 Total Uses 983.3 1,529.5 1,793.0 1,532.5 969.6 726.8 621.7 551.2 577.7 619.7 9,905.0

Sources 983.3 1,276.6 1,508.3 1,286.6 826.3 628.0 550.4 490.6 517.2 548.1 8,615.4 Surplus/
(Shortage)
- (252.9) (284.7) (245.9) (143.3) (98.8) (71.3) (60.6) (60.5) (71.6) (1,289.6) FY 2023-24 Capital Plan Update (This Year)
This year’s balanced Capital Plan has total expenditures (uses) of $8.8 B and total sources of $8.8 B.

The following table summarizes the entire capital plan, followed by a table for each enterprise.

Table 3. FY2023-24 to FY 2032-33 Capital Plan
$million FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Uses
Water 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2,263.9 Wastewater 985.5 894.5 818.4 521.1 353.6 280.5 232.6 214.7 253.2 325.2 4,879.4 Hetchy Water 85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9 Hetchy Power 21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5 CleanPowerSF 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0 Total Uses 1,384.5 1,568.1 1,510.3 1,092.2 778.2 556.5 475.6 420.2 450.3 552.9 8,788.7

Sources
Revenue
Funded
154.3 217.7 230.5 222.1 216.3 234.6 241.2 237.5 256.4 225.1 2,235.6 Debt Funded 1,230.2 1,350.4 1,279.8 870.1 561.9 322.0 234.4 182.7 193.9 327.7 6,553.1 Total Sources 1,384.5 1,568.1 1,510.3 1,092.2 778.2 556.5 475.6 420.2 450.3 552.9 8,788.7 FY 2023-24 to FY 2032-33 10-Year Capital Plan

5 Water
Table 4. Water FY2023-24 to FY 2032-33 Capital Plan
$million FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Sources 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2263.9

Uses
Water -
Regional
181.5 188.0 191.5 176.0 180.0 53.1 26.6 23.5 22.1 92.9 1,135.3 Water -Local 108.5 249.3 252.1 161.4 65.4 65.0 58.7 60.2 58.3 49.7 1,128.6 Water-Totals 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2,263.9 Hetch Hetchy Water
Table 5. Hetch Hetchy Water FY2023-24 to FY 2032-33 Capital Plan $million FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Sources 85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9

Uses
Hetchy
Water-Water

48.9 59.4 31.1 16.4 5.3 4.7 4.8 4.9 5.0 5.1 185.6 Hetchy
Water-Power

0.0 32.2 27.1 39.6 14.4 38.9 29.8 11.5 10.3 19.4 223.3 Hetchy
Water-Joint

37.0 64.0 94.4 85.6 74.9 56.0 65.3 41.1 32.1 17.7 568.1 Hetchy
Water Total

85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9

Wastewater
Table 6. Wastewater FY2023-24 to FY 2032-33 Capital Plan $million FY 23-24 FY 24-25 FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 Total Sources 985.5 894.5 818.4 521.1 353.6 280.5 232.7 214.7 253.2 325.2 4879.4

Uses
SSIP 778.5 676.0 590.2 323.9 151.7 86.7 63.3 40.4 69.3 133.7 2,913.8 Non-SSIP 207.0 218.5 228.2 197.2 201.9 193.8 169.3 174.3 183.9 191.5 1,965.6 Wastewater
Total
985.5 894.5 818.4 521.1 353.6 280.5 232.7 214.7 253.2 325.2 4,879.4

Hetch Hetchy Power
Table 7. Hetchy Power FY2023-24 to FY 2032-33 Capital Plan $million FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Sources 21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5

Uses
Hetchy
Power

21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5 Hetchy
Power Total

21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5

FY 2023-24 to FY 2032-33 10-Year Capital Plan

6 CleanPowerSF
Table 8. CleanPowerSF FY2023-24 to FY 2032-33 Capital Plan $million FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Sources 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0

Uses
CleanPowerSF 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0 CleanPowerSF
Total

1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0 10-Year Capital Plan Comparison
The FY 2023-24 Capital Plan update represents an 11% reduction in total size from last year’s proposed expenditures, reflecting a decrease from $9.9 B last year to $8.8 B this year. This significant reduction shows the many hard choices we made as an agency to constrain capital spending, taking our ability to spend the money and keep our rate growth affordable in the long term.

The following table shows the capital plan comparison by enterprise:

Table 9. Capital Plan Comparison
$million Last Year: Uses This Year: Uses Difference
Water 2,127.9 2,263.9 136.0
Wastewater 6,127.0 4,879.3 (1,247.6)
Hetchy-Water 974.4 976.9 2.5
Hetchy-Power 611.0 595.5 (15.5)
CleanPowerSF 64.5 73.0 8.5
Total 9,905.0 8,788.7 (1,116.2)
As you can see from the table, the largest driver of reductions versus last year is the Wastewater Enterprise. Wastewater has the largest share of the capital plan and has also made the biggest reductions in capital requests. Their $1.2 B reduction was driven by decreases including $636 M in the Sewer System Improvement program (SSIP) overall budget, $599 M in Renewal and Replacement Programs, Collection System and Treatment Facilities Projects and $13 M for other Wastewater Facilities Improvement Projects.

In the Water Enterprise, the $136 M increase includes $80 M in the Regional Program of which $70 M is for the Palo Alto Pipeline Replacement Project in FY 2032-33 to be paid by wholesale water customers and $55 M for Local Water Supply ($23 M), Reservoirs ($21 M) and other Local projects ($11 M).

There is a $2.5 M increase to Hetchy Water (up-country Water, Power and Joint asset projects) and a $15.5 M decrease to Hetchy Local Power Projects including a $35 M decrease to Grid Connection Distribution projects, offset by a $20 M increase to other Hetchy Power projects including the Power Asset Acquisition project, $11 M. CleanPowerSF’s capital plan increased by $8.5 M to fund the new Disadvantaged Communities and Community Solar Green Tarif Programs.

Although this is a reduction overall, with the exception of Wastewater it is still an increase over the assumed sources in last year’s plan that were incorporated into last year’s 10-Year Financial Plan and rate projection. Additionally, for Wastewater, because so much of the cost is front- loaded, it will still impact rates due to the near-term cost increases vs last year’s assumed sources in the early years of the plan. These source increases to balance this year’s plan have been taken into account into the current 10-Year Financial Plan and will be paid for with rate increases impacting the later years of the financial plan with costs smoothed over the 30-year debt term.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

7 3. Budget Context and Hard Choices to Constrain Costs It is critical the capital budget and capital plan balances the SFPUC’s infrastructure and maintenance needs with long term customer affordability and our ability to deliver capital projects. Taken together, these challenges have informed the development of the capital plan and have meant that constraining costs was extremely important. We also recognized that solving the big questions of capital deliverability and affordability will not be done in this budget cycle alone, and is a long term project to align our delivery capacity and investment needs. However, significant progress has been made in this cycle.

Affordability
The Capital Plan is SFPUC’s single largest cost driver, and thus the most significant driver of rate growth for our customers. In FY 2023-24, around a third of the total
SFPUC operating budget is dedicated to supporting capital expenditures though cash-funded projects as well as paying debt service on debt-funded projects. Over the next ten years, this share is projected to rise to half of the operating budget. This increase is largely driven by the SSIP project in Wastewater, as well as Water’s overall capital plan. By enterprise, this increasing share of the budget going to capital is even more stark, as can be seen in table 10, two-thirds of Wastewater’s revenue will be going to pay for capital by the end of the ten-year period. Over the past ten years, the combined Water and Wastewater bill has increased by over 75%. The 10-Year Financial Plans project an increase in the combined Water/Wastewater bill of 90% over next ten years, in large part to cover these growing capital costs.

While this issue is particularly significant for the Water and Wastewater enterprises, power purchases are SFPUC’s second largest overall cost driver, which affects Hetch Hetchy Water and Power and CleanPowerSF. Over two-thirds of the combined HHWP and CleanPowerSF budget is dedicated to power purchases. Recently, there have been major increases in power prices, which have approximately tripled between 2020 and 2023. These rising costs are putting major pressure on the Power budget and rates, which must be balanced against their rising capital costs.

Another consideration is the size of the SFPUC’s debt portfolio. As of October 1, 2022, SFPUC’s outstanding debt was approximately $7.4 B in Bonds, Notes and Commercial Paper and an additional $2 B in executed Federal and State Loans. The 10-Year Capital Plan is approximately 75% debt funded, and as such the 10-Year Financial Plan projects an anticipated additional debt issuance by FY 2022-33 of $6.3 B. Increasing interest rates drive borrowing costs up. Thirty-year debt terms mean our decisions impact ratepayers decades into the future.

This capital plan was developed within the context of several other challenges facing the agency.

These challenges include the ongoing drought coupled with extreme storm events, inflationary pressures, and an unstable economy as we emerge from the pandemic. These newer challenges are coupled with the already existing challenge of aging infrastructure in our water, power, and sewer systems as well as increasing regulatory requirements. These challenges put pressure on our revenues and costs, as well as our ratepayers’ ability to absorb rate increases.

% Capital
FY 2023-24
% Capital FY
2032-33
Water 48% 51%
Wastewater 54% 66%
HHWP 3% 18%
Table 10. Share of operating budget
dedicated to capital uses

FY 2023-24 to FY 2032-33 10-Year Capital Plan

8 The Wastewater enterprise also faces risks related to potential regulatory obligations, which would add significant costs. At this time these costs are unknown but could be significant. We need to be prudent in constraining costs now in case we must cover these costs in the future.

Lastly, the Water and Wastewater enterprises are in the midst of a cost of service study, which involves an in-depth analysis of cost drivers and will culminate in a 3-year rate package that will be adopted by the Commission in Spring 2023. This means that there will be increased scrutiny of our rates from our ratepayers and other stakeholders, and it is important that we have done the work make sure our costs of service are fair and affordable.

Deliverability
We also face challenges to effectively deliver capital projects as planned. This is driven by factors including staffing shortages, contracting challenges, procurement challenges and delays, and growing capital needs. Many of these challenges were exacerbated during the pandemic. This led to a past mismatch between projected budgets and spending and significant unspent balances which carry forward from year to year and have been growing. At the beginning of FY 2022-23 the SFPUC had a balance of over $2.5 B in appropriated, unencumbered, capital funds. With $918 M being the highest agencywide annual capital spending, this balance represents approximately 2.5x maximum annual spending and an inefficient use of resources. To reduce these balances to a level closer to what is needed to fund projects, we must constrain our capital plans, taking existing project balances into account and set the future budget more closely to what is realistically deliverable in the time period in which it is planned.

Historical analysis of capital spending
To better understand the deliverability of our Capital Plan, the Finance Team conducted an evaluation of each enterprise's capital spending of budgeted funds and the change in total unspent appropriation balances from 2017 through 2022. Figure 2 illustrates the change in unspent appropriations for the Water, Wastewater, and Power enterprises, which have fluctuated from $1.8 B in FY 2017 to over $3 B in FY 2020, and with the exception of FY 2021, have increased steadily year over year. This is mostly driven by the emergence of the large-scale Sewer System Improvement Program in the Wastewater enterprise in recent years, as major capital projects began construction. As of the end of FY 2021-22, the of the total appropriation balance was $2.6 B, with only $1 B encumbered.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

9 Figure 2. Total Unspent Capital Appropriations for the Water, Wastewater , and Power Enterprises from FY 2017 through FY 2022

This trend of increasing appropriation balances indicates that the budget has historically and continues to be in excess of what is deliverable by the enterprises.

At the beginning of the 2022-23 fiscal year, excluding encumbered funds and adding the new appropriation for FY 2022-23, the SFPUC had over $2.5 B unencumbered balance available to spend— but has only spent at most $918 M in any single year. This almost $1.6 B difference represents capital budget inefficiency.

Table 11. Available balance as of July 1, 2022

Carried forward Balance FY 2022-23
appropriation
Encumbrances Total available balance

Water $719,865,133 $144,021,441 $168,056,114 $695,603,851 Hetchy Water $265,995,644 $122,592,889 $152,156,049 $236,325,141 Wastewater $1,477,158,192 $693,852,373 $789,199,041 $1,378,803,717 Hetchy Power $185,031,671 $71,377,994 $41,838,090 $214,416,431 CleanPowerSF $3,994,394 $3,727,592 $635,998 $7,082,351
Total $2,652,045,034 $1,035,572,289 $1,151,885,291 $2,532,231,491

Why has this inefficiency occurred? There are several factors, and it is a very complex question to answer. At a high-level, reasons include ambitious planning that does not align with the reality of project timing, resulting in appropriations occurring too early versus the actual project schedule. Furthermore,

FY 2023-24 to FY 2032-33 10-Year Capital Plan

10 complexities in budget and appropriation management make it hard to access funds and understand funding availability. In addition to rightsizing our budget, we are also undertaking a large-scale capital planning and delivery improvement program (discussed in section 11) that will address the internal factors that lead to underspending.

Overly ambitious capital plans and underspending, leading to the accumulation of large (up to $3 B in recent years) carryforwards, creates multiple risks for the enterprises.

Firstly, while we only issue revenue bonds “just in time” for capital spending (which means it does not directly cost us money to have a large unspent appropriation), our capital plans feed into our financial planning models which drive multi-year forward rate setting. Thus, overly ambitious capital plans may place an undue burden on rate payers and causes a risk of over collection which may draw the attention of rate payer groups. A successful Proposition 218 rate challenge could result in the SFPUC refunding revenues. It would also severely damage our reputation with the public, Commission, and Supervisors and may hinder our ability to enact future rate increases.

From a capital finance perspective, our capital plans are a focus of bond credit rating analysts and investors in assessing the credit worthiness and management of the SFPUC. Having overly ambitious capital budgets causes credit analysts to think capital costs will place a greater burden on our resources than is actually the case. And to the extent we do not deliver on our budgets, this could cause external parties to wonder about the appropriate management and oversight of our capital projects. Overly ambitious capital programs are considered a credit negative by rating agencies and may result in lower bond ratings, which could translate into higher interest rates. Debt service is already the SFPUC’s largest cost driver, so increased interest rates would have major impacts on the agency.

During the most recent budget process, the Board closely scrutinized our existing bond authorizations and questioned our request for further authority due to the fact we had such high unspent prior appropriations. These issues are gaining attention of both City Hall as well as the ratepayer.

Moreover, while the SFPUC does not issue bonds in anticipation of expenditures, because we use commercial paper first, having budgets which diverge so much from actual expenditures makes it difficult to manage the size of our commercial paper and timing of our bond issuance. For example, if we knew for certain that spending would be slower, we might be able to manage with smaller bank credit facilities on our commercial paper facilities, thus saving money and reducing our overall borrowing costs, especially at a time when borrowing costs are growing in the current rising interest rate environment. Another constraint is the SFPUC’s current $1.5 B commercial paper program has reached its capacity and cannot grow further, both from available banking credit support as well as administrative burden.

Therefore, it is crucial we right size the capital plan, and ensure what we plan for is deliverable in the timeframe it is budgeted.

Capital Project Deliverability Review
The proposed costs in this capital plan went through a rigorous development process to ensure planned expenditures are realistically deliverable within the proposed project schedules. When new capital budgets are proposed, the Infrastructure Division analyzes the deliverability (the ability to implement projects and spend budgets according to the proposed schedules) of the capital programs using both “bottom up” and “top down” approaches. Larger ongoing projects have regularly updated project plans with detailed staffing, contracting, and funding requirements to deliver the project, allowing oversight on alignment of schedules and budgets. In addition, the project controls systems provide data FY 2023-24 to FY 2032-33 10-Year Capital Plan

11 for verifying each project’s schedule and budget performance. The “bottom up” analysis includes a detailed review of the projects’ resource plans and spending capability, and adjustment of the budgets and schedules to align with any changes in scope or project constraints. For the “top down” analysis, each functional group within Infrastructure reviews staffing assignments to each project and determines if sufficient staffing and contracting resources are in place to deliver the projects. Finally, Infrastructure prepares a high-level resource estimate of total “full-time equivalent” staff needed to deliver all programs, separated by City staff and consultants, and reviews current staffing levels and vacancies compared to needs. Hiring plans, long-term staffing plans, and contracting plans are updated by Infrastructure management to reflect current and future resource needs.

For Enterprise-managed projects comprising 20-40% of the capital funding, the Enterprises work with Infrastructure to estimate annual funding that may be needed to meet the short-term repair and replacement (R&R) needs during the budget cycle. During past and this years’ budget cycles, Infrastructure focused greater attention to the deliverability review for ability to spend down already appropriated funds. The proposed capital budget includes realignment of existing funds instead of new funding requests for many projects to better spend down existing appropriations.

Overall, the deliverability review has brought to light many challenges and resource needs that have impacted deliverability. In general, the findings support that the current programs can be delivered with current staffing and contracting levels, but there is very little contingency built in for risks such as staff turnover, long procurement times, and emergency response needs. In addition, current hiring and retention challenges warrant significant attention to fill existing vacancies and maintain staffing levels.

Additional resources would need to be expanded to accommodate any increases in the programs.

During the past year, the Strategy, Innovation and Change bureau within Business Services worked with staff from all sectors to review challenges with the capital program planning and deliverability (as described in the following chapter). It is anticipated that initial short-term improvements to capital budget development processes will be implemented by the next budget cycle, and longer-term improvements will continue to be developed and implemented over the next five years.

Hard Choices to Constrain Costs
In addition to rightsizing the capital budget for deliverability, costs must also be constrained to keep utility bills affordable for our customers. In each enterprise, a thorough prioritization process was undertaken to ensure the proposed capital plan was affordable to all customers.

Wastewater
Wastewater’s initial 10-year capital request in September 2022 was $5.9 B, exceeding the sources assumed in the last version of the 10-Year Financial Plan by more than $1 B. The biggest cost driver in Wastewater’s capital plan is the Sewer System Improvement Program (SSIP) and the $2.4 B Biosolids Digester Facilities project specifically which has experienced significant cost increases since it began.

As this project is in construction, Wastewater 10-year capital plan expenses are heavily weighted in the first few years of the plan with limited flexibility for cost reductions. However, we recognized that hard choices needed to be made to reduce the overall size of the plan and make it affordable. In addition, the Wastewater Enterprise faces significant risks related to potential regulatory action, which could add significant new capital costs in future years. Given that substantial rate increases are already projected, the Executive Team felt it would be prudent to cut back the current plan as much as possible. The Wastewater team worked to reduce this amount by $1 B over the 10-year plan vs the initial request.

This was achieved by deferring certain projects outside the 10-year horizon, reducing renewal and FY 2023-24 to FY 2032-33 10-Year Capital Plan

12 replacement budgets, and modifying delivery strategies for improved efficiencies. More details about the projects that were deprioritized from the plan can be found at section 7. The final plan total of $4.9 B represents a decrease of $1.2 B over the costs assumed in the prior version of the 10-year Financial Plan. Despite a decrease in the plan total, due to increased costs in the early years of the plan, rate increases will be incorporated which will impact the later years of the plan with costs smoothed over the 30-year debt term.

Water
Water’s initial 10-year capital request in September 2022 was $2.9 B, exceeding the sources assumed in the last version of the 10-year financial plan by more than $1 B. Finance worked with both the Water team and the project managers for the Water capital program in Infrastructure to reduce this request by $744 M over the planning period. This was achieved by more thoughtfully incorporating existing project balances before adding new funding, cuts to certain projects as well as significant smoothing of large project costs over more years. More details about the projects that were deprioritized from the plan can be found at section 5. The capital plan total of $2.3 B represents an increase of $136 M over the costs assumed in the prior version of the 10-year Financial Plan. This increase will be covered with retail and wholesale rate increases which will impact the later years of the plan with costs smoothed over the 30- year debt term.

It is important to note that both Wastewater and Water’s capital plans includes several years that exceed the annual project spending delivered in prior years. This was well considered during the deliverability analysis and was scrutinized by the project managers to ensure the amounts were needed. Given that numerous projects are already in construction, or will soon be in construction, the amounts were considered to be reasonable, as spending is expected to ramp up during the construction phase.

Hetch Hetchy Water
Last year’s Hetch Hetchy Water 10-year plan was balanced and the team did not materially increase their request for this year. Based on prior spending, the plan was also deemed to be deliverable.

However, this is not to say that hard choices were not made to develop a balanced and deliverable plan. The enterprise is currently transitioning to a risk-based capital planning strategy to prioritize its capital projects. This cycle, Hetch Hetchy Water implemented a prioritization tool using a semi- quantitative risk analysis technique to inform its decisions on which projects to cut and which to fund.

The prioritization tool includes a framework to define the likelihood of failure (LoF) and consequences of failure (CoF) scores and thresholds so a consistent scoring system could be applied to both the active and candidate projects. The prioritization tool, as well as discussions with management, was used to cut the initially requested budget of $1.7 B to $977 M in order to balance its capital plan.

Hetch Hetchy Power
The Power and Finance teams worked together to develop a final capital plan that addressed the needs of the enterprise, balanced by constraining rate growth. The Power Enterprise is in a new financial position this year, with their 2022 rate study completed and 2-year rate package adopted in spring 2022. They now can vary rates based on cost of service, and therefore have more flexibility in capital planning. However, power purchase costs have significantly increased which puts pressure on their budget, and must be balanced against increasing capital costs. The Power enterprise’s capital plan represents strategic investments in both maintaining existing infrastructure and developing new load growth from both existing and new customers. More details on the projects that are included in the plan and those that were deprioritized can be found at section 8. Based on prior spending, the plan was also FY 2023-24 to FY 2032-33 10-Year Capital Plan

13 deemed to be deliverable. Their final plan total of $596 M represents a decrease of $16 M over the costs assumed in the prior version of the 10-year Financial Plan.

CleanPowerSF
The CleanPowerSF capital plan totals $73 M over the planning period and doesn’t represent a material change from the prior version.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

14 4. Capital Planning Process
Capital Planning and Delivery Program
During the January 2022 budget discussions SFPUC committed to developing a balanced FY 2023-24 Capital Budget and a 10-Year Capital Plan for Commission review and approval in February 2023, informed by several factors including capital project deliverability. This work examined capital planning and deliverability to more closely align the capital planning process with our execution capacity.

Between May-July 2022, staff reviewed the complex SFPUC capital planning and delivery processes which touch almost all SFPUC Enterprises and Bureaus. The assessment included interviews, workshops, data gathering, and initial planning meetings, and has helped catalog the complex requirements for delivering infrastructure improvements which rely on adequate staffing and resources, funding and contracting processes, and dependencies with external organizations, among other factors.

The review revealed that 1) the effort required to develop and implement solutions to adapt capital plans based on deliverability would be a significant undertaking; and 2) it is not enough to improve our capacity to measure deliverability – we must also increase our capacity to execute on projects to match the growing Capital Improvement Plan (CIP). The following timeline was developed based on the initial discovery:

Phase 1: Discovery and planning (May-July 2022)
• Identify problems and define scope / workstreams
Phase 2: Budget development & near-term improvements (July-Dec 2022) • Deliver / implement new tools to support planning and budgeting • Update our capital plan and balance the FY 2023-2024 budget Phase 3: Continuous improvement (2023 onwards)
Between July-August 2022, the Budget, Project Controls and Strategy, Innovation & Change (SIC) teams rolled out enhanced guidance to support the development of a balanced FY 2023-24 Capital Budget and a 10-Year Capital Plan. These interventions were presented as resources for supporting the planning and budget approach led by the Project Controls and Budget teams.

Phase 3 of this initiative was launched in December 2022 to review and continually improve existing processes for developing the CIP and budget in future years. Teams have been assembled to review governance practices across all three enterprises for CIP development, criteria for reviewing capital projects for inclusion in the CIP, current systems, tools and processes for tracking projects and budgets, resource planning and contracting, and our financial policies for funding the CIP. Initial short- term improvements to capital budget development will be implemented by the next budget cycle.

Longer-term improvements will continue to be developed and implemented over the next five years.

Budget Process
While SIC was leading the overall Capital Planning and Delivery Program, in July 2022 the finance team began preparing for the capital budget and 10-Year Capital Plan development process. The first step was to understand the fiscal outlook for the agency and determine if revenue projections would be changed as we began the process. For Power, the rate study had recently been adopted so rates are fixed through FY 2023-24. For Water and Wastewater, the rate study was underway, with new rates not FY 2023-24 to FY 2032-33 10-Year Capital Plan

15 to be adopted until early 2023. We also decided that we would not make any volumetric changes in our projection, therefore revenues projections would remain the same as in the February 2022 adopted 10- Year Financial Plan.

Budget Instructions
In August 2022 budget instructions were issued to AGMs of each Enterprise on how to proceed with their capital planning efforts. The overarching goal in the capital budgeting process was to execute a balanced plan that is affordable to the ratepayer in the long term, delivers capital projects in the timeframe they are budgeted for, and meets the asset management needs of the agency.

Based on historic spending analysis, deliverability (ability to spend budgets and deliver projects within the time planned) was the major issue. Therefore, the planning effort focused on developing plans that were realistically deliverable. Also, given no additional revenue was projected, AGMs were instructed to propose capital plans at amounts assumed in the prior version of the 10-Year Financial plan, adopted in February 2022.

Internal de liberations and approval
Beginning in September through mid-November 2022, weekly Budget Steering Committee meetings were held. These meetings were chaired by the Deputy General Manager, AGM of Infrastructure, and the Chief Financial Officer, and attended by the AGMs of each enterprise plus staff. The Steering Committee jointly reviewed the capital plans as they were developed. Discussions included overall financial planning and strategy, project priorities, and ultimately the hard choices we had to make to develop plans that were deliverable and affordable. The final recommendation of the Steering Committee was brought to the General Manager for his review and approval at the end of November.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

16 5. Water Capital Plan
Introduction
The Water Enterprise is responsible for the distribution of high-quality water to customers in San Francisco and three Bay Area counties. The Water Distribution System consists of a number of Regional Water Systems: the Hetch Hetchy System; the Regional Water System (East Bay), Regional Water System (Peninsula/West Bay) and the Local Water distribution which includes an In-City Distribution System.

Hetch Hetchy System: Water is diverted from Hetch Hetchy Reservoir into a series of tunnels and aqueducts from the Sierra Nevada to the San Joaquin Pipelines that cross the San Joaquin Valley to the Coast Range Tunnel which connects to the Alameda system at the Alameda East Portal.

Regional Water System (East Bay): This includes two reservoirs, San Antonio Reservoir and Calaveras Reservoir, which collect water from the upper Alameda and San Antonio Creek watersheds in Alameda County plus conveyance facilities connecting the Hetch Hetchy System and Alameda water sources to the Peninsula System. These conveyance facilities include pipelines known as the Alameda Siphons that connect the Coast Range Tunnel to the Irvington Tunnel.

Regional Water System (Peninsula/West Bay): This includes conveyance facilities connecting the Bay Division Pipelines to the In-City Distribution System and to other SFPUC customers on the Peninsula. Three reservoirs, Crystal Springs, San Andreas, and Pilarcitos collect runoff from the San Mateo Creek and Pilarcitos watersheds. Water from these reservoirs serves all wholesale customers, including the Coastside County Water District.

In-City Distribution System: The City’s retail water supply is delivered to the City in several major pipelines that convey water from the Peninsula System. Two pipelines provide water to the eastside of the In-City Distribution System and three pipelines serve the west side of the In-City Distribution System. The “In-City Distribution System” delivers water to homes and businesses in the City.

Capital Plan Summary
In FY 2023-24, the Water Enterprise’s capital budget is $290 M, of which $239.6 M or 82.6% is funded by debt and $50.4 M or 17.4% is revenue funded. Debt funding includes local and regional bonds. The majority of the revenue funding is from local and regional water sales revenues.

The adopted capital project costs for the Water Enterprise total approximately $2.3 B over the next ten years. Identified capital needs will be financed with a combination of water revenue bonds and Water Enterprise revenues. Project timelines may be adjusted to match available funding.

Most of the spending is in the first 5 years of the plan averaging approximately $350 M per year. The average spending in the last 5 years, FY 2028-2033 drops to an approximately $102 M per year.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

17 Table 12. Water Capital Plan
$million FY
23-24
FY
24-25
FY
25-26
FY
26-27
FY
27-28
FY
28-29
FY
29-30
FY
30-31
FY
31-32
FY
32-33
Total
Regional
Water Treatment
Program
153.1 99.7 17.2 16.4 10.4 13.5 3.8 4.2 2.7 2.7 323.8 Water Transmission
Program

0.0 30.5 86.6 51.2 40.5 19.7 7.0 5.6 8.3 78.2 327.5 Water Supply & Storage
Program

4.8 29.6 55.3 6.9 31.5 8.6 8.2 7.6 5.2 5.2 162.9 Watersheds & Land
Management

12.2 1.5 1.3 0.4 0.4 0.4 0.4 0.4 0.4 0.4 17.9 Communication &
Monitoring Program

2.0 4.0 4.4 3.5 2.5 2.5 1.0 1.0 0.8 0.8 22.2
Buildings And Grounds
Programs

9.1 19.8 19.4 93.3 91.3 5.9 3.7 2.3 2.3 2.3 249.5 Long Term Monitoring &
Permit Program

0.4 3.0 7.4 4.2 3.6 2.5 2.6 2.3 2.4 3.3 31.6
Total Water-Regional 181.5 188.0 191.5 176.0 180.0 53.1 26.6 23.5 22.1 92.9 1,135.3

Local
Water Supply Projects 2.3 8.1 15.8 0.1 0.0 0.0 0.0 0.0 0.0 0.0 26.4 Local Water
Conveyance/Distribution
System

87.8 101.5 73.5 62.7 58.0 58.9 53.8 55.3 53.7 45.2 650.5 Systems Monitoring and
Control

3.8 5.8 5.6 0.0 0.0 0.1 0.1 0.1 0.0 0.0 15.5
Local Tanks/Reservoir
Improvements

10.6 7.6 3.6 2.8 2.4 1.8 0.4 0.4 0.2 0.0 29.8 Pump Station
improvements

0.9 3.8 1.6 0.7 0.0 0.0 0.0 0.0 0.0 0.0 7.1
Groundwater Project 0.0 9.2 0.7 0.1 0.0 0.0 0.0 0.0 0.0 0.0 10.0 Recycled Water Project 0.0 1.6 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.4 Automated Meter
Reading System

3.1 3.1 3.0 4.8 4.8 4.1 4.2 4.3 4.3 4.3 40.2
Buildings & Grounds
Improvements - Local

0.0 108.7 147.6 90.0 0.1 0.1 0.1 0.1 0.1 0.1 346.9 Total Water-Local 108.5 249.3 252.1 161.4 65.4 65.0 58.7 60.2 58.3 49.7 1,128.6 Total Uses - Water 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2,263.9

Revenue Funded 50.4 78.6 83.6 65.1 56.6 68.6 67.0 49.2 57.2 46.5 622.8 Debt Funded 239.6 358.7 360.0 272.2 188.8 49.5 18.3 34.5 23.3 96.1 1,641.1 Total Sources 290.0 437.3 443.7 337.4 245.4 118.2 85.3 83.7 80.4 142.6 2,263.9

Key Projects
Regional Water – Regional Water Treatment Program: $323.8 million This program provides funding for improvements to the major water treatment facilities located at Tesla Portal Ultra-Violet Light Disinfection Facility, Thomas Shaft Chlorination Facility, Sunol Valley Chloramination Facility, Sunol Valley Water Treatment Plant (SVWTP), Pulgas Dechloramination Facility, Harry Tracy Water Treatment Plant (HTWTP), and other locations. Major projects include FY 2023-24 to FY 2032-33 10-Year Capital Plan

18 SVWTP Ozone project to install ozone treatment facilities as a long-term solution to control taste and odor events encountered in the raw water supply from both the San Antonio and Calaveras Reservoir sources. Other projects include a new polymer feed facility at the SVWTP, and other short-term and long-term improvements at SVWTP to improve regional delivery reliability by addressing various conditions and deficiencies of the SVWTP.

Regional Water – Regional Water Transmission Program : $327.5 million This program provides upgrades to the Transmission System including pipeline inspection and repairs, pipeline and valve replacements, metering upgrades, corrosion protection, and pump station and vault upgrades. As part of the pipeline improvement program, funding is included to monitor, strengthen, and replace older pipeline to achieve higher level performance and reliability. Funding included for the Crystal Springs Pipeline 2 & 3 Rehabilitation will relocate and replace approximately 1.5 miles of 60- inch diameter pipe into Crystal Springs Road, reline sections of the pipe with cement mortar lining, and upgrade appurtenances to meet current standards.

Regional Water – Regional Water Supply and Storage Program : $162.9 million This program includes upgrades to reservoir dams and structures to meet State Division of Safety of Dams requirements including geotechnical work, installation of monitoring systems, and major improvements to dam spillways and structures as needed.

The program also includes funding for Alternative Water Supply projects that increase regional water supply diversification and explore alternative methods for expanding water sources including purified water, recycled water and desalination projects. The Daly City Recycled Water Expansion Project will provide recycled water to customers of the Regional Water System and help offset groundwater pumping in the Westside Basin. The Los Vaqueros Reservoir Expansion Project will enlarge the existing reservoir located in northeastern Contra Costa County in order to increase water supply reliability for municipal, industrial, and agricultural customers as well as provide ecosystem benefits to south-of-Delta wildlife refuges and Delta fisheries.

Regional Water – Regional Watersheds and Land Management: $17.9 million This program supports projects that improve and/or protect the water quality and/or ecological resources impacted by the siting and operation of SFPUC facilities. Projects include the repair, replacement, maintenance, or construction of roads, fences, or trails, the acquisition of easements and/or fee title of properties, and other ecosystem restoration or public access, recreation, and education projects.

Regional Water – Regional Communications and Monitoring Program : $22.2 million This project will provide much needed redundant emergency communications capability and increased bandwidth for secure data transfer. Specifically, it will build a microwave backbone to link the entire SFPUC regional water system from the O’Shaughnessy Dam site in Yosemite to the rest of the SFPUC sites (San Francisco, San Mateo, Santa Clara, and Alameda counties).

Regional Wat er – Regional Buildings and Grounds Programs : $249.5 million This program provides funding for major improvements to the Sunol and Millbrae Yards. Sunol Yard improvements are already complete and included LEED replacement facilities for maintenance shops and equipment storage, a new fueling center and administration building, re-surfacing of the yard, demolition of six dilapidated structures, and on-going renewal and replacement of worn or aging equipment. Millbrae Yard improvements include a new laboratory and office building to update the lab facilities and consolidate staff from the Rollins Road facility, maintenance shop, and equipment storage, FY 2023-24 to FY 2032-33 10-Year Capital Plan

19 demolition of a large unused abandoned building, a new parking lot, and a new vehicle wash site. The upgrades address occupational safety, reliability, and functional regulatory compliance.

Regional Water - Long Term Monitoring & Permit Program : $31.6 million The purpose of this program is to meet the long-term monitoring and permit requirements associated with capital projects and the operation and maintenance of the SFPUC water supply system and watershed/right-of-way lands within the Bay Area. Projects with long-term monitoring required by environmental permits include Water System Improvement Program (WSIP) related environmental mitigation and permit requirements (i.e., Bioregional Habitat Mitigation Program) and non-WSIP capital projects.

Local Water – Water Supply Projects: $26.4 million
This program includes planning for local water diversification to explore alternative methods for expanding local water sources. Such sources include the Eastside Water Purification Project and Innovations for San Francisco ratepayers that highlight innovative water supplies and technologies.

Local Water – Local Water Conveyance/Distribution System: $650.5 million This program includes funding to install, replace and renew distribution system pipelines ($420.9 million) and service connections for the 1,230 miles of drinking water mains in San Francisco to meet customer level of service goals for uninterrupted service. Improvements include replacement, rehabilitation, re-lining, and cathodic protection of all pipe categories to extend or renew pipeline useful life. The program also includes partial funding for new Potable Emergency Firefighting Water System pipelines as well as funding for joint-department City street improvement projects.

The Renew Services Program provides funding to renew assets between the water main and the customer's service connection. This program includes the Lead Component Services Program ($37.8 million) to replace any lead components for the customer’s water service line and the Water Loss Reduction Program to implement of cost-effective and comprehensive strategies to reduce water loss.

The GIS distribution system mapping program and the Water Quality Distribution Systems are also included.

Additional projects include the New Services Connection Program, Asset Management Platform, and Town of Sunol Pipeline projects.

Local Water –Systems Monitoring and Control: $15.5 million Projects include an upgrade to the Customer Service Center System that will modernize current existing technology to optimize business processes aligning with current and future Customer Service needs and increased operational effectiveness. Continued improvements to facilities for controlling and monitoring San Francisco's water distribution system include enhancements to the Supervisory Control and Data Acquisition (SCADA) system for remote monitoring of pressure, flow, and valve position status at key locations throughout the distribution system Local Water – Local Reservoir and Tanks Improvements: $29.8 million This program provides long-term funding for renewal and rehabilitation of water storage reservoirs and tanks within the San Francisco Distribution System. Projects included improvements to the Sunset South and University Mound reservoirs and replacement of coatings for roofs and tanks at multiple locations to extend the useful service life of the facilities and to provide for the installation of solar energy panels. Major seismic improvements for the College Hill Reservoir and outlet structure are included, as well as geotechnical improvements for Lombard Reservoir.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

20 Local Water – Pump Station Improvem ents: $7.1 million The SFPUC’s 12 major water pump stations and seven hydropneumatics tanks that boost pressure within the San Francisco distribution system need ongoing renewal and rehabilitation. This program provides long term funding for renewal and rehabilitation of the water pump stations and hydro- pneumatic tanks that boost water pressure within the distribution system including the automation of the five pump suction valves at Lake Merced Pump Station. The program also includes improvements at the Harding Park Recycled Water Pump Station and the Bay Bridge West Pump Station.

Local Water – Groundwater Project: $10.0 million
Funding for the Lake Merced Water Level Restoration Project includes improvements to the Vista Grande Drainage Basin to address storm related flooding and diverting recycled water from the new Westside Recycled Water facility into Lake Merced to increase and stabilize lake levels.

Local Water – Recycled Water Project: $2.4 million
This program includes all facilities to produce and deliver about 2 million gallons per day (mgd) of recycled water for irrigation use in the western end of San Francisco. The project includes a new recycled water treatment facility consisting of membrane filtration, reverse osmosis, and ultraviolet light disinfection; a 1.1 million gallon storage reservoir; distribution pumping facilities; and 5 to 6 miles of new pipelines.

Local Water – Automated Meter Reading System: $40.2 million This program provides funding for the ongoing Automated Water Meter Program (AWMP) including meter renewal, replacement, automation, and replacement planning for the entire AWMP System by the end of its 20-year useful life (ending in 2031).

Local Water – Local Buildings and Grounds Improvements: $346.9 million This program provides funding for capital improvements at City Distribution Division facilities and structures. Projects include yard improvements to address health and safety issues and security, continuing renewal and replacement of aging assets at existing buildings and grounds including vehicle and pedestrian gates, fencing at reservoirs, and exterior lighting improvements at reservoirs and pump stations.

The bulk of the funding is included for a new CDD Headquarters at 2000 Marin to address life safety standards for seismic events, building code requirements and facilities that are past useful life. The 2017 Condition Assessment found all buildings aged, water-damaged, and deficient in meeting seismic, ADA, electrical and other building code standards. Existing facilities include administrative offices, warehouse, shops, materials and equipment storage and vehicle fleet.

Deprioritized Projects
The Water team worked alongside infrastructure to develop a proposed capital plan that was submitted to finance in September 2022. This process included an initial prioritization as well as a deliverability review to ensure the agency had the capacity to realistically deliver it. Water’s initial 10-year capital request in September 2022 was $2.9 B, exceeding the costs assumed in the last version of the 10-year financial plan by more than $1 B. Finance worked with both the Water team and the project managers for the Water capital program in Infrastructure to reduce this request by $744 M over the 10-year plan vs the initial request. This was achieved by more thoughtfully incorporating existing project balances before adding new funding, cuts to certain projects as well as significant smoothing of large project FY 2023-24 to FY 2032-33 10-Year Capital Plan

21 costs over more years. The largest cuts were in the Water Main Replacement Program ($332 M) and the Develop Alternative Water Supplies Program ($221.6 M). Because they were the two largest programs in the capital plan that could be reduced while leaving substantial funding in the programs.

Other cuts were distributed across different Water programs so that no single program had to absorb disproportionate cuts.

Table 13. Water project funding reductions during capital planning process Project Name Project Objective Amount
Reduced
Amount
Remaining
Consequences of this action
SVWTP Long Term
Improvements
Improve SVWTP water
treatment capability
(28.5M) - Deferral of various improvements to the
SVWTP, however, there are 3 significant
projects at the plant that are commencing in
the next two years already
Regional
Groundwater
Treatment
Improvements
Improve Regional
GSR Project treatment
capability
(31.1M) 3.3 M Deferral of treatment improvements,
limiting/precluding the use six of the thirteen
installed wells for this drought year supply
project. This will result in an inability to meet
the project production goals and result in a
shortfall of anticipated supply within the
Wholesale Service Area during drought.

Purified Water &
Other Supplies
Develop Alternative
Water Supplies
(221.6M) 82.7 M Commission action on the AWS plan is
anticipated after July 1, 2023 when we would
revisit the level of funding.

Sneath Lane Gate Construct trail
connector on north
end of Peninsula
watershed
(11.0M) - Deferral of this useful Peninsula trail
connector project while we focus on
completing the Bay Ridge Trail extension
project.

Watershed and ROW
Protection - Land
Acquisition
Acquire privately held
important watershed
lands if and when they
become available
(22.6M) - Elimination of funding for land acquisition. If new opportunities arose for acquisition, new
appropriations would be needed.

Local Groundwater
Treatment Project
Improve Local
groundwater project
treatment capability
(14.5M) - Deferral of treatment project to deal with volatile organic chemicals, limiting the use of
three of the six project wells making
approximately 50% of anticipated production.

This will result in an inability to meet the
project production goals and result in a
shortfall of anticipated supply within the
Retail Service Area.

Local Water
Conveyance /
Distribution System
Water main
replacement
(332.0M) 360.8 M Beginning in year 5, reduction in annual funding for the program means we would end
up achieving 4-6 miles of replacement per
year instead of 12.

AWMP Completion
(FY21) & Repl.

Planning (FY22-26)
Complete automated
water meter
installation and then
begin replacement of
older components
(82.1M) 14.7 M Delays in replacing old meter components will result in lost revenue due to meter aging.

NRLM San Francisco
Land Management
Facility
Construct facility for
arborist crew in San
Francisco
(10.3M) - Arborist crew will need to work out of CDD facilities that are not adjacent to the
properties where the vast majority of the tree
work exists resulting in inefficiencies.

Other project needs
Other potential project needs have been identified but are not yet fully ascertained and costs are not certain. These potential future needs were not addressed during this year’s capital planning process but FY 2023-24 to FY 2032-33 10-Year Capital Plan

22 we are including them here in the report as they are important to keep on our radar for future planning.

These project needs will be reviewed for potential inclusion in future capital planning cycles.

Table 14. Water projects with potential funding shortfalls not addressed in the capital planning process Project Name Project Objective FY24-33
Proposed
Budget
Amount of
Future
Anticipated
Funding
Required
Need for Project
Pilarcitos Dam
Improvements
Remediation of the
embankment dam; outlet
structure, outlet tunnel
and pipeline; spillway;
and other ancillary
structures.

30.1M 25-80M Dam safety issues identified by
SFPUC and Division of Safety
of Dams need to be
remediated.

San Andreas Dam and
Facility Improvements
Remediation of the
embankment dam; outlet
structure, outlet tunnel
and pipeline; spillway;
and other ancillary
structures.

32.2M 23-103M Dam safety issues identified by
SFPUC and Division of Safety
of Dams need to be
remediated.

Turner Dam and Reservoir
Improvements
Remediation of the
embankment dam, outlet
structure, outlet tunnel
and pipeline, spillway,
and other ancillary
structures.

7.5M unknown Dam safety issues identified by
SFPUC and Division of Safety
of Dams need to be
remediated.

Calaveras Reservoir
Expansion
Raising the dam,
increasing the capacity
of outlet structures and
spillway, and
transmission and
pumping needs to bring
surplus water to
Calaveras Reservoir for
storage.

7.5M 214M-2B Potential Alternative Water
Supply Project
Sunset South Basin Seismically strengthen
reservoir roof and other
reservoir structural
elements.
8M 85-170M Sunset North Basin Roof and
Dam were seismically
strengthened in WSIP. Similar
work is needed to correct
deficiencies in Sunset South
Basin.

University Mound South
Basin
Seismically strengthen
reservoir roof and other
reservoir structural
elements.

2.4M 53-89M University Mound North Basin
Roof was seismically
strengthened in WSIP. Similar
work is needed to correct
deficiencies in University
Mound South Basin.

Stanford Heights Reservoir Perform geotechnical
investigations and
stability analysis of
embankment; construct
improvements if needed.

0.2M 1-12M Dependent on results of the
geotechnical investigations and
stability analysis

FY 2023-24 to FY 2032-33 10-Year Capital Plan

23 6. Hetch Hetchy Water Capital Plan
Introduction
The Hetch Hetchy Water division of the Water Enterprise is responsible for operating, maintaining and upgrading the Hetch Hetchy system of assets, which extend from Hetch Hetchy Reservoir in Yosemite National Park to Alameda East Portal (water) and Newark (electrical transmission) in Alameda County.

The Hetch Hetchy system provides 85% of the water supply to 2.7 million in-City and regional Bay Area water customers. Additionally, Hetch Hetchy Water generates electricity via several hydro-generation plants to power in-City departments.

Much of the Hetch Hetchy system is at or approaching 100 years old and on average is approximately 135% of its anticipated useful life. Hetch Hetchy Water operates under a “Water First’ policy, which means that operational needs and capital investment decisions are heavily weighted to meet water reliability objectives.

The Hetch Hetchy Water Capital Program includes Water Only (100% Water Costs), up-country Power Only (100% Power Cost) and Joint (45% Water/55% Power costs) for operating, managing, and maintaining the Hetchy Water Infrastructure.

Capital Plan Summary
In FY 2023-24, Hetch Hetchy Water’s capital budget is $85.9 M and is 100 % funded by debt. Of the debt funding, $65.5 M is from water bonds, with the remainder $20.4 M met by power bonds.

The $976.9 million Ten-Year Capital Plan represents a consistent and growing investment over ten years with funds allocated to Hetchy-Water totaling $441.2 M and Hetchy-Power totaling $535.7 M.

Table 15. Hetch Hetchy Water Capital Plan
Hetchy-
Water/
$million
FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Water
Infrastructure

48.9 59.4 31.1 16.4 5.3 4.7 4.8 4.9 5.0 5.1 185.6
Power
Infrastructure

0.0 32.2 27.1 39.6 14.4 38.9 29.8 11.5 10.3 19.4 223.3
Joint Projects 37.0 64.0 94.4 85.6 74.9 56.0 65.3 41.1 32.1 17.7 568.1 Total Uses -
Hetchy Water

85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9

Debt Funded 85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9 Total
Sources

85.9 155.6 152.6 141.6 94.6 99.6 100.0 57.5 47.4 42.3 976.9 Key Projects
Water Infrastructure : $185.6 million
The Water Infrastructure program provides capital funding for Renewal & Replacement (R&R) and Large Infrastructure projects on HHWP’s assets that are classified by the Water Supply Agreement (WSA) as Water. The proposed FY23-24 10-Year Capital Plan includes $185.6 M under the Water Infrastructure authority level which is used to fund capital improvements on the San Joaquin Pipelines, Mountain Tunnel, and other water assets.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

24 Power Infrastructure : $223.3 million
The Power Infrastructure program provides capital funding for Renewal & Replacement (R&R) and Large Infrastructure projects on HHWP’s assets that are classified by the Water Supply Agreement (WSA) as Power. The proposed FY23-24 10-year Capital Plan includes $223.3 M under the Power Infrastructure authority level which is used to fund capital improvements on the power facilities such as Moccasin Switchyard, Kirkwood Powerhouse, Moccasin Powerhouse, Holm Powerhouse, 115kV and 230kV Transmission Lines, Warnerville Substation, Cherry-Eleanor Pumps, and other power assets.

Joint Infrastructure : $568.1 million
The Joint Infrastructure program provides capital funding for Renewal & Replacement (R&R) and Large Infrastructure projects on Hetch Hetchy Water a’s assets that are classified by the Water Supply Agreement (WSA) as Joint. The proposed FY23-24 10-year Capital Plan includes $568.1M under the Joint Infrastructure authority level which is used to fund capital improvements on the joint facilities such as O’Shaughnessy Dam, Canyon Tunnel, Mountain Tunnel, Moccasin Wastewater Treatment Plant, Power Distribution Lines, Cherry Dam, Buildings & Grounds, and other joint assets.

Deprioritized Projects
The Hetchy Water team worked alongside infrastructure to develop a proposed capital plan that was submitted to finance in September 2022. This process included a thorough prioritization analysis as well as a deliverability review to ensure the team had the capacity to realistically deliver the proposed plan. Last year’s Hetch Hetchy Water 10-year plan was balanced and the team did not materially increase their request for this year.

Risk-Based Prioritization
HHWP’s risk framework for the FY 2023-24 capital planning effort was presented to management and implemented in July 2022 as a prioritization tool. Hetch Hetchy Water then applied the risk framework to all active and candidate projects through a scoring process that was completed by a multi-disciplined team that included Hetch Hetchy Water Operations, Engineering, and Asset Management. The scoring effort documented the assumed failure mode(s), the Consequence of the Failure (CoF), and Likelihood of the Failure (LoF) all of which were used to calculate an overall Risk Score to prioritize projects. The results of the scoring effort were uploaded to Hetch Hetchy Water’s PowerBI.

Deliverability Review
HHWP completed multiple efforts to support the deliverability review of the projects included in its draft Capital Plan including: (1) Evaluation of Historical Capital Spending, (2) Quality Assurance Review of Projects, (3) Identification of Projects with Unused Appropriations Greater than $5 M, (4) Detailed Spending Plan for R&R Subprojects, and (5) review and adjustments to project timeline/encumbrance assumptions to more closely tie budget requests with project spending.

Deferred Capital Investments
To deliver a balanced capital plan, Hetch Hetchy Water cut approximately $339 M from its 10-year capital plan during this planning process. In addition to small budget cuts throughout the plan, multiple projects were deferred beyond the 10 years to balance budget limitations with operational priorities. A summary of the significant deferred capital improvements is provided below, including some high-level information regarding the perceived risk of the deferment.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

25 Table 16. Hetch Hetchy Water project funding reductions in the capital planning process Project Name Project Objective Amount
Reduced
Amount
Remaining
Consequences of this action
Kirkwood
Powerhouse
Rehabilitation
Rehabilitation of Kirkwood
Powerhouse Unit 3, and
rehabilitation or
replacement of systems in
Kirkwood Powerhouse to
modernize and improve
reliability.
(54.88M) - Deferment of this project represents a
moderate risk to HHW Operations. HHW can
accommodate deferment by ongoing
maintenance and R&R work, as well as
redundancy provided by Kirkwood Powerhouse
Generators Unit 1 and Unit 2. However, long
term deferment can lead to potential failure of
Kirkwood Powerhouse Generator Unit 3 and
associated systems, and reduced power
generation and water deliveries.

Intake
Switchyard
Control Room
Upgrade
Replacement/rehabilitation
of mechanical and electrical
equipment located in the
Intake Switchyard Control
Room.
(15.42M) - Deferment of this project represents a
moderate risk to HHW operations due to the
age of the assets in the Control Room. Failure
could result in the temporary operation of
Kirkwood Powerhouse Bypass in order to
maintain water deliveries, and would also
eliminate all generation from Kirkwood
Powerhouse and Holm Powerhouse.

Calaveras
Substation
Upgrade
Rehabilitate existing
electrical infrastructure at
Calaveras Substation.
(24.85M) - Calaveras Substation has a single transformer and lacks the redundancy required to maintain
service to Water System & Treatment Division
in the event of a failure or planned outage for
maintenance. Failure would potentially impact
Water System & Treatment Division facilities,
including San Antonio Pump Station,
Chlorination Plant, and Sunol Filter Plant.

Therefore, we are moving forward with
planning for this project in the existing capital
budget.

Cherry Dam
Spillway and
Intake Tower
Rehab
Increase spillway capacity
to safely pass the updated
design flood without
overtopping existing
embankment dam, and
improve the intake tower
structure to withstand the
design seismic loadings.

(116.86M)
- Deferment of this project represents a low to
moderate risk to HHW operations due to two
mitigations: 1) HHW has implemented a
Forecast Informed Reservoir Operations
operating strategy to manage the reservoir and
2) the approved Cherry Spillway Short Term
Improvements project.

Moccasin Water
Quality Building
Construction of a
replacement water quality
laboratory in Moccasin to
perform mission-critical
microbiological and
chemical analyses to
support filtration avoidance
compliance.
(12.46M) - The water quality lab is in poor condition which may eventually impact the Water Quality
Division’s ability to perform tasks that are
required by regulators and essential to HHW
Water Operations. In the event the building
deteriorates to the point that it can no longer
be occupied by Water Quality Division staff, a
temporary facility would need to be mobilized
to support the required tasks.

Moccasin Yard
Improvements
Phase II
Construction of a
warehouse addition,
storage building, truck port,
automobile/ machine shop
addition, carpentry shop
addition, security fence,
retaining wall, and other
associated works.
(88.92M) - Deferment of this project represents a
moderate risk to HHW operations. While
deferment does not directly impact water or
power operations, the project is needed to
provide efficient and safe work and storage
areas and to meet the current and future
operational needs of HHW, as well as bring the
buildings into code.

Install Penstock
Safe Isolation
Valves
Install new isolation valves
at or below valve houses to
allow safe entry into
(16.08M) - Deferment of this project represents a
moderate risk to HHW operations. HHW can
accommodate deferment by dewatering
FY 2023-24 to FY 2032-33 10-Year Capital Plan

26 penstocks without
dewatering tunnels, in
compliance with the SFPUC
Safe Pipeline Isolation
procedure.
tunnels upstream of the valve houses to
provide safe entry per updated safety
guidelines.

San Joaquin
Pipeline Life
Extension
Program
Deliver capital improvement
projects to sustain the
reliability of the San
Joaquin Pipeline (SJPL)
system that are expected to
delay the need for planned
large scale replacement for
20 to 60 years.
(9.50M) 48.60M Reductions in annual funding for this program will result in reduced budget flexibility to
complete needed repairs along the San
Joaquin Pipeline system.

Other project needs
Other potential project needs have been identified but are not yet fully ascertained and costs are not certain. These potential future needs were not addressed during this year’s capital planning process but we are including them here in the report as they are important to keep on our radar for future planning.

These project needs will be reviewed for potential inclusion in future capital planning cycles.

Table 17. Hetch Hetchy Water projects with potential funding shortfalls not addressed in the capital planning process Project Name Project Objective FY24-33
Proposed
Budget
Amount of
Future
Anticipated
Funding
Required
Need for Project
Moccasin
Penstock
Rehabilitation
Rehabilitation of anchor blocks,
penstock coating, penstock
saddles, air valves, large-diameter
butterfly valves, bifurcation
sections, and flow meters. In
addition, upgrade of electrical
system, power transformers, and
the standby generator at West
Portal Valve House and of the
bulkhead isolation valves in the
surge tower.

47.3M unknown, but
potentially
$100M
Phased Array Ultrasonic Testing
results received after
development of the 10-year CIP
FY24-33 have indicated the
potential need for an expanded
scope of work, including
replacement of the hammer-
forged steel portions of the
penstocks. An Alternatives
Analysis Report is due by March
2023. Deferment of this project
represents a high risk to HHWP
Operation's capability to deliver
water to the SFPUC customers.

SJPL 1
Rehabilitation
and Replacement
Replacement and/or rehabilitation
of multiple segments of San
Joaquin Pipeline Number 1 that
have limited life remaining.

-
307.59M Deferment of this project
represents a high risk to HHWP
Operations. HHWP can
accommodate deferment during
this cycle due to investments
under the R&R SJPL Life
Extension Program, the
proposed SJPL Valve Remote
Control and Monitoring project,
and redundancy provided by
adjacent lines. However, long
term deferment can lead to
potential failures of San Joaquin
Pipeline Number 1 and reduced
water deliveries.

Priest Shoreline
Erosion Control
Protection
Provide erosion protection to the
shoreline to reduce frequency of
turbidity events and protect water
quality.
- 5.38M Deferment of this project
represents a low risk to HHWP
Operations. HHWP can
accommodate deferment by
FY 2023-24 to FY 2032-33 10-Year Capital Plan

27 deliveries through the Priest
Bypass. However, long term
deferment can lead to increased
turbidity and a decrease of water
quality.

Moccasin to
Standiford
OPGW
Installation
Installation of Optical Ground Wire
(OPGW) to serve as the primary
communication between Moccasin
and the Modesto area.
- 20.73M Deferment of this project
represents a minimal risk to
HHWP operations. The new
asset would not improve water or
power operations, but would
improve communication
reliability.
230kV Power
Transmission
Line
Rehabilitation
Replace or rehabilitate significant
elements (towers, electrical
conductors, insulators, switches,
relays) to extend the operating life
of the system.
303.13M Deferment of this project
represents a moderate risk to
HHWP Operations given the age
of the transmission lines and
towers. A failure of these assets
would require bypass operations
to maintain water deliveries and
would eliminate all generation
from Holm Powerhouse and
Kirkwood Powerhouse until
repaired. This risk is partially
mitigated by the ongoing work
that is completed under the R&R
Transmission Lines Clearance
mitigation and R&R Power
Transmission Life Extension
projects.
115kV
Transmission
Lines Rehab
Condition Assessments of these
assets will be performed over the
next two years. Capital projects
will be defined by 2026.

TBD Unknown, but
potentially
nearing $1B
Deferment of this project
represents a high risk to HHWP
Operations given the age of the
transmission lines and towers. A
failure of these assets would
require bypass operations to
maintain water deliveries and
would eliminate all generation
from Moccasin Powerhouse until
repaired. This risk is partially
mitigated by the ongoing work
that is completed under the R&R
Transmission Lines Clearance
mitigation and R&R Power
Transmission Life Extension
projects.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

28 7. Wastewater Capital Plan
Introduction
The Wastewater Enterprise operates and maintains three wastewater treatment plants, one wet weather facility, 27 pump stations, 1,900 miles of sewer mains and laterals, 216 green infrastructure assets, and 25,000 catch basins to protect public health and the environment. Wastewater facilities process approximately 70 million gallons per day (MDG) of dry weather flows and have 565 mgd of wet weather treatment capacity.

North Point Wet Weather Facility: The North Point Wet Weather Facility has been in operation since 1951. The facility provides primary-level treatment and disinfection of combined sewage collected in the north part of the City during rainstorms. The facility has a treatment capacity of 150 MGD. Treated combined sewage is discharged approximately 800 feet into the San Francisco Bay.

Southeast Treatment Plant: The Southeast Treatment Plant was built in 1952 and has been expanded several times since.  The Plant treats an average dry-weather flow of approximately 58 MGD and discharges into the San Francisco Bay through an 810 foot-long pipe. The Plant has a peak wet- weather capacity of 250 MGD which is discharged through both the 810 foot-long pipe into the Bay and an auxiliary wet-weather-only outfall into Islais Creek.

Oceanside Treatment Plant: Completed in 1993, the Oceanside Treatment Plant treats an average dry-weather flow of approximately 16 mgd and has a total capacity of 65 MGD during wet-weather. It treats wastewater from the west side of the City. Treated wastewater is discharged from the plant to the Pacific Ocean through the Southwest Ocean Outfall 4.5 miles offshore.

Treasure Island Treatment Plant: The SFPUC, under a 1997 Cooperative Agreement between the U.S. Navy, agreed to operate and maintain the utility systems at Treasure Island, including the Treasure Island Plant, while the Navy retains ownership of all the utility systems. The Plant provides secondary treatment of wastewater from facilities on Treasure Island and Yerba Buena Island. It serves a population of approximately 2,400 and has a design capacity of 2 MGD.

Pump Stations and Force Mains: The Wastewater Enterprise operates 27 pump stations with capacities ranging from less than 1 MGD to 175 MGD. The system includes three major force mains:

North Shore, Channel, and Westside. In addition to these major force mains, there are several smaller force mains (2” in diameter and larger) downstream of pump stations, totaling 7 miles.

Gravity Sewers: Wastewater Enterprise owns, operates, and maintains approximately 800 miles of sewer mains equal or smaller than 36” in diameter (“small diameter sewers”), and nearly 200 miles of major interceptors and tunnels larger than 36” in diameter (“large diameter sewers”). In addition, WWE replaces sewer service laterals with structural deficiencies located on the pipe portion extending from face of curb to the sewer main (“sewer lateral”). There are approximately 160,000 sewer laterals.

Transport/Storage Boxes and Combined Sewer Discharge Structures: Transport/storage boxes capture combined stormwater and sewage as it overflows the sewer system and before it reaches the shoreline of the Bay or Pacific Ocean. The boxes can hold approximately 200 million gallons of stormwater and sewage for later treatment at wastewater treatment plants. The storage boxes completely fill up during the most prolonged intense rainstorms, and water is discharged into either the Bay or Ocean through one of 36 combined sewer discharge structures.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

29 Capital Plan Summary
The Capital plan is organized into the following five categories – Sewer System Improvement Program (SSIP), R&R Treatment Facilities and Collection System, Facilities and Infrastructure Projects and Treasure Island.

In FY 2023-24, the Wastewater Enterprise’s capital budget is $985.5 M, of which $890.2 M or 90% is funded by debt and $95.3 M or 10.0% is revenue funded. Debt funding consists of revenue bonds. The majority of the revenue funding is from sewer service charges, with the remainder being from capacity fees.

The Ten-Year Plan for FY 2023-24 through FY2032-33 is $4.879 B and includes the Sewer System Improvement Program at $2.913 B, the Collection System and Treatment Facilities Renewal and Replacement Programs at $1.635 B, the Treasure Island Treatment Plant at $153 M and improvements to other Wastewater Facilities and Infrastructure at $178 M.

Table 18. Wastewater capital plan
$million FY
23-24
FY
24-25
FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
SSIP 778.5 676.0 590.2 323.9 151.7 86.7 63.3 40.4 69.3 133.7 2,913.7 R&R 95.3 148.7 172.1 170.7 174.0 163.0 165.2 171.5 183.7 191.1 1,635.4 Treasure
Island
111.7 39.0 1.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 152.6 Wastewater
Facilities &
Infrastructure

0.0 30.8 54.2 26.5 27.9 30.8 4.1 2.8 0.2 0.5 177.7 Total Uses -
Wastewater
985.5 894.5 818.4 521.1 353.6 280.5 232.6 214.7 253.2 325.2 4,879.4

Revenue
Funded

95.3 128.4 130.8 133.3 135.9 138.5 141.1 143.8 146.6 149.4 1,343.1 Debt Funded 890.2 766.2 687.6 387.8 217.7 142.0 91.5 70.9 106.6 175.8 3,536.3 Total Sources 985.5 894.5 818.4 521.1 353.6 280.5 232.6 214.7 253.2 325.2 4,879.4 Key projects
Collection System Renewal & Replacement (R&R) - Condition Assessment Projects:
$192.2 million
This program includes cleaning and inspection of small and large diameter sewers. The results of the inspection program will inform the Small and Large Diameter Sewer Improvements subprograms, and potentially inform major improvements delivered by the Sewer System Improvement Program (SSIP).

This project is a part of the on-going data gathering necessary for the Wastewater Enterprise Collection Systems Asset Management Program.

Collection System R&R - Small Diameter Sewer Improvements: $498.6 million This program maintains the existing functionality of the sewage collection system and includes planned and emergency repairs and replacement of structurally inadequate sewers. Failure of the collection system will reduce the City’s ability to handle and dispose of wastewater and stormwater which can lead to public health, safety, and environmental risks, and non-compliance with the State discharge permit.

Projects are identified utilizing an asset management approach which factors in physical condition, age, location, risk, public safety, paving schedule, and other factors. This program allows for the renewal and replacement of approximately 15 miles of sewer per year. WWE is shifting focus to utilize more trenchless construction methods for sewer main and lateral R&R, including cured-in-place-lining (CIPP), FY 2023-24 to FY 2032-33 10-Year Capital Plan

30 pipe bursting, sliplining, and alternative pipe materials. Trenchless construction methods are industry best practice and provide the benefits of substantially lower average cost per mile, shorter construction times per mile, and lower overall disruption to the public from the construction activity. As reflected in the newest 10 year CIP, WWE’s goal is to have 50% or more of gravity sewer R&R work done using trenchless construction methods within the next 7 years.

Collection System R&R - Large Diameter Sewer Improvements: $403.3 million This is a collection of large sewer improvement projects that will rehabilitate and/or replace Large Diameter Sewers (sewers greater than 36-inches in diameter or equivalent diameter) that have the highest risk for failure.

Treatment Facilities R&R: $305.0 million
The Treatment Plant Improvement program helps maintain the capacity and reliable performance of the Wastewater treatment facilities owned and operated by the Wastewater Enterprise. This is a continuing annual program to extend the useful life of Wastewater treatment assets including Discharge Structures, Pump Stations, Force Mains, and Treatment Plants. The projects are prioritized based upon worker health and safety, regulatory compliance, condition assessments, operation staff recommendations, and levels of service formally adopted as part of the SSIP. The completion of projects under the Treatment Facilities R&R Program will increase reliability and efficiency of Wastewater Enterprise facilities and ensure that the performance of the treatment facilities meets the established levels of service.

Treasure Island Wastewater Improvements: $152.6 million This project provides continued funding for a new tertiary four-million gallon per day wastewater treatment facility for the Treasure Island/Yerba Buena Island service area to replace the existing, aged facility. The objective of the project is to build a new wastewater treatment plant that will provide reliable service for the Treasure Island residents and meet the recycled water demands of the future redevelopment on the island. The new treatment facility will include influent screening, a combined primary/secondary treatment process, sludge thickening and truck load-out, disinfection, odor control, and tertiary treatment.

Ocean Beach Climate Adaptation Project : $130.9 million This project will develop a comprehensive shoreline management and protection plan in partnership with relevant stakeholders and regulatory agencies and establish a long-term solution to the erosion issues along Ocean Beach. This long-term solution is necessary to protect the integrity of critical wastewater assets that were constructed to protect public health and the environment. These assets include the Lake Merced Transport/Storage facility, the Westside Pump Station, and the Oceanside Treatment Plant, which are threatened by sea level rise and erosion at Ocean Beach.

SSIP Treatment Faci lities: $1.7 billion
SSIP treatment facilities projects include the Bayside Biosolids Digester Facility Project in southeast San Francisco; improvements to the liquid treatment at the Southeast Water Pollution Control Plant, the North Point Wet Weather Facility, the North Shore Pump Station and associated outfalls; and improvements to the Oceanside Water Pollution Control Plant, Westside Pump Station, and Westside Force Main.

SSIP Sewer/Collection System: $279.6 million
This program also replaces existing sewers to increase hydraulic capacity, and rehabilitates transportation/storage facilities, combined sewer discharge structures, pump stations, and force mains.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

31 SSIP Storm water Management and Flood Resilience : $548.9 million This program includes work on green infrastructure, flood resilience, the Floodwater Management Grant Assistance Program, and the Green Infrastructure Stormwater Management Grant Program.

Flood resilience projects manage combined sewer flooding caused by heavy rain through capital improvements, grant programs, financial incentives, Building Code amendments, options for affordable flood insurance, and enhanced coordinated storm response. Green infrastructure construction of permeable surfaces and engineers’ subsurface systems sustainably augments the collection system for the management of stormwater flows. The Green Infrastructure Stormwater Management Grant Program incentivizes property owners to construct and maintain green infrastructure on large parcels.

These projects support the levels of service goals to minimize flooding, provide benefits to impacted communities, and achieve economic and environmental sustainability. Ancillary benefits may include reduced energy use (reduced pumping and treatment), potable water conservation, groundwater recharge, and improved community aesthetics.

Side Stream Treatment Removal Project: $15 million
Project to provide near term interim progress on nutrient removal during the next 6 to 7 years at Southeast Treatment Plant. Following completion of the Biosolids Digester Facility Project, a separate capital project would be created to provide long term nutrient removal. The costs and timing of that permanent facility is not established yet. The interim side stream nutrient removal facility will treat highly concentrated flow from current centrifuge dewatering facility. The treated flow/effluent from this planned facility will return to upstream existing liquid treatment train on northside of Southeast Plant prior to discharging to San Francisco Bay through current outfall system Deprioritized projects
The Wastewater team worked alongside infrastructure to develop a proposed capital plan that was submitted to Finance in September 2022. This process included a prioritization analysis as well as a deliverability review to ensure the team had the capacity to realistically deliver the proposed plan.

Wastewater’s initial 10-year capital request in September 2022 was $5.9 B, exceeding the costs assumed in the last version of the 10-year financial plan by more than $1 B. The biggest cost driver in Wastewater’s capital plan is the SSIP, namely the Biosolids Digester Facility Project which has experienced significant cost increases since it began, and when complete will have cost over $2.3 B.

This project is already in construction phase with a contractor in place and money being spent. Thus, the costs in Wastewater 10-year plan are heavily weighted in the first few years of the plan with limited room for cuts. However, we recognized that hard choices needed to be made to reduce the overall size of the plan and make it affordable. In addition, the Wastewater Enterprise faces significant risks related to potential regulatory obligations, which would add significant new capital costs in future years. Given that substantial rate increases are already projected, the executive team felt it would be prudent to cut back the current plan as much as possible. The Wastewater team worked to reduce this amount by $1 B over the 10-year plan vs the initial request. This was achieved by deferring certain projects outside the 10-year horizon, reducing renewal and replacement budgets, and modifying delivery strategies for improved efficiencies.

Process for prioritization
We consider there to be significant limitations to defer projects or scopes when the projects are already in construction and/or have been committed to regulators. Accordingly, these projects were not considered in the efforts to reduce the Wastewater Capital Plan budget. We identified other projects in the Capital Plan for budget reductions if they met any of the following criteria:

FY 2023-24 to FY 2032-33 10-Year Capital Plan

32 • Project provides a system enhancement (e.g., stormwater management, seismic protection), and has not started
• Project covers design and construction phases only, and can be deferred until the preceding “Phase 1” assessment and planning project is completed
• Project does not address a high-risk reliability, safety, or regulatory issue and has not started • Project has had deliverability challenges (e.g., staffing, contracting, partnerships) • We then applied one of the following budget reduction strategies to the deprioritized projects:
• Delay project start (and complete immediate needs through R&R program, as needed) • Defer project outside of 10-year horizon (and complete immediate needs through R&R program, as needed)
• Reduce R&R funding
• Modify delivery strategy for improved efficiencies
The final step was to then assess what risk profile changes were presented by the removal of the projects from the current 10-Year Capital Plan, both individually and in total. These risk categories are similar to the categories used for Wastewater Enterprise’s overall capital program prioritization approach and include staff safety impacts, increased risk of regulatory violations, reduced system reliability, lower customer service reliability, and excessive volatility in annual spending, delivery resources (internal staffing levels) and rates.

The following table summarizes the projects that were reduced or not included in the final version of the plan.

Table 19: Projects deprioritized from Wastewater’s Capital Plan proposal, $ million Deprioritized Treatment Plant Projects
Project Name Project
objective
Amount
reduced
Amount
remaining
in CIP
Action Consequence of this action
R&R Treatment
Plant
Improvements
State of good
repair, health
and safety
(116.6 M) 305 M Reduced funding This results in a higher risk to worker health and safety,
service disruptions, permit
violations, and lower system
reliability.

Southeast Plant
Pipe Gallery (SEP
960) Rehab
State of good
repair
-

14.6 M Delayed project start Starting project in year 4 instead of year 1 results in a higher risk
to worker health and safety and
lower system reliability.

Aeration Tank
(SEP 200) Rehab –
Design and
Construction
State of good
repair
(62.2 M) - Deferred project outside
of 10-year horizon, until
condition assessment
and planning are
completed (in another
project funded in the
CIP) and used to define
the project’s design and
construction needs.

There is a risk that the design
and construction of the aeration
tank rehab cannot be funded in
the 10-year CIP due to budget
limitations.

North Point Facility
Sedimentation
Tanks (NPF
040/041) Flushing
System
Operational
enhancement
(12.7 M) - Deferred project outside
of 10-year horizon
At present, the sedimentation
tanks are manually flushed with
hoses after a wet weather
event. Delaying this project
prolongs the manual, labor-
FY 2023-24 to FY 2032-33 10-Year Capital Plan

33 intensive, and less efficient
operational practice.

Oceanside Plant
OSP Condition
Improvement
Projects - Part 3
State of good
repair, health
and safety
(24.6 M) - Deferred project outside
of 10-year horizon
This results in a higher risk to
worker health and safety,
service disruptions, and lower
system reliability.

Admin Bldg (OSP
930) Seismic
Retrofit
Seismic
protection
(12.7 M) - Deferred project outside
of 10-year horizon

This results in greater
vulnerability to earthquakes,
which poses a higher risk to
worker health and safety, and
service disruptions.

Pretreat. & Solids
Bldg (OSP 011)
Struct. & Seismic
Retrofit
Seismic
protection
(15.3 M)

- Deferred project outside
of 10-year horizon
Primary Clarifier
(OSP 042)
Structural &
Seismic Retrofit
Seismic
protection
(46.6 M) - Deferred project outside
of 10-year horizon
Westside FM
Reliability Project -

DESIGN &

CONSTRUCTION
Operational
reliability
(redundancy)
(46 M) 42.8M Deferred $45M of
construction
encumbrance by 1 year
None
Grit Removal (OSP
011) Upgrades -

DESIGN &

CONSTRUCTION
Process
improvement
(19 M) - Deferred project outside
of 10-year horizon, until
planning is completed
(in another project
currently funded by the
CIP) and used to define
the project’s design and
construction needs.

There is a risk that the design
and construction of the grit
removal upgrades cannot be
funded in the 10-year CIP due
to budget limitations.

Deprioritized Pump Station and Force Main Projects
Project Name Project
objective
Amount
reduced
Amount
remaining
in CIP
Action Consequence of this action
Channel FM
Reliability Project
State of good
repair
(190 M) - Deferred project
outside of 10-year
horizon
This results in a higher risk to
service disruptions and lower
system reliability. The Channel
Force Main, part of the Bayside
Collection System, transports 64%
of the City’s entire wastewater
flows.

Berry St PS
Improvements
State of good
repair
(11.5 M) - Deferred project
outside of 10-year
horizon
This results in a higher risk to
service disruptions and lower
system reliability.

Channel PS
Improvements
State of good
repair
(32.4 M) - Deferred project
outside of 10-year
horizon
This results in a higher risk to
service disruptions and lower
system reliability.

Deprioritized Gravity Sewer Projects
Project Name Project
objective
Amount
reduced
Amount
remainin
g in CIP
Action Consequence of this action
R&R Sewer
Improvements –
Small Diameter
Repair and
replace sewer
mains (≤36-
inch dia.
(135.4 M) 498.6 M Expanded application of
trenchless construction
technology for small
diameter sewers
Repurposed a portion of
funding allocated for full
block main replacement
Beginning in FY25-26, reduction
in annual funding for the
program; instead of improving
15 miles per year, the projected
target would be 13.5 miles per
year. From FY 26-27 to FY30-
31, the reduced target is 9.8
FY 2023-24 to FY 2032-33 10-Year Capital Plan

34 to focus on sewer main
spot repair.

Reduced projected open-
cut sewer replacement
targets

miles for five years. This results
in a higher probability of
breakages, an increased risk of
service disruptions, lower
system reliability, and potential
regulatory challenges. The shift
from open cut to trenchless
construction may impact the
bidding environment and
contracting community.

R&R Sewer
Improvements –
Large Diameter
Rehab sewer
mains >36-
inch dia.)
(67 M) 403.3 M Reduced sewer rehab
targets

Beginning in FY28-29, reduction
in annual funding for the
program; instead of improving

1.5 to 1.75 miles per year, the
projected target would be 1.2 to

1.4 miles per year. This results
in a higher probability of
breakages, increase risk of
service disruptions, and lower
system reliability.

Kansas and Marin
Streets Sewer
Improvements
Increase wet
weather flow
conveyance to
meet LOS
storm
(23.3 M) - Deferred project until
Alternatives Analysis is
completed.

The LOS storm will not be met
for this project area until project
implementation. There is a risk
that this project cannot be
funded in the 10-year CIP due
to budget limitations.

Deprioritized Stormwater and Flood Management Projects
Project Name Project
objective
Amount
reduced
Amount
remaining
in CIP
Action Consequence of this action
Green Infrastructure
Regional
School/Park:

Lincoln High
School
Manage
stormwater
in the LOS
storm
through
green
infrastructure
(10.7 M) - Deferred project outside of 10-
year horizon
The project deferral delays
stormwater management in
the area and co-benefits
associated with implementing
green infrastructure.

Streetscape
Synergy
Projects:

Bayside
Manage
stormwater
in the LOS
storm
through
green
infrastructure
(48.6 M) - Deferred project outside of 10-
year horizon
The project deferral delays
stormwater management in
the area and co-benefits
associated with implementing
green infrastructure. There is
a risk that project funding
would not be available when
streetscape opportunities
arise from other City
Departments.

Streetscape
Synergy
Projects:

Westside
Manage
stormwater
in the LOS
storm
through
green
infrastructure
(14.6 M) - Deferred project outside of 10-
year horizon
The project deferral delays
stormwater management in
the area and co-benefits
associated with implementing
green infrastructure. There is
a risk that project funding
would not be available when
streetscape opportunities
arise from other City
Departments.

Twin Peaks:

Sutro Reservoir
Manage
stormwater
(28.4 M) - Deferred project outside of 10-
year horizon
The project deferral delays
stormwater management in
FY 2023-24 to FY 2032-33 10-Year Capital Plan

35 Stormwater
Space
in the LOS
storm
through
green
infrastructure
the area and co-benefits
associated with implementing
green infrastructure.

Flood Resilience
Ocean and
Urbano Pipe
Enhancement
Flood
management
in the LOS
storm
(50.3 M) - Deferred project outside of 10-
year horizon
The area will continue to
experience flood risks in the
LOS storm until the project is
completed. The community
that this project serves has
been vocal about their
desires for a project, and
deferring the project outside
the next decade may impact
public perception.

Gough Pipe
Enhancement
Flood
management
in the LOS
storm
(21.6 M) - Deferred project outside of 10-
year horizon
The area will continue to
experience flood risks in the
LOS storm until the project is
completed.

Other Deprioritized Projects
Project Name Project
objective
Amount
reduced
Amount
remaining
in CIP
Action Consequence of this action
CSD Structure
Rehab &
Upgrades - Part 2
State of good
repair
(25.2 M) - Deferred project outside
of 10-year horizon
This results in a higher risk to
service disruptions and lower
system reliability.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

36 8. Hetch Hetchy Power Capital Plan
Introduction
The Power capital program includes renewable generation and energy efficiency projects, solar at SFPUC and other City facilities, the Streetlight Repair and Replacement program and Transmission and Distribution projects consistent with the City’s goal establishing the SFPUC as the exclusive electrical services provider to existing and new City facilities and development/redevelopment projects.

Capital Plan Summary
In FY 2023-24, the Hetch Hetchy Enterprise’s capital budget is $21.5 M, of which $14.5 M or 65% is funded by debt and $7.0 M or 35.0 % is revenue funded. Revenue funding includes Power operating revenue, Distributed Antenna System, Low Carbon Fuel Standards and Power Cap and Trade revenue.

The $595.5 M Power Ten-Year Capital Plan represents a consistent and growing investment over ten years with funded by Power bonds $398.8 M and revenues $196.7 M.

Table 20: Hetch Hetchy Power Capital Plan
Hetchy
Power/
$million
FY 23-
24 FY 24-
25 FY 25-
26 FY 26-
27 FY 27-
28 FY 28-
29 FY 29-
30 FY 30-
31 FY 31-
32 FY 32-
33 Total
Transmission/
Distribution

9.1 67.7 82.9 79.3 71.9 45.4 39.2 36.5 33.4 30.3 495.7
Streetlights 2.8 3.8 3.8 3.8 3.8 3.8 3.8 3.8 3.8 3.8 37.2 Renewable/
Generation

1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 10.0
Energy
Efficiency

1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 10.0
PG&E Acq 7.6 4.2 3.9 3.9 3.8 3.8 3.8 3.8 3.8 3.8 42.7
Total- Hetchy
Power

21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5

Revenue
Funded

7.0 7.8 13.0 20.7 20.7 24.1 24.3 26.4 26.4 26.4 196.7
Debt Funded 14.5 69.9 79.6 68.4 60.9 30.9 24.6 19.8 16.7 13.6 398.8 Total Sources 21.5 77.7 92.7 89.1 81.5 55.0 48.8 46.1 43.1 40.0 595.5 Key Projects
Transmission & Distribution Program: $495.7 million
These projects are consistent with San Francisco Administrative Code Section 99.3 establishing the SFPUC's role as the exclusive electric service provider for existing and new City facilities, and redevelopment and development projects.

SFO Substation Improvements -– This project provides for the SFPUC to serve SFO’s anticipated load increase. The project will plan, design, and construct needed upgrades at the substations to provide reliable and redundant service to the airport.

Distribution Interface Redevelopment Projects - This project provides for the design and construction of new electric distribution systems and facilities for the SFPUC to provide electric services to various new developments within San Francisco. The project will consider the use and implementation of proven and new and emerging technologies. Beneficial technologies will be identified, researched, and FY 2023-24 to FY 2032-33 10-Year Capital Plan

37 analyzed, prior to making a proposal for any implementation on the project, where ratepayer benefit is demonstrated.

Customer Programs projects- The SFPUC provides a variety of energy programs to Hetch Hetchy Power customers that incentive energy efficiency, distributed energy resources, and building and transportation electrification. These programs benefit our customers through providing technical and financial support to install new energy technologies designed to accelerate the transition towards a net zero carbon future, in alignment with the City’s climate action goals. This budget funds staff time and consulting resources for developing and implementing programs, as well as the incentives paid out to the customers.

Alice Griffith/Candlestick Point - This project provides for the second phase of development at Hunters Point Shipyard, Candlestick Point, and the Alice Griffith Housing Complex. The Development Team comprised of the Office of Community Investment and Infrastructure and Developer will pay for the installation of the infrastructure and substructure required for the new 12-kV underground electrical distribution system. The SFPUC as the electric utility provider will install the conductors in the conduits, transformers, switches, and metering equipment required for the electric distribution system.

Grid Connections - Project to connect customers to SFPUC owned and operated distribution and transmission infrastructure. Hetchy Power has identified a number of customers along the Bay Corridor and current SFPUC grid customers to be connected to our systems including, The Shipyard, 2000 Marin, 1990 Newcomb, UCSF block 34, Wastewater Facilities; in addition to providing for the interconnections and other customers throughout the City.

Streetlights : $37.2 million
Hetchy provides power to all of San Francisco’s 44,528 streetlights, maintains the 25,509 streetlights owned by the City, and funds the maintenance of the 19,019 streetlights owned by Pacific Gas & Electric Company (PG&E). Street lighting area improvements, the conversion of high voltage series loop circuits into multiple standard voltage service and Lighting Emitting Diode (LED) lighting, holiday and festivity pole use, assessments to determine the severity of pole deterioration, streetlight pole rehabilitation, and replacement of poles are all funded through this program.

Energy Efficiency : $10.0 million
Energy efficiency improvements reduce facility operating costs and electric bills for customers, improve system functionality, and reduce the environmental impact of energy use. This program funds energy efficiency investments in City facilities covering the planning, design, and construction of "direct install" projects, as well as technical assistance and project assistance for departments utilizing their own capital funds. Energy retrofits include lighting, heating and ventilation, retro-commissioning, and energy management systems projects. The SFPUC performs three to five energy efficiency projects each year.

The budget funds efficiency projects in municipal facilities for departments such as Police, Real Estate, Recreation and Parks, SFMTA, Yerba Buena Center, and Fine Arts. Planned funding for lighting and mechanical system efficiency upgrades are consistent with state policies that place emphasis on energy efficiency and that support greenhouse gas reduction.

Renewable/Generation Power : $10.0 million
In accordance with City policies and directives to increase renewable energy and reduce greenhouse gases, Hetchy Power is continuously developing and implementing new renewable generation resources. Projects focus on small to mid-sized municipal facilities including solar photovoltaic, energy storage, biogas fuel cells, EV charging, micro-grid, and other renewable energy projects. The power FY 2023-24 to FY 2032-33 10-Year Capital Plan

38 generated from the Renewable/Generation Power projects will offset on-site power need at each project location.

Alternative Transmission Project: $42. 7 million
The Public Power Expansion Project funds financial, technical, regulatory, and legal analysis and City staff time toward assessment of acquiring PG&E's electrical assets, preparing to execute the possible transaction, and readying the SFPUC for operation of the acquired system. This work is on-going. We have completed a number of analyses and continue to refine the work and perform further analyses.

We are also working through the Valuation proceeding at CPUC and the CEQA EIR process.

Deprioritized Projects
The Power and Finance teams worked together to put together a final plan that addressed the needs of the enterprise, balanced by constraining rate growth. Power is in a new position this year, with their rate study completed and 2-year rate package adopted in Spring 2022. They now have the ability to vary rates based on cost of service, and therefore have more flexibility in capital planning. However, Power’s plan final represents strategic investments in both maintaining existing infrastructure and developing new load growth from both existing and new customers.

Power focused on maintaining funding for projects that had been approved and prioritized by the Executive Team and the Commission in the prior capital plan, as well as projects that rely on restricted outside revenue sources (e.g., streetlights, renewables, and cap and trade capital projects) that cannot otherwise be spent on other projects. Cuts and de-prioritization were focused on distribution services, where revenues from the sale of power are utilized. Such cuts limit revenue the Power Enterprise and Hetchy Water and Power will have in the future, as the associated projects typically connect new customers or allow increased sales to existing customers.

To determine which cuts to distribution services projects would have the least impact on project execution, Power conducted a review of the deliverability of our existing capital plan. Project managers reviewed their existing project balances, updated their spending projections, and made the reductions that they determined would have the lowest impact on project execution. Generally, de-prioritized projects are at earlier stages of planning and electrification deadlines. However, there are projects that are critically needed to meet City priorities on decarbonization and housing that due to Power’s funding constraints remain deprioritized in the current capital plan. Power has a study underway with a third- party consultant in advance of the next year’s capital planning process to provide more rigorous prioritization criteria and conduct high level planning.

The following table summarizes the projects that were reduced or not included in the final version of the plan.

Table 21: Projects deprioritized from Hetchy Power’s Capital Plan proposal, $ million Project Name Project objective Amount
reduced
Amount
remaining in
CIP
Consequence of this
action
Redevelopment Funds four large redevelopment
projects in active construction
(Mission Rock, Pier 70, and HopeSF
Sunnydale and Potrero) and three
smaller redevelopment projects in
initial planning phases (India Basin,
Balboa Reservoir, Visitacion Valley).

(55.5M) 141.6M The lack of funding for
the beginning of each
phase compromises the
SFPUC’s commitment to
serve and jeopardizes
our ability to connect new
customers.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

39 Each project under construction has
gone through the city’s entitlement
process and commitment to serve
from SFPUC through Disposition
and Development Agreements,
Interagency Coordination
Agreements, Electric Service
Agreements. The funds support the
construction of SFPUC-owned
distribution systems. Each project is
constructed in multiple phases and
over several years. Our funding
need is timed to the developer’s
schedule. Funding is needed to
cover high up-front construction
costs to ensure timing for vertical
development.

Intervening Facilities To interconnect SFPUC’s customers to PG&E’s grid and wheel Hetchy
Power over PG&E’s lines.
(11.0M) 105.5M Due to updated
construction timelines, we
can delay this $11M for
one year. The $11M is
approximately the PUC
contribution for six low-
voltage connection
projects.

Grid Connections To interconnect SFPUC’s customers
to SFPUC’s grid.
(7.6M) 19.3M Delays in the
electrification of SFPUC
Power’s customers’
projects, including
affordable housing and
the Water Enterprise.

Purchase of material and
labor would have to be
deferred until funding
becomes available. Due
to the long lead time, we
need to start ordering
materials as soon as
possible to have a good
inventory level to support
planned connections to
customers.

Transportation
Decarbonization for
the SF Port
(Substation)
To implement the City’s Climate
Action Plan and serve the Port’s
tenant projected load increases.

By 2026, the California Air Resource
Board requires that all ferry service
under 3 nautical miles be zero
emissions. To meet this
requirement, WETA, the Water
Emergency Transportation
Authority, must electrify their fleet
within the next few years. In
addition, the Port of San Francisco
expects their tenants to utilize more
electric power within the next 20
years, including for electric vehicle
charging.
(146.7M) - If SFPUC does not fund
this project, WETA and
the Port tenants would
have to apply to Hetchy
Power for individual
services, which would be
served through the PG&E
wholesale distribution
tariff (WDT), or WETA
and the Port tenants
would become PG&E
retail customers.

Decarbonization of
the Civic Center
To support the City’s goal of fuel
switching from natural gas to electric
(130.0M)
-
The City will be unable to
meet its Climate Action
FY 2023-24 to FY 2032-33 10-Year Capital Plan

40 Steam Loop – especially for City buildings in the
Civic Center Historic District in
which the existing buildings are
space constrained.

Plan commitments and
switch away from fossil
fuel heating, or the
service would be
provided by PG&E.

Treasure
Island/Yerba Buena
Island Resiliency
(Oakland Port 25kV)
To provide sufficient power to
Treasure Island/Yerba Buena
Island.
(112.3M) - SFPUC will be unable to
transmit sufficient power
over the existing wires by
2028, and we will be
unable to meet our
obligations to serve
customers unless we
initiate this project as
soon as possible.

Municipal
Electrification
Program
To implement the City’s Climate
Action Plan and support our
municipal customers to transition
away from fossil fuel.
(7.5M) - The City will be unable to
meet its Climate Action
Plan commitments.

Failure to fund this
project will prevent Power
from participating in
MTA’s transportation
decarbonization program.

Further, Power will not be
able to support our
municipal customers who
are required to replace
gas appliances with
electric as required by
updated Chapter 7
requirements.

Mobile Substations
and Emergency
Response
To have a mobile substation ready
in the event of switchgear damage
or if there are immediate
construction or emergency power
needs.
(4.7M) - Risk of extended outages
remains unmitigated. This
can be delayed in order
to fund more urgent
priorities.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

41 9. CleanPowerSF Capital Plan
Introduction
A program of the San Francisco Public Utilities Commission, CleanPowerSF is a local solution to the climate crisis, offering renewable, affordable and accessible energy to our community. We empower residents and businesses to choose a more sustainable future. CleanPowerSF buys electricity from sources such as wind and solar, and that electricity is delivered to homes via PG&E’s existing poles and wires.

Management of CleanPowerSF’s financial business functions include developing and maintaining long- range capital and financial plans. The Capital Plan will evaluate opportunities for local renewable energy development in San Francisco city-owned and regional sites and other opportunities in and near San Francisco.

Capital Plan Summary
CleanPowerSF’s capital budget is $1.6 M in FY 2023-24 and is funded by revenue and Disadvantaged Community and Green Tariff Solar Programs funding.

The CleanPowerSF 10-Year Capital Plan for FY 2023-24 through FY 2032-33 is $73 M, all of which $60.8 M is funded by CleanPowerSF revenues and $12.2 M by Disadvantaged Community and Green Tariff Solar Programs funding. CleanPowerSF does not expect to rely on debt to fund its current Capital Improvement Program between FY 2023-24 and FY 2032-33.

Table 22: CleanPowerSF FY2023-33 Capital Plan
$million FY
23-24
FY
24-25
FY
25-26
FY
26-27
FY
27-28
FY
28-29
FY
29-30
FY
30-31
FY
31-32
FY
32-33
Total
CleanPower SF Capital 0.8 1.9 1.9 1.8 1.8 2.0 7.6 16.8 24.9 1.4 60.8 DAC Solar Program 0.8 1.0 1.1 1.2 1.2 1.3 1.3 1.4 1.4 1.4 12.2 Total Uses 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0

Revenue Funded 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0 Total Sources 1.6 2.9 3.0 3.0 3.1 3.3 8.9 18.1 26.3 2.8 73.0

Key Projects
Local Renewable Energy Program: $48.8 million
This program will fund the development of new renewable energy (solar photovoltaic) and battery storage projects on select SFPUC sites. The project is structured around six major phases, including:

Planning, Request for Proposals, Construction and Commissioning, Power Purchase Agreement, Asset Management, and Project Buyout. The initial renewable energy facilities developed under this program would be structured as power purchase agreements (PPA) with third parties that would develop and operate the projects for an initial period of time. The PPAs would include a buy-out option for the City.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

42 Customer Programs: $12.1 million
This program funds the development and implementation of programs that incentivize CleanPowerSF customers to invest in new clean energy technologies that can reduce their energy costs and further San Francisco’s decarbonization goals. Incentives will be available for residents and businesses investing in new clean and efficient equipment like solar power generating equipment, battery storage, electrical vehicle chargers and electric heat pump water heating.

Disadvantaged Community and Green Tariff Solar Programs : $12.2 million The California Public Utilities Commission created the DAC Green Tariff and Community Solar Green Tariff programs to increase renewable energy produced and consumed within Disadvantaged Communities. By offering these programs, CleanPowerSF will be able to provide participating customers 100% renewable energy at a 20% discount. These programs will be funded by revenues from PG&E’s sale of carbon dioxide allowances under the State’s Cap and Trade program and the Public Purpose Program Charge, which is collected from all PG&E retail customers, including those that receive generation service from CleanPowerSF.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

43 10. Affordability
Capital expenditures are the SFPUC’s biggest cost driver and thus the most important driver of rate increases for our customers. Over the past ten years, the combined Water and Wastewater bill has increased by over 75%. The 10 Year Financial Plans project an increase in the combined Water/Wastewater bill of 90% over next ten years.

In addition to the cost constraining measures detailed in this report, staff have made great strides to mitigate against harsh bill impacts on our ratepayers, including expanding customer assistance programs. In addition, the Finance team partnered with External Affairs to initiate a study on affordability. A consultant was procured to survey the suite of affordability metrics that are used by our peer agencies to help us identify the processes that can best illustrate the financial burden of rates on customers across the SFPUC service area. The SFPUC’s current metric for assessing affordability uses Median Household Income, which does not account for the cost of living in San Francisco.

Furthermore, the SFPUC’s current metric target of 2.5% was not selected based on rigorous data analysis, so alternative metrics researched by the consultant are being looked into. Additionally, the Finance Team is investigating key performance indicators that are used by ratings agencies to establish bond ratings to help us better understand how our plans may impact future borrowing terms.

As we hone in on the most appropriate customer affordability and utility financial performance KPIs, the Finance team plans to incorporate these metrics into the 10-Year Financial Plan model to provide a more complete picture of the impacts of our capital finance scenario planning and to inform future rate- setting and customer assistance program discount design.

This process is still in its early stages so there are not any definitive spending thresholds based on affordability at this point in time. Over the coming months, the Finance team will be continuing to evaluate the affordability metrics and present a recommended policy on affordability to the commission for adoptions, aiming to have this complete during 2023.

To learn more about how the SFPUC is placing affordability at the forefront of its mission, please refer to the 10-Year Financial Plan.

FY 2023-24 to FY 2032-33 10-Year Capital Plan

44 11. Next Steps
Deliverability work and capital planning process work is a long-term project that we know we cannot solve in one budget cycle. This year’s process will bring in guidance on some internal deliverability factors and we will continue to refine the deliverability review approach as we move into to the next 2- year budget cycle. In turn, we will continue to review the long-term capital needs for our water, power and sewer systems and look for innovative strategies to reduce costs in line with ratepayer affordability while still meeting the asset replacement needs for our facilities.

The short-term goal for Phases 1 and 2 of the Capital Planning and Delivery Program was to develop a balanced FY 23-24 Capital Budget and 10-year Capital Plan informed by project deliverability and ratepayer affordability factors by December 2022.

The long-term goals in focus for Phase 3 are to:
• Build a unified approach for capital project planning, prioritization and decision making across SFPUC
• Improve our ability to assess deliverability for project planning and budgeting • Develop solutions to key deliverability issues to increase our capacity to execute on projects These objectives seek to improve, modernize, and unify the SFPUC’s Capital Planning approach - one of the most fundamental strategic activities of the SFPUC and its biggest cost driver. The goal to unify includes some nuance – to unify as much as possible our systems, governance, and processes to enable more informed decision making, while allowing for variation in prioritization criteria to account for the differing demands on each enterprise.

Given the broad scope, this program will likely span at least five years to include at least two full budget development cycles which occur every other year. Also, given the existing workload of SFPUC staff, it will be important to identify what can be accomplished in time and in support of the next two-year budget cycle in 2023; and what can be accomplished in subsequent years.

It is important to mention however, that given the many internal and external factors that impact project execution, building the tools and capacity to measure deliverability consistently and effectively – and embed this practice within our agency long-term -- will require a dedicated, continuous, cross- functional effort. It may also be very difficult to develop an approach that accounts for all factors. Long term, it will be important to balance deliverability reviews with an analysis of spending patterns and use both inputs to refine the CIP, while ensuring we invest in the capital improvement needs of our facilities.